Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s...

236
162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division: Screening Questions Yes No Remarks A. PROJECT SITING IS THE PROJECT AREA ADJACENT TO OR WITHIN ANY OF THE FOLLOWING ENVIRONMENTALLY SENSITIVE AREAS? Cultural heritage site X No cultural heritage site is located within the road ROW or vicinity. Protected Area X None of the project road is inside or adjacent to any notified protected area. However, eleven Road have found open forest patches are present in few stretches along project roads. Wetland X None. Mangrove X None Estuarine X None Buffer zone of protected area X None Special area for protecting biodiversity X No special biodiversity area is located within the project area. B. POTENTIAL ENVIRONMENTAL IMPACTS WILL THE PROJECT CAUSE… encroachment on historical/cultural areas; disfiguration of landscape by road embankments, cuts, fills, and quarries? X No encroachment of historical places. However, some religious structures exist along the project road which may get partially impacted. Disfiguration of landscape is not envisaged since it is expansion/reconstruction of existing roads without any new bypass hence involving large scale cut and fills. Quarry material will be procured from existing licensed quarries. Opening and operation of new quarry, if needed will follow consent conditions of Pollution Control Board. encroachment on precious ecology (e.g. sensitive or protected areas)? X No National Parks, wildlife sanctuaries or similar eco-sensitive areas along the project road India / Madhya Pradesh District Roads II Sector Project (23 Road Sections) SARD - SATC

Transcript of Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s...

Page 1: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

162 Appendix 1

Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist

Country/Project Title:

Sector Division:

Screening Questions Yes No Remarks

A. PROJECT SITING IS THE PROJECT AREA ADJACENT TO OR WITHIN ANY OF THE FOLLOWING ENVIRONMENTALLY SENSITIVE AREAS?

Cultural heritage site

X No cultural heritage site is located within the road ROW or vicinity.

Protected Area X None of the project road is inside or adjacent to any notified protected area. However, eleven Road have found open forest patches are present in few stretches along project roads.

Wetland X None.

Mangrove X None

Estuarine X None

Buffer zone of protected area X None

Special area for protecting biodiversity

X No special biodiversity area is located within the project area.

B. POTENTIAL ENVIRONMENTAL IMPACTS

WILL THE PROJECT CAUSE…

encroachment on historical/cultural areas; disfiguration of landscape by road embankments, cuts, fills, and quarries?

X No encroachment of historical places. However, some religious structures exist along the project road which may get partially impacted. Disfiguration of landscape is not envisaged since it is expansion/reconstruction of existing roads without any new bypass hence involving large scale cut and fills. Quarry material will be procured from existing licensed quarries. Opening and operation of new quarry, if needed will follow consent conditions of Pollution Control Board.

encroachment on precious ecology (e.g. sensitive or protected areas)?

X No National Parks, wildlife sanctuaries or similar eco-sensitive areas along the project road

India / Madhya Pradesh District Roads II Sector Project (23 Road Sections)

SARD - SATC

Page 2: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 1 163

Screening Questions Yes No Remarks

alteration of surface water hydrology of waterways crossed by roads, resulting in increased sediment in streams affected by increased soil erosion at construction site?

X Project area is drained by a No. of rivers/Nallah and also intersecting the project roads. Bridge construction on perennial rivers will be done during lean flow period. In some cases minor channels may be diverted for a very short period and will be bring back to its original course immediately after construction. Partial loss of some ponds is also envisaged. Large numbers of borrow areas are proposed to be converted into ponds. Adequate measures like retaining walls/breast walls have been proposed to avoid/reduce siltation in the water bodies/ponds close to the alignment.

deterioration of surface water quality due to silt runoff and sanitary wastes from worker-based camps and chemicals used in construction?

X Adequate sanitary facilities and drainage in the workers camps will help to avoid this possibility. as the construction activity in this project will not contain any harmful ingredients, no impact on surface water quality is anticipated.

increased local air pollution due to rock crushing, cutting and filling works, and chemicals from asphalt processing?

X Air pollution level is likely to be increased for short duration during construction period. Appropriate distance from settlement area and wind direction may be taken into account to locate air polluting facility like stone crushing unit etc. use of environment friendly equipments/machineries will help to reduce air pollution.

risks and vulnerabilities related to occupational health and safety due to physical, chemical, biological, and radiological hazards during project construction and operation during project construction and operation?

X Workers may get exposed to dust and noise during construction activities. However the exposure levels are likely to be short and insignificant. Workers will be provided requisite PPEs to minimise such exposure and associated harmful occupational health effects. Traffic on roads is expected to be low and as such, no occupational health hazard is anticipated during operation phase.

noise and vibration due to blasting and other civil works?

X Blasting is not involved. Ambient noise level is expected to increase in the range of 80-90 db (a) due to various construction activities, maintenance workshops, and earthmoving equipment. Although this level of noise exceeds national standards, their occurrence will be intermittent and co-terminus with the project construction.All stationary noise making equipment will be installed with acoustic enclosures. Timings of noise construction activities will be regulated near sensitive receptors. Multi-layered plantation proposed.

dislocation or involuntary resettlement of people?

X Extent of impact being assessed

dislocation and compulsory resettlement of people living in right-of-way?

X Extent of impact being assessed

Page 3: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

164 Appendix 1

Screening Questions Yes No Remarks

disproportionate impacts on the poor, women and children, Indigenous Peoples or other vulnerable groups?

X Extent of impact being assessed

other social concerns relating to inconveniences in living conditions in the project areas that may trigger cases of upper respiratory problems and stress?

X Deterioration in ambient air quality will be localized and temporarily during construction activity. The project area is largely located in open areas except some air pollution units at Maharajpur and Gagha urban area. Extensive plantation along the highway and improved road conditions will improve the air quality of the area.

hazardous driving conditions where construction interferes with pre-existing roads?

X Suitable traffic management plan will be designed and implemented by the contractor to prevent any hazardous driving condition in above situations.

poor sanitation and solid waste disposal in construction camps and work sites, and possible transmission of communicable diseases (such as STI's and HIV/AIDS) from workers to local populations?

X Proper provisions for sanitation, health care and solid waste disposal facilities will be available in the contract documents to avoid such possibility. workers will be made aware about communicable diseases

creation of temporary breeding habitats for diseases such as those transmitted by mosquitoes and rodents?

X No such condition is anticipated. Most of borrow areas are likely to be converted into ponds. Fish culture will be promoted in these ponds which will naturally restrict mosquito breeding.

accident risks associated with increased vehicular traffic, leading to accidental spills of toxic materials?

X Adequate safety measures will be adopted to avoid such conditions.

increased noise and air pollution resulting from traffic volume?

X Increase in noise and air pollution is expected during construction phase. Adequate mitigation measures will be adopted to minimise them.During operation phase, the main source of noise and air will be traffic. Improved road conditions, extensive plantation will help reduce the noise and air impact. Moreover, the alignment mostly passes through open agricultural land which will provide adequate dispersion of gaseous emission.If measures suggested for noise sensitive receptors prove inadequate, solid noise barrier will be placed.

increased risk of water pollution from oil, grease and fuel spills, and other materials from vehicles using the road?

X This is expected from accidental spillage. Adequate safety provisions have been proposed to avoid such situation.

social conflicts if workers from other regions or countries are hired?

X Most of the workers will be from local areas and hence such conflict is not anticipated.

Page 4: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 1 165

Screening Questions Yes No Remarks

large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?

X Workers will be mostly from local villages. Worker from remote places will be provided with adequate facility. The ratio of local and outside workers will be such balanced that there is minimum burden on existing social infrastructures and services.

risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel and other chemicals during construction and operation?

X IEE will outline such anticipated risks and recommend necessary mitigative measures to avoid them.

community safety risks due to both accidental and natural causes, especially where the structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation and decommissioning.

X Adequate measures have been adopted to mitigate such risks. Adequate awareness will be created amongst people and workers through information disclosure, safety signage and public consultation about safety aspects.

Climate Change and Disaster Risk Questions

Yes No Remarks

Is the Project area subject to hazards such as earthquakes, floods, landslides, tropical cyclone winds, storm surges, tsunami or volcanic eruptions and climate changes

X Project area is located in moderate damage risk zone w.r.t seismicity (Zone III). All civil structures have been designed as per relevant IS Codes corresponding to seismic zones. The study area being predominantly rolling does not have flood problem. However, flash floods occurred sometime in district including some parts of project. All structure have been designed for 50 yr return period with anticipated risk of rarer flood generally of next higher frequency i.e. 100 yr return period flood on the designed structure. Project Area is not vulnerable to landslides, tropical cyclone winds, storm surges, tsunami or volcanic eruptions. However, Many studies for the state show that the Madhya Pradesh is tending towards precarious situation due to climate sensitivity and vulnerability, combined with low adaptive capacity. The state is already suffering due to its high dependence on mineral resources. Further the forest and water resources in the State are facing threat due to industrial and urban growth and being uneven in distribution both temporally and spatially. Hence the challenge of climate change calls for appropriate, evidence based and coherent policy response, followed by the adequate action that can help reduce its vulnerability and build resilience of the various sectors of the state in the context of climate change impacts. (Source: Madhya Pradesh- Action Plan for Climate Change, Govt. of Madhya Pradesh, 2013)

Page 5: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

166 Appendix 1

Could changes in temperature, precipitation, or extreme events patterns over the Project lifespan affect technical or financial sustainability (eg. increased erosion or landslides could increase maintenance costs, permafrost melting or increased soil moisture content could affect sub-grade).

X All provisions as per IRC codes and international best practices have been made in the road design to avoid erosion and damage to sub grade based on historical climatic data.

Are there any demographic or socio-economic aspects of the Project area that are already vulnerable (eg. high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)?

X Increase in marginalization is not envisaged. High rate of urbanization is witnessed and it has outpaced the population growth trend in the state due to migration from rural to urban centers. During 2001-2011, the urban population expanded by 18.22%, this is in line with the decadal national urban population growth rate of 31.8% (Census of India 2011). However, migration in the project area is comparatively low due to proximity to industrial township ofMandla

Could the Project potentially increase the climate or disaster vulnerability of the surrounding area (e.g., by encouraging settlement in areas that will be more affected by floods in the future, or encouraging settlement in earthquake zones)?

X Displaced persons will be resettled at nearby places which are in moderate earthquake and no flood zone.

Page 6: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 1 167

A Checklist for Preliminary Climate Risk Screening

Country/Project Title:

Sector :

Subsector:

Division/Department:

Screening Questions Score Remarks14

Location and Design of project

Is siting and/or routing of the project (or its components) likely to be affected by climate conditions including extreme weather related events such as floods, droughts, storms, landslides?

0

Would the project design (e.g. the clearance for bridges) need to consider any hydro-meteorological parameters (e.g., sea-level, peak river flow, reliable water level, peak wind speed etc.)?

0

Materials and Maintenance

Would weather, current and likely future climate conditions (e.g. prevailing humidity level, temperature contrast between hot summer days and cold winter days, exposure to wind and humidity hydro-meteorological parameters likely affect the selection of project inputs over the life of project outputs (e.g. construction material)?

0

Would weather, current and likely future climate conditions, and related extreme events likely affect the maintenance (scheduling and cost) of project output(s) ?

0

Performance of project outputs

Would weather/climate conditions, and related extreme events likely affect the performance (e.g. annual power production) of project output(s) (e.g. hydro-power generation facilities) throughout their design life time?

0

Options for answers and corresponding score are provided below:

Response Score

Not Likely 0

Likely 1

Very Likely 2

Responses when added that provide a score of 0 will be considered low risk project. If adding all responses will result to a score of 1-4 and that no score of 2 was given to any single response, the project will be assigned a medium risk category. A total score of 5 or more (which include providing a score of 1 in all responses) or a 2 in any single response, will be categorized as high risk project.

Result of Initial Screening (Low, Medium, High):______Low_____

Other Comments:______________________________________________________________

_________________________________________________________________________

Prepared by: ________________

14

If possible, provide details on the sensitivity of project components to climate conditions, such as how climate parameters are considered in design standards for infrastructure components, how changes in key climate parameters and sea level might affect the siting/routing of project, the selection of construction material and/or scheduling, performances and/or the maintenance cost/scheduling of project outputs.

Page 7: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

168 Appendix 2

Appendix 2: List of Proposed Road Sections and Packages

No. of Packages

No. of Roads District Length (Km)

Package Length (km)

Package 4 Sanwer Chadravatiganj, Gautampura road Indore 33.94 33.94

Package 6

Podar Barha Sukhakhairi Road Narsinghpur 23.57 70

Gadarwara-Gotetoria road Narsinghpur 13.57

Kareli-Singpur- Dangidhana Road Narsinghpur 32.86

Package 12

Khairlianji-Agasi Road Balaghat 28.96 87.96

Lal Barra- Samnapur Road Balaghat 8.4

Rampayali-Garra Chouki road Balaghat 27.56

SitapathaourMahakaipar-Goreghat Road Balaghat 23.04

Package 15

Teothar-Shakargarh Road Rewa 14.6 48.44

Bahera Dabar Piprahi Jarkud Road Rewa 19.7

Nai Garhi Garh Road Rewa 14.14

Subtotal 240.34 240.36

Package 16

Kharamseda Kirhai Ramgarh Road Satna 34.35 78.35

Jharkua Raigaon Karsara Road Satna 23.95

Bhatura Bhadpur Barrakhurd Road Satna 20.05

Package 18

Parsona Mada Road Singrauli 24.39 75.7

Ramgarh Mada Road Singrauli 19.87

Jhurai – Sarai Road Singrauli 31.44

Package 17 Harphari Khaira Misirgawan via Shivpurva Road Singrauli 25.99 48.66

Chitrangi-Garhwa Road Singroli 22.67

Package 20

Anuppur Jaitpur Road Anuppur & Shahdol

36.66 100.09

Gohparu Rasmohni Budhar (via Bathiya) Road Shahdol 39.94

Pasgarhi Devri Janakpur Road Shahdol 23.49

Package 19

Sohagpur – Manpur Road Umaria 59.4 59.4

Subtotal 362.2 362.2

Package 7

Samnapur-Bilhera-NanhiDeori-Narayanpur Road

Sagar 45.4 84.91

Maharajpur-Sahejpur Road Sagar 24.45

Kesli-Sahejpur Road Sagar 15.06

Package 8

Garhpahera-Dhamoni Road Sagar 35.33 88.96

Barodiya-Dhamoni Road Sagar 19.81

Noniya-Madanpur Road Sagar 2

Rajwas – Khurai (MDR) Road Sagar 31.82

Package 10

Chhatarpur-Bikrampur-Rajnagar Road Chhatarpur 10.24 102.17

Bariyachoki-Lugasi-GarhiMalhera Road Chhatarpur 15.54

Rajnagar-Bachhon Road Chhatarpur 23.85

Bamitha (Rajnagar)-Dumra Road Chhatarpur 28.07

Khaptiya-banspahadi Road Chhatarpur 24.47

Package 11

Barghat-Kanhiwada road Seoni 21.79 78.62

Dharna-Asta-Dondiwada-Dharmakua Seoni 26.23

Waraseoni-Katangi road Balaghat 30.6

Package 1 Khatakia to Suthaliya via NH-3, Kumbhraj, Barod, Mragwas, Batawda, Chanchoda, Binaganj, Teligaon

Guna 70.79 70.79

Package 2 Sirsod-Pichhore road Shivapuri 31.24 57.57

Narwar-Chitori to Amola road Shivapuri 26.33

Package 3

Mungawali-Malahargarh road Ashok Nagar 16.72 62.31

Piprod-Thubon road Ashok Nagar 7.74

Belai-Kareela Mata Mandir road Ashok Nagar 17.72

Page 8: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 2 169

No. of Packages

No. of Roads District Length (Km)

Package Length (km)

Bhounrasa-Malhargarh road Vidisha 20.13

Package 14

Chourai-Panjara-Chand road Chindwara 17.22 76.52

Chand-Bichhua-Khamarpani road Chindwara 59.3

Subtotal 621.85 621.85

Package 5

Bijawar-Kataphod—Satwas-Khategaon Road Ujjain 55.17 55.17

Package 8 (extra road)

Rajwas – Khurai (MDR) Road Sagar 31.82 31.82

Total Subtotal 1279.56 1279.56

Note: Totals may not exactly match because of rounding

Page 9: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

170 Appendix 3

Appendix 3: Comparison of World Bank and GoI Ambient Air Quality Standards

A comparison between the ambient air quality requirements between the World Bank (WB) Environment, Health and Safety (EHS) guidelines and the National Ambient Air Quality standards (NAAQS) under the Air (Prevention and Control of Pollution) Act, 1981 of GOI as given in table below shows that the NAAQS has requirements on three more parameters (Pb, Co and NH3) in comparison to the WB EHS. The NAAQS has differentiated standards for two types of areas: i) industrial, residential, rural and other areas and ii) ecologically sensitive areas. The WB EHS has guidelines values which are the required standards but allows for gradual compliance to the guideline values through staged interim targets. Most WB EHS guideline requirements are more stringent than NAAQS except for the NOx one year average in ecologically sensitive areas where the NAAQS requirements are more stringent.

Table 52: Ambient Air Quality standards of WB EHS Vs. the GOI NAAQS

Ambient Air Quality

Parameter

Averaging Period

WB Guideline Value GOI Standards for Industrial,

Residential, Rural and Other Areas

GoI Ecologically Sensitive Area

(notified by Central Government)

Sulfur dioxide

(SO2) (ug/m3)

24-hr

125 (Interim target 1)

80

80

50 (Interim target 2)

20 (guideline)

10 min 500 (guideline)

Annual None 50 20

Nitrogen dioxide (NO2) (ug/m

3)

1 Year 40 (guideline) 40 30

24 Hour None 80 80

1 Hour 200 (guideline)

PM10

(ug/m3)

1 Year

70 (Interim target 1)

50 (Interim target 2)

30 (Interim target 3)

20 (guideline) 60 60

24-hr

150 (Interim target 1)

100 (Interim target 2)

75 (Interim target 3)

50 (guideline) 100 100

PM2.5 (ug/m3) 1 year

35 (Interim target 1)

25 (Interim target 2)

15 (Interim target 3)

10 (guideline) 40 40

24-Hour

75 (Interim target 1)

50 (Interim target 2)

37.5 (Interim target 3)

25 (guideline) 60 60

Ozone (O3) (ug/m

3)

8-hr daily max 160 (Interim target 1)

100 (guideline) 100 100

Lead (Pb) µg/m

3)

Annual 0.5 0.5

24 hours 1.0 1.0

Carbon Monoxide (CO) µg/m

3

8 hours 2000 2000

1 hour 4000 4000

Ammonia (NH3) µ/m

3

Annual 100 100

24 hours 400 400

Page 10: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 4 171

Appendix 4: Comparison of WB EHS and GoI Ambient Noise Level Standards

A comparison on noise level requirements between the WB EHS guidelines and the NAAQS under the Air (Prevention and Control of Pollution) Act, 1981 of GOI as given in table B shows that the required levels are equal for residential, institutional and educational areas. The NAAQS requirements for commercial areas are more stringent while the WB EHS requirement for daytime noise in industrial area is more stringent.

Table 53: Ambient Noise level standards of WB EHS Vs. the GOI NAAQS

Receptor WB EHS GOI NAAQS

Daytime Nighttime Daytime Nighttime

7:00-22:00 22:00-7:00 6:00-22.00 22:00-6:00

Residential 55 45 55 45

Institutional; educational None None

Industrial 70 70 75 70

Commercial 65 55

Silence Zone None None 50 40

Page 11: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

172 Appendix 5

Appendix 5: Indian Standard Drinking Water Specification: II 10500:1991

Sl. No.

