Application of A Heat-Integrated Post- combustion CO ...

23
Application of A Heat-Integrated Post- combustion CO 2 Capture System with Hitachi Advanced Solvent into Existing Coal-Fired Power Plant Kunlei Liu, Jim Neathery and Joe Remias Center for Applied Energy Research University of Kentucky Lexington, KY 40511

Transcript of Application of A Heat-Integrated Post- combustion CO ...

Page 1: Application of A Heat-Integrated Post- combustion CO ...

Application of A Heat-Integrated Post-

combustion CO2 Capture System with

Hitachi Advanced Solvent into Existing

Coal-Fired Power Plant

Kunlei Liu, Jim Neathery and Joe Remias Center for Applied Energy Research

University of Kentucky

Lexington, KY 40511

Page 2: Application of A Heat-Integrated Post- combustion CO ...

Outline

• Project Overview – Team and funding

– Objective

– SOW

– Test site

• The facts of slipstream – Development history

– System feature

– Test site information

– Experimental plan

– Slipstream apparatus

Page 3: Application of A Heat-Integrated Post- combustion CO ...

Team and Funding Structure

University of Kentucky Research Foundation on behalf

of Center for Applied Energy Research Applicant

DOE NETLFunding ($14.5M)

Partner & Subcontractor

KY DEDI

Co-Funding ($3.64M)

Utility Group in CMRG

(AEP, Duke, EKPC, EPRI, and LKE)

Co-Funding ($300K)

HPSA

Advanced Solvent

System Integration

KMPS

Engineering Design

Fabrication, commissioning

Subcontractor

SMG

Permitting

EH&S

EPRI

Techno-Eco Anal

3rd Party Eval

Participants’ Contribution

UKy -- $337K

HPSA -- $350K

EPRI -- $200K

SMG -- $20K

$1.7M $1.0M $5.5M $208K

$10.9M

Page 4: Application of A Heat-Integrated Post- combustion CO ...

Objectives

1) To demonstrate a heat-integrated post-combustion

CO2 capture system with advanced solvent;

2) To gather data on solvent degradation, water

management as well as other information during

the long-term verification runs;

3) To provide scale-up data and design information for

commercial-scale projects;

4) To collect information/data on material corrosion

and identify appropriate materials for a 550 MWe

commercial-scale carbon capture plant;

Page 5: Application of A Heat-Integrated Post- combustion CO ...

What will We Do?

• The design, start-up/commissioning of a 2MWth test

facility (1400 cfm);

• Parametric investigation and long-term verification;

• New corrosion resistance coatings for material used in

CCS system (access ports needed in scrubber and

stripper areas)

• Solvent degradation (liquid product and gaseous

emissions from CCS)

• A series of transient tests to quantify the ability of the

carbon capture system to follow load demand.

Page 6: Application of A Heat-Integrated Post- combustion CO ...

Test Site

• Located at 815 Dix Dam Rd, Harrodsburg, KY 40330

• 40 miles from UKy-CAER

Page 7: Application of A Heat-Integrated Post- combustion CO ...

Absorb40°C1 atm

Steam 3 atm

CO2

150 Bar

Strip117°C2 atm

12% CO2

30% MEA (7 m)

Lean

0.2

Rich

0.5

MonoEthanolAmine Absorption/Stripping

C

1.2% CO2

The Origin for Proposed Process

Heat

Rejected

to CW

(400 Btu/lb

CO2)

Heat

rejected

(100 Btu/lb

CO2)

Heat

needed

(1300

Btu/lb

CO2)

Heat

Rejected

(400 Btu/lb

CO2)

Heat

Rejected

(600 Btu/lb

CO2)

Page 8: Application of A Heat-Integrated Post- combustion CO ...

Background – Heat Recovery from

Overhead Condenser

Page 9: Application of A Heat-Integrated Post- combustion CO ...

Relative Humidity on Steam Turbine

Output Correction

Page 10: Application of A Heat-Integrated Post- combustion CO ...

Advanced Solvent (H3-1)

Page 11: Application of A Heat-Integrated Post- combustion CO ...

Advanced Solvent (H3-1)

0

1

2

3

4

5

6

7

8

MEA B solv A solv H3 H3-1

No

rma

lize

d A

min

e L

oss

Page 12: Application of A Heat-Integrated Post- combustion CO ...

Corrosivity of H3-1

Temperature

(°C)

Corrosion rate

(mmpy)

Solvent H3-1 5 M MEA

Carbon

steel A106

40 UN 0.79

90 0.350 4.97

Stainless

steel 304 40 UN UN

90 0.104 0.187

UN – within the uncertainty of instrument used

Page 13: Application of A Heat-Integrated Post- combustion CO ...

The Effect of CO2 Concentration at Absorber

Inlet on Carbon Loading in Rich Solution

Page 14: Application of A Heat-Integrated Post- combustion CO ...

The Effect of CO2 Concentration at

Absorber Inlet on Energy Consumption

0

500

1000

1500

2000

2500

12 14 17

Ene

rgy

(Btu

/Ib

CO

2)

% CO2

16.3%

21.5%

Page 15: Application of A Heat-Integrated Post- combustion CO ...

CAER's CCS Technology

Two-stage stripping

Integrated Cooling Tower

Advanced Solvent

What We Have Proposed

1.

