Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial...

24
 Appendix D Decommissioning and Reclamation 

Transcript of Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial...

Page 1: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

 

Appendix D Decommissioning and Reclamation 

Page 2: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

 

Appendix D.1 Decommissioning and Reclamation Plan

Page 3: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

  

BOSWELL SPRINGS PROJECT Decommissioning and Reclamation Plan August 2017

Page 4: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

BoswellWindLLC.2017.BoswellSpringsProjectDecommissioningandReclamationPlan.August.

Page 5: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

i August 2017

 

Contents 

Page 

Chapter 1 Wind Facility Decommissioning ......................................................................................... 1‐1

1.1 Nature and Location of Facility ........................................................................................ 1‐1

1.2 Facility Decommissioning................................................................................................. 1‐1

Chapter 2 Reclamation ...................................................................................................................... 2‐1

2.1 Noxious Weed Control ..................................................................................................... 2‐1

2.2 Interim Reclamation ........................................................................................................ 2‐1

2.3 Final Reclamation ............................................................................................................. 2‐2

2.4 Reclamation Success ........................................................................................................ 2‐3

Chapter 3 Reclamation Seed Mixes ................................................................................................... 3‐1

3.1 Shallow Loamy Ecological Site Description ...................................................................... 3‐1

3.2 Loamy Ecological Site Description ................................................................................... 3‐2

3.3 Sandy Ecological Site Description .................................................................................... 3‐3

3.4 Shallow Sandy Ecological Site Description ....................................................................... 3‐3

3.5 Coarse Upland Ecological Site Description ...................................................................... 3‐4

Chapter 4 References ........................................................................................................................ 4‐1

 

Page 6: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

ii August 2017

 

Tables 

Table  Page 

Table 3‐1.  Seed Mixes for Bluebunch Weatgrass/Rhizomatous Wheatgrass Plant 

Community (Shallow Loamy ESD) .................................................................................... 3‐2 

Table 3‐2.  Seed Mixes for Rhizomatous Wheatgrass/Needle and Thread Plant Community 

(Loamy ESD) ..................................................................................................................... 3‐2 

Table 3‐3.  Seed Mixes for Needle and Thread/Rhizomatous Wheatgrass Plant Community 

(Sandy ESD) ...................................................................................................................... 3‐3 

Table 3‐4.  Seed Mixes for Mid Bunchgrass Plant Community (Shallow Sandy ESD) ........................ 3‐4 

Table 3‐5.  Seed Mixes for Mid Bunchgrass/Bitterbrush Plant Community (Coarse Upland 

ESD) .................................................................................................................................. 3‐4 

Page 7: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

iii August 2017

 

Acronyms 

BMPs  best management practices  

ESDs  Ecological Site Descriptions  

ISC  Industrial Siting Council  

MLRA  Major Land Resource Area  

NRCS  Natural Resource Conservation Service  

PLS lbs./ac  Pure Live Seeds per acre  

SWPPP  Stormwater Pollution Prevention Plan  

Page 8: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

iv August 2017

 

ThisPageIntentionallyLeftBlank

Page 9: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

1‐1 August 2017

 

Chapter 1 Wind Facility Decommissioning 

ThissectionprovidesinformationonthemethodologyfordecommissioningtheProject.Asrequiredbyagenciesandlandowner,BoswellWindwillprovideassurancesthattheplanscanbeimplementedintheformofasuretybond,certificateofdeposit,corporateguaranteeorotherformacceptabletotheWDEQandtheIndustrialSitingCouncil(ISC)priortoconstruction.ThevalueofthesecuritywillreflectthegrossdecommissioningandreclamationcostsfortheProject.

Facilitydecommissioningandreclamationwillbeginwithin12monthsafterthefacilityoranindividualwindturbineceasestoproduceelectricity.TheCouncilmayextendthetimeperiodofSection(8)(a)(iii)(B)ifthefacilitydemonstratesgoodcausepriortotheendofthecontinuousperiodof(12)monthsofthefacilityorwindenergygeneratingtowersnotgeneratingelectricity.BoswellWindwillprovideupdatestotheAdministratoreveryfive(5)years.

