Annual Implementation Report No. 4 - pdf.usaid.gov
Transcript of Annual Implementation Report No. 4 - pdf.usaid.gov
Independent Quality Assurance for USAID’S Stabilization
Program Activities in FATA and KP
Annual Implementation Report No. 4
IQC Contract No. AID-391-I-11-00002
Task Order No. AID-391-TO-15-00005
April 2018 to March 2019Halcrow Pakistan (Pvt) Limited
3rd Floor, Nawa-e-Waqt House, Mauve Area
Sector G-7/1, Zero Point, Islamabad, Pakistan
Tel + 92 51 220 3451 Fax + 92 51 220 3462
www.halcrowpk.com
This report is made possible by the support of the American People though the
United States Agency for International Development. The contents are the sole
responsibility of Halcrow Pakistan (Pvt) Ltd and do not necessarily reflect the
views of USAID or the United States Government.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 (ii) HPK
Document history
Independent Quality Assurance for USAID’s Stabilization Program Activities in FATA and KP
Annual Implementation Report No. 4 (April 2018 to March 2019)
This document has been issued and amended as follows:
Version Date Description Created by Reviewed by Approved by
1 30/04/2019 Final AM SAK, RZG, ZAK,
FMK, UR MSZ
AM Asim Masud
FMK Fazal Mahmood Khakwani
MSZ Muhammad Saeed Zia
RZG Rustam Zad Gul
SAK Said Afsar Khan
UR Ubaid ur Rehman
ZAK Zafar Alam Khan
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 (iii) HPK
Acronyms
AASHTO American Association of State Highway & Transportation Officials
ACI American Concrete Institute
AIR Annual Implementation Report
ASTM American Society for Testing & Materials
BHU Basic Health Unit
BOQ Bill of Quantities
BS British Standards
COR Contracting Officer Representative
CoP Chief of Party
DLP Defect Liability Period
DWSS Drinking water supply schemes
EDF Environmental Documentation Form
EMMP Environmental Monitoring & Mitigation Plan
EN European Standards
FATA Federally Administrated Tribal Areas
FIP FATA Infrastructure Program
FR Frontier Region
FWO Frontier Works Organization
HMC Hayatabad Medical Complex
HPK Halcrow Pakistan (Pvt) Ltd
IQA Independent Quality Assurance
IWSS Irrigation Water Supply Scheme
JMP Journey Management Plan
KP Khyber Pakhtunkhwa
KPRP Khyber Pakhtunkhwa Reconstruction Program
LEA Law Enforcing Agency
NTDC National Transmission & Despatch Company
PaRRSA Provincial Reconstruction Rehabilitation and Settlement Authority
PCC Plain Cement Concrete
PIL Project Implementation Letter
PMU Project Management Unit
QA Quality Assurance
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 (iv) HPK
QC Quality Control
SOP Standard Operating Procedure
TO Task Order
USAID United States Agency for International Development
WAPDA Water And Power Development Authority
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 (v) HPK
Contents
1 Executive Summary ..................................................... 1
2 Project Introduction ...................................................... 4
2.1 FATA Infrastructure Program .............................................................................. 4
2.2 KP Reconstruction Program ............................................................................... 5
2.3 Types of Projects ................................................................................................. 5
2.4 Geography ............................................................................................................ 6
3 Results Achieved .......................................................... 7
3.1 Element 1: General Management and Administrative Support ......................... 7
3.1.1 General Advice ...................................................................................................... 7
3.1.2 Overall Management and Administrative Support .................................................. 7
3.1.3 Security .................................................................................................................. 8
3.1.4 Branding and Marking ............................................................................................ 8
3.1.5 Reporting System .................................................................................................. 9
3.1.6 Project Communications ........................................................................................ 9
3.2 Element 2: Design Quality Assurance and Cost Review ................................... 9
3.2.1 QA for Design Review Services ............................................................................. 9
3.2.2 Design Codes and Technical Specifications ........................................................... 9
3.2.3 Review of Bill of Cost Estimates ............................................................................. 9
3.3 Element 3: Construction Quality Assurance .................................................... 10
3.3.1 Establishment of Field Offices .............................................................................. 11
3.3.2 Construction Quality Assurance, Inspections & Testing ....................................... 11
3.3.3 Third Party Inspection .......................................................................................... 11
3.3.4 Environmental Compliance .................................................................................. 12
3.3.5 Overview of Public Events ................................................................................... 12
3.4 Milestone Certification for Construction Projects ........................................... 12
4 Significant Implementation Problems ...................... 14
4.1 Building Sector .................................................................................................. 14
4.2 Road Sector ........................................................................................................ 14
4.3 Power Sector ...................................................................................................... 14
4.4 Water Sector ....................................................................................................... 15
4.4.1 Munda Headworks ............................................................................................... 15
4.4.2 Amandara Headworks .......................................................................................... 15
4.4.3 Dhana Weir .......................................................................................................... 15
5 Actions Taken by HPK ............................................... 16
6 Recommendations...................................................... 17
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 (vi) HPK
Appendices Annexure A - Task Order Deliverables
Annexure B - Project Organization Chart
Annexure C - HPK Deployed Staff List
Annexure D - Progress Review of Sub projects
Annexure E - Pictorial Progress
Annexure F - Success Stories
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 1 HPK
1 Executive Summary
This Annual Implementation Report (AIR) No. 4, covers the performance period
for year 4 of the IQA Task Order (TO) commencing from April 1, 2018 to March 31,
2019. This report is submitted pursuant to TO deliverables under Clause F.5.1.3, on
completion of the fourth performance year. This report comprises an introduction
to the projects, results achieved during the fourth year of the project
implementation, problems encountered and actions suggested to enhance
qualitative and quantitative values of the works. The report also shows a preview
of public events such as collecting feedback of local community directly benefiting
from the USAID stabilization program.
Halcrow Pakistan (Pvt.) Ltd. is providing Architect-Engineer Services for
Independent Quality Assurance for USAID’s Stabilization Program activities in
Federally Administrated Tribal Areas (FATA) and Khyber Pakhtunkhwa (KP) as
per the Task Order assigned in April 2015 for 4 years. The contract period of TO
completed on March 31, 2019, however, keeping in view the ongoing works under
KPRP and upcoming works under FIP and on the basis of available savings in the
allocated budget HPK suggested a “No Cost” extension to the TO till September
30, 2019. USAID accorded approval and constituted Modification No. 08, to the
Task Order.
The main objective of the AIR is to provide a preview of overall status of various
ongoing and upcoming sub-projects in the sectors of Buildings, Roads, Power and
Water during this period. USAID enhanced the projects list by adding new projects
under FIP and KPRP. These sub-projects include rehabilitation and reconstruction
of roads, education buildings, rehabilitation of damaged electrical infrastructure
and construction of solar based tube wells for irrigation and water supply.
The subprojects assigned to HPK have been categorized into three zones - North,
South and Centre. The North Zone comprises districts in Malakand Division and
Bajaur Agency, the South Zone comprises North/South Waziristan, Mohmand,
Khyber, Orakzai and Kurram Agencies, Frontier Regions of Peshawar, Kohat and
Tank and Bannu & DI Khan districts and the Central zone comprises districts of
Peshawar, Nowshera and Charsadda.
One of the core components of the AIR is to demonstrate the accomplishments
made within the fourth year. Focusing on key deliverables during the year, HPK
successfully:
i. Carried out assessment of various projects proposed under savings in KPRP
ii. Checked and verified detailed cost estimates for construction projects
including schools, governmental buildings, basic health units, transmission
lines, grid stations, roads, and water supply schemes in FIP as well as KPRP.
iii. Assisted various stakeholders in compilation of milestones and processed
payment invoices of different PILs accordingly.
iv. Attended/participated the bidding process of the newly awarded sub projects
in FIP on behalf of USAID.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 2 HPK
v. Provided construction quality assurance for all the ongoing construction
projects. During this tenure 01 militancy damaged schools, 15 flood damaged
schools, 2 BHU and 08 water supply schemes in the North Zone and Burns &
Trauma Centre, Peshawar in Central Zone attained final completion. In
addition, numerous subprojects are near completion.
vi. Certified US$ 20.114 Million worth of payment milestones in accordance with
the relevant Project Implementation Letters (PILs) in all four sectors of the
project.
Work on 69 flood damaged schools is in progress while 15 schools attained final
completion and 02 schools are partially completed while construction activities on
24 flood damaged schools are likely to commence soon.
The schools reconstructed under KPRP are being equipped with furniture through
a direct USAID’s contract with local manufacturing firm for providing the
specified equipment to the completed schools. HPK is also providing monitoring
services to ensure that the supplies being procured and delivered meet required
specifications. Similarly, HPK will provide the same services for FIP schools.
Construction activities on signature projects such as GHSS Akbar Pura in District
Nowshera and Tehsil - Level Government Complex Kabal in District Swat are
underway while Burns & Trauma Centre at HMC Peshawar is completed and
functional.
Under modification 04 to the Task Order, HPK has so far conducted 23 third party
inspection visits to 14 different sites across Pakistan and submitted detailed visit
reports to USAID.
During the course of construction, numerous types of issues are generally
encountered which are regularly communicated to USAID on weekly / monthly
basis. A preview of some of the issues encountered and the prompt actions taken
by HPK to address the issues is described in the relevant section of this report.
HPK suggested corrective measures to USAID and other stakeholders throughout
the year and communicated the status of all the subprojects through its reporting
system which, as per provisions of the TO contains field visit reports, weekly email
updates and monthly progress reports.
The security situation in the North, South and Central Zones remained peaceful
due to effective involvement of LEAs. During this tenure site visits by HPK staff
were regularly conducted adhering to the security protocols set forth in the
security assessment plan.
The TO deliverables which serve as means of communication with USAID are also
discussed in detail in this report. These include, but are not limited to, QA Plan,
Pre-Construction Visit Reports, Security Plan, Monthly Progress Reports, Weekly
Email Updates, Minutes of Coordination Meetings and Success Stories. During the
fourth year, HPK submitted all deliverables within the stipulated time.
Pursuant to TO Clause F.5.1.1, HPK regularly updated and submitted the QA Plan
which aims to outline the procedures for undertaking quality assurance of
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 3 HPK
construction activities and milestone certification. To date, HPK has submitted 9
versions of the QA Plan with respect to the updated scope and number of projects.
The potential adverse environmental impacts of the construction activities on local
environment were monitored by HPK throughout the year as per guidelines and
recommendations of the Environmental Documentation Form (EDF) and
Environmental Management and Monitoring Plan (EMMP).
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 4 HPK
2 Project Introduction
The United States Agency for International Development (USAID) appointed
Halcrow Pakistan (Pvt.) Ltd. (HPK) in March 2015 to provide Architect-Engineer
services for Independent Quality Assurance (IQA) of USAID’s Stabilization
Program Activities in the Federally Administered Tribal Areas (FATA) and Khyber
Pakhtunkhwa (KP) province.
Further, in January 2017 via Modification 4 to the Task Order, USAID expanded
the geographical and programmatic scope of HPK. The objective was to conduct
third party visits to various projects funded by the USAID across Pakistan on their
behalf.
In July 2018, USAID enhanced the scope of HPK by adding the monitoring and
oversight of procurement and delivery of furniture and equipment for the schools
reconstructed under KPRP and FIP.
