Response to ASD Comments
ASD Comments (LetterRef: ASD63/6104/SSP318/C50/500(104) )
Submission 1st AIP 3rd Submission Central Plants and Rooms and Undergroundand External Works (Part B Open Space)
Sub. Date: 12-Jan-2009
Doc. Ref.: DSF/BS/143
ASD Comment JRP Response Appendix
1 Major comments on design brief and reports:-
a Clause 1.0 - Introduction
i) The scope of this submission package and the space/areas, which are
classified as Open Space presumably to be managed by LCSD, to be
covered under the submission are still missing from the report (3rd
reminder)
Have been revised in this report.
The details demarcation of the Open Space areas can refer to
Appendix - D for details.
-
ii) The facilities shared use amongst the different user groups of
CGC/LegCo, CGC/Open Space, CGC/LegCo/Open Space and
LegCo/Open Space should be under separate package of communalfacilities. This submission shall only be focused on Open Space and
shared facilities in relation to Open Space
Have been revised in this report. -
b Clause 2.1.2 Design Criteria for MV space
Only those rooms/areas solely designed for Open Space should be
mentioned in the design criteria table. Design criteria for irrigation
water pump room, water pump room, filtration plant room, etc., which
are served use should be submitted under Common Facilities
package
Have beed revised in this report. -
c Clauses 2.2.3 & 2.2.4 - Plumbing and drainage installations
Plumbing and drainage installations shall be submitted under separate
packages
Noted. -
Clause 2.2 Air and water distribution velocity
d The proposed design criteria for air distribution velocity shall be
subject to the recommendation of acoustic report.
Noted. -
e Clause 3.1.1 AC system
Tee off reserve from the central chiller plant should be allowed for
Open Space.
Chilled water and hot water tee-off will be provided inside
Central chiller plant room.
-
Ref
-
7/30/2019 Appendix - Response to ASD Comment2
2/7
Response to ASD Comments
ASD Comments (LetterRef: ASD63/6104/SSP318/C50/500(104) )
Submission 1st AIP 3rd Submission Central Plants and Rooms and Undergroundand External Works (Part B Open Space)
Sub. Date: 12-Jan-2009
Doc. Ref.: DSF/BS/143
ASD Comment JRP Response AppendixRef
f Clause 3.1.2.4 Park toilet
CCMS with time scheduling supplemented with local control for
circulating fans installed in toilets shall be provided.
Confirmed to provide. -
g Clause 3.1.3 - CCMS
Description of CCMS proposed shall be specific for Open Space.
Irrelevant information shall be removed from the report
Have been revised in this report. -
h Clause 3.2 FS installation
Areas/rooms of Open Space proposed with shared use of fire hydrant/hose reel system, sprinkler, street hydrant, manual fire alarm, AFA,
shall be summarized in the report for ease of reference
i Clause 3.2.5 AFA
i) The fire alarm and evacuation matrix table has not included Open
Space
ii) Please note the comment made on the same table under CGCO,
CGCL and LegCo submissions
iii) Fire alarm signal to be repeated to fire repeater station in Park
Management office shall be stated in the report
iv) Please indicate whether the actuation of building alarm will trigger the
alarming in facilities of Open Space or vice versa
j Clause 3.5 Electrical installation
i) In view of optimization of transformer loading capacity, please review
if the electric loading of common facilities/ open space can be
combined into one single transformer and paired up with the
transformer group of central chiller plant for resilience design
It will be revised in schematic drawing and loading estimation
in report
-
7/30/2019 Appendix - Response to ASD Comment2
3/7
-
7/30/2019 Appendix - Response to ASD Comment2
4/7
Response to ASD Comments
ASD Comments (LetterRef: ASD63/6104/SSP318/C50/500(104) )
Submission 1st AIP 3rd Submission Central Plants and Rooms and Undergroundand External Works (Part B Open Space)
Sub. Date: 12-Jan-2009
Doc. Ref.: DSF/BS/143
ASD Comment JRP Response AppendixRef
p Clause 3.5.13 Active harmonic filtering equipment
Harmonic filter shall be sized according to the harmonic
characteristics of the associated non-linear equipment load so as to
meet the requirement as laid down in the Electrical Energy Code
instead of 15% of the rating of the connected load as stated in the
report. Design calculation shall be submitted
It will be provided in DDA.
q Clause 3.5.15 Lightning protection system
Lightning protection system proposed shall be subject to your
submission of risk assessment as per the BS EN 62305 which has
superseded BS6651 as effective on 31 Aug 2008
It will be incorporated in report.
r Clause 3.5.16 Public address system
Design criteria of sound level shall be given in the report.
It will be incorporated in report.
s Clause 3.5.17 - Induction loop system.
Please state the area of Open Space is to be provided with induction
loop system. (2nd reminder)
It will be incorporated in report.
t Clause 3.5.18 Water leakage detection system
Please explicitly state where the leakage detection system is to beprovided for Open Space. The proposed areas fall outside the scope of
Open Space. Please review
u Clause 3.5.19 Intercommunication system
Please confirm whether intercom has been allowed for plant rooms of
Open Space and EMSD office which is located under the Green
Carpet
It will be incorporated in report.
v Appendix D Demarcation plan
Please update the demarcation plan based on the latest agreement with
the users. Also, please check and confirm if the B/F drivers room isunder management of Open Space
The demarcation plan has been updated. The B/F driver's
room is under the management of CGCO.
