Annexure-Ienvironmentclearance.nic.in/writereaddata/online/... · MoM of 32nd meeting of the EAC...

196
Annexure-I Land Details

Transcript of Annexure-Ienvironmentclearance.nic.in/writereaddata/online/... · MoM of 32nd meeting of the EAC...

Annexure-I

Land Details

Sr No Land Details Acres Guntha

1

MASPL acquired 101 Acres 21 Gunthas of Land for its Proposed Green Field Rolling Mill ( Wire Rod cumBar Mill) Project of 700,000 TPA

101 21

Annexure-II

ToR Letter

Annexure-III

Minutes of Meeting of 24th EAC

(Industry-1) held during 13th – 15th

November 2017 with MoM

Compliance

Minutes of 24thEAC (Industry-1) held during 13th – 15th November 2017

Page 1 of 101

Ministry of Environment, Forest and Climate Change

Impact Assessment Division

(Industry-I Sector)

SUMMARY RECORD OF THE TWENTY- FOURTH (24TH) MEETING OF EXPERT

APPRAISAL COMMITTEE HELD ON 13TH–15THNOVEMBER 2017 FOR

ENVIRONMENTAL APPRAISAL OF INDUSTRY-I SECTOR PROJECTS

CONSTITUTED UNDER EIA NOTIFICATION, 2006.

The Twenty-fourth meeting of the Expert Appraisal Committee (EAC) for Industry-I

Sector as per the provisions of the EIA Notification, 2006 for Environmental Appraisal of Industry-

I Sector Projects was held on 13th – 15th November 2017 in the Ministry of Environment, Forest

and Climate Change. The list of participants is annexed.

24.1 After welcoming the Committee Members, discussion on each of the agenda items was

taken up ad-seriatim. First two days i.e. 13th and 14th November, 2017, the meeting was chaired

by Dr. C.N Pandey and on 15th November, 2017 by Shri Jagadish kishwan.

24.2 Confirmation of the minutes of the 23rdMeeting

The minutes of the 23rd meeting, as circulated were confirmed.

DATE: 13th November 2017

24.3. Expansion of Re-rolling mill by installation of new 30 T Rolling Mill Furnace (from 13000

TPA to 180500 TPA) by M/s JMD Alloys Ltd. (JMDAL) at Vill. Deokuli, Bihta, District

Patna, Bihar [Proposal No IA/BR/IND/67762/2017; MoEF&CC File No. IA-J-

11011/478/2017-IA.II(I)] – Environmental Clearance based on ToR.

1.0 M/s JMD Alloys Ltd. (JMDAL) has made online application vide proposal no.

IA/BR/IND/67762/2017dated 29th August 2017along with the copies of EIA/EMP seeking

Environmental Clearance under the provisions of the EIA Notification, 2006 for the above

mentioned proposed project. The proposed project activity is listed at S. No. 3(a) Metallurgical

industries (ferrous & non-ferrous) under Category “B” EIA Notification, 2006 and due to non-

existence of the SEIAA in the state of Bihar the proposal is appraised at Central level.

2.0 The proposed Rolling Mill and Induction Furnace project of M/s JMD Alloys Ltd., is

located near Vill. Deokuli, Block Bihta, Dist. Patna, State Bihar, was initially received in SEIAA,

Bihar on 11th February 2017 for obtaining Terms of Reference (ToR) as per EIA Notification,

2006. The project was appraised by the State Expert Appraisal Committee [Bihar] during its

meeting held on 07thMarch 2017 and prescribed ToRs to the project for undertaking detailed EIA

study for obtaining environmental clearance. Accordingly, SEIAA, Bihar had prescribed ToRs to

the project on 16.03.2017 vide Lr. Ref. No. 570.

3.0 The present proposal of M/s JMD Alloys Ltd., is for enhancement of production of

MS/TMT Bar from 13000 tonnes per annum (TPA) to 180500 tonnes per annum (TPA). The

project is located near Village Deokuli, Block Bihta, Dist. Patna, State Bihar. The existing project

is a Secondary metallurgical processing industry was established in 1995 and not listed in the

Schedule I of EIA Notification 1994 for obtaining Environment Clearance (EC) and project is still

Minutes of 24thEAC (Industry-1) held during 13th – 15th November 2017

Page 57 of 101

junction (Badokar mod) – 2.2 km – 2750 no of trees and Bargawan Police station

to Dhaurar -3.3 km – 4750 no of trees

13.0 After detailed deliberations, the recommendation of the committee is given below:

1 Increase in the Aluminium metal

production from 3.59 LTPA to 3.71

LTPA through process optimization

Recommended

2 Change in the Fuel Mix (use of Pet coke

and Rice husk)

Not recommended

3 Change in source of fuel Recommended for road transportation as

follows:

Year %

allowed

through

road

%

allowed

by road

Via

Bina –

Anpara –

Singruali

– Mahan

% allowed

via

Baikuntpur

–Baidan-

Mahan /

Shadol –

Siddhi -

Mahan

2017-18 27% 75% 25%

2018-19 21% 95% 5%

2019-20 21% 95% 5%

2020-21 16% 95% 5%

4 Sale of carbon anode Recommended

5 Sale of Bath material Not recommended

6 Use of Aluminium Scrap from sister units Not recommended

7 Sale of molten metal Not recommended

24.11. Proposed Integrated Steel Plant of 0.7 MTPA Capacity by M/s. Mukand Ltd. at

VillageKanakapur, Taluka & District- Koppal, Karnataka by M/s Mukund Limited [Online

Proposal No. IA/KA/IND/51427/2016; MoEF File No. IA-J-11011/105/2016-IA.II(I)] -

Amendment in Terms of Reference.

1.0 M/s. Mukand Limited has made online application vide proposal no.

IA/KA/IND/51427/2016 dated 26th September 2017 seeking amendments in Terms of Reference

granted for the proposed Integrated Steel Plant of 0.7 MTPA Capacity vide J-11011/105/2016-IA

II (I) dated 19.05.2016.

2.0 It was informed that the name of the company has been changed from M/s. Mukand Ltd.

to M/s. Mukand Alloy Steels Private Ltd. (MASPL) and changes of the components in phasing.

The details of amendments sought are given below: Sr.

No. Description As Per ToR dated 19.05.2016 Amendment required

1 Change the name of

the Company.

M/s. Mukand Ltd. M/s. Mukand Alloy Steels Private

Ltd. (MASPL)

EIA3
Highlight
EIA3
Highlight
EIA3
Highlight

Minutes of 24thEAC (Industry-1) held during 13th – 15th November 2017

Page 58 of 101

2 Registered Address M/s. Mukand Ltd. (Hospet Division), Hospet-

Koppal Road, Village- Kanakapur, Taluka&

District- Koppal, Karnataka.

M/s. Mukand Alloy Steels Private

Ltd. Flat No. 11, 7 West wing, Shah

House, JankiKutir, Juhu Tara Road,

Vile Parle (W), Mumbai-400049,

Maharashtra, India.

3 Production Details Phase I

Phase II

Phase I

Phase II

i Wire Rods

Cold heading wire

rods, low

carbon/Boron

steels, special steel

wire rods i.e. semi

free/free

cutting/Alloy

steels/high

carbon/mild steel

rods

Installation of

following facilities:

1. Wire Rod Mill -

550,000MetricTo

nnes Per Year

2. Blast Furnace - 1

3. E.O.F

4. Ladle furnace - 1

5. Vacuum

Degassing - 1

6. Billet/Bloom

Caster - 1

7. Sinter Plant - 1

8. Oxygen Plant – 1

9. Power Plant - 1

Installation of

following facilities:

1. Blast Furnace -

1

2. Ladle Furnace -

1

3. Vacuum

Degassing-1

4. Billet/Bloom

Caster - 1

5. Sinter Plant - 1

6. Oxygen Plant -

1

7. Power Plant – 2

(One from

Waste Gases)

700,000

TPA – Wire

Rod cum

Bar Mill

Installation of

following facilities:

1. Blast Furnace

2. DRI

3. Coke oven Plant

4. E.O.F

5. Ladle Furnace

6. Vacuum

Degassing

7. Billet/Bloom

Caster

8. Sinter plant

9. Oxygen plant

10. Power Plant

ii Bar Products

Special steel bar

products

Bar Mill –150,000

TPA

Total 700,000 TPA 700,000 TPA

3.0 After details deliberation, the committee opined that the change in the name and phasing

of the components are administrative in nature. The committee opined that no amendment is

required and may be applied to the ministry directly for change in the name of the company with

requisite documents as envisaged in the clause 11 of EIA Notification, 2006. Therefore the

proposal is returned in the present form.

24.12. Expansion of Steel Plant (Sponge Iron:1,12,500 TPA; MS Billets:1,21,500 TPA; TMT

Bars:1,00,000 TPA; and Power Plant:15 MW) by M/s Amoda Iron and Steel Limited

located at Sy. No. 79/80, 81, 82, 83 & 172, Jayanthipuram Village, Jaggayyapet Mandal,

Krishna District, Andhra Pradesh [Online Proposal No. IA/AP/IND/21175/1910; MoEFCC

File No. J-11011/502/2009-IA.II(I)] – Extension of validity of EC.

1.0 The proponent has made online application vide proposal no. IA/AP/IND/21175/1910

dated 13th October 2017 seeking extension of validity of Environmental Clearance granted on

2ndNovember 2010 for the proposed expansion of Steel Plant by M/s Amoda Iron and Steel Limited

located at Sy. No. 79/80, 81, 82, 83 & 172, Jayanthipuram Village, Jaggayyapet Mandal, Krishna

District, Andhra Pradesh.

2.0 M/s Amoda Iron and Steel Limited has obtained Environmental Clearance vide no. F. No.

J-11011/502/2009-IA.II(I) dated 2ndNovember 2010 for following plant configuration:

S.

No Units

Products Capacity

Existing

Expansion

After

Expansion

EIA3
Highlight

Annexure-IV

Minutes of Meeting of 29th EAC

(Industry-1) held during 13th – 15th

March 2018 with MoM Compliance

Annexure- V

Transfer Letter received from MoEF&

CC

Annexure-VI

Minutes of Meeting of 32nd EAC

(Industry-1) held during 13th – 15th

June 2018 with MoM Compliance

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 229 of 290

following specific ToRs for undertaking detailed EIA and EMP study in addition to the generic ToR

enclosed at Annexure I read with additional ToRs at Annexure-2:

1. Public Hearing to be conducted by the concerned State Pollution Control Board.

2. The issues raised during public hearing and commitment of the project proponent on the

same along with time bound action plan to implement the commitment and financial

allocation thereto should be clearly provided.

3. The project proponent should carry out social impact assessment of the project and submit

�W�K�H���&�R�U�S�R�U�D�W�H���(�Q�Y�L�U�R�Q�P�H�Q�W���5�H�V�S�R�Q�V�L�E�L�O�L�W�\���D�V���S�H�U���W�K�H���0�L�Q�L�V�W�U�\�¶�V���2�I�I�L�F�H���0�H�P�R�U�D�Q�G�X�P���Y�L�G�H��F.No. 22-65/2017-IA.III dated 1st May 2018.

4. Certificate compliance of earlier EC conditions from the regional office of MoEFCC shall

be submitted along with EIA/EMP.

5. The project proponent shall recycle and reuse iron ore fines, coal and coke fines, lime fines

and such other fines collected in the pollution control devices and vacuum cleaning devices

in the process after briquetting/ agglomeration by installation of briquetting plant

13th June 2018

32.26. Proposed Integrated Steel Plant of 0.7 MTPA capacity at Village- Kanakapur, Taluka &

District- Koppal, Karnataka by M/s. Mukund Ltd. [Online Proposal No.

IA/KA/IND/51427/2016; MoEF&CC File No. J-11011/105/2016-IA-II(I)] �± Environmental Clearance.

1.0 Based on the ToRs prescribed to the project, the project proponent submitted an

application for environmental clearance to the Ministry online on 10th March 2016 vide Online

Application No. IA/KA/IND/51427/2016.

2.0 The proposed 700,000 Integrated Steel Plant Project of M/s Mukand Ltd. located in

Village Kanakapura, Tehsil & District Koppal, State Karnataka was initially received in the

Ministry on 10th March 2016 for obtaining Terms of Reference (ToR) as per EIA Notification,

2006. The project was appraised by the Expert Appraisal Committee (Industry) [EAC(I)] during

its4th meeting held on 30th -31st March,2016 and prescribed ToRs to the project for undertaking

detailed EIA study for obtaining environmental clearance. Accordingly, the Ministry of

Environment, Forest and Climate Change had prescribed ToRs to the project on 19th May 2016

vide Lr. No. F.No.J-11011/105/2016-IA.II(I). (MUKAND LTD).

3.0 Based on the ToRs prescribed to the project, the project proponent submitted an

application for environmental clearance to the Ministry online on 10th March 2016 vide Online

Application No. IA/KA/IND/51427/2016. M/s Mukand Ltd made an application on 30th Mar 2018

for transfer of name to M/s Mukand Alloy Steels Private Ltd and thereafter MoEFCC Vide its

letter dated 24thApril 2018 granted approval for transfer of TORs from M/s Mukand Ltd to M/s

Mukand Alloy Steels Private Ltd.

4.0 The project of M/s Mukand Alloy Steels Private Ltd. located in Kanakapura Village,

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 230 of 290

Koppal Tehsil &District ,Karnataka State is for setting up of a new Integrated Steel Plant Project

for production of 0.7 million tones per annum (million TPA) of Specialty Alloy Steels. The

proposed capacity for different products for new site area as below:

Name of Unit No. of

Units

Capacity of Each Unit Production Capacity

Sinter Plant 1 75M2 866,910 TPA

Blast Furnace 1 750M3 790,000 TPA

SMS comprising:

Basic Oxygen Furnace

Ladle Furnace

Vacuum Degasser

CCM

1

2

2

2

70 Ton

70 Ton

70 Ton

Two Casting machines

of 3 strands each with

Section size 160 to 280

x 320.

SMS Capacity:

736,842 TPA

Rolling Mill 2 Two mills with Bars,

Bar in Coil and Wire

Rods.

700,000 TPA

Power Plant 2 15 MW 30 MW

Air Separation Plant

(Oxygen/Nitrogen/Argon)

1 350 Ton 124,250 TPA

Coke Oven Plant 2 200,000TPA 400,000TPA

PRODUCTS

Alloy Steel bar, Bar in coil,

Wire Road

700,000 TPA

Pig Iron 80,000 TPA

5.0 The total land required for the project is 121.406 ha (300 Acres), out of which 89.53ha

(221.22 Acres) is an agricultural land and 33.74 ha (83.375 Acres) is grazing land. The water

bodies include Tungabhadra dam is about 5 km in SE away from project site.

6.0 The topography of the area is flat and reported to lies between 15° �����¶�����������´�� �W�R��15°�����¶�����������´���1���/�D�W�L�W�X�G�H���D�Q�G������°�����¶�����������´���W�R������°�����¶�����������´���(���/�R�Q�Jitude in Survey of India topo

sheet No. 57 A/3, at an elevation of 510 m AMSL. The ground water table reported varies between

0.82 m to 13.55 m below the land surface during the post-monsoon season and 1.82 m to 12.26 m

below the land surface during the pre-monsoon season. Based on the hydro-geological study, it

has been reported that the radius of influence of pumped out water will be 5,733 ha m. Further, the

stage of groundwater development is reported to be 68 % (Koppal taluka).

7.0 The National Park/WL etc are located at a distance of 30.06 KM (Daroji Sloth Bear

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 231 of 290

Sanctuary) KM. There is no national park wild life sanctuary/biosphere reserve/tiger

reserve/elephant reserve etc. are reported to be located in the core and buffer zone of the project.

The area does not report any kind of form corridor for Schedule-I fauna. The authenticated list of

flora and fauna provided through reporting shows presence of no /schedule-I fauna in the study

area.

8.0 The process of project inter alia include usage of basic Raw Materials such as Iron

Ore/Sinter (Agglomerated Form of Iron Ore Fines) and Met Coke / Coal as fuel and Limestone

/Quartz as Flux, the Hot Iron is produced through reduction Process in Blast Furnace which

subsequently converted into Crude Steel in Basic Oxygen Furnace through Oxidation Process. The

Liquid Crude Steel is then refined along with addition of various alloy elements to attain the

desired properties. This liquid Steel is cast in desired section /shape in Continuous Casting

Machine under controlled parameters. These Cast Blooms/Billets are reheated and Rolled in

�Y�D�U�L�R�X�V���V�L�]�H�V���D�Q�G���O�H�Q�J�W�K���W�R���G�L�V�S�D�W�F�K���W�R���2�(�0�¶�V�����'�X�U�L�Q�J���W�K�H�V�H���3�U�R�F�H�V�V�H�V slag at various stations i.e.

Granulated Slag from Blast Furnace, Slag from Basic Oxygen Furnace and LRF is generated. Dust

from various Fume Control Systems which is used in Sinter making process. The Waste Gases

generated from the Blast Furnace& Waste Heat from the Coke Oven shall be used for Power

Generation.

9.0 The targeted production capacity of the Integrated Steel Plant is 0.7 million TPA. The ore

for the plant would be procured from E-Auctions. The ore transportation will be done through

Rail/Road.

Raw Material /

Fuel

Quantity

per Annum Unit

Source (incase

of Import,

please specify

country and

Name of the

port from

which Raw

Material / Fuel

is received)

Mode of

Transport

Distance of

Source from

Project Site (in

Kilo meters) (In

case of import,

distance from

the Port from

which raw

material /Fuel is

received

Type of

Linkage

(Linkage /

Fuel Supply

Agreement

/e-auction

/MoU / LOA

/Captive

/Open

market/

Others)

1 Hard Coal 3,78,000 TPA

Imported

(Mormugao

Port)/Indigeni

ous

Road/Rail 350Kms Open

Market

2 Soft Coal 1,62,000 TPA

Imported

(Mormugao

Port)/Indigeni

ous

Road/Rail 350Kms Open

Market

3 Iron Ore/Pellets 3,70,440 TPA

Imported

(Mormugao

Port)/Indigeni

ous

Road/Rail 350Kms Open

Market

4 PCI Coal 88,200 TPA Purchase from

Market Road/Rail 350Kms

Open

Market

5 Coke* 3,30,750 TPA Purchase from

Market Road/Rail 700Kms

Open

Market

6 DRI 41,303 TPA Purchase from

Market Road/Rail 100Kms

Open

Market

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 232 of 290

7 Purchased Scrap 56,413 TPA Purchase from

Market Road/Rail 350Kms

Open

Market

8 Revert Scrap 26,193 TPA In-House

Production Road/Rail

Transport within

the Plant Others

9 Ore Fine 7,85,784 TPA Purchase from

Market Road/Rail 100Kms

Local

Market

10 Mill Scale 24,556 TPA In-House

Production Road/Rail

Transport within

the Plant Others

11 Flue Dust 14,733 TPA In-House

Production Road/Rail

Transport within

the Plant Others

12 Fluxes 1,96,446 TPA Purchase from

Market Road/Rail 100Kms Others

13 Burnt Lime 4,911 TPA Purchase from

Market Road/Rail 100Kms

Local

Market

14

LPG Bullets

(Capacity: 10

MT x 4 Nos.)

6.5

MT/Day TPA Local Market Road/Rail 300 Kms

Local

Market

10.0 The water requirement of the project is estimated as 7,620 m3/day, out of which 7,620

m3/day of fresh water requirement will be obtained by drawing water from the downstream of

Tungabhadra reservoir within the sanctioned capacity of 18 MLD by the Government of

�.�D�U�Q�D�W�D�N�D�¶�V���O�H�W�W�H�U���Q�R�����:�5�'���������0�7�3�������������G�D�Wed 22 December 2015. For this Project no ground

water shall be used.

11.0 The power requirement of the project is estimated as 69 MW, out of which 30 MW shall

be met by captive power generation from waste gases of Blast Furnaces and Coke Ovens and rest

of the 39 MW will be sourced from the state utility grid (KTPCL/GESCOM). Three no. of D.G.

sets of 1250 KVA each will be used for power back-up.

12.0 Baseline Environmental Studies were conducted during Pre monsoon season i.e. from

April 2016 to June 2016. Ambient air quality monitoring has been carried out at 8 locations during

�$�S�U�L�O�¶�������W�R���-�X�Q�H�¶�������D�Q�G���W�K�H���G�D�W�D���V�X�E�P�L�W�W�H�G���L�Q�G�L�F�D�W�H�G�����3�0���������������������J���P3 �W�R�����������J���P3), PM2.5 (34.41

�W�R�����������������J���P3�������6�2�������������������W�R���������������J���P3�����D�Q�G���1�2�[�����������������W�R�����������������J���P3). The results of the

modelling study indicates that the maximum increase of GLC for the proposed project is 0.18

���J���P�����Z�L�W�K���U�H�V�S�H�F�W���W�R���W�K�H���3�010.

13.0 Ground water quality has been monitored in six (6) locations in the study area and

analysed. pH: 6.96 to 7.35, Total Hardness: 212 to 690 mg/l, Chlorides: 32 to 136 mg/l, Fluoride:

0.61 to 0.84 mg/l. Heavy metals are within the limits. Surface water samples were analysed from

3 locations. pH: 7.38 to 8.02 ; /l and BOD: 6 to 8 mg/l. COD from 20 to 32 mg/l.

14.0 Noise levels are in the range of 42 to 61.3 dB(A) for daytime and 41 to 52.64 dB(A) for

night-time.

15.0 It has been reported that there are no people in the core zone of the project. No/ R&R is

involved. It has been envisaged that no families to be rehabilitated, which will be provided

compensation and preference in the employment (only Job for 47 land losers in the upcoming

factory).

16.0 It has been envisaged that an area of 47.3 ha (117 acre) ha will be developed as green belt

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 233 of 290

around the project site to attenuate the noise levels and trap the dust generated due to the project

development activities. Solid wastes generated during the Project will be reused in the process or

sold to authorized vendors. Following are the details of the Solid Non-Hazardous Waste Details:

Sr.

No Type of waste

Proposed

Quantity Disposal

1 Granulated Slag 2,45,000 TPA

Sold to Cement plants and reused in

Construction of buildings, as a Replacement

for sand & Cement.

2 SMS Slag 1,40,000 TPA Reuse for Brick making/road making/sold to

authorized parties.

3 Revert Scrap 26,193 TPA Will be reused in SMS Plant

4 Mill Scale 24,556 TPA Will be reused in Sinter Plant

5 STP Sludge 30 TPA Disposed to Gardening manure.

17.0 The Non-Hazardous waste generated from the plant process will be sold to authorized

vendors. The details of the Non-Hazardous Waste is mentioned below:

�6�U�������1�R��

Type of waste Category Proposed

Quantity Disposal

�� Used Oil 5.1 14 KL/Annum Sold to HW Authorized

parties.

�� Contaminated cotton rags

or other cleaning materials 35.1

0.3

MT/Annum

Sold to HW Authorized

parties.

�� E-Waste

E- waste

Rules,20

11

57 kg/Month Sale to Authorized

recyclers

��

Empty

Barrels/containers/liners

contaminated with

hazardous

chemicals/wastes.

33.1 6 TPA Sold to Authorized

parties.