HPK is required to provide services on activities being undertaken in the following
two USAID stabilization programs:
2.1 FATA Infrastructure Program
In FATA Infrastructure Program, USAID is in partnership with FATA Secretariat.
The main objective of the FATA Infrastructure Project is to improve conditions for
the long-term development of the Federally Administered Tribal Areas by
constructing or rehabilitating public service infrastructure in water, energy,
irrigation systems, education, health and roads.
In March 2017, USAID enhanced the scope of HPK’s services by adding new
projects under FIP. These sub-projects include rehabilitation and reconstruction of
roads, grid stations, education buildings, hospital, rehabilitation of damaged
electrical infrastructure and construction of solar based tube wells for irrigation
and water supply in Bajaur, Mohmand, Khyber, Orakzai, Kurram and South
Waziristan Tribal Districts and Frontier Regions.
In Building Sector, PILs of all 69 militancy damaged schools in Orakzai, Kurram,
FR Peshawar and FR Kohat, Govt. Degree College Dogar in Kurram, Govt.
Technical Institute Ghiljo in Orakzai and Civil Hospital Alizai, Muzaffakot in
Kurram are approved and issued.
Work orders of 15 schools in Orakzai have been issued while tendering of
remaining schools, Degree College, technical institute and civil hospital is at
various stages.
In roads sector, PILs of all 06 roads in Kurram, Bajaur, Khyber and Orakzai have
been approved. Construction activities on Loesam-Nawa Pass & Asil Targhaw
Roads in Bajaur and Marghan-Nikka Ziarat Road in Kurram are commenced while
Letter of Acceptance has been issued for Jamrud Bypass. Pre-qualification of
bidders for Bara-Mastak and Ghiljo-Dabori roads is underway.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 5 HPK
Similarly in Power Sector, PILs of 132kV Grid Station at Jandola and Rehabilitation
of 11kV Damaged Distribution System in South Waziristan Tribal District are
signed while final cost estimate along with milestones table of 132kV Transmission
Line Jandola have been submitted to USAID for PIL preparation and approval.
Construction activities on 132kV Grid Station Jandola and rehabilitation of 11 kV
damaged distribution system in South Waziristan have been started.
In Water sector, PILs of 65 Drinking Water Supply Schemes and 110 Irrigation
Water Supply Schemes in Bajaur, Mohmand & Khyber and FR Peshawar & Kohat
have been approved. Work orders of DWSS in Bajaur, Mohmand, FR Peshawar
and Kohat have been issued while tendering process of schemes of other tribal
districts is underway. Similarly work orders of IWSS in Bajaur have been issued
and tendering of other schemes is in process.
2.2 KP Reconstruction Program
In KP Reconstruction Program, USAID is in partnership with Provincial
Reconstruction Rehabilitation and Settlement Authority (PaRRSA). The main
objective of the KP Reconstruction Program is to enhance the stabilization and
development of Khyber Pakhtunkhwa by rebuilding public infrastructure for
education, health, water and sanitation and increasing the capacity of the
provincial government.
Work on 55 flood damaged schools is in progress while 15 schools attained final
completion. Work on 38 more schools is likely to commence. In addition, works on
11 DWSS in District Buner have been started while 22 DWSS in Swat, 06 PCC roads
in Swat and flood protection works of River Swat are likely to commence.
Construction activities on the signature projects like GHSS Akbar Pura in District
Nowshera and Tehsil - Level Government Complex Kabal in District Swat are
already in progress but pace of work is quite slow.
Burns & Trauma Centre, Peshawar is fully functional and inaugurated by Chief
Minister KP during the previous quarter. PIL for the provision of medical
equipment and ambulances for Saidu Group of Teaching Hospital has been
approved while tendering process is in progress.
2.3 Types of Projects
The sectors and the types of engineering projects in this Task Order (TO) include:
Roads
Bridges
Schools (including Flood and Militancy damaged)
Government Buildings and Hospitals
Basic Health Units (BHUs)
Weirs
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 6 HPK
Irrigation Head Works
Grid Stations
Transmission Lines
Rehabilitation of Damaged Distribution System
Drinking Water Supply Schemes and Solarized Tube Wells
2.4 Geography
Geographically planned / upcoming projects under FATA Infrastructure Program
are located in South Waziristan, Bajaur, Orakzai, Kurram, Mohmand and Khyber
Tribal Districts and Frontier Regions of Peshawar, Kohat and Tank.
The Projects in KP are primarily in areas that are part of the Malakand Division
and other districts of KP including Peshawar, Charsadda, Nowshera and DI Khan.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 7 HPK
3 Results Achieved
During the fourth year of the project, HPK continued working in compliance with
the following three elements of TO and the results achieved are discussed in the
subsequent paragraphs;
i. Element-1: Provided general management and administrative support to
USAID, including reports and deliverables;
ii. Element-2: Provided design quality assurance and reviewed bills of quantities
(BOQs) and cost estimates;
iii. Element-3: Provided construction quality assurance support to USAID,
including reports and deliverables.
Accomplishments against TO deliverables are described in detail in the following
sections and summarized in Annexure-A.
3.1 Element 1: General Management and Administrative Support
Under this element the activities executed for the fourth year are covered but not
limited to general advice and support, overall management and administrative
support, security, performance monitoring, branding and marking and
communications with USAID through various reports as per TO by deploying the
proposed staff at the project / design offices.
Annexure-B presents an organization chart of all HPK personnel who rendered
services during the fourth year of the project. USAID had accorded 2nd line item
adjustment on August 03, 2018 but due to delay in commencement of FIP works
some of the resources remained unutilized. On the basis of available savings in the
allocated budget, HPK submitted a no-cost extension to the TO till September 2019
for approval. USAID accorded approval and constituted Modification No. 8 to TO.
3.1.1 General Advice
HPK continued providing general advice to USAID FATA/KP office and its G2G
partners that related mostly to engineer’s estimates, preparation of milestones,
preparation and revision of PILs and other matters relating to quality assurance for
the works in power, building and road sectors.
3.1.2 Overall Management and Administrative Support
HPK provided management and administrative services by using proper and
efficient management and administration practices, information technology,
reporting system, human resource management, asset control, security and cost
control systems.
HPK further ensured an effective and optimized use of staff and other facilities.
The deployed human resources and their utilization in the fourth year have been
outlined in Annexure-C.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 8 HPK
3.1.3 Security
Security Assessment Plan was prepared by HPK and duly approved by USAID in
July 2015. It was framed to mitigate prevailing threats and risks to enable the staff
to conduct their duties in a safe and secured environment. Standard Operating
Procedures (SOPs) for each activity have been formulated to be followed in
different eventualities during all project related activities by the project staff.
Considering the upcoming projects in Orakzai, Kurram, Mohmand, Bajaur, Khyber
& South Waziristan Tribal Districts and Frontier Regions of Peshawar, Kohat &
Tank where security cover will not be provided by FWO, a “Supplementary
Security Instructions” plan in conjunction with already approved “IQA Threat
Risk Assessment and Security Plan - KP & FATA” were submitted and approved
by USAID on January 17, 2018. The instructions are based on the threats and risks
assessed by HPK security team as per dynamics of the FATA regions.
In view of multi-facet projects, spread over a vast area in a security sensitive
regions, it is imperative to ensure availability of requisite security and
boarding/lodging arrangements for HPK field staff for smooth conduct of field
inspections. Security arrangements as per agreed protocols are being provided by
PMU FATA Secretariat through Political Agent’s administration of the concerned
tribal district whereas, boarding/lodging of the visiting teams is being provided by
HPK. Currently, construction activities have been commenced in FR Peshawar &
Kohat and Tribal Districts of Bajaur, Mohmand, Kurram and South Waziristan
which are monitored through HPK’s Peshawar, Timergara & DI Khan Offices
while office cum residence is already planned to be established by HPK in Kurram
to monitor sites in Kurram and Orakzai Agencies. On the basis of reconnaissance
survey conducted by HPK, various places have been identified for establishment
of office cum residence in Kurram and administrative matters are underway.
While planning field visits for any HPK IQA staff member, a Journey Management
Plan (JMP) is prepared by the project security manager with the approval of Chief
of Party. The Visiting team follows the travel protocols as per duly approved
Security Assessment Plan.
In perspective of overall security situation in the country the staff is made aware,
on a regular basis, about the various risks and threats.
3.1.4 Branding and Marking
Under the Task Order deliverables, Branding and Marking Plan was submitted to
the USAID on November 02, 2015 and duly approved by USAID.
HPK provided services with regards to branding and marking activities as
outlined in the Plan. During the implementation of its desired activities, HPK
ensured that the stakeholders and beneficiaries who came in contact with the
project were all apprised of the fact that this project would not have been possible
without the generous support of the American People through the U.S. Agency for
International Development (USAID).
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 9 HPK
The reports and information charts / presentations or literature developed during
the course of the project followed the exclusive branding and marking guidelines
mentioned in the ADS 320 and the USAID Graphic Standards Manual (GSM).
3.1.5 Reporting System
HPK submitted all reports and deliverables/outputs required under the TO in a
timely manner. These included Quality Assurance Plan, Pre-Construction and
Field Visit Reports, Security Plan, Monthly Progress Reports, Weekly Email
Updates, Minutes of Coordination Meetings, Annual Implementation Report and
PAKINFO Reporting.
3.1.6 Project Communications
The Chief of Party (CoP) as well as HPK’s key staff coordinated with USAID
TOCOR for all the communications set forth in the TO. The CoP frequently
communicated the issues and held numerous coordination meetings with USAID
and other stakeholders.
3.2 Element 2: Design Quality Assurance and Cost Review
HPK provided design quality assurance under the task order from time to time.
The activities executed during the fourth year of the project are as follows:
3.2.1 QA for Design Review Services
HPK reviewed structural designs and drawings to ensure its conformity to the
desired codes and standards. HPK reviewed the structural designs and drawings
of the following sub-projects during the reporting year:
i. Militancy damaged schools in Orakzai & Kurram (Package II & III) and FR
Peshawar & Kohat
ii. Govt. Degree College Dogar, Kurram
iii. Govt. Technical Institute Ghiljo
iv. Civil Hospital Muzaffar Kot
v. Electrical design of solar components of DWSS in Mohmand and Bajaur
3.2.2 Design Codes and Technical Specifications
Testing was carried out as per ASTM, AASHTO, BS EN, however mix-designs of
cement concrete was made according to relevant sections of American Cement
Concrete Institute Manuals. Similarly hot and cold weather concreting was done
according to ACI Manual sections 305-1 and 306-1. Concrete test results were
evaluated as per ACI-214.
Standard specifications of National Transmission & Dispatch Company (NTDC)
WAPDA were followed for inspection and testing of electrical material/equipment.
3.2.3 Review of Bill of Cost Estimates
HPK periodically reviewed numerous BOQs and engineer’s cost estimates of sub-
projects under buildings, roads, power and water sectors. These cost estimates
served as the basis for establishing PILs as mentioned below:
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 10 HPK
i. Reviewed the revised engineer’s estimates and prepared the milestones for
Tehsil Level Judicial Complex at Kabal, District Swat (PIL-29)
ii. Reviewed the engineer’s estimate and prepared the milestones of 31 flood
damaged schools (PIL-36)
iii. Reviewed engineer’s estimates and prepared the milestones of militancy
damaged schools in Orakzai & Kurram (Package II & III) and FR Peshawar &
Kohat
iv. Reviewed the engineer’s estimate and prepared the milestones of Bara -
Mastak Road
v. Reviewed the engineer’s estimate and prepared the milestones of Ghiljo -
Dabori Road
vi. Reviewed the engineer’s estimate and prepared the milestones of proposed
132kV Grid Station at Jandola, FR Tank
vii. Reviewed the engineer’s estimates and prepared the milestones of 65 Drinking
Water Supply Schemes in Bajaur, Mohmand & Khyber Agencies and FR
Peshawar and Kohat
viii. Reviewed the engineer’s estimates of 110 Irrigation Water Supply Schemes in
Bajaur, Mohmand & Khyber Agencies and FR Peshawar and Kohat
ix. Reviewed the engineer’s estimate and prepared the milestones of Govt.