1.1 Nature and Location of Facility TheproposedProjectislocatedinAlbanyCounty,10milesnorthofRockRiver,WY,and15mileseastofMedicineBow,WY,atelevationsrangingfrom6,713to7,192feet.ThemainaccesstotheProjectwillbeviaInterstate80(locatedabout50milessouthoftheProject),U.S.Highway30,andFettermanRoad,whichbisectstheProjectArea.Thesiteisrelativelyflatandischaracterizedbyrollingplainswithhills,cuestas,mesas,andterraces.Thesiteisdominatedbygrasslandwithpocketsofsagebrushinthenorthwesternandnortheasternportionsofthesite.ThereareafewriparianemergentwetlandsalongSevenmileCreekandSpringCreek,butnolargebodiesofopenwaterexistwithinthesite.TheProjectAreaislargelyundevelopedandmainlyusedforcattleranching.Stockhandlingareas,roadsandfences,andstockpondsandreservoirsaretheprimaryconstructedfeaturescurrentlyonsite.

1.2 Facility Decommissioning Decommissioningisastep‐by‐step,methodicaldeconstructionprocess,whichinvolvesremovinganddisposingoftheProject’sturbinesandassociatedfacilitiesandinfrastructure.Withsomeexceptions,sitedecommissioninginvolvesthereverseofsiteconstruction.DecommissioningoftheBoswellSpringsProjectisexpectedtofollowastandardprocedure,whichtypicallyincludesthefollowing:

Allturbineswillbedismantledandeitherrelocatedtootherwindenergyprojectsorsoldforscrapvalue;

Electronicequipmentwillberecycledwheneverpossible.Ifnot,itwillbedisposedofinlandfillsorproperlylicensedhazardouswastefacilitiesasappropriate(someelectronicsareconsideredhazardouswasteduetothepresenceofheavymetals);

Transformersandelectricalcontroldeviceswillbereusedinotherapplicationsorsoldasscrapafterfluidremoval;

Page 10: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

1‐2 August 2017

 

Turbinefoundationswillberemoveddowntoadepthoffourfeetandbackfilledwithstockpiledsubsoilandtopsoil;

Undergroundcollectorcableswillberemoved;

Accessroads,rockorgravelintheelectricalsubstations,transformerpads,andbuildingfoundationswillberemovedandrecycledifnolongerneededorwantedbythelandowners;

Landareascoveredinrock,gravel,orbuilding/towerfootprintswillberestoredtoanaturalgrade(whichincludesamelioratingsoilcompactionthatmighthaveresultedfromprojectuses)andreseededorreplantedwithnativevegetationorpasturegrassesfollowingconsultationwithcurrentlandowners;

Electricalsubstationsandstoragebuildingwillbedismantled,includinginspectionforandremediationofanyenvironmentalcontamination;

Demolitionorremovalofequipmentfacilitieswillmeetapplicableenvironmentalandhealthregulations,andeconomicallyrecoverablematerialswillbesalvaged;

Alldisturbedareaswillbereclaimedandrestoredsopriorlandusescanberesumed.

Withlandownerapproval,BoswellWindmayleavethemaintenancebuildingonsite.ThiswouldalsorequirewrittennotificationtotheAdministrator.

Page 11: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

2‐1 August 2017

 

Chapter 2 Reclamation 

Followingdecommissioning,interimreclamationwillincluderevegetationoftemporarysurfacedisturbancewithseedmixesagreeduponwiththelandowner.

Afterdecommissioningthedisturbedareaswillbereclaimedandreturnedtopre‐Projectlanduses(grazing).Asrequiredbylandowneruseagreement,finalreclamationwillincluderegradingorre‐contouring,soilamendments,andreseedingdisturbedareaswithagreeduponseedmixes,andcontrollingnoxiousweeds.RefertoChapter3,EcologicalSiteDescriptions,forthepreferredseedmixesforbothinterimandfinalreclamationdependingonthevariousecologicalsiteconditionsthroughouttheProjectArea.

2.1 Noxious Weed Control BoswellWindwillcontrolnoxious,non‐native,andinvasiveweedsintheProjectArea.Asappropriate,BoswellWindwillimplementthefollowingbestmanagementpractices(BMPs):

Onlyapproved,certifiedweed‐freeseedswillbeused.

MonitoringthroughouttheProjectAreafornoxiousandinvasiveweedswilloccurregularly.

Weedswillbecontrolledasneededandwithappropriatecontrolmethods.

Contractorswillwashconstructionequipmenttoensurethatitisfreetopotentialweedseeds.

