APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at...

60
APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY

Transcript of APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at...

Page 1: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

APPENDIX 20

CONSTRUCTION AND OPERATIONS NOISE STUDY

Page 2: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Crossroads Ventures, LLC Mount Temper, New York

March 2011

Noise Assessment Modified Belleayre Resort at Catskill Park

REPORT

Page 3: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

REPORT

360° Engineering and Project Delivery Solutions

Modified Belleayre Resort at Catskill Park Noise Assessment

Crossroads Ventures, LLC Mount Temper, New York

MARK A. DISTLER Vice President

13972│42106

SCOTT C. MANCHESTER Project Manager

Page 4: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

i | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

TABLE OF CONTENTS

List of Tables ............................................................................................................................................................................ ii List of Figures ........................................................................................................................................................................... ii List of Enclosures .................................................................................................................................................................... ii

Executive Summary .............................................................................................................................................................................. iii 1. Introduction and Project Review ................................................................................................................................................ 1 2. Noise Receptors and Existing Sound Levels ........................................................................................................................... 3 3. Noise Assessment Guidelines ........................................................................................................................................................ 4

3.1 Project Construction ................................................................................................................................................................... 4 3.2 Project Operation ......................................................................................................................................................................... 5

4. Construction Noise ............................................................................................................................................................................ 6 4.1 Noise Prediction Methodology and Assumptions .......................................................................................................... 6 4.2 Noise Sources and Sound Levels ........................................................................................................................................... 6

4.2.1 Off-site Construction Traffic ............................................................................................................................................ 6 4.2.2 Access Road Construction ................................................................................................................................................ 7 4.2.3 Golf Course Construction .................................................................................................................................................. 9 4.2.4 Buildings Construction and Renovation ..................................................................................................................... 9

4.3 Construction Noise Impact Assessment and Mitigation ........................................................................................... 10 4.3.1 Access Roads ....................................................................................................................................................................... 10 4.3.2 Highmount Golf Club ........................................................................................................................................................ 10 4.3.3 Front-9 Village and Front-9 Village Clubhouse .................................................................................................... 11 4.3.4 Golf Maintenance Facility .............................................................................................................................................. 11 4.3.5 Highmount Hotel and Highmount Lodge ................................................................................................................ 11 4.3.6 Rock Crushing at Highmount. ...................................................................................................................................... 12 4.3.7 Highmount Detached Lodging Units. ........................................................................................................................ 12

4.4 Impact and Tonal Noise .......................................................................................................................................................... 12 4.5 Blasting Noise ............................................................................................................................................................................. 12

5. Operations Noise ............................................................................................................................................................................. 13 5.1 Noise Prediction Methodology and Assumptions ....................................................................................................... 13 5.2 Noise Sources and Sound Levels ....................................................................................................................................... 13

5.2.1 On-site Traffic Sources .................................................................................................................................................... 13 5.2.2 Stationary Sources ............................................................................................................................................................ 14 5.2.3 Golf Course (Quasi Mobile) Sources .......................................................................................................................... 14

5.3 Operational Noise Impact Assessment and Mitigation ............................................................................................ 15 5.3.1 Nighttime Sound Levels – Continuous Project Operations ............................................................................. 15 5.3.2 Nighttime Sound Levels – Continuous and Non-continuous Project Operations .................................. 16 5.3.3 Daytime Sound Levels ..................................................................................................................................................... 16

5.4 Impact and Tonal Noise ......................................................................................................................................................... 16 6. References .......................................................................................................................................................................................... 17

Page 5: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

ii | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

LIST OF TABLES

2-1 Ambient Sound Levels Results 4-1 Off-site Construction Traffic – Predicted Sound Levels 4-2 Access Road Construction – Predicted Sound Levels 4-3 Golf Course Construction – Predicted Sound Levels 4-4 Construction Sound Levels 4-5 Building Construction and Upgrade Construction Sound Levels 4-6 Project Construction Noise Assessment and Mitigation 5-1 Project Operation – Sound Sources and Reference Sound Levels 5-2 Project Operation Noise Assessment and Mitigation – Nighttime; Continuous Sources 5-3 Project Operation Noise Assessment and Mitigation – Nighttime; Continuous and Non-continuous

Sources 5-4 Project Operation Noise Assessment and Mitigation – Daytime

LIST OF FIGURES

2-1 Noise Survey and Receptor Locations

LIST OF ENCLOSURES

1 Calibration Certificates, Field forms and Data Summary Printouts 2 Construction Noise Barrier Calculation Diagrams 3 CadnaA Graphical Output - Decibel Contours

Page 6: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

iii | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

EXECUTIVE SUMMARY

A noise assessment was performed on behalf of Crossroads Ventures by O'Brien & Gere Engineers, Inc. for the proposed Modified Belleayre Resort at Catskill Park project (Project) in the Towns of Shandaken and Middletown NY. The purpose of this study is to evaluate potential noise impacts of major Project noise sources from construction and operation, and determine mitigative controls. This report was prepared pursuant to requirements specified the Agreement in Principle (AIP) and in Part B of the Final Scoping Document (NYSDEC, 2008), and supplements the original Project noise assessment conducted for the Project DEIS (ENSR, 2002).

It is important to note that sound levels estimated in this assessment are conservatively based. Construction noise impacts were evaluated at the work areas nearest to the receptor, which represents a worst-case condition. Further, estimates used sound levels of typical equipment that maybe higher that sound from lower-noise equipment options ultimately selected for the Project. Since Project sound levels from actual Project construction and operation may be lower that estimated herein, reduced noise levels may be achieved through alternate mitigation methods such as selection of lower-noise equipment, and need for mitigative barriers may in some cases be reduced or eliminated.

The noise assessment consisted of: 1) an ambient sound survey, 2) estimation of predicted sound levels from Project construction and operation, and 3) evaluation of potential adverse noise impacts. Where adverse noise impacts were predicted, noise mitigation was proposed to address the impact.

The ambient sound survey was conducted in February 2001 for the original Project DEIS to determine existing ambient sound levels at the nearest residential receptors to the Project. A second sound survey was conducted in May 2007 to determine existing ambient sound levels at the nearest State Forest Preserve land. Average sound levels for each area were determined to be characteristic of a typical rural environment. Results were used with estimated Project sound levels from construction and operation to determine the predicted noise impact from the Project at each receptor based on the increase in ambient sound level.

Project construction sound levels were estimated and noise impacts were assessed for construction of the following: access roads, golf course, and buildings/facilities. Rock crushing to support construction was also assessed. Construction noise impact assessment results and proposed mitigation are summarized as follows:

Access Road – Unmitigated sound for a limited time period would likely impact receptors W-1 and W-7, and W-8 under worst-case conditions when construction is within 500 feet of receptors only. Proposed mitigation consists of minimizing on-site equipment usage when within 500 feet of residences. Additional mitigation of access road construction, such as the construction of barriers, was not deemed practical due to the local topography and the additional construction sound that would result during barrier construction compared with the limited duration of the noise impacts.

Highmount Golf Club – Unmitigated sound was, at times, expected to impact residences at receptors W-7, W-11, and to a lesser degree other nearby receptors with a line-of-sight view of construction. These impacts are only anticipated under the worst-case condition when golf course construction activities are near receptors, and not predicted under more typical construction distances. Mitigation of noise can be accomplished within 500 feet of receptors by minimizing equipment use and by placing temporary earthen berms when construction is anticipated for an extended period. Mitigation of noise when over 500 feet of receptors can be accomplished by maintaining vegetative buffers between the construction and the receptor, as feasible.

Building and Facility Construction and Renovation – Unmitigated sound from construction of the Front-9 Village and Clubhouse, Golf Maintenance Facility, and the Highmount Hotel, Lodge and Detached Lodging Units may at times result in noise impact at receptors W-11, W-6 and W-1, respectively. Proposed mitigation consisted of minimizing on-site equipment during excavation and finishing aspects of construction. In addition, added control of sound during Front-9 Clubhouse and Highmount Lodge construction can be accomplished when needed by placing a temporary line-of-sight barrier between the construction equipment and receptors W-11 and W-1, respectively.

Page 7: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

iv | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during construction Year 1 was predicted to result in potential noise impacts at receptor W-1. As a result, mitigation was proposed consisting of constructing a barrier between the rock crusher and W-1 which is predicted to control the temporary rock crushing noise at W-1 to below significance.

Project operation noise levels and impacts were assessed for both the daytime and nighttime considering all major Project noise sources, continuous and non-continuous. In addition, nighttime continuous sound levels were also assessed considering only continuous Project noise sources. Major continuous noise sources consist of heating, cooling and ventilation system (HVAC) for the hotels and major facility buildings, and hotel room heater/air conditioners. Major non-continuous (intermittent or time-varying) noise sources consisted of on-site traffic, golf course maintenance, and new ski slope snowmaking operations. Operation noise impact assessment results and proposed mitigations are summarized as follows:

Nighttime Sound Levels; Continuous Sources – Without mitigation, Project operation of continuous sound sources are predicted to result in potential noise impacts at receptors W-1, W-3, W-4, W-5, and W-11 due to HVAC noise. Mitigative options to reduce HVAC sound include specifying lower-noise HVAC units, or placing sound shielding barriers around each HVAC units. A combination of lower-noise HVACs and shielding is also an option, since HVAC systems with lower noise specifications may reduce or eliminate need for sound shielding.

Nighttime Sound Levels; Continuous and Non-continuous Sources – Without mitigation, Project nighttime operation of intermittent or time-varying sound sources (including continuous sound sources) is predicted to result in potential noise impacts at receptor W-1 due to snowmaking equipment operation. Mitigation of snowmaking equipment noise at night can be accomplished by curtailing nighttime operation (no operation between 10 PM and 7 AM) of the six north-most snowmakers on the west slope. Snowmaking equipment at these six locations would only be operated during the daytime (7 AM to 10 PM).

Daytime Sound Levels – Project daytime operation, assuming mitigation of HVAC sound as proposed above, is predicted to increase ambient sound levels by 2 dBA or less at all receptors which indicates no adverse noise impact. As a result, no further mitigation to reduce daytime sound levels was proposed.

Page 8: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

1 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

1. INTRODUCTION AND PROJECT REVIEW

This report presents the noise assessment for the Modified Belleayre Resort at Catskill Park (Project) in the Towns of Shandaken and Middletown NY. The purpose of this study is to evaluate potential noise impacts of major Project noise sources from construction and operation, and determine mitigative controls. This report is prepared pursuant to requirements specified the AIP and in Part B of the Final Scoping Document (NYSDEC, 2008), and supplements the original Project noise assessment conducted for the Project DEIS.

