Anode Retrofitting - PNWS- · PDF file•What is Anode Retrofitting? •Anode Retrofit...
date post
29-Apr-2018Category
Documents
view
216download
3
Embed Size (px)
Transcript of Anode Retrofitting - PNWS- · PDF file•What is Anode Retrofitting? •Anode Retrofit...
Anode Retrofitting Lengthen Pipe Service Life at a Fraction of the Cost of Replacement
Matthew Palmer
Tualatin Valley Water District
Washington County, Oregon
2
Presentation Outline
Galvanic Corrosion Cells
Premature Failure of Pipelines
What is Anode Retrofitting?
Anode Retrofit Pilot Program
Cost Comparison vs. Pipe Replacement
Identified Issues
Further Research
Washington County, Oregon
3
TVWD Location
Washington County, Oregon
4
TVWD Background
2nd largest water district
200,000 people served1
28 pressure zones
12 pump stations
800 miles of pipe
19 MGD (ADD)
60 MG water storage
1 Seattle Public Utilities serves water to 1.3 million
Galvanic Corrosion Cells
Washington County, Oregon
6
Corrosion is the deterioration of a substance or its properties as a result of an undesirable reaction with the environment. NACE International
Washington County, Oregon
7
Anode Location where corrosion takes place
Cathode Location where corrosion does not occur
Electrolyte Soil, Water, Moisture, etc.
Metallic Path Pipe, wire, etc.
Galvanic Corrosion Cell (Metallic Pipe)
Four Elements for Corrosion to Occur
Washington County, Oregon
8
23 year old Ductile Iron (Hillsboro)
Washington County, Oregon
9
Unknown Age Ductile Iron (Tigard)
Washington County, Oregon
10
Washington County, Oregon
11
Dissimilar Metal Corrosion
Washington County, Oregon
12
The Galvanic Series Difference in voltage potential
Typical Service Material
Typical Main Material
CORRODES
Washington County, Oregon
13
Dissimilar Metal Corrosion
Washington County, Oregon
14
Dissimilar Metal Corrosion
Washington County, Oregon
15
Dissimilar Metal Corrosion
Washington County, Oregon
16
Pipe life is expected to be a minimum of 50 years.
Corrosive soils is causing pipe failure after 25-30 years.
District cannot afford to replace piping on a 25- to 30-year replacement schedule.
Premature Failure of Pipelines
A Potential Solution?
Anode Retrofitting
What is Anode Retrofitting?
Washington County, Oregon
18
Anode Retrofitting is the practice of:
connecting sacrificial anodes to existing, corroding pipe
to minimize or halt the effects of galvanic corrosion
while minimizing disruption to the surface above existing pipe.
Washington County, Oregon
19
The Galvanic Series Difference in voltage potential
Typical Service Material
Typical Main Material
Typical Anode Materials CORRODES
Washington County, Oregon
20
Anode Location where corrosion takes place
Cathode Location where corrosion does not occur
Electrolyte Soil, Water, Moisture, etc.
Metallic Path Pipe, wire, etc.
Pipe with Sacrificial Anode Installed
ANODIC AREA
(CORRODING)
WELD TO PIPE
Washington County, Oregon
21
Anode Retrofit Pilot Program
Washington County, Oregon
22
Pilot Program Goals
The goal of the Anode Retrofit Pilot Program is to:
Determine necessary tools/equipment/material
Determine procedures for anode installation
Determine average cost on a per LF basis
Determine allowable anode spacing
Generate policy for when to install anodes vs. replacing pipe vs. letting pipe go to failure
Washington County, Oregon
23
Anode Retrofitting Beta Test
Beta Test Location: NW Damascus St., Portland, OR
January 6, 2015
What information was collected?
Average time to excavate, install anode, and backfill
Equipment used to perform the work
Type of materials used and quantities
Issues that our crews observed during installation
Washington County, Oregon
24
Installation Procedure: 6 Easy Steps!
STEP 1: Excavation
STEP 2: Remove Asphaltic Coating from Pipe
STEP 3: Weld Anode Lead Wire to Pipe
STEP 4: Place Weld Patch Pad over Weld Location
STEP 5: Place Anode
STEP 6: Backfill and Surface Restoration
Washington County, Oregon
25
STEP 1: Excavation
Crews used a Hydro Excavator to excavate over top of weld locations.
