ANNUAL REPORT OASE PeriodicReport D1.9 P3 …...THIRD YEAR - 2012-2013 - ANNUAL REPORT...
Transcript of ANNUAL REPORT OASE PeriodicReport D1.9 P3 …...THIRD YEAR - 2012-2013 - ANNUAL REPORT...
“THIRD YEAR - 2012-2013 - ANNUAL REPORT”
D 1.9
‘OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
Version: 2.0
Last Update: 17/09/2013
Distribution Level: PU
Distribution level PU = Public, RE = Restricted to a group of the specified Consortium, PP = Restricted to other program participants (including Commission Services), CO= Confidential, only for members of the OASE Consortium (including the Commission Services)
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 2 of 80
PROJECT PERIODIC REPORT
Grant Agreement number: 249025
Project acronym: OASE
Project title: Optical Access Seamless Evolution
Funding Scheme: SEVENTH FRAMEWORK PROGRAMME
ICT-2009.1.1: The Network of the Future (IP)
Date of latest version of Annex I against which the assessment will be made: October 13th
, 2009
Periodic report: 1st □ 2
nd □ 3
rd x 4th □
Period covered: from January 1st, 2012 to February 28th, 2013
Project co-ordinator name, title and organisation: POINT Jean-Charles, CEO, JCP-CONSULT
Tel: +33 223 271 246
Fax: + 33 299 277 782
E-mail: [email protected]
Project website address: http://www.ict-oase.eu
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 3 of 80
Declaration by the project coordinator
I, as co-ordinator of this project and in line with my obligations as stated in Article II.2.3 of the Grant
Agreement, declare that:
The attached periodic report represents an accurate description of the work carried out in this
project for this reporting period;
The project (tick as appropriate):
has fully achieved its objectives and technical goals for the period;
□ has achieved most of its objectives and technical goals for the period with relatively
minor deviations1;
□ has failed to achieve critical objectives and/or is not at all on schedule.
The public website, if applicable
is up to date
□ is not up to date
To my best knowledge, the financial statements which are being submitted as part of this report
are in line with the actual work carried out and are consistent with the report on the resources used
for the project (section 3.6) and if applicable with the certificate on financial statement.
All beneficiaries, in particular non-profit public bodies, secondary and higher education
establishments, research organisations and SMEs, have declared to have verified their legal status.
Any changes have been reported under section 5 (Project Management) in accordance with
Article II.3.f of the Grant Agreement.
Name of Coordinator: Jean-Charles Point
Date: 24/04/2013
Signature of Coordinator:
1 If either of these boxes is ticked, the report should reflect these and any remedial actions taken.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 4 of 80
Table of content
DECLARATION BY THE PROJECT COORDINATOR ................................................................................................. 3
1. PUBLISHABLE SUMMARY .................................................................................................................................... 5
2. PROJECT OBJECTIVES FOR THE PERIOD .......................................................................................................... 8
3. WORK PROGRESS AND ACHIEVEMENTS DURING THE PERIOD ................................................................. 9
3.1 WP2 - REQUIREMENTS FOR EUROPEAN NEXT-GENERATION OPTICAL ACCESS NETWORKS .......... 9
3.2 WP3 - NEXT-GENERATION OPTICAL ACCESS ARCHITECTURES ............................................................ 12
3.3 WP4 - SYSTEM CONCEPTS NEXT-GENERATION OPTICAL ACCESS NETWORKS ................................. 15
3.4 WP5 - TECHNO-ECONOMIC ASSESSMENT .................................................................................................... 18
3.5 WP6 - BUSINESS MODELLING AND REGULATORY ASPECTS .................................................................. 20
3.6 WP7 - EXPERIMENTAL VALIDATION ............................................................................................................. 23
3.7 WP8 - DISSEMINATION OF RESULTS .............................................................................................................. 25
4. DELIVERABLES AND MILESTONES TABLES.................................................................................................. 34
5. PROJECT MANAGEMENT .................................................................................................................................... 36
6. EXPLANATION OF THE USE OF THE RESOURCES ........................................................................................ 51
7. FINANCIAL STATEMENTS – FORM C AND SUMMARY FINANCIAL REPORT .......................................... 73
8. CERTIFICATES – TO BE UPDATED .................................................................................................................... 73
9. ANNEX 1 – POST REVIEW – 2011 _ “HOW WE ADDRESSED REMARKS” .................................................. 75
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 5 of 80
1. Publishable summary
http://www.oase.eu
Duration: 01/2010– 02/2013 Total Cost: 7,664,241.00 €
EC Contribution: 4,980,257.00€
Grant agreement n° 249025
OASE: Optical Access Seamless Evolution
Partners: JCP-Consult (F), Deutsche Telekom AG (D), iMinds vzw (B), Technische Universität München
(D), Kungliga Tekniska Högskolan (S), ADVA Optical Networking SE (D), Ericsson AB (S), Ericsson
Telecomunicazioni S.p.A (I), ACREO SWEDISH ICT AB (S), Magyar Telekom (H), Slovak Telekom (SK),
University of Essex (UK)
The OASE Integrated Project has examined Fibre-to-the-Home (FTTH) within a multi-disciplinary study
to provide a self-consistent and coherent set of technological solutions. The OASE project federated
partners from all over Europe and is composed of major operators, industrial leaders in FTTH
technologies, and European universities.
Main Objectives
The aim of the OASE project is the assessment and development of next-generation optical access (NG-
OA) network architectures and systems concepts for the “2020” timeframe, focusing particularly on
European requirements. The OASE project has examined FTTH solutions based on four multidisciplinary
approaches: regulatory, technical and financial aspects, and business models. In combination with these
aspects, NG-OA network architectures has been developed featuring the highest potential of enabling:
1 Gbit/s per customer
1000 customers per fibre feed
100 km transmission distance
at economically competitive prices within a well-regulated and open market environment.
OASE has achieved the following objectives:
Study current and future requirements for NG-OA networks from economic, business, operational
and regulatory Europe-centric perspectives,
Identify possible network architectures, and employ a set of energy-efficiency metrics and models to
analyse their suitability, as well as assess the most appropriate migration strategies,
Identify network technologies that may be employed by using relevant cost and technical factors,
Examine the interactions between businesses in an “open network” marketplace by studying how
increased convergence may offer new value chains and business opportunities,
Validate the findings of the comparative merits for the identified network architectures and
technologies in a controlled environment via experimental testing.
Technical Approach
The aim of the project was to address in a coordinated way all aspects of NG-OA networks: architectures,
technical aspects, feasibility, techno-economic issues, business modelling, and regulation. WP2 and WP3,
which respectively examined requirements and architectures, were the core WPs around which the other
WPs interact:
WP2 has identified technical, economic, operational and regulatory needs, and also served to
establish a basis for broad acceptance in the operator and vendor communities to provide
consolidated requirements for European NG-OA solutions.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 6 of 80
WP3 has reviewed existing optical access
network architectures, proposing novel
solutions, and evaluated them in terms of
complexity, reliability performance,
resource allocation, and energy
consumption etc.
WP4 has developed new system concepts
based on existing and new technical
solutions defined by WP3, taking into
account migration scenarios.
WP5 and WP6 closely interacted together
to perform the following: WP5 provided
the techno-economic modelling of
CapEx/OpEx for the identified solutions
and the assessment and analysis of the scenarios while WP6 performed business modelling, and also
considered regulatory impact on the final business models.
WP7 took inputs from all WPs and performed experimental validation via extensive laboratory testing.
The impact of the project including: standardisation, dissemination of the results within the industry through
the creation of an industry board, industry events and workshops, and publications, was ensured by WP8.
The project includes major vendors and operators ensuring relevant standardisation and exploitation of the
results.
Key Issues
The OASE project addressed 5 key issues: Open Access – open interfaces, enabling the simple and easy use
of third party infrastructure, clear definitions of services and their quality, and operational responsibilities.
Key achievements
In 2010 extensive work was done to identify and analyse key requirements, potential technologies and
architectures. With respect to techno-economic assessment and business analysis for co-operation models a
joint framework and scenarios were established.
In 2011 extensive work was done to further investigate the suitability of the different system concepts and
proposed architectures for their suitability to support node consolidation scenarios. This work was
accompanied by intensive investigations on CapEx and initial OpEx studies. The key requirements as
outlined in the previous yearly report served as a basis and reference for the investigations.
In 2012-2013, among others, followings main objectives were successfully achieved:
This third period of activity completes the requirement review and allowed establishing consolidated
requirements (WP2) towards European NGOA networks.
While in 2010 and 2011 major architectures and system concepts (WP3 - WP4) where defined, those were
analysed in 2012–2013 with a focus on potential for lowest total cost of ownership; this was made possible
by analyzing the proposed architectures and system concepts with respect to operational processes, e.g.
OpEx models based methodologies and tools developed and approved previously. Optimal path trajectories
to enable minimum-risk migration strategies were identified, enabling co-operation models by developing
and applying decision models and risk assessment methodologies for NGOA migration scenarios.
Cost and business evaluation (WP5 – WP6) of different case studies for NGOA networks were developed,
including different architectures and technologies, different migration strategies and different business
models and (open) value networks, also taking into account the regulatory impact on the final business
models.
Technology feasibility and basic operational aspects were demonstrated in lab trials as it as been reported
under WP7. Main outcomes from OASE were brought to standardization bodies (WP8) with respect to
European solutions for NGOA network architectures and technologies
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 7 of 80
Finally, as a conclusion of these highly productive three years, a white paper (entitled “Integrated OASE
results overview” - D8.5) has been written; This paper gives an overview of potential Next Generation
Optical Access (NGOA) solutions, enabling optical access network technologies, architecture principles and
related economics taking CAPEX and OPEX into account.
Project website: www.ict-oase.eu
Project Coordinator: Jean-Charles POINT- JCP-CONSULT SAS - Tel: +33 2 23 27 12 46- Fax: +33 2 99
27 77 82 –
Email: [email protected]
Project Technical Leader: Dirk BREUER - DEUTSCHE TELEKOM AG -Tel: +49 30 835358828- Fax:
+49 391 580 240 533
Email: [email protected]
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 8 of 80
2. Project objectives for the period
A. As a reminder, during Period 1 (2010), following objectives were targeted and results were
presented during the review held on March 22nd, 2011
Objective 1: Establish European-based requirements for next-generation optical access networks
(horizon 2020) by discussions among major European network operators and system vendors.
Objective 2: Define a next-generation optical access network domain boundary based on European
requirements.
Objective 3: Establish an overview of methodologies and models for assessing TCO, CapEx, OpEx,
and different business models
Objective 4: Develop test cases, test lab requirements, and set-up of small-scale test-labs
infrastructure suitable for research on new architectures and concepts
B. During Period 2 (2011), following objectives were targeted and results were presented
during the review held on March 27th, 2012
Objective 5: Develop a next-generation optical access technology roadmap by evaluating the
potential of available and emerging next-generation passive and active access technologies and all-
packet transport methods,
Objective 6: Define the optimum NG-OA architectures including mobile backhaul and broadband
business customers. At the demarcation points between home and NG-OA, and NG-OA and metro-
core the potential need for network related functionalities will be identified.
Objective 7: Develop a generic cost model for the most important processes in next-generation
optical access networks and include them in a first version of the TCO evaluation tool
Objective 8: Identify anticipated innovative business roles, market players, networks of open value
chains, valuable market demand and revenue models, and preliminary co-operation models
C. Following objectives were targeted during Period 3 - activities (2012-2013), and results will
be presented during the review to be held on April 24th, 2013
Objective 9: Identify architectures and system concepts with potential for lowest total cost of
ownership by analyzing the proposed architectures and system concepts with respect to operational
processes, e.g. OpEx models based methodologies and tools developed and approved under
Objective 7.
Objective 10: Establish consolidated requirements towards European NGOA networks.
Objective 11: Develop and assess next-generation optical access network architectures and system
concepts with respect to the reviewed requirements.
Objective 12: Identify optimal path trajectories to enable minimum-risk migration strategies and
enabling co-operation models by developing and applying decision models and risk assessment
methodologies for NG optical access migration scenarios.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 9 of 80
Objective 13: Cost and business evaluation of different case studies for next-generation optical
access networks, including different architectures and technologies, different migration strategies
and different business models and (open) value networks, also taking into account the regulatory
impact on the final business models.
Objective 14: Demonstrate technology feasibility and basic operational aspects in lab trials.
Objective 15: Drive standardization bodies with respect to European solutions for next-generation
optical access network architectures and technologies by active participation and submission of
contributions to the appropriate institutions.
