ANNUAL AWARDS - Institution of Civil Engineers...ANNUAL AWARDS Medium Project Award entry Melbourne,...
1
ANNUAL AWARDS Medium Project Award entry Melbourne, Leicestershire Melbourne Water Treatment Works High Lift Pump Sump Bypass In AMP6, Severn Trent Water have adopted a new ‘manufacturing process’ approach to review the effectiveness of its Water Treatment Works (WTWs). This approach highlighted the High Lift Sump as a single point of failure at Melbourne WTW, which was subsequently assessed as an unacceptable risk to the business. A fast track approach to the delivery of the project to address this risk, has required significant collaboration, innovation, project management and an overarching drive to deliver within the project team. CLIENT: Severn Trent Water DESIGNERS: MWH Treatment CONTRACTORS: MWH Treatment
Transcript of ANNUAL AWARDS - Institution of Civil Engineers...ANNUAL AWARDS Medium Project Award entry Melbourne,...
ANNUAL AWARDSMedium Project Award entry
Melbourne, Leicestershire
Melbourne Water Treatment Works High Lift Pump Sump BypassIn AMP6, Severn Trent Water have adopted a new ‘manufacturing process’ approach to review the effectiveness of its Water Treatment Works (WTWs). This approach highlighted the High Lift Sump as a single point of failure at Melbourne WTW, which was subsequently assessed as an unacceptable risk to the business. A fast track approach to the delivery of the project to address this risk, has required significant collaboration, innovation, project management and an overarching drive to deliver within the project team.
CLIENT: Severn Trent Water
DESIGNERS: MWH Treatment
CONTRACTORS: MWH Treatment