APPENDIX - JICA · 2016. 10. 11. · 9 Ms. Yasumi TSUTSUI Environmental/ Social-condition NJS...
Transcript of APPENDIX - JICA · 2016. 10. 11. · 9 Ms. Yasumi TSUTSUI Environmental/ Social-condition NJS...
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
APPENDIX
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
Appendix
A-1 Member List of the Survey Team .................................................................................................. A-1
A-2 Survey Schedule ............................................................................................................................ A-4
A-3 List of Parties Concerned in the Recipient Country ...................................................................... A-8
A-4 Minutes of Discussions ............................................................................................................... A-10
A-4-1 Minutes of Discussions on the First Preparatory Survey ..................................................... A-10
A-4-2 Minutes of Discussions on the Second Preparatory Survey ................................................. A-24
A-4-3 Minutes of Discussions on the Schematic Design Overview ............................................... A-52
A-5 Soft Component (Technical Assistance) Plan ........................................................................... A-108
A-6 Other Relevant Data .................................................................................................................. A-116
A-6-1 Land Acquisition Monitoring Form ................................................................................... A-116
A-6-2 Monitoring Form (Draft) .................................................................................................... A-120
A-6-3 JICA Environmental Checklist........................................................................................... A-125
A-6-4 Seismic Capacity of Pipes Selected in the Project ............................................................. A-135
A-6-5 Setting Basis of Water Leakage Rate after Completion of the Project .............................. A-136
A-6-6 Water Quality of the Mardi River and Others .................................................................... A-141
A-6-7 Result of Soil Survey ......................................................................................................... A-151
A-6-8 Estimated Income & Expenditure Statement by Water Tariff Scenario Estimated ........... A-199
A-6-9 Report of Social Condition Survey .................................................................................... A-211
A-6-10 Future measures for water services improvement of Pokhara City (Suggestion) ............ A-246
A-6-11 Result of Capacity Assessment ........................................................................................ A-251
A-6-12 Basis for Calculation of O&M Cost ................................................................................. A-254
A-6-13 Calculation of Quantitative Effect Index (Frequency of Water Supply) .......................... A-257
A-7 References ................................................................................................................................. A-259
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-1
A-1 Member List of the Survey Team
(1) The First Preparatory Survey (2015)
No. Name Duty Occupation Term
1 Mr. Shigeyuki
MATSUMOTO
Team Leader Senior Advisor, JICA 2-Apr to 11-Apr
2 Mr. Sadanobu
SAWARA
Water Supply/
Business Administration
Senior Advisor, JICA 2-Apr to 11-Apr
3 Ms. Momoko
OTSUKA
Survey Planning Water Resources Management Division 1,
Global Environmental Department, JICA
2-Apr to 11-Apr
4 Mr. Toru
YAGI
Chief Consultant /
Water Supply Planning
NJS Consultants Co., Ltd. 2-Apr to 6-Jun
5 Mr. Shinichi
OSAKA
Deputy Chief Consultant / Planning and Design of Water Supply Facility
NJS Consultants Co., Ltd. 2-Apr to 21-Apr
3-May to 6-Jun
6 Mr. Satoru
ONIKI
Planning of O&M NJS Consultants Co., Ltd. 21-Apr to 12-May
7 Mr. Kengo
FUJIKAWA
Planning and Design of Pipes NJS Consultants Co., Ltd.
2-Apr to 4-Jun
8 Mr. Tsutomu
KAMEYAMA
Planning of River/ Flood Control Yachiyo Engineering Co., Ltd. 2-Apr to 21-Apr
9 Ms. Yasumi
TSUTSUI
Environmental/ Social-condition NJS Consultants Co., Ltd.
21-Apr to 25-May
10 Ms. Izumi
TAKAI
Business Administration and
Finance
Yachiyo Engineering Co., Ltd. 16-Apr to 30-Apr
11 Mr. Shinji
ASANO
Estimation/ Procurement/
Construction Planning
NJS Consultants Co., Ltd. 8-May to 22-May
12 Mr. Kenta
HAYASHI
Coordination/Estimation
Assistant
NJS Consultants Co., Ltd. 2-Apr to 30-May
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-2
(2) The Second Preparatory Survey (2015)
No. Name Duty Occupation Term
1 Mr. Shigeyuki
MATSUMOTO
Team Leader Senior Advisor, JICA 12-Jul to 17-Jul
2 Mr. Sadanobu
SAWARA
Water Supply/
Business Administration
Senior Advisor, JICA 12-Jul to 17-Jul
3 Ms. Momoko
OTSUKA
Survey Planning Water Resources Management Division 1,
Global Environmental Department, JICA
12-Jul to 17-Jul
4 Mr. Toru
YAGI
Chief Consultant /
Water Supply Planning
NJS Consultants Co., Ltd. 9-Jul to 11-Sep
5 Mr. Shinichi
OSAKA
Deputy Chief Consultant / Planning and Design of Water Supply Facility
NJS Consultants Co., Ltd. 11-Jul to 25-Aug
6 Mr. Satoru
ONIKI
Planning of O&M NJS Consultants Co., Ltd. 27-Jul to 22-Aug
7 Mr. Kengo
FUJIKAWA
Planning and Design of Pipes NJS Consultants Co., Ltd.
9-Jul to 11-Sep
8 Mr. Tsutomu
KAMEYAMA
Planning of River/ Flood Control Yachiyo Engineering Co., Ltd. 16-Jul to 4-Aug
9 Mr. Akira
HASEBE
Planning and Design of
Electrical Facilities
NJS Consultants Co., Ltd.
27-Jul to 21-Aug
10 Ms. Yasumi
TSUTSUI
Environmental/ Social-condition NJS Consultants Co., Ltd.
15-Jul to 3-Aug
11 Ms. Izumi
TAKAI
Business Administration and
Finance
Yachiyo Engineering Co., Ltd. 29-Jul to 22-Aug
12 Mr. Shinji
ASANO
Estimation/ Procurement/
Construction Planning
NJS Consultants Co., Ltd. 22-Jul to 7-Sep
13 Mr. Kenta
HAYASHI
Coordination/Estimation
Assistant
NJS Consultants Co., Ltd. 22-Jul to 7-Sep
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-3
(3) The Third Preparatory Survey (2016) (DOD Surveys)
No. Name Duty Occupation Term
1 Mr. Shigeyuki
MATSUMOTO
Team Leader Senior Advisor, JICA 3-Jul to 10-Jul
2 Ms. Yasuyo
KAWAMURA
Survey Planning Water Resources Management Division 1,
Global Environmental Department, JICA
3-Jul to 10-Jul
3 Mr. Toru
YAGI
Chief Consultant / Water Supply
Planning
NJS Consultants Co., Ltd. 29-Jun to 10-Jul
4 Mr. Shinichi
OSAKA
Deputy Chief Consultant /
Planning and Design of Water
Supply Facility
NJS Consultants Co., Ltd. 29-Jun to 10-Jul
5 Ms. Yasumi
TSUTSUI
Environmental/ Social-condition NJS Consultants Co., Ltd.
29-Jun to 10-Jul
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-4
A-2 Survey Schedule
(1) The First Preparatory Survey
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-5
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-6
(2) The Second Preparatory Survey
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-7
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-8
(3) The Third Preparatory Survey (DOD Survey)
A-3 List of Parties Concerned in the Recipient Country
(1) The First Preparatory Survey
Ministry of Urban Development
1 Mr. Ram Chandra Devkota Joint Secretary Chief, Water and Environment
Division
2 Mr. Nawai Kishor Mishra Joint Secretary
Nepal Water Supply Corporation (NWSC)
Head Office
1 Dr. Er. Parameshor Pokharel Chairman
2 Mr. Jhalak Ram Adhikari Chief Executive Officer
3 Mr. Arjun Babu Dhakal General Manager
4 Dr. Bhupendra Prasad Acting Manager
Pokhara Office
1 Mr. Buddha Ratna Maharjan Office Chief
2 Mr. Dineshwar Yadar Acting Office Chief, Engineer
Mr.
MATSUMOTO
Ms.
KAWAMURA
Mr.
YAGI
Mr.
OSAKA
Ms. TSUTSUI
1 29-Jun Wed Mr.Yagi, Mr.Osaka, Ms.Tsutsui : Transfer from Haneda to Kathmandu ◯ ◯ ◯
2 30-Jun Thu Meeting in NWSC Headquarters ◯ ◯ ◯
3 1-Jul Fri Meeting with NWSC Headquarters ◯ ◯ ◯
4 2-Jul Sat Revising Draft Final Reports, etc ◯ ◯ ◯
5 3-Jul Sun Mr.Matsumoto, Ms.Kawamoto : Transfer from Haneda to Kathmandu ◯ ◯ ◯ ◯ ◯
6 4-Jul MonMeeting at JICA Nepal OfficeMeeting at Water and Sewerage Ministry, NWSC Headquarters
◯ ◯ ◯ ◯ ◯
7 5-Jul TueMeeting at NESC HeadquartersMeeting at Ministry of Finance
◯ ◯ ◯ ◯ ◯
8 6-Jul Wed M/D signature (Water and Sewerage Ministry) ◯ ◯ ◯ ◯ ◯
9 7-Jul Thu End of Ramadan holiday ◯ ◯ ◯ ◯ ◯
10 8-Jul Fri Meeting with Ministry of Finance, Report to the Embassy ◯ ◯ ◯ ◯ ◯
11 9-Jul Sat ◯ ◯ ◯ ◯ ◯
12 10-Jul Sun ◯ ◯ ◯ ◯ ◯
Members
Transfer from Kathmandu to Haneda
No. Date Day Schedule
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-9
(2) The Second Preparatory Survey
Ministry of Urban Development
1 Mr. Ram Chandra Devkota Joint Secretary Chief, Water and Environment Division
2 Mr. Nawai Kishor Mishra Joint Secretary
Nepal Water Supply Corporation (NWSC)
Head Office
1 Dr. Er. Parameshor Pokharel Chairman
2 Mr. Arjun Babu Dhakal General Manager
3 Dr. Bhupendra Prasad Acting Manager
4 Mr. Ishwar Prasad Acting Deputy Manager
Pokhara Office
1 Mr. Buddha Ratna Maharjan Office Chief
2 Mr. Dineshwar Yadar Acting Office Chief, Engineer
(3) The Third Preparatory Survey
Ministry of Water Supply and Sanitation (MoWSS)
1 Mr. Rajan Raj Pandey Joint Secretary
Nepal Water Supply Corporation (NWSC)
Head Office
1 Mr. Arjun Babu Dhakal General Manager
2 Dr. Bhupendra Prasad Acting Manager
3 Mr. Ishwar Prasad Acting Deputy Manager
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-10
A-4 Minutes of Discussions
A-4-1 Minutes of Discussions on the First Preparatory Survey
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-11
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-12
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-13
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-14
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-15
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-16
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-17
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-18
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-19
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-20
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-21
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-22
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-23
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-24
A-4-2 Minutes of Discussions on the Second Preparatory Survey
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-25
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-26
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-27
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-28
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-29
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-30
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-31
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-32
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-33
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-34
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-35
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-36
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-37
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-38
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-39
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-40
Pre
para
tory
Sur
vey
on P
okha
ra W
ater
Sup
ply
Impr
ovem
ent
Pro
ject
in
Nep
al
App
endi
x
A-4
1
Pre
para
tory
Sur
vey
on P
okha
ra W
ater
Sup
ply
Impr
ovem
ent
Pro
ject
in
Nep
al
App
endi
x
A-4
2
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-43
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-44
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-45
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-46
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-47
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-48
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-49
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-50
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-51
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-52
A-4-3 Minutes of Discussions on the Schematic Design Overview
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-53
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-54
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-55
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-56
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-57
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-58
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-59
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-60
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-61
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-62
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-63
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-64
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-65
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-66
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-67
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-68
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-69
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-70
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-71
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-72
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-73
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-74
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-75
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-76
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-77
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-78
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-79
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-80
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-81
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-82
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-83
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-84
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-85
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-86
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-87
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-88
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-89
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-90
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-91
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-92
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-93
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-94
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-95
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-96
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-97
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-98
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-99
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-100
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-101
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-102
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-103
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-104
Preparatory Survey on P
okhara Water Supply Im
provement P
roject in Nepal
Appendix
A-105
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-106
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-107
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-108
A-5 Soft Component (Technical Assistance) Plan
1. Background of Planning Soft Component
The Project covers construction of a new WTP and reservoirs, improvement of transmission and distribution pipelines, and provision of customer meters in Pokhara City and its surrounding two villages. The Project contributes to the improvement of the NWSC Pokhara Branch’s financial situation and living environment for citizens of Pokhara by improving the water supply system (such as drinking water quality and water supply conditions).
1) Current Condition
Water supply service in Pokhara is operated by NWSC Pokhara Branch, and the branch has the following technical problems on their services.
a. Water quality: the system does not have a water treatment plant and supplying water is unsafe and high turbidity, especially in rainy season.
b. Inhomogeneous water supply: water supply in the service area is uneven water supply, due to lack of capacity in the water sources, lack of capacity in the existing pipeline network, and inadequate operation of the water distribution.
c. Lack of capacity of facilities: current water demand assumes about 62,000m3/day assumed from service population of 304,900, daily average water consumption of 130 L/capita/day and leakage of 36 %. But actual water supply is about 54,120m3/day. The current supply capacity is short.
d. High rate of leakage: The current rate of leakage assumed about 36%, and more than a half of the raw water is unaccounted for water.
e. O&M capacity: operation/maintenance of water supply facilities in Pokhara is done without manual/Standard Operating Procedure (SOP). Instructions to operators are given in verbal and symptomatic way. There is no systematic training program. Also there is no regular inspection and maintenance record.
