APPENDIX D: LIST OF INTERESTED AND AFFECTED ...eia.met.gov.na/screening/732_epl_7071_public...From...
Transcript of APPENDIX D: LIST OF INTERESTED AND AFFECTED ...eia.met.gov.na/screening/732_epl_7071_public...From...
APPENDIX D: LIST OF INTERESTED AND AFFECTED PARTIES (I&APS)
1
Pre-Identified List of Interested and Affected Parties (I&APs)
Environmental Assessment for Exclusive Prospecting License (EPL) No. 7071, Ombombo Settlement in the Kunene Region
No Name Position Tel / Fax / Cell: Postal and Email Address
Ministry of Environment and Tourism (Department of Environmental Affairs)
1. Mr. Teofillus Nghitila Executive Director
2. Dr. Fredrick Sikabongo Deputy Environmental Commissioner
Aloe Investments Two Hundred and Thirty Eight (Pty) Ltd (Proponent)
3. Mr Robert Middleton Senior Manager
Ministry of Land and Reform
4. Ms. Esther Kaapanda Executive Director (Acting)
Ministry of Agriculture Water and Forestry
5. Mr. Percy Misika Executive Director
6. Mr John Hailwa Directorate of Forestry - Director
Ministry of Works and Transport
7. Mr Willem Goeiemann Executive Director
2
No Name Position Tel / Fax / Cell: Postal and Email Address
8. Ms. Monica A. Uupindi Personal Assistant to Executive Director
Ministry of Urban and Rural Development
9. Mr N. Daniel Executive Director
10. Ms. Rosalia Ruben Secretary to Executive Director
Ministry of Health and Social Services
11. Mr. Ben Nangombe Executive Director
12. Ms. Petty Tjaimba Personal Assistant to the Executive Director
Ministry of Mines and Energy
13. Mr Simeon Negumbo Executive Director
Roads Authority
14. Mr C. M. Lutombi Chief Executive Officer
15. Mr E. de Paauw Senior Specialist Road Legislation, Advice & Compliance NP&C
Kunene Regional Council
16. Hon. Marius Sheya Governor
Opuwo Rural Constituency
17. Hon. Cllr. Kazeongere Tjeundo
National Council Member
3
No Name Position Tel / Fax / Cell: Postal and Email Address
Owners / Occupiers of Land and Neighbouring Property Owners
18. Refer to the Attendance Register for more registered I&APs
APPENDIX E: BACKGROUND INFORMATION DOCUMENT (BID)
1
Document Type: Background Information Document (BID)
Project Name: Environmental Impact Assessment (EIA) For
Exclusive Prospecting License (EPL) No. 7071 Northwest of
Ombombo Village in the Kunene Region
Environmental Assessment Practitioner: Excel Dynamic Solutions (Pty) Ltd
Proponent: Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd
Date: 05 September 2019
Physical Address: 112, Robert Mugabe Avenue, Windhoek Postal Address: PO Box 997154 Maerua Mall, Windhoek Telephone: +264 (0) 61 259 530 Fax2email: +264 (0) 886 560 836 Email: [email protected] Web: www.edsnamibia.com
2
1 INTRODUCTION
Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd (The
Proponent) has been granted with Exclusive Prospecting License
(EPL) No. 7071 by the Ministry of Mines and Energy (MME). The
tenure of the licence is from 28 February 2018, as per agreement
with the Ministry of Mines and Energy. The earth data of the
covered area is prospective with regards to three groups of
commodities, upon which detailed prospecting and exploration
activities will be conducted.
- Base Metals and Rare Metals (main targeted commodities)
- Precious Metals
The tenement is situated northwest of Ombombo Settlement in the
Kunene Region, covering a total area of 19,804.5463 Ha. From the
capital city of Windhoek, the property is accessed by a paved two-
lane highway to the town of Opuwo, the nearest population center.
From Opuwo a well-maintained gravel road D3710 leads to the
eastern part of the EPL. The locality map is shown under Figure 1.
Known copper showings in the Sesfontein-Opuwo areas of
northwestern Namibia (“Kaokoland”) were recognized as potential
Copperbelt analogues by Goldfields, Anglo, African Selection Trust
and others in the late 1960’s These companies carried out the first
regional stream sediment surveys in Kaokoland in the early 1970’s
(INV Metals Inc, 2010). Aloe Investments Two Hundred and Thirty-
Eight (Pty) plans to conduct prospecting and exploration activities
leading to the estimation and delineation of the target resource.
Prospecting and exploration form part of the listed activities that
may not be undertaken without an Environmental Clearance
Certificate (ECC). Thus, the EPL 7071 is subjected to a Clearance
Certificate to be issued by the Ministry of Environment and Tourism
(MET) upon submission of an Environmental Assessment Report
(EAR) and draft Environmental Management Plan (EMP).