Degree College Dogar, Kurram
x. Reviewed the engineer’s estimate and prepared the milestones of Govt.
Technical Institute Ghiljo
xi. Reviewed the engineer’s estimate and prepared the milestones of Civil
Hospital Muzaffar Kot
xii. Reviewed the electrical design of solar components of DWSS in Mohmand and
Bajaur
xiii. Reviewed the engineer’s estimate for furniture under FIP
xiv. Reviewed the engineer’s estimate and prepared the milestones of 132kV
Transmission Line from Pezu-Tank-Jandola Grid Station
xv. Reviewed the engineer’s estimate and prepared the milestones for 11 DWSS
Schemes under saving in District Buner
xvi. Reviewed the engineer’s estimate and prepared the milestones for 23 DWSS
Schemes under saving in District Swat
xvii. Reviewed the engineer’s estimate and prepared the milestones for 06 PCC
roads under saving in District Swat
xviii. Reviewed the engineer’s estimate and prepared the milestones for flood
protection works under saving in District Swat.
3.3 Element 3: Construction Quality Assurance
HPK delivered Independent Quality Assurance services for the fourth year of the
project as per the Task Order. Activities described under this element are, field
visits and tests performed for construction quality assurance, environmental
compliance and record keeping. The activities executed under this element are
detailed below:
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 11 HPK
3.3.1 Establishment of Field Offices
As per original task order HPK has already established main project office in
Peshawar and field offices in DI Khan, Swat and Timergara to conduct IQA
activities for the ongoing works under KPRP and 132kV Grid Station and
Transmission Line Khar,
However, to cater the upcoming projects in Orakzai and Kurram Tribal Districts,
HPK intends establishing another office cum residence at a suitable location in
Tribal District Kurram.
After constituting Modification No. 08 to TO, which reflects “No Cost” extension
and budget re-alignment till September 30, 2019, HPK would be in need to hire the
staff against already approved positions i.e. 01 QA Supervisor, 01 Junior Engineer
and 01 Driver within the ceiling budget. The attached organization chart can be
referenced in this context.
3.3.2 Construction Quality Assurance, Inspections & Testing
Pursuant to Task Order Clause F.5.1.1, HPK submitted version-9 of QA Plan to
USAID. The project teams deployed in North, South and Central Zones continued
and followed procedures as laid down in the approved QA plan to ensure that all
construction activities were performed in accordance with the approved designs,
drawings and technical specifications.
During site inspections HPK field staff performed the following main activities:
i. Conducted independent inspections and testing of the ongoing works as per
frequency outlined in the QA Plan
ii. Certified invoices of the implementing agencies for payments based on
independent quality testing
iii. Monitored environmental compliance, reported safety conditions at
construction sites and identified violations in compliance of regulations
iv. Recorded security incidents, extreme weather conditions, and any other events
that could potentially affect the progress of work
v. Regularly communicated the above works to USAID along with pictorial
records
The comparison of progress of all the subprojects between March 2017, March 2018
and March 2019 has been outlined in Annexure-D.
3.3.3 Third Party Inspection
In January 2017 through a modification no. 04 in the Task order, USAID assigned
the task to HPK to inspect the construction status of all ongoing works funded by
USAID all over Pakistan on their behalf.
Under this modification to the Task Order, so far HPK has conducted 23 inspection
visits to 14 sites across Pakistan and submitted comprehensive reports to USAID.
In recent times, USAID instructed HPK to conduct the visits for verification of
snags rectification emerged during the Defect Liability Period (DLP) to Centre of
Advanced Studies in Faisalabad and Jamshoro.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 12 HPK
3.3.4 Environmental Compliance
Environmental monitoring compliance of the project as per approved
Environmental Documentation Form (EDF) and Environmental Mitigation and
Monitoring Plan (EMMP) is also a main component of the Task Order.
Environmental compliance monitoring for the ongoing projects was ensured by
HPK’s Environmental Compliance Specialist. ECS conducted visits to the project
sites as per need and the frequency outlined in implementation plan of the EMMP
by the supervision consultants.
All the non-compliances were discussed in detail at sites with contractors and
supervisory consultants for mitigation in light of EDF/EMMP. The overall findings
of environmental compliance monitoring have been shared with USAID through
field visit reports and monthly progress reports. Also, the success stories of the
completed projects were prepared on the defined template and shared with
USAID.
Environmental team of HPK had also conducted detailed assessment of the local
environmental and social conditions of project areas during pre-construction
phase. The issues and concerns identified during the pre-construction visits were
then accordingly incorporated in the relevant EDF/EMMP submitted by the
supervision consultants for review.
All environmental non-compliances noted were reported to USAID with
recommendations for corrective actions in the form of field visit reports and
monthly progress reports. All non-compliances were discussed in detail at site
with contractors and supervisory consultants for rectification and advised for
implementation of EDF/EMMP.
3.3.5 Overview of Public Events
As per the Task Order, HPK during this year arranged and prepared public
feedback regarding the impact of USAID funded projects on local community by
the name of success stories. HPK’s Environmental Compliance Specialists
conducted field visits to a few completed sub-projects like schools, water supply
schemes and signature project Burns & Trauma Centre to get feedback from the
local beneficiaries.
This feedback was then recorded and shared in the form of success stories with
USAID on a format approved by USAID Development Outreach and
Communication Officer. Pursuant to the Task Order Deliverables Clause F.5.1.10,
eight success stories were prepared and submitted. A few submitted success
stories are attached in Annexure-F.
3.4 Milestone Certification for Construction Projects
HPK certified the achievement of payment milestones of all the ongoing
construction projects during this period. Payment milestone certification was done
in accordance with the relevant PIL based on established testing protocols as per
QA Plan.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 13 HPK
Sector wise detail of the certified amount from April 2018 to March 2019 is
summarized in the following table:
S.
No. Sector No. of Invoices Certified Amount (US$)
1 Building Sector 73 19,177,520.08
2 Road Sector - -
3 Power Sector 02 936,957.00
4 Water Sector - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 14 HPK
4 Significant Implementation Problems
Sector wise significant implementation problems encountered during the fourth
year of IQA Project are summarised below:
4.1 Building Sector
i. Pace of work on flood damaged schools is slow due to financial constraints of
the construction contractors. The implementing agency needs to resolve
financial issues of the contractors to ensure timely completion.
ii. Works on Water Supply Schemes in Buner and Swat have been progressing on
an extremely slow pace. In Buner, 11 schemes and in Swat only 06 schemes are
completed but work on the remaining schemes is either stopped or going on
quite slowly. PaRRSA needs to enhance coordination with the line department
(TMA Mingora in Swat and PHED in Buner) to complete all the schemes.
iii. Pace of work on Tehsil Level Judicial Complex Kabal is significantly slow. PU
C&W needs to take appropriate measures to expedite the works.
iv. The pace of work at GHSS Akbar Pura is slow due to cash flow problems.
v. In FD schools, actual progress was lagging behind the construction schedule
and no contractual action was taken against the contractors with slow
progress.
4.2 Road Sector
i. Due to the limited capacity of W&S Dept. FATA and M/s Cameos consultants,
delay in reviewing the technical & financial bids has been noted which
resultantly delayed the award of works to the successful bidders.
ii. Joint x-sections of Marghan - Nikka Ziarat Road Package-II, Loeasm - Nawa
Pass Road Package-I & II and Asil Targhaw Road package-II not yet submitted
to the construction contractors and HPK by supervisory consultants which is
causing delay to the construction work.
4.3 Power Sector
i. The local land owners are hindering the construction works of towers
foundations at a few locations which could cause delay as well as modification
in the route of 132kV Transmission Line Khar. The executing agency, TESCO
needs to settle the land acquisition issues with the locals.
ii. There are a few tower foundations at 132kV Transmission Line which are
exposed due to uneven terrain. TESCO needs to recommend proper protection
either with stone masonry or earth filling in consultation with PMU FIP.
iii. Installed 100 kVA transformer for tube well at 132kV Grid Station Khar is yet
to be connected / energized by TESCO.
iv. TESCO has not yet issued work order for installation of lightning protection of
CHB, at Khar Grid Station.
v. TESCO to expedite the pace of construction works of 132 kV Grid Station and
Transmission Line, Khar for early completion before September 2019.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 15 HPK
vi. Duly signed hardcopies of final construction drawings for the construction of
Transmission Line Jandola as well as Line bays at Tank and Pezu, are yet to be
shared by Cameos.
4.4 Water Sector
4.4.1 Munda Headworks
Submission of an updated “Maintenance Plan” as a milestone is awaited from
PaRRSA.
4.4.2 Amandara Headworks
Submission of an updated “Maintenance Plan” as a milestone is awaited from
PaRRSA.
4.4.3 Dhana Weir
Approved As-Built drawings of DWS scheme from FATA Secretariat are awaited.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 16 HPK
5 Actions Taken by HPK
HPK has been recommending immediate and corrective actions to USAID and
other stakeholders throughout the fourth year of IQA services in view of the
problems faced from time to time. A synopsis of actions taken is as follows:
i. HPK communicated all issues raised on sites to USAID in a timely manner
through weekly email updates, field visit reports and monthly progress
reports.
ii. HPK field staff enhanced their inputs where supervision consultant was not
deployed or was short of capacity and conducted QA tests on majority of the
consignments of construction materials.
iii. HPK provided all sorts of technical assistance to the executing agencies
especially Hayatabad Medical Complex to complete the first state of the art
burn and trauma centre Peshawar in KP.
iv. Prompt processing of payment invoices was done by HPK to resolve financial
constraints of construction contractors.
v. HPK promptly processed the review of structural designs and cost estimates
as and when instructed by USAID.
vi. HPK field team continued coordination with the executing agencies and
highlighted quality related issues. HPK also requested USAID for their
intervention in resolving non-compliances.
vii. HPK conducted pre-shipment testing and assisted the implementing agencies
in procurement of electrical equipment for all sub-projects in Power Sector.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 17 HPK
6 Recommendations
Following are some of the recommendations for smooth execution of the project
activities:
i. Cash flow problems of the construction contractors need to be addressed by
the executing / implementing agencies for expedition of the ongoing works
especially education buildings and water supply schemes.
ii. It is noted that the stipulated completion dates of majority of the sub-projects
is not properly pursued by the executing agencies which causes delay in
completion. It is recommended that the work schedules of each sub-project are
strictly monitored by the executing agencies.
iii. The construction contractors are not aware of compositions of payment
milestones. The executing agencies need to educate the construction
contractors to work according to the sequence of milestones for smooth cash
flow.
iv. For the upcoming sub-projects under KPRP and FIP the capacity of design and
supervision consultant should be properly scrutinized by the executing
agencies before award of work.
v. Due to the limited capacity of executing agency, delay in reviewing the
technical & financial bids has been noted which resultantly delayed the award
of works to the successful bidders in FIP and Saidu Group of Teaching
Hospital, Swat. The delay in procurement process needs to be addressed by
the executing / implementing agencies.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
Annexure A - Task Order Deliverables
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 A-1 HPK
TO Clause Report Title Frequency Last Submission
F.5.1.1 Quality Assurance Plan – Rev 9 Quarterly 05 May 19
F.5.1.2 Pre-Construction Visit Report As and when required -
F.5.1.3 Annual Implementation Report Annual 5 Jun 18
F.5.1.4 Security Assessment Plan As and when required 15 Jul 15
F.5.1.5 Cost Control Report Once in project’s life
span 15 May 15
F.5.1.7 Monthly Progress Report Monthly 12 Apr 19
F.5.1.8 Weekly Progress Report Weekly 29 Apr 19
F.5.1.10 Success Stories Semi-Annual 24 Jan 19
F.5.1.12 PAKINFO Reporting Quarterly 21 Feb 19
C.5.1.9 Branding and Marking Plan Once in project’s life
span 2 Nov 15
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
Annexure B - Project Organization Chart
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 B-1 HPK
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
Annexure C - HPK Deployed Staff List
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 C-1 HPK
S.