Furthermore, it can be expected to improve in business conditions of NWSC Pokhara Branch by improving such technical problems. In particular, lack of the appropriate water distribution technology and high leakage rate has become a major cause of the short of income, by improving these causes. Improvement of business conditions can be expected, and NWSC Pokhara Branch becomes better management conditions.
2) Necessity of Soft Component
The Project will cover the construction of water supply facilities, water reservoirs and installation of clear water transmission pipes, distribution pipes. The outline scope of the Project is shown in Table.
Table-1 Outline of the Project Facilities/ Items Contents of the Proposed Facilities
Facilities Construction Raw Water Transmission Pipe Dia. 800mm, Length 1.2km
(Replacement)
Grit Chamber/ Sedimentation Tank 42,000m3/day
WTP Slow Sand Filter 41,000m3/day
Clear Water Transmission Pipe Dia. 300-500mm, Length 7.9km
Reservoir, Overhead Tank Water Reservoir: 2 tanks Overhead Tank :1 tank
Distribution Main Dia. 150-500mm, Length 49.8km
Distribution Sub Main Dia. 50-150mm, Length 52.9km
Service Pipe 7,300 Locations
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-109
Facilities/ Items Contents of the Proposed Facilities
Facilities Rehabilitation Existing Reservoir 2 nos
Rehabilitation of Chlorination Facilities Flow Metter Dia. 200-400mm
Existing Elevated Tank Flow Metter Dia. 200mm, Dia. 400
Existing Tube Well 3 nos Flow Meter
Material and Equipment Procurement
Customer Meter 9,000 units
Water Quality Analysis Equipment 1 lot
Small Size Excavator 2 units
Pipe Detector 2 units
Valve Detector 2 units
Soft Component (S/C) - O&M of Constructed Facilities - O&M of Distribution System - Quality Control of Service Pipe
Installation - Water Quality Analysis
Detailed Design and Construction Supervision 1 set Presently, NWSC Pokhara Branch does not own a grit chamber, sedimentation tank and WTP (slow sand filter). Therefore, they do not have any knowledge and or experience to operate and maintain the facilities, requiring the training for NWSC staff. Knowledge on water quality management is also required for them including measuring and control of water quality at the plant, reservoirs and tap. After completion of the Project, an effective and fair water distribution to meet demand by sub-service area is required. Moreover, a proper installation method shall be applied for house connections to improve current high water leakage in the distribution network. Activities related to soft component are necessary for NWSC to improve and enhance the capacity of operation and maintenance of the water supply facilities. 2. Target of Soft Component
This soft component provides technical guidance and training program relating to the operation and maintenance of water supply facilities, improvement of water quality, improvement of water supply frequency, after construction, commissioning, hand-over of water facilities developed in this project. The goal of this project is intended to help the improvement of water quality and reduction of the leakage, and to the improve its management of NWSC Pokhara Branch. 3. Target of Soft Component
The purpose of the soft Component is to provide technical staff of NWSC Pokhara Branch with the technical knowledge for proper and effective operation and maintenance of newly constructed water supply facilities. Concretely, technology transfer will be implemented on “O&M of WTP”, “O&M of Water Distribution System”, “Installation of Hose Connections” and “Water Quality Monitoring and Control”, and the following target. “Technical staff in NWSC Pokhara Branch obtain , a new operation and maintenance of construction and water purification facilities, operation and maintenance of appropriate water distribution system, appropriate water supply pipe laying, and the knowledge and necessary to the regular water supply water quality measurement and water quality management by learning the technology, which is the main business objectives improvement of water supply water quality, improvement of water supply frequency, reduction of water leakage, and NWSC management improvement of Pokhara branch office will be able to achieve.”
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-110
4. Assessment of Achievement
Table-2 shows the results and its assessment of the achievement of this soft component. Trainer will uses achievement checklist and assess the trainees’ understanding of the knowledge and technology.
Table-2 Soft Component and the Expected Result
Expected Result Assessment of Achievement
Result 1: O&M of WTP Able to properly operate and maintain water treatment facilities and produce good quality of drinking water continuously.
・Confirm the understanding of trainees by questions and answers on topics
lectures ・Confirm the understanding of trainees by actual O&M works of WTP
facilities and its reports. (Judgments will be made using the checklists)
Result 2: O&M of Water Distribution System Able to properly operate and maintain water distribution facilities and supply water efficiently.
・Confirm the understanding of trainees by questions and answers on topics
lectures ・Confirm the understanding of trainees by actual O&M works of water
distribution facilities and its reports. (Judgments will be made using the checklists)
Result 3: Installation of House Connections To reduce water leakage from house connections by gaining proper house connection techniques.
・Confirm the understanding of trainees by actual house connection installation
works. (Judgments will be made using the checklists)
Result 4: Water Quality Monitoring and Control To control water quality continuously by regular water monitoring of treatment and distribution network.
・Confirm the understanding of trainees by questions and answers on topics
lectures ・Confirm the understanding of trainees by actual measurement of its data.
(Judgments will be made using the checklists)
5. Activities of Soft Component
Soft components, Water Supply Consulting Engineers (Japanese consultants: water treatment process, water distribution system, house connection pipe, water quality), four Japanese consultants directly work for the period of 12.0 months, including works in Japan. Nepali local consultants and interpreter/translator will be hired to support in Japan consultants in local work each 10.5 months. Action plan is shown in Table-3.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-111
Table-3 Activities of Soft Component
Item Description Achievement Method Required Input Remarks
1. O&
M of C
onstructed Facilities
- to understand the component of water treatment facilities and objectives/function of each facilities
- to adequately control raw water intake to maintain required water production.
- to operate grit chamber/sedimentation tank running and cleaning.
- to operate roughing filters running and washing the filters to maintain required water.
- to operate slow sand filters running and cleaning the filters to maintain required water.
- to control chlorination system to maintain clear water to drinking water standard.
- to implement daily inspection and keep records of each component of water supply facilities
- to check water quality on turbidity, colour, pH and residual chlorine at each treatment process.
- Training Plan - Training Manual
(Operation Guideline)
- Reporting Format (Daily/Monthly Report)
- Trainees’ evaluation
- Classroom Training
- OJT at WTP - Trainee
Plant Manager/ Operators/ Operator Assistant (total: 15)
- Water Treatment Specialist (Japanese Consultant)
Planning: 1 x 0.5 month Training: 1 x 2 months in dry season/1 x 2 months in rainy season
- Local Consultant Translation: 1 x 4 months
OIC/Operators/ Operator Assistant should be assigned before implementation of this course.
2. O&
M of D
istribution System
- to understand the component of water distribution facilities and objectives/function of each facilities
- to understand how to control clear water to distribute in the network.
- to adequately operate clear water transmission lines to maintain water level in water reservoirs.
- to adequately monitor flow and pressure in the distribution system.
- to properly clean distribution pipes. - to properly monitor water leakage.
- Training Plan - Training Manual
(Maintenance Guideline)
- Reporting Format (Maintenance Report)
- Trainees’ evaluation
- Classroom Training
- OJT at WTP - Trainee
OIC/Supervisor/ Fitter/Labour (total: 10)
- Water Distribution Specialist (Japanese Consultant)
Planning: 1 x 0.5 month Training: 1 x 1.5 months in dry season/ 1 x 1.5 months in rainy season
- Local Consultant Translation: 1 x 3 months
OIC/Supervisor/ Fitter/Labour should be assigned before implementation of this course.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-112
Item Description Achievement Method Required Input Remarks
3. Quality C
ontrol of S
ervice Pipe
Installation
- to understand the boundary limit of NWSDB and house-owners
- to understand importance of water meters - to install house connections - to install/repair water meters - to implement pressure test - to prepare/store the installation record
- Training Plan - Training Manual
(House Connection Guideline)
- Reporting Format (Service Report)
- Trainees’ evaluation
- Classroom Training
- OJT at field - Trainee Supervisor/
Fitter/Labour (total: 22)
- Piping Specialist (Japanese Consultant)
Planning: 1 x 0.5 month Training: 1 x 2 months - Local Consultant Translation: 1 x 2 months
Supervisor/ Fitter/Labour should be assigned before implementation of this course.
4. Water Q
uality Analysis
- to understand the importance of monitor and control water quality
- to set regular water quality monitoring points in the distribution network.
- to understand the component of water supply facilities and objectives/function of each facilities
- to set the water quality target at each treatment process.
- Training Plan - Training Manual
(House Connection Guideline)
- Reporting Format (Service Report)
- Trainees’ evaluation
- Classroom Training
- OJT at WTP - Trainee Chemist/ Assistant (total: 4) Plat Manage/
Operators/ Operator Assistant
(total: 10)
- Water Quality Specialist (Japanese Consultant)
- Water Treatment Specialist (Japanese Consultants)
Planning: 1 x 0.5 month Training: 1 x 1 month - Local Consultant Translation: 1 x 1 month
Plant manager/ Chemist/ Assistants should be assigned before implementation of this course.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-113
6. Procurement of Resources for Soft Component
Soft component will be implemented through direct-assistant by four Japanese consultants with assistance
of Nepali consultants and interpreter/translator, because the technology is hardly implemented by the Nepali
consultant alone.
7. Schedule of Project and Soft Component
Overall schedule of this Project is shown in Table-4.
Table-4 Overall Schedule of the Project
Soft component will be stared in 35th month from this project start for dry season component and in 43th
month for rainy season component. However, for the "water quality analysis and control" will start in 27th
month to collect water quality data necessary for WTP operation.
In implementing the soft component, first, starts developing a training plan in Japan, to determine the
specific implementation processes and training procedures.
Then, the technology transfer related to the operation and maintenance will be performed using the actual
facility after the construction of major facilities has been completed. ("O&M of water treatment plant",
"O&M of water distribution system", and "water quality analysis and control"). As for "O&M of water
treatment plant", due to change the quality of raw water in the dry season and rainy season, at first, training
of water treatment technology by slow filtration is implemented considering that the operation is relatively
easy in dry season. Then, training will be done to monitor the status of the raw water turbidity, to understand
the measures necessary situation of water intake and to determine limit or stop the raw water at high
turbidity of the rainy season. In addition, by operating grit chamber and sedimentation basin (pre-treatment)
of the raw water with high turbidity, sent to slow sand filter.
In order to perform the water purification process, this pre-treatment facility operation and maintenance
technology shall be studied. In addition, in the water distribution system is also the dry season and the rainy
0 1 2 3 4 8 9 10 11 12 13 14 16 17 18 20 21 22 23 24 25 26 28 29 30 31 33 34 35 36 37 38 39 40 41 42 44
(Field Survey)
(Detail Design in Japan)
【Detail Design】
(Field Survey) Total 6 Months
0 1 2 3 4 8 9 10 11 12 13 14 16 17 18 20 21 22 23 24 25 26 28 29 30 31 33 34 35 36 37 38 39 40 41 42 44
(Prepartaion Works)
(Construction of Grit Chamber/Sedimentation Tank)
(Installation of Raw Water Transmission Pipe)
(Construction of Water Treatment Plant(C & A))
【Construction Works】
(Construction of Water Treatment Plant(M & E)) Total 30 Months
(Construction of Transmission & Distribution Facilities)
(Test Run & Inspection)
(Procurement of Equioment) 【Procurement】
Total 19 Months
(Soft Component)
【Soft Component】
Total 4.75 Months
43 45 46
43 45 4632
Cons
tructio
n w
ork
s , P
rocurm
ent a
nd S
oft C
om
pone
nts
Deta
il Desig
n
5 6 7 15 19 27
5 6 7 15 19 3227
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-114
season, because the water distribution methods are different, divided into two times of the dry season, the
rainy season, to understand the appropriate method of operating water distribution system. As for "Water
quality analysis and control", it is necessary to implement simultaneously with ("O&M of water treatment
plant", "O&M of water distribution system".
Implementation Schedule of Soft Component is shown in Figure-5
Japanese
Consultant 27 28 35 36 37 38 44 45 46 47
Construction Work (WTP) Test Operation
O&M of WTP Water
Treatment Process
12days
30 days
30 days
15 days
30 days
15 days
3 days
O&M of Water Distribution System
Water Supply System
12 days
30 days
15 days
15 days
30 days
3 days
Installation of House Connections
House Connection
4 days
30 days
30 days
2
days
Water Quality Monitoring and Control
Water Quality
15 days
4 days 2 days
15 days
30 days 3 days
Report/Manual
Training
Manual
Traini
ng Manual
Training Manual
Report
NWSC Employee for new assignment
WTP Manager-1 Chemist-1 Helper-1
Pre-Treatment Operator-3/ WTP Operator-9 Distribution Plumber-4/Meter Reader-4
Figure-5 Soft Component – Implementation Schedule (Tentative)
8. Schedule of Project and Soft Component
Overall schedule of this Project is shown in Table-4.