The Project consists of two development areas- the Wildacres Resort (Wildacres) and the Highmount Spa Resort (Highmount). Both Wildacres and Highmount are currently primarily wooded. Wildacres is located on approximately 254 acres on the eastern side of the Project site with access from County Route 49A south of the Alpine Osteria Bed and Breakfast, and near the upper driveway to Belleayre Mountain Ski Center and access from Gunnison/Kraft Road. The old Wildacres Motel and the former Marlowe Mansion are currently located on this part of the site. Development proposed for Wildacres Resort includes the following:

a 250 unit hotel building with dining, spa and limited hotel-related commercial space,

139 detached lodging units operated by the hotel

an 18-hole golf club, and

the Wilderness Activity Center using existing buildings at the base of the former Highmount Ski Area

Highmount is located on approximately 237 acres with development proposed to the south and west of the former Highmount Ski Area with access proposed off Route 49A. Highmount includes the upper portion of the old Ski Area and lands to the west including the old Leach farm. Development proposed for the Highmount includes the following:

a 120 unit hotel with spa facilities,

53 semi-detached lodging units located in the hotel,

a multi-level lodge building containing 27 detached lodging units,

40 additional detached lodging units in 32 buildings, and

a public ski lift and two trails to be operated by Belleayre Mountain Ski Center (BMSC).

Construction of Wildacres and Highmount is anticipated to be conducted in three phases over an 8-year period. During construction, sound will be generated from the following:

off-site construction traffic,

access road construction and improvement,

golf course construction, and

construction and renovation of buildings.

As construction phases are completed and operation begins, project operation may generate sound from the following:

1. On-site traffic at the Wildacres and Highmount resorts and facilities consisting of the following sources:

› traffic along on-site access roads

› parking area traffic

2. Stationary sources consisting of the following major sources:

› heating, ventilation and cooling (HVAC) systems and room heater/air conditioners at the Wildacres and Highmount hotel and resort facilities

› snowmaking equipment for two new ski slopes along the Highmount access road

Page 9: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

2 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

3. Quasi-stationary golf course maintenance sources consisting of equipment for the Highmount Golf Club

The following assessment first discusses the nearest potential area that may be impacted by noise from Project construction and operations, then evaluates potential noise impacts, and finally proposes noise mitigation where appropriate to control potential adverse impacts.

Page 10: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

3 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

2. NOISE RECEPTORS AND EXISTING SOUND LEVELS

Receptors are areas that may be sensitive to unwanted sound (noise), and typically include residences, schools, houses of' worship, and hospitals. Recreational areas such as certain types of State Forest Preserve are also considered noise-sensitive receptors. Commercial and industrial properties are not considered noise-sensitive receptors.

Residences lie within a half-mile of Project boundaries to the northwest, northeast and southeast. The nearest recreational area is a State Forest Preserve located over a half-mile south of Highmount. These residences and recreational use areas may be affected by noise from the Project construction and/or operation, and are classified as potential noise-sensitive receptors. The nearest individual residences and Forest Preserve location were selected as the specific receptors at which Project sound levels were predicted and potential impacts were assessed. Receptors for the Project are identified in Figure 1. Residential receptors are discussed in further detail in the Project DEIS Noise Assessment (ENSR, 2002).

The measurement locations pertinent to this Project site are summarized below and depicted in Figure 1.

Site ID Location and Description ML-1 County Road 49A (CR 49A) approximately 1 mile northeast of Hanley Corner.

Characterizes residences on CR 49A in the Highmount Resort area (receptors W-1, W-2, W-3, W-4 and W-5).

ML-2 Gunnison Road approximately 1500 yards west of the intersection of Gunnison Road and CR 49A. Characterizes the residences along Gunnison Road north and northeast of the Wildacres Resort area (receptors W-6, W-7, W-8, W-9, W-11, and W-12)

ML-4 At east end of Lake Street. Characterizes residences on Van Loan Road near Route 28 (receptor W-10).

ML-W1 New York State Forest Preserve; 0.9 miles south of the former Highmount Ski Area. Characterizes recreational land use/Forest Preserve.

Sound measurement surveys were conducted to characterize the acoustical environment of the nearby receptors and determine existing (ambient) sound levels. The sound survey of residential receptors is presented in the Project DEIS Noise Assessment (DEIS Appendix 22).

The sound survey at the State Forest Preserve was conducted on May 9 to 10, 2007 at one location in the State Forest Preserve, 0.9 miles south of the former Highmount Ski Area. This location is the very northwest corner of the Big Indian Wilderness Area, and the closest location of Forest Preserve classified as Wilderness. Sound levels were measured for a 24-hour period using an ANSI S1.4 Type 1 portable real-time sound level meter. To minimize extraneous weather-related noise, the sound level meter microphone was equipped with a windscreen. Field calibration checks of the sound level meter were conducted before and after the measurements using a sound level calibrator, and the sound level meter was factory-calibrated within 12 months of the measurements. Calibration certificates, field forms and data summary printouts are presented in Enclosure 1. Weather conditions were recorded at the start and end of the measurement period. During the measurement period, winds were calm to 3 miles per hour from the south, air temperature was 69 to 74 degrees Fahrenheit, humidity was 41 to 71 percent, and there was no precipitation. Major sources of ambient noise were from birds, distant aircraft, and wind in the trees.

Results of the sound level survey including applicable results from the original DEIS noise assessment are presented in Table 2-1. Results as presented in terms of the daytime and nighttime residual sound level (L90), energy-average sound level (Ld and Ln) and the day-night sound level (Ldn). The L90 is used for evaluating continuous steady-state noise, while the Ld and Ln are used for evaluating non-continuous and/or time-varying noise. The Ldn is used to compare each location’s acoustical environment with typical settings. The Ldn at each receptor was between 46 and 52 dBA, which is typical of a “rural” type environment (USEPA, 1974).

Page 11: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

4 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

3. NOISE ASSESSMENT GUIDELINES

3.1 PROJECT CONSTRUCTION

There are no Federal, or state regulations that apply to this Project’s construction noise. In addition, there are no local ordinances that limit construction noise for this Project. However, the NYSDEC has guidelines that require estimation and evaluation of construction noise impacts as part of their review and approval. The NYSDEC provides guidance on evaluating the impact from project noise in the program policy document “Assessing and Mitigating Noise Impacts” (NYSDEC Program Policy) (NYSDEC, 2001). These guidelines were used in this project to assist in assessing construction noise impacts.

The NYSDEC Program Policy recommends that project noise impacts be assessed based on the increase that the project noise causes to the existing ambient sound level. Generally, noise from continuous steady-state sound sources is added to the ambient residual (L90) sound level. However, since construction sound has significant temporal variations, construction sound levels for the Project were added to the ambient average energy-equivalent sound level (Leq).

To determine noise impacts, the total sound level resulting from the decibel sum of the Project construction Leq sound level and the ambient Leq sound level was compared to the ambient Leq sound level. Human responses to increases in the ambient sound level as suggested in the NYSDEC Program Policy are presented below:

Increase in Sound Pressure Level Expected Human Reaction

Under 5 Unnoticeable to tolerable

5 to 10 Intrusive

10 to 15 Very noticeable

15 to 20 Objectionable

Over 20 Very objectionable to intolerable

A limit for noise impacts is not specifically defined in the NYSDEC Program Policy. However, according to the NYDEC Program Policy, sound sources increasing the ambient sound level by 6 dBA may cause complaints, but that in some instances increases of greater than 6 dBA may be acceptable. The NYSDEC Program Policy specifies that “an increase in 10 dBA deserves consideration of avoidance and mitigation” (NYSDEC, 2001). Therefore, the Project construction noise assessment assumes that increases in ambient sound level due to the Project construction of 10 dBA or more (very noticeable) indicate a potentially significant temporary noise impact that requires further consideration and possible mitigation.

Therefore, temporary Project construction sound was evaluated for noise impact significance and need for mitigation as follows:

Estimated Project construction sound levels at the nearest residential receptors was compared to the existing daytime energy-equivalent A-weighted sound levels (Ld);

Increases in existing Ld at the nearest residential receptor due to construction of 9 dBA or less indicated an insignificant temporary construction noise impact and will not require mitigation;

Increases in existing Ld at the nearest residential receptor due to construction of 10 dBA or greater indicated a potential significant construction noise impact requiring further discussion and/or possible mitigative steps to reduce or eliminate the impact.

Project construction tonal sound levels (prominent discrete tones) will also be identified and discussed.

Page 12: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

5 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

3.2 PROJECT OPERATION

Local regulations that apply to the Project’s operational noise are contained in the town codes for the towns of Middleton and Shandaken. The Town of Middletown Code specifies that 70 dBA must not be exceeded at the property line. However, the Town of Shandaken has more restrictive limits that apply to Project operation as follows:

Receiving Property Time Period Sound Level Limit (dBA)a

Residential Zones (R5, R3, R1.5, HR) 7 AM to 7 PM 57 7 PM to 7 AM 53

Commercial Zones (HC, HB, and CLI) 7 AM to 9 PM 64 9 PM to 7 AM 60

a Sound level limits are reduced by 5 dBA if the noise is a pure tone. Source: Town of Shandaken, 1992

The Shandaken code, however, does not address potential noise impacts due to increases in ambient noise as suggested by NYSDEC. In its noise Program Policy document, NYSDEC suggests that an incremental increase of over 6 dBA at the receptor may result in complaints. For operation noise, which unlike noise from temporary construction has potential for long term noise impact, it is appropriate to use this NYSDEC 6 dBA incremental increase guideline as a noise impact criterion. Steady-state noise sources that operate continuously every day such as hotel building HVAC systems will be evaluated based in comparison with the ambient L90 sound level. Non-continuous, time-varying Project operation sources such as snowmakers, golf course mowers, and traffic will be evaluated in comparison with the ambient Leq sound level.

Review of existing ambient sound levels indicated that the NYSDEC 6 dBA criterion would be lower and thus more restrictive than the Town of Shandaken noise limits with the exception of in the evening when the Town’s evening/nighttime limit of 53 dBA would be most restrictive. Therefore, the Project operation noise impact significance criterion was evaluated for noise impact significance and need for mitigation as follows:

» Estimated Project operation sound levels from continuous steady-state noise sources will be compared to the existing nighttime A-weighted L90 sound levels and evening 53 dBA limit;

» Estimated Project operation sound levels from non-continuous, time-varying sources from continuous steady-state noise sources will be compared to the existing daytime and nighttime A-weighted Leq sound levels (Ld and Ln);

» Increases in existing L90, Ld, or Ln due to Project operation of 6 dBA or less indicated an insignificant operational noise impact and will not require mitigation;

» Increases in existing Ld L90, Ld, or Ln due to Project operation greater than 6 dBA indicated a potential significant noise impact from Project operation requiring further mitigative steps to reduce or eliminate the impact.

