Annexure-I List of OCC Members - Welcome to Western ... · Annexure-I List of OCC Members Fax No....

122

Transcript of Annexure-I List of OCC Members - Welcome to Western ... · Annexure-I List of OCC Members Fax No....

  • Annexure-IList of OCC Members

    Fax No.1. Chief Engineer (L D), GETCO, Gotri 0265-23520192. Chief Engineer (Generation), GSECL, Vadodara 0265-2344734/23388473. Superintendent Engineer (CP & SS), GETCO, Vadodara 0265-2337918, 23381644. Chief Engineer (L D), MPPTCL, Jabalpur 0761-26643435. Chief Engineer (O&M:Gen), MPPGCL, Jabalpur 0761-2664572/26680506. Chief Engineer (L D), MSETCL, Kalwa 022–276017697. Chief Engineer (PP), MSEDCL, Mumbai8. Chief Engineer (Works),MSPGCL, Mumbai 022-264738969. Superintending Engineer (LD), MSETCL Ambazari 07104-22027510. Chief Engineer (L D), CSPTCL /Raipur 0771-257417411. Chief Engineer (O&M:GEN), CSPGCL, Raipur 0771-257442512. Executive Director, PGCIL Raipur13. General Manager, POSOCO, Mumbai 022-2820263014. General Manager (WRTS-I), Powergrid, Nagpur 0712-264136615. General Manager (O & M),WRTS-II, PGCIL,Vadodara 0265-248754216. Chief Engineer (Transmission), NPCIL, Mumbai 25580741/2556335017. Station Director, TAPS, Tarapur 1 & 2 02525-282125/24412518. Station Director, TAPS, Tarapur 3 & 4 02525-244021/24416919. Station Director, KAPP, Kakrapar 02626-23123120. General Manager (OS), NTPC, Mumbai 022-2821669221. General Manager, NTPC, Korba 07759- 237462/23755222. General Manager (OS), NTPC, HQ-II Raipur 0771-254455023. General Manager, NTPC, Vindhyachal, M.P. 07805 –24771124. General Manager, NTPC, SIPAT, CG 07752-24650425. General Manager NTPC LARA26. General Manager NTPC Solapur27. General Manager, NTPC, Kawas, Surat 0261-286029028. General Manager, NTPC, Gandhar 02642-28740229. General Manager, NTPC, Mouda 07115-281221/28121930. CLD TPC, Mumbai 022-25541908/6717538531. Head (O), Dahanu TPS, Dahanu 02528-22203932. Sr V P Reliance Transmission, Pune 0124-3917982/020-

    3047155533. Vice President (Generation), Torrent Power Ltd, Ahmedabad 079-2750667934. Executive Director, Sugen CCPP, Torrent Power Ltd, Surat. 02621-66115135. Vice President (O &M), APL Mundra , Gujarat 02838-26636436. Head Operation CGPL Mundra37. Vice President (Opn), Jindal Power Ltd.,Raigarh 07767-281993/28199538. AGM(OS) NSPCL Delhi 011-26717363,2671736639. GENERAL MANAGER ( POWER), RGPPL, Ratnagiri 02359-241071/ 24101140. Member (Power), NCA, Indore 0731-255988841. Chief Engineer (PM & C), NHDC, Bhopal 0755 4030188/403013042. E. E. Elect. (Ponda), Goa 0832-231378043. Executive Engineer DD (UT), Daman 0260-/2230771/2250889/223055044. Executive Engineer DNH (UT), Silvassa 0260-264233845. Secretary, CERC, New Delhi 011-24360010/2375392346. CEO, JSW Energy ltd. 011-46032343/2618354647. VP-Power Infra-Essar Hazira Surat 0261-6688498/022-6708219848. Chief Electrical Distribution Engineer CR 022-2262106049. Vice President EPTCL Hazira Surat 0261-668274750. COO, Korba West Power Co. Ltd. Raigarh51. VP(COMML) Essar Power MP Ltd MP52. GM Torrent power grid ltd. Ahmedabad, Gujarat53. Adani Power Maharashtra Ltd Tiroda54. CGM, R K M Powergen Pvt Ltd55. ED, Athena Chattishgarh Power Ltd.56. Head(O&M) Dhariwal Infra Ltd C’pur57. Head Operation Jaypee Nigrie STPP Singrauli.58. VP(O&M), GCEL, Chhattishgarh59. Head Operation DB Power, Chhattishgarh.60. Head operation Hindustan Power, Anuppur MP61. Head operation GMR, Warora Energy ltd.62. Head O&M, Sterlite Grid Ltd Bhopal63. Head Operation Balco, Chhattishgarh.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 1

    Western Regional Power CommitteeMumbai

    Title: Minutes of the MeetingNumber: 508Name of meeting: Operation & Coordination sub-CommitteeDate & venue: 14th June, 2018 at WRPC, Mumbai.

    508th meeting of Operation & Co-ordination sub-Committee (OCC) of Western

    Regional Power Committee (WRPC) was held on 14th June, 2018 at WRPC,

    Mumbai. The list of participants is enclosed at Annexure-A.

    Member Secretary (MS), WRPC extended warm welcome to all the participants of

    the 508th OCC meeting. He informed the forum about some of the important

    operational highlights of WR grid during month of May, 2018:

    MS, WRPC informed that power scenario during the last month was

    satisfactory, except last week of the May month during which wherein

    approximately 1200 MW load shedding was observed in Gujarat system

    due to 2000MW increase in summer peak demand.

    He expected good monsoon this year & hope for more hydro generation.

    He informed that frequency remained within IEGC band for 70.06% of the

    time only and 22.52% of the time frequency is below 49.90 Hz. He further

    stated that increase in % of time frequency below 49.9 Hz might be due

    increase in summer load and reduced availability of generation..

    He informed that peak shortage of WR was recorded as 1399MW during

    the last month and under interregional exchange, WR exported 6312

    MUs to other regions.

