Appendix A6: Records of Public Information Meetings (24 ...

95
Appendix A6: Records of Public Information Meetings (24 & 25 November 2010; and 22 & 23 March 2011)

Transcript of Appendix A6: Records of Public Information Meetings (24 ...

Page 1: Appendix A6: Records of Public Information Meetings (24 ...

Appendix A6:

Records of Public Information

Meetings

(24 & 25 November 2010;

and 22 & 23 March 2011)

Page 2: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

1

NEW LARGOOPENCAST COLLIERY

Project Overview and Description

CONFIDENTIAL

THERMAL COAL

2

CONTENTS

Motivation for the Proposed Mine

Locality Plan

Geology Overview

Preliminary Mine Plan & Mining Philosophy

Infrastructure

Safety & Sustainable Development

Community Development

Questions

Page 3: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

2

THERMAL COAL

3

1.0MOTIVATION FOR PROPOSEDMINE

THERMAL COAL

4

1.0MOTIVATION FOR PROPOSEDMINE

0

10

20

30

40

50

60

70GW

Installed Capacity Demand

Load shedding in 2008

Today Impact of Kusile /Medupi

Further massive investment requiredto address gap; IPPs may help withminor improvements, but continued

major effort needed by Eskom, ie. coalor nuclear

ELECTRICITY SUPPLY & DEMAND IN SA

Page 4: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

3

THERMAL COAL

5

2.0LOCALITY PLAN & PROJECTOVERVIEW

THERMAL COAL

6

NEW LARGO PROJECT IN THE WITBANK COAL HUB INCORPORATESBOTH NEW LARGO AND ZONDAGSFONTEIN RESOURCES

New LargoOpencast 632 Mt

Zondagsfontein EastMiddlingsUnderground 49 Mt

+4 SeamUnderground 139 Mt

Kusile power station(under construction)Lifetime50-60 years (potential)

ZondagsfonteinWestUnderground(potential)50 Mt

Page 5: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

4

THERMAL COAL

7

NEW LARGO AND KUSILE POWER STATION – KEY FACTS

AAIC Supply to KusileAAIC Supply to Kusile

> 15 mtpa supply commitment over 43 yearsagreed in MoU, but currently exploringextension due to Eskom's 55 yearrequirement

Coal supply from 4 mining operations:• New Largo• Zondagsfontein East Middlings• Zondagsfontein East No 4 Seam• Zondagsfontein West

Study Work commenced in 2006

Currently in a Feasibility Study phase

Eskom – Kusile power stationEskom – Kusile power station

•Key step in expanding Eskom's capacity andensure power supply over the next 60 years

•Intention of going online in early 2014

•Construction ongoing; started in August 2008

•Total capacity of 4.8 GW

•More stringent quality requirements than onmajority of past projects

> 10 mtpa

>3mtpa

THERMAL COAL

8

3.0GEOLOGY OVERVIEW

Page 6: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

5

THERMAL COAL

ACSA: New Largo

North SouthN12 Highway

South ValleyNorth Valley

Palaeohigh

GEOLOGICALSECTION N-S

N12Highway

Palaeohigh

N

S

THERMAL COAL

ACSA: New Largo

~0.91 m No. 5 Seam

4.6 - 8.2 m No. 2 Seam

~0.25 m No. 3 Seam

~4.50 m No. 4 Seam

~0.95 m No. 1 SeamBasement

14 mmainlysandstoneinterburden

11 mmudrockgrading tosandstone

1.8 msandstone

sandstone

Interburden = 13 m

Overburden = 17 m to 47m

STRATIGRAPHIC PROFILE

Page 7: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

6

THERMAL COAL

Various old underground collieries and adits

exist within the New Largo reserves

Prospecting Permit Area – 12 773Ha

Disturbed Area – 5 600 Ha

Underground Workings – 1 300Ha (23%)

An estimated 45 Mt have been extracted by

previous mining in the area

11

Old New Largo

Colliery

Alpha Colliery

Klipfontein Colliery

Balmoral Colliery

ACME Colliery

Goodyear & Old Klipfontein Collieries

OLD UNDERGROUND WORKINGS

THERMAL COAL

12

4.0PRELIMINARY MINE PLAN &MINING PHILOSOPHY

Page 8: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

7

THERMAL COAL

13

MINING PHILOSOPHY

Opencast mining selected due• Low strip ratio• Ability to maximize coal extraction – to sustain the life of Kusile Power Station• Ability to recover coal reserves remaining in areas previously mined by underground

methods.

Dragline vs Truck & Shovel for primary overburdenDraglines selected due to lower operating costs and safer exposure of coal in previouslymined underground areasSome small scale truck & shovel operations will be used to meet full coal supplyrequirements

Larger 190 ton payload trucks for coal hauling vs 150 ton trucks previously used - more efficient

Mine design manages :• spontaneous combustion in previously mined areas - mining buffer incorporated in the blast

design• dewatering of underground workings prior to opencast mining

Coal beneficiation plant required to wash coal from poorer quality areas of the opencast mine

THERMAL COAL

OPENCAST STRIP MINING METHOD Topsoil Stripping and Stockpiling / Live Placing

by Truck & Shovel

Overburden and Interburden Drilling, Blasting

and removal by Dragline

2 and 4 Seam Drilling, Blasting, Loading and

Hauling

Spoil flattening and compaction by Dozers

Topsoil Placement

Seeding, Fertilizing and Monitoring

14

MiningDirection

TopsoilStripping

Coaling

Dragline ExcavatingOverburden

Page 9: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

8

THERMAL COAL

15

Primary Production Equipment ApplicationFleetSize

Large Electric Walking Dragline – 100m3 Overburden removal 1- 2

Hydraulic Face Shovel 21m3 - 380 tonne (electric) Coal & OverburdenLoading 3 - 4

Hydraulic Backhoe 7m3 - 110 tonne (diesel) Topsoil and Parting 2

Front End Loader 20m3 - 200 tonne (diesel) Coal Loading 1

Track Dozer 100 tonne Doze over 3

Rear Dump Truck 180 - 190 tonne payload Coal Hauling 6 - 16

Rear Dump Truck 90 tonne payload Topsoil and Parting 3 - 6

Large Electric Overburden Drill Overburden Drilling 3 - 5

Coal Drill (diesel) Coal Drilling 3 - 5

Parting Drill (diesel) Parting Drilling 1 - 2

Track Dozer 65 tonne Dragline and shovels 5

NEW LARGO MINING EQUIPMENT

THERMAL COAL

MININGSEQUENCE

16

First Coal – 2015

(2015 – 2024) One Dragline with Truck &

Shovel support

(2025 – 2064) Two Dragline Operations

with DMS coal processing plant

Coal Reserves

ROM – 617Mt

Sales – 537Mt

Yield – 87%

North Pit

South Pit

Page 10: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

9

THERMAL COAL

17

0

2,000,000

4,000,000

6,000,000

8,000,000

10,000,000

12,000,000

14,000,000

16,000,000

18,000,000

2011 2014 2017 2020 2023 2026 2029 2032 2035 2038 2041 2044 2047 2050 2053 2056 2059 2062 2065 2068

Year

COAL SUPPLY TO KUSILE

Dragline No. 2 &DMS Plant in 2025

•51 Years Life in Total (2013 – 2063)•Includes coal from 3rd party sources & coal to be delivered via Phola/Kusile Overland conveyor

Zfn. East 4 Seam

Zibulo Middlings

Dragline 2

Dragline 1

3rd Party

Truck &Shovel

Dragline No. 1in 2015

THERMAL COAL

18

MINING PHILOSOPHY: DUST CONTROL

Dust Allaying on the Haul Roads

Transfer Points

Dust-hood at the ROM Tips

Dust Monitoring Programmes

Specialist Blast Design

Page 11: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

10

THERMAL COAL

MINING PHILOSOPHY: BLASTING CONTROL

Specialist input into New Largo’s blast design

Compliance to regulatory requirements – Air Blast (Noise) & Ground Vibration

Pre-blast and periodic surveys of structures and houses by a third party

Monitoring & Communication– Collaborative approach

500m Buffer Zones including Topsoil berms with trees to deflect the noise

Operational procedures around sensitive areas – N12 Highway, Oil Pipelines,

Towns etc.

THERMAL COAL

MININGPHILOSOPHY: REHABILITATION & GROUND WATERPOLLUTION CONTROL

20

eMalahleni Water Reclamation PlantRehab and Post-mining Topography Design

Topsoil Management

Page 12: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

11

THERMAL COAL

21

5.0INFRASTRUCTURE

THERMAL COAL

LOCATIONCurrent location of main infrastructure takes cognisance of:

Land ownership,

Prospecting permitting area

Topography,

Access,

Location of natural recourses and features, and

Existing infrastructure – Kusile Power Station

The direction of prevailing winds

Maximising sun energy with regards to the orientation of infrastructure.

22

Page 13: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

12

THERMAL COAL

OVERALL BLOCKPLAN LAYOUT

23

1. N12 & N4 Highways2. Kusile Power Station3. New Largo Admin, Workshops

& Stockpile Area4. Phola/Kusile Overland

Conveyor5. 2 x Tips6. Explosive Magazine Area7. Water Treatment Plant &

Balancing Dams

Infrastructure to be relocated:A. 400kV Duvha Minerva

Overhead PowerlinesB. R545 Provincial road

1

1

6

2 3

7

5

5

AA

4

BB

THERMAL COAL

R545 DEVIATION OPTIONS

24

3 Options being investigated:

• Option 1 (24,7km)• Via Balmoral Interchange• R104 (existing surfaced road)• D432 (gravel road)• Route turns right at Hartebeeslaagte

crossing the Saalklapspruit• Option 2 (17,8km)

• Via Rondebult Interchange• Linking onto R104• Road-over-rail bridge before linking

onto D432• Traverses D432 until it crosses N12

with a bridge overpass• No access to N12

• Option 3 (20,1km)• Route starts at D686 (Eskom re-

alignment)• Traverses in mostly AAIC

prospecting right boundary• Joins onto R545 near W ilge Village• Approval in-principle obtained from

Mpumalanga roads department.