18.0 As this is a New Project the Consent for Establish and Consent to Operate for the plant

shall be taken from the State Government after grant of Environment Clearance from MoEF&CC.

19.0 The Public hearing of the project was held on 30 January 2018 at M/s Mukand Alloy Steels

Pvt Ltd. Project Site in Sy No 67/1, 67/2, Kanakapura-Village, Koppal Taluk & District. under the

chairmanship of Deputy Commissioner Koppal for production of 0.7 million TPA of Speciality

Alloy Steels by setting up of New Integrated Steel Plant. The Statement of main issues raised by

the public and response of the project proponent with action plan is as follows: S.

N.

Issue Raised Response by PP Time Bound Action

Plan

Budget

provision

1. Job opportunities

to the local

people.

Direct Employment

47 Nos of Land losers are promised for

Job on Company Role.

Shall be done in phase

manner and

completed before

-

Direct Employment

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 234 of 290

S.

N.

Issue Raised Response by PP Time Bound Action

Plan

Budget

provision

All young deserving candidates based on

qualification and skill level shall be given

preference during recruitment and

transparency in recruitments shall be

assured

commissioning of the

plant.

Indirect Employment

Preference shall be given to local

deserving candidates while awarding

petty contracts.

2. Awareness &

Monitoring of

Environment

Well Qualified personnel of Company

will conduct formal awareness programs

across the Gram panchayat periodically

Periodic and

Continuous process

10 lakhs

/Annum

Online Monitoring system for Ambient

Air will be installed and will be displayed

in the Main gate of the premises.

Before hot

commissioning Mar-

2020

100 Lakhs

Continuous Tree Plantation 35 Lacks

3 Protection of

Environment

1) Company is determined to install latest

and efficient technology in terms of

controlling pollution.

2) Planning to install plenty of fog generator

and water sprinklers across the company

premises.

3) Covering of maximum dumping and

loading points of raw Materials

4) Continuous Tree Plantation

Right from Basic

Engineering. To Hot

Commissioning of the

Plant

498.8 Crores

(EMP

Budget)

4. Ground water

quality &Water

availability

Water shall be allowed to guard pond after

treatment through latest and efficient

water treatment plants.

�%�\���'�H�F�¶������ 100 lakh

High Focus on Rain Water Harvesting.

The Plant will ensure zero water discharge

and hence the quality of Ground water

shall not be affected.

A Pipeline from TB Dam backwater to

Village for Drinking Purpose.

By 2023. 325 lacks in

2 Phases

5. Health of the

local people was

affected due to

pollution from

the existing

industries

located nearby.

Special Health awareness camp and

medical camps for primary checkup will

be arranged at least once in a year in

nearby villages for health check-ups.

Yearly- Mar-2020

onwards

10lakhs/Ann

um

6 Requirement of

CBSE school and

facility for Skill

development

School shall be considered.

Facility for Skill development shall be

created.

By 2023. 10 Lacks

20.0 An amount of Rs 2400 Lakhs (0.77% of Project cost) has been earmarked as Corporate

Environment Responsibility (CER)based on public hearing issues. The details of Corporate

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 235 of 290

Environment Responsibility as follows:

Budget for Corporate Environment Responsibility (CER)

PROJECT PHASE

Budget for Improvements

in physical infrastructure

(Rs in Lacs)

Budget for Improvements

in social infrastructure

(Rs in Lacs)

TOTAL

(Rs in

Lacs)

Phase -1

(2018 -2021) 466 128 594

Phase -2

(2021-2023) 945 861 1806

GRAND TOTAL 1411 989 2400

BREAK- UP PHASE 1 (Improvements in physical infrastructure): Improvements in physical infrastructure

Sr.

No

PLAN & BUDGET ESTIMATION FOR THE PERIOD2018 to 2021

Welfare Activities

HosaKanakapura

Village

Kanakapura

Tanda

Hale Kanakapura

Village

Ginigera

Village

TOTAL

BUDGET

Budget

(Rs in Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in

Lacks)

Budget

(Rs in

Lacks)

1

Development of

connecting road to

NH-63

150 connected 50 connected 200

2 R O Plant for drinking

water available 18 18 25 61

3 Water line from T B

Dam 120 50 0 170

4 Drains Along Village

Street 10 10 10 5 35

5 GRAND TOTAL 466

BREAK- UP PHASE 1 (Improvements in Social infrastructure): Improvements in social infrastructure

Sr.

No

PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018 to 2021

Welfare Activities

Hosa

Kanakapura

Village

Kanakapura

Tanda

Hale

Kanakapura

Village

Ginigera

Village

TOTAL

BUDGET

Budget

(Rs in Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in

Lacks)

Budget

(Rs in

Lacks)

1 Anganwadi (Pre School) 10 10 0 0 20

2 Infrastructure Facilities for

Computer Education 2 2 2 2 8

3 Establishment of Community

Centres 15 5 5 15 40

4 Facilities /Infrastructures for

skill development of Women 2 1 1 2 6

5

Avenue Plantation all along the

Roads, Plantation at Public

Places & Barren Lands

3 3 2 4 12

6 Provide 2 Ambulances for

Medical EmergencyServices 22 22

7 Soil Conservation measures and 5 5 5 5 20

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 236 of 290

Forest Management nearby site

in consultation with Forest

Department.

8 GRAND TOTAL 128

BREAK- UP PHASE 2 (Improvements in physical infrastructure):

Improvements in physical infrastructure

Sr.

No

PLAN & BUDGET ESTIMATION FOR THE PERIOD 2021 to 2023

Welfare Activities

Hosa

Kanakapura

Village

Kanakapura

Tanda

Hale

Kanakapura

Village

Ginigera

Village

TOTAL

BUDGET

Budget

(Rs in Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in

Lacks)

Budget

(Rs in Lacks)

1 New school building 0 200 0 0 200

2 R O Plant for drinking water 15 0 0 30 45

3 water line from T B Dam 0 0 200 200

4 RCC roads inside villages 100 100 100 200 500

5 GRAND TOTAL 945

BREAK- UP PHASE 2 (Improvements in Social infrastructure):

Improvements in social infrastructure

Sr.

No

PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018 to 2023

Welfare Activities

HosaKana

kapura

Village

Kanakapur

aTanda

Hale

Kanakapura

Village

Ginigera

Village

TOTAL

BUDGET

Budget

(Rs in

Lacks)

Budget

(Rs in

Lacks)

Budget

(Rs in Lacks)

Budget

(Rs in

Lacks)

Budget

(Rs in

Lacks)

1

Skill Development for the ITI

persons in advance

technology.

500 0 0 0 500

2 Computer Education Facility 2 2 2 2 8

3

Upgradation of primary

health centre with repair

works, additional

constructions, medical

equipment supply

0 0 0 100 100

4

Development of School

Grounds and providing

Indoors sports facilities

0 0 0 200 200

5 Facilities /Infrastructures for

skill development of Women 2 1 1 2 6

6

Avenue Plantation all along

the Roads , Plantation at

Public Places & Barren

Lands

5 4 3 5 17

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 237 of 290

7

Soil Conservation measures

and Forest Management

nearby site in consultation

with Forest Department. At

other part of Hill.

10 5 5 10 30

8 GRAND TOTAL 861

21.0 The capital cost of the project is Rs. 3129 Crores and the capital cost for environmental

protection measures is proposed as Rs 150 Lakhs in construction Phase and Rs 49880 Lakhs in

Operation Phase. The annual recurring cost towards the environmental protection measures is

proposed as Rs 2500 Lakhs. The detailed CSR plan has been provided in the EMP in its page

No.212 to 215. The Project will create direct & indirect employment opportunities within the

surrounding region. Local people will be employed as per their qualification and skills. In

operation phase, the proposed project would require significant workforce of non-technical and

technical persons. The total manpower required for the proposed project will be around 730

permanent as well 1000 Outsourced staff during operation of the Plant.

22.0 Greenbelt will be developed in 47.35 Ha which is about 39% of the total acquired area. A

100 m wide greenbelt, consisting of at least 3 tiers around plant boundary will be developed as

greenbelt and green cover as per CPCB/MoEF&CC, New Delhi guidelines. Local and native

species will be planted with a density of 2500 trees per hectare. Total no. of 50,000 saplings will

be planted and nurtured in 47.7 hectares in first years.

23.0 The proponent has mentioned that there is no court case or violation under EIA Notification

to the project or related activity.

Observations of the committee:

24.0 After detailed deliberations the committee observed that the EIA/EMP is not clear in following:

1. The details about the implementation of the ZLD and specific measures for energy

conservation have not been clearly spelled out.

2. Specific water consumption per ton of steel has not been assessed quantitatively.

3. The responsibility of the implementation of oxygen plant as proposed to operate on BOO

basis has not been clarified.

4. EIA report does not mention in quantitative terms, the details of ground water recharge

measures.

5. Non-recovery coven plant shall be of stamp charged type and equipped with CDQ

6. Provision of secondary fume extraction system in the SMS

7. 100% recycling and reuse of iron ore fines, coal and coke fines in process by way of

briquetting/agglomeration etc.

8. Guard pond shall be proposed only to cater in case of exigency but not as ETP /rainwater

harvesting.

9. The approach road from the National Highway is not clear.

MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018

Page 238 of 290

10. The project proposal involves diversion of an existing road passing through the middle of

proposed plant area. However, no plan of action for diverting the road or providing

alternative route to the people has been proposed.

11. There is an existing cart road, about 500 m long, which connects the National Highway to

the proposed site in the Kasangandi village. The PP informed during deliberations that they

would be using this road for transporting the material after upgrading this road. However,

no specific details about the plan for upgradation of the road was not furnished. Further,

there was no plan of action for acquisition of land for upgradation of link road. The traffic

analysis of found to be wanting on many details.

12. The status of acquisition of land

13. The EIA /EMP has been found to be not in compliance with prescribed ToRs

Recommendations of the committee:

25.0 In view of above, after detailed deliberations, the committee recommended to return the

EIA report in the present form.

32.27. Expansion of Iron Ore Pelletisation Plant (0.6 MTPA to 1.8 MTPA), Iron Ore

Beneficiation Plant (3.0 MTPA), DRI Plant (0.6 MTPA ), Pig Iron BF (0.6 MTPA), Sinter

Plant (0.8 MTPA), SMS (1.2 MTPA), Rolling Mills (1.2 MTPA) & Captive Power Plant

(125 MW) at Village- Phuljhar, Block- Bansapal, Tehsil- Telkoi, District- Keonjhar,

Odisha by M/s Ardent Steel Limited [Online proposal No. IA/OR/IND/74964/2018;

MoEFCC File No. J-11011/112/2013-IA-II(I) �± Prescribing Terms of Reference.

1.0 The proponent has made online application vide proposal no. IA/OR/IND/74964/2018

dated 14th May, 2018 along with the application in prescribed format (Form-I), copy of pre-

feasibility report and proposed ToRs for undertaking detailed EIA study as per the EIA

Notification, 2006 for the project mentioned above. The proposed project activity is listed at Sl.

No. 3(a) Metallurgical industries (ferrous & non-�I�H�U�U�R�X�V�����X�Q�G�H�U���&�D�W�H�J�R�U�\���³�$�´���(�,�$���1�R�W�L�I�L�F�D�W�L�R�Q����2006 and the proposal is appraised at Central level

2.0 M/s. Ardent Steel Limited proposes its existing Iron Ore Pelletisation plant from 0.6

MTPA to 1.8 MTPA , Iron Ore Beneficiation Plant ( 3 .0 MTPA), DRI Plant ( 0.6 MTPA),

Pig Iron Blast furnace ( 0.6 MTPA) Sinter plant ( 0.8 MTPA) , SMS (1.2 MTPA), Rolling

Mills (1.2 MTPA ) along with Captive Power Plant of 125 MW (WHRB -75 MW and AFBC -

50 MW) at Vill : Phuljhar, Block : Banspal of Keonjhar District. It is proposed to set up the plant

for rolled steel products based on proved technology.

3.0 The existing project was accorded environmental clearance vide lr No. J-11011 / 112 /

2013-IA II(I) dated 29/03/2016. Consent to Operate was accorded by Odisha State Pollution

Control Board vide Letter No. 3702, dated 27.03.2018 validity of CTO is up to 31.03.2019.

4.0 The proposed unit will be located at Village: Phuljhar, Tehsil: Telkoi, Block: Bansapal,

District: Keonjhar, State: Odisha

5.0 The land area acquired for the proposed plant is Ac 432.019 out of which Government

Annexure-VII

Permission letter from T.B Dam for

water

1

GOVERNMENT OF KARNATAKA No. WRD.15/MTP/20I3 Karnataka Government Secretariat Vikasa Soudha Bangalore, Dated 22.12.2015 From, The Secretary to Government Water Resources Department To, The Managing Director Karnataka Irrigation Corporation Ltd. Coffee Board Building Bangalore Sir, Sub : To provide water to the proposed 700,000 integrated Steel Plant

Expansion of M/s. Mukand Ltd., to be established at Kanakapura Village, Koppala District - Reg.

Ref : Your Letter No. KNN/TBP/Mukand Steel/2014-15/6023 dated 24.01.2015 With reference to the above captioned subject, for the 700,000 Integrated Steel Plant Expansion of M/s. Mukand Ltd. proposed to be established at Kanakapura Villege, Koppala District, I am hereby directed to inform that the aforesaid Company is accorded approval to extract 18 M.L.D. (0.232 T.M.C per Annum) water directly from Tungabhadra river under Tunga-Bhadra Dam near Hulgi Village (upstream of Hulgi Railway Bridge) during rainy season, i.e. during Surplus Period, with a condition to uttlize the same with storage arrangement for sufficient quantity of water in its own premises and also subject to the following conditions.

CONDITIONS

1. The Company shall use water during excess flow of water in the Dam, i.e., from

June to December. 2. The Company shall obtain approval from the Competent Authority about drawl of

water from the river under the Dam. 3. The Company shall ensure that it will not drawl water in the event the water in the

river is under River Assistance Quota of Karnataka or Andhra Pradesh. 4. The Company shall obtain permission from the concerned Departments such as

Forest and Environment Department, State Pollution Control Board and other required Departments before initiating the Project.

sumitpal
Typewritten Text
Annexure - 5(ii)

2

5. Water shall be used for the purpose for which permission is accorded. 6. If there is less water in the river for whatsoever reason, no compensation will be

given by the Government and in future, if the Government undertakes any irrigation project or any other projects in the said region, Government will not give any compensation to the Company.

7. While undertaking the construction work, the Company shall take care not to

damage the properties of the Irrigation Department and private properties. If any damage occurs, all such losses and expenses shall be borne by the Company only.

8. Before commencing the work, company shall obtain No Objection Certificate

from the neighboring land owners and company shall construct proper protection walls for the banks of the river near the working spot at its own cost.

9. If any forest region is going to be submerged by water, Company shall obtain

permission from the Forest Department. 10. Care should be taken not to harm irrigation of the lands coming below the

project. 11. Company shall be absolutely responsible for loss or damage to the private or

Government assets or endangering of life if any or any other loss and in case of any accidents, company will be subjected to legal action and shall pay the compensation fixed by the Government.

12. If the Government or its designated Authorities stop water in view of the

requirements of irrigation or drinking water schemes because of which the company suffers any loss or other inconveniences or adverse effects, Government will not be responsible for the same. In such an event, Company shall not lodge any complaints and even if it lodges, same will not be considered.

13. In future, Government can take up any works for the purpose of water storage

usage and for any other reasons without company's permission. If such works are undertaken and if company suffers any loss in its production, Government will not be responsible and if the company's project or asset is affected due to submerging, Government will not be responsible for the same and will not give any compensation. The Government may undertake these works before or after the Company project location.

14. Any buildings constructed by the Company (Mechanical, Civil or Electrical)

collapsed due to irrigation or drinking water disturbance or any other problem is there, material or financial losses occurred by this shall be borne by the company itself. The compensation towards such losses will decide by the Government without giving any notice the Company.

3

15. Service Charges and other revenues fixed by the Government shall be paid by the Company.

16. The Company shall install Hydrometers in prominent places at its own cost as

directed by Authorities of the Department of Water Resources. 17. Measurements of water used will be determined by the Government or its

designated Officer. Company shall bear the water charge for quantity of water measured by the Government or its designated Officer. Government may enhance this amount anytime without prior notice to the Company.

18. Care should be taken that the drinking water schemes above and below this

project are not disturbed in any manner. 19. For the Government land and other properties required for the power project,

company shall pay the amounts to the Government before commencing the works, at the rates prescribed by the Government. Company shall not raise any objections in this regard.

20. If the private lands are submerged in water or if required for company's works,

Company shall obtain the same by making payment. If any objections raised in acquiring the private lands, Company shall get it solved at its own cost. Government will not take any responsibility in this regard.

21. Company shall adopt water recycling system and shall consume water by making

arrangements for using rain water and for water storage system at the time of water scarcity.

22. If any articles available in the Government Land used for company's works,

Company shall pay royalty to the Government as prescribed by the Government without any objections.

23. Company shall not destroy flora and fauna while executing its project or after

execution of its project. If so, Company will be absolutely responsible for the same. In such an event, Company shall bear the penalty fixed by the Government or any other sort of penalty to the Government without any objection.

24. If any legal issues arise at the time of execution of the project or after execution

of the project, Company shall get it solved at its own cost. Government is no way responsible for this and the Government will not bear any such expenses.

25. Before commencing the Project, the Company, shall enter into Agreement/MoU

with the Water Resources Department about consumption of river water. 26. While constructing the project, company shall not store excavated muck and

other excavated stuff in the Government land for whatsoever reason. The Company shall collect only in the land acquired by the Company for its use.

4

27. The Company shall ensure that the local people do not suffer due to this project implementation.

28. Before executing the project, the Company shall enter into an Agreement with

the concerned. Executive Engineer of the Water Resources Department by incorporating all the above conditions and shall execute the project according to his direction.

29. Apart from the above conditions, if the concerned officer of the Water Resource

Department suggests any other conditions deemed to be necessary locally, the Company shall enter into Agreement with the Departmental Authorities by incorporating the same.

30. If the Company violates any of the above conditions, permission will be

withdrawn without any prior notice and the Government has right to recover the losses suffered by the Government whatsoever reason from the Company.

Yours faithfully,

Sd/ - (C. Srinivasulu) Under Secretary to Government Water Resources Department

Copy to:

1) The Chief Engineer, Karnataka Irrigation Corporation Ltd., Irrigation Center Zone Munirabad

2) Chief Engineer, Water Resource Development Company, Anandrao Circle, Bangalore.

3) The Joint Managing Director, M/s. Mukand Ltd, Bajaj Bhavan, Jamnalal Bajaj Marg, 226, Nariman Point, Mumbai – 400021.

4) Director (Technical Wing), Department of Commerce and industries, Vikasa Soudha Bangalore.

Annexure-VIII

MoU for Establishment of Project

efm-*f u#.G;

Governmenl of Kamalaka

MEMORANDUM OF UNDERSTANDING

dtoat ffit*rcns F[fttl*otaota t.n Jvilf, &r,

This Memorandum of Understanding is entered on 7th/8th day of June 2012 at theBangalore International Exhibition Centre (BIEC) in Bangalore (Karnataka) during GlobalInvestors' Meet 2012.

between

Mukand Ltd. a Company incorporated under the Companies Act L956, having its CorporateOffice at 3rd Floor, Bajaj Bhawan,226, Jamnalal Bajaj Marg, Nariman Point, Mumbai - 400

021..

and

The Government of Karnataka

Government of Kamataka would facilitate Mukand Ltd, to obtain necessary permissions /registrations / approvals/ clearances etc. from the concemed departments of the State, as perthe existing policies f rules and regulations of the State Government.This Memorandum of Understanding is made to facilitate Mukand Ltd. for establishment ofthe aforesaid Project in Karnataka in a time bound manner.

For and on behalf of Government ofKarnataka

For and onbehalf Mukand Ltd

(.-. \1,42 14

Mukand Ltd wishes to establish the following project in Karnataka:

(Authorised Signatory) (Authorised Signatory)

Name: Mr. M Badgandi

Designation: Sr. Manager

Contact no. : 93 41,44185 6

E mail: [email protected],

Contact address: No. 51, 1't Floor, St John'sChurch Road\ Opp Coles Park Mok Booth,Behind DTDC Courier Office, Bangalore -560005

Name: R. GIRISI{Joint Directoi

Designatilrrnttaka Udyo g ir I ttraEangalore

Lontact no.l

E mail:

Contact address:

Annexure-IX

Government of Karnataka order for

Land Acquisition

Annexure-X

Government of Karnataka order for

Transfer of Approval in name of

MASPL

Annexure-XI

Raw data of Ambient Air Quality

Monitoring Results

 

Raw data of Ambient Air Quality Monitoring Results

Name of Location: Project Site AAQ1

Date of

Monitoring Week PM 10 PM 2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

04/04/2016 1 89.62 49.29 9.14 31.37 1012.71 36.49 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/04/2016 1 81.58 44.87 8.32 28.55 921.85 36.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

11/04/2016 2 84.63 46.55 8.63 29.62 956.32 34.85 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/04/2016 2 93.65 51.51 10.25 35.60 1058.25 37.72 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

18/04/2016 3 84.10 46.26 8.58 29.44 950.33 24.44 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/04/2016 3 85.60 47.08 8.73 29.96 967.28 34.85 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

25/04/2016 4 82.10 45.16 8.37 28.74 927.73 33.21 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/04/2016 4 77.60 42.68 7.92 27.16 876.88 21.57 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/05/2016 5 82.90 45.60 8.46 29.02 936.77 33.62 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/05/2016 5 92.70 50.99 9.46 32.45 1047.51 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/05/2016 6 84.20 46.31 8.59 29.47 951.46 34.44 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/05/2016 6 83.60 45.98 8.53 29.26 944.68 34.03 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/05/2016 7 81.70 44.94 8.33 28.60 923.21 33.21 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/05/2016 7 80.90 44.50 8.25 28.32 914.17 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/05/2016 8 79.60 43.78 8.12 27.86 899.48 32.636 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/05/2016 8 78.30 43.07 7.99 27.41 884.79 32.103 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/06/2016 9 77.70 42.74 7.93 27.20 878.01 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

07/06/2016 9 76.18 41.90 7.77 26.66 860.83 31.2338 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/06/2016 10 75.12 41.32 7.66 26.29 848.86 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/06/2016 10 79.03 43.47 8.06 27.66 893.04 32.39 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/06/2016 11 80.30 44.17 8.19 28.11 907.39 32.8 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/06/2016 11 78.80 43.34 8.04 27.58 890.44 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/06/2016 12 81.20 44.66 8.28 28.42 917.56 33.21 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/06/2016 12 89.30 49.12 9.11 31.26 1009.09 36.49 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 93.65 51.51 10.25 35.60 1058.25 38.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 75.12 41.32 7.66 26.29 848.86 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 82.52 45.38 8.45 29.00 932.44 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 93.48 51.41 10.11 35.03 1056.31 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Kanakapur AAQ 2

Date of

Monitoring Week PM 10 PM 2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

04/04/2016 1 85.2 46.86 8.69 29.82 962.76 33.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/04/2016 1 82.3 45.27 8.39 28.805 929.99 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

11/04/2016 2 86.9 47.80 8.86 30.415 981.97 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/04/2016 2 79.2 43.56 8.08 27.72 894.96 30.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