Page 13: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

6 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

4. CONSTRUCTION NOISE

4.1 NOISE PREDICTION METHODOLOGY AND ASSUMPTIONS

Construction noise generated by the proposed Project's construction equipment (noise sources) was estimated and extrapolated to the nearest potential noise-sensitive receptor locations using the same methods used in the original DEIS noise assessment. The resultant sound levels at the receptors were used to predict Project construction sound levels and potential noise impacts at each location.

Construction activities that may generate noise emissions at Highmount and Wildacres Resorts will be the same as in the original DEIS and consist of the following:

» Off-site Construction Traffic

» Access Road Construction and Improvement

» Golf Course Construction

» Buildings Construction and Renovation (hotels, detached lodging units, and activity buildings)

Most Project construction activities except for the detached lodging units will be conducted in the first three years. Construction of detached lodging units and some limited construction of other facilities will be conducted during construction Years 4 through 8, or at a later date, according to demand. Construction will be conducted in three phases as follows:

Phase 1 (Years 1 and 2)

› Wildacres hotel, 10 holes of the Highmount Golf Club, and Wilderness Activities Center at old Highmount Ski Center buildings

› Highmount Spa Hotel, the access road to the top of Highmount and the conference/clubhouse facilities at the old Leach Farm

Phase 2 (Years 3 through 5)

› Remaining 8 holes at the Highmount Golf Club

› The Highmount Lodge and the lower elevation detached units

Phase 3 (Years 4 through 8)

› Wildacres Front-9 Village and other detached lodging units

› Highmount higher elevation detached units

Project construction noise will consist of on-site activities as well as off-site noise created by the transportation of construction materials. Each activity will consist of one or more aspects, which were assessed separately or together depending upon whether the aspects will coincide.

4.2 NOISE SOURCES AND SOUND LEVELS

4.2.1 Off-site Construction Traffic Construction of the Project will result in some temporary increase in construction vehicle traffic along NY 28, CR 49A, and the access roads to the Wildacres and Highmount parcels. Commuter automobile traffic to the construction sites is assumed to be minor in comparison, and an insignificant source of construction traffic noise. All construction traffic is expected to arrive via NY 28 to CR 49A to the Wildacres Resort access roads or the Highmount access road.

Maximum noise impacts due to construction traffic are expected to occur along CR 49A and the site access roads, due to the proximity of residences and relatively low volumes of existing traffic. Construction vehicles are expected during daytime periods only for a nine-month season each year. Most construction traffic will occur during the first two years of construction to complete the following activities:

Page 14: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

7 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

› Fill for Highmount access road sub-base

› Golf course topsoil and material

› Topsoil for Highmount and Wildacres resort buildings

› Trucking in construction equipment and miscellaneous deliveries

For the first two years, there is expected to be an average of 53 truck roundtrips per 10-hour day. In comparison with the first two years, construction traffic for construction Years 3 and after will be significantly less at only 7 to 10 trucks per day, and resulting noise levels will be significantly lower.

Sound levels due to construction traffic were calculated using the same procedure used in the DEIS noise assessment, and were based on the expected number of vehicle pass-bys per hour using the following equation (adapted from ESEERCO, 1977):

Equation 1. Sound Level from Construction Traffic Sound Level at Receptor (Leq in dBA) = SPLa - A - B - 15Log[D] - C - E

where: SPLa = Lso sound level (50 feet) for given vehicle trips/hr at 30 mph

A = Lso to L10 sound level correction B = L10 to Leq sound level correction SPLa – A –B = Average construction traffic sound level (Leq) at 50 feet D = distance between traffic and receptor, in feet C = 3 dB/100 foot correction for insertion loss of woods (NYSDEC, 2000) E = -6 dBA reduction for terrain barrier to line-of sight (Hoover and Keith, 1981)

Equation 1 estimates sound levels at receptors assuming a reduction of 4.5 dBA per doubling of the source reference distance that occurs between the source and the receptor. When woods were located between the construction source and the receptor, estimated sound levels also include a conservative insertion loss of 3 dBA per 100 feet of woods up to a maximum insertion loss of 25 dBA. According to the NYSDEC Program Policy document, the actual insertion loss by vegetated areas may be up to 7 dBA per 100 feet depending on vegetation type and density. Reductions due to barriers caused by topography between the construction source and the receptor were also conservatively assumed to reduce sound levels by 6 dBA. Actual reductions due to topography barriers can range from 6 to over 20 dBA (Hoover & Keith, 1981).

Predicted sound levels at nearest receptors for off-site construction traffic are presented in Table 4-1. Estimates are based on the average number of vehicle pass-bys per hour, assuming two vehicle pass-bys per trip, trips are made over a 10-hour day, and half of the vehicle trips would continue on past Wildacres to Highmount.

4.2.2 Access Road Construction Access road construction for the Project will be conducted and substantively completed during the first three years of Project construction. An estimate of the aspects of construction was estimated by the applicant's engineer for the original Project DEIS. The aspects for this current Project are anticipated to be the same, and consist of the following aspects: › Clearing › Earth Excavation › Rock Excavation › Drainage Pipework (Highmount only) › Subgrade Subbase › Trim/Clean-up/Topsoil/Grade › Asphalt Pavement › Rock Crushing

Page 15: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

8 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

Rock crushing will be the only aspect of the access road construction that is not conducted by moving along the length of the roadway. Rock crushing will be conducted at two fixed locations – one just north of the Wildacres Resort, and one next to the Highmount access road just south of the Highmount Hotel. The construction equipment types, size, quantities, and methodology used to estimate access road construction noise was the same as used in the noise assessment for original Project DEIS. Aspects were assumed to be performed sequentially along the roadway. Sound levels estimates for the Project access road construction were calculated for each construction aspect at the nearest sensitive receptor to the roadway. Estimates reflect the worst-case scenario in that they are calculated based on the closest point of roadway construction to the receptor.

Access road construction sound levels were calculate using the same procedure used in the DEIS noise assessment. The maximum instantaneous construction sound pressure level (SPL) of each piece of equipment at its rated peak output was converted to its Leq sound levels based on the following equation (adapted from ESEERCO, 1974):

Equation 2. Equipment Reference Sound Level Equipment Reference Leq (dBA) = SPLa - A - B

where: SPLa = Equipment maximum sound level (50 feet) at peak load A = Usage Factor; correction for percent time of actual use (BBN, 1971) B = Acoustical Max Factor; correction for operation at less than peak load.

The reference Leq's for each piece of equipment at 50 feet were then summed using decibel addition to yield the total construction reference Leq for each aspect using the following equation for summating sound levels from multiple sources:

Equation 3. Decibel Addition Total Sound Level (dBA) = 10 Log{(10L1/10 + 10L2/10 + ... + 10Ln/10}

where: Ln = nth sound level (piece of equipment)

Total construction reference Leq for each construction aspect was then used to estimate the construction sound level at the nearest receptor based on the following equation (adapted from NYSDEC, 2001):

Equation 4. Total Construction Leq at Receptor Total Construction Leq at Receptor (dBA) for each aspect = SPLa - 20Log[Drec/Dref] - A - B

where: SPLa = Total Construction Reference Leq for each aspect 20Log[Drec/Dref] = attenuation of sound due to distance (6 dBA per doubling) Drec = distance to nearest receptor in feet Dref = construction reference Leq distance = 50 feet A = 3 dBA per 100 feet insertion loss for woods between source and receptor B = -6 dBA reduction for terrain barrier to line-of sight

As indicated in Equation 4, estimated construction sound levels at receptors were calculated assuming a reduction of 6 dBA per doubling of the 50-foot reference distance between the source and receptor. When woods were located between the construction source and the receptor, estimated sound levels also include a conservative insertion loss of 3 dBA per 100 feet of woods up to a maximum insertion loss of 25 dBA. Distances from the nearest receptor were conservatively determined by choosing the closest point in the road construction to the receptor. Estimated sound levels from access road construction are presented in Table 4-2.

Page 16: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

9 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

4.2.3 Golf Course Construction Noise from the Project golf course construction is expected to occur over the first two years of construction. During the first year of construction, 10 of the holes will be completed, with the remaining 8 the following year. An estimate of the construction to be completed each year was provided by the applicant's engineer and the applicant for the Project DEIS, and consists of clearing, grubbing, pond excavation, limited blasting, and golf course construction. These aspects of construction within each year are expected to overlap each year (some aspects will take place concurrent with others). Therefore, sound levels were calculated by conservatively assuming that all construction aspects during the given year occur at the same time (worst-case scenario).

The types and quantities of noise-generating equipment used in the golf course construction are the same as in the noise assessment for original Project DEIS. The sound level from each individual piece of equipment was determined from literature based on the equipment type, size and/or horsepower expected to be used. Sound level estimates for the golf course construction were calculated based on the expected construction sound level (Leq) for each construction aspect at the nearest sensitive receptor to the course. Estimates present the worst-case scenario in that they are calculated for the golf course hole closest to the receptor, and at the nearest tee-box, fairway section or green.

Estimated sound levels from golf course construction are presented in Table 4-3. Methodologies and equations for estimating the golf course construction levels at each receptor are the same as used for estimating the access road construction sound level. Sound levels were estimated for each year of construction, assuming aspects of construction would overlap within each year.

4.2.4 Buildings Construction and Renovation Project building construction and renovation will include hotels, support facilities, and detached lodging units. Specific equipment details for the construction and renovations are not available at this design stage of the Project. However, it is anticipated noise will be emitted from a variety of construction equipment that generally includes the following:

› Earth moving equipment (compactors, loaders, backhoes, graders, pavers, and trucks)

› Material handling equipment (cranes, concrete mixers and concrete pumps)

› Stationary diesel equipment (pumps, compressors and generators)

› Impact equipment (jack hammers, pneumatic tools, and pile drivers)

› Other equipment such as welders, vibrators and saws

Such equipment will be operated simultaneously, individually or in various combinations. Since details on types, quantities and sizes of the major construction noise sources are not available, single descriptors of overall sound levels at typical building construction sites were used to estimate Project building construction. Table 4-4 presents the typical energy-average (Leq at 50 feet) construction noise estimates that are provided in literature for five types of construction including large and small buildings and differing equipment quantities (BBN, 1971). As indicated in Table 4-4, the highest typical construction sound levels generally occur during the excavation and finishing, where energy-average sound levels (Leq) are 88 dBA for residences and smaller building construction and 89 dBA at 50 feet for hotels, and large buildings.

Most building construction except for the Highmount Lodge building and detached lodging is planned for the first three years of Project construction (Phases 1 and 2). The Highmount Lodge building is scheduled to be constructed in Years 4 and 5 (Phase 3). Though a few lodging units are planned for the first three construction years, most will be constructed as needed over construction Years 4 through 8.

