Annexure-Ienvironmentclearance.nic.in/writereaddata/online/... · MoM of 32nd meeting of the EAC...
Transcript of Annexure-Ienvironmentclearance.nic.in/writereaddata/online/... · MoM of 32nd meeting of the EAC...
Sr No Land Details Acres Guntha
1
MASPL acquired 101 Acres 21 Gunthas of Land for its Proposed Green Field Rolling Mill ( Wire Rod cumBar Mill) Project of 700,000 TPA
101 21
Annexure-III
Minutes of Meeting of 24th EAC
(Industry-1) held during 13th – 15th
November 2017 with MoM
Compliance
Minutes of 24thEAC (Industry-1) held during 13th – 15th November 2017
Page 1 of 101
Ministry of Environment, Forest and Climate Change
Impact Assessment Division
(Industry-I Sector)
SUMMARY RECORD OF THE TWENTY- FOURTH (24TH) MEETING OF EXPERT
APPRAISAL COMMITTEE HELD ON 13TH–15THNOVEMBER 2017 FOR
ENVIRONMENTAL APPRAISAL OF INDUSTRY-I SECTOR PROJECTS
CONSTITUTED UNDER EIA NOTIFICATION, 2006.
The Twenty-fourth meeting of the Expert Appraisal Committee (EAC) for Industry-I
Sector as per the provisions of the EIA Notification, 2006 for Environmental Appraisal of Industry-
I Sector Projects was held on 13th – 15th November 2017 in the Ministry of Environment, Forest
and Climate Change. The list of participants is annexed.
24.1 After welcoming the Committee Members, discussion on each of the agenda items was
taken up ad-seriatim. First two days i.e. 13th and 14th November, 2017, the meeting was chaired
by Dr. C.N Pandey and on 15th November, 2017 by Shri Jagadish kishwan.
24.2 Confirmation of the minutes of the 23rdMeeting
The minutes of the 23rd meeting, as circulated were confirmed.
DATE: 13th November 2017
24.3. Expansion of Re-rolling mill by installation of new 30 T Rolling Mill Furnace (from 13000
TPA to 180500 TPA) by M/s JMD Alloys Ltd. (JMDAL) at Vill. Deokuli, Bihta, District
Patna, Bihar [Proposal No IA/BR/IND/67762/2017; MoEF&CC File No. IA-J-
11011/478/2017-IA.II(I)] – Environmental Clearance based on ToR.
1.0 M/s JMD Alloys Ltd. (JMDAL) has made online application vide proposal no.
IA/BR/IND/67762/2017dated 29th August 2017along with the copies of EIA/EMP seeking
Environmental Clearance under the provisions of the EIA Notification, 2006 for the above
mentioned proposed project. The proposed project activity is listed at S. No. 3(a) Metallurgical
industries (ferrous & non-ferrous) under Category “B” EIA Notification, 2006 and due to non-
existence of the SEIAA in the state of Bihar the proposal is appraised at Central level.
2.0 The proposed Rolling Mill and Induction Furnace project of M/s JMD Alloys Ltd., is
located near Vill. Deokuli, Block Bihta, Dist. Patna, State Bihar, was initially received in SEIAA,
Bihar on 11th February 2017 for obtaining Terms of Reference (ToR) as per EIA Notification,
2006. The project was appraised by the State Expert Appraisal Committee [Bihar] during its
meeting held on 07thMarch 2017 and prescribed ToRs to the project for undertaking detailed EIA
study for obtaining environmental clearance. Accordingly, SEIAA, Bihar had prescribed ToRs to
the project on 16.03.2017 vide Lr. Ref. No. 570.
3.0 The present proposal of M/s JMD Alloys Ltd., is for enhancement of production of
MS/TMT Bar from 13000 tonnes per annum (TPA) to 180500 tonnes per annum (TPA). The
project is located near Village Deokuli, Block Bihta, Dist. Patna, State Bihar. The existing project
is a Secondary metallurgical processing industry was established in 1995 and not listed in the
Schedule I of EIA Notification 1994 for obtaining Environment Clearance (EC) and project is still
Minutes of 24thEAC (Industry-1) held during 13th – 15th November 2017
Page 57 of 101
junction (Badokar mod) – 2.2 km – 2750 no of trees and Bargawan Police station
to Dhaurar -3.3 km – 4750 no of trees
13.0 After detailed deliberations, the recommendation of the committee is given below:
1 Increase in the Aluminium metal
production from 3.59 LTPA to 3.71
LTPA through process optimization
Recommended
2 Change in the Fuel Mix (use of Pet coke
and Rice husk)
Not recommended
3 Change in source of fuel Recommended for road transportation as
follows:
Year %
allowed
through
road
%
allowed
by road
Via
Bina –
Anpara –
Singruali
– Mahan
% allowed
via
Baikuntpur
–Baidan-
Mahan /
Shadol –
Siddhi -
Mahan
2017-18 27% 75% 25%
2018-19 21% 95% 5%
2019-20 21% 95% 5%
2020-21 16% 95% 5%
4 Sale of carbon anode Recommended
5 Sale of Bath material Not recommended
6 Use of Aluminium Scrap from sister units Not recommended
7 Sale of molten metal Not recommended
24.11. Proposed Integrated Steel Plant of 0.7 MTPA Capacity by M/s. Mukand Ltd. at
VillageKanakapur, Taluka & District- Koppal, Karnataka by M/s Mukund Limited [Online
Proposal No. IA/KA/IND/51427/2016; MoEF File No. IA-J-11011/105/2016-IA.II(I)] -
Amendment in Terms of Reference.
1.0 M/s. Mukand Limited has made online application vide proposal no.
IA/KA/IND/51427/2016 dated 26th September 2017 seeking amendments in Terms of Reference
granted for the proposed Integrated Steel Plant of 0.7 MTPA Capacity vide J-11011/105/2016-IA
II (I) dated 19.05.2016.
2.0 It was informed that the name of the company has been changed from M/s. Mukand Ltd.
to M/s. Mukand Alloy Steels Private Ltd. (MASPL) and changes of the components in phasing.
The details of amendments sought are given below: Sr.
No. Description As Per ToR dated 19.05.2016 Amendment required
1 Change the name of
the Company.
M/s. Mukand Ltd. M/s. Mukand Alloy Steels Private
Ltd. (MASPL)
Minutes of 24thEAC (Industry-1) held during 13th – 15th November 2017
Page 58 of 101
2 Registered Address M/s. Mukand Ltd. (Hospet Division), Hospet-
Koppal Road, Village- Kanakapur, Taluka&
District- Koppal, Karnataka.
M/s. Mukand Alloy Steels Private
Ltd. Flat No. 11, 7 West wing, Shah
House, JankiKutir, Juhu Tara Road,
Vile Parle (W), Mumbai-400049,
Maharashtra, India.
3 Production Details Phase I
Phase II
Phase I
Phase II
i Wire Rods
Cold heading wire
rods, low
carbon/Boron
steels, special steel
wire rods i.e. semi
free/free
cutting/Alloy
steels/high
carbon/mild steel
rods
Installation of
following facilities:
1. Wire Rod Mill -
550,000MetricTo
nnes Per Year
2. Blast Furnace - 1
3. E.O.F
4. Ladle furnace - 1
5. Vacuum
Degassing - 1
6. Billet/Bloom
Caster - 1
7. Sinter Plant - 1
8. Oxygen Plant – 1
9. Power Plant - 1
Installation of
following facilities:
1. Blast Furnace -
1
2. Ladle Furnace -
1
3. Vacuum
Degassing-1
4. Billet/Bloom
Caster - 1
5. Sinter Plant - 1
6. Oxygen Plant -
1
7. Power Plant – 2
(One from
Waste Gases)
700,000
TPA – Wire
Rod cum
Bar Mill
Installation of
following facilities:
1. Blast Furnace
2. DRI
3. Coke oven Plant
4. E.O.F
5. Ladle Furnace
6. Vacuum
Degassing
7. Billet/Bloom
Caster
8. Sinter plant
9. Oxygen plant
10. Power Plant
ii Bar Products
Special steel bar
products
Bar Mill –150,000
TPA
Total 700,000 TPA 700,000 TPA
3.0 After details deliberation, the committee opined that the change in the name and phasing
of the components are administrative in nature. The committee opined that no amendment is
required and may be applied to the ministry directly for change in the name of the company with
requisite documents as envisaged in the clause 11 of EIA Notification, 2006. Therefore the
proposal is returned in the present form.
24.12. Expansion of Steel Plant (Sponge Iron:1,12,500 TPA; MS Billets:1,21,500 TPA; TMT
Bars:1,00,000 TPA; and Power Plant:15 MW) by M/s Amoda Iron and Steel Limited
located at Sy. No. 79/80, 81, 82, 83 & 172, Jayanthipuram Village, Jaggayyapet Mandal,
Krishna District, Andhra Pradesh [Online Proposal No. IA/AP/IND/21175/1910; MoEFCC
File No. J-11011/502/2009-IA.II(I)] – Extension of validity of EC.
1.0 The proponent has made online application vide proposal no. IA/AP/IND/21175/1910
dated 13th October 2017 seeking extension of validity of Environmental Clearance granted on
2ndNovember 2010 for the proposed expansion of Steel Plant by M/s Amoda Iron and Steel Limited
located at Sy. No. 79/80, 81, 82, 83 & 172, Jayanthipuram Village, Jaggayyapet Mandal, Krishna
District, Andhra Pradesh.
2.0 M/s Amoda Iron and Steel Limited has obtained Environmental Clearance vide no. F. No.
J-11011/502/2009-IA.II(I) dated 2ndNovember 2010 for following plant configuration:
S.
No Units
Products Capacity
Existing
Expansion
After
Expansion
Annexure-IV
Minutes of Meeting of 29th EAC
(Industry-1) held during 13th – 15th
March 2018 with MoM Compliance
Annexure-VI
Minutes of Meeting of 32nd EAC
(Industry-1) held during 13th – 15th
June 2018 with MoM Compliance
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 229 of 290
following specific ToRs for undertaking detailed EIA and EMP study in addition to the generic ToR
enclosed at Annexure I read with additional ToRs at Annexure-2:
1. Public Hearing to be conducted by the concerned State Pollution Control Board.
2. The issues raised during public hearing and commitment of the project proponent on the
same along with time bound action plan to implement the commitment and financial
allocation thereto should be clearly provided.
3. The project proponent should carry out social impact assessment of the project and submit
�W�K�H���&�R�U�S�R�U�D�W�H���(�Q�Y�L�U�R�Q�P�H�Q�W���5�H�V�S�R�Q�V�L�E�L�O�L�W�\���D�V���S�H�U���W�K�H���0�L�Q�L�V�W�U�\�¶�V���2�I�I�L�F�H���0�H�P�R�U�D�Q�G�X�P���Y�L�G�H��F.No. 22-65/2017-IA.III dated 1st May 2018.
4. Certificate compliance of earlier EC conditions from the regional office of MoEFCC shall
be submitted along with EIA/EMP.
5. The project proponent shall recycle and reuse iron ore fines, coal and coke fines, lime fines
and such other fines collected in the pollution control devices and vacuum cleaning devices
in the process after briquetting/ agglomeration by installation of briquetting plant
13th June 2018
32.26. Proposed Integrated Steel Plant of 0.7 MTPA capacity at Village- Kanakapur, Taluka &
District- Koppal, Karnataka by M/s. Mukund Ltd. [Online Proposal No.
IA/KA/IND/51427/2016; MoEF&CC File No. J-11011/105/2016-IA-II(I)] �± Environmental Clearance.
1.0 Based on the ToRs prescribed to the project, the project proponent submitted an
application for environmental clearance to the Ministry online on 10th March 2016 vide Online
Application No. IA/KA/IND/51427/2016.
2.0 The proposed 700,000 Integrated Steel Plant Project of M/s Mukand Ltd. located in
Village Kanakapura, Tehsil & District Koppal, State Karnataka was initially received in the
Ministry on 10th March 2016 for obtaining Terms of Reference (ToR) as per EIA Notification,
2006. The project was appraised by the Expert Appraisal Committee (Industry) [EAC(I)] during
its4th meeting held on 30th -31st March,2016 and prescribed ToRs to the project for undertaking
detailed EIA study for obtaining environmental clearance. Accordingly, the Ministry of
Environment, Forest and Climate Change had prescribed ToRs to the project on 19th May 2016
vide Lr. No. F.No.J-11011/105/2016-IA.II(I). (MUKAND LTD).
3.0 Based on the ToRs prescribed to the project, the project proponent submitted an
application for environmental clearance to the Ministry online on 10th March 2016 vide Online
Application No. IA/KA/IND/51427/2016. M/s Mukand Ltd made an application on 30th Mar 2018
for transfer of name to M/s Mukand Alloy Steels Private Ltd and thereafter MoEFCC Vide its
letter dated 24thApril 2018 granted approval for transfer of TORs from M/s Mukand Ltd to M/s
Mukand Alloy Steels Private Ltd.
4.0 The project of M/s Mukand Alloy Steels Private Ltd. located in Kanakapura Village,
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 230 of 290
Koppal Tehsil &District ,Karnataka State is for setting up of a new Integrated Steel Plant Project
for production of 0.7 million tones per annum (million TPA) of Specialty Alloy Steels. The
proposed capacity for different products for new site area as below:
Name of Unit No. of
Units
Capacity of Each Unit Production Capacity
Sinter Plant 1 75M2 866,910 TPA
Blast Furnace 1 750M3 790,000 TPA
SMS comprising:
Basic Oxygen Furnace
Ladle Furnace
Vacuum Degasser
CCM
1
2
2
2
70 Ton
70 Ton
70 Ton
Two Casting machines
of 3 strands each with
Section size 160 to 280
x 320.
SMS Capacity:
736,842 TPA
Rolling Mill 2 Two mills with Bars,
Bar in Coil and Wire
Rods.
700,000 TPA
Power Plant 2 15 MW 30 MW
Air Separation Plant
(Oxygen/Nitrogen/Argon)
1 350 Ton 124,250 TPA
Coke Oven Plant 2 200,000TPA 400,000TPA
PRODUCTS
Alloy Steel bar, Bar in coil,
Wire Road
700,000 TPA
Pig Iron 80,000 TPA
5.0 The total land required for the project is 121.406 ha (300 Acres), out of which 89.53ha
(221.22 Acres) is an agricultural land and 33.74 ha (83.375 Acres) is grazing land. The water
bodies include Tungabhadra dam is about 5 km in SE away from project site.
6.0 The topography of the area is flat and reported to lies between 15° �����¶�����������´�� �W�R��15°�����¶�����������´���1���/�D�W�L�W�X�G�H���D�Q�G������°�����¶�����������´���W�R������°�����¶�����������´���(���/�R�Q�Jitude in Survey of India topo
sheet No. 57 A/3, at an elevation of 510 m AMSL. The ground water table reported varies between
0.82 m to 13.55 m below the land surface during the post-monsoon season and 1.82 m to 12.26 m
below the land surface during the pre-monsoon season. Based on the hydro-geological study, it
has been reported that the radius of influence of pumped out water will be 5,733 ha m. Further, the
stage of groundwater development is reported to be 68 % (Koppal taluka).
7.0 The National Park/WL etc are located at a distance of 30.06 KM (Daroji Sloth Bear
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 231 of 290
Sanctuary) KM. There is no national park wild life sanctuary/biosphere reserve/tiger
reserve/elephant reserve etc. are reported to be located in the core and buffer zone of the project.
The area does not report any kind of form corridor for Schedule-I fauna. The authenticated list of
flora and fauna provided through reporting shows presence of no /schedule-I fauna in the study
area.
8.0 The process of project inter alia include usage of basic Raw Materials such as Iron
Ore/Sinter (Agglomerated Form of Iron Ore Fines) and Met Coke / Coal as fuel and Limestone
/Quartz as Flux, the Hot Iron is produced through reduction Process in Blast Furnace which
subsequently converted into Crude Steel in Basic Oxygen Furnace through Oxidation Process. The
Liquid Crude Steel is then refined along with addition of various alloy elements to attain the
desired properties. This liquid Steel is cast in desired section /shape in Continuous Casting
Machine under controlled parameters. These Cast Blooms/Billets are reheated and Rolled in
�Y�D�U�L�R�X�V���V�L�]�H�V���D�Q�G���O�H�Q�J�W�K���W�R���G�L�V�S�D�W�F�K���W�R���2�(�0�¶�V�����'�X�U�L�Q�J���W�K�H�V�H���3�U�R�F�H�V�V�H�V slag at various stations i.e.
Granulated Slag from Blast Furnace, Slag from Basic Oxygen Furnace and LRF is generated. Dust
from various Fume Control Systems which is used in Sinter making process. The Waste Gases
generated from the Blast Furnace& Waste Heat from the Coke Oven shall be used for Power
Generation.
9.0 The targeted production capacity of the Integrated Steel Plant is 0.7 million TPA. The ore
for the plant would be procured from E-Auctions. The ore transportation will be done through
Rail/Road.
Raw Material /
Fuel
Quantity
per Annum Unit
Source (incase
of Import,
please specify
country and
Name of the
port from
which Raw
Material / Fuel
is received)
Mode of
Transport
Distance of
Source from
Project Site (in
Kilo meters) (In
case of import,
distance from
the Port from
which raw
material /Fuel is
received
Type of
Linkage
(Linkage /
Fuel Supply
Agreement
/e-auction
/MoU / LOA
/Captive
/Open
market/
Others)
1 Hard Coal 3,78,000 TPA
Imported
(Mormugao
Port)/Indigeni
ous
Road/Rail 350Kms Open
Market
2 Soft Coal 1,62,000 TPA
Imported
(Mormugao
Port)/Indigeni
ous
Road/Rail 350Kms Open
Market
3 Iron Ore/Pellets 3,70,440 TPA
Imported
(Mormugao
Port)/Indigeni
ous
Road/Rail 350Kms Open
Market
4 PCI Coal 88,200 TPA Purchase from
Market Road/Rail 350Kms
Open
Market
5 Coke* 3,30,750 TPA Purchase from
Market Road/Rail 700Kms
Open
Market
6 DRI 41,303 TPA Purchase from
Market Road/Rail 100Kms
Open
Market
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 232 of 290
7 Purchased Scrap 56,413 TPA Purchase from
Market Road/Rail 350Kms
Open
Market
8 Revert Scrap 26,193 TPA In-House
Production Road/Rail
Transport within
the Plant Others
9 Ore Fine 7,85,784 TPA Purchase from
Market Road/Rail 100Kms
Local
Market
10 Mill Scale 24,556 TPA In-House
Production Road/Rail
Transport within
the Plant Others
11 Flue Dust 14,733 TPA In-House
Production Road/Rail
Transport within
the Plant Others
12 Fluxes 1,96,446 TPA Purchase from
Market Road/Rail 100Kms Others
13 Burnt Lime 4,911 TPA Purchase from
Market Road/Rail 100Kms
Local
Market
14
LPG Bullets
(Capacity: 10
MT x 4 Nos.)
6.5
MT/Day TPA Local Market Road/Rail 300 Kms
Local
Market
10.0 The water requirement of the project is estimated as 7,620 m3/day, out of which 7,620
m3/day of fresh water requirement will be obtained by drawing water from the downstream of
Tungabhadra reservoir within the sanctioned capacity of 18 MLD by the Government of
�.�D�U�Q�D�W�D�N�D�¶�V���O�H�W�W�H�U���Q�R�����:�5�'���������0�7�3�������������G�D�Wed 22 December 2015. For this Project no ground
water shall be used.
11.0 The power requirement of the project is estimated as 69 MW, out of which 30 MW shall
be met by captive power generation from waste gases of Blast Furnaces and Coke Ovens and rest
of the 39 MW will be sourced from the state utility grid (KTPCL/GESCOM). Three no. of D.G.
sets of 1250 KVA each will be used for power back-up.
12.0 Baseline Environmental Studies were conducted during Pre monsoon season i.e. from
April 2016 to June 2016. Ambient air quality monitoring has been carried out at 8 locations during
�$�S�U�L�O�¶�������W�R���-�X�Q�H�¶�������D�Q�G���W�K�H���G�D�W�D���V�X�E�P�L�W�W�H�G���L�Q�G�L�F�D�W�H�G�����3�0���������������������J���P3 �W�R�����������J���P3), PM2.5 (34.41
�W�R�����������������J���P3�������6�2�������������������W�R���������������J���P3�����D�Q�G���1�2�[�����������������W�R�����������������J���P3). The results of the
modelling study indicates that the maximum increase of GLC for the proposed project is 0.18
���J���P�����Z�L�W�K���U�H�V�S�H�F�W���W�R���W�K�H���3�010.
13.0 Ground water quality has been monitored in six (6) locations in the study area and
analysed. pH: 6.96 to 7.35, Total Hardness: 212 to 690 mg/l, Chlorides: 32 to 136 mg/l, Fluoride:
0.61 to 0.84 mg/l. Heavy metals are within the limits. Surface water samples were analysed from
3 locations. pH: 7.38 to 8.02 ; /l and BOD: 6 to 8 mg/l. COD from 20 to 32 mg/l.
14.0 Noise levels are in the range of 42 to 61.3 dB(A) for daytime and 41 to 52.64 dB(A) for
night-time.
15.0 It has been reported that there are no people in the core zone of the project. No/ R&R is
involved. It has been envisaged that no families to be rehabilitated, which will be provided
compensation and preference in the employment (only Job for 47 land losers in the upcoming
factory).
16.0 It has been envisaged that an area of 47.3 ha (117 acre) ha will be developed as green belt
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 233 of 290
around the project site to attenuate the noise levels and trap the dust generated due to the project
development activities. Solid wastes generated during the Project will be reused in the process or
sold to authorized vendors. Following are the details of the Solid Non-Hazardous Waste Details:
Sr.
No Type of waste
Proposed
Quantity Disposal
1 Granulated Slag 2,45,000 TPA
Sold to Cement plants and reused in
Construction of buildings, as a Replacement
for sand & Cement.
2 SMS Slag 1,40,000 TPA Reuse for Brick making/road making/sold to
authorized parties.
3 Revert Scrap 26,193 TPA Will be reused in SMS Plant
4 Mill Scale 24,556 TPA Will be reused in Sinter Plant
5 STP Sludge 30 TPA Disposed to Gardening manure.
17.0 The Non-Hazardous waste generated from the plant process will be sold to authorized
vendors. The details of the Non-Hazardous Waste is mentioned below:
�6�U�������1�R��
Type of waste Category Proposed
Quantity Disposal
�� Used Oil 5.1 14 KL/Annum Sold to HW Authorized
parties.
�� Contaminated cotton rags
or other cleaning materials 35.1
0.3
MT/Annum
Sold to HW Authorized
parties.
�� E-Waste
E- waste
Rules,20
11
57 kg/Month Sale to Authorized
recyclers
��
Empty
Barrels/containers/liners
contaminated with
hazardous
chemicals/wastes.
33.1 6 TPA Sold to Authorized
parties.
18.0 As this is a New Project the Consent for Establish and Consent to Operate for the plant
shall be taken from the State Government after grant of Environment Clearance from MoEF&CC.
19.0 The Public hearing of the project was held on 30 January 2018 at M/s Mukand Alloy Steels
Pvt Ltd. Project Site in Sy No 67/1, 67/2, Kanakapura-Village, Koppal Taluk & District. under the
chairmanship of Deputy Commissioner Koppal for production of 0.7 million TPA of Speciality
Alloy Steels by setting up of New Integrated Steel Plant. The Statement of main issues raised by
the public and response of the project proponent with action plan is as follows: S.
