TQI APC Fall Seminar 2019| November 21, 2019 1 Improving Constructability - Early Contractor Project Reviews

Transcript of APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads...

Page 1: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

TQIAPC Fall Seminar 2019| November 21, 2019

1

Improving Constructability - Early Contractor Project Reviews

Page 2: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Overview of TQI

2

Brian Link, PE, Project Manager, Michael Baker International

Page 3: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

• Minimize owner-contractor conflicts• Collaborate to address critical industry issues that represent barriers

to mutual project success

3

Goals of TQI

Page 4: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

4

Executive Team

Integration TeamPennDOT | PTC | APC | ACEC

Co-Chairs Co-ChairsCo-Chairs

Process Teams

Design ConstructionProcurement

Page 5: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

5

TQI and Other Committees

TQI complements, not duplicates, other efforts

Workforce CommitteesSTIC/TAGs

TQI

RAC Quality WG

Page 6: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Structural Coatings – Concrete and Steel Constructability Reviews Alternative Procurement (Design-Build Best Value) Contractor Evaluations Stormwater Management – BMP Manual Revisions

6

Current TQI Topics

Page 7: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Over the past year, a TQI Design Process Team gathered to brainstorm ways to improve the Constructability of projects advertised by PennDOT and the PA Turnpike

The team consists of members of PennDOT, PA Turnpike, ACEC/PA, and APC

7

Introduction - Constructability

Page 8: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

To improve constructability of projects advertised by the Pennsylvania Department of Transportation and the Pennsylvania Turnpike Commission

Suggested improvements: Constructability Policy Revision

Contractor Plan Review – Preliminary Design

Purpose

8

Page 9: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Responding states

9

Survey of Other States on Constructability

Page 10: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

When are Constructability Reviews performed?

10

What other states are doing

Feasibility/ Study Phase

PreliminaryEngineering

Final Design

Page 11: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Do contractors participate in Constructability Reviews?

11

What other states are doing

Page 12: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

At what phase(s) of Constructability Review does the contractor participate?

12

What other states are doing

Page 13: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Constructability - PennDOT

13

Kristen A. Swan, Constructability/Maintainability Coordinator, PennDOT

Page 14: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Constructability Policy Revision was in process when TQI Team first met

Policy revision is a result of efforts from: PNG Team TQI Design Process Team Statewide workshop of Department Representatives

14

PennDOT – Constructability Policy Revision

Page 15: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Policy revision necessary – to formalize and provide consistency for District constructability reviews and pre-bid schedule preparation and to incorporate the department’s focus on PennDOT Connects and future maintainability of the transportation system Future opportunities for improvement Documentation system to carry issues/resolutions from Design to

Construction to Maintenance Involve contractors in constructability reviews earlier in Design (in PE rather

than in FD for VEEACT)

15

PennDOT – Constructability Policy Revision

Page 16: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Purpose: To solicit opinions/alternate ideas from the contracting community concerning a project’s constructability and assumed methods of construction

Suggested on the following types of projects: Feasibility/study projects Corridor projects Large projects with multiple restrictions Projects with complex or unique issues

16

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 17: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

PennDOT would utilize the “Unofficial Plans Process” in ECMS to accomplish this effort At Line & Grade or during Design Field View preparation, when sufficient

project information is developed, prepare a Constructability Review package Constructability Review package should consist of project description

which outlines areas of concern, environmental constraints, proposed staging, access areas, etc.; plans at line & grade or mid-design field view stage (including traffic control, structure, etc.); cost estimate; specifications; preliminary pre-bid schedule

17

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 18: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

18

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 19: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

19

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 20: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

20

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 21: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

21

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 22: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

22

PennDOT – Preliminary Constructability Review Process (by Contractors)

Page 23: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Constructability – PA Turnpike

23

Fawn R. Cassel, PE, Engineering-Project Manager 3, PTC

Page 24: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Similar timing to PennDOTDifferences Through PTC EBS Comments will be kept anonymous – PTC staff will not see which contractors

are making comments

24

PTC – Preliminary Design Contractor Reviews

Page 25: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Pilot projects will be done through EBS news items to gauge interest and feedback Focusing on larger and/or complex projects where phasing or

constructability issues may be more prevalent Posting two projects in Q1 of 2020 Pilot projects are more developed than PE, but we are open to feedback

25

PTC – Preliminary Design Contractor Reviews

Page 26: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

26

PTC EBS

Page 27: APC Fall Seminar 2019 | November 21, 2019 Improving …apcfallseminar.com › wp-content › uploads › 2019 › 11 › TQI... · 2019-11-25 · Pilot projects will be done through

Mike Bougher/Stantec Tom Macioce/PennDOT Wally Wimer/PTC Kelly Barber/PennDOT Steve Grassetti/JMT Bernie Zielinski/PTC Brent Trivelpiece/PennDOT

Kristen Swan/PennDOT Fawn Cassel/PTC Kent Wible/Hempt Geoff Gribble/Borton-Lawson Joe Catena/Trumbull Jim Andrews/PennDOT

27

Questions and CommentsThank you to our TQI Design Process Team Members