18/04/2016 3 85.1 46.81 8.68 29.785 961.63 33.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/04/2016 3 61.9 34.05 6.31 21.665 699.47 24.141 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

25/04/2016 4 82.3 45.27 8.39 28.805 929.99 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/04/2016 4 86.5 47.58 8.82 30.275 977.45 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/05/2016 5 83.7 46.04 8.54 29.295 945.81 32.37 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/05/2016 5 98.1 53.96 10.01 34.335 1108.53 38.22 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/05/2016 6 74.8 41.14 7.63 26.18 845.24 29.172 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/05/2016 6 79.5 43.73 8.11 27.825 898.35 30.42 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/05/2016 7 78.1 42.96 7.97 27.335 882.53 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/05/2016 7 72.6 39.93 7.41 25.41 820.38 30.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/05/2016 8 68.9 37.90 7.03 24.115 778.57 25.701 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/05/2016 8 84.3 46.37 8.60 29.505 952.59 32.76 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/06/2016 9 86.9 47.80 8.86 30.415 981.97 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

07/06/2016 9 62.8 34.54 6.41 21.98 709.64 24.492 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/06/2016 10 87.5 48.13 8.93 30.625 988.75 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/06/2016 10 81.7 44.94 8.33 28.595 923.21 31.59 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/06/2016 11 83.2 45.76 8.49 29.12 940.16 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/06/2016 11 74.3 40.87 7.58 26.005 839.59 28.86 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/06/2016 12 81.7 44.94 8.33 28.595 923.21 31.863 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/06/2016 12 81.2 44.66 8.28 28.42 917.56 32.799 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 98.10 53.96 10.01 34.34 1108.53 38.22 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 61.90 34.05 6.31 21.67 699.47 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 80.36 44.20 8.20 28.13 908.10 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 94.29 51.86 9.62 33.00 1065.50 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Ginigera AAQ 3

Date of

Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

04/04/2016 1 74.60 39.54 8.21 26.11 842.98 30.59 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/04/2016 1 76.90 40.76 8.46 26.92 868.97 31.53 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

11/04/2016 2 72.30 38.32 7.95 25.31 816.99 29.64 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/04/2016 2 74.60 39.54 8.21 26.11 842.98 30.59 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

18/04/2016 3 70.00 37.10 7.70 24.50 791.00 28.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/04/2016 3 76.30 40.44 8.39 26.71 862.19 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

25/04/2016 4 79.00 41.87 8.69 27.65 892.70 32.39 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/04/2016 4 74.50 39.49 8.20 26.08 841.85 30.55 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/05/2016 5 78.00 41.34 8.58 27.30 881.40 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/05/2016 5 92.90 49.24 10.22 32.52 1049.77 38.09 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/05/2016 6 74.50 39.49 8.20 26.08 841.85 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/05/2016 6 76.30 40.44 8.39 26.71 862.19 21.28 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/05/2016 7 78.90 41.82 8.68 27.62 891.57 32.35 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/05/2016 7 72.30 38.32 7.95 25.31 816.99 29.64 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/05/2016 8 74.00 39.22 8.14 25.90 836.20 30.34 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/05/2016 8 74.45 39.46 8.19 26.06 841.29 30.52 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/06/2016 9 78.00 41.34 8.58 27.30 881.40 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

07/06/2016 9 79.60 42.19 8.76 27.86 899.48 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/06/2016 10 79.00 41.87 8.69 27.65 892.70 32.39 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/06/2016 10 73.20 38.80 8.05 25.62 827.16 30.01 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/06/2016 11 78.50 41.61 8.64 27.48 887.05 32.19 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/06/2016 11 79.60 42.19 8.76 27.86 899.48 32.64 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/06/2016 12 79.00 41.87 8.69 27.65 892.70 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/06/2016 12 82.00 43.46 9.02 28.70 926.60 33.62 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 92.90 49.24 10.22 32.52 1049.77 38.09 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 70.00 37.10 7.70 24.50 791.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 77.02 40.82 8.47 26.96 870.31 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 87.89 46.58 9.67 30.76 993.11 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Bevinhalli AAQ 4

Date of

Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

04/04/2016 1 72.6 34.848 7.986 24.684 813.12 29.04 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/04/2016 1 75.3 36.144 8.283 25.602 843.36 30.12 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

11/04/2016 2 77.2 37.056 8.492 26.248 864.64 30.88 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/04/2016 2 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

18/04/2016 3 72.3 34.704 7.953 24.582 809.76 28.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/04/2016 3 71.2 34.176 7.832 24.208 797.44 28.48 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

25/04/2016 4 75.2 36.096 8.272 25.568 842.24 30.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/04/2016 4 72 34.56 7.92 24.48 806.4 28.8 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/05/2016 5 76.3 36.624 8.393 25.942 854.56 30.52 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/05/2016 5 89.9 43.152 9.889 30.566 1006.88 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/05/2016 6 71 34.08 7.81 24.14 795.2 28.4 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/05/2016 6 68.9 33.072 7.579 23.426 771.68 27.56 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/05/2016 7 65 31.2 7.15 22.1 728 26 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/05/2016 7 62.3 29.904 6.853 21.182 697.76 24.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/05/2016 8 66 31.68 7.26 22.44 739.2 26.4 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/05/2016 8 69 33.12 7.59 23.46 772.8 27.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/06/2016 9 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

07/06/2016 9 72 34.56 7.92 24.48 806.4 28.8 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/06/2016 10 62.3 29.904 6.853 21.182 697.76 24.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/06/2016 10 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/06/2016 11 58.9 28.272 6.479 20.026 659.68 23.56 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/06/2016 11 75 36 8.25 25.5 840 30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/06/2016 12 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/06/2016 12 72.3 34.704 7.953 24.582 809.76 28.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 89.90 43.15 9.89 30.57 1006.88 35.96 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 58.90 28.27 6.48 20.03 659.68 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 71.70 34.41 7.89 24.38 802.99 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 84.06 40.35 9.25 28.58 941.45 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Agalkera AAQ 5

Date of

Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

07/04/2016 1 85.60 43.66 9.50 31.67 967.28 35.10 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

08/04/2016 1 81.20 41.41 9.01 30.04 917.56 33.29 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/04/2016 2 86.50 44.12 9.60 32.01 977.45 35.47 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

15/04/2016 2 81.90 41.77 9.09 30.30 925.47 33.58 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/04/2016 3 86.20 43.96 9.57 31.89 974.06 35.34 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

22/04/2016 3 67.80 34.58 7.53 25.09 766.14 27.80 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/04/2016 4 81.50 41.57 9.05 30.16 920.95 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

29/04/2016 4 65.20 33.25 7.24 24.12 736.76 26.73 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/05/2016 5 88.80 45.29 9.86 32.86 1003.44 36.41 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/05/2016 5 98.80 50.39 10.97 36.56 1116.44 20.51 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/05/2016 6 78.90 40.24 8.76 29.19 891.57 32.35 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/05/2016 6 78.40 39.98 8.70 29.01 885.92 32.14 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/05/2016 7 85.49 43.60 9.49 31.63 966.07 35.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/05/2016 7 86.51 44.12 9.60 32.01 977.57 35.47 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/05/2016 8 87.53 44.64 9.72 32.39 989.06 35.89 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/05/2016 8 88.54 45.16 9.83 32.76 1000.56 36.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/06/2016 9 89.56 45.68 9.94 33.14 1012.05 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/06/2016 9 90.58 46.20 10.05 33.51 1023.54 37.14 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/06/2016 10 73.60 37.54 8.17 27.23 831.68 30.18 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/06/2016 10 84.09 42.89 9.33 31.11 950.22 34.48 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/06/2016 11 97.40 49.67 10.81 36.04 1100.62 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/06/2016 11 87.10 44.42 9.67 32.23 984.23 35.71 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/06/2016 12 65.10 33.20 7.23 24.09 735.63 26.69 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/06/2016 12 81.20 41.41 9.01 30.04 917.56 33.29 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 98.80 50.39 10.97 36.56 1116.44 26.69 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 65.10 33.20 7.23 24.09 735.63 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 89.00 42.45 9.24 30.79 940.49 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 89.00 42.45 9.24 30.79 940.49 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Halwarti AAQ 6

Date of

Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

07/04/2016 1 88 39.6 8.97 32.56 994.4 22.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

08/04/2016 1 82.2 36.99 8.38 30.41 928.86 20.55 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/04/2016 2 80.6 36.27 8.22 29.82 910.78 20.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

15/04/2016 2 79.5 35.775 8.10 29.41 898.35 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/04/2016 3 88.6 39.87 9.03 32.78 1001.18 30.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

22/04/2016 3 85 38.25 8.67 31.45 960.5 21.25 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/04/2016 4 86.1 38.745 8.78 31.85 972.93 21.53 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

29/04/2016 4 88.2 39.69 8.99 32.63 996.66 22.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/05/2016 5 76.4 34.38 7.79 28.26 863.32 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/05/2016 5 84.6 38.07 8.62 31.30 955.98 21.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/05/2016 6 78.5 35.325 8.00 29.04 887.05 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/05/2016 6 84.3 37.935 8.59 31.19 952.59 21.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/05/2016 7 82.2 36.99 8.38 30.41 928.86 30.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/05/2016 7 78.6 35.37 8.012 29.08 888.18 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/05/2016 8 87.1 39.195 8.882 32.27 984.23 21.78 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/05/2016 8 85.3 38.385 8.706 31.51 963.89 21.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/06/2016 9 84.9 38.205 8.658 31.43 959.37 21.23 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/06/2016 9 83.5 37.575 8.57 30.85 943.55 20.88 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/06/2016 10 81.2 36.54 8.224 30.04 917.56 20.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/06/2016 10 80.6 36.27 8.22 29.82 910.78 20.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/06/2016 11 79.5 35.775 8.19 29.45 699 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/06/2016 11 88.6 39.87 9.02 32.72 1001.18 22.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/06/2016 12 86.1 38.745 8.72 31.87 972.93 21.53 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/06/2016 12 87 39.15 8.84 32.19 983.1 21.75 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 88.60 39.87 9.04 32.78 1001.18 30.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 76.40 34.38 7.79 28.27 699.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 83.61 37.62 8.53 30.94 936.47 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 88.60 39.87 9.04 32.78 1001.18 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Hirekhasankandi AAQ 7

Date of

Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

07/04/2016 1 81.67 39.20 8.33 30.22 922.92 36.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

08/04/2016 1 83.61 40.13 8.53 30.94 944.84 33.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/04/2016 2 89.73 43.07 9.15 33.20 1013.89 33.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

15/04/2016 2 75.76 36.36 7.73 28.03 856.05 32.60 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/04/2016 3 83.03 39.86 8.47 30.72 938.26 36.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

22/04/2016 3 92.73 44.51 9.46 34.31 1047.87 34.85 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/04/2016 4 75.76 36.36 7.73 28.03 856.05 35.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

29/04/2016 4 83.03 39.86 8.47 30.72 938.26 36.16 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/05/2016 5 87.01 41.76 8.87 32.19 983.20 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/05/2016 5 92.15 44.23 9.40 34.10 1041.30 34.69 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/05/2016 6 69.45 33.34 7.08 25.70 784.81 32.19 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/05/2016 6 95.06 45.63 9.70 35.17 1074.18 24.56 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/05/2016 7 96.13 46.14 9.80 35.57 1086.24 33.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/05/2016 7 96.03 46.09 9.80 35.53 1085.14 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/05/2016 8 95.74 45.95 9.77 35.42 1081.85 35.71 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/05/2016 8 86.82 41.67 8.86 32.12 981.01 34.97 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/06/2016 9 85.75 41.16 8.75 31.73 968.95 34.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/06/2016 9 83.13 39.90 8.48 30.76 939.36 24.24 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/06/2016 10 95.06 45.63 9.70 35.17 1074.18 33.29 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/06/2016 10 96.03 46.09 9.80 35.53 1085.14 33.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/06/2016 11 91.67 44.00 9.35 33.92 699.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/06/2016 11 83.03 39.86 8.47 30.72 938.26 36.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/06/2016 12 92.15 44.23 9.40 34.10 1041.30 35.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/06/2016 12 80.61 38.69 8.22 29.82 910.86 35.67 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 96.13 46.14 9.80 35.57 1086.24 36.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 69.45 33.34 7.08 25.70 699.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 87.13 41.82 8.89 32.24 970.54 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 96.08 46.12 9.80 35.55 1085.73 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

 

Name of Location: Allanagar AAQ 8

Date of

Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni

Benzo(a)

Pyrene VOC

07/04/2016 1 84.2 42.94 9.35 31.15 951.46 34.52 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

08/04/2016 1 86.2 43.96 9.57 31.89 974.06 35.34 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

14/04/2016 2 92.5 47.18 10.27 34.23 1045.25 37.93 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

15/04/2016 2 78.1 39.83 8.67 28.90 882.53 32.02 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

21/04/2016 3 85.6 43.66 9.50 31.67 967.28 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

22/04/2016 3 95.6 48.76 10.61 35.37 1080.28 39.20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

28/04/2016 4 78.1 39.83 8.67 28.90 882.53 32.02 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

29/04/2016 4 85.6 43.66 9.50 31.67 967.28 35.10 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

05/05/2016 5 89.7 45.75 9.96 33.19 1013.61 36.78 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

06/05/2016 5 95 48.45 10.55 35.15 1073.50 28.95 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

12/05/2016 6 71.6 36.52 7.95 26.49 809.08 29.36 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

13/05/2016 6 98 49.98 10.88 36.26 1107.40 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

19/05/2016 7 90.1 45.95 10.00 33.34 1018.13 36.94 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

20/05/2016 7 94.1 47.99 10.45 34.82 1063.33 38.58 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

26/05/2016 8 98.7 50.34 10.96 36.52 1115.31 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

27/05/2016 8 89.5 45.65 9.93 33.12 1011.35 36.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

02/06/2016 9 88.4 45.08 9.81 32.71 998.92 36.24 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

03/06/2016 9 85.7 43.71 9.51 31.71 968.41 35.14 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

09/06/2016 10 98 49.98 10.88 36.26 1107.40 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

10/06/2016 10 97.1 49.52 10.78 35.93 1097.23 39.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

16/06/2016 11 94.5 48.20 10.49 34.97 1067.85 28.75 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

17/06/2016 11 85.6 43.66 9.50 31.67 967.28 35.10 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

23/06/2016 12 95 48.45 10.55 35.15 1073.50 38.95 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

24/06/2016 12 83.1 42.38 9.22 30.75 939.03 34.07 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Maximum 98.70 50.34 10.96 36.52 1115.31 39.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Minimum 71.60 36.52 7.95 26.49 809.08 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Average 89.00 45.48 9.90 32.99 1007.58 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

98percentile 95.49 48.70 10.60 35.33 1079.06 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1

Annexure-XII

Proceeding of Public Hearing

mastl1
Typewritten Text
Annexure - 4

Annexure-XIII

Toposheet

20

PROJECT SITE

Topo Map

Topo Sheet No - 57 A/3 Topo Sheet No - 57 A/7

Topo Sheet No - 57 A/4 Topo Sheet No - 57 A/7

76 15' 76 10'

15 15'

Annexure-XIV

High Court Stay Order

Typewritten text

Print

HIGH COURT OF GUJARAT

SPECIAL CIVIL APPLICATION No. 5312 of 2016

Status : PENDING ( Converted from : C/ST/5331/2016 ) CCIN No : 001021201605312

 

Next Listing Date:20/02/2018

Coram HONOURABLE THE CHIEF JUSTICE MR.

R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL M.

PANCHOLI

S.NO. Name of the Petitioner Advocate On Record

1

2

3

4

5

6

7

8

9

10

11

12

JAYESHKUMAR SOMABHAI PATEL

CHANDRASHEKHAR BHANUPRASAD UPASANI

MALAV PRAFULBHAI DALWADI

SNEHAL BHARATBHAI SATYAPATHI

PRADEEP PRABHAKAR JOSHI

GAURANG VINODBHAI PARMAR

DARSHAN JITENDRABHAI PAREKH

SURESH TULSHIBHAI MORADIA

SUDHIR NARAISINGH VERMA

SEEMA CHANDRAKANT ABHALE

DILIP CHANDUBHAI THAKKAR

BALU TRIBHOVAN PATEL

less

MR NILESH P SHAH for: Petitioner(s) 1 - 12

ANSHUL N SHAH for: Petitioner(s) 1 - 12

S.NO. Name of the Respondant Advocate On Record

1 UNION OF INDIA NOTICE NOT RECD BACK for :Respondent(s) 1

NOTICE SERVED for :Respondent(s) 1

 

Presented On : 30/03/2016 Registered On : 04/04/2016

Bench Category : DIVISON BENCH District : SURAT

Case Originated From : THROUGH HIS/HER/THEIR

ADVOCATE

Listed : 18 times

StageName : NOTICE & ADJOURNED MATTERS

Classification DB - VIRES CHALLENGED - VIRES CHALLENGED - CONSTITUTION OF INDIA - CENTRAL ACT / STATE ACT /

RULE / STATUTORY NOTIFICATION / REGULATIONS

Act CONSTITUTION OF INDIA

Office Details

S. No. Filing Date Document Name Advocate NameCourt Fee on

DocumentDocument Details

1 30/03/2016 VAKALATNAMA ANSHUL N SHAH ADVOCATE

for PETITIONER(s) 1

0 ANSHUL N SHAH(8540) for

P:1 - 12

2 30/03/2016 VAKALATNAMA MR NILESH P SHAH ADVOCATE

for PETITIONER(s) 1

5 MR NILESH P SHAH(3215)

for P:1 - 12

3 30/03/2016 MEMO OF

PETITION/APPEAL/SUIT

MR NILESH P SHAH ADVOCATE

for PETITIONER(s) 1

100 MR NILESH P SHAH(3215),

ANSHUL N SHAH(8540),

for P:1 - 12

4 01/04/2016 ADDITIONAL FEE ON

MEMO OF

APPEAL/PETITION/SUIT

MR NILESH P SHAH ADVOCATE

for PETITIONER(s) 1

500 MR NILESH P

SHAH(3215),ANSHUL N

SHAH(8540) for P:1 - 12

Linked Matters

S.

No.CaseDetail Status Name Disposal Date Action/Coram

1 SPECIAL CIVIL

APPLICATION/17039/2016

PENDING - -

HONOURABLE THE CHIEF JUSTICE MR. R.SUBHASH

REDDY

HONOURABLE MR.JUSTICE VIPUL M. PANCHOLI

2 SPECIAL CIVIL

APPLICATION/11208/2017

PENDING - -

HONOURABLE THE CHIEF JUSTICE MR. R.SUBHASH

REDDY

HONOURABLE MR.JUSTICE VIPUL M. PANCHOLI

3 SPECIAL CIVIL

APPLICATION/20606/2017

PENDING - -

HONOURABLE THE CHIEF JUSTICE MR. R.SUBHASH

REDDY

HONOURABLE MR.JUSTICE VIPUL M. PANCHOLI

Court Proceedings

S. No.Notified

DateCourtCode

Board

Sr. No.Stage Action Coram

1 05/04/2016 1 6 URGENT ADMISSION (FRESH

MATTERS)

FIXED NOTICE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

2 13/06/2016 1 31 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

3 04/07/2016 1 35 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

4 21/07/2016 1 55 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

5 14/09/2016 1 119 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

6 05/10/2016 1 119 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

7 07/11/2016 1 29 NOTICE & ADJOURNED

MATTERS

HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

8 18/11/2016 1 73 NOTICE & ADJOURNED

MATTERS

HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

9 19/12/2016 1 88 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

10 20/01/2017 1 69 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

11 21/02/2017 1 50 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

12 14/03/2017 1 86 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

13 20/04/2017 1 109 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

14 03/07/2017 1 97 NOTICE & ADJOURNED

MATTERS

HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

15 04/09/2017 1 86 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

16 14/11/2017 1 74 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

17 12/01/2018 1 49 NOTICE & ADJOURNED

MATTERS

NEXT DATE HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

18 20/02/2018 1 - NOTICE & ADJOURNED

MATTERS

HONOURABLE THE CHIEF JUSTICE

MR. R.SUBHASH REDDY

HONOURABLE MR.JUSTICE VIPUL

M. PANCHOLI

Available Orders

S.

No.Case Details Judge Name

Order

DateCAV Judgement Questions Transferred Download

1 SPECIAL CIVIL

APPLICATION/5312/2016

HONOURABLE

THE CHIEF

JUSTICE MR.

R.SUBHASH

REDDY

HONOURABLE

MR.JUSTICE

VIPUL M.

PANCHOLI

05/04/2016 N ORDER - YDownload

2 SPECIAL CIVIL

APPLICATION/5312/2016

HONOURABLE

THE CHIEF

JUSTICE MR.

R.SUBHASH

REDDY

HONOURABLE

MR.JUSTICE

VIPUL M.

PANCHOLI

21/07/2016 N ORDER - YDownload

3 SPECIAL CIVIL

APPLICATION/5312/2016

HONOURABLE

THE CHIEF

JUSTICE MR.

R.SUBHASH

REDDY

HONOURABLE

MR.JUSTICE

VIPUL M.

PANCHOLI

18/11/2016 N ORDER - YDownload

4 SPECIAL CIVIL

APPLICATION/5312/2016

HONOURABLE

THE CHIEF

JUSTICE MR.

R.SUBHASH

REDDY

HONOURABLE

MR.JUSTICE

VIPUL M.

PANCHOLI

20/01/2017 N ORDER - YDownload

Certified Copy

S.

No.ApplicantName ApplicationType

Application

Date

UOL

NumberOrder Date

Notify

Date

Delivery

DateStatus

Nature Of

Document

1 MR NILESH P

SHAH

URGENT 05/04/2016 U/2292/201605/04/2016 07/04/2016 11/04/2016 Delivered ORDER

2 MR NILESH P

SHAH

URGENT 18/04/2016 U/2604/201605/04/2016 19/04/2016 21/04/2016 Delivered ORDER

TOP CLOSE

Annexure-XV

Environment Policy

Annexure-XVI

SIA Report

SOCIAL IMPACT STUDY REPORT

For proposed Green Field Project

“Alloy Steel Rolling Mill of 700,000 TPA”

By

M/s. MUKAND ALLOY STEELS PRIVATE LTD.

(MASPL)

At village Kanakapur, Taluka & District Koppal,

State: Karnataka

FEBRUARY 2018

Prepared By:

GREEN CIRCLE, INC.,

Vadodara

M/s Mukand Alloy steels Private Limited

Green Circle Inc. Vadodara 2

Client: MASPL

Project No: GCI/V/2017-18/EIA

Summary and version history: R00

Compiled by: Vikash Bhagat

Reviewed by: Pradeep Joshi

Peer Reviewed by: Dr.Deepika Mondal

1 Social Impact Assessment Study

Distribution: For inclusion in the EIA for the

MASPL ,Hospet, Karnataka

This report has been prepared for

MASPL in accordance with the terms

and conditions of TOR issued by

MoEF&CC, GCI contract with for

submission to commenting authorities

and the Competent Authority in

support of MASPL application for an

Environmental Clearance.

Any other use, distribution or

publication of this report is prohibited

without the prior written approval of

GCI & MASPL.