N.
Issue Raised Response by PP Time Bound Action
Plan
Budget
provision
1. Job opportunities
to the local
people.
Direct Employment
47 Nos of Land losers are promised for
Job on Company Role.
Shall be done in phase
manner and
completed before
-
Direct Employment
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 234 of 290
S.
N.
Issue Raised Response by PP Time Bound Action
Plan
Budget
provision
All young deserving candidates based on
qualification and skill level shall be given
preference during recruitment and
transparency in recruitments shall be
assured
commissioning of the
plant.
Indirect Employment
Preference shall be given to local
deserving candidates while awarding
petty contracts.
2. Awareness &
Monitoring of
Environment
Well Qualified personnel of Company
will conduct formal awareness programs
across the Gram panchayat periodically
Periodic and
Continuous process
10 lakhs
/Annum
Online Monitoring system for Ambient
Air will be installed and will be displayed
in the Main gate of the premises.
Before hot
commissioning Mar-
2020
100 Lakhs
Continuous Tree Plantation 35 Lacks
3 Protection of
Environment
1) Company is determined to install latest
and efficient technology in terms of
controlling pollution.
2) Planning to install plenty of fog generator
and water sprinklers across the company
premises.
3) Covering of maximum dumping and
loading points of raw Materials
4) Continuous Tree Plantation
Right from Basic
Engineering. To Hot
Commissioning of the
Plant
498.8 Crores
(EMP
Budget)
4. Ground water
quality &Water
availability
Water shall be allowed to guard pond after
treatment through latest and efficient
water treatment plants.
�%�\���'�H�F�¶������ 100 lakh
High Focus on Rain Water Harvesting.
The Plant will ensure zero water discharge
and hence the quality of Ground water
shall not be affected.
A Pipeline from TB Dam backwater to
Village for Drinking Purpose.
By 2023. 325 lacks in
2 Phases
5. Health of the
local people was
affected due to
pollution from
the existing
industries
located nearby.
Special Health awareness camp and
medical camps for primary checkup will
be arranged at least once in a year in
nearby villages for health check-ups.
Yearly- Mar-2020
onwards
10lakhs/Ann
um
6 Requirement of
CBSE school and
facility for Skill
development
School shall be considered.
Facility for Skill development shall be
created.
By 2023. 10 Lacks
20.0 An amount of Rs 2400 Lakhs (0.77% of Project cost) has been earmarked as Corporate
Environment Responsibility (CER)based on public hearing issues. The details of Corporate
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 235 of 290
Environment Responsibility as follows:
Budget for Corporate Environment Responsibility (CER)
PROJECT PHASE
Budget for Improvements
in physical infrastructure
(Rs in Lacs)
Budget for Improvements
in social infrastructure
(Rs in Lacs)
TOTAL
(Rs in
Lacs)
Phase -1
(2018 -2021) 466 128 594
Phase -2
(2021-2023) 945 861 1806
GRAND TOTAL 1411 989 2400
BREAK- UP PHASE 1 (Improvements in physical infrastructure): Improvements in physical infrastructure
Sr.
No
PLAN & BUDGET ESTIMATION FOR THE PERIOD2018 to 2021
Welfare Activities
HosaKanakapura
Village
Kanakapura
Tanda
Hale Kanakapura
Village
Ginigera
Village
TOTAL
BUDGET
Budget
(Rs in Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in
Lacks)
Budget
(Rs in
Lacks)
1
Development of
connecting road to
NH-63
150 connected 50 connected 200
2 R O Plant for drinking
water available 18 18 25 61
3 Water line from T B
Dam 120 50 0 170
4 Drains Along Village
Street 10 10 10 5 35
5 GRAND TOTAL 466
BREAK- UP PHASE 1 (Improvements in Social infrastructure): Improvements in social infrastructure
Sr.
No
PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018 to 2021
Welfare Activities
Hosa
Kanakapura
Village
Kanakapura
Tanda
Hale
Kanakapura
Village
Ginigera
Village
TOTAL
BUDGET
Budget
(Rs in Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in
Lacks)
Budget
(Rs in
Lacks)
1 Anganwadi (Pre School) 10 10 0 0 20
2 Infrastructure Facilities for
Computer Education 2 2 2 2 8
3 Establishment of Community
Centres 15 5 5 15 40
4 Facilities /Infrastructures for
skill development of Women 2 1 1 2 6
5
Avenue Plantation all along the
Roads, Plantation at Public
Places & Barren Lands
3 3 2 4 12
6 Provide 2 Ambulances for
Medical EmergencyServices 22 22
7 Soil Conservation measures and 5 5 5 5 20
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 236 of 290
Forest Management nearby site
in consultation with Forest
Department.
8 GRAND TOTAL 128
BREAK- UP PHASE 2 (Improvements in physical infrastructure):
Improvements in physical infrastructure
Sr.
No
PLAN & BUDGET ESTIMATION FOR THE PERIOD 2021 to 2023
Welfare Activities
Hosa
Kanakapura
Village
Kanakapura
Tanda
Hale
Kanakapura
Village
Ginigera
Village
TOTAL
BUDGET
Budget
(Rs in Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in
Lacks)
Budget
(Rs in Lacks)
1 New school building 0 200 0 0 200
2 R O Plant for drinking water 15 0 0 30 45
3 water line from T B Dam 0 0 200 200
4 RCC roads inside villages 100 100 100 200 500
5 GRAND TOTAL 945
BREAK- UP PHASE 2 (Improvements in Social infrastructure):
Improvements in social infrastructure
Sr.
No
PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018 to 2023
Welfare Activities
HosaKana
kapura
Village
Kanakapur
aTanda
Hale
Kanakapura
Village
Ginigera
Village
TOTAL
BUDGET
Budget
(Rs in
Lacks)
Budget
(Rs in
Lacks)
Budget
(Rs in Lacks)
Budget
(Rs in
Lacks)
Budget
(Rs in
Lacks)
1
Skill Development for the ITI
persons in advance
technology.
500 0 0 0 500
2 Computer Education Facility 2 2 2 2 8
3
Upgradation of primary
health centre with repair
works, additional
constructions, medical
equipment supply
0 0 0 100 100
4
Development of School
Grounds and providing
Indoors sports facilities
0 0 0 200 200
5 Facilities /Infrastructures for
skill development of Women 2 1 1 2 6
6
Avenue Plantation all along
the Roads , Plantation at
Public Places & Barren
Lands
5 4 3 5 17
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 237 of 290
7
Soil Conservation measures
and Forest Management
nearby site in consultation
with Forest Department. At
other part of Hill.
10 5 5 10 30
8 GRAND TOTAL 861
21.0 The capital cost of the project is Rs. 3129 Crores and the capital cost for environmental
protection measures is proposed as Rs 150 Lakhs in construction Phase and Rs 49880 Lakhs in
Operation Phase. The annual recurring cost towards the environmental protection measures is
proposed as Rs 2500 Lakhs. The detailed CSR plan has been provided in the EMP in its page
No.212 to 215. The Project will create direct & indirect employment opportunities within the
surrounding region. Local people will be employed as per their qualification and skills. In
operation phase, the proposed project would require significant workforce of non-technical and
technical persons. The total manpower required for the proposed project will be around 730
permanent as well 1000 Outsourced staff during operation of the Plant.
22.0 Greenbelt will be developed in 47.35 Ha which is about 39% of the total acquired area. A
100 m wide greenbelt, consisting of at least 3 tiers around plant boundary will be developed as
greenbelt and green cover as per CPCB/MoEF&CC, New Delhi guidelines. Local and native
species will be planted with a density of 2500 trees per hectare. Total no. of 50,000 saplings will
be planted and nurtured in 47.7 hectares in first years.
23.0 The proponent has mentioned that there is no court case or violation under EIA Notification
to the project or related activity.
Observations of the committee:
24.0 After detailed deliberations the committee observed that the EIA/EMP is not clear in following:
1. The details about the implementation of the ZLD and specific measures for energy
conservation have not been clearly spelled out.
2. Specific water consumption per ton of steel has not been assessed quantitatively.
3. The responsibility of the implementation of oxygen plant as proposed to operate on BOO
basis has not been clarified.
4. EIA report does not mention in quantitative terms, the details of ground water recharge
measures.
5. Non-recovery coven plant shall be of stamp charged type and equipped with CDQ
6. Provision of secondary fume extraction system in the SMS
7. 100% recycling and reuse of iron ore fines, coal and coke fines in process by way of
briquetting/agglomeration etc.
8. Guard pond shall be proposed only to cater in case of exigency but not as ETP /rainwater
harvesting.
9. The approach road from the National Highway is not clear.
MoM of 32nd meeting of the EAC (Industry-I) held during 11th to 13th June, 2018
Page 238 of 290
10. The project proposal involves diversion of an existing road passing through the middle of
proposed plant area. However, no plan of action for diverting the road or providing
alternative route to the people has been proposed.
11. There is an existing cart road, about 500 m long, which connects the National Highway to
the proposed site in the Kasangandi village. The PP informed during deliberations that they
would be using this road for transporting the material after upgrading this road. However,
no specific details about the plan for upgradation of the road was not furnished. Further,
there was no plan of action for acquisition of land for upgradation of link road. The traffic
analysis of found to be wanting on many details.
12. The status of acquisition of land
13. The EIA /EMP has been found to be not in compliance with prescribed ToRs
Recommendations of the committee:
25.0 In view of above, after detailed deliberations, the committee recommended to return the
EIA report in the present form.
32.27. Expansion of Iron Ore Pelletisation Plant (0.6 MTPA to 1.8 MTPA), Iron Ore
Beneficiation Plant (3.0 MTPA), DRI Plant (0.6 MTPA ), Pig Iron BF (0.6 MTPA), Sinter
Plant (0.8 MTPA), SMS (1.2 MTPA), Rolling Mills (1.2 MTPA) & Captive Power Plant
(125 MW) at Village- Phuljhar, Block- Bansapal, Tehsil- Telkoi, District- Keonjhar,
Odisha by M/s Ardent Steel Limited [Online proposal No. IA/OR/IND/74964/2018;
MoEFCC File No. J-11011/112/2013-IA-II(I) �± Prescribing Terms of Reference.
1.0 The proponent has made online application vide proposal no. IA/OR/IND/74964/2018
dated 14th May, 2018 along with the application in prescribed format (Form-I), copy of pre-
feasibility report and proposed ToRs for undertaking detailed EIA study as per the EIA
Notification, 2006 for the project mentioned above. The proposed project activity is listed at Sl.
No. 3(a) Metallurgical industries (ferrous & non-�I�H�U�U�R�X�V�����X�Q�G�H�U���&�D�W�H�J�R�U�\���³�$�´���(�,�$���1�R�W�L�I�L�F�D�W�L�R�Q����2006 and the proposal is appraised at Central level
2.0 M/s. Ardent Steel Limited proposes its existing Iron Ore Pelletisation plant from 0.6
MTPA to 1.8 MTPA , Iron Ore Beneficiation Plant ( 3 .0 MTPA), DRI Plant ( 0.6 MTPA),
Pig Iron Blast furnace ( 0.6 MTPA) Sinter plant ( 0.8 MTPA) , SMS (1.2 MTPA), Rolling
Mills (1.2 MTPA ) along with Captive Power Plant of 125 MW (WHRB -75 MW and AFBC -
50 MW) at Vill : Phuljhar, Block : Banspal of Keonjhar District. It is proposed to set up the plant
for rolled steel products based on proved technology.
3.0 The existing project was accorded environmental clearance vide lr No. J-11011 / 112 /
2013-IA II(I) dated 29/03/2016. Consent to Operate was accorded by Odisha State Pollution
Control Board vide Letter No. 3702, dated 27.03.2018 validity of CTO is up to 31.03.2019.
4.0 The proposed unit will be located at Village: Phuljhar, Tehsil: Telkoi, Block: Bansapal,
District: Keonjhar, State: Odisha
5.0 The land area acquired for the proposed plant is Ac 432.019 out of which Government
1
GOVERNMENT OF KARNATAKA No. WRD.15/MTP/20I3 Karnataka Government Secretariat Vikasa Soudha Bangalore, Dated 22.12.2015 From, The Secretary to Government Water Resources Department To, The Managing Director Karnataka Irrigation Corporation Ltd. Coffee Board Building Bangalore Sir, Sub : To provide water to the proposed 700,000 integrated Steel Plant
Expansion of M/s. Mukand Ltd., to be established at Kanakapura Village, Koppala District - Reg.
Ref : Your Letter No. KNN/TBP/Mukand Steel/2014-15/6023 dated 24.01.2015 With reference to the above captioned subject, for the 700,000 Integrated Steel Plant Expansion of M/s. Mukand Ltd. proposed to be established at Kanakapura Villege, Koppala District, I am hereby directed to inform that the aforesaid Company is accorded approval to extract 18 M.L.D. (0.232 T.M.C per Annum) water directly from Tungabhadra river under Tunga-Bhadra Dam near Hulgi Village (upstream of Hulgi Railway Bridge) during rainy season, i.e. during Surplus Period, with a condition to uttlize the same with storage arrangement for sufficient quantity of water in its own premises and also subject to the following conditions.
CONDITIONS
1. The Company shall use water during excess flow of water in the Dam, i.e., from
June to December. 2. The Company shall obtain approval from the Competent Authority about drawl of
water from the river under the Dam. 3. The Company shall ensure that it will not drawl water in the event the water in the
river is under River Assistance Quota of Karnataka or Andhra Pradesh. 4. The Company shall obtain permission from the concerned Departments such as
Forest and Environment Department, State Pollution Control Board and other required Departments before initiating the Project.
2
5. Water shall be used for the purpose for which permission is accorded. 6. If there is less water in the river for whatsoever reason, no compensation will be
given by the Government and in future, if the Government undertakes any irrigation project or any other projects in the said region, Government will not give any compensation to the Company.
7. While undertaking the construction work, the Company shall take care not to
damage the properties of the Irrigation Department and private properties. If any damage occurs, all such losses and expenses shall be borne by the Company only.
8. Before commencing the work, company shall obtain No Objection Certificate
from the neighboring land owners and company shall construct proper protection walls for the banks of the river near the working spot at its own cost.
9. If any forest region is going to be submerged by water, Company shall obtain
permission from the Forest Department. 10. Care should be taken not to harm irrigation of the lands coming below the
project. 11. Company shall be absolutely responsible for loss or damage to the private or
Government assets or endangering of life if any or any other loss and in case of any accidents, company will be subjected to legal action and shall pay the compensation fixed by the Government.
12. If the Government or its designated Authorities stop water in view of the
requirements of irrigation or drinking water schemes because of which the company suffers any loss or other inconveniences or adverse effects, Government will not be responsible for the same. In such an event, Company shall not lodge any complaints and even if it lodges, same will not be considered.
13. In future, Government can take up any works for the purpose of water storage
usage and for any other reasons without company's permission. If such works are undertaken and if company suffers any loss in its production, Government will not be responsible and if the company's project or asset is affected due to submerging, Government will not be responsible for the same and will not give any compensation. The Government may undertake these works before or after the Company project location.
14. Any buildings constructed by the Company (Mechanical, Civil or Electrical)
collapsed due to irrigation or drinking water disturbance or any other problem is there, material or financial losses occurred by this shall be borne by the company itself. The compensation towards such losses will decide by the Government without giving any notice the Company.
3
15. Service Charges and other revenues fixed by the Government shall be paid by the Company.
16. The Company shall install Hydrometers in prominent places at its own cost as
directed by Authorities of the Department of Water Resources. 17. Measurements of water used will be determined by the Government or its
designated Officer. Company shall bear the water charge for quantity of water measured by the Government or its designated Officer. Government may enhance this amount anytime without prior notice to the Company.
18. Care should be taken that the drinking water schemes above and below this
project are not disturbed in any manner. 19. For the Government land and other properties required for the power project,
company shall pay the amounts to the Government before commencing the works, at the rates prescribed by the Government. Company shall not raise any objections in this regard.
20. If the private lands are submerged in water or if required for company's works,
Company shall obtain the same by making payment. If any objections raised in acquiring the private lands, Company shall get it solved at its own cost. Government will not take any responsibility in this regard.
21. Company shall adopt water recycling system and shall consume water by making
arrangements for using rain water and for water storage system at the time of water scarcity.
22. If any articles available in the Government Land used for company's works,
Company shall pay royalty to the Government as prescribed by the Government without any objections.
23. Company shall not destroy flora and fauna while executing its project or after
execution of its project. If so, Company will be absolutely responsible for the same. In such an event, Company shall bear the penalty fixed by the Government or any other sort of penalty to the Government without any objection.
24. If any legal issues arise at the time of execution of the project or after execution
of the project, Company shall get it solved at its own cost. Government is no way responsible for this and the Government will not bear any such expenses.
25. Before commencing the Project, the Company, shall enter into Agreement/MoU
with the Water Resources Department about consumption of river water. 26. While constructing the project, company shall not store excavated muck and
other excavated stuff in the Government land for whatsoever reason. The Company shall collect only in the land acquired by the Company for its use.
4
27. The Company shall ensure that the local people do not suffer due to this project implementation.
28. Before executing the project, the Company shall enter into an Agreement with
the concerned. Executive Engineer of the Water Resources Department by incorporating all the above conditions and shall execute the project according to his direction.
29. Apart from the above conditions, if the concerned officer of the Water Resource
Department suggests any other conditions deemed to be necessary locally, the Company shall enter into Agreement with the Departmental Authorities by incorporating the same.
30. If the Company violates any of the above conditions, permission will be
withdrawn without any prior notice and the Government has right to recover the losses suffered by the Government whatsoever reason from the Company.
Yours faithfully,
Sd/ - (C. Srinivasulu) Under Secretary to Government Water Resources Department
Copy to:
1) The Chief Engineer, Karnataka Irrigation Corporation Ltd., Irrigation Center Zone Munirabad
2) Chief Engineer, Water Resource Development Company, Anandrao Circle, Bangalore.
3) The Joint Managing Director, M/s. Mukand Ltd, Bajaj Bhavan, Jamnalal Bajaj Marg, 226, Nariman Point, Mumbai – 400021.
4) Director (Technical Wing), Department of Commerce and industries, Vikasa Soudha Bangalore.
efm-*f u#.G;
Governmenl of Kamalaka
MEMORANDUM OF UNDERSTANDING
dtoat ffit*rcns F[fttl*otaota t.n Jvilf, &r,
This Memorandum of Understanding is entered on 7th/8th day of June 2012 at theBangalore International Exhibition Centre (BIEC) in Bangalore (Karnataka) during GlobalInvestors' Meet 2012.
between
Mukand Ltd. a Company incorporated under the Companies Act L956, having its CorporateOffice at 3rd Floor, Bajaj Bhawan,226, Jamnalal Bajaj Marg, Nariman Point, Mumbai - 400
021..
and
The Government of Karnataka
Government of Kamataka would facilitate Mukand Ltd, to obtain necessary permissions /registrations / approvals/ clearances etc. from the concemed departments of the State, as perthe existing policies f rules and regulations of the State Government.This Memorandum of Understanding is made to facilitate Mukand Ltd. for establishment ofthe aforesaid Project in Karnataka in a time bound manner.