    He appreciated the efforts by all constituents for maintaining the grid

    discipline in WR despite less availability of generation due to many

    reasons.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 2

    He informed that there are no major grid disturbance events in WR and

    he appreciated WRLDC for maintaining the operation of grid within the

    limits of various parameters..

    He mentioned about “Mechanism for implementation of new

    environmental norms for thermal power plants supplying power to

    distribution licensees under long term and medium term power

    purchasing agreements” under which MoP assigned the task to Hon’ble

    CERC for framing the guidelines for addressing the compensation for

    installing the FGD.

    He informed that “Draft amendments relating to captive power plants in

    Electricity rules-2005” is available in MoP website for comments and

    requested all utilities for submitting comments, if any, by 18th June 2018.

    He also informed that “Proposed amendment to tariff policy-2016” draft

    amendments are available in MoP website for comments up to 20th June

    2018.

    He announced that SLDC Gujarat brought out the “Annual Report”

    summarizing all important aspects of Gujarat power system and

    congratulated Chief Engineer, SLDC Gujarat for their efforts in preparing

    the document.

    After the opening remarks, the agenda items were taken up for discussion by

    Superintending Engineer (Opn), WRPC.

    █ Item no. 1: Confirmation of the MinutesMinutes of 507th meeting of Operation & Coordination Sub-Committee (OCC) of

    WRPC held on 15th May, 2018 at WRPC Mumbai were forwarded vide letter No.

    WRPC/OPN/OCC-Minutes/2018-19/4720 dated 28.05.2018.

    OCC discussed a comment received from ED, SLDC, Chhattishgarh for inclusion

    in the MoM and opined that the since addition wanted by SLDC Chhattishgarh

    was not a part of discussion in 507th OCC and therefore the request of CSPTCL

    cannot be acceded.

    Sub-Committee confirmed the Minutes of 507thOCC without any modifications.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 3

    █ Item no. 2: Review of System Operation during the month of May, 2018.2.1 A. Frequency Particulars (May 2018)

    The frequency profile for last three months was as under:

    Discussions:

    SE (Opn.), WRPC informed the statistics of frequency recorded during the

    month of May 2018. The frequency particulars are enclosed at Annex-2.1.

    Chief engineer, SLDC Gujarat expressed concern about frequency touching to

    49.57 Hz. He said that that no defense mechanism is available up to 49.2 Hz

    due to which there was no AULF operation even when the grid was being

    operated at a very alarming condition. It is very difficult for system operator to

    manage the grid without any help of automatic load shedding. He further stated

    that first AULFS stage must be set at least 49.5 or 49.6 Hz with appropriate

    quantum of load shedding instead of 49.4 Hz as agreed during AULFS meeting.

    He informed that they operated Gujarat power grid without any reserve in the

    month of May, 2018.

    MP SLDC representative stated that as frequency is same in integrated grid

    operation, the load relief implemented should be implemented proportional in

    all regions of India.

    Range01st – 31stMarch,2018(% time)

    01st –30thApril,2018(% time)

    01st – 31st May,2018(% time)

    IEGC band(49.9 < f <50.05 Hz)

    79.29 79.57 70.06

    < 49.9 Hz 12.99 12.80 22.52

    > 50.05 Hz 7.72 7.63 7.42

    Particulars Frequency Date TimeMaximuminstantaneous

    50.22 Hz 3rd May, 2018 04:03:10 hrs

    Minimuminstantaneous

    49.57Hz 26th May , 2018 19:49:10 hrs

    Average 49.95 Hz

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 4

    Gujarat SLDC representative suggested that load relief mechanism implemented

    at 49.6 Hz may be designed such that frequency should rise by 0.1 Hz to 49.7

    Hz after load shedding. He stated that, All India power number is around 9000-

    10000 MW, load shedding required for increasing frequency by 0.1Hz will be

    1000 MW when divided between states it will be less than 50 MW.

    SE (Opn.) informed that during special meeting of AULFS on 13.4.2018 held at

    WRPC it was agreed to increase first stage setting to 49.4 Hz with the same

    State-wise quantum of load shedding and therefore the quantum of load

    shedding will be decided by NPC after studying the proposals received from

    different regions. He further informed that the matter is under consideration of

    NPC and the same would be deliberated thoroughly in upcoming NPC meeting

    before taking any decision with regard to stages and State-wise quantum of load

    shedding.

    Representative from WRLDC informed as below:

    The minimum frequency during the month of May’18 was 49.57 HZ

    during which Maharashtra was over drawing in Western Region.

    Section 7.1 of CERC (Deviation Settlement Mechanism and related

    matters) Regulations, 2014 mandates that no over drawal of electricity by

    any buyer shall be permissible when grid frequency is “below 49.70 HZ”

    All states are informed to initiate the actions immediately through load

    shedding/increase the intrastate generation when the frequency touches

    49.90HZ.

    GM, WRLDC opined that there shall be margin available with all the states for

    contingencies and if frequency is going downward it will be better to pick up

    from available margin. He further informed that system operators shall initiate

    actions at 49.9 Hz downwards itself.

    SE(Opn),WRPC informed that NPC vide its letter dated 30.05.2018 has given

    two options for UFR operation considering power number of 7000 MW.

    Option 1: Increasing the State-wise quantum of load shedding by keeping the

    frequency slabs same. i.e. 49.2, 49.0, 48.8 and 48.6 Hz.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 5

    Option 2: Increasing the quantum of load shedding and frequency slabs of

    operation of UFR setting. i.e at 49.4, 49.2, 49.0, 48.8 Hz.

    However, in that letter, NPC welcomed any different principle for computation of

    load relief by RPCs/NLDC.

    The Sub-Committee noted as above.