Under the Environmental Management Act (EMA) (2007) and its
2012 EIA Regulations, the proposed prospecting and exploration
activities are listed activities that require an Environmental
Clearance Certificate (ECC) from the Department of Environmental
Affairs (DEA) of the Ministry of Environment and Tourism (MET).
The relevant listed activities as per EIA regulations are:
3.1 The construction of facilities for any process or activities
which requires a license, right of other forms of
authorization, and the renewal of a license, right or other
form of authorization, in terms of the Minerals (Prospecting
and Mining Act, 1992).
3
3.2 other forms of mining or extraction of any natural
resources whether regulated by law or not.
3.3 Resource extraction, manipulation, conservation and
related activities.
Consequently, Aloe Investments Two Hundred and Thirty-Eight (Pty)
Ltd appointed Excel Dynamic Solutions (Pty) Ltd, an independent
team of Environmental Consultants to conduct the required EA
process and submit the ECC application to the Environmental
Commissioner on their behalf.
Figure 1: Location of the EPL no. 7071 near Ombombo
settlement, in the Kunene Region
2 PURPOSE OF THIS DOCUMENT
The purpose of this document is to provide background information
to interested and affected parties (I&APs) of the project, thus
providing an opportunity for them (I&APs) to receive information,
comment and raise issues regarding the environmental
authorization process.
3 I&AP’S/ STAKEHOLDERS
Communities, neighbors, government representatives, community
leaders, churches, non-governmental organizations are being
invited to participate in the EA Public Participation process by
means of published advertisements, notices and written
correspondence.
4
4 NEED AND DESIRABILTY OF THE ACTIVITY
Exploration and mining activities have been the backbone of the
Namibian economy for decades. Participation of local communities
in mining and exploration sector does not only create employment
and increase revenue, but also contribute to the GDP of the
country, which can help achieve a balance between the creation
and distribution of wealth. Additionally, mining forms the core of
some of Namibia’s development plans, namely: National
Development Plan 5 (NDP5) and Harambee Prosperity Plan (HPP).
These plans are benchmarks on the ideals of Vision 2030. Successful
exploration work on EPL 7030 can lead to mining activities that
would feed into the mentioned development plans.
5 PROJECT DESCRIPTION
The prospecting and exploration activities entail the following three
mineral commodity groups: (i) Base and rare metals, and (ii)
precious metals. Base metal (i.e. copper metal) is the main target
for the planned exploration activities. The selection of the potential
mineralization model and exploration targets has been specially
selected based on the regional and likely local geology as well as the
results of the past exploration activities. According to the
information contained in the technical report prepared using
available geological data sets pertaining to previous exploration
activities in the surroundings area, EPL 7071 has a potential to host
stratabound copper-silver mineralization. The objective of the
planned prospecting and exploration is to delineate the mineral
(copper) deposits and determine whether the deposits are
economically viable for mining. The EA process will identify sensitive
environmental features that might be affected by the proposed
prospecting and exploration activities. The level and magnitude of
planned exploration work is not clear at this stage. However, both
invasive and non-invasive exploration activities are expected to take
place upon issuance of an environmental clearance certificate. Non-
invasive activities include geological field mapping, geophysical
survey work, airborne and ground based surveys. Invasive activities
involve soil and rock sampling, trenching and drilling.
5.1 Accessibility
The EPL 7071 is situated near Ombombo Settlement. From the
capital city of Windhoek, the property is accessed by a tarred two-
lane highway to the town of Opuwo, the nearest population center.
5
From Opuwo a well-maintained gravel road D3710 leads to the
eastern part of the EPL 7071.
5.2 Water Supply
Water required for exploration activities will be obtained from
existing boreholes, or from approved water sources, through water
abstraction permits. In accordance with the Water Resources
Management Act, 2004, (Act No. 24 of 2004) and in view of the arid
nature of the Namibian environment, the disposal of wastewater as
well as all other type of waste is strictly controlled. In most cases
and in particular wastewater is disposed of in evaporation ponds
because no effluent may be discharged into the ephemeral, dry
river beds in the interior of Namibia. The reclamation, re-use and
recycling of waste is encouraged whenever an industry applies for a
waste water disposal permit.