No. Location Company Name Designation Status
1 PEW HPK M. Saeed Zia Chief of Party Mobilized
2 PEW HPK Zafar Alam Khan QA Manager
(Buildings) Mobilized
3 PEW HPK Said Afsar Khan QA Manager
(Roads) Mobilized
4 PEW HPK Rustam Zad Gul QA Manager
(Power) Mobilized
5 ISB HPK Fazal Mahmood QA Manager
(Water) Mobilized
6 ISB HPK Altaf Yunus Khan Design
Coordinator Mobilized
7 PEW AID Roze Muhammad
Sherani
QA Engineer
(South) Mobilized
8 PEW HPK Muhammad Asim
Masud Office Engineer Mobilized
9 PEW HPK Mian Ashfaq
Hussain Shah
Project Security
Manager Mobilized
10 PEW HPK Shehryar Afridi Junior Engineer Mobilized
11 PEW HPK Muhammad Qazzafi Quantity
Surveyor Mobilized
12 PEW HPK Ubaid ur Rehman
Environment
Compliance
Specialist
Mobilized
13 PEW HPK Rowaid Ullah
Environment
Compliance
Specialist
Mobilized
14 PEW HPK Manzar Habib IT & Admin
Manager Mobilized
15 PEW HPK Tanveer Ahmad Computer
Operator Mobilized
16 PEW HPK Arshad Zaman Admin Assistant Mobilized
17 PEW HPK Arsalan Vohra QA Monitor (Bio-
Medical) Mobilized
18 PEW AID Lai Khan QA Monitor Mobilized
19 PEW AID Adil Kurshid QA Monitor Mobilized
20 PEW HPK Ahsan Qazi QA Monitor Mobilized
21 PEW HPK M. Murtaza Khan QA Monitor Mobilized
22 PEW HPK Shoaib QA Monitor Mobilized
23 PEW AID Zia ur Rehman QA Supervisor Mobilized
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 C-2 HPK
S.
No. Location Company Name Designation Status
24 PEW HPK Zahoor Shah QA Supervisor Mobilized
25 PEW HPK Rafi Ullah QA Supervisor Mobilized
26 PEW AID Hamid Rehman Lab Technician Mobilized
27 PEW HPK Suleman Khattak Peon / LH Mobilized
28 PEW AID Nadeem Khan Driver - 1 Mobilized
29 PEW AID Karamat Ullah Driver - 2 Mobilized
30 PEW AID Muhammad
Ibrahim Driver - 3 Mobilized
31 PEW HPK Sarfraz Driver - 4 Mobilized
32 PEW HPK Adil Shahzad Driver - 5 Mobilized
33 PEW HPK Abidullah Driver - 6 Mobilized
34 PEW HPK Shahzad Munsif Driver - 7 Mobilized
35 PEW HPK Muhammad Riaz Driver - 8 Mobilized
36 PEW HPK Jahangir Cook Mobilized
37 PEW HPK Junaid Josef Janitor Mobilized
38 PEW HPK Wasif Ullah Peon – 1 Mobilized
39 PEW HPK Akbar Hussain Peon – 2 Mobilized
40 South AID Adnan Khan QA Monitor Mobilized
41 South AID Muhammad Abrar
Khan QA Supervisor Mobilized
42 South HPK Capt. Hassan Niazi Project Security
Officer Mobilized
43 South HPK Zeeshan Ahmed Admin Assistant Mobilized
44 South AID Afaq Dad Peon / Lab
Helper Mobilized
45 South AID Adil Jalil Driver – 1 Mobilized
46 South AID Muhammad Shahid Driver – 2 Mobilized
47 South AID Aqeel Sanobi Janitor Mobilized
48 South AID Ghulam
Muhammad Peon Mobilized
49 South AID Naeem Iqbal Cook Mobilized
50 North HPK Shahid ur Rahman QA Engineer Mobilized
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 C-3 HPK
S.
No. Location Company Name Designation Status
51 North HPK Imran Rashid Quantity
Surveyor Mobilized
52 North HPK Sharafat Ali QA Monitor Mobilized
53 North HPK Pazir Muhammad QA Monitor Mobilized
54 North HPK Inam Khan QA Supervisor Mobilized
55 North HPK Abrarullah QA Supervisor Mobilized
56 North HPK Muhammad Haroon QA Supervisor Mobilized
57 North HPK Qazi Burhan QA Supervisor Mobilized
58 North HPK Ayaz Hussain QA Supervisor Mobilized
59 North HPK Muhammad Tahir QA Supervisor Mobilized
60 North HPK Intikhab Ahmad QA Supervisor Mobilized
61 North HPK Muhammad Arif QA Supervisor Mobilized
62 North HPK Kaleem Ullah Jan QA Supervisor Mobilized
63 North HPK Umer Farooq QA Supervisor Mobilized
64 North HPK Amin Khan Lab Technician Mobilized
65 North HPK Haider Ali Lab Technician Mobilized
66 North HPK Muhammad Shoaib Lab Helper Mobilized
67 North HPK Capt. Asif Raza Project Security
Officer Mobilized
68 North HPK Muhammad Qaisar Admin Assistant Mobilized
69 North HPK Yaad Nazar Driver - 1 Mobilized
70 North HPK Yaqoob Khan Driver - 2 Mobilized
71 North HPK Muhammad Zada Driver - 3 Mobilized
72 North HPK Sharif Ullah Driver - 4 Mobilized
73 North HPK Said Rehman Driver - 5 Mobilized
74 North HPK Mian Said Jan Driver - 6 Mobilized
75 North HPK Ubaid ur Rahman Janitor Mobilized
76 North HPK Suleman Khan Janitor/LH Mobilized
77 North HPK Shafiq ur Rehman Cook Mobilized
78 North HPK Nisar Muhammad Cook Mobilized
79 North HPK Said Muhammad Peon Mobilized
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
Annexure D - Progress Review of Sub projects
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
PROGRESS REVIEW OF SUB-PROJECTS UNDER KPRP
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
Building Sector - Militancy Damaged Schools (KPRP)
1 GGPS Bar Kalay
Bishbanr Swat 100% 100% 100% Completed
2 GGMS Shakardara Swat 100% 100% 100% Completed
3 GGPS Ditpanai Swat 100% 100% 100% Completed
4 GGPS Paindai
Sakhra Swat 100% 100% 100% Completed
5 GGPS Toor Toot
Kishwara Swat 100% 100% 100% Completed
6 GHSS Zaimdara Dir Lower 100% 100% 100% Completed
7 GHS Sangolai Dir Lower 100% 100% 100% Completed
8 GGHS Tirat Qandil Swat 100% 100% 100% Completed
9 GGPS Bishbanr Swat 100% 100% 100% Completed
10 GGPS Seer
Telegram Swat 100% 100% 100% Completed
11 GGHS Ganori Dir Upper 100% 100% 100% Completed
12 GGMS Bar Shawar Swat 100% 100% 100% Completed
13 GGPS Ghari
Chuprial Swat 100% 100% 100% Completed
14 GHS Shekolai
Tormang Dir Lower 100% 100% 100% Completed
15 GGPS Balasur
Chuprail Swat 100% 100% 100% Completed
16 GGPS Chuprial Swat 67% 99.16% 100% Completed
17 GPS Mirgam Bala Dir Lower 100% 100% 100% Completed
18 GGPS Saeed Abad
No. 1 Swat 100% 100% 100% Completed
19 GHS Bar Shawar Swat 100% 100% 100% Completed
20 GGPS Asharay
Malam Jaba Swat 100% 100% 100% Completed
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
21 GGPS Mangra
Sakhra Swat 100% 100% 100% Completed
22 GPS Dapoor Dir Lower 100% 100% 100% Completed
23 GPS Chiragali Dir Upper 100% 100% 100% Completed
24 GHS Gul Bandai Buner 100% 100% 100% Completed
25 GGPS Qayumabad
Lalkoo Swat 100% 100% 100% Completed
26 GMS Gul Bandai Buner 33% 51% 77% In Progress
27 GGPS Kass Khass Swat 100% 100% 100% Completed
28 GGPS Lalkoo
Sakhra Swat 100% 100% 100% Completed
29 GGPS Manglawar Swat 100% 100% 100% Completed
30 GGPS SpinaKhpa Swat 100% 100% 100% Completed
31 GPS No. 1 Inzer
Maira Buner 1.50% 24% 52% In Progress
32 GPS Maidan Bandai Dir Lower 27.84% 84.78% 100% Completed
33 GHS Maidan
Bandai Dir Lower 18% 60.18% 80.55% In Progress
34 GGPS Raidgai Dir Lower - 41.49% 83.25% In Progress
35 GHSS Charbagh Swat - 31.79% 73.49% In Progress
36 GPS Meramai Dir Lower - 1.44% 100% Completed
Building Sector - Flood Damaged Schools (KPRP) - PIL - 28
1 GPS Biha Swat 17.50% 54.57% 96% In Progress
2 GPS Muraday Swat 11% 32.30% 58.17% In Progress
3 GGPS Serai Gut Swat 12% 40.52% 55.85% In Progress
4 GGMS Qayum
Abad Swat 26% 95.14% 100% Completed
5 GHSS Manai Swat - - - In tendering
stage
6 GGPS Qambari Shangla 0.91% 42% 60% In Progress
7 GGPS Shalmano
Kotkai Shangla 3.55% 35% 49% In Progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
8 GHS Mian Brangola Dir Lower 1.83% 23.70% 61.31% In Progress
9 GPS Hisar Baba Malakand 21.37% 63.92% 83.28% In Progress
10 GPS Shahidan Charsadda 43.50% 95.72% 100% Completed
11 GGPS Samunat Charsadda 34.80% 90.89% 100% Completed
12 GPS Sherin Kotai Nowshera 54.49% 79.07% 99.04% In Progress
13 GPS Tor Dheri Nowshera 24.98% 54.15% 79.64% In Progress
14 GGPS Pushtoon
Garhi Nowshera 68.09% 98.78% 100% Completed
15 GPS Baab e Jadeed Nowshera 25.38% 85.75% 94.78% In Progress
16 GPS Kandi Taaza
Din Nowshera 45.98% 98.78% 100% Completed
17 GPS No.1 Mishak Nowshera 22.47% 45.62% 49.40% In Progress
18 GGPS Maroba Nowshera 17.85% 36.07% 45.94% In Progress
19 GPS Jhoke Umaray
Wali DI Khan 4.17% 57.30% 58.49% In Progress
20 GPS Rora Nawa DI Khan 53.89% 82.89% 98.48% In Progress
21 GPS Bairoon Sharqi DI Khan 18.50% 48.59% 62.34% In Progress
22 GGPS Jhoke Gomla DI Khan 7.27% 54.46% 54.46% In Progress
Building Sector - Flood Damaged Schools (KPRP) - PIL - 30
1 GPS No. 2 Maloch Swat 49.52% 97.86% 98.60% In Progress
2 GPS Chinda Khora Swat 24.24% 74.09% 82.54% In Progress
3 GGPS Kass Swat 15.69% 46.24% 92.41% In Progress
4 GPS Pacha Kalay Swat 29.84% 91.55% 100% Completed
5 GPS Godha Swat 24.07% 92.57% 100% Completed
6 GGPS Godha Swat 4.30% 53.99% 74.65% In Progress
7 GHS Inzargai Malakand 10.81% 62.71% 100% Completed
8 GPS Jalal Kot Malakand 45.65% 100% 100% Completed
9 GHS Shang Shangla 4.22% 27.81% 42.51% In Progress
10 GGPS Shalmano
Chakesar Shangla 6.08% 44.75% 85.71% In Progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