3. Work progress and achievements during the period
3.1 WP2 - Requirements for European next-generation
optical access networks
Workpackage number 2 Start date: M1- End date: M34
Activity type RTD
WPL DTAG
Sub-tasks
Task 2.1: Identification and analysis of common European requirements
[MT]
Task 2.2: Requirements for European next-generation optical access
networks [DTAG]
Deliverables / P3
[Due date]
D2.2.2 Consolidated requirements for European next-generation optical
access networks [M34]
Milestones / P3
[Due date]
/
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 6 1 4,6 2 0,55 1,4 3 0,50 0,9 3 1 2
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 1 0 1 0 0 0 4 0,7 2,6 4 0,7 2,6
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
4 0 0,4 3 0,99 0,8 30 5,44 17,6
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 10 of 80
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
According to the Annex I, the objectives of WP2 are as follows:
Objective 1: Provide consolidated requirements for European NG-OA solutions regarding
technical, economic, operational, and political regulatory aspects to establish a basis for
broad acceptance in the operator and vendor community thus achieving necessary market
volumes
Objective 2: Establish a broad basis (of operators, vendors) to drive standardisation
activities and to drive a European based standard for NG-OA networks by initiating a
network operator board
These objectives were successfully achieved within this second period’s plan.
During the kick-off meeting, the work plan had been clarified: WP2 and WP8 are jointly working
on the communication with other operators with respect to e.g. Industry Board that is lead by
IMINDS within the WP8.
Task 2.1 Identification and analysis of common European requirements
It fulfils objectives 1 and 2 according to the work plan.
Finalised in year 1
Task 2.2 Requirements for European next-generation optical access networks
It fulfils objectives 1 and 2 according to the work plan.
Significant results:
Based on the requirements and their backgrounds which were provided in OASE Deliverable D2.1
and the requirements review provided in the intermediate Deliverable D2.2.1 (that took previous
review recommendations into account), the last deliverable related to task 2.2 was submitted on
Nov. 14, 2012; the D2.2 entitled "Consolidated requirements for European next Generation optical
access network". summarizes the key requirements consolidated during the course of third OASE
project year in 2012 and which need to be taken into account for system and architecture design.
This revised version addresses the categories “service and network requirements” as well as
“business and operation” requirements. They cover, for example, network architecture and system
design, network topology, geographical distribution and coverage of customers, future traffic
growth, service penetration evolution, and open access solutions amongst others.
In addition, an economic evaluation of the NGOA requirements has been performed and the impact
of the major cost-driving requirements were analysed and considered for the refinement of the
requirements.
Furthermore, external sources as the Industry board meetings of OASE, related FP7 projects and the
Full Service Access Network Initiative (FSAN) have been used to review the requirements in order
to ensure a wide acceptance to enable a cost efficient design.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 11 of 80
The main conclusions can be summarized as follows:
According to the quantitative OASE results, most of the requirements can be fulfilled with some
exceptions (table 1 below); there is an issue with the quality requirement: availability ≥99.99%
cannot be fulfilled. For the residential market this requirement has been adjusted to ≥99.98%.
Another issue is the backhaul requirement: delay < 1ms and jitter << 1ms, especially required for
some mobile use cases. This might become critical if one considers extreme node consolidation
scenarios where the distance becomes close to the upper end of the protected distance of 90 km.
Furthermore, the use of dynamic resource allocation within a concept might seriously compromise
fulfilment of the backhaul delay and jitter requirements. Hence, for clients with the most stringent
backhaul requirements, backhaul should be based on static resource allocation and preferably utilise
dedicated PtP links or wavelengths.
For the architecture requirements, with respect to migration, the studies have shown that three out
of the NGOA architecture options (WR-WDM PON, NG-AON, and two-stage WDM PON) could
not reuse a power splitter based ODN infrastructure and would also not allow a seamless migration
(i.e. no user-wise switchover) on a PtP based ODN infrastructures. A migration starting from a non-
coexisting architecture would lead to additional effort in upgrading network infrastructure. For
Greenfield scenarios this has no relevance.
However, there are no knock-out criteria that exclude any concept from the technical point of view,
because all technical constraints could be overcome with additional measures and money.
Results from the economic evaluation and from the business analyses are therefore of major
importance for the adjustment of the requirements. The impact of major cost driving requirements
on system and architecture design, network operation and open access has been analysed in a
sensitivity study.
From the business perspective, multiple network providers in an area must be supported, taking into
account isolation functions and dynamic allocation of resources depending on market share. There
should also be a coordinating rule set in place. Furthermore, network interconnection via
standardized interfaces and open-access-enabling interoperability across different carrier networks
must be supported.
The NGOA requirements specified in OASE are essentially in-line with the key requirements for
the NG-PON2 system concepts defined in FSAN as well as with feedback received form the
Industry board meetings. The related FP7 projects have, of course, different targets, but in general
they are also quite well aligned with the OASE requirements. The technical focus of these projects
is in most cases complementary to OASE, and can deliver interesting input on OFDMA-PON
(ACCORDANCE), higher network layers (SPARC), and core network aspects (STRONGEST), as
well as on low-cost system design (GigaWaM). ALPHA and SARDANA are most in line with the
OASE project, and in general their requirements are very similar.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 12 of 80
Table 1 Requirements fulfilment by NGOA architectures
* Note: Seamless migration starting from a PtP/AON architecture will by all architectures not be supported, because
user-wise manual switchovers are required in all cases.
�Open issues: none
3.2 WP3 - Next-generation optical access architectures
WP number 3 Start date: M1 - End date: M36
Activity type RTD
WPL KTH
Sub-tasks
Task 3.1: Architecture options [Acreo]
Task 3.2: Co-operation models [Acreo]
Task 3.3 Assessment of architectures [KTH]
Task 3.4: Migration paths [IMINDS]
Deliverables / P3
[Due date]
D3.2.2 - Description and assessment of architecture options [M34]
D3.3.2 - Co-operation models [M35]
D3.4 - Migration paths [M36]
Milestones/ P3
[Due date]
M3.5 _ Preliminary evaluation of architectures II [M26]
M3.6 - Architecture options [M31]
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 13 of 80
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0,1 11 3,95 6,3 15 6,02 8,9 4 1,28 2,4 20 6,02 14,1
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
12 3,4 8,8 4 1,32 2,7 5 2,39 3,1 18 10,5 15,1 6 2,2 3,8
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
4 0,25 4,2 17 5,17 9,7 116 42,5 79
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
According to the Annex I, the objectives of WP3 are as follows:
Objective 1: To define the boundaries of NG-OA network domains
Objective 2: To review existing optical access architectures and study both, passive and
active concepts
Objective 3: To propose novel optical access network architectures according to the
requirements provided by WP2 which support open access scenarios and site reduction
Objective 4: To evaluate the proposed network architectures in respect to complexity,
scalability, reliability, energy and cost efficiency, and resource allocation
Objective 5: To study migration paths from the existing infrastructures to the NG-OA
networks
The first two objectives have been fulfilled in Year 1. Objective 3, 4 and 5 were partly achieved within
Year 2 and have been finalized in Year 3. Furthermore, intensive interactions with other WPs have
been carried out.
Task 3.1 Architecture options
Fulfilled objectives: WP3 Objective 3
Significant results: Based on a survey of architectures (D3.1) with potential of fulfilling the identified
requirements from WP2, four main groups of solutions have been selected by OASE for next generation
optical access (NGOA) networks, which are referred to as: WDM-PON, hybrid WDM/TDM-PON, two-stage
WDM-PON (or WDM-PON backhaul), and NG-AON. All of them are able to support node consolidation
and open access. A comprehensive assessment in terms of key architectural aspects by mapping them in
different node consolidation scenarios has been carried out within Task 3.3. Regarding open access, a
detailed analysis has been included in Task 3.2.
Furthermore, we noticed that efficient resource allocation is extremely important for hybrid WDM/TDM-
PON to mitigate performance degradation caused by an increased reach required by NGOA. Therefore,
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 14 of 80
several new algorithms have been developed to improve delay and jitter. Regarding resilience, protection of
the central access node and feeder fibre have been proposed for all four selected NGOA architectures, since
it can effectively avoid the single point of failure affecting a large number of users and decreasing the impact
on the whole network operation. Meanwhile, providing protection only for the shared part is not sufficient
for business access, which would pay more for high connection availability (99.99%). Cost efficient
protection down to the selected end users has also been investigated.
Task 3.2 Co-operation models
Fulfilled objectives: WP3 Objective 3
Significant results: Task T3.2 continued in Year 3 and finally completed in M35. This task has introduced
and evaluated various architectural concepts for next-generation open access based network infrastructures.
Such a study has been performed within the scope of OASE concerning specific challenges of the several
aspects, in terms of layers (i.e. fibre, wavelength or bit-stream) to open networks, impact on monitoring,
traffic models, and access and aggregation/metro architectures. Regarding open access on wavelength level,
it is relatively easy to be realized in WR-WDM-PON, e.g., using M:N AWG to replace 1:N AWG. However,
for all the other types of PONs the required power splitter in optical distribution network (ODN) causes
isolation issue while it is even not possible for some variants of two-stage WDM-PON and NG-AON. A
short list of open access concepts have been proposed to be further evaluated in WP5 and WP6 in terms of
cost and business aspects.
Task 3.3 Assessment of architectures
Fulfilled objectives: WP3 Objective 4
Significant results: A detailed assessment by mapping them in different node consolidation scenarios has
been done to compare the selected NGOA options in terms of different architectural aspects, such as power
consumption, resiliency, operation complexity, resource allocation, control and management as well as
impact on aggregation network. According to the obtained evaluation results, most of passive NGOA
architectures, i.e., WS-WDM-PON, UDWDM-PON and hybrid WDM/TDM-PON consume obviously
higher power than their active counterpart, namely two-stage WDM-PON and NG-AON; while the passive
architectures have better resiliency than the active approaches. From the operators’ perspective, i.e., without
considering the equipment located at the user side, thanks to its high splitting ratio hybrid WDM/TDM-PON
always performs best on the operational aspects, such as footprint, failure rate, and operator related power
consumption, among all four OASE architectures. On the other hand, resource allocation to schedule
upstream bandwidth is an issue mainly for hybrid WDM/TDM-PON. An efficient algorithm for hybrid PON
is needed to mitigate the performance degradation caused by reach extension due to the node consolidation.
It should be noted that apart from these technical-based aspects, the ultimate choice of deployment of a
particular NGOA architecture option also depends on the standard commercial criteria (techno-economic
modelling, OpEx/CapEx, business models etc.) and regulatory environment that may be present. The
assessment of these economic, business and regulatory aspects have been carried out in WP5 and WP6 to
achieve the final conclusions for the project.
Task 3.4 Migration paths
Fulfilled objectives: WP3 Objective 5
Significant results: Task T3.4 includes 2 activities, both of which have been completed in the end of the
project. Four groups of migration assessment criteria have been identified, mapping to four migration
challenges (i.e. support of coexistence, reuse of legacy infrastructure, minimizing disruption time and
introduction of node consolidation). For each of the considered NGOA architectures, the migration starting
from a point-to-point (P2P) and a power splitter based ODN has been assessed. It is clear that a P2P ODN as
starting point offers the highest flexibility for migration, but in many cases such an ODN is not available. For
a power splitter based ODN, the (passive) hybrid WDM/TDM-PON and WS-WDM-PON (and UD-WDM-
PON) are most suitable from a migration perspective. The other NGOA architectures are less optimal to
migrate to, but may offer other opportunities like a better support for open access, protection, energy saving
techniques, etc. as discussed in other WP3 tasks. A set of migration scenarios has been provided to WP5 as
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 15 of 80
an input for the cost study.
�Open issues: none
3.3 WP4 - System concepts next-generation optical access
networks
WP4 Start date: M1 - End date: M32
Activity type RTD
WPL EAB
Sub-tasks
Task 4.1 - Technology scanning [TEI]
Task 4.2 - Technical assessment of system concepts based on
requirements [UESSEX]
Task 4.3 - Operational impact on system concepts [DTAG]
Task 4.4 - Implementation and integration into new system concepts
[TEI]
Deliverables / P3
[Due date]
D4.2.2 - Technical assessment and comparison of next-generation
optical access system concepts [M27]
D4.3.2 - Operational impact on system concepts [M27]
D4.4.1 - Development of selected system concepts [M33]
D4.4.2 - Development of selected system concepts (Public version,
confidential data removed when necessary) [M33]
Milestones / P3
[Due date]
M4.3 - System concepts for next-generation optical access; Further
development results [M30]
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3(CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 10 0,95 9 13 6,02 7,1 2 0,99 1,6 18 4,8 13,2
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
12 2,22 13,5 8 1,14 6,6 8 4,2 6,8 17 8,32 7,3 4 0,75 3,3
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
0 0 0 16 4,55 10,3 108 33,94 78,8
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 16 of 80
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
According to the Annex I, the objectives of WP4 are as follows:
Objective 1: Comprehensive survey of suitable NG-PON system concepts, which will result
in a Technology Roadmap.