Page 14: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

13

THERMAL COAL

25

TIPS2 x Tips (designed to accommodate 190Tpayloads)Dust hoods compulsory for all tips - dust suppression to be installed.Taking cognizance of prevailing wind direction

CONVEYORSDesigned for Optimum speedDust & Fire suppression to be included for all lengths of conveyors

STOCKPILESOnly ROM stockpiles – Run of mine (before beneficiation)Minimum capacity of 300 000tonsFootprint for product stockpiles - if required by customer (ESKOM) at a later stageFire Suppression

DMS PLANTDeshaling Plant to be commissioned in approx 2025Throughput of approx 9mtpa (ave)

THERMAL COAL

MAIN INFRASTRUCTURE/CONT……

26

WATER MANAGEMENTTreatment on site with a base case to discharge into the streams once the mine’s needs are met.No untreated water will leave siteIn line with the resource water quality objectives

WORKSHOP AND SERVICESEMV, LDV, Plant workshop, tyre bay, cable repair, etc

SURFACE INFRASTRUCTURE RELOCATIONProvincial road R545 to be deviated as it transgresses the coal resources.400kV Eskom Duvha Minerva Powerlines to be relocated - Eskom busy with separate EIA.Transnet pipelines & supporting infrastructure relocation to be further investigated

ELECTRICAL RETICULATIONConsumer Substation – 132kV premium power supply from ESKOM132kV to south pit, 22kV, 6,6kV, 550V, 380VDragline reticulation – 22kV

C&IAutomate, CCTV at transfers points,Central control room

Page 15: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

14

THERMAL COAL

NEW LARGO: ADMIN AREA BLOCKPLAN

27

1. Access Road from D6862. Consumer Substation3. Offices4. Stores & Workshop Area5. DMS Plant6. Stockpiles7. Pollution Control Dams

1

2

3

4

5

67

7

THERMAL COAL

28

6.0SAFETY & SUSTAINABLEDEVELOPMENT

Page 16: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

15

THERMAL COAL

29

SAFETY AND SUSTAINABLE DEVELOPMENT

SHEProject objectives are aligned with the AA target of achieving Zero Harm.Equipment design and procurement ensures AFRS compliance. Construction of the draglineswill require particular safety focusOperational risks are as per existing AATC operationsOHSAS 18001 & ISO 14001 to be implemented.

Legislation and permittingE&SIA aligned with Anglo Environment Way requirementsNew Mining Right Application required and has been submitted in April 2011EIA to comply with requirements of MPRDA and NEMA.NEMA application submitted in March 2011Integrated Water Use Licence required and to be submitted in line with Mining RightApplication.Permitting schedule integrated into overall project schedule.

Affected PartiesPlanned operations will be close to 2 settlements – Wilge Village and Kendal Forest Holdings.Buffers planned.Acquisition of surface rights progressing.Cumulative impacts of mine and power station to be assessed.Project located in a Priority Area with respect to air quality.

THERMAL COAL

30

7.0COMMUNITY DEVELOPMENT

Page 17: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

16

THERMAL COAL

31

COMMUNITY DEVELOPMENT

Employment

• Local recruitment – New Largo will endeavour to recruit locally where possible (terms andconditions will apply)

Local Economic Development

• Substantial investment in projects that will uplift the local economy – create jobs, upgrade anddevelop new skills and promote entrepreneurship

• CSI projects

Local Procurement

• Look into projects that will promote small businesses through – services and consumables asper the revised Mining Charter targets. To be delivered through the Ogies Zimele Hub.

THERMAL COAL

32

Current Investments in the area

• Phola Sewerage Upgrade – R 40m

• Phola/Ogies and Wilge – R 3m

• Phola Electrical Substation – R 8m

COMMUNITY DEVELOPMENT/Cont…

Page 18: Appendix A6: Records of Public Information Meetings (24 ...

5/20/2011

17

THERMAL COAL

33

8.0QUESTIONS

THERMAL COAL

34

THANKYOU

Page 19: Appendix A6: Records of Public Information Meetings (24 ...

1

Environmental Impact Assessment & Environmental Management ProgrammeWater Use License Application

Waste Management License (Potential)Scoping Phase Public Meetings – 11 & 12 May 2011

(Mari Wolmarans & Marline Medallie)

§ Map Orientation

§ Project Need and Desirability

§ Development Alternatives to be Considered

§ Environmental Legislation

§ Approvals and Authorisations Required

§ Study Process and Programme

§ Description of Affected Environment

§ Specialist Studies to inform EIA

§ Issues and Comments

Page 20: Appendix A6: Records of Public Information Meetings (24 ...

2

Location of New Largo Colliery

Page 21: Appendix A6: Records of Public Information Meetings (24 ...

3

Page 22: Appendix A6: Records of Public Information Meetings (24 ...

4

§ Eskom currently relies on coalfired power stations to produce~95% of the electricity in SouthAfrica

§ Eskom will remain dependent oncoal mining until such time asalternative energy generationoptions can be implemented ona sufficiently large scale

§ Kusile Power Station forms partof the South African NationalGovernment strategy to supplymuch needed electricity to theSouth African national electricitygrid

Page 23: Appendix A6: Records of Public Information Meetings (24 ...

5

§ The Ministry of Energy and Eskom maintain that:§ “In the absence of Kusile there will not be enough power into the South

African electricity grid"(Ministry of the Energy spokesperson Bheki Khumalo1).

§ “Without the additional power from Kusile from 2014, there could beconstraints on South Africa's economic growth"

(Eskom's Finance Director, Paul O'Flaherty).

Media release compiled by the GovernmentCommunication and Information System,26 Aug 2010.http://www.buanews.gov.za/rss/10/10082611151001

§ AAIC maintains that the proposed New Largo Colliery is needed to:

§ Ensure the supply of a secure, long-term supply of coal to Kusile

§ Enable Kusile to provide power to the national electricity grid on schedule

§ Address power shortages in the national grids since there are no short tomedium term options to replace Kusile’s energy generation capacity at anational level

§ Avoid negative impacts of energy shortages on national economic growthand development

Page 24: Appendix A6: Records of Public Information Meetings (24 ...

6

§ Main purpose of the project is to supply coal to Kusile

THUS

§ Development alternatives will focus on feasible options for supplycoal to Kusile

§ No project (no-go) alternative (implies alternative coal supplies to Kusile)

§ Mine plan and scheduling, including alternative box-cut positions and direction ofmining

§ Mining methods and mining equipment.

§ Methods and location for overburden and discard disposal.

§ Alignments for associated linear infrastructure such as pipelines, power lines andconveyor belts

§ Alignments for access roads and haul roads

§ Positions of tips, crushers and coal stockpiles

§ Locations for mine infrastructure, including the locations of offices, workshops,change houses, refuelling bays, explosive magazines, stores, etc.

Page 25: Appendix A6: Records of Public Information Meetings (24 ...

7

§ Water sources (process water and potable water) options

§ Routes for the realignment of the roads to be demolished

§ Land uses, i.e. agriculture, for the area

§ Technologies for the treatment of mine water (water treatment plant)

§ Uses for water treated at water treatment plant

§ Locations and designs for water management infrastructure

§ End land use objectives

§ Rehabilitation objectives and methods

§ Mitigation alternatives for biodiversity impacts / impacts on wetlands

§ EIA for opencast mining of the New Largo coal reserve initiated in2006§ Participation by stakeholders and development of a stakeholder issues

and response report§ Various specialist baseline studies

§ Project was delayed in 2007 and then postponed

§ Process started from scratch as regulations changed in 2010

§ 2007 issues and response report appended to the current reports

§ All past reports will be used to inform current studies and to identifyenvironmental trends

Page 26: Appendix A6: Records of Public Information Meetings (24 ...

8

EnvironmentalAuthorisation

Mpumalanga Departmentof Economic

Development,Environment and Tourism

(MDEDET)

• National Environmental ManagementAct (No 107 of 1998) (NEMA) andGovernment Notice Regulations 543to 546 (18 June 2010).

Approval of anenvironmental

management programme

Department of MineralResources.

• Mineral and Petroleum ResourcesDevelopment Act (No 28 of 2002)(MPRDA)

Approval of an integratedwater use license

Department of WaterAffairs

• National Water Act (No 36 of 1998)(DWA)

Approval of a wastemanagement license

National Department ofEnvironmental Affairs

and/or MDEDET (if it isconfirmed that a licenseis needed for this mining

project).

• National EnvironmentalManagement: Waste Act (No. 59 of2008) NEMWA

Heritage Assessment South AfricanHeritage

ResourcesAgency

• National Heritage Resources Act (No 25 of1999).

Permits for the destructionor removal of heritage

resources affectedPermits for removal,

relocation or destruction ofprotected species

MDEDET• Mpumalanga Nature Conservation Act (No 10 of

1998) and National Environmental Management:Biodiversity Act (No 10 of 2004).

Permits for removal,relocation or destruction of

protected trees(not applicable to date)

Department ofForestry and

Fisheries(DAFF)

• National Forestry Act (No 84 of 1989)

General legal complianceand environmental

management programmeVarious

• Conservation of Agricultural Resources Act (No43 of 1983).

• Environment Conservation Act (No 73 of 1989).• National Forests Act (No 84 of 1998).• National Veld and Forest Fire Act (No 10 1998).

Page 27: Appendix A6: Records of Public Information Meetings (24 ...