    2.1 B. State wise Power Scenarios’ of the Region & PSP

    System operation during the month of May 2018 was satisfactory. The regionaldemand (Ex-bus) was 53817 MW. The corresponding peak shortfall was in therange of 1399 MW (peak deficit of 2.60 %). The energy requirement during thesaid period was 35134 MUs (Ex-bus).The power supply position for the month of May 2018 was as follows:

    Peak Demand Availability/Unrestricted Requirement (Ex-Bus) In (MW)

    GUJ MP CG MAH GOA DD DNH ESIL WR

    REQUIREMENT 17016 8764 3663 23395 532 350 778 838 53817

    AVAILABILITY 15818 8745 3652 23254 530 350 778 838 52418

    SHORTFALL 1198 19 11 141 2 0 0 0 1399

    % SHORTFALL 7.04 0.21 0.30 0.60 0.42 0.00 0.00 0.00 2.60

    Energy Availability/ Requirement etc.(Ex-Bus) in (MUs)

    GUJ MP CG MAH GOA DD DNH ESIL WR

    Net ActualEnergySupplied 10572 5754 2330 15182 391 224 527 139 35118

    UnrestrictedRequirement 10584 5754 2333 15182 391 224 527 139 35134

    SHORTFALL 12.82 0.00 2.74 0.01 0.00 0.00 0.00 0.00 15.57

    %SHORTFALL 0.121 0.000 0.117 0.000 0.000

    0.000 0.000 0.000 0.044

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 6

    Discussions:SE (Opn.) requested CE,SLDC Gujarat to inform the OCC forum the reasons for1198 MW load shedding done by Gujarat during last month.

    CE,SLDC Gujarat informed that power shortage occurred in Gujarat due topersistent high demand, non availability of large generator, non availability ofpower in bilateral market, non availability of central sector generator for which PPAlinked, non availability of KAPS power.

    SE (Opn.) enquired with Mauda TPS representative for under generation of MaudaTPS.

    Mauda TPS representative informed that less generation is due to coal shortage inMauda plant. He informed that due to logistical issues with railways the plant isnot getting full supply of coal and management is taking up this issue withrailways. He also informed that wagon tipplers have developed cracks due to whichunloading of coal became difficult. He hoped that power situation at Mauda TPSwill be improved by 22nd June 2018.

    MS,WRPC enquired why coal shortage is present with pithead plants of NTPC.

    NTPC Sipat representative informed that plant is receiving less coal from minesthan requirement leading to coal shortage.

    MS,WRPC enquired with CGPL representative about unit#10 forced outage.

    CGPL representative informed that steam from gland of HP turbine was coming outwhich necessitated forced outage of unit#10.

    SE(Opn.) requested CGPL to make available URS power to WR needy States incases when NR beneficiaries don’t need power and they give their approval forsupply of power to WR states. He also requested CGPL to revive unit# 50 at theearliest so that the WR States in general and Gujarat in particular can easily meetthe demand with supply.

    WRPC requested to update the status of revival of KAPS unit 1 & 2. Representativefrom NPCIL informed that KAPS unit 1 & 2 will be expected to revive in the monthof October 2018 & June 2019 respectively.

    In view of the power shortage faced by the states, WRPC and WRLDC requested allthe central sector and State generators to pick up generation available with themwhen frequency falls below 49.90 Hz.

    WRPC and WRLDC also requested all states to take corrective measures whenfrequency falls below 49.90Hz.

    The Sub-Committee noted as above.

    2.1 Inter-Regional Exchanges (May-2018)There was a net inter-regional export of 6312 MUs from WR to other regionsagainst net export schedule of 6236 MUs.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 7

    (Figures are in MU)

    IR link SCH DRAWL OD/UD

    WR-ER-206 -1006 -800

    WR-NR-4357 -4746 -390

    WR-SR-1674 -559 1114

    WR NET-6236 -6312 -76

    (+ import; - export)

    The Sub-Committee noted as above.

    2.3 Voltage ProfileVoltage profile at some of 765/400 kV sub-stations furnished by WRLDC

    is enclosed at Annexure-2.3.

    Discussion:OCC forum discussed about high voltages at Dhule substation. Chief

    Engineer. SLDC Maharashtra informed that vendor is not supporting forreviving the 2x50MVAR bus reactors at Dhule substation, A new bus reactor of125 MVAR will be coming into service by July 2018.Representative from WRLDC stated as below

    Reverse reactive power flow (i.e from LV side to HV side) is observed at

    Karad (MSETCL) and Kolhapur (MSETCL) even when the voltages in the

    system are high which leads to further increase in system voltages.

    The reactive energy from wind stations is injected into system irrespective

    of the system voltages in Maharashtra in compliance to their SERC

    regulations. In view of this, Maharashtra is suggested to take up the

    matter with their SERC for regulatory changes so that wind stations will

    absorb the MVAR during high voltage condition.

    Generators also have to contribute in controlling high voltage by

    absorbing MVAR during high voltage or at least by not injecting MVAR by

    maintaining unity pf.

    OCC forum requested SLDCs to advise all DISCOMs and wind generators tocontrol MVAR flow to HV side at the time of High voltage.

    The Sub-Committee noted as above.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 8

    2.4 U/F Relay OperationsAs per WRLDC records the system frequency didn’t reach 49.2 Hz and no

    UFR operation was reported to WRLDC.

    The Sub-Committee noted as above.

    2.5 Power Cuts / Load Restrictions

    Details of Power Cuts and Regulatory measures as furnished by the State utilitiesare given in Annex. 2.5.Discussion:SE(opn) thanked all OCC members for giving power cut report in uniform format.

    The Sub-Committee noted as above.

    2.6 Details of Generating Units under Forced outages

    Details of generating units under forced outages are given in Annex-2.6.

    Discussions:

    SE (Opn), WRPC enquired about the status of revival of Wanakbori unit no. 6,

    GPCC unit 2, GPEC unit 3, Uran unit 8, Ghatghar unit 1,SGTPS unit 5,JPL stg

    II unit 1.

    CE, SLDC Gujarat informed that Wanakbori unit 6 was revived on 12th Jun2018.GPCC unit 2 and GPEC unit 3 are on reserve shutdown. SGTPS unit 5revived on 08th Jun 2018.