Substance/ Characteristic Desirable Limit Permissible

limit Remarks

1 Colour, Hazen units, Max 5 25 Extended to 25 if toxic substance are not suspected in absence of alternate sources

2 Odour Unobjectionable a) Test cold and when heated

b) Test at several dilution

3 Taste Agreeable Test to be conducted only after safety has been established

4 Turbidity NTU, Max 5 10

5 pH value 6.5 to 8.5 No relaxation

6 Total Hardness (as CaCO3 mg/lit)

600 600

7 Iron (as Fe mg/lit, Max 0.3 1.0

8 Chlorides (as Cl mg/lit Max 250 1000

9 Residual Free Chlorine, mg/lit Max

0.2

To be applicable only when water is chlorinated. Treated at consumer end. When protection against viral infection is required, it should be Min 0.5 mg/lit

10 Dissolved Solids mg/l, Max 500 2000

11 Calcium (as Ca) mg/l, Max 75 200

12 Copper (as Cu) mg/l, Max 0.05 1.5

13 Manganese (Mn) mg/l Max 0.1 0.3

14 Sulphate (As SO4), Max 200 400 May be extended up to 400 provided (as Mg) does not exceed 30

15 Nitrate (as NO3) mg/l, Max 45 100

16 Fluoride (as F) mg/l, Max 1.0 1.5

17 Phenolic Compounds (as C6H6OH) mg/l Max

0.001 0.002

18 Arsenic (as As mg/l 0.05 No relaxation To be tested when pollution is suspected

19 Lead (as Pb) mg/l 0.05 No relaxation

20 Anionic Detergents (as MBAS) mg/l

0.2 1.0

21 Chromium (as Cr) mg/l 0.05 1.0 To be tested when pollution is suspected

22 Mineral Oil mg/l 0.01 0.03

23 Alkalinity mg/l 200 600

24 Total Coliform 95% of the sample should not contain coliform in 100 ml. 10 coliform

/100 ml

Page 12: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 173

Appendix 6: Record Of Public Consultations

A. Photo Plat

1. Garhpahera – Dhamoni Road

Group Discussion along Garhpahera

Dhamoni Road Household Survey on Garhpahera

Dhamoni Road

Key Informant Interview Garhpahera-

Dhamoni Road Household Survey (Women) on

Garhpahera-Dhamoni Road

2. Barodiya Dhamoni Road

Group Discussion along BarodiyaDhamoni Road

Household Survey on BarodiyaDhamoni Road

Page 13: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

174 Appendix 6

Key Informant Interview

onBarodiyaDhamoni Road Household Survey (Women) on

BarodiyaDhamoni Road

3. Noniya - Madanpur Road

Group Discussion along Noniya

Madanpur Road Household Survey on Noniya Madanpur

Road

Key Informant Interview On Noniya

Madanpur Road Household Survey (Women) on Noniya

Madanpur Roa

Page 14: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 175

4. Samnapur - Bilhara - Nanhi Devri - Narayanpur Road

Group Discussion along Samnapur

Bilhara Nanhi Devri Narayanpur Road Household Survey on Samnapur Bilhara

Nanhi Devri Narayanpur Road

Key Informant Interview On Samnapur Bilhara Nanhi Devri -Narayanpur Road

Household Survey (Women) on Samnapur Bilhara Nanhi Devri-

Narayanpur Road

5. Kesli - Sahejpur Road

Group Discussion along Kesli Sahejpur

Road Household Survey on Kesli Sahejpur

Road

Page 15: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

176 Appendix 6

Key Informant Interview On Kesli

Sahejpur Road Household Survey (Women) on Kesli

Sahejpur Road

6. Maharajpur - Sahejpur Road

Group Discussion along Maharajpur

Sahejpur Road Household Survey on Maharajpur

Sahejpur Road

Key Informant Interview On Maharajpur

Sahejpur Road Household Survey (Women) on

Maharajpur Sahejpur Road

Page 16: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 177

7. Bariya Chowki Lugasi Garhi Malhera Road

Group Discussion along Bariya Chowki

Lugasi Garhi Malhera Road Household Survey on Bariya Chowki

Lugasi Garhi Malhera Road

Key Informant Interview On Bariya Chowki Lugasi Garhi Malhera Road

Household Survey (Women) on Bariya Chowki Lugasi Garhi Malhera Road

8. Khapatiya - Banspahadi Road

Group Discussion along Khapatiya

Banspahadi Road Household Survey on Khapatiya

Banspahadi Road

Page 17: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

178 Appendix 6

Key Informant Interview on Khapatiya

Banspahadi Road Household Survey (Women) on Khapatiya

Banspahadi Road

9. Chattarpur – Bikrampur - Rajnagar Road

Group Discussion along Chattarpur

Bikrampur Rajnagar Road Household Survey on Chattarpur

Bikrampur Rajnagar Road

Key Informant Interview on Chattarpur

Bikrampur Rajnagar Road Household Survey (Women) on

Chattarpur Bikrampur Rajnagar Road

Page 18: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 179

10. Rajnagar – Bachhon Road

Group Discussion along Rajnagar

Bachhon Road Household Survey on Rajnagar Bachhon

Road

Key Informant Interview on Rajnagar

Bachhon Road Household Survey (Women) on Rajnagar

Bachhon Road

11. Bamitha (Rajnagar) - Dumra Road

Page 19: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

180 Appendix 6

Group Discussion along Bamitha Dumra Road

Household Survey on Bamitha Dumra Road

Key Informant Interview On Bamitha Dumra Road

Page 20: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 181

B. Attendance Sheets

a) Garhpehra – Dhamoni Road

i. Dhamoni Village FGD Female Group

Page 21: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

182 Appendix 6

ii. Dhamoni Village FGD Mixed Group

Page 22: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 183

iii. Garpehra Mohal Village FGD Female Group

Page 23: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

184 Appendix 6

iv. Garpehra Mohal Village Mixed Group

Page 24: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 185

iv. Kudari Village FGD Female Group

Page 25: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

186 Appendix 6

V. Kudari Village Mixed Group

Page 26: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 187

vi. Kull Village FGD Female Group

Page 27: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

188 Appendix 6

vii. Kull Village Mixed Group

Page 28: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 189

b) Barodiya – Dhamoni Road

i. Dhamoni Village FGD Female Group

Page 29: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

190 Appendix 6

ii. Dhamoni Village Mixed Group

Page 30: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 191

iii. Noniya Village FGD Female Group

Page 31: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

192 Appendix 6

iv. Noniya Village Mixed Group

Page 32: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 193

v. Sesai Saji Village FGD Female Group

Page 33: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

194 Appendix 6

vi. Sesai Saji Village Mixed Group

Page 34: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 195

C) Noniya – Madanpur Road

i) Noniya Village FGD Female Group

Page 35: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

196 Appendix 6

ii) Noniya Village Mixed Group

Page 36: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 197

d) Samnapur - Bilhara - Nanhi Devri - Narayanpur Road

i) Amoda Village FGD Female Group

Page 37: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

198 Appendix 6

iii) Bilhara Village FGD Female Group

Page 38: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 199

iv) Bilhara Village Mixed Group

Page 39: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

200 Appendix 6

v) Chowka Village FGD Female Group

Page 40: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 201

vi) Chowka Village Mixed Group

Page 41: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

202 Appendix 6

vii) Manjila Village FGD Female Group

Page 42: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 203

viii) Manjila Village Mixed Group

Page 43: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

204 Appendix 6

ix) Nittari Village FGD Female Group

Page 44: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 205

x) Nittari Village Mixed Group

Page 45: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

206 Appendix 6

Page 46: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 207

xi) Padariya Village FGD Female Group

Page 47: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

208 Appendix 6

xiii) Samnapur Village FGD Female Group

Page 48: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 209

xiv) Samnapur Village Mixed Group

Page 49: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

210 Appendix 6

xv) Singna Village FGD Female Group

Page 50: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 211

xvi) Singna Village Mixed Group

Page 51: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

212 Appendix 6

e) Kesli – Sahajpur Road

i) Chowka Village FGD Female Group

Page 52: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 213

ii) Chowka Village Mixed Group

Page 53: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

214 Appendix 6

Page 54: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 215

iii) Sahejpur Village FGD Female Group

Page 55: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

216 Appendix 6

iv) Sahejpur Village Mixed Group

Page 56: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 217

f) Maharajpur –Sahejpur Road

i) Sahejpur Village FGD Female Group

Page 57: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

218 Appendix 6

iii) Saraivan Village FGD Female Group

Page 58: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 219

iv) Saraivan Village Mixed Group

Page 59: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

220 Appendix 6

v) Rasena Village FGD Female Group

Page 60: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 221

vi) Rasena Village Mixed Group

Page 61: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

222 Appendix 6

vii) Dhobi Village FGD Female Group

Page 62: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 223

viii) Dhobi Village Mixed Group

Page 63: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

224 Appendix 6

h) Bariya Choki – Lugasi – Garhi Malhera

i) Lugasi Village FGD Female Group

Page 64: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 225

ii) Lugasi Village mix Group

Page 65: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

226 Appendix 6

iii) Garhi Malhera Village FGD Female Group

Page 66: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 227

iv) Garhi Malhera Village mixed Group

Page 67: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

228 Appendix 6

i) Khaptiya-Banspahadi Road

i) Khaptiya Village FGD Female Group

Page 68: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 229

ii) Khaptiya Village mixed Group

Page 69: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

230 Appendix 6

iii) Ragoli Village FGD Female Group

Page 70: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 231

iv) Ragoli Village mixed Group

Page 71: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

232 Appendix 6

j) Chhatarpur – Bikrampur – Rajnagar

i) Bhouska Village FGD Female Group

Page 72: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 233

ii) Bhouska Village mixed Group

Page 73: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

234 Appendix 6

iii) Pai Village FGD Female Group

Page 74: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 235

iv) Pai Village Mixed Group

Page 75: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

236 Appendix 6

v) Rajnagar Village FGD Female Group

Page 76: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 237

vi) Rajnagar Village Mixed Group

Page 77: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

238 Appendix 6

k) Rajnagar – Bachhon Road

i) Rajnagar Village FGD Female Group

Page 78: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 239

ii) Rajnagar Village Mixed Group

Page 79: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

240 Appendix 6

iii) Bandargarh Village FGD Female Group

Page 80: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 241

iv) Bandargarh Village mixed Group

Page 81: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

242 Appendix 6

v) Bila Village FGD Female Group

Page 82: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 243

vi) Bila Village Mixed Group

Page 83: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

244 Appendix 6

v) Kurela Village FGD Female Group

Page 84: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 245

v) Kurela Village mixed Group

Page 85: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

246 Appendix 6

l) Bamitha (Rajnagar) – Dumra Road

i) Rajnagar Village FGD Female Group

Page 86: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 247

ii) Rajnagar Village Mixed Group

Page 87: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

248 Appendix 6

iii) Khajwa Village FGD Female Group

Page 88: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 249

iv) Khajwa Village mixed Group

Page 89: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

250 Appendix 6

v) Maniya Village FGD Female Group

Page 90: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 251

vi) Maniya Village mixed Group

Page 91: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

252 Appendix 6

vii) Kishanpura Village FGD Female Group

Page 92: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 6 253

viii) Kishanpura Village Mixed Group

Page 93: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

254 Appendix 7

Appendix 7: GRM Information Sheet

Page 94: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 7 255

Page 95: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

256 Appendix 7

Page 96: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 7 257

Page 97: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

258 Appendix 7

Page 98: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 259

Appendix 8: Environmental Management and Monitoring Plan

Environmental Management Plan (Contract Package No. 1)

This EMP is applicable to three subproject road included in Civil Works Contract Package No 1 i.e. . 1) Katakiya-Kumbraj-Chanchoda Road

EnvironmentalIssue / component

RemedialMeasure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction andDesignStage

1. Alignment

1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no. of cross drainage structures based on drainage pattern around the alignment.

Design requirement

Throughout the alignment Design of both cross & side drains,

No. of CD structures & their spans

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC / CSC

1.2 Loss of 898 trees and vegetation cover

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 8980 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment No. of trees to be cut

Observation,

Included in construction

cost

Design Consultant

MPRDC / CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement

Location of temples, schools and other sensitive receptors along the project roads.

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

1.4 Safety along the proposed alignment

Provis ion of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement, IRC-67 for road signs, IRC-73 for geometric

design standards, IRC-119 for traffic safety, IRC-75 for

slope stabilisation

in high embankment

Places where height of embankment is more than 3.00 m

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC / CSC

2. Natural Hazards

Page 99: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

260 Appendix 8

EnvironmentalIssue / component

RemedialMeasure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction andDesignStage

1. Alignment

2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC /CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road

construction in water logged

areas and

IRC-75 for design of high embankment

Design of both cross & side drains, 80 no. of Pipe Culverts & 07 no slab/box culverts 03 no & size of Hume pipes structures proposed.

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC /CSC

3. Shifting of utility structures

3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement

The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ CSC

MPRDC /CSC

Page 100: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 261

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge works, Air

(P & CP) Act 1974 and Central

Motor and Vehicle Act

1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC/ CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981

(Amended1987) and

Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC /CSC

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Time regulation near residential, built up and forest areas construction shall be restricted to daylight hours.

Legal requirement

Noise

Pollution (Regulation and Control) Rules, 2000

and amendments

Thereof + Clause No 501.8.6.

MORT&H Specification

s for Road and

Bridge works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise barriers has been proposed in total 1640m length (700m in KRM, 740m in JRK and 200m in BB road)

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC/ CSC

Page 101: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

262 Appendix 8

Environmental

Issue/ component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement

Throughout the project section and

Borrow areas (Km 2.5, Km 7.5 & Km 11 of KRM road , Km 13, Km 17.5, Km 19, Km 22.5 & Km 23.9 of JRK road and Km 0.3, Km 7.55, Km 9.75 & Km 15 of BB road)

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC/ CSC

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works,

Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC/ CSC

3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

IRC-10 for guidelines on borrow areas

and for quarries, Environmental Protection Act

and Rules, 1986; Water Act, Air

Act, Clause No. 305.2.2

Borrow sites location (Km 2.5, Km 7.5 & Km 11 of KRM road, Km 13, Km 17.5, Km 19, Km 22.5 & Km 23.9 of JRK road and Km 0.3, Km 7.55, Km 9.75 & Km 15 of BB road). These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor

MPRDC/ CSC

Page 102: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 263

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

MORT&H Specifications for Road and Bridge works Guidelines V for Borrow Areas management

Complaints from local people.

,

3.4 Quarry operations

Aggregates will be sourced from existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H

Specifications for Road and Bridge

works, Guidelines VI for

quarry area management

Quarry area locations

Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC/ CSC

3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC/ CSC

Page 103: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

264 Appendix 8

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement

Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC/ CSC

4. WaterResources 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

4. WaterResources

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010

EP Act 1986 MORT&H

Specifications for Road and

Bridge works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

Page 104: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 265

Environmental Issue/ component

Remedial Measure Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications

for Road and

Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

5. Flora and Fauna

5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

Forest Conservation

Act 1980, IRC SP: 21 and

IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation cost is included in project costs.

Relevant agency

specialized in afforestation

MPRDC /CSC

Page 105: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

266 Appendix 8

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage In the event of design changes during the

construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

6. ConstructionCamps 6.1 Impact associated with location

All camps should maintain minimum distance from following:

1) 500 m from habitation, 2) 500 m from forest areas where possible, 3) 500 m from water bodies where possible, 4) 500 m from through traffic route where

possible.

Design Requirement

All construction camps

Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to CSC prior to their construction. The construction shall commence only after approval of CSC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

The building and other construction

workers (Regulation of

Employment and Conditions of

Service) Act 1996 and The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof

All construction camps

Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

Page 106: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 267

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and

MORT&H guidelines

At all dumping sites

Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

8. TrafficManagementandSafety

8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

Design requirement and

IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC /CSC

Page 107: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

268 Appendix 8

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage On stretches where it is not possible to pass the

traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement,

IRC-SP-27 for recommendati

ons of IRC regional

workshops on Highway Safety, IRC-

SP-32 for road Safety

for Children, IRC-

SP-44 for highway

Safety, IRC-SP-55 for

safety in road construction

zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Construction sites Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

Page 108: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 269

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites

Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement

Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

Page 109: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

270 Appendix 8

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of

Pollution) Act, 1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC / CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

thereof

Sensitive receptors

Noise barriers have been proposed in total 1640m length (700m in KRM, 740m in JRK and 200m in BB road)

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC / CSC

3. Land and Soil

3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC / CSC

Page 110: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 271

Environmental Issue/ component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation

Supervision

C. Operation stage

4. Water resources/Flooding and Inundation 4.1 Siltation Regular checks shall be made for soil

erosion and turning conditions of river training structures for its effective maintenance.

Project requirement

Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC / CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement

Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance e cost

MPRDC / CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement

Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC / CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation

Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC / CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement

Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC / CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC / CSC

Page 111: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

272 Appendix 8

Environmental Issue/ component

Remedial Measure Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

C. Operation stage

6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC / CSC

Note EA: Executing Agency, MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC: Indian Road Congress

a. The“Project engineer ”or“ the engineer”is the team of Construction Supervision Consultants (CSC) responsible for approving the plans, engineering drawing, release of payments to contractor etc.on behalf of the employer (MPRDC). It is usually the team leader of the CSC that takes the responsibility of signing approval documents on behalf of the CSC team.

b. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 112: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 273

Environmental Monitoring Plan (Contract Package No. 1) Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through

approved monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 113: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

274 Appendix 8

Environmental Management and Monitoring Plan (Contract Package No. 2)

Environmental Management Plan (Contract Package No. 2)

This EMP is applicable to two subproject road included in Civil Works Contract Package No 2 i.e. 1) Sirsod - Pichhore Road 2). Narwar - Chitori - Amola Road Chitrangi-Garhwa Road

Environmental Issue / Component

RemedialMeasure Referenceto laws Location Monitoring

indicators Monitoring Methods

Mitigation Costs

Institutional Responsibility Implementation Supervision

A. Pre-construction and Design Stage 1. Alignment 1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no. of cross drainage structures based on drainage pattern around the alignment.

Design requirement

Side drains have been proposed in Korsar, Mudrpali&Dharauli villages (1.500 Km both side) in HKM road & NO Side drains have also been proposed in CG road

Existing CD structures are sufficient. No new CD structures proposed.

Design of both cross & side drains,

No. of CD structures & their spans

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC / CSC

1.2 Loss of 636 trees and vegetation cover @ 586 at Harphari-Khhaira Road Road, 254 at Chitrangi-Garhwa Road

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 6360 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment

No. of trees to be cut

Observation, Included in construction

cost

Design Consultant

MPRDC CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement

Location of temples, schools and other sensitive receptors along the project roads (Refer to Table. 25).

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

Page 114: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 275

Environmental Issue / Component

RemedialMeasure Referenceto laws Location Monitoring

indicators Monitoring Methods

Mitigation Costs

Institutional Responsibility Implementation Supervision

A. Pre-construction and Design Stage 1. Alignment 1.4 Safety along the proposed alignment

Provision of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement, IRC-67 for road signs, IRC-73 for geometric

design standards, IRC-119 for traffic safety, IRC-75 for

slope stabilisation in

high embankment

Length of W-beam crash barriers (where height of embankment is more than 3.0 m) provided is 1300 m (bothside).

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC / CSC

2. Natural Hazards

2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch

Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC / CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road construction in water logged

areas and

IRC-75 for design of high embankment

Sub-grade top has been kept 0.6m above HFL throughout the stretch and profile has been raised at water logged areas.

Design of both cross & side drains Sirsod- Pichhore Road 8 no. of Pipe Culverts & 23 no slab/box culverts , 20 no & Narwar-chittori- amola Road 57 no. of Pipe Culverts & 02 no slab/box culverts , 10 no size of Hume

pipes

Existing CD structures are sufficient. No new CD structures proposed.

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC / CSC

Page 115: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

276 Appendix 8

Environmental

Issue/Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction and Design Stage

3. Shifting of utility structures 3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement

The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ CSC

MPRDC //CSC

B. Construction Stage

1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge works, Air (P & CP) Act 1974 and Central Motor

and Vehicle Act 1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC /CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981

(Amended1987) and

Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC / CSC

Page 116: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 277

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Time regulation near residential, built up and forest areas construction shall be restricted to daylight hours.

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

Legal requirement

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

Thereof + Clause No 501.8.6. MORT&H

Specifications for Road and Bridge

works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC / CSC

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement

Throughout the project section and

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC /CSC

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works, Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC / CSC

Page 117: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

278 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

IRC-10 for guidelines on borrow areas and for

quarries, Environmental Protection Act and

Rules, 1986; Water Act, Air Act,

Clause No. 305.2.2 MORT&H

Specifications for Road and Bridge works

Guidelines V for Borrow Areas management

These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Complaints from local people.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.4 Quarry operations Aggregates will be sourced from existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H Specifications

for Road and Bridge works,

Guidelines VI for quarry area management

Quarry area locations

Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC /CSC

3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC /CSC

Page 118: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 279

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement

Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC /CSC

4. WaterResources 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010 EP Act 1986

MORT&H Specifications for Road and Bridge

works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for Road and Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC / CSC

Page 119: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

280 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

4. WaterResources

4.4 Siltation in water bodies due to construction activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Design requirement, Clause No

501.8.6. MORT&H Specifications for

Road and Bridge works

Near all water bodies, river embankment slopes.