For and on behalf of Government ofKarnataka
For and onbehalf Mukand Ltd
(.-. \1,42 14
Mukand Ltd wishes to establish the following project in Karnataka:
(Authorised Signatory) (Authorised Signatory)
Name: Mr. M Badgandi
Designation: Sr. Manager
Contact no. : 93 41,44185 6
E mail: [email protected],
Contact address: No. 51, 1't Floor, St John'sChurch Road\ Opp Coles Park Mok Booth,Behind DTDC Courier Office, Bangalore -560005
Name: R. GIRISI{Joint Directoi
Designatilrrnttaka Udyo g ir I ttraEangalore
Lontact no.l
E mail:
Contact address:
Raw data of Ambient Air Quality Monitoring Results
Name of Location: Project Site AAQ1
Date of
Monitoring Week PM 10 PM 2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
04/04/2016 1 89.62 49.29 9.14 31.37 1012.71 36.49 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/04/2016 1 81.58 44.87 8.32 28.55 921.85 36.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
11/04/2016 2 84.63 46.55 8.63 29.62 956.32 34.85 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/04/2016 2 93.65 51.51 10.25 35.60 1058.25 37.72 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
18/04/2016 3 84.10 46.26 8.58 29.44 950.33 24.44 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/04/2016 3 85.60 47.08 8.73 29.96 967.28 34.85 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
25/04/2016 4 82.10 45.16 8.37 28.74 927.73 33.21 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/04/2016 4 77.60 42.68 7.92 27.16 876.88 21.57 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/05/2016 5 82.90 45.60 8.46 29.02 936.77 33.62 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/05/2016 5 92.70 50.99 9.46 32.45 1047.51 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/05/2016 6 84.20 46.31 8.59 29.47 951.46 34.44 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/05/2016 6 83.60 45.98 8.53 29.26 944.68 34.03 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/05/2016 7 81.70 44.94 8.33 28.60 923.21 33.21 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/05/2016 7 80.90 44.50 8.25 28.32 914.17 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/05/2016 8 79.60 43.78 8.12 27.86 899.48 32.636 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/05/2016 8 78.30 43.07 7.99 27.41 884.79 32.103 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/06/2016 9 77.70 42.74 7.93 27.20 878.01 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
07/06/2016 9 76.18 41.90 7.77 26.66 860.83 31.2338 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/06/2016 10 75.12 41.32 7.66 26.29 848.86 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/06/2016 10 79.03 43.47 8.06 27.66 893.04 32.39 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/06/2016 11 80.30 44.17 8.19 28.11 907.39 32.8 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/06/2016 11 78.80 43.34 8.04 27.58 890.44 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/06/2016 12 81.20 44.66 8.28 28.42 917.56 33.21 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/06/2016 12 89.30 49.12 9.11 31.26 1009.09 36.49 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 93.65 51.51 10.25 35.60 1058.25 38.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 75.12 41.32 7.66 26.29 848.86 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 82.52 45.38 8.45 29.00 932.44 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 93.48 51.41 10.11 35.03 1056.31 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Kanakapur AAQ 2
Date of
Monitoring Week PM 10 PM 2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
04/04/2016 1 85.2 46.86 8.69 29.82 962.76 33.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/04/2016 1 82.3 45.27 8.39 28.805 929.99 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
11/04/2016 2 86.9 47.80 8.86 30.415 981.97 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/04/2016 2 79.2 43.56 8.08 27.72 894.96 30.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
18/04/2016 3 85.1 46.81 8.68 29.785 961.63 33.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/04/2016 3 61.9 34.05 6.31 21.665 699.47 24.141 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
25/04/2016 4 82.3 45.27 8.39 28.805 929.99 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/04/2016 4 86.5 47.58 8.82 30.275 977.45 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/05/2016 5 83.7 46.04 8.54 29.295 945.81 32.37 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/05/2016 5 98.1 53.96 10.01 34.335 1108.53 38.22 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/05/2016 6 74.8 41.14 7.63 26.18 845.24 29.172 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/05/2016 6 79.5 43.73 8.11 27.825 898.35 30.42 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/05/2016 7 78.1 42.96 7.97 27.335 882.53 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/05/2016 7 72.6 39.93 7.41 25.41 820.38 30.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/05/2016 8 68.9 37.90 7.03 24.115 778.57 25.701 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/05/2016 8 84.3 46.37 8.60 29.505 952.59 32.76 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/06/2016 9 86.9 47.80 8.86 30.415 981.97 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
07/06/2016 9 62.8 34.54 6.41 21.98 709.64 24.492 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/06/2016 10 87.5 48.13 8.93 30.625 988.75 33.54 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/06/2016 10 81.7 44.94 8.33 28.595 923.21 31.59 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/06/2016 11 83.2 45.76 8.49 29.12 940.16 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/06/2016 11 74.3 40.87 7.58 26.005 839.59 28.86 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/06/2016 12 81.7 44.94 8.33 28.595 923.21 31.863 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/06/2016 12 81.2 44.66 8.28 28.42 917.56 32.799 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 98.10 53.96 10.01 34.34 1108.53 38.22 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 61.90 34.05 6.31 21.67 699.47 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 80.36 44.20 8.20 28.13 908.10 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 94.29 51.86 9.62 33.00 1065.50 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Ginigera AAQ 3
Date of
Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
04/04/2016 1 74.60 39.54 8.21 26.11 842.98 30.59 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/04/2016 1 76.90 40.76 8.46 26.92 868.97 31.53 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
11/04/2016 2 72.30 38.32 7.95 25.31 816.99 29.64 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/04/2016 2 74.60 39.54 8.21 26.11 842.98 30.59 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
18/04/2016 3 70.00 37.10 7.70 24.50 791.00 28.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/04/2016 3 76.30 40.44 8.39 26.71 862.19 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
25/04/2016 4 79.00 41.87 8.69 27.65 892.70 32.39 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/04/2016 4 74.50 39.49 8.20 26.08 841.85 30.55 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/05/2016 5 78.00 41.34 8.58 27.30 881.40 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/05/2016 5 92.90 49.24 10.22 32.52 1049.77 38.09 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/05/2016 6 74.50 39.49 8.20 26.08 841.85 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/05/2016 6 76.30 40.44 8.39 26.71 862.19 21.28 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/05/2016 7 78.90 41.82 8.68 27.62 891.57 32.35 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/05/2016 7 72.30 38.32 7.95 25.31 816.99 29.64 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/05/2016 8 74.00 39.22 8.14 25.90 836.20 30.34 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/05/2016 8 74.45 39.46 8.19 26.06 841.29 30.52 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/06/2016 9 78.00 41.34 8.58 27.30 881.40 31.98 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
07/06/2016 9 79.60 42.19 8.76 27.86 899.48 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/06/2016 10 79.00 41.87 8.69 27.65 892.70 32.39 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/06/2016 10 73.20 38.80 8.05 25.62 827.16 30.01 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/06/2016 11 78.50 41.61 8.64 27.48 887.05 32.19 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/06/2016 11 79.60 42.19 8.76 27.86 899.48 32.64 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/06/2016 12 79.00 41.87 8.69 27.65 892.70 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/06/2016 12 82.00 43.46 9.02 28.70 926.60 33.62 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 92.90 49.24 10.22 32.52 1049.77 38.09 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 70.00 37.10 7.70 24.50 791.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 77.02 40.82 8.47 26.96 870.31 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 87.89 46.58 9.67 30.76 993.11 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Bevinhalli AAQ 4
Date of
Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
04/04/2016 1 72.6 34.848 7.986 24.684 813.12 29.04 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/04/2016 1 75.3 36.144 8.283 25.602 843.36 30.12 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
11/04/2016 2 77.2 37.056 8.492 26.248 864.64 30.88 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/04/2016 2 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
18/04/2016 3 72.3 34.704 7.953 24.582 809.76 28.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/04/2016 3 71.2 34.176 7.832 24.208 797.44 28.48 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
25/04/2016 4 75.2 36.096 8.272 25.568 842.24 30.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/04/2016 4 72 34.56 7.92 24.48 806.4 28.8 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/05/2016 5 76.3 36.624 8.393 25.942 854.56 30.52 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/05/2016 5 89.9 43.152 9.889 30.566 1006.88 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/05/2016 6 71 34.08 7.81 24.14 795.2 28.4 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/05/2016 6 68.9 33.072 7.579 23.426 771.68 27.56 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/05/2016 7 65 31.2 7.15 22.1 728 26 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/05/2016 7 62.3 29.904 6.853 21.182 697.76 24.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/05/2016 8 66 31.68 7.26 22.44 739.2 26.4 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/05/2016 8 69 33.12 7.59 23.46 772.8 27.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/06/2016 9 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
07/06/2016 9 72 34.56 7.92 24.48 806.4 28.8 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/06/2016 10 62.3 29.904 6.853 21.182 697.76 24.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/06/2016 10 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/06/2016 11 58.9 28.272 6.479 20.026 659.68 23.56 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/06/2016 11 75 36 8.25 25.5 840 30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/06/2016 12 74 35.52 8.14 25.16 828.8 29.6 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/06/2016 12 72.3 34.704 7.953 24.582 809.76 28.92 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 89.90 43.15 9.89 30.57 1006.88 35.96 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 58.90 28.27 6.48 20.03 659.68 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 71.70 34.41 7.89 24.38 802.99 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 84.06 40.35 9.25 28.58 941.45 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Agalkera AAQ 5
Date of
Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
07/04/2016 1 85.60 43.66 9.50 31.67 967.28 35.10 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
08/04/2016 1 81.20 41.41 9.01 30.04 917.56 33.29 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/04/2016 2 86.50 44.12 9.60 32.01 977.45 35.47 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
15/04/2016 2 81.90 41.77 9.09 30.30 925.47 33.58 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/04/2016 3 86.20 43.96 9.57 31.89 974.06 35.34 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
22/04/2016 3 67.80 34.58 7.53 25.09 766.14 27.80 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/04/2016 4 81.50 41.57 9.05 30.16 920.95 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
29/04/2016 4 65.20 33.25 7.24 24.12 736.76 26.73 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/05/2016 5 88.80 45.29 9.86 32.86 1003.44 36.41 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/05/2016 5 98.80 50.39 10.97 36.56 1116.44 20.51 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/05/2016 6 78.90 40.24 8.76 29.19 891.57 32.35 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/05/2016 6 78.40 39.98 8.70 29.01 885.92 32.14 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/05/2016 7 85.49 43.60 9.49 31.63 966.07 35.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/05/2016 7 86.51 44.12 9.60 32.01 977.57 35.47 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/05/2016 8 87.53 44.64 9.72 32.39 989.06 35.89 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/05/2016 8 88.54 45.16 9.83 32.76 1000.56 36.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/06/2016 9 89.56 45.68 9.94 33.14 1012.05 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/06/2016 9 90.58 46.20 10.05 33.51 1023.54 37.14 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/06/2016 10 73.60 37.54 8.17 27.23 831.68 30.18 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/06/2016 10 84.09 42.89 9.33 31.11 950.22 34.48 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/06/2016 11 97.40 49.67 10.81 36.04 1100.62 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/06/2016 11 87.10 44.42 9.67 32.23 984.23 35.71 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/06/2016 12 65.10 33.20 7.23 24.09 735.63 26.69 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/06/2016 12 81.20 41.41 9.01 30.04 917.56 33.29 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 98.80 50.39 10.97 36.56 1116.44 26.69 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 65.10 33.20 7.23 24.09 735.63 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 89.00 42.45 9.24 30.79 940.49 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 89.00 42.45 9.24 30.79 940.49 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Halwarti AAQ 6
Date of
Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
07/04/2016 1 88 39.6 8.97 32.56 994.4 22.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
08/04/2016 1 82.2 36.99 8.38 30.41 928.86 20.55 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/04/2016 2 80.6 36.27 8.22 29.82 910.78 20.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
15/04/2016 2 79.5 35.775 8.10 29.41 898.35 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/04/2016 3 88.6 39.87 9.03 32.78 1001.18 30.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
22/04/2016 3 85 38.25 8.67 31.45 960.5 21.25 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/04/2016 4 86.1 38.745 8.78 31.85 972.93 21.53 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
29/04/2016 4 88.2 39.69 8.99 32.63 996.66 22.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/05/2016 5 76.4 34.38 7.79 28.26 863.32 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/05/2016 5 84.6 38.07 8.62 31.30 955.98 21.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/05/2016 6 78.5 35.325 8.00 29.04 887.05 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/05/2016 6 84.3 37.935 8.59 31.19 952.59 21.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/05/2016 7 82.2 36.99 8.38 30.41 928.86 30.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/05/2016 7 78.6 35.37 8.012 29.08 888.18 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/05/2016 8 87.1 39.195 8.882 32.27 984.23 21.78 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/05/2016 8 85.3 38.385 8.706 31.51 963.89 21.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/06/2016 9 84.9 38.205 8.658 31.43 959.37 21.23 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/06/2016 9 83.5 37.575 8.57 30.85 943.55 20.88 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/06/2016 10 81.2 36.54 8.224 30.04 917.56 20.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/06/2016 10 80.6 36.27 8.22 29.82 910.78 20.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/06/2016 11 79.5 35.775 8.19 29.45 699 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/06/2016 11 88.6 39.87 9.02 32.72 1001.18 22.15 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/06/2016 12 86.1 38.745 8.72 31.87 972.93 21.53 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/06/2016 12 87 39.15 8.84 32.19 983.1 21.75 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 88.60 39.87 9.04 32.78 1001.18 30.00 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 76.40 34.38 7.79 28.27 699.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 83.61 37.62 8.53 30.94 936.47 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 88.60 39.87 9.04 32.78 1001.18 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Hirekhasankandi AAQ 7
Date of
Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
07/04/2016 1 81.67 39.20 8.33 30.22 922.92 36.08 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
08/04/2016 1 83.61 40.13 8.53 30.94 944.84 33.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/04/2016 2 89.73 43.07 9.15 33.20 1013.89 33.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
15/04/2016 2 75.76 36.36 7.73 28.03 856.05 32.60 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/04/2016 3 83.03 39.86 8.47 30.72 938.26 36.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
22/04/2016 3 92.73 44.51 9.46 34.31 1047.87 34.85 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/04/2016 4 75.76 36.36 7.73 28.03 856.05 35.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
29/04/2016 4 83.03 39.86 8.47 30.72 938.26 36.16 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/05/2016 5 87.01 41.76 8.87 32.19 983.20 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/05/2016 5 92.15 44.23 9.40 34.10 1041.30 34.69 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/05/2016 6 69.45 33.34 7.08 25.70 784.81 32.19 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/05/2016 6 95.06 45.63 9.70 35.17 1074.18 24.56 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/05/2016 7 96.13 46.14 9.80 35.57 1086.24 33.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/05/2016 7 96.03 46.09 9.80 35.53 1085.14 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/05/2016 8 95.74 45.95 9.77 35.42 1081.85 35.71 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/05/2016 8 86.82 41.67 8.86 32.12 981.01 34.97 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/06/2016 9 85.75 41.16 8.75 31.73 968.95 34.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/06/2016 9 83.13 39.90 8.48 30.76 939.36 24.24 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/06/2016 10 95.06 45.63 9.70 35.17 1074.18 33.29 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/06/2016 10 96.03 46.09 9.80 35.53 1085.14 33.05 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/06/2016 11 91.67 44.00 9.35 33.92 699.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/06/2016 11 83.03 39.86 8.47 30.72 938.26 36.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/06/2016 12 92.15 44.23 9.40 34.10 1041.30 35.30 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/06/2016 12 80.61 38.69 8.22 29.82 910.86 35.67 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 96.13 46.14 9.80 35.57 1086.24 36.33 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 69.45 33.34 7.08 25.70 699.00 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 87.13 41.82 8.89 32.24 970.54 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 96.08 46.12 9.80 35.55 1085.73 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Name of Location: Allanagar AAQ 8
Date of
Monitoring Week PM10 PM2.5 SO2 NOX CO O3 Pb NH3 C6H6 As Ni
Benzo(a)
Pyrene VOC
07/04/2016 1 84.2 42.94 9.35 31.15 951.46 34.52 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
08/04/2016 1 86.2 43.96 9.57 31.89 974.06 35.34 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
14/04/2016 2 92.5 47.18 10.27 34.23 1045.25 37.93 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
15/04/2016 2 78.1 39.83 8.67 28.90 882.53 32.02 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
21/04/2016 3 85.6 43.66 9.50 31.67 967.28 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
22/04/2016 3 95.6 48.76 10.61 35.37 1080.28 39.20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
28/04/2016 4 78.1 39.83 8.67 28.90 882.53 32.02 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
29/04/2016 4 85.6 43.66 9.50 31.67 967.28 35.10 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
05/05/2016 5 89.7 45.75 9.96 33.19 1013.61 36.78 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
06/05/2016 5 95 48.45 10.55 35.15 1073.50 28.95 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
12/05/2016 6 71.6 36.52 7.95 26.49 809.08 29.36 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
13/05/2016 6 98 49.98 10.88 36.26 1107.40 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
19/05/2016 7 90.1 45.95 10.00 33.34 1018.13 36.94 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20/05/2016 7 94.1 47.99 10.45 34.82 1063.33 38.58 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
26/05/2016 8 98.7 50.34 10.96 36.52 1115.31 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
27/05/2016 8 89.5 45.65 9.93 33.12 1011.35 36.70 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
02/06/2016 9 88.4 45.08 9.81 32.71 998.92 36.24 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
03/06/2016 9 85.7 43.71 9.51 31.71 968.41 35.14 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
09/06/2016 10 98 49.98 10.88 36.26 1107.40 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
10/06/2016 10 97.1 49.52 10.78 35.93 1097.23 39.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
16/06/2016 11 94.5 48.20 10.49 34.97 1067.85 28.75 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
17/06/2016 11 85.6 43.66 9.50 31.67 967.28 35.10 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
23/06/2016 12 95 48.45 10.55 35.15 1073.50 38.95 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
24/06/2016 12 83.1 42.38 9.22 30.75 939.03 34.07 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Maximum 98.70 50.34 10.96 36.52 1115.31 39.81 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Minimum 71.60 36.52 7.95 26.49 809.08 <20 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
Average 89.00 45.48 9.90 32.99 1007.58 - <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
98percentile 95.49 48.70 10.60 35.33 1079.06 <0.01 <20 <3.0 <0.5 <1.0 <0.01 <1
20
PROJECT SITE
Topo Map
Topo Sheet No - 57 A/3 Topo Sheet No - 57 A/7
Topo Sheet No - 57 A/4 Topo Sheet No - 57 A/7
76 15' 76 10'
15 15'
HIGH COURT OF GUJARAT
SPECIAL CIVIL APPLICATION No. 5312 of 2016
Status : PENDING ( Converted from : C/ST/5331/2016 ) CCIN No : 001021201605312
Next Listing Date:20/02/2018
Coram HONOURABLE THE CHIEF JUSTICE MR.
R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL M.
PANCHOLI
S.NO. Name of the Petitioner Advocate On Record
1
2
3
4
5
6
7
8
9
10
11
12
JAYESHKUMAR SOMABHAI PATEL
CHANDRASHEKHAR BHANUPRASAD UPASANI
MALAV PRAFULBHAI DALWADI
SNEHAL BHARATBHAI SATYAPATHI
PRADEEP PRABHAKAR JOSHI
GAURANG VINODBHAI PARMAR
DARSHAN JITENDRABHAI PAREKH
SURESH TULSHIBHAI MORADIA
SUDHIR NARAISINGH VERMA
SEEMA CHANDRAKANT ABHALE
DILIP CHANDUBHAI THAKKAR
BALU TRIBHOVAN PATEL
less
MR NILESH P SHAH for: Petitioner(s) 1 - 12
ANSHUL N SHAH for: Petitioner(s) 1 - 12
S.NO. Name of the Respondant Advocate On Record
1 UNION OF INDIA NOTICE NOT RECD BACK for :Respondent(s) 1
NOTICE SERVED for :Respondent(s) 1
Presented On : 30/03/2016 Registered On : 04/04/2016
Bench Category : DIVISON BENCH District : SURAT
Case Originated From : THROUGH HIS/HER/THEIR
ADVOCATE
Listed : 18 times
StageName : NOTICE & ADJOURNED MATTERS
Classification DB - VIRES CHALLENGED - VIRES CHALLENGED - CONSTITUTION OF INDIA - CENTRAL ACT / STATE ACT /
RULE / STATUTORY NOTIFICATION / REGULATIONS
Act CONSTITUTION OF INDIA
Office Details
S. No. Filing Date Document Name Advocate NameCourt Fee on
DocumentDocument Details
1 30/03/2016 VAKALATNAMA ANSHUL N SHAH ADVOCATE
for PETITIONER(s) 1
0 ANSHUL N SHAH(8540) for
P:1 - 12
2 30/03/2016 VAKALATNAMA MR NILESH P SHAH ADVOCATE
for PETITIONER(s) 1
5 MR NILESH P SHAH(3215)
for P:1 - 12
3 30/03/2016 MEMO OF
PETITION/APPEAL/SUIT
MR NILESH P SHAH ADVOCATE
for PETITIONER(s) 1
100 MR NILESH P SHAH(3215),
ANSHUL N SHAH(8540),
for P:1 - 12
4 01/04/2016 ADDITIONAL FEE ON
MEMO OF
APPEAL/PETITION/SUIT
MR NILESH P SHAH ADVOCATE
for PETITIONER(s) 1
500 MR NILESH P
SHAH(3215),ANSHUL N
SHAH(8540) for P:1 - 12
Linked Matters
S.
No.CaseDetail Status Name Disposal Date Action/Coram
1 SPECIAL CIVIL
APPLICATION/17039/2016
PENDING - -
HONOURABLE THE CHIEF JUSTICE MR. R.SUBHASH
REDDY
HONOURABLE MR.JUSTICE VIPUL M. PANCHOLI
2 SPECIAL CIVIL
APPLICATION/11208/2017
PENDING - -
HONOURABLE THE CHIEF JUSTICE MR. R.SUBHASH
REDDY
HONOURABLE MR.JUSTICE VIPUL M. PANCHOLI
3 SPECIAL CIVIL
APPLICATION/20606/2017
PENDING - -
HONOURABLE THE CHIEF JUSTICE MR. R.SUBHASH
REDDY
HONOURABLE MR.JUSTICE VIPUL M. PANCHOLI
Court Proceedings
S. No.Notified
DateCourtCode
Board
Sr. No.Stage Action Coram
1 05/04/2016 1 6 URGENT ADMISSION (FRESH
MATTERS)
FIXED NOTICE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
2 13/06/2016 1 31 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
3 04/07/2016 1 35 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
4 21/07/2016 1 55 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
5 14/09/2016 1 119 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
6 05/10/2016 1 119 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
7 07/11/2016 1 29 NOTICE & ADJOURNED
MATTERS
HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
8 18/11/2016 1 73 NOTICE & ADJOURNED
MATTERS
HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
9 19/12/2016 1 88 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
10 20/01/2017 1 69 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
11 21/02/2017 1 50 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
12 14/03/2017 1 86 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
13 20/04/2017 1 109 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
14 03/07/2017 1 97 NOTICE & ADJOURNED
MATTERS
HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
15 04/09/2017 1 86 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
16 14/11/2017 1 74 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
17 12/01/2018 1 49 NOTICE & ADJOURNED
MATTERS
NEXT DATE HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
18 20/02/2018 1 - NOTICE & ADJOURNED
MATTERS
HONOURABLE THE CHIEF JUSTICE
MR. R.SUBHASH REDDY
HONOURABLE MR.JUSTICE VIPUL
M. PANCHOLI
Available Orders
S.
No.Case Details Judge Name
Order
DateCAV Judgement Questions Transferred Download
1 SPECIAL CIVIL
APPLICATION/5312/2016
HONOURABLE
THE CHIEF
JUSTICE MR.
R.SUBHASH
REDDY
HONOURABLE
MR.JUSTICE
VIPUL M.
PANCHOLI
05/04/2016 N ORDER - YDownload
2 SPECIAL CIVIL
APPLICATION/5312/2016
HONOURABLE
THE CHIEF
JUSTICE MR.
R.SUBHASH
REDDY
HONOURABLE
MR.JUSTICE
VIPUL M.
PANCHOLI
21/07/2016 N ORDER - YDownload
3 SPECIAL CIVIL
APPLICATION/5312/2016
HONOURABLE
THE CHIEF
JUSTICE MR.
R.SUBHASH
REDDY
HONOURABLE
MR.JUSTICE
VIPUL M.
PANCHOLI
18/11/2016 N ORDER - YDownload
4 SPECIAL CIVIL
APPLICATION/5312/2016
HONOURABLE
THE CHIEF
JUSTICE MR.
R.SUBHASH
REDDY
HONOURABLE
MR.JUSTICE
VIPUL M.
PANCHOLI
20/01/2017 N ORDER - YDownload
Certified Copy
S.
No.ApplicantName ApplicationType
Application
Date
UOL
NumberOrder Date
Notify
Date
Delivery
DateStatus
Nature Of
Document
1 MR NILESH P
SHAH
URGENT 05/04/2016 U/2292/201605/04/2016 07/04/2016 11/04/2016 Delivered ORDER
2 MR NILESH P
SHAH
URGENT 18/04/2016 U/2604/201605/04/2016 19/04/2016 21/04/2016 Delivered ORDER
SOCIAL IMPACT STUDY REPORT
For proposed Green Field Project
“Alloy Steel Rolling Mill of 700,000 TPA”
By
M/s. MUKAND ALLOY STEELS PRIVATE LTD.
(MASPL)
At village Kanakapur, Taluka & District Koppal,
State: Karnataka
FEBRUARY 2018
Prepared By:
GREEN CIRCLE, INC.,
Vadodara
M/s Mukand Alloy steels Private Limited
Green Circle Inc. Vadodara 2
Client: MASPL
Project No: GCI/V/2017-18/EIA
Summary and version history: R00
Compiled by: Vikash Bhagat
Reviewed by: Pradeep Joshi
Peer Reviewed by: Dr.Deepika Mondal
1 Social Impact Assessment Study
Distribution: For inclusion in the EIA for the
MASPL ,Hospet, Karnataka
This report has been prepared for
MASPL in accordance with the terms
and conditions of TOR issued by
MoEF&CC, GCI contract with for
submission to commenting authorities
and the Competent Authority in
support of MASPL application for an
Environmental Clearance.
Any other use, distribution or
publication of this report is prohibited
without the prior written approval of
GCI & MASPL.
