Antares Status, Presented by Dan Givens
-
Upload
wallopsislandregionalalliance -
Category
Technology
-
view
453 -
download
5
Transcript of Antares Status, Presented by Dan Givens
Antares Status
Dan Givens
Wallops Site Manager
12 January 2016
CRS Return To Flight Plan
The Orbital ATK Plan Has the Following
Elements:
Return Antares to Flight Using New, In-
Production RD-181 Engines
Launch Cygnus on the Atlas V 401 Launch
Vehicle during the Antares Down-time
− No Significant Atlas Modifications are
Required
Increased Capability of Atlas V and the New
Antares With RD-181 Engines Allow the
Remaining 13,100kg Obligation to be Delivered
in 4 Missions
1 Fewer Than the Original Planned 5 Missions
Subsequent to the Above Plan, We Jointly Decided
With NASA to Convert the OA-6 Mission to an
Atlas V Mission as Well
Increases Cargo Delivery to ISS During This
Critical Resupply Period by 300kg
2
Orbital ATK
Return to Flight Planning Launch Dates
3
Mission Orbital Working Launch Dates
Launch Vehicle
Original Planned Upmass
(kg)
CurrentPlanned Upmass
(kg)
OA-4* December 2015 Atlas V 2630 3500
OA-6* March 2016 Atlas V 2620 3500
OA-5 May-June 2016 Antares 2620 3200
OA-7 October 2016 Antares 2620 3200
OA-8 June 2017 Antares 2620 3200
OA-9 October 2017 Antares N/A 3200
OA-10 March 2018 Antares N/A 3200
Original
CRS1
Contract
4 Missions
Deliver
13,100 kg
(28,880 lbs)
CRS1
Contract
Extension
Period
* - OA-6 converted from an Antares to an Atlas V to enable increased cargo deliveries to the ISS
OA-11 2018 Antares N/A Competition
OA-12 … Antares N/A SensitiveCRS2
Contract
2018 – 2024
To Be Awarded
NLT 30 Jan 2016
* - Launched successfully
Cygnus Cargo Resupply Vehicle
Cygnus Evolution to a New Configuration
Pressurized Cargo Module (PCM)
Heritage: Multi-Purpose Logistics Module (ISS); ATV
Total Payload Mass: 2,300 kg (Standard), 3200-3500 kg (Enhanced)
Pressurized Volume: 18.7 m3, 27 m3
Service Module (SM)
Heritage: Orbital ATK GEO and LEO missions
Power Generation: 2 Fixed Wing Solar Arrays, 3.5 kW
Compatible with multiple LVs
Standard Cygnus
4
Enhanced Cygnus
Antares 230 Configuration
Development Status Update
Orbital ATK (OA) has developed a new configuration of Antares – the Antares 230 configuration – that features new stage 1 rocket engines
RD-181 engines were selected as an ideal replacement for prior AJ26 engines
Decision was made in consultation with our NASA customer and is now publicly disclosed
Directly addresses Orb-3 AIB corrective action #1
The Antares 230 configuration will be capable of launching a 7000kg Cygnus (carrying 3200kg of cargo) to ISS as early as May 2016
Will use existing Stage 1 Core tanks with minor modifications necessary to accommodate new RD-181 engines – and same upper stack used on Orb-3 with minor avionics changes
RD-181 engine development is complete and production is well underway
− Certification testing program complete
− First three flight engines completed acceptance testing and were delivered in July 2015
◦ Acceptance test profile is flight duration at flight power levels, which directly addresses Orb-3 AIB corrective action #2
A hot fire Stage Test at Launch Pad 0A in March 2016 will be the major system level verification activity prior to the OA-5 mission
− The Stage Test will verify operation of the integrated first stage
5
Antares 230
Stage Test Overview
6
Stage Test Plan For The Upgraded Antares 230 is the Major
Verification Activity Prior to the OA-5 Return to Flight Mission
The Stage Test Features Two Main Activities
One Wet Dress Rehearsal (WDR)
Verify And Demonstrate All Processes And Operations
Required To Properly Configure The Test Article For Engine
Ignition
One Hot Fire Test
Verify Operation And Performance Of Integrated First Stage
Featuring Upgraded Propulsion System
Test Planning (Test Configuration, Schedule, Documentation,
Operations, Etc) Is Underway, Schedule Forecast: March 2016
Test Article Assembly Has Begun
Major Partners (NASA, MARS, Energomash, Yuzhnoye, Etc)
Have Been Briefed On Test Plan, And Are Working With
Antares Program In Various Roles To Prepare For The TestTest Article Mounted To Pad
Pad 0A Repairs and Upgrades Completed
All Concrete Structure Damage Has Been Repaired, Lightning Masts Replaced and Repair of
Damaged Fueling and Pressure System Piping is Complete.
Modifications Required to Support RD-181 are Complete
Modification and Testing of Transporter/Erector Launcher and Hydraulic Systems Complete
Performance Testing of Pad Systems Completed
7
Antares Integration - HIF High Bay
8
Currently Processing Two Vehicles
Stage Test/OA-7 & OA-5
Stage Test/OA-7 Mission
RD-181 Engines Mated to 0.6 Core at Wallops Island
9
10
OA-5 Mission
Vehicle Integration Status
0000.7 Core Unpacked and Ready for Lift to Rails for Transfer to Dollies
0000.7 Core Transfer to Dollies
OA-5 Mission
Vehicle Integration Status
Aft Bay Removed
RD4A & RD5A Engines Unpacked at HIF
11
Summary
Orbital ATK is Meeting its Commitment to NASA Under the CRS-1 Contract:
Deliver the Remaining Cargo Obligation on the Original Contract by the End of 2016
Deliver Additional Cargo in 2017 Via Extension Missions
Purchase of Atlas V Missions Restarted Cargo Deliveries to ISS While Antares
Upgrade to the 230 Configuration is Completed
Antares 230 configuration incorporates new-built RD-181 engines that are an ideal
replacement for the previous AJ26 engines
RD-181 certification testing program has completed successfully
RD-181 flight engines will be acceptance tested through a flight-representative profile
Replacement of the AJ26 engines with the RD-181 engines fully addresses the AIB
recommended corrective actions
Antares 230 and Pad 0A schedules support the Stage Test in March 2016 followed by
the OA-5 mission in 2Q2016 and OA-7 mission in 4Q2016
12
Orbital ATK Will Be Ready to Restart Cargo Deliveries
to the ISS with Antares Later This Year