Annexure-III - Revised DPR - 2 MW Biomass Power Plant at SA
-
Upload
nguyenngoc -
Category
Documents
-
view
225 -
download
2
Transcript of Annexure-III - Revised DPR - 2 MW Biomass Power Plant at SA
SURYACHAKRA GREEN FUELS PRIVATE
LIMITED
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 2 of 111
DETAILED PROJECT REPORT
FOR
2.28 MW BIOMASS BASED
POWER PROJECT AT ANDAMAN & NICOBAR
ISLANDS
NOVEMBER 2012
PROJECT CONSULTANT:
AQUATHERM ENGINEERING CONSULTANTS
(INDIA) PRIVATE LIMITED,
CHENNAI 600 004,
INDIA.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 3 of 111
TABLE OF CONTENTS
SECTION – 1 ...................................................................................................................... 7
1. INTRODUCTION ..................................................................................................... 8
1.1. ABOUT THE PROJECT .............................................................................................. 8
1.2. PREFACE ................................................................................................................... 9
SECTION – 2 .....................................................................................................................15
2. EXECUTIVE SUMMARY ........................................................................................16
SECTION 3 ........................................................................................................................18
3. PROJECT AT A GLANCE ......................................................................................19
3.1. PLANT DETAILS ....................................................................................................... 19
3.2. TECHNICAL DETAILS OF THE PLANT ................................................................... 19
3.3. EXCERPTS FROM BIOMASS ASSESSMENT REPORT ........................................ 21
SECTION 4 ........................................................................................................................23
4. SALIENT FEATURES OF THE SITE ......................................................................24
4.1. SITE LOCATION ....................................................................................................... 24
4.2. METEOROLOGICAL DATA ...................................................................................... 24
4.3. WIND AND SEISMIC DATA ..................................................................................... 24
4.4. WATER SOURCE ..................................................................................................... 24
4.5. FUEL ......................................................................................................................... 25
4.6. POWER EVACUATION ............................................................................................ 25
SECTION 5 ........................................................................................................................26
5. SELECTION OF COMBUSTION TECHNOLOGY ..................................................27
5.1. MACHINERY REQUIRED FOR DIRECT COMBUSTION TECHNOLOGY ............. 27
5.2. PROCESS FLOW OF THE POWER PLANT............................................................ 28
5.3. SELECTION OF EQUIPMENT ................................................................................. 29
5.4. TYPE OF BIOMASS FUELS AND COMBUSTION MECHANISMS ......................... 30
5.5. TYPE AND SIZE OF POWER PLANT ...................................................................... 31
5.6. THERMAL CYCLES AND STEAM PARAMETERS ................................................. 31
5.7. HEAT AND MASS BALANCE ................................................................................... 33
5.8. SIZING OF PLANT & MACHINERY ......................................................................... 33
SECTION – 6 .....................................................................................................................35
6. PLANT LAYOUT ....................................................................................................36
6.1. LAYOUT CONSIDERATIONS .................................................................................. 36
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 4 of 111
6.2. ASH, EFFLUENT & SEWAGE DISPOSAL ............................................................... 37
6.3. PLANT LAYOUT ....................................................................................................... 37
6.4. APPROACH & INTERNAL ROADS .......................................................................... 39
SECTION - 7 ......................................................................................................................40
7. DESCRIPTION OF THE MECHANICAL SYSTEMS ...............................................41
7.1. GENERAL DESCRIPTION ....................................................................................... 41
7.2. BOILER SYSTEM ..................................................................................................... 41
7.3. SUPERHEATER SYSTEM ....................................................................................... 43
7.4. ATTEMPERATOR SYSTEM ..................................................................................... 43
7.5. SOOT BLOWING SYSTEM ...................................................................................... 44
7.6. FUEL FEEDING SYSTEM ........................................................................................ 44
7.7. DRAFT SYSTEM ...................................................................................................... 44
7.8. DUCTING SYSTEM .................................................................................................. 45
7.9. CHEMICAL DOSING SYSTEM ................................................................................ 45
7.10. ESP ........................................................................................................................... 45
7.11. CHIMNEY .................................................................................................................. 46
7.12. ASH HANDLING SYSTEM ....................................................................................... 46
7.13. BOTTOM ASH HANDLING SYSTEM ....................................................................... 46
7.14. FLY ASH HANDLING SYSTEM ................................................................................ 46
7.15. TURBO-GENERATOR SYSTEM .............................................................................. 46
7.16. STEAM TURBINE GOVERNING SYSTEM .............................................................. 48
7.17. WATER TREATMENT PLANT ................................................................................. 52
7.18. SERVICE WATER .................................................................................................... 52
7.19. FIRE WATER & FIRE PROTECTION SYSTEM ....................................................... 53
7.20. CRANES AND HOISTS ............................................................................................ 55
7.21. COMPRESSED AIR SYSTEM .................................................................................. 55
7.22. AIR-CONDITIONING AND VENTILATION SYSTEM ............................................... 55
7.23. TECHNICAL DATA FOR MAJOR MECHANICAL EQUIPMENT.............................. 56
SECTION 8 ........................................................................................................................59
8. DESCRIPTION OF ELECTRICAL SYSTEMS ........................................................60
8.1. GENERATOR ........................................................................................................... 60
8.2. SURGE PROTECTION EQUIPMENT ...................................................................... 64
8.3. POWER EVACUATION ............................................................................................ 64
8.4. 11 KV SWITCHGEAR ............................................................................................... 64
8.5. POWER TRANSFORMERS ..................................................................................... 65
8.6. 33KV SWITCHYARD ................................................................................................ 65
8.7. AUXILIARY POWER SUPPLY ARRANGEMENT .................................................... 68
8.8. 415V SYSTEM .......................................................................................................... 68
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 5 of 111
8.9. CONTROL & PROTECTION SYSTEM ..................................................................... 69
8.10. EMERGENCY POWER SUPPLY ............................................................................. 71
8.11. DIRECT CURRENT SUPPLY SYSTEM ................................................................... 71
8.12. UNINTERRUPTED POWER SUPPLY (UPS) SYSTEM ........................................... 72
8.13. LIGHTING ................................................................................................................. 72
8.14. CABLING .................................................................................................................. 73
8.15. LIGHTNING PROTECTION SYSTEM ...................................................................... 74
8.16. FIRE ALARM SYSTEM ............................................................................................. 74
8.17. FIRE CONTAINMENT ............................................................................................... 74
8.18. PLANT COMMUNICATION SYSTEM ...................................................................... 74
8.19. SAFETY EARTHING SYSTEM ................................................................................. 75
8.20. INSTRUMENTATION AND CONTROL SYSTEM .................................................... 75
SECTION 9 ........................................................................................................................77
9. ENVIRONMENTAL IMPACT AND POLLUTION CONTROL ..................................78
9.1. CONTROL METHODS FOR AIR POLLUTION ........................................................ 78
9.2. CONTROL METHODS FOR WATER POLLUTION ................................................. 79
9.3. CONTROL METHODS FOR THERMAL POLLUTION ............................................. 80
9.4. CONTROL METHODS FOR NOISE POLLUTION ................................................... 80
9.5. DG SETS .................................................................................................................. 80
9.6. INPUTS AND OUTPUTS FROM POWER PLANT ................................................... 81
SECTION 10 ......................................................................................................................82
10. STATUTORY CELARANCES REQUIRED .............................................................83
10.1. IN PRINCIPLE CLEARANCE FROM ELECTRICAL DEPARTMENT OF A&N
ISLANDS ................................................................................................................... 83
10.2. APPROVAL FOR PARALLEL OPERATION............................................................. 83
10.3. CLEARANCE FROM AIR PORT AUTHORITY OF INDIA ........................................ 83
10.4. POLLUTION CONTROL BOARD ............................................................................. 83
10.5. APPROVAL FROM LOCAL PANCHAYAT ............................................................... 83
10.6. INSURANCE ............................................................................................................. 83
10.7. APPROVAL FOR THE ELECTRICAL INSTALLATION ............................................ 84
10.8. APPROVAL FOR THE FACTORY INSTALLATION ................................................ 84
10.9. BOILER AND PRESSURE PART COMPONENTS .................................................. 84
10.10. APPROVAL FROM GOVERNMENT AUTHORITY ................................................ 84
SECTION 11 ......................................................................................................................85
11. OPERATION AND MAINTENANCE .......................................................................86
11.1. BASIC STRUCTURE OF THE O&M TEAM .............................................................. 86
11.2. FACILITIES TO BE EXTENDED TO THE EMPLOYEES ......................................... 87
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 6 of 111
11.3. STATION MAINTENANCE PHILOSOPHY ............................................................... 88
11.4. MAINTENANCE PLAN AND SCHEDULED MAINTENANCE .................................. 88
11.5. MAINTENANCE MANAGEMENT SYSTEM ............................................................. 89
11.6. SPARE PARTS MANAGEMENT SYSTEM .............................................................. 89
11.7. AVAILABILTY OF O & M MANUALS ........................................................................ 89
11.8. SPECIAL TOOLS AND TACKLES ............................................................................ 90
11.9. OPERATION REQUIREMENTS ............................................................................... 90
11.10. CHECK-LIST AND PROTOCOL ............................................................................... 90
SECTION 12 ......................................................................................................................92
12. COST ESTIMATION AND FINANCIAL ANALYSIS ................................................93
SECTION – 13 ...................................................................................................................94
13. SWOT ANALYSIS ..................................................................................................95
SECTION – 14 ...................................................................................................................97
14. SOCIO-ECONOMIC & ENVIRONMENTAL BENEFITS ..........................................98
SECTION 15 ......................................................................................................................99
15. PROJECT IMPLEMENTATION ............................................................................ 100
15.1. PROJECT SCHEDULE ........................................................................................... 100
15.2. PROJECT MANAGEMENT..................................................................................... 100
15.3. CONSTRUCTION MANAGEMENT ........................................................................ 102
15.4. CONSTRUCTION MANAGEMENT ORGANISATION ........................................... 103
15.5. INFRASTRUCTURAL FACILITIES & CIVIL SYSTEM ........................................... 104
15.6. QUALITY ASSURANCE & INSPECTION ............................................................... 105
15.7. MAN POWER TRAINING & PLACEMENT ............................................................. 106
SECTION 16 .................................................................................................................... 108
16. LIST OF DRAWINGS ........................................................................................... 109
SECTION – 17 ................................................................................................................. 110
17. ANNEXURES ....................................................................................................... 111
ANNEXURE –I FINANCIAL STATEMENT
ANNEXURE –II WATER ANALYSIS REPORT (Will be submitted shortly)
ANNEXURE –III BIOMASS STUDY AVAILABILITY REPORT
ANNEXURE –IV PROJECT SCHEDULE
ANNEXURE –V SITE PLAN
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 7 of 111
SECTION – 1
INTRODUCTION
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 8 of 111
1. INTRODUCTION
1.1. ABOUT THE PROJECT
1.1.1. M/s. Suryachakra Green Fuels Private Limited (hereinafter referred to as SGFPL),
proposes to set up biomass based power generation plant at at Mithakhari village,
Ferrargunj Tehsil in South Andaman Islands.
1.1.2. SGFPL is a professionally managed company promoted by well qualified people
who have several years of experience in creating power generation projects
using renewable energy sources.
1.1.3. There has been a deficit power situation in the union territory of A&N Islands.
With depleting fossil fuels, the renewable source of energy has gained importance
worldwide. The A&N Government has been encouraging setting up of mini power
plants based on the usage of renewable sources. Keeping in view the deficit
situation for power and encouragement given by Government for setting up of
renewable energy projects.
1.1.4. In view of the above, M/s. Suryachakra Green Fuels Private Limited proposes to
establish 2.28 MW Biomass based Power Project in Andaman & Nicobar Islands
1.1.5. Based on the availability of biomass (Coconut, arecanut, red oil palm, cashenut,
cereals like paddy, maize, pulse, napier grass and wood chips) with in 50km
radius from the site. The estimated availability of surplus biomass is 1,83,000 Ton,
which is much more of the annual biomass requirement for the 2.28 MW plant.
The annual biomass fuel requirement for proposed 2.28 MW plant is estimated at
18,754.56 MT/year
1.1.6. The power will be evacuated to 33 / 11 kV through generator transformer.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 9 of 111
1.2. PREFACE
1.2.1. Today, most of the regions in the country are plagued with power shortages
leading to erratic and unreliable supply. The problem becomes acute during peak
hours and thus necessitates planned load shedding by many utilities to maintain
the grid in a healthy state. The all India average shortages during 2001-2002 were
7.8 percent in terms of energy and 13 per cent in terms of peak load. Based on the
projections of demand made in the 16th Electric Power Survey, additional
generation capacity of over 1,00,000 MW needs to be added to ensure 'Power on
Demand by 2012. This amounts to nearly doubling the existing capacity of about
1,00,000 MW. In other words, the achievements of more than five decades need to
be replicated in the next decade. Apart from massive resource mobilisation, the
task of identifying a basket of techno-economically viable and environmentally
sustainable projects in it is a daunting challenge. India is endowed with vast
energy resources, both conventional and non-conventional Meeting the additional
capacity demand of over 1,00,000 MW requires taking advantage of all
economically viable sources of energy in an optimum manner within the energy
mix. In the new millennium, environment compulsions on one hand and the need
to achieve energy security on the other demand thrust on development power
from non-conventional resources. The Ministry of New and Renewable Energy has
recently announced a National Renewable Energy Policy. The policy envisages
capacity addition of 10,000 MW during the time-frame 2002-2012.
1.2.2. Fossil fuels and hydro-electricity will continue to play a dominant role in the
country's energy sector in the next few decades. However, fossil fuel resources are
limited, and nonrenewable energy sources, therefore, need to be used prudently.
At the same time the existing technologies of production, transmission and
distribution of electricity as well as end-use have inherent inefficiencies. It is,
therefore, imperative to diversify the country's energy supply. The future
requirements of electricity are likely to be for decentralised, people-managed
systems. This would, however, call for a major transition in terms of technologies,
organisation and attitudes. Renewable energy is seen as an effective option for
ensuring access to modern energy services. In addition, it also provides a degree
of national energy security.
1.2.3. Today India is in the forefront of international effort to harness renewable energy
resources and has one of the largest and most broad-based programmes in non-
conventional energy. There is significant potential in India for generation of power
from renewable energy sources such as wind, small hydro, biomass and solar
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 10 of 111
energy. Special emphasis has, therefore, been given on the generation of grid
quality power from renewable energy sources.
1.2.4. Over 3700 MW of power generating capacity based on renewable energy sources
has already been installed in the country. This constitutes about 3.4 percent of the
total installed capacity. This has largely come about through private investment
The Prime Minister has already announced a goal of 10 per cent share for
renewable, or 10,000 MW, in the power generating capacity to be added in the
next twelve years. The notable initiatives include a biomass resource assessment
programme with a view to bringing out a Biomass Resource Atlas for India;
a programme to identify fast track projects and accelerate their financial closure.
1.2.5. As per the 16th
Electric Power Survey of India conducted by CEA, New Delhi and
published during September 2000 the projected power requirements for A & N
Islands is detailed below;
Categories 2001-02 2002-03 2003-04 2004-05 2006-7 2011-12 2016-17
-------------------------Estimated---------------------------
Energy
Consumption(MU)
119.31
130.48*
142.41
157.00
236.00
374.00
591.00
Requirement(MU) 148 161 176 194
Demand
Peak Load (MW) 31 33 37 40 49 70 111
Capacity
required (MW) 44 47 53 57 70 100 158
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 11 of 111
1.2.6. To meet the energy requirement as detailed above, present development model
for generation of power followed so far has been based on excessive
consumption of conventional fossil fuels, diesel. Dependence on this model has
endangered the environment and ecology with disastrous consequences to
natural resources and has proved to be highly expensive and unviable. It is
estimated that, at this rate well before the end of the new millennium the world will
run out of conventional source of energy. Environmental degradation, socio
economic pressures and geo political tilts would only aggravate the situation.
Already the impact is visible in the peak atmospheric pollution leading to climate
change as manifested in global bio diversity and ecology of different regions
1.2.7. It is in the above background, the renewable sources of energy have attracted
global attention and evoked interest among planners, policy makers, economists
and environmental activists as a viable option to achieve the goal of sustainable
development. If the current interest in renewable source of energy gets
concretized into projects to tap their enormous potential, the energy generation in
21st
century can be expected to move away from fossil fuels.
1.2.8. The commitment has been received from all nations in the Kyoto Protocol to
pursue the goal of sustainable economic development. Following this the MNCs
and Multilateral agencies like World Bank and Asian Development Bank have
pledged to provide resources necessary to achieve the goal. Carbon free energy
technologies, which do not depend on fossil fuels, are emerging as viable
commercial proposals and gives exciting opportunities for potential investors
1.2.9. The Ministry of Power (MoP), Ministry of New and Renewable Energy (MNRE) and
Government of Andaman & Nicobar have decided to promote biomass based
sources of energy, recognizing the need to explore alternatives to fossil fuels,
socio-economic aspects and the environmental benefits associated with such
Projects. Andaman & Nicobar energy scenario calls for the optimum management
of all available resources in order to attain the national goals of development and
social equity. A well-balanced energy mix, in which all energy resources are
utilised on the basis of their economic value and environmental costs, is essential
for sustainable development Renewable energy resources are non-depleting, can
effectively meet energy demand and are environmentally benign.
1.2.10. Biomass based Projects offer several other benefits such as avoided use of fossil
fuels, modular nature and efficient generation of heat and power, improved local
and general security of supply, increasing cost effectiveness, and reduced need
for waste disposal. The environmental benefits associated with these projects
include reduction in greenhouse gases and protection of the ozone layer.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 12 of 111
1.2.11. Since biomass fuels will be used in this power plant, this plant qualifies for MNRE
subsidy on capital cost and interest on loan.
This plant will also qualifies for CDM benefits, since the biomass fuels will be
used instead of fossil fuels, thereby generate carbon credits.
1.2.12. PROMOTERS
M/s. Suryachakra Green Fuels Private Limited [SGFPL] was promoted by
Sri S.M. Manepalli & Associates.
Dr. S. M. Manepalli hails from an agricultural and business family from Bhimavaram,
West Godavari District, Andhra Pradesh and is a qualified medical doctor. During the
period 1974-87, he was engaged in the rice milling business and operated 6 rice mills
belonging to the family. He had served as the President of Bhimavaram Rice & Oil
Merchants Association during 1983-87. He had also operated Deep-sea Foreign
Fishing Vessels on Charter basis during 1987-92.
Since 1992 he was engaged in Aqua-culture Business. During this period he was also
engaged in Construction & Operation of Prawn/Fish Tanks, Hatchery, Feed Mill &
Processing Plants
Inspired by the liberalization policies of Govt. of India, during 1995 he diversified his
business interests by setting up power generation plants following the privatization of
power sector. He promoted Suryachakra Power Corporation Limited (SPCL) for setting
up of 20 MW power plant in A & N islands.
At present, Suryachakra Group has been operating 4 units of 10 MW biomass power
plants at various places in India.
Mr. M. Seshavatharam is a graduate in commerce. He hails from business community.
He has to his credit varied business experience. He has gained experience particularly
in power projects, agriculture and fresh water fish culture. He is the Director on the
Board of M/s. Suryachakra Power Corporation Limited, a company which established a
20 MW Independent Power Project at Port Blair in Andaman & Nicobar Islands. He is
also a Director in various other Companies whose main business is generation of
Power.
Mr. K. Vijay Kumar is Bachelor of Engineering (Electrical). He had worked in APSEB/
APGENCO as Asst. Engineer to Superintending Engineer. He has over 30 year of
experience.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 13 of 111
Mr. K. Satyanarayana is a graduate in engineering and having rich experience in
development of power projects and engineering related projects. He has over all
experience of 30 years in various fields. He had worked with reputed firms in India. He
also worked in Malaysia and Singapore for several years in engineering related projects
1.2.13. About the Consultants
Aquatherm Engineering Consultants (India) Pvt. Ltd., is engaged in the consultancy
services for various types of power plant in India and abroad. The field of operations
involved offering total consultancy services right from project feasibility stage to
performance testing stage.
The Company offers services like preparation of feasibility report, Detailed Project
Report, Preparation of detail technical specification for the equipment to be procured,
preparation of detail engineering drawings wherever required by the client, purchase
management and project management.
The company assists the client in floating of tenders for procurement of major
equipment and helps them in evaluating the offers to arrive at the best choice.
Wherever necessary detailed engineering, drawings are prepared on behalf of the client
for the equipment, which are to be directly procured by them.
The company offers necessary support to the client in project monitoring in order to
complete project on schedule and co-ordinate the activities with the main equipment
suppliers to achieve the guarantee performance figures. The Company is involved in
the above mentioned activities in thermal power plant namely coal based, combined
cycle plant, engine based power plant, Bagasse fired sugar biomass plants, biomass
based and Hydro power plant.
Company had successfully relocated 63.75 MW coal fired thermal power plant from
South Africa to Chennai, Tamil Nadu. The plant has been running satisfactorily from
1999 with a PLF of 95% plus. Aquatherm is also currently executing biomass power
plant in Tamil Nadu with capacity ranging from 5 MW to 18 MW. Aquatherm is
executing a 60 MW Combined Cycle Power Plant using natural gas as fuel in Tamil
Nadu.
Aquatherm Engineering has built up substantial experience in power plant engineering,
having been responsible for over 450 electric generating plants completed or in
progress, with a total value of engineering projects handled over Rs.7000 Crores
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 14 of 111
Power Generating Experience
Steam Power Plants - 36 nos. upto 660 MW rating
Overseas Projects - 23 nos. upto 190 MW rating
Biomass Projects - 19 nos. upto 22 MW rating
Cogeneration Projects - 12 nos. upto 27.3 MW rating
Gas Turbine - 7 nos. upto 59 MW rating
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 15 of 111
SECTION – 2
EXECUTIVE SUMMARY
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 16 of 111
2. EXECUTIVE SUMMARY
Project : 2.28 MW Biomass Power Project
Location
Plant : Mithakhari village, Ferrargunj Tehsil
union territory : Andaman & Nicobar
Promoters : Suryachakra Green Fuels Private Limited.,
Hyderabad.
Report Prepared by : Aquatherm Engineering Consultants (India)
Pvt. Ltd., Chennai.
The scope of this detailed project report includes the following:
Justification for installation of a power project at Mithakhari village, Ferrargunj
Tehsil, Andaman & Nicobar Islands.
Confirmation regarding the maximum power generation capacity possible,
considering the quantum of Biomass / alternate fuel availability for sizing the
Turbo-alternator
Basic design of all main and auxiliary systems based on selection of optimum
alternatives / configurations.
Preparation of plant overall layout covering all buildings and equipment.
Proposals for meeting the pollution control board norms.
Outline of project implementation plan.
Plant operation philosophy and manning schedule for Operation and
Maintenance.
Preparation of capital cost estimate and financial analysis.
The tariff fixed by Andaman & Nicobar Government for purchase of power from
biomass based power plant is Rs. 9.81 per unit. The same is considered for the
financial calculations.
The power plant will use Coconut, arecanut, red oil palm, cashenut, Hybrid Napier
Grass, cereals like paddy, maize, pulse, napier grass and wood chips. The annual
requirement will be approximately 18,754.56 MT/year. The availability of biomass
in the area covering 50 kms radius is more than 183,000 tons.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 17 of 111
The water requirement of the plant will be 6.74 m³/hr. The water requirement will
be met from the bore wells to be dug in the project site.
The generated power will be exported to grid through 33 kV lines. The power will
be evacuated to the Electricity Department sale through UT grid by stepping-up
the generated power to 33 KV.
The project cost works out to Rs.1495.18 lakhs including interest during
construction and working capital margin.
The promoters are contributing Rs 448.55 lakhs of the project cost as equity and
the balance Rs 1046.63 lakhs will be met by term loans from financial institutions.
The moratorium is considered as 18 months including construction period
The results of the financial analysis are as follows:
IRR– Internal rate of return : 14.54 %
DSCR (debt service coverage ratio) : 1.40
Payback period : 7 years
Return on equity : 19 %
The project is techno economically viable, based on the various technical and
financial analyses for generating power using biomass, and it is recommended to
implement the project.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 18 of 111
SECTION 3
PROJECT AT A GLANCE
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 19 of 111
3. PROJECT AT A GLANCE
3.1. PLANT DETAILS
Name of the plant : 2.28 MW Biomass Power Plant.,
Andaman & Nicobar.
Site Address : Mithakhari village, Ferrargunj Tehsil,
Andaman & Nicobar Islands
.
3.2. TECHNICAL DETAILS OF THE PLANT
Boiler data:
Boiler capacity at MCR (100% load) : 12.50 tons / hr
Steam pressure at Superheater Outlet : 44 Kg/sq.cm (a)
Steam temperature at Superheater outlet : 450 Deg C
Design fuels : Coconut, arecanut, red oil palm,
cashew nut, Hybrid Napier Grass,
cereals like paddy, maize, pulse
and wood chips
Turbo generator data:
Rated capacity of the turbine : 2280 kW
Steam pressure at the TG inlet : 42 kg/sq.cm (a)
Steam temperature at the TG inlet : 445 Deg. C
Type of turbine : Bleed cum condensing
Generator voltage : 11 kV
Condenser type : Air Cooled
Water:
Water sources : Ground water.
Water requirement : 6.74 m³/hr
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 20 of 111
Power evacuation:
Voltage : 33 kV
Nearest Substation : Garacharma
Fuel handling : Series of Belt and Slat Conveyors
Ash handling
Bottom ash : Manually handled
Fly ash : Dense Phase Ash Handling System
Chimney : Steel
DM plant capacity : 1.5 m³/hr
Biomass proposed to be used : Biomass from Coconut, arecanut,
red oil palm, Hybrid Napier Grass,
cashenut, cereals like
paddy, maize, pulse and wood
chips. Densification of the above
material in to Pellets & Briquettes.
Backward integration of biomass
Yearly consumption in Tons : 1st year – 16,410.24 MT/year
2rd year onwards – 18,754.56
MT/year
Radius of Collection : Largely Andaman Group of Islands.