2.

3. Engineering design, build and install an advanced

CO2 capture system into an existing PC power

plant at a 0.7 MWe slipstream scale (~15 TPD CO2)

Three novel processes will be designed and

integrated: 2-stage solvent striping, cooling tower

desiccant, and Hitachi solvent

1. Two-stage Stripping:

- Increase solvent working capacity by providing a secondary air-stripping column following

the conventional steam stripping column.

- Air stripping stream sent to boiler as combustion air to increase flue gas PCO2 exiting boiler

2. Integrated Cooling Tower:

- Use regenerated CO2 stream waste heat to dry liquid desiccant

- Liquid desiccant is used to dry cooling tower air Improved power plant cooling tower and

steam turbine efficiency

3. Advanced Hitachi Solvent:

- Primary amine analogous to MEA

Page 16: Application of A Heat-Integrated Post- combustion CO ...

Testing Site: LG&E and KU’s Brown Generating Station

Page 17: Application of A Heat-Integrated Post- combustion CO ...

Boilers Used for Testing

• Unit 1: B&W wall fired sub-critical boiler with

Westinghouse 110 (gross) MW reheat turbine (1450

psig/1000°F/1000°F), ESP, and Low NOx burners;

• Unit 2: CE t-fired sub-critical boiler with Westinghouse

180 MW (gross) reheat turbine (1800 psig /1000°F

/1000°F), ESP, Low NOx burners, and OFA;

• Unit 3: CE t-fired sub-critical boiler with Westinghouse

457 MW (gross) reheat turbine (2400 psig/1000°F

/1000°F), ESP, Low NOx burners, and OFA.

• FGD common to all 3 units, in near future, SCR

and SAM Mitigation Equipment

Page 18: Application of A Heat-Integrated Post- combustion CO ...

BPs and Tasks (still under discussion)

BP Task Name

1.0, 5.0, 9.0, 17.0 Project Management & Planning

2.0 System and Economic Analysis.

3.0 Initial EH&S Assessment

4.0 Basic Process Specification and Design

6.0 Slipstream Site Suvery

7.0 Finalized Engineering Specification and Design

8.0 Test Condition Selection and Test Plan

10.0 System Engineering Update and Model Refinements

11.0 Update of EH&S Assessment

12.0 Site Preparation

13.0 Fabrication of Slip-stream Modules

14.0 Procurement and Installation of Control Room/Field

15.0 Fabrication of Corrosion Coupons

16.0 Slipstream Facility Erection, Start-up, Commissioning

18.0 Slip-stream Test Campaign

19.0 Final Updater of Techno-Economic Analysis

20.0 Final EH&S Assessment

1

2

3

4

Page 19: Application of A Heat-Integrated Post- combustion CO ...

Test Variables

Factors Description Level 1

(-1)

Level 2

(0)

Level 3

(1)

A L/G Ratio (wt/wt) 0.2 0.5 0.8

B Stripper Pressure (bar) 1.3 3 4.5

C Inlet CO2

Concentration (vol %)

10 12 14

D Solvent Blow-down (%) 0.5 1 2

Page 20: Application of A Heat-Integrated Post- combustion CO ...

Sampling and Instrumentation

Instrumentation Items Determined Samples

On-line Gas and Liquid

Analyzers

Gaseous composition

Carbon loading Gas and Liquid

HPLC-MS and GC-MS Solvent and degradation

products Gas and liquid

IC Halogen, sulfur-, nitro-

compounds Gas and liquid

ICP Trace metals Liquid

Titrator / phosphoric

acid method

Alkalinity and total solution

carbon Liquid

pH, density meter Solution pH, density Liquid

Capillary viscometer

and rise tensiometer

Solution viscosity and

surface tension Liquid

XRD Coating and corrosion

product Metal coupon

Page 21: Application of A Heat-Integrated Post- combustion CO ...

Design Considerations

• Design pressure for stripper and associated components: 150 psi

• Turn-down operation will be 4:1 ratio

• Structure support: (middle suspension??)

Heat Required for Regeneration (Btu/lb-CO2)

Heat Capacity relative to MEA

Viscosity relative to MEA

Net Cycle Capacity (mole/kg Solu)

Mass Transfer flux in CO2 absorper (relative to MEA)

The Performance of Solvent Used in this Project

Solvent Design Solvent (30 wt% MEA)

Performance Solvent

(Hitachi H3-1)

1 1.25

baseline 1.0x

baseline 1.0x

baseline 1.0x

Foaming Tendency relative to MEA baseline less

Surface Tension relative to MEA

1380 1035

baseline 1.2x

Page 22: Application of A Heat-Integrated Post- combustion CO ...

Preliminary 3-D View of Slipstream Unit

• 80 ft tall

• 1000 ft2 footprint

(15’x65’, but could be

rearranged)

• 5 to 6 modulus with

100,000lbs/modulus

• Plus control/lab trailer

and others

Page 23: Application of A Heat-Integrated Post- combustion CO ...

Output

• An advanced heat-integrated post-combustion CO2 capture process that could be applied to various solvents;

• Knowledge on water balance and solvent management, and metal corrosion as well;

• Gain experience on system dynamics corresponding to load, trip and upset;

• Data on gas/liquid emission and solvent degradation