Objective 2: Assessment and comparison of the system concepts with respect to technical
requirements (from WP2 and WP4), space and power consumption, cost, etc.
Objective 3: Understanding of the operations aspects of the candidate systems, such as
installation, configuration, maintenance, fault management and resilience, performance
monitoring, etc.
Objective 4: Selection of candidate system concepts to be further investigated
These objectives were partially fulfilled within this first year, to large extent fulfilled during the second
year and completely fulfilled during the third year.
T4.1 Technology scanning [M1 - M10]
Fulfilled objectives: Objective 1
Significant results: Finalized during year 1
T4.2 – Technical assessment of system concepts based on requirements [M11 – M26]
Fulfilled objectives: Objective 2
Significant results: In the final deliverable D4.2.2, we have provided a detailed comparison of the
different system concepts (and different implementation options) with respect to technical
performance parameters such as bandwidth, reach, fan-out, cost, power consumption, footprint, etc,
We have also provided additional qualitative discussions of the resilience, security, upgradeability
and mobile backhaul requirements that each system variant needs to satisfy. Different concepts
provide favourable performance with respect to different parameters, i.e. DWDM-PON (low cost,
long passive reach, but low fan-out), hybrid-TDM/WDM PON (low cost, large fan-out, but short
passive reach), UDWDM-PON (large fan-out, long passive reach, but high cost), etc
The quantitative results have been provided to the parallel workpackage WP5 which used the raw
data to conduct a comprehensive techno-economic (total cost of ownership, TCO) calculation for
the various system variants. The results presented in T4.2 provide additional important insights into
the most-likely evolution paths of next-generation optical access networking complementing results
emerging from WP6 which considers additional regulatory and competition (open access) impacts,
as well as the migration studies arising from WP3,
T4.3 – Operational impact on system concepts [M11– M26]
Fulfilled objectives: Objective 3
Significant results: A comparison of the different system concepts with respect to operational
aspects such as basic requirements on operation, power consumption, floor space, service
provisioning, fault and performance management, etc, is presented in D4.3.2. With respect to
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 17 of 80
parameters such as floor space and power consumption a quantitative comparison is performed.
With respect to other aspects a qualitative comparison is performed. Input data such as MTBF for
modelling of e.g. availability in WP3 or fault management costs in WP5 is also provided by the
task. From T4.3 it is found that basic operational requirements can be fulfilled within all concepts.
With respect to some aspects differences are found between the concepts. The importance of these
differences depend on their contribution to the total cost of ownership with is addressed in WP5.
T4.4 – Implementation and integration into new system concepts [M18 - M32]
Fulfilled objectives: Objective 4
Significant results: T4.4 provides an in-depth study of selected challenges of the OASE system
concepts for next-generation optical access (NGOA). Key areas of improvement for various
candidate concepts within the scope of WP4 are addressed. With WP7 coving research related to the
optical PHY, T4.4 covers topics relating to sleep modes, bandwidth allocation, fault localization,
etc. D4.4.1 and D4.4.2 provide a summary of research in different areas on different system concept
performed by partners within the scope of the task.
The main summarized outcomes from D4.4 are presented hereafter:
For mobile/business backhaul it has been shown that the initial requirements defined in D2.1 can be
supported within all the presented concepts with limited or some additional effort, where some
additional effort may at most consist of manual patching work for service provisioning.
For the effect of power saving techniques a comparison was made of ONU power saving modes for
the different system concepts. The ONU represents the dominating contribution to access network
power. Although results rely heavily on assumptions on traffic, it can generally be said that power
saving modes can reduce average ONU power consumption by about 90% when it is applied to
NGOA system concepts with a burst mode transmission and reception like high bit rate TDMA-
PONs and about 80% in hybrid TWDM-PONs. Moderate savings between 35 to 41% are found for
WDM-PON, AON and PtP systems. We have also described an innovative master-slave scheme that
can enable significant energy-efficiency savings across a range of equipment and system types in
the next-generation access network area. In particular, the master-slave approach offers a generic
scheme to enable devices and equipment (e.g. optical amplifiers, wavelength-selective switches,
routers, port aggregators etc.) to have a quasi-elastic power consumption profile with respect to the
offered traffic load. Whereas on their own, these types of equipment tend to have a high, fixed
power consumption, so that the overall energy dissipated during operation is inelastic with varying
incoming traffic load, when configured into a master-slave scheme, the overall power dissipation is
more elastic with respect to traffic load, and enables useful power saving. Offering a degree of
equipment redundancy, this also has the advantage of making the overall architecture/system more
resilient and robust. Although this may have higher CapEx implications, the combined higher
resilience and improved energy-efficiency should offer OpEx savings. In addition, we have
identified an innovative upgrade trajectory solution, which re-uses master units as slave units in a
subsequent generation upgrade, so saving on CapEx and offering still more TCO savings. These
master-slave schemes are applicable to all the NGOA architectures discussed in the OASE project,
and are complementary to the more conventional sleep/idle/hibernation modes that can also be
employed to reduce the overall carbon footprint of NGOA architecture solutions.
For the WDM-PON architecture, work related to implementation of efficient ODN fault-
localization was presented. The development enables accurate identification of faults in a wave-
length routed ODN providing operational advantages for this particular ODN with respect to ODN
fault localization and repair costs.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 18 of 80
For the hybrid WDM/TDM-PON architecture resource allocation is a critical point. The deliverable
presents work related to development of efficient TDMA resource allocation in the long-reach limit
where the large round-trip-time presents a challenge. The deliverable also presents work related to
dynamic wavelength allocation and expected efficiency of different wavelength allocation schemes.
Regarding power saving techniques a scheme for sleep mode control based on service requirements
was delevloped and evaluated in a simulation demonstrating some of the assumed energy saving
opportunities within this architecture.
For the NG-AON architecture a control plane implementation was implemented in order to
demonstrate intelligent control mechanisms, which enable reduction of network energy
consumption, reduction in core load and reduction in transit costs.
Finally, for the WDM-PON backhaul architecture to which much of the work associated with the
WDM-PON architecture and NG-AON applies, the deliverable reports work related to future
developments in mobile networks and support for CPRI transport.
�Open issues: none
3.4 WP5 - Techno-economic assessment
WP5 Start date: M0 - End date: M36
Activity type RTD
WPL TUM
Sub-tasks
Task 5.1- Overview of tools and methods [DTAG]
Task 5.2 - Modelling CapEx and OpEx [IMINDS]
Task 5.3 – Assessment and analysis of scenarios [TUM]
Deliverables / P3
[Due date] D5.3 - “Techno-economic” assessment studies [M36]
Milestones/ P3
[Due date]
M5.2 - First cost studies for different architectures and technologies
[M27]
M5.3 - TCO modelling and proposed TCO evaluation tool [M33]
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 10 4,8 6,2 15 6 9 17 5,96 11,3 12 6,1 5,9
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 1 0,3 0,3 1 0,48 0,2 9 5,79 6,2 4 1,55 2,5
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 19 of 80
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
0 0 0 6 1,81 2,8 75 32,79 44,4
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
According to the Annex I, the objectives of WP5 are as follows:
Objective 1: Survey of existing methods and tools and selection of the most suitable ones for
NG-OA networks (year 1)
Objective 2: Soundly cost classification to perform a detailed cost evaluation (year 1)
Objective 3: Detailed and accurate process-based cost modelling able to identify the cost
drivers (year 2)
Objective 4: Implementation of a TCO evaluation tool (first version in year 2, complete
version in year 3)
Objective 5: Analysis of different case studies, which would allow operators to identify the
most cost effective fibre roll out strategies given the deployment area, business scenario, etc.
(year 3)
Objective 6: Cost assessment of other work packages’ scenarios as for example, refinement
on the architecture to decrease its associated cost. (Year 3)
Objectives 1 and 2 were successfully achieved within this first period’s plan. The outputs regarding
objectives 3 and 4 were included in D5.2 and M5.3. Furthermore, objectives 5 and 6 were targeted
by task T5.3 and presented in D5.3.
T5.1– Overview of tools and methods [M1 – M9]
It fulfils WP5 objectives 1 and 2.
Significant results: Finalized during year 1
T5.2- Modelling CapEx and OpEx [M8 – M33]
It fulfils WP5 objectives 3 and 4.
Significant results: At the end of T5.2, a complete cost modelling of NGOA and its migration from
existing solutions has been presented. The cost modelling includes CAPEX (required investment,
its installation, etc.) as well as OPEX (fault management, power consumption, service provisioning,
etc.). A detailed cost model has been proposed for more complex operation processes such as fault
management and service provisioning.
The proposed TCO evaluation tool is able to dimension and evaluate cost of different architectures
(GPON, XGPON, Hybrid PON, WS WDM PON, WR WDM PON, AON + WDM Backhaul) for
different areas (dense urban, urban, rural) and different network consolidation scenarios (non-node
consolidation, conservative node consolidation, and aggressive node consolidation). Given this
dimensioning and the initial migration scenario and year, the yearly cost evaluation is presented.
Furthermore, NP and PIP costs are distinguished so that they can be used for business studies
(WP6). Last but not least, the tool considers the increase of salaries and energy cost per year and
provides discounted and non-discounted values.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 20 of 80
T5.3- Assessment and analysis of scenarios [M19-M36]
It fulfils WP5 objectives 5 and 6.
Significant results: Task 5.3 aimed at comparing the cost of different NGOA solutions on different
areas and node consolidation scenarios. The first study focused on the migration from an existing
traditional optical access network such as GPON or AON to an NGOA solution or any upgrade able
to offer 300Mpbs per user. In this migration scenario, the investments in terms of infrastructure and
equipment are considered assuming an existing optical distribution network (ODN). The cost
assessment showed that all the architectures have higher OPEX than CAPEX costs when summing
the costs from 2020 to 2030 (NGOA operational time) for any type of area (i.e. DU, U and R). The
most costly architecture is the UDWDM for any area, whereas the less costly solutions is to upgrade
existing optical access networks: upgrade existing GPON by reducing the splitting ration from 32 to
8 so that the bandwidth increases or to keep the AON as it is. However, when considering node
consolidation, the upgrade of GPON by reducing the splitting ratio is not an option due to the high
costs related to the new LL5 links (increases more than 1 CU/year per user). In that case, the
migration from GPON to HPON architecture is the most effective solutions for any type of area.
For AON, the best options is to connect AON AS with a WDM Backhaul.
If an operator do not start with a traditional optical access but has a non optical access solution, the
increase of cost with respect the previous study is mainly on the service provisioning (due to the
higher effort required to connect all users), as well as on the infrastructure cost (especially in rural
areas where the distances are significantly longer). Furthermore, the delta cost when considering a
purely greenfield scenario and implementing an NGOA has also been calculated for the node
consolidation scenario. The impact of duct availability on the infrastructure cost differs on the
architecture and on the area: higher for DU than rural areas, higher for AON P2P and WRWDM
PON than HPON solutions.
These studies show the key cost factors of each solution at each area and scenario. Furthermore, the
dependence of these results on different parameters such as regional differences, architecture fan
out, etc. have been studied in a sensitivity study. The salary and the adoption curves are the most
important impacting factors to the cost.
�Open issues: none
3.5 WP6 - Business modelling and regulatory aspects
WP6 Start date: M1 - End date: M36
Activity type RTD
WPL IMINDS
Sub-tasks
Task 6.1 Overview of tools and methods and identification of roles, actors
and value networks (DTAG)
Task 6.2 Market place models (UESSEX)
Task 6.3 Value network evaluation (IMINDS)
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 21 of 80
Task 6.4 Regulatory impact (Acreo)
Deliverables / P3
[Due date]
D6.3 - Value network evaluation [M36]
D6.4 - Regulatory impact [M36]
Milestones/ P3
[Due date] M6.3 - Market place models and adapted value network results [M27]
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
3 1,64 0,2 15 6,06 8,5 20 7,57 12,4 6 1,6 2 0 0 0
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 2 1,12 1 2 0,94 0,9 12 5,96 8,3 0 0 0
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
0 0 0 12 3,15 6,8 69 28,03 40,2
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
According to the Annex I, the objectives of WP6 are as follows:
Objective 1: Survey of existing tools and methods
Objective 2: Identification of roles, actors and value networks
Objective 3: Development of tools and methods for evaluating new business models and value
networks.