Siltation of rivers, streams, ponds and other water bodies in project area

Field observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

5. Flora and Fauna 5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

Forest Conservation

Act 1980, IRC SP: 21 and

IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation cost is included in project costs.

Relevant agency

specialized in afforestation

MPRDC /CSC

6. ConstructionCamps

Page 120: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 281

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 6.1 Impact associated with location

All camps should maintain minimum distance from following: # 500 m from habitation, # 500 m from forest areas where possible, # 500 m from water bodies where possible, # 500 m from through traffic route where possible.

Design Requirement

All construction camps

Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to CSC prior to their construction. The construction shall commence only after approval of CSC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The building and other construction

workers (Regulation of

Employment and Conditions of

Service) Act 1996 and The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof

All construction camps

Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and

MORT&H guidelines

At all dumping sites

Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

Page 121: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

282 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

8. TrafficManagementandSafety 8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

Design requirement and

IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC /CSC

Page 122: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 283

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement,

IRC-SP-27 for recommendations of IRC regional

workshops on Highway

Safety, IRC-SP-32 for road Safety for

Children, IRC-SP-44 for

highway Safety, IRC-SP-55 for safety in road construction

zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction sites

Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites

Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

Page 123: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

284 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of Pollution)

Act, 1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC / CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

thereof

Sensitive receptors

Noise barriers has been proposed

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC / CSC

3. Land and Soil

Page 124: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 285

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC / CSC

Page 125: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

286 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation

Supervision

C. Operation stage

4. Water resources/Flooding and Inundation

4.1 Siltation Regular checks shall be made for soil erosion and turning conditions of river training structures for its effective maintenance.

Project requirement

Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC / CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement

Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance e cost

MPRDC / CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement

Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC / CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation

Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC / CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement

Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC / CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC / CSC

Page 126: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 287

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC / CSC

Notes: EA: Executing Agency, MPRDC: Construction Supervision Consultants (CSC): Supervision Quality Controller, EO: Environmental Officer, IRC: Indian Road Congress

a. The “Project engineer” or “the engineer” is the team of Construction Supervision Consultants (CSC) responsible for approving the plans, engineering drawing, release of payments to contractor etc. on behalf of the employer (MPRDC). It is usually the team leader of the CSC that takes the responsibility of signing approval documents on behalf of the CSC team.

b. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 127: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

288 Appendix 8

Environmental Monitoring Plan (Contract Package No. 2)

Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 128: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 289

Environmental Management and Monitoring Plan (Contract Package No.3 )

Environmental Management Plan (Contract Package No. 3)

This EMP is applicable to subproject road included in Civil Works Contract Package No 3 i.e. ) Mungawali - Malaharghah Road , 2) Piprod - Thou ban Road 3) Belai - Karila mata Mandir Road 4) Bhorasa Malhargarh Road

EnvironmentalIssue / Component

RemedialMeasure Referenceto laws Location Monitoring

indicators Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction andDesignStage

1. Alignment 1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate (a) 16 no for Mungawali - Malahargarh Road, (b) 8 no for Piprod - Thouban Road, (c) 38 no for Belai - Karela Mata Mandir Road & (d) 29no for Bhorasa - Malhargarh Road of cross drainage structures based on drainage pattern around the alignment.

Design requirement

Design of both cross & side drains Mungawali - Malaharghah Road 04 no. of Pipe Culverts & 05 no slab/box culverts , 01 no size of Hume pipes & Piprod - Thouban Road 02 no. of Pipe Culverts & no slab/box culverts ,01 no size of Hume pipes

Belai - Karila mata Mandir Road 32 no. of Pipe Culverts & 00 no slab/box culverts ,05 no size of Hume pipes & (d). Bhorasa Malhargarh Road 3no. of Minor, 24 no. of Pipe Culverts & 01 no slab 1 no of VCW culverts

Design of both cross & side drains,

No. of CD structures & their spans

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC / CSC

1.2 Loss of 224 trees and vegetation cover

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 2240 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment No. of trees to be cut

Observation, Included in construction

cost

Design Consultant

MPRDC CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement Location of temples, schools

and other sensitive receptors along the project roads

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

Page 129: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

290 Appendix 8

1.4 Safety along the proposed alignment

Provision of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement, IRC-67 for road signs, IRC-73 for geometric

design standards, IRC-119 for traffic safety, IRC-75 for

slope stabilisation

in high embankment

139 numbers of different types of sign boards proposed in PM road, 52 numbers in MR road & 244 numbers in JS road.

Substandard curves have been improved

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC / CSC

Page 130: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 291

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction and Design Stage

2. Natural Hazards

2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC / CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road

construction in water logged

areas and

IRC-75 for design of high embankment

Design of both cross & side drains Mungawali - Malaharghah Road 04 no. of Pipe Culverts & 05 no slab/box culverts , 01 no size of Hume pipes & Piprod - Thouban Road 02 no. of Pipe Culverts & no slab/box culverts ,01 no size of Hume pipes

Belai - Karila mata Mandir Road 32 no. of Pipe Culverts & 00 no slab/box culverts ,05 no size of Hume pipes & (d).Bhorasa Malhargarh Road 3no. of Minor, 24 no. of Pipe Culverts & 01 no slab 1 no of VCW culverts

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC / CSC

3. Shifting of utility structures 3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement

The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ CSC

MPRDC / CSC

Page 131: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

292 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge works, Air

(P & CP) Act 1974 and Central

Motor and Vehicle Act

1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC /CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981

(Amended1987) and

Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC / CSC

Page 132: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 293

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Time regulation near residential, built up and forest areas construction shall be restricted to daylight hours.

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

Legal requirement

Noise

Pollution (Regulation and Control) Rules, 2000

and amendments

Thereof + Clause No 501.8.6.

MORT&H Specification

s for Road and

Bridge works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise barriers has been proposed

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC /CSC

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement

Throughout the project section and

Borrow areas (Km 7 & Km 18.3 of PM road, Km 1 & Km 3.5of MR road and Km 26, Km 28 & Km 31 of JS road)

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC /CSC

Page 133: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

294 Appendix 8

Environmental

Issue/Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works,

Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

IRC-10 for guidelines on borrow areas

and for quarries,

Environmental Protection Act

and Rules, 1986; Water Act, Air

Act, Clause No. 305.2.2

MORT&H Specifications for Road and Bridge works Guidelines V for Borrow

Areas management

Borrow areas

These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Complaints from local people.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.4 Quarry operations Aggregates will be sourced from existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H

Specifications for Road and Bridge works, Guidelines VI for quarry area management

Quarry area locations Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC /CSC

Page 134: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 295

Environmental

Issue/Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement

Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC /CSC

3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement

Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC /CSC

4. WaterResources 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

Page 135: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

296 Appendix 8

Environmental

Issue/Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

4. WaterResources

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010

EP Act 1986 MORT&H

Specifications for Road and

Bridge works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications

for Road and

Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC /CSC

4.4 Siltation in water bodies due to construction activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for Road and Bridge works

Near all water bodies, river embankment slopes.

Siltation of rivers, streams, ponds and other water bodies in project area

Field observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

Page 136: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 297

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

5. Flora and Fauna 5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

Forest Conservation

Act 1980, IRC SP: 21 and

IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation

cost is included in

project costs.

Relevant agency

specialized in afforestation

MPRDC /CSC

6. ConstructionCamps 6.1 Impact associated with location

All camps should maintain minimum distance from following: # 500 m from habitation, # 500 m from forest areas where possible, # 500 m from water bodies where possible, # 500 m from through traffic route where possible.

Design Requirement

All construction camps Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to CSC prior to their construction. The construction shall commence only after approval of CSC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The building and other

construction workers

(Regulation of Employment

and Conditions of Service) Act 1996 and The

Water (Prevention

and Control of Pollution) Act,

1974 and amendments

thereof

All construction camps Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

Page 137: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

298 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision The Contractor will take all precautions to protect

the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and MORT&H

guidelines

At all dumping sites Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

Page 138: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 299

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

8. TrafficManagementandSafety 8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

Design requirement and IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC / CSC

8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement, IRC-SP-27 for

recommendations of IRC regional

workshops on Highway Safety, IRC-SP-32 for road Safety

for Children, IRC-SP-44 for highway Safety,

IRC-SP-55 for safety in road construction

zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

Page 139: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

300 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage 8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction sites

Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites

Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

Page 140: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 301

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of Pollution) Act,

1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC / CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

thereof

Sensitive receptors

Noise barriers has been proposed in total 1760m length (1000m in PM, 60m in MR and 700m in JS road)

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC / CSC

3. Land and Soil

3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC / CSC

Page 141: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

302 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation

Supervision

C. Operation stage

4. Water resources/Flooding and Inundation 4.1 Siltation Regular checks shall be made for soil erosion and

turning conditions of river training structures for its effective maintenance.

Project requirement

Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC / CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement

Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance e cost

MPRDC / CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement

Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC / CSC

5. Flora 5.1 Vegetation Planted trees, shrubs, and grasses to be properly

maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation

Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC / CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement

Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC / CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC / CSC

C. Operation stage 6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC / CSC

Page 142: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 303

Note EA: Executing Agency , MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC: Indian Road Congress

a. The“Projectengineer”or “theengineer”istheteamof ConstructionSupervisionConsultants(CSC)responsiblefor approvingtheplans, engineeringdrawing,releaseofpaymentstocontractoretc.onbehalfoftheemployer(MPRDC).ItisusuallytheteamleaderoftheCSCthat takestheresponsibilityofsigningapprovaldocumentson behalfof theCSCteam.

b. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 143: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

304 Appendix 8

Environmental Monitoring Plan (Contract Package No. 3) Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 144: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 305

Environmental Management and Monitoring Plan (Contract Package No. 7)

Environmental Management Plan (Contract Package No. 7)

This EMP is applicable to one subproject road included in Civil Works Contract Package No 7 i.e. 1) Samnapur-Bilhera-Narayanpur Road 2) Maharajpur-Sahejpur Road 3) Kesli-Sahejpur Road Road

EnvironmentalIssue / Component

RemedialMeasure Referenceto laws Location Monitoring

indicators Monitoring Methods

Mitigation Costs

Institutional Responsibility Implementation Supervision

A. Pre-construction and Design Stage

1. Alignment 1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no. of cross drainage structures based on drainage pattern around the alignment. Provision of adequate (a). 75 no. for Samnapur-Bilhera-Narayanpur Road (b). 45 no. for Maharajpur-Sahejpur Road c) 36 no. for Kesli-Sahejpur of cross drainage structures based on drainage pattern around the alignment

Design requirement

Existing CD structures are sufficient. No new CD structures proposed.

Design of both cross & side drains,

(a) Samnapur- Bilhera - Narayan pur Road 8 no. of Minor, 3no. of Major, 55 no. of Pipe Culverts & 7 no slab & 2 no. of box culverts

(b) Maharajpur- Sahejpur Road - 8no. of minor, 32 no. of Pipe Culverts &3no Slab / 2no. of box culverts

(c). Kesli- Sahejpur Road - 5no. Of minor, 22 no. of Pipe Culverts & 9no Slab culverts.

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC /CSC

1.2 Loss of 376 trees and vegetation cover

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 3760 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment No. of trees to be cut

Observation, Included in construction

cost

Design Consultant

MPRDC /CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement

Location of temples, schools and other sensitive receptors along the project roads (Refer to Table. 25).

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

Page 145: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

306 Appendix 8

EnvironmentalIssue / Component

RemedialMeasure Referenceto laws Location Monitoring

indicators Monitoring Methods

Mitigation Costs

Institutional Responsibility Implementation Supervision

1.4 Safety along the proposed alignment

Provision of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement, IRC-67 for road signs, IRC-73 for geometric

design standards, IRC-119 for traffic safety, IRC-75 for

slope stabilisation

in high embankment

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC / CSC

2. Natural Hazards

2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC / CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road

construction in water logged

areas and

IRC-75 for design of high embankment

Sub-grade top has been kept 0.6m above HFL throughout the stretch and profile has been raised at water logged areas.

Existing CD structures are sufficient. No new CD structures proposed.

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC / CSC

3. Shifting of utility structures 3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement

The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ SQC

MPRDC CSC

Page 146: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 307

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge

works, Air (P & CP) Act 1974 and

Central Motor and Vehicle Act 1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC /CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981

(Amended1987) and Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC /CSC

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Legal requirement

Noise Pollution (Regulation and

Control) Rules, 2000 and amendments

Thereof + Clause No 501.8.6. MORT&H Specifications for Road and Bridge

works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise barriers have been proposed in total 1920m length as noise preventive measures.

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC /CSC

Page 147: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

308 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision Time regulation near residential, built up and

forest areas construction shall be restricted to daylight hours.

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement Throughout the project section and

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC /CSC

3. Land and Soil

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works, Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

IRC-10 for guidelines on

borrow areas and for quarries,

Environmental Protection Act and

Rules, 1986; Water Act, Air Act,

Clause No. 305.2.2 MORT&H Specifications for Road and Bridge

works Guidelines V for Borrow Areas

management

Borrow areas are located.

These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Complaints from local people.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

Page 148: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 309

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 3.4 Quarry operations Aggregates will be sourced from existing

licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H

Specifications for Road and Bridge

works, Guidelines VI for

quarry area management

Quarry area locations

Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC /CSC

3. Land and Soil

3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC /CSC

3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC /CSC

4. WaterResources

Page 149: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

310 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010 EP Act 1986

MORT&H Specifications for Road and Bridge

works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for Road and Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC /CSC

4.4 Siltation in water bodies due to construction activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for

Road and Bridge works

Near all water bodies, river embankment slopes.

Siltation of rivers, streams, ponds and other water bodies in project area

Field observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act, 1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

Page 150: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 311

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

5. Flora and Fauna 5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

Forest Conservation

Act 1980, IRC SP: 21 and

IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation

cost is included in

project costs.

Relevant agency

specialized in afforestation

MPRDC /CSC

6. ConstructionCamps 6.1 Impact associated with location

All camps should maintain minimum distance from following: # 500 m from habitation, # 500 m from forest areas where possible, # 500 m from water bodies where possible, # 500 m from through traffic route where possible.

Design Requirement

All construction camps Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to SQC prior to their construction. The construction shall commence only after approval of SQC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The building and other

construction workers

(Regulation of Employment

and Conditions of Service) Act 1996 and The

Water (Prevention

and Control of Pollution) Act,

1974 and amendments

thereof

All construction camps Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

Page 151: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

312 Appendix 8

Environmental

Issue/Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision The Contractor will take all precautions to protect the

workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and MORT&H

guidelines

At all dumping sites

Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

Page 152: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 313

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

8. TrafficManagementandSafety 8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

Design requirement and

IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC /CSC

8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement,

IRC-SP-27 for recommendations of IRC regional

workshops on Highway

Safety, IRC-SP-32 for road Safety for

Children, IRC-SP-44 for

highway Safety, IRC-SP-55 for safety in road construction

zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

Page 153: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

314 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction sites

Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites

Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement

Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

Page 154: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 315

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of

Pollution) Act, 1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC /CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

thereof

Sensitive receptors

Noise barriers have been proposed in total 1920m length.

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC /CSC

3. Land and Soil

3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

Page 155: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

316 Appendix 8

Environmental Issue/Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation

Supervision

C. Operation stage

4. Water resources/Flooding and Inundation

4.1 Siltation Regular checks shall be made for soil erosion and turning conditions of river training structures for its effective maintenance.

Project requirement Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC /CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC /CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC /CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC /CSC

Page 156: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 317

Environmental

Issue/Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC /CSC

Note EA: Executing Agency , MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC: Indian Road Congress

c. The “Project engineer” or “the engineer” is the team of Construction Supervision Consultants (CSC) responsible for approving the plans, engineering drawing, release of payments to contractor etc.on behalf of the employer (MPRDC). It is usually the team leader of the CSC that takes the responsibility of signing approval documents on behalf of the CSC team.

d. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 157: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

318 Appendix 8

Environmental Monitoring Plan (Contract Package No. 7) Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 158: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 319

Environmental Management and Monitoring Plan (Contract Package No. 11)

Environmental Management Plan (Contract Package No. 11) This EMP is applicable to three subproject road included in Civil Works Contract Package No 11 i.e. 1) Barghat - kanhiwada Road 2) Dharna Aata Dondiwada

Dharmakua Road 3) Waraseoni - Katangi Road

EnvironmentalIssue / Component

RemedialMeasure Referenceto

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction andDesignStage

1. Alignment

1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no. of 1)Barg hat - kanhiwada Road 36 no.,2)Dharna-Aata Dondiwada Dharmakua Road 40 no. and 3) Waraseoni - Katangi Road 81 no. of cross drainage structures based on drainage pattern around the alignment

Design requirement

Side drains have been proposed

Design of both cross & side drains, 1)Barghat kanhiwada Road 33 no. of Pipe Culverts & 00 no slab/box culverts, 0 no & size of Hume pipes Dharna-Aata Dondiwada Dharmakua Road 37no.of Pipe Culverts & 01 no slab/box culverts, 0 no & size of Hume pipes. Waraseoni - Katangi Road 68 no.of Pipe Culverts & 13 no slab/box culverts, 1no & size of Hume pipes

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC /CSC

1.2 Loss of 691 trees and vegetation cover

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 6910 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment No. of trees to be cut

Observation, Included in construction

cost

Design Consultant

MPRDC CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement

Location of temples, schools and other sensitive receptors along the project roads (Refer to Table. 25).

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

Page 159: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

320 Appendix 8

EnvironmentalIssue / Component

RemedialMeasure Referenceto

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

1.4 Safety along the proposed alignment

Provision of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement, IRC-67 for road signs, IRC-73 for geometric

design standards, IRC-119 for traffic safety, IRC-75 for

slope stabilisation

in high embankment

Field Observationn ,interview of locals

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC /CSC

2. Natural Hazards

2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC /CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road

construction in water logged

areas and

IRC-75 for design of high embankment

Sub-grade top has been kept 0.6m above HFL throughout the stretch and profile has been raised at water logged areas.

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC /CSC

3. Shifting of utility structures 3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement

The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ SQC

MPRDC /CSC

Page 160: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 321

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge works, Air (P &

CP) Act 1974 and Central Motor and Vehicle Act 1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC /CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981 (Amended1987) and Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC /CSC

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Time regulation near residential, built up and forest areas construction shall be restricted to daylight hours.

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

Legal requirement

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

Thereof + Clause No 501.8.6. MORT&H

Specifications for Road and Bridge

works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC /CSC

Page 161: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

322 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement Throughout the project section and

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC /CSC

3. Land and Soil

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works, Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

IRC-10 for guidelines on

borrow areas and for quarries,

Environmental Protection Act and

Rules, 1986; Water Act, Air Act,

Clause No. 305.2.2 MORT&H Specifications for Road and Bridge

works Guidelines V for Borrow Areas

management

These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Complaints from local people.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.4 Quarry operations

Aggregates will be sourced from existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H

Specifications for Road and Bridge

works, Guidelines VI for

quarry area management

Quarry area locations

Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC /CSC

Page 162: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 323

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement

Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC /CSC

3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement

Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC /CSC

4. WaterResources 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

Page 163: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

324 Appendix 8

Environmental

Issue/ Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

4. WaterResources

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010

EP Act 1986 MORT&H

Specifications for Road and

Bridge works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications

for Road and

Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC /CSC

4.4 Siltation in water bodies due to construction activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for Road and Bridge works

Near all water bodies, river embankment slopes.

Siltation of rivers, streams, ponds and other water bodies in project area

Field observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

Page 164: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 325

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

5. Flora and Fauna 5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

Forest Conservation

Act 1980, IRC SP: 21 and

IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation

cost is included in

project costs.