Weedoccurrenceswillbemarkedduringdecommissioning.

2.2 Interim Reclamation InterimreclamationwillcomplywithapplicablepermittingrequirementsoftheDEQWaterQualityDivisionstormwaterprogram.Oncevegetationiscleared,BoswellWindwillsalvagesoilduringconstructionactivitieswhichwillberemovedascut,usedasfill,orstockpiledforfutureinterimoffinalreclamation.Followingdecommissioning,temporaryworkareas(e.g.,parkingandlaydownareas,accessroadshoulders,cabletrenches,etc.)willbereclaimedandrevegetatedwithlandowner‐approved,habitat‐appropriateseedmixesincludedinthisplan.Temporaryworkareaswillbepreparedforseedingbyusingmethodsincludingbynotlimitedtosoilconditioning,decompaction,andtopsoilprotectionmeasurestoreestablishtopsoilpropertiesandtoprotecttheseedingsurface.Seedbedpreparationmayincludetopsoilreplacement,discing,mulching,hydro‐seeding,targetedfertilization,watering,andothersurfacerougheningtechniquesasappropriatewhichwillhelpensuresuccessfulestablishmentofvegetation.Initialseedingwillbeusedtoachievetemporaryvegetationcoverageorstabilizationofsoilstockpilesuntilinterimreclamationmeasurescanbeimplemented.

RecommendedseedmixesbasedonEcologicalSitespresentwithintheProjectAreaareprovidedbelowinChapter3.ReclamationSeedMixes.Seedmixeswillbedevelopedincoordinationwithlandownersandwillbetailoredtoestablishspeciescomposition,structure,andtotalgroundcover

Page 12: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

2‐2 August 2017

 

appropriateforthedesiredplantcommunity.Seedingwillbeimplementedduringallphasesofdevelopmentdependingoninterimorfinalreclamationobjectives.Whenpossible,seedingwilloccurpriortoprecipitationeventstoincreasethelikelihoodofgerminationandvegetationestablishment.SeedingofaffectedlandwillbeconductedduringthefirstnormalperiodforfavorableplantingconditionsafterfinalpreparationunlessanalternativeplanisapprovedbyISC.

BoswellWindwillcontrolnoxious,non‐native,andinvasiveweedsintheProjectAreaincooperationwithlandowners.Areasmostsusceptibletonoxiousandinvasiveweedinfestations(e.g.,disturbedsoils,roadsides,drainages)willbemonitoredregularlyforthepresenceofnoxiousandinvasiveweeds.

2.3 Final Reclamation  

2.3.1 Existing Site Conditions 

TheProjectsiteislocatedinAlbanyCounty,10milesnorthofRockRiver,WY,and15mileseastofMedicineBow,WY,atelevationsrangingfrom6,713to7,192feet.Thesiteisrelativelyflatandischaracterizedbyrollingplainswithhills,cuestas,mesas,andterraces.Thesiteisdominatedbygrasslandwithpocketsofsagebrushinthenorthwesternandnortheasternportionsofthesite.ThereareafewriparianemergentwetlandsalongSevenmileCreekandSpringCreek,butnolargebodiesofopenwaterexistwithinthesite.TheProjectsiteislargelyundevelopedandmainlyusedforcattleranching.

VegetationcoveristypicaloftheLaramieBasinandFoothillShrublandsandLowMountainsecoregions,whichisdominatedbysagebrushsteppeandmixed‐grassprairie.TheFoothillShrublandischaracterizedbymontaneshrublandconsistingofmountainbigsagebrush(Artemisiatridentata),rabbitbrush(Chrysothamnusspp.),bluebunchwheatgrass(Pseudoroegneriaspicata)andIdahofescue(Festucaidahoensis)atlowerelevationsandbyRockyMountainjuniper(Juniperusscopulorum)andponderosapine(Pinusponderosa)athigherelevations.Utahjuniper(Juniperusosteosperma)andmountainmahogany(Cercocarpusledifolius)woodlandsoccuronrockoutcrops.TheLaramieBasinisdominatedbybluegrama(Boutelouagracilis),Indianricegrass(Achnatherumhymenoides),westernwheatgrass(Pascopyrumsmithii),rabbitbrush,fringedsage(Artemisiafrigida),andavarietyofotherforbandshrubspecies.