Objective 4: Evaluation of different business models and value networks taking into account
cooperation, competition, strategic decisions and regulatory aspects
Objective 5: Meeting requirements related to new business and cooperation models e.g.,
common use of infrastructure, demarcation lines and corresponding monitoring
Objective 6: Inspecting the regulatory impact on the business model and value network
WP6 objectives 4 and 5 were successfully achieved within the last reporting period, within task 6.3.
Objective 6 was successfully achieved within task 6.4.
T6.1– Overview of tools and methods and identification of roles, actors and value networks
[M1-M10]
Finalised in year 1
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 22 of 80
Fulfils: WP6 objective n°1, 2, 3
T6.2 Market place models [M9-M27]
Partially fulfils: WP6 objective n°4
Significant results:
Within this task, market demand and revenue models for next-generation optical access (NGOA)
networks have been described, based on a variety of methodological approaches: adoption models,
surveys, econometric analysis and case studies. Based on econometric analysis on a per country
basis, we have studied drivers and barriers for FTTH deployment. Lower level analysis was added
by different case studies. Starting from an overview of 11 deployments in Western Europe, we have
divided our analysis into three parts: urban cases, rural cases and large-scale deployments, and have
discussed the different characteristics for each of them. Revenue scenarios have been developed for
the timeframe 2011-2030, considering different levels of (inter- as well as intra-platform)
competition. Finally, we have reviewed the technologies to be employed in NGOA networks from
the perspective that they should be able to function within cooperative or open access environments.
T6.3 – Value network evaluation [M11-M36]
Fulfils: WP6 objective n°4, 5
Significant results:
Within this task, we have combined the costs and revenues from WP5 and D6.2 to evaluate
different business models and scenarios. We focused on the passive infrastructure (PIP) and active
equipment (NP), as well as on the cost and consequences for providing open access. We
furthermore investigated the impact of competition on the business case, and looked how demand
aggregation, longer planning horizons, duct reuse and flexibility options can improve the business
case for both actors. Finally, we also looked into other sources of revenues, so-called indirect
effects that could help to enhance the incentive to deploy for market players or increase the
willingness to pay of end-customers.
T6.4- Regulatory impact [M28-M36]
Fulfills WP6 objectives n°6
Significant results:
Within task 6.4, a thorough overview of the current regulatory situation was given, together with
reviews of regulatory trends and future directions. We described main stakeholder understandings
and presented quantitative evaluation of the impact of regulation by calculating the missing
revenues to come to a positive business case for the physical infrastructure provider. This was done
by applying extended game theoretic analysis, and by comparing the expected equilibrium to the
social optimum. The main conclusion of this analysis is that regulation can have a decisive impact
on the success of NGOA deployment and user take-up.
Finally, we formulated some regulatory guidelines to encourage and stimulate the deployment of
fiber-based infrastructure, the necessary profitability of the business case for the different NGOA
stakeholders, and a high service take-up rate among the European citizens in order to fullfill the
Digital Agenda for Europe.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 23 of 80
�Open issues: none
3.6 WP7 - Experimental Validation
WP7 Start date: M1 - End date:M36
Activity type RTD
WPL ADVA
Sub-tasks
Task 7.1 - Initial Lab Study [TEI]
Task 7.2 - Hardware Lab Trials [ADVA]
Task 7.3 – Basic Operational Concepts Trials [DTAG]
Deliverables / P3
[Due date]
D7.2.2 - Description of the test cases and specifications, and detailed
summary of the related test results of the hardware lab tests
(broken down into D7.2a/b), [M36]
D7.3.2 - Description of the test cases and specifications and detailed
summary of the related test results of the basic operational concepts lab
tests
(broken down into D7.3a/b), [M36]
Milestones/ P3
[Due date] /
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
0 0 0 12 3,58 4,1 0 0 0 0 0 0 0 0 0
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
35 8,22 16,2 0 0,05 0 11 5,02 7,6 0 0 0 5 5 0,8
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
10 15,9 1,9 0 0 0 73 37,77 29,9
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
WP7 objectives are:
Objective1: Provide two independent testbeds in order to test, and compare against each
other, two versions of NG-OA systems as specified in WP3 and WP4
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 24 of 80
Objective 2: Experimentally verify and, if applicable, quantify all relevant architecture-
related and systems hardware parameters as defined in WP3 and WP4
Objective 3: Experimentally verify and, if applicable, quantify selected (basic) operational
concepts functionalities and parameters (as defined in WP3/4 and in particular in T7.3a/b)
Objective 4: Provide feedback to WP2-WP6 and WP8.
T7.1 – Initial Lab Study [M1 – M12]
Finalised in year 1
T7.2 – Hardware Lab Trials [M13 – M36]
Fulfilled objectives 2, 4
Significant results: T7.2, associated with Objectives 2 and 4, was continued and finalized in Year
3. The hardware-related work in WP7 concentrated on various aspects of the WDM layer of next-
generation PON systems. As such, it covers both, relevant aspects of NG-PON2 (according to draft
recommendation G.989.2) and also future systems beyond NG-PON2. The work also covers pure
WDM-PON and WDM-based PON like Hybrid WDM/TDMA-PON or OFDM-PON running on
several wavelengths.
The hardware-related work focused on two approaches for the WDM layer: seeded reflective
transmitters and tunable lasers. Regarding seeded reflective transmitters, the wavelength-reuse
approach with combined IRZ/RZ coding (Inverse Return-to-Zero / Return-to-Zero) was followed.
Regarding tunable lasers, wavelength-control schemes which enable low cost were followed. In
both areas, significant advances were made in Year 3 (compared to end of Year 2, or the beginning
of the project).
The IRZ/RZ wavelength-reuse scheme was improved towards higher bit rates and higher reaches.
This addressed the requirements which were defined in WP2. Bit rates of 10 Gb/s per channel were
achieved with distances up to 20 km. For 2.5 Gb/s per channel, distances up to 60 km were
achieved. Both bit-rate reach products represent significant advances over former prior art.
For tunable lasers, the work of Year 2 was continued. A new wavelength-control scheme was
developed and successfully tested. Together, the wavelength-control schemes investigated and
developed in OASE are the formerly missing enabler for low-cost tunable lasers which can be used
in the PON context. Altogether, several schemes were tested with several types of lasers, including
DS-DBR and Y-Branch lasers.
Throughout the project, feedback was given to the other work packages. The T7.2 work also led to
several dissemination activities.
T7.3 – Basic Operational Concepts Trials [M25 – M36]
Fulfilled objectives 3, 4
Significant results: T7.3 directly addressed Objectives 3 and 4. Here, the focus was on operational
aspects, rather than hardware and related performance. This work split into two major parts:
migration-related tests with a commercial WR-WDM-PON which were conducted as a lab trial by
Magyar Telekom and a field trial by Slovak Telekom, and complementing investigation of
operations-related aspects in the ADVA lab.
The field trial in Bratislava confirmed that WR-WDM-PON is able to coexist with GPON on the
same PON feeder fibre between the remote node and the OLT in the central office. It does not
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 25 of 80
support full coexistence in the first mile, i.e., between the end user and the remote node, due to the
need of WDM filters (AWGs). Therefore, for full coexistence, parallel operation of two systems is
required. This finding holds for all WDM-filtered PON variants.
In addition, the lab trial in Budapest confirmed that the (commercial) WR-WDM-PON system is
easy to configure and manage. Set-up of an access line only required Ethernet VLAN configuration,
as compared to GPON which in addition required configuration of the MAC layer.
The originally planned operations-related work in the ADVA lab had to be re-scheduled during the
project runtime due to lack of availability of key components. In particular, low-cost tunable lasers
will only become available around 2015. This delayed tests regarding ONU self-tuning and self-
installation. These tests will later be conducted, and results reported in either the EU PIANO+
projects TUCAN/IMPACT, or the EU project COMBO. As a replacement, several tests regarding
reach extension (where covering extended reach is an operational aspect) were conducted. These
tests successfully confirmed that with remotely-pumped Erbium fibres, up to 100 km reach can be
achieved for tunable-laser-based WDM-PON. Here, it has to noted that remotely pumped amplifiers
have significant (management, power-supply) advantages over lumped active components placed
somewhere in the ODN.
Similar to T7.2, feedback was given to the other work packages.
�Open issues: none
3.7 WP8 - Dissemination of results
WP8 Start date: M1 - End date: M38
Activity type RTD
WPL ACREO
Sub-tasks
Task 8.1 Dissemination material & publication policy (JCP)
Task 8.2 – Standardisation (DTAG)
Task 8.3 – Collaborations (Acreo)
Deliverables / P3
[Due date]
D8.2 - Dissemination material and publication policy [M36]
D8.4 - Report on standardization and dissemination activities [M36]
D8.5 - OASE - key results presentation [M38]
Milestones/ P3
[Due date] /
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
7,5 3,03 4,2 13,5 4,3 8,2 7,5 1,84 5,1 5,5 2,11 4 8,5 3,2 5,2
ADVA EA TEI ACREO MT
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 26 of 80
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
17,5 4,6 11,8 4,5 1,8 2,1 2 0,57 2,7 14,5 10,3 7,9 1 0,25 0,8
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
3 0,15 0,7 6 1,82 3,7 87 33,67 56,2
Overall Men/Months (MM) table, detailed information per partner and graphical representation of
MM spending are to be found in Chapter 5 “Project Management” – Section 5.4 – page 38”
The objectives of WP8 are:
Objective 1: To make the objectives and the scope of the project publicly available and to
coordinate and handle the dissemination of OASE results
Objective 2: To recommend the findings and results of OASE with respect to a European
NG-OA solution to standardisation bodies
Objective 3: To communicate with relevant European projects and European network
operators to establish a broad consensus for standardisation activities
T8.1 – Dissemination material & publication policy [M1 – M36]
Fulfilled objectives: Objective 1 for year 3 was fulfilled
At the end of year 1, this objective had been specified in more detailed targets, which were
successfully met during the all project duration
To complete and update the “communication kit” (leaflet, new logo, updated poster and
website)
To produce project newsletters (four totally)
To disseminate the project results to the research community (over 100 papers, several
invited presentations, over ten workshops)
Significant results:
OASE was extremely visible.
The communication kit (Poster, leaflet) was updated and shown at several events partners attended.
Project results have been published through articles, papers and presentations at various
international and national conferences and workshops. Among others, OASE has had a presence at
the following major events:
• OFC/NFOEC 2012
• CTTE 2012
• ICTON 2012
• ECOC 2012
• ACP 2012
• ONDM 2012
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 27 of 80
• FTTH Forum 2012
Moreover, the project results will be presented at few more prestigious events during the spring of
2013, including ONDM 2013, where the OASE project has been invited to organise a dedicated
workshop. Information was largely distributed through the 5th
and final newsletter that was
distributed early February 2013.
As already done during previous years, some of the academic partners of the project have
disseminated the project vision and results within their students in the form of lectures and courses.
Dissemination was also achieved by actively contributing to Concertation and Cluster Meetings
organised by the EC but also towards the FTTH Council Europe, the Technology Platforms such as
the Photonics21 events, the NEM Summit and FIA events or the Future Network & Mobile
Summit.
As reported in previous years, Collaboration was established not only with several EC funded
projects, (namely NoE TREND, ACCORDANCE,ALPHA, SPARC, COMBO & C-3PO projects)
but also with with various relevant national projects.
The complete dissemination activities have been detailed in D8.4.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 28 of 80
Authors Paper title/ Tutorial title Name of journal,
conference, etc.
Vol., no.,
pages,
location
Date Status
1
Marilet De Andrade, Jiajia
Chen, Björn Skubic, Jawwad
Ahmed and Lena Wosinska
Enhanced IPACT: Solving the Over-Granting
Problem in Long-Reach EPON
Telecommunicati
on Systems Accepted
2
Bart Lannoo, Goutam Das,
Abhishek Dixit, Didier Colle,
Mario Pickavet, Piet
Demeester
Novel hybrid WDM/TDM PON architectures to
manage flexibility in optical access networks
Telecommunicati
on Systems Accepted
3
Goutam Das, Bart Lannoo,
Abhishek Dixit, Didier Colle,
Mario Pickavet, Piet
Demeester
Flexible hybrid WDM/TDM PON architectures using
wavelength selective switches
Optical Switching
and Networking
(OSN)
Vol. 9, Iss.
2, pp. 156-
169
Apr.
2012 Accepted
4
Abhishek Dixit, Bart Lannoo,
Goutam Das, Didier Colle,
Mario Pickavet, Piet
Demeester
AMGAV: Adaptive Multi-GATE polling with Void
filling for Long-Reach Ethernet Passive Optical
Networks
IEEE Network
Magazine Submitted
5
K. Grobe, R. Huelsermann, D.
Breuer, C. Cehovin, J.-P.