    SE(opn) requested for early revival of Ghatghar unit no. 1 considering lessavailability of power in the region.

    During the discussion, WRPC and WRLDC requested all entities to continuouslyupdate the reasons given for forced unit outage so that updated information can bemaintained regarding forced unit outages.

    The Sub-Committee noted the information.

    2.7 Details of Generating Units under Planned outages

    The updated details of generating units under Planned Outages are given inAnnex-2.7.

    The Sub-Committee noted the same.

    2.8 Presentation on operational aspects by SLDCs & RLDCThe group members noted the same.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 9

    2.9 List of New Grid Elements added / list of elementsdecommissioned.

    The list of New Elements added in WR Grid is attached at Annexure-2.9.

    The Sub-Committee noted the same.

    2.10 List of grid elements failure.All constituents are requested to furnish the details of grid elements failure

    (i.e. Generators, EHV transmission elements etc.).

    Discussions:

    Members were agreed to furnish the details.

    The Sub-Committee noted the same.

    █ Item no. 3: Operational Planning3.1 Proposed planned maintenance programme of generating units

    The maintenance programme of generating units for the month of May 2018& June 2018 was discussed. The finalised list of maintenance programme ofgenerating units for the months April 2018 & May 2018is given in Annexure3.1.Discussions:Representative from Gujarat informed that Sikka TPS unit 3 which is proposed foroutage from 10-07-2018 was postponed and unit will be taken out on 20-07-2018.

    Representative from Madhya Pradesh informed that Satpura TPS unit 6 was underoutage for AOH from 06th Jun 2018. Jhabua power representative informed thatunit no. 1 will be under outage from 22nd July 2018 to 13th august 2018 for A.O.H.

    Representative of Maharashtra informed that Khaparkeda unit 5 will be taken outinstead of proposed unit no 1 from 25th July 2018, Koradi unit no. 8 outage willnot be taken. Parli unit 6 will be taken out for AOH from 01.07.2018 instead ofproposed unit no. 7. JSW unit no. 2 will be taken out from 01st august 2018against scheduled date of 1st July 2018.

    Representative of NTPC Vindhyachal informed that unit no. 12 will be taken outfrom 27th July to 20th August 2018 against scheduled outage from 1st July 2018.He also requested for outage of unit no. 8 from 19th June to 28th July 2018 forwhich OCC consented.

    Representative of NTPC Solapur informed that unit no. 1 will be taken outage from31st July 2018 to 20th August 2018 against scheduled date of 26th June 2018.

    The Sub-Committee noted as above.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 10

    3.2 Outage programme of Transmission Lines/Elements.List of proposals for transmission elements outage to be availed during the

    month of July 2018 is given in Annex 3.2.

    WRPC opined that for planning the outages of transmission elements, completeinformation about the elements is essential. It was also felt that some of theagencies are not properly describing the name of elements, due to which lot ofdifficulty is being faced for considering outages. Outages planning group alsoopined the followings:

    1. In order to reduce the post OCC outage proposals, regular outages periodfor the consideration of OCC and its approval should be from fifth dayfrom the date of OCC to the last day of next calendar month basis (i.e.D+5+ Next complete calendar Month, where D is date of OCC meeting).For example, If OCC is conducted on 16th June, then outage proposalswill be discussed for the period from 21st June to 31st July ( on an average40 days approximately).

    2. The above procedure should be implemented with effect from July 2018month OCC(i.e. planning for outages for the period consisting some partof July & complete August 2018)

    3. If above procedure is implemented, then there would be some overlappingperiod for which outages might have already been approved in previousOCC and therefore review of these previous OCC approved outages shouldbe done in current OCC.

    4. Two Separate lists of outage proposal would be prepared. First list wouldcomprise regular outage whereas second list would comprise list ofoutages to be reviewed in OCC.

    5. Transmission element outage which have been planned shall be adheredto by all the concern entities.

    6. Post–OCC outages shall be minimised for better grid operation.7. The transmission licensees shall propose clearly the name of the elements

    describing its name and transmission agency, particulars of the elementin detail and reason for outage in detail, else it will not be consideredduring planning of outages.

    8. If OCC approved outage of elements are not availed and deferred byconcerned transmission agency during the last two months, this outageshall not be considered in next two month planning provided element isdeferred for system constraints. Post-OCC outages plan shall be on D-5basis only.

    9. Sometimes outages for a particular element is requested by the agenciesother than the owner of these elements. It is therefore to be noted thatonly Owner of transmission elements are entitled to request outages oftheir elements. If request is made by other entity, the same shall bedenied.

    10. The Outages planning group agreed the same.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 11

    Discussions:In addition to outage planning for July 2017, additional OCC outages for

    the month of June 2017 were also discussed in the meeting. This was discussedto reduce the post OCC outages proposals. However, the outages approved by507th OCC meeting for June 2018 month will be the first priority in the outageplan. The practice will be continued for next month onwards.

    The Sub-Committee noted and agreed as above.

    3.3 Anticipated power supply position for the months –June & July2018Details of anticipated restricted & un-restricted demands for the months ofJune & July 2018 are given in Annex 3.3.

    Maharashtra, Gujarat, MP & Chhattisgarh updated the anticipated data.

    The Sub-Committee noted the information.

    █ Item no. 4: Operational Statistics for the month of May 2018The details of actual generation, demand, drawl of power from grid;

    exchanges etc. are given in the following Annexure:

    Annexure 4.1 - Actual generation and requirement.Annexure 4.2 - Peak demand data.Annexure 4.3 - Integrated operation of the system and operation of

    Inter-state tie-lines.

    Annexure 4.7 – Details of level of major reservoirs in Western Region.

    The Sub-Committee noted the information.

    █ Item no. 5: System Disturbances in Western RegionThere was no major grid disturbance in the Western Region during the

    month of May, 2018. However the details of minor incidences during the monthreceived from WRLDC are enclosed at Annexure-5.