M/s Mukand Alloy steels Private Limited
Green Circle Inc. Vadodara 3
CONTENTS
1. INTRODUCTION ....................................................................................................... 7 1.1 PROJECT BACKGROUND ............................................................................................... 7 1.2 TERMS OF REFERENCE ................................................................................................ 7 1.3 STUDY APPROACH AND METHODOLOGY ................................................................... 7 1.4 IMPACT ASSESSMENT METHODOLOGY ...................................................................... 8 1.4.1 Impact Prediction .............................................................................................................. 9 1.4.2 Impact Evaluation ........................................................................................................... 10 1.5 ASSUMPTIONS AND LIMITATIONS .............................................................................. 16 1.6 SPECIALIST DETAILS ................................................................................................... 16
2. PROJECT DESCRIPTION ...................................................................................... 16 2.1 PROJECT BACKGROUND ............................................................................................. 17 2.1.1 Project Location .............................................................................................................. 17 2.1.2 Land Ownership and Acquisition ..................................................................................... 17 2.2 PROJECT COMPONENTS ............................................................................................. 18 2.3 PROJECT PHASING AND SCHEDULE ......................................................................... 20 2.3.1 Construction Phase ......................................................................................................... 20 2.3.2 Operation Phase ............................................................................................................. 21
3. PROJECT MOTIVATION ........................................................................................ 23 4. SOCIO-ECONOMIC BASELINE.............................................................................. 24
4.1 AREA OF INFLUENCE (AOI) .......................................................................................... 24 4.1.1 Area of Direct Influence................................................................................................... 24 4.1.2 Indirect Area of Influence ................................................................................................ 24 4.2 ADMINISTRATIVE STRUCTURE ................................................................................... 26 4.3 SITE SETTING AND LANDUSE ..................................................................................... 26 4.3.1 Land-use of the Project Site ............................................................................................ 26 4.4 DEMOGRAPHIC PROFILE ............................................................................................. 29 4.5 LIVELIHOODS AND ECONOMY .................................................................................... 33 4.6 SOCIAL INFRASTRUCTURE AND SERVICES .............................................................. 35 4.6.1 Connectivity, Transport and Communication ................................................................... 35 4.6.2 Water .............................................................................................................................. 37 4.6.3 Housing .......................................................................................................................... 37
5. IMPACT ASSESSMENT ......................................................................................... 38 5.1 EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS
OPPORTUNITIES ...................................................................................................................... 38 5.1.1 Construction: Employment, Skills Enhancement and Local Business Opportunities ........ 39 Impact Description ...................................................................................................................... 39 5.1.2 Operation: Employment, Skills Enhancement and Local Business Opportunities ............ 42 5.2 IMPACTS ON COMMUNITY HEALTH AND SAFETY ..................................................... 44
5.2.1 Construction and Operation: Impacts Associated with the Presence of the Workforce and Jobseekers ......................................................................................................... 44 5.2.2 Construction and Operation: Pressure on Social Infrastructure and Services .................. 47
5.2.3 Construction Phase: Impact on Human Health due to Air Emissions and Dust Generation .................................................................................................................................. 49 5.2.4 Operations Phase: Impact on Human Health due to Air Emissions ................................. 50 5.3 INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE ................. 52
5.3.1 Construction and Phase: Increased Nuisance Factors and Change in Sense of Place 52
5.3.2 Operation Phase: Increased Nuisance Factors ............................................................... 54 5.4 WORKER HEALTH AND SAFETY AND RIGHTS ........................................................... 57 5.4.1 Construction Phase: Risk to Workers’ H&S due to Construction Activities ...................... 58 5.4.2 Operation Phase: Risk to Workers’ H&S due to Hazardous Operation Activities ............. 61 5.5 CUMULATIVE IMPACTS ................................................................................................ 62
M/s Mukand Alloy steels Private Limited
Green Circle Inc. Vadodara 4
5.5.1 Method ............................................................................................................................ 63 5.5.2 Cumulative Impacts of the Socioeconomic Environment ................................................. 63 5.6 UNPLANNED EVENTS................................................................................................... 68
6. KEY FINDINGS AND RECOMMENDATIONS ......................................................... 69 7. IMPACT STATEMENT ............................................................................................ 72 8. REFERENCES ........................................................................................................ 72
List of Tables
TABLE 4.1 LAND USE DISTRIBUTION OF THE STUDY AREA (10 KM RADIUS) ............................................................................ 27 TABLE 4.2 VILLAGE-WISE DETAILS OF POPULATION ............................................................................................................ 29 TABLE 4.3 SOCIAL DISTRIBUTION ................................................................................................................................... 30 TABLE 4.4 LITERACY RATE ............................................................................................................................................ 31 TABLE 4.5 EMPLOYMENT SCENARIO ............................................................................................................................... 32 TABLE 5.1 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS
OPPORTUNITIES .................................................................................................................................................. 41 TABLE 5.2 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS
OPPORTUNITIES DURING CONSTRUCTION ................................................................................................................. 41 TABLE 5.3 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS
OPPORTUNITIES .................................................................................................................................................. 43 TABLE 5.4 PRE- AND POST - MITIGATION SIGNIFICANCE FOR EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS
OPPORTUNITIES DURING OPERATION ...................................................................................................................... 43 TABLE 5.5 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH THE PRESENCE OF THE WORKFORCE AND
JOBSEEKERS ....................................................................................................................................................... 46 TABLE 5.6 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH THE PRESENCE OF A WORKFORCE AND
JOBSEEKERS ....................................................................................................................................................... 46 TABLE 5.7 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH PRESSURE ON SOCIAL INFRASTRUCTURE AND
SERVICES ........................................................................................................................................................... 48 TABLE 5.8 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED PRESSURE ON SOCIAL INFRASTRUCTURE AND
SERVICES ............................................................................................................... ERROR! BOOKMARK NOT DEFINED. TABLE 5.9 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST
GENERATION ...................................................................................................................................................... 49 TABLE 5.10 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST
GENERATION .......................................................................................................... ERROR! BOOKMARK NOT DEFINED. TABLE 5.11 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST
GENERATION ...................................................................................................................................................... 51 TABLE 5.12 PRE - AND POST- MITIGATION SIGNIFICANCE FOR IMPACT ON HUMAN HEALTH DUE TO AIR EMISSIONS AND DUST
GENERATION ...................................................................................................................................................... 51 TABLE 5.13 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE ..... 54 TABLE 5.14 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE
DURING CONSTRUCTION AND ................................................................................................................................ 54 TABLE 5.15 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE
DURING OPERATION ............................................................................................................................................ 56 TABLE 5.16 PRE- AND POST- MITIGATION SIGNIFICANCE FOR INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE
OPERATION........................................................................................................................................................ 57 TABLE 5.17 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS CONSTRUCTION
ACTIVITIES ......................................................................................................................................................... 60 TABLE 5.18 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS CONSTRUCTION AND
ACTIVITIES ......................................................................................................................................................... 60 TABLE 5.19 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS OPERATION ACTIVITIES62 TABLE 5.20 PRE- AND POST- MITIGATION SIGNIFICANCE FOR RISK TO WORKERS’ H&S DUE TO HAZARDOUS OPERATION ACTIVITIES62 TABLE 5.21 PRE- AND POST - MITIGATION SIGNIFICANCE FOR ECONOMY, EMPLOYMENT AND SKILLS DEVELOPMENT CUMULATIVE
IMPACT ............................................................................................................................................................. 65 TABLE 5.22 PRE- AND POST - MITIGATION SIGNIFICANCE FOR ECONOMY, EMPLOYMENT AND SKILLS DEVELOPMENT CUMULATIVE
IMPACT ............................................................................................................................................................. 65 TABLE 5.23 PRE- AND POST- MITIGATION SIGNIFICANCE FOR COMMUNITY HEALTH AND SAFETY CUMULATIVE IMPACT ................. 66 TABLE 5.24 PRE- AND POST- MITIGATION SIGNIFICANCE FOR COMMUNITY HEALTH AND SAFETY CUMULATIVE IMPACT ................. 67 TABLE 5.25 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED WITH PRESSURE ON SOCIAL INFRASTRUCTURE AND
SERVICES CUMULATIVE IMPACT ............................................................................................................................. 68
M/s Mukand Alloy steels Private Limited
Green Circle Inc. Vadodara 5
TABLE 5.26 PRE- AND POST- MITIGATION SIGNIFICANCE FOR IMPACTS ASSOCIATED PRESSURE ON SOCIAL INFRASTRUCTURE AND
SERVICES ........................................................................................................................................................... 68
List of Figures
FIGURE 1.1 PROJECT LOCATION MAP ............................................................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 1.2 METHODOLOGY OF EIA STUDY ..................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.1 GOOGLE IMAGE SHOWING FOUR CORNERS OF THE PROJECT SITE .......................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.2 GOOGLE MAP OF PROJECT SITE ..................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.3 GOOGLE IMAGE OF 2 KM AND 5 KM RADIUS FROM THE PROJECT SITE .................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.4 GOOGLE IMAGE OF 5 KM AND 10 KM RADIUS FROM THE PROJECT SITE .................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 2.5 PHOTOGRAPHS OF THE PROPOSED PLANT SITE ................................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 2.6 PLANT LAYOUT ........................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.7 SCHEMATIC PROCESS FLOW WITH MATERIAL FLOW CHART ................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 2.8 WATER BALANCE DIAGRAM .......................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.9 EFFLUENT TREATMENT PLANT LAYOUT ........................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.10 STP PLANT LAYOUT ................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 2.11 LAYOUT FOR RAIN WATER HARVESTING ......................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.1 DEM OF MASPL PROJECT STUDY AREA ......................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.2 LAND USE MAP AT PROJECT SITE ................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.3 WIND ROSE DIAGRAM................................................................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 3.4 GOOGLE IMAGE SHOWING AMBIENT AIR MONITORING LOCATIONS ..................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.5 STATISTICAL COMPARISON OF PM 10 IN STUDY AREA ......................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.6 STATISTICAL COMPARISON OF PM 2.5 IN STUDY AREA ....................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.7 STATISTICAL COMPARISON OF SO2 IN STUDY AREA ............................................................ ERROR! BOOKMARK NOT DEFINED. FIGURE 3.8 STATISTICAL COMPARISON OF NOX IN STUDY AREA ........................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.9 IMAGE SHOWING NOISE MONITORING LOCATION ............................................................. ERROR! BOOKMARK NOT DEFINED. FIGURE 3.10 IMAGE SHOWING SURFACE & GROUND WATER SAMPLING LOCATIONS ............................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.11 GOOGLE IMAGE SHOWING SOIL MONITORING LOCATIONS................................................ ERROR! BOOKMARK NOT DEFINED. FIGURE 3.12 DEMOGRAPHIC PATTERN ........................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.13 SOCIAL PATTERN ...................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 3.14 LITERACY RATE ......................................................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 4.1 GROUND LEVEL CONCENTRATION OF PM10 ...................................................................... ERROR! BOOKMARK NOT DEFINED. FIGURE 4.2 GROUND LEVEL CONCENTRATION OF SO2 ........................................................................ ERROR! BOOKMARK NOT DEFINED. FIGURE 4.3 GROUND LEVEL CONCENTRATION OF NOX ....................................................................... ERROR! BOOKMARK NOT DEFINED.
M/s Mukand Alloy steels Private Limited
Green Circle Inc. Vadodara 6
List of Abbreviations and TERMs
BAR Basic Assessment Report
BFS Bankable Feasibility Study
CBA Critical Biodiversity Area
MoEFCC Department of Environmental Affairs and Development Planning
EIA Environmental Impact Assessment
EIR Environmental Impact Report
EPC Engineering Procurement Construction
GNR Government Notice Regulation
HP High Pressure
HFO Heavy Fuel Oil
HRSG Heat Recovery Steam Generator
HV High Voltage
IDZ Industrial Development Zone
IRP Integrated Regional Plan
LP Low Pressure
NID Notice of Intent to Develop
SDFP Spatial Development Framework Plan
S&EIR Scoping and Environmental Impact Report
WML Waste Management Licence
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 7
1. INTRODUCTION
1.1 PROJECT BACKGROUND
M/s. Mukand Alloy Steels Private Ltd (MASPL) is a subsidiary of M/s. Mukand Ltd and M/s. Mukand
Ltd has decided to delegate its Alloy Steel business to M/s. MASPL. The site at which M/s. Mukand
Ltd proposed to setup Integrated Steel Plant of 0.7 MTPA at Village- Kanakapur, Taluka & District-
Koppal, State - Karnataka shall be used by its subsidiary company M/s. MASPL to setup the
proposed plant. Mukand Ltd. (Formerly known as Mukand Iron & Steel Works Ltd.), is one of the
largest producer of ‘Alloys and Special Steels’ and Stainless Steels in the country meeting the
requirements of Original Equipment Manufacturers (OEM) for automobiles, auto-component
industries as also of railways, defence, transportation and engineering industries.
1.2 TERMS OF REFERENCE
The approach to this Socio-economic Study has been guided by the MoEF&CC Manual and the
MOEF has finalized the Terms of References (TORs) for carrying out Environmental Studies vide
letter no. J-11011/105/2016-IA.II (I)). Dated 19th May 2016.
1.3 STUDY APPROACH AND METHODOLOGY
Associated MoEF&CC Manual, as well as referring to IFC & ADB guidelines,
The Social Study was divided into the following three Phases:
Phase 1: Desktop Study;
Phase 2: Fieldwork; and
Phase 3: Update Socio-economic Baseline and Impact Assessment.
Phase 1: Desktop Study
The desktop component of the study has drawn on the use of secondary data sourced from previous
project reports, as well as other Internet-based sources including:
• District and Local Development Plans;
• District and Local Spatial Development Frameworks;
• Statistics from Census;
• Other similar EIAs undertaken in the same region and
• Other EIAs undertaken for Integrated Steel Plants
The information collected through desktop research included: demographic (including human
settlements on affected properties), economic, health and education information as well as the
availability of physical infrastructure and services. The purpose of collecting this information was to
provide a basis upon which the impact assessment can be conducted, and to enable the
measurement and monitoring of the impacts.
Through a review of the existing documentation, gaps in information were identified to be addressed
through primary data collection, as outlined in Phase 2 and via drawing on any additional sources of
secondary data that were identified during the course of the study.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 8
Phase 2: Fieldwork and Primary Data Collection
In order to gather clear and current information for the baseline and impact assessment, a field visit
was undertaken. The field visit was undertaken during Baseline survey (April to June, 2016) and
later updated before the public hearing (January 2017). This afforded the social consultants the
opportunity to engage with the relevant community members and authorities, as well as get a
general sense of the stakeholder issues.
Where the relevant stakeholders were not available at the time of the site visit, follow-up was made
for the same.
Phase 3: Update Socio-economic Baseline and undertake Impact Assessment
The socio-economic baseline from the Scoping Report was updated using the secondary and
primary data collected in Phase 2. The findings of the public consultation process were also
incorporated into the baseline in order to ensure that it accurately describes the current situation and
needs of the local communities.
The Social Specialist has identified potential positive and negative – direct, indirect, induced and
cumulative – impacts associated with the Project. The identification of impacts was informed by the
baseline study and the public consultation process. The findings of other specialist impact
assessment studies have been reviewed and used to inform the impact assessment component of
the SIA where appropriate.
Feedback from stakeholders, primarily received during the Scoping Phase was used to inform the
impact assessment.
The identified impacts will be assessed using the methodology provided by GCI, as outlined in
Section 1.4, below.
1.4 IMPACT ASSESSMENT METHODOLOGY
This section provides an overview of the assessment methodology used to assess the
environmental and social impacts associated with the construction, operation phases of the project.
The identified impacts presented within this section have been assessed according to this
methodology which includes a description of the impact, subsequent assessment, mitigation
measures and finally the residual impact after the application of these mitigation measures.
Impact identification and assessment starts with scoping. Interactions with the potential for
significant effects were subjected to a detailed impact assessment. The principal ESIA steps are
summarised in Figure 1.1 and comprise the following.
• Impact prediction: to determine what could potentially happen to resources or receptors as
a consequence of the Project and its associated activities.
• Impact evaluation: to evaluate the significance of the predicted impacts by considering the
magnitude and likelihood of occurrence, and the sensitivity, value and/or importance of the
affected resource or receptor.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 9
• Mitigation and enhancement: to identify appropriate and justified measures to mitigate
negative impacts and enhance positive impacts.
• Residual impact evaluation: to evaluate the significance of impacts assuming effective
implementation of mitigation and enhancement measures.
Figure 1.1 Environmental Impact Assessment Process
1.4.1 Impact Prediction
Prediction of impacts is an objective process to determine what is likely to happen to the
environment as a consequence of the Project and associated activities. From the potentially
significant interactions identified in scoping, the impacts to the various resources/receptors are
elaborated and evaluated. The diverse range of potential impacts considered in the IA process
typically results in a wide range of prediction methods being used, including quantitative, semi-
quantitative and qualitative techniques.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 10
1.4.2 Impact Evaluation
Environmental impacts arise as a result of Project activities either interacting with environmental
receptors directly or causing changes to the existing environment such that an indirect effect occurs.
Impacts may be described and quantified in a number of ways.
Nature of Impact
The nature of an impact is defined as the type of change from baseline conditions or the
introduction of a new desirable or undesirable factor. The nature of an impact is described as
being either positive or negative.
Type of Impact
Impact type indicates the relationship of the impact to the Project activity in terms of cause and
effect, as either:
• Direct impact resulting from the direct interaction between a project activity and the receiving
environment.
• Indirect impact between the proposed activity and the environment as a result of subsequent
interactions within the environment.
• Induced impact resulting from other non-project activities that happen as a consequence of
the Project activities.
• Cumulative impacts that act together with other impacts (including those from concurrent or
planned future third party activities) to affect the same resources and/or receptors as the
Project.
Extent of Impact
Impact extent relates to the geographic reach of the impact and is described in Table 1.1
Table 1.1 : Determining Extent
Duration of Impact
Impact duration refers to the time period over which a resource or receptor will be affected
described in Table 1.2.
Designation Description
Local
Impact would affect local resources or receptors and would be
restricted to a single community (ie impacts in the footprint of project
activities and the immediate adjacent area).
Regional Impact would affect regional resources or receptors and would be
experienced at a regional scale for example at a state level.
National Impact would affect resources or receptors throughout the country.
International International impact would affect internationally important resources or
receptors outside of the country.
Trans-boundary Impact would be those that are experienced in one country as a result of
activities in another country.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 11
Table 1.2 : Determining Duration
Designation Description
Temporary
Impacts would last for a short duration, are reversible and intermittent or
occasional in nature. The resource or receptor would return to the
previous state when the effect ceases or after a short period of recovery,
typically less than one year.
Short-term
Impacts would last for the life of the proposed short term activity activities
and a limited short period thereafter, typically one to four years. The
impact would cease when the effect ceases following a short period of
recovery.
Long-term Impacts would continue for an extended period of time after the Project
activity, for example between five and 15 years.
Permanent
Impacts would occur during the development of the Project and cause a
permanent change in the affected receptor or resource that endures
substantially beyond the Project lifetime.
Scale of Impact
Impact scale relates to the size of the impact, in a social context it typically relates to the degree
of change experienced by receptors, either at an individual or household level.
Table 1.3 Determining Scale
Designation Description
Small Impact would result in a subtle change in baseline conditions.
Medium Impact would result in some change to baseline conditions within a
community, but would not dominate over baseline conditions.
Large
Impact would result in a fundamental change in the way of life of
receptors, or to the nature of relationships within a community, or to the
livelihood patterns within a community.
Frequency of Impact
Impact frequency relates to the constancy or periodicity of the impact. This could be a once off
occurrence or continuous. The designations used in the Impact Assessment are as follows:
• Constant a permanent occurrence
• Often occurs at least once a month
• Occasional occurs at least once every six months
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 12
• Rare occurs about once a year
• One-off could occur, but reasonably expected to occur only once.
Magnitude of Impact
Once an impact’s characteristics are defined, the next step in the impact assessment phase is to
assign each impact a ‘magnitude’. Magnitude is typically a function of some combination (depending
on the resource/receptor in question) of the following impact characteristics:
• Extent;
• Duration;
• Scale; and
• Frequency.
Additionally, for unplanned events only, magnitude incorporates the likelihood factor. An unplanned
event is defined as ‘a reasonably foreseeable event that is not planned to occur as part of the Project,
but which may conceivably occur as a result of Project activities (eg accidents), even with a low
probability’. These differ from planned events which are activities which are expected to occur as part
of the normal Project development and operation. The likelihood of an unplanned event occurring is
designated using a qualitative scale:
• Unlikely events are unlikely but may occur at some time during normal operating
conditions.
• Likely events are likely to occur at some time during normal operating conditions.
• Definite events will occur during normal operating conditions (ie, it is essentially
inevitable).
Magnitude essentially describes the intensity of the change that is predicted to occur in the
resource/receptor as a result of the impact. Magnitude designations themselves are universally
consistent, but the descriptions for these designations vary on a resource/receptor-by-
resource/receptor basis. The magnitude designations are described in Table 1.4.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 13
Table 1.4 Describing Magnitude
Vulnerability The vulnerability of receptors is underpinned by a low existing level of livelihoods assets (such as
health or education) or inadequate access to structures and processes to protect or improve
livelihoods. It is important to understand the vulnerability context as it will affect the ability of social
receptors to adapt to socio-economic/cultural or bio-physical changes. A higher level of vulnerability
can result in increased susceptibility to negative impacts or a limited ability to take advantage of
positive impacts. A project may also exacerbate existing vulnerabilities if the status of individuals and
communities and their coping mechanisms are not adequately understood or considered. The
vulnerability designations are described in Table 1.5.
Table 1.5 Describing Vulnerability
Receptor
Vulnerability Description
Low Minimal vulnerability; consequently with a high ability to adapt to changes
brought by the Project and opportunities associated with it.
Medium
Some, but few areas of vulnerability; still retaining an ability to at least in
part adapt to change brought by the Project and opportunities associated
with it.
High
Profound or multiple levels of vulnerability that undGCIine the ability to
adapt to changes brought by the Project and opportunities associated with
it.
Evaluation of Significance
Once magnitude of impact and sensitivity/vulnerability/importance of resource/receptor have been
characterised, the significance can be assigned for each impact.
Designation Description
Positive
In the case of positive impacts, no intensity is assigned unless there is
ample data to support a more robust characterisation. It is sufficient to
indicate that the Project will result in a positive impact, without
characterising the exact degree of positive change likely to occur
Negligible A difference from baseline conditions is marginally perceptible.
Small
Perceptible difference from baseline conditions. Tendency is that impact
is local, rare and affects a small proportion of households and is of a
short duration.
Medium
Clearly evident difference from baseline conditions. Tendency is that
impact affects a substantial area or number of people and/or is of
medium duration. Frequency may be occasional and impact may be
regional in scale.
Large
Change dominates over baseline conditions. Affects the majority of the
area or population in the area of influence and/or persists over many
years. The impact may be experienced over a regional or national area.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 14
For the purposes of this ESIA, the following definition of significance has been adopted:
An impact is significant if, in isolation or in combination with other impacts, it should, in the judgement
of the EIA team, be taken into account in the decision-making process, including the identification of
mitigation measures and consenting conditions.
In assessing whether an impact is significant, reference has been made, where appropriate, to
criteria on which the evaluation is based. These may include legal standards, policy guidance or
accepted practice and past experience.
The significance of impacts is then devised from a combination of the vulnerability of the receptor
and the magnitude of impact. A convenient way of representing the overall significance is through a
matrix of magnitude versus sensitivity or vulnerability/value as shown in Table 1.6.
Table 1.6 Overall Significance Criteria for Environmental Impacts in the ESIA
For this assessment, five impact significance categories have been applied:
• Positive impact;
• Negligible impact;
• Minor significance;
• Moderate significance; and
• Major significance.
These general definitions of Categories of Impact Significance have been applied to the
assessment of social and environmental impacts for the Project as shown in Table 1.7.