Table-4 Reports/Manuals Item Reports/Manuals Contents Submission Page
Manual Water treatment facilities - operation manual (English-5/Nepali-20)
- Function of treatment facilities - Operation of each facility - Operation recording
46th month 30
Water treatment facilities - maintenance manual (English-5/Nepali-20)
- Cleaning of treatment facilities - Scraping of filter sand - Washing of filter sand - Maintenance recording
46th month 20
Water distribution facilities – operation/maintenance manual (English-5/Nepali-20)
- Function of water distribution facilities
- Operation of each facility - Operation/maintenance recording
45th month 30
Work in Japan
Work in Nepal
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-115
House connection - installation manual (English-5/Nepali-30)
- Installation of house connection - Installation of water meter - repair of existing house
connection
37th month 20
Water quality analysis - manual (English-5/Nepali-15)
- procedure of water analysis 28th month 20
Water quality control - manual (English-5/Nepali-15)
- procedure of water analysis in water distribution system 45th month 20
Report Completion Report (both Japanese and Nepali sides)
- Plan and actual - Result/Achievement - Impact effected to result/
achievement - Lesson learned and suggestions
etc. for sustaining and developing the results
- Reports/Manuals
46th month 30
9. Responsibility of Nepal side
The followings are responsibility of Nepal side for the implementation of soft component.
◇Providing trainees, facilities and materials required
◇All cost for trainees, facilities and materials required
◇All necessary manpower, materials, etc. required for continuous energy audit activities.
A-116
A-6
Oth
er Relevan
t Data
A-6-1 L
and
Ac
qu
isition
Mo
nito
ring
Fo
rm
A-117
A-118
A-119
A-120
A-6-2 Monitoring Form (Draft)
Monitoring Form (Draft)
Part I: Environemental and Social Impact
1. Natural Environment
1-1 Air Quality
Item Unit Measured
Value (Mean)
Measured Value (Max.)
Standard in Nepal(Annual/24hours)
Remarks*
1 TPS μg/m3 -/230
2 PM10 μg/m3 -/120
3 Suplhur Dioxide μg/m3 50/70
4 Nitrogen Dioxide μg/m3 40/80
5 Carbon Monoxide μg/m3 10,000/100,000**
6 Lead μg/m3 0.5/0
7 Benzene μg/m3 20/0 *Location, method, frequency shall be described. **8hours/15minutes
1-2 Noise and Vibration
Date Reported Problem/Complain Proposed Solution Solved In case “Solved-No”,
describe further action
1 Yes / No
2
1-3 Odor
Date Reported Problem/Complain Proposed Solution Solved In case “Solved-No”,
describe further action
1 Yes / No
2
1-4 Soil Pollution
No. Monitoring Factor Monitoring Place Monitoring Method
Frequency Monitoring Result
(1) Soil erosion and turbidity of surface water
Downstream point near construction site of intake weir and
Measure of turbidity
At the transportation time of sludge
A-121
No. Monitoring Factor Monitoring Place Monitoring Method
Frequency Monitoring Result
of outlet of discharge pipes.
1-5 Solid Waste
No. Monitoring Factor Monitoring Place Monitoring Method
Frequency Monitoring Result
(1) Adequate treatment of solid wastes
All construction sites, laborers camps and its neighboring areas
Physical observation
Once/week
1-6 Working Environment
No. Monitoring Factor Monitoring Place Monitoring Method
Frequency Monitoring Result
Risk of HIV/AIDS and other infections (1) Control risk of HIV/AIDS All construction
sites Physical
observation During
construction
Workplace Safety (2) Wear of safety shoes and hats
and safety control manners at construction sites
All construction sites
Physical observation
Once/week
Accidents (3) Adequate safety traffic
control manners Entrance and exit for construction of new water treatment plant, ground reservoir, transmission pipelines, water intake weir.
Physical observation
Two times/week
(4) Fallen object and grade of dirtiness of roads
Passage roads of vehicles for transportation of equipment and materials, and surplus excavation soils.
Physical observation
Two times/week
A-122
2. Social Environment
2-1 Resettlement/Land Acquisition
Date Reported Problem/Complain Proposed Solution Solved In case “Solved-No”,
describe further action
1 Yes / No
2
2-2 Public Consultation
Date Place Contents of the consultation/main comments and answers
1
Issues (example)
Chage of livelihood
Change of economical situation of PAPs
Other problems related to land acquisition & involuntary resettlement
2
A-123
3.Environmental Standard
3-1 Ambient Air Quality
Table 1: National Ambient Air Quality Standard, 2003
Parameters Units Averaging
Time
Concentration in Ambient Air,
maximum Test Methods
TSP (Total Suspended Particulates)
μg/m3 Annual - -
24-hours* 230 High Volume Sampling
PM10 μg/m3 Annual -
24-hours* 120 Low Volume Sampling
Sulphur Dioxide μg/m3 Annual 50
Diffusive sampling based on weekly average
24-hours** 70 To be determined before 2005 A.D.
Nitrogen Dioxide μg/m3 Annual 40
Diffusive sampling based on weekly average
24-hours** 80 To be determined before 2005 A.D.
Carbon Monoxide μg/m3 8 hours** 10,000 To be determined before 2005 A.D.
15 minute 100,000 Indicative samplers**
Lead μg/m3 Annual 0.5
Atomic Absorption Spectrometry, analysis of PM10 samples****
24-hours 0 -
Benzene μg/m3 Annual 20*****
Diffusive sampling based on weekly average
24-hours -
*Note: 24 hourly values shall be met 95% of the time in a year. 18 days per calendar year the standard may be exceeded but not on two consecutive days. **Note: 24 hourly standards for NO2 and SO2 and 8 hours standard for CO are not to be controlled before MoPE has recommended appropriate test methodologies. This will be done before 2005. ***Note: Control by spot sampling at roadside locations: Minimum one sample per week taken over 15 minutes during peak traffic hours, i.e. in the period 8am - 10am or 3pm - 6pm on a workday. This test method will be re-evaluated by 2005. ****Note: If representativeness can be proven, yearly averages can be calculated from PM10 samples from selected weekdays from each month of the year. *****Note: To be re-evaluated by 2005.
3-2 Noise
Table 2: National noise quality standard, 2069
Area Noise Limit (dB)
Day Night
Industrial Area 75 70
Business Area 65 55
Rural Residential Area 45 40
Urban Residential Area 55 50
Mixed Residential Area 63 55
Peace Zones/Area 50 40
A-124
Part II: Economic Impact to Project Affected Persons (PAPs)
4.1 Monitoring of Economic Impact to PAPs
Household ID
Name of Household Head
Income revel before the project start*
(Unit: NPR/per)
Date of Interview
Income lever at interview date
(Unit: NPR/per)
PAPs Opinion of economic situation at interview date compare to before the project start**
Evaluation
(1) (2) (3) (4) (5)
(1) (2) (3) (4) (5)
(1) (2) (3) (4) (5)
(1) (2) (3) (4) (5)
(1) (2) (3) (4) (5)
(1) (2) (3) (4) (5)
(1) (2) (3) (4) (5)
*Refer to RAP report of the project ** (1) Obviously bad, (2) Relatively Bad, (3) No change, (4) Relatively better, (5) Obviously better
4-2 Monitoring of Impact to the Involuntary Resettlement Household
Household ID Name of Household Head Date of Interview
Income revel before the project start*
(Unit: NPR/per)
Income lever at interview date
(Unit: NPR/per)
Opinion of the household in terms of economic situation at interview date compare to before the project start**
Opinion of the household in terms of general situation all over their livelihood
Evaluation
(1) (2) (3) (4) (5) (1) (2) (3) (4) (5)
*Refer to RAP report of the project ** (1) Obviously bad, (2) Relatively Bad, (3) No change, (4) Relatively better, (5) Obviously better
A-125
A-6-3 JICA Environmental Checklist
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
1 Permits and
Explanation
(1) EIA and
Environmental
Permits
(a) Have EIA reports been already prepared in
official process?
(b) Have EIA reports been approved by
authorities of the host country's government?
(c) Have EIA reports been unconditionally
approved? If conditions are imposed on the
approval of EIA reports, are the conditions
satisfied?
(d) In addition to the above approvals, have other
required environmental permits been obtained
from the appropriate regulatory authorities of the
host country's government?
(a) Y
(b) Y*
(c) Y*
(d)N
(a)(b) EIA is started to prepare on July 2015.
The process of EIA has two stages, first stage
is approval of Scoping and TOR, and second
stage is approval of EIA Report. Approval of
Scoping and TOR document was done on
December 2015. Meanwhile, approval of EIA
report is planned on July 2016.
(c) No condition was required at the approval
of first stage of EIA documentation (Scoping
and TOR). In case any conditions will be
added in further process, NWSC shall satisfy
the condition and requirement for EIA
approval.
(d) Not applicable.
(2) Explanation to the
Local Stakeholders
(a) Have contents of the project and the potential
impacts been adequately explained to the Local
stakeholders based on appropriate procedures,
including information disclosure? Is
understanding obtained from the Local
stakeholders?
(a) Y
(b) Y
(a) Local people are notified through
publication of notice and frequent
consultations. There is no objection from
local stakeholders to the project.
(b) Suggestions provided by the local people
are addressed in the EIA report.
A-126
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
(b) Have the comment from the stakeholders
(such as local residents) been reflected to the
project design?
(3) Examination of
Alternatives
(a) Have alternative plans of the project been
examined with social and environmental
considerations?
(a) Y (a) Alternatives for the project, including no
project implementation, are examined.
2 Pollution Control (1) Air Quality (a) Is there a possibility that chlorine from
chlorine storage facilities and chlorine injection
facilities will cause air pollution? Are any
mitigating measures taken?
(b) Do chlorine concentrations within the working
environments comply with the country’s
occupational health and safety standards?
(a) N
(b) Y
(a) Storage shall be done in safe and leakage
free storage tank.
(b) National Ambient Air Quality Standards
for Nepal 2003 is applicable for this issue.
(2) Water Quality (a) Do pollutants, such as SS, BOD, COD
contained in effluents discharged by the facility
operations comply with the country’s effluent
standards?
(a) Y (a) Effluents will be disposed safely ensuring
minimum environmental impacts. For
monitoring, National Drinking Water Quality
Standards (NDWQS) shall be applicable.
(3) Wastes (a) Are wastes, such as sludge generated by the
facility operations properly treated and disposed
in accordance with the country’s regulations?
(a) Y (a) All waste shall be treated in accordance
with Solid Waste Management Act 2011.
Generated waste will be disposed in safe
disposal area at Tallo Purunchaur Phant with
A-127
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
retaining structures to avoid run off, wash off
during rainy season.
(4) Noise and
Vibration
(a) Do noise and vibrations generated from the
facilities, such as pumping stations comply with
the country’s standards?
(a) Y (a) There is no environmental standard for
noise in Nepal. However, significant noise
and vibration impact is not expected since
noise-free facilities, such as underwater pump
and noise-free generator are used in the
project. In case of problems of noise, the
project side takes care as per complaints by
residents.
(5) Subsidence (a) In the case of extraction of a large volume of
groundwater, is there a possibility that the
extraction of groundwater will cause subsidence?
(a) N (a) The project will use only surface water
source of Mardi river.
3 Natural
Environment
(1) Protected Areas (a) Is the project site or discharge area located in
protected areas designated by the country’s laws
or international treaties and conventions? Is
there a possibility that the project will affect the
protected areas?
(a) N (a) Both of the project site and discharge area
are not applicable for international treaties
and conventions in Nepal.
(2) Ecosystem (a) Does the project site encompass primeval
forests, tropical rain forests, ecologically valuable
habitats (e.g., coral reefs, mangroves, or tidal
flats)?
(a) N
(b) N
(c) N
(d) N
(a) The project does not lie in forest area/
conservation area with high value of
ecological importance.
(b) Project site or discharge area doesn’t lie in
the protected habitats of endangered species.
A-128
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
(b) Does the project site or discharge area
encompass the protected habitats of endangered
species designated by the country’s laws or
international treaties and conventions?
(c) If significant ecological impacts are
anticipated, are adequate protection measures
taken to reduce the impacts on the ecosystem?
(d) Is there a possibility that the amount of
water used (e.g., surface water, groundwater) by
project will adversely affect aquatic
environments, such as rivers? Are adequate
measures taken to reduce the impacts on aquatic
environments, such as aquatic organisms?
(c) The project does not lie in forest area/
conservation area with high value of
ecological importance.
(d) The project will use water of Mardi khola.
However, no dangerous chemicals are applied
for water treatment process, and discharge
water from the plant is environmentally
harmful.
(3) Hydrology (a) Is there a possibility that the amount of water
used (e.g., surface water, groundwater) by the
project will adversely affect surface water and
groundwater flows?
(a) N (a) The project will use water that collected
from Mardi khola by existing intake facility.
No new water-source development is carried
out, and no impact to hydrogeology.
A-129
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
4 Social
Environment
(1) Resettlement (a) Is involuntary resettlement caused by project
implementation? If involuntary resettlement is
caused, are efforts made to minimize the impacts
caused by the resettlement?
(b) Is adequate explanation on compensation and
resettlement assistance given to affected people
prior to resettlement?
(c) Is the resettlement plan, including
compensation with full replacement costs,
restoration of livelihoods and living standards
developed based on socioeconomic studies on
resettlement?
(d) Is the compensations going to be paid prior to
the resettlement?
(e) Is the compensation policies prepared in
document? (f) Does the resettlement plan pay
particular attention to vulnerable groups or
people, including women, children, the elderly,
people below the poverty line, ethnic minorities,
and indigenous peoples?
(g) Are agreements with the affected people
obtained prior to resettlement?
(h) Is the organizational framework established to
properly implement resettlement? Are the
(a) Y
(b)Y
(c) Y
(d) Y
(e) N
(f) Y
(g) Y
(h) N
(i) Y
(j) Y
(a) There is a house in the site, and the
household have to move out. This household
already agreed to involuntary resettlement
with NWSC, and they are satisfied proposed
compensation for their damages caused by the
involuntary resettlement. In addition, land
acquisition is carried out for 59 landowners,
and compensation is planned to be paid by
reference with reasonable price which able to
purchase other land in same value in other
place.