    The Sub-Committee noted as above.

    █ Item no. 6: Healthiness status of SERs/DRs of equipmentin the system.The updated status of Constituents who have furnished the status of

    healthiness of SER/DRs in their systems is given at Annexure-6.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 12

    WRPC enquired about entities who have not submitted the status of

    SERs/DRs of equipment in the system. Constituents assured to submit the status

    on time.

    The Sub-Committee noted as above.

    █ Item No. 7: Status of completion of ongoing schemes in WR7.1 Status of Commissioning of Reactors

    7.2 Status of Transmission schemes - 765/400 kV and above7.3 Status of Commissioning of new Generating units in WR

    The updated status of above items is at Annexure-7.

    The Sub-Committee noted the above information.

    █ Item no. 8: Miscellaneous Operational Items8.1: Quarterly review of Crisis Management Plan (CMP) and Physical &

    Cyber Security (P&CS) in power sectorAll constituents are requested to submit current status of CMP and P&CS

    report (constituent wise) for the Fourth quarter (January to March 2018) as performat enclosed at Annexure-8.1.Discussions:

    The forum requested all other constituents to submit the reports positively

    and timely.

    Sub-committee noted and agreed as above.

    8.2: Monitoring of Schemes funded from PSDFAs per the decision taken in NPC meetings, RPC may follow up with the

    utilities regularly in OCC to expedite the completion of various approvedschemes by giving due priority. Accordingly, WRPC has been taking up thisissue in OCC forum for discussion.

    In this matter, the details related to State-wise sanctioned grant anddisbursement amount for the approved schemes to be funded from PSDF isattached at Annexure-8.2A.

    Also, as per the procedure, the utilities are required to furnish theinformation in the prescribed format by first week of every month on regularbasis to Member Convener, PSDF project monitoring group (AGM, NLDC,

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 13

    POSOCO) with a copy to NPC & WRPC division. A copy of prescribed format isattached at Annexure–8.2B.

    Discussions:The utilities were requested to update the current status of progress of scheme

    under PSDF.

    The Sub-committee noted as above.

    8.3 State-wise details for Installation of capacitors to befurnished to WRPCIn accordance with provision in clause 1.5 (ii) of IEGC, “RPC shall file

    monthly report on installation of capacitors by states vis-a-vis the

    requirement/targets, as decided in the RPC”

    SLDC’s /DISCOMs are therefore requested to expedite the matter and

    ensure to furnish the status of capacitor report in format attached at Annexure8.3 on monthly basis regularly. SLDC’s are also requested to compile the detailsof various utilities and send the compiled report of entire state by 8th day of

    every month.

    The Sub-Committee noted and agreed to furnish the same.

    8.4 Review of LILO arrangement of 400 KV CGPL - Chorania atBhachau and Power order on ± 500 KV HVDC Mundra -Mohindergadh line:

    Chief Engineer, SLDC Gujarat vide email dated 07/06/2018 informedthat, at present, generation at various nodes in Gujarat is as under:

    APL, Mundra on 400 KV Bus 1500

    APL, Mundra on 220 KV Bus Zero MW

    CGPL, Mundra 3000 MW

    EPGL, Vadinar Zero MW

    Wind generation in Kutch 700 to 800 MW

    Power order on HVDC Mundra –Mohindergadh bipolar:

    More than APL generation

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 14

    He informed that under such conditions, the loading on 400 KV D/C

    Bhachau - Varsana line remains @ 500 MW in each circuit. To control loading

    on 400 KV D/C Bhachau – Varsana line, 400 KV Varsana – Kansari or 400 KV

    Varsana – Hadala line keeps open frequently.

    In order to avoid above situation, CE, SLDC Gujarat suggested that

    the LILO arrangement of 400 KV CGPL – Chorania line at Bhachau to be

    removed to reduce injection at Bhachau node OR the power order on ± 500 KV

    HVDC Mundra - Mohindergadh line to be kept below generation at APL, Mundra

    complex.

    Discussions:CE, SLDC Gujarat briefed OCC forum that under the conditions stated in the

    above table, frequent opening of STU lines is occurring. In order to avoid this

    condition, one of the CGPL-Bhachau line may be connected directly at

    Chorania. He informed that STU lines are being opened frequently because of

    constraints in CTU network. He also informed that availing of outages at

    Bhachau and Varsana substations are becoming difficult in the present

    scenario.

    Representative from WRLDC stated as below

    Studies have been already carried out to review bypassing of LILO

    arrangement of 400kV CGPL-Chorania at Bhachau. It is observed from

    the studies that there is very less impact of bypassing LILO arrangement

    at Bhachau on the loading of 400kV D/C Bhachau-Varsana D/C line. The

    results were already shared with SLDC Gujarat. Further, less generation

    at APL and Bachhau-Versana being very short line is the main reason for

    overloading.

    In the real time grid operation, the LILO has helped to reduce the loading

    on CGPL-Bachhau lines during full generation at CGPL and no generation

    backing down is required for single ckt outage from CGPL. SPS at CGPL

    as suggested by WRLDC in 132nd PCM( removal of SPS for single ckt

    outage of Bachhau lines and double ckt outage of Jetpur lines) is also

    implemented by CGPL.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 15

    400 KV Varsana – Kansari or 400 kV Varsana – Hadala linesare not being

    opened frequently to control the loading on 400kV D/C Bhachau-Varsana

    line except for extreme contingencies. In May 18, CGPL generation was

    around 3000MW and APL generation also picked up around 1200-

    1800MW, therefore Bachhau-Versana loadings were normal.

    During the month of June’18 (up to 14/06/18), 400kV Varsana-Kansari

    was opened only once (08:22 hrs of 05.06.18 to 11:02 hrs of 07.06.18)

    when HVDC Mundra-Mohindragarh flow was increased when there were

    multiple trippings in the grid due to tower collapse. Due to forced

    outages of 765kV Agra-Gwalior-1 ,765kV Satna-Bina-2, 800kV Champa-

    Kurukshetra HVDC Pole-2, power flow on Mundra-Mohindergarh-HVDC

    Bipole increased for line load controlling on 765kV Satna-Oraiduring

    which the maximum power flow on 400kV Bachau-Varsana D/C was

    570MW/Ckt.