Relevant agency

specialized in afforestation

MPRDC /CSC

6. ConstructionCamps 6.1 Impact associated with location

All camps should maintain minimum distance from following: # 500 m from habitation, # 500 m from forest areas where possible, # 500 m from water bodies where possible, # 500 m from through traffic route where possible.

Design Requirement

All construction camps

Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to SQC prior to their construction. The construction shall commence only after approval of SQC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The building and other

construction workers

(Regulation of Employment and

Conditions of Service) Act

1996 and The Water

(Prevention and Control of

Pollution) Act, 1974 and

amendments thereof

All construction camps

Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

Page 165: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

326 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision The Contractor will take all precautions to

protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and MORT&H

guidelines

At all dumping sites Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

Page 166: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 327

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

8. TrafficManagementandSafety 8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

Design requirement and

IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC /CSC

8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement,

IRC-SP-27 for recommendations of IRC regional

workshops on Highway

Safety, IRC-SP-32 for road Safety for

Children, IRC-SP-44 for

highway Safety, IRC-SP-55 for safety in road construction

zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

Page 167: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

328 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage 8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction sites

Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites

Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement

Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

Page 168: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 329

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of

Pollution) Act, 1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC /CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

thereof

Sensitive receptors

Noise barriers has been proposed

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC /CSC

3. Land and Soil

3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

Page 169: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

330 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation

Supervision

C. Operation stage

4. Water resources/Flooding and Inundation

4.1 Siltation Regular checks shall be made for soil erosion and turning conditions of river training structures for its effective maintenance.

Project requirement

Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement

Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance e cost

MPRDC /CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement

Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC /CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation

Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC /CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement

Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC /CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC /CSC

Page 170: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 331

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC /CSC

Note EA: Executing Agency , MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC: Indian Road Congress

e. The“Projectengineer”or “theengineer”istheteamof ConstructionSupervisionConsultants(CSC)responsiblefor approvingtheplans, engineeringdrawing,releaseofpaymentstocontractoretc.onbehalfoftheemployer(MPRDC).ItisusuallytheteamleaderoftheCSCthat takestheresponsibilityofsigningapprovaldocumentson behalfof theCSCteam.

f. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 171: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

332 Appendix 8

Environmental Monitoring Plan (Contract Package No. 11) Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 172: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 333

Environmental Management and Monitoring Plan (Contract Package No. 10)

Environmental Management Plan (Contract Package No. 10)

This EMP is applicable to three subproject road included in Civil Works Contract Package No 10 i.e. 1) Bariya Chowki - Lugasi - Garhi Malhera Road 2)

Bamitha (Rajnagar) - Dumra Road 3) Rajnagar - Bachhon Road 4) Khaptiya - Banspahadi Road 5) Chhatarpur - Bikrampur - Rajnagar Road

EnvironmentalIssue / Component

RemedialMeasure Referenceto laws Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction andDesignStage

1. Alignment

1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no. of (a) 23nos for Bariya Chowki - Lugasi - GarhiMalhera Road, (b) 56nos for Bamitha(Rajnagar) - Dumra Road, (c) 43nos for Rajnagar - Bachhon Road (d) 54nos for Khaptiya - Banspahadi Road & (e) 14nosfor Chhatarpur-Bikrampur - Rajnagar Road of cross drainage structures based on drainage pattern around the alignment.

Design requirement

Side drains have been proposed

Design of both cross & side drains,

No. of CD structures & their spans

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC /CSC

1.2 Loss of 890 trees and vegetation cover @ 346

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 3460 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment

No. of trees to be cut

Observation, Included in construction

cost

Design Consultant

MPRDC CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement

Location of temples, schools and other sensitive receptors along the project roads (Refer to Table. 25).

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

1.4 Safety along the proposed alignment

Provision of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement,

IRC-67 for road signs, IRC-73 for geometric design standards, IRC-

119 for traffic safety, IRC-75 for slope stabilisation

in high embankment

Field

Observationn ,interview of locals

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC /CSC

Page 173: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

334 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction and Design Stage

2. Natural Hazards 2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch

Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC /CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road construction in water

logged areas and

IRC-75 for design of high embankment

Sub-grade top has been kept 0.6m above HFL throughout the stretch and profile has been raised at water logged areas.

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC /CSC

3. Shifting of utility structures 3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ SQC

MPRDC /CSC

B. Construction Stage

1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge works, Air (P &

CP) Act 1974 and Central Motor and Vehicle Act 1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC /CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981 (Amended1987) and Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC /CSC

Page 174: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 335

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Time regulation near residential, built up and forest areas construction shall be restricted to daylight hours.

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

Legal requirement

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

Thereof + Clause No 501.8.6. MORT&H

Specifications for Road and Bridge

works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC /CSC

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement

Throughout the project section and

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC /CSC

3. Land and Soil

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works, Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

Page 175: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

336 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

IRC-10 for guidelines on

borrow areas and for quarries,

Environmental Protection Act and

Rules, 1986; Water Act, Air Act,

Clause No. 305.2.2 MORT&H Specifications for Road and Bridge

works Guidelines V for Borrow Areas

management

These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Complaints from local people.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.4 Quarry operations Aggregates will be sourced from existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H

Specifications for Road and Bridge

works, Guidelines VI for

quarry area management

Quarry area locations

Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC /CSC

3. Land and Soil

3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement

Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC /CSC

Page 176: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 337

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement

Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC /CSC

4. WaterResources 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

4. WaterResources

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010 EP Act 1986

MORT&H Specifications for Road and Bridge

works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for Road and Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC /CSC

Page 177: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

338 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 4.4 Siltation in water bodies due to construction activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for

Road and Bridge works

Near all water bodies, river embankment slopes.

Siltation of rivers, streams, ponds and other water bodies in project area

Field observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

5. Flora and Fauna 5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

Forest Conservation

Act 1980, IRC SP: 21 and

IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation

cost is included in

project costs.

Relevant agency specialized in afforestation

MPRDC /CSC

6. ConstructionCamps

Page 178: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 339

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 6.1 Impact associated with location

All camps should maintain minimum distance from following: # 500 m from habitation, # 500 m from forest areas where possible, # 500 m from water bodies where possible, # 500 m from through traffic route where possible.

Design Requirement

All construction camps

Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to SQC prior to their construction. The construction shall commence only after approval of SQC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The building and other construction

workers (Regulation of

Employment and Conditions of

Service) Act 1996 and The Water (Prevention and

Control of Pollution) Act,

1974 and amendments

thereof

All construction camps

Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and

MORT&H guidelines

At all dumping sites

Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

Page 179: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

340 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

8. TrafficManagementandSafety 8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

Design requirement and IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC /CSC

Page 180: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 341

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement, IRC-

SP-27 for recommendations

of IRC regional workshops on Highway Safety,

IRC-SP-32 for road Safety for

Children, IRC-SP-44 for highway

Safety, IRC-SP-55 for safety in road construction zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction sites Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

Page 181: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

342 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement

Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of

Pollution) Act, 1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC /CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

thereof

Sensitive receptors

Noise barriers has been proposed in total 1710m length (800m in GRB and 910m in PDJ road)

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC /CSC

3. Land and Soil

Page 182: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 343

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

4. Water resources/Flooding and Inundation 4.1 Siltation Regular checks shall be made for soil erosion

and turning conditions of river training structures for its effective maintenance.

Project requirement Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance e cost

MPRDC /CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC /CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC /CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC /CSC

Page 183: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

344 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC /CSC

6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC /CSC

Note EA: Executing Agency , MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC: Indian Road Congress

g. The“Projectengineer”or “theengineer”istheteamof ConstructionSupervisionConsultants(CSC)responsiblefor approvingtheplans, engineeringdrawing,releaseofpaymentstocontractoretc.onbehalfoftheemployer(MPRDC).ItisusuallytheteamleaderoftheCSCthat takestheresponsibilityofsigningapprovaldocumentson behalfof theCSCteam.

h. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 184: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 345

Table 2: Environmental Monitoring Plan (Contract Package No. 10) Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5

,PM10

,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved monitoring

agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 185: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

346 Appendix 8

Environmental Management and Monitoring Plan (Contract Package No. 14)

Environmental Management Plan (Contract Package No. 14)

This EMP is applicable to three subproject road included in Civil Works Contract Package No 11 i.e. 1) CHAND - BICHHUA - KHAMARPANI ROAD 2)CHAURAI -

PANJARA- CHAND ROAD

EnvironmentalIssue / Component

RemedialMeasure Referenceto laws Location Monitoring

indicators Monitoring Methods

Mitigation Costs

Institutional Responsibility Implementation Supervision

A. Pre-construction andDesignStage

1. Alignment 1.1 Pavement damage and inadequate drainage provision in habitat areas

Provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate 161 no. of cross drainage structures based on drainage pattern around the alignment.

Design requirement

Side drains have been proposed

Design of both cross & side drains, 155 no. pipe slab & size of VCW/FCW/pipes

Review of detail design documents & drawings

Included in construction

cost

Design Consultant

MPRDC /CSC

1.2 Loss of 980 trees and vegetation cover

Restricting tree cutting within construction limit.

Avoiding tree cutting at ancillary sites.

Providing and maintaining compensatory tree plantation of 9880 trees @ 1:10 ratio.

Design requirement,

Throughout the alignment No. of trees to be cut

Observation, Included in construction

cost

Design Consultant

MPRDC CSC

1.3 Protection of sensitive receptors

Careful selection of alignment to avoid damages to the sensitive receptors

Timely scheduling of construction activities

Provision of noise suitable barriers

Project requirement Places where height of

embankment is more than 3.00 m

Design and alignment plan

Review of design

Included in construction

Contractor MPRDC / CSC

1.4 Safety along the proposed alignment

Provision of retro-reflective warning sign boards nears school, hospital, religious places, and other areas, speed restriction sign in built-ups, forests areas etc.

Improving substandard curves, grading & other geometric features as per IRC Standards

Provision of metal beam crash barriers/guard stones at high embankment locations.

Provision of slope stabilization measures in high embankment/cutting to prevent any land slide situation.

Design requirement, IRC-67 for road signs, IRC-73 for geometric

design standards, IRC-119 for traffic safety, IRC-75 for

slope stabilisation

in high embankment

Field Observationn ,interview of locals

No. of accident & Vehicle collisions

Field observation, interview of locals

Included in construction

cost

Design Consultant

MPRDC /CSC

Page 186: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 347

Environmental

Issue/ Component Remedial Measure

Reference to laws

Location Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

A. Pre-construction and Design Stage

2. Natural Hazards

2.1 Protection for damage from Earthquake

Design considering relevant IRC guidelines for earthquakes in bridges.

IRC-6 for structure design,

IS-1893 for earthquake

resistant design

Throughout the stretch Incorporation of IRC guidelines for earthquake in bridge design

Review of bridge design

Project preparation

Cost

Design Consultant

MPRDC /CSC

2.2 Protection of road embankment in Flood prone Areas

Raise embankment height above the HFL levels in the flood prone areas.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

Provision of adequate balancing culverts.

IRC-34 for road

construction in water logged

areas and

IRC-75 for design of high embankment

Design of both cross & side drains ,155 no. Pipe/slab/box culverts & size of VCW/FCW pipes

Design of embankment/ road profile,

Design of both cross & side drains,

No. of CD structures & their spans

Included in construction

cost

Design Consultant

MPRDC /CSC

3. Shifting of utility structures 3.1 Disruption of utility services to local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any.

Project requirement

The contractor will shift all utility structure throughout the corridor with permission from relevant authorities before commencement of physical works.

Utility shifting plan

Complaints from local people

Status of local utility services

Interaction with concerned utility authorities and local public

Included in Construction

cost

Contractor/ SQC

MPRDC /CSC

Page 187: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

348 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage 1. Air Quality 1.1 Dust generation due to construction activities & transport, storage and handling of construction materials

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers.

MORT&H Specifications for Road and Bridge works, Air (P &

CP) Act 1974 and Central Motor and Vehicle Act 1988

Throughout the project corridor.

PM10 level measurement,

Dust pollution or complain of locals

Standards CPCB methods of observation s, Public consultation

Included in project cost

Contractor MPRDC /CSC

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion & use of equipment and machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used.

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring.

The Air (P & CP) Act,1981 (Amended1987) and Rules1982

Asphalt mixing plants, crushers, DG sets locations

Monitoring of ambient air quality & checking PUC certificates

Standards CPCB methods

Included in project cost

Contractor MPRDC /CSC

2. Noise

2.1 Noise from Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Time regulation near residential, built up and forest areas construction shall be restricted to daylight hours.

Initiation of multi layered plantation, to serve as mitigation option for operation phase.

Provision of Noise barriers at sensitive locations

Noise monitoring as per EMoP.

Legal requirement

Noise Pollution (Regulation and Control) Rules,

2000 and amendments

Thereof + Clause No 501.8.6. MORT&H

Specifications for Road and Bridge

works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise levels measurements

Complaints from local people

As per Noise rule, 2000 Consultation with local people

Included in project cost Plantation

cost is separate

Contractor MPRDC /CSC

3. Land and Soil 3.1 Land use Change and Loss of productive/top soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement Throughout the project section and

Borrow pit Locations Top soil storage area

Review borrow area plan, site visits

Included in construction

cost

Contractor MPRDC /CSC

Page 188: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 349

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

3. Land and Soil

3.2 Slope failure and soil erosion due to construction activities, earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications.

Care should be taken that the slope gradient shall not be greater than 2:1.

IRC-56 for treatment of embankment

slopes for erosion control,

Clause No. 306 and 305.2.2

MORT&H Specifications for Road and Bridge works, Guidelines IX for Soil erosion

Throughout the entire project road especially along hilly areas

Occurrence of slope failure or erosion issues

Review of design documents and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.3 Borrow site locations

Non-productive, barren lands, upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

To the extent borrow areas shall be sited away from habitation areas. Borrow areas shall be levelled with salvaged material or other filling materials which do not pose contamination of soil.

IRC-10 for guidelines on

borrow areas and for quarries,

Environmental Protection Act and

Rules, 1986; Water Act, Air Act,

Clause No. 305.2.2 MORT&H Specifications for Road and Bridge works Guidelines

V for Borrow Areas

management

These are located away from habitation areas & mainly are non-productive barren lands.

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area management practices.

Incidents of accidents.

Complaints from local people.

Review of design document s and site observation

Included in Construction

cost

Design consultant and

Contractor,

MPRDC /CSC

3.4 Quarry operations

Aggregates will be sourced from existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry Redevelopment plan, as per the Mining Rules of the state and submit a copy of the approval to EA.

Clause 111.3 MORT&H

Specifications for Road and Bridge

works, Guidelines VI for

quarry area management

Quarry area locations

Existence of licenses for all quarry areas from which materials are being sourced

Complaints from local people.

Review of design document s, contractor document s and site observation

Included in Construction

cost

Contractor MPRDC /CSC

3. Land and Soil

Page 189: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

350 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 3.5 Compaction of soil and impact on quarry haul roads due to movement of vehicles and equipment

Construction vehicles, machinery and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design requirement

Parking areas,

Haulage roads and construction yards.

Location of approach and haulage roads

Presence of destroyed /compacted agricultural land or land which has not be restored to its original condition

Site observation

Included in construction

cost

Contractor MPRDC /CSC

3.6 Contamination of soil due to leakage /spillage of oil, bituminous and non-bituminous debris generated from demolition and road construction

Construction vehicles and equipment will be maintained and refuelled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refuelling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refuelling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labelled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors.

Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board.

Design requirement

Fuelling station, construction sites, and construction camps and disposal location.

Quality of soil near storage area

Presence of spilled oil or bitumen in project area

Site observation

Included in Construction

cost.

Contractor MPRDC /CSC

4. WaterResources 4.1 Sourcing of water during construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority.

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

- Throughout the project section

Approval from competent authority,

complaints from local people on water availability

checking of documentation on Talk to local people

Included in construction

cost

Contractor MPRDC /CSC

Page 190: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 351

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

4. WaterResources

4.2 Disposal of water during construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No.1010 EP Act 1986

MORT&H Specifications for Road and Bridge

works

Throughout the Project section

Design of road side drains

Existence of proper drainage system for disposal of waste water

Standards methods Site observation and review of documents

Included in construction

cost

Contractor MPRDC /CSC

4.3 Alteration in surface water hydrology due to embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for Road and Bridge

Near all drainage channels, river crossings etc.

Design of road side drains

Review of Design documents Site observation

Included in construction

cost

Contractor MPRDC /CSC

4.4 Siltation in water bodies due to construction activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Design requirement, Clause No 501.8.6.

MORT&H Specifications for

Road and Bridge works

Near all water bodies, river embankment slopes.

Siltation of rivers, streams, ponds and other water bodies in project area

Field observation

Included in construction

cost

Contractor MPRDC /CSC

4.5 Deterioration in Surface water quality due to leakage from vehicles and equipment’s and waste from construction camps.

No vehicles or equipment should be parked or refuelled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted platform with catch pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up.

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically

The Water (Prevention and

Control of Pollution) Act, 1974 and amendments

thereof.

Water bodies, Refuelling stations, construction camps.

Water quality of ponds, streams, rivers and other water bodies in project area,

Presence of oil floating in water bodies in project area

Conduction of water quality tests as per the monitoring plan Field observation

Included in construction

cost

Contractor MPRDC /CSC

Page 191: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

352 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

B. Construction Stage

5. Flora and Fauna 5.1 Vegetation loss due to site preparation and construction activities and

Minimize tree cutting to the extent possible.

Roadside trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including maturing.

Forest Conservation

Act 1980, IRC SP: 21

and IRC SP:66

Throughout the project corridor

ROW width,

Number of trees for felling

Compensatory plantation plan

Number of trees replanted

Review of Relevant documents– tree cutting permit, compensatory plantation plan , Field observation s

Road side plantation

cost is included in

project costs.

Relevant agency

specialized in afforestation

MPRDC /CSC

6. ConstructionCamps 6.1 Impact associated with location

All camps should maintain minimum distance from following: # 500 m from habitation, # 500 m from forest areas where possible, # 500 m from water bodies where possible, # 500 m from through traffic route where possible.

Design Requirement

All construction camps

Location of camp sites and distance from habitation/forest /water bodies

On site Observation, Interaction with workers and local community

Included in construction

cost

Contractor and EO

MPRDC /CSC

6.2 Worker’s Health in construction camp

The location, layout and basic facility provision of each labour camp will be submitted to SQC prior to their construction. The construction shall commence only after approval of SQC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out.

The building and other

construction workers

(Regulation of Employment

and Conditions of Service) Act

1996 and The Water

(Prevention and Control of

Pollution) Act,

1974 and amendments

thereof

All construction camps

Camp health records,

Existence of proper first aid kit in camp site

Complaints from local people

Camp records, Site observation, Consultation with local people living nearby

Part of the Contractors

costs

Contractor MPRDC /CSC

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant Workers /local community on communicable and sexually transmitted diseases.

Page 192: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 353

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

7. Management of Construction Waste/Debris 7.1 Selection of Dumping Sites

Unproductive/waste lands shall be selected for dumping sites away from residential areas and water bodies.

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design Requirement and MORT&H

guidelines

At all dumping sites

Location of dumping sites,

Public complaints

Field survey & interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

7.2 Reuse and disposal of construction and dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

MORT&H guidelines

Throughout the project corridor

Percentage of reuse of existing surface material

Method and location of disposal site of construction debris

Contractor Records, Field observation, Interaction with local people

Included in Construction

cost.

Contractor MPRDC /CSC

8. TrafficManagementandSafety 8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC- SP-55.

The Contractor will ensure that the diversion is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Use of adequate signage’s to ensure traffic management and safety.

Conduct of regular safety audit on safety measures.

Design requirement

and IRC SP:55

Throughout the project corridor especially at intersections.

Traffic management plan Safety signs on site,

Number of traffic accidents

Review traffic management plan Field observation of traffic management and safety system Interaction with people in vehicles using the road

Included in construction

cost.

Contractor MPRDC /CSC

Page 193: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

354 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 8.2 Pedestrians, animal movement

Temporary access and diversion, with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts near habitations may be widened to facilitate cattle movement.

Design requirement,

IRC-SP-27 for recommendati

ons of IRC regional

workshops on Highway Safety, IRC-

SP-32 for road Safety

for Children, IRC-

SP-44 for highway

Safety, IRC-SP-55 for

safety in road construction

zone

Near habitation on both sides of schools, temples, hospitals, graveyards, construction sites, haulage roads, diversion sites.