A&N Islands
Fuel GCV : 3800 kcal/kg
Cost of Biomass Rs./MT : 4850 (Total Fuel price Rs.5338/MT)
Supplementary fuels : Diesel
Operating Hours : 7920 hours with PLF 70% on 1st year,
7920 hours PLF 80% on 2nd
year
onwards
Electricity output
a. Auxiliary consumption : 14 %
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 21 of 111
b. Exportable Power : 1st year 110.88 lakhs kwh
2nd Year 126.72 lakhs kwh
Financing : Debt Equity ratio – 70:30
Equity : 448.55
Debt : 1046.63
3.3. EXCERPTS FROM BIOMASS ASSESSMENT REPORT
3.3.1. Availability of Biomass Fuel in the Command Area
M/s. Aquatherm Engineering Consultants India (P) Ltd., a reputed renewable energy
consultants conducted biomass resource assessment study in the islands and locations
surrounding the proposed plant location at Mithakhari village, Ferrargunj Tehsil in South
Andaman Islands and assessed the availability of surplus biomass residues consists of
Coconut, arecanut, red oil palm, Hybrid Napier Grass, cashenut, cereals like paddy ,
maize, pulse and wood chips.of 1,83,000 MTs. It may be noted that in the islands, the
length of the Andamans is 467 km with an average width of 24 km, whereas the
maximum width is 52 km. The length of the Nicobar Islands is 259 km with a maximum
width of 58 km. The estimated availability of surplus biomass is 1,83,000 MTs, which is
much more of the annual biomass requirement for the 2.28 MW plant.
Therefore, the available source of biomass was considered as Andaman & Nicobar
Islands.
However, it may be noted that most of the population is settled in and around Port Blair.
1. Major sources of biomass are the agricultures are a significant source only in certain
areas, especially in the Nicobar group of islands. 2. The difficulty, however, in the case of the above biomass, is unlike in the mainland,
where these wastes have some commercial value and therefore a collection, transporting and a trading channel, none exists in these islands. Therefore, a mechanism to collect these wastes is required.
3. In addition, any collection mechanism has to take into account accessibility of the
area or island. However, in general, biomass from agriculture is concentrated in a narrow area within an island.
4. In Great Nicobar, where some potential exists for using the biomass generated from
coconut and arecanut plantations, the farmers and traders are more interested in
copra dryers than in producing power from waste.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 22 of 111
A detailed assessment of the identified sources of biomass generation – agriculture,
plantation and timber cuttings and saw dust has been made. The surplus biomass
availability has been ascertained from the following observations:
Surplus Biomass Availability all Sources
About 1.1 to 1.4 kg can be converted into 1 unit of power generation. Therefore, the
available surplus biomass of 1,83,166 MTs can support a power generation unit of an
installed capacity of 17.5 MW. Based on the estimates Suryachakra Green Fuels Pvt.
Limited proposes to install 2.28 MW biomass based power plant in the islands by
supplementing the biomass with the following net fuel ratio:
Particulars % Net Fuel Ratio by
weight
Bio mass 98.7%
Diesel 1.3%
The woodchips may be imported from main land or from neighboring countries such as
Malaysia, Indonesia etc. Therefore, it may summarize that the availability of biomass is
not a constraint for the setting up of a 2.28 MW biomass power plant at Mithakhari
village, Ferrargunj Tehsil in South Andaman Islands. The cost of biomass collection,
dealer commissions and transportation to the site has been estimated to be Rs.5250
per MT. The estimation of fuel requirement based on 1.1 to 1.4 Kg of fuel per unit of
power generation has been arrived as Rs.9.81 per unit generation.
S.No Source Quantity [MTs]
1 Crop residue 57135
2 Paddy husk 5832
3 Coconut fronds 56610
4 Coconut husk 40000
5 Coconut shells 10680
6 Arecanut 2589
7 Timber lops /saw dust 10320
Total 1,83,166
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 23 of 111
SECTION 4
SALIENT FEATURES OF THE SITE
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 24 of 111
4. SALIENT FEATURES OF THE SITE
4.1. SITE LOCATION
The proposed biomass based plant at Mithakhari village, Ferrargunj Tehsil in South
Andaman Islands.
4.2. METEOROLOGICAL DATA
Height of the plant above MSL : meters
Maximum daily mean temperature : 32 ºC
Minimum daily mean temperature : 22 ºC
Maximum temperature recorded on a day : 33 ºC
Minimum temperature recorded on a day : 21 ºC
Max. Relative Humidity : 87 %
Min. Relative Humidity : 74 %
Range of average rainfall received per year : 3176 mm
Nearest substation : Garacharma
4.3. WIND AND SEISMIC DATA
Basic wind speed as per IS 875 Part III
Seismic zone as per IS 1893
4.4. WATER SOURCE
Water is taken from the bore well in the plant site. The biomass power project will
require about 6.74 m³/hr. of water for normal plant operation.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 25 of 111
4.5. FUEL
The main fuel for this Biomass based project will be Coconut, arecanut, red oil palm,
cashenut, Hybrid Napier Grass,cereals like paddy, maize, pulse and wood chips.
Availability of biomass with in 50km radius from the site is 1,83,000 MTs per annum.
SGFPL can collect the required quantity of biomass from the command area.
4.6. POWER EVACUATION
The power generated from the Biomass power plant will be exported to Electricity
Department of A&N Government through the 33 kV grid.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 26 of 111
SECTION 5
SELECTION OF MAIN PLANT AND MACHINERY
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 27 of 111
5. SELECTION OF COMBUSTION TECHNOLOGY
A thermal steam power plant continuously converts energy stored in fuels (fossil /
biomass) into mechanical energy and ultimately into electrical power. Water is used as
the working medium to carry energy released by fuels and to convert the energy into
mechanical energy.
Upon transfer of energy released by fuels, water becomes high pressure and high
temperature steam, which is a very potential pack of thermal energy and is ready to do
any mechanical work. High potential steam exerts a mechanical force if passed against
an obstruction. Same principle is used in conversion of thermal energy into mechanical
energy in which the high pressure and high temperature steam is continuously passed
on to a series of obstructions in a guided manner and the forces exerted by steam on
each obstruction collectively forms the source of mechanical energy. After doing work
steam becomes expanded to a low pressure and low temperature steam and finally
condenses into water. Thus, energy acquired by the water is transferred into
mechanical energy. The mechanical energy generated by the working medium is
converted into electrical power according to Faraday’s laws of electromagnetism.
5.1. MACHINERY REQUIRED FOR DIRECT COMBUSTION TECHNOLOGY
Combustion of fuels, release of energy and energy transfer to the working medium i.e.
water takes place in the Boiler. Hence, the boiler requires fuel as input material and
delivers high pressure and high temperature steam. Thermal energy in the form of
steam is converted in to mechanical energy in the Steam Turbine. Electrical power will
be generated in the Alternator / Generator utilising mechanical motion of the steam
turbine. Hence, the proposed power plant mainly consists of the following elements.
A BOILER UNIT, which converts the energy available in fuels into thermal energy,
A STEAM TURBINE UNIT, which converts potential thermal energy into mechanical
energy,
An ALTERNATOR UNIT which converts mechanical energy into electrical power. Apart
from the above main equipment, number of other equipments as listed below are also
form part of the power plant.
Fuel and ash handling systems
Air Cooled Condenser
Aux Cooling Water system including Cooling tower
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 28 of 111
DM Water system and Air Compressor Plant
Electrical systems and Instrumentation system
Miscellaneous supporting machinery as required
5.2. PROCESS FLOW OF THE POWER PLANT
Raw fuel from the collection points will be transported to the power plant, where fuel will
be weighed and stored in fuel storage yard near boiler house. Fuel will be screened/
chipped/shredded and then conveyed to fuel bunkers located near the Boiler unit from
where it will be fed to the boiler by Screw / Rotary feeders. Quantity of fuel fed to boiler
will be controlled by variable frequency drives depending on steam requirements for the
power plant.
Fuel fed into the boiler will be burnt directly in the combustion chamber / furnace of the
boiler through combustion air from the Forced draught fan to generate high pressure
and high temperature steam. Steam generated by boiler will be supplied to steam
turbine where all the thermal energy available in the high pressure steam will be
converted into mechanical energy. Steam gets expanded over a series of specially
profiled blades attached to a cylindrical rotor thus creating a rotary motion. Steam
turbine is coupled to a Generator for converting mechanical energy into the electrical
energy. Power generated at the terminals of the generator will be evacuated and
connected to the grid through a series electrical equipment like Transformer, Switch
yard, Control gear and protection systems etc.
The high pressure & high temperature steam after utilizing the thermal energy in the
steam turbine becomes low pressure and low temperature steam with a small amount
of remaining thermal energy. In between one uncontrolled extractions will be at 3.5 ata
for Deaerator respectively. The final low pressure steam will be condensed in the Air
cooled condensing system. Air is blown over the finned tubes carrying the steam which
is condensed by cooling. Condensing system includes an Air Cooled condenser,
condensate extraction pumps, steam ejectors etc. The condensate will be collected in
the condensate storage tank and from the storage tank condensate extraction pump
sucks the condensate to send to the Deaerator cum feed water storage tank.
Condensate will be re-circulated to the condensate storage tank.
Condensate will be deaerated in the Deaerator to remove all dissolved non-
condensable gases and oxygen, which affect boiler performance in long run.
Temperature of the condensate will also be raised in Deaerator for better boiler
efficiency using the steam taken from turbine and the same will be stored in Feed water
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 29 of 111
storage tank. Feed water from the storage tank will be pumped to steam drum through
economiser, by means of two numbers of boiler feed pumps of which, normally one will
be working and the other will be standby. The feed water gets heated in the boiler to
form high pressure and high temperature super heated steam. Thus the thermal cycle
gets completed.
Combustion gases after maximum heat transfer in the boiler will be led to the exhaust
stack through ESP, Induced draught fan. Ash particles remaining in the exhaust gases
will be removed to the maximum extent in the ESP.
Ash generated in the boiler after burning the fuel will be collected in ash hoppers
located at the bottom of the furnace, economizer, air preheater & ESP. This ash will be
removed through pneumatic ash handling system to the ash silo which is also located
near the boiler. Ash from ash silo through ash conditioner will be transported outside the
plant using trucks. Complete system which includes pneumatic vessels, rotary air lock
valves, air compressor, air receiver, ash silo, ash conditioner etc. constitutes ash
handling system.
Other systems required for power plant include Auxiliaries Cooling Water System, DM
Plant, Instrument air compressor system etc. Cooling water enters the various coolers
provided for the auxiliaries and takes away the heat available. Heat acquired by the
cooling water will be again removed in the aux. cooling tower. Two numbers of cooling
water pumps will be used for pumping cooling water to the various coolers provided.
DM Water system is used to feed make up water for boiler to compensate the losses
associated with boiler operation. Only treated DM water has to be supplied for better
performance of the boiler and to avoid rusting of boiler heat transfer tubes. Makeup
water will be regulated to the deaerator through deaerator level controller.
5.3. SELECTION OF EQUIPMENT
For a biomass power plant various factors influence the selection and sizing of the plant
equipment, auxiliary equipment. Hence, for economical power generation, the following
shall be considered for the biomass power plant.
- Type of biomass fuels and combustion mechanisms
- Type and size of power plant
- Thermal cycles and Steam parameters
- Cost economics of power generation
- Each of these is described below:
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 30 of 111
5.4. TYPE OF BIOMASS FUELS AND COMBUSTION MECHANISMS
As the proposed biomass power plants are located in the densely forested islands, the
biomass available is in the form of Coconut, arecanut, red oil palm, cashenut, cereals
like paddy, maize, pulse, wood chips or empty fruit bunches. SGFPL has considered
the following fuel ratio for their proposed power plants.
Biomass : 98.70%
Diesel : 1.30%
The company proposes to import wood chips from neighboring countries Malaysia or
Indonesia or from main land.
The availability of biomass for the proposed plants is summarized as below based on a
biomass assessment study conducted.
Surplus Biomass Availability all Sources
The composition of the fuel (Napier grass) as per the mentioned ratio is estimated to
have the ultimate analysis details as given below:
ULTIMATE %Wt Biomass
Carbon 43.51
Hydrogen 6.76
Nitrogen 0.68
Sulphur 0.13
Ash Content 9.04
Oxygen as O (balance) 39.88
TOTAL 100.00
S. No Source Quantity [MTs]
1 Crop residue 57,135
2 Paddy husk 5,832
3 Coconut fronds 56,610
4 Coconut husk 40,000
5 Coconut shells 10,680
6 Arecanut 2,589
7 Timber lops /saw dust 10,320
Total 1,83,166
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 31 of 111
Type of fuel and its characteristics influence the selection of boiler and fuel handling
equipment. While selecting boiler, fuel characteristics are to be studied for their efficient
combustion. Another factor, which is to be considered is multi-fuel firing capability since
different fuels as indicated above will be used based on their availability. Various types
of combustion mechanisms are available for burning of various fuels.
- Packed fuel bed combustion using stokers (Travelling / Dumping grate)
- Cyclone combustion
- Fluidized bed combustion
- Pulverized fuel combustion
The travelling grate type of boiler will perform effectively for burning of variety of
biomass fuels & hence it is preferred. Hence travelling grate boiler is selected for this
project.
5.5. TYPE AND SIZE OF POWER PLANT
Type and size of the proposed power plant also influence the size of various plant and
equipment. The proposed biomass power plant is new and only an Independent power
plant generating electric power and exporting the same to the grid.
Hence, the proposed biomass power plant is not required any additional systems like
process steam systems other than its auxiliary consumption for deaerator.
5.6. THERMAL CYCLES AND STEAM PARAMETERS
Thermal cycle indicates the thermal processes that take place in a cyclic manner right
from the combustion of fuel till generation of mechanical output. Generation of electrical
power by using mechanical output from the cycle however will not be included in the
cycle. Any thermal cycle is designed for getting work output from heat input and vice
versa for which the basic requirement is a working fluid.
Number of thermal cycles are proposed for power generation out of which only one
cycle i.e. RANKINE CYCLE is being used for almost all thermal power plants. Same
cycle can be used for conventional power plants as well as biomass power plants. The
variables to work with in the Rankine cycle are temperature, pressure, dryness fraction,
heat quantity, quantity of work, rate of heat quantity transferred as related to the
temperature at which the heat transfer takes place.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 32 of 111
After selecting the cycle, next important task is the selection of proper steam
parameters. The following aspects shall be considered while selecting the steam
parameters.
Efficiency of the thermal cycle
Capacity of the Power Plant
Specific steam consumption of the steam turbine
Fuel requirement to generate the steam
It can be seen from the thermal cycle diagrams that higher steam parameters yields
better efficiency and reduce the steam consumption of the turbine. Hence, requires less
fuel to generate the required quantity of steam.
On the other hand, various power plant equipment like Steam turbine, boiler heat
transfer elements, High Pressure heater, boiler feed pumps, process piping, valves etc.
are to be selected to suit steam conditions. If high steam parameters are selected,
equipment shall be designed to withstand and operate under high steam pressure and
temperature conditions which require special types of materials for construction, special
manufacturing processes etc. which further increase the cost of the equipment. Hence,
the equipment cost is directly proportional to steam parameters.
The combinations of parameters that are being adopted in various power generating
equipment are given below.
44 kg/cm2 440 / 490C For power plants of capacity less than 3 MW
66 kg/cm2 490C For power plants of capacity more than 3 MW
87 kg/cm2 520C For power plants of capacity higher than 6 MW
After considering various aspects including cost economics of the power plant, it is
decided to have 44 kg/cm2(a) / 450°C for 2.28 MW Biomass power plant due to the
higher cycle efficiency and less fuel consumption. In view on the fuel that is being fired
(Coconut, arecanut, red oil palm, Napier grass, cashenut, cereals like paddy, maize,
pulse and wood chips) it is decided to have 42 kg/cm2(a) / 445°C.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 33 of 111
5.7. HEAT AND MASS BALANCE
As per preliminary thermal calculations for the proposed biomass power project, the
heat and mass balance is estimated as given below.
To generate 2280 KW of electrical power at the generator terminals,
approximately 11.50 TPH of steam of 42 ata / 445C is required at the Turbine
inlet. While calculating the main steam requirement, bleed steam from the turbine
is considered to meet the auxiliary steam requirements of ejectors and feed
heating in deaerator.
The exhaust steam will be condensed in ACC and pumped to the deaerator.
In deaerator, the condensate will be heated to by the auxiliary steam taken from
the turbine bleed.
The condensate after raising the temperature will be fed to the boiler economiser
by boiler feed pumps.
The approximate quantity of fuel required to generate high pressure and high
temperature steam at boiler outlet at 44 ata / 450C will be around 2.96 TPH. The
superheated steam from the boiler will be fed to the turbine. Depending on length
of piping system between the turbine and boiler, the steam parameters at the
turbine inlet are slightly less than the boiler steam parameters which are
considered as 42 ata / 445 C.
5.8. SIZING OF PLANT & MACHINERY
As already stated above, the power plant mainly consists of one number Steam turbine
generator set of 2280 KW generating capacity. Steam requirements for the Turbine
generator set will be met through one number Travelling grate boiler. The plant apart
from STG and Boiler units, consists of various auxiliary plants and systems like DM
Water system, Cooling water system, Compressed air system, Firefighting equipment,
Fuel and Ash handling systems, switch gear and switch yard etc.
Based on power generation capacity of 2280 KW various equipment are sized in
accordance with the standard engineering practices
The Steam Turbine considered for the power plant is of Condensing turbine with one
bleeds for feed water heating in Deaerator. The steam required for the turbine to
generate 2280 KW is around 11.50 TPH with inlet steam parameters of
42 kg/cm2, 445 C.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 34 of 111
The power rating of the generator is 2280 KW at the generator terminals with 10%
overload capacity. The speed of the generator is 1500 rpm and the generator is
designed according to IEC 45 to generate electrical power at 11KV, 50 Hz, 0.8 Power
factor.
Based on steam requirement for Turbine, one number 12.50 TPH boiler is selected.
The generating voltage at generator terminals is considered as 11KV. This will be
stepped up to 33 kV of A&N grid level. Accordingly all other electrical equipment like
grid transformer, switchyard etc. are sized.
It is proposed that the plant will be started using auxiliary power supply from the Diesel
Generator Sets purchased by the promoter for supply of startup power and
synchronized to the state grid. One number Diesel generator set is considered as back
up facility to supply power in case of total blackout. Subsequently, all auxiliaries will be
switched over to the internal power supply from the DG power supply. For this purpose,
one number auxiliary transformer is envisaged to step down the generated voltage level
at 11 KV to auxiliary consumption level of 415 V. It is estimated that about 280 KW at
415 V will be consumed by plant auxiliaries. The remaining 2000 KW net power is
available for export to the grid at 33 kV level.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 35 of 111
SECTION – 6
PLANT LAYOUT
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 36 of 111
6. PLANT LAYOUT
6.1. LAYOUT CONSIDERATIONS
6.1.1. Layout Design Issues
Major layout design issues, which have been considered while developing the proposed
plant layout, are as follows:
Available land for the Power Plant at site location
Topography of the land and contour limitations
Area requirements for various plant buildings, storage areas, admin building,
miscellaneous areas, etc.
Direction / velocities of wind.
Likely ingress of dust on to cooling tower, transformers etc. and precautions to be
taken to mitigate
Optimum men and material movement
Minimum length of high pressure piping
Disposal of ash
6.1.2. Area available & Layout
The area available for locating Power plant equipment and biomass storage is about
9.8 acres. Water reservoir is located in the plant. Sufficient free space is provided for
truck movement for the fuel & ash handling. The area for green belt development has
been considered.
Based on the above considerations and the area requirement, the preliminary plant
layout is prepared and presented in the report. The final layout will be frozen based on
the detailed discussions with the chosen vendors / contractors. The required land is
under acquisition from A&N Administration.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 37 of 111
6.2. ASH, EFFLUENT & SEWAGE DISPOSAL
6.2.1. Ash
At 100% capacity utilization of the proposed bio mass power plant, annual ash
generation is 1125 TPA. This ash will be collected in silos and given to the nearby users
for manufacturing bricks.
6.2.2. Effluent
Waste water from a bio mass power plant does not have any significant BOD / COD
level. The levels of liquid effluent and their treatment have been detailed in the
subsequent chapters.
6.2.3. Sewage
All sewage will be collected in a common septic tank and discharged as per accepted
norms.
6.3. PLANT LAYOUT
6.3.1. General
The project are located at Mithakhari Village, Ferrargunj Tehsil in South Andaman
Islands. These are nearer to Port Blair, where the majority of the population of the A&N
Islands is concentrated. There are various Government Departments, hospitals, schools
and banks, which are established in and around Port Blair.
6.3.2. Layout of Major Outdoor Equipment
The boiler will be designed for outdoor operation. The boiler will include an electro-
static-precipitator and a steel chimney. The self-supporting chimney will satisfy the
environmental norms and height of chimney is 35 meters.
The Fuel will be fed to the boiler via the conveyor system.
Ash handling will be Pneumatic handling system. Ash from furnace bottom,
Air Preheater, Economiser and ESP will be separately conveyed to the silos by pipes.
All water and storage tanks will be located outdoors. The tanks will be field erected and
constructed of carbon steel typically with an exception of DM tank, which will be epoxy
coated carbon steel. The tanks will be located to allow for optimal arrangements of
piping and will be accessible by road.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 38 of 111
The air cooled condenser & its auxiliaries will be located outdoors.
The aux cooling tower and the cooling water pumps will be located outdoors.
6.3.3. Biomass Power Plant Layout
The powerhouse will be approximately 26 m X 15 m in size, it will house the steam turbine
generator and its auxiliaries, the control room, the boiler feed pumps, the electrical
equipment room (distribution transformers, switchgear, motor control centres), battery
room, etc.
The boiler and its auxiliaries will be located in an area of about 27 m X 8 m (Including
bunker, fan, etc) Biomass will be fed through a fuel handling system from the open
storage yard.
The Air Cooled Condenser will be located in line with the turbine and will be located
outdoors.
It will require a space of about 19 m X 9 m. All the required auxiliaries will be located
adjacent to the ACC.
The makeup water for the boiler is supplied from a DM plant and DM storage tank. The
dry ash from boiler bed, Economizer & ESP will be conveyed pneumatically to the ash
silo. Ash will be collected in silos and dispatched through trucks or trolleys.
Proper air conditioning will be provided for the control room. For all other areas
adequate ventilation system will be provided. Special precautions will be taken for air
intake and exhaust for the emergency diesel area and for the battery room.
A suitable capacity overhead crane with a suitable capacity auxiliary hook will be
provided over the turbine generator bay. Its capacity will be adequate to provide lifting
capability to meet the needs of all steam turbine generator components. Roll up doors
will be located in the steam turbine area and the condenser area, to provide access for
maintenance. Single and double doors will also be provided throughout the building for
personnel access and maintenance of smaller equipment.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 39 of 111
6.4. APPROACH & INTERNAL ROADS
The site is located near to State highway. However approach road & bridges are to be
built. Required internal roads for movement of men and material will have to be
constructed within the plant area. The cost for this has been provided in the financials.
An administrative office, staff quarters, Switch Yard, security office, weigh bridge & toilet
blocks are located suitably. The operating engineers will be stationed at 5 m level in the
powerhouse.
Tentative locations of the Power plant equipment are shown in Preliminary Plant
Layout.
The steam turbine generator will be supported on a reinforced concrete pedestal. The
building superstructure will be RCC construction. Pitched roof will be provided to facilitate
drainage.
Control room will be in brick wall construction and the walls will be plastered. The
building structure will also be used to support piping, cable trays, conduits, etc. Suitable
coating materials will be used for interior and exterior surfaces. A special coating will be
provided in the acid / caustic soda storage area and battery room. The site area does
not have a high percentage of humidity and as such a suitable exterior coating may last
for ten years after which the building will be repaired.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 40 of 111
SECTION - 7
DESCRIPTION OF MECHANICAL SYSTEMS
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 41 of 111
7. DESCRIPTION OF THE MECHANICAL SYSTEMS
7.1. GENERAL DESCRIPTION
The proposed power plant will consist of 1 no. high pressure travelling grate type Boiler
of 12.50 TPH capacity with steam parameters at 44 ata, 450 Deg. C and 1 no. bleed
cum condensing steam turbine with a nominal capacity 2.28 MW. The steam pressure
at the inlet of the turbine will be 42 ata and temperature 445 Deg. C.
Apart from the boiler and turbo generator, the Biomass based power plant will consist
of fuel handling system, boiler feed water system, Air cooled condenser system,
electrical system, power evacuation system, control system, utilities like compressed air
system, ash handling system, fire protection system etc.,
7.2. BOILER SYSTEM
7.2.1. Boiler
The boiler will be designed for firing Coconut, arecanut, Hybrid Napier Grass, red oil
palm, cashenut, cereals like paddy, maize, pulse , wood chips, etc., The superheated
outlet steam will have a pressure of 44 ata and temperature of 450 Deg. C. The boiler
will be designed for outdoor installation. The boiler will have sub systems like pressure
parts, feeding system, firing system, draft system, feed water system, ESP and
chimney.
7.2.2. Furnace – Water wall System
The furnace which is fully water cooled is formed by carbon steel seamless tubes of
membrane wall construction connecting the respective top and bottom headers. The
bottom headers for all the walls are fed with water from mud drum through down
comers and bed evaporator headers. The heated water rises along furnace tubes to the
top headers which in turn are connected to the steam drum by riser pipes.
Necessary provisions will be made in the furnace for admitting the required quantity of
over fire air at various levels. Adequate number of inlet and outlet headers, with the
necessary stubs, commensurate with the arrangement of the furnace will be provided.
The down comers, supply pipes and relief tube sizing will be based on the circulation
calculations.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 42 of 111
7.2.3. Travelling grate assembly
The firing of biomass fuel will take place on the travelling grate unit. An electric drive
with VFD control or an hydraulic drive will be driving the grate. The speed of the
travelling grate is decided so that sufficient time is available for the fuel to burn on the
grate. The main combustion air is supplied by FD fan. The hot air is admitted in the
plenum below the grate. The ash remaining on the grate is dumped on one side of the
furnace which is connected to the ash hopper. The temperature in the grate zone will be
around 800 – 8500 C.