9

§ Various listed activities from§ GNR 544: Activities requiring a basic environmental assessment§ GNR 545: Activities requiring a full environmental impact assessment§ GNR 546 Activities in provincial sensitive areas (i.e. critical biodiversity

areas in Mpumalanga) requiring a basic environmental assessment

§ Full scoping and environmental impact assessment will be conducted

§ Application form was submitted to MDEDET on 1 March 2011(reference number 17/2/3N-41)

§ Governs all mining activities in South Africa

§ Mining right required prior to the commencement

§ Mining right may only be granted if:§ The mineral can be mined optimally and in accordance with a mining

work programme;§ The applicant has access to financial resources and technical ability;§ The financing plan is compatible with the intended operations;§ The mining will not result in unacceptable pollution, ecological

degradation or damage to the environment;§ The applicant has provided financially and otherwise for a social and

labour plan;§ The applicant can comply with the provisions of the Mine Health and

Safety Act;§ The applicant is not in contravention with provisions of this Act; and§ The granting of the right will further the objects of the MPRDA.

Page 28: Appendix A6: Records of Public Information Meetings (24 ...

10

§ Upon acceptance of a mining right application by the DME(typically 14 days after submission of the application) the applicantmust:§ Submit a scoping report (30 days) – 2 June 2011§ Conduct an environmental impact assessment (EIA) and submit an

environmental management programme (EMP) in terms of section 39 ofthe Act (180 days) – 21 October 2011

§ Notify and consult with interested and affected parties within 180 daysfrom the date of the notice (180 days) – 21 October 2011

§ The Act does not allow for delays or extension

§ Effectively limits the time available for public participation, specialiststudies and EIA reporting

§ To comply with Act, submission of reports to DMR will be prior to thefinalisation of the scoping report and EIA report produced in terms ofthe NEMA

§ There are a number of pans, drainage lines and hill slope seeps(wetlands) located within the proposed opencast mining footprintarea

§ ~9.7% of mining area classified as wetlands

§ Water uses in terms of Section 21 of the National Water Act requirelicensing

§ Water uses will be discussed and confirmed with the Department ofWater Affairs during the authority consultation process

Page 29: Appendix A6: Records of Public Information Meetings (24 ...

11

Section 21(a) Taking of water from a water resource .• Pumping of water from opencast mine pit.• Using water from the opencast p it area fo r dust suppression on haul roads and stockpiles.• Borehole water abstraction.• Pumping of water from the o ld underground workings.

Section 21 (b) Storing of water.• Potable water storage / reservoirs.• Raw water storage (clean , untreated water) / reservoirs.• Storing of con taminated water in pollution contro l dams.

Section 21 (c) Impeding or d iverting the flow of water in a watercourse.

• Activ ities within or near wetlands, or activities affecting wetlands.• Linear infrastructure (roads, pipe lines, power lines, and power lines) crossing streams and streams

associated with wetlands (culverts, causeways, bridges).

Section 21 (d) Engag ing in a stream flow reduction activitycontemplated in Section 36 of the Act. • To be confirmed.

Section 21 (e)Engaging in a controlled activity: S37(1)(a)irrigationoff any land with waste, or water containing wastegenerated th rough any industrial activity or by a

water work.• Water used for dust suppression (to be confirmed).

Section 21 (f) Discharging waste or water containing waste into awater resource.

• Discharge of treated water into a watercourse or into a wetland / pan.• Discharge of sewerage effluent.

Section 21 (g) Disposing of waste in a manner which may impacton a water resource.

• Disposal of waste produced at water treatment p lant (i.e. brine and gypsum)• Disposal of waste produced at sewerage treatment p lant (slurry).• Storage of process water (contamina ted water) in a pollution contro l dam / balancing dam /

evaporation dam.• Overburden dumps.• Disposal of coal processing waste (discard) – water use license only required from 2023.• Process water tanks / reservoirs associated with coal processing plant – water use license only

required in 2023.

Section 21 (h)Disposing in any manner of water wh ich conta ins

waste from, or which has been heated in, anyindustrial o r power generation process.

• To be confirmed.

Section 21 (i)Alte ring the bed, banks, course, or characteristics o fa watercourse. This includes altering the course of a

watercourse (previously referred to as a riverdiversion).

• Activ ities within or near wetlands, or activities affecting wetlands.• Linear infrastructure (roads, pipe lines, power lines, and power lines) crossing streams and streams

associated with wetlands.

Section 21 (j)Removing, d ischarging or disposing of water found

underground if it is necessary for the efficientcontinuation of an activity, or for the safety of

people.

• Dewatering of old underground workings / g roundwater abstraction before and during mining tolower water levels and to ensure safe working cond itions in the opencast mine pit.

Section 21 (k) Using water for recrea tional purposes. Not applicable.

Page 30: Appendix A6: Records of Public Information Meetings (24 ...

12

§ Mining wastes and wastes incidental to mining, as defined in theNational Environmental Management: Waste Act (No 59 of 2008)(NEMWA), do not require a waste management license (WML)

§ Consultation with the relevant authorities will confirm the applicabilityof NEMWA and whether or not a waste management license will beneeded for this mining project

§ NEMWA requires an EIA process and reports structured in terms ofthe requirements of GNR 543 (EIA regulations) in terms of the NEMA

§ The EIA for New Largo Colliery will specifically address theenvironmental impacts of the different wastes and EMP will deal withthe management of the wastes to avoid or minimise impacts

• Draft stakeholder issues and response report.• Comprehensive environmental specialist baseline

studies.• Draft scoping report.

Public participat ion process(First and second round of meetings). 2006 to 2007

• Seasonal ecological surveys.• Water quality monitoring (surface water and ground

water).All reports will be available during EIA review phase. 2010 to early 2011

Project notifications to landowners.Project notifications to general public andstakeholders.General and focus group meetings.Authority meetings.Stakeholder review of the draft and final scopingreport.

February 2011 to July2011

• All reports will be available during EIA review phase. February 2011 toAugust 2011

Registered I&APs will be notified of general and focusgroup meetings, and report review details.Authority meetings.General and focus group meetings.Stakeholder review of the draft and final reports(including review of all specialist reports.

August 2011 toFebruary 2012

Page 31: Appendix A6: Records of Public Information Meetings (24 ...

13

Environmental approvals and licensing.Public Participation Process and Authority Consultation

Process.2005 to October 2012

Construction,box-cut 1 (northern portion of mining area) and

commissioning of dragline 1EMP Implementation Monitoring. Nov 2012 to June 2015

First Coal Delivered to Kusile EMP Implementation Monitoring. June 2015

Mining Activity Ramp Up EMP Implementation Monitoring. June 2015 to 1017

Phase 1 Production Phase

(Open Pit 1 – Northern Mining Area)EMP Implementation Monitoring. 2018 to 2023

DMS coal processing plant construction,box-cut 2 (southern mining area) and commissioning

of dragline 2EMP Implementation Monitoring. 2021 to 2023

Full Production Phase (Phase 1 and Phase 2)

(Open Pit 1 – Northern Mining Area, and Open Pit 2– Southern Mining Area)

EMP Implementation Monitoring. 2023 to 2063

EMP Implementation Monitoring. From 2063

Page 32: Appendix A6: Records of Public Information Meetings (24 ...

14

District and LocalAuthorities in OlifantsRiver Catchment(OR EMF)

Local GovernmentBoundaries withinOlifants CatchmentQuaternary CatchmentsB20F – Upper Wilge (west)B20G – Saalklapspruit (east)

Page 33: Appendix A6: Records of Public Information Meetings (24 ...

15

§ Predominant wind direction within the New Largo region is from thewest-north-west (Kendal 2)

§ Less frequent winds are from the southern sector.

§ During daytime there is an increase in winds from the north-westerlysectors (Kendal 2)

§ At night-time the winds are more dominant from the east.

§ Night-time conditions reflect a decrease in wind speeds and anincrease in calm conditions.

§ Nearest sensitive receptors (human settlements)§ Ogies§ Phola§ Kendal Forest Holdings§ Wilge Village

§ Sources of SOx and NOx (gasses)§ Eskom power stations§ Chemical industries§ Brick manufacturers which use coal (e.g. Witbank§ Woodburning and wood drying by sawmills§ Other heavy industries§ Fuel combustion (primarily coal) by institutions such as schools and

hospitals§ Blasting operations at mines§ Spontaneous combustion at coal mines§ Veld burning§ Vehicle exhaust emissions§ Household fuel burning.

Page 34: Appendix A6: Records of Public Information Meetings (24 ...

16

§ Particulates : fine / suspended particulates (PM10) and dustfall§ Local

• Winderosion from exposed areas• Ash dams and dumps (i.e. Kendal)• Fugitive dust from agricultural and mining operations• Materials handling operations associated with mining and power station

activities• Vehicle entrainment from roadways• Veld burning.• Household fuel burning.• Releases from industrial operations.

§ Long-range transport of particulates• Remote tall stacks• Large-scale biomass burning north of South Africa

Page 35: Appendix A6: Records of Public Information Meetings (24 ...

17

Page 36: Appendix A6: Records of Public Information Meetings (24 ...

18

§ Only 14% of SA land surface suitable for rain-fed crop agriculture

§ 3% with ‘high potential’ crop lands

§ Delmas and Emalahleni fall within 3% with ‘high potential’ crop lands

§ 80% of Delmas, Emalahleni and Kungwini moderate to high potentialarable soils

§ 3-5 tons/ha dryland maize

§ 8 tons/ha under irrigation

§ ~700 mm rainfall

§ Soils generally in good condition

Page 37: Appendix A6: Records of Public Information Meetings (24 ...

19

§ Moderate to high agricultural land potential

§ Hutton soils – arable

§ Clovelly soils – grazing potential

§ Glencoe soils – grazing potential

Page 38: Appendix A6: Records of Public Information Meetings (24 ...

20

Page 39: Appendix A6: Records of Public Information Meetings (24 ...

21

§ Urban Centres§ Local Settlements§ Eastward expansion of Phola§ Agriculture§ Mining around Ogies and Phola§ Power generation (Kendal and Kusile)§ Construction (Kusile)§ Brick making (Balmoral, north)§ Chicken farms, egg producing§ Major national roads, N4 & N12§ Rural areas zoned for agriculture and mining with no restrictions (local

strategic plans)

Page 40: Appendix A6: Records of Public Information Meetings (24 ...