2.3.2 Reclamation Methods 

Afterturbinedecommissioningandremoval,thedisturbedareaswillbereclaimedandreturnedtopre‐Projectlanduses(grazing)andwillfollowlandowneruseagreements.Disturbedareaswillbefilledinwithnativesoilandcompacted.Thesurfacewillbegradedandre‐contouredtoblendinwithexistingtopographyandsurroundingterrain.Majordisturbancefromdecommissioningactivitieswillberepairedandroadswillbeleftinplaceforlandowneruse.Thesubstationareawillbefilledinwithnativesoilandwillbegradedandreturnedtonaturalcontours.

Themethodsoffinalreclamationwillfollowmethodsdiscussedaboveforinterimreclamationincludingsoilandseedbedpreparation,seeding,andinvasiveweedcontrol.

Page 13: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

2‐3 August 2017

 

2.4 Reclamation Success Reclamationwillbeimplemented,managed,androutinelymonitoredbyBoswellWindwithoversight/approvalfromISC.SuccessstandardswilltiertothosesuccessstandardsidentifiedintheStormwaterPollutionPreventionPlan(SWPPP)thatwillbedevelopedfortheWyomingPollutantDischargeEliminationSystem–LargeConstructionPermit.

 

Page 14: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

3‐1 August 2017

 

Chapter 3 Reclamation Seed Mixes 

ThedominantvegetationhabitattypesarederivedfromNaturalResourceConservationService(NRCS)EcologicalSiteDescriptions(ESDs)presentintheProjectArea.ESDsprovideguidelinesforwhichspeciesshouldoccurinplantcommunitiesindifferentrainfallzonesandsoiltypes(Miller2010).TheProjectAreaislocatedwithintheCoolCentralDeserticBasinsandPlateaus(HighPlainsSoutheast)MajorLandResourceArea(MLRA),whichreceivesanaverageof10to14inchesofrainfallperyear.ThedominantESDsarecomposedofShallowLoamy(6,652acres;30.8percentoftheProjectArea);Loamy(5,766acres;26.7percentoftheProjectArea);Sandy(3,401acres;15.8percentoftheProjectArea);ShallowSandy(1,868;8.7percentoftheProjectArea);andCourseUpland(1,119;5.2percentoftheProjectArea).Combined,theseESDscompriseapproximately17,687acres,or87percentoftheProjectArea.

Thetablesinthissection(listedbydominanthabitattype)areproposedspeciestobeseededduringreclamationandrestorationeffortsassociatedwiththeBoswellSpringsWindProject.Speciesproposedforseedingarebasedonexistinghabitattypes,commercialavailability,andcurrentlanduses.Speciessubstitutionscanbefurthertailoreddependingonlong‐termandcurrentlanduseobjectivesbythelandownerandonthedesiredhabitatsfollowingprojectrestoration.Thespecieslistedbelowareappropriatefortemporaryreclamationfollowingconstructionactivities,andforpermanentreclamationfollowingdecommissioningoftheProject.

TheapplicationrateofeachspeciesismeasuredaspoundsofPureLiveSeedsperacre(PLSlbs./ac.).NRCSrecommendsaminimumof20PLSlbs./ac.persquarefootfordrillseedingsofmostspecies.Thetablesbelowassumedrilledapplications.NRCSfurtherrecommendsdoublingtherateforbroadcastseedingandforseedingcriticalareaswheregerminationisinhibitedbylowsoilqualityorotherfactors.Theratesincludedinthetablesbelowarebetween20–30PLSlbs./ac.

Speciessubstitutionscanandshouldbeadjustedbasedonspecificsitecharacteristicssuchassoiltexture,slopeaspect,moistureavailability,andspecificlanduses.Speciessubstitutionscanbefurthertailoreddependingonlong‐termandcurrentlanduseobjectivesbythelandownerandonthedesiredhabitatsfollowingprojectreclamation.

3.1 Shallow Loamy Ecological Site Description Potentialvegetationisapproximately70percentgrassorgrass‐likeplants,10percentforbs,and20percentwoodyplants.Themajorgrassesincludebluebunchwheatgrass,westernwheatgrass,neadleandthread,andIndianricegrass.Othergrassesinclude,Sandbergandmuttonbluegrass,prairiejunegrass,bottlebrushsquirreltail,plainsreedgrass,andthreadleafsedge.Blacksagebrush,bigsagebrush,andgreenrabbitbrusharethemajorwoodyplants.