11 GMS Bilkanai Shangla 7.77% 39.11% 46.82% In Progress
12 GGPS Begumar
Lahore Shangla 10.71% 24.28% 44.85% In Progress
13 GHS Amnavi Shangla 1.43% 15.37% 22.89% In Progress
14 GPS Zimdara Dir Lower 6.85% 31.04% 44.65% In Progress
15 GHS Mirgam Bala Dir Lower 0.90% 13.54% 13.54% In Progress
16 GGMS Kotkay Dir Lower 10.61% 84.80% 100% Completed
17 GHS Sadbar Kalay Dir Lower 52.11% 100% 100% Completed
18 GPS Raidgai Dir Lower 8.60% 88.20% 100% Completed
19 GPS No.1
Sherkhanai Dir Lower 8.86% 62.02% 100% Completed
20 GMS Asigi Kalay Dir Lower 3.82% 26.22% 48.82% In Progress
21 GPS Kass Barikot Dir Upper 2.10% 49.22% 63.95% In Progress
22 GPS Tangi Sar Dir Upper 8% 54.30% 66.69% In Progress
23 GPS Remin Kass Dir Upper 2.10% 49.60% 63.43% In Progress
24 GPS Shomai Dir Upper - - - In tendering
stage
25 GPS Nihag Dir Upper 6.59% 72.96% 100% Completed
26 GPS Zakria Dir Upper 1.42% 44.85% 74.25% In Progress
27 GPS Sundrai Dir Upper - 22.85% 41.41% In Progress
28 GPS Sundal Dir Upper 15.35% 49.51% 97.13% In Progress
29 GPS Mansooka Charsadda 8.08% 37.23% 80.05% In Progress
32 GPS Shahab Khail
Kaka Sahib Nowshera 30.12% 82.96% 100% Completed
33 GPS Kotar Pan No.
1 Nowshera 19.62% 71.87% 99.90% In Progress
34 GPS Makar DI Khan 40.35% 83.98% 98.88% In Progress
35 GPS No. 1 Yarak DI Khan 13.46% 58.45% 79.36% In Progress
Building Sector - Flood Damaged Schools (KPRP) - PIL 32
1 GGPS Bara Bandai Swat 2.90% 20.55% 32.02% In Progress
2 GPS Daro Maira Swat - - 2.00% In progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
3 GHS Islampur Swat - - -
WO issued but
not yet started
4 GHS Swegalai Swat - - -
5 GPS Balat Swat - - -
6 GPS Chatoria Swat - - -
7 GPS Doghlai Swat - - -
8 GPS Fatima Swat - - -
9 GPS Kandowgai
Gut Swat - - -
10 GPS Loye Namal Swat - - -
11 GPS Mailaga Swat - - -
12 GPS Pansat Swat - - -
13 GPS Shandal Swat - - -
14 GPS Shofin Swat - - -
15 GPS Talkar Swat - - -
16 GGPS Aman Kot Nowshera - - 22.92% In Progress
17 GHS Pashtoon
Garhi Nowshera - - 15.59% In Progress
18 GPS Hawai Nowshera - - 35.75% In Progress
19 GPS Mohallah
Mulla Khan Nowshera - - 47.70% In Progress
20 GPS Toha Nowshera - - 34.50% In Progress
21 GPS Jaroba Nowshera - - 46.33% In Progress
22 GPS Khan Jan
Kalay Nowshera - - 61.12% In Progress
23 GPS Zakhi
Qabristan Nowshera - - 48.41% In Progress
24 GHSS Akbar Pura Nowshera - 18.56% 45.02% In Progress
Building Sector - Flood Damaged Schools (KPRP) - PIL-36
1 GGPS Sadar Garhi Charsadda - - 2.08% In Progress
2 GPS No.1 Katozai Charsadda - - 11.33% In Progress
3 GHS Khwishgi Bala Nowshera - - 2.29% In progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
4 GHSS No.1
Nowshera Kalan Nowshera - - 1.48% In progress
5 GPS Karam Khel
Mushtarzai Peshawar - - 1.90% In progress
6 GHS Matani Peshawar - - 2.92% In progress
7 GPS Yari Koroona Peshawar - - 6.10% In progress
8 GHS Jan Batti Dir Upper 2.20% 30.81% 44.63% In progress
9 GHS Masho Khel Peshawar - - -
In tendering
stage
10 GGHS Nahaqi Peshawar - - -
11 GGPS Panam Dari Peshawar - - -
12 GPS No. 2 Maira
Balar Zai Peshawar - - -
13 GGPS Bara Samai Swat - - -
14 GGPS Chur
Dardyal Swat - - -
15 GGPS Kemyari Swat - - -
16 GGPS Khwar Kotay
Qalagai Swat - - -
17 GGPS Look Maira Swat - - -
18 GGPS Kalagay Swat - - -
19 GGPS Shah Dherai Swat - - -
20 GHS Matiltan Swat - - -
21 GHS Utror Swat - - -
22 GPS Bahadar Banda Swat - - -
23 GPS Balogram Swat - - -
24 GPS Dardyal Swat - - -
25 GPS Matiltan Swat - - -
26 GPS Pir Patey
Qalagai Swat - - -
27 GPS Qala Qalagai Swat - - -
28 GPS Usho Swat - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
29 GGHS Mingora Swat - - -
In tendering
stage
30 GGPS Naway Kalay Swat - - -
31 GGCMHS Thana Malakand - - -
32 GPS Gulzada Kalay Malakand - - -
Building Sector - BHUs
1 BHU Chongai
Shamozai Swat 100% 100% 100% In Progress
2 BHU Mian Kalay Swat 100% 100% 100% In Progress
3 BHU Nazarabad Swat 100% 100% 100% In Progress
4 BHU Kishwara Swat 100% 100% 100% Completed
5 BHU Topai Buner 96% 96% 96% In Progress
6 MCH Kithiari Dir Lower 100% 100% 100% Completed
7 CD Telegram Swat 99.93% 100% 100% Completed
8 CD Pararai Swat 100% 100% 100% Completed
9 BHU Bishbanr Swat 100% 100% 100% Completed
10 BHU Mashkomai Swat 54.25% 84.15% 100% Completed
11 BHU Shalpin Swat 100% 100% 100% Completed
12 BHU Kotanai Swat 100% 100% 100% Completed
13 BHU Bandai Swat 100% 100% 100% Completed
Drinking Water Supply Schemes (DWSS)
1 DWSS Chonge
(Hand Pumps) Buner 100% 100% 100% Completed
2 DWSS Shalbandi Buner 100% 100% 100% Completed
3 DWSS Maskipur Buner 58.07% 68% 100% Completed
4 DWSS Banda
(Krapa)
Buner 96% 100% 100% Completed
5 DWSS Dagai Buner 36% 60% 100% Completed
6 DWSS Jang Dara Buner 65% 100% 100% Completed
7 DWSS Dewana
Baba
Buner 41% 98% 100% Completed
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
8 DWSS Sunigram Buner 46% 78% 87% In Progress
9 DWSS Qibla Maira Buner 100% 100% 100% Completed
10 DWSS Soor Kamar
Maira
Buner 80% 90% 100% Completed
11 DWSS Bagra Maira Buner 100% 100% 100% Completed
12 DWSS Jowar Buner 25.15% 50% 92% In Progress
13 DWSS Aso Dara Buner 100% 100% 100% Completed
14 DWSS Shagai zone
1 Swat 75% 85% 100% Completed
15 DWSS 120 Hand
Pumps Swat 63% 63% 63% In Progress
16 DWSS Naway
Kaley Swat 85% 100% 100% Completed
17
DWSS Akram &
adjoining
Muhallahs
Swat 67% 90% 100% Completed
18 DWSS Barama Swat 48% 62% 90% In Progress
19 DWSS Akhon Baba Swat 62% 75% 94% In Progress
20 DWSS Makan Bagh Swat 68% 93% 100% Completed
21 DWSS Gul Kada
Maira Swat 67% 82% 100% Completed
22 DWSS Shahidabad
Fizagat Swat 62% 72% 78% In Progress
23 Transformers &
Voltage Regulators Swat 100% 100% 100% Completed
Water Sector - Head Works (KPRP)
1
Restoration of
Munda Head
Works
Munda,
Charsadda 100% 100% 100% Completed
2
Restoration of
Amandara Head
Works
Batkhela,
Malakand 100% 100% 100% Completed
Reconstruction of Bridges Damaged by 2010 Floods
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
1. Mingora Bridge Swat 99.50% 99.50% 100% Completed
2. Khwazakhela
Bridge Swat 100% 100% 100% Completed
Building Sector - Health Facilities (KPRP)
1
Burns & Trauma
Centre, HMC
Peshawar (PIL-33)
Peshawar - - 100% Completed
Building Sector - Government Buildings (KPRP)
1 Tehsil Level Judicial
Complex, Kabal Swat - - 24% In Progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
PROGRESS REVIEW OF SUB-PROJECTS UNDER FIP
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
Building Sector - Militancy Damaged Schools in Orakzai Tribal District
1. GGPS Farid Khan
Mela Upper Orakzai - - -
Work orders of
11 schools have
been issued and
contract
agreement
signed. Soil
investigation in
progress. 4 out
of 15 schools are
being
constructed
through ADP.
PMU FIP to
identify alternate
schools.