22

View of a pan found within mining area, withsurrounding agricultural land use

Page 41: Appendix A6: Records of Public Information Meetings (24 ...

23

View of old surface infrastructure associated with theold Wilge Power Station and old New LargoUnderground Mine

View of Wilge Village

Page 42: Appendix A6: Records of Public Information Meetings (24 ...

24

View of Phola Town

Page 43: Appendix A6: Records of Public Information Meetings (24 ...

25

§ Education (adult population)§ Mpumalanga

• 28% no schooling• 18% matriculated• 6% tertiary education

§ Emalahleni• 14% no schooling• 24% matriculated• 8% tertiary education

§ Health Services§ Mpumalanga

• Generally poor§ Emalahleni

• Above provincial standards

Page 44: Appendix A6: Records of Public Information Meetings (24 ...

26

§ Basic Services§ Mpumalanga

• Lack of access to water and sanitation§ Emalahleni

• Above provincial average• 41% of households with piped water• 25% of households with pit latrines without ventilation

§ Housing§ Mpumalanga

• 60% of population in brick houses• 12% in informal settlements

§ Emalahleni• 56% of population in brick houses• High number of informal settlements.• 40000 housing backlog (2004)

Page 45: Appendix A6: Records of Public Information Meetings (24 ...

27

§ Grassland Biome

§ Vegetation Units§ Eastern Highveld Grassland

• endangered§ Eastern Temperate Highveld Freshwater Wetlands

• only 5% conserved, national conservation target is 24%§ Rand Highveld Grassland

• endangered

§ Plant Communities (21% of mining area)§ 1: High lying rocky shrubland (2%)§ 2: Tall dry grassland on sandy midslopes (17%)§ 3: Tall moist grassland on seldom waterlogged footslopes (1%)§ 4: Tall wet grassland on seldom waterlogged footslopes (1%)

§ Remainder of mining area transformed (mostly agriculture)

Page 46: Appendix A6: Records of Public Information Meetings (24 ...

28

Page 47: Appendix A6: Records of Public Information Meetings (24 ...

29

s

Spotted Genet

Page 48: Appendix A6: Records of Public Information Meetings (24 ...

30

Page 49: Appendix A6: Records of Public Information Meetings (24 ...

31

Wilge River Quaternary CatchmentsB20F – Upper Wilge (west)B20G – Saalklapspruit (east)

Page 50: Appendix A6: Records of Public Information Meetings (24 ...

32

§ Stressed§ Considerably transformed and degraded§ Aquatic organism deaths in Loskop Dam and KNP (fish and crocodiles)§ Ecological Reserve§ Total 460 million m3/a (2000) (83 million m3/a for Upper Olifants)§ Water deficit§ 194 million m3/a (2000)§ Water use expected to increase, deficit to increase§ 242 – 280 million m3/a (2025), depending on economic growth and

development in catchment

Page 51: Appendix A6: Records of Public Information Meetings (24 ...

33

§ Quaternary catchments• B20F – Upper Wilge• B20G - Saalklapspuit

§ Wilge River catchment§ Upper Olifants River catchment§ Loskop Dam located after confluence of Wilge and main stem of Upper

Olifants§ International watercourse

§ B20F – Upper Wilge§ Present Ecological State = C§ Ecological Importance = C§ Sensitivity = C§ Recommended Ecological State = C

§ B20G – Saalklapspuit§ Present Ecological State = D§ Ecological Importance = C§ Sensitivity = C§ Recommended Ecological State = D

Page 52: Appendix A6: Records of Public Information Meetings (24 ...

34

Valleyhead

Hillslopeseepage wetlands

Footslope

Valley bottom wetland

Midslope

Pan

§ B20F – Upper Wilge§ Seepage wetlands heavily degraded = D and E class§ Riparian, floodplain and no-floodplain wetlands = B and C class

§ B20G – Saalklapspuit§ Seepage wetlands heavily degraded = D and E class§ Riparian, floodplain and no-floodplain wetlands = C class

Page 53: Appendix A6: Records of Public Information Meetings (24 ...

35

54 0

9 0 9 Kilometers

N

Mineral rights boundary

Coal reserve boundary.

PESB

C

D

LEGEND

540

9 0 9 Kilometers

N

Mineral rights boundary

Coal reserve boundary.

EISC

B

C

D

LEGEND

Page 54: Appendix A6: Records of Public Information Meetings (24 ...

36

§ Ecology and Biodiversity (including Natural Vegetation and Animal Life)Assessment.

§ Wetland Assessment.§ Soils Assessment.§ Air Quality Assessment.§ Traffic Impact Assessment.§ Noise Assessment.§ Vibrations and Blasting Specialist Assessment.§ Heritage Resources Assessment.§ Surface Water Assessment.§ Water Use License and Integrated Water and Waste Management Plan.§ Groundwater Assessment.§ Visual Assessment.§ Social Assessment.§ Economic Assessment.§ Agricultural and Land Use Potential Assessment.

Environmental Impact Assessment & Environmental Management ProgrammeWater Use License ApplicationProject Announcement – 11 & 12 May 2011

(Mari Wolmarans & Marline Medallie)

Page 55: Appendix A6: Records of Public Information Meetings (24 ...

37

§ Development Alternatives§ Option 1: Development of a New Road Directly East of the New Largo Colliery

• New road from the R545 ~2 km south of the Kendal-Balmoral intersection• runs south-eastwards and then southwards along the eastern border of New Largo Colliery• Meet with R545 near Wilge Village

§ Option 2a: Upgrading of Existing Road Network East of the New Largo Colliery• R104 from the R545 to the intersection with gravel road D432• D432 southwards to where it joins with a secondary gravel road• South-westwards until joining the R545 to the west of Phola Town

§ Option 2b: Upgrading of Existing Road Network East of the New Largo Colliery• Road running south from the Rondebult intersection on the N4 to the R104• R104 to where it then joins road D432• Southwards until it crosses the N12 with a bridge overpass (no current interchange with N12)

§ No-Go Development Option• The no-go development assumes that no road replacement gets approved but that the

demolition of the section of the R545 Provincial Road between the N4 and N12 proceeds

(Option 1: N ew Road)

Page 56: Appendix A6: Records of Public Information Meetings (24 ...

38

§ Demolition of R545§ Not a listed activity requiring an Environmental Impact Assessment in terms

of the National Environmental Management Act (No 107 of 1998)§ Impacts of demolition will be addressed in the EIA for New Largo Colliery as

a separate process.§ The project proponent for the New Largo Colliery is Anglo American through

its subsidiary Anglo American Inyosi Coal (AAIC).

§ Activities in GNR 544, GNR 545 and GNR 546 triggered by Option 1

§ Activity from GNR 546 are triggered by Option 2

§ Environmental Impact Assessment• Required in terms of the National Environmental Management Act (No 107 of 1998)

and the EIA regulations (Government Notice Regulation (GNR) 543 to 546,published 18 June 2010)

§ Water use license• Required in terms of Section 21 of the National Water Act (No 36 of 1998) for

watercourses and drainage lines along routes

§ Project Applicant• Mpumalanga Department of Public Works, Roads and Transport.

Page 57: Appendix A6: Records of Public Information Meetings (24 ...

39

§ Is the New Largo Colliery needed?

§ Do we need New Largo Colliery tosupply to Kusile Power Station?

§ Is the New Largo Collierydesirable?

Page 58: Appendix A6: Records of Public Information Meetings (24 ...

40

§ If the New Largo Colliery is developed as an open cast mine and asper plans presented by AAIC….

…what should happen with the land at the end of the life of the mine?

§ Water Resources§ Air Quality§ Noise, Blasting and Vibrations§ Biological Environment§ Technical and Design Considerations§ Rehabilitation§ Land and Agriculture§ Roads, Transport and Infrastructure§ Socio-economic Issues§ Prospecting and Mining Rights§ The EIA Process§ Land Claims

Page 59: Appendix A6: Records of Public Information Meetings (24 ...

41

• How will Anglo American supply water to the mine? Land owners would prefer itif water pipelines did not run through their properties.

• The effect of blasting and mining on boreholes should be investigated.• The impact of the mine on water quantity and quality must be determined.• What rights do landowners and business people have in the event of something

happening to their water supply?• The boreholes on certain properties may be deeper than the proposed mining

depth. It should be clarified whether boreholes will be affected by waterseepage out of the mine pit.

• Will the mine produce acid drainage and where will this decant?• The effect of blasting activities on borehole water must be investigated.• The amount of water needed for the proposed mine should be clarified.• The municipality, as the service provider, must be consulted in regard to the

mine’s water use requirements.• The cumulative impact of all the mines in the area on water quality should be

clarified.

Page 60: Appendix A6: Records of Public Information Meetings (24 ...

42

• Clarity should be provided on the treatment of polluted water.• What mitigation measures will be in place to supply water to land owners,

should blasting affect water supply to the area?• A number of dams and pans are found on the proposed site. It should be

clarified who would be responsible to purify the water and manage thewatercourses underneath the rehabilitated land.

• The impacts of changed water quality and quantity on surrounding businessessuch as fish farming, paint manufacturer, the brick making factory, and variousKendal operations.

• The effect on the health needs of the surrounding communities, and the needfor another clinic in the area to cope with the health needs of the community.

• The effect of air quality impactson neighbouring properties.• Dust may affect the cattle (their grazing, drinking water and subsequently their

fertility) thus also affecting milk production and quality.• The effect of dust on the local brick-makingactivities and what mitigation

measures would be put in place to prevent the staining of the bricks.• The impact of dust from the proposed coal mine on the proposed fish farming

and also on the paint manufacturingbusiness should be investigated.• On windy days dust can travel further than the proposed 500m buffer zone. The

management of this dust should be investigated.• The effect of dust on neighbouring properties must be investigated as well as

alternativesites for the mine operations.

Page 61: Appendix A6: Records of Public Information Meetings (24 ...