Page 15: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

3‐2 August 2017

 

Table 3‐1.  Seed Mixes for Bluebunch Weatgrass/Rhizomatous Wheatgrass Plant Community (Shallow Loamy ESD) 

ScientificName CommonName PLSlbs./ac

Pseudoroegneriaspicata Bluebunchwheatgrass 2.7

Pascopyrumsmithii Westernwheatgrass 2.5

Hesperostipacomata Needleandthread 2.6

Koeleriamacrantha Prairiejunegrass 1.5

Achnatherumhymenoides Indianricegrass 3.6

Artemisiafrigida Fringedsagewort 2.0

Achilleamillefolium Commonyarrow 1.0

Chrysothamnusviscidiflorus Greenrabbitbrush 2.0

Artemisianova Blacksagebrush 3.0

Artemisiatridentata Basinbigsagebrush 3.0

Total 23.9

3.2 Loamy Ecological Site Description Potentialvegetationincludesapproximately80percentgrassesorgrass‐likeplants,10percentforbs,and10percentwoodyplants.Themajorgrazesincluderhizomatouswheatgrass,needdleandthread,bluebunchwheatgrass,andgreenneedlegrass.Bigsagebrushandrubberrabbitbrusharethemajorwoodyplants.

Table 3‐2.  Seed Mixes for Rhizomatous Wheatgrass/Needle and Thread Plant Community (Loamy ESD) 

ScientificName CommonName PLSlbs./ac

Pascopyrumsmithii Westernwheatgrass 2.5

Hesperostipacomata Needleandthread 2.6

Pseudoroegneriaspicata Bluebunchwheatgrass 2.7

Nassellaviridula Greenneedlegrass 4.2

Koeleriamacrantha Prairiejunegrass 1.5

Achnatherumhymenoides Indianricegrass 3.6

Boutelouagracilis Bluegrama 2.0

Sphaeralceacoccinea Scarletglobemallow 1.1

Artemisiafrigida Fringedsagewort 2.0

Artemisiatridentata Basinbigsagebrush 3.0

Total 25.2

Page 16: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

3‐3 August 2017

 

3.3 Sandy Ecological Site Description Potentialvegetationincludes75percentgrassesorgrass‐likeplants,10percentforbs,and15percentwoodyplants.Themajorgrassesincludeneedleandthread,Indianricegrass,andrhizomatouswheatgrass.Bigandsilversagebrusharethemajorwoodyplants.

Table 3‐3.  Seed Mixes for Needle and Thread/Rhizomatous Wheatgrass Plant Community (Sandy ESD) 

ScientificName CommonName PLSlbs./ac

Hesperostipacomata Needleandthread 2.6

Elymuslanceolatus Thickspikewheatgrass 3.5

Pascopyrumsmithii Westernwheatgrass 2.5

Boutelouagracilis Bluegrama 2.0

Pseudoroegneriaspicata Bluebunchwheatgrass 2.7

Poasecunda Sandbergbluegrass 2.0

Koeleriamacrantha Prairiejunegrass 1.5

Penstemonangustifolius Broadleafbeardtongue 7.2

Artemisiacana Silversagebrush 2.0

Artemisiatridentata Wyomingbigsagebrush 3.0

Total 29.0

3.4 Shallow Sandy Ecological Site Description Potentialvegetationincludes75percentgrassesorgrass‐likeplants,10percentforbs,and15percentwoodyplants.Themajorgrassesincludeneedleandthread,Indianricegrass,andbluebunchwheatgrass.Othergrassesandgrass‐likespeciesincludethickspikewheatgrass,Sandbergandmuttonbluegrass,prairiejunegrass,bottlebrushsquirreltail,plaisnreedgrass,andthreadleafsedge.Wyomingbigsagebrushandgreenrabbitbrusharethemajorwoodyplants.