Elbers
Combined OLT Form-Factor and Power-
Consumption Analysis for WDM-based Next-
Generation PON
ITG Workshop
Photonic
Networks
Leipzig,
Germany
April
2012 Submitted
6
Orthodoxos Kipouridis,
Carmen Mas Machuca,
Achim Autenrieth, Klaus
Grobe
Cost assessment of Next-Generation Passive Optical
Access Networks on Real-Street Scenario
OFC/NFOEC
2012
Los
Angeles,
USA
Mar.
4-8,
2012
Accepted
7
Markus Roppelt, Michael
Eiselt, Klaus Grobe and Jörg-
Peter Elbers
Tuning of an SG-Y Branch Laser for WDM-PON OFC/NFOEC
2012
Los
Angeles,
USA
Mar.
4-8,
2012
Accepted
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 29 of 80
8 D. Breuer Results from the OASE projects ONDM 2012 USA
9
Björn Skubic, Alberto
Bianchi, Stefan Dahlfort,
Fabio Cavaliere
Cost, Power and Performance Analysis of WDM-
PON Systems Based on Reflective Transmitters for
Next-Generation Optical Access
OFC/NFOEC
2012
Los
Angeles,
USA
Mar.
4-8,
2012
Accepted
10 K. Grobe, J.-P. Elbers Overview on WDM-PON – the NG-PON2
Perspective
ITG Conf.
Breitband-
versorgung in
Germany
Berlin,
Germany
Mar.
19-20,
2012
Accepted
11
Marlies Van der Wee, Crister
Mattsson, Anand Raju,
Olivier Braet, Alberto
Nucciarelli, Bert Sadowski,
Sofie Verbrugge, Mario
Pickavet
Measuring the success rate of fiber-based access
networks. Evaluation of the Stokab case and
comparison to other Western European cases
Journal of the
Institute of
Telecommunicati
ons Professionals
(ITP)
2012
(uploa
ded in
2011,
see
comm
ent)
Accepted
12 M. Forzati and C. Mattsson The uncaptured values of FTTH FTTH Conference
2012
Munich,
Germany
Mar.
14-16
2012
Accepted
13 M.C. Parker, S.D. Walker
Stochastic Energy-Efficiency Optimization in
Photonic Networking by use of Master-Slave
Equipment Configurations
ONDM 2012 Colchester
, UK
April
2012 Accepted
14
Orthodoxos Kipouridis,
Carmen Mas Machuca,
Achim Autenrieth, Klaus
Grobe
Street-aware infrastructure planning tool for Next
Generation Optical Access networks ONDM 2012
Colchester
, UK
April
2012 Accepted
15
Marlies Van der Wee, Koen
Casier, Karel Bauters, Sofie
Verbrugge, Didier Colle,
Mario Pickavet
A modular and hierarchically structured techno-
economic model for FTTH deployments.
Comparison of technology and equipment placement
as function of population density and number of
flexibility points
ONDM 2012 Colchester
, UK avr-12 Accepted
16 Carmen Mas Machuca, Jiajia
Chen, Lena Wosinska Cost-Efficient Protection in TDM PONs IEEE COMMAG
vol. 50,
pp. 110-
Aug.
2012 Accepted
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 30 of 80
117
17
Mozhgan Mahloo, Carmen
Mas Machuca, Jiajia Chen,
Lena Wosinska
Protection cost evaluation of WDM-based Next
Generation Optical Access Networks
Optical Switching
and Networking
(OSN)
Accepted
18 Lech Wosinski, Jiajia Chen
and Lena Wosinska,
Si-based monolithically integrated triplexer
transceiver for FTTH applications
SPIE Photonics
North Canada
June
2012 Accepted
19
Abhishek Dixit, Jiajia Chen,
Mozhgan Mahloo, Bart
Lannoo, Didier Colle and
Mario Pickave
Efficient Protection Schemes for Hybrid WDM/TDM
Passive Optical Networks ICC 2012 Canada
June
2012 Accepted
20 Carmen Mas Machuca Complete cost analysis of Hybrid PON architectures
for Next Generation Optical Access Networks ACP 2012
Guangzho
u
nov-
12 Accepted
21 Carmen Mas Machuca Energy evaluation of NGOA architectures on
different deployment scenarios ACP 2012
Guangzho
u
nov-
12 Accepted
22 S. Verbrugge, K. Casier, C.
Mas Machuca,
Business models and their costs for the next
generation optical access networks ICTON 2012
Conventry
, UK
juil-
12 Accepted
23 Carmen Mas Machuca NGOA cost modeling and its application to HPON
cost evaluation CTTE 2012
Athens,
Greece
juin-
12 Accepted
24 C. Mas Machuca, K. Wang,
M. Kind, K. Casier
Total Cost Comparison of Next Generation Optical
Access Networks with Node Consolidation NOC 2012
Vilanova,
Spain
juin-
12 Accepted
25 C. Mas Machuca, K. Wang,
M. Kind, K. Casier
Cost-based assessment of NGOA architectures and
its impact in the business model CTTE 2012
Athens,
Greece
juin-
12 Accepted
26 Marlies Van der Wee Business modeling for NGOA - Impact of revenue
potential and multiple actors on the business case CTTE 2012
Athens,
Greece
juin-
12 Accepted
27
Jawwad Ahmed, Jiajia Chen,
Biao Chen, Lena Wosinska
and Biswanath Mukherjee
Efficient Inter-Thread Scheduling Scheme for Long-
Reach Passive Optical Networks IEEE COMMAG Accepted
28
Michele Chincoli, Luca
Valcarenghi, Jiajia Chen,
Paolo Monti, and Lena
Wosinska
Investigating the Energy Savings of Cyclic Sleep
with Service Guarantees in Long Reach PONs ACP 2012
Guangzho
u
nov-
12 Accepted
29 Jiajia Chen, Mozhgan Reducing the Impact of Failures in Next Generation ACP 2012 Guangzho nov- Accepted
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 31 of 80
Mahloo, and Lena Wosinska Optical Access Networks u 12
30
Marlies Van der Wee, Menno
Driesse, Bernd
Vandersteegen, Pierre Van
Wijnsberge, Sofie Verbrugge,
Bert Sadowski, Mario
Pickavet
Identifying and quantifying the indirect benefits of
broadband networks: a bottom-up approach
19th ITS Biennial
Conference
Bangkok,
Thailand
nov-
12 Accepted
31
Sofie Verbrugge, Marlies Van
der Wee, Maria Fernandez-
Gallardo, Kristaps Dobrajs,
Mario Pickavet
Some insights in regulation and potential profitability
of passive fiber infrastructure in Europe
19th ITS Biennial
Conference
Bangkok,
Thailand
nov-
12 Accepted
32 M. Forzati Socio-economic effects of FTTH/FTTx in Sweden ICTON 2012 Coventry,
UK
juin-
12 Invited
33 M. Forzati, C. Mattsson, S.
Aal E-Raza
Early effects of FTTH/FTTx on employment and
population evolution, an analysis of the 2007-2010
time period in Sweden
CTTE 2012 Athens,
Greece
juin-
12 Accepted
34 Jiajia Chen, Patryk Urban and
Lena Wosinska
Fast Fault Monitoring Technique for Reliable WDM
PON: Achieving Significant Operational Saving OFC 2013 USA Accepted
35
Paweł Wiatr, Jiajia Chen,
Paolo Monti and Lena
Wosinska
Green WDM-PONs: Exploiting Traffic Diversity to
Guarantee Packet Delay Limitation ONDM2013
Budapest,
Hungary Accepted
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 32 of 80
T8.2 – Standardisation [M13 – M36]
Fulfilled objectives: WP8 objective n°2 fulfilled for year 2
Driving the various standardisation bodies towards a European-based standard for next-generation
access was an important objective of the project. As such, the OASE industrial partners have
participated in and sent contributions to meetings organised by institutions such as the IEEE, ITU-
T, OIF, MEF; in particular, the findings and results of OASE with respect to a European NG-OA
solution have been heavily promoted towards the FSAN forum, which is the gateway to ITU
standardisation (see D8.4 for more details)
Significant results: Made an impact on standardisation via FSAN
Date Host(s) and
venue
Meeting Contribution
November 2009 Mitsubishi,
Kyoto
FSAN Meeting
Q4/2009
ADVA poster on NG-PON
February 2-4
2010
Cortina Systems,
San Francisco,
CA, USA
FSAN Meeting
Q1/2010
ADVA contribution on WDM-PON
April 20-22
2010
Huawei, China
August 31-
September 2
2010
Nokia Siemens
Networks,
Munich,
Germany
FSAN Meeting
Q3/2010
ADVA contribution on WDM-PON
DTAG contribution on requirements
(FSAN operator group)
November 2010 Vitesse, Las
Vegas
FSAN Meeting
Q4/2010
ADVA contribution on WDM-PON
January 2011 OKI, Tokyo FSAN Meeting
Q1/2011
ADVA contribution on OASE WP4
results
Joint ADVA+EA contribution on
solutions for NG-PON2
May 2011 DTAG, Berlin FSAN Meeting
Q2/2011
Joint ADVA+NSN contribution on
WDM-PON components, ADVA
contribution on WDM-PON,
EA contribution on protection for
WDM-PON
June 2011 ITU, Seoul ITU-T Q.6&7/SG15
interim meeting
EA and ADVA contribution on
G.sdapp, together with ZTE and
others
September 2012 ITU, Geneva ITU Geneva meeting Contributions by ADVA to
SG15/Q6, Metro WDM (Q2 and Q6
are somewhat overlapping)
February 2013 Fuzhou, China FSAN meeting Two joint contributions NSN-ADVA
regarding the WDM point-to-point
part of NG-PON2.
T8.3 – Collaborations [M1 – M36]
Fulfilled objectives: WP8 objective n°3 fulfilled for year 2
OASE has had extensive collaboration with several European projects (mainly through workshops),
various relevant national projects (Belgian, Swedish, German) or organisations, some technology
Platforms (Photonics21, NEM, FIA) and European network operators (mainly through bilateral
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 33 of 80
meetings within the Industry Board, and the newly formed Alternative Operator Board); see D8.4
for more details.
Significant results:
Discussion on requirements with other operators through the activity of the Industry Board
(IB - that includes the major incumbent telecom operators in Europe today: Telecom Italia
(TI) represented by Mr. Paolo Solina (currently Chair of FSAN) , France Telecom (FT)
represented by Mr. Bruno Capelle (member of the FSAN management); British Telecom
(BT) represented by Mr. Derek Nesset and Telefonica (TID) represented by Rafael Canto
Palancar
Establishment of Alternative Operator Board (AOB) chaired by iMinds including
representatives from alternative (non-incumbent ) operators with a potential interest in
optical access network deployment; The purpose of this board was, on one hand, to gather
views and directions from actors on the requirements and the choice made by the project in
order to complement the feedback received by the IB and ,on the other hand , Equally
importantly, to provide inputs regarding transaction costs, and business operation
considerations on open networks.
Several joint workshops with other EU projects, namely with ALPHA, ACCORDANCE,
SARDANA, STRONGEST, NoE TREND and GIGAWAM)
�Open issues: none
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 34 of 80
4. Deliverables and milestones tables
Del. no. Deliverable name WP
no.