Minimize disturbance at surface
Keeps excavation size to a minimum
Washington County, Oregon
26
STEP 2: Remove Coating on Pipe
Prior to welding anode lead wire to pipe, coating (typically asphaltic) must be removed.
Grinder powered by portable generator.
Grinder-On-A-Stick
Washington County, Oregon
27
Washington County, Oregon
28
STEP 3: Weld Anode Lead Wire
Cadwelder-On-A-Stick
Anode lead wire to be exothermically welded to pipe using a handheld Cadwelder.
Rubber bands break as weld is made.
Works surprisingly well!
Washington County, Oregon
29
STEP 4: Install Weld Patch Pad
Once the weld is made, grinded pipe area must be protected.
Multiple products on the market today for this exact use.
Handy Cap IP and Trenton Patch Pad have been tried by the District.
Washington County, Oregon
30
Washington County, Oregon
31
STEP 5: Place Anode
Pre-packaged anode is dropped into place, offset from the existing pipeline.
Depending on the size of the existing pipe and soil corrosivity, different size anodes will be used.
Washington County, Oregon
32
STEP 6: Backfill and Surface Restoration
Anode is backfilled with sand and native soil. Water is dumped into anode pit to consolidate material.
Trench is backfilled with crushed aggregate.
Surface restoration:
Gravel, native soil
Asphalt, concrete
Cost Comparison to Pipe Replacement
Washington County, Oregon
34
District uses $23/in-dia to estimate per LF pipe replacement costs
Historical project financial data used to generate value
Includes all pipe, excavation, service reconnections, backfill, surface restoration
Cost of Pipe Replacement
Pipe Diameter Cost per LF
6 $138
8 $184
12 $276
Washington County, Oregon
35
Cost Type Includes Cost per Hour Cost per AnodeA
Labor Staff time (5 person crew) and benefits $341.13 $85.28
Equipment Hydro Excavator, Dump trucks, etc. $166.50 $41.63B
Material Anodes, sand, rock, welding cartridges - $138.39C
Total (per anode) $265.30
Total (per LF of pipe) $14.74
Cost of Anode Retrofitting
Assumptions:
A Crews installed anodes every 15 minutes. B Cost assumes excavation is within gravel. C Cost assumes 17 pound anodes, installed every 18 feet.
Washington County, Oregon
36
Pipe Diameter Cost per LF Anode per LF % of Replacement
6 $138 $14.74 10.7%
8 $184 $14.74 8.0%
12 $276 $14.74 5.3%
16 $368 $18.00 4.9%
Anode Retrofit versus Pipe Replacement
Spoiler Alert! Anode Retrofitting is cheaper than Pipe Replacement
Upsize to 32 Lb. Anode
Washington County, Oregon
37
0
50
100
150
200
250
300
350
400
6" 8" 12" 16"
$ p
er
foot
Pipe Diameter
Anode Retrofitting vs. Pipe Replacement
Replacement Anode Retrofit
Washington County, Oregon
38
Anchorage Water & Wastewater Utility (AWWU) states 10% the cost of pipe replacement (2014).
Des Moines Water Works (DMWW) states less than 10% the cost of pipe replacement (2005).
TVWD has found that it is less than 10% the cost of pipe replacement, depending on pipe diameter.
Assuming gravel surface, more if in asphalt/concrete
What have other utilities found?
Washington County, Oregon
39
How much life does it add?
Much factors into this answer:
Condition of pipe at time of anode retrofitting
Corrosivity of native soil
Native backfill vs. crushed aggregate backfill
Proper sizing and placement of anodes
Des Moines Water Works (DMWW) states an additional 20 years (2005).
Others have estimated 25 years of added life
Washington County, Oregon
40
Anode retrofitting is a valuable tool in lieu of pipe replacement in some situations.
Cost savings are large but variable (dependent on pipe dia.)
Very cost effective for large diameter pipes, especially welded joint pipes (steel transmission mains, larger spacing possible).
Years of life added is not clearly defined, some other pilot programs have stated 20 to 25 years.
TVWD Conclusions
Washington County, Oregon
41
Local jurisdictions: max core size of 8 diameter.
8 hole not feasible, not enough room to place anode
May require full lane grind and inlay
Wet pipes dont get along well with Patch pads
Pipe needs to dry prior to placing patc