43

• The possibility of the value of the surrounding (nearby) houses may decreasedue to blasting activities.

• The indirect impacts to neighbouring properties of mining e.g. blasting andcracked houses and swimmingpools should be investigated.

• The influence of noise and air pollution on wild and domestic animals (includingfish) should be addressed.

• What will happen to the people who stay next to the proposed mine site?Houses may be affected by blasting. What assurance will be given that theirhomes will be looked after?

• What remedial measures will be put in place to mitigate the effects of blastingon houses?

• That the effect of blasting on nearby businesses such as the paint factory, andfish farming?

• If mining, particularly blasting, were to occur closer than 500m from the N4, theDepartment of Mineral Resources would require special exemption from theSouth African National Roads Agency and TRAC.

• The cumulative effect of a new mine and blasting activities on already crackedhouses in the nearby communities.

• The blasting methods that will be used should be clarified.• Blasting during school hours might cause disturbance to pupils.

Page 62: Appendix A6: Records of Public Information Meetings (24 ...

44

• The area already suffers from a severe disturbance of the natural biodiversity.• The impact on the habitat of scarce and endangered species occurring in the

area should be investigated.• An ecological study should be carried out.• The impact on wetlands should be investigated, and the protection of wetlands

and pans clarified.• The occurrence and protection of intact Highveld grassland within the mine

area.• A full wetland study should be conducted. The functions provided by the

wetland as well as biodiversityof the wetland in terms of vegetation surveys,invertebrate surveys, bird, mammal, fish and amphibiansurvey should bedocumented.

• Specialist studies should be conducted on the ecology of the area includingcomprehensive fauna and flora studies.

• A full survey should be done to determine species richness. The time of year toconduct surveys should depend on the activity pattern of the species. Thesurvey area should not be restricted to the proposed site of development, butshould include all habitat types over the entire property as well as adjacentareas.

• An ethically accepted plan for the eradication or removal of anyexotic/introduced species posing a threat to indigenous species should beincluded in the report.

Page 63: Appendix A6: Records of Public Information Meetings (24 ...

45

• Will the mine provide the power station with coal and when will implementationof this start?

• What will the life of mine be?• It should be clarified why mining would start two years before the power station

becomes operational and also whether the mine will stockpile coal for export.• The direction of mining should be clarified.• What is the time-line of the proposed project?• Will Anglo American be able to mine the amount of coal required by the power

station?• How will the current employees at the Kendall facilities be affected?• How deep will the mine will be?• Will the spoil piles be prone to burning? What about the spontaneous

combustionof waste coal?• Is the existence of a large coal field proven already in this case? It has

happened at other mine sites e.g. Majuba that less coal was found thanexpected.

• What will the total volume of coal to be excavated be?• Whether the mine will be a multiple pit operation?• It should be investigated whether the Vaal water piping does not cross the mine

area.• Will any of the coal produced be exported.• What is the reason why the coal at the Kendal Forest Holdings will not be

mined? Is it due to economic considerations or the disturbance of people?• Is this the only suitable site for mining?

Page 64: Appendix A6: Records of Public Information Meetings (24 ...

46

• How long after rehabilitationcan the land be used for agricultural purposesagain?

• Will a percentage of each tonne of coal be set aside for the rehabilitationcosts?• Who is responsible for enforcing the regulations regarding rehabilitation?• Consideration should be given to turning the mine into a tourist attraction such

as Gold Reef City when rehabilitationoptions are investigated.• Is vegetation the best way to stop stockpiles being blown away?• Concerns that compactionduring rehabilitationcan never be done as successful

as in nature and that the mine pits could fill up with water. The poor quality coalhas a high sulphur content and the overflow water containing heavy metalscould infiltrate potable water in the area.

• What will happen to the topsoil in the area, as the entire area appears as thoughit will be mined? Will the soil will be stored off the mining rights area / outsidethe boundary area?

• Should land owners continue with their normal farmingactivities for the timebeing as it is clear that mining will not start in the whole area at the same timeand the road re-alignment will also take some time to be completed?

• Will negotiations be entered into with land owners through a regulated process iftheir land needs to be acquired by Anglo American for the mine?

• The agricultural potential of the area must be investigated in full.• Livestock diseases may increase due to the mining activities especially the

effect on the water supply and the coal dust. It is possible that cows can sufferfrom lung disease.

• It appears that agricultural impacts were neglected in favour of social impactsand that previous studies have indicated the negative impact of coal mines onagriculture.

• Anglo American should keep farmers informed of developments as soon as theyhappen, as farmers have difficulty continuing with their activities and planningfor the future.

• The effect of mining on the neighbouring poultry farm must be investigated.

Page 65: Appendix A6: Records of Public Information Meetings (24 ...

47

• The sensitivity of Fairacres chicken farm’s highly automated operations tovibrations and dust must be considered.

• The potential for dust from mining operations to spread Newcastle disease tochicken farming operations should be considered.

• Can land owners who are in the process of selling their properties go aheadwith such transactions?

• It must be clarified which owners fall within the proposed mining area and whichland owners fall next to the area to ensure that land owners are clear on thefuture of their properties. The properties next to the mine area will also beimpacted.

• The roads are not in good condition and require upgrading.• The relocation of the R545 and the positioning of the relocated road is a

concern. Businesses may be affected by the placement of the relocated road,for example the paint manufacturingbusiness requires good roads whentransportingpaint to markets.

• The post office boxes for land owners on the western side of the mining areaare situated at Voltargo. The realignment of the R545 road will cut businessesand land owners off from the post office at Voltargo.

• Access to farms should be investigated should the R545 road be re-aligned.• Residents might be cut off from their businesses by the re-alignment of the

R545 road.• Children travelling to school along the R545 will be affected be the re-alignment.• That the relocation of the R545 may disrupt suppliers and distribution for the

farmingand business operations.• Will the coal be transported by road or conveyor belt?• What will be done to avoid accidents on the N12 caused by dust etc. from

mining?

Page 66: Appendix A6: Records of Public Information Meetings (24 ...

48

• TRAC would have to be consulted should the N4/R545 Interchange berelocated.

• How will mining affect the N12? Will mining take place underneath the N12 orhow far away will it be?

• Trucks, mostly from mining companies, are ruining the roads and localgovernment does not have the capacity to maintain the roads.

• Residents would like to be assured that they are not being deceived when AngloAmerican says they will use conveyor belts instead of trucks. Other mines in thearea had also undertaken not to use trucks in mining but had subsequently usedtrucks anyway.

• Will the mine have an impact on the Petronet pipeline?• Impacts could be experienced at the Transtel facility in the area such as the

disturbance of “line of sight” signal used for cellular phones if mininginfrastructureand spoil piles are too high (+ 25 m); impacts on thecommunications tower and pump station and the copper cable running betweenthem; and dust at the equipment centre could be a problem for sensitiveequipment.

• Will the Telkom towers be affected?• What will be the impact of the mine on dams and pipelines be, particularly in

terms of sensitive radio activity; highly flammable fluids and vibration topipelines?

Page 67: Appendix A6: Records of Public Information Meetings (24 ...

49

• The influx of people into the area due to the proposed mine development is aconcern.

• Crime in the area, and the increase of crime due to the influx of people andinformal settlements, is a concern.

• Where will employees from the mine be housed?• Elderly people came to the area to retire here to enjoy the peacefulness but now

the property values will be affected by the mine and power station.• A number of land owners in the area are in retirement and would find it difficult

to start somewhere else.• Should plans to expand businesses and developments be put on hold?• Mines in the past had not made any contribution to community facilities. Phola

residents would like a guarantee that Anglo American will contribute to thedevelopment of Phola.

• Will Anglo American offer training, capacity building and communitydevelopment? Skills to operate the larger equipment will not be readily availablein Phola but the people can receive training in order to do such skills in future.

• Local communities and businesses should benefit from the proposed project interms of employment and sub-contracting.

• The young farmers in the area will no longer produce food for their families.How will they be assisted to find alternative livelihoods?

• The number of jobs created during construction and operations is very limited.There are just as many farm workers that will be without work.

• What criteria will be used for labour recruitment?• A survey of skills must be undertaken and should include the residents of Phola

and Ogies. The community should be trained in the skills that will be required bythe mine and the power station.

• How will employment selection be conducted? How will small businesses becatered for? Will SMMEs have the opportunity to tender?

• How is the relocation of residents handled, and what monitoring approach willbe used to ensure that the people are relocated to a better place?

• If there is to be a relocation process, the mine must bear in mind that theEmalahleni Municipality is now facing the challenge of land shortage.

Page 68: Appendix A6: Records of Public Information Meetings (24 ...

50

• Many of the residents rent houses and not many own them. Should villages(e.g. Wilge) be relocated, who will be compensated, the owner or the tenant?

• How will the residents of Wilge be affected if they stay next to the mine?• What will happen to the people living on the farms with regard to relocation and

resettlement?• Farm workers will lose jobs.• How will the communities and farm workers be compensated?• Concern regarding familygraves in the area.• Family members must be consulted if the graves are to be relocated.• The effect of mining on property values in the area should be investigated.

• Does Anglo American have underground mining rights and prospecting rights?• The coal rights on this farm were already sold in the 1800s.• A possible conflict with the existing sand mine in the area should be clarified

Page 69: Appendix A6: Records of Public Information Meetings (24 ...

51

• Objection to the assessment of the impact of the proposed New Largo Collieryand proposed Eskom Power station in isolation of each other. These activitiesshould be investigated before or simultaneously with these assessments inrespect of the opencast mining activity and Eskom power station. TheEnvironmental Management Plan must address the construction andoperational phases as a unit to ensure that fragmentationdoes not take place.

• Anglo American should appoint an Environmental Control Officer (ECO) for themonitoringof the constructionand operational phases of the proposeddevelopment.

• An environmental management system should be put in place and shouldinclude non-conformance reporting and corrective action procedures. Incidentsand complaintsshould be reported in accordance with the proceduresdocumented in an incident management plan.