Page 17: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

3‐4 August 2017

 

Table 3‐4.  Seed Mixes for Mid Bunchgrass Plant Community (Shallow Sandy ESD) 

ScientificName CommonName PLSlbs./ac

Pseudoroegneriaspicata Bluebunchwheatgrass 2.7

Achnatherumhymenoides Indianricegrass 3.6

Hesperostipacomata Needleandthread 2.6

Poasecunda Sandbergbluegrass 2.0

Boutelouagracilis Bluegrama 2.0

Elymuslanceolatus Thickspikewheatgrass 3.5

Koeleriamacrantha Prairiejunegrass 1.5

Artemisiafrigida Fringedsagewort 2.0

Chrysothamnusviscidiflorus Greenrabbitbrush 2.0

Artemisiatridentata Wyomingbigsagebrush 3.0

Total 22.9

3.5 Coarse Upland Ecological Site Description Thisvegetationcommunityevolvedwithgrazingbylargeherbivoresandiswellsuitedforgrazingbydomesticlivestock.Potentialvegetationincludes60percentgrassesorgrass‐likeplants,15percentforbs,and25percentwoodyplants.Themajorgrassesincludebluebunchwheatgrass,littlebluestem,andwesternwheatgrass.OthergrassesmayincludeIndianricegrass,prairiejunegrass,Sandbergbluegrass,andgreenneedlegrass.Bitterbrushandblacksagebrusharethedominantwoodyplants.Otherwoodyspeciesmayincludebigsagebrush,greenrabbitbrush,andserviceberry.

Table 3‐5.  Seed Mixes for Mid Bunchgrass/Bitterbrush Plant Community (Coarse Upland ESD) 

ScientificName CommonName PLSlbs./ac

Pseudoroegneriaspicata Bluebunchwheatgrass 2.7

Schizachyriumscoparium Littlebluestem 6.0

Pascopyrumsmithii Westernwheatgrass 2.5

Achnatherumhymenoides Indianricegrass 3.6

Koeleriamacrantha Prairiejunegrass 1.5

Artemisiafrigida Fringedsagewort 2.0

Achilleamillefolium Commonyarrow 1.0

Amelanchieralnifolia Saskatoonserviceberry 1.0

Purshiatridentata Antelopebitterbrush 0.5

Artemisianova Blacksagebrush 3.0

Total 23.8

 

Page 18: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Boswell Wind, LLC 

 

Boswell Springs Project 

 

Decommissioning and Reclamation Plan  

4‐1 August 2017

 

Chapter 4 References 

Miller,S.L.2010.Successfulrestorationofseverelydisturbedlands:seedingessentialforreclaimingdisturbedlands.B‐1204,April2010.UniversityofWyoming,CollegeofAgricultureandNaturalResources.

NaturalResourcesConservationService.2011.EcologicalSiteDescriptionSystemforRangelandandForestland.U.S.DepartmentofAgriculture,NaturalResourcesConservationService.Availableonline:https://esis.sc.egov.usda.gov/Welcome/pgESDWelcome.aspx.

NaturalResourcesConservationService.2008.SeedMixtureCalculatorSpreadsheet,ElectronicFieldOfficeTechnicalGuide.U.S.DepartmentofAgriculture,NaturalResourcesConservationService.

Page 19: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

 

Appendix D.2 Decommissioning Cost Estimate

Page 20: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Project Decommission Report

Intermountain Wind LLC– Boswell Springs A 400 MW Wind farm project

Albany County, WY

June 26, 2017

Page 21: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Intermountain Wind , LLC| Boswell Springs Project Project Decommissioning Report

Table of Contents DECOMMISSIONING ESTIMATE GENERATL DESCRIPTION: ....................................................................... 2

DECOMMISSIONING ACTIVITIES ............................................................................................................... 3

RECLAMATION ACTIVITIES ........................................................................................................................ 4

CONCLUSION ............................................................................................................................................. 4

APPENDIX: DECOMMISIONING COST ESTIMATE ..................................................................................... 5

1

Page 22: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Intermountain Wind , LLC| Boswell Springs Project Project Decommissioning Report

DECOMMISSIONING ESTIMATE GENERATL DESCRIPTION: The Boswell Springs project consists of 170 Wind turbine generators (WTG) with 34.5kV collection system, four power substations and 230kV transmission line system. Salvage and recycling value was not taken into consideration for this estimate. Decommissioning cost estimates were based on several sources of cost information. When possible, contractor bids from previous projects were used for equipment removal. When costs from previous projects were not available, industry standard publications, such as RSMeans cost data were used to estimate cost of decommissioning activities.

Decommissioning duration will depend on the time of year, number of crews, and equipment available. The biggest activity dictating decommissioning duration is the removal of the turbines. It is estimated that this will take a total of 8 to 9 months of this decommission the project. This estimate is based on one crane removing one turbine per day on a five day work week.