7.2.4. Boiler Drums
The boiler will be provided with one steam and one water drum and drums will be of
fusion welded type. Both the drums will be provided with Torispherical / Semi-
Ellipsoidal dished ends fitted with 320 x 420 MM elliptical man ways at either end. The
man way doors will be arranged to open inwards. The drum shell, dished ends and the
man way doors will conform to SA 515 Gr. 70 or equivalent material specification. The
steam drum will be liberally sized to assure low steam space loading, with adequate
space to accommodate the internals. The drum design pressure will have a minimum
margin of 6% over drum operating pressure.
The steam drum will be provided with internals of proven design, shall be bolted type,
and of size that will enable removal through the man ways. The system of internals
consisting of the primary and secondary separators will ensure steam of highest purity
with dissolved silica carry over limited to a maximum of 0.02 ppm, at all loads of the
boiler. All the components of the internals, except the dryer screens, shall be carbon
steel and the dryer shall be of SS 304.
7.2.5. Bank Tubes
The bank design will be of inline arrangement and the tube spacing will enable easy
removal of the tubes in case of any failure. The bank tubes will be expanded into both
the top and the bottom drums, and the tubes after expansion will be bell mouthed.
There will be adequate approach space to the tubes of the bank for maintenance.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 43 of 111
7.3. SUPERHEATER SYSTEM
The superheater (SH) system will be of Two(2) stage design with interstage
desuperheating to achieve the rated steam temperature over 60 to 100% load range.
The superheater will be of convection or a combination of convection and radiation type
arranged to give the minimum metal temperature. The superheater pressure drop, the
inlet and outlet header sizing, arrangement and sizing of their respective inlet and take
off connections will be so as to give minimum unbalance and the tube element material
selection will be based on the actual metal temperature calculations.
7.4. ATTEMPERATOR SYSTEM
The attemperator system to control the temperature of the final superheater outlet
steam temperature within the specified value will be provided in between the two stages
of the superheaters. The interstage attemperator will be drum coil type with single 3
way control valve.
The desuperheating system will be complete with all required control valve, bypass,
piping and supports, etc.
7.4.1. Economiser
The Economiser will be located immediately downstream of the boiler bank. The design
will be of bare tube construction with inline, counter flow, and drainable arrangement.
The Economiser will be designed for an inlet feed water temperature of 105°C. The coil
arrangement will take care of proper calculated end gaps to avert gas bypassing and
the consequent erosion of the element tubes. Tubes will be of seamless type.
7.4.2. Air Heater
The Air heater will be arranged as the last heat recovery section downstream of the
economizer. The Air heater will be recuperative type with flue gas flowing inside the
tubes and the combustion air flowing over the tubes. The air heater will be arranged
with the tubes in the vertical direction. The tubes except those required for staying
purposes will be expanded into the tube sheets on both ends.
The air heater arrangement will be provided with adequate access for replacing the
tubes. Considering the high moisture in the flue gases, suitable precautions should be
taken to prevent the tube corrosion at the air inlet side of the air heater. The Low
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 44 of 111
Temperature bank of the Air preheater will be designed to prevent corrosion and the
cold end material of the air heater tubes will be Carbon Steel.
7.5. SOOT BLOWING SYSTEM
The boiler will be provided with a complete system of soot blowers to effectively
dislodge deposits from the heat transfer areas. The soot blowers will be motor operated
with steam, taken from the outlet of Super heater First stage, as the cleaning medium.
7.6. FUEL FEEDING SYSTEM
The Boiler will be designed for firing Coconut, arecanut, red oil palm, cashenut, cereals
like paddy, maize, pulse, wood chips and a combination of the available biomass fuels
independently or in combination. The bunker will have suitable lining, inerting system,
isolation gates, manholes, vibrators etc. Fuel is extracted from the bunker by drag
chain feeders and fed into the bed by mixing nozzles, cross and fuel nozzles. The fuel
is transported by the required number of feeders which transfer the fuel on to the
travelling grate through suitable chutes.
Drag chain feeders will be provided with variable frequency drives. Isolation gates will
be provided at Bunker outlets. Surge hoppers will be provided in between the Bunker
chute outlet and drag chain feeders’ inlet.
Fuel feeding system will be designed in such a way that there are no bends on the feed
chutes. This avoids choking of fuel in the fuel line and improves the flow ability.
High pressure air from SA fan (if required) is admitted above the grate area for aiding
combustion.
7.7. DRAFT SYSTEM
The draft system for the boiler will be suitable for producing a balanced draft with sub-
atmospheric pressure conditions in the furnace.
The boiler will have 1 x 100% capacity Induced Draft Fan, 1 x 100% capacity Forced
Draft Fan and One (1) x 100% capacity Secondary Air Fan (if required) making up the
complete draft system for the boiler. The FD fan flow will be varied according to the fuel
flow by a combustion control system. The ID fan will handle the flow of flue gas
corresponding to 12.50 TPH of steam generation.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 45 of 111
7.8. DUCTING SYSTEM
All ducts will be rectangular in cross section and will be of welded construction, properly
stiffened. All the air ducts will be fabricated from steel plates of minimum 5 mm thick,
and all flue ducts will be of minimum 6 mm thick. The duct plate material will conform to
IS 2062 Gr A. Carbon steel plates will not be used for ducting system if the operating
temperature of flue gas exceeds 425°C. The duct corners will be stitch welded
internally and full welded on the outside.
All ducts will be suitably stiffened and reinforced on the outside and designed to
withstand the pressures encountered.
Ducts will be sized considering a maximum velocity of 15 m/sec for hot air and flue
gases and 12 m/sec for cold air. The duct design consideration will include the
operating internal pressure, medium temperature, dead loads, ash loads, live loads,
seismic loads, expansion joint reaction etc.
Dampers, in the ducting system, will be provided as required, for the proper operation of
the boiler. All dampers will be of the `louver’ or butterfly type with the necessary
frames, shafts, blades, bearings, linkages, seals etc.
All fans will be provided with isolation dampers at the discharge ends for online
maintenance.
7.9. CHEMICAL DOSING SYSTEM
The boiler will be provided with a tri-sodium phosphate based High pressure (HP)
dosing system and a hydrazine and ammonia based Low Pressure (LP) dosing system.
The HP dosing system will continuously add the chemical to the boiler water and to
maintain the phosphate reserve and to remove silica from drum water.
The LP dosing is done to the feed water preferably in the deaerator storage tank to
scavenge the traces of oxygen and to increase the feed water pH.
7.10. ESP
The boiler will be equipped with ESP, which will remove the dust and ash particles from
the flue gas, before the ID fan could handle it. The efficiency of the precipitator will be
90% and the dust concentration at the outlet of the ESP will be not more than
50 mg/Nm³ with all fields working.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 46 of 111
7.11. CHIMNEY
The size and height of the chimney will be designed with sufficient capacity to cater to
the gas flow requirement and the local pollution control norms. The height of the
chimney will be about 35 Mts.
7.12. ASH HANDLING SYSTEM
The ash handling system is a dense phase pneumatic handling system. The ash
handling system is used to handle fly ash. Out of the total ash generated, the bottom
ash will account to about 30% while the fly ash will constitute about 70%.
7.13. BOTTOM ASH HANDLING SYSTEM
Bottom ash is the ash that is generated due to combustion of biomass on the travelling
grate and will be falling into the sump for submerged belt conveyor. The bottom ash
produced is handled by a submerged belt conveyor & dumped into a storage silo from
which vehicle will empty the collected ash periodically for disposal.
7.14. FLY ASH HANDLING SYSTEM
Fly ash is the ash carried over by the flue gases. The separation of fly ash is mainly
done in ESP, about 70% and about 20% is removed in the economizer hopper and air
heater hopper.
The suitable capacity of ash silo will be sized to hold the ash generated before it is
disposed.
7.15. TURBO-GENERATOR SYSTEM
7.15.1. Steam Turbine
The proposed Biomass power plant will have 2.28 MW turbo generator. The turbine will
be an bleed cum condensing type and running at high speed. The generator speed will
be 1500 rpm. Hence, the turbine will be coupled with the generator through a gear box,
if required.
Steam is admitted into the turbine through an emergency stop valve actuated by
hydraulic cylinders. The turbine speed is controlled by an electronic governing system.
The extraction pressures are arrived at based on the process requirements.
Accordingly, one bleed will be provided, one at 3.5 ata. The turbine exhaust pressure
will be 0.13 ata.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 47 of 111
The turbine will be preferably single cylinder, single exhaust, extraction, condensing
type. All casing will be horizontally split and the design will be such as to permit
examination of the blading without disturbing shaft alignment or causing damage to the
blades.
The design of the casing and the supports will be such as to permit free thermal
expansion in all directions.
The blading will be designed to withstand all vibrations, thermal shocks, and other
loading that may be experienced during service and system disturbances. The blades
will be machined from forged bars or die forged and the materials used will be
chromium steels consistent with proven experience and standards.
The glands will preferably of labyrinth type and sealed with same. A vacuum system
required by the design will be provided. All piping and components of shaft seal and
vacuum system will be sized for 300 percent of the calculated leakage. Steam leaving
the glands will be condensed in seal steam condenser. It will be possible to inspect and
replace the end seals without opening the casing and without damaging the thermal
insulation.
7.15.2. Bearings
The Turbine will be provided with liberally rated hydrodynamic radial and thrust
bearings. The radial bearings will be split for ease of assembly, and of the sleeve or
pad type, with steel shell backed, babbitted replaceable pads.
These bearings will be equipped with anti-rotation pins and will be positively secured in
the axial direction. The thrust bearings will be of the steel backed babbitted multiple
segment type, designed for equal thrust capacity in both directions.
A liberal flow of lube oil under pressure will be supplied to all the bearings for lubrication
and cooling.
7.15.3. Lubrication and control oil system
A pressure lubrication and control oil system will be furnished for the turbo generator
unit to supply oil at the required pressure to the steam turbine, gearbox, generator and
governing system. Oil in the reservoir will be maintained at an appropriate temperature
when the TG set is idle by providing suitable electric heaters and temperature controls.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 48 of 111
The oil system will include the following:
The oil system will include the Main oil pump, Auxiliary oil pump, Emergency oil
pump, Control oil pump, Oil storage and settling tank, Centrifugal type oil purifier,
Oil cooler and Oil filter.
7.15.4. Oil coolers
The oil coolers will be water-cooled with a duplicate arrangement and changeover
valves. The coolers will be of shell and tube type.
The coolers will be constructed in accordance with TEMA class C. The provided surface
area will be adequate to cool the oil with Inlet cooling water temperature at 32 °C even
with 20% of the tubes plugged.
7.15.5. Filters
Full flow oil filters will be used downstream of the coolers and will be piped in a parallel
arrangement with a continuous flow transfer valve. Filtration will be 10 microns nominal.
Filter cartridges will be designed for minimum pressure drop and suitable for maximum
discharge pressure of the oil pumps.
7.15.6. Oil reservoir
The interior of oil reservoirs will be de scaled and made rust proof with a permanent
coating. Reservoirs with top mounted equipment will have sufficient rigidity. All openings
for piping will be made dust and waterproof.
7.15.7. Oil purifier
A centrifugal type oil purifier will be provided for the removal of water, sediments and
other oxidation products. The purifier will be a separate package.
7.16. STEAM TURBINE GOVERNING SYSTEM
The turbine governing system will be electro-hydraulic or electronic type designed for
high accuracy, speedy and sensitive response. The electrical/electronic and hydraulic
component of the control system will be selected on the basis of reliability over a wide
range of operating conditions.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 49 of 111
All components used will be well proven to assure overall system reliability and will be
designed for easy and quick replacement when necessary. The governor will ensure
controlled acceleration of the turbo generator and will prevent over speed without
tripping the unit under any operating conditions including the event of maximum load
rejection.
The governor will also ensure that the unit does not trip in the event of sudden
frequency fluctuation in the grid and also sudden grid failure / load through off.
The governor will have linear droop characteristics with a suitable range for stable
operation and will have provision for adjusting the droop in fine steps.
The governing system will have the following important functions:
Speed control
Over speed control
Load control
Steam pressure control
7.16.1. Condensing Equipment – Air Cooled Condenser
The condensing plant will consist of one air cooled condenser. The condenser will be
designed for the maximum anticipated steam flow conditions under maximum output of
turbine. Exhaust steam from the turbine is conveyed into the fin tube heat exchangers
via the exhaust steam duct and the upper steam distribution ducts connected to it. The
cooling air supplied by the fan flows over the fin, tube bundles and removes the heat
from condensation.
The ambient temperature considered for the ACC design will be 33 Deg. C based on
the meteorological data provided by the promoter of the project.
2 x 100% capacity steam jet ejectors units’ along with all accessories for efficient and
trouble-free operation of the unit, 2 x 100% horizontal condensate extraction pumps
with, suction and discharge pipe, valves, temporary strainers, expansion joint and drive
motor will form a part of the ACC package.
Maximum heat load delivering rated 2.28 MW power.
Cleanliness factor of 85%.
ACC capacity shall be designed for an exhaust flow of 10.16TPH.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 50 of 111
7.16.2. Steam Ducting
A carbon steel steam duct form the turbine exhaust to the ACC inlet header shall be
furnished including expansion joints as required.
7.16.3. Steam Ejector System
Steam ejector shall be able to remove the specified quantity of dry air from the
condenser shell during operation. The capacity shall be as per recommendation of the
Heat Exchange Institute Standards.
Each of the condensate extraction pumps shall have 100% capacity and shall be
capable of handling the full condensate during the various conditions of operation.
Selection of pump capacity shall consider maximum steam flow condensed under worst
back pressure plus 10% leakage through recirculation valve and various condenser
drains coming to condenser.
7.16.4. Hot well Tank
The condenser shall be provided with a hot well made of fabricated steel having a total
storage capacity of at least 5 minutes with the water level at normal operating position.
Nozzles shall be provided in each half of the hot well for connecting the condensate to
the pump suction pipes. Suitable strainers shall be provided at the inlet of each
condensate pump. The hot well shall be provided with suitable access doors.
Hot well level shall be controlled by a control valve situated in the discharge line of the
condensate pump connected to deaerator and in unison with a recirculation control
valve. The hot well level control valve at condensate discharge shall be capable of
controlling the flow from full extraction to zero extraction of condensate flow. Water
System.
7.16.5. Water Requirement
Water is used as a cooling medium in the heat exchanger equipment in this power plant
such as lube oil coolers, generator air coolers etc. of turbo-generator. In addition, it is
used as make-up water for boiler after de-mineralization, dust suppression system in
fuel storage area, dust conditioning in dry ash handling system and fire -fighting system.
A small quantity of water will be required for drinking and sanitation for plant personnel.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 51 of 111
The break-up of make-up water for various consumers are given in Table 7-1.
TABLE 7-1 – MAKE-UP WATER REQUIREMENT
Sl. No. System Maximum make-
up water (m3 / hr)
1 Auxiliary Cooling System, Evaporation loss and Blow down 3.04
2 De-mineralised make-up water for boiler make-up 1.30
3 Drinking, sanitation & miscellaneous use 2.4
TOTAL 6.74
The total treated effluent from the plant is expected to be about 1 m3 / hr. and the same
will be used in ash handling system and green belt development.
7.16.6. Water Source
Total plant make-up water requirement is around 6.74 m3 / hr. and the same has to be
drawn from network of bore wells in the plant.
7.16.6.1. Water Supply System
The following facilities will be envisaged to meet the power plants water requirements:
a. Make-up water, pumping and piping system of capacity 6.74 m3 / hr. to meet the
make-up water requirements of the plant
b. Softener plant of capacity 3 m3 / hr. to cater the make-up water for auxiliary cooling
c. Auxiliary cooling water system of capacity 150 m3 / hr. for the turbo-generator, boiler,
and other auxiliary cooling loads.
d. Fire hydrant system complete with piping and hydrant accessories.
e. De-mineralised water system of 1.5 cu m/hr. to meet the make-up water requirement
of boilers.
f. Drinking water system.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 52 of 111
7.16.6.2. Water System
The water will be drawn from bore well in plant. The water will be stored in reservoir
having capacity of 600 m3. It will cater for plant requirement as well as fire protection
system.
The auxiliary cooling water system will consist of the following major items of
equipment:
i. Two (2) electrically driven horizontal centrifugal pumps of 150 m3 / hr. capacity
(one working and one standby) with associated drive motor.
ii. A compact FRP cooling tower to cool 150 m3 / hr. over a temperature range of
8°C - 10°C
Cold water from the cooling tower basin will be pumped by the auxiliary cooling water
pumps to the auxiliary consumers in the power plants. The hot water return from the
consumers will return to the cooling towers for cooling and recirculation. About
3.03 m3 / hr. of make-up water will be added in the cooling tower basin to compensate
the evaporation, drift and blow-down losses.
It is envisaged to provide for a side stream filter for recirculation of water in the Cooling
Tower Basin along with necessary chemical treatment.
In order to meet the requirements of treated water for the cooling tower a softener is
provided which will produce soft water .
7.17. WATER TREATMENT PLANT
To cater the make-up water requirements of the boiler, it is proposed to install a
DM plant having capacity 1.5 m³/hr. The DM plant shall have a regeneration time of
4 hours/day.
7.18. SERVICE WATER
The service water required for general wash, gardening, toilets etc., required for the
power plant will be taken from the outlet of the activated carbon filter in the DM plant.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 53 of 111
7.18.1. Drinking Water System
To meet the drinking water and sanitation requirement of plant personnel, the water
after activated carbon filter will be and chlorinated. The water will be stored in an
elevated HDPE tank of 2 cu m storage capacity, where from water will be supplied to all
consuming points.
7.19. FIRE WATER & FIRE PROTECTION SYSTEM
The following systems of fire protection are proposed to be provided for the power plant:
Hydrant system for the entire plant.
High velocity water spray (HVWS) system for transformers and lube oil tanks.
Carbon dioxide flooding system for the generator of the steam turbine.
Portable fire extinguishers.
The fire protection will basically comply with the Loss Prevention Association (LPA)
requirements.
7.19.1. Reserve Storage
A reserve storage of 262 cu m will be provided in the raw water storage tank to cater to
the water requirements of the fire protection system.
The suction nozzles of the fire water pumps in the common sump of the raw water
storage tank will be at a lower elevation compared to the suction nozzles of the plant
raw water pumps in order to ensure drawl of water from the reserve storage of
262 cu.mt. In view of the above, pump house elevation will also be suitably lowered at
the location of the fire water pumps as compared to the floor elevation at the location of
the raw water pumps.
7.19.2. Hydrant System
The hydrant system will comprise the following:
1. One motor driven and one diesel engine driven fire water pump. These pumps
will take the suction from the water storage tank. As per TAC regulations, the
above hydrant pump capacity will be adequate to cater to the total number of
Hydrant provided in the plant.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 54 of 111
2. One motor driven jockey pump of 10 m³/hr. capacity will be provided to keep both
the hydrant and HVWS system mains pressurised. These pumps will also take
suction from the raw water tank.
3. External fire hydrants in all areas of the power plant including boiler, TG, DM
Plant, control room, switch yard, canteen, stores, workshop and administration
buildings.
4. Internal fire hydrants in all storied buildings and structures such as Boiler
platforms, TG building, fuel handling building, canteen and administration
building.
7.19.3. High Velocity Water Spray System
The HVWS system is proposed to be provided for the Generator transformer and the
steam turbine lube oil tank. Water supply to the HVWS system will be provided by one
motor driven pump. Since the parameters for the HVWS system will be identical to that
of the hydrant system, the diesel engine driven pump described in the hydrant system,
can serve as a common standby for both HVWS system and hydrant system.
The HVWS system will consist of a number of high velocity water projectors mounted
on a pipe network around each transformer and steam turbine lube oil tank. Water
supply to each pipe network from the HVWS system mains will be through a deluge
valve. The HVWS system for the transformers will be of automatic type. In case of fire,
quartzoid bulb sensors mounted around the transformers will automatically actuate the
deluge valve on the spray water line. The HVWS system for the turbine lube oil tank will
be manually actuated.
7.19.4. Portable fire extinguishers
It is proposed to provide an adequate number of wall/column mounted type portable fire
extinguishers in various areas of the plant including the control room, administration
building, canteen, stores, workshop, pump house, etc. These portable fire extinguishers
would basically be of carbon dioxide and dry power type.
7.19.5. Waste Water System
The neutralized effluents from DM plant, blow down from cooling tower, boiler will be
admitted into the waste water tank and the final effluent will be pumped to the nearby
drain canal. The TDS of the final effluent is expected to be lower than the specified
norms.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 55 of 111
7.20. CRANES AND HOISTS
An electrically operated overhead travelling (EOT) crane with a span of 9.5 meters, with
the main hook lifting suitable capacity and an auxiliary hook lifting suitable capacity shall
be provided to facilitate erection and maintenance of the turbo generators and their
auxiliaries. The crane travel will cover the entire length of the turbo generator building.
7.21. COMPRESSED AIR SYSTEM
Instrument air is required for various pneumatically operated control valves in the boiler
and TG systems. The air is required to be supplied at a pressure of 5 to 7 Kg/sq.cm (g)
at the various consumption points. Instrument air from the air compressors will be dried
by heatless air drier making use of the dried air for regeneration of the drier medium
(desiccant).
Service air is required for cleaning of various areas of the plant. Accordingly, the service
air connections are proposed to be provided in the Boiler area, TG building, workshop,
DM Plant etc.
Considering the quantity of air required for the power plant, two (2) air compressors will
be required. These compressors will supply the instrument air and the required service
air.
7.22. AIR-CONDITIONING AND VENTILATION SYSTEM
In the power plant the control room will be air conditioned. The main control room
housing the control panels of boiler and TG, switch yard control panels and auxiliary
panel room housing the associated system cabinets will be located on the 6.00m floor
in the TG Building.
The above area will be air conditioned using window type/spilt type air conditioners.
The capacity of the air conditioning units will be decided based on the area of the room
and heat load dissipated in the room.
The following mechanical ventilation systems are proposed to be provided for various
buildings/rooms in the power plant.
Required no of roof exhausters of adequate capacity for evacuating the hot air
from the TG building.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 56 of 111
Suitable number of propeller type exhaust fans in the electrical switch gear room,
water pump house, DM Plant, filtration plant, workshop and stores.
Propeller type exhaust fans in all toilets in the power plant.
7.23. TECHNICAL DATA FOR MAJOR MECHANICAL EQUIPMENT
7.23.1. Boiler
Number of boilers : One
MCR capacity tph : 12.50
Steam pressure at SH outlet ata : 44
Steam temp. at SH outlet Deg. C : 450
Feed water inlet temp. Deg. C : 105
Boiler efficiency % : 70
Gas temperature at the outlet of AH Deg. C : 150 (Max.)
7.23.2. Turbogenerator
7.23.2.1. Steam turbine
Power rated kW : 2280
Inlet steam pressure ata : 42
Inlet steam temperature Deg. C : 445
7.23.2.2. Steam flow
Bleed:
Pressure ata : 3.50
Temperature Deg. C : 191
Flow tph : 1.04
Air Cooled Condenser
Steam flow : 10.16 t/hr
Number of Streams : One
Number on Modules : Two
Wind Wall : Provided
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 57 of 111
Condensate Extraction Pump & Steam Ejectors.
Type : Centrifugal
Capacity m³/hr : 10
Suction pressure ata : 0.13
Discharge pressure Kg/sq.cm g : 5.0
Number of pumps : 2 (2 x 100%)
Steam Ejectors : 2 (2 X 100%)
Starting Ejector : 1
Hot Well Tank : 1X100%
Hot well Pumps : 2 X 100%
Condensate Tank : 1 No
Aux Cooling water system
Type of cooling tower : Induced draft
Number of cooling towers : One (1)
Capacity m³/hr : 150
Cooling water supply temperature Deg. C : 32
Cooling water return temperature Deg. C : 41
Cooling water return pressure Kg/sq.cm : 0.5 (at the spray
nozzle)
Evaporation loss and blow down % : 2.0
No. of cells : Two
Boiler Feed Pumps
Number of pumps : two (2 x 100%)
Capacity m³/hr. : 13
Head MLC : 570
Type : Multistage
Centrifugal
Drive : Electric motor with
soft starter
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 58 of 111
Deaerator
Type : Spray cum tray
Capacity tph : 13
Outlet water temperature ºC : 105
Operating pressure ata : 1.23
Design pressure ata : 1.8 /Full vaccum
Steam inlet pressure ata : 1.3
Oxygen content in the outlet water ppm : 0.007
DM Water Plant
Capacity m³/hr. : 1.50
Regeneration : 4hrs/day
DM Water Specification:
Hardness : Nil
Chloride : Nil
Silica as SiO2, max. ppm : <0.02
Iron as Fe, max. ppm : Nil
Conductivity at 20 Deg.C max : 0.5 micro
siemens/cm
pH : 8.5 to 9.2
Oxygen (max.) ppm : 0.007
DM water plant will be complete with filter unit, SAC, SBA plant, degassers, pumps,
mixed bed exchangers, acid/alkali tank and pumps, raw water pumps etc.,
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 59 of 111
SECTION 8
DESCRIPTION OF ELECTRICAL AND I & C SYSTEMS
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 60 of 111
8. DESCRIPTION OF ELECTRICAL SYSTEMS
8.1. GENERATOR
The generator will be rated 2.28 MW, 11 kV, 50 Hz, 3 ph, 0.8 pf. The generator winding
will have class F insulation for both rotor & stator with temperature raise will be limited
to class B limits for both rotor & stator. The winding will be star connected. The star
point will be earthed through a resistor to limit the fault current. The generator will be
air-cooled with an air-air heat exchanger. The generators will have brushless excitation
system.
The line side & neutral side terminals of the steam turbine-generator will be brought out
through the terminal boxes located on both side of generator. The Line side generator
terminals will be connected to the LAVT panel incoming through 11kV XLPE FRLS
cable. From LAVT panel outgoing will be connected to 11kV switchgear panel by means
of 11kV XLPE FRLS cable. The LAVT cubicle will house necessary current
transformers, voltage transformers, lightning arrestors etc. Similarly, generator neutral
side terminals will be taken to the Neutral Grounding Resistor (NGR) Cubicle through a
short run of 11kV XLPE FRLS cable. The current transformers required for Protection &
Metering will be housed in the NGR & LAVT cubica. The neutral star formation will be
made in the generator only. The cubicle will house, motorized isolator, grounding
resistor, neutral current transformer etc.
The generator shall be of closed circuit air-cooled type housed in an IP55 (CACW)
enclosure and driven by steam turbine through a speed reducer, if necessary. The
necessary coupling and coupling bolts shall also form part of the supply. The generator
air cooler will be top mounted.