Estimated sound levels for building construction are presented in Table 4-5. Methodologies and equations for estimating the reduction in construction level to each receptor were the same as used for estimating sound reductions for the access road and golf course constructions. Receptor distances were assumed to be from building site to the receptor, or in the cases of multiple buildings, from worst-case scenario of the nearest

Page 17: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

10 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

building site to the receptor. Estimates were also conservatively estimated based on the worst-case scenario of the loudest construction type, and, except where noted, assumed that all pertinent equipment would be present at the site rather than minimum required equipment. Due to the relatively large size of the overall Project construction area compared with the distances to receptors, construction sound levels for each building were estimated separately, and assume that sound from construction of one building will not increase sound levels in the construction of other buildings.

4.3 CONSTRUCTION NOISE IMPACT ASSESSMENT AND MITIGATION

Noise impact assessment for each construction activity is summarized in Table 4-6 and discussed below. In general, temporary noise impacts were predicted where Project construction was estimated to increase the ambient sound levels by 10 dBA or more. Increases in sound level at receptors of 9 dBA or less were assessed an insignificant temporary noise impact, assuming the character of the sound was not dominated by tonal noise (prominent discrete tones). In addition, potential impacts from tonal noise and blasting are also discussed.

Table 4-6 indicates temporary construction noise impacts before mitigation are predicted to potentially occur during portions of the following construction activities:

» Access Roads

» Highmount Golf Club

» Front-9 Village and Front-9 Village Clubhouse

» Golf Maintenance Facility

» Highmount Hotel and Highmount Lodge

» Rock Crushing at Highmount

» Highmount Detached Lodging Units

Each of these construction activities are discussed below along with proposed mitigation, if applicable.

4.3.1 Access Roads Noise from the Wildacres and Highmount access road construction will occur during construction Year 1 and is, for a very limited period of time, expected to impact receptors W-1 and W-7, and to a lesser degree may impact receptor W-8 which is within 500 feet of a small portion of the access road. Noise impacts are expected to be transient and limited to portions of the access road within 500 feet of receptors. Access road construction conducted more than 500 feet from receptors is not expected to result in significant noise impacts (9 dBA increase or less). Since only approximately 15 percent of any access roadways are within 500 feet of a receptor, access road construction impacts are expected to be short term, and noise impacts on any specific receptor are expected to be limited to approximately a month and a half in duration. Mitigation of the Wildacres access roads would be accomplished by minimizing on-site equipment usage when within 500 feet of residences. A reduction of approximately 3 dBA can be expected by reducing on-site equipment usage by 50%. Additional mitigation of access road construction, such as the construction of barriers, is not deemed practical due to the local topography and the additional construction sound that would result during barrier construction compared with the limited duration of the noise impacts.

4.3.2 Highmount Golf Club Noise from the golf course construction of the Highmount Golf Club will occur during construction Years 1 and 2, and is, at times, expected to impact residences at receptors W-7, W-11, and to a lesser degree other nearby receptors with a line-of-sight view of construction. As a result, mitigation is recommended in order to reduce the noise impacts.

Mitigation of the Highmount Golf Club construction noise impacts is recommended in two steps. Mitigation of noise at distances of greater than 500 feet from the line-of-sight to a receptor may be accomplished by maintaining a 500-foot vegetative barrier between the construction and the receptor. This would mean that the

Page 18: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

11 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

clearing, grading and preparation of holes within 500 feet of receptors should be conducted later in the construction schedule. Please note that where line-of-sight from the construction area to the receptor is blocked by a natural or man-made barrier, then the vegetative-buffer distance may be reduced to 300 feet. Sound level reductions due to distance attenuation and vegetative insertion loss over the 500 feet are expected to be -23 dBA and sufficient to decrease noise impacts at all receptors to below significance.

For distances within 500 feet of a residence, a mitigative barrier and reduced equipment usage is recommended when construction is anticipated for an extended period. To provide satisfactory sound reduction, the barrier should be located within 150 feet of either the receptor or the construction area, and it should extend at least 10 feet above the line-of-sight between the construction noise sources and the receptor (see Enclosure 2). In addition to the barrier, further sound reduction can be achieved by using the minimal required construction equipment. In addition, construction equipment not in active use at the site should be shut off. Additional sound attenuation due to the barrier (approximately -20 dBA) and reduced equipment usage of 50% (approximately -3 dBA) are estimated to decrease noise impacts of the golf course construction at all receptors below significance. Please note that the barrier is expected to consist of an earthen berm, which will require approximately two weeks to construct and one week to remove. During this time period, construction noise at the receptor may temporarily exceed significance criteria. Further, when golf course construction time (and potential noise impacts) within 500 feet of the receptor is anticipated to be short with respect to the barrier construction time, then berms will not be constructed.

4.3.3 Front-9 Village and Front-9 Village Clubhouse Sound during portions of construction of the Front-9 Village Clubhouse during construction Year 1, and the nearest Front-9 Village lodging units during the eight-year construction period is estimated to impact receptor W-11. As a result, mitigation is recommended to reduce the noise impacts.

During Clubhouse construction, mitigation resulting in 11 dBA lower construction sound levels can be accomplished by minimizing on-site equipment, and placing a temporary barrier when needed between the construction equipment and receptor W-11. The barrier should be tall enough to prevent line-of-sight from the construction equipment noise sources to receptor W-11, and may be constructed of any material (including earth or stone berms, or a fence with hanging flexible curtain barrier walls) having a sound transmission loss of 16 dBA or more. The actual height of the barrier above grade will depend upon siting and local topography.

During the construction of the Front-9 Village, mitigation resulting in 5 dBA lower construction sound levels can be accomplished by minimizing on-site equipment. This is predicted to reduce typical construction levels to below significance. Noise during construction of the nearest units, especially those closest to receptor W-11 may result in brief noise impacts typical of residential construction. During such construction at the nearest set of housing units, therefore, temporary barriers or shielding will be used as-needed to further control noise.

4.3.4 Golf Maintenance Facility Noise from construction of Golf Maintenance Facility will occur during construction Years 1 and 2, and are, at times, estimated to impact receptor W-6. As a result, mitigation is recommended to reduce the noise impacts to below significance. Mitigation resulting in 5 to 15 dBA lower sound levels can be accomplished by minimizing on-site equipment during excavation and finishing aspects of construction.

4.3.5 Highmount Hotel and Highmount Lodge Sound from construction of the Highmount Hotel (Years 1 and 2) and Highmount Lodge (Years 1 through 5) is predicted to result in noise impacts at receptor W-1 during portions of their construction. As a result, mitigation is recommended to reduce the noise impacts to below significance. Mitigation resulting in 5 dBA lower sound levels can be accomplished by minimizing on-site equipment during excavation and finishing aspects of construction. In addition, a barrier between the construction equipment and receptor W-1 should be constructed. The barrier should be tall enough to prevent line-of-sight from the construction equipment noise sources to receptor W-1, and may be constructed of any material (including earth or stone berms, or a fence with hanging flexible curtain barrier walls) having a sound transmission loss of 16 dBA or more. The actual height of the barrier above grade will depend upon siting and local topography.

Page 19: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

12 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

4.3.6 Rock Crushing at Highmount. Sound from rock crushing near the Highmount Hotel during construction Year 1 is predicted to result in potential noise impacts at receptor W-1. As a result, mitigation by is recommended to reduce the noise impacts.

Mitigation of noise impacts from the rock crusher the can be accomplished by constructing a barrier between the rock crusher and W-1. A reduction of approximately -16 dBA can be expected from the barrier. The barrier should be located in the direction of W-1, placed within 30 feet of the crusher, and extend straight 30 feet past each end of the crusher. The barrier should be built to a height at least 10 feet above the line-of-sight between the top of the rock crusher noise source and the receptor (see Enclosure 2). The barrier may be constructed of any material (including earthen or stone berms, or berms with a barrier on top) having a sound transmission loss of 27 dBA or more1

4.3.7 Highmount Detached Lodging Units.

.

Sound from construction of the Highmount detached lodging units located along the Highmount access road will occur likely after the eight-year construction period. Sound from construction of the four units nearest receptor W-1 during clearing foundations and finishing is predicted to result in noise impacts. Such temporary construction sound levels would be brief and typical of normal residential construction. However, mitigation resulting in 5 dBA lower sound levels can be accomplished at the four units nearest W-1 by minimizing on-site equipment, which would reduce noise impacts to below significance.

4.4 IMPACT AND TONAL NOISE

Project construction will consist primarily of diesel engine noise that is broadband in nature without predominant tonal noise, and not characterized as impact noise. Though some tonal noise may be emitted by some individual pieces of equipment, these tones would be masked by sound from other sources, and are anticipated to result in no audible prominent discrete tones at any receptor. The only major tonal noise expected from Project construction will be due to back-up beepers, which are a law-required safety feature that cannot practically be avoided on temporary construction sites. However, since most construction will be conducted at considerable distance from receptors, and through large distances of wooded areas, impacts from back-up beeper tonal noise on any specific receptor are expected to be minimal and short term.

4.5 BLASTING NOISE

Excavation for Wildacres and Highmount buildings, roadways and golf course will include some explosive blasting of bedrock. The size of the explosive charges to be used is not yet determined. However, instantaneous sound levels from typical construction blasting has been documented as approximately 93 to 94 dBA at a distance of 50 feet (Hoover and Keith, 1981), which is only a few decibels higher than the expected reference sound level from several of the Project construction activities. In comparison with other construction sound, the sound from blasting will be brief and relatively infrequent. Though some limited and minor blasting may be conducted at locations proximal to residential properties, most blasting will be conducted at locations several hundred feet from receptors, and will often be shielded by woods and terrain. The SDEIS contain numerous mitigation measures relating to blasting, including providing pre-blast notification to people with ¼ mile who wish to be notified in the hour before blasts will be made.

1 Sound transmission loss is the dBA reduction of sound that passes directly through the barrier material. Sound transmission loss of shields and barriers should be at least 10 dBA above its insertion loss so the barrier’s effectiveness is not compromised by sound going through the barrier.

Page 20: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

13 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

5. OPERATIONS NOISE

5.1 NOISE PREDICTION METHODOLOGY AND ASSUMPTIONS

Project operation sound levels were estimated at the nearest receptors using CadnaA noise prediction software. CadnaA predicts sound propagation from each noise source taking into account sound attenuation due the following:

» normal hemispheric sound propagation over distance (standard conditions of 10°F/90% humidity),

» reductions to sound due to ground attenuation over absorptive surfaces,

» additions to sound due to reflection, and

» reductions in sound due to shielding from intervening topography, barriers and wooded areas.

Other conditions and bases for the noise evaluation include the following:

» octave band reference sound level data were used for HVAC, snowmaking equipment, and on-site traffic,

» overall A-weighted reference sound levels were used for golf course mowers and hotel PTACs, and

» receptor heights were assumed to be 4 meters above ground surface.