Table 1.7 Categories of Impact Significance
Positive
Positive impacts provide resources or receptors, most often people, with positive benefits. It is
noted that concepts of equity need to be considered in assessing the overall positive nature of
some impacts such as economic benefits, or opportunities for employment.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 15
Negligible
Negligible impacts are where a resource or receptor (including people) will not be affected in
any way by a particular activity or the predicted effect is deemed to be ‘negligible’ or
‘imperceptible’ or is indistinguishable from natural background variations.
Minor
An impact of minor significance (‘Minor impact’) is one where an effect will be experienced, but
the impact magnitude is sufficiently small (with or without mitigation) and well within accepted
standards, and/or the receptor is of low sensitivity/value.
Moderate
An impact of moderate significance (‘Moderate impact’) is one within accepted limits and
standards. Moderate impacts may cover a broad range, from a threshold below which the
impact is minor, up to a level that might be just short of breaching a legal limit. Clearly to
design an activity so that its effects only just avoid breaking a law and/or cause a major impact
is not best practice. The emphasis for moderate impacts is therefore on demonstrating that the
impact has been reduced to a level that is ALARP. This does not necessarily mean that
‘Moderate’ impacts have to be reduced to ‘Minor’ impacts, but that moderate impacts are being
managed effectively and efficiently.
Major
An impact of major significance (‘Major impact’) is one where an accepted limit or standard
may be exceeded, or large magnitude impacts occur to highly valued/sensitive
resource/receptors. An aim of EIA is to get to a position where the Project does not have any
major residual impacts, certainly not ones that would endure into the long-term or extend over
a large area. However, for some aspects there may be major residual impacts after all
practicable mitigation options have been exhausted (ie ALARP has been applied). It is then the
function of regulators and stakeholders to weigh such negative factors against the positive
ones such as employment, in coming to a decision on the Project.
Mitigation and Enhancement
Mitigation and/or enhancement measures are identified for significant impacts identified during the
impact evaluation stage. These measures represent a feature, procedure or other action that the
Project commits to implement to avoid or reduce the magnitude of an adverse impact, or to enhance
the magnitude of a positive impact. As such, these should avoid unnecessary damage to the
environment; safeguard valued or finite resources, natural areas, habitats and ecosystems; and
protect humans and their associated social environments.
Residual Impact Evaluation
The residual impacts are described in terms of their significance and the nature of the impact is
qualified, where appropriate, on the basis of the descriptors, within each of the impact assessment
sections presented within this Chapter. The criteria take into account the degree to which impacts can
be quantified and compared with accepted limits and standards or a combination of the magnitude of
change caused by the Project in combination with the value/sensitivity of the receptor/resource that is
impacted.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 16
Dealing with Uncertainty in the Assessment of Impacts
The impact assessment process deals with the future and there is inevitably uncertainty that arises
between the predictions made and what will actually happen during the course of the Project.
However, the sources of impacts due to plant processes & operations are well-understood and the
areas of interaction with the receiving environment have been well-characterised by past projects.
Impact predictions have, wherever practicable, been made using available data, but where significant
uncertainty remains, this is outlined in the text. Where the vulnerability of a resource and impact
magnitude is not supported by quantitative data, this is reported accordingly and qualitative
information, professional experience and a conservative approach is used instead to judge whether a
significant impact is likely to occur or not.
1.5 ASSUMPTIONS AND LIMITATIONS
Detailed socio-economic data were collected within 10 km radius of the proposed Project site.
Preliminary information was collected during field investigation followed by secondary data from the
census of India 2011.
• It is assumed the Project information provided is accurate and design is compliant with
Central & state regulations.
• It is assumed that the feasibility of the Project has been assessed by the proponent.
• It is assumed all stipulated mitigation measures will be implemented to avoid and reduce the
respective negative impacts and enhance positive impacts.
1.6 SPECIALIST DETAILS
Gunesh Deosthali is a member within GCI’s Impact Assessment and Planning Team based in Pune
and engaged more than 20+ years experience in on Social Impact Assessment where he has been
responsible for planning and getting the primary and secondary information gathering, baseline
compilation, impact identification/ assessment, and formulation of mitigation and management
measures. Gunesh has extensive experience in industrial & infra sectors. Through his experience in
the sectors, Gunesh has developed a deep understanding of the impacts (both adverse and
beneficial) integrated steel plant project can have on surrounding communities. He is familiar with
the requirements and implementation of MoEFCC requirements. Gunesh has worked on project with
complex social impacts, with highly sensitive affected communities.
He has worked on projects which have required multiple stakeholder (including multiple localities and
individuals) engagement and collation of primary data, where he has been instrumental in designing
and implementing socio-economic primary data collection tools including household surveys, focus
group discussion and one-to-one interview questionnaires. In addition, Gunesh has undertaken
several Environmental Impact Assessments (EIAs) at existing facilities and green field sites in India .
His responsibilities included project management, integration of specialist studies and public
participation activities
2. PROJECT DESCRIPTION
The description of the Project that follows is focus on aspects of the project description relevant to
the assessment of socio-economic impacts. A detailed project description can be found in Chapter 3
of the EIA.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 17
2.1 PROJECT BACKGROUND
MASPL has proposed to set up a green field Rolling Mill (Wire Rod cum Bar Mill) of 700,000 Ton /
Year capacity which is backward integration of integrated steel plant
2.1.1 Project Location
The proposed project site is located at Village- Kanakapur, Taluka and District- Koppal, State-
Karnataka. The nearest Highway is NH-63 (adjacent to Plant) and NH-13 (13.5 Km, East). The
nearest cities are Koppal and Hospet, which are situated at a distance of 11 km and 22 km in west
and east directions respectively. The nearest Railway station is Ginigera at a distance of 1.7 km,
NW.
2.1.2 Land Ownership and Acquisition
There are 47 families having their land parcels on which the proposed integrated steel plant site will be
located are detailed in Table 2.1.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 18
Table 1.1 Details of Land Parcels
2.2 PROJECT COMPONENTS
The key project components considered in this EIA are as follows:
• Rolling Mill
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 19
Total Land required for the proposed Integrated Steel Plant project is 300 acre/1,213,800 m2. Out of which
the land required for the Rolling Mill (Wire Rod cum Bar Mill) and Finishing Facility is 101 Acres 21Gunthas
(4,10,568 m2) which is under possession of MASPL.
Table 2.2.
Table 1.2 Project components general surface areas and lengths
Sr. No. Description Area (m2) Area (Acre) Percentage
(%)
1 Plant Area including
Storage Area
121380 30 29
2 Utilities 4046 1 1
3 Parking Area 4046 1 1
4 Administrative Building
/Restroom/Canteen/Offices
4046 1 1
5 Green belt & Green Area 141610 35 35
6 Roads & Drainage 32368 8 8
7 Rain Water Harvesting &
Water Storage
48552 12 12
8 Softener, STP & ETP 4046 1 1
9 Open Area 48552 12 12
Total 4,08,646 101 100
Table 1.3 Access routes and roads
The Project has accounted for certain road works, described below, deemed necessary for safety and
compliance with regional legislative requirements. Permissions have not yet been sought for the
proposed road works, the costs of which will be borne by the project and executed according to local
regulations, requirements and guidelines.
Concrete-paved roads will be constructed early after commencement of construction works and will
serve to carry heavy load traffic (mobile cranes, multi axle heavy equipment trailers, cement delivery
trucks, etc.) during the early stages of construction.
All concreted roads will play an important role for rainwater harvesting, in addition to the concreted
lay-down areas. The site’s natural slope is towards the south where the raw water storage tanks will
be situated. The east-west thoroughfares (‘streets’) will channel rainwater into the rain-water drains
of the thoroughfares (‘avenues’). Rainwater will run to the bulk water storage tanks.
Approach to the Plant
For road safety considerations and in light of the increased traffic (particularly during construction
phase) the provincial road leading past the two integrated steel plant entrances will wide enough to
carry the traffic.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 20
For the office and administration gate a wide entrance (12 m) and a 12 m radius bend into the plant
site and offices from the access road to the gate house is planned.
2.3 PROJECT PHASING AND SCHEDULE
2.3.1 Construction Phase
The proposed project is Rolling Mill if 700,000 Ton /Annum capacity.
During peak construction activity, it is expected that up to approximately 1000 workers will be directly
employed. Most of this workforce will be employed by the engineering, procurement and construction
(EPC) contractor and will consist in semi-skilled to skilled workforce. The breakdown of skills required
during the construction phase will be as follows:
• Skilled labour: 400 persons
• Semi-skilled labour: 300 persons
• Unskilled labour: 300 persons
It is understood that there will be no worker accommodation on site during construction. The unskilled
workforce will, as far as possible be employed from the local community, reducing the need to the
provision of accommodation. The skilled and semi-skilled workforce from outside the area will be
housed within Area Local Body.
Traffic Requirements during the Construction Phase
Bulk cement and concrete aggregate, tons re-bar steel, and tons equipment and structural steel will
need to be transported to the construction site.
It is envisaged that construction staff, up to a maximum of 1000 persons, would be bussed to site in
mini busses and pass through this gate; busses per day, twice a day. Light vehicle traffic due to
construction will start by vehicles and increase rapidly where it will remain for the bulk of the
construction period.
There will be an expected bulk gravel, bulk sand, and bulk cement respectively for the duration of
the construction phase 1, after which it tails off rapidly.
The heavy equipment will be delivered via truck. This will involve some abnormal loads being moved
on the roads during this time
Water Requirements during the Construction Phase
During the construction phase the main water requirement will be for the concrete batching plant.
Water will be required for the concrete batching. Additional water will be required for:
• Off-site dust control: Post treatment recycled water will be used for dust control on
unsurfaced roads where required during high traffic periods and during construction.
• Domestic purposes by on site workers: Maximum water usage during peak construction period
will be the labour and constriction curing.
• Construction and on-site dust control: Water is required for the manufacture of concrete during
construction. The integrated steel plant will require concrete for foundations, road works, hard
standing and other site works.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 21
2.3.2 Operation Phase
The integrated steel plant will be operated on a 24 hour, 7 days a week basis.
Employment during the Operation Phase
The number of workers on site during operations will be about 730. These will include plant
management and maintenance staff, skilled mechanical and electrical technicians, drivers, medical,
quality control, and cleaning staff and a number of experienced plant operators who will operate and
maintain the plant, and who are expected to be a mix of expatriate and local staff.
As the plant will operate 24 hours a day, three full-time shifts will be created per day, and the
breakdown of the skills required will be as follows:
• Skilled labour
• Semi-skilled labour and
• Unskilled labour:
Table 1.4 Estimated Employment Positions Available During Operation
Position Number of Positions Available
Admin 5
Security 10
Warehouse and Stores 50
Medical 2
Plant Control 50
Engineers 93
Technicians 90
Skilled 200
Unskilled 200
Tuition and Training 5
Quality Control, Water 5
Canteen 5
Total 715
It is understood that there will be no worker accommodation on site during operation. The unskilled
workforce will, as far as possible be employed from the local community, reducing the need to the
provision of accommodation. The skilled and semi-skilled workforce from outside the area will be
housed near to the site.
Traffic Requirements during the Operation Phase
During commercial operations there will be some traffic bringing supplies and spares to the integrated
steel plant. This will increase during shutdowns and periods of major maintenance.
Maintenance activities will be undertaken by an Operations and Maintenance (O&M) contractor.
Water Requirements during the Operation Phase
Water during operation will be required for the following activities:
Total water requirement of the project will be 1525 M3/Day. Source of Water is from downstream of
Tungabhadra Reservoir. Tungabhadra River is a perennial river and caters to the need of irrigation
and potable water. Water from downstream of reservoir will be drawn within the sanctioned capacity
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 22
of 18 MLD by the Government of Karnataka’s letter no. WRD.15/MTP/2013 dated 22 December
2015.
Liquid Effluents in the proposed Project:
1) Backwash from Softener: During Rolling, water is used for cooling of equipment, hot
bars and rolls. Water has to be soft so as to avoid deposit in the water pipes. MAPSL
will use water from the downstream of TB Dam. Depending on the hardness some
quantity of water (make-up water) will need to be softened.
Backwash from the softening plant is categorized as effluent. Quantity of backwash
water is estimated to be about 10 cum/Day. This water is collected in a pit and treated
for neutralization. After treatment, water becomes neutral (PH-7-8) and sent to the
collecting tank for dilution and further used for gardening and dust suppression
purpose.
2) Blowdown from Water Supply system: When the recirculation water becomes hard,
some quantity is removed from the system and fresh soft water is added. This is called
Blowdown. Blowdown water is neutral (PH 7-8) and is directly used for dust
suppression and gardening in the plant. Thus, Zero water Discharge is achieved.
3) Discharge from Canteen & toilets:
The waste water from the Canteen and toilets are treated in STP of capacity 25 KLD
and the water after treatment in STP is sent to the Effluent Treatment Tankand
treated with lime. After treatment, water becomes neutral (PH-7-8) and used for
gardening purpose and dust suppression purpose.
4) Scale Pit Water: The water from the various rolling processes shall be collected in the
Scale Pit. The water in the Scale pit contains oil and grease. The Oil Skimmer is
required to be installed for removing floating Oil and grease from contaminated
Water consisting of Oil, Grease and shop scale. Design of oil skimmer depends on the
laws of gravity, surface tension and principle of adhesion in order to function. Oil
skimmer works because they are made of materials to which oil is more likely to stick
than the fluid it is floating on.
The skimmer shall be installed near the scale pit. The Oil Skimmer shall be made from
corrosion resistant material. The special type of rotating endless tubes floats on the
liquid surface for removing oil/grease. The tube moves through the skimmer pulley
installed above ground level and the oil is wiped from the tube at the top with the
help of special wiper pulley. The skimmed oil shall be collected in a container through
a hose connector attached with the skimmer and the reclaimed oil shall be sold.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 23
After skimming of the oil and grease the water is send to the settling tank and the
water from the settling tank after filtration again reused in the cooling Tower. The
backwash collected from the filter is then send to the thickener and coagulants are
added for separating the solid and liquid particles and thereafter the water overflow
of the thickener is sent to the Scale pit for reusing. The residual from the thickener is
collected and dried to make in form of Metallic cake which is sold to the local parties.
In the proposed project approximately 25 KLD Domestic and Canteen waste will be generated and
it will be treated in the STP of Capacity 25KLD.
30 KLD Effluent is generated which shall be treated in Effluent Treatment Tank and then reused
for gardening and dust suppression purpose. Thus there will be no effluent released from the
Rolling Mill and hence MASPL will adhere to “Zero Liquid Discharge” for this proposed project.
Table 1.2 Water Consumption Details
Sr. No. Purpose (Total input) Total Water Consumption in
Rolling Mill (KLD)
1 Make Up Water for Cooling Tower for Contact
Water
1200
2 Make Up Water for Cooling Tower for Non-
Contact Water
240
3 Domestic &Canteen Purpose 25
5 Filter Backwash& Softening regeneration 60
6 TOTAL 1525
The Project will not relay on reservoir for water but also planning to harvest the rain water
3. PROJECT MOTIVATION
When considering an application submitted under the EIA Regulations, the relevant competent
authority must take a number of factors into consideration, including the need for, and desirability
of, the activity.
The need and desirability of this project is discussed below including strategic plans, frameworks and
policies applicable to the area and project.
Need and Desirability
The Indian economy is rapidly growing and is emerging as the second largest developing economy of
the world, which has a great impact on domestic consumption of steel as well as export potential to
other countries. As a result of this, the demand for iron & steel remains extremely good, which would
continue for next 10 years if not less, since the per capita consumption of steel in India is still very low
compared to other developed countries? For rapid development of economy and infrastructure of the
country, it is necessary to increase the production of steel within the country.
The Indian steel industry is very modern with state-of-the-art steel mills. It has always strived for
continuous modernisation and up-gradation of older plants and higher energy efficiency levels.
As per the report of the Working Group on Steel for the 12th Five Year Plan, there exist many factors
which carry the potential of raising the per capita steel consumption in the country. These include
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 24
among others, an estimated infrastructure investment of nearly a trillion dollars, a projected growth of
manufacturing from current 8% to 11- 12%, increase in urban population to 600 million by 2030 from
the current level of 400 million.
At the time of its release, the National Steel Policy 2005 had envisaged steel production to reach 110
million tonnes by 2019-20. However, based on the assessment of the current ongoing projects, both in
greenfield and brownfield, the Working Group on Steel for the 12th Five Year Plan has projected that
domestic crude steel capacity in the county is likely to be 140 million tonnes by 2016-17 and has the
potential to reach 149 million tonnes, if all requirements are adequately met. Thus, the project will be a
part of the vision.
4. SOCIO-ECONOMIC BASELINE
This section describes the socio-economic environment in which the Project is situated. The
description provided in this section is based on publicly available and secondary information, as well
as primary data collected for the Project.
4.1 AREA OF INFLUENCE (AOI)
The socio-economic baseline description is focused on local level, i.e. within the Area Local Body,
situated in the proposed project site. This is because it is expected that although the proposed Project
will result in macro-economic benefits at a national level, the primary socio-economic impacts of the
Project will be experienced at a district and local level.
The socio-economic area of influence has been divided into the Direct Area of Influence and the
Indirect Area of Influence, these are described below.
4.1.1 Area of Direct Influence
The Area of Direct Influence, ADI, includes the Project footprint and related facilities as well as the
associated effects of the Project on the receiving environment. This encompasses:
• Integrated steel Plant site;
• Roads
In the context of this study, the ADI further includes areas around the site likely to be affected by the
Project activities during the pre-construction, construction and operation phases. The effects can be
positive or negative, short or long term or permanent, as well as direct and in-direct. These areas
include the settlements located within close proximity to the Project Site
4.1.2 Indirect Area of Influence
The Area of Indirect Influence, AII, includes areas within a wider radius of the Project Site, which may
be affected by the Project, this includes, although to a lesser extent
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 25
Figure 4.1 Google Map of Project Site
Co-ordinates of the side corner of the project site:
Corner Points Co-ordinates
A 15°20'7.84"N, 76°15'22.04"E
B 15°20'8.79"N, 76°15'32.49"E
C 15°19'38.56"N, 76°15'38.56"E
D 15°19'39.05"N, 76°15'26.93"E
E 15°19'52.02"N, 76°15'34.48"E
F 15°19'59.06"N, 76°15'20.01"E
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 26
4.2 ADMINISTRATIVE STRUCTURE
Figure 4.2 Administrative Structure
4.3 SITE SETTING AND LANDUSE
4.3.1 Land-use of the Project Site
The basic purpose of land use pattern and classification in an EIA study is to identify the manner in which
different parts of land in an area are being utilized or not utilized. Remote sensing data provides reliable
accurate baseline information for land use mapping, as it is a rapid method of acquiring up-to-date
information of over a large geological area.
A systematic digital image interpretation approach was used to delineate the land use classes. The
present study was focused on demarcating boundaries of different land use/land cover units from an
analysis of different types of colour registrations of land use/land cover units from satellite imagery. Data
Used in the land use map preparation is the satellite Imagery of Indian Remote Sensing Satellite (IRS- ID
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 27
, sensor P6, LISS III) of 24 m resolution. The Swath of the imagery is 141 Km x 141 Km. Band used are
2, 3 4 and 5. LANDSAT imagery of 30 meter resolution and 185 x 185 km swath is also used for the
comparative and overall analysis of the area. LISS III imagery and LANDSAT 4-5 TM imagery were used
for the complete coverage of the study area. Band used are 2, 3 and 4.
Table 4.1 Land Use Distribution of the Study Area (10 km Radius)
LULC Class Area in Ha. % of Area
Crop Land 17038.12 54.23%
Reservoir 2869.30 9.13%
Settlement 740.50 2.36%
Industry 1508.01 4.80%
Quary 212.31 0.68%
Land with Scrub 2468.46 7.86%
Fallow Land 2787.23 8.87%
Urban Built Up 290.93 0.93%
Stony Waste 1324.03 4.21%
Pond/Lake 220.32 0.70%
Mixed Built Up 260.02 0.83%
Hill Forest 1696.27 5.40%
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 28
Figure 4.3 Land Use map at Project Site
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 29
4.4 DEMOGRAPHIC PROFILE
Demography
The study there is 19 villages in the study area. The demographic pattern of all the settlements as per
2011 census is given in Table 4.2
Sex Ratio
Sex ratio is number of females per 1000 males. In the study area the sex ratio is 974.44. As per the
Census 2011 the male population is 50.77 % while female population is 49.23 % of the total population.
Table 4.2 Village-wise details of Population
S.N. Name No of Households
Total Population
Person
Total Population
Male
Total Population
Female
Sex ratio
1 Agalkera 958 4895 2429 2466 1015.23
2 Allanagar 257 1212 627 585 933.01
3 Bahaddurbandi 504 2872 1505 1367 908.31
4 Basapur 395 1968 976 992 1016.39
5 Bevinhalli 460 2315 1173 1142 973.57
6 Budugumpa 1079 5641 2748 2893 1052.77
7 Ginigera 1863 8449 4509 3940 873.81
8 Guldahalli 521 2752 1390 1362 979.86
9 Halahalli 282 1624 817 807 987.76
10 Hireboganhal 471 2411 1271 1140 896.93
11 Hitnal 1113 5608 2820 2788 988.65
12 Indargi 972 5594 2852 2742 961.43
13 Kanakapura 171 1063 521 542 1040.31
14 Kinhal 1995 9802 4936 4866 985.82
15 Koppal (Rural) 3806 18988 9629 9359 971.96
16 Kunikera 577 3471 1781 1690 948.91
17 Lachankera 574 3282 1675 1607 959.40
18 Shivapur 851 4139 2058 2081 1011.18
19 Tankankal 238 1322 658 664 1009.12
Total 17087 87408 44375 43033 974.44
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 30
.
Figure 4.4 Demographic Pattern
Social Distribution: Out of total population, 21.68 % is SC population and 7.69 % is ST Population.
Table 4.3 Social Distribution
Name Total
Population Person
Scheduled Castes
population Person
Scheduled Castes
population Male
Scheduled Castes
population Female
Scheduled Tribes
population Person
Scheduled Tribes
population Male
Scheduled Tribes
population Female
Agalkera 4895 1303 630 673 238 123 115
Allanagar 1212 174 76 98 43 20 23
Bahaddurbandi 2872 209 105 104 159 84 75
Basapur 1968 636 321 315 418 214 204
Bevinhalli 2315 226 113 113 178 92 86
Budugumpa 5641 1309 634 675 492 223 269
Ginigera 8449 2346 1190 1156 532 280 252
Guldahalli 2752 513 260 253 208 101 107
Halahalli 1624 823 420 403 13 7 6
Hireboganhal 2411 313 170 143 42 26 16
Hitnal 5608 820 420 400 435 213 222
Indargi 5594 1207 629 578 829 418 411
Kanakapura 1063 95 53 42 0 0 0
Kinhal 9802 1276 633 643 664 336 328
Koppal (Rural) 18988 3652 1915 1737 648 311 337
Kunikera 3471 2010 1012 998 217 109 108
Lachankera 3282 705 343 362 848 434 414
Shivapur 4139 1157 576 581 720 359 361
Tankankal 1322 175 97 78 37 20 17
Total 87408 18949 9597 9352 6721 3370 3351
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 31
Figure 4.5 Social Pattern
Literacy The overall percentage of literate in the area is 59.69 % and percentage of illiterate population is 40.31.