2. GGMS Tooti Bagh Lower Orakzai - - -
3. GGPS Khwaga Seri Upper Orakzai - - -
4. GGPS Ramandan
(Pacha Panra) Upper Orakzai - - -
5. GPS Khadazai No.2 Upper Orakzai - - -
6. GPS Malang Garhi Upper Orakzai - - -
7. GPS Inzarki Ali
Khel Upper Orakzai - - -
8. GMS Khadizai
Stara Kada Upper Orakzai - - -
9. GPS Dray Sotay Upper Orakzai - - -
10. GPS Baghnak Upper Orakzai - - -
11. GGPS Talay Ali
Khel Upper Orakzai - - -
12. GGPS Chota Bezot Lower Orakzai - - -
13. GPS Kasim Khel Lower Orakzai - - -
14. GPS Kandi Mishti Central
Orakzai - - -
15. GPS Garhi Mishti Central
Orakzai - - -
Building Sector - Militancy Damaged Schools in Orakzai Tribal District (Package-II &
III)
1. GHS Goeen Orakzai - - -
Tendering of 9
schools in
progress. 5
schools having
cost over Rs. 50
2. GPS Goeen Bala Orakzai - - -
3. GGHS Spin Beghi Orakzai - - -
4. GPS Spin Beghi Orakzai - - -
5. GGHS Togha Sam Orakzai - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
6. GGPS Sarki Khel Orakzai - - - million
forwarded to
Chief Engineer
W&S for his
approval.
7. GPS Kool Orakzai - - -
8. GHS Swaro Kot Orakzai - - -
9. GGMS Saifal Dara Orakzai - - -
10. GGPS Dago
Takhtak Orakzai - - -
11. GGPS Gori Chak Orakzai - - -
12. GGPS Zanka Khel Orakzai - - -
13. GHS Awi Mela Orakzai - - -
14. GPS Kasha Orakzai - - -
Building Sector - Militancy Damaged Schools Kurram Tribal District
1. GGPS Tari Tang Central
Kurram - - -
Technical bid
opening of 17
schools
underway
2. GPS Star Jumat Central
Kurram - - -
3. GPS Dargai No.3 Central
Kurram - - -
4. GPS Dargai No.2 Central
Kurram - - -
5. GPS Sherkhana Central
Kurram - - -
6. GPS Tatang Central
Kurram - - -
7. GPS Kuram Central
Kurram - - -
8. GPS Takhtak Central
Kurram - - -
9. GMHS Badama Central
Kurram - - -
10. GPS Mandan Central
Kurram - - -
11. GMS Gawaki Central
Kurram - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
12. GGPS Darkali Central
Kurram - - -
Technical bid
opening of 17
schools
underway
13. GGPS Kot Nakai Central
Kurram - - -
14. GPS Margha Dara Central
Kurram - - -
15. GPS Arghonja Central
Kurram - - -
16. GPS Nika Ziarat Central
Kurram - - -
17. GPS Samander
Kalai
Central
Kurram - - -
Building Sector - Militancy Damaged Schools Kurram Tribal District (Package – II)
1. GPS Baza Kurram - - -
NIT is under
process by C&W
Dept.
2. GGPS Hassan Zai Kurram - - -
3. GPS Durani Kurram - - -
4. GPS Maro Khel Kurram - - -
5. GGPS Khurmana Kurram - - -
Building Sector - Militancy Damaged Schools FR Peshawar
1. GPS Bora No.2 FR Peshawar - - -
NIT is under
process by C&W
Dept.
2. GGPS Janat Khan FR Peshawar - - -
3. GHS Bora FR Peshawar - - -
4. GHS Musa Dara FR Peshawar - - -
5. GGHS Samand
Khan FR Peshawar - - -
6. GGHS Malik
Noman Kalay FR Peshawar - - -
Building Sector - Militancy Damaged Schools FR Kohat
1. GPS Shahi Khel FR Kohat - - -
NIT is under
process by C&W
Dept.
2. GPS Feroz Kili FR Kohat - - -
3. GPS Sarwar Khel FR Kohat - - -
4. GGPS Zoor Kili FR Kohat - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
5. GMS Kohi Wal FR Kohat - - -
NIT is under
process by C&W
Dept.
6. GGMS Noor Ali
Khel FR Kohat - - -
7. GGMS Sara Meal
Bosti Khel FR Kohat - - -
8. GGMS Jammu
Shahi Khel FR Kohat - - -
9. GGMS Bila Kili FR Kohat - - -
10. GGMS Surak Toor
Chapper FR Kohat - - -
11. GGMS Jani Khel FR Kohat - - -
12. GGMS Suni Khel FR Kohat - - -
Building Sector - Government Degree College & Technical Institute
1. Reconstruction of
GDC Dogar Kurram - - -
Pre-qualification
of bidders
completed and
forwarded to CE
W&S for further
necessary action.
2. Reconstruction of
GTI Ghiljo Orakzai - - -
Pre-qualification
of bidders
completed and
forwarded to CE
W&S for further
necessary action.
Building Sector - Health Facilities
1.
Reconstruction of
Civil Hospital
Muzaffar Kot, Ali
Zai
Kurram - - -
Pre-qualification
of bidders
completed and
Administrative
approval issued.
Road Sector
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
1.
DI Khan - Tank
Road including
Tank Bypass & Link
to Tank City
DI Khan and
Tank 100% - Dec-15 Completed
2.
Bannu - Miran
Shah - Ghulam
Khan road
including bridges
North
Waziristan 100% - Jun-16 Completed
3.
Wana - Shakai -
Makin road
including bridges
South
Waziristan 100% - Dec-15 Completed
4. Construction of
Jamrud Bypass Khyber - - -
Signing of
contract in
progress
5.
Rehab. &
improvement of
Loesam - Nawapass
Road
Bajaur 0.5% - - Earthwork in
progress
6.
Widening &
improvement of
road from Marghan
to Nika Ziarat via
Murghan Kandao
in Central Kurram
Kurram 0.5% - - Earthwork in
progress
7.
Rehab. &
improvement of
Asil Targhaw Road
Bajaur 1% - - Earthwork in
progress
8.
Improvement &
widening of Bara -
Mastak Road
Khyber - - -
Pre-qualification
of bidders in
progress
9.
Improvement &
widening of Ghiljo
to Daburi Road
Orakzai - - -
Pre-qualification
of bidders in
progress
Bridges on Wana - Shakai - Makeen Road (76 Km)
1. Makeen Bridge
(29.29m) at Km 71
South
Waziristan 100% - Dec-15 Completed
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
2. Badar Bridge
(46.79m) at Km 58
South
Waziristan 100% - Dec-15 Completed
3. Torwam Bridge at
Km 28
South
Waziristan 100% - Dec-15 Completed
Bridges on Bannu - Miranshah - Ghulam Khan Road (82 Km)
1. Baran Bridge
(176m) at Km 07
North
Waziristan 100% - Jun-16 Completed
2. Chorai Bridge
(30m) at Km 26
North
Waziristan 100% - Jun-16 Completed
3. Khajuri Bridge
(61m) at Km 30
North
Waziristan 100% - Jun-16 Completed
4. Charkha Bridge
(96.94m) at Km 72
North
Waziristan 100% - Jun-16 Completed
5. Eidak Bridge
(156.84m) at Km 45
North
Waziristan 100% - Jun-16 Completed
6. Dinga Bridge
(88.03m) at Km 62
North
Waziristan 100% - Jun-16 Completed
7. Churkhai Bridge at
Km 81
North
Waziristan 100% - Jun-16 Completed
Power Sector
1.
Reconstruction / up
gradation of 66kV
to 132kV Grid
Station Khar
Bajaur 91% - Dec-18 In Progress
2.
Transmission line
from Gomal Zam
Dam to Wana Grid
station,
South
Waziristan 100% - Dec-15 Completed
3.
Rehabilitation of
11kv/33kv
distribution system
(PIL 11)
South
Waziristan 100% - Dec-16 Completed
4. 132kV Wana Grid
station,
South
Waziristan 100% - Jun-15 Completed
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
5.
Transmission Line
from Timergara to
Khar Grid Station.
Bajaur 47% - Dec-18 In Progress
6.
Reconstruction / up
gradation of 66kV
to 132kV Jandola
Grid Station
FR Tank 03% - Sep-20 In Progress
7.
Rehabilitation of
11kV distribution
system (PIL 37)
South
Waziristan - - -
PIL/FARA
amount of $
5,474,068 was
approved by
USAID
8.
Transmission Line
from Pezu to Tank
to Jandola Grid
Stations
FR Tank - - - PIL approval in
process
Irrigation and Water Supply Schemes
1.
Dhana irrigation
and water supply
scheme
South
Waziristan 100% - Jun-16 Completed
Rehabilitation & Solarization of Drinking Water Supply Schemes - Bajaur Tribal District
1. Loe Sum, Khar Bajaur - - -
Civil
Component:
Work orders for
22 schemes
issued. Layout
for 18 schemes
carried out
Solar
Component:
Evaluation of
financial bids is
in progress.
2. Zoor Bandar, Khar Bajaur - - -
3. Bai China Khar Bajaur - - -
4. Nawagai B/Station-
1
Bajaur - - -
5. Loe Jowar Khar Bajaur - - -
6. Lagharai, Mamund Bajaur - - -
7. Yousaf Abad, Khar Bajaur - - -
8. Khar Old Hospital Bajaur - - -
9. Kamar Kili,
Mamund
Bajaur - - -
10. Tangi Tube Well
No.1, Charmang
Bajaur - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
11. Jowar Qilla,
Salarzai, Zone-B
Bajaur - - -
Civil
Component:
Work orders for
22 schemes
issued. Layout
for 18 schemes
carried out
Solar
Component:
Evaluation of
financial bids is
in progress.
12. Loe Ghunai, Khar Bajaur - - -
13. Maramd Ghundai
Sara Mena, Khar
Bajaur - - -
14. Dak Qilla Atizi,
Khar
Bajaur - - -
15. Pakhawro,
Nawagai
Bajaur - - -
16. Shukrata, Utman
Khel
Bajaur - - -
17. Lara Dagai, Salarzai Bajaur - - -
18. Shagai, Salarzai Bajaur - - -
19. Malangai, Mamund Bajaur - - -
20. Mena, Mamund Bajaur - - -
21. Shago, Khar Astana
Gul Killi
Bajaur - - -
22. Dolasmanai,
Salarzai
Bajaur - - -
Rehabilitation & Solarization of Drinking Water Supply Schemes - Mohmand Tribal
District
1.
Hamza Khel
Halimzai
(Hameesh)
Mohmand - - -
Civil
Component:
Work Orders for
21 schemes
issued
Solar
Component:
Evaluation of
financial bids is
in progress. 10
nos. of schemes
yet to be
tendered.
2. Khuram Cheena,
Halimzai
Mohmand - - -
3. Yousaf Khel
Halimzai
Mohmand - - -
4. Sultan Khel
Nasapay
Mohmand - - -
5. Alam Baig Kamaly Mohmand - - -
6. Shah Baig Yasin
Kore
Mohmand - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
7. Shati Kor Halimzai Mohmand - - -
Civil
Component:
Work Orders for
21 schemes
issued
Solar
Component:
Evaluation of
financial bids is
in progress. 10
nos. of schemes
yet to be
tendered.
8. Sultan Khel
Halimzai
Mohmand - - -
9. Ato Khel Halimzai Mohmand - - -
10. Charagan Raha
Khan Halimzai
Mohmand - - -
11. Mohra Mettaid
Baizai
Mohmand - - -
12. Ghanum Shah
Baizai
Mohmand - - -
13. Dag Killi Baizai Mohmand - - -
14. Mazi Kore Baizai Mohmand - - -
15. Abdul Khel Zaman
Kore Baizai
Mohmand - - -
16. Faqir Abad Baizai Mohmand - - -
17. Jabbar Jaour Baizai Mohmand - - -
18. Ghanum Shah
Baizai
Mohmand - - -
19. Koda Khel Baizai Mohmand - - -
20. Kuzo Kas Khewzai Mohmand - - -
21. Ghair Dhand Baizai Mohmand - - -
22. Ghanam Shah Mohmand - - -
Rehabilitation & Solarization of Drinking Water Supply Schemes - Khyber Tribal
District
1. Shahkass 2 Jamrud Khyber - - - Civil
Component:
Evaluation of
financial bids of
12 schemes in
progress.