As indicated Section 3, Project noise was assessed by comparing the predicted total sound level at each receptor due to the Project with the 6 dBA incremental increase limit. Existing ambient sound levels were assumed to be the energy-average sound level (Ld or Ln) for non-continuous/time-varying sound sources, and the L90 for continuous sound sources. Project noise impacts were deemed significant and in need of mitigation if predicted Project sound levels exceeded the 6 dBA limit.

5.2 NOISE SOURCES AND SOUND LEVELS

5.2.1 On-site Traffic Sources On-site Project traffic sound will result from: 1) entering or exiting traffic travelling on access roads within the Project site, and 2) vehicles entering or exiting site parking areas.

On-site access road traffic can be evaluated separately from the stationary noise sources by assessing off-site Project traffic. Potential noise impacts from Project traffic was assessed as part of the Project off-site traffic study of traffic entering and exiting the Project sites (Creighton Manning, 2011). Results indicated receptor sound levels would increase by 3 dBA or less during peak Project traffic. Compared with the off-site traffic entering and exiting the Project site, on-site traffic along site access roads will have lower speeds and will be farther from receptors. Therefore, sound levels due to on-site access road traffic are predicted to be less than the 3 dBA, and would add at most 1 dBA to the average sound level (Leq) at any receptor.

On-site traffic entering, exiting and moving within parking areas will generate sound similar to other stationary sound sources from Project operations. The largest parking areas at the site were assumed to be the major noise sources of parking area sound at any given time. The Project’s major parking areas are located at the following four areas:

› Wildacres Hotel - 458 parking spaces

› Golf Clubhouse and Front-9 Village -117 parking spaces

› Highmount Hotel - 310 parking spaces

› Highmount Lodge – 31 parking spaces

Traffic in these parking areas will constantly vary. However, to quantify normal traffic sound levels, sound level estimates assumed that 10 percent of the parking capacity may be operating at any given time during the day (7 AM to 10 PM) and 2 percent of the parking capacity may be operating at any given time during the night (10 PM to 7 AM). Parking area traffic sound levels were determined assuming traffic would be predominantly comprised

Page 21: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

14 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

of passenger vehicles traveling at 10 mph and located at the parking entrance. Reference sound levels for the Project’s four major parking areas are presented in Table 5-1.

5.2.2 Stationary Sources Major Project stationary noise sources will consist of the following:

› Air handling systems (HVAC) for common space at Wildacres Hotel, Highmount Hotel, Highmount Lodge, and the four other major building facilities (Clubhouse at Old Leach Farm, Wilderness Activities Center, Marlowe Mansion, and the Front-9 Village Clubhouse),

› Hotel room heater/air conditioners (PTACs) at Wildacres Hotel and Highmount Hotel, and

› Snowmaking equipment along the two new ski trails adjacent to the Highmount access road.

Sound levels for each major stationary noise source are presented in Table 5-1. Other lesser noise sources such small outdoor pumps and motors associated with ski lift operations and heating/cooling of detached housing units are assumed to be minor and insignificant in comparison with higher sound levels of the HVAC, PTAC and snowmaking major noise sources.

HVAC system design details including location and specification are not currently determined. Therefore, sound levels of open common space at hotels and major facilities were evaluated based on typical HVAC engineering requirements specifying approximately 1-ton of capacity per 400 square feet2

In addition to the HVAC system servicing hotel common area, each hotel room at Wildacres Hotel and Highmount Hotel will have an individual package terminal air conditioner (PTAC). PTACs will operate as-needed based on heating cooling needs and occupancy, However, estimated sound level conservatively assume the worst-case conditions of all PTACs in simultaneous operation.

. Reference sound levels for the HVAC were based on published empirical octave band sound level data versus tonnage for package chillers using reciprocating compressors (below 200 tons) or centrifugal compressors (above 200 tons). HVACs will operate as-needed based on heating and cooling needs. However, estimated sound levels conservatively assume worst-case conditions that HVACs operate continuously and at all seven major buildings.

Snowmaking equipment will consist of Standard Polecat fan-driven snowmakers. Reference sound levels for the Standard Polecat were based on manufacturer’s octave band sound level data from measured sound levels of 67 dBA at 50 feet to the side of the snow maker. Estimated sound levels assume the following:

› snowmakers will be placed at a height of 10-feet above grade approximately every 100 feet along the west edge of each of the two new ski trails, and

› snowmakers will be oriented facing northeast across each trail and aligned so that they are not pointed directly at or away from receptors W-1 and W-2 (sound levels directly in front or directly behind the snowmakers are estimated to be 7 dBA higher than sound levels to the side).

Sound levels during snowmaking conservatively assume all snowmakers will be operated simultaneously. Estimated sound levels from snowmaking were also included as both a day and nighttime sound source of intermittent Project noise, since snowmaking may occur during any time period.

5.2.3 Golf Course (Quasi Mobile) Sources Major noise sources for the operation and maintenance of the Highmount Golf Club will consist primarily of grass cutting and rolling equipment. Though some maintenance of the rough will be conducted in the afternoon, most maintenance operations will be conducted in the morning, which will represent the period of worst-case noise levels. Morning maintenance equipment and duration of activities for each type is anticipated to be the following:

2 Based on conversations with O'Brien & Gere engineering staff; engineering typical rule-of-thumb for estimating HVAC needs from total floor space area prior to building design.

Page 22: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

15 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

› 4 greens mowers (3.5 AM hours),

› 1 greens roller (4 AM hours),

› 1 collar mower/stepcut mower (4 AM hours)

› approach mowers (4 mowers x 4 hours in the morning), and

› fairway mowers (4 mowers x 4 hours in the morning).

Reference sound levels for each mower are presented in Table 5-1 and are based on sound levels measured for similar golf maintenance equipment (PCD, 2004). Estimation of potential noise impacts also conservatively assumes the worst-case condition when mowers are operating in the nearest greens and fairways to potential receptors, and assumes one mower is operating at any given part of a hole at any given time. Predicted sound levels were compared with daytime average ambient sound levels (Ld), since the mowing will not be continuous and will occur only during the day.

5.3 OPERATIONAL NOISE IMPACT ASSESSMENT AND MITIGATION

Potential noise generated by the proposed Project's operation was estimated and extrapolated to the nearest potential receptor locations using CadnaA noise prediction software. Similar to the construction noise assessment, resultant total sound levels at the receptors were estimated and used to predict potential Project noise impacts at each receptor including the State Forest Preserve. Project operation was assessed for the following three conditions:

» Nighttime from continuous Project operations – Compared continuous steady-state Project sound to the nighttime residual ambient sound level (L90).

» Nighttime from continuous and non-continuous Project operations – Compared Project nighttime sound to the average nighttime ambient sound level (Ld), and

» Daytime (continuous and non-continuous Project operations) – Compared Project daytime sound to the average daytime ambient sound levels (Ld),

5.3.1 Nighttime Sound Levels – Continuous Project Operations As indicated in Section 3, major continuous sound from Project operations is due to hotel and facility building ventilation systems. Estimated Project sound levels are presented in Table 5-2. CadnaA graphical output depicting decibel contours before and after mitigation are presented in Enclosure 3.

As indicated in Table 5-2, building ventilation systems, without mitigation (unshielded), are predicted to result in noise impacts at receptors W-1, W-3, W-4, W-5, and W-11. The greatest increase in sound levels is predicted at W-1 (18 dBA), and is due to Highmount Lodge and Highmount Hotel HVACs, and, to a lesser degree, the Clubhouse at Old Leach Farm HVAC. Predicted elevations in sound level at W-3, W-4 and W-5 are predominantly affected by noise from the Wilderness Activities Center HVACs and to a lesser degree by HVACs at the Wildacres Hotel and Marlowe Mansion (W-5 only). Sound levels at estimated at W-11 are affected almost entirely by the Font-9 Village Clubhouse HVAC.

Mitigation of HVAC sound can be accomplished by 1) attenuating the sound from the HVAC by shielding them from transmitting sound in the direction of potentially impacted receptors, or by specifying lower-noise HVAC units than the typical HVACs assumed in Table 5-1. Lower-noise HVACs would reduced or possibly eliminate shielding needs. Mitigation of typical HVAC units may be accomplished by placing a sound shielding barrier around and within six feet of the HVAC units. The shielding should extend six feet above the noise sources on the HVAC, except for the side of the Highmount Lodge HVAC facing receptor W-1 which should be 8 feet above the HVAC. The estimated effective sound reduction (insertion loss) of such shielding would be -16 dBA and the mitigation would reduce potential for audible Project sound at the State Forest Preserve. The shielding can be constructed out of any material or structure having sound transmission loss of at least 26 dBA or more and absorptive on the interior side facing the HVAC. If building walls are to be used as all or part of the shielding, then absorptive material may be needed on the wall surfaces to minimize reflection of sound.

Page 23: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

16 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

Estimated sound levels after proposed mitigation are presented in Table 5-2 and indicate that increases in ambient sound levels will be 4 dBA or less at all receptors. In addition, estimated nighttime continuous sound levels from Project operation at the State Forest Preserve are predicted to be below 10 dBA and result in no increase to the ambient sound level.

5.3.2 Nighttime Sound Levels – Continuous and Non-continuous Project Operations In addition to continuous nighttime Project sound, at times Project operation will also generate non-continuous nighttime sound that is intermittent and/or time-varying. As indicated in Section 3, intermittent or time-varying operational sound at night is generated by on-site traffic and snowmaking equipment, and is evaluated in comparison with the average ambient sound level (Leq). Estimated Project nighttime sound levels are presented in Table 5-3. CadnaA graphical output depicting decibel contours before and after mitigation are presented in Enclosure 3.

As indicated in Table 5-3, Project nighttime operation, without additional mitigation3

Mitigation of snowmaking equipment noise at night can be accomplished by curtailing nighttime operation (10 PM to 7AM) of the six north-most snow guns on the west slope. Snowmaking at these six locations would only be conducted during the daytime (7 AM to 10 PM). The estimated effectiveness of the proposed mitigation is predicted to be -5 dBA at W-1. In addition, overall nighttime sound levels from snowmaking will be reduced by approximately 1 dBA, which may tend to reduce nighttime audibility of snow maker operation at the State Forest Preserve.

, is predicted to result in potential noise impacts at receptor W-1. The increase in sound levels at W-1 (+9 dBA) is primarily due to sound from operation of the snowmaking equipment – most notably the snowmaking equipment on the west slope, closest to W-1.