(b) Entitlement, including compensation, is
explained several times during public
consultations, resettlement survey, and
distribution of Application format.
(c) Resettlement Action Plan (RAP),
including socio-economic survey, was
prepared.
(d) NWSC will have power to control the
project site only after landowners and
residents will receive compensation and
ownership will be changed officially.
(e) Compensation policies are discussed and
recognized in PAPs though public
A-130
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
capacity and budget secured to implement the
plan?
(i) Are any plans developed to monitor the
impacts of resettlement?
(j) Is the grievance redress mechanism
established?
consultations, resettlement survey, and
distribution of Application. In addition, RAP
is prepared along with JICA’s regulation, and
all entitlement is written in the RAP report.
(f) Socially vulnerable households, such as
woman-headed households, are reported in
RAP. Life-support compensation is planned to
be paid to these households.
(g) Agreement had made prior to resettlement.
In NWSC’s system, resettlement can start
only after “Application” has submitted.
Application is NWSC’s document form which
shows agreement with affected persons in
terms of land acquisition and resettlement.
(h) NWSC, the implementing organization,
has a system of dealing with resettlement land
acquisition, and it has all responsibilities
including budget arrangement and
implementation of the project.
(i) Monitoring for land acquisition progress,
receipt of compensation, and economic
situation of PAPs are planned.
A-131
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
(j) Grievance redress mechanism is prepared
to address disputes, and mainly it will be
handled in CDC (Chief District Office)
4 Social
Environment
(2) Living and
Livelihood
(a) Is there a possibility that the project will
adversely affect the living conditions of
inhabitants? Are adequate measures considered to
reduce the impacts, if necessary?
(b) Is there a possibility that the amount of water
used (e.g., surface water, groundwater) by the
project will adversely affect the existing water
uses and water area uses?
(a) Y
(b) N
(a) Impact on land acquisition is major issue
for local people’s life and livelihood. In
addition to cash compensation, additional
assistance (additional payment) will be made
for valuable households such as woman-
headed households and handicapped
households.
(b) Mardi river is not used for drinking/
irrigation and recreation purpose. So no any
adverse impact is predicted on water use
issues
(3) Heritage (a) Is there a possibility that the project will
damage the local archeological, historical,
cultural, and religious heritage? Are adequate
(a) N (a) The project area does not have any
archaeological sites with historical and
cultural value.
A-132
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
measures considered to protect these sites in
accordance with the country’s laws?
(4) Landscape (a) Is there a possibility that the project will
adversely affect the local landscape? Are
necessary measures taken?
(a) N (a) The major construction building is water
treatment plant in this project, and this is
one story building. Therefore, there
is no impact to the surrounding
landscape.
(5) Ethnic Minorities
and Indigenous
Peoples
(a) Are considerations given to reduce impacts on
the culture and lifestyle of ethnic minorities and
indigenous peoples?
(b) Are all of the rights of ethnic minorities and
indigenous peoples in relation to land and
resources respected?
(a) N/A
(b) N/A
(a)(b) There are no ethnic minorities and
indigenous people that applicable for World
Bank OP.4.10.
(6) Working
Conditions
(a) Is the project proponent not violating any laws
and ordinances associated with the working
conditions of the country which the project
proponent should observe in the project?
(b) Are tangible safety considerations in place for
individuals involved in the project, such as the
installation of safety equipment which prevents
industrial accidents, and management of
hazardous materials?
(c) Are intangible measures being planned and
implemented for individuals involved in the
(a) Y
(b)Y
(c) Y
(d)Y
(a) The project will be constructed /operated
within all the legal provisions set forth by the
GoN
(b) Adequate PPEs are proposed for the
workers.
(c) Workers will be trained well regarding
health and safety matters.
(d) Project area is controlled and observer
for local security.
A-133
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
project, such as the establishment of a safety
and health program, and safety training (including
traffic safety and public health) for workers etc.?
(d) Are appropriate measures taken to ensure that
security guards involved in the project not to
violate safety of other individuals involved, or
local residents?
5 Others (1) Impacts during
Construction
(a) Are adequate measures considered to reduce
impacts during construction (e.g., noise,
vibrations, turbid water, dust, exhaust gases, and
wastes)?
(b) If construction activities adversely affect the
natural environment (ecosystem), are adequate
measures considered to reduce impacts?
(c) If construction activities adversely affect the
social environment, are adequate measures
considered to reduce impacts?
(d) If the construction activities might cause
traffic congestion, are adequate measures
considered to reduce such impacts?
(a) Y
(b) Y
(c) Y
(d) Y
(a)Appropriate mitigation measures are
proposed to reduce impacts during
construction (e.g., noise, turbid water, dust,
exhaust gases, and wastes). Implementation of
monitoring is proposed in Environmental
Monitoring Plan (EMP).
(b) No impact to natural environment is
assumed.
(c) Appropriate mitigation measures with
sufficient budget are proposed to
avoid/minimize/compensate the impact.
Mitigation measures in environmental/social
impact from the project are described in EMP
and RAP respectively.
(d)Traffic signs, speed limits, transportation
by covering the materials are proposed.
A-134
Category Environmental Item Main Check Items Yes: Y
No: N
Confirmation of Environmental
Considerations
(Reasons, Mitigation Measures)
5 Others (2) Monitoring (a) Does the proponent develop and implement
monitoring program for the environmental items
that are considered to have potential impacts?
(b) What are the items, methods and frequencies
of the monitoring program? (c) Does the
proponent establish an adequate monitoring
framework (organization, personnel, equipment,
and adequate budget to sustain the monitoring
framework)?
(d) Are any regulatory requirements pertaining to
the monitoring report system identified, such as
the format and frequency of reports from the
proponent to the regulatory authorities?
(a)Y
(b)Y
(c)Y
(d)Y
(a) Monitoring program is proposed with
adequate budget
(b) Monitoring items such as air quality, water
quality, noise level, impact due to waste
disposal etc. are proposed during construction
and operation phase. Monitoring of social
parameters is also proposed in EIA with
regard to project location and project affected
people.
(c) Monitoring program is proposed with
adequate budget
(d) Monitoring is planned in quarterly bases,
and checklist is attached in the EIA report.
6 Note Reference to Checklist
of Other Sectors
(a) Where necessary, pertinent items described in
the Dam and River Projects checklist should also
be checked.
(a)N (a) Not Applicable
Note on Using
Environmental
Checklist
(a) If necessary, the impacts to transboundary or
global issues should be confirmed (e.g., the
project includes factors that may cause problems,
such as transboundary waste treatment, acid rain,
destruction of the ozone layer, or global
warming).
(a)N (a) Not Applicable
A-135
A-6-4 Seismic Capacity of Pipes Selected in the Project Material and joint type of transmission and distribution pipes selected in the project are as follow;
Transmission pipes and distribution main: Ductile iron (DI) pipe (tyton type joint)
Distribution sub-main: Polyethylene (PE) pipe
DI pipe is selected due to its durability as the material of main pipes; transmission pipes and distribution
mains. PE pipe is selected as the material of distribution sub-mains because distribution sub-mains are low
priority compared to main pipes.
Ministry of Health, Labor and Welfare of Japan defined seismic capacity of pipes on material and joint type
basis in their report. DI pipe (K type joint) was reported to have seismic capacity against level 1 earthquake
and even level 2 earthquake only under the hard ground. DI pipe (tyton type joint) can be considered to
have the same level of seismic capacity as DI pipe (K type joint). On the other hand, PE pipe also have
seismic capacity against both of level 1 and level 2 earthquakes.
Level 1 and level 2 earthquakes were defined by Japan Water Works Association as follows;
Level 1 earthquake; earthquake which likely occur during service period on facility location
Level 2 earthquake; largest scale of earthquake which possibly occur in the future on facility location
Generally, service period of pipes is considered to be for 50 years. Large earthquake occurred on April 25,
2015 in Nepal is after 81 years from the same magnitude level of earthquake occurred in 1934. Therefore,
such a large earthquake, level 2 earthquake, will not be likely to occur during service period of pipes.
Pokhara is undulating hills and categorized as a gravel/rock plateau and terrace which can be considered as
hard ground. In addition, N value near the ground surface is over 50 in the soil survey and this result
indicates pipes are laid under hard ground. For that reason, DI pipe (tyton type joint) can be consider having
enough seismic capacity against even level 2 earthquakes.
We concluded that material and joint type of pipes selected in the Project has enough seismic capacity
against earthquakes.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-136
A-6-5 Setting Basis of Water Leakage Rate after Completion of the Project Water leakage rate (Rate of real losses) before implementation of the Project is assumed as 36%, as
mentioned in “Section 2-2-1 Water Demand Analysis”. On the other hands, reduction of water leakage can
be expected through the Project by 1) replacement of existing distribution mains and optimization of water
pressure, 2) replacement of existing distribution sub-mains, and 3) renewal of customer meters and service
pipes.
In this section, effectiveness of water leakage reduction by these three ways was evaluated. And then the
water leakage rate after completion of the project was calculated. Calculation result is shown in Table A-
6-5-1.
Table A-6-5-1 Calculation Result of Water Leakage Rate after Completion of the Project
Items Unit Quantity Calculation Notes
(1) Laying of distribution mains km 50 (A), setting value Table A-6-2 (1)
(2) Laying of distribution sub-mains km 50 (B), setting value Table A-6-4 (1)
(3) Renewal of customer meters and service pipes
connection 9,000 (C), setting value Table A-6-5 (2)
(4) Distribution volume m3/day 54,120 (D), actual value ※1
(5) Consumption volume m3/day 21,609 (E), actual value ※2
(6) Water losses m3/day 32,511 (F) = (D) – (E)
(7) Water leakage (real losses) m3/day 19,507 (G) = (F) x 60%, assumed value ※3
(8) Water leakage rate before completion of the project
% 36% (H) = (G) / (D)
(9) Water leakage reduction by replacement of distribution mains and optimization of water pressure
m3/day 3,337 (I), assumed value Table A-6-2 (11)
+ Table A-6-3 (8)
(10) Water leakage reduction by replacement of distribution sub-mains
m3/day 500 (J), assumed value Table A-6-4 (11)
(11) Water leakage reduction by renewal of customer meters and service pipes
m3/day 3,051 (K), assumed value Table A-6-5 (13)
(12) Volume of water available after completion of the project
m3/day 29,497 (L) = (E) + (I) + (J) + (K)
(13) Water leakage rate after completion of the project % 27% (M) = ((D) – (L)) x 60% / (D)
As the result, the water leakage rate after completion of the project was calculated as 27%. Detail of the
calculation is mentioned below.
1. Water Leakage Reduction by Replacement of Distribution Mains and Optimization of
Water Pressure
Water leakage reduction by replacement of distribution mains can be divided into the reduction by
replacement of existing deteriorated cast iron pipes and the reduction by optimization of water pressure
with setting new water distribution areas. These two ways of reductions were evaluated below.
1.1 Water Leakage Reduction by Replacement of Distribution Mains
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-137
Water leakage reduction by replacement of existing distribution mains is shown in Table A-6-5-2.
Table A-6-5-2 Water Leakage Reduction by Replacement of Existing Cast Iron Mains
Items Unit Quantity Calculation Notes
(1) Laying of distribution mains km 50 (A), setting value
(2) Replacement of existing CI mains km 21 (B), setting value
(3) Distribution volume m3/day 54,120 (C), actual value ※1
(4) Consumption volume m3/day 21,609 (D), actual value ※2
(5) Water losses m3/day 32,511 (E) = (C) – (D)
(6) Water leakage (real losses) m3/day 19,507 (F) = (E) x 60%, assumed value ※3
(7) Water leakage rate % 36% (G) = (F) / (C)
(8) Water leakage from service pipes m3/day 11,700 (H) = (F) x 60%, assumed value ※4
(9) Water leakage from distribution pipes m3/day 7,803 (I) = (F) x 40%, assumed value ※4
(10) Reduction rate of water leakage after replacement of distribution mains
% 9.5% (J) = (B) / 220, assumed value ※5
(11) Water leakage reduction after replacement of distribution mains
m3/day 740 (K) = (I) x (J)
1.2 Water Leakage Reduction by Optimization of Water Pressure
Water distribution with optimum water pressure will be accomplished by setting new water distribution
areas through the construction of new water reservoirs and distribution mains. As the result, water leakage
due to high water pressure in existing distribution areas will be reduced.
Since elevation difference in the distribution areas of Bindhabashini reservoirs are larger than other existing
reservoirs, high water pressure in some areas leads to water leakage. Water pressure in some distribution
areas of Amalabisauni reservoir is also high. However, the distribution areas of Amalabisauni reservoir are
not clear. For that reason, water leakage reduction by optimization of water pressure was evaluated on the
distribution areas of Bindhabashini reservoir. Calculation result is shown in Table A-6-5-3.
Table A-6-5-3 Water Leakage Reduction by Optimization of Water Pressure
Items Unit Quantity Calculation Notes
(1) Water pressure in Bindhabashini distribution areas
m 130 (A), elevation of distribution areas is assumed as 930~800m
※6
(2) Average water pressure in Bindhabashini distribution areas
m 65 (B) = (A) / 2
(3) Water pressure after setting of new distribution areas
m 75 (C), assumed value ※7
(4) Average water pressure after setting of new distribution areas
m 38 (D) = (C) / 2
(5) Reduction rate of water leakage after setting of new distribution areas
% 24% (E)=1-((D) / (B))^0.5 ※8
(6) Distribution volume from Bindhabashini reservoir
m3/day 30,000 (F), actual value
(7) Water leakage in Bindhabashini m3/day 10,800 (G) = (F) x 36% ※9
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-138
Items Unit Quantity Calculation Notes
distribution areas
(8) Water leakage reduction by optimization of water pressure
m3/day 2,597 (H) = (G) x (E)
2. Water Leakage Reduction by Replacement of Distribution Sub-mains
Water leakage reduction by replacement of existing distribution sub-mains is shown in Table A-6-5-4.