M/s Mukand Alloy steels Private Limited

Green Circle Inc. Vadodara 3

CONTENTS

1. INTRODUCTION ....................................................................................................... 7 1.1 PROJECT BACKGROUND ............................................................................................... 7 1.2 TERMS OF REFERENCE ................................................................................................ 7 1.3 STUDY APPROACH AND METHODOLOGY ................................................................... 7 1.4 IMPACT ASSESSMENT METHODOLOGY ...................................................................... 8 1.4.1 Impact Prediction .............................................................................................................. 9 1.4.2 Impact Evaluation ........................................................................................................... 10 1.5 ASSUMPTIONS AND LIMITATIONS .............................................................................. 16 1.6 SPECIALIST DETAILS ................................................................................................... 16

2. PROJECT DESCRIPTION ...................................................................................... 16 2.1 PROJECT BACKGROUND ............................................................................................. 17 2.1.1 Project Location .............................................................................................................. 17 2.1.2 Land Ownership and Acquisition ..................................................................................... 17 2.2 PROJECT COMPONENTS ............................................................................................. 18 2.3 PROJECT PHASING AND SCHEDULE ......................................................................... 20 2.3.1 Construction Phase ......................................................................................................... 20 2.3.2 Operation Phase ............................................................................................................. 21

3. PROJECT MOTIVATION ........................................................................................ 23 4. SOCIO-ECONOMIC BASELINE.............................................................................. 24

4.1 AREA OF INFLUENCE (AOI) .......................................................................................... 24 4.1.1 Area of Direct Influence................................................................................................... 24 4.1.2 Indirect Area of Influence ................................................................................................ 24 4.2 ADMINISTRATIVE STRUCTURE ................................................................................... 26 4.3 SITE SETTING AND LANDUSE ..................................................................................... 26 4.3.1 Land-use of the Project Site ............................................................................................ 26 4.4 DEMOGRAPHIC PROFILE ............................................................................................. 29 4.5 LIVELIHOODS AND ECONOMY .................................................................................... 33 4.6 SOCIAL INFRASTRUCTURE AND SERVICES .............................................................. 35 4.6.1 Connectivity, Transport and Communication ................................................................... 35 4.6.2 Water .............................................................................................................................. 37 4.6.3 Housing .......................................................................................................................... 37

5. IMPACT ASSESSMENT ......................................................................................... 38 5.1 EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS

OPPORTUNITIES ...................................................................................................................... 38 5.1.1 Construction: Employment, Skills Enhancement and Local Business Opportunities ........ 39 Impact Description ...................................................................................................................... 39 5.1.2 Operation: Employment, Skills Enhancement and Local Business Opportunities ............ 42 5.2 IMPACTS ON COMMUNITY HEALTH AND SAFETY ..................................................... 44

5.2.1 Construction and Operation: Impacts Associated with the Presence of the Workforce and Jobseekers ......................................................................................................... 44 5.2.2 Construction and Operation: Pressure on Social Infrastructure and Services .................. 47

5.2.3 Construction Phase: Impact on Human Health due to Air Emissions and Dust Generation .................................................................................................................................. 49 5.2.4 Operations Phase: Impact on Human Health due to Air Emissions ................................. 50 5.3 INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE ................. 52

5.3.1 Construction and Phase: Increased Nuisance Factors and Change in Sense of Place 52

5.3.2 Operation Phase: Increased Nuisance Factors ............................................................... 54 5.4 WORKER HEALTH AND SAFETY AND RIGHTS ........................................................... 57 5.4.1 Construction Phase: Risk to Workers’ H&S due to Construction Activities ...................... 58 5.4.2 Operation Phase: Risk to Workers’ H&S due to Hazardous Operation Activities ............. 61 5.5 CUMULATIVE IMPACTS ................................................................................................ 62

M/s Mukand Alloy steels Private Limited

Green Circle Inc. Vadodara 4

5.5.1 Method ............................................................................................................................ 63 5.5.2 Cumulative Impacts of the Socioeconomic Environment ................................................. 63 5.6 UNPLANNED EVENTS................................................................................................... 68

6. KEY FINDINGS AND RECOMMENDATIONS ......................................................... 69 7. IMPACT STATEMENT ............................................................................................ 72 8. REFERENCES ........................................................................................................ 72

List of Tables

TABLE 4.1 LAND USE DISTRIBUTION OF THE STUDY AREA (10 KM RADIUS) ............................................................................ 27 TABLE 4.2 VILLAGE-WISE DETAILS OF POPULATION ............................................................................................................ 29 TABLE 4.3 SOCIAL DISTRIBUTION ................................................................................................................................... 30 TABLE 4.4 LITERACY RATE ............................................................................................................................................ 31 TABLE 4.5 EMPLOYMENT SCENARIO ............................................................................................................................... 32 TABLE 5.1 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS

OPPORTUNITIES .................................................................................................................................................. 41 TABLE 5.2 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS

OPPORTUNITIES DURING CONSTRUCTION ................................................................................................................. 41 TABLE 5.3 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS

OPPORTUNITIES .................................................................................................................................................. 43 TABLE 5.4 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS

OPPORTUNITIES DURING OPERATION ...................................................................................................................... 43 TABLE 5.5 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH THE PRESENCE OF THE WORKFORCE AND

JOBSEEKERS ....................................................................................................................................................... 46 TABLE 5.6 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH THE PRESENCE OF A WORKFORCE AND

JOBSEEKERS ....................................................................................................................................................... 46 TABLE 5.7 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH PRESSURE ON SOCIAL INFRASTRUCTURE AND

SERVICES ........................................................................................................................................................... 48 TABLE 5.8 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED PRESSURE ON SOCIAL INFRASTRUCTURE AND

SERVICES ............................................................................................................... ERROR! BOOKMARK NOT DEFINED. TABLE 5.9 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST

GENERATION ...................................................................................................................................................... 49 TABLE 5.10 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST

GENERATION .......................................................................................................... ERROR! BOOKMARK NOT DEFINED. TABLE 5.11 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST

GENERATION ...................................................................................................................................................... 51 TABLE 5.12 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST

GENERATION ...................................................................................................................................................... 51 TABLE 5.13 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE ..... 54 TABLE 5.14 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE

DURING CONSTRUCTION AND ................................................................................................................................ 54 TABLE 5.15 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE

DURING OPERATION ............................................................................................................................................ 56 TABLE 5.16 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE

OPERATION........................................................................................................................................................ 57 TABLE 5.17 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS CONSTRUCTION

ACTIVITIES ......................................................................................................................................................... 60 TABLE 5.18 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS CONSTRUCTION AND

ACTIVITIES ......................................................................................................................................................... 60 TABLE 5.19 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS OPERATION ACTIVITIES62 TABLE 5.20 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS OPERATION ACTIVITIES62 TABLE 5.21 PRE- AND POST - MITIGATION SIGNIFICANCE FOR ECONOMY, EMPLOYMENT AND SKILLS DEVELOPMENT CUMULATIVE

IMPACT ............................................................................................................................................................. 65 TABLE 5.22 PRE- AND POST - MITIGATION SIGNIFICANCE FOR ECONOMY, EMPLOYMENT AND SKILLS DEVELOPMENT CUMULATIVE

IMPACT ............................................................................................................................................................. 65 TABLE 5.23 PRE- AND POST- MITIGATION SIGNIFICANCE FOR COMMUNITY HEALTH AND SAFETY CUMULATIVE IMPACT ................. 66 TABLE 5.24 PRE- AND POST- MITIGATION SIGNIFICANCE FOR COMMUNITY HEALTH AND SAFETY CUMULATIVE IMPACT ................. 67 TABLE 5.25 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH PRESSURE ON SOCIAL INFRASTRUCTURE AND

SERVICES CUMULATIVE IMPACT ............................................................................................................................. 68

M/s Mukand Alloy steels Private Limited

Green Circle Inc. Vadodara 5

TABLE 5.26 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED PRESSURE ON SOCIAL INFRASTRUCTURE AND

SERVICES ........................................................................................................................................................... 68

List of Figures

FIGURE 1.1 PROJECT LOCATION MAP ............................................................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 1.2 METHODOLOGY OF EIA STUDY ..................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.1 GOOGLE IMAGE SHOWING FOUR CORNERS OF THE PROJECT SITE .......................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.2 GOOGLE MAP OF PROJECT SITE ..................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.3 GOOGLE IMAGE OF 2 KM AND 5 KM RADIUS FROM THE PROJECT SITE .................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.4 GOOGLE IMAGE OF 5 KM AND 10 KM RADIUS FROM THE PROJECT SITE .................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 2.5 PHOTOGRAPHS OF THE PROPOSED PLANT SITE ................................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 2.6 PLANT LAYOUT ........................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.7 SCHEMATIC PROCESS FLOW WITH MATERIAL FLOW CHART ................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 2.8 WATER BALANCE DIAGRAM .......................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.9 EFFLUENT TREATMENT PLANT LAYOUT ........................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.10 STP PLANT LAYOUT ................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.11 LAYOUT FOR RAIN WATER HARVESTING ......................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.1 DEM OF MASPL PROJECT STUDY AREA ......................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.2 LAND USE MAP AT PROJECT SITE ................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.3 WIND ROSE DIAGRAM................................................................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 3.4 GOOGLE IMAGE SHOWING AMBIENT AIR MONITORING LOCATIONS ..................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.5 STATISTICAL COMPARISON OF PM 10 IN STUDY AREA ......................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.6 STATISTICAL COMPARISON OF PM 2.5 IN STUDY AREA ....................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.7 STATISTICAL COMPARISON OF SO2 IN STUDY AREA ............................................................ ERROR! BOOKMARK NOT DEFINED. FIGURE 3.8 STATISTICAL COMPARISON OF NOX IN STUDY AREA ........................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.9 IMAGE SHOWING NOISE MONITORING LOCATION ............................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 3.10 IMAGE SHOWING SURFACE & GROUND WATER SAMPLING LOCATIONS ............................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.11 GOOGLE IMAGE SHOWING SOIL MONITORING LOCATIONS................................................ ERROR! BOOKMARK NOT DEFINED. FIGURE 3.12 DEMOGRAPHIC PATTERN ........................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.13 SOCIAL PATTERN ...................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.14 LITERACY RATE ......................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 4.1 GROUND LEVEL CONCENTRATION OF PM10 ...................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 4.2 GROUND LEVEL CONCENTRATION OF SO2 ........................................................................ ERROR! BOOKMARK NOT DEFINED. FIGURE 4.3 GROUND LEVEL CONCENTRATION OF NOX ....................................................................... ERROR! BOOKMARK NOT DEFINED.

M/s Mukand Alloy steels Private Limited

Green Circle Inc. Vadodara 6

List of Abbreviations and TERMs

BAR Basic Assessment Report

BFS Bankable Feasibility Study

CBA Critical Biodiversity Area

MoEFCC Department of Environmental Affairs and Development Planning

EIA Environmental Impact Assessment

EIR Environmental Impact Report

EPC Engineering Procurement Construction

GNR Government Notice Regulation

HP High Pressure

HFO Heavy Fuel Oil

HRSG Heat Recovery Steam Generator

HV High Voltage

IDZ Industrial Development Zone

IRP Integrated Regional Plan

LP Low Pressure

NID Notice of Intent to Develop

SDFP Spatial Development Framework Plan

S&EIR Scoping and Environmental Impact Report

WML Waste Management Licence

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 7

1. INTRODUCTION

1.1 PROJECT BACKGROUND

M/s. Mukand Alloy Steels Private Ltd (MASPL) is a subsidiary of M/s. Mukand Ltd and M/s. Mukand

Ltd has decided to delegate its Alloy Steel business to M/s. MASPL. The site at which M/s. Mukand

Ltd proposed to setup Integrated Steel Plant of 0.7 MTPA at Village- Kanakapur, Taluka & District-

Koppal, State - Karnataka shall be used by its subsidiary company M/s. MASPL to setup the

proposed plant. Mukand Ltd. (Formerly known as Mukand Iron & Steel Works Ltd.), is one of the

largest producer of ‘Alloys and Special Steels’ and Stainless Steels in the country meeting the

requirements of Original Equipment Manufacturers (OEM) for automobiles, auto-component

industries as also of railways, defence, transportation and engineering industries.

1.2 TERMS OF REFERENCE

The approach to this Socio-economic Study has been guided by the MoEF&CC Manual and the

MOEF has finalized the Terms of References (TORs) for carrying out Environmental Studies vide

letter no. J-11011/105/2016-IA.II (I)). Dated 19th May 2016.

1.3 STUDY APPROACH AND METHODOLOGY

Associated MoEF&CC Manual, as well as referring to IFC & ADB guidelines,

The Social Study was divided into the following three Phases:

Phase 1: Desktop Study;

Phase 2: Fieldwork; and

Phase 3: Update Socio-economic Baseline and Impact Assessment.

Phase 1: Desktop Study

The desktop component of the study has drawn on the use of secondary data sourced from previous

project reports, as well as other Internet-based sources including:

• District and Local Development Plans;

• District and Local Spatial Development Frameworks;

• Statistics from Census;

• Other similar EIAs undertaken in the same region and

• Other EIAs undertaken for Integrated Steel Plants

The information collected through desktop research included: demographic (including human

settlements on affected properties), economic, health and education information as well as the

availability of physical infrastructure and services. The purpose of collecting this information was to

provide a basis upon which the impact assessment can be conducted, and to enable the

measurement and monitoring of the impacts.

Through a review of the existing documentation, gaps in information were identified to be addressed

through primary data collection, as outlined in Phase 2 and via drawing on any additional sources of

secondary data that were identified during the course of the study.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 8

Phase 2: Fieldwork and Primary Data Collection

In order to gather clear and current information for the baseline and impact assessment, a field visit

was undertaken. The field visit was undertaken during Baseline survey (April to June, 2016) and

later updated before the public hearing (January 2017). This afforded the social consultants the

opportunity to engage with the relevant community members and authorities, as well as get a

general sense of the stakeholder issues.

Where the relevant stakeholders were not available at the time of the site visit, follow-up was made

for the same.

Phase 3: Update Socio-economic Baseline and undertake Impact Assessment

The socio-economic baseline from the Scoping Report was updated using the secondary and

primary data collected in Phase 2. The findings of the public consultation process were also

incorporated into the baseline in order to ensure that it accurately describes the current situation and

needs of the local communities.

The Social Specialist has identified potential positive and negative – direct, indirect, induced and

cumulative – impacts associated with the Project. The identification of impacts was informed by the

baseline study and the public consultation process. The findings of other specialist impact

assessment studies have been reviewed and used to inform the impact assessment component of

the SIA where appropriate.

Feedback from stakeholders, primarily received during the Scoping Phase was used to inform the

impact assessment.

The identified impacts will be assessed using the methodology provided by GCI, as outlined in

Section 1.4, below.

1.4 IMPACT ASSESSMENT METHODOLOGY

This section provides an overview of the assessment methodology used to assess the

environmental and social impacts associated with the construction, operation phases of the project.

The identified impacts presented within this section have been assessed according to this

methodology which includes a description of the impact, subsequent assessment, mitigation

measures and finally the residual impact after the application of these mitigation measures.

Impact identification and assessment starts with scoping. Interactions with the potential for

significant effects were subjected to a detailed impact assessment. The principal ESIA steps are

summarised in Figure 1.1 and comprise the following.

• Impact prediction: to determine what could potentially happen to resources or receptors as

a consequence of the Project and its associated activities.

• Impact evaluation: to evaluate the significance of the predicted impacts by considering the

magnitude and likelihood of occurrence, and the sensitivity, value and/or importance of the

affected resource or receptor.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 9

• Mitigation and enhancement: to identify appropriate and justified measures to mitigate

negative impacts and enhance positive impacts.

• Residual impact evaluation: to evaluate the significance of impacts assuming effective

implementation of mitigation and enhancement measures.

Figure 1.1 Environmental Impact Assessment Process

1.4.1 Impact Prediction

Prediction of impacts is an objective process to determine what is likely to happen to the

environment as a consequence of the Project and associated activities. From the potentially

significant interactions identified in scoping, the impacts to the various resources/receptors are

elaborated and evaluated. The diverse range of potential impacts considered in the IA process

typically results in a wide range of prediction methods being used, including quantitative, semi-

quantitative and qualitative techniques.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 10

1.4.2 Impact Evaluation

Environmental impacts arise as a result of Project activities either interacting with environmental

receptors directly or causing changes to the existing environment such that an indirect effect occurs.

Impacts may be described and quantified in a number of ways.

Nature of Impact

The nature of an impact is defined as the type of change from baseline conditions or the

introduction of a new desirable or undesirable factor. The nature of an impact is described as

being either positive or negative.

Type of Impact

Impact type indicates the relationship of the impact to the Project activity in terms of cause and

effect, as either:

• Direct impact resulting from the direct interaction between a project activity and the receiving

environment.

• Indirect impact between the proposed activity and the environment as a result of subsequent

interactions within the environment.

• Induced impact resulting from other non-project activities that happen as a consequence of

the Project activities.

• Cumulative impacts that act together with other impacts (including those from concurrent or

planned future third party activities) to affect the same resources and/or receptors as the

Project.

Extent of Impact

Impact extent relates to the geographic reach of the impact and is described in Table 1.1

Table 1.1 : Determining Extent

Duration of Impact

Impact duration refers to the time period over which a resource or receptor will be affected

described in Table 1.2.

Designation Description

Local

Impact would affect local resources or receptors and would be

restricted to a single community (ie impacts in the footprint of project

activities and the immediate adjacent area).

Regional Impact would affect regional resources or receptors and would be

experienced at a regional scale for example at a state level.

National Impact would affect resources or receptors throughout the country.

International International impact would affect internationally important resources or

receptors outside of the country.

Trans-boundary Impact would be those that are experienced in one country as a result of

activities in another country.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 11

Table 1.2 : Determining Duration

Designation Description

Temporary

Impacts would last for a short duration, are reversible and intermittent or

occasional in nature. The resource or receptor would return to the

previous state when the effect ceases or after a short period of recovery,

typically less than one year.

Short-term

Impacts would last for the life of the proposed short term activity activities

and a limited short period thereafter, typically one to four years. The

impact would cease when the effect ceases following a short period of

recovery.

Long-term Impacts would continue for an extended period of time after the Project

activity, for example between five and 15 years.

Permanent

Impacts would occur during the development of the Project and cause a

permanent change in the affected receptor or resource that endures

substantially beyond the Project lifetime.

Scale of Impact

Impact scale relates to the size of the impact, in a social context it typically relates to the degree

of change experienced by receptors, either at an individual or household level.

Table 1.3 Determining Scale

Designation Description

Small Impact would result in a subtle change in baseline conditions.

Medium Impact would result in some change to baseline conditions within a

community, but would not dominate over baseline conditions.

Large

Impact would result in a fundamental change in the way of life of

receptors, or to the nature of relationships within a community, or to the

livelihood patterns within a community.

Frequency of Impact

Impact frequency relates to the constancy or periodicity of the impact. This could be a once off

occurrence or continuous. The designations used in the Impact Assessment are as follows:

• Constant a permanent occurrence

• Often occurs at least once a month

• Occasional occurs at least once every six months

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 12

• Rare occurs about once a year

• One-off could occur, but reasonably expected to occur only once.

Magnitude of Impact

Once an impact’s characteristics are defined, the next step in the impact assessment phase is to

assign each impact a ‘magnitude’. Magnitude is typically a function of some combination (depending

on the resource/receptor in question) of the following impact characteristics:

• Extent;

• Duration;

• Scale; and

• Frequency.

Additionally, for unplanned events only, magnitude incorporates the likelihood factor. An unplanned

event is defined as ‘a reasonably foreseeable event that is not planned to occur as part of the Project,

but which may conceivably occur as a result of Project activities (eg accidents), even with a low

probability’. These differ from planned events which are activities which are expected to occur as part

of the normal Project development and operation. The likelihood of an unplanned event occurring is

designated using a qualitative scale:

• Unlikely events are unlikely but may occur at some time during normal operating

conditions.

• Likely events are likely to occur at some time during normal operating conditions.

• Definite events will occur during normal operating conditions (ie, it is essentially

inevitable).

Magnitude essentially describes the intensity of the change that is predicted to occur in the

resource/receptor as a result of the impact. Magnitude designations themselves are universally

consistent, but the descriptions for these designations vary on a resource/receptor-by-

resource/receptor basis. The magnitude designations are described in Table 1.4.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 13

Table 1.4 Describing Magnitude

Vulnerability The vulnerability of receptors is underpinned by a low existing level of livelihoods assets (such as

health or education) or inadequate access to structures and processes to protect or improve

livelihoods. It is important to understand the vulnerability context as it will affect the ability of social

receptors to adapt to socio-economic/cultural or bio-physical changes. A higher level of vulnerability

can result in increased susceptibility to negative impacts or a limited ability to take advantage of

positive impacts. A project may also exacerbate existing vulnerabilities if the status of individuals and

communities and their coping mechanisms are not adequately understood or considered. The

vulnerability designations are described in Table 1.5.

Table 1.5 Describing Vulnerability

Receptor

Vulnerability Description

Low Minimal vulnerability; consequently with a high ability to adapt to changes

brought by the Project and opportunities associated with it.

Medium

Some, but few areas of vulnerability; still retaining an ability to at least in

part adapt to change brought by the Project and opportunities associated

with it.

High

Profound or multiple levels of vulnerability that undGCIine the ability to

adapt to changes brought by the Project and opportunities associated with

it.

Evaluation of Significance

Once magnitude of impact and sensitivity/vulnerability/importance of resource/receptor have been

characterised, the significance can be assigned for each impact.

Designation Description

Positive

In the case of positive impacts, no intensity is assigned unless there is

ample data to support a more robust characterisation. It is sufficient to

indicate that the Project will result in a positive impact, without

characterising the exact degree of positive change likely to occur

Negligible A difference from baseline conditions is marginally perceptible.

Small

Perceptible difference from baseline conditions. Tendency is that impact

is local, rare and affects a small proportion of households and is of a

short duration.

Medium

Clearly evident difference from baseline conditions. Tendency is that

impact affects a substantial area or number of people and/or is of

medium duration. Frequency may be occasional and impact may be

regional in scale.

Large

Change dominates over baseline conditions. Affects the majority of the

area or population in the area of influence and/or persists over many

years. The impact may be experienced over a regional or national area.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 14

For the purposes of this ESIA, the following definition of significance has been adopted:

An impact is significant if, in isolation or in combination with other impacts, it should, in the judgement

of the EIA team, be taken into account in the decision-making process, including the identification of

mitigation measures and consenting conditions.

In assessing whether an impact is significant, reference has been made, where appropriate, to

criteria on which the evaluation is based. These may include legal standards, policy guidance or

accepted practice and past experience.

The significance of impacts is then devised from a combination of the vulnerability of the receptor

and the magnitude of impact. A convenient way of representing the overall significance is through a

matrix of magnitude versus sensitivity or vulnerability/value as shown in Table 1.6.

Table 1.6 Overall Significance Criteria for Environmental Impacts in the ESIA

For this assessment, five impact significance categories have been applied:

• Positive impact;

• Negligible impact;

• Minor significance;

• Moderate significance; and

• Major significance.

These general definitions of Categories of Impact Significance have been applied to the

assessment of social and environmental impacts for the Project as shown in Table 1.7.