Solar
Component:
Financial bids
for 12 schemes
2. Shahakass 3,
Jamrud Khyber - - -
3. Shahkass 4, Jamrud Khyber - - -
4. Shahkass 5, Jamrud Khyber - - -
5. Ghundi 1, Jamrud Khyber - - -
6. Ghundi 2, Jamrud Khyber - - -
7. Ghundi 5, Jamrud Khyber - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
8. Ghariza 1, Jamrud Khyber - - - opened on Apr
8, 2019,
evaluation in
progress.
9. Surkamar 1, Jamrud Khyber - - -
10. Godar 3, Jamrud Khyber - - -
11. Wazir Dhand 2,
Jamrud Khyber - - -
12. Ali Masjid Area,
Jamrud Khyber - - -
13. Landi Kotal 1 Khyber - - -
14. Landi Kotal 2 Khyber - - -
Rehabilitation & Solarization of Drinking Water Supply Schemes - FR Peshawar
1. Faridi Hassan Khel FR Peshawar - - - In progress
2. Sama Bada Bera
T/W1 FR Peshawar - - - In progress
3. Sama Bada Bera
T/W2 FR Peshawar - - - In progress
4. Hassan Khel-2 FR Peshawar - - - In progress
5. Hassan Khel-3 FR Peshawar - - - In progress
Rehabilitation & Solarization of Drinking Water Supply Schemes - FR Kohat
1. Akhurwal FR Kohat - - - In progress
2. Dara Adam Khel FR Kohat - - - In progress
Rehabilitation & Solarization of Irrigation Water Supply Schemes – Bajaur Tribal
District
1. Tang Khata Bajaur - - -
Civil
Component:
Work orders for
41 schemes
issued. Work on
11 schemes is in
progress.
Solar
Component:
Acceptance letter
2. Khair Abad Bajaur - - -
3. Aman Kot Bajaur - - -
4. Sham shak (Sadiq
Abad) Bajaur - - -
5. Ghali Shah Bajaur - - -
6. Dherai Tangkhatta Bajaur - - -
7. Mulano Killi Bajaur - - -
8. Narrai Shah Bajaur - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
9. Shukrata(Qazafi) Bajaur - - - issued to the
successful
bidders.
Civil
Component:
Work orders for
41 schemes
issued. Work on
11 schemes is in
progress.
Solar
Component:
Acceptance letter
issued to the
successful
bidders.
10. Dag Loe Sum Bajaur - - -
11. Bar Kamer Bajaur - - -
12. Kamer Jan Bajaur - - -
13. Sewai Bajaur - - -
14. Umarai Bajaur - - -
15. Jang Zai Bajaur - - -
16. Dando Bajaur - - -
17. Loe Sam Bajaur - - -
18. Shago Chianagai Bajaur - - -
19. Earb Bajaur - - -
20. Chingazo Bajaur - - -
21. Kharai Kamer Bajaur - - -
22. Tangi Bajaur - - -
23. Girai Bajaur - - -
24. Pacha Killi Bajaur - - -
25. Muslim Bagh Bajaur - - -
26. Threma Thrash Bajaur - - -
27. Gafoor Shah Bajaur - - -
28. Bar Khalozai Bajaur - - -
29. Bar Khar Kano Bajaur - - -
30. Balolai Bajaur - - -
31. Dabdaboo Bajaur - - -
32. Toot Shah Bajaur - - -
33. Kausar Bajaur - - -
34. Jour Qilla Bajaur - - -
35. Mammer Dag Bajaur - - -
36. Zaga Dherai Bajaur - - -
37. Girai Bajaur - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
38. Lar Khar Kano Bajaur - - -
39. Bahi Cheena Bajaur - - -
40. Badi Samoor Bajaur - - -
41. Umaria Bajaur - - -
Rehabilitation & Solarization of Irrigation Tube Well for Mohmand Tribal District
1. Said Rehman Mohmand - - -
Civil
Component:
Evaluation of
financial bids of
22 schemes in
progress.
Solar
Component:
Evaluation of
technical bids of
22 schemes in
progress.
2. Raees Khan Mohmand - - -
3. Shahid khan Mohmand - - -
4. 31/2046 Mohmand - - -
5. 16/2029 Mohmand - - -
6. 2009/1 Mohmand - - -
7. 2014/26 Mohmand - - -
8. M6/2006 Mohmand - - -
9. 12/20 24 Mohmand - - -
10. 15 /2028 Mohmand - - -
11. 2032/19 Mohmand - - -
12. 2 / MT-2002 Mohmand - - -
13. 3 / MT-3 Mohmand - - -
14. Gul Zada Mohmand - - -
15. Imad Uddin Mohmand - - -
16. M. Zahoor Mohmand - - -
17. M. Hayat Mohmand - - -
18. Zahir Muhammad Mohmand - - -
19. Wisal Muhammad Mohmand - - -
20. Faheed Gul Mohmand - - -
21. Faiz Ullah Mohmand - - -
22. Ibrar Khan Mohmand - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
Rehabilitation & Solarization of Irrigation Tube Well for Khyber Tribal District
1. 3003 Khyber - - -
Civil
Component:
Evaluation of
technical bids of
29 schemes in
progress.
Solar
Component:
Evaluation of
technical bids of
29 schemes in
progress.
2. 3004/2 Khyber - - -
3. 3005/3 Khyber - - -
4. 3006 Khyber - - -
5. 3011/5 Khyber - - -
6. 3012 Khyber - - -
7. 3021/4 Khyber - - -
8. 3039 Khyber - - -
9. 3041 Khyber - - -
10. 3043 Khyber - - -
11. 3044 Khyber - - -
12. 3047 Khyber - - -
13. 3048 Khyber - - -
14. 3059 Khyber - - -
15. 3071 Khyber - - -
16. SK-1 Khyber - - -
17. SK-2 Khyber - - -
18. SK-3 Khyber - - -
19. 3031/2 Khyber - - -
20. 431/1 Khyber - - -
21. 433/3 Khyber - - -
22. 435/1 Khyber - - -
23. 436/1 Khyber - - -
24. TW #01 Khyber - - -
25. TW #02 Khyber - - -
26. TW #03 Khyber - - -
27. TW #06 Khyber - - -
28. TW #07 Khyber - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
S.
No. Name of Project Location
Progress
as of
March
2017
Progress
as of
March
2018
Progress
as of
March
2019
Status
29. TW #08 Khyber - - -
30. TW #10 Khyber - - -
31. TW # 40 Khyber - - -
32. TW # 24t Khyber - - -
33. TW # 433/2 Khyber - - -
34. TW # 09 Khyber - - -
Rehabilitation & Solarization of Irrigation Tube Well for FR Kohat
1. 1/4503 (Gadia Khel) FR Kohat - - - Civil
Component:
Evaluation of
financial bids of
7 schemes in
progress.
Solar
Component:
Evaluation of
technical bids of
7 schemes in
progress.
2. 2/4504 (Shin
Dhand) FR Kohat - - -
3. 4-4506 (Bashri Kali) FR Kohat - - -
4. 4511(Shamal Khel) FR Kohat - - -
5. 4513 (Akhur Wall) FR Kohat - - -
6. 4514 (Shin Dhand) FR Kohat - - -
Rehabilitation & Solarization of Irrigation Tube Well for FR Peshawar
1. TW # 2 (Shamt
Khel) FR Peshawar - - -
Civil
Component: PC-
1 approved
while tendering
process started.
Solar
Component:
Evaluation of
technical bids of
4 schemes in
progress.
2. TW # 5 (Khoi
Hassan Khel) FR Peshawar - - -
3. TW # 7 (Masri Khel) FR Peshawar - - -
4. TW # 8 (Abdullah
Khel) FR Peshawar - - -
5. TW # 9 (Amir Khel) FR Peshawar - - -
6. TW # 10 (Amer
Khel) FR Peshawar - - -
7. Khewa Kheil FR Peshawar - - -
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
Annexure E - Pictorial Progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-1 HPK
BUILDING SECTOR - KPRP (Militancy Damaged Schools)
April 2018 - March 2019
Fig. 01. GPS Meramai, Dir Lower attained
completion during the reporting period
Fig. 02. Overall view of GPS Maidan Bandai
Dir Lower
Fig. 03. GGPS Chuprial, Swat attained
completion during the reporting month
Fig. 04. Finishing works in progress at GHSS
Charbagh, Swat
Fig. 05. Plastering work completed at GGPS
Raidgai, Dir Lower
Fig. 06. Work on Over Head tank is in progress
at GHS Maidan Bandai, Dir Lower
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-2 HPK
BUILDING SECTOR - KPRP (Militancy Damaged Schools)
April 2018 - March 2019
Fig. 07. GMS Gulbandai, Buner in final stages
of construction
Fig. 08. Plastering work in progress at GPS
Inzar Maira No.1 Buner
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-3 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 01. GPS Godha, Swat attained completion
during the reporting month
Fig. 03. GPS Pacha Kalay Swat attained
completion during the reporting month Fig. 04. GGMS Qayum Abad Lalkoo Swat
attained completion during the reporting month
Fig. 02. Over all view of GPS Godha, Swat
Fig. 05. GPS Biha, Swat in final stages of
construction
Fig. 06. Finishing works in progress at GPS
Chinda Khora, Swat
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-4 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 09. Plastering in progress at GGPS Bara
Bandai, Swat
Fig. 10. Plastering work completed in GGPS
Kass, Swat
Fig. 07. Finishing works in progress at GGPS
Godha, Swat
Fig. 08. Bore well is in progress at GPSS No. 2
Maloch, Swat
Fig. 11. Marble work is in progress at GGPS
Serai Gut, Swat
Fig. 12. Removal of snags in progress at GPS
Raidgai, Dir Lower (April, 2018)
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-5 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools) April 2018 - March 2019
Fig. 13. GGMS Kotkay, Dir Lower attained
completion during the reporting period
Fig. 14. GPS No. 1 Sherkhanai Dir Lower
attained completion during the reporting month
Fig. 15. Plastering work in progress at GHS
Mian Brangola, Dir Lower
Fig. 16. RCC work completed at GMS Asigi
Kalay, Dir Lower
Fig. 17. Brick work in progress at GPS
Zaimdara, Dir Lower Fig. 18. Neck columns concrete poured at GHS
Mirgam Bala, Dir Lower
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-6 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 19. GPS Nihag Dir Upper attained
completion during the reporting month
Fig. 20. Finishing works in progress at GPS
Sundal, Dir Upper
Fig. 21. Finishing works in progress at GPS
Zakria, Dir Upper
Fig. 22. Finishing Works in progress at GPS
Tangai Sir, Dir Upper
Fig. 23. Finishing works are in progress at GPS
Kass Barikot, Dir Upper
Fig. 24. Finishing works are in progress at GPS
Remin Kass, Dir Upper
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-7 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 25. Concreting of Gable columns in
progress at GPS Sundrai, Dir Upper
Fig. 26. Gable beam concreting in progress at
GHS Jan Bhatti, Dir Upper
Fig. 27. Truss installation in progress at GHS
Shung, Shangla
Fig. 28. Truss installation in progress at GMS
Belkanai, Shangla
Fig. 29. Truss installation in progress at GGPS
Shalmano Chakesar, Shangla Fig. 30. Marble work is in progress at GGPS
Begumar Lahore, Shangla
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-8 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 31. Steel fixing of GF Roof Beam is in
progress at GHS Amnavi, Shangla
Fig. 32. Concreting of Gable beam in progress at
GGPS Shalmano Kotkay, Shangla
Fig. 33. Fixing of Steel of Water Tank is in
progress at GGPS Qambari, Shangla
Fig. 34. GHS Inzergay, Malakand in final
stages of construction
Fig. 35. Finishing works in progress at GPS
Hisar Baba, Malakand
Fig. 36. View of GPS Shahidan, Charsadda