5.3 Infrastructure
Infrastructure on the EPL 7071 is limited to the network of roads
and tracks described in 5.1. A number of small villages are present
on the property. None of the villages has electricity, running water
or sewage facilities. Cell phone coverage is sporadic at best. Long
distance communication is accomplished via radio, satellite phone
or over the internet using the Inmarsat satellite network. Opuwo,
the nearest town, has a clinic, postal service, grocery stores, fuel
stations, hotels and is the seat of government for the Kunene
region. The tarred highway begins at Opuwo and provides access to
the rest of the country. From Opuwo it is 600 kilometres by road to
the copper smelter at Tsumeb and 650 kilometres to the port of
Walvis Bay.
6
6 ENVIRONMENTAL ASSESSMENT
This EA process is conducted according to the provisions laid out in
the Environmental Management Act (No 7 of 2007) and its’
Environmental Impact Assessment Regulations (2012). The primary
objective of the EA will be to identify potential negative impacts
that may be associated with the proposed activity, assess them and
recommend practical and effective mitigation measures that will be
implemented by Aloe Investments Two Hundred and Thirty Eight
(Pty) Ltd and their contractor(s) to minimize these impacts, if they
cannot be avoided altogether, while maximizing positive impacts.
The EA process serves primarily to inform the public and relevant
authorities about the proposed project and to determine any
impacts. The project duration is 4-5 months.
The main objectives of this EA are to:
Comply with Namibia’s Environmental Management Act
(2007) and its EIA regulations (2012).
Identify potential impacts associated with the proposed
Activity.
Inform Interested and Affected Parties (I&APs) and relevant
authorities about the mining activities and to provide them
with a reasonable opportunity to participate during the EA
process.
Assess the significance of issues and concerns raised.
Compile a report addressing all identified issues and
potential impacts related to various aspects of the activity.
Compile an Environmental Management Plan (EMP) which
includes impact mitigation measures.
We are here
7
6.1 Environmental and Social Baseline
The proposed prospecting and exploration activities will be
undertaken in a specific environmental and social conditions. The
summary of selected environmental and social baseline information
pertaining to the exploration area is given below.
6.1.1 Climate and Vegetation
In the absence of site-specific (Ombombo) climatic data, the general
Kunene region and where possible Opuwo climate information will
be used for this report. Kunene region’s temperature can be
classified as semi-arid to very arid (IRDNC, 2015). The variation of
rainfall range between 50mm to 350mm rain per year and
consequently, livestock and wildlife are exposed to severe drought
and flooding. The Region has a solar radiation of around 6 to 6.2
kWh/m2 per day for Opuwo and an annual average temperature of
20 - 21°C, indicating sunny and hot temperature. This high
temperature results in a high average annual evaporation of
between 3000 - 3200 mm annually and potential evapotranspiration
ranging between 1250 - 1500 mm per annum. In general, for
exploration stage projects, certain field activities can be carried out
year-round; however, movement of heavy equipment such as drill
rigs is problematic during the rainy season due to deteriorated road
conditions. Drilling is typically suspended during the rainy season
from December through to March or April.
6.1.2 Physiography and Local Geology
Opuwo area and the surrounding Kaokoland are geologically
situated within the Kaoko and Damara Belt (Miller, 2008). Damara
Orogen rocks which forms part of Neoproterozoic orogenic belt
comprises the Kaokoland or Kunene region. In the Kaoko Belt the
Swakop Group overlies the Nosib Group west of the Sesfontein
thrust fault. East of the fault where Nosib age sediments were
deposited in half-grabens on the basin margin the Group is overlain
by more carbonate rich units of the Otavi Group. The region is
characterized by a series of north-northeast trending ridges and
valleys. The sedimentary and tectonic framework of the Damaran
succession within the EKZ has many of the essential ingredients for
developing a sediment-hosted copper deposit. Ridge top elevations
vary from over 1,700 metres in the north to around 1,200 metres in
the south. Vegetation is dominated by thorny brush of various
types. No permanent running water exists in the EPL area although
flash floods are common during the rainy season (Mendelsonh,
1999).
8
6.2 Potential Impacts
The following potential impacts have been identified so far for the
surrounding towns, settlements and property:
Positive:
Creation of jobs to the locals.
Helps boost local economic growth.
Open up other investment opportunities.
Contribution to regional economic development.
Negative:
Generation of dust from the prospecting and exploration
activities and access gravel road.
Possible destruction of faunal habitats as well as removal of
vegetation that may be encountered within the target
areas.
Visual impact (scars) on landscape that will, because of low
rainfall, remain so for a very long time if not rehabilitated.
Potential health and safety risks associated with
mishandling of handheld mining equipment.
Environmental pollution.
The potential impacts listed above were pre-identified. More
potential impacts will be identified as the EA process progresses i.e.
upon site visit and consultation with the public. All impacts and
public concerns/comments will be incorporated and addressed in
the Environmental Assessment Report.