Table 1.7 Categories of Impact Significance

Positive

Positive impacts provide resources or receptors, most often people, with positive benefits. It is

noted that concepts of equity need to be considered in assessing the overall positive nature of

some impacts such as economic benefits, or opportunities for employment.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 15

Negligible

Negligible impacts are where a resource or receptor (including people) will not be affected in

any way by a particular activity or the predicted effect is deemed to be ‘negligible’ or

‘imperceptible’ or is indistinguishable from natural background variations.

Minor

An impact of minor significance (‘Minor impact’) is one where an effect will be experienced, but

the impact magnitude is sufficiently small (with or without mitigation) and well within accepted

standards, and/or the receptor is of low sensitivity/value.

Moderate

An impact of moderate significance (‘Moderate impact’) is one within accepted limits and

standards. Moderate impacts may cover a broad range, from a threshold below which the

impact is minor, up to a level that might be just short of breaching a legal limit. Clearly to

design an activity so that its effects only just avoid breaking a law and/or cause a major impact

is not best practice. The emphasis for moderate impacts is therefore on demonstrating that the

impact has been reduced to a level that is ALARP. This does not necessarily mean that

‘Moderate’ impacts have to be reduced to ‘Minor’ impacts, but that moderate impacts are being

managed effectively and efficiently.

Major

An impact of major significance (‘Major impact’) is one where an accepted limit or standard

may be exceeded, or large magnitude impacts occur to highly valued/sensitive

resource/receptors. An aim of EIA is to get to a position where the Project does not have any

major residual impacts, certainly not ones that would endure into the long-term or extend over

a large area. However, for some aspects there may be major residual impacts after all

practicable mitigation options have been exhausted (ie ALARP has been applied). It is then the

function of regulators and stakeholders to weigh such negative factors against the positive

ones such as employment, in coming to a decision on the Project.

Mitigation and Enhancement

Mitigation and/or enhancement measures are identified for significant impacts identified during the

impact evaluation stage. These measures represent a feature, procedure or other action that the

Project commits to implement to avoid or reduce the magnitude of an adverse impact, or to enhance

the magnitude of a positive impact. As such, these should avoid unnecessary damage to the

environment; safeguard valued or finite resources, natural areas, habitats and ecosystems; and

protect humans and their associated social environments.

Residual Impact Evaluation

The residual impacts are described in terms of their significance and the nature of the impact is

qualified, where appropriate, on the basis of the descriptors, within each of the impact assessment

sections presented within this Chapter. The criteria take into account the degree to which impacts can

be quantified and compared with accepted limits and standards or a combination of the magnitude of

change caused by the Project in combination with the value/sensitivity of the receptor/resource that is

impacted.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 16

Dealing with Uncertainty in the Assessment of Impacts

The impact assessment process deals with the future and there is inevitably uncertainty that arises

between the predictions made and what will actually happen during the course of the Project.

However, the sources of impacts due to plant processes & operations are well-understood and the

areas of interaction with the receiving environment have been well-characterised by past projects.

Impact predictions have, wherever practicable, been made using available data, but where significant

uncertainty remains, this is outlined in the text. Where the vulnerability of a resource and impact

magnitude is not supported by quantitative data, this is reported accordingly and qualitative

information, professional experience and a conservative approach is used instead to judge whether a

significant impact is likely to occur or not.

1.5 ASSUMPTIONS AND LIMITATIONS

Detailed socio-economic data were collected within 10 km radius of the proposed Project site.

Preliminary information was collected during field investigation followed by secondary data from the

census of India 2011.

• It is assumed the Project information provided is accurate and design is compliant with

Central & state regulations.

• It is assumed that the feasibility of the Project has been assessed by the proponent.

• It is assumed all stipulated mitigation measures will be implemented to avoid and reduce the

respective negative impacts and enhance positive impacts.

1.6 SPECIALIST DETAILS

Gunesh Deosthali is a member within GCI’s Impact Assessment and Planning Team based in Pune

and engaged more than 20+ years experience in on Social Impact Assessment where he has been

responsible for planning and getting the primary and secondary information gathering, baseline

compilation, impact identification/ assessment, and formulation of mitigation and management

measures. Gunesh has extensive experience in industrial & infra sectors. Through his experience in

the sectors, Gunesh has developed a deep understanding of the impacts (both adverse and

beneficial) integrated steel plant project can have on surrounding communities. He is familiar with

the requirements and implementation of MoEFCC requirements. Gunesh has worked on project with

complex social impacts, with highly sensitive affected communities.

He has worked on projects which have required multiple stakeholder (including multiple localities and

individuals) engagement and collation of primary data, where he has been instrumental in designing

and implementing socio-economic primary data collection tools including household surveys, focus

group discussion and one-to-one interview questionnaires. In addition, Gunesh has undertaken

several Environmental Impact Assessments (EIAs) at existing facilities and green field sites in India .

His responsibilities included project management, integration of specialist studies and public

participation activities

2. PROJECT DESCRIPTION

The description of the Project that follows is focus on aspects of the project description relevant to

the assessment of socio-economic impacts. A detailed project description can be found in Chapter 3

of the EIA.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 17

2.1 PROJECT BACKGROUND

MASPL has proposed to set up a green field Rolling Mill (Wire Rod cum Bar Mill) of 700,000 Ton /

Year capacity which is backward integration of integrated steel plant

2.1.1 Project Location

The proposed project site is located at Village- Kanakapur, Taluka and District- Koppal, State-

Karnataka. The nearest Highway is NH-63 (adjacent to Plant) and NH-13 (13.5 Km, East). The

nearest cities are Koppal and Hospet, which are situated at a distance of 11 km and 22 km in west

and east directions respectively. The nearest Railway station is Ginigera at a distance of 1.7 km,

NW.

2.1.2 Land Ownership and Acquisition

There are 47 families having their land parcels on which the proposed integrated steel plant site will be

located are detailed in Table 2.1.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 18

Table 1.1 Details of Land Parcels

2.2 PROJECT COMPONENTS

The key project components considered in this EIA are as follows:

• Rolling Mill

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 19

Total Land required for the proposed Integrated Steel Plant project is 300 acre/1,213,800 m2. Out of which

the land required for the Rolling Mill (Wire Rod cum Bar Mill) and Finishing Facility is 101 Acres 21Gunthas

(4,10,568 m2) which is under possession of MASPL.

Table 2.2.

Table 1.2 Project components general surface areas and lengths

Sr. No. Description Area (m2) Area (Acre) Percentage

(%)

1 Plant Area including

Storage Area

121380 30 29

2 Utilities 4046 1 1

3 Parking Area 4046 1 1

4 Administrative Building

/Restroom/Canteen/Offices

4046 1 1

5 Green belt & Green Area 141610 35 35

6 Roads & Drainage 32368 8 8

7 Rain Water Harvesting &

Water Storage

48552 12 12

8 Softener, STP & ETP 4046 1 1

9 Open Area 48552 12 12

Total 4,08,646 101 100

Table 1.3 Access routes and roads

The Project has accounted for certain road works, described below, deemed necessary for safety and

compliance with regional legislative requirements. Permissions have not yet been sought for the

proposed road works, the costs of which will be borne by the project and executed according to local

regulations, requirements and guidelines.

Concrete-paved roads will be constructed early after commencement of construction works and will

serve to carry heavy load traffic (mobile cranes, multi axle heavy equipment trailers, cement delivery

trucks, etc.) during the early stages of construction.

All concreted roads will play an important role for rainwater harvesting, in addition to the concreted

lay-down areas. The site’s natural slope is towards the south where the raw water storage tanks will

be situated. The east-west thoroughfares (‘streets’) will channel rainwater into the rain-water drains

of the thoroughfares (‘avenues’). Rainwater will run to the bulk water storage tanks.

Approach to the Plant

For road safety considerations and in light of the increased traffic (particularly during construction

phase) the provincial road leading past the two integrated steel plant entrances will wide enough to

carry the traffic.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 20

For the office and administration gate a wide entrance (12 m) and a 12 m radius bend into the plant

site and offices from the access road to the gate house is planned.

2.3 PROJECT PHASING AND SCHEDULE

2.3.1 Construction Phase

The proposed project is Rolling Mill if 700,000 Ton /Annum capacity.

During peak construction activity, it is expected that up to approximately 1000 workers will be directly

employed. Most of this workforce will be employed by the engineering, procurement and construction

(EPC) contractor and will consist in semi-skilled to skilled workforce. The breakdown of skills required

during the construction phase will be as follows:

• Skilled labour: 400 persons

• Semi-skilled labour: 300 persons

• Unskilled labour: 300 persons

It is understood that there will be no worker accommodation on site during construction. The unskilled

workforce will, as far as possible be employed from the local community, reducing the need to the

provision of accommodation. The skilled and semi-skilled workforce from outside the area will be

housed within Area Local Body.

Traffic Requirements during the Construction Phase

Bulk cement and concrete aggregate, tons re-bar steel, and tons equipment and structural steel will

need to be transported to the construction site.

It is envisaged that construction staff, up to a maximum of 1000 persons, would be bussed to site in

mini busses and pass through this gate; busses per day, twice a day. Light vehicle traffic due to

construction will start by vehicles and increase rapidly where it will remain for the bulk of the

construction period.

There will be an expected bulk gravel, bulk sand, and bulk cement respectively for the duration of

the construction phase 1, after which it tails off rapidly.

The heavy equipment will be delivered via truck. This will involve some abnormal loads being moved

on the roads during this time

Water Requirements during the Construction Phase

During the construction phase the main water requirement will be for the concrete batching plant.

Water will be required for the concrete batching. Additional water will be required for:

• Off-site dust control: Post treatment recycled water will be used for dust control on

unsurfaced roads where required during high traffic periods and during construction.

• Domestic purposes by on site workers: Maximum water usage during peak construction period

will be the labour and constriction curing.

• Construction and on-site dust control: Water is required for the manufacture of concrete during

construction. The integrated steel plant will require concrete for foundations, road works, hard

standing and other site works.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 21

2.3.2 Operation Phase

The integrated steel plant will be operated on a 24 hour, 7 days a week basis.

Employment during the Operation Phase

The number of workers on site during operations will be about 730. These will include plant

management and maintenance staff, skilled mechanical and electrical technicians, drivers, medical,

quality control, and cleaning staff and a number of experienced plant operators who will operate and

maintain the plant, and who are expected to be a mix of expatriate and local staff.

As the plant will operate 24 hours a day, three full-time shifts will be created per day, and the

breakdown of the skills required will be as follows:

• Skilled labour

• Semi-skilled labour and

• Unskilled labour:

Table 1.4 Estimated Employment Positions Available During Operation

Position Number of Positions Available

Admin 5

Security 10

Warehouse and Stores 50

Medical 2

Plant Control 50

Engineers 93

Technicians 90

Skilled 200

Unskilled 200

Tuition and Training 5

Quality Control, Water 5

Canteen 5

Total 715

It is understood that there will be no worker accommodation on site during operation. The unskilled

workforce will, as far as possible be employed from the local community, reducing the need to the

provision of accommodation. The skilled and semi-skilled workforce from outside the area will be

housed near to the site.

Traffic Requirements during the Operation Phase

During commercial operations there will be some traffic bringing supplies and spares to the integrated

steel plant. This will increase during shutdowns and periods of major maintenance.

Maintenance activities will be undertaken by an Operations and Maintenance (O&M) contractor.

Water Requirements during the Operation Phase

Water during operation will be required for the following activities:

Total water requirement of the project will be 1525 M3/Day. Source of Water is from downstream of

Tungabhadra Reservoir. Tungabhadra River is a perennial river and caters to the need of irrigation

and potable water. Water from downstream of reservoir will be drawn within the sanctioned capacity

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 22

of 18 MLD by the Government of Karnataka’s letter no. WRD.15/MTP/2013 dated 22 December

2015.

Liquid Effluents in the proposed Project:

1) Backwash from Softener: During Rolling, water is used for cooling of equipment, hot

bars and rolls. Water has to be soft so as to avoid deposit in the water pipes. MAPSL

will use water from the downstream of TB Dam. Depending on the hardness some

quantity of water (make-up water) will need to be softened.

Backwash from the softening plant is categorized as effluent. Quantity of backwash

water is estimated to be about 10 cum/Day. This water is collected in a pit and treated

for neutralization. After treatment, water becomes neutral (PH-7-8) and sent to the

collecting tank for dilution and further used for gardening and dust suppression

purpose.

2) Blowdown from Water Supply system: When the recirculation water becomes hard,

some quantity is removed from the system and fresh soft water is added. This is called

Blowdown. Blowdown water is neutral (PH 7-8) and is directly used for dust

suppression and gardening in the plant. Thus, Zero water Discharge is achieved.

3) Discharge from Canteen & toilets:

The waste water from the Canteen and toilets are treated in STP of capacity 25 KLD

and the water after treatment in STP is sent to the Effluent Treatment Tankand

treated with lime. After treatment, water becomes neutral (PH-7-8) and used for

gardening purpose and dust suppression purpose.

4) Scale Pit Water: The water from the various rolling processes shall be collected in the

Scale Pit. The water in the Scale pit contains oil and grease. The Oil Skimmer is

required to be installed for removing floating Oil and grease from contaminated

Water consisting of Oil, Grease and shop scale. Design of oil skimmer depends on the

laws of gravity, surface tension and principle of adhesion in order to function. Oil

skimmer works because they are made of materials to which oil is more likely to stick

than the fluid it is floating on.

The skimmer shall be installed near the scale pit. The Oil Skimmer shall be made from

corrosion resistant material. The special type of rotating endless tubes floats on the

liquid surface for removing oil/grease. The tube moves through the skimmer pulley

installed above ground level and the oil is wiped from the tube at the top with the

help of special wiper pulley. The skimmed oil shall be collected in a container through

a hose connector attached with the skimmer and the reclaimed oil shall be sold.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 23

After skimming of the oil and grease the water is send to the settling tank and the

water from the settling tank after filtration again reused in the cooling Tower. The

backwash collected from the filter is then send to the thickener and coagulants are

added for separating the solid and liquid particles and thereafter the water overflow

of the thickener is sent to the Scale pit for reusing. The residual from the thickener is

collected and dried to make in form of Metallic cake which is sold to the local parties.

In the proposed project approximately 25 KLD Domestic and Canteen waste will be generated and

it will be treated in the STP of Capacity 25KLD.

30 KLD Effluent is generated which shall be treated in Effluent Treatment Tank and then reused

for gardening and dust suppression purpose. Thus there will be no effluent released from the

Rolling Mill and hence MASPL will adhere to “Zero Liquid Discharge” for this proposed project.

Table 1.2 Water Consumption Details

Sr. No. Purpose (Total input) Total Water Consumption in

Rolling Mill (KLD)

1 Make Up Water for Cooling Tower for Contact

Water

1200

2 Make Up Water for Cooling Tower for Non-

Contact Water

240

3 Domestic &Canteen Purpose 25

5 Filter Backwash& Softening regeneration 60

6 TOTAL 1525

The Project will not relay on reservoir for water but also planning to harvest the rain water

3. PROJECT MOTIVATION

When considering an application submitted under the EIA Regulations, the relevant competent

authority must take a number of factors into consideration, including the need for, and desirability

of, the activity.

The need and desirability of this project is discussed below including strategic plans, frameworks and

policies applicable to the area and project.

Need and Desirability

The Indian economy is rapidly growing and is emerging as the second largest developing economy of

the world, which has a great impact on domestic consumption of steel as well as export potential to

other countries. As a result of this, the demand for iron & steel remains extremely good, which would

continue for next 10 years if not less, since the per capita consumption of steel in India is still very low

compared to other developed countries? For rapid development of economy and infrastructure of the

country, it is necessary to increase the production of steel within the country.

The Indian steel industry is very modern with state-of-the-art steel mills. It has always strived for

continuous modernisation and up-gradation of older plants and higher energy efficiency levels.

As per the report of the Working Group on Steel for the 12th Five Year Plan, there exist many factors

which carry the potential of raising the per capita steel consumption in the country. These include

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 24

among others, an estimated infrastructure investment of nearly a trillion dollars, a projected growth of

manufacturing from current 8% to 11- 12%, increase in urban population to 600 million by 2030 from

the current level of 400 million.

At the time of its release, the National Steel Policy 2005 had envisaged steel production to reach 110

million tonnes by 2019-20. However, based on the assessment of the current ongoing projects, both in

greenfield and brownfield, the Working Group on Steel for the 12th Five Year Plan has projected that

domestic crude steel capacity in the county is likely to be 140 million tonnes by 2016-17 and has the

potential to reach 149 million tonnes, if all requirements are adequately met. Thus, the project will be a

part of the vision.

4. SOCIO-ECONOMIC BASELINE

This section describes the socio-economic environment in which the Project is situated. The

description provided in this section is based on publicly available and secondary information, as well

as primary data collected for the Project.

4.1 AREA OF INFLUENCE (AOI)

The socio-economic baseline description is focused on local level, i.e. within the Area Local Body,

situated in the proposed project site. This is because it is expected that although the proposed Project

will result in macro-economic benefits at a national level, the primary socio-economic impacts of the

Project will be experienced at a district and local level.

The socio-economic area of influence has been divided into the Direct Area of Influence and the

Indirect Area of Influence, these are described below.

4.1.1 Area of Direct Influence

The Area of Direct Influence, ADI, includes the Project footprint and related facilities as well as the

associated effects of the Project on the receiving environment. This encompasses:

• Integrated steel Plant site;

• Roads

In the context of this study, the ADI further includes areas around the site likely to be affected by the

Project activities during the pre-construction, construction and operation phases. The effects can be

positive or negative, short or long term or permanent, as well as direct and in-direct. These areas

include the settlements located within close proximity to the Project Site

4.1.2 Indirect Area of Influence

The Area of Indirect Influence, AII, includes areas within a wider radius of the Project Site, which may

be affected by the Project, this includes, although to a lesser extent

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 25

Figure 4.1 Google Map of Project Site

Co-ordinates of the side corner of the project site:

Corner Points Co-ordinates

A 15°20'7.84"N, 76°15'22.04"E

B 15°20'8.79"N, 76°15'32.49"E

C 15°19'38.56"N, 76°15'38.56"E

D 15°19'39.05"N, 76°15'26.93"E

E 15°19'52.02"N, 76°15'34.48"E

F 15°19'59.06"N, 76°15'20.01"E

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 26

4.2 ADMINISTRATIVE STRUCTURE

Figure 4.2 Administrative Structure

4.3 SITE SETTING AND LANDUSE

4.3.1 Land-use of the Project Site

The basic purpose of land use pattern and classification in an EIA study is to identify the manner in which

different parts of land in an area are being utilized or not utilized. Remote sensing data provides reliable

accurate baseline information for land use mapping, as it is a rapid method of acquiring up-to-date

information of over a large geological area.

A systematic digital image interpretation approach was used to delineate the land use classes. The

present study was focused on demarcating boundaries of different land use/land cover units from an

analysis of different types of colour registrations of land use/land cover units from satellite imagery. Data

Used in the land use map preparation is the satellite Imagery of Indian Remote Sensing Satellite (IRS- ID

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 27

, sensor P6, LISS III) of 24 m resolution. The Swath of the imagery is 141 Km x 141 Km. Band used are

2, 3 4 and 5. LANDSAT imagery of 30 meter resolution and 185 x 185 km swath is also used for the

comparative and overall analysis of the area. LISS III imagery and LANDSAT 4-5 TM imagery were used

for the complete coverage of the study area. Band used are 2, 3 and 4.

Table 4.1 Land Use Distribution of the Study Area (10 km Radius)

LULC Class Area in Ha. % of Area

Crop Land 17038.12 54.23%

Reservoir 2869.30 9.13%

Settlement 740.50 2.36%

Industry 1508.01 4.80%

Quary 212.31 0.68%

Land with Scrub 2468.46 7.86%

Fallow Land 2787.23 8.87%

Urban Built Up 290.93 0.93%

Stony Waste 1324.03 4.21%

Pond/Lake 220.32 0.70%

Mixed Built Up 260.02 0.83%

Hill Forest 1696.27 5.40%

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 28

Figure 4.3 Land Use map at Project Site

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 29

4.4 DEMOGRAPHIC PROFILE

Demography

The study there is 19 villages in the study area. The demographic pattern of all the settlements as per

2011 census is given in Table 4.2

Sex Ratio

Sex ratio is number of females per 1000 males. In the study area the sex ratio is 974.44. As per the

Census 2011 the male population is 50.77 % while female population is 49.23 % of the total population.

Table 4.2 Village-wise details of Population

S.N. Name No of Households

Total Population

Person

Total Population

Male

Total Population

Female

Sex ratio

1 Agalkera 958 4895 2429 2466 1015.23

2 Allanagar 257 1212 627 585 933.01

3 Bahaddurbandi 504 2872 1505 1367 908.31

4 Basapur 395 1968 976 992 1016.39

5 Bevinhalli 460 2315 1173 1142 973.57

6 Budugumpa 1079 5641 2748 2893 1052.77

7 Ginigera 1863 8449 4509 3940 873.81

8 Guldahalli 521 2752 1390 1362 979.86

9 Halahalli 282 1624 817 807 987.76

10 Hireboganhal 471 2411 1271 1140 896.93

11 Hitnal 1113 5608 2820 2788 988.65

12 Indargi 972 5594 2852 2742 961.43

13 Kanakapura 171 1063 521 542 1040.31

14 Kinhal 1995 9802 4936 4866 985.82

15 Koppal (Rural) 3806 18988 9629 9359 971.96

16 Kunikera 577 3471 1781 1690 948.91

17 Lachankera 574 3282 1675 1607 959.40

18 Shivapur 851 4139 2058 2081 1011.18

19 Tankankal 238 1322 658 664 1009.12

Total 17087 87408 44375 43033 974.44

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 30

.

Figure 4.4 Demographic Pattern

Social Distribution: Out of total population, 21.68 % is SC population and 7.69 % is ST Population.

Table 4.3 Social Distribution

Name Total

Population Person

Scheduled Castes

population Person

Scheduled Castes

population Male

Scheduled Castes

population Female

Scheduled Tribes

population Person

Scheduled Tribes

population Male

Scheduled Tribes

population Female

Agalkera 4895 1303 630 673 238 123 115

Allanagar 1212 174 76 98 43 20 23

Bahaddurbandi 2872 209 105 104 159 84 75

Basapur 1968 636 321 315 418 214 204

Bevinhalli 2315 226 113 113 178 92 86

Budugumpa 5641 1309 634 675 492 223 269

Ginigera 8449 2346 1190 1156 532 280 252

Guldahalli 2752 513 260 253 208 101 107

Halahalli 1624 823 420 403 13 7 6

Hireboganhal 2411 313 170 143 42 26 16

Hitnal 5608 820 420 400 435 213 222

Indargi 5594 1207 629 578 829 418 411

Kanakapura 1063 95 53 42 0 0 0

Kinhal 9802 1276 633 643 664 336 328

Koppal (Rural) 18988 3652 1915 1737 648 311 337

Kunikera 3471 2010 1012 998 217 109 108

Lachankera 3282 705 343 362 848 434 414

Shivapur 4139 1157 576 581 720 359 361

Tankankal 1322 175 97 78 37 20 17

Total 87408 18949 9597 9352 6721 3370 3351

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 31

Figure 4.5 Social Pattern

Literacy The overall percentage of literate in the area is 59.69 % and percentage of illiterate population is 40.31.