Table 4.4 Literacy Rate
Name Total Population
Person
Literates Population
Person
Literates Population
Male
Literates Population
Female
Illiterate Persons
Illiterate Male
Illiterate Female
Agalkera 4895 2883 1661 1222 2012 768 1244
Allanagar 1212 703 403 300 509 224 285
Bahaddurbandi 2872 1707 1025 682 1165 480 685
Basapur 1968 953 524 429 1015 452 563
Bevinhalli 2315 1370 801 569 945 372 573
Budugumpa 5641 3061 1778 1283 2580 970 1610
Ginigera 8449 5255 3232 2023 3194 1277 1917
Guldahalli 2752 1544 902 642 1208 488 720
Halahalli 1624 1010 564 446 614 253 361
Hireboganhal 2411 1457 846 611 954 425 529
Hitnal 5608 3343 1934 1409 2265 886 1379
Indargi 5594 2536 1559 977 3058 1293 1765
Kanakapura 1063 460 272 188 603 249 354
Kinhal 9802 6346 3609 2737 3456 1327 2129
Koppal (Rural) 18988 13229 7311 5918 5759 2318 3441
Kunikera 3471 1644 1047 597 1827 734 1093
Lachankera 3282 1931 1176 755 1351 499 852
Shivapur 4139 2153 1243 910 1986 815 1171
Tankankal 1322 586 339 247 736 319 417
Total 87408 52171 30226 21945 35237 14149 21088
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 32
Figure 4.6 Literacy Rate
Employment Scenario
The overall percentage of workers in the area is 45.46 %.
Table 4.5 Employment Scenario
Name Total Popula
tion Person
Total Worke
r Popula
tion Person
Total Worker Populat
ion Male
Total Worker Populat
ion Female
Main Working Populati
on Person
Main Cultivat
or Populat
ion Person
Main Agricult
ural Labour
ers Populat
ion Person
Main Household Industries
Population Perso
n
Main Other Workers
Population Perso
n
Margina
l Worker Population Person
Non Working Population Person
Agalkera
4895 2076 1371 705 2014 446 842 27 699 62 2819
Allanagar
1212 575 364 211 414 76 43 12 283 161 637
Bahaddurban
di
2872 1340 780 560 1234 202 373 21 638 106 1532
Basapur
1968 821 556 265 675 189 329 0 157 146 1147
Bevinhalli
2315 1066 666 400 917 256 60 8 593 149 1249
Budugumpa
5641 2509 1499 1010 2256 981 922 21 332 253 3132
Ginigera
8449 3477 2653 824 2967 379 461 65 2062 510 4972
Guldahalli
2752 1310 780 530 1210 226 453 44 487 100 1442
Halahalli
1624 895 479 416 520 234 128 90 68 375 729
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 33
Hireboganhal
2411 1262 709 553 604 206 130 17 251 658 1149
Hitnal 5608 2409 1527 882 1861 252 886 131 592 548 3199
Indargi 5594 3000 1603 1397 2677 1000 1085 29 563 323 2594
Kanakapura
1063 575 297 278 224 179 18 2 25 351 488
Kinhal 9802 4549 2758 1791 4046 466 1045 365 2170 503 5253
Koppal (Rural)
18988 7618 5297 2321 6871 321 399 456 5695 747 11370
Kunikera
3471 1718 956 762 1362 508 609 31 214 356 1753
Lachankera
3282 1880 975 905 1682 143 1361 15 163 198 1402
Shivapur
4139 2041 1212 829 1215 243 595 31 346 826 2098
Tankankal
1322 617 352 265 616 358 89 20 149 1 705
Total 87408 39738 24834 14904 33365 6665 9828 1385 15487 6373
47670
4.5 LIVELIHOODS AND ECONOMY
The growth of GSDP at constant prices (year-on-year) slightly decreased from 7.2% in 2013-14 to 7.0%
in 2014-15, mainly attributable to the decline in the growth of agriculture from 9.4% in 2013-14 to 4.5%
in 2014-15. However, the growth of industry and services slightly increased from 4.2% and 8.0% in
2013-14 to 4.4% and 8.9% during 2014- 15 respectively. The State economy showed reviving trends
with anticipated growth rate of 6.1% in 2012-13, 7.2% in 2013-14 and 7.0% during 2014-15.
Karnataka’s Gross State Domestic Product (GSDP) at constant (2004-05) prices is expected to grow at
7.0% and reach Rs. 344106 crore in 2014-15. ‘Railways’, ‘Storage’, ‘Trade, Hotels and Restaurants’,
‘Transport by other means’, ‘Real Estate, Ownership of dwellings and Business Services’,
‘Communication’, ‘Public Administration’ and ‘Other Services’ have all contributed to the growth of
services sector (8.9%). Manufacturing sector is expected to grow at 3.2%. The expected growth rate of
‘Electricity, Gas and Water Supply’ is around 8.7%. ‘Agriculture and Livestock’ (4.3%) is the main
contributor to the growth rate achieved in the Agriculture sector (4.5%).
Tourism is one of the fastest growing sectors of Karnataka economy with its contribution to the
country's gross domestic product (GDP) of the state and makes a significant contribution to economic
development and jobs, thus being the most important growth sector in the state.
Further, eco-tourism and agri-tourism are recognized as ways of supplementing the income of farmers.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 34
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 35
4.6 SOCIAL INFRASTRUCTURE AND SERVICES
4.6.1 Connectivity, Transport and Communication
Transport activities included bus and tour-bus services, taxis, school buses, travel agents, the hiring of
transport equipment and telephone and radio-communication services.
• Mangaluru-Sholapur (Maharashtra) NH 13 passes through Kustagi town.
• Ankola-Gooty NH 63 passes through Koppal town.
• Bengaluru-Ballari-Gadag-Hubballi Railway line passes through Koppal town.
• Goods transport facility available from Koppal and Munirabad stations.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 36
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 37
Education:
Educational Institutions in Koppal District
Healthcare:
Healthcare in Koppal District
4.6.2 Water
The only and important river in this district is Tungabhadra river, which form the Southern boundary-of the
district. It has been associated from time immemorial with regional cultural and religious activities and has
several famous shrines on its banks. In the historical and cultural developments of the country, the river
had played a vital role. Legend and tradition have sanctified these perennial sources of water, which has
given an immense impetus to civilization and prosperity of the land.
4.6.3 Housing
The people in the village of the district live in house built of mud with the mud roofing. The walls are
raised by heaping mud layer after layer and leveling the sides with a wooden leveller. In the eastern parts
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 38
of the district palm leaves and stems are used for roofing and are found to be quite useful. Presently,
constructions of concrete roofing house with brick walls are taking place of mud roofing. Few rich people
of the village are having modem type of constructions.
Houses in the rural areas are built with scant respect for sanitation and hygiene; more of them are ill-
ventilated and often lack elementary amenities like drains for waste water. Cattle live in enclosures very
near to the house and add to the insanitation of the houses. Fields round about the village are used for
calls of nature and in many of the house, there are no latrines. The summer season witnesses a period of
water scarcity in many villages.
IMPACT ASSESSMENT
This section presents the potential socio-economic impacts associated with the Project. The potential
impacts have been assessed using the impact assessment methodology provided in Section 1.4.
The following potential impacts are discussed further below:
• Employment creation, skills enhancement and local business opportunities.
• Impacts on community health and safety, including:
• Impacts associated with the presence of the workforce and jobseekers;
• Impacts associated with pressure on social infrastructure;
• Impact on human health due to air emissions and dust generation; o Nuisance due to noise,
dust and traffic on sense of place;
• Worker health and safety and rights; and
• Cumulative impacts.
5. IMPACT ASSESSMENT
5.1 EMPLOYMENT CREATION, SKILLS ENHANCEMENT AND LOCAL BUSINESS OPPORTUNITIES
The Project is expected to generate positive impacts on the local economy and livelihoods in terms of:
• Employment and skills enhancement; and
• Local business opportunities through the procurement of goods and services.
Positive impacts will be primarily associated with the construction phase and therefore temporary in
nature. The termination of construction contracts will occur once construction activities are completed.
Workers who have relocated to the area for the Project are likely to leave the area in search of other
opportunities, especially if they are permanent employees of contractors and subcontractors.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 39
Those who have worked on the Project will have an advantage when seeking alternative jobs on similar
projects due to the experience and any training received through this Project. The area is characterised
by a number of new industrial developments and is earmarked for other integrated steel projects which
may offer alternative employment opportunities. This is considered within the cumulative impacts Section
5.1.1 Construction: Employment, Skills Enhancement and Local Business Opportunities
Impact Description
The construction phase will last approximately 4-5 years in duration (Phase I & II) and it is expected that
approximately 1000 contact persons opportunities will be available during the peak of construction. The
breakdown of skills required during the construction phase will be as follows:
• Skilled labour
• Semi-skilled labour and
• Unskilled labour
It is assumed that the majority of skilled workforce will come from outside the ADI and AII, but that many
of them will be local. Given that almost half the population in the region have some level of skills training,
it is anticipated that many semi-skilled positions will be available to the local workforce, and that unskilled
positions will also be available to the local workforce. Indirect employment through the construction
supply chain will be limited as the major components of the integrated steel plant are highly specialised
and will be manufactured outside of Karnataka. However, much of the balance of plant of plant
infrastructure for the Project will be procured within region and where possible, from within the Locals.
Local procurement is going to benefit the hospitality and service industries primarily, such as
accommodation, catering, cleaning, transport and security services. Local businesses will benefit during
the construction phase as there will be increased spending within the area by the wage labour who will
have improved buying integrated steel while employed by the Project. Those who are able to secure
employment on the Project will have the opportunity to improve their skills and experience through on-the-
job training, and will thereby improve their opportunities for future employment.
Given that Karnataka has ear-marked for further industrial development, with a focus on the natural
resources, the upskilling of the local workforce will put the local workforce in a favourable position to
secure future employment. Employment numbers during commissioning are not known at this stage, but it
is expected that the make-up of the workforce will be similar to the construction phase.
Impact Assessment
The creation of local employment opportunities, skills enhancement and local business opportunities will
be a direct, indirect and induced impact. The duration will be short-term, for the duration of the
construction phase and work contracts will vary in length, based on the type of work being performed.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 40
Employment will be created for Region at a local level depending on skills and capacity availability, as
such the extent will be regional. For those who are able to secure employment on the Project the scale
will be medium, as they secure an income for the duration of their contract. The frequency of the impact
will be constant for the duration of the construction phase. The magnitude of the impact will be positive.
Given the capacity of the local workforce to fill unskilled and semi-skilled employment positions,
together with the opportunity to increase skills and work experience, the vulnerability is medium.
The significance of the impact is rated as Moderate (+ve).
Proposed mitigation/ enhancement
The objective of mitigation is to optimise opportunities for employment of local people, wherever
possible, or alternatively that employment of Region is prioritised over outside persons
The following measures will be implemented to ensure that employment of local people is maximised:
• The Project will establish a recruitment policy which prioritises the employment of Indian and
local residents (originating from the Local body) over foreigners. Criteria will be set for
prioritising local residents and then other Region as part of the recruitment process.
• All contractors will be required to recruit in terms of the Project’s recruitment policy,
where practical.
• The Project will meet with the Local body to access any available skills/employment-seekers
database for the area. This database is to be updated and made available to the appointed
contractors.
• The Project will advertise job opportunities and criteria for skills and experience needed
through local media, at least three months ahead of recruitment. This information should
also be provided to all relevant authorities, community representatives and organisations on
the interested and affected party database.
• The recruitment policy and procedure should promote the employment of women as a means of
ensuring that gender equality is attained.
• On-the-job performance and training will be monitored through performance reviews. Training
needs will be identified and provided by the Project.
• No employment will take place at the entrance to the site. Only formal channels for
employment will be used.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 41
A local procurement policy will be implemented to ensure that local procurement is
maximised, the policy will include:
• Reasonable targets for using local suppliers.
• A clause of none discrimination on any grounds of gender, ethnicity, religion.
• Criteria for monitoring local procurement and reporting on supplier performance
management.
• Clearly communicate the criteria and tendering process prior to the commencement of
construction activities; and
• The procurement policy and tendering requirements must be easily accessible to
potential suppliers.
• The following management measures will be implemented to enhance skills development and
on-the-job training
• Develop internal training 'certification' or reference letter provisions to those who receive
internal training.
• Training plans will be developed according to each permanent employee work agreement and
relevant to their job description.
Residual impacts
A summary for the impact the construction and phases of the Project is present below.
Table 5.1 Pre- and Post - Mitigation Significance for Employment Creation, Skills
Enhancement and Local Business Opportunities
Impact Project Phase Significance
(Pre-mitigation)
Residual Impact
Significance
(Post-mitigation)
Employment Creation, Skills
Enhancement and Local
Business Opportunities
Construction
Moderate (+ve) Moderate (+ve)
Table 5.2 Pre- and Post - Mitigation Significance for Employment Creation, Skills
Enhancement and Local Business Opportunities during Construction
Nature and Type: Direct, indirect and induced positive impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Positive
• Extent: Regional
• Duration: Short
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 42
• Scale: Large
• Frequency: Constant
• Reversibility: N/A
• Likelihood: N/A
Impact Significance (Pre-Mitigation): Moderate Positive
Impact Significance (Post-Mitigation): Enhancement measure will ensure the impact remains
Moderate Positive.
5.1.2 Operation: Employment, Skills Enhancement and Local Business Opportunities
Impact Description
The integrated steel plant will be operated on a 24 hour, 7 days a week basis for the duration of the
operation phase. It is anticipated that there will be employment positions available during this phase. As
the plant will operate 24 hours a day, three full-time shifts will be created per day, and the breakdown of
the skills required will be as follows:
• Skilled labour:
• Semi-skilled labour: and
• Unskilled labour:
Similar to the construction phase, local workers are expected to be qualified to fill unskilled and semi-
skilled positions at first, whilst a limited number of people may be sufficiently qualified for skilled
positions. Semi-skilled and skilled positions will initially be recruited from elsewhere in the region and
India . Over time, however, local workers will be able to fill more of the semi-skilled and skilled positions
as training will be provided by the Project to the local workforce, will improve skills levels relevant to the
Project.
During the operation phase the contracts that were in place during the construction phase will be
terminated and procurement opportunities will be centred around maintenance activities, and providing
goods and services to the Project. For those companies that meet eligibility criteria, become approved
suppliers and enter the supply chain, there will be long-lasting and sustained benefits to the businesses
and their employees through increased experience, capacity and training. As such, during the operation
phase there will be opportunity for local business growth and development
Impact Assessment
The creation of local employment opportunities, skills enhancement and local business opportunities will
be a direct, indirect and induced impact. The duration will be long-term, for the duration of the operation
phase. Employment will be created for Region at a local and regional level depending on skills and
capacity availability, as such the extent will be regional. For those who are able to secure employment
or procurement contracts with the Project the scale will be large, as they secure long-term, stable
income. The frequency will be constant for the duration of the operation phase. The magnitude of the
impact will be Positive.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 43
Given the limited employment and procurement opportunities during the operation phase, together
with the lack of appropriate skills in the ADI, the vulnerability is low.
The significance of the impact is rated as Minor (+ve).
Proposed mitigation/ enhancement
The mitigation/ enhancement measure provided for the construction phase, will apply to the operation
phase.
Residual impacts
A summary for the impact during the operation phases of the project is presented below.
Table 5.3 Pre- and Post - Mitigation Significance for Employment Creation, Skills
Enhancement and Local Business Opportunities
Impact Project
Phase
Significance
(Pre-mitigation)
Residual Impact
Significance
(Post-mitigation)
Employment Creation,
Skills Enhancement
and
Local Business
Opportunities
Operation Minor (+ve) Minor (+ve)
Table 5.4 Pre- and Post - Mitigation Significance for Employment Creation, Skills
Enhancement and Local Business Opportunities during Operation
Nature and Type: Direct, indirect and induced positive impact Sensitivity/Vulnerability/Importance of Resource/Receptor: Low Impact Magnitude: Positive • Extent: Regional • Duration: Long Term • Scale: Large • Frequency: Constant • Reversibility: N/A • Likelihood: N/A IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR POSITIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): Enhancement measures will ensure the impact remains
MINOR POSITIVE.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 44
5.2 IMPACTS ON COMMUNITY HEALTH AND SAFETY
The presence of the Project could affect the health, safety and security of the communities in the area
of influence as a result of worker-community interactions, in-migration to the area, increased incomes in
the local community that may be used for drugs, alcohol and prostitution, the risk of injury associated
with construction and activities, increased pressure on health care resources and changes to the
environment. Any community concerns or perceptions with regard to reduced health and physical safety
and security by the community need to be addressed.
There are numerous ways in which the development of the Project could impact on community and
individual levels of health. The term “health” is used broadly to include physical and mental health
and well-being. The expected impacts on community health, safety and security as a result of
construction, operation and of the Project are:
• Impacts associated with the presence of the Project workforce.
• Impacts associated with an influx of jobseekers.
• Impact on human health due to air emissions.
5.2.1 Construction and Operation: Impacts Associated with the Presence of the Workforce and Jobseekers
Impact Description
An increase in disposable income within the Project Area (among Project
workers, both local and external) has been observed to result in a change in
spending habits and behaviour resulting in increase in alcohol and drug
abuse, increased incidences of prostitution and casual sexual relations, which poses a threat to
community health and safety. Anticipated impacts associated with the presence of the workforce are:
• Increased incidence of alcohol and drug use;
• Increase in the spread of HIV/ Aids and other STIs;
• Increased incidence of teenage or unwanted pregnancies; and
It is estimated that there will be employed people during the peak construction phase. The Project will
seek to maximise the employment of local people, thereby reducing the size of the external workforce in
the ADI, however an external workforce will be required. The external workforce (largely comprised of
semi-skilled and skilled workers) will be housed with the ADI, as onsite worker accommodation is not
feasible for health and safety reasons given the Project
Site’s close proximity to Hospet.
Experience from large infrastructure projects elsewhere in India has shown that increased disposable
income within the local workforce may result in increased incidences of illegal activities as well as
increased levels of substance abuse. Abuse of alcohol (and drugs, should this occur) often correlates with
increased levels of criminal behaviour and violence (e.g.domestic violence) while under the influence of
the substance. Such behaviour increases the number of people indirectly affected by, or vulnerable to,
alcohol and drug abuse; and casual sexual relations could lead to an increased incidence of HIV/AIDS.
Further, it has been shown that members of an external workforce are likely to father children with local
women while they are living in the Project Area. Given the temporary nature of the work, it is possible that
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 45
both the women and children will be abandoned when the construction phase ends and the contractors
move on, leaving single female-headed households. A further impact associated with an influx of
jobseekers is the potential for their jobs. Competition for jobs has been raised as a concern by some
stakeholders.
Impact Assessment
The impacts related to the presence of the workforce and jobseekers in the Project Area will be indirect
and negative as the presence of a mostly male workforce, with an increased disposable income may
adversely impact on health, safety and security of the local community through a likely increase in illegal
or antisocial behaviour., The impact will be experienced at a local level, within the ADI. While the
workforce will be in the Project Area for a limited time during the construction phase, jobseekers may
stay in the area. Those affected by antisocial behaviour, such as the victims of abuse and people living
with HIV/ AIDS, the duration of the impact will be long-term. The scale of the impact will be large for
those affected as it will lead to a fundamental change in their life, and/ or health status, particularly for
those affected by violence, unwanted pregnancies or HIV/ AIDS. For those affected, the impact will be
largely irreversible. The frequency of the impacts will not be uniform, but may be felt often. Given the
above, the magnitude of the impact is considered medium.
The external workforce will be housed within the Area and will interact with the local community. The
local workforce will come from residential areas within the ADI.
During the operation phase, there will be limited employment opportunities and the external construction
workforce will likely leave the area. The number of local people with disposable income will decrease, as
will the impacts associated with this. This impact will not be felt during the operation phase.
Proposed mitigation/ enhancement
The Project will develop an induction programme, including a Code of Conduct, for all workers directly
related to the project. A copy of the Code of Conduct is to be presented to all workers and signed by
each person. The Code of Conduct must address the following aspects:
• respect for local residents and customs;
• zero tolerance of bribery or corruption;
• zero tolerance of illegal activities by construction personnel including: unlicensed prostitution;
illegal sale or purchase of alcohol; sale, purchase or consumption of drugs; illegal gambling or fighting;
• no alcohol and drugs policy during working time or at times that will affect ability to work;
• description of disciplinary measures for infringement of the Code and company rules. If workers
are found to be in contravention of the Code of Conduct, which they signed at the commencement of
their contract, they will face disciplinary procedures that could result in dismissal.
The Project will implement a grievance procedure that is easily accessible to the local community,
through which complaints related to contractor or employee behaviour can be lodged and responded
to. The Project will respond in a serious manner to any such complaints. Key steps include:
• Circulation of contact details of ‘grievance officer’ or other key Project contact;
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 46
• Awareness raising among the local community regarding the grievance procedure and how it
works; and
• Establishment of a grievance register to be updated and maintained by the Project.
The Project will develop and implement an HIV/AIDS policy and information document for all workers
directly related to the Project. The information document will address factual health issues as well as
behaviour change issues around the transmission and infection of HIV/AIDS.
Residual impacts
The implementation of the above mitigation measures would ensure that the construction phase
significance is reduced to Minor- Moderate significance. A summary for the impact the construction
phase of the Project is present below.
Table 5.5 Pre- and Post- Mitigation Significance for Impacts Associated with the Presence
of the Workforce and Jobseekers
Table 5.6 Pre- and Post- Mitigation Significance for Impacts Associated with the Presence
of a Workforce and Jobseekers
Nature and Type: Indirect negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Medium
• Extent: Local
• Duration: Permanent
• Scale: Large
• Frequency: Constant
• Reversibility: Irreversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MINOR - MODERATE NEGATIVE
Impact Project Phase Significance
(Pre-mitigation)
Residual Impact
Significance
(Post-mitigation)
Impacts Associated
with
the Presence of a
Workforce
Construction
and Decommissioning
Moderate (-ve) Minor - Moderate (-ve)
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 47
5.2.2 Construction and Operation: Pressure on Social Infrastructure and Services
Impact Description
It is generally accepted that large-scale infrastructure projects attract job- seekers into the Project Area.
The Project is expected to stimulate in-migration as job-seekers enter the area with the intention of
securing employment on the Project. In-migration of people will be further stimulated by possibility of
business opportunities linked to the provision of goods and services to the Project, and by real or
perceived opportunities arising from the general increase in economic activity in the area.
It is likely that a number of people will continue to stay in the area irrespective of whether they are able to
secure employment and these people may move their families to the area. There is the possibility that
people will return to their place of origin or move on to seek employment elsewhere if there are no
employment opportunities for them, or when the construction phase is complete. The expected impacts
associated with an influx of jobseekers are:
• Pressure on existing social infrastructure – particularly housing, education and health facilities
The presence of the Project is likely to increase the rate of in-migration into the area, as people
are attracted to the area in the hope of securing employment. The increase in population is
expected to add pressure on existing infrastructure and services; specifically on housing services.
This could be further exacerbated if job seekers decide to relocate their families to the area.
An influx of jobseekers and their families would place pressure on health and education facilities. These
already understaffed clinics would be placed under pressure to cope with the increase in population
within their catchment.
Impact Assessment
The impacts related to pressure on social infrastructure and services will be an indirect impact. The
impacts will be negative as they will place pressure on infrastructure and services and the local
government, who will have to provide the services should the influx occur.