Table A-6-5-4 Water Leakage Reduction by Replacement of Existing Sub-mains
Items Unit Quantity Calculation Notes
(1) Laying of distribution sub-mains km 50 (A), setting value
(2) Replacement of existing sub-mains km 14 (B), setting value
(3) Distribution volume m3/day 54,120 (C), actual value ※1
(4) Consumption volume m3/day 21,609 (D), actual value ※2
(5) Water losses m3/day 32,511 (E) = (C) – (D)
(6) Water leakage (real losses) m3/day 19,507 (F) = (E) x 60%, assumed value ※3
(7) Water leakage rate % 36% (G) = (F) / (C)
(8) Water leakage from service pipes m3/day 11,700 (H) = (F) x 60%, assumed value ※4
(9) Water leakage from distribution pipes m3/day 7,803 (I) = (F) x 40%, assumed value ※4
(10) Reduction rate of water leakage after replacement of distribution sub-mains
% 6.4% (J) = (B) / 220, assumed value ※5
(11) Water leakage reduction after replacement of distribution sub-mains
m3/day 500 (K) = (I) x (J)
3. Renewal of Customer Meters and Service Pipes through the Project
Water leakage from service connections will be reduced by renewal of customer meters and service pipes.
Water leakage reduction by renewal of customer meters and service pipes are shown in Table A-6-5-5.
Table A-6-5-5 Water Leakage Reduction by Renewal of Customer Meters and Service Pipes
Items Unit Quantity Calculation Notes
(1) Total number of service connection connection 34,523 (A), actual value
(2) Renewal of customer meters and service pipes
connection 9,000 (B), setting value
(3) Distribution volume m3/day 54,120 (C), actual value ※1
(4) Consumption volume m3/day 21,609 (D), actual value ※2
(5) Water losses m3/day 32,511 (E) = (D) – (C)
(6) Water leakage (real losses) m3/day 19,507 (F) = (E) x 60%, assumed value ※3
(7) Water leakage rate % 36% (G) = (F) / (C)
(8) Water consumption per connection m3/connection/day 0.63 (H) = (D) / (A)
(9) Water consumption per capita L/capita/day 130 (I), assumed value
(10) Number of users per connection capita/connection 4.8 (J) = (H) / (I)
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-139
(11) Water leakage from service pipes m3/day 11,704 (K) = (F) x 60%, assumed value ※4
(12) Water leakage from distribution pipes m3/day 7,803 (L) = (F) x 40%, assumed value ※4
(13) Water leakage reduction by renewal of customer meters and service pipes
m3/day 3,051 (M) = (K) x ((B) / (A))
※1 “Distribution volume” is estimated as shown in Table A-6-5-6.
Table A-6-5-6 Distribution Volume
Water source Capacity (m3/day) Notes
Mardi Khola 46,000 Result of flow measurement by JICA survey team
Bhote Khola 1,500
Kali Khola 2,000
Baldhara Spring 300
Deep Well 4,320 1 m3/min×3 wells =1,440 m3/day×3 wells
Total 54,120
* Capacities of Bhote Khola, Kali Khola, Baldhara spring were determined by referring to “Pokhara Water Supply Report (2005). The capacities of Bhote Khola, Kali Khola in this table represent the minimum amount in the dry season. The average amount for these is as follows. Bhote Khola = 1,500~5,000m3/day, Kali Khola = 2,000~5,000m3/day (Pokhara Water Supply Report, 2005)
※2 “Water Consumption” is estimated as shown in Table A-6-5-7.
Table A-6-5-7 Detail of Water Consumption
Breakdown Water Amount
(m3/day)
I. Billed Consumption (A+B+C ) 21,043
(A) Small Consumer 20,666
(B) Large Consumer 268
(C) Tourist 109
II. Unbilled Consumption (D) 675
(D) Public water stand 675
Total = I + II 21,718
※3 “Water leakage (real losses)” is calculated as follows:
“Water Leakage” = “Water Losses” × 60%*
*Referring to the Challenge of Reducing Non-Revenue Water in Developing Countries, World Bank (2006)
※4 “Water leakage from service pipes and distribution mains” are set at 60% for service pipes and 40%
for distribution mains referring to “Nepal- Leak Detection and Waste Control Program, IDA (1995)”.
※5 “Reduction rate of water leakage by replacement of existing distribution mains/submains” is calculated
based on the length ratio of the replacement to total length of existing pipes. Total length of existing
pipes are approximately 220 km.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-140
“Reduction rate of water leakage by replacement of existing distribution mains/sub-mains (%)”
= “Length of replacement”/ “Total length of existing pipes (220 km)”
※6 “Water pressure in Bindhabashini distribution areas” is assumed as 130m which is elevation
difference between Bindhabashini reservoir (930m) and distribution area in South Pokhara (800m).
Although the distribution area of Bindhabashini reservoir covers to 750m at the boundary of Pokhara,
frequency of water supply is quite low in these distribution areas.
“Water pressure in the distribution areas from Bindhabashini reservoir”
= 930m – 800m = 130m
※7 “Water pressure after setting of new distribution areas” is set at 75m as mentioned in “2-2-5
Distribution Network”.
※8 “Reduction rate of water leakage after setting of new distribution areas” is calculated as follows:
Relation between water pressure and water leakage can be expressed with following equation on
the assumption that pore which water leaks from is a kind of orifice.
Q = C × A × P0.5
Q: Water leakage volume
C: Coefficient depending on the shape of the pole
A: Cross section of pole
P: Pipe internal water pressure
As water leakage is proportional to the second root of water pressure, reduction rate of water
leakage is calculated as follows:
“Reduction rate of water leakage after setting new distribution areas” =
1 – (“Average water pressure after setting new distribution areas”/”Average water pressure in
Bindhabashini distribution areas”) 0.5
※9 “Water leakage in Bindabashini distribution areas” is calculated based on current rate of water leakage
is 36%.
“Water leakage in Bindhabashini distribution areas” = 30,000 × 36%
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-141
A-6-6 Water Quality of the Mardi River and Others
Water quality analysis of raw water samples taken at 4 existing intake points (Mardi River, Baldhara Spring,
Bhote River, Kali River) and tap water was conducted in the survey. The raw water sampling was collected
in both dry and rainy seasons at each point. Water quality analysis was contracted out to official institute
in Nepal and Japan.
1 Result of Water Quality Analysis of Mardi River
(1) Result of Water Quality Analysis in Dry Season
Sampling point: 4 existing intakes
Number of times: Twice in Nepal and once in Japan (from late April to beginning of May)
Analysis parameters: 30 parameters including the items of national drinking water quality standards
in Nepal
Analysis result of raw water of the Mardi River in dry season is shown on Table A-7-1. The result shows
that turbidity and iron slightly exceeds the Nepal standards. Particular, iron exceeds 0.3mg/L on the result
of both analysis in Nepal and Japan.
In addition, odor and Aluminum also slightly exceeds Nepal standards on the result of analysis in Japan.
Table A-6-6-1 Result of Water Quality Analysis in Dry Season
1st 1st 2nd
Late Apr Late Apr Beginning of May
Color - 2 TCU < 5 < 5 5 (15) < 5
Turbidity - 4 NTU 22 3 5 (10) < 2
Electrical Conductivity (EC) μS/cm 171 µS/cm 167 191 1500
pH - 7.6 - 8.1 8.1 6.5-8.5 About 7.5
Total Dissolved Solid (TDS) mg/L 120 mg/L 90 95 1000
Taste - missing data Non-Objctional Non-Objctional
Odor - Fine earthy mg/L Odourless Odourless Non-Objctional Non-Objctional
Iron (Fe) mg/L 0.76 mg/L 1.2 0.53 0.3 (3) 0.3
Manganese (Mn) mg/L 0.02 mg/L < 0.05 < 0.05 0.2 0.05
Arsenic (As) mg/L 0.001 mg/L < 0.005 < 0.005 0.05 0.01
Cadmium (Cd) mg/L <0.0003 mg/L < 0.003 < 0.003 0.003 0.003
Chromium (Cr) mg/L <0.005 mg/L < 0.02 < 0.02 0.05 0.05
Cyanide (CN-) mg/L <0.02 mg/L <0.05 <0.05 0.07 0.01
Lead (Pb) mg/L <0.001 mg/L < 0.01 < 0.01 0.01 0.01
Ammmonia (NH3) mg/L <0.1 mg/L 0.12 0.12 1.5
Chloride (Cl-) mg/L <1 mg/L 1 1 250 200
Sulphate (SO4--) mg/L 11 mg/L 1 1 250
Nitrate (NO3-) mg/L <1 mg/L 0.873 0.39 50 10
Copper (Cu) mg/L <0.1 mg/L < 0.02 < 0.02 1 1
Total Hardness mg/L 84 mg/L 84 92 500 300
Calcium (Ca) mg/L 22 200
Zinc (Zn) mg/L <0.1 mg/L < 0.05 < 0.05 3 1
Mercury (Hg) mg/L <0.0003 mg/L < 0.001 < 0.001 0.001 0.0005
Aluminum (Al) mg/L 0.39 mg/L < 0.05 < 0.05 0.2 0.1
Fluoride (F+) mg/L <0.08 mg/L < 0.5 < 0.5 0.5-1.5 0.8
E.Coli MPN/100mL 64 CFU/100ml TNTC 700 0 0
Total Coliform MPN/100mL 1100 CFU/100ml TNTC TNTC 0 in 95% Samples
General Bacteria MPN/mL 200 100MPN/mL
Selenium (Se) mg/L <0.001 0.01
Anionic Surfactant mg/L <0.02 0.2
Total Organic Carbon (TOC) mg/L 0.7 mg/L <0.02 0.23 3
Magnesium mg/L 5.24 5
Phosphate mg/l < 0.05 0.06
Sodium (Na) mg/L 2.68 3.18 200
Items
Analysis in Japan Analysis in Nepal
Nepali Standard Japanese StandardUnit Unit
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-142
(2) Result of Water Quality Analysis in Rainy Season
Sampling point: 4 existing intakes
Number of times: Once in Nepal and once in Japan (in late May)
Twice in Nepal and once in Japan (from mid to late August)
Analysis parameters: 30 parameters including the items of national drinking water quality standards
in Nepal and Cryptosporidium (once in Japan)
Analysis result of raw water of the Mardi River in rainy season is shown on Table A-7-2. As well as dry
season, the result shows that turbidity and iron slightly exceeds the Nepal standards. Aluminum also slightly
exceeds Nepal standards on the result of analysis in Japan. As for the result of Cryptosporidium analysis, it
has not been detected.
Furthermore, bacteria have been detected at all the sampling points including the Mardi River both in dry
season and rainy season. However, it will be solved since necessary disinfection is implemented at chlorine
dosing facilities to be installed at the WTP and the 2 existing reservoirs by the Project.
Table A-6-6-2 Result of Water Quality Analysis in Rainy Season
1st 1st 2nd
Late Aug(20 Aug)
Late Aug(20 Aug)
Late Aug(27 Aug)
Color - 2 TCU ND(< 5) ND(< 5) 5 (15) < 5
Turbidity - 7 NTU 7.6 19 5 (10) < 2
Electrical Conductivity (EC) μS/cm 123 µS/cm 118 143 1500
pH - 7.7 - 7.4 7.4 6.5-8.5 About 7.5
Total Dissolved Solid (TDS) mg/L 82 mg/L 64 65 1000
Taste - missing data Non-Objctional Non-Objctional
Odor - Odourless mg/L Odourless Odourless Non-Objctional Non-Objctional
Iron (Fe) mg/L 1 mg/L 0.91 2.62 0.3 (3) 0.3
Manganese (Mn) mg/L 0.017 mg/L ND(< 0.05) ND(< 0.05) 0.2 0.05
Arsenic (As) mg/L 0.001 mg/L ND(< 0.005) ND(< 0.005) 0.05 0.01
Cadmium (Cd) mg/L <0.0003 mg/L ND(< 0.003) ND(< 0.003) 0.003 0.003
Chromium (Cr) mg/L <0.005 mg/L ND(< 0.02) ND(< 0.02) 0.05 0.05
Cyanide (CN-) mg/L <0.02 mg/L ND(< 0.05) ND(< 0.05) 0.07 0.01
Lead (Pb) mg/L <0.001 mg/L ND(< 0.01) ND(< 0.01) 0.01 0.01
Ammmonia (NH3) mg/L <0.1 mg/L 0.12 0.11 1.5
Chloride (Cl-) mg/L <1 mg/L 1 1 250 200
Sulphate (SO4--) mg/L 4 mg/L 2.88 1.65 250
Nitrate (NO3-) mg/L <1 mg/L 1.71 ND(< 0.2) 50 10
Copper (Cu) mg/L <0.1 mg/L ND(< 0.02) ND(< 0.02) 1 1
Total Hardness mg/L 57 mg/L 62 60 500 300
Calcium (Ca) mg/L 14 mg/L 16 17 200
Zinc (Zn) mg/L <0.1 mg/L ND(< 0.05) ND(< 0.05) 3 1
Mercury (Hg) mg/L <0.0003 mg/L ND(< 0.001) ND(< 0.001) 0.001 0.0005
Aluminum (Al) mg/L 0.88 mg/L 0.06 0.06 0.2 0.1
Fluoride (F+) mg/L <0.08 mg/L ND(< 0.5) ND(< 0.5) 0.5-1.5 0.8
E.Coli MPN/100mL 50 CFU/100ml 94 TNTC 0 0
Total Coliform MPN/100mL 800 CFU/100ml TNTC 7100 0 in 95% Samples
General Bacteria MPN/mL 1600 100MPN/mL
Selenium (Se) mg/L <0.001 0.01
Anionic Surfactant mg/L <0.02 0.2
Total Organic Carbon (TOC) mg/L 0.6 mg/L 0.46 1 3
Magnesium mg/L 5 4
Phosphate mg/l ND(< 0.05) ND(< 0.05)
Sodium (Na) mg/L 1.11 1.68 200
Items
Analysis in Japan Analysis in Nepal
Nepali Standard Japanese StandardUnit Unit
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-143
(3) Result of Turbidity Measurement in Rainy Season
Turbidity of the Mardi River was measured for 36 days from 17th July to 3rd September.