Lead
participant Nature
Dissem.
level
Due
delivery date
Annex I
Delivered
Yes/No
delivery
date Comments
D4.2.2 Technical assessment and comparison of next-
generation optical access system concepts 4 UESSEX R PU 27 Yes 03/04/2012 Delivered on time
D4.3.2 Operational impact on system concepts 4 DTAG R PU 27 Yes 03/04/2012 Delivered on time
D4.4.1 Development of selected system concepts 4 TEI R RE 33 Yes 08/10/2012 Delivered on time
D4.4.2
Development of selected system concepts (Public
version, certain confidential data is removed if
necessary)
4 TEI R PU 33 Yes 08/10/2012 Delivered on time
D2.2.2 Consolidated requirements for European next-
generation optical access networks 2 DTAG R PU 34 Yes 14/11/2012 2 weeks delayed
D3.2.2 Description and assessment of architecture options 3 KTH R PU 34 Yes 02/11/2012 Delivered on time
D3.3 Co-operation models 3 Acreo R PU 35 Yes 07/12/2012 Delivered on time
D3.4 Migration paths 3 IMINDS R PU 36 Yes 31/03/2013 Delayed
D5.3 “Techno-economic” assessment studies 5 TUM R PU 36 Yes 21/01/2013 3 weeks delayed
D6.3 Value network evaluation 6 IMINDS R PU 36 Yes 08/02/2013 4 weeks delayed
D6.4 Regulatory impact 6 ACREO R PU 36 Yes 27/12/2012 Delivered on time
D7.2.2
Description of the test cases and specifications, and
detailed summary of the related test results of the
hardware lab tests
(broken down into D7.2.1 and D7.2.2),
7 TEI R RE 36 Yes 27/12/2012 Delivered on time
D7.3.2
Description of the test cases and specifications and
detailed summary of the related test results of the
basic operational concepts lab tests (broken down
into D7.3.1 and D7.3.2),
7 DTAG R RE 36 Yes 27/12/2012 Delivered on time
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 35 of 80
D8.2 Dissemination material and publication policy 8 ACREO R PU 36 Yes 28/02/2013 Delivered on time
D8.4 Report on standardization and dissemination
activities II 8 ACREO R PU 36 Yes 28/02/2013 Delivered on time
D8.5 OASE - key results presentation 8 DTAG R PU 38 Yes 18/03/2013 2 weeks delayed
D1.9 Third year Annual Report 1 JCP R PU 38 Yes 08/04/2013 2 weeks delayed
D1.10 Final Report 1 JCP R PU 38 Not yet /
Planned to be
delivered by
18/04/2013
Table 2 - Deliverables submitted during 2012-2013
*Remark: all the Public deliverables are available for download on the OASE Website
Milestone
no. Milestone name
Due date
From
Annex I
Achieved
Yes/No
Actual /
Forecast
achievement
date
Comments
M1.1x QMR 7 to 10
27
30
33
35
Yes
June 1st, 2012
Sept. 5th 2012
Nov.15th
, 2012
Feb. 26, 2013
Reports, submitted to EC
M3.5 Preliminary evaluation of architectures II M26 Yes Available in due time
M3.6 Architecture options M31 Yes Available in due time
M4.3 System concepts for next-generation optical
access; Further development results M30 Yes Available in due time
M5.2 First cost studies for different architectures and
technologies M27 Yes Available in due time
M5.3 TCO modelling and proposed TCO evaluation tool M33 Yes Available in due time
M6.3 Market place models and adapted value network
results M27 Yes Available in due time
Table 3 - Milestones produced within 2012-2013
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 36 of 80
5. Project management
WP1 Start date M1 - End date M38
Activity type MGT
WPL JCP-Consult
Sub-tasks
Task 1.1 - Project Organization and Management [JCP]
Task 1.2 - Project Quality Management [JCP]
Task 1.3 – Project Risk Management [JCP]
Deliverables /P3 D1.9– Annual Periodic report (M38+2)
Milestones/ P3
QMR M25-M27 (M28)
QMR M28-M30 (M31)
QMR M31-M33 (M34)
QMR M34-M36 (M37)
Participant MM expenses – Total Project (TP) / Cumulated expenses Period 3 (CE)
Cumulated expenses Year 1+Year2 (CE2Y)
JPC DTAG IMINDS TUM KTH
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
22 8,5 14,2 6 1,4 4,3 1 0,5 0,5 1 0,41 0,5 1 0,4 0,7
ADVA EA TEI ACREO MT
TP CE CE2
Y TP CE CE2Y TP CE CE2Y TP CE
CE2
Y TP CE CE2Y
1 0,42 0,8 1 0,38 0,6 1 0,27 0,9 1 0,35 0,7 1 0,5 0,6
ST UESSEX TOTAL
TP CE CE2
Y TP CE CE2Y TP CE CE2Y
1 1,42 -0,1 1 0 0,4 38 14,54 25,1
WP1 aims at addressing all the administrative and financial management of the project.
The main objectives that follow were successfully addressed during this third period
Establish appropriate relationships and communication channels with the funding
actors as well as between consortium partners
Administer the project resources and monitor the overall project performance
Coordination/operation management
Risk management
Reporting to the EU
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 37 of 80
5.1 Task 1.1 - Project Organisation and Management
During this third reporting period (January 2012-February 2013), WP1 coordinated the financial,
legal and administrative work in the consortium.
After several iterations, latest modifications to the DoW were accepted and the official version is
dated January 25th
, 2013, the main modification being related to the project overall duration
extension (from 36 to 38 months) and the introduction of an additional deliverable (D8.5). The
contract was amended and officially notified by registered letter dated February 25th
, 2013.
During that third period, WP1 took care of all the administrative and financial questions related to
the second Annual review that took place on March 27th
, 2012; several iterations were provided on
D1.8 (2011 Annual report), additional information on financial statements were provided by
partners and the NEF session was submitted by the end of November 2012; we received notification
of payment processing by November 30th
and payment (531 182 €) arrived on bank account on
January 22nd
2013; payment was made to partners on February 21st, 2013.
With regard to the legal aspect of the project, the fifth General Assembly was convened on March
4th
, 2013 mostly to acknowledge funds’ receipts and to comment overall results generated by the
project that just ended.
Table 4 – 4th funds distribution – February 21
st, 2013
The table below summarizes the overall financial situation after the second yearly review
A
Beneficiary
short name
Total requested
grant
JCP 366 631,00
DTAG 741 403,00
IBBT 639 860,00
TUM 296 300,00
KTH 577 808,00
ADVA 635 626,00
EA 128 958,00
TEI 238 562,00
Acreo 769 821,00
MT 76 820,00
ST 83 418,00
UESSEX 425 050,00
≠ due to
rounded figures
4 980 257,00
*total Paid after 3rd payment including prepayments made on jan & sept 2010 and 3rd payment madecearly oct 2011
**before end of project (90% ceiling - EC guarantee) -
OASE (GA 249025) - 4 Payment proposal (February 2013)
B
CE
Guarantee
18 332 €
37 070 €
31 993 €
14 815 €
28 890 €
31 781 €
6 448 €
11 928 €
38 491 €
3 841 €
4 171 €
21 253 €
-1 €
249 012 €
*total Paid after 3rd payment including prepayments made on jan & sept 2010 and 3rd payment madecearly oct 2011
**before end of project (90% ceiling - EC guarantee) -
OASE (GA 249025) - 4 Payment proposal (February 2013)
C D
total Paid
after 3rd
payment*
2nd review
accepted
funding
294 750 € 124 514 €
534 744 € 220 121 €
454 772 € 245 709 €
223 756 € 86 765 €
459 541 € 229 306 €
454 440 € 129 909 €
97 521 € 56 492 €
160 034 € 51 206 €
589 927 € 242 333 €
55 643 € 15 049 €
48 659 € 12 058 €
328 251 € 160 498 €
3 702 036 € 1 573 960 €
*total Paid after 3rd payment including prepayments made on jan & sept 2010 and 3rd payment madecearly oct 2011
**before end of project (90% ceiling - EC guarantee) -
OASE (GA 249025) - 4 Payment proposal (February 2013)
E F G H
4th payment
proposal90% ceiling
max to be
paid**
achieved after
4th payment
16 886 € 329 967,90 € 311 636,35 € 311 635,98 €
95 449 € 667 262,70 € 630 192,55 € 630 192,77 €
89 109 € 575 874,00 € 543 881,00 € 543 880,66 €
28 099 € 266 670,00 € 251 855,00 € 251 854,66 €
31 596 € 520 027,20 € 491 136,80 € 491 136,86 €
85 842 € 572 063,40 € 540 282,10 € 540 282,22 €
12 094 € 116 062,20 € 109 614,30 € 109 614,70 €
42 744 € 214 705,80 € 202 777,70 € 202 777,96 €
64 421 € 692 838,90 € 654 347,85 € 654 348,14 €
9 654 € 69 138,00 € 65 297,00 € 65 296,67 €
12 058 € 75 076,20 € 70 905,30 € 60 716,70 €
33 042 € 382 545,00 € 361 292,50 € 361 292,83 €
520 994 €
*total Paid after 3rd payment including prepayments made on jan & sept 2010 and 3rd payment madecearly oct 2011
**before end of project (90% ceiling - EC guarantee) -
OASE (GA 249025) - 4 Payment proposal (February 2013)
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 38 of 80
Table 5 - OASE Consolidated (2010-2011) financial Overview
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 39 of 80
In addition to the emails exchanges addressing daily activity of the project (assistance to partners),
WP1 assisted partners who hosted the project meetings in organizing them; WP1 distributed
information related to the practical aspects such as accommodation, list of attendees & agenda but
also took care of the completion of the minutes and follow-up action items.
In addition to the face-to-face meetings, WP1 helped in setting-up several conferences calls on
technical matters, and, when needed, on administrative matters.
With regards to the reporting matters, WP1 organised the monthly (internal purposes) and Quarterly
Management report (QMR contractual) reporting tools
The 9th QMR (QMRM25-M27) has been delivered to the EC on June 1st, 2012.
The 10th QMR (QMRM28-M30): has been delivered to the EC on September 5th 2012.
The 11th QMR (QMRM31-M33) a first has been delivered to the EC on October 29th
, 2012 and
the released version was delivered by November 15th
, 2012
The 12th
QMR (QMRM34-M36) has been delivered to the EC on February 26, 2013
Specific time slots to prepare the second review (held in March 2012) were defined and organised:
2 PMC telcos (January 13 and March 2nd
, 2012), one WPLs 's telco (January 26 and 2 review
preparation days (February 10th
and March 26th
).
The preparation of the third annual review was launched during plenary meeting that was organised
on December 4 to 6, 2012 in Berlin; the initial review was planed to be co-located with the ONDM
conference (April 16-April 18, Brest France) where OASE planed to present its overall project
results in a dedicated workshop. Due to unavailability of some reviewers at that period, those plans
were modified by the end of January 2013 and the review date and location were finally defined to
be Brussels, April 24th
, 2013.
5.2 Task 1.2 - Project Quality Management
During the third period of activity, the quality of results provided stayed the first concern of the
consortium.
As for previous period, a high level of communication was maintained within the consortium; WP1
allocated a constant effort in organising regular project meetings and, in between them, teleconferences
(general and/or technical).
As for previous period, each first Friday of the month, monthly teleconferences have been organised
where the Project Management Committee (PMC) and at least one representative per partners attended.
In parallel, as reported in the WP technical description of activities, each WP Leader has set-up regular
teleconferences with the partners involved. For each of these teleconferences, a document summarizing
the minutes and action points has been uploaded on the collaborative tool.
The internal monthly report was maintained as it allows an easy follow-up of resources, spending and
track of activities.
Following to the rules described in the D1.3 "project Quality Insurance Manual" all the deliverables
submitted this year, except the deliverables produced in WP1 and WP8 reviewed by all the consortium
members, were controlled by at least two internal reviewers appointed inside the consortium
companies.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 40 of 80
5.3 Task 1.3 - Project Risks Management
During this third year of activities, risks aspects were continuously controlled during the meetings
but also during monthly PMC conference calls. Reaching the end of the project, we can now report
that none of the major risks, which we had been able to identify, previously applied to any of our
activities.
The biggest challenge has been to aggregate all results within the defined and agreed deadlines.