The impact will be experienced at a local level, within the ADI. The impacts will be long-term despite the
fact that the period of influx may be limited to the construction phase, the associated impacts will
continue to occur into the future. The scale of the impact will be medium, as the Project is not expected
to attract large volumes of in-migration and the degree of change for local population will therefore be
notable but will not dominate over existing conditions. The frequency of the impacts will not be uniform,
but will felt often until in-migration stabilises and upgrades to infrastructure are undertaken. The impact
is revisable as social infrastructure and services can be improved to address the impact. Given the
information presented above, the impact will be medium in magnitude.
The population within the area like Hospet has been increasing which has been attributed to the in-
migration of people seeking economic opportunities. Therefore, the vulnerability of receptors is
considered low.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 48
Therefore, the significance of the impact is rated as Moderate, the level of in-migration, and
movement of job-seekers cannot be accurately predicted.
During the operational phase, there will limited employment opportunities and the Project is unlikely to
attract further job seekers.
Proposed Mitigation Measures
The Project will implement a grievance procedure that is easily accessible to the local community,
through which complaints related to contractor or
employee behaviour can be lodged and responded to. The Project will respond in a serious
manner to any such complaints. Key steps include:
• Circulation of contact details of ‘grievance officer’ or other key Project contact.
• Awareness raising among the local community regarding the grievance procedure and how it
works.
• Establishment of a grievance register to be updated and maintained by the Project.
Implement management measures associated with the prioritization of local labour, as outlined in
Section 5.1.1
Residual impacts
The implementation of the above mitigation measures would ensure that the construction phase
significance remains of Moderate significance.
A summary for the impact the construction phase of the Project is present below.
Table 5.7 Pre- and Post- Mitigation Significance for Impacts Associated with Pressure on
Social Infrastructure and Services
Impact Project Phase Significance
(Pre-mitigation)
Residual Impact
Significance
(Post-mitigation)
Impacts Associated with
Pressure on Social
Infrastructure and
Services
Construction Moderate (-ve) Moderate (-ve)
Nature and Type: Indirect negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Medium
• Extent: Local
• Duration: Long term
• Scale: Medium
• Frequency: Often
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 49
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE
5.2.3 Construction Phase: Impact on Human Health due to Air Emissions and Dust Generation
Impact Description
Most construction and activities generate dust, which settles on surrounding properties and land, and is
often more of a nuisance than a health issue. The dust is generally coarse, but may include fine
respirable particles (PM10) and these are known to be a risk to human health. Exhaust emissions from
construction vehicles and equipment typically include particulates (including PM10), carbon monoxide
(CO), nitrogen oxides (NOX), sulphur dioxide (SO2). The creation of dust associated with vehicle traffic
will be limited as most of the roads in the ADI are tar & paved.
Impact Assessment
The impacts on human health due to air emissions and dust generation will be a direct, negative impact.
The duration will be short-term, for the duration of the construction phase. The extent of the impact will
local, as the pollutants will be limited in dispersion and will occur onsite and around the main transport
routes. Based on the outcomes of the Air Quality Report of EIA , air emissions generated as a result of
construction phase activities not expected to have an adverse effect on health, therefore the degree of
change experienced by individuals will be negligible and the scale of the impact will be small. The impact
is considered reversible. The frequency of the impact will vary depending on construction activities, but it
will be often for the duration of the construction phase. Given the above factors, the magnitude of the
impact is considered small.
The vulnerability of receptors is considered low as the Project Site located in an industrial area with no
sensitive receptors located adjacent to the site. People living along transport routes have access to
health care and would be able to seek medical attention if their health was adversely affect by air
emissions.
Therefore it is anticipated that the significance of the impact will be negligible.
Mitigation
All of the mitigation measures outlined in EIA report must be implemented by the Project. In
addition, the Project will develop and implement a Grievance Mechanism to address stakeholder
concerns related to the Project in a timely manner.
Residual Impact
The implementation of mitigation measures will ensure that the impact remains of negligible
significance.
Table 5.8 Pre - and Post- Mitigation Significance for Impact on Human Health due to Air
Emissions and Dust Generation
Impact Project Phase Significance
(Pre-mitigation)
Residual Impact
Significance
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 50
(Post-mitigation)
Impact on Human Health
due to Air Emissions and
Dust Generation
Construction Negligible Negligible
Nature and Type: Direct, negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Low
• Extent: Local
• Duration: Short-term
• Scale: Small
• Frequency: Often
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): NEGLIGABLE
IMPACT SIGNIFICANCE (POST-MITIGATION): NEGLIGABLE
5.2.4 Operations Phase: Impact on Human Health due to Air Emissions
Impact Description
The operation of the integrated steel plant will result in emissions due to the operations , which could
result in decreases in air quality. Emissions of air pollutants from the integrated steel plant will result
during operations resulting in PM 10 & 2.5 , SOx, NOX, CO and CO2 emissions . Increased emissions
of any of these pollutants may not result in negative implications for human health as the emissions are
quiet low . In order to protect human health, air quality standards have been established and emissions
below these standards are considered to have a negligible impact on the health of communities.
Impact Assessment
The impacts on human health due to air emissions and dust generation will be a direct, negative impact.
The duration will be long-term, for the duration of the operation phase. The extent of the impact will local,
as the pollutants will be limited in dispersion, occurring onsite and adjacent to the site, as well as the
main transport routes. Based on the outcomes of the Air Quality Report, (Refere EIA report) for all
pollutants the predicted ambient concentrations are well below the respective National Ambient Air
Quality Standards (NAAQS). Therefore, air emissions generated as a result of the operation phase is not
expected to have an adverse effect on health - the degree of change experienced by individuals will be
negligible and the scale of the impact will be small. The impact is considered reversible. The frequency of
the impact will be constant, as the integrated steel plant will operate 24 hrs a day, 7 days a week. Given
the above factors, the magnitude of the impact is considered medium.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 51
The vulnerability of receptors is considered low as the Project Site is located in an industrial area with no
sensitive receptors located adjacent to the site. People living along transport routes have access to
health care and would be able to seek medical attention if their health was adversely affect by air
emissions.
Therefore it is anticipated that the significance of the impact will be Minor (-ve).
Mitigation
All of the mitigation measures outlined in EIA report must be implemented by the Project.
In addition, the Project will develop and implement a Grievance Mechanism to address stakeholder
concerns related to the Project in a timely manner.
Residual Impact
The implementation of mitigation measures will ensure that the impact remains of Minor
significance.
Table 5.9 Pre - and Post- Mitigation Significance for Impact on Human Health due to Air
Emissions and Dust Generation
Table 5.10 Pre - and Post- Mitigation Significance for Impact on Human Health due to Air
Emissions and Dust Generation
Nature and Type: Direct, negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Low
Impact Magnitude: Medium
• Extent: Local
• Duration: Long-term
• Scale: Small
• Frequency: Constant
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 52
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR
IMPACT SIGNIFICANCE (POST-MITIGATION): MINOR
5.3 INCREASED NUISANCE FACTORS AND CHANGE IN SENSE OF PLACE
The Project Site is located within an industrial area, adjacent to the Saldanha Steel facility. The land
immediately surrounding the site it utilised for industrial purposes, grazing or is vacant land. Within the
broader area, much of the surrounding land to the north and east is utilised for agriculture, nature
reserves.
There are existing visual intrusions around the Project Site, such as steel plants , railway lines ,
industrial , therefore, the landscape should not be seen as pristine.
The Project will introduce integrated steel plant and associated infrastructure such as a power plant,
substation and Operation and Maintenance (O&M) buildings into the area, within close proximity to
existing industrial infrastructure. The construction and operation of the Project will lead to an
increase in ambient noise, the generation of dust and increased traffic volumes, all of which have the
ability to alter the sense of place of the existing environment.
5.3.1 Construction and Phase: Increased Nuisance Factors and Change in Sense of Place
Impact Description
Impacts associated with air quality, traffic and noise have been assessed by specialists and are
discussed in EIA in Traffic Assessment Report, the Noise Impact Assessment Report and Air Quality
Report .
The Project will cause nuisance of the communities in the ADI due to noise, dust and vibration, as well as
increased traffic volumes during construction and .
Noise levels are expected to increase as a result of construction activities on site such as trucks that
deliver construction equipment and materials; earthworks using heavy machinery, and site preparation, or
piling activities if required.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 53
Additional vehicle movements during peak periods are anticipated during the peak hour, the minibus,
taxis. The buses & cars will collect and dispatch the workforce in the vicinity of the site, including areas in
the ADI.
The anticipated ambient noise levels during the construction phase of the Project has been modelled and
based on the results thereof, it is anticipated that the change in ambient noise levels will be negligible
during construction.
The construction phase sound levels may impact on the ambient noise levels for an area will affect very
small radius from Project Site.
The increase in traffic volumes will be notable during peak traffic times in the morning and afternoon, and
may frustrate other road users, but the increase in traffic will be manageable through the implementation
of mitigation measures.
Dust associated with the Project will be largely limited to the Project site. While each of the above
mentioned impacts are considered to be largely manageable, the combined effect of the noise, dust and
traffic impacts are likely to have a negative impact on the sense of place for some stakeholders.
Impact Assessment
The impacts associated with increased nuisance factors and change in sense of place during construction
and will be a direct, negative impact. The duration will be short-term, for the duration of the construction
phase. The extent of the impact will local, limited to the site and immediate surrounds, as well as the local
transport routes. The scale of the impact will be medium. The impact is considered reversible. The
frequency of the impact will vary depending on construction activities, but it will be often as it relates to
nuisance factors, and constant as it relates to sense of place. Given the above factors, the magnitude of
the impact is considered medium.
The vulnerability of receptors is considered small to medium, as traffic volumes in the area are low, and
road users will find the increased traffic volumes quiet low . The construction phase sound levels may
impact on the ambient noise levels for an area very near to the Project Site.
Therefore it is anticipated that the significance of the impact will be Moderate negative.
Mitigation
All of the mitigation measures outlined in EIA report , Traffic Assessment Report, the Noise Impact
Assessment Report and Air Quality Report must be implemented by the Project.
In addition, the Project will develop and implement a Grievance Mechanism to address stakeholder
concerns related to the Project in a timely manner.
Residual Impact
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 54
The implementation of mitigation measures will result in the impact being of Minor significance.
Table 5.11 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and
Change in Sense of Place
Table 5.12 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and
Change in Sense of Place during Construction and
Nature and Type: Direct, negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Medium
• Extent: Local
• Duration: Short-term
• Scale: Medium
• Frequency: Often to constant
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MINOR NEGATIVE.
5.3.2 Operation Phase: Increased Nuisance Factors
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 55
Impact Description
The Project will cause nuisance to the communities in the ADI due to noise, dust and vibration, as well as
increased traffic volumes during operation. This will affect the communities and households closest to the
Project site and along the main access roads, as well as along the routes used to transport the workforce
to and from the site on a daily basis.
During operation, the integrated steel plant will operate 24 hours a day, seven days a week. It is
anticipated that the change in ambient noise levels will be negligible during Phase 1 of the project and
lately during Phase 2, .This noise will have a more constant characteristic and will be perceived as a
humming sound. Operational phase sound levels may not impact the area beyond the facility.
The Project associated traffic will decrease during the operations phase as there will be fewer people
employed by the Project during this phase. Additional vehicle movements are associated with the
commuting of employees to and from work each day. Additional vehicle movements during peak periods
are anticipated.
The presence of the Project may alter the visual character of the landscape during the operation phase.
While the Project Site is not located in industrial area Based on a Visual Impact Assessment for a similar
integrated steel plant facility.
The Project will not be visible from tourism spots nor roads.
Impact Assessment
The impacts due to increased nuisance factors and change in sense of place during operation will be a
direct, negative impact. The duration will be long-term, for the duration of the operation phase. The
extent of the impact will local, limited to the site and immediate surrounds, as well as the local transport
routes. It is anticipated that the change in ambient noise levels will be negligible during Phase 1 of the
project and low during Phase 2 .The Project will not be visible from a any tourist areas . Given the
distance between the Project and the potential receptors, it can be concluded that while the Project will
not be visible, it will not dominate the landscape or detract from the receptors experience in of the area.
Never-the-less, for those receptors impacted by for increased nuisance factors and change in sense of
place the scale of the impact will be medium.
The impact is considered irreversible. The frequency of the impact will be constant for the duration of
the operation phase. Given the above factors, the magnitude of the impact is considered medium.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 56
The vulnerability of receptors is considered medium as most sensitive receptors are located in quiet
areas, with low ambient noise levels, low traffic volumes, and are people who are attracted to the area
for outdoor.
Therefore it is anticipated that the significance of the impact will be Moderate (-ve).
Mitigation
The ability to which visual impacts can be managed is limited by the size of the facility and the
industry standards governing setbacks and fire control. However, the following measures should be
implemented to minimise the impact of lighting at night:
• Lighting should be limited to areas where it is required.
• Lights should be directional and avoid light spillage.
• Low-level lights should be used over flood lights along walkways.
All of the mitigation measures outlined in EIA report , the Traffic Assessment Report the Noise Impact
Assessment Report and Air Quality Report must be implemented by the Project.
In addition, the Project will develop and implement a Grievance Mechanism to address stakeholder
concerns related to the Project in a timely manner.
Residual Impact
The implementation of mitigation measures will result in the remaining of Moderate negative
significance.
Table 5.13 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and
Change in Sense of Place During Operation
Impact Project Phase Significance
(Pre-mitigation)
Residual Impact
Significance
(Post-mitigation)
Increased nuisance
factors
and change in sense of
place operation
Operation Moderate (-ve) Moderate (-ve)
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 57
Table 5.14 Pre- and Post- Mitigation Significance for Increased Nuisance Factors and
Change in Sense of Place Operation
Nature and Type: Direct, negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Medium
• Extent: Local
• Duration: Long-term
• Scale: Medium
• Frequency: Constant
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE.
5.4 WORKER HEALTH AND SAFETY AND RIGHTS
Workers’ rights including occupational health and safety need to be considered to avoid accidents and
injuries, loss of man-hours, labour abuses and to ensure fair treatment, remuneration and working and
living conditions.
These issues will be considered not only for workers who are directly employed by the Project but also
contractors (including sub-contractors) and workers within the supply chain. The main risks in relation
to worker’s management and rights are associated with the use of contractors and subcontractors and
the supply chain.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 58
The Project is expected create direct employment opportunities during the peak of the construction
period, which will be 2-3 years in duration. The majority of workers will be engaged by the EPC
contractor and will consist of a semi-skilled to skilled workforce. The operation phase is planned for a
lifespan of 25 - 30 years and will involve around 95 permanent site employees including skilled and
semi-skilled staff.
The expected impacts on worker rights and H&S as a result of construction, operation and activities and
Project operation are as follows:
• Risk to workers H&S due to construction and activities;
• Risk to workers H&S due to hazardous operation activities; and
• Violation of workers’ rights.
This impact assessment is based on the assumption that no specific Project H&S policies, procedures
and training provisions are in place for construction workers (both of EPC Contractor and subcontractors)
as limited information is available on this at the current Project stage.
5.4.1 Construction Phase: Risk to Workers’ H&S due to Construction Activities
Impact Description
The construction activities will involve the following main activities (in order of occurrence):
• Site preparation including levelling;
• Piling of the foundations;
• Concrete works in scope of building construction;
Details of the activities associated with are not yet detailed but will involve removal of all installed
infrastructure.
These activities will involve the operation of heavy equipment and trucks, working at height, working in
confined spaces, construction traffic, use of electric devices, handling of hazardous materials and other
hazardous activities. Due to the nature of the activities being undertaken during construction and ,
worker H&S is a key risk with the potential for accidents that may result in injuries and fatalities as well
as lost man-hours.
Within India , worker health and safety falls under the ambit of the Department of Labour, and is
primarily governed through the EPA 1986,Cosntrcors workers safety rules . Employees working
informally and those with limited or without awareness of their rights (for example, migrant workers, or
those newly entering the labour market) are likely to be most at risk of working in unsafe conditions.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 59
Impact Assessment
The impact on worker health and safety from the Project will be a direct, negative impact. The duration
will be short-term, for the duration of the construction phase. The extent of the impact will be regional, as
it will affect those directly employed by the Project, as well as people employed in the supply chain. The
scale of the impact will be large for anyone adversely affected by a health and safety incident on the
Project, as they may experience a temporary loss of work time, or in the worst-case scenario may be
rendered permanently unable to work. In most instances, this impact is considered reversible, as
incidences can be addressed through medical intervention where required and health and safety can be
constantly improved to avoid future incidences. The frequency of the impact will not be uniform, but will
likely occur often the duration of the construction phase. The magnitude of the impact is therefore
considered Medium.
The vulnerability of the workers to this impact is considered low, as there are laws in place in India to
protect worker rights. However, migrant workers, or those newly entering the labour market may not be
aware of their rights, and people may be willing to compromise their rights to secure employment in light
of high unemployment rates.
The impact is therefore considered to be of Minor - Moderate negative significance.
Mitigation
• The Project will comply with all applicable India n legislation in terms of health and safety, and
worker rights, which will include access to workmans compensation for loss of income resulting from an
onsite incident.
• As part of the contractor and supplier selection process the Project will take into consideration
performance with regard to worker management, worker rights, health and safety as outlined in India n
law, international standards and the Project’s policies.
• The Project will provide support to contractors and subcontractors to ensure that labour and
working conditions are in line with India n law through capacity building.
• Workers will be provided with primary health care and basic first aid at construction camps
/worksites.
• Facilities and operations will be developed, planned and maintained such that robust barriers
are in place to prevent accidents. All employees have the duty to stop any works if adequate systems to
control risks are not in place.
• In line with the worker code of conduct employees should not be under the influence of
intoxicants which could adversely affect the ability of that employee to perform the work or adversely
affect the health and safety of other employees, other persons or the environment.
• The Project will provide of Personal Protective Equipment (PPE), training and monitoring as
well as ongoing safety checks and safety audits.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 60
Residual Impact
Following the implementation of mitigation measures the impact significance will be (post-mitigation) of
Minor negative significance.
Table 5.15 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to
Hazardous Construction Activities
Table 5.16 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to
Hazardous Construction and Activities
Nature and Type: Direct, negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Low to Medium
Impact Magnitude: Low
• Extent: Regional
• Duration: Short-term
• Scale: Large
• Frequency: Often
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR to MODERATE NEGATIVE IMPACT
SIGNIFICANCE (POST-MITIGATION): Enhancement measures will ensure the impact remains MINOR
NEGATIVE.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 61
5.4.2 Operation Phase: Risk to Workers’ H&S due to Hazardous Operation Activities
Please note: For the operation of the Project the mitigation and prevention measures outlined above
for construction (Section 5.4.1) are considered as embedded controls.
Impact Description
Hazardous activities during the operation phase and regular maintenance activities will include, but not
be limited to; the operation of heavy equipment and trucks, use of electrical devices including high
voltage, working at height, maintenance of high pressure pipework and vessels and handling of
hazardous materials. During these activities the workers will be at risk for accidents and injury.
Impact Assessment
The impact on worker health and safety as a result of the Project will be a direct, negative impact. The
duration will be long-term, for the duration of the operation phase. The extent of the impact will be
regional, as it will affect those directly employed by the Project, as well as people employed in the supply
chain. The scale of the impact will be large for anyone adversely affected by a health and safety incident
on the Project, as they may experience a temporary loss of work time, or in the worst-case scenario may
be rendered permanently unable to work. In most instances, this impact is considered reversible, as
incidences can be addressed through medical intervention where required and health and safety can be
constantly improved to avoid future incidences. The frequency of the impact will not be uniform, but will
likely occur occasionally the duration of the operation phase. The magnitude of the impact is therefore
considered small.
The vulnerability of the workers to this impact is considered low, as there are laws in place in India to
protect worker rights and most employees will be highly skilled engineers and technicians, who have
likely been educated around their rights and H&S practices.
The impact is therefore considered to be of minor significance.
Mitigation
The implementation of mitigation measures defined for the construction phase will continued throughout
the operation phase with consideration in the health and safety management system of the specific risks
associated with operation and maintenance activities and the new size and structure of the workforce. In
this regard, mitigation measures outlined in Section 5.4.1 above are applicable to the operation.
Residual Impacts
The implementation of mitigation measures will ensure that the significance remains of minor negative
significance.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 62
Table 5.17 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to
Hazardous Operation Activities
Table 5.18 Pre- and Post- Mitigation Significance for Risk to Workers’ H&S due to
Hazardous Operation Activities
Nature and Type: Direct, negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Low
Impact Magnitude: Low
• Extent: Regional
• Duration: Long TERM
• Scale: Large
• Frequency: Rare
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MINOR NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): Enhancement measures will ensure the impact remains
MINOR NEGATIVE.
5.5 CUMULATIVE IMPACTS
The Project is located in an area ear-marked for further industrial development. The National
Department of Energy, through its Gas to Integrated steel Programme, is investigating the feasibility of
development of a gas-fired integrated steel station in the area. In addition, the IDZ is being promoted
as an oil and gas hub and industrial development is being encouraged in the area.
The preceding impact assessment assessed the socio-economic impacts associated with the Project
largely in isolation. It is important to, assess cumulative impacts associated with a proposed
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 63
development and there also is a legislated requirement in India to do so. The cumulative impacts on the
socio-economic environment are discussed below.
5.5.1 Method
There are numerous proposed developments in the area. At this stage, not all developments can be
confirmed and the timing of the developments is not known. A selection of similar developments and
those either confirmed or most likely have been considered in this cumulative impact assessment
including the existing & proposed industries .
The cumulative impact of the above mentioned projects, together with the Integrated steel Plant
may impact of the following:
• Economy, Employment and Skills
• Community Health Safety and Security
• Pressure on Social Infrastructure and Services
As per the ToR issued by MoEF&CC, the methodology described in Chapter 1 of EIA has been used
to assess the cumulative impacts.
5.5.2 Cumulative Impacts of the Socioeconomic Environment
Economy, Employment and Skills Development
Impact Description
The development of large scale industrial projects will result in increased direct and indirect employment
during the construction and operation of each of the projects. The nature and extent of the benefits will
depend on the employment strategy of the various developers and the extent to which they are
committed to maximise local employment.
There may be overlap between the construction phases of the Project with the other developments, or
they may run consecutively. Either way, this will result in a significant uplift in local employment directly
and indirectly through the procurement of goods and services. Furthermore, those that have been
employed by one of the developers may be in better position to find employment with the other
developers as they will have increased their skills and experience. As such, the potential for cumulative
positive benefits associated with economy, employment and skills development is considered to be
higher than for the Project alone.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 64
The operation of the developments outlined will occur over the same period of time and will be located in
close proximity as such the economic, employment and skills development opportunities outlined will be
greater for all the projects combined then just for the Project development.
It should be noted that expectations regarding economic development, employment and skills
development will be high amongst stakeholders in the local community and as such, in the event that
one developer does not meet expectations, there is the potential for all developers to be the target of
this negative feedback.
Impact Assessment
The cumulative creation of local employment opportunities, skills enhancement and local business
opportunities will be a direct, indirect and induced impact. The duration will be medium to long-term, as
the Projects will not all happen concurrently. Employment will be created for Region at a local and
regional level depending on skills requirements of each project, as such the extent will be regional. For
those who are able to secure employment on the Project the scale will be medium to high, depending on
the duration of the contract. The magnitude of the impact will be positive.