8.1.1. Stator
The stator frame shall be a single piece consisting of a cylindrical casing of welded
plate construction, reinforced internally in the radial and axial direction by stationary
web plates making the entire frame perfectly rigid. The stator winding shall be of the
double layer lap type with Class ‘F’ insulation.
8.1.2. Rotor
The generator rotor shall be forged from a single piece ingot of special alloy steel
carefully heat treated to obtain excellent mechanical and magnetic properties and
a comprehensive series of ultrasonic examinations on the rotor body shall be
done to ensure that absolutely no inadmissible internal defects are present and
that the material meets the quality standards.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 61 of 111
The design and construction of the rotor shall be in accordance with the best
modern practice and shall be fully described in the offer.
The insulation between turns of field winding shall be consistent class F
insulation.
The field poles shall be provided with adequate damper windings to ensure
stability under fault conditions and to meet I22 t value of 20.
8.1.3. Earth Terminal
Two numbers of Earth terminals shall be provided. The earth terminals shall be
designed to terminate Galvanized iron conductors. The size shall be as specified in
IEC 34-1.
8.1.4. Speed Regulation
The moment of inertia of the alternator together with that of the turbine shall be
sufficient to ensure stability and the speed regulation as specified covering turbine for
full load rejection.
8.1.5. Shaft
a) The generator shaft shall be made of best quality forged alloy steel, properly treated.
The shaft shall be of ample size to operate at all speeds, including maximum over
speed without vibration or distortion and shall be able to withstand short circuit and
other stresses without damage. To prevent the flow of harmful shaft currents damaging
the bearings, suitable shaft earthing shall be provided.
b) A complete set of test reports covering metallurgical strength, crystallographic and
ultrasonic and baroscopic tests performed in each shaft during various stages of its
manufacturing shall be furnished as also the complete specifications of the shaft forging
material and its design parameters such as stresses and critical speed.
c) The generator shaft shall have a suitably shaped flange for coupling to the
turbine/gearbox shaft. The coupling shall be forged integral with the shaft and the shaft
coupling shall comply with the requirements of IEC for shaft coupling. All coupling bolts,
nut and nut guards for coupling shall be furnished by the vendor. The alignment limit for
the shaft shall be as per the latest NEMA/DIN standards.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 62 of 111
8.1.6. Space Heaters
Suitably rated heaters shall be installed within the enclosure of the generator. Location
and the maximum temperature of the heaters shall be such that no damage can be
caused to any insulation. Heaters shall be suitable for operation on a single-phase
230 V AC supplies. A suitable thermostat controlled switch shall be mounted on or
adjacent to the stator frame for the switching of the heaters.
8.1.7. Excitation System
a) A brushless exciter shall be used and it shall be mounted on the out board end of the
generator frame. A static voltage regulator shall be included to control the voltage of the
synchronous generator by varying the current supplied to the field. Details of the
equipment shall be furnished along with the bid.
b) A self-excited static excitation system shall be provided. A high speed, fully tropicalized,
printed circuit, draw out type, automatic digital voltage regulator shall be provided. It
should be complete with necessary sensing PT’s, cable entries, cast resin type current
transformer, adjusting rheostats, and auto/manual and on/off selector switches. The
following meters of class 0.2 accuracy of size not less than 144x144 mm shall be
provided in the excitation cubicle and also in the unit control panel.
Exciter Field Current
Generator Field Current
Generator Field Voltage
Generator Terminal Voltage
c) The excitation system shall be provided with the following features:
Generator voltage control
Excitation current control
Excitation buildup during startup and fields suppression shutdown.
Limiter for the under excited range and delayed limiter for overexcited range.
Feature for parallel operation of the generator with the grid system incorporating
power factor control mode and feature for islanding operation during sudden grid
failure.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 63 of 111
d) The system offered shall have the following facilities:
Manual mode of operation
Two Auto mode of operation
Follow on mode to have bumped less transfer from one mode of operation to the
other.
Auto/Manual changeover facility shall be provided. For manual mode voltage
lower/raise pistol grip type spring return type switch shall be provided. Following
minimum alarms shall be transmitted to the unit control desk. The excitation system
shall have diode protection relays to detect failure of the Rotating Diodes.
AVR fault
AVR automatic changeover to manual
Diode failure
8.1.8. Accessory Equipment
a) The generator shall be provided with RTD’s (temperature sensors) installed in the stator
winding with leads, brought out to a separate terminal box.
These RTD’s shall be hooked up to the temperature scanner in the control panel.
Necessary vibration transducer, displacement transducers with transmitters shall be
provided which shall be hooked up to the control panel in the control room.
b) Adequately rated neutral grounding resistor shall be supplied, the resistor shall be
stainless steel edge wound type mounted in shielded safe enclosure. A current
transformer shall be provided for ground fault current measurements for protection. The
rating of the resistor shall be furnished.
c) Necessary surge capacitors and lightning arrestors shall be provided for generator
protection. The surge capacitors shall conform to the latest IS: 2834 and shall be rated
0.25 Micro Farad. The capacitors shall be suitable for indoor mounting and shall be
provided with built-in discharge resistor.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 64 of 111
8.2. SURGE PROTECTION EQUIPMENT
The surge protection equipment would comprise lightning arrestors with suitable
discharge characteristics to suit the generator insulation level in parallel with suitably
rated capacitor for smoothening the rate of rise of impulse voltage. The lightning
arrestors will be located as close as possible to the generator terminals.
Parameters of Generator:
8.3. POWER EVACUATION
The power generated from the proposed biomass based power plant will be evacuated
to the 33 kV grid through one number of 3.15 MVA, 11/ 33 kV generator transformer.
The generator is earthed through a resistor to limit to earth fault current to acceptable
limits so that generator core is not damaged. Hence this system will be of
non-effectively earthed type.
8.4. 11 KV SWITCHGEAR
The power generated from the generator will be fed to indoor metal clad 11 kV
switchgear panel through 11kV XLPE FRLS cable. The 11kV circuit breakers will be
draw out type which is either VCB or SF6 type.
Sl.No. Parameters Generators
1 Rating (KW) 2280 KW
2 Applicable Standard IEC-34
3 Rated power factor 0.8
4 Rated frequency (Hz) 50
5 Rated speed (rpm) 1500
6 Excitation system Brushless
7 Cooling Air cooled
8 Voltage 415V
9 Insulation class F
10. Enclosure IP-55
11. Efficiency @ rated output,
voltage and p.f. 0.8
97%
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 65 of 111
8.5. POWER TRANSFORMERS
One no Generator transformer of rating 3.15 MVA, 11kV / 33kV, Ynd1, Z = 6.25%,
ONAN cooled, with OLTC on the HV side which is having the voltage variation as
+10% to -10% range in steps of 1.25% will be provided for stepping up the voltage &
power evacuation. The HV side will be provided with bushings and LV side will be
provided with cable box for connecting the 11kV XLPE FRLS cable. The HV neutral will
be solidly earthed. Generator transformer will be interconnected with the grid for the
evacuation of balance power.
Technical Parameters of Generator Transformer
Sl.No. Description Parameters
1 Rating (MVA) 3.15 MVA
2 Type of cooling ONAN
3 No load voltage ratio (kV) 33 / 11
4 No. of phases 3
5 Impedance (%) 6.25%
6 Vector group Ynd1
7 Tap range 10% to -10% in steps of 1.25% on
HV side
8 Type of tap changer OLTC
8.6. 33KV SWITCHYARD
The 33kV switchyard shall be of single bus bar arrangement with one incomer from
Generator transformer and one outgoing feeder for connecting the 33kV grid. The
maximum fault level at the 33kV bus will be considered as 750MVA. However, as the
minimum available SF6 breaker rating for 33KV will be suitable for breaking capacity of
31.5 kA. The isolators will be horizontal centre pole double break type with motor
operated closing mechanism. The current and potential transformers will be of oil filled
type and will be suitable for the short time rating of 31.5kA. The switchyard will be of
outdoor type with galvanized steel lattice structures.
Equipments such as
− HV circuit breakers,
− HV isolators,
− Earth switches,
− Current transformers, electromagnetic voltage transformers,
− Surge arrestors etc.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 66 of 111
Parameters of 33kV Switchyard
Sl. No Parameters Ratings
1 Nominal System Voltage 33kV (rms)
2 Highest System Voltage 36kV (rms)
3 Basic Insulation Level 170KV (peak)
4 Symmetrical short circuit level 31.5 KA (rms), 1.0 sec.
5 Minimum creepage distance 31 mm/kV
6 Clearance: Phase-Phase
Phase-Earth
915 mm
610 mm
7 Section clearance 2800 mm
8 Ground clearance 3700 mm
Parameters of 33kV Circuit Breakers & Isolators:
Sl. No. Parameters Circuit Breakers Isolators
1 Type SF6 Horizontal centre break
2 Normal current rating 800 A 800 A
3 Breaking capacity
(rms)
31.5 KA -
4 Short time rating 31.5 kA rms
for 1 sec
31.5 kA rms
Parameters of 33kV Current Transformers & Voltage Transformers:
Sl. No. Parameters Current Transformers Voltage Transformers
1 Ratio 75/1/1/1/1 A 33kV/3 / 110 V/3 /
110 V/3 110 V/3
2 Short time
Rating
31.5 kA rms for 1 sec -
3
Burden & Acc.
Class
As required for protection and metering
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 67 of 111
Parameters of 30kV Lightning Arrestors
Sl.No. Parameters Ratings
1 Type Gapless (metal-oxide)
2 Rated voltage (kV rms) 30
3 Discharge current (kA) 10
Parameters of 11 / 0.433kV Auxiliary Transformers
Sl.No. Description Parameters
1 Rating 400KVA
2 No. of phases 3
3 Type of cooling ONAN
4 No load voltage ratio 11 /0.433kV
5 Percentage impedance 6.25%
6 Vector group Dyn11
7 Tap range +5 to -5% in steps of 2.5%on HV side
8 Type of tap changer Off-Circuit Taps
9 Neutral grounding resistance Solidly earthed
10 Quantity One(1) number
Parameters of 11 kV Switchgear
Sl.No. Description Parameters
1.0 Switchgear 11kV Switchgear
1.1 Type of Construction Indoor Metal Clad.
1.2 Bus bar rating 630A
1.3 Power frequency withstand voltage 28 kV (rms)
1.4 Impulse withstand voltage 75 kV(rms)
1.5 Short time rating 31.5kA rms 3 sec.
2.0 CIRCUIT BREAKERS
2.1 Type VCB
2.2 Rated current 630A, 31.5kA for 3Sec
2.3 Symmetrical breaking capacity 31.5kA (rms)
2.4 Rated short circuit making capacity 63kA (rms)
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 68 of 111
8.7. AUXILIARY POWER SUPPLY ARRANGEMENT
The total auxiliary load of power plant is estimated to be 250KW respectively.
The power plant load will be catered by one number auxiliary transformer of rating
400kVA, 11/0.433KV. The main single line diagram for the power plant, enclosed
indicates the auxiliary power distribution. The various auxiliaries of the power plant
would be supplied at the following nominal voltages depending upon their ratings and
functions:
415V, 3 phases, 3 wires effectively grounded AC supply for motors.
240V, 1 phase, AC supply for lighting, space heating of motors and panels, single
phase motors, etc.
230 V, 1 phase grounded AC supply for AC control circuits.
110 V, ungrounded DC supply for control and indication.
The power & motor control center (PCC) switchgear will feed the following MCCs /
Distribution boards:
Auxiliary MCC
Emergency MCC
Water system MCC
ACDB
Lighting DB
8.8. 415V SYSTEM
The 415V, 3phase, 4 wire power for the LT auxiliaries would be obtained from the
auxiliary transformer. The 415V PCC switchgear would be of metal enclosed design
with symmetrical short circuit rating of 65 kA/1 sec. The motor control centre (MCC) will
be designed for 50kA/1 sec short circuit rating.
All the power and motor control centers would be compartmentalized and would be of
single / double front execution and non-draw out design with all the circuit components
mounted on a sheet metal chassis. The circuit breakers would be air break type. Motor
starting would be direct on-line.
Motors rated above 160kW will be provided with HT supply, Motors rated 160kW and
below up to 200W will be provided with 3phase LT supply and motors rated below
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 69 of 111
200kW, lighting, space heater, AC control & protective devices will be provided with 1
phase LT supply.
The switchgear would be located in the control building.
Parameters of 415 V PCC:
Sl. No. Description Parameters
1.0 SWITCHGEAR
1.1 Switchgear Metal enclosed
1.2 Type of construction Draw out
1.3 Single / Double front Single front
1.4 Normal current rating (A) 800
1.5 Symmetrical short circuit current (kA
rms)
50
1.6 Dynamic withstand (kA peak) 110
1.7 Degree of protection IP-52
2.0 CIRCUIT BREAKERS
2.1 Type ACB
2.2 Normal current rating (A) 800
2.3 Symmetrical breaking capacity (kA
rms)
50
8.9. CONTROL & PROTECTION SYSTEM
8.9.1. Generator:
The following protections are proposed to be provided for the generators:
Differential protection
95% & 100% Stator earth fault protection
Loss of field protection
Negative phase sequence current protection
voltage restrained over current back-up protection
Reverse power protection
Over voltage protection
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 70 of 111
Under voltage protection
Under / over frequency protection
Rate of change of frequency
Instantaneous over current relay
Instantaneous over current earth fault protection
1st & 2
nd stage rotor earth fault protection
Over fluxing protection
Fuse failure
Low forward power protection
3.15 MVA, 11 KV / 33 KV Transformers:
The following protections are proposed for the above transformer:
Under voltage protection
Differential protection
phase over current protection
Instantaneous over current protection
I.D. M.T over load protection
I.D.M.T earth fault protection
REF protection
Over fluxing protection
Buchholz, oil and winding temperature protection
Over voltage protection
Thermal overload protection
Under / over frequency relay
Standby Earth fault protection
33 KV Line:
Under voltage relay
Instantaneous over current relay
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 71 of 111
I.D.M.T over current relay
I.D.M.T earth fault relay
Over voltage relay
Under frequency relay
Over frequency
Rate change of frequency relay
Directional over current relay
Directional earth fault relay
Vector surge relay
8.10. EMERGENCY POWER SUPPLY
To shut down safely during complete AC supply failure, certain important plant
auxiliaries will be provided with a reliable AC supply through a separate source. For this
purpose, 100 KVA, 415V quick starting, automatic mains failure diesel generator (DG)
sets will be provided. The diesel generators will feed power to the AC system,
emergency lights and UPS. When the AC supply is healthy, these essential loads will
be fed from the auxiliary transformer. When the AC supply fails, the DG set will start
and come in automatically and will feed the loads connected to the emergency
switchgear. When the normal AC supply is restored, these essential loads will be
manually changed over to the normal power supply.
8.11. DIRECT CURRENT SUPPLY SYSTEM
The Direct Current System (DC) is the most reliable source of supply in the power
station and will be used for the control and protection of the power plant equipment. The
DC system will be used for the following:
Electrical control of equipment and indications on the control panel.
Power supply to the essential auxiliaries of the power plant and turbines in case
of AC power failure.
Power supply to the following services in case of total AC power failure.
Communication system
The battery sizing will be done to cater to the following type of loads:
Momentary load for 1 minute
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 72 of 111
Emergency load for 2 hours
Continuous load for 10 hours
Under normal conditions, the battery will be on float charger. The float charger is
connected to a distribution board and meets the requirements of DC load. In case of
additional demand of load or AC supply failure, the battery will meet the requirements of
DC loads.
The boost charger will be designed to charge the fully discharged battery banks in
12 hours before putting it back on float charge.
A set of one 110V battery bank of suitable capacity with two float and boost chargers
and a direct current switch board will meet the DC load of the power plant. Similarly
another set of 110V battery bank suitable capacity with two float and boost chargers
and a direct current switch board will meet the DC load of the switchyard. The batteries
would be of stationary, valve regulated lead acid type, complete with racks, porcelain
insulators, inter-cell and interior connectors. The chargers would be of silicon rectifier
type with automatic voltage control and load limiting features.
8.12. UNINTERRUPTED POWER SUPPLY (UPS) SYSTEM
The instrumentation and control system will be powered by 230 V single phase AC
uninterruptible power supply. A battery bank of suitable capacity with associated two
100% float and boost chargers and inverters would be provided. This power supply will
be derived from 415 V AC supply through isolating transformer, rectifier and inverter
with dedicated battery bank for back-up power supply. Sufficient redundancy will be
built in the system. UPS systems each rated for 100% capacity and with each battery
having one (1) hour back-up will be provided. The type of batteries and chargers for the
UPS system would be similar to that described above for the DC system.
24 V DC power supply requirement will be derived from UPS bus by providing
necessary rectifier and 24 V DC distribution board.
8.13. LIGHTING
The power station lighting system would comprise the following:
8.13.1. Normal 240 V AC Lightning System
The lighting circuit in the normal 240 V AC lighting system would be fed through Main
lighting switchboard which in turn will be fed from main PCC. During grid/STG power
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 73 of 111
supply failure emergency diesel generator will cater power plant lighting. During the
total black out, before the DG is switched ON, emergency lighting will be provided for
critical areas like control room, stair case, boiler plot form, TG hall, etc. through UPS
power supply or portable DC lighting.
The proposed illumination levels for various areas are given below:
Area Illumination Level
Control room 300 lux.
Switchgear / MCC rooms 200 – 250 lux
Power house 200 lux.
Outlying areas 50 lux.
Transformer yard & switchyard 10 – 20 lux.
Boiler area 50 lux
Air/Gas compressors house, DM plant 200 lux
Workshop 300 lux
Canteen 150 lux.
Stores 100 – 150 lux.
Parking area and cycle stand 70 lux.
Battery room 150 lux.
Cable vaults 100 lux.
Administration building and office rooms 350 lux.
Roads 10 lux.
8.14. CABLING
All cables would be selected to carry the load current under site conditions, with
permissible voltage drop. In addition, high voltage cables would be sized to withstand
the short circuit current.
The following type of cables would be used:
For 11 kV generator system : 11 kV unearthed grade, single / multi-core, stranded
aluminium conductor, cross linked polyethylene insulated, screened, Aluminium wire
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 74 of 111
/ galvanized steel wire armored and overall XLPE sheathed FRLS cables conforming
to IS 7098 Part II.
For medium voltage and low voltage power cables: 650 / 1100 V grade, stranded
aluminium conductor, XLPE insulated, FRLS.
Control, protection, signaling and supervisory cables would be of 650/1100 V grade,
annealed high conductivity stranded copper conductor, PVC insulated and overall PVC
sheathed. Signaling and supervisory cables would be twisted pairs and screened
wherever required. The inner and outer sheaths of all the above cables would have fire
retardant capabilities.
Cables would be laid in steel ladder type cable trays, suitably supported in the control
building, STG building, other auxiliary buildings. In outdoor areas, cables would be laid
in racks/built-up trenches or would be buried directly underground depending on the
environment.
8.15. LIGHTNING PROTECTION SYSTEM
A lightning protection system would be provided as per IS 2309 and Indian Electricity
Rules. The protections would consist of roof conductors, air terminals and down comers
and would be provided for tall structures such as the STG building.
8.16. FIRE ALARM SYSTEM
A fire alarm system would be installed to provide visual and audible alarm in the power
station for fire detection at the incipient stage. This system would comprise manual call
points located at strategic locations in areas which are normally manned, and automatic
smoke and heat detectors located at important points such as the cable vault, the
control room, switchgear room etc., to detect fire at an early stage, and provide visual
and audible alarm.
8.17. FIRE CONTAINMENT
Strategic areas in the plant would be separated by adequately rated fire walls. All
openings for switchgears and cable entry would be sealed by fire proof seals to prevent
spread of fire from one area to another.
8.18. PLANT COMMUNICATION SYSTEM
In view of the high noise level in power plants, public address system is not
recommended. For effective communication in the plant, automatic dial type telephones
would be set up, having the following features:
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 75 of 111
8.18.1. Inter-communication Telephones
This system would comprise a telephone exchange and an adequate number of dial
type hand set stations located in soundproof cabins with suitable flashing indication on
top of if to indicate incoming call.
The hand sets in the control room would be provided with priority service facility to
enable them to have immediate access to any of the handsets even if the hand sets are
already engaged. A private automatic exchange for communication with outside parties
would also be provided.
8.18.2. Walkie-Talkie Sets
Walkie-Talkie sets would be provided for key personnel. This would, however require
special permission from the statutory authorities.
8.19. SAFETY EARTHING SYSTEM
A Safety earthing system as per IS 3043 & IEEE 80 consisting of a buried mild steel
conductor earthing grid would be provide for the power plant transformer yard,
switchyard and other outlying areas. These would be connected to the earth grids in
various buildings. The buried earthing grid would be further connected to earthing grid
would be further connected to earthing electrodes buried under ground and located at
representative points. The earth electrodes will be 100 mm diameter and 3000 mm long
13mm thickness Cast iron pipe and the main earth conductors will be 75 mm x 10 mm
G.I flats. The earth conductors when buried will be of mild steel and galvanized
wherever exposed to atmosphere.
8.20. INSTRUMENTATION AND CONTROL SYSTEM
The objective of this Detailed Project report is to outline the design philosophy to be
adopted for Control and Instrumentation (C&I) systems for 2.28 MW Biomass Power
Project.
The function of the instrumentation and control system would be to aid the operator in
achieving safe and efficient operation of the unit. The C&I system would be of the type
which normally relieves the operator of continuous duties and would take preplanned
actions in case unsafe trends or conditions develop in any regime of operation, i.e., start
up, shut down, normal working and emergency conditions. The design of C&I system
would be such so as to permit rectification of fault in the minimum possible time. Ease of
maintenance would be given due importance at system design stage.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 76 of 111
8.20.1 PLC CONTROL SYSTEM
The instrument and control system will be provided with a microprocessor-based PLC
and a few other analog instruments and control devices. It will perform the functions of
monitoring, control, alarm, protection and interlock, diagnosing, accident treatment and
maintenance guidance of the unit to meet all requirements at various operational
conditions.
The system will fulfill the following basic functions:
I. Monitor all major plant functions inputted to the PLC
II. Provide the operator with a central, universal and instantaneous means to monitor
the plant.
III. Collect and store data for trending of various plant functions. Keep track of
various plant events and record them for historical purposes.
IV. Perform required basic calculations for performance monitoring and optimization.
V. Produce operating logs for record purposes and post trip review reports.
VI. Provide sequence of events monitoring and reporting.
VII. Perform self-checking and self-diagnosis
Provide capability to add, delete and modify points from the system by means of
conversional mode
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 77 of 111
SECTION 9
ENVIRONMENTAL IMPACT AND POLLUTION CONTROL
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 78 of 111
9. ENVIRONMENTAL IMPACT AND POLLUTION CONTROL
The type of pollutions, which affect the environment, emanating from the biomass
based plant can be classified as follows:
Air pollution
Water pollution
Thermal pollution
Noise pollution
The pollutants generated from the biomass plant are as follows:
Dust and particulate matter in the flue gas
Fly ash from the hoppers
Furnace bottom ash
Effluent from water treatment plant
Sewage from the plant
9.1. CONTROL METHODS FOR AIR POLLUTION
9.1.1. Dust and particulate matters
The pollution control norm stipulates a maximum dust concentration of
100 mg//N.cu.mt. The proposed biomass based plant will have ESP, which will separate
the dust from the flue gas and has an efficiency of 90 %. The dust concentration in the
flue gas leaving the ESP will be maximum 100 mg/N.cu.mt.
The dust concentration level in the chimney will be periodically monitored. Corrective
steps will be taken, if the concentration is not within the acceptable limits.
9.1.2. Sulphur dioxide and nitrogen dioxide
The main fuels, for the proposed biomass based plant are Coconut, arecanut, red oil
palm, cashenut, cereals like paddy, maize, pulse and wood chips. The quantity of
sulphur di oxide in flue gas determines the height of the chimney. Owing to the
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 79 of 111
negligible amounts of sulphur and nitrogen in proposed fuel, little or no sulphur di oxide
or nitrogen di oxide is produced.
9.1.3. Fly ash and bottom ash
The ash content present in Coconut, arecanut, red oil palm, cashenut, cereals like
paddy, maize, pulse and wood chips is around 4.86 %. Ash collected from the bottom of
furnace is taken to an ash silo through a submerged belt conveyor. The fly ash from air
heater, ESP and economiser hoppers is taken to the fly ash silo by a dense phase ash
handling system. Depending on the fuel from which ash is generated, the ash produced
will be disposed. For example, the ash produced by burning biomass fuels can be used
as manure and can be given to the farmers.
9.2. CONTROL METHODS FOR WATER POLLUTION
9.2.1. Effluents from Water treatment Plant
The water drained from the water treatment plant will have to be treated so that the
water let out is neutral (pH 7.0). To achieve this, the water drained from the water
treatment plant is pumped to a neutralization pit.
The neutralization pit will have acid resistant brick lining. The effluent flowing into the
neutralizing pit will be self-neutralizing type & hence no additional chemical is required
to be used for treatment of the effluent from the DM plant.
The quantity of effluent from the softener & DM stream will be around 1 tph and from
the filters will be around 0.50 tph .
9.2.2. Boiler Blowdown
In order to maintain the solid concentration in the boiler feed water, two types of
blowdown are employed in the boiler. One type is continuous blowdown and the other
intermittent blowdown.
The drain water from blowdown tank will be at a temperature of 100 Deg. C. The
quantity of blowdown will be around 0.32 tph. This water can be taken to the waste
water tank , where it will get cooled naturally.
Apart from Boiler blowdown there will be blowdown from the aux cooling tower which
will be around 0.67 tph .
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 80 of 111
The water from blowdown, neutralizing pit will be taken to a waste water tank where the
water will achieve near about atmospheric temperature. This water can be used for ash
quenching / conditioning, dust suppression in the fuel storage yard and in the plant
area.
Used Lube oil will be stored in barrels & will be disposed off by certified agency
9.2.3. Sewage from the power plant buildings
The sewage from the various power plant buildings will be taken to a common septic
tank through trenches. The sewage from the septic tank will be disposed off through
concrete trenches. As the sewage is taken in trenches the soil will not get
contaminated.