Road signage & drainage as per IRC guideline,

Complaints from local people

Field Observation, Interaction with local people

Included in construction

cost.

Contractor MPRDC /CSC

8.3 Safety of Workers and accident risk from construction activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retro-reflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied With.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work.

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction sites

Availability of safety gears to workers,

Safety signage,

Training records on safety,

Number of safety related accidents

Site Observation, Review records on safety training and accidents, Interact with construction workers

Included in construction

cost

Obligation of Contractor

MPRDC /CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement.

Construction sites

Safety signs and their location,

Incidents of accidents,

Complaints from local people

Site inspection,

Consultation with local people

Included in construction

cost

Contractor MPRDC /CSC

9. Site restoration and rehabilitation

Page 194: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 355

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision 9.1 Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

Project requirement

Throughout the project corridor, construction camp sites and borrow areas

Clean and restored camp sites presence /absence of construction material/ debris after completion of construction works on construction site

Site observation, Interaction with locals, Issue completion certificate after restoration of all sites are found satisfactory

Included in construction

cost .

Contractor MPRDC /CSC

C. Operation stage 1. Air quality 1.1 Air pollution due to due to vehicular movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioural changes.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment.

Environmental Protection Act, 1986; The Air

(Prevention and Control of Pollution) Act,

1981

Throughout the corridor

Ambient air quality (PM10, CO, NOx)

Survival rate of trees planted

As per CPCB requirement s, site inspection

Included in Operation/ Maintenance cost

MPRDC /CSC

2. Noise 2.1 Noise due to movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation & honking restrictions may be enforced near sensitive locations.

The effectiveness of the multi-layered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution

(Regulation and Control) Rules, 2000

and amendments

thereof

Sensitive receptors

Noise barriers has been proposed

Noise levels Noise monitoring as per noise rules, 2000, Discussion with people in sensitive receptor sites

Included in Operation/ Maintenance cost

MPRDC /CSC

3. Land and Soil

3.1 Soil erosion at Embankment during heavy rain fall.

Periodic checking to be carried to assess the effectiveness of the stabilization measures viz. turning, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures.

Project requirement

At bridge locations & embankment slopes and other probable soil erosion areas.

Existence of soil erosion sites

Number of soil erosion sites

On site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

Page 195: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

356 Appendix 8

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation

Supervision

C. Operation stage

4. Water resources/Flooding and Inundation 4.1 Siltation Regular checks shall be made for soil erosion

and turning conditions of river training structures for its effective maintenance.

Project requirement

Near surface water bodies

Water quality Site observation

Included in Operation/ Maintenance cost

MPRDC /CSC

4.2 Water logging due to blockage of drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels /streams.

Monitoring of water borne diseases due to stagnant water bodies.

Project requirement

Near surface water bodies

Presence of flooded areas or areas with water stagnation

Site observation

Included in Operation/ Maintenance e cost

MPRDC /CSC

4.3 Road inundation due to choking of drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project requirement

Near surface water bodies

Incidents of flooding & road inundation with details

Field observation, Interaction with local community

Included in Operation/ Maintenance cost

MPRDC /CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness.

Forest Conservation

Act 1980

Project tree plantation sites

Minimum of 70% of tree survival

Records and fields observations

Operation and Maintenance Cost

MPRDC /CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk due to uncontrolled growth of vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the roadside.

Invasive plant not to be planted near the road.

Project requirement

Throughout the project route

Presence of and extent of vegetation growth on either side of road Accident data

Visual Inspection, Accident records

Included in operation/ Maintenance cost

MPRDC /CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

IRC:SP:55 Throughout the project route

Police records on accident condition and existence of safety signs, rumble strips etc. on the road

Presence/ absence of sensitive receptor structures inside the stipulated planning line as per relevant local law

Review accident records, Site observation s

Included in operation/ Maintenance cost

MPRDC /CSC

Page 196: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 357

Environmental Issue/ Component

Remedial Measure Reference to

laws Location

Monitoring indicators

Monitoring Methods

Mitigation Costs

Institutional Responsibility

Implementation Supervision

C. Operation stage 6.3 Transport of dangerous goods

Existence of spill prevention and control and emergency responsive system.

Emergency plan for vehicles carrying hazardous material.

Throughout the project stretch

Status of emergency system–whether operational or not

Review of spill prevention and emergency response system Spill

Included in Operation/ Maintenance cost.

MPRDC /CSC

Note EA: Executing Agency , MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC: Indian Road Congress

i. The“Projectengineer”or “theengineer”istheteamof ConstructionSupervisionConsultants(CSC)responsiblefor approvingtheplans, engineeringdrawing,releaseofpaymentstocontractoretc.onbehalfoftheemployer(MPRDC).ItisusuallytheteamleaderoftheCSCthat takestheresponsibilityofsigningapprovaldocumentson behalfof theCSCteam.

j. The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the engineer”.

Page 197: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

358 Appendix 8

Environmental Monitoring Plan (Contract Package No. 14) Environmenta

l Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an

approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 198: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 359

Environmental Management and Monitoring Plan (Contract Package No. 8)

Environmental Management Plan (Contract Package No. 8)

For the Road 1.Garhpahera-Dhamoni Road. 2 Barodiya-Dhamoni Road. 3. Noniya– madanpur Road. Environmental

Issue/ Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

Pre-construction and Design Stage

1. Alignment

1.1 Pavement

damage and

inadequate

drainage provisions

in habitat areas

Construction of concrete pavement in habitat areas considering alignment level and drainage.

Raise road level above the nearby areas with provision of adequate side drains to evacuate the rain water and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no. of cross drainage structures based on drainage pattern around the alignment.

Design requirement

All habitat Areas throughout the alignment

Cross &side drains

(a).Garhpahera-

Dhamoni Road 5

no. of Minor, 1no.

of Major, 21 no. of

Pipe Culverts & 9 no

slab & 9 no. of box

culverts

(b) Barodiya-

Dhamoni Road-

5 no. of minor, 18

no. of Pipe Culverts

&5no Slab / box

culverts

(c) Noniya–

madanpur Road –3 no.

Review of detail

Design documents & drawings

Included in construction cost

Design Consultant

MPRDC/ (CSC)

1.2 Loss of tree and vegetation

Restricting tree cutting within construction limit

Avoid tree cutting at ancillary site.

Martian Compensatory tree plantation of 7050 trees @ 1: 10

Design requirement

Throughout the alignment

(a).Garhpahera–

Dhamoni Road 45Nos.

(b).Barodiya-

Dhamoni Road 28nos.

(c).NoniysmadanpurRoad

2Nos.tree will be cut.

Observation Included in construction cost

Design Consultant

MPRDC/ (CSC)

1.3 Protection of sensitive receptors

Careful selection of alignment to the sensitive receptor.

Timely schedule ling of construction activity

Provision of noise suitable barriers

Project requirement

Location of sensitive receptors(Refer Table )

Design and alignment plan

Review of design

Included in construction cost

Contractor MPRDC/ (CSC)

1.4 Safety along

the proposed

alignment

Make provisions of crash barriers at accident prone areas as identified in the road safety studies.

Provision of rumble strips in habitat areas to regulate speed.

Provision of retro-reflective warning sign boards nears school, hospital, religious places and forests areas.

Provision of proper sidewalks/pedestrian zone along the road near habitat areas, school, hospital, religious places and forests.

Compliance with norms specified in IRC codes for state highway for curvature and grading

Design requirement

Places where

height of embankment is

more than 3.0 m.

No. of accident &

Vehicle collision

Field

observation, interview of

locals

Included in

construction

cost

Design Consultant

MPRDC/ (CSC)

Page 199: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

360 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

Provision of safety kerb at all bridges.

The design should attempt to equalize cut and fill.

Minimize the cutting in hill areas. Incorporate slope stabilization measures to prevent any land slide situation.

Incorporate Slope stabilization measures to prevent any land slide situation.

2. Natural Hazards

2.1 Protection for

damage from

Earthquake

Design considering relevant seismic standard in the clause under IRC 6-2014 for earthquakes in bridges

Throughout the

stretch

Incorporation of

IRC 6-2014 guidelines for

earthquake in

bridge design

Review of

bridge

design

Project

preparation

Cost

Design Consultant

MPRDC

2.2 Protection of road embankment

in Flood prone

Areas.

Raise embankment height above the HFL levels in the flood prone areas.

Provision of adequate balancing culverts.

Improvement in existing culverts/ Bridges to increase their carrying capacity.

IRC:34 Recommendations

for road construction

in waterlogged area and IRC: 75 and MORT&H guidelines for Design of High Embankments

All the existing

culverts/bridges

Design of both

cross & side drains

, no. of slab/box

culverts ,no & size

of Hume pipes.

Included in

construction

cost

Design Consultant

MPRDC

3. Shifting of utility structures

3.1 Disruption of

utility services to

local community

All telephone and electrical poles/wires and underground cables should be shifted before start of construction.

Necessary permission and payments should be made to relevant utility service agencies to allow quick shifting and restoration of utility services.

Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any

Project

requirement

The contractor will shift all utility structures throughout the corridor with permission from relevant authorities before commencement of physical works

Utility shifting plan

Complaints from

local people

Status of local

utility services

Interaction

with

concerned

utility

authorities

and local

public

Included in

Construction cost

Contractor MPRDC/ CSC

B. Construction Stage

1. Air Quality

1.1Dust Generation due to construction activities and

Transport, loading and unloading of loose and fine materials through covered vehicles.

Paved approach roads.

MORT&H

Specifications for Road and Bridge works

Throughout

Project corridor.

PM10 level

measurements

Dust pollution or

complain of locals

Standards

CPCB

methods

Observations

Included in

project cost

Contractor MPRDC/ CSC

Page 200: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 361

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

transport, storage and handling of construction materials

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Air (P and CP) Act 1981 and Central Motor and Vehicle

Act 1988

Public

consultation

1.2 Emission of air pollutants (HC, SO2, NOX, CO etc) from vehicles due to traffic congestion

and use of equipment and

machinery

Regular maintenance of machinery and equipment.

Batching, asphalt mixing plants and crushers at downwind (1km) direction from the nearest settlement.

Only crushers licensed by the PCB shall be used

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Ambient air quality monitoring

Follow traffic management plan as given in Section 8.

The Air (Prevention

and Control of

Pollution) Act,

1981(Amended 1987) and Rules1982

Asphalt mixing

plants,

crushers, DG

sets locations

Monitoring of

ambient air quality & checking PUC

certificates

Standards

CPCB

methods

Included in

project cost

Contractor MPRDC / CSC

2. Noise

2.1 Noise from

Construction vehicle, equipment and machinery.

All equipment to be timely serviced and properly maintained.

Bottlenecks to be removed.

Construction equipment and machinery to be fitted with silencers and maintained properly.

Only IS approved equipment shall be used for construction activities.

The regulation near residential, built up and forest area construction shall be restricted to daylight hours.

Timing of noisy construction activities shall be done during night time and weekends near schools and selected suitable times near temples when there are no visitors, concurrent noisy operations may be separated to reduce the total noise generated, and if possible re-route traffic during construction to avoid the accumulation of noise beyond standards. Else provision of temporary noise barrier at sensitive locations or near sources.

Legal requirement

Noise Pollution

(Regulation

and Control)

Rules, 2000

and amendments

thereof

+Clause No 501.8.6.

MORT&H

Specifications for Road and Bridge works

Throughout project section especially at construction sites, residential and identified sensitive locations.

Noise levels

Measurements

Complaints from

local people

As per

Noise rule,

2000

Consultation

with local

people

Included in

Project Cost

Plantation

cost is

separate

Contractor MPRDC/ CSC

3. Land and Soil

3.1 Land use

Change and Loss of productive/top

soil

Non-agricultural areas to be used as borrow areas to the extent possible.

If using agricultural land, top soil to be preserved and laid over either on the embankment slope for growing vegetation to protect soil erosion.

Project requirement

Throughout the

project section

and borrow

areas

Borrow pit

Locations

Top soil storage

area

Review borrow area plan, site

visits

Included in

construction

cost

Contractor MPRDC/ CSC

Page 201: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

362 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

3.2 Slope failure

and Soil erosion

due to Construction

activities,

earthwork, and cut and fill, stockpiles etc.

Bio-turfing of embankments to protect slopes.

Slope protection by providing frames, dry stone pitching, masonry retaining walls, planting of grass and trees.

The side slopes of all cut and fill areas will be graded and covered with stone pitching, grass and shrub as per design specifications. Care should be taken that the slope gradient shall not be greater than 2:1

The earth stockpiles to be provided with gentle slopes to prevent soil erosion.

IRC: 56 -1974 recommended practice for treat-ment of embank-ment slopes for erosion control Clause No.306 and 305.2.2 MORT&H Specifications for Road and Bridge works Guidelines IX for Soil erosion

Throughout the

entire project

road

especially

along hilly

areas

Occurrence of

slope failure or

erosion issues

Review of

design

documents

and site

observation

Included in

Construction

cost

Design consultant

and Contractor,

MPRDC/ CSC

3.3 Borrow area

management Non-productive, barren lands,

upland shall be used for borrowing earth with the necessary permissions/consents.

Depths of borrow pits to be regulated and sides not steeper than 25%.

Topsoil to be stockpiled and protected for use at the rehabilitation stage.

Transportation of earth materials through covered vehicles.

IRC recommended practice for borrow pits (IRC 10: 1961).

Borrow areas not to be dug continuously.

To the extent borrow areas shall be sited away from habituated areas. Borrow areas shall be leveled with salvaged material or other filling materials which do not pose contamination of soil. Else, it shall be converted into fishpond in consultation with fishery department and land owner/community.

Rehabilitation of the borrow areas as per Guidelines for redevelopment of Borrow Areas.

IRC Guidelines

on borrow areas and for quarries(Environmental

Protection Act

And Rules,1986;

Water Act, Air Act)+ Clause No.

305.2.2 MORT&H

Specifications for

Road and Bridge

works Guidelines

V for Borrow

Areas

management

Borrow sites

location

Existence of borrow areas in inappropriate unauthorized locations.

Poor borrow area

Management practices.

Incidents of accidents.

Complaints from local people.

Review of

design

documents

and site

observation

Included in

Construction

cost

Design consultant

and Contractor,

MPRDC/ CSC

3.4 Quarry

Operations Aggregates will be sourced from

existing licensed quarries.

Copies of consent/ approval / rehabilitation plan for a new quarry or use of existing source will be submitted to EO, MPRDC.

The contractor will develop a Quarry

Clause No.

111.3 MORT&H

Specifications for

Road and

Bridge works

Quarry area

locations

Existence of

licenses for all

quarry areas from

which materials

are being sourced

Existence of a

Quarry redevelopment

Review of

design

documents,

contractor

documents

and site

observation

Included in

Construction

cost

Contractor MPRDC/ CSC

Page 202: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 363

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

Redevelopment plan, as per the Mining Rules of the state and submit a copy of approval to EA.

Guidelines VI for

Quarry Areas

Management

Plan

3.5 Compaction of soil and impact on quarry haul roads due to movement of

vehicles and

equipment

Construction vehicles, machinery, and equipment to be stationed in the designated ROW to avoid compaction.

Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Load of haulage trucks will be monitored to ensure they do not exceed the standard limits to avoid safety issues and excessive damage on the roads

Land taken for construction camp and other temporary facility shall be restored to its original conditions.

Design

requirement

Parking areas,

Haulage roads and construction yards.

Location of

approach and

haulage roads

Presence of

destroyed/compact

ted agricultural

land or land which

has not be

restored to its

original condition

Site

observation

Included in

construction

cost

Contractor MPRDC/ CSC

3.6 Contamination

of soil due to

leakage/ spillage of oil, bituminous and non bituminous

debris generated

from demolition and road construction

Construction vehicles and equipment will be maintained and refueled in such a fashion that oil/diesel spillage does not contaminate the soil.

Fuel storage and refueling sites to be kept away from drainage channels.

Unusable debris shall be dumped in ditches and low lying areas.

To avoid soil contamination Oil-Interceptors shall be provided at wash down and refueling areas.

Waste oil and oil soaked cotton/ cloth shall be stored in containers labeled ‘Waste Oil’ and ‘Hazardous’ sold off to MoEF/SPCB authorized vendors

Non-bituminous wastes to be dumped in approved borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit.

Bituminous wastes will be disposed off in an identified dumping site approved , appropriately designed,

Design

requirement

Fuelling station,

Construction sites, and construction camps and disposal location.

Quality of soil near

storage area

Presence of

spilled oil or

bitumen in project area

Site

observation

Included in construction cost.

Contractor MPRDC/ CSC

Page 203: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

364 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

compliant waste management facilities (land fills).

4. Water Resources

4.1 Sourcing of

water during

Construction

Requisite permission shall be obtained for abstraction of groundwater from Central Groundwater Authority

Arrangements shall be made by contractor that the water availability and supply to nearby communities remain unaffected.

-

Throughout

the Project

section

Approval from

competent

authority

Complaints from

local people on

water availability

Checking of

documentation

on

Talk to local

people

Included in

construction

cost

Contractor MPRDC/ CSC

4.2 Disposal of

water during

construction

Provisions shall be made to connect road side drains with exiting nearby ponds otherwise make provision of water harvesting pits intermittently.

Clause No. 1010

EP Act 1986

MORT&H

Specifications for Road and Bridge works

Throughout

the Project

section

Design of road

side drains

Existence of

proper drainage

system for

disposal of waste

water

Standards

methods

Site

observation

and review

of documents

Included in

construction

cost

Contractor MPRDC/ CSC

4.3 Alteration in

surface water

hydrology due to

embankment

Existing drainage system to be maintained and further enhanced.

Provision shall be made for adequate size and number of cross drainage structures esp. in the areas where land is sloping towards road alignment.

Road level shall be raised above HFL level wherever road level is lesser than HFL.

Design requirement,

Clause No 501.8.6.

MORT&H Specifications

Near all

drainage

channels,

river crossings

etc.

Design of road

side drains

Review of

design

documents

Site

observation

Included in

construction

cost

Contractor MPRDC/ CSC

4.4 Siltation in water bodies due to construction

activities/ earthwork

Embankment slopes to be modified suitably to restrict the soil debris entering water bodies.

Provision of Silt fencing shall be made at water bodies.

Silt/sediment should be collected and stockpiled for possible reuse as surfacing of slopes where they have to be re-vegetated.

Earthworks and stone works to be prevented from impeding natural flow of rivers, streams and water canals or existing drainage system.

Design

requirement ,

Clause No

501.8.6. MORT&H

Specifications for

Road and Bridge

works

(CP and CP)

and worldwide

best practices

Near all water

bodies, river

embankment

slopes.

Siltation of rivers,

streams, ponds

and other water

bodies in project

area

Field

observation

Included in

construction

cost

Contractor MPRDC/ CSC

4.5 Deterioration in Surface water

quality due to

leakage from

vehicles and

equipments and

waste from construction camps.

No vehicles or equipment should be parked or refueled near water-bodies, so as to avoid contamination from fuel and lubricants.

Oil and grease traps and fuelling platforms to be provided at re-fuelling locations.

All chemicals and oil shall be stored away from water and concreted

The Water (Prevention and Control of Pollution) Act, 1974 and amendments thereof.

Water bodies, refueling stations, construction camps.

Water quality of

ponds, streams,

rivers and other

water bodies in

project

Presence of oil

floating in water

bodies in project

area

Conduction

of water

quality tests

as per the

monitoring

plan

Field

observation

Included in

construction

cost

Contractor MPRDC/ CSC

Page 204: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 365

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

platform with catchment pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual clean-up. Readily available, simple to understand and preferably written in the local language emergency response procedure, including reporting, will be provided by the contractors.

Construction camp to be sited away from water bodies.

Solid Wastes shall be collected, strong and taken to the approved, appropriately designed, compliant waste management facility (landfills) only.

Water quality shall be monitored periodically

All equipments operators, divers, and ware house personal will be trained in immediate response for spill containment and eventual cleanup. Readily available, simple to understand and preferably retain in the local language emergency response procedure, including reporting, will be provided by the contractor,

5. Flora and Fauna

5 .1 Vegetation loss due to site

preparation and

construction

activities and

Minimize tree cutting to the extent possible.