Given the capacity of the local workforce to fill unskilled and semi-skilled employment positions,
together with the opportunity to increase skills and work experience, the vulnerability is medium.
The significance of the impact is rated as Moderate (+ve).
Proposed mitigation/ enhancement
It is recommended the Project investigates opportunities to work with other developers to develop a
collaborative approaches to training, employment and skills development for the local population,
starting now in the run up to Project construction. This may include developing a coordinated standard
set of requirements for service providers (eg required labour numbers of carpenters, welders, Heavy
Goods Vehicle drivers, etc. and the minimum qualifications required for these) and making the
communities aware of these requirements. The developers should also plan and implement a
coordinated approach to community skills development based on these requirements.
Residual impacts
The implementation of the above mentioned mitigation measures will ensure that the positive impact on
the Economy, Employment and Skills Development remains moderate positive.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 65
Table 5.19 Pre- and Post - Mitigation Significance for Economy, Employment and Skills
Development Cumulative Impact
A summary for the impact presented below.
Table 5.20 Pre- and Post - Mitigation Significance for Economy, Employment and Skills
Development Cumulative Impact
Nature and Type: Indirect positive impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Positive
• Extent: Regional
• Duration: Long TERM
• Scale: Medium to Large
• Reversibility: N/A
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE POSITIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE POSITIVE.
Community Health Safety and Security
Impact Description
The presence of an external workforce for the combined projects housed within the communities and
construction camps could increase the spread of communicable diseases and STIs such as HIV/AIDS.
The profile of these diseases will be influenced by the existing health profile of communities within the
area of influence of the project and that of the workers, which is difficult to predict for the various
projects.
Increased air emissions as a result of the Project and another integrated steel plant as well as additional
risks of industrial accidents and explosions could result in cumulative impacts on community health and
safety. However, according to the Air Quality Report (Annex D of EIR), the cumulative impact on air
quality is expected to be minor, and according to the QRA(Annex D of EIR), the cumulative risks
associated with the Project are acceptable.
While the Project alone is not expected to attract vast numbers of jobseekers to the area, the
development of multiple projects is likely to attract people seeking employment opportunities, particularly
in light of a declining agricultural sector in the West Coast District Body , and given that Area is already
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 66
seen as an economic hub. An influx of jobseekers will result in increased competition for employment
which may contribute locally to social tension and conflict within the local communities.
Impact Assessment
The impacts related to community health and safety in the Project Area will be indirect and negative. The
impact will be experienced at a local level, within the ADI. The duration of the impact will be long term, as
projects may occur over an extended period of time. The scale of the impact will be large for those
affected as it will lead to a fundamental change in their life, and/ or health status, particularly for those
affected by violence, unwanted pregnancies or HIV/ AIDS. For those affected, the impact will be largely
irreversible. Given the above, the magnitude of the impact is considered medium.
In light of this, the vulnerability of receptors is considered medium, however, teenage girls are
considered to be highly sensitive to this impact.
The significance of the impact is rated as Moderate negative overall, but the significance will be of
high negative to those affected by unwanted pregnancies and HIV/ AIDS.
Proposed mitigation/ enhancement
• The Project should engage with other developers to ensure that community education and
awareness campaigns in relation to health, safety and security are developed and implemented
collaboratively to avoid duplication of effort.
• The Project should engage with its neighbours to develop combined emergency response plans
which take into account all the proposed developments and the community. This should consider
combined use of security personal and risks from unplanned events.
Residual impacts
The implementation of the above mitigation measures would ensure that the impact significance
remains that of Moderate.
A summary for the cumulative impact is present below.
Table 5.21 Pre- and Post- Mitigation Significance for Community Health and Safety
Cumulative Impact
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 67
Table 5.22 Pre- and Post- Mitigation Significance for Community Health and Safety
Cumulative Impact
Nature and Type: Indirect negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Medium
• Extent: Local
• Duration: Long term
• Scale: Large
• Reversibility: Irreversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE
Pressure on Social Infrastructure and Services
Impact Description
Related to the above, the influx of jobseekers together with presence of the workforce associated with
each Project could place additional pressure on the delivery of social infrastructure and services, in
particular housing. This is largely related to the unskilled workforce, as it is expected that the skilled and
semi-skilled workforce would be able to enter the housing market.
Projects that bring a large external unskilled workforce in the area and do not provide accommodation
will be increasing the burden on the provision of low cost housing.
Impact Assessment
The impacts related to increased pressure on existing social infrastructure and services will be an
indirect impact. The impacts will be negative as they will place pressure on infrastructure and services
and the local government, who will have to provide the services as demand grows.
The impact will be experienced at a local level, within the ADI. The impacts will be long-term as the
provision of social infrastructure and services may take time to catch-up with the increased demand. The
scale of the impact will be medium, as it will notable but will not dominate over existing conditions. The
impact is revisable as social infrastructure and services can be improved to address the impact. Given
the information presented above, the impact will be medium in magnitude. The population within the area
has been increasing at a rate greater than expected which has been attributed to the in-migration of
people seeking economic opportunities.
Therefore, the significance of the impact is rated as Moderate negative.
Proposed mitigation/ enhancement
Mitigation measures implemented by the Project, particularly a commitment to employing local labour
will help to minimise this impact, however, the potential impact on social infrastructure and services
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 68
remains that of moderate, as the Project cannot influence how other developments employ or house
their workforce.
Residual Impact
The impact significance remains of Moderate significance. A summary for the impact is present below.
Table 5.23 Pre- and Post- Mitigation Significance for Impacts Associated with Pressure
on Social Infrastructure and Services Cumulative Impact
Table 5.24 Pre- and Post- Mitigation Significance for Impacts Associated Pressure on
Social Infrastructure and Services
Nature and Type: Indirect negative impact
Sensitivity/Vulnerability/Importance of Resource/Receptor: Medium
Impact Magnitude: Medium
• Extent: Local
• Duration: Long term
• Scale: Medium
• Frequency: Often
• Reversibility: Reversible
• Likelihood: N/A
IMPACT SIGNIFICANCE (PRE-MITIGATION): MODERATE NEGATIVE
IMPACT SIGNIFICANCE (POST-MITIGATION): MODERATE NEGATIVE
5.6 UNPLANNED EVENTS
An unplanned event is a reasonably foreseeable event that is not planned to occur as part of the
Project (i.e. would not occur as part of routine operating procedures), but which may conceivably occur
as a result of Project activities (e.g. accidents). The risks of unplanned events related to the Project are
accessed in EIA report.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 69
6. KEY FINDINGS AND RECOMMENDATIONS
Both potential positive and negative socio-economic impacts associated with the development of the
MASPL Integrated steel Plant have been identified and assessed through this SIA. The key findings
have been summarized below.
• Employment creation, skills enhancement and local business opportunities: The Project will
create up to 1000 (tentatively inc. contract persons) employment opportunities during the construction
phase and 730 person during the operation phase. It is anticipated the unskilled and to a large extent
semi-skilled workforce will be drawn from the local area. Those who secure employment will benefit from
on the job training which will leave them well-placed to secure future employment on similar projects.
• Impacts on community health and safety: The presence of the Project may not majorly affect the
health, safety and security of the communities in the area of influence as a result of worker-community
interactions, in-migration to the area, increased disposable income in the local community, the risk of
injury associated with construction and activities, increased pressure on health care resources and
changes to the environment. Air emissions, noise and increased traffic associated with the Project are
also considered impacts that may affect community health and safety temporarily.
The impacts on community health and safety range from minor to moderate, however, with the
implementation of management measures, these impacts will be minor in significance, with the
exception of impacts associated with the presence of the workforce. This is largely due to the long-term
impacts that may arise from incidence of HIV/ AIDS.
• Worker health and safety and rights: Workers’ rights, including occupational health and safety
need to be considered to avoid accidents and injuries, loss of man-hours, labour abuses and to ensure
fair treatment, remuneration and working and living conditions. The development of health and safety
plans and policies will ensure that this impact is of minor significance.
The implementation of management measures detailed in this report, as well as in other specialist
reports are fundamental to ensuring that negative impacts associated with the Project are managed, and
the positive impacts are enhanced. Key management measures are summarized below.
• The Project will establish a recruitment policy which prioritises the employment of Indian and
local residents (originating from the Local Body) over outsiders. Criteria will be set for prioritising
local residents and then other states as part of the recruitment process.
• All contractors will be required to recruit in terms of the Project’s recruitment policy,
where practical.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 70
• The Project will develop an induction programme, including a Code of Conduct, for all workers
directly related to the project. A copy of the Code of Conduct to be presented to all workers and signed by
each person. The Code of Conduct must address the following aspects:
• respect for local residents and customs; o zero tolerance of bribery or corruption;
• zero tolerance of illegal activities by construction personnel including: unlicensed prostitution;
illegal sale or purchase of alcohol; sale, purchase or consumption of drugs; illegal gambling or fighting;
• no alcohol and drugs policy during working time or at times that will affect ability to work;
• Description of disciplinary measures for infringement of the Code and company rules. If workers
are found to be in contravention of the Code of Conduct, which they signed at the commencement of their
contract, they will face disciplinary procedures that could result in dismissal.
• The Project will implement a grievance procedure that is easily accessible to the local
community, through which complaints related to contractor or employee behaviour can be lodged and
responded to. The Project will respond in a serious manner to any such complaints. Key steps include:
• circulation of contact details of ‘grievance officer’ or other key Project contact; awareness
raising among the local community regarding the grievance procedure and how it works; and
establishment of a grievance register to be updated and maintained by the Project.
• The Project will develop and implement an HIV/AIDS policy and information document for all
workers directly related to the Project. The information document will address factual health issues as
well as behaviour change issues around the transmission and prevention of of HIV/AIDS.
• All of the mitigation measures outlined in EIA & EMP reports , Traffic Assessment Report , the
Noise Impact Assessment Report and Air Quality Report must be implemented by the Project.
Social Welfare & Upliftment Plan:
Budget for Corporate Environment Responsibility (CER)
PROJECT
(2018-19 to 2020-21)
Budget for Improvements in
physical infrastructure
(Rs in Lacs)
Budget for Improvements in
social infrastructure
(Rs in Lacs)
TOTAL
(Rs in Lacs)
Rolling Mill (Wire Rod
Cum Bar Mill) 515 435 950
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 71
BREAK- UP (Improvements in physical infrastructure):
Improvements in physical infrastructure
Sr.No PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018-19 to 2020-21
Welfare Activities Amount in Lacks Villages
1 Development of connecting road to NH-63
100
1. HosaKanakapura Village 2. KanakapuraTanda 3. Hale Kanakapura Village 4. Ginigera Village
2 R O Plant for drinking water 50
3 Water line from T B Dam 150
4 Drains Along Village Street 50
5 Construction of Sanitation Facility for Male and Female with provision of Overhead Water Tanks
75
6 Providing LED lighting with Solar Panels at Village Streets
50
7 Providing Computers and Science Lab Equipment to the ZP High Schools and Primary Schools
40
8 GRAND TOTAL (Rs in Lacks) 515
Improvements in social infrastructure
S.N PLAN & BUDGET ESTIMATION FOR THE PERIOD 2018-19 to 2020-21
Welfare Activities Amount in Lacks Villages
1 School Building 75
1. HosaKanakapura Village 2. KanakapuraTanda 3. Hale Kanakapura Village 4. Ginigera Village
2 Infrastructure Facilities for Computer Education 5
3 Establishment of Community Centres 150
4 Facilities /Infrastructures for skill development of Women
50
5 Avenue Plantation all along the Roads, Plantation at Public Places & Barren Lands
20
6 Provide 2 Ambulances for Medical Emergen cy Services
35
7
Soil Conservation measures and Forest Management nearby site in consultation with Forest Department.
50
8 Distribution of Fruit Bearing Sapling, Seeds to villagers Plantation.
50
9 GRAND TOTAL (Rs in Lacks) 435
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 72
7. IMPACT STATEMENT
The findings of the Social Impact Assessment for the MASPL Integrated steel Plant indicate that the
Project will have positive benefits for the local community through the creation of employment and skills
enhancement, during both the construction and operation phases. While potential negative impacts
associated with the Project have been identified, these can be managed through the implementation of
the mitigation measures outlined in this SIA, the EIA and EMP.
It is, therefore, recommended that the Project be supported subject to the implementation of the
mitigation measures outlined in this SIA, the EIA & EMP.
8. REFERENCES
MoEFCC Manual
CPCB
KSPCB
1 INTRODUCTION
The MoEF&CC requires that reports that are compiled by EIA consultant and are reviewed by GCI
team.
1.1 Review Approach
The review was undertaken as a desk-based exercise to assess the draft SIA in terms of the
specific criteria defined by MoEF&CC & ToR.
The reviewer was briefed by the lead author about the proposed Project, the SIA methodology (including
determination of the area of influence, selection of data gathering techniques, process of identifying and
assessing impacts, and process for Determining mitigation and management measures), integration
with related specialist studies, and assumptions and limitations of the study.
For each of the review criteria stipulated by MoEFCC , the reviewer has rated the information provided
in the SIA on a scale of 1 to 5, where 1 = inadequate and 5 = comprehensive. A comment is provided
to support each rating and recommended actions are provided.
M/s Mukand Alloy steels Private Limited
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
& Green Circle Inc. Vadodara 73
1.2 Assumptions and Limitations
The following assumptions and limitations apply to this review.
The review is based only on the criteria defined by the MoEF&CC ; no other national or international
requirements have been assessed.
It assumed that all Project and baseline information is correct and accurately reflects the respective sources.
The related specialist studies have not been reviewed, the information and assertions drawn from those
reports are assumed to be accurate.
ACTIVITY:
N / AB / E LC BC IPCPRO
(5)
EXP
O
(5)
SEV
(10)
A HANDLING OF FURNACE OIL & LDO
1 Unloading N Vehicular Accident Body Injury Skilled Worker Y
Motor
Vehicles
Act,1988
& Motor
Vehicles
Rules,19
89
2 2 3 12 NS
E Exposure to Fire Burn Injury Skilled Worker Caution Display Y 2 3 7 42 S
2 Storage E Exposure to Fire Burn Injury Skilled Worker Y
Section
7 of
Petroleu
m Act
1934,Rul
es
1976,up
graded
rules,20
02
2 3 7 42 S
3 Issuses E Exposure to Fire Burn Injury Skilled Worker Y 2 3 7 42 S
RISKS
PROPOSED CONTROLS/ IMPROVEMENTS / CHANGES / MODIFICATIONS PLANNED
QUANTITATIVE
RPN
HIRA HANDLING OF FURNACE OIL & LDO
HAZARD IDENTIFICATION, RISK ASSESMENT AND CONTROL PLAN
DEPARTMENT: RMS STORE HANDLING OF FURNACE OIL & LDO
SN ACTIVITIES
OCCURRENCE
OF HAZARDS
HAZARDSS/ NS
ABBREVATIONS: N: Normal, AB: Abnormal, E: Emergency, LC: Legal Concern, BC: Business Concern, IPC: Interested Party Concern, S: Significant, NS: Nonsignificant and OCP: Operational Control Procedures, PPE-Personal Protective equipment, RPN-
- Risk Priority Number.
EVALUATION OF RISK
REF.
OCP /
MPENGG ADMIN PPE's OTHERS
QUALITATIVE
REF
LEGAL
SL.
No
CREPGuidelines Compliance
1 Airemissions
1. AdequatelydesignedESPoranyother
adequateairpollution control
system/combinationofsystem should be
installed toachieve theprescribedstack
emissionstandards.
As installation and operation of Pollution
ControlEquipmentforplantswith lessthan
100TPDcapacityisnot economicallyviable,
therefore,itisrecommendedthat plantswith less
than 100TPD shall not be permittedin future.
Programfor phasingout old plantshaving
capacityless than 100TPD shall be worked
outbytheStatePollutionControl Board
Bag House & Chimney of
adequate Height
All Pollutioncontrolequipment should be
providedwith separateelectricity meter
andtotaliserfor continuousrecordingof
powerconsumption.The a m p e r a g e
oftheI D fanshouldalso
berecordedcontinuously.Non-
functioningofPollution control equipment should
be recorded in the same logbook along with
reasonsfornotrunning the PollutionControl
It willbeadhereda ccordingly
The safety cap/emergency stack of rotary kiln
type plant, which isgenerallyinstalled above the
After Burner Chamber(ABC) of feedend column
shouldnotbeused for discharging untreated
emission, bypassingthe air pollution control device.
Not Applicable
In order to prevent bypassing of emissions through
safety cap and non-operation of ESP or any
other pollution control device, software
controlled interlocking facility should be provided
on the basis of real time data from the plant
control system, to ensure stoppage of feed
conveyor, so that, feed to the kiln would stop
automatically, if safety cap of the rotary kiln is
opened or ESP is not in operation. The system
should be able to take care of multiple operating
parameters and their inter relations to prevent
any possibility of defeating the basic objective of
the interlock. The system should be foolproof to
prevent any kind of tempering. The software
based interlocking system, proposed to be
installed by industry should be get approved by
the concerned StatePollution Control Board, for its
adequacy, before installation by the industry.
Not Applicable
Mechanical operated system for timely collection
and removal of the flue dust generated in ESP or
any other pollution control device shall be
installed
Bag House & Chimney of
adequate Height
Stack Emission from de-dusting units
All de-dusting units should be connected to a stack
having a minimum stack height of 30 m. Sampling
porthole and platform etc. shall be provided as per
CPCB emission regulation to facilitate stack
monitoring. De-dusting units can also be
connected to ABC Chamber and finally emitted
through common stack with kiln off-gas emissions
It will be adhered
accordingly
Fugitive Emission
The measurement may be done, preferably on 8-
hour basis with high volume sampler. However,
depending upon the prevalent conditions at the site,
the period of measurement can be reduced.
Steps will be taken to control
fugitive dust emission.
2 Effluent Discharge
i. All efforts should be made toreuse and re- circulate
thewater and to maintain zero effluent discharge.
ii. Storm water / garland drain should be provided in
the plant.
In the proposed project
approximately 30 KLD Effluent
is generated which shall be
treated in Effluent Treatment
Tank and then reused for
gardening and dust
suppression purpose.There
will be no effluent released
from the Rolling Mill and
hence MASPL will adhere to
“Zero Liquid Discharge” for
this proposed project.
3 Noise Control
The industry should take measures to control the
NoisePollution so thatthe noise level standards
already notified for industrial area are complied.
It will be adhered
accordingly
4 Solid Waste Management
Char :
Char should be mixed with coal or coal
washery rejects and used as fuel in Fluidized Bed
Combustion Boilers (FBC) for generation of power.
The plants having capacity 200TPD and above
shouldinstall Fluidized Bed Combustion Boilers (FBC)
for generation of power. Also the smaller capacity
individual Sponge Iron Plants (Capacity upto 100
TPD) and operating in cluster can collectively
install common Fluidized Bed Combustion Boilers
(FBC) for power generation. The Sponge Iron Plant
are free to explore other options / possibilities to
use char for generation of power.
Char can be sold to local entrepreneurs for making
coal briquettes. It can also be mixed with coal fines,
convertedto briquettes and used inbrick kilns. Under
no circumstanceschar shouldbe disposedoff in
agricultural fields/other areas. Logbook for daily
record, of Char production and usage must be
maintained by the industry and the record shall be
made available to officials of CPCB/SPCB/PCC
during inspection.
Not Applicable
Kiln Accretions:
The kiln accretions are heavy solid lumpsand
can be used as sub- base material for road
construction or landfill, after ascertaining the
composition for its suitability and ensuring that it
should not have any adverse environmental impact.
Not Applicable
Gas Cleaning Plant (GCP)/Scrubber Sludge
The sludge should be compacted and suitably
disposed off after ascertaining the composition for its
suitabilityand ensuring that it should not have
any adverse environmental impact.
Not Applicable
Flue Dust / Fly ash
Flue dust is generated from air pollution control
system i.e. ESP or any other air pollution control
system installedwith kiln. Secondary flue dust is also
generated from Bag Filters or any other air pollution
control equipment installed with Raw Material
Handling, Coal Crusher, Cooler Discharge and
Product house unit. The reuse/ recycling of the flue
dust generated / collected may be explored and
suitably implemented.
Fly ash brick manufacturingplant should be installed
for fly ash utilization. Fly ash can be utilized in
cement making by Cement industry also.
Not Applicable
Bottom Ash
Bottom ash may have objectionable metallic
compounds, thereforeshould be stored in properly
designed landfills as per CPCB guidelines to prevent
leaching to the sub-soil and underground aquifer.
Not Applicable
General
(a) Solid waste management program should be
prepared with thrust on reuse and recycling.
Solid waste disposal site should be earmarked within
the plant premises. The storage site of solid waste
should be scientifically designed keeping in view
that the storage of solid waste should not have
any adverse impact on the air quality or water
regime, in any way.
It will be adhered
accordingly
(b) The various types of solid wastes
generated should be stored separately as per CPCB
guidelines so that it should not adversely affect
the air quality, becoming air borne by wind or water
regime during rainy season by flowing along with
the storm water.
It will be adhered
accordingly
Raw Material handling and Preparation
Unloading of coal by trucks or wagons should
becarried out with proper careavoiding dropping
of the materials from height. It is advisable to
moist the material by sprinkling water while
unloading.
Not Applicable
Crushing and screening operation should be carried
out in enclosed area. Centralized de- dusting facility
(collection hood and suction arrangements
followed by de-dusting unit like bag filter or ESP
or equally effective method or wet scrubber and
finally discharge of emission through a stack)
should be provided to control Fugitive
Particulate Matter Emissions. The stack should
confirm to the emissionstandards notified for de-
dusting units. Water sprinkling arrangement should
be providedat raw material heaps and on land
aroundthe crushing and screening units.
Not Applicable
Work area includingthe roads surrounding the plant
shall be asphalted or concreted.
It will be adhered
accordingly
Enclosure should be provided for belt conveyors and
transfer points of belt conveyors.
The above enclosures shall be rigid and
permanent (and not of flexible/ cloth type
enclosures) and fitted with self- closing doors and
close fitting entrances and exits, where conveyors
pass through the enclosures. Flexible covers shall be
installed at entry and exit of the conveyor to
the enclosures, minimizing the gaps around the
conveyors.
In the wet system, water sprays/ sprinklers shall be
provided at the following strategic locations for
dust suppression during raw
material transfer:
- Belt conveyor discharge/ transfer point
- Crusher/screen discharge locations
Not Applicable
Waste Heat Recovery Boiler (WHRB)
Sponge Iron Plants of capacity more than 100
TPD kilns shall use Waste Heat Recovery
Boiler (WHRB) for generation of power.
Not Applicable
Cooler Discharge and Product Separation
Unit
Permanent and rigid enclosures shall be provided for
belt conveyors and transfer points of belt
conveyors. Dust extraction cum control system
preferablybag filters or ESP to arrest product loss in
cooler discharge and product separation area shall
be installed.
Not Applicable
Char based Power Plant
For plant having capacity of 200 TPD of
cumulative kiln capacity, the power
production through FBC boiler using char as a part
of fuel, is a viable option. Power generation
through FBC boiler using char as a part of fuel be
implemented in a phased manner within 4 years of
commissioning and targeting for 100% utilization of
char. Individual Sponge Iron Plants of capacity
upto 100 TPD and located in cluster can install
a common char based power plant collectively.
Not Applicable