9.3. CONTROL METHODS FOR THERMAL POLLUTION
The water used in the surface condenser to condense the steam, will be cooled in a
cooling tower of either induced or forced draft type. The water let out from the cooling
tower will have a temperature very close to the ambient.
9.4. CONTROL METHODS FOR NOISE POLLUTION
The major source of noise pollution in the proposed biomass based plant is from the
following:
Rotating equipments like ID, FD and SA fans
Feed pumps
Boiler and superheater safety valves
Start-up vent
Steam turbine
9.5. DG SETS
As per OSHA standards, the sound level from the rotating equipments shall be 85 to
90dBA. The rotating equipments will be designed to achieve this.
The start-up vent, safety valve outlets and the DG sets will be provided with silencers to
reduce the noise level to the acceptable limits.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 81 of 111
The power house building will be constructed with sound proof walls to keep the noise
level within the acceptable limits in the control room.
Rain Water Harvesting
It is planned to have rain water harvesting in the power plant area. Suitable
arrangements will be made at site for this purpose during project execution. There will
not be any mix up of the plant drains & the storm water drain.
9.6. INPUTS AND OUTPUTS FROM POWER PLANT
INPUTS
Fuel 18754.56 t / yr Water 6.74 cum / hr
OUTPUTS Power 126.72 Lakh kwh per annum (Gross
output 80 % PLF) Ash 1080 t / yr
a. Boiler Blowdown 0.38 t / hr
b. Cooling Tower Blowdown 0.7 t / hr
c. Cooling Tower Evaporation 2.6 t / hr
d. Steam from Deaerator Vent 0.1 t / hr
e. Filter Back wash 0.40 t / hr
f. DM plant effluent 0.32 t / hr
g. Domestic waste water 2.4 t / hr
Blowdown from Boiler and Cooling Tower (water at around 42 deg. C ) will be admitted
into a waste water tank where it gets cooled automatically. The effluent from DM plant &
the filter backwash will be admitted into the neutralizing pit where it will be self
neutralizing. The effluent from neutralizing pit will be transferred to the waste water tank
for further disposal.
The water from the waste water tank will be used for ash quenching, dust suppression
in the plant area by water spray, gardening, etc.
The domestic waste will be admitted into septic tank & then through dispersion trenches
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 82 of 111
SECTION 10
STATUTORY CLEARANCES REQUIRED
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 83 of 111
10. STATUTORY CELARANCES REQUIRED
The following are the statutory clearances required for the proposed biomass based
plant at Mithakhari village, Ferrargunj Tehsil in South Andaman Islands.
10.1. IN PRINCIPLE CLEARANCE FROM ELECTRICAL DEPARTMENT OF A&N ISLANDS
The clearances for export of power are to be obtained from A&N Government.
10.2. APPROVAL FOR PARALLEL OPERATION
Approval of the Government of A&N union territory for parallel operation of generating
set with the grid has to be obtained.
10.3. CLEARANCE FROM AIR PORT AUTHORITY OF INDIA
Permission has to be obtained from the Airport Authority of India, New Delhi, for the
chimney height.
10.4. POLLUTION CONTROL BOARD
Consent order for establishment from the A&N Government Pollution Control board to
be obtained for the air pollution, water pollution and noise pollution. The source of
pollution and the control methods proposed are discussed in the chapter,
“Environmental Impact and Pollution Control”.
10.5. APPROVAL FROM LOCAL PANCHAYAT
The local Panchayat has to approve the layout and buildings of the power plant
10.6. INSURANCE
Approval from the Loss Prevention Association is required for the firefighting systems
like hydrant system and portable fire extinguishers, proposed to protect the boiler, TG,
switch yard and other buildings. The premium for the insurance will be fixed based on
the recommendations given by the Tariff Advisory Committee.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 84 of 111
10.7. APPROVAL FOR THE ELECTRICAL INSTALLATION
The electrical installations like transformers, switch yard equipment etc., shall be
approved by the Chief Electrical Inspector, Government of A&N for the safety features,
location etc.
10.8. APPROVAL FOR THE FACTORY INSTALLATION
The approval for establishing the power plant to be obtained from the Chief Inspector of
Factories.
10.9. BOILER AND PRESSURE PART COMPONENTS
The approval from the Chief Inspector of Boilers, A&N is required for the installation and
operation of the boilers, steam and water pipings.
10.10. APPROVAL FROM GOVERNMENT AUTHORITY
Approval has to be obtained from the Government authorities for drawl of water from
the ground.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 85 of 111
SECTION 11
OPERATION AND MAINTENANCE
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 86 of 111
11. OPERATION AND MAINTENANCE
The proposed organisation structure for the operation and maintenance (O&M) of the
power plant is presented in the exhibits. In order to ensure a high level of performance
of the power plant, it is proposed to induct experienced O&M engineers from the very
beginning of the project.
11.1. BASIC STRUCTURE OF THE O&M TEAM
The basic structure and the broad functional area within the O&M organisation would be
as follows:
The power station superintendent would have the primary responsibility for the O&M of
the power plant. The organisation will comprise of four broad functional areas viz.
Operation, maintenance, technical and administration. The basic duties covered under
each of these functional areas would be as follows:
11.1.1. Operation
Operation of main generating equipment, fuel handling systems, water systems
including water treatment plant, 33 kV switch yard and other auxiliary plant.
Except for the Power Station Superintendent, Manager Operations and Manager
Maintenance, all other operation personnel would work on three shift basis.
Manpower for shift personnel planning for key areas has been generally done on 3+1
concept, to take into account leave taken by shift personnel.
The day to day operation of the power plant will be controlled by the Managers who will
be assisted by the Control room operators and shift engineers.
11.1.2. Maintenance
Maintenance of mechanical and electrical plant, control systems, buildings, roads,
drainages and sewage systems etc.,
Operation of the plant work shop, planning and scheduling maintenance works and
deciding the requirement of spare parts.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 87 of 111
The maintenance manager will be assisted by departmental engineers, who take care
of the maintenance aspects of all the mechanical, electrical and I&C requirements.
Trained technicians will be employed to assist the maintenance group in day to day
maintenance of the plant.
11.1.3. Efficiency Department
Monitoring of plant performance, plant water chemistry, maintenance of documents,
improvements in the plant systems, plant safety aspects including firefighting and
training.
Excepting the Chemists/Lab technicians, all other personnel in this functional area
would be in general shift.
This department is also known as Efficiency Department, as the prime responsibility of
them will be metering the energy exported to the Electricity Board apart from monitoring
the performance of the plant.
11.1.4. Administration
The main responsibilities of this department will be as follows:
Purchase
Plant Security
Liaison with local labour officers
Stores management
Finance & Accounts
Medical Services
Secretarial & Clerical
Transport services
HRD
11.2. FACILITIES TO BE EXTENDED TO THE EMPLOYEES
The number of employees required for the proposed power plant will be around 45
including 10 persons per shift for operation of the Plant. Maintenance department
personnel will be from different disciplines like Mechanical, Electrical, I&C etc. The
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 88 of 111
personnel required for administration and Finance & Accounts will also be included in
the above including the persons taken on contract basis.
11.2.1. In plant facilities:
The following facilities will be provided in the power plant:
Administration building and technical office
Construction offices and stores
Time and security offices
First aid and firefighting station
Canteen and welfare center
Toilets and change rooms
Car parks and cycle/scooter stands.
11.3. STATION MAINTENANCE PHILOSOPHY
The power plant’s maintenance philosophy is based on the following aspects.
11.3.1. Ordinary Maintenance
Which covers routine checking and minor and refurbishment activities to be performed
according to operating manuals on component / equipment in operating conditions.
11.3.2. Emergency Maintenance
Which is a corrective maintenance to be performed when a significant failure occurs.
To minimise forced outages duration, an effective Emergency Maintenance must be
supported by:
A proper stock of spare parts.
Permanent monitoring and Diagnostic systems for main components.
11.4. MAINTENANCE PLAN AND SCHEDULED MAINTENANCE
Scheduled maintenance is carried out according to maintenance plan, which should be
discussed and optimized according to the needs of the customer/client.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 89 of 111
The maintenance plan is based on scheduled outages for the following components:
Boiler
Steam Turbine
Alternator
11.5. MAINTENANCE MANAGEMENT SYSTEM
The maintenance of this plant will be carried out as per the above philosophy. This
system aims at maximising the availability of the power plant, while ensuring minimum
maintenance cost and safety of the plant and personnel.
11.6. SPARE PARTS MANAGEMENT SYSTEM
The primary objective of spare part management system will be to ensure timely
availability of proper spare parts for efficient maintenance of the plant without excessive
build-up of non-moving and slow moving inventory.
The spare parts management system for this project will cover the following areas:
Proper codification of all spares and consumables.
Spare parts indenting and procurement policy.
Ordering of critical mandatory and recommended spares judicious fixation of
inventory levels and ordering levels for spare parts based on the experience.
Development of more than one source of manufacturer / supplier wherever
practicable.
11.7. AVAILABILTY OF O & M MANUALS
All contracts include provision of at least 7 sets of detailed O & M manuals, which will
be distributed to all departments concerned well in advance. Installation and
commissioning procedures of various equipment will also be prepared as separate
documents for distribution to the concerned.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 90 of 111
11.8. SPECIAL TOOLS AND TACKLES
All contracts will include the provision for supply of one set of all types of special tools
and tackles, which are required for installation, commissioning and proper maintenance
of plant and equipment.
11.9. OPERATION REQUIREMENTS
With the completion of the official hydraulic test of the boiler, the pre-commissioning and
commissioning activities start. Pre-commissioning checks of the individual equipment
will lead to safe commissioning of the equipment. Installation procedure and
commissioning procedure as stipulated in the O & M manuals supplied by the various
equipment supplier shall be carefully followed.
Wherever possible, it is advisable to keep the vendor’s representative at site for
commissioning the critical equipment of the power plant.
However, the boiler, turbo-alternators and other critical equipment have to be
commissioned by the supplier himself, as the performance guaranties are with them.
Controls and Instrumentation system along with alarm and trip interlocks should be put
into operation to safeguard the equipment as well as the operating personnel.
11.10. CHECK-LIST AND PROTOCOL
A Detailed check-list for the various equipment, supplemented with the check-list
submitted by the supplier shall be drawn and logged for future reference. This will also
form part of the plant’s base history/datum.
Whenever an equipment in commissioned, the important parameters of that particular
equipment should be observed for a period of eight hours and the readings shall be
logged as per the log sheets.
11.10.1. ORGANISATION LEVELS
GRADING OF POSITIONS
Every position in an organisation is graded within these decision taking bands based on
a short description below. These grading levels range from A Band (unskilled labour) to
E-Band (Top Management). The definitions for the classification of different positions
are as follows:
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 91 of 111
A-Band
Basic elementary decisions where the options and alternatives are limited. Information
required by the worker is limited, simple, and easy to understand. A-band mainly
requires unskilled labour and its training requirements are minimum.
B-Band
Operational decisions are in a logical sequence of elements involved Experience and
practice is essential for taking decisions in this band. Training normally takes a few
months.
C-Band
Process decisions in a systematic sequence of operational activities. Problems have to
be diagnosed and the best solution forms a range of alternative needs to be selected
and implemented. A broad spectrum of intensive formal education, as well as
experience, is required for these jobs.
D-Band
Interpretative decisions by middle Management.
E-Band
Strategic decisions by Senior Management.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 92 of 111
SECTION 12
COST ESTIMATION AND FINANCIAL ANALYSIS
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 93 of 111
12. COST ESTIMATION AND FINANCIAL ANALYSIS
REFER ANNEXURE - I
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 94 of 111
SECTION – 13
SWOT ANALYSIS
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 95 of 111
13. SWOT ANALYSIS
While the promoters have undertaken pre-feasibility study they have also made a
SWOT analysis on the project, which are summarized in the succeeding paragraphs.
SWOT analysis would bring out the strengths and opportunities in setting up the
biomass based power project as well as its weaknesses and threats. The SWOT
analysis would enable the promoters to consider the positive and negative aspects of
setting up of these mini power projects.
STRENGTHS
Demand for the Power: In an energy starving country like ours, the energy supply and
demand gap is widening at a rapid rate. It is estimated that another 100000 MW has to
be added by 2012 along with the present generation to meet the future demand. This
project will contribute in its own way to reduce the deficit power situation.
Easy accessibility to raw material resources: The projects will be located at
Mithakhari village, Ferrargunj Tehsil in South Andaman Islands. The raw materials
available as biomass fuel are Coconut, arecanut, red oil palm, cashenut, napier grass,
cereals like paddy, maize, pulse, wood chips and empty fruit bunches. Wood chips may
be imported from main land or from neighboring countries such as Malaysia or
Indonesia.
The biomass assessment study carried out for ensuring the availability of Biomass from
different sources in different islands is compiled to determine the capacity of power
plant that may be established and operated on a continuous basis. The length of the
Andaman is 467 km with an average width of 24 km, whereas the maximum width is
52 km. The length of the Nicobar Islands is 259 kms with a maximum width of 58 kms.
Therefore, the available sources of biomass have been considered as Andaman &
Nicobar Islands. However, it may be noted that most of the population is settled in and
around Port Blair within 50 km radius of the proposed sites indicates that these two
fuels are abundantly available.
Rural Employment: The project contributes to the rural economy by creating rural
employment and also enables farmers to earn more money by selling stalks at better
prices. The project is environment friendly and reduces green house gases.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 96 of 111
WEAKNESSES
The project is based on biomass, which is nature’s gift and depends on vagaries of
nature. When there is a crop failure, there will not be any production of agricultural
waste.
The viability of the project depends on the fluctuations in prices of biomass. The
suppliers can hike the price of biomass.
OPPORTUNITIES
With the government encouraging, renewable projects in place of projects based
on conventional fuels; there is always scope for expanding the activity.
Presently, the proposed capacities are of the order of 2.28 MW and will be
operating on biomass fuel.
There is a clear cut demand supply gap in the A&N islands.
The company can export ash from the boiler since the ash from biomass fuels is
supposed to have silica content having export market.
The company can manufacture bricks from ash and can be sold in the market.
THREATS
Success of the project depends on Government power policies and approvals for
setting up of the units. Timely payment from the Third parties would also be a
matter of concern.
The establishment of number of biomass projects could affect the availability of
biomass endangering their very survival.
The state may become a surplus power generating state bringing down the power
purchase policies.
As could be seen from the above the strengths are more and opportunities are
enormous there by the weaknesses can be eliminated and threats can be
surmounted
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 97 of 111
SECTION – 14
SOCIO-ECONOMIC & ENVIRONMENTAL BENEFITS
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 98 of 111
14. SOCIO-ECONOMIC & ENVIRONMENTAL BENEFITS
The proposed biomass project will be a landmark achievement at Mithakhari village,
Ferrargunj Tehsil in South Andaman Islands. It will truly become a role model of utilizing
the agro residues in the most efficient manner for eco-friendly products like renewable
and decentralized power generation. The sound techno-economic and commercial
viability of this project, coupled with highest efficiency in all aspects of power
generation, will pave the way for Integration of agriculture industry & power industry in
the union territory of A&N.
Establishment of the latest and most efficient technologies adopted for biomass power
generation and biomass fuel linkages will also help the power industry of A&N and
equipment manufacturers to grow leaps and bounds, at the national and the
international levels.
The socio-economic benefits arising out of this project for the local populace wilt include
creation of direct and indirect jobs and consequent rise in the income levels, associated
commercial and social infrastructure development in the mofussil areas, improved
quality and availability of power due to grid benefits (in terms of deemed generation and
power factor improvement), better environment and higher returns for the crops due to
higher yield and price.
At the national and the State levels, the benefits include decentralized power
generation, reduction in T&D loss, reduced emissions, increased tax revenues and
reduction in the transportation costs,
At the project and promoter levels, the captioned project offers excellent opportunities
for expansion and diversification in to power sector, flexibility of operations depending
on the market situation for each product and improved returns from trade of emission
reductions due to biomass based power generation from the upcoming international
emissions trade market, under the Kyoto Protocol.
The project will have excellent multiplier effect and will become truly a win-win situation
for all the stakeholders. Thus, the proposed project has substantial socio-economic and
environmental benefits at the local, the State, the Regional and the National levels.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 99 of 111
SECTION 15
PROJECT SCHEDULE AND IMPLEMENTATION
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 100 of 111
15. PROJECT IMPLEMENTATION
15.1. PROJECT SCHEDULE
The project schedule for the implementation of 2.28 MW Biomass based project will be
16 months from the date of ordering of boiler and turbine. The project schedule
indicates the various activities starting from Engineering, Detailed Engineering,
Procurement, to Erection and Commissioning of the project.
15.2. PROJECT MANAGEMENT
15.2.1. Engineering Management system
Engineering Management System is a functional strategy developed to meet the tasks
of the engineering division keeping in view the overall project and the company’s
objectives.
It is a set of planned and well-defined systems and procedures for each activity and
sub-activity for engineering tasks to complete the project from feasibility, conceptual
design, detailed engineering up to commissioning and operation of the plant. The
following major constituents of the Engineering management systems are being used
for the execution of this project:
15.2.2. Division of Responsibility & Authority,
Division of Responsibility & Authority which defined the role and responsibilities against
the tasks identified for the engineering services, project engineering and Quality
Assurance & Inspection services in various disciplines such as Mechanical, Electrical,
C&I and Civil.
15.2.3. Engineering and Monitoring System
Engineering and Monitoring System covers identification of various Engineering
activities and sub-activities both pre-award and post-award of the main plant equipment
for this project.
The monitoring of the progress reports and look ahead planning are made on the basis
of Scheduled dates against the actual date of completion of the activities or anticipated
dates to complete the activities for every month.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 101 of 111
15.2.4. Vendor Drawing Control System
Vendor drawing control system provides the status reporting and monitoring for Vendor
submitted drawings, which give the clue to identify the vendor drawings, falling in
different approval categories, drawings which are overdue for submission by the
vendor, drawings which are pending for transmittal of the comments / distribution etc.
This is very important from the point of vendor progress monitoring.
15.2.5. Drawing Control Procedure
Drawing control procedure elaborates how to control drawings received from the vendor
or developed in-house. The system identifies how the drawings are to be processed
and who has the authority to approve these drawings / documents and transmittal of the
drawings to the site office concerned, project consultant and to the vendor.
15.2.6. System for Feed Back
This project has got a group of field engineers, which will perform the engineering tasks
at the site office and support the engineering group concerned at the Head office. The
engineering group is the focal point for all engineering issues and the field problems
pertaining to engineering. They also receive drawings and documents and distribute
amongst the various departments of the project, provide any clarification or modification
of any nature and give the feedback during construction and commissioning stage of
the project. They are also responsible to co-ordinate the project drawings and data to
AS-Built information.
15.2.7. Computer Aided Design
The use of Computer Aided Design (CAD) for development of engineering design and
drawings is being emphasized by the company. Presently almost all the engineering
tasks are performed using CAD with the software programs already available and
developed within the company.
15.2.8. Assurance of Engineering Quality
With the use of standardized document, model technical specification, design guide
lines and check list, the engineering quality is possible to achieve.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 102 of 111
15.2.9. Cost Control
To have control on the cost of the project, the project is split into no. of packages and
the cost is worked on the basis of the price data obtained from various vendors, as well
as on the basis of the trends of the cost variations.
15.2.10. Time Control
This is achieved during project planning and monitoring system. Monitoring is done at
every place – Regional office, Consultant’s office and the Site office.
15.3. CONSTRUCTION MANAGEMENT
15.3.1. Power Plant and Facilities
Site activities of project group shall be carried out as per Consultants Construction
Management Manual Prescribing systems and procedures, their scope of
responsibilities, inter-relationships as outlined in the various chapters.
This management system is a part of Integrated Project Management and Control
System developed by the consultant for implementation of power projects with the
object of achieving the goal within the defined schedule of time, cost and quality.
Organization tasks and frame work for construction management has been organized in
four distinct headings namely :
Construction Management Tasks.
Construction Management Organization
Functional Boundaries & Scope of Work
Construction Management Interface.
The Construction Management Tasks cover the following:-
iii. Infrastructure development
iv. Construction execution supervision
v. Safety and security
vi. Planning, Scheduling, Reviewing and Control
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 103 of 111
vii. Field quality surveillance
viii. Site contracting
ix. Material Management
x. Cost control
xi. Liaison with external agencies
xii. Personnel administration and welfare
xiii. Finance and Account.
15.4. CONSTRUCTION MANAGEMENT ORGANISATION
Construction Organization at project site is headed by Project Manager a senior
executive assisted by a consultant engineer from the consultant side. The project
manager is assisted in carrying out site functions by functional heads viz.
Head of project construction, planning, scheduling and project co-ordination.
Head of Field Engineering and Field Quality Surveillance.
Head of Personnel Management, which includes finance and accounts. The
construction, erection and commissioning is carried out by the contractors with
the technical supervision from the Consultant/ Customer Engineers in association
with the representatives of equipment manufacturer to the satisfaction of the
power plant authorities. The tools and plants for construction and erection are
brought by the contractor.
The functional boundaries and scope of work cover the following areas:
Construction planning and scheduling,
Civil construction
Equipment erection
Field engineering
Field quality control and surveillance: This group will ensure development and
enforcement of quality norms and checks.
Site contract group, which provides centralized services at site for awarding work
contracts.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 104 of 111
Material management functions cover activities of material planning, procurement,
storage issue etc.
Site service is a centralized service group which provides and maintains all
common construction facilities, tools, plants and construction utility services.
Personnel and Administration group at site is guided by the HRD division at
Head Quarters and it is responsible for man power planning, recruitment etc.
Finance & Accounts.
15.5. INFRASTRUCTURAL FACILITIES & CIVIL SYSTEM
15.5.1. Preliminary Works
GEO TECHNICAL INVESTIGATION AND SITE SPECIFIC SIESMIC STUDIES.
Detailed geotechnical investigation to be carried out to obtain the details of soil profile,
sub surface condition , soil resistivity and physical and engineering. Properties of the
soil for the purpose of design of suitable type of foundation for the various structures
and equipment.
Detailed geo-technical investigation to be carried out in three parts (i.e.)
Main plant building and switchyard area.
Site facilities like cooling tower, DM plant area.
Raw water tank & pump house.
Water analysis to be carried out to find out the quality and quantity of raw water
available. This dictates the size and type of DM plant.
Other infrastructural facility lease of land, levelling, grading, storage reservoir, internal
roads, drainage and effluent system, sewage system, boundary wall and fencing has
been envisaged for this project.
15.5.2. Construction & Drinking Water
The water requirement for construction purpose including drinking water is drawn from
the reservoir located within the plant boundary. The water is pumped to different
places with the help of pumps.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 105 of 111
For drinking water purposes, the treated water is pumped to an overhead tank and from
the tank, the drinking water is supplied through a ring header to various areas of work
place.
15.5.3. Construction Offices, Storage Sheds etc.,
Temporary office will be constructed to accommodate the construction personnel inside
the plant boundary. This shall be a single storied building with load bearing brick wall
and A.C. sheet roofing. Sufficient open space has been kept for various contractor’s
office and storage of steel materials.
15.5.4. Construction Power
About 100 KVA at 415 V power is required for construction purposes.
15.5.5. Buildings
Separate buildings will be located within the power plant for Administration, Stores,
Workshop.
15.6. QUALITY ASSURANCE & INSPECTION
In order to ensure high reliability and better performance, quality assurance programs
have been developed for all packages. For this purpose, bid documents for all contract
packages stipulate that the bidders have to submit their own quality assurance
programs for manufacturing and field activities.
They include identification of
Quality organization
Documentation control
Procedure for purchase of materials, components, selection of subcontractors,
services including vendor analysis, source inspection, raw material inspection etc.
Control and testing of calibration, measuring and testing equipment.
Handling, storage and delivery.
Maintenance of records to meet all the contractual requirements.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 106 of 111
All the contractors are required to develop such QA programs after the review of all
technical specification and contract requirements. The QA programs of the vendors are
taken into consideration during bid evaluation by the consultants. At the time of
finalisation of the agreement with the successful vendors, a detailed quality plan setting
and the quality practices and procedures, relevant standards and acceptance level for
all the components of all the equipment will be mutually discussed and agreed to.
Further, consultant / client witnesses tests / inspection etc as per the customer hold
points (CHP) to be selected by the consultant in quality plans, beyond which the work
will progress only with the consent of the consultant. Apart from this, the quality
surveillance of the system and procedures of the contractor’s quality control
organisation will be carried out for monitoring the implementation status.
In addition, the consultant / customer will carry out quality audits on the systems and
processes for the areas of manufacture and field activities to determine the
effectiveness of implementation and to ensure conformance to code, contract and
procedure requirements.
Control of quality in the field right from the stage of material receipt till final
commissioning will be effected by the field quality control group. This group will be
independent of actual execution schedules and costs and will function under technical
guidance from the consultant’s QA group.
15.7. MAN POWER TRAINING & PLACEMENT
15.7.1. Organisation Structure
The project will be headed by a Power Plant Superintendent, a senior level executive
from the customer side, who will have overall administrative as well as technical control
of the cogeneration plant. For effective operation, maintenance and administration of
the project, adequate no. of suitable technical and administrative personnel will be
posted under him.
15.7.2. Training and Development
Performance of the employees always depends upon the training and developmental
programmes organised by the consultants / customers from time to time. This is one of
the important tools to derive improved performance from the operators of the
cogeneration plant.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 107 of 111
15.7.3. Type of Training – Pre-Employment Training
Pre-employment training aims at providing requisite skills and confidence to the
personnel, who enter the organisation as fresh trainees at different induction levels.
Long duration training schemes and on the job training schemes are in vogue to take
care of further training.
15.7.4. Post – Employment Training
Post – Employment Training provides opportunities to personnel at various levels of the
organisation hierarchy to take-up higher responsibility and skills and also to re-orient
them to keep pace with the advancement in power plant operations / technology. This
package basically has three components Viz. Management development for senior level
executives for developing functional knowledge and managerial skills, specialized
training activities to acquaint the employees with the latest technology around the world
in cogen industries and employee development programs to develop and upgrade skills
and also to attain higher educational levels for the benefit of personnel at different
levels.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 108 of 111
SECTION 16
DRAWINGS
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 109 of 111
16. LIST OF DRAWINGS
PLOT PLAN 0-94XX-000-001
HEAT AND MASS BALANCE DIAGRAM - 4-94XX -100-001
WATER BALANCE DIAGRAM 4-94XX -100-002
HT SINGLE LINE DIAGRAM 2-94XX -400-001
PROCESS FLOW DIAGRAM 1-94XX -100-001
4445
044
450
11.5
079
4.3
11.3
794.