Appendix-D
-
7/30/2019 Appendix - Response to ASD Comment2
5/7
Response to ASD Comments
ASD Comments (LetterRef: ASD63/6104/SSP318/C50/500(104) )
Submission 1st AIP 3rd Submission Central Plants and Rooms and Undergroundand External Works (Part B Open Space)
Sub. Date: 12-Jan-2009
Doc. Ref.: DSF/BS/143
ASD Comment JRP Response AppendixRef
w Appendix E Load estimate
i) Please elaborate the breakdown of load estimate of (150kVA normal
+ 37kVA essential) allowed for building landscape lighting
Noted and It will be subject to LDP design.
ii) Please elaborate the breakdown of load estimate of 60kVA allowed
for ACMV installation
It will be shown in load estimation.
iii) Please elaborate the breakdown of load estimate of 132kVA allowed
for irrigation water pump (2nd
reminder)
It will be shown in load estimation.
iv) Please elaborate the breakdown of load estimate of 158kVA allowed
for water feature (2nd
reminder)
It will be shown in load estimation.
v) Firemans lift has been included into the load schedule of FSI
generator. Please clarify if such is allowed for Open Space. If not,
please delete it from the schedule
It will be incorporated in common area report.
x Appendix F Schedule of Maintenance Work
The maintenance schedule is incomplete. FS, CCMS, generator, etc.,
have been missing from the schedule
Have been included in this report.
y Appendix I Major Equipment Maintenance Route
The proposed access route for major equipment maintenance in
basement has not been shown on the submitted drawings. Also, the
minimum clearance of access dimension required to be maintained all
along the route is to be given.
Will be provided in DDA submission for the details of
maintenance route.
z Please elaborate the design provision to cater for seismic situation and
natural disasters as per the requirement stated in the ER.
Have been included in this report. Section 1.0 in design report.
-
7/30/2019 Appendix - Response to ASD Comment2
6/7
Response to ASD Comments
ASD Comments (LetterRef: ASD63/6104/SSP318/C50/500(104) )
Submission 1st AIP 3rd Submission Central Plants and Rooms and Undergroundand External Works (Part B Open Space)
Sub. Date: 12-Jan-2009
Doc. Ref.: DSF/BS/143
ASD Comment JRP Response AppendixRef
aa Maintenance requirements and strategy shall be proposed to address
the shared use of installations amongst different groups of users, such
as CGC/LegCo, CGC/LCSD, CGC/LegCo/LCSD or LegCo/LCSD.
(2nd
reminder)
It will be provided in report.
ab Please also refer to comments given on the same submission on
Common Facilities for those areas relevant to the Open Space
Have been included in this report. -
ac Some of the replies to previous ArchSDs comments on 1st
AIP 2nd
submission is unsatisfactory. Please note the markup comment on the
returned report and amend accordingly.
Noted
ad Please refer to other comments marked up on the returned design
report
Noted
2 Major comments on drawings:-
a Power distribution shall be divided into Open Space; Shared facilities
of Open Space; and Shared facilities of non-open space
There are two kind of power distribution. One is Open Space,
another is Common area.
b Power distribution feeders from the main cubicle switchboard and
emergency generator cubicle designed for Open Space and Shared
facilities of Open Space shall be dedicated in order to demarcate
maintenance responsibility
It will be shown in DDA drawings.
c Local maintenance bypass switch shall be provided for those ATS of
non-ACB or non-MCCB types.
There is no ATS in kind of non ACB or non MCCB.
-
7/30/2019 Appendix - Response to ASD Comment2
7/7
Response to ASD Comments
ASD Comments (LetterRef: ASD63/6104/SSP318/C50/500(104) )
Submission 1st AIP 3rd Submission Central Plants and Rooms and Undergroundand External Works (Part B Open Space)
Sub. Date: 12-Jan-2009
Doc. Ref.: DSF/BS/143
ASD Comment JRP Response AppendixRef
d Main switch shall be allowed for the respective main supplies of
essential and normal power circuits of Open Space and Common
Facilities in order to differentiate the ownership of the power supply
system.
It will be revised in schematic drawings.
e Separate switchroom should be allowed for open space and common
facilities for ease of future maintenance work under different
ownership
It will be revised in drawing layout.
f PA Schematic The headend equipment of PA system should installed
in Park Management office instead of G/F security control room
Noted and will be incorporated in drawing layout.
g Cubicle switchboard layout plan shall be submitted It will be incorporated in drawings.
h IT infrastructure schematic diagram. Please indicate the provision for
Open Space
It will be incorporated in drawings.
i The following areas/rooms which have been shown on Airside
Schematic diagram should not be classified as open space:-
HV generator room
Fuel tank room for HV generator room
It shall be SWHP plant room.