    The power flow pattern of important WR-NR lines, Bachhau-Varsana-D/C

    lines and HVDC line flows for the month of May’18 is shown below

    MS, WRPC informed that as the plan is approved in SCM, change of network

    conditions requires SCM approval.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 16

    After long delibration, DGM, WRLDC agreed that 400 KV Varsana – Kansari or

    400 kV Varsana – Hadala lines will not be opened regularly to control line

    loading, but in case of credible contingency in the grid , appropriate actions will

    be taken to ensure grid security .

    Decision:(1) WRLDC shall not open 400 KV Varsana – Kansari or 400 kV Varsana –

    Hadala lines regularly during normal operation of grid.(2) In case of contingency in the grid, WRLDC shall take appropriate action

    including opening of above lines based on real time situation.(3) Status quo shall be maintained for LILO arrangement of 400 KV CGPL -

    Chorania at BhachauThe Sub-Committee noted the same.

    8.5 Creation of GIS based energy map of India by NITI Aayog.NITI Aayog is developing a user friendly GIS based Energy map of India,

    which would provide true locations of all energy resources in India including

    power plants, coal and oil reserves, transmission lines, refineries etc. MoP

    designated CEA as the nodal agency to collect all the data pertaining to the

    power sector of India by collecting it from different utilities of power sector and

    submit it to NITI Aayog for early development of GIS energy map of India.

    Accordingly, CEA sent letters dated 09/02/2018 and

    01/05/2018(Attached as Annexure-8.5.1) vide which DP&T Division of CEA

    requested heads of DISCOMs/Power departments of states to furnish data as

    per format attached at Annexure-8.5.2. However, data not have been received by

    DP&T Division from the DISCOMs.

    All SLDC are requested to coordinate with Discoms and provide data in

    prescribed format attached at Annexure-8.5.2 by 22/06/2018 to CEA vide email

    to [email protected] under intimation to this office on email ([email protected]).

    Discussion:

    SE(Opn.)requested all the SLDCs to coordinate with concerned DISCOMs

    and Transcos to furnish the requisite information in prescribed format directly

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 17

    to CEA through email on [email protected] under intimation to WRPC on email

    ([email protected]).

    CE, SLDC Gujarat informed that the information with regard to 11 KV and

    above substations are available with GETCO and therefore they coordinate

    with STU to furnish the information in time..

    CE, SLDC Maharashtra informed that in Maharashtra network, 33 KV

    substations are maintained by DISCOM and 132 KV and above Substations are

    maintained by MSETCL and therefore they will coordinate with them to give

    details in time. For Maharashtra, the requisite information would be furnish by

    DISCOMs and STU.

    SE(opn.) requested SLDC Maharashtra representative to coordinate with Private

    DISCOMs such as Reliance Infrastructure, BEST and TATA Power Co. for

    furnishing information to CEA. CE, SLDC Maharashtra agreed to coordinate

    with Private DISCOMs in Maharashtra.

    SLDC Madhya Pradesh representative informed that in MP, 33 KV substations

    are maintained by DISCOM and 132 KV Substations are maintained by

    MPPTCL and therefore data will be provided by DISCOMs and STU.

    SLDC Chhattisgarh representative informed that in Chhattisgarh, 33 KV

    substations are maintained by DISCOM and 132 KV Substations are

    maintained by CSPTCL. He further stated that they would coordinate with them

    to furnish details to CEA in time.

    Member Secretary, WRPC requested all Transco & Discoms to furnish the data

    in prescribed format in time bound manner.

    After long discussion, the members agreed on following :

    (1) All SLDC shall coordinate with their DISCOMs and STU to furnish the

    information in prescribed format to CEA in time.

    (2) Maharashtra SLDC shall also coordinate with the private DISCOMs i.e.

    Reliance Infrastructure, BEST and TATA Power Co. to furnish the

    information in prescribed format to CEA in time.

    The Sub-Committee noted the same.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 18

    8.6 Additional RoE for transmission elements of PGCIL under“inter-regional system strengthening scheme in WR and NR(part-b)” project commissioned within CERC specifiedtimeline.

    AGM (commercial), PGCIL requested WRPC to issue certificate for earlycommissioning of transmission elements as per CERC tariff regulation 2014-19 Chapter 6, clause 24(iii) which states that

    “additional RoE of 0.5 % may be allowed if any element of the transmissionproject is completed within the specified timeline and it is certified by theregional power committee/national power committee that commissioning ofthe particular element will benefit the system operation in theregional/national grid.”

    Sr.No.

    Name of theproject

    Name of the asset Zerodate ofproject

    Timeline ofproject issuedby CERC (inmonths)

    DOCO

    1

    Inter-RegionalSystemstrengtheningscheme in WR andNR (Part-B)

    Conversion of existingline reactor at Gwaliorend of Satna-GwaliorCkt-1 TL (to be LILO atOrai) in to switchableline reactor 24th Dec

    2014

    36(Targeted dateof completion24th Dec 2017)

    01stApril2017

    2 765 KV D/c JabalpurPooling station - Orai TLalong with 2*330 MVARLine Reactor along withBay Extension at765/400 kV JabalpurPooling Station & 02 nos765 Jabalpur Line baysalong with 2*330 MVARline reactor at Orai S/s

    40 (Targeteddate ofcompletion 24thApril 2018)

    31stMarch2018

    3 LILO of one circuit of 765KV Satna-Gwalior TLalong with 765 kV SatnaLine Bay at Orai SubStation & 240 MVARLine Reactor at Orai S/sand 765 kV Gwalior bayat Orai S/s

    40 (Targeteddate ofcompletion 24thApril 2018)

    31stMarch2018

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 19

    Discussion:

    SE(opn.) briefed the OCC forum about the request made by M/s PGCIL and asked

    AGM(Commercial), PGCIL for additional clarifications.