• Pre-constructionmanagement guidelines should be developed for the designphase and the constructionsite.

• The environmental management plan must be send to all IAPs for comment aswell as the environmental authorisation record of decision.

• What happens if the study is undertaken and then indicates another direction?People’s expectations will have been raised and there may even be individualswho have sold their businesses or farms in view of the mining planned for thearea.

• Why are two EIA processes being followed for Eskom’s Kusile Power Stationand Anglo American’s mine? Why do Eskom and Anglo American not undertakea joint EIA?

• What experience does the Environmental Assessment Practitioner have inmanagingEIAs for opencast coal mining activities?

• If the power station is approved on the basis of the demand for more power,there is no way that the mine will be stopped as it will have to supply the coal.

• What is the review / comment period?• Stakeholders prefer focus group meetings as we can all voice our needs.• Traditional leaders should participate in the process.• On-going communication is important. How will this be achieved? Will a project

office be established in the area?

Page 70: Appendix A6: Records of Public Information Meetings (24 ...

52

• Major impacts should be considered in conjunction with existing impactsofmining in the area and these should be regarded as a key concern.

• Present and potential future cumulativeand synergistic effects should be takeninto account.

• Maps indicating areas of sensitivity, areas already disturbed as well as the sizeof such area, proposed development and size, land-use on surroundingproperties as well as the location of important species as well as roosting andhibernation sites, e.g. caves of ecological importance in relation to the proposeddevelopment should be supplied.

• Specialist studies are required to address the impact of the activity withreference to wind directions on neighbouring farms.

• Was any specialist study conducted to determine if there are any existing landclaims on the site?

Page 71: Appendix A6: Records of Public Information Meetings (24 ...

53

• Review and update baseline studies completed previously and conductseasonal field surveys in the broader study area.

• Determine terrestrial and aquatic habitat status and importance.• Determine terrestrial and aquatic species and habitat diversity.• Obtain Red Data information.• Compileecological sensitivity analysis.• Identify areas with high biodiversity sensitivity.• Conduct a comparativeevaluation of the development alternatives.• Define the impact on terrestrial vegetation, animal life and aquatic habitats.• Define impactson ecology and biodiversity.• Define project zone of influence.• Make recommendations for the management of biodiversity, sensitive sites, and

rare or valuable species and communities.• Propose measures for mitigationof impacts.

Page 72: Appendix A6: Records of Public Information Meetings (24 ...

54

• Update and revise baseline studies completed previously.• Define the location (delineation) of the wetlands and riparian zones in affected

areas.• Classify and define the conservation status and functional importance of

wetlands on a local and regional scale.• Confirm classification and status in terms of provincial conservation plans.• Report on wetland ecological and biodiversity functionality.• Conduct a comparativeevaluation of the development alternatives.• Define project zone of influence.• Make recommendations for the management and protection of wetlands.• Propose measures for mitigationof affected wetlands.• Provide input into the rehabilitationplan for New Largo Colliery.

• Characterisationand mapping of soils, focusing specifically on the delineation ofwetlands, areas sensitive to soil disturbance, erosion and contamination, andsoils for use in rehabilitationstrategies.

• Conduct a comparativeevaluation of the development alternatives.• Define the potential impacts on soils, including potential for soil sterilisation, for

loss of agricultural potential, potential for increased soil erosion.• Establisha soil balance system for use during operational phase to ensure that

sufficient soil is available for the rehabilitationprogramme.• Make recommendations for the management of sensitive areas, steep slopes

and soil contamination risks.• Propose measures for mitigationof impacts and prevention of soil

contamination.• Provide input into the rehabilitationplan for New Largo Colliery.

Page 73: Appendix A6: Records of Public Information Meetings (24 ...

55

• Review and update baseline studies completed previously and conductseasonal field surveys in the broader study area.

• Determine terrestrial and aquatic habitat status and importance.• Determine terrestrial and aquatic species and habitat diversity.• Obtain Red Data information.• Compileecological sensitivity analysis.• Identify areas with high biodiversity sensitivity.• Conduct a comparativeevaluation of the development alternatives.• Define the impact on terrestrial vegetation, animal life and aquatic habitats.• Define impactson ecology and biodiversity.• Define project zone of influence.• Make recommendations for the management of biodiversity, sensitive sites, and

rare or valuable species and communities.• Propose measures for mitigationof impacts.

• Update and revise baseline studies completed previously.• Define the location (delineation) of the wetlands and riparian zones in affected

areas.• Classify and define the conservation status and functional importance of

wetlands on a local and regional scale.• Confirm classification and status in terms of provincial conservation plans.• Report on wetland ecological and biodiversity functionality.• Conduct a comparativeevaluation of the development alternatives.• Define project zone of influence.• Make recommendations for the management and protection of wetlands.• Propose measures for mitigationof affected wetlands.• Provide input into the rehabilitationplan for New Largo Colliery.

Page 74: Appendix A6: Records of Public Information Meetings (24 ...

56

• Characterisationand mapping of soils, focusing specifically on the delineation ofwetlands, areas sensitive to soil disturbance, erosion and contamination, andsoils for use in rehabilitationstrategies.

• Conduct a comparativeevaluation of the development alternatives.• Define the potential impacts on soils, including potential for soil sterilisation, for

loss of agricultural potential, potential for increased soil erosion.• Establisha soil balance system for use during operational phase to ensure that

sufficient soil is available for the rehabilitationprogramme.• Make recommendations for the management of sensitive areas, steep slopes

and soil contamination risks.• Propose measures for mitigationof impacts and prevention of soil

contamination.• Provide input into the rehabilitationplan for New Largo Colliery.

• Update baseline air quality characterisation for the area.• Monitor baseline air quality.• Compilean emissions inventory.• Describe legal requirements and standards.• Perform dispersion modelling; incremental for Phase 1 and Phase 2 as well as

cumulative impacts.• Predict dust fallout and fine particulate (PM10) concentrations.• Define dust nuisance (dust fallout) and potential health impact areas.• Propose dust control measures for construction and operation, particularly for

areas within the air quality buffer and management zones.• Estimate emission control efficiencies of proposed dust control on roads and at

materialshandling facilities.• Conduct a comparativeevaluation of the development alternatives.• Define air quality buffer and management zones (minimum distances to

sensitive receptors).• Define project zone of influence.• Predict compliancewith air quality standards (local and international).

Page 75: Appendix A6: Records of Public Information Meetings (24 ...

57

• Collect available traffic information.• Contract traffic counts on local road network.• Describe existing transportation routes and traffic volumes and users.• Define impactsassociated with the transport of people, equipment, materials

and products on travel times, road safety, and road conditions.• Assess risks of traffic disruptions associated with construction taking place in

close proximity to major roads such as the N4 and N12 highways.• Define project zone of influence.• Recommendations for construction traffic management and prevention of traffic

disruptions.

• Identify sensitive receptors.• Describe legal requirements and standards.• Monitor baseline noise and vibration levels on the project site and at key

sensitive receptors around the project location e.g. communities, neighbouringfarmers, roads, etc.

• Define existing ambient noise levels in the area.• Estimate noise output and emissions during construction and operation.• Define impactson receptors during construction and operation.• Define noise buffer and management zones (minimum distances to sensitive

receptors) for specific project components such as the coal processing plant.• Define project zone of influence.• Predict compliancewith air noise standards.• Make recommendations for mitigationof noise impacts, particularly for areas

within the air quality buffer and management zones.

Page 76: Appendix A6: Records of Public Information Meetings (24 ...

58

• Describe legal requirements.• Assess impacts of blasting and vibration impacts during construction and

operation.• Define project zone of influence.• Define minimum distances to structures and linear infrastructuresensitive to

vibrations.• Identify the most likely paths for blasting related vibrations and potential blasting

shrapnel and if these could impact on resident fauna (outside the mining area),passing traffic and neighbours.

• Predict compliancewith legal requirements.

• Update Phase 1 heritage field survey (to include areas not surveyed previously).• Identify and quantify visible graves and other heritage sites and artefacts and

provide locations for mapping.• Conduct a comparativeevaluation of the development alternatives.• Define the impact on heritage resources.• Produce a heritage assessment report for submission to the South African

Heritage Resource Agency (SAHRA) and obtain comments.• Make recommendations for mitigationof impacts.

Page 77: Appendix A6: Records of Public Information Meetings (24 ...

59

• Setup water quality monitoring points.• Conduct seasonal water quality sampling in the study area.• Map the locations of existing dams, reservoirs, natural springs and wetlands (as

applicable).• Define the 1:50 and 1:100 flood lines.• Define baseline conditions.• Describe legal requirements and standards.• Conduct a comparativeevaluation of the development alternatives.• Define existing water uses and users in the area.• Review the water requirements of the total catchment water balance including

all other users of the system and their demands on the available water.• Characterise the surface water quality from all monitoringpoints ensuring that

the full range of parameters are analysed as appropriate for each monitoringpoint.

• Assess impacts of all project components.

• Assess risks of surface water pollution associated with the construction andoperation of the proposed mine and associated activities.

• Define project zone of influence.• Make recommendations for the management and protection of surface water

resources.

Page 78: Appendix A6: Records of Public Information Meetings (24 ...

60

• Identify water uses for registration and licensing in terms of Section 21 of theNational Water Act (No 36 of 1998).

• Complete water use registration and licensing forms.• Develop a water balance.• Develop a salt / metal balance.• Predict compliancewith legal requirements and standards.• Produce an Integrated Water and WasteManagement Plan (IWWMP).• Compileand submit an Integrated Water Use Licence Application (IWULA) to

the DWA.

• Interpretationof data from all existing boreholes to obtain additionalgroundwater information.