Three Locations of the sampling points to analyze raw water quality were selected: (1) intake wire, (2)
wash-out valve near the Yamdi River which locates 7.7km downstream from intake wire, connected to raw
water transmission pipeline with diameter of 500mm and (3) Bindhabashini Reservoirs locates about 10km
downstream from the intake weir (Water travel hour from intake weir to the reservoir is about 1.5 hours).
Water sampling for raw water analysis was conducted at one of the three candidate points. Following table
summarizes the results of the analysis.
NTU >10 10-20 20-50 50-100 100-200 200-500 <500
Number of Day 13 5 8 4 3 1 2
Based on the above examination results, the following are confirmed about the rainfall and the turbidity of
raw water in rainy season.
a) Raining often occurs near the intake wire during night time.
b) Since the catchment area of the Mardi River is small, high turbidity occurs after heavy rain.
c) High turbidity shall be continued until stopping the rain in the following morning.
d) High turbidity of 500 NTU usually dropped to 50 NTU within half a day to a day, if the rain was not
continued.
e) Turbidity of 200 NTU may continue for several days, if the rain continue.
f) Even in the rainy season, turbidity does not exceed the 20 NTU in more than half of the number of
days in that period.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-144
2 Turbidity Data at Bindhabasini Reservoir in Rainy Season
Table A-6-6-3 Turbidity Data at Bindhabasini Reservoir in Rainy Season
Date Bindhabasini Yamdi-WashOut Intake
(NTU) (NTU) (NTU)
2015/7/17 73.4/81.4/82.2 - 70.6/74.5/80.2
2015/7/18 - - -
2015/7/19 - - 8.49/9.04/10.3
2015/7/20 9.14/9.75/11.3 - 7.77/8.42/9.20
2015/7/21 4.66/4.78/4.88 - -
2015/7/22 5.11/6.15/7.06 - -
2015/7/23 3.72/3.89/3.95 4.19/4.73/5.97 -
2015/7/24 - - -
2015/7/25 - - -
2015/7/26 21.6/22.6/24.7 15.7/19/19.8 16.2/16.7/22.0
2015/7/27 18.3/19.8/23.7 18.7/19.9/20.7 -
2015/7/28 57.6/61.2/68.2 33.9/34.4/44.3 17.8/19.1/19.7
2015/7/29 11.5/13.5/13.6 7.91/8.44/11.1 -
2015/7/30 AM:382/401/419 - -
PM:208/211/221 PM:162/189/193 -
2015/7/31 - - AM:142/153/154
2015/8/1 - - -
2015/8/2 AM:18.6/22.1/23.5 AM:22.1/27.1/29.3 -
2015/8/3 AM:16.3/16.7/17.0 AM:16.1/21.7/23.1 -
2015/8/4 AM:9.58/12.7/13.2 AM:8.18/8.78/9.37 -
2015/8/5 AM:5.57/6.04/6.62 AM:7.49/7.68/7.89 -
2015/8/6 - AM:5.62/6.02/6.53 AM:4.01/4.76/5.15
2015/8/7 AM:4.67/4.96/5.46 AM:4.97/5.18/5.63 -
2015/8/8 - - -
2015/8/9 AM:2.50/3.89/3.99 AM:3.18/4.46/4.71 -
2015/8/10 AM:129/132/148 AM:153/163/172 AM:67.6/68.5/70.5
2015/8/11 AM:146/155/200 AM:156/163/188 -
2015/8/12 AM:27.1/29.4/33.8 - -
2015/8/13 AM:42.8/46.2/51.7 - -
2015/8/14 AM:7.64/8.00/8.87 AM:7.15/7.45/7.51 -
2015/8/15 - - -
2015/8/16 - - -
2015/8/17 - - -
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-145
Date Bindhabasini Yamdi-WashOut Intake
(NTU) (NTU) (NTU)
2015/8/18 AM:23.0/24.7/27.4 AM:18.4/19.6/20.2 AM:14.1/16.9/19.6
2015/8/19 AM:28.8/29.2/30.0 AM:24.8/27.3/28.2 -
2015/8/20 AM:8.69/9.30/9.38 AM:9.40/10.2/11.3 -
2015/8/21 AM:41.6/42.4/54.4 AM:32.3/33.2/33.3 -
2015/8/22 - - -
2015/8/23 - - -
2015/8/24 - - -
2015/8/25 AM:5.51/7.96/7.08 AM:4.90/5.17/4.54 -
2015/8/26 AM:66.5/71.4/58.6 AM:57.4/60.0/61.5 -
2015/8/27 AM:22.8/19.5/21.3 AM:25.5/22.2/17.9 -
2015/8/28 AM:10.9/8.32/9.04 AM:10.2/9.08/7.90 -
2015/8/29 - - -
2015/8/30 AM:26.5/27.2/30.4 AM:21.7/28.3/31.4 -
2015/8/31 AM:7.31/6.15/5.92 AM:4.90/4.46/5.20 -
2015/9/1 AM:15.8/13.8/11.3 AM:11.5/12.2/12.9 -
2015/9/2 AM:6.08/5.96/5.07 AM:6.52/5.73/5.08
Note: Turbidity standard 4-419 (NTU) written in Table 4-4-1 of main report is set between minimum
turbidity 4.01≒4 (NTU) and maximum turbidity 419 (NTU) (Written in red) shown in Table A-6-6-3 that
is result of turbidity survey of Bindhabasini reservoir in rainy season.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-146
3 Result of Water Quality Analysis about Other Rivers
(1) Result of Water Quality Analysis in Dry Season (Sampling in 22th, 23th of April)
Table A-6-6-4 Result of Water Quality Analysis (1)
(2) Result of Water Quality Analysis in Dry Season (Sampling in 10th, 11th of May)
Table A-6-6-5 Result of Water Quality Analysis (2)
Unit Result Unit Result Unit Result Unit Result Unit Result Unit Result
Color - <1 TCU < 5 - 2 TCU < 5 - <1 TCU < 5 5 (15) <5
Turbidity - <1 NTU 1 - <1 NTU 1 - <1 NTU 1 5 (10) <2
Electrical Conductivity (EC) μS/cm 369 µS/cm 347 μS/cm 109 µS/cm 115 μS/cm 346 µS/cm 357 1500
pH - 7.6 - 8.1 - 7.7 - 7.8 - 8.2 - 8.3 6.5-8.5 About 7.5
Total Dissolved Solid (TDS) mg/L 240 mg/L 181 mg/L 65 mg/L 56 mg/L 230 mg/L 168 1000
Taste - missing data - missing data - missing data Non-Objctional Non-Objctional
Odor - Fine earthy mg/L Odourless - Fine earthy mg/L Odourless - Non-Objectional mg/L Odourless Non-Objctional Non-Objctional
Iron (Fe) mg/L 0.03 mg/L 0.2 mg/L <0.03 mg/L 0.23 mg/L <0.03 mg/L 0.29 0.3 (3) 0.3
Manganese (Mn) mg/L <0.005 mg/L < 0.05 mg/L <0.005 mg/L < 0.05 mg/L <0.005 mg/L < 0.05 0.2 0.05
Arsenic (As) mg/L <0.001 mg/L < 0.005 mg/L <0.001 mg/L < 0.005 mg/L 0.002 mg/L < 0.005 0.05 0.01
Cadmium (Cd) mg/L <0.0003 mg/L < 0.003 mg/L <0.0003 mg/L < 0.003 mg/L <0.0003 mg/L < 0.003 0.003 0.003
Chromium (Cr) mg/L <0.005 mg/L < 0.02 mg/L <0.005 mg/L < 0.02 mg/L <0.005 mg/L < 0.02 0.05 0.05
Cyanide (CN-) mg/L <0.02 mg/L <0.05 mg/L <0.02 mg/L <0.05 mg/L <0.02 mg/L <0.05 0.07 0.01
Lead (Pb) mg/L <0.001 mg/L < 0.01 mg/L <0.001 mg/L < 0.01 mg/L <0.001 mg/L < 0.01 0.01 0.01
Ammmonia (NH3) mg/L <0.1 mg/L 0 mg/L <0.1 mg/L 0.03 mg/L <0.1 mg/L 0.26 1.5
Chloride (Cl-) mg/L 2 mg/L 3 mg/L <1 mg/L 1 mg/L <1 mg/L 1 250 200
Sulphate (SO4--) mg/L 1 mg/L 0.82 mg/L 1 mg/L 0.62 mg/L 29 mg/L 0.82 250
Nitrate (NO3-) mg/L 2 mg/L 2.423 mg/L <1 mg/L 0.411 mg/L <1 mg/L 0.899 50 10
Copper (Cu) mg/L <0.1 mg/L < 0.02 mg/L <0.1 mg/L < 0.02 mg/L <0.1 mg/L < 0.02 1 1
Total Hardness mg/L 200 mg/L 118 mg/L 44 mg/L 51 mg/L 180 mg/L 176 500 300
Calcium (Ca) mg/L 76 mg/L 14 mg/L 37 200
Zinc (Zn) mg/L <0.1 mg/L < 0.05 mg/L <0.1 mg/L < 0.05 mg/L <0.1 mg/L < 0.05 3 1
Mercury (Hg) mg/L <0.0003 mg/L < 0.001 mg/L <0.0003 mg/L < 0.001 mg/L <0.0003 mg/L < 0.001 0.001 0.0005
Aluminum (Al) mg/L 0.03 mg/L < 0.05 mg/L <0.02 mg/L < 0.05 mg/L <0.02 mg/L < 0.05 0.2 0.1
Fluoride (F+) mg/L <0.08 mg/L < 0.5 mg/L <0.08 mg/L < 0.5 mg/L <0.08 mg/L < 0.5 0.5-1.5 0.8
E.Coli MPN/100mL 5 CFU/100ml 22 MPN/100mL 28 CFU/100ml 86 MPN/100mL 18 CFU/100ml 26 0 in 95% Samples
Total Coliform MPN/100mL 24000 CFU/100ml 331 MPN/100mL 2100 CFU/100ml 2447 MPN/100mL 1000 CFU/100ml 1800 0 0
General Bacteria MPN/mL 1500 MPN/mL 980 MPN/mL 71 100MPN/mL
Selenium (Se) mg/L <0.001 mg/L <0.001 mg/L <0.001 0.01
Anionic Surfactant mg/L <0.02 mg/L <0.02 mg/L <0.02 0.2
Total Organic Carbon (TOC) mg/L <0.3 mg/L <0.02 mg/L 0.7 mg/L <0.02 mg/L 0.3 mg/L <0.02 3
Magnesium mg/L 2.99 mg/L 2.38 mg/L 20.48
Phosphate mg/l < 0.05 mg/l < 0.05 mg/l < 0.05
Sodium (Na) mg/L 3.14 mg/L 3.76 mg/L 3.14 200
Nepal Standard Japanese StandardNepal Japan NepalItems
Baldhara Spring Bhote Khola Kali KholaJapan Nepal Japan
Unit Result Unit Result Unit Result Unit Result Unit Result Unit Result
Color - TCU < 5 - TCU < 5 - TCU < 5 5 (15) <5
Turbidity - NTU 1 - NTU 1 - NTU 1 5 (10) <2
Electrical Conductivity (EC) μS/cm µS/cm 378 μS/cm µS/cm 104 μS/cm µS/cm 330 1500
pH - - 7.4 - - 7.8 - - 7.9 6.5-8.5 About 7.5
Total Dissolved Solid (TDS) mg/L mg/L 175 mg/L mg/L 54 mg/L mg/L 183 1000
Taste - - - Non-Objctional Non-Objctional
Odor - mg/L Odourless - mg/L Odourless - mg/L Odourless Non-Objctional Non-Objctional
Iron (Fe) mg/L mg/L 0.4 mg/L mg/L 0.2 mg/L mg/L 0.07 0.3 (3) 0.3
Manganese (Mn) mg/L mg/L < 0.05 mg/L mg/L < 0.05 mg/L mg/L < 0.05 0.2 0.05
Arsenic (As) mg/L mg/L < 0.005 mg/L mg/L < 0.005 mg/L mg/L < 0.005 0.05 0.01
Cadmium (Cd) mg/L mg/L < 0.003 mg/L mg/L < 0.003 mg/L mg/L < 0.003 0.003 0.003