Roadside 705 trees to be removed with prior approval of competent authority.

Compensatory plantation at 1:10 basis and additional plantation as per the IRC guidelines in consultation with Forest Department.

Regular maintenance of all trees planted.

Provision of LPG in construction camp as fuel source to avoid tree cutting, wherever possible.

Plantation of trees on both sides of the road. Integrate vegetation management (IVM) with the carriage way completely clear of vegetation. From the edge of the

Forest

Conservation Act

1980

&

IRC SP: 21 and

IRC SP:66

Throughout

project

corridor

ROW width

705 Number of trees

for felling

Compensatory

plantation plan

7050 Number of trees

replanted

Review of

relevant

documents

– tree

cutting

permit,

compensatory

plantation

plan

Field

observations

Road side

Plantation cost is included in project costs.

Relevant agency

specialized in

a forestation

MPRDC / CSC

Page 205: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

366 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

road to the boundary of ROW, vegetation structured with smaller plants near the line and larger trees further away to avoid costly and provide habitats for a wide variety of plants and animals. Additional plantation near river banks to check erosion as part of compensatory plantation.

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA.

Road side Plantation Strategy as per IRC specifications including manuring.

6. Construction Camps

6.1 Impact

associated with

location

All camps should maintain

minimum distance from

following:

I. 500 m from habitation II. 500 m from forest areas

where possible III. 500 m from water bodies

where possible IV. 500 m from through traffic

route where possible The average distance between two camps should be 50 km

Design

Requirement

All

construction

camps

Location of

campsites and

distance from

habitation, forest

areas, water

bodies, through

traffic route and

other construction

camps

On site

Observation

Interaction

with workers

and local

community

Included in

construction

cost

Contractor and

EO

MPRDC/ CSC

6.2 Worker’s Health

in construction

camp

The location, layout and basic facility provision of each labor camp will be submitted to SQC prior to their construction. The construction shall commence only after approval of SQC.

The contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic manner as approved by the EA.

Adequate water and sanitary latrines with septic tanks attached to soak pits shall be provided.

Preventive medical care to be provided to workers including a First-Aid kit that must be available in the camp.

Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out .

The Building

and Other

Construction

workers

(Regulation of

Employment and

Conditions of

Service) Act

1996 and

The Water

(Prevention

and Control of

Pollution) Act,

1974 and

amendments

thereof

All

construction

camps

Camp health

Records

Existence of

proper first aid kit

in camp site

Complaints from

local people

Camp

Records

Site

Observation

Consultation

with local

people living

nearby

Part of the

Contractors

costs

Contractor MPRDC/ CSC

Page 206: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 367

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides hitch should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, and barter to the workers of host community.

Awareness raising to immigrant workers/local community on communicable and sexually transmitted diseases.

7. Management of Construction Waste/Debris

7.1 Selection of

Dumping Sites Unproductive/wastelands shall be

selected for dumping sites.

Away from residential areas and water bodies

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Design

Requirement and

MORT&H

guidelines

At all

Dumping

Sites

Location of

dumping sites

Public complaints

Field survey

and

interaction

with local

people

Included in

construction

cost

Contractor MPRDC/ CSC

7.2 Reuse and

disposal of

construction and

dismantled waste

The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

Unusable and non-bituminous debris materials should be suitably disposed off at pre-designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MOSRTH guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping

MORT&H

guidelines

Throughout

the project

corridor

Percentage of

reuse of existing

surface material

Method and

location of

disposal site of

construction

debris

Contractor

Records

Field

Observation

Interaction

with local

people

Included in

construction

cost

Contractor MPRDC/ CSC

Page 207: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

368 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

8. Traffic Management and Safety

8.1 Management of existing traffic and safety

Temporary traffic diversion shall be planned by the contractor and approved by the ‘Engineer’.

The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for night time traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC’s SP 55 document’.

The Contractor will ensure that the diversion/detour is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

Restriction of construction activity to only one side of the existing road.

The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Design

requirement and

IRC SP:55

Throughout the project corridor especially at intersections.

Traffic

management plan

Safety signs on

Site

Number of traffic

accidents

Review

traffic

management

plan

Field

observation

of traffic

management

and safety

system

Interaction

with people

in vehicles

using the

road

Included in

construction

cost

Contractor MPRDC/ CSC

8.2 Pedestrians,

animal movement Temporary access and diversion,

with proper drainage facilities.

Access to the schools, temples and other public places must be maintained when construction takes place near them.

Fencing wherever cattle movement is expected.

To avoid the need for cattle underpasses, some of the proposed culverts `near habitations may be widened to facilitate cattle movement.

Design requirement

And IRC: SP: 27 -1984 IRC:SP: 32 -1988 Road Safety for

Children (5-12

Years Old)

IRC:SP: 44 -1994 Highway Safety Code

IRC: SP: 55 -2001

Guidelines for The Building and other Construction

workers Act 1996 and Cess Act of

Near

habitation on

both sides of

schools, temples,

hospitals,

graveyards,

construction

sites, haulage

roads, diversion

sites.

Road signage &

drainage as per

IRC guideline

Complaints from

local people

Field

observation

Interaction

with local

people

Included in

construction

cost

Contractor MPRDC/ CSC

Page 208: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 369

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

1996 Factories Act

1948

8.3 Safety of

Workers and

accident risk from

construction

activities

Contractors to adopt and maintain safe working practices.

Usage of fluorescent and retroflectory signage, in local language at the construction sites

Training to workers on safety procedures and precautions.

Mandatory appointment of safety officer.

All regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress shall be complied with.

Provision of PPEs to workers.

Provision of a readily available first aid unit including an adequate supply of dressing materials.

The contractor will not employ any person below the age of 18 years for any work

Use of hazardous material should be minimized and/or restricted.

Emergency plan (to be approved by engineer) shall be prepared to respond to any accidents or emergencies.

Accident Prevention Officer must be appointed by the contractor.

Construction

sites

Availability of

Safety gears to

Workers

Safety signage

Training records

on safety

Number of safety

related accidents

Site

Observation

Review

records on

safety

training and

accidents

Interact with

construction

workers

Included in

construction

cost

Obligation of Contractor

MPRDC/ CSC

8.4 Accident risk to local community

Restrict access to construction sites to authorized personnel.

Physical separation must be provided for movement of vehicular and human traffic.

Adequate signage must be provided for safe traffic movement

Construction

sites

Safety signs and

their location

Incidents of

Accidents

Complaints from

local people

Site

Inspection

Consultation

with local

people

Included in

construction

cost

Contractor MPRDC/ CSC

9. Site restoration and rehabilitation

9.1 Clean-up

Operations,

Restoration and

Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the ‘Engineer’.

The clean-up and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites,

Project

requirement

Throughout

the project

corridor,

construction

camp sites

and borrow

areas

Clean and

restored camp

sites

Presence/absence

of construction

material/debris

after completion

of construction

Site

Observation

Interaction

with locals

Issue

completion

certificate

Included in

construction

cost

Contractor MPRDC/ CSC

Page 209: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

370 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer.

All the opened borrow areas will be rehabilitated and ‘Engineer’ will certify in this regard.

works on

construction site

after

restoration

of all sites

are found

satisfactory

C. Operation stage

1. Air quality

1.1 Air pollution due

to due to vehicular

movement

Roadside tree plantations shall be maintained.

Regular maintenance of the road will be done to ensure good surface condition.

Vehicular air pollution will be managed and monitored.

Ambient air quality monitoring. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Technological and behavioral changes

Road signs shall be provided

reminding the motorist toproperly maintains their vehicles to economize on fuel consumption and unprotect the environment.

Environmental

Protection Act,

1986; The Air

(Prevention and

Control of Pollution)

Act, 1981

Throughout

the Corridor

Ambient air quality

(PM10, CO, NOx)

Survival rate of

trees planted

As per

CPCB

requirements

Site

inspection

Included in

Operation/

Maintenance

cost

Contractor MPRDC/ CSC

2. Noise

2.1 Noise due to

movement of traffic

Effective traffic management and good riding conditions shall be maintained to reduce the noise level throughout the stretch and speed limitation and honking restrictions may be enforced near sensitive locations.

The effectiveness of the multilayered plantation should be monitored and if need be, solid noise barrier shall be placed.

Create awareness amongst the residents about likely noise levels from road operation at different distances, the safe ambient noise limits and easy to implement noise reduction measures while constructing a building close to the road.

Noise Pollution

(Regulation

and Control)

Rules, 2000

and amendments

thereof

Sensitive

receptors

Noise levels Noise

monitoring

as per noise

rules ,2000

Discussion

with people

in sensitive

receptor

sites

Included in

Operation/

Maintenance

cost

Contractor MPRDC/ CSC

3. Land and Soil

3.1 Soil erosion at embankment

Periodic checking to be carried to assess the effectiveness of the

Project

requirement

At bridge

locations and

Existence of soil

erosion sites

On site

observation

Included in Construction

Contractor MPRDC/ CSC

Page 210: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 371

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

during heavy rain fall.

stabilization measures viz. turfing, stone pitching, river training structures etc.

Necessary measures to be followed wherever there are failures

embankment

slopes and

other probable soil erosion areas.

Number of soil

erosion sites

cost

4. Water resources/Flooding and Inundation

4.1 Siltation Regular checks shall be made for soil erosion and turfing conditions of river training structures for its effective maintenance.

Project

requirement

Near

surface

Water

bodies

Water quality Site

observation

Included in

Operation/

Maintenance

cost

Contractor MPRDC/ CSC

4.2 Water logging due to blockage of

drains, culverts or streams

Regular visual checks and cleaning of drains shall be done along the alignment to ensure that flow of water is maintained through cross drains and other channels/streams.

Monitoring of water borne diseases due to stagnant water bodies

Project

requirement

Near

surface

Water

bodies

Presence of

flooded areas or

areas with water

stagnation

Site

observation

Included in

Operation/

Maintenance

cost

Contractor MPRDC/ CSC

4.3 Road inundation

due to choking of

drainage channels

MPRDC will ensure that all drains (side drains and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

Project

requirement

Flood prone

sections

Incidents of

flooding and road

inundation with

details on

change

Field

observation

Interaction

with local

community

Included in

Operation/

Maintenance

cost

Contractor MPRDC/ CSC

5. Flora

5.1 Vegetation Planted trees, shrubs, and grasses to be properly maintained.

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness

Forest

Conservation Act

1980

Project tree

plantation

sites

Minimum of 70%

of tree survival

Records

and fields

observations

Operation

and

Maintenance

Cost

Contractor MPRDC/ CSC

6. Maintenance of Right of Way and Safety

6.1 Accident Risk

due to uncontrolled

growth of

vegetation

Efforts shall be made to make shoulder completely clear of vegetation.

Regular maintenance of plantation along the road side.

Invasive plant not to be planted near the road.

Project

requirement

Throughout

the Project

route

Presence of and

extent of

vegetation growth

on either side of

road

Accident data

Visual

Inspection

Accident

records

Included in

operation/

Maintenance cost

Contractor MPRDC/ CSC

6.2 Accident risks associated with traffic movement.

Traffic control measures, including speed limits, will be enforced strictly.

Further encroachment of squatters within the ROW will be prevented.

No school or hospital will be allowed to be established beyond the stipulated planning line as per

relevant local law

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

IRC:SP:55 Throughout

the Project

route

Police records on

Accident

Condition and

existence of safety

signs, rumble

strips etc. on the

road

Presence/absence

of sensitive

receptor structures

inside the

Review

accident

records

Site

observation

Included in

operation/

Maintenance

cost

Contractor MPRDC/ CSC

Page 211: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

372 Appendix 8

Environmental Issue/

Component

Remedial Measure Reference to laws

/guidelines

Location Monitoring indicators Monitoring Methods

Mitigation Coast

Institutional Responsibility

Implementation Supervision

Highway patrol unit(s) for round the clock patrolling. Phone booths for accidental reporting and ambulance services with minimum response time for rescue of any accident victims, if possible.

Tow-away facility for the break down vehicles if possible.

stipulated planning

line as per

relevant local law

6.3 Transport of

Dangerous Goods Existence of spill prevention and

control and emergency responsive system

Emergency plan for vehicles carrying hazardous material

Throughout

the project

stretch

Status of

emergency

system – whether

operational or not

Review of

spill

prevention

and

emergency

response

system

Included in

operation/

Maintenance

cost.

Contractor MPRDC/ CSC

Note: EA Executing Agency, MPRDC: Madhya Pradesh Road Development Corporation, EO: Environmental Officer, IRC Indian Road Congress.

a) The “Project engineer” or “the engineer” is the team of Construction Supervision Consultants (CSC) responsible for approving the plans, engineering drawing, release of payments to contractor etc. on behalf of the employer (MPRDC). It is usually the team leader of the CSC that takes the responsibility of signing approval documents on behalf of the CSC team.

b) The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving

activities specific to environment safeguards on behalf of “the engineer”.

Page 212: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 8 373

Environmental Monitoring Plan (Contract Package No. 8) Environmental Components

Monitoring Location Frequency

Institutional Responsibility

Parameters Special Guidance Standards Implementation Supervision

Air PM2.5,PM10,

SO2,NOX,CO

AsperCPCB guidelines TheAir (Prevention&Controlof Pollution)Rules, CPCB,1982

Atsiteswhere hotmixplant/batchingplant is located

3 times in a year for 3 years or construction period at 3 sites & once in year for five years at 3 sites during operation/ defect liability period

Contractorthrough approved

monitoringagency

PIU,MPRDC, CSC

Water pH, BOD, COD, TDS, TSS, DO, Total coliform, Conductivity, Oil & Grease

Grab sample collected from source and analyze as per standard methods for examination of water and wastewater

Water quality standards by CPCB

river tributaries, roadside ponds and ground water at construction camp sites

Once during preconstruction stage 3 times in a year for 3 years or construction period at 3 locations

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

NoiseLevels Noise level for day and night on dB(A) scale

In free field at 1m distance from the equipment to be monitored

Noise standard by CPCB

At equipment yards, camp and villages along the alignment.

3 times in a year for 3 years or construction period, 3 locations & once in a year for 5 years at 3 sites during operation/defect liability period.

Contractor through approved

monitoring agency

PIU,MPRDC, CSC

Soilquality Monitoring of NPK & heavy metals and grease

As per IRC code of practice

Ad hock if accident/ spill locations involving bulk transport of carrying hazardous materials

- PIU through an approved agency

PIU,MPRDC

Road side Plantation

Monitoring of felling of trees

It should be ensured that the marked trees are felled only

As given in the IEE report

All along the corridor During the felling of trees Forest department PIU,MPRDC

Survival rate of trees, success of re- vegetation

The number of trees surviving during each visit should be compared with the number of saplings planted

The survival rate should be at least 75% below which re-plantation should be done

At locations of compensatory afforestation

Every year for 3 years PIU PIU,MPRDC

Note Madhya Pradesh Road Development Corporation, PIU- Project Implementation Unit, CSC- Construction Supervision Consultant

Page 213: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

374 Appendix 9

Appendix 9: Guidelines for Tree Plantation and Management

Preparation of the Plantation Area: For plantation in new areas it always economical and comfortable to plant trees in blocks. The open areas near the subproject roads will be identified and selected. During the selection of the block plantation sites, the availability of the water in nearby areas will be taken into consideration as the survival of the tree saplings depends on the availability of water or watering facilities.

Preparation of Pits and Sapling Transplantation: The location of each plantation pit will be marked according to the design and distance of the plantation. The size of the plantation pit varies depending upon the species of the plants, height of the saplings. Trees will be planted on the alternate rows in a straight line for the prevention of the horizontal dispersion of the pollutants. Hence the pit will be dig accordingly. During the time of placing the tree saplings the roots will be freed from plastic or any type of cover which is normally use for the transplantation of the tree saplings from the seed bed to the tree plantation pits. This exercise will help the root hairs to reach the soil.

Spacing: For the survivability of the tree species planted spacing between the saplings should be maintained. Spacing which are usually used for teak planting are 2 x 2 m2, 3 x 1 m2, 3 x 3 m2, 4 x 2 m2 and 4 x 4 m2, depending on site condition. However, wider spacing of 6 x 1 m2 can also be adopted sometimes where the survivability is high. Closer spacing is used for straight timber of good quality.

Time of Plantation: As per the normal practices followed under the silvicultural guidelines plantation of the tree sapling to be done only after the first shower during the rainy season. The best time for plantation is after 15 days from the day of first shower during rainy season.

Protection of Tree saplings: Circular tree guard should be placed after the plantation of the saplings for the protection of these young plants from the ravages of cattle, sheep and goat and other animals. If tree saplings died or damage occur after placing the circular tree guard, timely replacements of damaged plant and thereafter care is important.

Selection of Tree Species: The selection of the tree species to be planted plays a crucial role for higher survivability rate. This is always better to choose the local and Vulnerable, endemic species.

Maintenance (include thinning) : Weeding: Low pruning at 6 months, Thinning: Thinning will start after the stand is 3-4 years old and repeated every 4 years until the stand is 15 years old. Between 15-25 years old, thinning should be conducted every 5 years and after 25 years old, thinning will be done after every 10 years. When the canopy closes, at about 6 years, 30-40% of the stems will be thinned to selectively remove suppressed, diseased and badly formed trees.

Survivability: Periodic assessment will be carried for survivability of the trees. Minimum

70% survival rate will be achieved.

Records: The following records will be maintained: 1. Record of Tree plantation 2. Record of Survivability rate

Reporting: The tree plantation and survivability report will be sent to EA six monthly

Page 214: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 9 375

Responsibility: Prime Responsibility: PIU through contractor or Forest Department Contractor will be responsible for tree cutting or plantation Supervisory Responsibility: Supervision Consultant to check compliance of above guidelines.

Page 215: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

376 Appendix 10

Appendix 10: Guidelines for Borrow Area Management

Selection and Rehabilitation of Borrow Pits: Guidelines for selection of borrow pits, amount that can be borrowed and its rehabilitation in line with The Indian Road Congress (IRC):10-1961 will be followed and are as follows:

Contractor must identify the borrow areas before start of construction and submit these details with rehabilitation plan.

Borrow areas will not be located on cultivable lands. However, if it becomes necessary to borrow earth from temporarily acquired cultivated lands, their depth will not exceed 45 cm. The topsoil to a depth of 15cm will be stripped and set aside. Thereafter, soil may be dug out to a further depth not exceeding 30 cm and used in forming the embankment.

A 15 cm topsoil will be stripped off from the borrow pit and this will be stored in stockpiles in a designated area for height not exceeding 2m and side slopes not steeper than 1:2 (Vertical: Horizontal).

Ridges of not less than 8m widths will be left at intervals not exceeding 300m. Small drains will be cut through the ridges, if necessary, to facilitate drainage. The slope of the edges will be maintained not steeper than 1:4 (vertical: Horizontal).

Borrow pit will be selected from wasteland ;

Priority will be given to the borrowing from humps above the general ground level within the road land;

Priority will be given to the borrowing by excavating/enlarging existing tanks;

Borrowing will be from land acquired temporarily and located at least 500m away from the road;

Borrowing will be from mounds resulting from the digging of well and lowering of agricultural fields in vicinity of the road;

Borrow area near to any surface water body will be at least at a distance of 15m from the toe of the bank or high flood level, whichever is maximum.

In case of settlements, borrow pits will not be selected within a distance 800 m from towns or villages. If unavoidable, earth excavation will not exceed 30cm in depth;

The haulage distance from site will not be too far.

Redevelopment plan will be prepared by the contractor before the start of work which should be duly agreed upon by land owner.

Borrow pits will be backfilled with rejected construction wastes and covered with vegetation.

Borrow areas might be used for aquaculture in case landowner wants such development.

Borrow pits located near habitat areas will be re-developed immediately after borrowing is completed. If spoils are dumped, that will be covered with a layers of stockpiled topsoil in accordance with compliance requirements with respect MOEFCC/SPCB guidelines.

Prohibit dumping of waste except inert construction rubble

Records: The following records will be maintained: 1. List of Borrow areas identification with capacity and rehabilitation plan 2. Agreement with land owners where applicable 3. Details of Earth excavated 4. Closure report of rehabilitated borrow pits.