Estimated sound levels after proposed mitigation of snowmaking sound, presented in a Table 5-3, indicate that increases in ambient sound levels will be 4 dBA or less at all receptors. In addition, Project nighttime sound levels at all receptors will be well below the Town of Shandaken nighttime noise limit of 53 dBA. Estimated Project nighttime sound levels at the State Forest Preserve are predicted to be below 20 dBA and result in no increase to the average ambient sound level.

5.3.3 Daytime Sound Levels Project operational noise during the daytime may be higher at some receptors than at night due to the following conditions: › maintenance of the Highmount Golf Club 18-hole golf course (not conduced at night) › operation of snowmakers – all 30 proposed snowmakers are conservatively assumed to be in simultaneous

operation (worst-case condition), and › increased sound from on-site traffic at major parking areas (from 2% of parking area capacity at night to

10% during the day). Estimated Project daytime sound levels are presented in Table 5-4. CadnaA graphical output depicting decibel contours are presented in Enclosure 3. As indicated in Table 5-4, Project daytime operation is predicted to increase ambient sound levels by 2 dBA or less at all receptors. Further, estimated Project daytime sound levels at the State Forest Preserve are predicted to be 20 dBA, which is 19 dBA below the average ambient sound level, and would not increase to the average ambient sound level. Therefore, no additional mitigation of Project daytime noise sources is needed or proposed.

5.4 IMPACT AND TONAL NOISE

Project operation will consist primarily of reciprocating engines, fans, compressors, and gas/diesel engine noise that is broadband in nature without predominant tonal noise. Impact noise is not anticipated. Though some minor tonal noise may be emitted by some individual pieces of equipment, these tones would be masked by sound from other sources, and are anticipated to result in no audible prominent discrete tones at any receptor. 3 In addition to mitigation proposed in Table 5.2.

Page 24: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

17 | FINAL: MARCH 25, 2011

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Noise_Final.docx

6. REFERENCES

BBN, 1971. Noise from Construction Equipment and Operations, Building Equipment, and Home Appliances, Bolt, Beranek and Newman Inc., December 31, 1971.

ENSR, 2002. Community Sound Survey and Construction Noise Impact Assessment - Belleayre Resort at Catskill Park. ENSR Corporation, January 2002.

Crossroads Ventures, 2001. Ken Graham of Crossroads Ventures telephone conversation with Scott Manchester of ENSR, January 14, 2001.

ESEERCO, 1977. Empire State Electric Energy Research Corporation. Power Plant Construction Noise Guide. Bolt Beranek and Newman, Inc. Report No. 3321. May 1977.

Hoover & Keith, 1981. Noise Control for Buildings. Manufacturing Plants. Equipment. and Products. Hoover & Keith, Inc. 1981.

Goodman, 2008. Amana® Brand PTAC Sound Report. Goodman Company, L.P., October 4, 2008.

K&S, 2006. Measured Sound Levels of the Standard Polecat by Snow Machines Incorporated. Kolano and Saha Engineers, March 30, 2006.

NYSDEC, 2001. New York State Department of Environmental Conservation Program Policy: Assessing and Mitigating Noise Impacts, October 6, 2000; revised February 2, 2001.

NYSDEC, 2008. Final Scoping Document – Belleayre Mountain Ski Center Unit Management Plan – DEIS and Modified Belleayre Resort at Catskill Park, Supplemental DEIS. February 28, 2008.

PCD, 2004. Rancho San Juan Specific Plan and HYH Property Project EIR, Section 5.6. Project Design Consultants, May, 2004

Town of Shandaken, 1992. Zoning Code of the Town of Shandaken, Chapter 116 Article VI Section 116-23 –Supplementary Regulations. Amended December 28, 1992.

USEPA 1974. Information on Levels of Environmental Noise Requisite to Protect Public Health and Welfare with an Adequate Margin of Safety. Document No. 550/9-74-004. United States Environmental Protection Agency. March 1974.

Page 25: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

TABLES

360° Engineering and Project Delivery Solutions

Page 26: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 2-1. Ambient Sound Levels Results

Measurement Location (Site ID)

Receptor(s) Characterized

(ID)

Daytime Average Sound Level (Ld dBA)

Nighttime Average

Sound Level (Ln dBA)

Day-Night

Sound Level (Ldn dBA)

Daytime Residual Sound Level

(L90 dBA)

Nighttime Residual Sound Level

(L90 dBA)

ML-1 W-1, W-2, W-3,

W-4, W-5 50 39 49 35 27

ML-2 W-6, W-7, W-8,

W-9, W-11, W-12 50 37 49 41 30

ML-4 W-10 48 45 52 43 41 ML-W1 FP-1 39 40 46 24 21

Notes: Daytime: 7 AM to 10 PM (includes evening hours from 7 PM to 10 PM); Nighttime: 10 PM to 7 AM

Ld and Ln based on time-weighted energy-equivalent average sound level (Leq) Ldn = 10Log{(15*(10Ln/10)+9(10Ln+10)}/24 L90 = sound level exceeded for 90 percent of measurement period

Page 27: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-1 Off-site Construction Traffic - Predicted Sound Levels

Project Area

Year

Average Vehicle

Pass-bys per hour

Average Traffic Sound Levela

(dBA at 50 feet)

Nearest Receptor

Receptor Distance

(feet)

Distance Attenuation

(dBA)

Wooded Distance

(feet)

Woods Insertion

Loss (dBA)

Traffic Sound Level at

Receptor (dBA)

Wildacres 1 to 2 10.6 61 W11 80 -3 0 0 58

3 to 8 2 42 W11 80 -3 0 0 39

Highmount 1 to 2 5.3 55 W3 50 0 0 0 55

3 to 8 1 39 W3 50 0 0 0 39 a Leq at 50 feet assuming truck traffic at 30 mph.

Page 28: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-2 Access Road Construction - Predicted Sound Levels

Project Area Aspect

Construction Reference

Sound Level (dBA at 50 ft)a

Nearest Receptor

Receptor Distance

(feet)

Distance Attenuation

(dBA)

Wooded Distance

(feet)

Woods Insertion

Loss (dBA)

Construction Sound Level

(dBA)

Wildacres Clearing 85 W7 200 -12 200 -6 67

Earth Excavation 90 W7 200 -12 200 -6 72

Rock Excavation 85 W7 200 -12 200 -6 67

Subgrade Subbase 81 W7 200 -12 200 -6 63

Trim/Cleanup/Topsoil/Grade 84 W7 200 -12 200 -6 66

Asphalt Pavement 79 W7 200 -12 200 -6 61

Rock Crushinga 89 (100 feet) W7 900 -19 400 -12 58

Typicalc 84 - 1000 -26 400 -12 46

Highmount Clearing 85 W1 160 -10 100 -3 72

Earth Excavation 90 W1 160 -10 100 -3 77

Rock Excavation 85 W1 160 -10 100 -3 74

Subgrade Subbase 81 W1 160 -10 100 -3 68

Trim/Cleanup/Topsoil/Grade 84 W1 160 -10 100 -3 71

Asphalt Pavement 79 W1 160 -10 100 -3 66

Rock Crushingd 89 (100 feet) W1 360 -11 100 -3 75

Typicalc 84 - 1200 -26 500 -15 41 a Access road construction reference sound levels from DEIS Noise Assessment (ENSR, 2002) b Rock crusher to be permanently located during construction near the proposed fractional units, ~ 250 feet west of the golf practice/driving range tees. c Based on typical construction sound level at 50 feet, and average distance from receptor. Excluding rock crusher noise which is a fixed sound source. d Rock crusher to be permanently located during construction at southwest parking lot of Highmount Resort Hotel.

Page 29: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-3 Golf Course Construction – Predicted Sound Levels

Construction Year Holes

Construction Reference

Sound Level (dBA at 50 ft)a

Nearest Receptor

Receptor Distance

(feet)

Distance Attenuation

(dBA)

Wooded Distance

(feet)

Woods Insertion

Loss (dBA)

Construction Sound Level

(dBA)

1 3 through 8, 10, 11, driving range

91 W11 340 (min)

1400 (typical) -17 -29

0 200

0 -6

74 56

2 1, 2, 9, 12 through 18 91 W7 370 (min)

1200 (typical) -17 -28

200 200

-6 -6

68 57

aGolf course construction reference sound levels from DEIS Noise Assessment (ENSR, 2002)

Page 30: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-4 Typical Building Construction Sound Levelsa

Construction Aspect

Hotel and Major Facilities Residences and Small Buildings Minimum Equipment

On-site (dBA)

All Pertinent Equipment On-site (dBA)

Minimum Equipment On-site (dBA)

All Pertinent Equipment On-site (dBA)

Clearing 84 84 83 83

Excavation 79 89 75 88

Foundations 78 78 81 81

Erection 75 87 65 81

Finishing 75 89 72 88 aLeq at 50 feet. Reference: BBN, 1971

Page 31: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-5 Building Construction and Renovation Sound Levels

Location Aspect

Construction Sound Level

(dBA at 50 ft)

Nearest Receptor

Receptor Distance

(feet)

Distance Attenuation

(dBA)

Wooded Distance

(feet)

Woods Insertion

Loss (dBA)

Construction Sound Level

(dBA)

Wildacres

Hotel and Facilities 89 W-7 1280 -28 400 -12 49

Clubhouse 88 W-7 920 -25 440 -13 50

Front-9 Village (Lodging Unit) Clubhouse, Pool

and Tennis Courts 88 W-9 400 -18 100 -3 67

Water Treat. Facilitya 72 W-6 300 -15 150 -5 52

Wilderness Activities Center Renovationb

81 W-4 240 -14 240 + terrain

barrier -7+ -6 54

Marlow Mansion 88 W-5 1400 -29 400 -12 47

Golf Maintenance Facility 88 W-6 720 -23 100 -3 62

Front-9 (East) Village - 84 Units

88 W-11 200 (min)

800 (typical) -12 -24

0 0

0 0

76 64

West Village - 56 units 88 W-7 770 -24 640 -18 46

Highmount

Highmount Spa Hotel 89 W-1 620 -22 130 -4 63

Highmount Lodge 88 W-1 330 -16 100 -3 69

Conference/Clubhouse; Renov. Old Leach Farmb 81 W-2 600 -22 400 -12 47

19 Detached Lodging Units (top of Highmount)

88 W-1 2,000 -32 200 -6 50

21 Detached Lodging Units (along access road)

88 W-1 480 -20 180 -5 63 a Pre-fabricated building anticipated. Sound level assumes minimal ground clearing, excavation and foundation work. Sound levels from finishing aspect assuming a minimum of equipment is required on-site. b Sound level assumes minimal or no significant ground clearing and minimum construction equipment on-site.