Below is description of major equipment on the project. • 25,000 Sq. ft O&M Building • 4 Substations

o 230kV metering equipment, switches and SF6 breakers. o 230/34.5kV main power transformers o 34.5kV Switchgear with vacuum breakers and 34.5 kV capacitor bank o Steel structures and equipment foundations o Fencing, grounding, and conduit o Station service power is provided by local utility and this estimate does not include the

station service transformer or utility circuit. • 34.5kV collection system

o Approximately 53 miles of 34.5kV underground collection buried 3’ deep o Approximately 9.9 miles of 34.5kV overhead collection. Assumed single wood pole

structures with 500’ between poles. • 230KV Intertie transmission line

o Approximately 13.25 miles of 230kV transmission line. Assumed wood Pole H frames structures with 750’ between structures.

• 230KV Gen-tie Line o Approximately 33.75 Miles of 230kV Transmission line. Assumed wood pole H frame

structures with 850 feet between structures. • Wind Turbine Generator

o 170 GE -2.3-116 Turbines. o 170 34.5kV/690V pad mount Generator step-up transformers (GSUs) o Assumed 55’ diameter spread footing turbine foundation 7 feet deep o Assumed 55’ by 80’ crane pad (crane pad surface 6” thick) o Assumed 40’ road section between main wind farm road and the turbine crane pad

(road surface 6” thick) o 45.5 Miles of 16’ wide (6” base and 6” surface aggregate) wind farm roads

2

Page 23: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning

Intermountain Wind , LLC| Boswell Springs Project Project Decommissioning Report

DECOMMISSIONING ACTIVITIES Disconnection of the 230kV Gen-tie line at the PacifiCorp’s Freeze Out substation will be completed by PacifiCorp. The rest of the 230kV line removal will be conducted by the project decommissioning contractor. The line conductors and static wire will be removed along with the static wire and pole hardware. 230kV poles will be cut at ground level and removed from the site. The removal of the line, hardware and poles can be conducted using typical utility equipment.

Wind turbine generator (WTG) interior small electrical equipment and cabling would be removed by hand. The oil in the gear boxes will be pumped out and hauled off site for proper disposal. A large crane will be required to remove the three turbine blades, blade hub, nacelle and three tower sections per WTG. The blades will be hauled to a land fill and the towers hauled to a recycling center. The nacelles and pad mount GSU transformers will be hauled to a salvage yard or a recycling center. Conduit and grounding around the WTGs will be removed. The WTG foundations will be removed 4 feet below the surface. The rest of the foundation will be left in place. The WTG foundation areas will be filled with soil and compacted. The surface material from the turbine roads, turn ins and crane pads will be removed after the turbine have been torn down and removed.

The 34.5kV underground collection system will be dug up and removed. This estimate assumes an automated trenching devise that excavates the trench, removes the cables, and backfills the trench will be used for this work. The cables will be cut to manageable sizes and hauled to a recycling center. Fiber optics cable and conduit will be hauled to a land fill. The 230kV intertie transmission conductor, the 34.5kV overhead conductor and pole hardware will be removed using utility bucket trucks. This material will be hauled to recycling center with the underground cable. The wood poles will be cut at ground level and left for the land owner’s use or hauled to a land fill along with the non recyclable pole hardware.

Substation decommissioning will start with disconnection and removal of the substation bus and conductors. This material will be taken to a recycling center. Power transformers will be drained of oil with an oil tank truck and the oil will be hauled off site for proper disposal. The SF6 breakers gas will be vacuumed out with a gas cart and the gas bottles will be hauled off site for proper disposal or re-use. Substation steel structures, power transformers and switchgear will be removed with a small crane and loaded on trucks for removal. The substation fence will be removed and hauled to recycling center. Substation gravel will be removed and hauled off site. Concrete foundations will be removed to 4 feet below grade with the remaining foundation abandoned in place. Below grade conduits, grounding, and cabling will be completely removed and hauled off site.

Substation station service power is provided by the local utility will be responsible for removal of this equipment. This will not be part of the project decommissioning activities. Cost for removal of main wind farm roads and O&M building is not included in total cost. These are intended to be left in place for land owner use.

3

Page 24: Appendix D Decommissioning and Reclamationdeq.wyoming.gov/media/attachments/Industrial Siting...Decommissioning and Reclamation Plan 1‐1 August 2017 Chapter 1 Wind Facility Decommissioning