Reporting: The Borrow area opening, earth borrowed and borrow area rehabilitation details will form part of half yearly report

Page 216: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 10 377

Responsibility:

Prime Responsibility: Contractor will be responsible for borrow area management and reporting

Supervisory Responsibility: Supervision Consultant will check compliance with the above guidelines.

Page 217: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

378 Appendix 11

Appendix 11: Guidelines for Emergency Management System

Many emergencies can occur in construction sites and will need to be effectively handled. The environmental and occupational health and safety aspects and related emergency can includes incidence such as Collapse / subsidence of soil / Fire / Explosion / Gas Leak, Collapse of Building / Equipment and other Occupational Accidents. On site and off site emergency management plan will be developed to effectively handle them. The following guidelines will be used to develop these plans Guidelines: Availability of ‘On-Site Emergency Management Plan’

The contractor will have a written on site emergency management plan. The contractor should submit a copy of this plan to MPRDC and the Supervision Consultant before the start of the work.

Contractor will develop the onsite emergency plan considering the potential environmental, occupational health and safety emergency situation at site.

Contractor will include a list of potential emergency situations in the emergency management plan including potential Environmental and Occupational Health and Safety Emergency Situations during construction, operation and maintenance stages.

Examples of potential emergency situations have been defined below for guidance purposes. The contractors may follow refer to this for developing site specific on site emergency preparedness plan.

Emergency conditions / situations Sources

Collapse / subsidence of soil and structures

Civil structures Heavy construction machinery

Bulk spillage Hazardous substance / inflammable liquid storage

Vehicular movement on highway

Fire and explosion Inflammable Storage Areas Gas Cylinder Storage Areas Electrical Circuits Isolated Gas Cylinders (LPG / DA) Welding / Gas Cutting Activity

Flooding Heavy monsoons Upstream activities of irrigation or damming Glacial lake outburst Flood at the source of the

river

Electrical Shock HT line LT distribution Electrically Operated Machines / Equipment /

Hand Tools / Electrical Cables

Gaseous Leakage Gas Cylinder Storage Areas Gas Cylinder used in Gas Cutting / Welding

Purposes

Accidents due to Vehicles Heavy Earth Moving Machinery Cranes Fork Lifts Trucks Workman Transport Vehicles (cars / scooters /

motor cycles / cycles) Collapse, toppling or collision of transport

equipment

Page 218: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 11 379

Emergency conditions / situations Sources

Slips & Falls (Man & Material)

Work at Height (Roof Work, Steel Erection, Scaffold, Repair & Maintenance, Erection of equipment, Excavation etc.)

Slips (Watery surfaces due to rain) Lifting tools & Tackles (Electric Hoist &

Forklifts) Falling into the river and drowning

Collision with stationary / moving objects

Vehicular movement on highway

Other Hazards Cuts &Wounds Confined Space (under & inside machinery

etc.) Hot Burns Pressure Impacts (Plant contains several

Pressure Vessels & pipefitting containing CO2, Air, Water, product & Steam, which can cause accidents & injuries to person around.)

Design of ‘On-Site Emergency Plan: The ‘On-site emergency plan’ to be prepared by contractor will include a minimum of the following information :

Name & Address of Contractor

Updation sheet

Project Location

Name, Designation & Contact Numbers of the organization, nearby hospitals, fire agencies etc. and key personnel including their assigned responsibilities in case of an emergency.

The roles and responsibilities of executing personnel

Site Layout Diagram

Identification of Potential Emergencies Situations/ preventive measures / control & response measures

Location of Emergency Control Centre (or designated area for emergency control / coordination) with requisite facilities.

Medical services / first aid

List of emergency equipment including fire extinguishers, fire suits etc.

Emergency Control Centre: The emergency control centre will be equipped with following facilities

Copy of current on-site emergency plan

Display of the name of site emergency controller

Appropriate numbers of artificial respiratory sets

Appropriate numbers of Stretchers

Vehicle/ambulances on each construction site for 24 hours

Adequate and reliable communication facilities (phone, handset etc.)

Site layout diagram with entry and exit routes / Assembly points

Directory of internal / external emergency phone Numbers

Fire extinguishers (DCP type / Foam Type / CO2) on all construction camps and yards

List of fire extinguishers installed in the construction sites and yards including maintenance records

A set of personal protective equipment (PPE) for each and every member of the construction team

Page 219: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

380 Appendix 11

First-aid boxes with prescribed first-aid medicines in every construction camp site and yard

List of competent first-aiders

List of fire trained personnel

Appropriate numbers of blankets, rescue ropes and high beam torches

Drinking water

Gas leak detectors

Life boats & jackets Records: The following records will be maintained:

1. Record of emergency preparedness plan with emergency contact numbers 2. Mock drill/emergency preparedness exercise records 3. Corrective preventive action record after emergency is occurred

Reporting: The accident and incident records and emergency preparedness drill reports will form part of quarterly report to MPRDC and the Supervision Consultant

Responsibility:

Prime Responsibility: Contractor will be responsible for implementing the Emergency plan and reporting Supervisory Responsibility: The Supervision Consultant will check compliance of the contractor with the above guidelines

Page 220: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 12 381

Appendix 12: Guidelines for Waste Disposal and Management

A Waste disposal and management plan will be prepared by the contractor before start of construction works and submitted to MPRDC and the Supervision Consultantfor their review and approval. The management plan will follow the guidelines as given below:

(i) The debris disposal site should be identified which are preferably barren or low-lying areas away from settlements.

(ii) Prior concurrence will be taken from concerned Govt. Authorities or land owner

(iii) Due care should be taken during site clearance and disposal of debris so that public/ private properties are not damage or effected, no traffic are interrupted.

(iv) All efforts should be made to use debris in road construction or any other public utilities.

(v) The debris should be stored at site ensuring that existing water bodies and drains within or adjacent to the site are kept safe and free and no blocking of drains occurs.

(vi) All dust prone material should be transported in a covered truck. (vii) All liquid waste like oils and paint waste should be stored at identified

locations and preferably on a cemented floor. Provision of spill collection pit will be made in the floor to collect the spilled oil or paint. These should be sold off to authorized recyclers.

(viii) All domestic waste generated at construction camp preferably be composted in portable mechanized composter. The composted material will be used as manure. In case composting is not feasible, the material will either be disposed off though municipal waste disposal system or disposed of through land burial. The dump site must be covered up with at least six inch thick layer of soil.

(ix) Only appropriately design and compliant landfills will be used for disposing waste

(x) All efforts should be made that no chemical/ oily waste spill over to ground or water bodies.

(xi) All precautions should be followed for emergency preparedness and occupational health & safety during construction and handling a waste.

(xii) Provision of fire extinguishers will be made at the storage area (xiii) Adequate traffic control signals and barriers should be used in case traffic is

to be diverted during debris disposal. All efforts should be made to ensure avoidance of traffic jam, which otherwise results in air pollution, noise pollution and public unrest.

(xiv) Hazardous waste and chemicals should be stored in a dedicated storage area that has: 1) weather protection, 2) solid impermeable surface and drainage to treatment system, 3) security fence/lock, 4) primary and secondary containment with 110% volume for liquids.

(xv) Domestic waste shall only be disposed of at the approved, appropriately designed, compliant waste management facility (landfill). Land burial of waste shall not be permitted.

Records: The following records will be maintained

Generation and disposal quantity with location of disposal

Recyclables waste generation and disposal

Domestic waste disposal locations details

Reporting:The waste generation and disposal details will form part of quarterly report to MPRDCL

Page 221: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

382 Appendix 12

Responsibility:

Prime Responsibility: Contractor will be responsible for waste management and reporting Supervisory Responsibility: Supervision Consultantwill check the contractor’s adherence to the above guidelines

Page 222: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 13 383

Appendix 13: Outline of an Environmental Monitoring Report

1. Introduction

(Report Purpose, Brief project background including organizational set up, list of roads, planned project schedule etc., Details on Project Implementation Progress with details on current site works, location, earthworks, vegetation clearing, spoils disposal, establishment of construction camp and other construction related facilities (e.g., concrete mixing plant, asphalt batching plant, crushing plant, etc.), establishment and operation of quarry/borrow areas, etc., including locations, schedules, dates, etc., Schedule of construction activities for the subsequent months).

2. Compliance on Environment Safeguards Requirements

(Status of compliance with ADB loan covenants: provide a list of environmental loan covenants and specify level of compliance). Status of compliance with government environmental requirements: provide a list of government environmental requirements (permits, etc.) for the project as well as construction-related facilities/ activities and specify level of compliance, indicate any required environmental permit/license/consent obtained to date and to be obtained (including schedule) for the project and construction related facilities/activities).

3. Changes in project scope

(Such as change in alignment or footprint in case of horizontal infrastructure, implementation of additional Project component/s, etc. (with reference to the Project scope identified in the ADB-cleared environmental assessment report , i.e., IEE or EIA) and corresponding safeguard measures undertaken, if applicable).

4. Implementation of Environmental Management Plan

(Indicate the manner by which EMP requirements are incorporated into contractual arrangements, such as with contractors or other parties. Summary of Environmental Mitigations and Compensation Measures Implemented. Based on EMP; may include measures related to air quality, water quality, noise quality, pollution prevention, biodiversity and natural resources, health and safety, physical cultural resources, capacity building, and others. Provide a table/matrix showing a summary of each environmental mitigation measure specified in the EMP.

EMP Requirement (list all mitigation measures specified in the EMP)

Compliance Attained (Yes, No, Partial)

Comment on Reasons for Partial or Non-Compliance

Issues for Further Action and Target

Dates

1.

2.

3.

4.

5.

etc.

5. Environmental Monitoring Activities

Page 223: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

384 Appendix 13

(Compliance Inspections, Summary of Inspection Activities, Mitigation Compliance15 Mitigation Effectiveness 16. Findings of Environmental Monitoring Plan (EMOP) on quality of air, noise, water etc. and Results Assessment17)

6. Key Environmental Issues

(Key Issues Identified (e.g., non-compliance to loan covenants, EMP and/or government environmental requirements, insufficient mitigation measures to address Project impacts, incidents, accidents, etc.) Actions Taken and Corrective Action Plan (specify actions taken and corrective action plans to be implemented to address non-compliance and other identified issues. Such action plan should provide details of specific actions to be undertaken to resolve identified issues, responsible persons who will carry out such actions and timeframe/target date to carry out and complete required actions. The action plan could be presented in a tabular/matrix form (see below). Timeframe and responsibilities for reporting to ADB on the progress of implementation of corrective action plan should also be specified under this section.)

Issue Cause Required

Action Responsibility

Timing (Target Dates)

Description of Resolution and Timing (Actual)

Old Issues from Previous Reports

1.

2.

New Issues from this Report

1.

2.

Complaints: Details of Complaint/s (Provide details of any complaints that have been raised by the local population and other stakeholders regarding environmental performance and environmental impacts (complainant, nature of complaint, date complaint was filed, which office received the complaint, etc.) Action Taken (Document how the complaints were addressed or will be addressed by indicating the following:

15

Overall compliance with mitigation implementation requirements could be described in qualitative terms or be

evaluated based on a ranking system, such as the following: 1. Very Good (all required mitigations implemented) 2. Good (the majority of required mitigations implemented) 3. Fair (some mitigations implemented) 4. Poor (few mitigations implemented) 5. Very Poor (very few or no mitigations implemented)

Additional explanatory comments should be provided as necessary. 16

Effectiveness of mitigation implementation could be described in qualitative terms or be evaluated based on a

ranking system, such as the following: 1. Very Good (mitigations are fully effective) 2. Good (mitigations are generally effective) 3. Fair (mitigations are partially effective) 4. Poor (mitigations are generally ineffective) 5. Very Poor (mitigations are completely ineffective)

Additional explanatory comments should be provided as necessary. 17

Discharge levels should be compared to the relevant discharge standards and/or performance indicators noted in

the EMP. Any exceedences should be highlighted for attention and follow-up. In addition, discharge levels could be compared to baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:

1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)

Additional explanatory comments should be provided as necessary.

Page 224: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 13 385

i. names and designation of specific staff or officials within the Grievance Redress

Committee, executing agency, project management unit, local government, contractor and/or supervision consultant involved in receiving, documenting, and resolving the complaint (s).

ii. specific actions taken to be taken to resolve the complaint and corresponding timeframe

7. Conclusion and Recommendation

Overall Progress of Implementation of Environmental Management Measures18

Problems Identified and Actions Recommended Monitoring adjustment (recommended monitoring modifications based on monitoring experience/trends and stakeholders response)

8. Appendices

Site Inspection / Monitoring Reports Source and Ambient Monitoring Results (Laboratory Analysis) Photographs Location Map of Sampling Stations Copies of Environmental Permits/Approvals Other relevant information/documents

18

Overall sector environmental management progress could be described in qualitative terms or be evaluated based

on a ranking system, such as the following: 1. Very Good 2. Good 3. Fair 4. Poor 5. Very Poor

Additional explanatory comments should be provided as necessary.

Page 225: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

386 Appendix 14

Appendix 14: Impacts of Climate Change on Road Transport in the State of Madhya Pradesh

1. Introduction

In general, transport can be vulnerable to many different types of weather conditions, of which, some of them could be exacerbated with climate change. Many of them relate to extreme weather conditions (e.g. storms, extreme precipitations, extreme temperatures) which on their turn may result in severe consequences for the physical environment (e.g. floods, landslides,…) and represent risks for transport infrastructures and operations.

Depending on future global warming and the region of Madhya Pradesh in India, transport modes and system components could be affected by one or several simultaneous changes in climate conditions, including hotter summers, extreme precipitation events and increased storminess. If such impacts are not anticipated in future transport infrastructure design and maintenance, those changing weather conditions could, in some regions, accelerate their deterioration, increase severe damages risks, traffic interruption and accidents which could, on their turn, affect economic activities.

Districts in Madhya Pradesh are identified as being amongst the highest in India in terms of social vulnerability in a study which examined exposure to the effects of climate change and economic globalization19. Natural calamities like drought, floods and hailstorms are a common feature for the state. Almost every year one or other part of the state is generally hot. The MP State of Environment report has analyzed the natural disasters in the state (mainly drought, floods and heat waves).

2. Literature Review on Climate Variability over Madhya Pradesh

2.1 Madhya Pradesh State Action Plan on Climate Change (MP SAPCC)20 This draft version of the State Action Plan on Climate Change (MP SAPCC), developed by the Government of Madhya Pradesh (GoMP), aims to address the regional concerns and to outline strategies required to develop a climate resilient state. The strategies and recommendations of the MPSAPCC intend in due course, to strengthen the developmental planning process of the state with policy level interventions favoring low carbon growth. Chapter 4 of draft MP SAPCC report, on observed climate trends and projected climate change, mentions Madhya Pradesh to have a subtropical climate with three distinct seasons, viz. winter from December to February followed by summer season from March to May and rainy season extending from June to October. During winters the mean temperature remains around 100C and mean maximum temperature remains 250C and the minimum temperature goes down to 10C in some regions. During summers, the mean minimum temperature is 220C and mean maximum is 380C. The maximum temperature during summer can go up to 480C, especially in May and June which are the hottest months. The average annual rainfall for the state is 1160 mm. Rainfall is heaviest in the south-eastern parts of the state and it decreases as one move towards the north-west. Balaghat in the south receives the maximum rains; where average rainfall is above 1600 mm. The other southern districts of Mandla, Dindori and Anuppur receive between 1200-1400 mm of rain. The rainfall drops to the 1000-1200 mm as one move further north and west. Western districts in MP including most of those in the Malwa plateau and Sheopur and Shivpuri in the north receives

19

O‟Brien, K R., Leichenko, U, Kelkar, H. Venema. G. Aandahl, H. Tomkins, A. Javed, S. Bhadwal, S. Barg, L. Nygaard and J. West, 2004; Mapping vulnerability to multiple stressors: climate change and globalisation in India. Global Environmental Change vol 14 p303-313.

20Prepared by Environmental Planning and Coordination Organization (EPCO), Housing and Environment

Department, Government of Madhya Pradesh (GoMP), a collaborative effort between the GoMP and UNDP, February, 2012; (www.epco.in)

Page 226: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 14 387

800-1000 mm of rain. Average annual rainfall is below 800 mm in the south-western tip of the state, including southern half of Jhabua and western half of Barwani district. The rainfall is below 800 mm in the districts lying in the north most part of the state including Morena, Datia, Gwalior and Bhind. Most of the rainfall in the state is received from the south-west monsoon during June to September Trends of average annual monsoon rain fall analyzed for the period 1961 to 2002 show an inter-annual variability of average monsoon rain fall in the 41 year period, and the rain fall trend is seen to be decreasing as deciphered from the negative slope of the equation representing the linear trends. Further a study carried out by Goswami et al (2006)21, for observations spanning 50 years in the Central Indian region including Madhya Pradesh, indicates that the extreme precipitation events which are above 100 mm are increasing in terms of their intensity and frequency, with low and moderate events becoming more and more infrequent. 2.2 Climate Projections – MP SAPCC draft report The MP SAPCC draft report provides climate projections for 2030s (2021-2050) and 2080s (2071-2098) that have been derived from PRECIS (Providing Regional Climate for Impact Studies), which is a desktop version of the HadRM3 model with a grid resolution of 0.44° x 0.44°. PRECIS simulation dataset was provided by the Indian Institute of Tropical Meteorology, Pune. The climate change scenarios were driven by the GHG emission scenarios - A1B which assumes a future world of very rapid economic growth, a global population that peaks in mid-century and declines thereafter, and assumes rapid introduction of new and more efficient technologies. Change in precipitation and temperature in 2030s and end of the century 2080s have been derived with respect to 1970s (1961-1990). 2.2.1 Temperature The average surface daily maximum temperatures, in the period 2030s is projected to rise by 1.8-2.0oC throughout Madhya Pradesh and the daily minimum temperature is projected to rise between 2.0oC to 2.4oC during the same period; the eastern half of the state experiencing more warming than the western half. By 2080s, the maximum temperature is projected to rise between 3.4oC to 4.4oC with northern region experiencing warmer temperatures. 2.2.2 Rainfall Projections of rainfall in Madhya Pradesh for the period 2021 to 2050 indicate that there is likely to be decrease in winter rainfall as one move from eastern part of MP to western part of MP. In pre-monsoon period, the rainfall is increasing only in the Southern part of MP, with decrease in rain fall in all other parts. In the Monsoon period, there is a slight increase in rainfall all over MP (the increase being 1.25 times the rainfall observed in the current climate), and with no change in the Morena, Shivpuri, Bhind, and Gwalior areas. During post monsoon period, slowly again the western end of MP is likely to face decrease in rain fall, with no change or little increase in rainfall in most other parts of the state. In 2100 there is an overall increase in rain fall with southern states likely to receive more rain fall in the northern states. The increase in rain fall during the post monsoon and pre monsoon periods are projected to be more than the increase in rain falls projected for the monsoon period. Table 1 summarizes the projected changes in climate parameters as derived from PRECIS.