Table 4.4 Literacy Rate

Name Total Population

Person

Literates Population

Person

Literates Population

Male

Literates Population

Female

Illiterate Persons

Illiterate Male

Illiterate Female

Agalkera 4895 2883 1661 1222 2012 768 1244

Allanagar 1212 703 403 300 509 224 285

Bahaddurbandi 2872 1707 1025 682 1165 480 685

Basapur 1968 953 524 429 1015 452 563

Bevinhalli 2315 1370 801 569 945 372 573

Budugumpa 5641 3061 1778 1283 2580 970 1610

Ginigera 8449 5255 3232 2023 3194 1277 1917

Guldahalli 2752 1544 902 642 1208 488 720

Halahalli 1624 1010 564 446 614 253 361

Hireboganhal 2411 1457 846 611 954 425 529

Hitnal 5608 3343 1934 1409 2265 886 1379

Indargi 5594 2536 1559 977 3058 1293 1765

Kanakapura 1063 460 272 188 603 249 354

Kinhal 9802 6346 3609 2737 3456 1327 2129

Koppal (Rural) 18988 13229 7311 5918 5759 2318 3441

Kunikera 3471 1644 1047 597 1827 734 1093

Lachankera 3282 1931 1176 755 1351 499 852

Shivapur 4139 2153 1243 910 1986 815 1171

Tankankal 1322 586 339 247 736 319 417

Total 87408 52171 30226 21945 35237 14149 21088

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 32

Figure 4.6 Literacy Rate

Employment Scenario

The overall percentage of workers in the area is 45.46 %.

Table 4.5 Employment Scenario

Name Total Popula

tion Person

Total Worke

r Popula

tion Person

Total Worker Populat

ion Male

Total Worker Populat

ion Female

Main Working Populati

on Person

Main Cultivat

or Populat

ion Person

Main Agricult

ural Labour

ers Populat

ion Person

Main Household Industries

Population Perso

n

Main Other Workers

Population Perso

n

Margina

l Worker Population Person

Non Working Population Person

Agalkera

4895 2076 1371 705 2014 446 842 27 699 62 2819

Allanagar

1212 575 364 211 414 76 43 12 283 161 637

Bahaddurban

di

2872 1340 780 560 1234 202 373 21 638 106 1532

Basapur

1968 821 556 265 675 189 329 0 157 146 1147

Bevinhalli

2315 1066 666 400 917 256 60 8 593 149 1249

Budugumpa

5641 2509 1499 1010 2256 981 922 21 332 253 3132

Ginigera

8449 3477 2653 824 2967 379 461 65 2062 510 4972

Guldahalli

2752 1310 780 530 1210 226 453 44 487 100 1442

Halahalli

1624 895 479 416 520 234 128 90 68 375 729

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 33

Hireboganhal

2411 1262 709 553 604 206 130 17 251 658 1149

Hitnal 5608 2409 1527 882 1861 252 886 131 592 548 3199

Indargi 5594 3000 1603 1397 2677 1000 1085 29 563 323 2594

Kanakapura

1063 575 297 278 224 179 18 2 25 351 488

Kinhal 9802 4549 2758 1791 4046 466 1045 365 2170 503 5253

Koppal (Rural)

18988 7618 5297 2321 6871 321 399 456 5695 747 11370

Kunikera

3471 1718 956 762 1362 508 609 31 214 356 1753

Lachankera

3282 1880 975 905 1682 143 1361 15 163 198 1402

Shivapur

4139 2041 1212 829 1215 243 595 31 346 826 2098

Tankankal

1322 617 352 265 616 358 89 20 149 1 705

Total 87408 39738 24834 14904 33365 6665 9828 1385 15487 6373

47670

4.5 LIVELIHOODS AND ECONOMY

The growth of GSDP at constant prices (year-on-year) slightly decreased from 7.2% in 2013-14 to 7.0%

in 2014-15, mainly attributable to the decline in the growth of agriculture from 9.4% in 2013-14 to 4.5%

in 2014-15. However, the growth of industry and services slightly increased from 4.2% and 8.0% in

2013-14 to 4.4% and 8.9% during 2014- 15 respectively. The State economy showed reviving trends

with anticipated growth rate of 6.1% in 2012-13, 7.2% in 2013-14 and 7.0% during 2014-15.

Karnataka’s Gross State Domestic Product (GSDP) at constant (2004-05) prices is expected to grow at

7.0% and reach Rs. 344106 crore in 2014-15. ‘Railways’, ‘Storage’, ‘Trade, Hotels and Restaurants’,

‘Transport by other means’, ‘Real Estate, Ownership of dwellings and Business Services’,

‘Communication’, ‘Public Administration’ and ‘Other Services’ have all contributed to the growth of

services sector (8.9%). Manufacturing sector is expected to grow at 3.2%. The expected growth rate of

‘Electricity, Gas and Water Supply’ is around 8.7%. ‘Agriculture and Livestock’ (4.3%) is the main

contributor to the growth rate achieved in the Agriculture sector (4.5%).

Tourism is one of the fastest growing sectors of Karnataka economy with its contribution to the

country's gross domestic product (GDP) of the state and makes a significant contribution to economic

development and jobs, thus being the most important growth sector in the state.

Further, eco-tourism and agri-tourism are recognized as ways of supplementing the income of farmers.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 34

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 35

4.6 SOCIAL INFRASTRUCTURE AND SERVICES

4.6.1 Connectivity, Transport and Communication

Transport activities included bus and tour-bus services, taxis, school buses, travel agents, the hiring of

transport equipment and telephone and radio-communication services.

• Mangaluru-Sholapur (Maharashtra) NH 13 passes through Kustagi town.

• Ankola-Gooty NH 63 passes through Koppal town.

• Bengaluru-Ballari-Gadag-Hubballi Railway line passes through Koppal town.

• Goods transport facility available from Koppal and Munirabad stations.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 36

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 37

Education:

Educational Institutions in Koppal District

Healthcare:

Healthcare in Koppal District

4.6.2 Water

The only and important river in this district is Tungabhadra river, which form the Southern boundary-of the

district. It has been associated from time immemorial with regional cultural and religious activities and has

several famous shrines on its banks. In the historical and cultural developments of the country, the river

had played a vital role. Legend and tradition have sanctified these perennial sources of water, which has

given an immense impetus to civilization and prosperity of the land.

4.6.3 Housing

The people in the village of the district live in house built of mud with the mud roofing. The walls are

raised by heaping mud layer after layer and leveling the sides with a wooden leveller. In the eastern parts

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 38

of the district palm leaves and stems are used for roofing and are found to be quite useful. Presently,

constructions of concrete roofing house with brick walls are taking place of mud roofing. Few rich people

of the village are having modem type of constructions.

Houses in the rural areas are built with scant respect for sanitation and hygiene; more of them are ill-

ventilated and often lack elementary amenities like drains for waste water. Cattle live in enclosures very

near to the house and add to the insanitation of the houses. Fields round about the village are used for

calls of nature and in many of the house, there are no latrines. The summer season witnesses a period of

water scarcity in many villages.

IMPACT ASSESSMENT

This section presents the potential socio-economic impacts associated with the Project. The potential

impacts have been assessed using the impact assessment methodology provided in Section 1.4.

The following potential impacts are discussed further below:

• Employment creation, skills enhancement and local business opportunities.

• Impacts on community health and safety, including:

• Impacts associated with the presence of the workforce and jobseekers;

• Impacts associated with pressure on social infrastructure;

• Impact on human health due to air emissions and dust generation; o Nuisance due to noise,

dust and traffic on sense of place;

• Worker health and safety and rights; and

• Cumulative impacts.

5. IMPACT ASSESSMENT

5.1 EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS OPPORTUNITIES

The Project is expected to generate positive impacts on the local economy and livelihoods in terms of:

• Employment and skills enhancement; and

• Local business opportunities through the procurement of goods and services.

Positive impacts will be primarily associated with the construction phase and therefore temporary in

nature. The termination of construction contracts will occur once construction activities are completed.

Workers who have relocated to the area for the Project are likely to leave the area in search of other

opportunities, especially if they are permanent employees of contractors and subcontractors.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 39

Those who have worked on the Project will have an advantage when seeking alternative jobs on similar

projects due to the experience and any training received through this Project. The area is characterised

by a number of new industrial developments and is earmarked for other integrated steel projects which

may offer alternative employment opportunities. This is considered within the cumulative impacts Section

5.1.1 Construction: Employment, Skills Enhancement and Local Business Opportunities

Impact Description

The construction phase will last approximately 4-5 years in duration (Phase I & II) and it is expected that

approximately 1000 contact persons opportunities will be available during the peak of construction. The

breakdown of skills required during the construction phase will be as follows:

• Skilled labour

• Semi-skilled labour and

• Unskilled labour

It is assumed that the majority of skilled workforce will come from outside the ADI and AII, but that many

of them will be local. Given that almost half the population in the region have some level of skills training,

it is anticipated that many semi-skilled positions will be available to the local workforce, and that unskilled

positions will also be available to the local workforce. Indirect employment through the construction

supply chain will be limited as the major components of the integrated steel plant are highly specialised

and will be manufactured outside of Karnataka. However, much of the balance of plant of plant

infrastructure for the Project will be procured within region and where possible, from within the Locals.

Local procurement is going to benefit the hospitality and service industries primarily, such as

accommodation, catering, cleaning, transport and security services. Local businesses will benefit during

the construction phase as there will be increased spending within the area by the wage labour who will

have improved buying integrated steel while employed by the Project. Those who are able to secure

employment on the Project will have the opportunity to improve their skills and experience through on-the-

job training, and will thereby improve their opportunities for future employment.

Given that Karnataka has ear-marked for further industrial development, with a focus on the natural

resources, the upskilling of the local workforce will put the local workforce in a favourable position to

secure future employment. Employment numbers during commissioning are not known at this stage, but it

is expected that the make-up of the workforce will be similar to the construction phase.

Impact Assessment

The creation of local employment opportunities, skills enhancement and local business opportunities will

be a direct, indirect and induced impact. The duration will be short-term, for the duration of the

construction phase and work contracts will vary in length, based on the type of work being performed.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 40

Employment will be created for Region at a local level depending on skills and capacity availability, as

such the extent will be regional. For those who are able to secure employment on the Project the scale

will be medium, as they secure an income for the duration of their contract. The frequency of the impact

will be constant for the duration of the construction phase. The magnitude of the impact will be positive.

Given the capacity of the local workforce to fill unskilled and semi-skilled employment positions,

together with the opportunity to increase skills and work experience, the vulnerability is medium.

The significance of the impact is rated as Moderate (+ve).

Proposed mitigation/ enhancement

The objective of mitigation is to optimise opportunities for employment of local people, wherever

possible, or alternatively that employment of Region is prioritised over outside persons

The following measures will be implemented to ensure that employment of local people is maximised:

• The Project will establish a recruitment policy which prioritises the employment of Indian and

local residents (originating from the Local body) over foreigners. Criteria will be set for

prioritising local residents and then other Region as part of the recruitment process.

• All contractors will be required to recruit in terms of the Project’s recruitment policy,

where practical.

• The Project will meet with the Local body to access any available skills/employment-seekers

database for the area. This database is to be updated and made available to the appointed

contractors.

• The Project will advertise job opportunities and criteria for skills and experience needed

through local media, at least three months ahead of recruitment. This information should

also be provided to all relevant authorities, community representatives and organisations on

the interested and affected party database.

• The recruitment policy and procedure should promote the employment of women as a means of

ensuring that gender equality is attained.

• On-the-job performance and training will be monitored through performance reviews. Training

needs will be identified and provided by the Project.

• No employment will take place at the entrance to the site. Only formal channels for

employment will be used.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 41

A local procurement policy will be implemented to ensure that local procurement is

maximised, the policy will include:

• Reasonable targets for using local suppliers.

• A clause of none discrimination on any grounds of gender, ethnicity, religion.

• Criteria for monitoring local procurement and reporting on supplier performance

management.

• Clearly communicate the criteria and tendering process prior to the commencement of

construction activities; and

• The procurement policy and tendering requirements must be easily accessible to

potential suppliers.

• The following management measures will be implemented to enhance skills development and

on-the-job training

• Develop internal training 'certification' or reference letter provisions to those who receive

internal training.

• Training plans will be developed according to each permanent employee work agreement and

relevant to their job description.

Residual impacts

A summary for the impact the construction and phases of the Project is present below.

Table 5.1 Pre- and Post - Mitigation Significance for Employment Creation, Skills

Enhancement and Local Business Opportunities

Impact Project Phase Significance

(Pre-mitigation)

Residual Impact

Significance

(Post-mitigation)

Employment Creation, Skills

Enhancement and Local

Business Opportunities

Construction

Moderate (+ve) Moderate (+ve)

Table 5.2 Pre- and Post - Mitigation Significance for Employment Creation, Skills

Enhancement and Local Business Opportunities during Construction

Nature and Type: Direct, indirect and induced positive impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Positive

• Extent: Regional

• Duration: Short

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 42

• Scale: Large

• Frequency: Constant

• Reversibility: N/A

• Likelihood: N/A

Impact Significance (Pre-Mitigation): Moderate Positive

Impact Significance (Post-Mitigation): Enhancement measure will ensure the impact remains

Moderate Positive.

5.1.2 Operation: Employment, Skills Enhancement and Local Business Opportunities

Impact Description

The integrated steel plant will be operated on a 24 hour, 7 days a week basis for the duration of the

operation phase. It is anticipated that there will be employment positions available during this phase. As

the plant will operate 24 hours a day, three full-time shifts will be created per day, and the breakdown of

the skills required will be as follows:

• Skilled labour:

• Semi-skilled labour: and

• Unskilled labour:

Similar to the construction phase, local workers are expected to be qualified to fill unskilled and semi-

skilled positions at first, whilst a limited number of people may be sufficiently qualified for skilled

positions. Semi-skilled and skilled positions will initially be recruited from elsewhere in the region and

India . Over time, however, local workers will be able to fill more of the semi-skilled and skilled positions

as training will be provided by the Project to the local workforce, will improve skills levels relevant to the

Project.

During the operation phase the contracts that were in place during the construction phase will be

terminated and procurement opportunities will be centred around maintenance activities, and providing

goods and services to the Project. For those companies that meet eligibility criteria, become approved

suppliers and enter the supply chain, there will be long-lasting and sustained benefits to the businesses

and their employees through increased experience, capacity and training. As such, during the operation

phase there will be opportunity for local business growth and development

Impact Assessment

The creation of local employment opportunities, skills enhancement and local business opportunities will

be a direct, indirect and induced impact. The duration will be long-term, for the duration of the operation

phase. Employment will be created for Region at a local and regional level depending on skills and

capacity availability, as such the extent will be regional. For those who are able to secure employment

or procurement contracts with the Project the scale will be large, as they secure long-term, stable

income. The frequency will be constant for the duration of the operation phase. The magnitude of the

impact will be Positive.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 43

Given the limited employment and procurement opportunities during the operation phase, together

with the lack of appropriate skills in the ADI, the vulnerability is low.

The significance of the impact is rated as Minor (+ve).

Proposed mitigation/ enhancement

The mitigation/ enhancement measure provided for the construction phase, will apply to the operation

phase.

Residual impacts

A summary for the impact during the operation phases of the project is presented below.

Table 5.3 Pre- and Post - Mitigation Significance for Employment Creation, Skills

Enhancement and Local Business Opportunities

Impact Project

Phase

Significance

(Pre-mitigation)

Residual Impact

Significance

(Post-mitigation)

Employment Creation,

Skills Enhancement

and

Local Business

Opportunities

Operation Minor (+ve) Minor (+ve)

Table 5.4 Pre- and Post - Mitigation Significance for Employment Creation, Skills

Enhancement and Local Business Opportunities during Operation

Nature and Type: Direct, indirect and induced positive impact Sensitivity/Vulnerability/Importance of Resource/Receptor: Low Impact Magnitude: Positive • Extent: Regional • Duration: Long Term • Scale: Large • Frequency: Constant • Reversibility: N/A • Likelihood: N/A IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR POSITIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): Enhancement measures will ensure the impact remains

MINOR POSITIVE.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 44

5.2 IMPACTS ON COMMUNITY HEALTH AND SAFETY

The presence of the Project could affect the health, safety and security of the communities in the area

of influence as a result of worker-community interactions, in-migration to the area, increased incomes in

the local community that may be used for drugs, alcohol and prostitution, the risk of injury associated

with construction and activities, increased pressure on health care resources and changes to the

environment. Any community concerns or perceptions with regard to reduced health and physical safety

and security by the community need to be addressed.

There are numerous ways in which the development of the Project could impact on community and

individual levels of health. The term “health” is used broadly to include physical and mental health

and well-being. The expected impacts on community health, safety and security as a result of

construction, operation and of the Project are:

• Impacts associated with the presence of the Project workforce.

• Impacts associated with an influx of jobseekers.

• Impact on human health due to air emissions.

5.2.1 Construction and Operation: Impacts Associated with the Presence of the Workforce and Jobseekers

Impact Description

An increase in disposable income within the Project Area (among Project

workers, both local and external) has been observed to result in a change in

spending habits and behaviour resulting in increase in alcohol and drug

abuse, increased incidences of prostitution and casual sexual relations, which poses a threat to

community health and safety. Anticipated impacts associated with the presence of the workforce are:

• Increased incidence of alcohol and drug use;

• Increase in the spread of HIV/ Aids and other STIs;

• Increased incidence of teenage or unwanted pregnancies; and

It is estimated that there will be employed people during the peak construction phase. The Project will

seek to maximise the employment of local people, thereby reducing the size of the external workforce in

the ADI, however an external workforce will be required. The external workforce (largely comprised of

semi-skilled and skilled workers) will be housed with the ADI, as onsite worker accommodation is not

feasible for health and safety reasons given the Project

Site’s close proximity to Hospet.

Experience from large infrastructure projects elsewhere in India has shown that increased disposable

income within the local workforce may result in increased incidences of illegal activities as well as

increased levels of substance abuse. Abuse of alcohol (and drugs, should this occur) often correlates with

increased levels of criminal behaviour and violence (e.g.domestic violence) while under the influence of

the substance. Such behaviour increases the number of people indirectly affected by, or vulnerable to,

alcohol and drug abuse; and casual sexual relations could lead to an increased incidence of HIV/AIDS.

Further, it has been shown that members of an external workforce are likely to father children with local

women while they are living in the Project Area. Given the temporary nature of the work, it is possible that

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 45

both the women and children will be abandoned when the construction phase ends and the contractors

move on, leaving single female-headed households. A further impact associated with an influx of

jobseekers is the potential for their jobs. Competition for jobs has been raised as a concern by some

stakeholders.

Impact Assessment

The impacts related to the presence of the workforce and jobseekers in the Project Area will be indirect

and negative as the presence of a mostly male workforce, with an increased disposable income may

adversely impact on health, safety and security of the local community through a likely increase in illegal

or antisocial behaviour., The impact will be experienced at a local level, within the ADI. While the

workforce will be in the Project Area for a limited time during the construction phase, jobseekers may

stay in the area. Those affected by antisocial behaviour, such as the victims of abuse and people living

with HIV/ AIDS, the duration of the impact will be long-term. The scale of the impact will be large for

those affected as it will lead to a fundamental change in their life, and/ or health status, particularly for

those affected by violence, unwanted pregnancies or HIV/ AIDS. For those affected, the impact will be

largely irreversible. The frequency of the impacts will not be uniform, but may be felt often. Given the

above, the magnitude of the impact is considered medium.

The external workforce will be housed within the Area and will interact with the local community. The

local workforce will come from residential areas within the ADI.

During the operation phase, there will be limited employment opportunities and the external construction

workforce will likely leave the area. The number of local people with disposable income will decrease, as

will the impacts associated with this. This impact will not be felt during the operation phase.

Proposed mitigation/ enhancement

The Project will develop an induction programme, including a Code of Conduct, for all workers directly

related to the project. A copy of the Code of Conduct is to be presented to all workers and signed by

each person. The Code of Conduct must address the following aspects:

• respect for local residents and customs;

• zero tolerance of bribery or corruption;

• zero tolerance of illegal activities by construction personnel including: unlicensed prostitution;

illegal sale or purchase of alcohol; sale, purchase or consumption of drugs; illegal gambling or fighting;

• no alcohol and drugs policy during working time or at times that will affect ability to work;

• description of disciplinary measures for infringement of the Code and company rules. If workers

are found to be in contravention of the Code of Conduct, which they signed at the commencement of

their contract, they will face disciplinary procedures that could result in dismissal.

The Project will implement a grievance procedure that is easily accessible to the local community,

through which complaints related to contractor or employee behaviour can be lodged and responded

to. The Project will respond in a serious manner to any such complaints. Key steps include:

• Circulation of contact details of ‘grievance officer’ or other key Project contact;

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 46

• Awareness raising among the local community regarding the grievance procedure and how it

works; and

• Establishment of a grievance register to be updated and maintained by the Project.

The Project will develop and implement an HIV/AIDS policy and information document for all workers

directly related to the Project. The information document will address factual health issues as well as

behaviour change issues around the transmission and infection of HIV/AIDS.

Residual impacts

The implementation of the above mitigation measures would ensure that the construction phase

significance is reduced to Minor- Moderate significance. A summary for the impact the construction

phase of the Project is present below.

Table 5.5 Pre- and Post- Mitigation Significance for Impacts Associated with the Presence

of the Workforce and Jobseekers

Table 5.6 Pre- and Post- Mitigation Significance for Impacts Associated with the Presence

of a Workforce and Jobseekers

Nature and Type: Indirect negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Medium

• Extent: Local

• Duration: Permanent

• Scale: Large

• Frequency: Constant

• Reversibility: Irreversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MINOR - MODERATE NEGATIVE

Impact Project Phase Significance

(Pre-mitigation)

Residual Impact

Significance

(Post-mitigation)

Impacts Associated

with

the Presence of a

Workforce

Construction

and Decommissioning

Moderate (-ve) Minor - Moderate (-ve)

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 47

5.2.2 Construction and Operation: Pressure on Social Infrastructure and Services

Impact Description

It is generally accepted that large-scale infrastructure projects attract job- seekers into the Project Area.

The Project is expected to stimulate in-migration as job-seekers enter the area with the intention of

securing employment on the Project. In-migration of people will be further stimulated by possibility of

business opportunities linked to the provision of goods and services to the Project, and by real or

perceived opportunities arising from the general increase in economic activity in the area.

It is likely that a number of people will continue to stay in the area irrespective of whether they are able to

secure employment and these people may move their families to the area. There is the possibility that

people will return to their place of origin or move on to seek employment elsewhere if there are no

employment opportunities for them, or when the construction phase is complete. The expected impacts

associated with an influx of jobseekers are:

• Pressure on existing social infrastructure – particularly housing, education and health facilities

The presence of the Project is likely to increase the rate of in-migration into the area, as people

are attracted to the area in the hope of securing employment. The increase in population is

expected to add pressure on existing infrastructure and services; specifically on housing services.

This could be further exacerbated if job seekers decide to relocate their families to the area.

An influx of jobseekers and their families would place pressure on health and education facilities. These

already understaffed clinics would be placed under pressure to cope with the increase in population

within their catchment.