Chromium (Cr) mg/L mg/L < 0.02 mg/L mg/L < 0.02 mg/L mg/L < 0.02 0.05 0.05
Cyanide (CN-) mg/L mg/L <0.05 mg/L mg/L <0.05 mg/L mg/L <0.05 0.07 0.01
Lead (Pb) mg/L mg/L < 0.01 mg/L mg/L < 0.01 mg/L mg/L < 0.01 0.01 0.01
Ammmonia (NH3) mg/L mg/L 0.06 mg/L mg/L < 0.05 mg/L mg/L 0.24 1.5
Chloride (Cl-) mg/L mg/L 12 mg/L mg/L 1 mg/L mg/L 1 250 200
Sulphate (SO4--) mg/L mg/L 1 mg/L mg/L 1.2 mg/L mg/L 1.8 250
Nitrate (NO3-) mg/L mg/L 3.71 mg/L mg/L 0.32 mg/L mg/L 0.37 50 10
Copper (Cu) mg/L mg/L < 0.02 mg/L mg/L < 0.02 mg/L mg/L < 0.02 1 1
Total Hardness mg/L mg/L 142 mg/L mg/L 50 mg/L mg/L 170 500 300
Calcium (Ca) mg/L mg/L mg/L 200
Zinc (Zn) mg/L mg/L < 0.05 mg/L mg/L < 0.05 mg/L mg/L < 0.05 3 1
Mercury (Hg) mg/L mg/L < 0.001 mg/L mg/L < 0.001 mg/L mg/L < 0.001 0.001 0.0005
Aluminum (Al) mg/L mg/L < 0.05 mg/L mg/L < 0.05 mg/L mg/L < 0.05 0.2 0.1
Fluoride (F+) mg/L mg/L < 0.5 mg/L mg/L < 0.5 mg/L mg/L < 0.5 0.5-1.5 0.8
E.Coli MPN/100mL CFU/100ml 12 MPN/100mL CFU/100ml 86 MPN/100mL CFU/100ml 49 0 in 95% Samples
Total Coliform MPN/100mL CFU/100ml 133 MPN/100mL CFU/100ml TNTC MPN/100mL CFU/100ml TNTC 0 0
General Bacteria MPN/mL MPN/mL MPN/mL 100MPN/mL
Selenium (Se) mg/L mg/L mg/L 0.01
Anionic Surfactant mg/L mg/L mg/L 0.2
Total Organic Carbon (TOC) mg/L mg/L 0.46 mg/L mg/L 0.23 mg/L mg/L 0.35 3
Magnesium mg/L 15 mg/L 1 mg/L 26
Phosphate mg/l < 0.05 mg/l < 0.05 mg/l < 0.05
Sodium (Na) mg/L 3.33 mg/L 3.92 mg/L 3.54 200
Nepal Standard Japanese StandardNepal Japan NepalItems
Baldhara Spring Bhote Khola Kali KholaJapan Nepal Japan
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-147
(3) Result of Water Quality Analysis in Rainy Season (Sampling in 20th, 21th of August)
Table A-6-6-6 Result of Water Quality Analysis (3)
(4) Result of Water Quality Analysis in Rainy Season (Sampling in 270th, 28th of August)
Table A-6-6-7 Result of Water Quality Analysis (4)
Unit Result Unit Result Unit Result Unit Result Unit Result Unit Result
Color - <1 TCU ND(< 5) - 2 TCU ND(< 5) - <1 TCU ND(< 5) 5 (15) <5
Turbidity - <1 NTU 1 - 3 NTU 10.4 - 2 NTU 8 5 (10) <2
Electrical Conductivity (EC) μS/cm 365 µS/cm 337 μS/cm 51 µS/cm 61 μS/cm 270 µS/cm 245 1500
pH - 7.5 - 7.3 - 7.4 - 7.4 - 8.2 - 7.9 6.5-8.5 About 7.5
Total Dissolved Solid (TDS) mg/L 230 mg/L 206 mg/L 79 mg/L 32 mg/L 170 mg/L 135 1000
Taste - Missing data - Missing data - Missing data Non-Objctional Non-Objctional
Odor - Non-Objectional mg/L Odourless - Non-Objectional mg/L Odourless - Non-Objectional mg/L Odourless Non-Objctional Non-Objctional
Iron (Fe) mg/L <0.03 mg/L 0.19 mg/L 0.2 mg/L 0.19 mg/L 0.3 mg/L 0.32 0.3 (3) 0.3
Manganese (Mn) mg/L <0.005 mg/L ND(< 0.05) mg/L 0.005 mg/L ND(< 0.05) mg/L 0.01 mg/L ND(< 0.05) 0.2 0.05
Arsenic (As) mg/L <0.001 mg/L < 0.005 mg/L <0.001 mg/L ND(< 0.005) mg/L 0.001 mg/L ND(< 0.005) 0.05 0.01
Cadmium (Cd) mg/L <0.0003 mg/L ND(< 0.003) mg/L <0.0003 mg/L ND(< 0.003) mg/L <0.0003 mg/L ND(< 0.003) 0.003 0.003
Chromium (Cr) mg/L <0.005 mg/L ND(< 0.02) mg/L <0.005 mg/L ND(< 0.02) mg/L <0.005 mg/L ND(< 0.02) 0.05 0.05
Cyanide (CN-) mg/L <0.02 mg/L ND(< 0.05) mg/L <0.02 mg/L ND(< 0.05) mg/L <0.02 mg/L ND(< 0.05) 0.07 0.01
Lead (Pb) mg/L <0.001 mg/L ND(< 0.01) mg/L <0.001 mg/L ND(< 0.01) mg/L <0.001 mg/L ND(< 0.01) 0.01 0.01
Ammmonia (NH3) mg/L <0.1 mg/L 0.03 mg/L <0.1 mg/L 0.06 mg/L <0.1 mg/L 0.19 1.5
Chloride (Cl-) mg/L 1 mg/L 1 mg/L <1 mg/L 1 mg/L <1 mg/L 1 250 200
Sulphate (SO4--) mg/L <1 mg/L 0.82 mg/L <1 mg/L 1.23 mg/L 11 mg/L 1.65 250
Nitrate (NO3-) mg/L 2 mg/L 4.59 mg/L <1 mg/L ND(< 0.2) mg/L <1 mg/L 0.7 50 10
Copper (Cu) mg/L <0.1 mg/L < 0.02 mg/L <0.1 mg/L ND(< 0.02) mg/L <0.1 mg/L ND(< 0.02) 1 1
Total Hardness mg/L 190 mg/L 200 mg/L 18 mg/L 30 mg/L 140 mg/L 130 500 300
Calcium (Ca) mg/L 73 mg/L 64 mg/L 6 mg/L 10 mg/L 30 mg/L 29 200
Zinc (Zn) mg/L <0.1 mg/L ND(< 0.05) mg/L <0.1 mg/L ND(< 0.05) mg/L <0.1 mg/L ND(< 0.05) 3 1
Mercury (Hg) mg/L <0.0003 mg/L < 0.00 mg/L <0.0003 mg/L ND(< 0.001) mg/L <0.0003 mg/L ND(< 0.001) 0.001 0.0005
Aluminum (Al) mg/L <0.02 mg/L 0.06 mg/L 0.16 mg/L 0.06 mg/L 0.18 mg/L 0.05 0.2 0.1
Fluoride (F+) mg/L <0.08 mg/L ND(< 0.5) mg/L <0.08 mg/L ND(< 0.5) mg/L <0.08 mg/L ND(< 0.5) 0.5-1.5 0.8
Total Coliform MPN/100mL 160 CFU/100ml 145 MPN/100mL 380 CFU/100ml 563 MPN/100mL 540 CFU/100ml 525 0 in 95% Samples
E.Coli MPN/100mL 170 CFU/100ml 14 MPN/100mL 15 CFU/100ml 129 MPN/100mL 24 CFU/100ml 49 0 0
General Bacteria MPN/mL 390 MPN/mL 100 MPN/mL 150 100MPN/mL
Selenium (Se) mg/L <0.001 mg/L <0.001 mg/L <0.001 0.01
Anionic Surfactant mg/L <0.02 mg/L <0.02 mg/L <0.02 0.2
Total Organic Carbon (TOC) mg/L <0.3 mg/L 0.23 mg/L 0.8 mg/L 0.23 mg/L 0.5 mg/L 0.23 3
Magnesium mg/L 10 mg/L ND(< 2) mg/L 14
Phosphate mg/l ND(< 0.05) mg/l ND(< 0.05) mg/l ND(< 0.05)
Sodium (Na) mg/L 1.23 mg/L 1.17 mg/L 1.01 200
Items
Baldhara Spring Bhote Khola Kali KholaJapaneseStandard
Japan Nepal Japan Nepal Japan Nepal Nepal Standard
Unit Result Unit Result Unit Result Unit Result Unit Result Unit Result
Color - TCU ND(< 5) - TCU ND(< 5) - TCU ND(< 5) 5 (15) <5
Turbidity - NTU 1 - NTU 2.5 - NTU 3.2 5 (10) <2
Electrical Conductivity (EC) μS/cm µS/cm 347 μS/cm µS/cm 50 μS/cm µS/cm 241 1500
pH - - 7.2 - - 7.4 - - 8.1 6.5-8.5 About 7.5
Total Dissolved Solid (TDS) mg/L mg/L 175 mg/L mg/L 25 mg/L mg/L 144 1000
Taste - - - Non-Objctional Non-Objctional
Odor - mg/L Odourless - mg/L Odourless - mg/L Odourless Non-Objctional Non-Objctional
Iron (Fe) mg/L mg/L 0.16 mg/L mg/L 0.17 mg/L mg/L 0.19 0.3 (3) 0.3
Manganese (Mn) mg/L mg/L ND(< 0.05) mg/L mg/L ND(< 0.05) mg/L mg/L ND(< 0.05) 0.2 0.05
Arsenic (As) mg/L mg/L ND(< 0.005) mg/L mg/L ND(< 0.005) mg/L mg/L ND(< 0.005) 0.05 0.01
Cadmium (Cd) mg/L mg/L ND(< 0.003) mg/L mg/L ND(< 0.003) mg/L mg/L ND(< 0.003) 0.003 0.003
Chromium (Cr) mg/L mg/L ND(< 0.02) mg/L mg/L ND(< 0.02) mg/L mg/L ND(< 0.02) 0.05 0.05
Cyanide (CN-) mg/L mg/L ND(< 0.05) mg/L mg/L ND(< 0.05) mg/L mg/L ND(< 0.05) 0.07 0.01
Lead (Pb) mg/L mg/L ND(< 0.01) mg/L mg/L ND(< 0.01) mg/L mg/L ND(< 0.01) 0.01 0.01
Ammmonia (NH3) mg/L mg/L 0 mg/L mg/L 0.06 mg/L mg/L 0.16 1.5
Chloride (Cl-) mg/L mg/L 3 mg/L mg/L 1 mg/L mg/L 1 250 200
Sulphate (SO4--) mg/L mg/L 1.85 mg/L mg/L 0.62 mg/L mg/L 1.23 250
Nitrate (NO3-) mg/L mg/L 0.9 mg/L mg/L ND(< 0.2) mg/L mg/L 0.36 50 10
Copper (Cu) mg/L mg/L ND(< 0.02) mg/L mg/L ND(< 0.02) mg/L mg/L ND(< 0.02) 1 1
Total Hardness mg/L mg/L 160 mg/L mg/L 22 mg/L mg/L 140 500 300
Calcium (Ca) mg/L mg/L 26 mg/L mg/L 8 mg/L mg/L 8.8 200
Zinc (Zn) mg/L mg/L NDD< 0.05) mg/L mg/L ND(< 0.05) mg/L mg/L ND(< 0.05) 3 1
Mercury (Hg) mg/L mg/L ND(< 0.001) mg/L mg/L ND(< 0.001) mg/L mg/L ND(< 0.001) 0.001 0.0005
Aluminum (Al) mg/L mg/L 0.05 mg/L mg/L 0.06 mg/L mg/L 0.05 0.2 0.1
Fluoride (F+) mg/L mg/L ND(< 0.5) mg/L mg/L ND(< 0.5) mg/L mg/L ND(< 0.5) 0.5-1.5 0.8
Total Coliform MPN/100mL CFU/100ml 24 MPN/100mL CFU/100ml TNTC MPN/100mL CFU/100ml TNTC 0 in 95% Samples
E.Coli MPN/100mL CFU/100ml 0 MPN/100mL CFU/100ml TNTC MPN/100mL CFU/100ml 135 0 0
General Bacteria MPN/mL MPN/mL MPN/mL 100MPN/mL
Selenium (Se) mg/L mg/L mg/L 0.01
Anionic Surfactant mg/L mg/L mg/L 0.2
Total Organic Carbon (TOC) mg/L mg/L 0.58 mg/L mg/L 0.92 mg/L mg/L 0.69 3
Magnesium mg/L 23 mg/L ND(< 2) mg/L 29
Phosphate mg/l ND(< 0.05) mg/l ND(< 0.05) mg/l ND(< 0.05)
Sodium (Na) mg/L 1.48 mg/L 1.26 mg/L 1.18 200
Items
Baldhara Spring Bhote Khola Kali KholaJapaneseStandard
Japan Nepal Japan Nepal Japan Nepal Nepal Standard
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-148
4 Result of Water Quality Analysis at Tap Water ( Household, Hotel and Restaurant)
Table A-6-6-8 Result of Water Quality Analisis at Tap Water
Turbidity
( NTU)
FRC
(mg/L)
Total Coliform
(CFU/100mL)
E coli
(CFU/100mL)
5(10) 0.1‐0.2 0 0
1 28°13'09"N/83°58'34"E Samishkya marg 5 NWSC HH 2 ND(< 0.1) 4700 67
2 28°13'16''N/83°56'30"E Male, Patan 5 NWSC HH 2 ND(< 0.1) 4200 45