342
445
11.2
792.
2
2.96
TPH
4445
00.
279
4.3
4244
50.
179
2.2
2.28
Q0.
35M
W
-10
6.96
0.13
51.0
011
.85
108.
5610
.16
600.
5
3.5
191.
01.
0467
9.9
535
0.45
35.2
0.1
-55
.810
.46
55.8
0.13
51.0
010
.46
51.0
0
-10
6.96
11.8
510
8.56
-55
.810
.46
55.8
LEG
END
:N
ote
CLI
EN
T:-
Blow
dow
n 3
%
P
RO
JEC
T:-
Kg/
Cm
2 (a)
Deg
C
NAM
ED
ATE
S
IGN
TPH
Kca
l/Kg
DR
AWN
E.D
20.1
1.12
CH
EC
KE
DK
.A.G
20.1
1.12
Live
Ste
amAP
PD
S.K
20.1
1.12
Extr
acte
d &
disc
harg
e St
eam
SC
ALE
:
Mak
e up
wat
er94
XX
N
TS
TITL
E :-
Cond
ensa
te
4-94
XX -1
00-0
01SUR
YA C
HAK
RA
GR
EEN
FU
ELS
PRIV
ATE
LIM
ITED
2.28
MW
BIO
MAS
S PO
WER
PLA
NT
P
RO
JEC
T N
O:
HEA
T AN
D M
ASS
BALA
NC
E D
IAG
RAM
STEA
M T
UR
BIN
E
BIO
MA
SS
CE
P
BLO
W D
OW
N
GS
CE
JC
ALTE
RN
ATO
R
MA
KE
UP
WA
TER
TO G
LAN
DS
FROM GLANDS
DEA
ERAT
OR
BO
ILER
EJECTOR
BFP
TO EJECTORS
ACC
HO
T W
ELL
√
AQ
UATH
ERM
CH
EN
NAI
- 600 0
04 :
IN
DIA
EN
GIN
EERIN
G C
ON
SU
LTAN
TS (
IND
IA)
PVT.
LTD
.
Sur
ya C
hakr
a G
reen
Fue
ls P
rivat
e Lt
d2.
28 M
W B
iom
ass
Pow
er P
lant
WA
TER
BA
LAN
CE
DIA
GR
AM
Stea
m G
ener
ated
12.5
0TP
H
R
AW W
ATER
STO
RAG
E TA
NK
0.1
Q0.
38
6.74
0.48
Mak
e up
Q0.
33
Q1.
30
T
O G
UA
RD
PO
ND
/ ETP
Q0.
50
T
O W
AS
HIN
G E
TC.
40.0
02.
31
150
3.03
320.
7200
Q2.
4
CLI
EN
T
SU
RYA
CH
AK
RA
GR
EEN
FU
ELS
PRIV
ATE
LIM
ITED
PR
OJE
CT
:N
AM
ED
ATE
S
IGN
DR
AW
NE
.D20
.11.
12
CH
EC
KE
DK
.A.G
20.1
1.12
AP
PD
S.K
20.1
1.12
Cu.
m/h
rS
CA
LE :
NTS
TITL
E:-
DR
AW
ING
NO
.
Lo
sses
to
A
tmos
pher
e
P
RO
JEC
T N
O:
94XX
4 - 9
4XX
- 100
- 00
2
WA
TER
BA
LAN
CE
DIA
GR
AM
Eva
pora
tion
Loss
Blo
wdo
wn
Loss
FOR
GA
RD
EN
ING
, DO
ME
STI
C U
SE
AS
H Q
UE
NC
HIN
G &
MIS
CE
LLA
NE
OU
S
2.28
MW
BIO
MA
SS P
OW
ER P
LAN
T
DEA
ERAT
OR
BO
ILER
11
.5TP
H
AUX.
CO
OLI
NG
DM
PLA
NT
NEU
TRAL
IZAT
ION
PIT
BLO
W D
OW
N
Q
CO
OLI
NG
Q
Aqu
athe
rm E
ngin
eerin
g (In
dia)
Pvt
. Ltd
.
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 110 of 111
SECTION – 17
ANNEXURES
Project: 2.28 MW Biomass Power Plant Detailed Project Report Client: Suryachakra Green Fuels Private Limited
Aquatherm Engineering Consultants (I) Pvt Ltd., Page 111 of 111
17. ANNEXURES
ANNEXURE –I FINANCIAL STATEMENT
ANNEXURE –II WATER ANALYSIS REPORT (Will be submitted shortly)
ANNEXURE –III BIOMASS STUDY AVAILABILITY REPORT
ANNEXURE –IV PROJECT SCHEDULE
ANNEXURE –V SITE PLAN
ASSUMPTIONS:
Capacity of the Plant 2.28 MW
Name of the Plant Suryachakra Green Fuels Private Limited
Plant operating capacity 80%
Sale Price 9.81 Anticipated Increase in Sale Price 4% YOY
Debt equity ratio 70:30
Working Capital Margin 25%
Number of days of operation 330 days
Project Schedule 12 Months
Calculation of Raw Material Cost
Name of the Material Rate / MT % of Use Cost in Rs
Agri Residues, Forestry Wastes and Coconut Residues 3000.00 100% 3000.00Pellets Conversion Cost 600.00Transportation 0.00 1250.00
TOTAL 4850.00
Increase by 3% YOY
Specific Fuel Consumption 1.30 Kgs per kwh
O & M Cost / MT 0.60 Rs /MtIncrease by 5% YOY
Consumables 300 Rs /MtIncrease by 10% YOY
Admin Expenses 2% on salesIncrease by 5% YOY
Interest Rate On Rupee Loan on TL 14.50%
Interest on WC Loan 14.00%
Repayment 18+96 months(18 months gestation and 96 months repayment)
DSCR 1.36IRR 14.18%
Start DateNumber of Months 12CODMoratorium 18Start of Repayment
Rs/Kw
Suryachakra Green Fuels Private Limited10
PROJECT COST AND MEANS OF FINANCE
A. PROJECT COST Interest rate 15%
1. Land 0.00 Period 4 Quarter2. Land Development expenses 37.00 Advance 10% 104.66 Months
3. Civil works 230.00 1 20% 209.33 11.38 12 313.99
4. Plant & Machinery (Incl of taxes) 955.00 2 20% 209.33 18.97 9 209.33
5. Miscellaneous Fixed Assets 17.00 3 25% 261.66 28.46 6 261.66
6. Prel. & Pre‐operative Expenses 48.47 4 25% 261.66 37.94 3 261.66
7. Interest During Construction 96.75 5 0% 0.00 0.00
8. Contingencies 34.61 6 0% 0.00 0.00
9. Working Capital Margin 76.36 7Total 1495.18 8
B. MEANS OF FINANCE 9 100% 1,046.63 96.75 1,046.63
1. Equity Share Capital 448.552. Unsecured Loans from Promoters 0.003. Term Loan from Bank 1046.63
Total 1495.18
Suryachakra Green Fuels Private Limited
PROJECTED PROFITABILITY STATEMENT(Rs. Lakhs)
Particulars \ Years Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10Installed Capacity (MW) 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28Lakh Kwh Units 180.58 180.58 180.58 180.58 180.58 180.58 180.58 180.58 180.58 180.58 Plant Load Factor (PLF) 70.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0%Average Annual Generation (Lakh Units) 126.40 144.46 144.46 144.46 144.46 144.46 144.46 144.46 144.46 144.46 Less: Auxiliary Consumption & Line Losses @ 14% 17.70 20.22 20.22 20.22 20.22 20.22 20.22 20.22 20.22 20.22 Net Annual Generation (Lakh Units) 108.71 124.24 124.24 124.24 124.24 124.24 124.24 124.24 124.24 124.24
Sale Price Per Unit ( In Rupees) 9.81 9.81 10.20 10.61 11.03 11.48 11.94 12.41 12.91 13.43 Add: Escalation (% age) 0 4% 4% 4% 4% 4% 4% 4% 4% 4%Aggregate Sale Price Unit ( In Rupees) 9.81 10.20 10.61 11.03 11.48 11.94 12.41 12.91 13.43 13.96
Revenue on account Sales (Rs in lacs) 1066.41 1267.51 1318.21 1370.94 1425.77 1482.81 1542.12 1603.80 1667.95 1734.67201.10 50.70 52.73 54.84 57.03 59.31 61.68 64.15 66.72
Total Revenue (Rs. Lakhs) 1066.41 1267.51 1318.21 1370.94 1425.77 1482.81 1542.12 1603.80 1667.95 1734.67
Description (Rs in Lacs)
Suryachakra Green Fuels Private Limited
PROJECTED PROFITABILITY STATEMENT (Contd.,)(Rs. lakhs)
Particulars \ Years Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10Cost of Operation Mar‐12 Mar‐13 Mar‐14 Mar‐15 Mar‐16 Mar‐17 Mar‐18 Mar‐19 Mar‐20 Mar‐21
Cost of Raw Materials (Incl transportation) 766.32 902.07 929.13 957.00 985.71 1015.28 1045.74 1077.12 1109.43 1142.71Operation and Maintainance Cost including Overheads 75.84 91.01 91.01 95.56 100.34 105.36 110.62 116.15 121.96 128.06
Fixed Expense
Admn Expenses 21.33 25.35 26.36 27.42 28.52 29.66 30.84 32.08 33.36 34.69Consumables 0.38 0.48 0.48 0.52 0.58 0.63 0.70 0.77 0.84 0.93Preliminary and Pre operative Expenses 48.47
Total Cost 912.34 1018.90 1046.98 1080.51 1115.14 1150.93 1187.91 1226.11 1265.60 1306.4086% 80% 79% 79% 78% 78% 77% 76% 76% 75%
Profit before Interest,depreciation and taxes 154.08 248.60 271.23 290.43 310.63 331.87 354.21 377.69 402.36 428.28
Depreciation 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39
Interest onTerm Loan 151.76 148.99 132.00 113.03 94.06 75.09 56.12 37.15 18.18 1.98W/C borrowing 31.65 37.55 38.91 40.32 41.78 43.30 44.87 46.50 48.18 49.93
Profit before Tax ‐92.73 ‐1.33 36.93 73.69 111.40 150.10 189.83 230.65 272.61 312.98
Provision for Tax 0.00 0.00 7.39 14.74 22.29 30.03 0.00 45.35 54.54 62.62
Profit after Tax ‐92.73 ‐1.33 29.54 58.95 89.11 120.07 189.83 185.30 218.06 250.36
Dividend 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Retained Profit ‐92.73 ‐1.33 29.54 58.95 89.11 120.07 189.83 185.30 218.06 250.36
Cumulative Retained Profit ‐92.73 ‐94.05 ‐64.51 ‐5.57 83.54 203.61 393.44 578.75 796.81 1047.17
Add: Depreciation & Other write offs 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39
Net Cash Accruals ‐29.34 62.06 92.93 122.34 152.50 183.46 253.22 248.69 281.45 313.75
Cumulative Cash Accruals ‐29.34 32.73 125.66 247.99 400.49 583.95 837.17 1085.87 1367.32 1681.07TAX CALCULATIONProfit Before Tax (PBT) ‐92.73 ‐1.33 36.93 73.69 111.40 150.10 189.83 230.65 272.61 312.98Add: Dep‐normal 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39Total ‐29.34 62.06 100.32 137.08 174.79 213.49 253.22 294.04 336.00 376.37Less: IT Dep 215.76 184.55 157.90 135.15 115.71 99.11 84.92 72.80 62.43 53.56
Taxable Profits under IT Act ‐245.10 ‐122.49 ‐57.58 1.93 59.08 114.38 168.30 221.25 273.57 322.81Carry forward of Losses ‐245.10 ‐245.10 ‐367.58 ‐425.16 ‐423.23 ‐364.15 ‐249.77 ‐81.47 0.00 0.00Total Taxable profits under IT Act ‐245.10 ‐367.58 ‐425.16 ‐423.23 ‐364.15 ‐249.77 ‐81.47 139.77 273.57 322.81
32.45%Prov. for Tax @32.445% ‐79.52 ‐119.26 ‐137.94 ‐137.32 ‐118.15 ‐81.04 ‐26.43 45.35 88.76 104.74(30% Tax + 5% SC.+ED Cess 3%) MAT @ 20.01% ‐18.55 ‐0.27 7.39 14.74 22.29 30.03 37.98 46.15 54.54 62.62(18.50% Tax+5% SC.+ED Cess 3%)
20.01%Income Tax payable 0.00 0.00 7.39 14.74 22.29 30.03 0.00 45.35 54.54 62.62(MAT or Income Tax whichever 74.19 138.60 139.40 105.18 63.07is higher)
Suryachakra Green Fuels Private Limited
PROJECTED CASH‐FLOW STATEMENT (Rs Lakhs)
Particulars Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Total
CASH INFLOW:Profit After Tax (92.73) (1.33) 29.54 58.95 89.11 120.07 189.83 185.30 218.06 250.36 1047.17Add back : Depreciation 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 633.90Prel. Expenses written off 48.47 48.47Increase in Current Liabilites 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00Term Loan Interest 151.76 148.99 132.00 113.03 94.06 75.09 56.12 37.15 18.18 1.98 828.36Equity / Unsecured loans 448.55 448.55Working Capital Loans 226.09 42.11 9.72 10.08 10.44 10.83 11.22 11.63 12.06 12.50 356.67Term Loans 1046.63 1046.63
Total Inflow 1495.18 399.98 253.16 234.65 245.44 257.00 269.37 320.56 297.48 311.69 328.22 4412.75
CASH OUTFLOW:Fixed Assets 1370.35 1370.35Term Loan Interest 151.76 148.99 132.00 113.03 94.06 75.09 56.12 37.15 18.18 1.98 828.36Term Loan Instalments 0.00 65.41 130.83 130.83 130.83 130.83 130.83 130.83 130.83 65.41 1046.63Working Capital 76.36 229.09 56.14 12.96 13.43 13.92 14.43 14.96 15.51 16.08 16.67 479.56Prel. Expenses 48.47
0.00Total Outflow 1495.18 380.85 270.55 275.79 257.29 238.81 220.35 201.91 183.49 165.09 84.06 3724.91
Opening balance 0.00 0.00 19.13 1.74 (39.40) (51.25) (33.06) 15.96 134.62 248.60 395.21 0.00Increase / decrease during the year 0.00 19.13 (17.39) (41.14) (11.85) 18.19 49.02 118.65 113.99 146.61 244.17 639.38Closing balance 0.00 19.13 1.74 (39.40) (51.25) (33.06) 15.96 134.62 248.60 395.21 639.38 639.38
Suryachakra Green Fuels Private Limited
CALCULATION OF DEBT SERVICE COVERAGE RATIOParticulars Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Total
Profit After Tax (92.73) (1.33) 29.54 58.95 89.11 120.07 189.83 185.30 218.06 250.36 1047.17Add back : Depreciation 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 63.39 633.90Prel. Expenses written off 48.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.47Term Loan Interest 151.76 148.99 132.00 113.03 94.06 75.09 56.12 37.15 18.18 1.98 828.36
Total 170.89 211.06 224.93 235.37 246.56 258.55 309.34 285.84 299.63 315.72 2557.89
Term Loan Interest 151.76 148.99 132.00 113.03 94.06 75.09 56.12 37.15 18.18 1.98 828.36Term Loan Instalments 0.00 65.41 130.83 130.83 130.83 130.83 130.83 130.83 130.83 65.41 1046.63
Total 151.76 214.41 262.83 243.86 224.89 205.92 186.95 167.98 149.01 67.39 1874.99
DSCR 1.13 0.98 0.86 0.97 1.10 1.26 1.65 1.70 2.01 4.68 1.36Average DSCR 1.36
Suryachakra Green Fuels Private LimitedPROJECTED BALANCE SHEETS
(Rs Lakhs)Particulars Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
(Pre‐production)
LIABILITIES Equity / Unsecured Loans 448.55 448.55 448.55 448.55 448.55 448.55 448.55 448.55 448.55 448.55 448.55Retained Profit (92.73) (94.05) (64.51) (5.57) 83.54 203.61 393.44 578.75 796.81 1047.17Sundry Creditors 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Others 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00Working Capital Loans 226.09 268.20 277.92 287.99 298.44 309.26 320.48 332.11 344.17 356.67Term Loans 1046.63 1046.63 981.21 850.39 719.56 588.73 457.90 327.07 196.24 65.41 (0.00)
Total 1495.18 1631.55 1606.91 1515.34 1453.54 1422.26 1422.33 1492.55 1558.66 1658 1855
ASSETSFixed Assets (Gross Block) 1370.35 1370.35 1370.35 1370.35 1370.35 1370.35 1370.35 1370.35 1370.35 1370.35 1370.35 Less: Depreciation 63.39 126.78 190.17 253.56 316.95 380.34 443.73 507.12 570.51 633.90
1370.35 1306.96 1243.57 1180.18 1116.79 1053.40 990.01 926.62 863.23 799.85 736.46Net cash accruals 0.00 19.13 1.74 (39.40) (51.25) (33.06) 15.96 134.62 248.60 395.21 639.38Current Assets 76.36 305.46 361.60 374.56 387.99 401.91 416.35 431.31 446.82 462.90 479.56Prel. Expenses 48.47
Total 1495.18 1631.55 1606.91 1515.34 1453.54 1422.26 1422.33 1492.55 1558.66 1657.95 1855.40
Suryachakra Green Fuels Private Limited
CALCULATION OF BREAK EVEN POINT(Rs Lakhs)
Particulars 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
SALES REVENUE 1066.41 1267.51 1318.21 1370.94 1425.77 1482.81 1542.12 1603.80 1667.95 1734.67Sales in Tons 126 144 144 144 144 144 144 144 144 144VARIABLE COSTS 766.32 902.07 929.13 957.00 985.71 1015.28 1045.74 1077.12 1109.43 1142.71CONTRIBUTION 300.09 365.44 389.08 413.93 440.06 467.52 496.37 526.69 558.53 591.96FIXED COSTS 316.98 275.76 261.14 244.68 228.32 212.07 195.92 179.88 163.96 150.92BREAK EVEN POINT : SALES REVENUE 1126.41 956.45 884.75 810.38 739.76 672.60 608.67 547.75 489.63 442.26Break Even in mill 133.51 109.01 96.96 85.39 74.95 65.53 57.02 49.34 42.41 36.83
Break Even %age 105.63% 75.46% 67.12% 59.11% 51.88% 45.36% 39.47% 34.15% 29.36% 25.50%94.67% 132.52% 148.99% 169.17% 192.74% 220.46% 253.36% 292.80% 340.65% 392.23%
INTERNAL RATE OF RETURNYear Net Cashflows
1 (1495) Investment2 154 PBIDT‐yearly3 2494 2715 2906 3117 3328 3549 37810 40211 428
IRR = 14%
Suryachakra Green Fuels Private Limited
SUMMARY
PARTICULARS Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10Installed Capacity (MW) 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 Capacity Utilisation ‐Plant Load Factor (%) 70% 80% 80% 80% 80% 80% 80% 80% 80% 80%Total Income 1066 1268 1318 1371 1426 1483 1542 1604 1668 1735PBDIT 154 249 271 290 311 332 354 378 402 428PBT (93) (1) 37 74 111 150 190 231 273 313PAT (93) (1) 30 59 89 120 190 185 218 250Depreciation 63 63 63 63 63 63 63 63 63 63Prel & Preop Exp Write off 48Cash Profit 19 62 93 122 153 183 253 249 281 314Annual DSCR 1.13 0.98 0.86 0.97 1.10 1.26 1.65 1.70 2.01 4.68Overall DSCR 1.36Annual Cash Flow DSCR 1.13 0.92 0.84 0.95 1.08 1.24 1.63 1.68 1.98 4.62Overall DSCR 1.34PBIDT/Total Income 14% 20% 21% 21% 22% 22% 23% 24% 24% 25%PAT / Total Income ‐9% 0% 2% 4% 6% 8% 12% 12% 13% 14%Equity Capital 449 449 449 449 449 449 449 449 449 449Networth 356 355 384 443 532 652 842 1027 1245 1496DER 2.94 2.77 2.21 1.62 1.11 0.70 0.39 0.19 0.05 (0.00)TOL / TNW 3.59 3.53 2.95 2.28 1.67 1.18 0.77 0.52 0.33 0.24FACR 1.25 1.27 1.39 1.55 1.79 2.16 2.83ROCE 11% 19% 22% 25% 28% 30% 30% 31% 31% 29%Return on capital ‐21% 0% 7% 13% 20% 27% 42% 41% 49% 56%Overall Interest Coverage Ratio 0.84 1.33 1.59 1.89 2.29 2.80 3.51 4.52 6.06 8.25Current Ratio 1.42 1.34 1.19 1.16 1.22 1.38 1.75 2.08 2.47 3.11IRR 14%
Suryachakra Green Fuels Private Limited
COST PROJECTIONS ‐ RAW MATERIALSRs. Lakhs
Particulars
Capacity Utilisation 70.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0% 80.0%Power Generated in lakh Kwh 126.40 144.46 144.46 144.46 144.46 144.46 144.46 144.46 144.46 144.46
Fuel RequirementFuel required in Kg per Kwh 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 Biomass requirement MT 15,800.40 18,057.60 18,057.60 18,057.60 18,057.60 18,057.60 18,057.60 18,057.60 18,057.60 18,057.60
Cost of BiomassAgri Residues, Forestry Wastes and Coconut Res 100.00% 4850
Transportation 0.00% 0
Cost of biomass Rs per MT 4850With 3% increase in the cost per anum 4850 4996 5145 5300 5459 5622 5791 5965 6144 6328
Total 766.32 902.07 929.13 957.00 985.71 1015.28 1045.74 1077.12 1109.43 1142.71
GRAND TOTAL 766.32 902.07 929.13 957.00 985.71 1015.28 1045.74 1077.12 1109.43 1142.71
Suryachakra Green Fuels Private Limited
WORKING CAPITAL PROJECTIONS:No. of
Particulars monthsrequirement
Current AssetsRaw Material / Fuel 2 127.72 150.34 154.85 159.50 164.29 169.21 174.29 179.52 184.90 190.45
Receivables 2 177.74 211.25 219.70 228.49 237.63 247.13 257.02 267.30 277.99 289.11
Sub total 305.46 361.60 374.56 387.99 401.91 416.35 431.31 446.82 462.90 479.56
Current LiabilitiesSundry Creditors 0% ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ Others 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Sub Total 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Working Capital Gap 302.46 358.60 371.56 384.99 398.91 413.35 428.31 443.82 459.90 476.56W/C Margin 25% 76.36 90.40 93.64 97.00 100.48 104.09 107.83 111.70 115.72 119.89
MPBF 226.09 268.20 277.92 287.99 298.44 309.26 320.48 332.11 344.17 356.67
Rate of IntWorking Capital Interest 14.00% 31.65 37.55 38.91 40.32 41.78 43.30 44.87 46.50 48.18 49.93
Year 7 Year 8
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Year 9 Year 10
Year 9 Year 10
Year 5 Year 6Year 1 Year 2 Year 3 Year 4
Details of Principal - Interest Payments on Term Loans
Amount borrowed Rs. Croresfrom the Inst./Banks 1046.63Rate of Interest: 14.50%Monthly instalment 10.90
Rs. LakhsAPR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR TOTAL
Month-1 Month-2 Month-3 Month-4 Month-5 Month-6 Month-7 Month-8 Month-9 Month-10 Month-11 Month-12Year 1 FY Opening Balance 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63
Addition during the month 0.00Installment during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Closing Balance 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63Interest for the month 12.65 12.65 12.65 12.65 12.65 12.65 12.65 12.65 12.65 12.65 12.65 12.65 151.76
Year 2 FY Opening Balance 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1035.73 1024.82 1013.92 1003.02 992.12 1046.63Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 0.00 0.00 0.00 0.00 0.00 0.00 10.90 10.90 10.90 10.90 10.90 10.90 65.41Closing Balance 1046.63 1046.63 1046.63 1046.63 1046.63 1046.63 1035.73 1024.82 1013.92 1003.02 992.12 981.21 981.21Interest for the month 12.65 12.65 12.65 12.65 12.65 12.65 12.52 12.38 12.25 12.12 11.99 11.86 148.99
Year 3 FY Opening Balance 981.21 970.31 959.41 948.51 937.60 926.70 915.80 904.90 893.99 883.09 872.19 861.29 981.21Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 970.31 959.41 948.51 937.60 926.70 915.80 904.90 893.99 883.09 872.19 861.29 850.39 850.39Interest for the month 11.72 11.59 11.46 11.33 11.20 11.07 10.93 10.80 10.67 10.54 10.41 10.28 132.00
Year 4 FY Opening Balance 850.39 839.48 828.58 817.68 806.78 795.87 784.97 774.07 763.17 752.26 741.36 730.46 850.39Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 839.48 828.58 817.68 806.78 795.87 784.97 774.07 763.17 752.26 741.36 730.46 719.56 719.56Interest for the month 10.14 10.01 9.88 9.75 9.62 9.49 9.35 9.22 9.09 8.96 8.83 8.69 113.03
Year 5 FY Opening Balance 719.56 708.65 697.75 686.85 675.95 665.05 654.14 643.24 632.34 621.44 610.53 599.63 719.56Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 708.65 697.75 686.85 675.95 665.05 654.14 643.24 632.34 621.44 610.53 599.63 588.73 588.73Interest for the month 8.56 8.43 8.30 8.17 8.04 7.90 7.77 7.64 7.51 7.38 7.25 7.11 94.06
Year 6 FY Opening Balance 588.73 577.83 566.92 556.02 545.12 534.22 523.31 512.41 501.51 490.61 479.70 468.80 588.73Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 577.83 566.92 556.02 545.12 534.22 523.31 512.41 501.51 490.61 479.70 468.80 457.90 457.90Interest for the month 6.98 6.85 6.72 6.59 6.46 6.32 6.19 6.06 5.93 5.80 5.66 5.53 75.09
Year 7 FY Opening Balance 457.90 447.00 436.10 425.19 414.29 403.39 392.49 381.58 370.68 359.78 348.88 337.97 457.90Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 447.00 436.10 425.19 414.29 403.39 392.49 381.58 370.68 359.78 348.88 337.97 327.07 327.07Interest for the month 5.40 5.27 5.14 5.01 4.87 4.74 4.61 4.48 4.35 4.22 4.08 3.95 56.12
Year 8 FY Opening Balance 327.07 316.17 305.27 294.36 283.46 272.56 261.66 250.75 239.85 228.95 218.05 207.15 327.07Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 316.17 305.27 294.36 283.46 272.56 261.66 250.75 239.85 228.95 218.05 207.15 196.24 196.24Interest for the month 3.82 3.69 3.56 3.43 3.29 3.16 3.03 2.90 2.77 2.63 2.50 2.37 37.15
Year 9 FY Opening Balance 196.24 185.34 174.44 163.54 152.63 141.73 130.83 119.93 109.02 98.12 87.22 76.32 196.24Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 10.90 130.83Closing Balance 185.34 174.44 163.54 152.63 141.73 130.83 119.93 109.02 98.12 87.22 76.32 65.41 65.41Interest for the month 2.24 2.11 1.98 1.84 1.71 1.58 1.45 1.32 1.19 1.05 0.92 0.79 18.18
Year 10 FY Opening Balance 65.41 54.51 43.61 32.71 21.80 10.90 0.00 0.00 0.00 0.00 0.00 0.00 65.41Addition during the month 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Installment during the month 10.90 10.90 10.90 10.90 10.90 10.90 0.00 0.00 0.00 0.00 0.00 0.00 65.41Closing Balance 54.51 43.61 32.71 21.80 10.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00Interest for the month 0.66 0.53 0.40 0.26 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.98
Mar‐12 Mar‐13 Mar‐14 Mar‐15 Mar‐16 Mar‐17 Mar‐18 Mar‐19 Mar‐20 Mar‐21Interest 151.76 148.99 132.00 113.03 94.06 75.09 56.12 37.15 18.18 1.98 828.36Installments 0.00 65.41 130.83 130.83 130.83 130.83 130.83 130.83 130.83 65.41 1046.63
Depreciation Calculation As Per Companies Act and Income Tax Act.Rs.In Crores
Depreciation as per Companies Act:
Description Total Cost Rate DepreciationRs. Cr % Rs. Cr
Buildings 230.00 3.34 7.68
Plant & Machinery& Fixed assets 1055.07 5.28 55.71
Total 1285.07 63.39
IT Depreciation Calculation: (WDV Basis) Buildings: Total Cost: 230.00 Rate: 10.00
Year 1 2 3 4 5 6 7 8 9 10 Total WDV 230.00 207.00 186.30 167.67 150.90 135.81 122.23 110.01 99.01 89.11
Depreciation 23.00 20.70 18.63 16.77 15.09 13.58 12.22 11.00 9.90 8.91 149.80
Plant And Machinery: Total cost: 1285.07 Rate: 15.00
Year 1 2 3 4 5 6 7 8 9 10 WDV 1285.07 1092.31 928.46 789.19 670.82 570.19 484.66 411.96 350.17 297.64
Depreciation 192.76 163.85 139.27 118.38 100.62 85.53 72.70 61.79 52.53 44.65 1032.07
Total Depreciation 215.76 184.55 157.90 135.15 115.71 99.11 84.92 72.80 62.43 53.56 1181.88
BIOMASS ASSESSMENT STUDY REPORT
FOR
2.28 MW BIOMASS BASED POWER PROJECT
AT
ANDAMAN & NICOBAR ISLANDS
SURYACHAKRA GREEN FUELS PRIVATE LIMITED
HYDERABAD
Prepared by
AQUATHERM ENGINEERING CONSULTANTS (INDIA) PVT. LTD.