Impact Assessment

The impacts related to pressure on social infrastructure and services will be an indirect impact. The

impacts will be negative as they will place pressure on infrastructure and services and the local

government, who will have to provide the services should the influx occur.

The impact will be experienced at a local level, within the ADI. The impacts will be long-term despite the

fact that the period of influx may be limited to the construction phase, the associated impacts will

continue to occur into the future. The scale of the impact will be medium, as the Project is not expected

to attract large volumes of in-migration and the degree of change for local population will therefore be

notable but will not dominate over existing conditions. The frequency of the impacts will not be uniform,

but will felt often until in-migration stabilises and upgrades to infrastructure are undertaken. The impact

is revisable as social infrastructure and services can be improved to address the impact. Given the

information presented above, the impact will be medium in magnitude.

The population within the area like Hospet has been increasing which has been attributed to the in-

migration of people seeking economic opportunities. Therefore, the vulnerability of receptors is

considered low.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 48

Therefore, the significance of the impact is rated as Moderate, the level of in-migration, and

movement of job-seekers cannot be accurately predicted.

During the operational phase, there will limited employment opportunities and the Project is unlikely to

attract further job seekers.

Proposed Mitigation Measures

The Project will implement a grievance procedure that is easily accessible to the local community,

through which complaints related to contractor or

employee behaviour can be lodged and responded to. The Project will respond in a serious

manner to any such complaints. Key steps include:

• Circulation of contact details of ‘grievance officer’ or other key Project contact.

• Awareness raising among the local community regarding the grievance procedure and how it

works.

• Establishment of a grievance register to be updated and maintained by the Project.

Implement management measures associated with the prioritization of local labour, as outlined in

Section 5.1.1

Residual impacts

The implementation of the above mitigation measures would ensure that the construction phase

significance remains of Moderate significance.

A summary for the impact the construction phase of the Project is present below.

Table 5.7 Pre- and Post- Mitigation Significance for Impacts Associated with Pressure on

Social Infrastructure and Services

Impact Project Phase Significance

(Pre-mitigation)

Residual Impact

Significance

(Post-mitigation)

Impacts Associated with

Pressure on Social

Infrastructure and

Services

Construction Moderate (-ve) Moderate (-ve)

Nature and Type: Indirect negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Medium

• Extent: Local

• Duration: Long term

• Scale: Medium

• Frequency: Often

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 49

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE

5.2.3 Construction Phase: Impact on Human Health due to Air Emissions and Dust Generation

Impact Description

Most construction and activities generate dust, which settles on surrounding properties and land, and is

often more of a nuisance than a health issue. The dust is generally coarse, but may include fine

respirable particles (PM10) and these are known to be a risk to human health. Exhaust emissions from

construction vehicles and equipment typically include particulates (including PM10), carbon monoxide

(CO), nitrogen oxides (NOX), sulphur dioxide (SO2). The creation of dust associated with vehicle traffic

will be limited as most of the roads in the ADI are tar & paved.

Impact Assessment

The impacts on human health due to air emissions and dust generation will be a direct, negative impact.

The duration will be short-term, for the duration of the construction phase. The extent of the impact will

local, as the pollutants will be limited in dispersion and will occur onsite and around the main transport

routes. Based on the outcomes of the Air Quality Report of EIA , air emissions generated as a result of

construction phase activities not expected to have an adverse effect on health, therefore the degree of

change experienced by individuals will be negligible and the scale of the impact will be small. The impact

is considered reversible. The frequency of the impact will vary depending on construction activities, but it

will be often for the duration of the construction phase. Given the above factors, the magnitude of the

impact is considered small.

The vulnerability of receptors is considered low as the Project Site located in an industrial area with no

sensitive receptors located adjacent to the site. People living along transport routes have access to

health care and would be able to seek medical attention if their health was adversely affect by air

emissions.

Therefore it is anticipated that the significance of the impact will be negligible.

Mitigation

All of the mitigation measures outlined in EIA report must be implemented by the Project. In

addition, the Project will develop and implement a Grievance Mechanism to address stakeholder

concerns related to the Project in a timely manner.

Residual Impact

The implementation of mitigation measures will ensure that the impact remains of negligible

significance.

Table 5.8 Pre - and Post- Mitigation Significance for Impact on Human Health due to Air

Emissions and Dust Generation

Impact Project Phase Significance

(Pre-mitigation)

Residual Impact

Significance

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 50

(Post-mitigation)

Impact on Human Health

due to Air Emissions and

Dust Generation

Construction Negligible Negligible

Nature and Type: Direct, negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Low

• Extent: Local

• Duration: Short-term

• Scale: Small

• Frequency: Often

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): NEGLIGABLE

IMPACT SIGNIFICANCE (POST-MITIGATION): NEGLIGABLE

5.2.4 Operations Phase: Impact on Human Health due to Air Emissions

Impact Description

The operation of the integrated steel plant will result in emissions due to the operations , which could

result in decreases in air quality. Emissions of air pollutants from the integrated steel plant will result

during operations resulting in PM 10 & 2.5 , SOx, NOX, CO and CO2 emissions . Increased emissions

of any of these pollutants may not result in negative implications for human health as the emissions are

quiet low . In order to protect human health, air quality standards have been established and emissions

below these standards are considered to have a negligible impact on the health of communities.

Impact Assessment

The impacts on human health due to air emissions and dust generation will be a direct, negative impact.

The duration will be long-term, for the duration of the operation phase. The extent of the impact will local,

as the pollutants will be limited in dispersion, occurring onsite and adjacent to the site, as well as the

main transport routes. Based on the outcomes of the Air Quality Report, (Refere EIA report) for all

pollutants the predicted ambient concentrations are well below the respective National Ambient Air

Quality Standards (NAAQS). Therefore, air emissions generated as a result of the operation phase is not

expected to have an adverse effect on health - the degree of change experienced by individuals will be

negligible and the scale of the impact will be small. The impact is considered reversible. The frequency of

the impact will be constant, as the integrated steel plant will operate 24 hrs a day, 7 days a week. Given

the above factors, the magnitude of the impact is considered medium.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 51

The vulnerability of receptors is considered low as the Project Site is located in an industrial area with no

sensitive receptors located adjacent to the site. People living along transport routes have access to

health care and would be able to seek medical attention if their health was adversely affect by air

emissions.

Therefore it is anticipated that the significance of the impact will be Minor (-ve).

Mitigation

All of the mitigation measures outlined in EIA report must be implemented by the Project.

In addition, the Project will develop and implement a Grievance Mechanism to address stakeholder

concerns related to the Project in a timely manner.

Residual Impact

The implementation of mitigation measures will ensure that the impact remains of Minor

significance.

Table 5.9 Pre - and Post- Mitigation Significance for Impact on Human Health due to Air

Emissions and Dust Generation

Table 5.10 Pre - and Post- Mitigation Significance for Impact on Human Health due to Air

Emissions and Dust Generation

Nature and Type: Direct, negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Low

Impact Magnitude: Medium

• Extent: Local

• Duration: Long-term

• Scale: Small

• Frequency: Constant

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 52

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR

IMPACT SIGNIFICANCE (POST-MITIGATION): MINOR

5.3 INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE

The Project Site is located within an industrial area, adjacent to the Saldanha Steel facility. The land

immediately surrounding the site it utilised for industrial purposes, grazing or is vacant land. Within the

broader area, much of the surrounding land to the north and east is utilised for agriculture, nature

reserves.

There are existing visual intrusions around the Project Site, such as steel plants , railway lines ,

industrial , therefore, the landscape should not be seen as pristine.

The Project will introduce integrated steel plant and associated infrastructure such as a power plant,

substation and Operation and Maintenance (O&M) buildings into the area, within close proximity to

existing industrial infrastructure. The construction and operation of the Project will lead to an

increase in ambient noise, the generation of dust and increased traffic volumes, all of which have the

ability to alter the sense of place of the existing environment.

5.3.1 Construction and Phase: Increased Nuisance Factors and Change in Sense of Place

Impact Description

Impacts associated with air quality, traffic and noise have been assessed by specialists and are

discussed in EIA in Traffic Assessment Report, the Noise Impact Assessment Report and Air Quality

Report .

The Project will cause nuisance of the communities in the ADI due to noise, dust and vibration, as well as

increased traffic volumes during construction and .

Noise levels are expected to increase as a result of construction activities on site such as trucks that

deliver construction equipment and materials; earthworks using heavy machinery, and site preparation, or

piling activities if required.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 53

Additional vehicle movements during peak periods are anticipated during the peak hour, the minibus,

taxis. The buses & cars will collect and dispatch the workforce in the vicinity of the site, including areas in

the ADI.

The anticipated ambient noise levels during the construction phase of the Project has been modelled and

based on the results thereof, it is anticipated that the change in ambient noise levels will be negligible

during construction.

The construction phase sound levels may impact on the ambient noise levels for an area will affect very

small radius from Project Site.

The increase in traffic volumes will be notable during peak traffic times in the morning and afternoon, and

may frustrate other road users, but the increase in traffic will be manageable through the implementation

of mitigation measures.

Dust associated with the Project will be largely limited to the Project site. While each of the above

mentioned impacts are considered to be largely manageable, the combined effect of the noise, dust and

traffic impacts are likely to have a negative impact on the sense of place for some stakeholders.

Impact Assessment

The impacts associated with increased nuisance factors and change in sense of place during construction

and will be a direct, negative impact. The duration will be short-term, for the duration of the construction

phase. The extent of the impact will local, limited to the site and immediate surrounds, as well as the local

transport routes. The scale of the impact will be medium. The impact is considered reversible. The

frequency of the impact will vary depending on construction activities, but it will be often as it relates to

nuisance factors, and constant as it relates to sense of place. Given the above factors, the magnitude of

the impact is considered medium.

The vulnerability of receptors is considered small to medium, as traffic volumes in the area are low, and

road users will find the increased traffic volumes quiet low . The construction phase sound levels may

impact on the ambient noise levels for an area very near to the Project Site.

Therefore it is anticipated that the significance of the impact will be Moderate negative.

Mitigation

All of the mitigation measures outlined in EIA report , Traffic Assessment Report, the Noise Impact

Assessment Report and Air Quality Report must be implemented by the Project.

In addition, the Project will develop and implement a Grievance Mechanism to address stakeholder

concerns related to the Project in a timely manner.

Residual Impact

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 54

The implementation of mitigation measures will result in the impact being of Minor significance.

Table 5.11 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and

Change in Sense of Place

Table 5.12 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and

Change in Sense of Place during Construction and

Nature and Type: Direct, negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Medium

• Extent: Local

• Duration: Short-term

• Scale: Medium

• Frequency: Often to constant

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MINOR NEGATIVE.

5.3.2 Operation Phase: Increased Nuisance Factors

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 55

Impact Description

The Project will cause nuisance to the communities in the ADI due to noise, dust and vibration, as well as

increased traffic volumes during operation. This will affect the communities and households closest to the

Project site and along the main access roads, as well as along the routes used to transport the workforce

to and from the site on a daily basis.

During operation, the integrated steel plant will operate 24 hours a day, seven days a week. It is

anticipated that the change in ambient noise levels will be negligible during Phase 1 of the project and

lately during Phase 2, .This noise will have a more constant characteristic and will be perceived as a

humming sound. Operational phase sound levels may not impact the area beyond the facility.

The Project associated traffic will decrease during the operations phase as there will be fewer people

employed by the Project during this phase. Additional vehicle movements are associated with the

commuting of employees to and from work each day. Additional vehicle movements during peak periods

are anticipated.

The presence of the Project may alter the visual character of the landscape during the operation phase.

While the Project Site is not located in industrial area Based on a Visual Impact Assessment for a similar

integrated steel plant facility.

The Project will not be visible from tourism spots nor roads.

Impact Assessment

The impacts due to increased nuisance factors and change in sense of place during operation will be a

direct, negative impact. The duration will be long-term, for the duration of the operation phase. The

extent of the impact will local, limited to the site and immediate surrounds, as well as the local transport

routes. It is anticipated that the change in ambient noise levels will be negligible during Phase 1 of the

project and low during Phase 2 .The Project will not be visible from a any tourist areas . Given the

distance between the Project and the potential receptors, it can be concluded that while the Project will

not be visible, it will not dominate the landscape or detract from the receptors experience in of the area.

Never-the-less, for those receptors impacted by for increased nuisance factors and change in sense of

place the scale of the impact will be medium.

The impact is considered irreversible. The frequency of the impact will be constant for the duration of

the operation phase. Given the above factors, the magnitude of the impact is considered medium.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 56

The vulnerability of receptors is considered medium as most sensitive receptors are located in quiet

areas, with low ambient noise levels, low traffic volumes, and are people who are attracted to the area

for outdoor.

Therefore it is anticipated that the significance of the impact will be Moderate (-ve).

Mitigation

The ability to which visual impacts can be managed is limited by the size of the facility and the

industry standards governing setbacks and fire control. However, the following measures should be

implemented to minimise the impact of lighting at night:

• Lighting should be limited to areas where it is required.

• Lights should be directional and avoid light spillage.

• Low-level lights should be used over flood lights along walkways.

All of the mitigation measures outlined in EIA report , the Traffic Assessment Report the Noise Impact

Assessment Report and Air Quality Report must be implemented by the Project.

In addition, the Project will develop and implement a Grievance Mechanism to address stakeholder

concerns related to the Project in a timely manner.

Residual Impact

The implementation of mitigation measures will result in the remaining of Moderate negative

significance.

Table 5.13 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and

Change in Sense of Place During Operation

Impact Project Phase Significance

(Pre-mitigation)

Residual Impact

Significance

(Post-mitigation)

Increased nuisance

factors

and change in sense of

place operation

Operation Moderate (-ve) Moderate (-ve)

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 57

Table 5.14 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and

Change in Sense of Place Operation

Nature and Type: Direct, negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Medium

• Extent: Local

• Duration: Long-term

• Scale: Medium

• Frequency: Constant

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE.

5.4 WORKER HEALTH AND SAFETY AND RIGHTS

Workers’ rights including occupational health and safety need to be considered to avoid accidents and

injuries, loss of man-hours, labour abuses and to ensure fair treatment, remuneration and working and

living conditions.

These issues will be considered not only for workers who are directly employed by the Project but also

contractors (including sub-contractors) and workers within the supply chain. The main risks in relation

to worker’s management and rights are associated with the use of contractors and subcontractors and

the supply chain.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 58

The Project is expected create direct employment opportunities during the peak of the construction

period, which will be 2-3 years in duration. The majority of workers will be engaged by the EPC

contractor and will consist of a semi-skilled to skilled workforce. The operation phase is planned for a

lifespan of 25 - 30 years and will involve around 95 permanent site employees including skilled and

semi-skilled staff.

The expected impacts on worker rights and H&S as a result of construction, operation and activities and

Project operation are as follows:

• Risk to workers H&S due to construction and activities;

• Risk to workers H&S due to hazardous operation activities; and

• Violation of workers’ rights.

This impact assessment is based on the assumption that no specific Project H&S policies, procedures

and training provisions are in place for construction workers (both of EPC Contractor and subcontractors)

as limited information is available on this at the current Project stage.

5.4.1 Construction Phase: Risk to Workers’ H&S due to Construction Activities

Impact Description

The construction activities will involve the following main activities (in order of occurrence):

• Site preparation including levelling;

• Piling of the foundations;

• Concrete works in scope of building construction;

Details of the activities associated with are not yet detailed but will involve removal of all installed

infrastructure.

These activities will involve the operation of heavy equipment and trucks, working at height, working in

confined spaces, construction traffic, use of electric devices, handling of hazardous materials and other

hazardous activities. Due to the nature of the activities being undertaken during construction and ,

worker H&S is a key risk with the potential for accidents that may result in injuries and fatalities as well

as lost man-hours.

Within India , worker health and safety falls under the ambit of the Department of Labour, and is

primarily governed through the EPA 1986,Cosntrcors workers safety rules . Employees working

informally and those with limited or without awareness of their rights (for example, migrant workers, or

those newly entering the labour market) are likely to be most at risk of working in unsafe conditions.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 59

Impact Assessment

The impact on worker health and safety from the Project will be a direct, negative impact. The duration

will be short-term, for the duration of the construction phase. The extent of the impact will be regional, as

it will affect those directly employed by the Project, as well as people employed in the supply chain. The

scale of the impact will be large for anyone adversely affected by a health and safety incident on the

Project, as they may experience a temporary loss of work time, or in the worst-case scenario may be

rendered permanently unable to work. In most instances, this impact is considered reversible, as

incidences can be addressed through medical intervention where required and health and safety can be

constantly improved to avoid future incidences. The frequency of the impact will not be uniform, but will

likely occur often the duration of the construction phase. The magnitude of the impact is therefore

considered Medium.

The vulnerability of the workers to this impact is considered low, as there are laws in place in India to

protect worker rights. However, migrant workers, or those newly entering the labour market may not be

aware of their rights, and people may be willing to compromise their rights to secure employment in light

of high unemployment rates.

The impact is therefore considered to be of Minor - Moderate negative significance.

Mitigation

• The Project will comply with all applicable India n legislation in terms of health and safety, and

worker rights, which will include access to workmans compensation for loss of income resulting from an

onsite incident.

• As part of the contractor and supplier selection process the Project will take into consideration

performance with regard to worker management, worker rights, health and safety as outlined in India n

law, international standards and the Project’s policies.

• The Project will provide support to contractors and subcontractors to ensure that labour and

working conditions are in line with India n law through capacity building.

• Workers will be provided with primary health care and basic first aid at construction camps

/worksites.

• Facilities and operations will be developed, planned and maintained such that robust barriers

are in place to prevent accidents. All employees have the duty to stop any works if adequate systems to

control risks are not in place.

• In line with the worker code of conduct employees should not be under the influence of

intoxicants which could adversely affect the ability of that employee to perform the work or adversely

affect the health and safety of other employees, other persons or the environment.

• The Project will provide of Personal Protective Equipment (PPE), training and monitoring as

well as ongoing safety checks and safety audits.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 60

Residual Impact

Following the implementation of mitigation measures the impact significance will be (post-mitigation) of

Minor negative significance.

Table 5.15 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to

Hazardous Construction Activities

Table 5.16 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to

Hazardous Construction and Activities

Nature and Type: Direct, negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Low to Medium

Impact Magnitude: Low

• Extent: Regional

• Duration: Short-term

• Scale: Large

• Frequency: Often

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR to MODERATE NEGATIVE IMPACT

SIGNIFICANCE (POST-MITIGATION): Enhancement measures will ensure the impact remains MINOR

NEGATIVE.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 61

5.4.2 Operation Phase: Risk to Workers’ H&S due to Hazardous Operation Activities

Please note: For the operation of the Project the mitigation and prevention measures outlined above

for construction (Section 5.4.1) are considered as embedded controls.

Impact Description

Hazardous activities during the operation phase and regular maintenance activities will include, but not

be limited to; the operation of heavy equipment and trucks, use of electrical devices including high

voltage, working at height, maintenance of high pressure pipework and vessels and handling of

hazardous materials. During these activities the workers will be at risk for accidents and injury.

Impact Assessment

The impact on worker health and safety as a result of the Project will be a direct, negative impact. The

duration will be long-term, for the duration of the operation phase. The extent of the impact will be

regional, as it will affect those directly employed by the Project, as well as people employed in the supply

chain. The scale of the impact will be large for anyone adversely affected by a health and safety incident

on the Project, as they may experience a temporary loss of work time, or in the worst-case scenario may

be rendered permanently unable to work. In most instances, this impact is considered reversible, as

incidences can be addressed through medical intervention where required and health and safety can be

constantly improved to avoid future incidences. The frequency of the impact will not be uniform, but will

likely occur occasionally the duration of the operation phase. The magnitude of the impact is therefore

considered small.

The vulnerability of the workers to this impact is considered low, as there are laws in place in India to

protect worker rights and most employees will be highly skilled engineers and technicians, who have

likely been educated around their rights and H&S practices.

The impact is therefore considered to be of minor significance.

Mitigation

The implementation of mitigation measures defined for the construction phase will continued throughout

the operation phase with consideration in the health and safety management system of the specific risks

associated with operation and maintenance activities and the new size and structure of the workforce. In

this regard, mitigation measures outlined in Section 5.4.1 above are applicable to the operation.

Residual Impacts

The implementation of mitigation measures will ensure that the significance remains of minor negative

significance.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 62

Table 5.17 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to

Hazardous Operation Activities

Table 5.18 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to

Hazardous Operation Activities

Nature and Type: Direct, negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Low

Impact Magnitude: Low

• Extent: Regional

• Duration: Long TERM

• Scale: Large

• Frequency: Rare

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): Enhancement measures will ensure the impact remains

MINOR NEGATIVE.

5.5 CUMULATIVE IMPACTS

The Project is located in an area ear-marked for further industrial development. The National

Department of Energy, through its Gas to Integrated steel Programme, is investigating the feasibility of

development of a gas-fired integrated steel station in the area. In addition, the IDZ is being promoted

as an oil and gas hub and industrial development is being encouraged in the area.

The preceding impact assessment assessed the socio-economic impacts associated with the Project

largely in isolation. It is important to, assess cumulative impacts associated with a proposed

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 63

development and there also is a legislated requirement in India to do so. The cumulative impacts on the

socio-economic environment are discussed below.

5.5.1 Method

There are numerous proposed developments in the area. At this stage, not all developments can be

confirmed and the timing of the developments is not known. A selection of similar developments and

those either confirmed or most likely have been considered in this cumulative impact assessment

including the existing & proposed industries .

The cumulative impact of the above mentioned projects, together with the Integrated steel Plant

may impact of the following:

• Economy, Employment and Skills

• Community Health Safety and Security

• Pressure on Social Infrastructure and Services

As per the ToR issued by MoEF&CC, the methodology described in Chapter 1 of EIA has been used

to assess the cumulative impacts.

5.5.2 Cumulative Impacts of the Socioeconomic Environment

Economy, Employment and Skills Development

Impact Description

The development of large scale industrial projects will result in increased direct and indirect employment

during the construction and operation of each of the projects. The nature and extent of the benefits will

depend on the employment strategy of the various developers and the extent to which they are

committed to maximise local employment.

There may be overlap between the construction phases of the Project with the other developments, or

they may run consecutively. Either way, this will result in a significant uplift in local employment directly

and indirectly through the procurement of goods and services. Furthermore, those that have been

employed by one of the developers may be in better position to find employment with the other

developers as they will have increased their skills and experience. As such, the potential for cumulative

positive benefits associated with economy, employment and skills development is considered to be

higher than for the Project alone.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 64

The operation of the developments outlined will occur over the same period of time and will be located in

close proximity as such the economic, employment and skills development opportunities outlined will be

greater for all the projects combined then just for the Project development.

It should be noted that expectations regarding economic development, employment and skills

development will be high amongst stakeholders in the local community and as such, in the event that

one developer does not meet expectations, there is the potential for all developers to be the target of

this negative feedback.

Impact Assessment

The cumulative creation of local employment opportunities, skills enhancement and local business

opportunities will be a direct, indirect and induced impact. The duration will be medium to long-term, as

the Projects will not all happen concurrently. Employment will be created for Region at a local and

regional level depending on skills requirements of each project, as such the extent will be regional. For

those who are able to secure employment on the Project the scale will be medium to high, depending on

the duration of the contract. The magnitude of the impact will be positive.