3 28°13'09''N/83°58'34"E Male, Patan 5 NWSC HH 1 ND(< 0.1) 680 60
4 28°13'7''N/83°58'34"E Samishkya marg 5 NWSC HH 1 ND(< 0.1) 500 42
5 28°13'1''N/83°57'35"E Khare 6 NWSC HH 2 ND(< 0.1) 492 51
6 28°12'57''N/83°57'36"E Khare 6 NWSC HH 20 ND(< 0.1) TNTC 45
7 28°13'1''N/83°57'36"E Khare 6 NWSC HH 2 ND(< 0.1) 1471 124
8 28°13'6''N/83°57'34"E Badam 6 NWSC HH 2 ND(< 0.1) 253 127
9 28°15'18''N/83°58'05"E Amar Dip 16 NWSC HH 2 ND(< 0.1) 520 72
10 28°15'32''N/83°58'34"E Ghati patan 16 NWSC HH 6 ND(< 0.1) TNTC 200
11 28°15'19''N/83°58'43"E Amar Dip 16 NWSC HH 4 ND(< 0.1) 700 170
12 28°15'15''N/83°58'58"E Amar Dip 16 NWSC HH 3 ND(< 0.1) 800 120
13 28°11'18''N/83°58'32"E Shanti Path 17 NWSC HH 46 ND(< 0.1) 2600 2500
14 28°11'26''N/83°58'16"E Shanti Path 17 NWSC HH 5 ND(< 0.1) 4600 110
15 28°11'25''N/83°58'14"E Shanti Path 17 NWSC HH 7 ND(< 0.1) 3000 322
16 28°11'55''N/83°58'10"E Dam Side 17 NWSC HH 18 ND(< 0.1) TNTC 78
17 28°11'19''N/83°58'32"E Gairi Kulo 17 NWSC HH 16 ND(< 0.1) TNTC 165
18 28°15'56''N/83°58'02"E Khatri Tahar 19 NWSC HH 9 ND(< 0.1) TNTC 70
19 28°15'55''N/83°58'10"E Lamachaur 19 NWSC HH 10 ND(< 0.1) TNTC 44
20 28°15'49''N/83°58'12"E Lamachaur 19 NWSC HH 14 ND(< 0.1) TNTC 60
21 28°15'52''N/83°58'09"E Khatri tole 19 NWSC HH 82 ND(< 0.1) 2600 46
22 28°14'36''N/83°59'12"E Bhim Bazar 1 NWSC HH 6 ND(< 0.1) 8000 30
23 28°14,'35''N/83°59'12"E Bhim Bazar 1 NWSC HH 9 ND(< 0.1) 7800 87
24 28°14'31''N/83°59'13"E Bhim kali, Patan bagar 1 NWSC HH 4 ND(< 0.1) 6900 185
25 28°14'36''N/83°59'10"E Lampatan marg, Gaighat chowk 1 NWSC HH 15 ND(< 0.1) TNTC 224
26 28°14'31''N/83°59'12"E Bhim bazar 1 NWSC HH 2 ND(< 0.1) 181 20
27 28°13'52''N/83°59'06"E Bhimsen tole 2 NWSC HH 5 ND(< 0.1) TNTC 200
28 28°13'49''N/83°59'03"E Nala mukha 2 NWSC HH 5 ND(< 0.1) TNTC 231
29 28°13'53''N/83°59'07"E Bhimsen tole 2 NWSC HH 5 ND(< 0.1) TNTC 167
30 28°13'52''N/83°59'06"E Bhimsen tole 2 NWSC HH 5 ND(< 0.1) TNTC 139
31 28°14'06''N/83°59'20"E Hamal tole 3 NWSC HH 5 ND(< 0.1) TNTC 400
32 28°14'05''N/83°59'20"E Hamal tole 3 NWSC HH 21 ND(< 0.1) TNTC 112
33 28°14'05''N/83°59'20"E Hamal tole 3 NWSC HH 17 ND(< 0.1) 1600 400
34 28°14'05''N/83°59'19"E Nadi pur 3 NWSC HH 23 ND(< 0.1) 702 160
35 28°13'47''N/83°59'02"E Nala mukha 4 NWSC HH 2 ND(< 0.1) TNTC 100
36 28°13'47''N/83°59'03"E Chhbis Kuriya 4 NWSC HH 1 ND(< 0.1) 2720 94
37 28°13'48''N/83°59'02"E Chhbis Kuriya 4 NWSC HH 2 ND(< 0.1) TNTC 180
38 28°13'39''N/83°59'01"E Koirala Birthamarg 4 NWSC HH 1 ND(< 0.1) 7800 169
39 28°12'53''N/83°58'17"E Shantinagar 7 NWSC HH 5 ND(< 0.1) TNTC 33
40 28°12'54''N/83°58'16"E Jagriti marg 7 NWSC HH 2 ND(< 0.1) 429 22
41 28°12'55''N/83°58'15"E Jagriti marg 7 NWSC HH 3 ND(< 0.1) 2500 241
42 28°13'10''N/83°59'08"E Shangam 8 NWSC HH 2 ND(< 0.1) 1500 51
43 28°13'12''N/83°59'30"E Shivalaya 9 NWSC HH 4 ND(< 0.1) 7100 135
44 28°13'12''N/83°59'30"E Shivalaya 9 NWSC HH 2 ND(< 0.1) 4900 59
45 28°13'13''N/83°59'31"E Shivalaya 9 NWSC HH 1 ND(< 0.1) 376 143
46 28°13'10''N/83°59'30"E Shivalaya 9 NWSC HH 4 ND(< 0.1) 312 61
47 28°12'08''N/83°58'24"E Rastrya bank chowk 7 NWSC HH 10 ND(< 0.1) TNTC 131
48 28°12'41''N/83°58'37"E Prativa marg 8 NWSC HH 1 ND(< 0.1) 253 41
49 28°12'11''N/84°00,08"E Shuvaraj marg 10 NWSC HH 2 ND(< 0.1) 298 67
50 28°13'22''N/83°59'34"E Rani pauwa 11 NWSC HH 1 ND(< 0.1) 18 2
51 28°13'20''N/83°59'36"E Tulsi marga 11 NWSC HH 1 ND(< 0.1) 1400 43
52 28°13'15''N/83°59'40"E Rani pauwa 11 NWSC HH 2 ND(< 0.1) 2600 125
53 28°13'15''N/83°59'40"E Rani pauwa 11 NWSC HH 3 ND(< 0.1) TNTC 82
54 28°11'35''N/84°01'25"E Prithivi raj marga 14 NWSC HH 28 ND(< 0.1) 41 8
55 28°11'32''N/84°01'24"E Chautha chowk 14 NWSC HH 34 ND(< 0.1) 6000 47
56 28°13'01''N/83°57'30"E Khare 6 TW H/R 3 ND(< 0.1) 2629 8
57 28°12'53''N/83°57'30"E Halan Chowk 6 JW H/R 1 ND(< 0.1) 4400 6
58 28°12'53''N/83°57'30"E Halan Chowk 6 JW H/R 1 ND(< 0.1) 310 2
59 28°12'27''N/83°57'31"E Barahi path 6 TW H/R 1 ND(< 0.1) 420 33
60 28°12'47''N/83°57'27"E Lakeside 6 JW H/R 1 ND(< 0.1) 7800 100
61 28°12'32''N/83°57'26"E Baidam 6 TW H/R 1 ND(< 0.1) 506 100
62 28°12'53''N/83°57'41"E Dehiko patan 6 JW H/R 1 ND(< 0.1) 1457 12
63 28°12'56''N/83°57'35"E Baidam 6 TW H/R 3 ND(< 0.1) TNTC 200
64 28°12'59''N/83°57'31"E Pahari marg 6 TW H/R 2 ND(< 0.1) 133 8
65 28°12'52''N/83°57'40"E Dihiko patan 6 TW H/R 8 ND(< 0.1) 6300 33
66 28°12'46''N/83°57'32"E Lake side 6 TW H/R 2 ND(< 0.1) TNTC 22
67 28°12'47''N/83°57'27"E Baidam 6 TW H/R 1 ND(< 0.1) 124 35
68 28°12'53''N/83°57'38"E Khara marg 6 TW H/R 1 ND(< 0.1) 1400 24
69 28°12'46''N/83°57'33"E Lake side 6 TW H/R 1 ND(< 0.1) 382 237
70 25°11'33''N/83°58'27"E RTO marg 17 TW H/R 1 ND(< 0.1) 0 0
71 28°11'49''N/83°58'11"E Dam side 17 TW H/R 1 ND(< 0.1) TNTC 33
72 28°11'48''N/83°58'11"E Dam side 17 TW H/R 1 ND(< 0.1) 324 33
28th
May
2015
29th
May
2015
31st
May
2015
1st
June 2
015
2nd
June 2
015
SourceWater
users
Parameters
NDWSQ
27th
May
2015
JW= jar water TW= ube well HH= household H/R= hotel/restaurant
SN Date GPS Place Ward No.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-149
Table A-6-6-9 Result of Water Quality Analisis at Tap Water (2)
* The sampling at every household was collected from tap water (NWSC) directly. It is not after the NWSC
tap water collected in their house water tanks or their kitchen bucket.
** The water samples collected from the hotel/restaurant was from the tube wells directly from pumping for
sometime. It is also not after it got collected in their reservoir/tank. But jar water was collected from the jar
itself.
Turbidity
( NTU)
FRC
(mg/L)
Total Coliform
(CFU/100mL)
E coli
(CFU/100mL)
5(10) 0.1‐0.2 0 0
73 28°13'00''N/84°00'01"E Machapuchhre tole 12 NWSC HH 3 ND(< 0.1) 157 12
74 28°13'03''N/84°00'0"E Machapuchhre tole 12 NWSC HH 1 ND(< 0.1) 1706 45
75 28°13'0''N/84°00'01"E Machapuchhre tole 12 NWSC HH 2 ND(< 0.1) 2029 22
76 28°12'59''N/84°00'00"E Machapuchhre tole 12 NWSC HH 8 ND(< 0.1) TNTC 29
77 28°12'25''N/84°00'53"E Indreni marg 13 NWSC HH 83 ND(< 0.1) 1900 100
78 28°12'24''N/84°00'55"E B.P marg 13 NWSC HH 10 ND(< 0.1) TNTC 131
79 28°12'24''N/84°00'55"E B.P marg 13 NWSC HH 5 ND(< 0.1) 273 8
80 28°12'24''N/84°00'54"E B.P marg 13 NWSC HH 3 ND(< 0.1) 16 10
81 28°11'37''N/84°00'17"E Hawali marg 18 NWSC HH 29 ND(< 0.1) 822 39
82 28°11'35''N/84°00'15"E Hawali marg 18 NWSC HH 85 ND(< 0.1) TNTC 700
83 28°11'35''N/84°00'15"E Hawali marg 18 NWSC HH 188 ND(< 0.1) TNTC 700
84 28°11'36''N/84°00'15"E Hawali marg 18 NWSC HH 3 ND(< 0.1) 8000 37
85 28°11'15''N/83°59'40"E Gauri marga 10 NWSC HH 2 ND(< 0.1) 261 45
86 28°11'12''N/84°00'00"E kalika tole 15 NWSC HH 6 ND(< 0.1) 118 4
87 28°11'56''N/83°59'57"E Laxmi tole 15 NWSC HH 32 ND(< 0.1) TNTC 1400
88 28°12'30''N/84°59'50"E Ram bazar 15 NWSC HH 2 ND(< 0.1) TNTC 196
89 28°12'01''N/84°59'57"E Ram bazar 15 NWSC HH 101 ND(< 0.1) TNTC 1000
90 28°11'56''N/83°59'51"E Laxmi marg 15 NWSC HH 5 ND(< 0.1) TNTC 225
91 28°13'16''N/83°57'22"E Bangaladi 6 spring H/R 2 ND(< 0.1) TNTC 39
92 28°12'49''N/83°57'34"E Dhiko Patan 6 TW H/R 1 ND(< 0.1) 1975 27
93 28°12'45''N/83°57'46"E Dhiko Patan 6 TW H/R 1 ND(< 0.1) 10 0
94 28°12'43''N/83°58'38"E Prativa marg 8 NWSC HH 1 ND(< 0.1) 6 2
95 28°12'36''N/83°58'36"E Prativa marg 8 NWSC HH 20 ND(< 0.1) TNTC 114
96 28°12'37''N/83°58'36"E Prativa marg 8 NWSC HH 6 ND(< 0.1) 6700 41
97 28°12'23''N/83°59'49"E Rakshya marg 10 NWSC HH 3 ND(< 0.1) 2082 31
98 28°12'24''N/83°59'49"E Rakshya marg 10 NWSC HH 2 ND(< 0.1) 2482 25
99 28°11'34''N/84°01'24"E Chautha 14 NWSC HH 1 ND(< 0.1) 8 6
100 28°11'36''N/84°01'23"E Chautha 14 NWSC HH 1 ND(< 0.1) TNTC 412
4th
June 2
015
3rd
June 2
015
SourceWater
users
Parameters
NDWSQ
JW= jar water TW= ube well HH= household H/R= hotel/restaurant
SN Date GPS Place Ward No.
Preparatory Survey on Pokhara Water Supply Improvement Project in Nepal Appendix
A-150
5 Analysis of the Cryptosporidium
Table A-6-6-10 Result of Analysis of the Cryptosporidium