Page 32: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-6 Project Construction Noise Assessment and Mitigation

Construction Const.Years

Nearest Receptor

Project Sound Level

(dBA)

Ambient Sound Levela

(Ld, dBA)

Total Sound Level (dBA)

Ambient Sound Level

Change (dBA)

Mitigative Action/

Estimated Reduction (dBA)

Mitigated Ambient

Sound Level Change (dBA)

Off-site Traffic 1-2

W11 W3

57 55

50 50

58 56

8 6

None required

Access Roads – Construction max when within 500 ft. of

receptor (~1.5 mo./receptor) 1-2 W1, W7

61-77 (max); ≤46 (typical)

50 61-77 (max); 51 (typical)

11-27 (max); 1 (typical)

Use minimum equipment

on-site: -3 dBA

9-24 (max); 1 (typical)

Highmount Golf Club – Maximum: Closest part of

nearest hole 1-2 W7, W11

74 (max); ≤57 (typical)

50 74 (max);

≤58 (typical) 24 (max); ≤8 (typical)

Minimum equip. Under 500 feet

on-site:-3 dBA; Barrierb: -15 dBA

500 foot vegetative buffer: -18 dBAc

Over 500 feet ≤8

Wildacres Hotel & Facilities 1-2 W7 49 50 53 3 None required Rock Crushing – Wildacres Hotel/Golf Club, Access Rd

1-2 W7 58 50 59 9 None required.

Clubhouse 1 W7 50 50 53 3 None required Front-9 Village (Lodging

Unit) Clubhouse, Pool and Tennis Courts

1 W9 67 50 67 17 Minimum equip. on-site:-5 dBA; Barrierd: -6 dBA

7

Wilderness Act. Center 1 W5 54 50 54 4 None required Marlow Mansion W6 47 50 52 2 None required

Golf Maintenance Facility 1 W6 62 50 62 12 Minimum equip. on-site: ≥-5 dBA;

≤8

Front-9 (East) Village – 84 Units

3-8 W11 77 (max);

63 (typical) 50

77 (max); 63(typical)

27 (max); 13 (typical)

Minimum equip. on-site:-5 dBA

≤22 (max)e; <9 (typical)

West Village – 56 Units 4-8 W7 46 50 51 1 None required Water Treatment Facility 1 W6 52 50 54 4 None required

Page 33: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 4-6 Project Construction Noise Assessment and Mitigation

Construction Const.Years

Nearest Receptor

Project Sound Level

(dBA)

Ambient Sound Levela

(Ld, dBA)

Total Sound Level (dBA)

Ambient Sound Level

Change (dBA)

Mitigative Action/

Estimated Reduction (dBA)

Mitigated Ambient

Sound Level Change (dBA)

Highmount Hotel 1-2 W1 63 50 63 13 Minimum equip. on-site: ≥-5 dBA

≤9

Rock Crushing – Highmount Hotel and Access Road

1-2 W1 75 50 75 25 Barrierf:-16 dBA 9

Highmount Lodge 1-5 W1 69 50 69 19 Minimum equip. on-site: ≥-5 dBA; Barrierd: -6 dBA

≤9

Conference Clubhouse (Old Leach Farm)

1 W2 47 50 52 2 None required

19 Detached Lodging Units (top of Highmount)

4-8 W1 50 50 53 3 None required

21 Detached Lodging Units

(along access road)

After Yr-8

(9-11) W1 63 50 63 13 Minimum equip.

on-site:-5 dBA; ≤9

a Ambient sound level from average daytime Leq (Ld). b Barrier assumption: only when within 150 feet of residence; extending 10 feet above source/receptor line-of-sight (Enclosure 2, Barrier B1). Barrier may be a temporary berm or solid fencing, or a combination of the two. c Includes -3 dBA for additional distance attenuation from 370 feet to 500 feet. d Line-of-sight barrier (berm or other temporary barrier such as a solid fence or barrier curtain) placed between construction noise sources and receptor as needed depending on construction sound levels. e Only during portions of the residential construction of the nearest octoplex of housing units. During such construction, temporary shielding will be used as needed depending on construction sound levels f Barrier assumption: within 30 feet of rock crusher, extending 10 feet above receptor/breaker line-of-sight (See Enclosure 2, Barrier B2).

Page 34: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 5-1 Project Operation – Sound Sources and Reference Sound Levels

Source Location Major Noise Source Unit Reference

Sound Power Level (dBA)

Quantity Total

Power Sound Level (dBA all units)

On-site Traffica

Wildacres Hotel Parking Lot Traffic 79 45 (Day) 9 (Night)

95 89

Highmount Hotel Parking Lot Traffic 79 31 (Day) 6 (Night)

94 87

Front-9 Village Clubhouse and Front-9 Village

Parking Lot Traffic 79 12 (Day) 2 (Night)

90 82

Highmount Lodge Parking Lot Traffic 79 3 (Day)

1 (Night) 84 79

Hotels, Conference Buildings and Clubhousesb,c

Wildacres Hotel HVAC – 490 ton 104 1 104

PTACs 61 250 85

Highmount Hotel HVAC – 275 ton 102 1 102

PTACs 61 120 82 Highmount Lodge HVAC – 30 ton 97 1 97

Wilderness Activities Center HVAC – 20 ton 97 1 97 Marlow Mansion HVAC – 30 ton 97 1 97

Front-9 Village Clubhouse HVAC – 15 ton 97 1 97 Clubhouse @Old Leach Farm HVAC – 30 ton 97 1 97

Ski Slopesd West Slope and Top Std. Pole Cat Snow Maker 99 17 111 East Slope Std. Pole Cat Snow Maker 99 13 110

Highmount Golf Clube

Fairway Mowers Fairway Mowers 96 4 102 Approach Mower Approach Mower 96 4 102

Collar/Stepcut Mower Collar/Stepcut Mower 94 1 94 Green Green Mowers 94 4 100 Greens Greens Roller 94 1 94

a Traffic level estimated assuming 10 percent of parking area capacity operates at any given time during the day and 2 percent at night (10 pm to 7 AM). b HVAC data based on square footage of common areas (excludes rooms); assumes HVAC = 400 sq. feet/ ton. HVAC reference sound levels are unshielded (unmitigated). Reference sound level source: Hoover and Keith, 1984. <200 Ton: Table 7.1; >200 ton: Equation 7-2 and Table 7-3. c PTAC Reference sound level source: Goodman 2008. d Reference sound level source: Octave band sound level measurements to the side of the Standard Polecat - K&S, 2006. e Reference sound level source: PCD. 2004

Page 35: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 5-2 Project Operation Noise Assessment and Mitigation – Nighttime; Continuous Sources

Receptor

Unmitigated Hotels

Conference Buildings

and Clubhouses

(dBA)

Unmitigated Project

Sound Level (dBA)

Ambient Sound Level (dBA)

Unmitigated Total

Sound Level (dBA)

Ambient Sound Level

Change (dBA)

Mitigation: (Control HVAC)a/

Estimated Reduction

(dBA)

Mitigated Project Sound Level (dBA)

Ambient Sound Level (dBA)

Mitigated Total

Sound Level (dBA)

Mitigated Ambient

Sound Level

Change (dBA)

FP-1 10 10 21 21 0 0 <10 21 21 0 W-1 45 45 27 45 18 -16 29 27 31 4 W-2 30 30 27 32 5 >-10 <20 27 28 1 W-3 35 35 27 36 9 -11 24 27 29 2 W-4 37 37 27 37 10 -13 24 27 29 2 W-5 39 39 27 39 12 -13 26 27 30 3 W-6 24 24 30 31 1 >-14 <20 30 30 0 W-7 32 32 30 34 4 -11 21 30 31 1 W-8 32 32 30 34 4 >-12 <20 30 30 0 W-9 27 27 30 32 2 >-7 <20 30 30 0

W-10 38 38 41 43 2 -13 25 41 41 0 W-11 42 42 30 42 12 -15 27 30 32 2 W-12 28 28 30 32 2 >-8 <20 30 30 0

Assumptions: NA – Not Applicable Ambient sound level from average nighttime Leq (Ln). a Mitigation: HVAC systems will be mitigated to reduce sound levels 16 dBA below unmitigated sound levels of typical HVAC systems (Table 5-1). Mitigation may be accomplished if 1) lower noise HVAC units are specified or 2) by shielding HVAC units. Mitigation can also be achieved through a combination of using lower noise HVACs and shielding. If shielding is used with typical HVACs, mitigation may be accomplished by placing the shield around the HVAC – within 6 feet horizontally and extending 6 feet above (except that the Highmount Lodge HVAC shield side facing Receptor W2 would extend 8 feet above the HVAC. Use of lower noise HVACs would reduce or potentially eliminated shielding needs.

Page 36: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 5-3 Project Operation Noise Assessment and Mitigation – Nighttime; Continuous and Non-continuous Sources

Receptor

Hotels Conference

Buildings and Clubhousesa

(dBA)

Unmitigated Ski Slopes

(dBA)

On-site Traffic (dBA)

Project Sound Level (dBA)

Ambient Sound Level (dBA)

Total Sound Level (dBA)

Ambient Sound Level

Change (dBA)

Additional Mitigative

Action/ Estimated Reduction

(dBA)

Mitigated Total

Sound Level (dBA)

Mitigated Ambient

Sound Level Change (dBA)

FP-1 <10 <20 <20 20 40 40 0 None needed <20

W-1 29 47 30 47 39 48 9 Reduced night operationsb:

-5 dBA 41 4

W-2 <20 31 <20 31 39 40 1 None needed 40 1 W-3 24 28 <20 29 39 39 0 None needed 39 0 W-4 24 33 <20 33 39 40 1 None needed 40 1 W-5 26 31 <20 32 39 40 1 None needed 40 1 W-6 <20 26 <20 26 37 37 0 None needed 37 0 W-7 21 28 <20 29 37 38 1 None needed 38 1 W-8 <20 27 <20 28 37 38 1 None needed 38 1 W-9 <20 22 <20 24 37 37 0 None needed 37 0

W-10 25 <20 24 28 45 45 0 None needed 45 0 W-11 27 <20 30 32 37 38 1 None needed 38 1 W-12 <20 24 <20 25 37 37 0 None needed 37 0

Assumptions: Ambient sound level from average nighttime Leq (Ln). Golf Course – Equipment not operating. Ski Slopes – Snow making equipment aligned on west side of each slope facing northeast, and not facing directly at or away from W-1 or W-2. Parking Lot – Assumes 2% of the parking lot capacity is operating and moving at 10 mph (10 PM to 7 AM) a Estimated sound levels assume HVAC mitigation as specified in Table 5-2. b No nighttime (10 PM to 7 AM) operation of the six north-most snow makers along the west slope (west and northwest of Highmount Lodge).

