Agreement No. CE 30/2014 (DS) Relocation of Sha Tin Sewage Treatment Works to Caverns: Caverns and Sewage Treatment Works - Investigation, Design and Construction Stage 4 Public Engagement Report AECOM September 2019 Appendix D Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on 9 May 2017

Transcript of Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin...

Page 1: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

Agreement No. CE 30/2014 (DS) Relocation of Sha Tin Sewage Treatment Works to Caverns: Caverns and Sewage Treatment Works - Investigation, Design and Construction Stage 4 Public Engagement Report

AECOM September 2019

Appendix D – Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting

on 9 May 2017

Page 2: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

Agreement No. CE 30/2014 (DS) Relocation of Sha Tin Sewage Treatment Works to Caverns: Caverns and Sewage Treatment Works - Investigation, Design and Construction Stage 4 Public Engagement Report

AECOM September 2019

[Blank Page]

Page 3: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

15/5/2019

1

沙田區議會交通及運輸委員會

工務工程項目4399DS號搬遷沙田污水處理廠往岩洞

馬鞍山梅子林路改善工程及沙田岩洞污水處理廠施工期間的臨時交通安排

2017年5月9日

目的

為配合沙田岩洞污水處理廠運作,現希望就以下工程徵詢委員意見:

• 現有梅子林路改善工程

• 施工期間的臨時交通安排

Page 4: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

15/5/2019

2

現有梅子林路改善工程

1. 擬議沙田岩洞污水處理廠的主要出入口將設置於梅子林路

2. 為提升交通安全,建議改善梅子林路部分路段,包括在出入口增設迴旋處

擬建梅子林路改善工程

現有部份梅子林路將永久封閉及拆卸

原擬臨時工地交通管制措施(可行性研究階段)

Page 5: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

15/5/2019

3

現擬臨時工地交通管制措施

1. 運載石料的工程車輛會使用臨時出入口及工地內的臨時車道

2. 限制運載石料的工程車輛於早上及下午繁忙時間進出工地

擬建工程專用臨時行車天橋(示意圖)

運載石料的工程車輛行車路線

臨時行車天橋例子

港鐵線

臨時行車天橋

Page 6: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

15/5/2019

4

臨時行車天橋例子

港鐵線

臨時行車天橋

臨時行人路及單車徑

於工程期間將臨時封閉和改道一段行人路及單車徑

擬建臨時行人及單車路線

現有行人路及單車徑將臨時封閉及重建

Page 7: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

15/5/2019

5

交通影響 –紓緩措施

• 岩洞建造工程施工前

➢ 成立社區聯絡小組

➢ 要求承建商設立臨時交通管理小組,與運輸署及警方密切監察有關交通安排

成立社區聯絡小組

召集人: 渠務署代表/ AECOM代表

成員(暫定):

• 所有沙田區區議員均歡迎參加• 附近的住宅和機構代表:

住宅: 富安花園、錦泰苑、亞公角漁民新村、 梅子林村、大水坑村、帝堡城

社區中心: 基督教香港信義會沙田青年中心康樂營暨培訓中心、突破青年村、方舟之家

醫院: 沙田慈氏護養院 、鄰舍輔導會怡欣山莊、城門之源康復中心、白普理寧養中心、賽馬會善寧之家

學校: 威寶中英文幼稚園、九龍城浸信會禧年小學、馬鞍山崇真中學、聖公會馬鞍山主風小學

• 地區團體• 承建商• 環境小組• 獨立環境查核人• 相關政府部門(如有需要)

Page 8: Appendix D Sha Tin District Council - Presentation Material of … · 2020-01-08 · Sha Tin District Council - Presentation Material of Traffic and Transport Committee Meeting on

15/5/2019

6

環境影響

• 工程項目已於二零一七年三月獲發環境許可證

• 會按照環境許可證的要求:

1) 委託環境小組實施環境監察及審核工程計劃; 以及

2) 聘請一名環境查核人核查整體環境監察工作、工程計劃和環境緩解措施的實施

THANK YOU搬遷沙田污水處理廠往岩洞