5.4 Project person per month resources declared in Year 3
JCP
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 22,00 8,50 14,14 22,64 -0,64
WP2 – Requirements for European
next-generation optical access networks - - - - -
WP3 Next-generation optical access
architectures - - 0,06 0,06 -0,06
WP4 System concepts for next-
generation optical access networks - - - - -
WP5 Techno-economic assessment - - - - -
WP6 Business modelling and
regulatory aspects 3,00 1,64 0,16 1,80 1,20
WP7 Experimental Validation - - - - -
WP8 Dissemination of results 7,50 3,03 3,99 7,02 0,48
Total PM 32,50 13,17 18,35 31,52 0,98
DTAG
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 6,00 1,40 4,30 5,70 0,30
WP2 – Requirements for European
next-generation optical access networks 6,00 1,00 4,57 5,57 0,43
WP3 Next-generation optical access
architectures 11,00 3,95 6,27 10,22 0,78
WP4 System concepts for next-
generation optical access networks 10,00 0,95 9,02 9,97 0,03
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 41 of 80
WP5 Techno-economic assessment 10,00 4,80 6,17 10,97 -0,97
WP6 Business modelling and
regulatory aspects 15,00 6,06 8,52 14,58 0,42
WP7 Experimental Validation 12,00 3,58 4,14 7,72 4,29
WP8 Dissemination of results 13,50 4,30 8,17 12,47 1,03
Total PM 83,50 26,03 51,16 77,19 6,31
iMinds
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,50 0,54 1,04 -0,04
WP2 – Requirements for European
next-generation optical access networks 2,00 0,55 1,36 1,91 0,09
WP3 Next-generation optical access
architectures 15,00 6,02 8,88 14,90 0,10
WP4 System concepts for next-
generation optical access networks 13,00 6,02 7,14 13,16 -0,16
WP5 Techno-economic assessment 15,00 6,00 9,01 15,01 -0,01
WP6 Business modelling and
regulatory aspects 20,00 7,57 12,44 20,01 -0,01
WP7 Experimental Validation - - - - -
WP8 Dissemination of results 7,50 1,84 5,13 6,97 0,53
Total PM 73,50 28,50 44,50 73,00 0,50
TUM
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,38 0,46 0,84 0,16
WP2 – Requirements for European
next-generation optical access networks 3,00 0,50 0,87 1,37 1,63
WP3 Next-generation optical access
architectures 4,00 1,28 2,39 3,67 0,33
WP4 System concepts for next-
generation optical access networks 2,00 0,99 1,63 2,62 -0,62
WP5 Techno-economic assessment 17,00 5,96 11,29 17,25 -0,25
WP6 Business modelling and
regulatory aspects 6,00 1,60 2,02 3,62 2,38
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 42 of 80
WP7 Experimental Validation - - - - -
WP8 Dissemination of results 5,50 2,11 3,96 6,07 -0,57
Total PM 38,50 12,82 22,62 35,44 3,06
KTH
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,40 0,70 1,10 -0,10
WP2 – Requirements for European
next-generation optical access networks 3,00 1,00 2,00 3,00 -
WP3 Next-generation optical access
architectures 20,00 6,02 14,10 20,12 -0,12
WP4 System concepts for next-
generation optical access networks 18,00 4,80 13,20 18,00 -
WP5 Techno-economic assessment 12,00 6,10 5,91 12,01 -0,01
WP6 Business modelling and
regulatory aspects - - - - -
WP7 Experimental Validation - - - - -
WP8 Dissemination of results 8,50 3,20 5,20 8,40 0,10
Total PM 62,50 21,52 41,11 62,63 -0,13
ADVA
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,42 0,58 1,00 -
WP2 – Requirements for European
next-generation optical access networks - - - - -
WP3 Next-generation optical access
architectures 12,00 3,40 10,52 13,92 -1,92
WP4 System concepts for next-
generation optical access networks 12,00 2,22 14,96 17,18 -5,18
WP5 Techno-economic assessment - - - - -
WP6 Business modelling and
regulatory aspects - - - - -
WP7 Experimental Validation 35,00 8,22 19,94 28,16 6,84
WP8 Dissemination of results 17,50 4,60 13,44 18,04 -0,54
Total PM 77,50 18,86 59,44 78,30 -0,80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 43 of 80
EAB
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,38 0,61 0,99 0,01
WP2 – Requirements for European
next-generation optical access networks 1,00 - 1,00 1,00 -
WP3 Next-generation optical access
architectures 4,00 1,32 2,67 3,99 0,01
WP4 System concepts for next-
generation optical access networks 8,00 1,14 6,64 7,78 0,22
WP5 Techno-economic assessment 1,00 0,30 0,30 0,60 0,40
WP6 Business modelling and
regulatory aspects 2,00 1,12 1,04 2,16 -0,16
WP7 Experimental Validation - 0,05 - 0,05 -0,05
WP8 Dissemination of results 4,50 1,80 2,05 3,85 0,65
Total PM 21,50 6,11 14,31 20,42 1,08
TEI
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,27 0,97 1,24 -0,24
WP2 – Requirements for European
next-generation optical access networks - - - - -
WP3 Next-generation optical access
architectures 5,00 2,39 3,09 5,48 -0,48
WP4 System concepts for next-
generation optical access networks 8,00 4,20 6,77 10,97 -2,97
WP5 Techno-economic assessment 1,00 0,48 0,23 0,71 0,29
WP6 Business modelling and
regulatory aspects 2,00 0,94 0,87 1,81 0,19
WP7 Experimental Validation 11,00 5,02 7,65 12,67 -1,67
WP8 Dissemination of results 2,00 0,57 2,69 3,26 -1,26
Total PM 30,00 13,87 22,27 36,14 -6,14
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 44 of 80
ACREO
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,35 0,67 1,02 -0,02
WP2 – Requirements for European
next-generation optical access networks 4,00 0,70 2,64 3,34 0,66
WP3 Next-generation optical access
architectures 18,00 10,50 15,09 25,59 -7,59
WP4 System concepts for next-
generation optical access networks 17,00 8,32 7,32 15,64 1,36
WP5 Techno-economic assessment 9,00 5,79 6,23 12,02 -3,02
WP6 Business modelling and
regulatory aspects 12,00 5,96 8,33 14,29 -2,29
WP7 Experimental Validation - - - - -
WP8 Dissemination of results 14,50 10,30 7,86 18,16 -3,66
Total PM 75,50 41,92 48,14 90,06 -14,56
MT
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 0,50 0,65 1,15 -0,15
WP2 – Requirements for European
next-generation optical access networks 4,00 0,70 2,60 3,30 0,70
WP3 Next-generation optical access
architectures 6,00 2,40 3,80 6,20 -0,20
WP4 System concepts for next-
generation optical access networks 4,00 0,75 3,30 4,05 -0,05
WP5 Techno-economic assessment 4,00 1,45 2,50 3,95 0,05
WP6 Business modelling and
regulatory aspects - - - - -
WP7 Experimental Validation 5,00 5,00 - 5,00 0,00
WP8 Dissemination of results 1,70 0,75 0,80 1,55 0,15
Total PM 25,70 11,55 13,65 25,20 0,50
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 45 of 80
ST
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 1,42 1,06 2,48 -1,48
WP2 – Requirements for European
next-generation optical access networks 4,00 - 0,40 0,40 3,60
WP3 Next-generation optical access
architectures 4,00 0,25 4,20 4,45 -0,45
WP4 System concepts for next-
generation optical access networks - - - - -
WP5 Techno-economic assessment - - - - -
WP6 Business modelling and
regulatory aspects - - - - -
WP7 Experimental Validation 10,00 15,90 1,89 17,79 -7,79
WP8 Dissemination of results 3,00 0,15 0,65 0,80 2,20
Total PM 22,00 17,72 8,20 25,92 -3,92
UESSEX
TOTAL
nb of
PM
spent Y3
Expenses
Y1+Y2
TOTAL
SPENT
Remaining
WP1 Project Management and
Coordination 1,00 -0,00 0,40 0,40 0,60
WP2 – Requirements for European
next-generation optical access networks 3,00 0,99 2,18 3,17 -0,17
WP3 Next-generation optical access
architectures 17,00 5,17 9,73 14,90 2,10
WP4 System concepts for next-
generation optical access networks 16,00 4,55 10,32 14,86 1,14
WP5 Techno-economic assessment 6,00 1,81 2,78 4,59 1,41
WP6 Business modelling and
regulatory aspects 12,00 3,15 6,84 9,99 2,01
WP7 Experimental Validation - - - - -
WP8 Dissemination of results 6,00 1,82 3,73 5,56 0,44
Total PM 61,00 17,48 35,99 53,47 7,53
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 46 of 80
TOTAL OASE PROJECT
TOTAL
planned
2010
+
2011
Remaining
Period 3
theoretical
nb of PM
spent P3
Difference
% P3
WP1 Project Management and
Coordination 38,00 25,08 12,92 14,51 -12,36
WP2 – Requirements for European
next-generation optical access
networks 30,00 17,62 12,38 5,44 56,02
WP3 Next-generation optical access
architectures 116,00 80,80 35,20 42,70 -21,31
WP4 System concepts for next-
generation optical access networks 108,00 80,30 27,70 33,94 -22,53
WP5 Techno-economic assessment 75,00 44,42 30,58 32,69 -6,89
WP6 Business modelling and
regulatory aspects 72,00 40,22 31,78 28,03 11,80
WP7 Experimental Validation 73,00 33,62 39,38 37,77 4,09
WP8 Dissemination of results 91,70 57,67 34,03 34,47 -1,31
Total PM 603,70 379,74 223,96 229,56 -2,50
TOTAL OASE PROJECT (1st January 2010 - 28 February 2013)
TOTAL
planned TOTAL SPENT
Difference %
WP1 Project Management and
Coordination 38,00 39,60 -4,20
WP2 – Requirements for European
next-generation optical access networks 30,00 23,07 23,11
WP3 Next-generation optical access
architectures 116,00 123,50 -6,47
WP4 System concepts for next-
generation optical access networks 108,00 114,24 -5,78
WP5 Techno-economic assessment 75,00 77,11 -2,81
WP6 Business modelling and regulatory
aspects 72,00 68,25 5,21
WP7 Experimental Validation 73,00 71,39 2,21
WP8 Dissemination of results 91,70 92,15 -0,49
Total PM 603,70 609,30 -0,93
in Percent 100,00 100,93
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 47 of 80
Comments on MM spending
WP1: a slight overspending due – for JCP - mainly to contract amendment
WP2: remaining budget – this can be explained by the fact that WP2 strongly interacted with other
WPs where time spent have been declared.
WP3 – WP4 and WP5: small overspending, respectively of 6%, 5% and 2 %, can be partly
explained by the balance of under spending in WP2
WP6 & WP7: almost aligned with plan
WP8: overspending by 0,49 PM –
In general, the project PM spending is well aligned with initial plans; it presents a total
overspending lower than 1 % while the total financial budget presents an under spending of about 5
%.
5.5 Problems and solutions
No specific issue is to be reported.
.
5.6 List of project meetings, dates and venues
Plenary meeting (Feb 8 to 10th, 2012) in Tallinn (Estonia / co-located to the joined
ACCORDANCE-Alpha-OASE workshop (Feb 7th
), hosted by JCP through its subsidiary
EPC.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 48 of 80
Review preparation meeting was organized on March 26st in a meeting room in Hotel Du
Congrès at Rue du Congres 42 in 1000 Bruxelles and the review meeting took place on
March 27th
in the EC premises, avenue de Beaulieu 25 in Bruxelles (BE)
A WP3 Workshop was organized on April 19th
, 2012 in Stockholm, hosted by KUNGLIGA
TEKNISKA HOEGSKOLAN (KTH) at 79 Valhallavaegen in STOCKHOLM (SW)
Plenary meeting organized from May 22nd to May 24th, 2011 in Rennes (FR), hosted by
JCP.
1 day WP Leaders meeting on August 14th
, 2012 hosted by Deutsche Telekom AG at
Winterfeldtstraße 21 10781 Berlin (DE)
Plenary meeting organised from September 11 to 13, 2012 in Meiningen (DE) hosted by
ADVA,
Plenary meeting organized from December 4th to 6th 2012 in Berlin (DE), hosted by
DTAG,
1 day WP Leaders meeting on February 22nd, 2013 hosted by ACREO at 79 Valhallavaegen
in STOCKHOLM (SW)
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 49 of 80
5.7 Project planning and status
Figure 1: OASE Gantt – Period 3 (from Jan 1
st 2012 up to Feb 28
th, 2013)
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 50 of 80
5.8 Impact of possible deviations from the planned
milestones and deliverables
No major deviations to be reported
5.9 Beneficiaries legal status
Along with the latest DoW modification (dated January 25th
, 2013), three partners legal status
modification were also registered in the 2nd
contract amendment.
IMINDS VZW
ACREO SWEDISH ICT AB
ADVA OPTICAL NETWORKING SE
These changes had no impact on the project.
5.10 Project website
The OASE website (www.ict-oase.eu) has been set-up at the very beginning of the project and
was officially delivered to the EC (Deliverable D1.1) in M2.
It has been maintained and populated with news, events and publications during 2012-2013.
5.11 Use of Foreground
No commercial use of Foreground has to be reported after this third period of activities but as stated in WP8, the OASE consortium has been very active in disseminating the results achieved.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 51 of 80
6. Explanation of the use of the resources
6.1 Use of the resources Period 3 – 01/01/2012 to 28/02/2013
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 52 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 53 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 54 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 55 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 56 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 57 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 58 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 59 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 60 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 61 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 62 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 63 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 64 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 65 of 80
6.2 Adjustment to Use of the resources Period 1
Beneficiary number 3 – iMinds – 1139,00 €
Beneficiary number 6 – ADVA – 35821,00 €
Beneficiary number 12 –UEssex – 792,00 €
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 66 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 67 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 68 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 69 of 80
6.3 Adjustment to Use of the resources Period 2
Beneficiary number 1 – JCP – 38,00 €
Beneficiary number 3 – iMinds – -276,00 €
Beneficiary number 6 – ADVA – 22 683,00 €
Beneficiary number 9 –ACREO – 18 021,00 €
Beneficiary number 12 –UEssex – -1065,00 €
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 70 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 71 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 72 of 80
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 73 of 80
7. Financial statements – Form C and Summary
financial report
A separate financial statement from each beneficiary together with a summary financial report
which consolidates the claimed EU contribution of all the beneficiaries in an aggregate form
will be provided through the NEF tool.