Table 1 Projected Changes in Climate Parameters for the State of Madhya Pradesh

Projected Changes in Climate 2021-2050 2071-2100

Daily maximum temperatures 1.8 - 2oC increase 3.4 - 4.4

oC increase

Daily Minimum Temperatures 2.0 - 2.4oC increase > 4.4

oC increase

21

B. N. Goswami, V. Venugopal, D. Sengupta, M. S. Madhusoodanan,2 Prince K. Xavier; Increasing Trend of Extreme Rain Events Over India in a Warming Environment, Science 1 December 2006: Vol. 314. no. 5804, pp. 1442 - 1445

Page 227: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

388 Appendix 14

Monsoon Precipitation Increase in precipitation by 1.25 times the current observed rainfall in most parts of Madhya Pradesh; No change in Morena, Shivpuri, Gwalior and Bhind; Increase in precipitation in eastern parts of Hoshangabad, northern part of Betul, north eastern parts of Betul and Southern part of Sehore

More than 1.35 times increase in precipitation with respect to observed climate in most parts of Madhya Pradesh. With major parts of Hoshangabad and Damoh, Manldla and northern parts of Balaghat will experience rain in excess of 1.45 times the observed climate now. The extreme northern and western part of the state will also experience excess rainfall but less than most of the other areas

Winter Precipitation Decrease in precipitation Substantial increase in precipitation in Central and South western part of Madhya Pradesh increasing from between 1.45 to 1.85 times

(Source: MP SAPCC, Govt. of Madhya Pradesh, Draft Version, 2012)

2.3 Chapter V - Anticipated Environmental Impacts and Mitigation Measures22 (Section D of Chapter V on “Climate Risks and Adaptation needs” is reproduced here as under) Climate risks were identified following both top down and bottom up approaches. Under the top down approach changes of key climate parameters, mainly temperature and precipitation were projected for 2050 using an ensemble of Global Climate Models (GCMs). Given the projected variations of temperature and precipitation the project roads were screened for 9 types of climate risks:

a. Landslide triggered by increased precipitation b. Fire c. Flood d. Drought e. Tsunami f. Cyclone wind g. Cyclone surge h. Sea level rise i. Coastal erosion

Climate risk maps based on information from the GCMs were created for the project area using Geographic Information System (GIS) maps. After overlaying the road locations on the climate risk maps low to medium risks identified for the project roads were flooding, landslides triggered by precipitation, coastal erosion and tsunami. The overall climate change risk level identified from the above exercise is low. The key risk identified is flooding (increased storminess). Bridges and road embankments are the main project components that will be prone to flooding. Increase in temperature may also affect road safety. Under the bottom up approach the flood prone areas in the project road were identified based on field surveys for the engineering design. Key engineering measures taken to address the risk of flooding in the design are: increase in road embankment height in flood prone areas/sections, improvement and provision of lined longitudinal and cross drains and new culverts, improvement and new construction of minor and

22

Initial Environmental Examination, IND: Madhya Pradesh District Connectivity Project, Jarkua – Raigaon-Karsara Road, Prepared by Madhya Pradesh Road Development Corporation for the Asian Development Bank, 2015

Page 228: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 14 389

major bridges. Bridge heights have been designed to have a height of 0.6m above HFL for minor bridges and 0.9m above HFL for major bridges. Flood return period of 50 years for minor bridges and 100 years for major bridges have been considered. 3. Climate Change Effects on Indian Roads

Conventionally, roads and highways are designed based on historic climate, however during their design life they could well be subjected to a very different climate. The vulnerability of highways to climate change would depend on factors such as pavement type and condition and also on location-specific factors such as geology, traffic flow, and proximity to water courses. Climate change induced deterioration will create more severe damage through increased frequency of extreme events and will necessitate more routine and structural maintenance. The cost of not taking climate change into consideration could be vast in terms of traffic disruption, public safety and infrastructure repairs.

3.1 Extreme High Temperature

The state of Madhya Pradesh is no stranger to heat extremes and heat waves. Under climate change scenario, heat extremes and heat waves are likely to become more intense, longer lasting, and more frequent during this century. Increasing periods of extreme heat will place additional stress on infrastructure, reducing service life and increasing maintenance needs. Extreme maximum temperature and prolonged duration heat waves are expected to lead to premature deterioration of infrastructure. Temperature increases have the potential to affect and reduce the life of asphalt road pavements through softening and traffic-related rutting. Extreme heat can also stress the steel in bridges through thermal expansion and movement of bridge joints and paved surfaces.

Highway pavements historically have been constructed from a combination of locally available natural materials, including natural soils, select soils such as natural gravel, and processed material such as quarried stone. Pavements are constructed in layers with the weaker or least durable materials at the bottom and the stronger or most durable materials at the top. The top layers are normally bound together with some sort of binder. Commonly used binders include hydraulic cements and bituminous cements. The most widely used binder in India is asphalt, a bituminous cement which is a petroleum product refined from crude oil. What makes asphalt desirable for pavement construction is its tendency to stick to the granular material used in the upper pavement layers and thus to keep this material in place. In addition, when asphalt is heated, it becomes very fluid and can be mixed with gravel or rock, making it an easy material to process in the mass quantities required for pavement construction.

4. Extreme Value Analysis (EVA)

The following abridged paragraphs as adopted from a WMO 23 publication highlights the rationale for focusing on weather and climate extremes. Changes in extreme weather and climate events are now recognized to have significant impacts and are among the most serious challenges to society in coping with a changing climate. Many practical problems require knowledge of the behavior of extreme values. In particular, the infrastructures we depend upon for food, water, energy, shelter and transportation are sensitive to high or low values of meteorological variables. For example, high precipitation amounts and resulting stream flows affect sewerage systems, dams, reservoirs and bridges. The motivation for analyzing extremes is often to find an optimum balance between adopting high safety standards that are very costly on the one hand, and preventing major damage to equipment and structures from extreme events that are likely to occur during the useful life of such infrastructure on the other hand.

23

Guidelines on Analysis of Extremes in a Changing Climate in Support of Informed Decisions for Adaptation;

Climate Data and Monitoring. WCDMP-72, 2009

Page 229: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

390 Appendix 14

Most existing systems for water management and other infrastructure have been designed under the assumption that climate is stationary. This basic concept from which engineers work assumes that climate is variable, but with variations whose properties are constant with time, and which occur around an unchanging mean state. This assumption of stationarity is still common practice for design criteria for (the safety of) new infrastructure, even though the notion that climate change may alter the mean, variability and extremes of relevant weather variables is now widely accepted. New infrastructure is typically designed on the basis of historical information on weather and climate extremes. Often, the maximum value of a particular variable in the historical record is considered to be the normative value for design. In other cases, extreme value theory is applied to the historical observations of extremes to estimate the normative value, again disregarding climate change. The report states that it is possible to account for non-stationary conditions (climate change) in extreme value analysis, but scientists are still debating the best way to do this. Nevertheless, adaptation strategies to climate change should now begin to account for the decadal scale changes (or low-frequency variability) in extremes observed in the past decades, as well as projections of future changes in extremes such as are obtained from climate models. 4.1 Data Establishment A March 2013 draft EIA report24 for a proposed nuclear power plant to be located at Chutka, Mandla25 district of Madhya Pradesh, devotes a whole chapter on extreme value analysis of meteorological parameters. In gist, the general principles behind their EVA analysis for temperature and precipitation extremes, lies in the common practice of assumption of stationarity for deriving design criteria of the proposed nuclear power plant. Raw data on annual maximum and annual minimum temperatures (Table 4.1, Figure 4.1), and 1-hourly and 24-hourly precipitation maximum (Table 4.2, Figure 4.2) as recorded by the Indian Meteorological Department (IMD) weather station based at Mandla, Madhya Pradesh are extracted from the nuclear plant EIA report for non-stationarity analysis as recommended by WMO under a changing climate.

By the WMO guideline (WCDMP- No. 72), a pragmatic approach is to calculate trends for any specified period regardless of cause. Trends are the simplest component of climate change and provide information on the first-order changes over the time domain considered. This implies that the physical mechanisms behind the detected trends remain unknown. The calculated trends represent changes that can be due to natural internal processes within the climate system and/or external forcing, which can either be natural, such as solar irradiance and volcanic aerosols, or anthropogenic, such as greenhouse gases. Note that there are data gaps in both temperature and in the annual daily maximum precipitation data and a trend analysis would be highly ambiguous

24

Technical Report No. 4811,Volume II(a) – Annexure I-XIV and XVI-XXII, EIA for Proposed 2x700 MWe PHWR, Chutka Madhya Pradesh Atomic Power Project; March 2013; Nuclear Power Corporation of India Ltd. Mumbai, National Environmental Research Institute, Nagpur, India

25Mandla is a tribal district situated in east-central Madhya Pradesh within the catchment of river Narmada and its tributaries

Page 230: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 14 391

Of particular concern in the expansion and improvement of district roads in Madhya Pradesh, stresses induced on roadways by intense high temperatures and high intensity and high frequency precipitation as a result of warming climate need to be addressed as far best as possible. Such extreme weather conditions exacerbated under future climate change is widely recognized now, and if neglected in the very initial design of transport infrastructure, could lead to increasing risks thus negatively affecting transport performance in terms of safety, reliability, cost efficiency. Though the level of deterioration of roadways depends on a multiplicity of parameters, e.g. locations, soil, traffic load, etc., besides intense temperature and precipitation it is practically not possible to portray and specify plausible illumination covering the entire network of roadways. The next section (Sec. 4.2) attempts a benign uncovering of magnitudes of extremes in maximum temperature and precipitation that could lead the infrastructure designer to a more climate change focused consideration.

4.2 Extreme Maximum Temperature Estimation - Return Periods vs. Return Levels

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

50.0

1965 1970 1975 1980 1985 1990 1995 2000 2005 2010

Tem

pe

ratu

re, 0

C

Year

Figure 4.1 Annual Max and Min Temperature(Station: Mandla, MP)

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

160.0

180.0

200.0

1965 1970 1975 1980 1985 1990 1995 2000 2005 2010

Max

. R

ain

fall,

mm

Figure 4.2 1-hourly and 24-hourly Max Precipitation(Station: Mandla, MP)

Year Max Min

1969 45.0 2.2

1970 44.6 2.4

1971 42.0 2.0

1972 44.0 2.4

1973 46.8 2.0

1974 43.2 2.0

1975 43.6 2.7

1976 42.6 4.3

1977 43.5 2.5

1978 43.0 2.6

1979 43.6 2.7

1980 43.8 4.0

1981 44.2 3.5

1982 42.5 3.3

1983 42.8 3.1

1984 43.6 3.1

1985 43.8 0.1

1986 41.0 3.0

1987 41.0 0.0

1988 44.0 1.0

1989 42.0 1.0

1990 42.0 3.5

1991 42.0 0.5

1992 44.2 1.8

1993 44.5 4.0

1994 45.1 5.8

1995 40.7 3.0

1996

1997

1998

1999

2000

2001 43.7 2.5

2002 44.0 1.7

2003 45.0 2.4

2004 44.0 4.5

2005 44.2 4.0

2006 42.8 3.9

Table 4.1 Annual Daily Maximum & Minimum

Temperature (Mandla ARG), 0C

Year n=1 hr n= 24 hr

1969 39.5 111.0

1970 80.0 102.1

1971 46.4 102.4

1972 35.1 163.0

1973 67.5 105.6

1974 90.0 177.6

1975 39.0 79.8

1976 39.0 80.4

1977 43.0 120.0

1978 44.5 120.0

1979 35.5 84.0

1980 54.1 124.2

1981 70.0 148.2

1982 30.0 72.0

1983 50.5 113.4

1984 34.7 152.2

1985 41.3 92.4

1986 23.0 67.6

1987 43.5 84.0

1988 41.3 81.0

1989 41.5 141.0

1990 108.8

1991 52.3 92.2

1992 96.2

1993 82.0

1994 83.5

1995 145.8

1996

1997

1998

1999

2000

2001 111.5

2002 116.2

2003 101.2

2004 98.4

2005 178.2

2006 187.2

Table 4.2 Annual Max Rainfall (n-hourly,

mm, as recored at Mandla)

Page 231: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

392 Appendix 14

Extreme value statistics are used primarily to quantify the stochastic behavior of a process at unusually large (or small) values. Particularly, such analyses usually require estimation of the probability of events that are more extreme than any previously observed. Many fields have begun to use extreme value theory and some have been using it for a very long time including meteorology, hydrology, finance and ocean wave modeling to name just a few. The block maxima series (BMS) is one generally used method based on an explicit extreme value theory. In this method, one considers the sample of extreme values obtained by selecting the maximum (or in some cases, the minimum) value observed in each block. Blocks are typically one year in length (365 daily observations per block), or occasionally a season in length (for example, the summer maximum temperature, or winter minimum temperature). Statistical theory indicates that the Generalized Extreme Value (GEV) distribution is appropriate for the block maxima when blocks are sufficiently large. In its general form, the GEV distribution has three parameters: location μ, scale σ, and shape ξ. Parameters can be estimated by the method of maximum likelihood, the method of L-moments (also referred to as probability weighted moments), or simply the ordinary method of moments. The maximum likelihood approach is preferred when samples of extremes are sufficiently large and when there is a possibility that the climate may not be stationary. Extremes toolkit is a weather and climate applications of extreme value statistics developed by National Center for Atmospheric Research (NCAR, US) which can be downloaded at website: http://www.esig.ucar.edu/extremevalues/evtk.html Simulation is an approach when uncertainty is high due to sparse data and advantageously the toolkit takes care of that and projects the parameters for each simulation run. The parameter estimations of GEV simulated for the annual highest maximum temperature at Mandla are run using “extRemes Toolkit Ver1.6, R Ver2.9.2”. (Kindly note that raw data for temperature and precipitation for 33 years with obvious data gaps as depicted in Tables 4.1 and 4.2 above, were extracted from IMD’s meteorological station at Mandla, Madhya Pradesh, as annexed in the cited Technical Report No. 4811, footnoted 4 in page 7 of this assessment report). Although a disclaimer stating the above cited technical report as the property of National Power Corporation of India Limited (NPCIL) with all rights reserved, this report just took the liberty to glean the raw data as they had for this climate change extreme value analysis. None of their outputs are reproduced here. The simulated GEV parameters for a stationarity case (or the conventional approach where no trend exists) and followed by another simulation assuming a shift in the location parameter (μ) by a conservative annual increment of 0.030C/year to fairly represent a warming climate within a century has been run through the “extRemes” program and are reproduced as self-explanatory and as screenshots in the following boxes 4.1 and 4.2.

Page 232: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 14 393

The above simulated outputs indicate that Gumbel distribution cannot be rejected based on maximum likelihood estimation (MLE) test. This assessment now takes advantage of the Gumbel distribution to evaluate the highest maximum temperature at Mandla station and compares outputs of the conventional stationarity and the trend induced non-stationarity and computes return period versus return levels derived from the simulated data. See Figure 4.3 Thus following Gumbel distribution (EVA Type I), the following equations estimates return periods (recurrence intervals) of extreme temperatures:

𝑥𝑇 = �̅� + 𝐼𝐾𝑇 𝑠 (Eq. 4.1) where,

𝑥𝑇 = n-year return period value of extreme temperature to be estimated, 0C

�̅� = mean of annual extreme maximum or minimum temperatures, 0C

Box 4.1 Simulated GEV(Stationarity Case)

Box 4.2 Simulated GEV (Non-Stationarity with trend in Location Parameter Introduced)

Page 233: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

394 Appendix 14

𝑠 = standard deviation of annual extreme maximum or minimum temperatures, 0C

𝐼= 1 if maximum is being considered; and, = - 1 if minimum is being considered and, frequency factor, KTas:

𝐾𝑇 = −√6

𝜋{0.5772 + 𝑙𝑛 [𝑙𝑛 (

𝑛

𝑛−1)]} (Eq. 4.2)

4.3 24-hourly Extreme Precipitation Estimation - Return Periods vs. Return Levels

(-similar analysis as in Sec 4.2; trend projected for 1.25 x current observed 24-hr rainfall by Table 2.1)- Results illustrated below.

Box 4.3 Simulated GEV(Stationarity Case)

Page 234: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 14 395

Theoretically, the intensity of a storm varies with duration in such a way that intensity generally corresponds to short durations, and low intensity to larger duration. In this analysis, average intensity of rainfall over relevant durations is estimated based on the non-stationary highest maximum projections of 24-hour rainfall as shown in Figure 4.4. As intense storms can produce heavy downpours on scales of minutes and where the design geometry of the bridge or highway drainage system would suffer by not being able to accommodate the sudden storm runoff, a depth-duration rating derived from Eq.(4.3) is presented in Table 4.3. The Indian Meteorological Department (IMD) uses an empirical reduction formula equation (Eq. 4.3)26 for estimation of rainfall depths for various duration like 1-hr, 2-hr, etc. rainfall values from annual maximum values. This formula is used to estimate the short duration rainfall from daily rainfall data in of Mandla Station as it is supposed to be the best estimation of short duration rainfall for the Indian sub-continent.

𝑃𝑡 = 𝑃24 √𝑡

24

3 (Eq. 4.3)

26

IOSR Journal of Environmental Science, Toxicology and Food Technology (IOSR-JESTFT) e-ISSN: 2319-2402,p- ISSN: 2319-2399.Volume 9, Issue 9 Ver. I (Sep. 2015), PP 41-47 www.iosrjournals.org

Box 4.4 Simulated GEV (Non-Stationarity with trend in Location Parameter Introduced)

Page 235: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

396 Appendix 14

where, t is specified time (in hours) for which rainfall amount needs to be estimated, Pt is rainfall depth in mm in t hours and P24 is total rainfall in 24 h.

Under cyclonic disturbances, heavy rainfall occurs in regions exposed to these disturbances, particularly the coastal areas of India. Rainfall caused by such depressions can range from 40 to 80 cm per day (Rakhecha & Picharoty, Current Science, Vol.71, No 3, Aug 1996); a screenshot (Box 4.5) of their estimate for highest rainfall for 1-day duration for the period 1875 to 1982 under cyclonic disturbances is reproduced below.

4.4 Wind and Cyclone Hazard

Climate change is speculated to increase the frequency of high-intensity storms mainly in coastal basins as in theory a warmer world should indeed produce more potent atmospheric disturbances creating cyclones. The Intergovernmental Panel on Climate Change (IPCC) reckons that the frequency of cyclones will stay the same or decrease while their average intensity goes up, but the evidence so far is confusing as there is no consensus on the cause of them. Worldwide, there is no trend in either the frequency or the intensity of tropical storms.

Literature (footnoted 8 on page 7 of this report) states that wind data are collected just twice a day at 8:30 hrs and 17:30 hrs in weather stations in Madhya Pradesh. Round the clock wind data recorded at least in hourly intervals would have been useful in establishing an EVA of wind speeds. Unfortunately such data do not exist and hence no further analysis can be performed.

However, a wind and cyclone vulnerability map27 produced by IMD (Box 4.6) may provide some indications as to maximum wind speeds. Madhya Pradesh seems to fall under moderate

27

http://www.hpsdma.nic.in/ResourceList/Maps/WindIndia.pdf

Box 4.5

Page 236: Appendix 1: ADB’s Rapid Environmental Assessment (REA ... · 162 Appendix 1 Appendix 1: ADB’s Rapid Environmental Assessment (REA) Checklist Country/Project Title: Sector Division:

Appendix 14 397

damage risk zone, with maximum winds at around 44 m/s. Under an uncertain future climate, it would be prudent judgment to consider the wind speed by an allowance, say some + 20%, in the design of bridges and other ancillary facilities related to the road project.

Bibliography

1. O‟Brien, K R., Leichenko, U, Kelkar, H. Venema. G. Aandahl, H. Tomkins, A. Javed, S. Bhadwal, S. Barg, L. Nygaard and J. West, 2004; Mapping vulnerability to multiple stressors: climate change and globalisation in India. Global Environmental Change vol 14 p303-313. 2. Madhya Pradesh State Action Plan on Climate Change (MP SAPCC), draft version, 2012 3. B. N. Goswami, V. Venugopal, D. Sengupta, M. S. Madhusoodanan,2 Prince K. Xavier;

Increasing Trend of Extreme Rain Events Over India in a Warming Environment, Science 1 December 2006: Vol. 314. no. 5804, pp. 1442 – 1445

4. Initial Environmental Examination, IND: Madhya Pradesh District Connectivity Project, Jarkua – Raigaon - Karsara Road, Prepared by Madhya Pradesh Road Development Corporation for the Asian Development Bank, 2015 5. Rutting Characteristics of 40mm thick Bituminous Concrete Mix with Plain and Modified Binders at Varying Temperatures using Treaded Wheel,Kiran Kumar V. & Ganesh K., Vol.41, No.11, (Page 16), November 2013, Indian Highways, A Review of Road and Road Transport Development, The Indian Road Congress, www.irc.org.in 6. Guidelines on Use of Modified Bitumen in Road Construction (Second Revision), November 2010, Indian Road Congress 7. Guidelines on Analysis of Extremes in a Changing Climate in Support of Informed Decisions for Adaptation; Climate Data and Monitoring. WCDMP-72, 2009 8. Technical Report No. 4811, Volume II(a) – Annexure I-XIV and XVI-XXII, EIA for Proposed 2x700 MWe PHWR, Chutka Madhya Pradesh Atomic Power Project; March 2013; Nuclear Power Corporation of India Ltd. Mumbai, National Environmental Research Institute, Nagpur, India 9. IOSR Journal of Environmental Science, Toxicology and Food Technology (IOSR-JESTFT) e-ISSN: 2319-2402,p- ISSN: 2319-2399.Volume 9, Issue 9 Ver. I (Sep. 2015), PP 41-47 www.iosrjournals.org

Box 4.6