Given the capacity of the local workforce to fill unskilled and semi-skilled employment positions,

together with the opportunity to increase skills and work experience, the vulnerability is medium.

The significance of the impact is rated as Moderate (+ve).

Proposed mitigation/ enhancement

It is recommended the Project investigates opportunities to work with other developers to develop a

collaborative approaches to training, employment and skills development for the local population,

starting now in the run up to Project construction. This may include developing a coordinated standard

set of requirements for service providers (eg required labour numbers of carpenters, welders, Heavy

Goods Vehicle drivers, etc. and the minimum qualifications required for these) and making the

communities aware of these requirements. The developers should also plan and implement a

coordinated approach to community skills development based on these requirements.

Residual impacts

The implementation of the above mentioned mitigation measures will ensure that the positive impact on

the Economy, Employment and Skills Development remains moderate positive.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 65

Table 5.19 Pre- and Post - Mitigation Significance for Economy, Employment and Skills

Development Cumulative Impact

A summary for the impact presented below.

Table 5.20 Pre- and Post - Mitigation Significance for Economy, Employment and Skills

Development Cumulative Impact

Nature and Type: Indirect positive impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Positive

• Extent: Regional

• Duration: Long TERM

• Scale: Medium to Large

• Reversibility: N/A

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE POSITIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE POSITIVE.

Community Health Safety and Security

Impact Description

The presence of an external workforce for the combined projects housed within the communities and

construction camps could increase the spread of communicable diseases and STIs such as HIV/AIDS.

The profile of these diseases will be influenced by the existing health profile of communities within the

area of influence of the project and that of the workers, which is difficult to predict for the various

projects.

Increased air emissions as a result of the Project and another integrated steel plant as well as additional

risks of industrial accidents and explosions could result in cumulative impacts on community health and

safety. However, according to the Air Quality Report (Annex D of EIR), the cumulative impact on air

quality is expected to be minor, and according to the QRA(Annex D of EIR), the cumulative risks

associated with the Project are acceptable.

While the Project alone is not expected to attract vast numbers of jobseekers to the area, the

development of multiple projects is likely to attract people seeking employment opportunities, particularly

in light of a declining agricultural sector in the West Coast District Body , and given that Area is already

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 66

seen as an economic hub. An influx of jobseekers will result in increased competition for employment

which may contribute locally to social tension and conflict within the local communities.

Impact Assessment

The impacts related to community health and safety in the Project Area will be indirect and negative. The

impact will be experienced at a local level, within the ADI. The duration of the impact will be long term, as

projects may occur over an extended period of time. The scale of the impact will be large for those

affected as it will lead to a fundamental change in their life, and/ or health status, particularly for those

affected by violence, unwanted pregnancies or HIV/ AIDS. For those affected, the impact will be largely

irreversible. Given the above, the magnitude of the impact is considered medium.

In light of this, the vulnerability of receptors is considered medium, however, teenage girls are

considered to be highly sensitive to this impact.

The significance of the impact is rated as Moderate negative overall, but the significance will be of

high negative to those affected by unwanted pregnancies and HIV/ AIDS.

Proposed mitigation/ enhancement

• The Project should engage with other developers to ensure that community education and

awareness campaigns in relation to health, safety and security are developed and implemented

collaboratively to avoid duplication of effort.

• The Project should engage with its neighbours to develop combined emergency response plans

which take into account all the proposed developments and the community. This should consider

combined use of security personal and risks from unplanned events.

Residual impacts

The implementation of the above mitigation measures would ensure that the impact significance

remains that of Moderate.

A summary for the cumulative impact is present below.

Table 5.21 Pre- and Post- Mitigation Significance for Community Health and Safety

Cumulative Impact

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 67

Table 5.22 Pre- and Post- Mitigation Significance for Community Health and Safety

Cumulative Impact

Nature and Type: Indirect negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Medium

• Extent: Local

• Duration: Long term

• Scale: Large

• Reversibility: Irreversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE

Pressure on Social Infrastructure and Services

Impact Description

Related to the above, the influx of jobseekers together with presence of the workforce associated with

each Project could place additional pressure on the delivery of social infrastructure and services, in

particular housing. This is largely related to the unskilled workforce, as it is expected that the skilled and

semi-skilled workforce would be able to enter the housing market.

Projects that bring a large external unskilled workforce in the area and do not provide accommodation

will be increasing the burden on the provision of low cost housing.

Impact Assessment

The impacts related to increased pressure on existing social infrastructure and services will be an

indirect impact. The impacts will be negative as they will place pressure on infrastructure and services

and the local government, who will have to provide the services as demand grows.

The impact will be experienced at a local level, within the ADI. The impacts will be long-term as the

provision of social infrastructure and services may take time to catch-up with the increased demand. The

scale of the impact will be medium, as it will notable but will not dominate over existing conditions. The

impact is revisable as social infrastructure and services can be improved to address the impact. Given

the information presented above, the impact will be medium in magnitude. The population within the area

has been increasing at a rate greater than expected which has been attributed to the in-migration of

people seeking economic opportunities.

Therefore, the significance of the impact is rated as Moderate negative.

Proposed mitigation/ enhancement

Mitigation measures implemented by the Project, particularly a commitment to employing local labour

will help to minimise this impact, however, the potential impact on social infrastructure and services

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 68

remains that of moderate, as the Project cannot influence how other developments employ or house

their workforce.

Residual Impact

The impact significance remains of Moderate significance. A summary for the impact is present below.

Table 5.23 Pre- and Post- Mitigation Significance for Impacts Associated with Pressure

on Social Infrastructure and Services Cumulative Impact

Table 5.24 Pre- and Post- Mitigation Significance for Impacts Associated Pressure on

Social Infrastructure and Services

Nature and Type: Indirect negative impact

Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium

Impact Magnitude: Medium

• Extent: Local

• Duration: Long term

• Scale: Medium

• Frequency: Often

• Reversibility: Reversible

• Likelihood: N/A

IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE

IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE

5.6 UNPLANNED EVENTS

An unplanned event is a reasonably foreseeable event that is not planned to occur as part of the

Project (i.e. would not occur as part of routine operating procedures), but which may conceivably occur

as a result of Project activities (e.g. accidents). The risks of unplanned events related to the Project are

accessed in EIA report.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 69

6. KEY FINDINGS AND RECOMMENDATIONS

Both potential positive and negative socio-economic impacts associated with the development of the

MASPL Integrated steel Plant have been identified and assessed through this SIA. The key findings

have been summarized below.

• Employment creation, skills enhancement and local business opportunities: The Project will

create up to 1000 (tentatively inc. contract persons) employment opportunities during the construction

phase and 730 person during the operation phase. It is anticipated the unskilled and to a large extent

semi-skilled workforce will be drawn from the local area. Those who secure employment will benefit from

on the job training which will leave them well-placed to secure future employment on similar projects.

• Impacts on community health and safety: The presence of the Project may not majorly affect the

health, safety and security of the communities in the area of influence as a result of worker-community

interactions, in-migration to the area, increased disposable income in the local community, the risk of

injury associated with construction and activities, increased pressure on health care resources and

changes to the environment. Air emissions, noise and increased traffic associated with the Project are

also considered impacts that may affect community health and safety temporarily.

The impacts on community health and safety range from minor to moderate, however, with the

implementation of management measures, these impacts will be minor in significance, with the

exception of impacts associated with the presence of the workforce. This is largely due to the long-term

impacts that may arise from incidence of HIV/ AIDS.

• Worker health and safety and rights: Workers’ rights, including occupational health and safety

need to be considered to avoid accidents and injuries, loss of man-hours, labour abuses and to ensure

fair treatment, remuneration and working and living conditions. The development of health and safety

plans and policies will ensure that this impact is of minor significance.

The implementation of management measures detailed in this report, as well as in other specialist

reports are fundamental to ensuring that negative impacts associated with the Project are managed, and

the positive impacts are enhanced. Key management measures are summarized below.

• The Project will establish a recruitment policy which prioritises the employment of Indian and

local residents (originating from the Local Body) over outsiders. Criteria will be set for prioritising

local residents and then other states as part of the recruitment process.

• All contractors will be required to recruit in terms of the Project’s recruitment policy,

where practical.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 70

• The Project will develop an induction programme, including a Code of Conduct, for all workers

directly related to the project. A copy of the Code of Conduct to be presented to all workers and signed by

each person. The Code of Conduct must address the following aspects:

• respect for local residents and customs; o zero tolerance of bribery or corruption;

• zero tolerance of illegal activities by construction personnel including: unlicensed prostitution;

illegal sale or purchase of alcohol; sale, purchase or consumption of drugs; illegal gambling or fighting;

• no alcohol and drugs policy during working time or at times that will affect ability to work;

• Description of disciplinary measures for infringement of the Code and company rules. If workers

are found to be in contravention of the Code of Conduct, which they signed at the commencement of their

contract, they will face disciplinary procedures that could result in dismissal.

• The Project will implement a grievance procedure that is easily accessible to the local

community, through which complaints related to contractor or employee behaviour can be lodged and

responded to. The Project will respond in a serious manner to any such complaints. Key steps include:

• circulation of contact details of ‘grievance officer’ or other key Project contact; awareness

raising among the local community regarding the grievance procedure and how it works; and

establishment of a grievance register to be updated and maintained by the Project.

• The Project will develop and implement an HIV/AIDS policy and information document for all

workers directly related to the Project. The information document will address factual health issues as

well as behaviour change issues around the transmission and prevention of of HIV/AIDS.

• All of the mitigation measures outlined in EIA & EMP reports , Traffic Assessment Report , the

Noise Impact Assessment Report and Air Quality Report must be implemented by the Project.

Social Welfare & Upliftment Plan:

Budget for Corporate Environment Responsibility (CER)

PROJECT

(2018-19 to 2020-21)

Budget for Improvements in

physical infrastructure

(Rs in Lacs)

Budget for Improvements in

social infrastructure

(Rs in Lacs)

TOTAL

(Rs in Lacs)

Rolling Mill (Wire Rod

Cum Bar Mill) 515 435 950

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 71

BREAK- UP (Improvements in physical infrastructure):

Improvements in physical infrastructure

Sr.No PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018-19 to 2020-21

Welfare Activities Amount in Lacks Villages

1 Development of connecting road to NH-63

100

1. HosaKanakapura Village 2. KanakapuraTanda 3. Hale Kanakapura Village 4. Ginigera Village

2 R O Plant for drinking water 50

3 Water line from T B Dam 150

4 Drains Along Village Street 50

5 Construction of Sanitation Facility for Male and Female with provision of Overhead Water Tanks

75

6 Providing LED lighting with Solar Panels at Village Streets

50

7 Providing Computers and Science Lab Equipment to the ZP High Schools and Primary Schools

40

8 GRAND TOTAL (Rs in Lacks) 515

Improvements in social infrastructure

S.N PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018-19 to 2020-21

Welfare Activities Amount in Lacks Villages

1 School Building 75

1. HosaKanakapura Village 2. KanakapuraTanda 3. Hale Kanakapura Village 4. Ginigera Village

2 Infrastructure Facilities for Computer Education 5

3 Establishment of Community Centres 150

4 Facilities /Infrastructures for skill development of Women

50

5 Avenue Plantation all along the Roads, Plantation at Public Places & Barren Lands

20

6 Provide 2 Ambulances for Medical Emergen cy Services

35

7

Soil Conservation measures and Forest Management nearby site in consultation with Forest Department.

50

8 Distribution of Fruit Bearing Sapling, Seeds to villagers Plantation.

50

9 GRAND TOTAL (Rs in Lacks) 435

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 72

7. IMPACT STATEMENT

The findings of the Social Impact Assessment for the MASPL Integrated steel Plant indicate that the

Project will have positive benefits for the local community through the creation of employment and skills

enhancement, during both the construction and operation phases. While potential negative impacts

associated with the Project have been identified, these can be managed through the implementation of

the mitigation measures outlined in this SIA, the EIA and EMP.

It is, therefore, recommended that the Project be supported subject to the implementation of the

mitigation measures outlined in this SIA, the EIA & EMP.

8. REFERENCES

MoEFCC Manual

CPCB

KSPCB

1 INTRODUCTION

The MoEF&CC requires that reports that are compiled by EIA consultant and are reviewed by GCI

team.

1.1 Review Approach

The review was undertaken as a desk-based exercise to assess the draft SIA in terms of the

specific criteria defined by MoEF&CC & ToR.

The reviewer was briefed by the lead author about the proposed Project, the SIA methodology (including

determination of the area of influence, selection of data gathering techniques, process of identifying and

assessing impacts, and process for Determining mitigation and management measures), integration

with related specialist studies, and assumptions and limitations of the study.

For each of the review criteria stipulated by MoEFCC , the reviewer has rated the information provided

in the SIA on a scale of 1 to 5, where 1 = inadequate and 5 = comprehensive. A comment is provided

to support each rating and recommended actions are provided.

M/s Mukand Alloy steels Private Limited

M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.

& Green Circle Inc. Vadodara 73

1.2 Assumptions and Limitations

The following assumptions and limitations apply to this review.

The review is based only on the criteria defined by the MoEF&CC ; no other national or international

requirements have been assessed.

It assumed that all Project and baseline information is correct and accurately reflects the respective sources.

The related specialist studies have not been reviewed, the information and assertions drawn from those

reports are assumed to be accurate.

Annexure-XVII

Layout Plan

 

Annexure-XVIII

HIRA SHEET

ACTIVITY:

N / AB / E LC BC IPCPRO

(5)

EXP

O

(5)

SEV

(10)

A HANDLING OF FURNACE OIL & LDO

1 Unloading N Vehicular Accident Body Injury Skilled Worker Y

Motor

Vehicles

Act,1988

& Motor

Vehicles

Rules,19

89

2 2 3 12 NS

E Exposure to Fire Burn Injury Skilled Worker Caution Display Y 2 3 7 42 S

2 Storage E Exposure to Fire Burn Injury Skilled Worker Y

Section

7 of

Petroleu

m Act

1934,Rul

es

1976,up

graded

rules,20

02

2 3 7 42 S

3 Issuses E Exposure to Fire Burn Injury Skilled Worker Y 2 3 7 42 S

RISKS

PROPOSED CONTROLS/ IMPROVEMENTS / CHANGES / MODIFICATIONS PLANNED

QUANTITATIVE

RPN

HIRA HANDLING OF FURNACE OIL & LDO

HAZARD IDENTIFICATION, RISK ASSESMENT AND CONTROL PLAN

DEPARTMENT: RMS STORE HANDLING OF FURNACE OIL & LDO

SN ACTIVITIES

OCCURRENCE

OF HAZARDS

HAZARDSS/ NS

ABBREVATIONS: N: Normal, AB: Abnormal, E: Emergency, LC: Legal Concern, BC: Business Concern, IPC: Interested Party Concern, S: Significant, NS: Nonsignificant and OCP: Operational Control Procedures, PPE-Personal Protective equipment, RPN-

- Risk Priority Number.

EVALUATION OF RISK

REF.

OCP /

MPENGG ADMIN PPE's OTHERS

QUALITATIVE

REF

LEGAL

Annexure-XIX

CREP Guidelines

SL.

No

CREPGuidelines Compliance

1 Airemissions

1. AdequatelydesignedESPoranyother

adequateairpollution control

system/combinationofsystem should be

installed toachieve theprescribedstack

emissionstandards.

As installation and operation of Pollution

ControlEquipmentforplantswith lessthan

100TPDcapacityisnot economicallyviable,

therefore,itisrecommendedthat plantswith less

than 100TPD shall not be permittedin future.

Programfor phasingout old plantshaving

capacityless than 100TPD shall be worked

outbytheStatePollutionControl Board

Bag House & Chimney of

adequate Height

All Pollutioncontrolequipment should be

providedwith separateelectricity meter

andtotaliserfor continuousrecordingof

powerconsumption.The a m p e r a g e

oftheI D fanshouldalso

berecordedcontinuously.Non-

functioningofPollution control equipment should

be recorded in the same logbook along with

reasonsfornotrunning the PollutionControl

It willbeadhereda ccordingly

The safety cap/emergency stack of rotary kiln

type plant, which isgenerallyinstalled above the

After Burner Chamber(ABC) of feedend column

shouldnotbeused for discharging untreated

emission, bypassingthe air pollution control device.

Not Applicable

In order to prevent bypassing of emissions through

safety cap and non-operation of ESP or any

other pollution control device, software

controlled interlocking facility should be provided

on the basis of real time data from the plant

control system, to ensure stoppage of feed

conveyor, so that, feed to the kiln would stop

automatically, if safety cap of the rotary kiln is

opened or ESP is not in operation. The system

should be able to take care of multiple operating

parameters and their inter relations to prevent

any possibility of defeating the basic objective of

the interlock. The system should be foolproof to

prevent any kind of tempering. The software

based interlocking system, proposed to be

installed by industry should be get approved by

the concerned StatePollution Control Board, for its

adequacy, before installation by the industry.

Not Applicable

Mechanical operated system for timely collection

and removal of the flue dust generated in ESP or

any other pollution control device shall be

installed

Bag House & Chimney of

adequate Height

Stack Emission from de-dusting units

All de-dusting units should be connected to a stack

having a minimum stack height of 30 m. Sampling

porthole and platform etc. shall be provided as per

CPCB emission regulation to facilitate stack

monitoring. De-dusting units can also be

connected to ABC Chamber and finally emitted

through common stack with kiln off-gas emissions

It will be adhered

accordingly

Fugitive Emission

The measurement may be done, preferably on 8-

hour basis with high volume sampler. However,

depending upon the prevalent conditions at the site,

the period of measurement can be reduced.

Steps will be taken to control

fugitive dust emission.

2 Effluent Discharge

i. All efforts should be made toreuse and re- circulate

thewater and to maintain zero effluent discharge.

ii. Storm water / garland drain should be provided in

the plant.

In the proposed project

approximately 30 KLD Effluent

is generated which shall be

treated in Effluent Treatment

Tank and then reused for

gardening and dust

suppression purpose.There

will be no effluent released

from the Rolling Mill and

hence MASPL will adhere to

“Zero Liquid Discharge” for

this proposed project.

3 Noise Control

The industry should take measures to control the

NoisePollution so thatthe noise level standards

already notified for industrial area are complied.

It will be adhered

accordingly

4 Solid Waste Management

Char :

Char should be mixed with coal or coal

washery rejects and used as fuel in Fluidized Bed

Combustion Boilers (FBC) for generation of power.

The plants having capacity 200TPD and above

shouldinstall Fluidized Bed Combustion Boilers (FBC)

for generation of power. Also the smaller capacity

individual Sponge Iron Plants (Capacity upto 100

TPD) and operating in cluster can collectively

install common Fluidized Bed Combustion Boilers

(FBC) for power generation. The Sponge Iron Plant

are free to explore other options / possibilities to

use char for generation of power.

Char can be sold to local entrepreneurs for making

coal briquettes. It can also be mixed with coal fines,

convertedto briquettes and used inbrick kilns. Under

no circumstanceschar shouldbe disposedoff in

agricultural fields/other areas. Logbook for daily

record, of Char production and usage must be

maintained by the industry and the record shall be

made available to officials of CPCB/SPCB/PCC

during inspection.

Not Applicable

Kiln Accretions:

The kiln accretions are heavy solid lumpsand

can be used as sub- base material for road

construction or landfill, after ascertaining the

composition for its suitability and ensuring that it

should not have any adverse environmental impact.

Not Applicable

Gas Cleaning Plant (GCP)/Scrubber Sludge

The sludge should be compacted and suitably

disposed off after ascertaining the composition for its

suitabilityand ensuring that it should not have

any adverse environmental impact.

Not Applicable

Flue Dust / Fly ash

Flue dust is generated from air pollution control

system i.e. ESP or any other air pollution control

system installedwith kiln. Secondary flue dust is also

generated from Bag Filters or any other air pollution

control equipment installed with Raw Material

Handling, Coal Crusher, Cooler Discharge and

Product house unit. The reuse/ recycling of the flue

dust generated / collected may be explored and

suitably implemented.

Fly ash brick manufacturingplant should be installed

for fly ash utilization. Fly ash can be utilized in

cement making by Cement industry also.

Not Applicable

Bottom Ash

Bottom ash may have objectionable metallic

compounds, thereforeshould be stored in properly

designed landfills as per CPCB guidelines to prevent

leaching to the sub-soil and underground aquifer.

Not Applicable

General

(a) Solid waste management program should be

prepared with thrust on reuse and recycling.

Solid waste disposal site should be earmarked within

the plant premises. The storage site of solid waste

should be scientifically designed keeping in view

that the storage of solid waste should not have

any adverse impact on the air quality or water

regime, in any way.

It will be adhered

accordingly

(b) The various types of solid wastes

generated should be stored separately as per CPCB

guidelines so that it should not adversely affect

the air quality, becoming air borne by wind or water

regime during rainy season by flowing along with

the storm water.

It will be adhered

accordingly

Raw Material handling and Preparation

Unloading of coal by trucks or wagons should

becarried out with proper careavoiding dropping

of the materials from height. It is advisable to

moist the material by sprinkling water while

unloading.

Not Applicable

Crushing and screening operation should be carried

out in enclosed area. Centralized de- dusting facility

(collection hood and suction arrangements

followed by de-dusting unit like bag filter or ESP

or equally effective method or wet scrubber and

finally discharge of emission through a stack)

should be provided to control Fugitive

Particulate Matter Emissions. The stack should

confirm to the emissionstandards notified for de-

dusting units. Water sprinkling arrangement should

be providedat raw material heaps and on land

aroundthe crushing and screening units.

Not Applicable

Work area includingthe roads surrounding the plant

shall be asphalted or concreted.

It will be adhered

accordingly

Enclosure should be provided for belt conveyors and

transfer points of belt conveyors.

The above enclosures shall be rigid and

permanent (and not of flexible/ cloth type

enclosures) and fitted with self- closing doors and

close fitting entrances and exits, where conveyors

pass through the enclosures. Flexible covers shall be

installed at entry and exit of the conveyor to

the enclosures, minimizing the gaps around the

conveyors.

In the wet system, water sprays/ sprinklers shall be

provided at the following strategic locations for

dust suppression during raw

material transfer:

- Belt conveyor discharge/ transfer point

- Crusher/screen discharge locations

Not Applicable

Waste Heat Recovery Boiler (WHRB)

Sponge Iron Plants of capacity more than 100

TPD kilns shall use Waste Heat Recovery

Boiler (WHRB) for generation of power.

Not Applicable

Cooler Discharge and Product Separation

Unit

Permanent and rigid enclosures shall be provided for

belt conveyors and transfer points of belt

conveyors. Dust extraction cum control system

preferablybag filters or ESP to arrest product loss in

cooler discharge and product separation area shall

be installed.

Not Applicable

Char based Power Plant

For plant having capacity of 200 TPD of

cumulative kiln capacity, the power

production through FBC boiler using char as a part

of fuel, is a viable option. Power generation

through FBC boiler using char as a part of fuel be

implemented in a phased manner within 4 years of

commissioning and targeting for 100% utilization of

char. Individual Sponge Iron Plants of capacity

upto 100 TPD and located in cluster can install

a common char based power plant collectively.

Not Applicable