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-9 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 40. Lean concrete for footings completed at
GGPS Sadar Ghari, Charsadda Fig. 39. Fixing of formwork for neck columns in
progress at GPS No. 01 Katozai, Charsadda
Fig. 37. Substantially completed GGPS
Sumunat, Charsadda
Fig. 38. Plastering of mumty in progress at
GPS Mansooka, Charsadda
Fig. 41. View of GPS Shahab Khel Kaka Sahib,
Nowshera
Fig. 42. View of main module of GPS Bab-e-
Jadeed Nowshera
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-10 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 43. View of LB at GPS Sherin Kotai,
Nowshera
Fig. 46. Finishing works in progress at GPS
No.1 Kotarpan, Nowshera
Fig. 44. View of GGPS Pashtoon Garhi,
Nowshera
Fig. 45. View of GPS Kandi Taza Din,
Nowshera
Fig. 47. View of GPS Zakhi Qabristan,
Nowshera
Fig. 48. Concrete pouring in GF columns
completed at GPS Aman Kot
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-11 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 49. FF slab concrete completed at GPS
Hawai, Nowshera
Fig. 50. Back filling in progress at GHS
Pashtoon Ghari, Nowshera
Fig. 51. Brickwork completed at GPS Khan Jan
Kale, Nowshera
Fig. 52. View of GPS Mohallah Mulla Khan,
Nowshera
Fig. 53. Lean concrete completed in foundation
of M-6 module at GHS Khwishgi Bala,
Nowshera
Fig. 54. Steel fixing for mumty slab completed
at GPS Toha, Peshawar
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-12 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 55. Steel fixing for LB in progress at GPS
Tor Dheri, Nowshera Fig. 56. View of GPS No.1 Mishak, Nowshera
Fig. 57. Steel fixing for SF slab in progress at
GGPS Marooba, Nowshera
Fig. 58. Brickwork in progress at FF of GPS
Jaroba, Nowshera
Fig. 59. Excavation for foundation in progress
at GPS Karam Khel Peshawar Fig. 60. Steel fixing in foundation in progress at
GPS Yari Korona, Peshawar
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-13 HPK
BUILDING SECTOR - KPRP (Flood Damaged Schools)
April 2018 - March 2019
Fig. 61. Levelling of court yard in progress at
GPS Bairoon Sharqi, DI Khan
Fig. 63. Brick masonry of LB in progress at
GPS No.1 Yarak, DI Khan
Fig. 62. Removal of snags in progress at GPS
Rora Nawa, DI Khan
Fig. 64. Formwork fixing for parapet wall in
progress at GPS Jhoke Umaray Wali, DI Khan
Fig. 65. Inner view of class room at GPS
Makkar, DI Khan
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-14 HPK
BUILDING SECTOR - KPRP (BURN & TRAUMA CENTRE, PESHAWAR)
April 2018 - March 2019
Fig. 01. Front view of Burns & Trauma Centre Fig. 02. Ambulances at Parking Area
Fig. 03. Modular Operation Theatre is
functional
Fig. 04. Modular Operation Theatre is
functional
Fig. 05. Packing of sterilized goods in process at
CSSD Department Fig. 06. Chairs placed for attendants at waiting
area
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-15 HPK
BUILDING SECTOR - KPRP (GHSS AKBAR PURA, NOWSHERA)
April 2018 - March 2019
Fig. 01. Overall view of GHSS Akbar Pura Fig. 02. Brick masonry at GF of block A in
progress
Fig. 03. Brick masonry at FF of block A in
progress
Fig. 04. View of a guard room
Fig. 05. Formwork fixing for FF slab of watch
tower in progress
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-16 HPK
BUILDING SECTOR - KPRP (TEHSIL COMPLEX KABAL, SWAT)
April 2018 - March 2019
Fig. 01. Plinth beam steel fixing in progress at
District Govt. Building
Fig. 02. Mumty floor steel fixing in progress at
Judicial Complex Building
Fig. 03. FF slab form work in progress at
Residence 1-5
Fig. 04. Brick work in foundation in progress at
Residence 6-10
Fig. 05. Plastering of pump house in progress Fig. 07. BHU Mashkomai, Swat attained
completion during the reporting month
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-17 HPK
BUILDING SECTOR - KPRP (WATSAN)
April 2018 - March 2019
Fig. 01. Testing of Pumping machinery in
progress at DWSS Akram Mohallah, Swat
Fig. 02. DWSS Makan Bagh, Swat attained
completion during the reporting month
Fig. 03. External electrification completed at
DWSS Shagai Zone 1, Swat
Fig. 04. Testing of pumping machinery at
DWSS Gulkada Miara, Swat is in progress
Fig. 05. Testing of rising main in progress at
DWSS Akhoon Baba, Swat
Fig. 06. Pump house of DWSS Barama, Swat
completed
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-18 HPK
BUILDING SECTOR - KPRP (WATSAN)
April 2018 - March 2019
Fig. 07. Testing of pumping machinery in
progress at DWSS Maskipur, Buner
Fig. 08. Final testing at DWSS Dagai Buner in
progress
Fig. 09. External electrification completed at
DWSS Jowar (Bazargay), Buner
Fig. 12. Lowering of casing in pipe in progress
at DWSS Jowar No. 2 Buner
Fig. 11. View of the Pump House of DWSS
Sunigram, Buner
Fig. 10. Finishing works in progress at pump
house of DWSS Soor Kamar Maira, Buner
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-19 HPK
BUILDING SECTOR - KPRP (WATSAN)
April 2018 - March 2019
Fig. 13. Boring of Tube well in progress at
DWSS Bampokha, Buner
Fig. 14. Boring of Tube well in progress at
DWSS Gagra, Buner
Fig. 15. Boring of tube well in progress at
DWSS Kingargalai, Buner
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-20 HPK
ROAD SECTOR - FIP (MARGHAN - NIKKA ZIARAT ROAD, KURRAM)
April 2018 - March 2019
Fig. 01. HPK staff checking width of sub grade
top in km 01
Fig. 02. Cutting with jack hammer in progress
at km 02
Fig. 03. Cleaning& grabbing with Dozer in
progress at km 02
Fig. 04. Excavation completed at km 01
Fig. 05. HPK staff checking the levels of
completed excavation at km 01
Fig. 06. HPK staff collecting sample for
subgrade at km 04
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-21 HPK
ROAD SECTOR - FIP (LOESUM - NAWAPASS ROAD, BAJAUR)
April 2018 - March 2019
Fig. 01. Cutting of trees along roadside in
progress at km 02
Fig. 02. Excavated shoulder along asphalt edges
at km 01
Fig. 03. Widening of road in progress at km 01 Fig. 04. HPK, Cameos, W&S Dept. meeting
with contractors of package 01 & 02 regarding
joint cross sections & construction material
Fig. 05. Site camp of contractor at package 01 Fig. 06. Cutting of existing asphalt for sub
grade level in progress at km 01
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-22 HPK
ROAD SECTOR - FIP (ASIL TARGHAW ROAD, BAJAUR)
April 2018 - March 2019
Fig. 01. Excavation with excavator in progress
at km 01
Fig. 02. Drilling with jack hammer in progress
at km 02
Fig. 03. Excavation completed at km 01 Fig. 04. HPK staff checking NSL at km 01
Fig. 05. Drilling with jack hammer in progress
at km 01
Fig. 06. Laboratory being set in contractor’s site
camp
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-23 HPK
POWER SECTOR - FIP (132kV GRID STATION KHAR, BAJAUR)
April 2018 - March 2019
Fig. 01. Over all view of Control House
Building
Fig. 02. An overview of 132kV Grid Station
Kahr-Bajaur from Earth Mast top
Fig. 03. No activity on excavation for Earth
Mesh in switch yard at 132kV Grid Station
Bajaur Agency
Fig. 04. The outdoor lay out of cables in
trenches is in progress
Fig. 05. Installation of Bus Bar Disconnector
switch box is in progress
Fig. 06. 11kV Steel Structures at 132kV Grid
station Bajaur
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-24 HPK
POWER SECTOR - FIP (132kV TRANSMISSION LINE KHAR, BAJAUR)
April 2018 - March 2019
Fig. 01. HPK staff inspecting the stub
foundations at location # 76 (ZM-30)
Fig. 02. Completed concrete in stub foundation
of tower location # 75 (ZM01+3M)
Fig. 03. Steel cages for foundation no. 03 & 04
of tower location # 07 (ZM-01+6M)
Fig. 05. The erection of super structure of tower
at location # 17 (ZM-01) is completed
Fig. 04. Pouring of concrete in pile foundation
No. 04 at tower location # 07 (ZM-01+6M)
Fig. 06. Casting of concrete test specimens
during concreting of stub foundation at tower
location # 67
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-25 HPK
POWER SECTOR - FIP (132kV GRID STATION JANDOLA, FR TANK)
April 2018 - March 2019
Fig. 01. Excavation for Control House Building
completed
Fig. 02. Layout for Control House Building has
been carried out
Fig. 03. Excavation for boundary wall
completed
Fig. 04. Curing tank constructed at site
Fig. 05. Steel supplied at site Fig. 06. HPK staff collecting sample for testing
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-26 HPK
WATER SECTOR - FIP (DRINKING WATER SUPPLY SCHEMES)
April 2018 - March 2019
Fig. 01. Formwork fixing for plinth beam of
boundary wall at DWSS Dara Adam Khel, FR
Kohat
Fig. 02. DWSS Hassan Khel-III FR Peshawar
Fig. 03. DWSS Sama Bada Bera- I FR
Peshawar
Fig. 04. DWSS Sama Bada Bera- II FR
Peshawar
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 E-27 HPK
ENVIRONMENT COMPLIANCE
April 2018 - March 2019
Fig. 01. Group photo at GPS Nihag, District
Dir Upper
Fig. 02. Teachers being trained on proper use of
fire equipment installed inside schools at GPS
Nihag District upper Dir
Fig. 03. Meeting with the teaching staff during
success story meeting in GHS Inzargai,
Malakand
Fig. 04. Teaching and non-teaching staff of the
GHS Inzargai being trained on use of fire
extinguishers
Fig. 05. Termites spray being carried out at
GHS Kheshgi bala. Mandatory PPE’s provided
to worker
Fig. 06. The area properly barricaded for un-
authorized entry before termites spray
application at GHS Kheshgi Bala, Nowshera
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 HPK
Annexure F - Success Stories
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 F-1 HPK
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 F-2 HPK
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 F-3 HPK
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP Annual Implementation Report No. 04
April 2018 to March 2019 F-4 HPK