According to Article II.4.4 of the Grant Agreement, no certificate on financial statements
shall be submitted by the any beneficiaries as the requested grant threshold of 375 000 € has
not been reached.
8. Certificates – to be updated
Beneficiary Organisation
short name
Certificate on
the financial
statements
provided?
yes / no
Any useful comment, in
particular if a certificate is not
provided
1 JCP No Expenditure threshold not reached
See summary table below
2 DTAG No CFS provided end of P2 (2011)
Expenditure threshold reached
See summary table below
3 iMinds No CFS provided end of P2 (2011)
2nd
Expenditure threshold not reached
See summary table below
4 TUM No Expenditure threshold not reached
See summary table below
5 KTH No CFS provided end of P2 (2011)
2nd
Expenditure threshold not reached
See summary table below
6 ADVA Yes Expenditure threshold reached
See summary table below
7 EA No Expenditure threshold not reached
See summary table below
8 TEI No Expenditure threshold not reached
See summary table below
9 ACREO Yes CFS provided end of P2 (2011)
2nd
Expenditure threshold reached
See summary table below
10 MT No Expenditure threshold not reached
See summary table below
11 ST No Expenditure threshold not reached
See summary table below
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 74 of 80
12 UESSEX Yes Expenditure threshold reached
See summary table below
Organisatio
n short
name
Budgeted
Funding
Cumulated
Funding after P2
Requested funding
P3
(incl Adjustments)
Overall
Requested
funding
CFS
1 JCP 366 631 242 059 112 367 354 426 /
2 DTAG 741 403 396 520 222 596 619 116 P2
3 iMinds 639 860 391 215 264 405 655 620 P2
4 TUM 296 300 167 309 96 471 263 780 /
5 KTH 577 808 409 573 208 430 618 003 P2
6 ADVA 635 626 277 130 164 841 441 971 P3
7 EA 128 958 91 683 40 713 132 396 /
8 TEI 238 562 95 935 104 688 200 623 /
9 ACREO 769 821 460 180 432 283 892 463 P2 – P3
10 MT 76 820 33 562 25 577 59 139 /
11 ST 83 418 20 398 40 820 61 218 /
12 UESSEX 425 050 283 308 120 433 403 741 P3
TOTAL 4 980 257 2 868 872 4 702 496
Remaining budget 277 761 €
Table 6 - Partners CFS needed
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 75 of 80
9. ANNEX 1 – Post review – 2011 –
“How we addressed remarks”
9.1 OVERALL COMMENTS
The OASE project [Optical Access Seamless Evolution - GA nr. 249025] has had its second
year activity review meeting organised on March 27, 2012 in Brussels.
The following experts performed this review meeting:
Prof. Ton Koonen, Eindhoven Univ. of Technology
Prof. Andreas Kirstädter, Stuttgart University
Dr. Karin Ennser, Swansea University
Dr. Alessio Giorgetti, Scuola Superiore Sant'Anna
Thierry Boulangé, Project Officer, chaired the meeting.
On April 25th, 2012, the consortium received the review report containing the reviewers’
assessments and recommendations.
First of all, we would like to thank the reviewers for the very detailed analyze of the work and
their valuable recommendations.
In this document, we will provide an answer on the way we intend to address all of those
recommendations.
b. Recommendations concerning the period under review:
The remark will be addressed by
1 Some deliverables are partially overlapping. For instance, open access tables
are contained in both D3.2.1 and D6.2. Cross-referencing would be better. WP3 & WP6
2 WP3 states that some of the requirements defined in WP2 cannot be fulfilled
by all the OASE NG-OA architectures. More detailed insight into requirements
that cannot be achieved is required, which should be added in D3.2. WP3
3 Public deliverables D4.1 and D5.1 need a further formatting revision to resolve
cross-reference issues. WP4 & WP5
4 In D5.2 some further clarification needs to be given regarding the impact of
regional differences on the techno-economic modelling. WP5
5 Preliminary results in D5,2 show only slight differences between GPON and
AON in terms of CapEx. This not-expected result should be better explained. WP5
6 In D6.2 details about rural deployment should be added, and inputs from
alternative operators should (at least at some first rudimentary level) be
included. WP6
7 The annual report should include a section about the plans for the last period. WP1 + WPLs
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 76 of 80
8 Justification for personnel costs and travel costs for some partners is missing.
Further detailed information such as names of the persons involved and effort
spent per person should be added.
WP1 + some
partners
c. Recommendations concerning future work:
The remark will be addressed by
1 ...to add an extra deliverable "D3.5 Recommendations and guidelines for NG-
OA in Europe (white paper) (M38)" WP8
2 The Alternative Operator Board should be established .... WP6
3 Interaction with other (FP7) projects should be intensified ... WP8
4 Not all technology options are inventoried yet; e.g. the pros/cons of OFDMA
have not been considered in OASE sufficiently. WP4 + WP7
5 ... OpEx assessment seems however still to be in the starting phase, and should
be speeded up. WP5
6 MAC layer testing of hybrid WDM-TDMA technology (cooperation btwn
WP4 and WP7) WP4 + WP7
7 As the selected architectures are not able to meet all OASE NGOA
requirements, a clear optimum mapping of architecture options .... WP3 + WP8
8 The studies on regulatory impact should start with high urgency... WP6
9 Regarding the business modelling, new broadband drivers continuously need
to be scouted (e.g. cloud computing). WP6
10 The assessment of the architectures should include all technical requirements
set by OASE. WP4
11 ... to make the TONIC tool (with proper documentation!) available to a wider
audience. WP5
12 The annual report should ....also list the conclusions and guidelines resulting
from these activities. WP1 + ALL
13 ... (especially work of WP5 and WP6) ... more publications in technical
journals should be made. WP8 + ALL
14 The scope of the user survey should be enlarged considerably (» 20 people) to
have a statistical meaning. WP6
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 77 of 80
9.2 WPs COMMENTS
9.2.1 WP1: Project Management
Recommendations concerning the period under review: Bullet point 7 & 8
The annual report should include a section about the plans for the last period.
Justification for personnel costs and travel costs for some partners is missing. Further
detailed information such as names of the persons involved and effort spent per person
should be added.
Recommendations concerning future work:
Rec. 12: The annual report should not only present the activities done, but also list the
conclusions and guidelines resulting from these activities.
Plans for future (in this case for last period) were presented in the slides during the
review.
No specific comments from WP1 – will be addressed accordingly
9.2.2 WP2: Requirements for European next-generation
optical access networks
Recommendations concerning the period under review: None
Recommendations concerning future work: the recommendations and remarks related
to D2.2.1 will be taken into account in the final/full version of D2.2
9.2.3 WP3: Next-generation optical access architectures
Recommendations concerning the period under review: Bullet point 1 & 2
Some deliverables are partially overlapping. For instance, open access tables are
contained in both D3.2.1 and D6.2. Cross-referencing would be better.
WP3 states that some of the requirements defined in WP2 cannot be fulfilled by all the
OASE
NG-OA architectures. More detailed insight into requirements that cannot be achieved is
required, which should be added in D3.2.
Recommendations concerning future work:
Rec 1 D3.5 Recommendations and guidelines for NG-OA in Europe (white paper) (M38)"
It was proposed to consider this additional deliverable rather under WP8 than in WP3.
It will be under the lead of DTAG with interaction of all WPLs.
Rec 7: As the selected architectures are not able to meet all OASE NGOA requirements, a
clear optimum mapping of architecture options…..
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 78 of 80
This will be addressed in the final D3.2 as well as in the D8.5 “Recommendations and
guidelines for NG-OA in Europe (white paper) (M38)"
9.2.4 WP4: System concepts for next-generation optical
access networks
Recommendations concerning the period under review: bullet point 3
D4.1 - cross-reference issues.
Will be solved easily and quickly
Recommendations concerning future work
Rec 4: the pros/cons of OFDMA
With regards to the FSAN position, WP7 will not address the point and WP4 will
comment briefly (refer to Accordance results)
Rec 6: MAC layer testing of hybrid WDM-TDMA technology
This topic was never promised. IBBT will address it partially in T4.4 with their internal
testbed (by testing e.g. long reach or QoS).
Rec 10: The assessment of the architectures should include all technical requirements set
by OASE
Will be taken into account in D4.2.2
9.2.5 WP5: Techno-economic assessment
Recommendations concerning the period under review: Bullet point 3, 4 & 5
D5.1 - cross-reference issues.
Will be solved easily and quickly
In D5.2 some further clarification needs to be given regarding the impact of regional
differences on the techno-economic modelling.
Preliminary results in D5,2 show only slight differences between GPON and AON in
terms of CapEx. This not-expected
Recommendations concerning future work:
Rec 5: n the second period there was a lot of survey and modelling work going on. OpEx
assessment seems however still to be in the starting phase, and should be speeded up.
Results starting to be available (Munich workshop in April)
Rec 11: to make the TONIC tool (with proper documentation!) available to a wider
audience.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 79 of 80
Tonic tool is already available but the specific use of TONIC (with Database) as done in
OASE will not be made available as it would request a lot of resource to have proper
and adequate documentation + a live “help/maintenance” desk
Rec 13: … more publications in technical journals should be made.
It is planed – also refer also to WP8
9.2.6 WP6: Business modelling and regulatory aspects
Recommendations concerning the period under review: Bullet point 1 & 6
Some deliverables are partially overlapping. …D3.2.1 and D6.2. Cross-referencing
Will be removed from D6.2, only a reference to D3.2.1 will be kept.
In D6.2 details about rural deployment should be added, and inputs from alternative
operators should (at least at some first rudimentary level) be included.
A case study for a rural deployment will be added: Säffle, a municipality in Värmland
County in west central Sweden with population 15,000.
Inputs from alternative operators will be gathered from the AOB (see below).
Recommendations concerning future work:
Rec 2: Alternative Operator Board (AOB) should be established....
We will work more formally with the AOB. This will include the following steps. First
the AOB members (5 up till now, maybe 1 or 2 more to be added) will be provided with
a list of questions. Second, there will be a form of one-to-one interaction between the
individual AOB members and the OASE project. Third, we will stimulate open
discussion between OASE and the AOB in the form a workshop. Two options are
considered for the latter point: the open access workshop we are doing at ECOC in Sept.
as well as a dedicated workshop in Ghent in Nov.
The involvement of cable operators in this board remains difficult to achieve. So far we
didn’t succeed in adding a cable operator to our AOB. In case the EC would be aware of
any cable operators working in other EC projects and willing to cooperate with OASE
on this point, we would be most happy to include these cable operators in our AOB.
Rec 8: The studies on regulatory impact should start with high urgency...
Official starting date of the task is M28;
Pending action towards the EC that should provide a contact point
Rec 9: Regarding the business modelling, new broadband drivers continuously need to be
scouted (e.g. cloud computing).
As we are constantly monitoring the field of FTTH, new broadband drivers are
definitely scouted.
Rec 13: ... (especially work of WP5 and WP6) ... more publications in technical journals
should be made.
It is planned – also refer also to WP8
Rec 14: The scope of the user survey should be enlarged considerably (» 20 people) to
have a statistical meaning.
THIRD YEAR - 2012-2013 - ANNUAL REPORT OASE_PeriodicReport_D1.9_P3_20122012_V2.0.docx
OASE FP7 – ICT– GA 249025
Page: 80 of 80
We feel that the reviewers have misunderstood the scope and aim of the study. The
objective was to sample a small number of experts in the field to provide a euro-centric
validation of the other cited surveys which have investigated added-value services for
NGOA. The results correlate well, and it is therefore unclear what different result is to
be expected with a larger survey.
9.2.7 WP7: Experimental Validation
Recommendations concerning the period under review: None
Recommendations concerning future work:
Rec 4: the pros/cons of OFDMA
With regards to the FSAN position, WP7 will not address
Rec 6: MAC layer testing of hybrid WDM-TDMA technology
Technology already standardized, and some extensions (e.g. long reach or QoS) will be
partially tested in T4.4; WP7 will not address this point.
9.2.8 WP8: Dissemination of results
Recommendations concerning the period under review: None
Recommendations concerning future work:
Rec 1: ...to add an extra deliverable "D3.5 Recommendations and guidelines for NG-OA
in Europe (white paper) (M38)"
As mention in WP3, it will be proposed as a WP8 add. Deliverable under the lead of
DTAG
Rec 2: The Alternative Operator Board should be established ....
Jointly with WP6: assessment to drop to results in/from other projects
Rec 3: Interaction with other (FP7) projects should be intensified …
Rec 13: ... (especially work of WP5 and WP6) ... more publications in technical journals
should be made.
---End of Document ---