1 AP1000 Plant Update IEEE SC2 Meeting June 2011 Gothenburg Sweden Suresh Channarasappa [email protected]

Transcript of AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1...

Page 1: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

1

AP1000 Plant Update

IEEE SC2 MeetingJune 2011

Gothenburg Sweden

Suresh [email protected]

Page 2: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

2

AP1000 Plant Update

● AP1000 - China– Sanmen 1 and 2 – Haiyang 1 and 2

● AP1000 - USA– Vogtle 3 and 4– V. C. Summer 2 and 3

Page 3: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

3

AP1000 Plant Update

● AP1000 China Update (Continued)– Sanmen Unit 1 and 2– Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

2010– Unit 2 CA01 module was set on December 2010– Commercial start-up of the AP1000 Sanmen Unit 1 in currently scheduled

in 2013. [Countdown Clock: ~716 Days]

Page 4: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

4

AP1000 Plant Update

Sanmen site view

Page 5: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

5

AP1000 Plant Update

Page 6: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

6

AP1000 Plant Update

Unit 1 Containment Vessel Rings

Page 7: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

7

AP1000 Plant Update

Unit 1 Containment Vessel Ring 4 (CVR4)

Page 8: AP1000 Plant Update - IEEE...3 AP1000 Plant Update AP1000 China Update (Continued) – Sanmen Unit 1 and 2 – Unit 1 Containment Vessel Ring 4 (CVR4) was set in place on December

8

AP1000 Plant Update

QUESTIONS??