• Setup groundwater monitoringprogramme.• Conduct water quality sampling in the study area.• Describe legal requirements and standards.• Characterise the groundwater quality from all monitoring points.• Describe baseline groundwater characteristics.• Identify all groundwater regimes and aquifers that could be affected by the

proposed development.• Quantify the groundwater levels, base flow requirements and recharge.• Define existing water users in the area.• Undertake hydro-census of groundwater users and receptors within an

appropriate radius of the project boundaries.• Characterise the geochemistry of the coal seams and overburden material to be

disturbed.• Determine the Acid Rock Drainage (ARD) potential.

Page 79: Appendix A6: Records of Public Information Meetings (24 ...

61

• Assess risks of groundwater pollution associated with the construction andoperation of the proposed mine and associated activities.

• Provide groundwater input into water balance.• Provide groundwater input into salt / metal balance.• Evaluate geotechnical characteristics.• Consider impacts of different residue / waste / discard management and

disposal options.• Predict long-term impacts.• Predict compliancewith legal requirements and standards.• Conduct a comparativeevaluation of the development alternatives.• Make recommendations for the management and protection of groundwater

resources.

• Describe the characteristics of the existing landscapes.• Analyse views from sensitive receptors e.g. neighbours, communities, tourist

routes, etc.• Define and describe the nature and scale of the proposed project.• Describe the environmental setting (visual resource).• Define landscape character and quality and sense of place (genius loci) of the

study area.• Simulate the visual intrusion of the different project components and associated

infrastructure from viewing points, using photographic simulation techniques.• Describe and assess the visual impacts. The visual impact will be described as

the change to the existing visual environment (caused by the physical presenceof the proposed project) and the extent to which that change compromises(negative impact) the visual quality and sense of place of the study area.

• Define project zone of influence.• Recommend and evaluate management measures to mitigate the negative

visual impacts.

Page 80: Appendix A6: Records of Public Information Meetings (24 ...

62

• Update existing social baseline documentation.• Conduct a social characterisationof the study area, including geographic and

historical context, demographics, economy and labour force, administrativestructure, health facilities and issues, educational facilities and issues, utilities,infrastructureand services, importanceof the natural environment to thecommunities, communityneeds and priority concerns.

• Ground truth existing information and targeted consultationwith specific interestgroups as and when required to determine the direct and indirect socialconsequences of the project.

• Define the impact during constructionand operation.• Define project zone of influence.• Define impactsof closure and sustainabilityof the communityafter mining.• Propose management and mitigationmeasures to enhance positive social

benefits and reduce negative impacts.• Identify potential opportunities for implementing / assisting with the

implementation of socio-economicdevelopment projects.• Recommendations for managing relationships with communities and interest

groups

• Develop a baseline profile of the study area.• Determine economic and spatial development trends.• Define economic impactsand implications.• Define project zone of influence.• Conduct a comparativeevaluation of the development alternatives.• Make recommendations for mitigatingpotential economic impacts.

Page 81: Appendix A6: Records of Public Information Meetings (24 ...

63

• Define the existing (pre-mining) agricultural and land use potential.• Conduct a comparativeevaluation of the development alternatives.• Define the potential impacts on agricultureand other land uses.• Define project zone of influence.• Propose measures for mitigationof impacts.• Determine impacts on agricultureand other potential land uses.

Page 82: Appendix A6: Records of Public Information Meetings (24 ...

New Largo Issues and Responses Report - Summary of main points of meetings on 11 and 12 May 2011

at Ons Huisie near Kendal

1 AAIC mentioned in its presentation on

Community Development that R40 million

has been spent. How much has been spent

develop the community of Phola Location?

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

All this money was spent to uplift the Phola

community, because it was used to fix and

upgrade the Phola Sewage Plant that was

leaking raw sewage into the street, creating

a health hazard that could have caused an

epidemic. Local labour was also used in

upgrading the sewage plant.

2 What does AAIC perceive to be local when

using local labour?

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Regarding this project it will be the nearest

community and the local municipality, which

is Phola/Ogies. Anglo American usually

views everybody within 50km of a

development as being a local.

3 What does CSI stand for? Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Corporate Social Investment.

4 There is still a little sewage running into the

nearby rivers in the vicinity of Phola

Mr Werner

Koekemoer,

Kendal

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Noted.

Page 83: Appendix A6: Records of Public Information Meetings (24 ...

5 Will the Kendal small holdings be affected

by this proposed new mine?

Mr Werner

Koekemoer,

Kendal

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

No, the proposed mine will not affect the

small holdings.

6 We are deeply disturbed about our

ancestral graves on the Farm Hönigkrantz

that lies within the area to mined.

We also have land claims against this farm.

Mr Dan Tlou,

Bathabile CPA

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

We are aware of the graves. All graves in

the proposed mining area will be identified.

This will be investigated by a Heritage

Resources Assessment that will provide

recommendations on what need to be done

before any mining activities may

commence.

7 What will be done to control dust? Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

An Air Quality Assessment will be done

during the next phase of this process. It will

investigate everything that can generate

dust at a mine. Methods to suppress dust

like sweeping roads, using water or water

mixed with chemicals, enclosed tips, etc will

also be given.

8 What will happen if all these

recommendations are in place and there is

still a dust problem?

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

That means that we at AAIC are not doing

our job properly. We will, however, strictly

adhere to the dust suppression

recommendations.

9 Equally important is land usage after mining

operations have been completed. What will

be done to rehabilitate the mine?

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

Public meeting

on 11 May

2011 at Ons

Huisie to

An Agricultural and Land Use Potential

Assessment will be done to look at the best

possible re-use of the mine.

Page 84: Appendix A6: Records of Public Information Meetings (24 ...

1021

Mr Ben Greyling,

Witbank

discuss DSR.

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

At tis stage we cannot say if it would be

possible to use this land again for

agriculture with the same high yield as

before.

It has always been a problem to change an

open cast coal mine back to agricultural

use, because it is not possible to have

dams, because water quality decrease to

the what is beneath the top soil.

10 How much food will be lost over the 50 plus

year lifespan of the mine from the area

taken up by the footprint of the mine? This

area is very important for food production

due to the high yield of the land.

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Mr Ben Greyling,

Witbank

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

An Agricultural and Land Use Potential

Assessment will be done to investigate this.

11 Will the quality and quantity of our

boreholes and water supply – at the

smallholdings be affected by the proposed

mine?

Mr Werner

Koekemoer,

Kendal

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Neighbours are affected by legislation and

cannot be poorer off due to the actions of a

new development. Various studies such as

a Surface Water Assessment, a Water Use

License and Integrated Water and Waste

Management Plan and a Groundwater

Assessment will be done during the next

phase of this study.

Page 85: Appendix A6: Records of Public Information Meetings (24 ...

12 What is meant by a closed water system? Facilitator Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

This means no water, untreated or treated,

leaves the premises where it has been

used. It is also not allowed to decant into

the environment. Water is treated and re-

used.

13 Where will AAIC source its water? Facilitator Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

There are various old underground mines

that have filled with water during the years.

This water will be used.

14 Will the water use of AAIC affect its

neighbours?

Facilitator Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

The specialist studies will look into this.

Studies done for a previous EIA in 2007 will

also be used to determine the current water

use.

15 What will happen if my borehole is affected

by the proposed New Largo mine?

Mr John Strick,

Roodepoortjie, PO

Box 2778,

Bronkhorstspruit,

1020.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

All boreholes on neighbouring properties will

be registered and plotted during the next

phase of this study.

16 The mine must not pump any untreated

water into the surrounding water bodies.

Mr Louw Boshoff,

PO Box 2169,

Witbank, 1035.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Noted. This will not happen. Only water

treated to a potable standard will be

pumped into the surrounding rivers.

17 What will happen to any excess water? Mr Harold Frylinck,

Landowner, PO

Public meeting

on 11 May

Any excess water will only happen later in

the lifespan of the mine. Should there be

Page 86: Appendix A6: Records of Public Information Meetings (24 ...

Box 105, Balmoral,

1037

2011 at Ons

Huisie to

discuss DSR.

any excess water then it will be pumped into

the Saalboom River and Zaalklap Spruit. It

will only be treated water.

18 There is an aquifer east of the proposed

mine towards Witbank. Will this be affected

by the proposed mine?

Mr Harold Frylinck,

Landowner, PO

Box 105, Balmoral,

1037

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

This will be investigated during the next

phase when various studies such as a

Surface Water Assessment, a Water Use

License and Integrated Water and Waste

Management Plan, a Wetland Assessment

and a Groundwater Assessment will be

done.

19 Water is a basic need. Should it run dry, will

the neighbours of the mine be relocated?

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

It is still far too early in the process to look

at such a scenario, but it could probably

been seen as an option, although it is the

most extreme option.

How do I prove that AAIC caused my

borehole to dry up?

Mr Albert Hertzog,

Farm Zaalklap.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

A thorough hydro census will be done

during the next stage of this process and

monitoring points have already been set up

on surrounding properties to measure the

baseline of all boreholes in the vicinity.

If neighbours of the proposed mine do not

think that the hydro census is thorough,

then they must complain as soon as

possible.

20 I have a monitoring point on my farm and

have never seen someone taking samples

Mr John Strick,

Roodepoortjie, PO

Box 2778,

Public meeting

on 11 May

2011 at Ons

The monitoring only happens twice a year

or even once a year.

Page 87: Appendix A6: Records of Public Information Meetings (24 ...

of the water. Bronkhorstspruit,

1020.

Huisie to

discuss DSR.

21 Can the hydro census details such as which

boreholes are being monitored, be made

available to all stakeholders?

Facilitator Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Yes, this will be done

22 Monitoring should also be done on

neighbouring farms that do not yet have

such points on them.

Teresa Steele,

AAIC

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Noted.

23 Monitoring is currently being done, but I will

not be able to judge from which side

potential pollution will come. The monitoring

points should also be placed at points two

farms away from the proposed mine. The

monitoring ring around the proposed mine

should, in other words, be made wider.

Mr Albert Hertzog,

Farm Zaalklap.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

A list of all boreholes currently being

monitored will be sent to all stakeholders.