6.3 Public Consultation
Public consultation is an important part of EA process. During the
consultation process, interested or affected members of the public
are given an opportunity to find out more about the activity and
raise any issues or concerns pertaining to the environmental
assessment.
To comment or receive further information on the project, please
register with Excel Dynamic Solutions (Pty) Ltd (contact details
below) as an Interested and Affected Party (I&AP).
9
Contact: Mr. Kai Kleingunther Tel: +264 61 259 530
Fax: +264 886 560 836 Email: [email protected]
All registered I&APs will be kept informed throughout the various
stages of the project and will be provided the opportunity to
comment on the Scoping Report.
Communication details
Comments Date: until 25 October 2019
I hereby wish to register as an Interested and Affected Party
(I&AP) for the
EPL 7071 EA process
Name:
_______________________________________________________
_______________________________
Organization:
_______________________________________________________
_______________________________
Postal address:
_______________________________________________________
_______________________________
Email:
_______________________________________________________
_______________________________
Phone #: ____________________________________
Fax #: ___________________________________
My initial comments, issues or concerns are:
10
_______________________________________________________
_______________________________
_______________________________________________________
_______________________________
_______________________________________________________
_______________________________
_______________________________________________________
_______________________________
_______________________________________________________
_______________________________
_______________________________________________________
_______________________________
Other individuals, stakeholders, organizations or entities that should
be registered are:
Name:
_______________________________________________________
_______________________________
Organization:
_______________________________________________________
_______________________________
Email:
_______________________________________________________
Phone #: ____________________________________
Fax #: __________________________________
Please return details to: Mr. Kai Kleingunther
P O Box 997154, Maerua Mall, Windhoek
APPENDIX F: NEWSPAPER ADVERTS (THE NAMIBIAN AND NEW ERA)
Newspaper Adverts (The Namibian and New Era) notifying the public
about the Environmental Assesment Process
APPENDIX G: MINUTES OF THE PUBLIC MEETING (EPL 7071)
Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd EA: EPL 7071
Meeting Minutes
Date: 25 September 2019 (rescheduled to 15th October, 2019)
Locality: Chief’s residence, Ombombo, Kunene Region
Methodology:
The public members in the meeting were given an opportunity to give their comments and concerns on
the proposed exploration project. A house-to-house consultation was also undertaken by the
consultant. These concerns and comments were noted down and are presented in the table below:
Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd EA: EPL 7071
No. Name of person
commented
Organization Comment/issue Name of person
responded
Response
1 R. Tuqundja
Mumbuu
Chief: Ombombo What other stakeholders did you
(consultant) approach? I am only in charge of
Ombombo and Okahua villages but projects
of these magnitude should be communicated
to both traditional and regional authorities.
N. Tjelos as the EAP
Various stakeholders
(government and non-
governmental) have
been informed about
the project and will
continue to receive
project information as
the project progresses.
The list of stakeholders
(interested and affected
parties) includes
different ministries,
regional offices among
others. The list of the
interested and affected
parties will be made
available in the scoping
report.
Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd EA: EPL 7071
When is the exploration work starting?
The project is good if work opportunities will
be generated for community members
N. Tjelos as the EAP
N. Tjelos as the EAP
According to the
exploration project
manager, work will start
soon after the granting
of an Environmental
Clearance Certificate.
Noted.
J. Virere Resident Why do you need our details? How safe is
our personal information?
N. Tjelos Your concern is noted.
Information requested
for by the consultant is
for project related
communications, only.
You may opt not to
share your details.
3 Anonymous Nurse at Ombombo clinic Directive for us to contribute to the process
should come from our head office (Ministry
of Health and Social Services head office in
N. Tjelos as the EAP
Noted and understood.
A letter and BID were
submitted to the
Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd EA: EPL 7071
Windhoek). Executive Director’s
office.
4 U. Kapeke Resident This is good news. Some of us have
exploration experience from previous
exploration projects
N. Tjelos as the EAP
Noted
5 S. Kakuva Resident (Okahua) We need enough time to collect views of
other public members. A second meeting
should be organized where findings of the
study will be shared with us.
N. Tjelos as the EAP Noted. Please note that
we did a house to house
visit prior to the
meeting. However,
another meeting will be
organized after the
impacts assessment as
per request. Exact date
and time will be
communicated to
community members
through the established
point of contact as
agreed at the start of
Aloe Investments Two Hundred and Thirty-Eight (Pty) Ltd EA: EPL 7071
Remark: Many of the public members are were in support of the Environmental Assessment being conducted prior to exploration because the
earmarked area has had prospecting activities in the past and community is in search for economic opportunities.
the meeting.
APPENDIX H: PUBLIC MEETING ATTENDANCE REGISTER