CHENNAI – 600 004
INDIA
Table of Contents
Sl No. Description Page No.
EXECUTIVE SUMMARY 01 1. INTRODUCTION 03 1.1 Back Ground 03 1.2 Objective 04 1.3 Study Area 04 2. PROFILE OF ANDAMAN & NICOBAR ISLANDS 06 2.1 Demographic features 06 2.2 Soil 10 2.3 Climate 10 2.4 Fresh water for availability 12 2.5 Economic Censes 12 2.6 Banking 13 2.7 LPG Connections 14 2.8 Industries 15 2.9 Power 16 3. BIOMASS SOURCES 18 3.1 Agriculture Activities 18 3.1.1 Paddy(Rice) 21 3.1.2 Coconut 22 3.1.3 Arecanut Plantations 24 3.2 Forest 25 3.2.1 Outturn of Major Forest Produce 26 3.3 Biomass From Fresh & Empty Fruit Bunches 29 4. SURPLUS BIOMASS & PROJECT JUSTIFICATION 32
BIOMASS ASSESSMENT STUDY REPORT
1
EXECUTIVE SUMMARY
Suryachakra Power Corporation Limited presently owns and operates 20 MW Diesel based Power
Plant at Bamboo flat, Port Blair, Andaman & Nicobar Islands and proposes to establish a Biomass
based power plants in the Andaman & Nicobar islands as diesel power generation is costly and the
potential biomass as renewable energy has not yet been utilized to any measure in the A&N
Islands. .
Suryachakra Power Corporation Limited[SPCL], supported by a broad based Board of Directors,
has been successfully operating a diesel based 20 MW Power Plant at Port Blair, A&N Islands,
India. The project was launched with Technical Collaboration from M/s Caterpillar, USA and M/s
BSES (now Reliance Energy Ltd) and was funded by SREI and SBI, IFB, Kolkata. The project was
implemented by M/s BSES as an EPC Contractor. The main equipment was supplied by M/s KAK
Motoren GmBH, Germany, a division of M/s Caterpillar International Power Systems and a
subsidiary of Caterpillar Inc, USA. O & M was undertaken by M/s.Caterpillar Commercial Pvt.
Ltd. Fuel supply was linked with M/s Indian Oil Corporation Limited, under fuel linkage clearance
from Ministry of Petroleum. The Plant has been supplying uninterrupted power supply to
Port Blair, since April 2003
SPCL is a ISO: 9001-2000 certified company with a license to trade in electricity. The company is
on a massive drive for expansion of its activities and is in the process of setting up of 2x10MW
Bio-mass based power plants at Chattisgarh and Maharashtra. Presently, SPCL is in the process of
setting up of a 1000 MW Natural Gas based Power Plant and a Petrochemicals Complex at
Bhairavalanka, E.G.District, Andhra Pradesh.
As part of its expansion drive in the power sector, SPCL by virtue of its close association and
acquaintance with the Andaman & Nicobar island resources and requirements, appointed
M/s. Aquatherm Engineering Consultants India (P) Ltd., to conduct a Biomass Assessment Study
in the Andaman & Nicobar islands for setting up of Biomass plants at Garacharma, Dundas point near Jetty Village Bambooflat, South Andaman near Bambooflat, Hope Town Jetty.
BIOMASS ASSESSMENT STUDY REPORT
2
A detailed assessment of the identified sources of biomass generation – agriculture, plantation and
timber cuttings and saw dust has been made. The surplus biomass availability has been ascertained
from the following observations:
Surplus Biomass Availability all Sources
As about 1.32 kg can be converted into 1 unit of power generation. Therefore, the available surplus
biomass of 1,83,166 MTs can support a power generation unit of an installed capacity of 17.5 MW.
Based on the estimates, Suryachakra Green Fuels Private Limited, proposes to install 2.28 MW
biomass based power plant in the islands by supplementing the biomass with the following net fuel
ratio:
Particulars % Net Fuel Ratio
Napier Grass 50%
Bio mass 25%
Wood Chips/ Empty Fruit
Bunches or other bio mass
25%
The woodchips may be imported from main land or from neighboring countries such as Malaysia,
Indonesia etc. Therefore, it may summarized that the availability of biomass is not a constraint for
the setting up of a 2.28 MW biomass power plants at Garacharma, Dundas point near Jetty Village Bambooflat, South Andaman near Bambooflat, Hope Town Jetty.
S.No Source Quantity [MTs] 1 Crop residue 57135 2 Paddy husk 5832 3 Coconut fronds 56610 4 Coconut husk 40000 5 Coconut shells 10680 6 Arecanut 2589 7 Timber lops /saw dust 10320
Total 1,83166
BIOMASS ASSESSMENT STUDY REPORT
3
1. INTRODUCTION
1. INTRODUCTION 1.1 Back ground
From time immemorial man has been dependent on nature's bounty of Forest Wealth,
Agricultural Wastes, Fossil fuels to cater to his energy needs. With time and increasing
sophistication in his standard of living especially in the current century he has become more
and more dependent on electricity for running the wheels of his civilization. Most of the
electricity till now is generated from fossil fuels in large power plants using coal, oil or by
nuclear fuels. However, continuously increasing use of fossil fuels has dangerously depleted
the availability of these natural resource. It has further seriously strained our national
economy through recurring payments to meet the bills incurred on the import of oil and
other fossil fuels required to sustain the ever increasing demand requirements. As on date
the price of petrol in the international markets is hovering around US$ 70 to 75 per barrel.
Faced with these constraints of energy availability and usage, man has been earnestly
exploring for effective utilization of alternate energy sources like the sun, wind, biomass,
gober gas, municipal and agricultural waste to fulfill his energy needs.
With a view of recovering and utilizing Biomass energy to cater to the demands of power
generation and to supplement the existing power capacity to meet the increasing power
demand of South Andaman M/s. Suryachakra Green Fuels Private Limited has entrusted
M/s. Aquatherm Ltd to study and assess the surplus quantity of Biomass and other available
fuels. This report will provide the basic information required for assessing the availability of
biomass.
1.2 Objective
The objectives of the biomass assessment study are: (i) To identify different types of biomass being generated in different islands and their
suitability for power generation.
BIOMASS ASSESSMENT STUDY REPORT
4
(ii) To study the production, consumption and surplus availability of biomass in the area of interest.
(ii) To make quantitative assessment and estimation of various types of Biomass availability along with details of present use of such biomass.
(iv) Also, highlight the availability and import of wood chips from main land and neighboring countries Malaysia and/or Indonesia to supplement the available biomass and ensure sustainability of the power generation.
1.3 Study area
The availability of Biomass from different services in different islands is compiled to
determine the capacity of power plant that may be established and operated on a continuous
basis at Garacharma, Dundas point near Jetty Village Bambooflat, South Andaman near
Bambooflat, Hope Town Jetty. The length of the Andamans is 467 km with an average
width of 24 km, whereas the maximum width is 52 km. The length of the Nicobar Islands is
259 kms with a maximum width of 58 kms.
Therefore, the available sources of biomass have been considered as Andaman & Nicobar
Islands. However, it may be noted that most of the population is settled in and around Port
Blair.
1. Major sources of biomass are the wood based industries. Agricultures is a significant source only in certain areas, especially in the Nicobar group of islands.
2. Even among the wood based industries, only the larger ones show potential. The smaller ones are facing an uncertain future with the Forest Department curtailing supply of wood to the entire industry.
[
3. The difficulty, however, in the case of the above biomass, is unlike in the mainland, where these wastes have some commercial value and therefore a collection, transporting and a trading channel, none exists in these islands. Therefore, a mechanism to collect these wastes is required.
4. In addition, any collection mechanism has to take into account accessibility of the
area or island. However, in general, biomass from agriculture is concentrated in an narrow area within an island.
5. In Great Nicobar, where some potential exists for using the biomass generated from
coconut and arecanut plantations, the farmers and traders are more interested in copra dryers than in producing power from waste.
BIOMASS ASSESSMENT STUDY REPORT
5
2. PROFILE OF ANDAMAN & NICOBAR ISLANDS
2. PROFILE OF ANDAMAN & NICOBAR ISLANDS 2.1 Demographic features
Andaman & Nicobar Islands [A & N] is one of the Union Territories of the Republic of
India. A&N islands are situated in Bay of Bengal spreading like a broken necklace in the
North-South direction and are located between 6° 45" and 13° 41" North latitudes, and
between 92° 12" and 93° 57" East longitude. Islands located north of 10° N latitude are
known as Andaman group of Islands while islands located south of 10° N latitude are called
Nicobar Islands. Total geographic area of islands cover 8249 sq.km of which Andaman
group of islands cover 6408 sq.km and Nicobar group cover 1841 sq.km.
The length of the Andamans is 467 km with an average width of 24 km, whereas the
maximum width is 52 KM. The length of the Nicobar Islands is 259 KM with a maximum
width of 58 KM.
The Andaman & Nicobar Islands are administratively divided into two districts and are
physically separated by the 145Km wide 10o channel. The total geographic area of the
Islands is 8249 Sq. Km. Of this the Andamans has anarea of 6408 Sq. Km. and the Nicobars
1841 Sq. Km. (Table 1.1)
The Andaman district is divided into 5 tehsils namely, Diglipur, Mayabunder, Rangat,
South Andaman and Little Andaman. The South Andaman is further bifurcated into Port
Blair and Ferragunj tehsils. The six tehsils are comsposited into three blocks. The North
Andaman block includes Diglipur tehsil and part of the Mayabunder tehsil and comprises
63 inhabited villages. The Middle Andaman consists of [part of Mayabunder and the Rangat
Tehsils] with about 100 inhabited villages. The South Andaman block comprises 157
inhabited villages drawn from the Ferrargunj, Port Blair and Little Andaman tehsils.
BIOMASS ASSESSMENT STUDY REPORT
6
Administratively A& N islands are classified into 2 districts- Andaman district and Nicobar
district. These two districts have four [4] sub-divisions and 7 tehsils. There are three [3]
towns in the islands. Out of the total 556 islands and islets only 38 islands are inhabited.
A&N islands are classified
S.No. Particulars Unit 2001 1. Total Area Sq.km 8249 a. Andaman District “ 6408 b. Nicobar District “ 1841 2. Urban Area “ 16.64 3. Rural Area “ 8232.36
S.No. Particulars Unit 2001
1. Sub-Divison-Wise Area Sq.Km a. Mayabunder “ 3428 b. South Andaman “ 2980 c. Car Nicobar “ 129 d. Nancowry “ 1712 2. Tahsil-Wise Area a. Diglipur “ 884 b. Mayabunder “ 1348 c. Rangat “ 1070 d. Ferrargunj “ 1085 e. Port Blair “ 2021 f. Car Nicobar “ 129 g. Nancowry “ 1712
Population. Almost every state of the country has been represented in the population of these islands. Indeed, it is truly a miniature India. The total population as per the 1991 census is about 2,80,661. Of this 2,05,706 is rural and the rest is urban. Of the total population about 2,41,453 (86%) is in the Andaman group of islands. The Nicobars account for 39,208 (14%), all of which is rural.
Unlike the mainland, the density of population (no. of people per Sq. Km.) is very low. However, in the last two decades, the pressure of population has begun to rise
BIOMASS ASSESSMENT STUDY REPORT
7
BIOMASS ASSESSMENT STUDY REPORT
8
Area wise population
The total population of the A& N islands as per 2001 census was 3,56,152 . The details of the population as rural and urban population and also district wise and Tehsil wise distribution are explained in the following tables.
Population Details
Sl.No. Particulars Unit 1981 1991 2001 1 2 3 4 5 6
1. TOTAL POPULATION No. 188741 280661 356152 a. Male “ 107261 154369 192972 b. Female “ 81480 126292 163180 2. RURAL POPULATION “ 139107 205706 239954 a. Male “ 78401 111986 128961 b. Female “ 60706 93720 110993 3. URBAN POPULATION “ 49634 74955 116198 a. Male “ 28860 42383 64011 b. Female “ 20774 32572 52187 4. SCHEDULED TRIBE
POPULATION “ 22361 26770 29469 a. Male “ 11586 13750 15127 b. Female “ 10775 13020 14342
District wise population
Sl.No. Particulars Unit 1981 1991 2001 1. Andaman District No. 158287 241453 314084 a. Male “ 90446 133058 170319 b. Female “ 67841 108395 143765 2. Nicobar District “ 30454 39208 42068 a. Male “ 16815 21311 22653 b. Female “ 13639 17897 19415 3. TAHSIL-WISE
POPULATION “ a. Diglipur “ 15702 23734 42877 b. Mayabunder “ 13954 21570 23912 c. Rangat “ 24289 33368 38824 d. Ferrargunj “ 28013 39277 48626 e. Port Blair “ 76329 123504 159845 f. Car Nicobar “ 15486 19336 20292 g. Nancowry “ 14968 19872 21776
BIOMASS ASSESSMENT STUDY REPORT
9
4. LITERATE POPULATION “ 97321 171086 253135
a. Male “ 62983 103377 146831 b. Female “ 34338 67709 106304 5. SEX RATIO “ 760 818 846 6. DENSITY OF
POPULATION “ 23 34 43 7. WORKING
POPULATION “ 69612 98901 136254 a. Male “ 60828 82317 109162 b. Female “ 8784 16584 27092 8. MAIN WORKERS “ 62680 90807 113607 a. Male “ 58549 80665 97349 b. Female “ 4131 10142 16258 9. MARGINAL
WORKERS “ 6932 8094 22647 a. Male “ 2279 1652 11813 b. Female “ 4653 6442 10834 10. NON-WORKERS “ 119129 181760 219898 a. Male “ 464333 72052 83810 b. Female “ 72696 109708 136088
2.2 Soil
The soil cover is thin, varying from 2m to 5m. It is mostly alluvial on hill-tops and diluvial
In ridges and valleys. The coastal flats have an admixture of sand, silt clay and diluvial
material with fine fragments of coral lime. The soil is in general, mild to moderately
acidic with high humus on top.
2.3 Climate
The A&N Islands are situated in the tropical zone and experience a tropical humid
climate. However the land and sea breezes that are characteristic of islands keep the weather
pleasant. These islands have a tropical climate, which is warm, moist and equable. The
mean minimum temperature and maximum temperature recorded during the year 2005 were
24.3 and 30.5 respectively. The proximity of the sea and the abundant rainfall prevent
extremes of heat. The normal rainfall at port Blair is 3180 mm and the actual rainfall
recorded during the year 2005 was 3773.8 mm. The rainfall details at port Blair during the
period 2002 and 2005 are as mentioned below:
BIOMASS ASSESSMENT STUDY REPORT
10
Year wise Rainfall at Port Blair [A&N Islands]
S.No Year Rainfall[mm]
1 2002 2617.4
2 2003 2443
3 2004 3188.7
4 2005 3773.8
Source: Directorate of Economics & Statistics, A&N Islands
Rainfall at Various Stations
Actual Rainfall(mm.) Station 2002 2003 2004
Mayabunder 3571.1 2658.2 2836.2 Long Island NA NA 1583.3 Port Blair 2617.4 2443 3188.7 Hut Bay 1575.5 2642.4 2446.3 Car Nicobar 1661.1 2657.1 1772.2 Nancowry 2240.8 2101.7 2422.2 Kondul 2056.4 2548.7 2599.0
Source: Directorate of Economics & Statistics, A&N Islands
The average rainfall is received from southwest and northeast monsoons, which extend over
a period of eight months.
The average mean relative humidity at port Blair during the year 2005 was 88.5%. The
humidity is high and ranges between varying from 66 to 88% during a year. In normal
conditions the mean wind speed is 5.8 km per hour. The wind speeds are high during May
to September period, even touching 12 to 14 kms per hour. It ranges from 4.2 kms per hour
during October to 6.6 kms per hour during December before dipping to about 3.5 kms per
hour during March- April.
2.4 Fresh water for availability:
The physiography of these islands is characterized by undulating topography and
intervening valleys. There are, however, some flat islands like Car Nicobar and Trinket.
There is no major perennial fresh water river in these islands except Kalpong in North-
Andaman, Alexendra, Dagmar, Galathia rivers in Great Nicobar. There are several rain fed
BIOMASS ASSESSMENT STUDY REPORT
11
streams which dry up in summer. The coastal line of these islands is wavy with large
number of bays, lagoons, serpentine creeks and extend to about 1961 KM. At several
places tidal creeks perpetrates for inside the land and farm out lets for fresh water streams.
2.5 Economic Censes
The summary of economic Censes [1998] is presented as below:
Rural Urban Combined Type of Enterprises Number % Number % Number % Agricultural Activities
1.All Enterprises a)Own Account Enterprises b)Establishments
353 241 112
92.4191.6394.12
29 22 7
7.59 8.37 5.88
382 263 119
100 100 100
2.Persons Usually Working a)Own Account Enterprises b)Establishments i. Total ii. Hired
894 395 499 468
91.8891.22 92.4193.91
79 38 41 33
8.12 8.78 7.59 6.59
973 433
540 501
100 100 100 100
Non – agricultural Activities 1.All Enterprises a) Own Account Enterprises b) Establishments
8522 5791 2731
63.8774.5249.01
4821 1980 2841
36.13 25.48 50.99
13343 7771 5572
100 100 100
2. Persons Usually Working a)Own Account Enterprises b)Establishments i. Total ii. Hired
36514 12305 24209 23011
59.2181.21 52.0353.25
25156 2835 22321 20203
40.79 18.73 47.97 46.75
61670 15140
46530 43214
100 100 100 100
Agriculture & None-agriculture Activities
1.All Enterprises a) Own Account Enterprises b) Establishments
8875 6032 2843
64.6675.0849.96
4850 2002 2848
35.34 24.92 50.04
13725 8034 5691
100 100 100
2. Persons Usually Working a)Own Account Enterprises b)Establishments i. Total ii. Hired
37408 12700 24708 23479
59.7281.55 52.4953.71
25235 2873 22362 20236
40.28 18.75 47.51 46.29
62643 15573
47070 43715
100 100 100 100
BIOMASS ASSESSMENT STUDY REPORT
12
2.6 Banking
The details of all India financial institutions, commercial banks, and cooperative banks
operating from A& N are mentioned below
Details of Banks
Sl. No. Name of Bank No. of
Offices/Branches 2005
A. ALL INDIA FINANCE INSTITUTION 1. National Bank of Agriculture & Rural
Development(NABARD) 1
2. Housing & Urban Development Corporation (HUDCO) 1
B. COMMERCIAL BANK 1. State Bank of India 20 i).Total Branches 18
Andaman Dist.=16 Nicobar Dist. = 2
ii).Total Offices a) Lead Bank Office. b) Regional Office.
2
2. Syndicate Bank 5 3. Canara Bank 1 4. Indian Bank 1 5. Punjab National Bank 1 6. UCO Bank 1 7. Indian Overseas Bank 1 8. Allahabad Bank 1 9. United Bank of India 1 10. Vijaya Bank 1 11. Bank of Baroda 1
C. CO-OPERATIVE BANK 1. UTI Bank 1
D. CO-OPERATIVE BANK 1. A & N State Co-Operative Bank Ltd. 30
Andaman Dist.=25 Nicobar Dist. = 5
BIOMASS ASSESSMENT STUDY REPORT
13
2.7.1 LPG Connections
The usage of Liquefied petroleum Gas [LPG] is an important parameter which can
contribute in the estimation of biomass that may be available by taking into account the
domestic fuel wood consumption
LPG Connections
LPG Connections during 2005 S.l. No. Particulars Andaman
District Nicobar District Total
1. No. of New Connection released (Consumers) Urban 1705 189 1894 Rural 2898 --- 2898 Total 4603 189 4792 2. No.of Connections (Consumers) Transferred from Mainland Urban 926 --- 926 Rural --- --- --- Total 926 --- 926 3. Total Connections (Consumers) Released during 2005 Urban 2631 189 2820 Rural 2898 --- 2898 Total 5529 189 5718
2.8 Industries
The details of industries as large, medium or small and the industrial centers or estates that
are established in the islands are in the A&N islands are presented in the following sections.
No. of Industries in Andaman & Nicobar Islands (As on)
Type 31.3.01 31.3.02 31.3.04 31.12.05 Large/Medium Scale Industries 5 5 5 5
Small Scale Industries 1361 1421 1536 1747
Industrial Centre 15 10 10 15 Industrial Estate 6 7 7 7
BIOMASS ASSESSMENT STUDY REPORT
14
Industries Unit (No)
2.8 POWER
Diesel, kerosene and fuel wood are the major sources of energy in the Islands. Of this diesel is
used in power generation and transport (both by water and road), kerosene for cooking and fuel
wood for industrial and domestic uses.
Electricity is generated in the Islands mainly by the Department of Electricity. Some power is
also generated by the defense services and by some industries for their own use. Almost the
entire electricity generated is by diesel generators. The total installed capacity in the Islands is
about 29.829 MW and the total units generated were 7,44,34,403 KWh. This works out to a
plant load factor The overall specific fuel consumption in the Islands for power generation is
about 0.30 l/kWh. This means on an average about 65 KL of diesel is consumed per day for
power production alone by the Department of Electricity. The purchase price of diesel from
Indian Oil Corporation is about Rs.9.56 per litre of diesel. The landed rate at the different
islands, however, could vary depending on distance, mode of transport, accessibility. On an
average, as per the Department of Electricity the landed cost works out to Rs.11 per litre of
diesel. Thus the daily outgo on account of diesel alone is Rs.7.15 lacs or Rs.26 crore per year.
This section presents the installed capacities, generation and consumption, status of electrified
villages and the Tehsil wise villages no of villages that have been electrified.
2001-02(As on 31.3.2002) 2002-03(As on 31.3.2003) Type South
Andaman Middle Andaman
North Andaman
Nicobar Islands
Total South Andaman
Middle Andaman
North Andaman
Nicobar Islands
Total
Wood Based 181 23 30 4 238 182 23 31 5 241 Agro Based 89 16 9 13 127 91 17 9 16 133 Marine Based 52 3 4 3 62 54 3 4 3 64 Food Based 69 14 11 9 103 72 16 12 10 110 Mineral Based 62 6 6 - 74 63 6 9 - 78 Chemical Based 39 - - - 39 39 - - - 39 Engineering Based 277 13 8 2 300 290 19 11 4 324 Leather Based 8 1 - - 9 8 1 - - 9 Textile Based 88 5 3 1 97 93 8 3 4 108 Coir Based 2 - - - 2 2 - - - 2 Miscellaneous 275 59 31 5 370 299 74 43 7 423 Total 1142 139 103 371 1421 1193 167 122 49 1531
BIOMASS ASSESSMENT STUDY REPORT
15
Installed Capacity Installed Capacity KW 64045 Generation KWH 157589961 Consumption KWH 112896344 Village Electrified (No.) 317
From the table it may be noted that 317 villages heve been electrified and that the installed capacity is only around 64 MW.