Page 37: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

NOISE ASSESSMENT - MODIFIED BELLEAYRE RESORT AT CATSKILL PARK

360° Engineering and Project Delivery Solutions

I:\Crossroads-Vent.13972\42106.Acoustical-Cons\Docs\Reports\Belleayre Tables_Final.Docx

Table 5-4 Project Operation Noise Assessment and Mitigation – Daytime

Receptor

Hotels Conference

Buildings and Clubhousesa

(dBA)

Golf Course (dBA)

Ski Slopes (dBA)

On-site Traffic (dBA)

Project Sound Level

(dBA)

Ambient Sound Level

(dBA)

Total Sound Level

(dBA)

Ambient Sound Level

Change (dBA)

Additional Mitigation Required

(dBA)

FP-1 <10 <20 <20 <20 20 39 39 0 None W-1 29 <20 47 36 47 50 52 2 None W-2 <20 <20 31 21 31 50 50 0 None W-3 24 23 28 <20 30 50 50 0 None W-4 24 <20 33 <20 34 50 50 0 None W-5 26 22 31 <20 32 50 50 0 None W-6 <20 <20 26 <20 27 50 50 0 None W-7 21 41 28 <20 42 50 51 1 None W-8 <20 38 27 20 39 50 50 0 None W-9 <20 38 22 22 38 50 50 0 None

W-10 25 45 <20 32 45 48 50 2 None W-11 27 45 <20 38 46 50 51 1 None W-12 <20 34 24 <20 35 50 50 0 None

Notes and Assumptions: Ambient sound level from average daytime Leq (Ld). Golf Course – Sound from mowers during daytime only. Ski Slopes – Snow makers aligned on west side of each slope facing northeast, and not facing directly at or away from W-1 or W-2. Parking Lot – Assumes 10% of the parking lot capacity is operating and moving at 10 mph. a Estimated sound levels assume HVAC mitigation as specified in Table 5-2.

Page 38: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

FIGURE 2-1

360° Engineering and Project Delivery Solutions

Noise Survey and Receptor Locations

Page 39: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

W-10

W-11

W-9W-8

W-7

W-4W-3

W-6

W-5

W-1

W-2

FP-1

W-12

ML-W1

ML-4

ML-1

ML-2

Figure 2-1. Noise Survey and Receptor Locations

LEGEND: ML-n NOISE SURVEY LOCATION (FEBRUARY 2001) W-n RECEPTOR LOCATION ML-W1 STATE FOREST PRESERVE NOISE SURVEY LOCATION (MAY 2007) FP-1 STATE FOREST PRESERVE RESERVE BOUNDARY GRID SCALE: METERS

HighmountProject Area

WildacresProject Area

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000

5200

5200

5400

5400

5600

5600

5800

5800

6000

6000

6200

6200

6400

6400

6600

6600

6800

6800

0 0

200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

2600

2600

Page 40: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

ENCLOSURE 1

360° Engineering and Project Delivery Solutions

Calibration Certificates, Field Forms, and Data

Summary Printouts

Page 41: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 42: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 43: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 44: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 45: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 46: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 47: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 48: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during
Page 49: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

ENCLOSURE 2

360° Engineering and Project Delivery Solutions

Construction Noise Barrier Calculation Diagram

Page 50: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Spreadsheet 9 (SS9) - Barrier Path Length Difference Calculation

Barrier

Receiver to Barrier Distance

Source to Barrier

Distance

Barrier Ht above

LOSPath Length Difference Source X Barrier X Receiver X Source Y Barrier Y Receiver Y

ID S in feet R in feet h in feet (delta in feet) Coordinate Coordinate Coordinate Coordinate Coordinate Coordinate

B1 150 30 10 2.0 -30 0 150 0 10.0 0

Reference: 0

0

3

6

9

12

-40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160

Bar

rier

Ht A

bove

Sou

rce/

Rec

eive

r Lin

e of

Sig

ht (f

eet)

Distance from Barrier to Source and Receiver (feet)

Barrier Path Length Difference

Source

Receiver

Barrier

Page 51: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Spreadsheet 9 (SS9) - Barrier Path Length Difference Calculation

Barrier

Receiver to Barrier Distance

Source to Barrier

Distance

Barrier Ht above

LOSPath Length Difference Source X Barrier X Receiver X Source Y Barrier Y Receiver Y

ID S in feet R in feet h in feet (delta in feet) Coordinate Coordinate Coordinate Coordinate Coordinate Coordinate

B2 360 30 10 1.8 -30 0 360 0 10.0 0

Reference: 0

Note: Assumed sound reduction for 250 Hz.

0

3

6

9

12

-50-40-30-20-10 0 10 20 30 40 50 60 70 80 90100110120130140150160170180190200210220230240250260270280290300310320330340350360370380

Bar

rier

Ht A

bove

Sou

rce/

Rec

eive

r Lin

e of

Sig

ht (f

eet)

Distance from Barrier to Source and Receiver (feet)

Barrier Path Length Difference

Source

Receiver

Barrier

Page 52: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

ENCLOSURE 3

360° Engineering and Project Delivery Solutions

CadnaA Graphical Output – Decibel Contours

Page 53: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Lodging Unit Clubhouse

Greens Mower

Greens MowerFairway Mower

Fairway Mower

Greens Mower

Fairway Mower

W7

W8

W9

W12

W10

W11Greens MowerApproach Mower

Collar MowerGreens Roller

Project Daytime OperationAssummed Golf Course Mower Positions

3850

3850

3900

3900

3950

3950

4000

4000

4050

4050

4100

4100

4150

4150

4200

4200

4250

4250

4300

4300

4350

4350

4400

4400

4450

4450

4500

4500

4550

4550

4600

4600

4650

4650

4700

4700

4750

4750

4800

4800

4850

4850

4900

490017

50

1750

1800

1800

1850

1850

1900

1900

1950

1950

2000

2000

2050

2050

2100

2100

2150

2150

2200

2200

2250

2250

2300

2300

2350

2350

2400

2400

2450

2450

2500

2500

2550

2550

> 15.0 dB > 20.0 dB > 25.0 dB > 30.0 dB > 35.0 dB > 45.0 dB > 50.0 dB > 55.0 dB > 60.0 dB > 65.0 dB > 70.0 dB

Page 54: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Highmount Hotel

Highmount Lodge

Clubhouse @ Old Leach Farm

Wilderness Activities Center

Wildacres Hotel

Lodging Unit Clubhouse

Greens Mower

Greens Mower

Fairway Mower

Fairway Mower

Greens Mower

Fairway Mower

Marlow Mansion

W2

W3W4

W5

W7

W8

W9

W12

W10

W11

FP1

Greens Mower Approach Mower

Collar MowerGreens Roller

W1

W6

Project Daytime Operation - Mitigated

1800

1800

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

> 15.0 dB

> 20.0 dB

> 25.0 dB

> 30.0 dB

> 35.0 dB

> 45.0 dB

> 50.0 dB

> 55.0 dB

> 60.0 dB

> 65.0 dB

> 70.0 dB

Page 55: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Highmount Hotel

Highmount Lodge

Clubhouse @ Old Leach Farm

Wilderness Activities Center

Wildacres Hotel

Lodging Unit Clubhouse

Greens Mower

Greens Mower

Fairway Mower

Fairway Mower

Greens Mower

Fairway Mower

Marlow Mansion

W2

W3W4

W5

W7

W8

W9

W12

W10

W11

FP1

Greens Mower Approach Mower

Collar MowerGreens Roller

W1

W6

Project Daytime Operation - Unmitigated

1800

1800

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

> 15.0 dB

> 20.0 dB

> 25.0 dB

> 30.0 dB

> 35.0 dB

> 45.0 dB

> 50.0 dB

> 55.0 dB

> 60.0 dB

> 65.0 dB

> 70.0 dB

Page 56: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Highmount Hotel

Highmount Lodge

Clubhouse @ Old Leach Farm

Wilderness Activities Center

Wildacres Hotel

Lodging Unit Clubhouse

Marlow Mansion

W2

W3W4

W5

W7

W8

W9

W12

W10

W11

FP1

W6

W1

Project Nighttime Operation - Continuous Sources; Mitigated

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000

5200

52000 0

200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

> 15.0 dB

> 20.0 dB

> 25.0 dB

> 30.0 dB

> 35.0 dB

> 45.0 dB

> 50.0 dB

> 55.0 dB

> 60.0 dB

> 65.0 dB

> 70.0 dB

Page 57: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Highmount Hotel

Highmount Lodge

Clubhouse @ Old Leach Farm

Wilderness Activities Center

Wildacres Hotel

Lodging Unit Clubhouse

Marlow Mansion

W2

W3W4

W5

W7

W8

W9

W12

W10

W11

FP1

W6

W1

Project Nighttime Operation - Continuous Sources; Unmitigated

1800

1800

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

> 15.0 dB

> 20.0 dB

> 25.0 dB

> 30.0 dB

> 35.0 dB

> 45.0 dB

> 50.0 dB

> 55.0 dB

> 60.0 dB

> 65.0 dB

> 70.0 dB

Page 58: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Highmount Hotel

Highmount Lodge

Clubhouse @ Old Leach Farm

Wilderness Activities Center

Wildacres Hotel

Lodging Unit Clubhouse

Marlow Mansion

W2

W3W4

W5

W7

W8

W12

W10

W11

FP1

W9

Project Nighttime Operation - Mitigated

W1

W6

1800

1800

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

> 15.0 dB

> 20.0 dB

> 25.0 dB

> 30.0 dB

> 35.0 dB

> 45.0 dB

> 50.0 dB

> 55.0 dB

> 60.0 dB

> 65.0 dB

> 70.0 dB

Page 59: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

Highmount Hotel

Highmount Lodge

Clubhouse @ Old Leach Farm

Wilderness Activities Center

Wildacres Hotel

Lodging Unit Clubhouse

Marlow Mansion

W2

W3W4

W5

W7

W8

W12

W10

W11

FP1

W9

Project Nighttime Operation - Unmitigated

W1

W6

1800

1800

2000

2000

2200

2200

2400

2400

2600

2600

2800

2800

3000

3000

3200

3200

3400

3400

3600

3600

3800

3800

4000

4000

4200

4200

4400

4400

4600

4600

4800

4800

5000

5000200

200

400

400

600

600

800

800

1000

1000

1200

1200

1400

1400

1600

1600

1800

1800

2000

2000

2200

2200

2400

2400

> 15.0 dB

> 20.0 dB

> 25.0 dB

> 30.0 dB

> 35.0 dB

> 45.0 dB

> 50.0 dB

> 55.0 dB

> 60.0 dB

> 65.0 dB

> 70.0 dB

Page 60: APPENDIX 20 CONSTRUCTION AND OPERATIONS NOISE STUDY 20 - Noise Assessment.pdf · Rock Crushing at Highmount – Unmitigated sound from rock crushing near the Highmount Hotel during

360° Engineering and Project Delivery Solutions

All materials printed on recycled paper.