    1. Whether Conversion of line reactor into switchable line reactor is eligible for

    additional RoE?

    2. Whether the time line of 36 month for carrying out the work listed at sr. no.

    1 is in line with the regulations?

    3. PGCIL may furnish details of discussion with regard to planning of the

    elements in SCM PGCIL representative replied that all the elements

    mentioned at sr. No. 1 to 3 are part of Inter-Regional System strengthening

    scheme in WR and NR (Part-B). He stated that the time line given against

    element at sr. No. 1 is actually a time line for a transmission line given in

    regulation. During discussion, CE, SLDC Gujarat and CE, SLDC

    Maharashtra agreed that the commissioning of all the elements mentioned

    above have definitely benefitted the system operation in the regional grid

    however they expressed their disagreement on 36 month time line for

    element at sr. No. 1 (for conversion of line reactor into switchable line

    reactor). They jointly stated that the work of conversion of line reactor into

    switchable line reactor need very little time and expressed concern about the

    timeline of Sr No.1 and requested to review the timeframe.

    SLDC MP representative said that Element at Sr No.1 does not qualify for RoE.

    WRLDC representative informed that:

    1. Switchable line reactor isolates the reactor in case of fault in reactor andline tripping will be avoided.

    2. Due to the commissioning of Jabalpur Orai double ckts along with linereactors, ATC and TTC of WR to NR increased.

    3. Due to the LILOing of Satna-Gwalior at Orai S/s, loading of Gwalior-Agralines has been reduced substantially.

    After long discussion, all states agreed that the elements at sr. No. 2 and 3 are

    beneficial for system operation in the regional grid may qualify for additional

    RoE.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 20

    At the end of discussion, the following decision were taken:

    (1) PGCIL & WRLDC shall prepare list of benefits due to early commissioningof all the three elements which are under consideration for additionalROE in accordance with the regulation.

    (2) WRLDC shall explain the listed benefits due to early commissioning of allthe three elements to the forum in the next OCC meeting.

    The Sub-Committee noted the same.

    Item No. 9. WRLDC Agenda Items

    1. Primary Frequency ResponseThe average primary response of generators for last three events are

    shown below.

    S.No

    Generator/Station

    Event-1 Event-2 Event-3 AverageResponseas % ofIdeal

    ER-1250 SR-935 WR-309030/01/1810:46:20

    07/03/1809:38:20

    23/04/1810:42:00

    49.90 49.98 50.0349.84 50.05 49.72-0.06 0.07 -0.31

    1Mouda-II (1x660) 125% 27% 51% 68%

    2 Mouda-I(2x500) 134% 0% 54% 63%3 KSTPS-II(3x500) 35% 85% 30% 50%

    4APMLTiroda(5x660)

    39% 50% 14% 35%

    5 TRN (1x300) 7% 86% 0% 31%6 VSTPS-V(1x500) 36% 37% 14% 29%7 SKS (1x300) 5% 75% 0% 26%8 APL-III(3x660) 48% 28% 0% 25%9 KSTPS-I (3x200) 37% 12% 25%

    10Kawas(4x106+2x116)

    0% 40% 20% 20%

    11 DB Power(1x600) 0% 53% 0% 18%

    12JPL Tamnar (StageII)(3x600)

    43% 1% 8% 17%

    13GMR Warora(2x300)

    48% 2% 0% 17%

    14 Jhabua (1x600) 48% 0% 0% 16%15 MB Power(1x600) 14% 17% 10% 14%16 SIPAT-I(3x660) 11% 19% 4% 11%17 Balco (4x300) 9% 17% 1% 9%

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 21

    18 SIPAT-II(2x500) 22% 0% 4% 9%19 Lanco (2x300) 24% 0% 0% 8%20 VSTPS-IV(2x500) 0% 15% 8% 8%21 CGPL(5x830) 9% 3% 9% 7%22 SASAN(6x660) 18% 0% 4% 7%

    23Gandhar(3x144+1+224)

    19% 0% 0% 6%

    24 VSTPS-I (6x210) 13% 0% 0% 4%25 MCPL (1x300) 12% 0% 0% 4%26 VSTPS-III(2x500) 0% 0% 6% 2%27 JPL I (4x250) 5% 0% 0% 2%

    28EssarMahan(1x600)

    0% 0% 1% 0%

    29 NSPCL (2x250) 0% 1% 0% 0%30 VSTPS-II(2x500) 0% 0% 0% 0%31 JP NIGRIE(2x600) 0% 0% 0% 0%32 SSP-CBPH (5x50) 0% 0% 0% 0%

    Generating stations whose frequency response is below 40% may apprise OCC,

    actions being taken to improve the frequency response.

    Discussions:Representative from WRLDC stated as under

    Vide its order dated 31st July 2017 and 5th amendment of IEGC, Hon’ble

    CERC reiterated the mandate for providing primary frequency response

    Non-compliance of FGMO/RGMO provision is liable for penal actions

    under Section 142 / reduction of 1% on RoE

    Hon’ble CERC had mandated conducting of periodic check-up of the

    governing system by independent agencies at the cost of the generating

    stations being tested

    Procedure for testing of primary frequency response of generators as per

    IEGC clause 5.2(g) is being prepared by NLDC and the same would be

    submitted to Hon’ble CERC for approval

    In view of the above, all generating stations mentioned above whose

    response is below 35 % are requested to ensure compliance to the

    regulations

    CGPL and NSPCL informed that the governor tuning at their stations was

    completed and now, the governors are compliant of IEGC Regulations 5.2 (f), (g),

    (h) & (i).

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 22

    VSTPS-II informed that governor tuning was completed and the new logic would

    be implemented by 31/05/18.

    VSTPS-I, III, IV & V stated that the logic implemented for frequency response

    would be reviewed and further tuning of governors will be done.