Electricity Generation in Urban/Rural Area Generation (KWH) Year Urban Rural A&N Islands
2001-02 94331869 37588839 131920708 2002-03 100075333 38529331 138604664 2003-04 117789952 39800009 157589961
Electricity Consumption in Urban (Headquarter)/ Rural Area
Generation (KWH) Year Urban Rural A&N Islands 2001-02 70325041 27084176 97409217 2002-03 73545741 28230361 101768102 2003-04 84613470 28282874 112896344
The following table presents the year wise generation and consumption of power
Generation & Consumption 2002-03 2003-04
Installed Cap (KW)
Generation (KWH)
Consumption (KWH)
Installed Cap (In KW)
Generation (KWH)
Consumption (KWH)
36762 128102110 93508875 56189 139383537 104572788 7293 10501554 8259227 7856 18200424 8323556 44055 138604664 101768102 64045 157589961 112896344
District-Wise/ Tehsil-wise No of Electrified Villages
No. of Villages Electrified as on District/Tahsil 31.3.02 31.3.03 31.3.04 Diglipur 31 31 30 Mayabunder 48 48 37 Rangat 68 68 49 Port Blair 83 83 44 Ferrargunj 78 78 59 Andaman District 308 308 219 Car Nicobar 16 16 16 Nancowry 155 155 82 Nicobar District 171 171 98 Total A & N Islands 479* 479* 317
BIOMASS ASSESSMENT STUDY REPORT
16
3. BIOMASS SOURCES
3 BIOMASS
The possible sources of biomass in the district are
A. Agriculture and plantation B. Forest cuttings and wood based industries
3.1 Agriculture Activities
As mentioned earlier, the soil is mostly an admixture of sand, silty clay and diluvial with
fine fragments of coal lime. It is mild to moderately acidic with high humus on top.
Agriculture is mostly dependent on rainfall as there are no perennial rivers and no canal
system. As there are abundant rains, about 3000mm spread over 8 months in a year there is
enough opportunity for agriculture development.
Land use pattern is available only for Andaman Group of islands. Total geographical area of
Andaman & Nicobar islands put together is around 8,24,900 Hectares out of which the land
under forest is 7,17,069 hectares and the area under cultivation is about 50,000 hectares. Of
the total geographic area of the islands nearly 87% is under forest cover. Most striking
feature of the islands apart from sea and beaches is its forest wealth.
The fallow land area is 1632 hectares.
Land Utilization of Andaman District (As per Agriculture Census 1990-91)
Sl.No. Type of Land Unit 1990-91 1. Culturable Waste Hect 1241.645 2. Current Fallow Land “ 1136.236 3. Other Fallow Land “ 3854.808 4. Net Cropped Area “ 19182.276 5. Total Cropped Area “ 20318.512
BIOMASS ASSESSMENT STUDY REPORT
17
Paddy is cultivated in10734.92 hectares and coconut cultivation is done in 25661 hectares.
Paddy is the major crop with an output of 29,192.23 MT. The recovery of rice is about 60%
and the approximate production of rice husk and bran is 9,921MT. As per the average crop
residue ratios, the crop residue for paddy is estimated as 1.5 times the produce. The quantity
has been included in the biomass residues from crops.
The year wise production details of crops and the estimated biomass that may be generated
from the available data have been presented in the following sections.
BIOMASS ASSESSMENT STUDY REPORT
21
The Zone-wise Area & production of different crops during the period 2004-2005 are as listed below:
YEAR WISE AREA AND PRODUCTION OF DIFFERENT CROPS
Source: Department of Agriculture, Andaman & Nicobar Islands
S. NO.
Name of Crop 2000- 2001 2001-02 2002-03 2003-04 2004-05
Area(Ha) Prodn[MTs] Area(Ha) Prodn[MTs] Area(Ha) Prodn[MTs] Area(Ha) Prodn[MTs] Area(Ha) Prodn[MTs] 1 2 3 4 5 6 7 8 9 10 11 12 1. Paddy 10881 32184 9801 27333 10885 32111.66 10561.37 30850.868 10734.92 29192.230 2. Pulses 670 449 420 200 1282.46 641.23 696.15 360.63 710.40 368.546 3. Oil Seeds 133 55 46 25 85.10 40.31 86.29 35.81 90.30 46.608 4. Vegetables 4244 25465 4250 21250 5572.67 31226.41 4730.70 23760.00 5738.24 22768.217 5. Coconut
[mill nuts] 25160 89 25205 89.68 25300 94.32
25394.74 95.24
25551.40 87.13
6. Arecanut 4354 7200 4354 7300 4363 7350 4379 6707 4425.37 4781.05 7. Fruits 4087 21000 4136 22350 4196 22141.02 4527 26062 4083.37 23436.23 8. Pepper 430 83 450 85.50 550 116 572.50 120.23 655 120.22 9. Clove 94 4.00 95 4.09 123.81 56 187.70 8.50 195.95 11.63 10. Cinnamon 50 6.60 53 6.99 57 798 80.20 11.25 103.44 14.43 11. Cashew
nut 800 219 800 225 800 232 833.50 234.64 800.00 223.00
Total 50906 86758.6 49615 78875.26 53222.04 94814.95 52058.15 88256.168 53099.38 81061.29
BIOMASS ASSESSMENT STUDY REPORT
22
Year-wise Biomass Generation
[MTs]
S. No. Crop 2002-03 2003-04 2004-05 1. Paddy 48167.49 46276.3 43788.345
2. Pulses 961.845 540.945 552.819
3. Oil Seeds 60.465 53.715 69.912
4. Vegetables 46839.62 35640 34152.3255
5. Fruits 33211.53 39093 35154.345
6. Pepper 174 180.345 180.33
7 Clove 84 12.75 17.445
8 Cinnamon 1197 16.875 21.645
9. Cashewnut 348 351.96 334.5
Total 142210.4 132369.3 114271
From the above table, the availability of biomass from the agricultural crops excluding coconut and arecanut is 1,14,271 MTs per year. Therefore, taking into account of more than 50% consumption for existing purposes of cattle feed and other utilization pattern, 57135 MTs of crop residues has been considered to be available. The most important source of Biomass for the power generation is from Agriculture and Plantations. Zone wise Area and production of different crops for 2004-05 are given below. Detailed study on the major agricultural crops has been made by a team of experts. A. Paddy B. Coconut plantations C. Arecanut D. Jatropha
3.1.1 Paddy (Rice):
Paddy is cultivated during rainy season. Harvesting is done by cutting the panicle (ear that bears the grain) leaving the straw in the field. The average productivity is only 2.95 tons per hectare. In view of the current practice of harvesting only the panicle the Biomass from this source is very limited. As there are no rice mills for paddy milling there is not single point source for rice husk.
Even otherwise also the husk generation from 10000 MT of paddy will be about 2000 MT. Based on the paddy cultivation quantity of 29192.230 MTs per year, the estimated husk availability is 5832 MTs per year.
BIOMASS ASSESSMENT STUDY REPORT
23
3.1.2 Coconut:
The important source of Biomass is coconut plantations. The total area under coconut cultivation in A&N Islands is 25160 hectares. The average productivity is about 3500 nuts per hectare. The actual production of nuts during the year 2004-2005 was 89 million nuts. There is one unit M/s Integrated Coco Products Pvt Limited, which is consuming whole coconuts for producing coconut based products. The purchase price of coconut is about Rs.5 per nut. The main Biomass from coconut plantations is from:
A. Fronds
B. Husk
C. Shells
A. Fronds:
Fronds are palm leaves that are shed periodically. On an average a palm sheds 10 to 12 fronds per year. The average weight of dried frond is about 2.5 to 3.0 kg. Every hectare of plantation would produce on an average 4.5 Ton dry fronds. Total availability of Biomass due to this source (fronds) is estimated as below: 4.5 tons per hectare x Area in hectares 25160 = 1,13,220 MTs per year.
As there is no system of collection of these fronds, the fronds are left on the soil for decomposing and making the land fertile. By providing proper returns part of this Biomass can be a source of employment for the rural population. Even if 50% can be collected the Biomass from this source is about 56,610 MTs of biomass would be additionally available. An effective collection mechanism and effort is needed to collect the fronds.
B. Husk:
Husk is protective covering made up of fibers that surrounds the coconut. It is 4'f"b removed to expose the nut. The average weight of sun dried husk is about 450 gms. Therefore the total 'production of husk from 8,90,00,000 would be about 40,000 MT per year. This biomass is not being of any use and most of it is dumped in the fields. Hence this source can be treated as available Biomass.
C. Shells:
Shell is the hard covering that protects the kennel inside. The coconut size in Andaman is
large as compared to those generally available at other places in mainland and therefore
shells are also large. The average weight of shells of one coconut is about 200 gm. At
present these shells are used for drying the coconuts to copra in kilns (Bhattis). A variety of
BIOMASS ASSESSMENT STUDY REPORT
24
crude methods are adopted to convert coconuts to copra. In the Nicobar tribal areas the husk
on the coconut is removed first. Then the coconut is broken to two halves. They are placed
on a grill about 3 ft. above the ground. Coconut shells are placed underneath the grill and
set fire to. The slow heat from the burning shells dries the coconut kernel into copra. The
quality of copra so produced is poor as it is susceptible to fungus growth. This process takes
3 to 6 days and each batch having 500 to 600 coconuts.
In another method is shells are heated in a closed kiln using shells to give the heat for
drying. About 1500 to 1700 shells are required to dry about 5000 broken nuts. Therefore the
net requirement of shells in the process is 30 to 40%. Therefore, 60% of he shells produced
are wasted and this quantity can be used as Biomass for the power generation. Total
quantity of shells produced in the Islands is estimated as below;
Total Qty. of Shells = No of nuts 8,90,00,000 X 0.2 MTs
1000
= 17800MT per year
After deducting the quantity of shells used for drying, the quantity available for power
generation is 60% of the above = 10680 MT per year.
Therefore, the total quantity of biomass available from coconut plantation, after taking into account the present utilization and consumption pattern, and considered as available for power generation is summarized as below:
S. No Biomass Source Quantity[MTs] 1 Fronds 56,610 2 Husk 40,000 3 Shells 10,680 Total 107,290
The total quantity of biomass available from coconut plantation is 107,290 MT per year. This total 1,07,290 MTs of biomass at the rate of 1.2Kg. of biomass per Kwh of electric
power produced and assuming 7200 hrs every year, this represents a power production
potential of 10 MW.
BIOMASS ASSESSMENT STUDY REPORT
25
3.1.3 ARECANUT PLANTATIONS:
Areca nut is one of the important commercial crops of A&N Islands. Because of better
returns, there is a preference to go for Areca nut plantations. The total area under Areca nut
in the islands is approximately 3596 Ha. The total production of nuts is 5143 MTs per year
based on an average productivity rate of 1.43 MT/Ha.
The husk of Areca nut is a valuable source of Biomass. At present the nuts are not
processed after de-husking and the husks are thrown away as waste. The average weight of
husk from one areca nut is 5gms. A palm produces about 120 nuts a year. Every hectare has
about 1150 to 1250 palms.
Therefore, the total nuts produced in the islands may be estimated as follows:
= 1200 palms x 120x 3596 hectares = 517824 X 103
Since each nut has about 5 grams of husk, the total husk available as Biomass has been
considered as = 5x517824 Kg=2589120 Kg. = 2589 MT/Year.
By proper encouragement and providing organized support to the rural poor, biomass
through this source, can be effectively utilized for power generation. This will provide
social upliftment and improving standard by rural poor and agricultural labor. The potential
for power generation from Arecanut husk is about 290 kw and units generated annually 17
lakhs units. From this information It is seen that the potential for power generation from
coconut & Arecanut plantations alone is about 10 MW.
The plantation details of rubber & red oil palm are mentioned as below:
Area and Production of Rubber & Red Oil Palm
Production of Rubber Production of Red Oil Palm Area Production Area Oil Production Year
Hect. MT Hect. MT 2001-02 960.00 353 1593 1840 2002-03 959.82 436 1593 1697 2003-04 747.55 486 1593 2041
This source of biomass is considered to be included in the crop residues and has not been
considered separately. Therefore, the total availability of biomass from the various agricultural
activities may be summarized as follows:
BIOMASS ASSESSMENT STUDY REPORT
26
Surplus Biomass Availability from Agricultural & Plantation Sources 3.2 FOREST
Forest account for 87% of the total geographic area of the Islands and there is sufficient
scope for
the biomass collection from dead trees, fallen trees and woodcuttings from extra grown branches.
Forest area in Andaman and Nicobar Islands
(Area sq.kms) Particulars 2001-2002 2002-2003 2003-04 2004-05 2005-06 Reserved Forest 2929 2929 2929 2929 2929 Protected Forest 4242 4242 4242 4242 4242 Total 7171 7171 7171 7171 7171
Source: Forest Department
The total forest area has consistently been maintained at 7171 sq km for the last several years. A& N islands is home to some of the best tropical forest in the country and boasts of a
variety of wood, soft wood and ornamental wood.
The division wise forest area as on 31st March 2006 in sq.km has been presented as below:
S.No Source Quantity [MTs] 1 Crop residue 57135 2 Paddy husk 5832 3 Coconut fronds 56610 4 Coconut husk 40000 5 Coconut shells 10680 6 Arecanut 2589
Total 1,72,846
BIOMASS ASSESSMENT STUDY REPORT
27
Division-wise Forest area as on 31st March 2004 (in Sq.Kms)
Source: Forest Department, A & N Islands
Timber from forests is extracted by the Forest Department and supplies logs to saw mills
and also exports to mainland.
3.2.1 Outturn of Major Forest Produce
The following table highlights the availability of various types and quantities of timber available in A& Nicobar Islands.
Availability of category–wise timber (Logs)
Availability of Timber (In cub. mtr.) Category 2001-02 2003-04 1 Ornamental Wood 646.75 1802.505 2 Superior Hardwood 2479.251 5925.899 3 Standard Hardwood 596.224 9494.562 4 Soft Wood 989.223 8869.794 5 Miscellaneous
Hardwood ----- 46.424 6 Miscellaneous
Softwood ----- ------ Total 4711.448 26139.184
Source: Directorate of Economics & Statistics
The data on availability of timber indicates that timber availability has actually increased from a
very low 4711 MTs in the year 2001-02 to 26139 MTs in the year 2003-04. Also, the major portion
of the total available timber is hard wood timber. The soft wood and superior hard wood are the
other types of timber widely available in the islands.
Forest Area Division Geographical Area Reserved Protected Total
South Andaman 1665 1208.28 111.66 1319.94 Baratang Middle 721 646.51 --- 646.51 Andaman 965 53.07 804.05 857.12 North Andaman 2325 314.41 1784.15 2098.56 Little Andaman 732 706.49 --- 706.49 Islands 1841 --- 1542.07 1542.07 Total 8249 2928.76 4241.93 7170.69
BIOMASS ASSESSMENT STUDY REPORT
28
The forest department is responsible for maintenance and regeneration of forests and logging. Most
of the logging activity takes place in Andaman group of Islands. During logging operations lot of
Biomass is generated in the form of tops and lops there is no agency to collect these woodcuttings
and are left as it is for decomposition. It is estimated that an average of 20% of the logs will be
available as lops and tops.
The table showing Agency wise Timber extraction in A&N Islands (in cubic meters) is shown in
another table showing the outturn of Major Forest Produce is shown below:
Agency-Wise Timber Extraction ( In cub. Mts.)
Government Year Dept.
Opern Work Contract
Total Private payment Royalty
Concessional Rate
Forest Plantation Dev Corporation
Total
1996-97 59205 555 59760 3728 698 43583 107769 1997-98 49439 --- 49439 --- 157 27501 77097 1998-99 35082 --- 35082 3 42 27507 62634 1999-00 25603 --- 25603 --- 22 22009 47634 2000-01 18002 --- 18002 --- 6 22060 40068 2001-02 4711 2002-03 -- 2003-04 --
Based on the estimation of 20% of lops and tops from the timber cutting, the available fuel
wood may be estimated as mentioned below:
( in cubic meters)
Year Timber (Logs) Fuel wood 2000-2001 40067 328162001-2002 4711 151482002-2003 --- 16762003-2004 --- 65312004-2005 -- 11000
From the above data it is possible to generate Biomass to the extent of 11000 cubic meter
from Forest produce on an average by suitable collection and transportation system. A cubic
meter of timber weighs about 600 kg. Therefore, based on 11000 Cubic meters of wood, an
estimated as 6600 MTs
BIOMASS ASSESSMENT STUDY REPORT
29
Another source of Biomass is wood based industries from the timber supplies to saw mills.
Wood cuttings can be used as fuel for Biomass power plants. At present, part of this
Biomass is used in saw mills as fire wood for drying, seasoning etc. Wood based industries
are either saw mills that produce planks for the construction or for furniture making
industry.
Saw mills process logs into planks. During the process they produce bark, end cuts. Sawn
timber is presently used as fuel wood. Presently, the Chatham saw mill and the Betapur saw
mill are only working. In the A& N districts, the wood cutting is banned. However,
harvesting from plantation is permitted. No naturally grown trees are allowed to be cut.
The intake and out turn of saw mills in the islands are mentioned below:
Intake and Out-turn of Govt. Saw Mills
(In cub. Mtr.)
Chatham Saw Mill Betapur Saw Mill Year Intake Outturn % Outturn Intake Outturn % Outturn 2001-02 6900 3151 45.67 1182 604 51.09 2002-03 5799 2561 44 1442 591 41 2003-04 9353 4516 48.28 1442 591 40.98
From the above the yield is about 48 to 41% ad the rest is waste generated in the mills out
of the waste generated. The composition is described as below:
Bark-<5%
End cuts & sawn timber waste - 25% to 30%
Saw dust - 8%
However, there is high moisture content in the above Biomass, which has to be considered
while assuming the Biomass. As per the above table the waste available is about 6238 cu.
mtrs and @ 600 Kg. Per cubic meter biomass available is about 3728 MTs per year. Though
this quantity is not significant this may considered as available surplus Biomass for the
power generation at present.
BIOMASS ASSESSMENT STUDY REPORT
30
3.3 Biomass From Fresh & Empty Fruit Bunches
The oil palm bears fruits jn bunches that have to be processed within 24 hours of harvest.
These bunches are called Fresh Fruit Bunches (FFB). A bunch contains about 600 to 1500
fruits depending on the size. The fruits are held in the bunch tightly even at harvest.
The harvest FFBs are taken to the plant for further processing. FFBs are sterilized by steam
and threshed to separate the fruits from the bunch. The empty bunches are sent to an
incinerator for destruction. The fruits are then crushed to recover the oil from the mesocarp
(fibrous parts). The nut is then separated from the fibres and shelled. The resulting seed or
kernel is then sold to private processors to extract kernel oil. Thus, the oil palm yields oil
from the mesocarp (ROP) and also kernel oil. The waste matter produced in the process are,
empty fruit bunches, fibre and shell. In the following paragraphs we shall discuss each one
of them.
Break-up of an FFB
Empty Fruit Bunch 40-50%
Oil 17-19%
Fibre 18% Nut Shell 7.3% Kernel 4%
Empty Fruit Bunches
Empty fruit bunches form 50% of the weight of the FFB. This weight is on a wet weight basis. As per the details provided by the plant-in-charge, the plant crushes about 10-11,000 t of FFB per year of about 300 working days. The no. of shifts works out to about 400 per year.
FFBs Are Steam Cooked
At 50% of the FFB the empty fruit bunch available per year is about 5500 MT. The actual
quantity that was available in 1996-97 as per the plant records was 4749.09 MT (Table 2.1).
This was on a wet weight basis. As per our estimation, the empty fruit bunch contains about
60-65% by way of moisture. Therefore, on a dry weight basis the empty fruit bunches
would amount to 1899.63 MT. or about 1900 tpa. This entire quantity would be available at
BIOMASS ASSESSMENT STUDY REPORT
31
the plant itself. The quantity of empty fruit bunches is however, directly linked, as all other
biomass is also to the yield An Empty FFB After Steam Cooking of the plantations. The
empty fruit bunches that come out after threshing is wet and would have to be dried to the
desired level of moisture before use. Since sun drying is not possible during the extended
period of the monsoon, a facility to dry these bunches would be essential.
Fibre & Nut Shells
After the fruits have been separated from the bunch, they are crushed to expel the oil. This
oil cake is then broken and beaten to separate the fibre from the nut. The amount of this
fibre in a FFB is about 18%. Based on an average crushing of about 10000 tpa, this works
out to 1800 tpa. During the years 1993-94 to 1995-96, the plant produced 1680, 1953, and
1633 tpa of fibre. However, the plant consumes fibre and nut shells to fire its steam boilers.
The consumption is about 600 Kg/hour. This works out to about 1920 tpa (8 hours x 400
shifts per year). Therefore, the no surplus fibre is likely to be available.
Nuts that are separated from the fibres are then hulled to separate the kernel. The nut shells
that are produced are also used in the boiler to generate steam. The total quantity of nut
shells produced is about 700 tpa. The actual production during the above mentioned years
was 680,791 and 662 tpa. Together, with the fibres this forms the major fuel that is used in
the boiler. Sometimes, whin there is a shortage of FFBs, the plants has also used firewood.
But since, 1994-95, no firewood has been used as per the plant records.
Therefore, the surplus that is likely to be available from fibres and nutshells is limited and
unreliable. However, for a plant crushing 10,000 tpa and running 4, shifts per year, the total
surplus fibre and nutshell that may be available after all current use would be about 580 tpa.
Biomass from Red Palm Oil
Fronds 1530 tpa Empty Fruit Bunches 1900 tpa Fibre & Nut Shells (Surplus) 580 tpa Total 4010 tpa
BIOMASS ASSESSMENT STUDY REPORT
32
4. SURPLUS BIOMASS & PROJECT JUSTIFICATION
In the previous chapters, the bio mass sources were highlighted to be
• Agricultural Sources
• Plantation Sources
• Forest and no forest sources
From the extent of the respective activities and the generation of bio mass and taking into
account the surplus biomass, which is available, is summarily presented as below;
Surplus Biomass Availability all Sources
On an average about 1.2 kg of biomass, with 10% handling losses, 1.32 kg can be converted
into 1 unit of power generation. Therefore, the available biomass of 1,83,166 MTs can
support a power generation of 13,87,62,000 units per year. This is equal to 17.5 MW of
installed capacity. M/s.Suryachakra Green Fuels Private Limited proposes to install
2.28 MW Biomass based power plants in the islands. Also, SGFPL proposes to explore
alternate source of fuel and arrive at a fuel composition as mentioned below:
Biomass : 98.70%
Diesel : 1.30%
The total Biomass requirement for 2.28 MW plant is 18754.56 MT per year
Therefore, the availability of biomass is not considered to be a constraint for 2.28 MW
Biomass power plant.
S.No Source Quantity [MTs] 1 Crop residue 57135 2 Paddy husk 5832 3 Coconut fronds 56610 4 Coconut husk 40000 5 Coconut shells 10680 6 Arecanut 2589 7 Timber lops /saw dust 10320
Total 1,83,166
ID S. No Task Name1 PROJECT DURATION2 1.0 PPA SIGNING34 2.0 CIVIL WORKS5 2.1 Boiler 6 2.2 Boiler auxiliaries7 2.3 STG Building8 2.4 STG Foundation9 2.5 Cooling Tower10 2.6 Raw water treatment11 2.7 WTP foundation12 2.8 Chimney Foundation13 2.9 FHS Foundation14 2.10 AHS Foundation1516 3.0 EQUIPMENTS SUPPLY17 Orders18 3.1 Boiler19 3.1.1 Boiler Structures20 3.1.2 Boiler Pressure Parts21 3.1.3 Boiler Auxiliaries22 3.2 STG
M‐1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Project: 2.28 MW Biomass Based Power Plant Client: Surya Chakra Green Fuels Private Ltd
Project Schedule
Aquatherm Engineering Consultants (India) Pvt Ltd., 1 of 4
Project: Project Schedule‐02.05.2Date: Wed 21/11/12
ID S. No Task Name23 3.2.1 Generator24 3.2.2 Steam turbine25 3.2.3 Auxiliaries26 3.3 Water Treatment Plant27 3.4 Cooling Tower28 3.5 Pumps29 3.6 Fuel Handling30 3.7 Ash Handling31 3.8 Electrical32 3.9 Control & Instrumentation33 3.10 EOT Crane34 3.11 HVAC35 3.12 Raw water Pumps36 3.13 Heat Exchanger37 3.14 Piping & Valves38 3.15 Plant Electrical39 3.16 Power Evacuation40 3.17 Lab equipments4142 4.0 ERECTION & COMMISSIONING43 4.1 Boiler44 4.2 STG
M‐1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Project: 2.28 MW Biomass Based Power Plant Client: Surya Chakra Green Fuels Private Ltd
Project Schedule
Aquatherm Engineering Consultants (India) Pvt Ltd., 2 of 4
Project: Project Schedule‐02.05.2Date: Wed 21/11/12
ID S. No Task Name45 4.3 Water Treatment Plant46 4.4 Cooling Tower47 4.5 Pumps48 4.6 Fuel Handling49 4.7 Ash Handling50 4.8 Electrical51 4.9 Control & Instrumentation52 4.10 EOT Crane53 4.11 HVAC54 4.12 Raw water Pumps55 4.13 Heat Exchanger56 4.14 Piping & Valves57 4.15 Plant Electrical58 4.16 Power Evacuation59 4.17 Lab equipments6061 5.0 MILESTONES62 5.1 Boiler Hydro Test63 5.2 Slow firing64 5.3 Safety valve floating65 5.4 Steam blowing66 5.5 Turbine Rolling
M‐1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Project: 2.28 MW Biomass Based Power Plant Client: Surya Chakra Green Fuels Private Ltd
Project Schedule
Aquatherm Engineering Consultants (India) Pvt Ltd., 3 of 4
Project: Project Schedule‐02.05.2Date: Wed 21/11/12
ID S. No Task Name67 5.6 Synchornising
M‐1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Project: 2.28 MW Biomass Based Power Plant Client: Surya Chakra Green Fuels Private Ltd
Project Schedule
Aquatherm Engineering Consultants (India) Pvt Ltd., 4 of 4
Project: Project Schedule‐02.05.2Date: Wed 21/11/12