Neighbours can then request to place

specific boreholes on the monitoring list.

24 When will blasting being done? Mr Louw Boshoff,

PO Box 2169,

Witbank, 1035.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Blasting will only happen between 08:00

and 17:00. It will probably be done around

12:00 daily when the ambient noise levels

are at its highest. It will never happen at

night.

Neighbouring houses will also be inspected

for cracks before the mine opens to assist

Page 88: Appendix A6: Records of Public Information Meetings (24 ...

with processing any claims due to blasting.

25 Will the explosives magazine be near a river

and what will happen should it explode?

Mr Carel Frylinck,

Landowner, PO

Box 105, Balmoral,

1037

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

The location must still be approved during

the next phase of the study.

26 What will the impact on the blasts be on the

graves in the area?

Mr Simon

Mahlangu,

Bathabile CPA, PO

Box 532, Ekangala

1021

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

A Vibrations and Blasting Specialist

Assessment will be done during the phase

of this study.

27 How do we know the water monitoring

results are correct? Can we verify the

results by using an independent laboratory?

The best monitor for a farmer is his cattle,

because currently our cattle will not drink

from the Zaalklap Spruit, because it is too

polluted.

Mr Basie Hertzog,

PO Box 52,

Balmoral, 1037.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

The Environmental Assessment Practitioner

is totally independent and bound only by

legislation. The water studies are being

done by Jones & Wagener and Jasper

Muller Associates who are using an

independent laboratory of good standing to

analyse the water samples.

Stakeholders are, however, more than

welcome to use their own independent

laboratories to verify the results.

28 The assessment of the water should also

include all aquatic organisms.

Mr Basie Hertzog,

PO Box 52,

Balmoral, 1037.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

This will be done during the next stage of

this study.

Page 89: Appendix A6: Records of Public Information Meetings (24 ...

29 Who decides the category of classification

of a specific water resource? Some of the

water resources in this region have been

given a Category E. We are afraid that this

water resource will be kept that low so that

mining may take place in this area. Who

takes an ethical decision regarding the

specific category of a water resource?

Unfortunately all these decisions are being

taken by Government.

Mr Louw Boshoff,

PO Box 2169,

Witbank, 1035.

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Noted.

30 There are no business representatives here

at this meeting. Why have they not been

invited?

Mr Johan

Duvenhage, PO

Box 330, Kendal,

2225

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

There is another meeting tomorrow morning

at this same venue and maybe these

representatives would attend that meeting.

Over a 1000 people have been invited to

these meetings.

31 Can we get all the details of the people here

tonight?

Mr Johan

Duvenhage, PO

Box 330, Kendal,

2225

Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Rather contact the Public Participation

Office if you need to contact all the people

for the sake of everybody’s privacy.

32 Will stakeholders be prepared to travel to

Witbank for a public meeting/

Facilitator Public meeting

on 11 May

2011 at Ons

Huisie to

discuss DSR.

Most people at the meeting said they would

prefer the school halls in Ogies or Balmoral.

33 We are surrounded by the proposed

development. We have done a due

diligence on our water resources such as a

Mr Paul Venter,

Malachite Mining

Public meeting

on 12 May

2011 at Ons

This will be investigated during the next

phase when various studies such as a

Surface Water Assessment, a Water Use

Page 90: Appendix A6: Records of Public Information Meetings (24 ...

dam and a spring. We are seriously

concerned about our water. A thorough

hydrological study also needs to be done.

Services. Huisie to

discuss DSR.

License and Integrated Water and Waste

Management Plan, a Wetland Assessment

and a Groundwater Assessment will be

done.

34 We need clarity on the EIA regarding the

deviation of the R545, because this could

have a negative impact on our transport

costs.

Mr Paul Venter,

Malachite Mining

Services.

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

This will be investigated during the EIA of

the new road. You will all be invited to

another meeting to discuss the impacts of

the proposed new road.

35 Is there a possibility that our water

resources can dry up?

Mr Paul Venter,

Malachite Mining

Services.

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

This will be investigated during the next

phase when various studies such as a

Surface Water Assessment, a Water Use

License and Integrated Water and Waste

Management Plan, a Wetland Assessment

and a Groundwater Assessment will be

done.

There is, however, a risk that water

resources can run dry, but studies during

the specialist phase will investigate all risks.

36 Farmers in the area are extremely worried

about the quality of their water. This is seen

as the biggest threat.

Mr Ben Greyling,

Witbank

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

Water quality monitoring has already

started. This includes boreholes and surface

water monitoring. Mitigatory measures to

counter any problems will also be given.

This monitoring has already started in 2007

when the original EIA started and was

restarted last year for the current process.

Page 91: Appendix A6: Records of Public Information Meetings (24 ...

37 Not untreated water must be discarded into

our regional streams and rivers.

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

Only water of a potable standard will be

discharged into the Saalboom River and

Zaalklap Spruit.

This will only happen much later during the

lifespan of the mine when the capacity of

our water treatment plant has been

increased. In the beginning a portable water

treatment plant will be used, due to the

small quantity of water that must be treated.

A permanent water treatment plant will be

built at a later stage that will have the

capacity to provide excess water that could

be supplied to neighbouring communities.

38 A water treatment plant is needed from the

very first day.

Mr Sunil

Mungaroo,

Umcebo Mining

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

Water will be treated from the very first day.

In the beginning a portable water treatment

plant will be used due to the low volumes of

water needing treatment. When the quantity

of water increase to a specific level, a

permanent plant will be constructed.

39 Could other mining companies make use of

this water treatment plant?

Mr Sunil

Mungaroo,

Umcebo Mining

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

This can be discussed with AAIC us at a

later stage.

40 Some of these old mines were used to store

bunker oil many years ago. Will your

Mr Robbie van

Bulderen, Transnet

Public meeting

on 12 May

2011 at Ons

AAIC is aware of the bunker oil. Pockets of

the oil are still down in some of the mines.

This has been include into our calculations

Page 92: Appendix A6: Records of Public Information Meetings (24 ...

treatment plant be able to handle this? Pipelines Huisie to

discuss DSR.

and the specifications of the water treatment

plant will take this into consideration.

41 What will happen if this oil has leaked into

the coal reserves?

Mr Robbie van

Bulderen, Transnet

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

AAIC is aware of this problem and will take

it into consideration.

42 How many people will eventually work on

the mine?

Mr Paul Venter,

Malachite Mining

Services.

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

It will be around 700 people.

43 There has been a request to form a Water

Focus Group to have further discussions

regarding water issues.

Ms Teresa Steele Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

All stakeholders will be invited to a special

meeting to discuss water in the near future.

44 What will occur during the pre-blasting

stage?

Mr Sunil

Mungaroo,

Umcebo Mining

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

A Vibrations and Blasting Specialist

Assessment will be only done during the

next phase of this study.

45 The Environmental Management Plan must

discuss blasting and the relevant

precautions in great detail.

Mr Sunil

Mungaroo,

Umcebo Mining

Public meeting

on 12 May

2011 at Ons

Huisie to

Noted.

Page 93: Appendix A6: Records of Public Information Meetings (24 ...

discuss DSR.

46 What three options do you have for the new

road to replace the R545?

Mr Ben Greyling,

Witbank

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

A map with the three alternatives was

discussed at the meeting. All stakeholders

will be invited to a dedicated meeting to

discuss the EIA for the proposed new road.

47 Are the records of the 2007 EIA still

available? Is it being used for this study. We

spent many hours with various scientists

during that process and it will be a loss if

none of that information is used in this

study.

Mr John Byrne,

Kendal Poultry

Farm, PO Box

69386 Bryanston,

2021

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

The data of the 2007 is available to the

current EIA team and will definitely be used

during this study. New studies will, however,

be done again, because almost five years

have passed since the previous meeting.

48 What studies are currently being

undertaken?

Mr John Byrne,

Kendal Poultry

Farm, PO Box

69386 Bryanston,

2021

Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

There are three EIAs:

1. EIA for the proposed New Largo

Colliery;

2. EIA for a coal conveyor belt; and

3. EIA for the new road to replace the

R545.

49 The names of stakeholders interested in

participating in a Water Focus Group were

taken down.

Facilitator Public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

An invitation to attend a meeting of the

Water Focus Group will be sent out to ALL

stakeholders on the database, because no

names of stakeholders interested in such a

meeting were taken at the meeting on 11

May 2011.

Page 94: Appendix A6: Records of Public Information Meetings (24 ...

50 Malachite Mining Services Pty Ltd

purchased Portion 6 of Klipfontein 566 JR

with an approved RoD from Government to

was and screen coal on site. The company

is operating a washing and screening plant

on the property.

Malachite Mining did and in-depth

investigation as to the water resources

before we purchased the property The

natural water resources on the property are

sufficient to supply the coal washing and

screening plant with clean unpolluted water.

Malachite Mining’s concern is that any

adjacent mining activities might negatively

influence the water supply to our property

since the water sources are all natural

springs.

The consultants must take these factors into

account when hydrological studies re being

done in the area, to prevent adjacent mining

activities that will negatively

influence/pollute or obstruct the natural flow

of underground water to Malachite Mining’s

property.

Clean adequate water is cardinal to

Malachite Mining’s coal washing and

screening plant on Klipfontein 566 JR.

Mr L Letcher,

Malachite Mining

Services, PO Box

2150, Bedfordview,

2008

Hand delivered

document at

public meeting

on 12 May

2011 at Ons

Huisie to

discuss DSR.

Noted.

Page 95: Appendix A6: Records of Public Information Meetings (24 ...

Malachite Mining would like to inform the

service providers managing the applicable

systems and procedures on behalf of Anglo

Coal that we are concerned regarding the

possible re-routing of the current access

roads to our property. We are not sure how

these diversions of existing roads will

influence the future costing of the

transportation of coal from our suppliers or

the distribution of washed products to our

clients.

The current road infrastructure must be

discussed at some point in the future to

enable Malachite Mining Services to make

informed decisions.