    The sub-committee noted the same.

    2. Voltage Regulation in Western Region

    In the month of April’18, voltages were above IEGC band at 765kV Durg, 400

    kV Dhule, Wardha, Raigarh, Kalwa, Dehgam and Karad. The Voltage Deviation

    Index of above nodes are tabulated below.

    S No. Voltage(kV)

    StationName

    % time Voltage is> than IEGCthreshold

    VoltageDeviationIndex

    1 765 Durg 14.83 0.15

    2 400 Dhule 53.47 0.53

    3 400 Wardha 33.70 0.344 400 Raigarh 30.06 0.305 400 Kalwa 23.28 0.236 400 Dehgam 21.90 0.227 400 Karad 14.46 0.14

    Concerned utilities to update the status of revival of following bus and line

    reactors that are under prolonged outage.

    S.No Element Owner Outage Date Reason

    1 80 MVAR BR atDhariwal

    DIL 22/07/2017 Oil leakage

    2 50 MVAR LR of400 kV Parli-Lonikhand_New-2 @Parli (MH)

    MSETCL 30/10/2015 Fire Accident inL/R

    3 80 MVAR LR of400 kV Karad-Lonikhand-1@Karad

    MSETCL 14/09/2017 R&Y Phase LABurst

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 23

    4 50MVAR LR of400kVChandrapur-Parli Ckt-3 LR atboth ends

    MSETCL - -

    5 80MVAR LR of400kVKhandwa-Seoni-2 LR @ Seoni

    POWERGRID 11/12/17 ForCommissioningof new TBEAmake LR

    6 63MVAR LR of400kVVindhyacha-Jabalpur-2@Jabalpur

    POWERGRIS 30/04/18 High AcetyleneGas contentissue

    7 50MVAR LR ofVindhyachal-Satna-3@Satna

    POWERGRID 01/04/18 Heavy oilleakage in RPhase bushing

    8 80 MVAR BR atEssar Mahan

    Mahan 04/04/18 Bus ReactorAbnormal Sound

    OCC members may like to deliberate on the following issues

    a. All the SLDCs may apprise the OCC regarding the actions taken to

    control the over voltages at above mentioned nodes.

    b. Concerned utilities to expedite revival of the bus reactors and line

    reactors under prolonged Outage LR would further help in for better

    voltage regulation.

    Discussions:Representative from WRLDC stated as under

    Concerned states to ensure the voltage regulation near by the above

    mentioned substations by regulating MVAR injection from nearby

    generating stations and through capacitor switching

    In the coming months during Monsoon, the voltage profile is expected to

    be on further higher side. All states to closely monitor and control the

    MVAR flow from LV side to HV sideand taking up with S/S personnel to

    switch off capacitors at LV and down below level

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 24

    Concerned utilities to restore bus reactors and line reactors which are

    under prolonged outage.

    Status given by concerned utilities is as under

    S.No Element Owner Outage Date Reason Expected revivaldate (Status in507th OCC)

    1 80 MVAR BR atDhariwal

    DIL 22/07/2017 Oil leakage Dec’18

    2 50 MVAR LR of400 kV Parli-Lonikhand_New-2 @Parli (MH)

    MSETCL 30/10/2015 Fire Accident inL/R

    24.05.18

    3 50MVAR LR of400kVChandrapur-Parli Ckt-3 LRat both ends

    MSETCL - - June’18

    WRPC would communicate to GMR Chhattisgarh who were not present in the

    OCCM to revive 125MAVR B/R at the earliest.

    Further, the group formed as per decision in 506th OCCM would study and

    submit the report with remedial suggestions to control high voltage.

    The sub-committee noted the same.

    3. MVAR absorption by Generating station to control high voltageEven after taking Bus Reactors, Line Reactors, Switchable Shunt Reactors inservice and opening lightly loaded lines, high voltages are observed at most ofthe EHV nodes during night hours. In view of inadequate shunt reactivecompensation, the generating units are being advised to contribute in voltageregulation by operating their units in under-excited mode (absorb ReactivePower) within the capability curve. The MW, MVAR and Voltage of generatingunits was analyzed for the month of May 18 with the help of SCADA dataavailable at WRLDC. The list of generators injecting MVAR into the grid evenwhen the bus voltage is above nominal are given below.

    1. IPPs: Essar Mahan, RKM, GMR-CG, Dhariwal, DB Power, Jhabua, TRN2. ISGS: KSTPS (U#3, U#2), Mouda-I3. Gujarat: Essar Vadinar (U#1 & U#2), Wanakbori (U#4, U#5 & U#6)4. Maharashtra: Koradi (U#8 & U#9), Bhuswal (U#4 & U#5);

    Chandrapur(U#7)

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 25

    5. M.P. JP Bina(U#1, U#2), Satpura (U#10 & U#11), Singhaji (U#1 & U#2)All the concerned utilities to update the plan to adjust setting of the AVR / GTtap so as to enable generating units to contribute in voltage regulation withincapability curve.

    Discussions:WRLDC informed generating stations whose contribution is inadequate for

    reviewing/adjustment of AVR settings and GT tap so as to enable generating

    units to contribute in voltage regulation within capability curve.

    The sub-committee noted the same.

    4. Tower collapse due to bad weather condition in Maharashtra and MadhyaPradesh

    It was observed that due to widespread rain and storm in Maharashtra and

    Madhya Pradesh, following EHV lines tripped.

    S.No Element Name Owner

    OutageDate

    Outage Time Reason

    1

    765kVJabalpur(PS)-Bhopal(BDTCL)-S/C

    Sterlite 18/05/2018 16:29R-E fault; Tower damaged@location 2A/3

    2765kVSatna(PG)-Bina(PG)-II

    PGCIL 30/05/2018 19:31R-Y Fault.;Tower bent atlocation 63

    3 765kV Tiroda-Koradi(3)-II ATIL02/06/2

    018 20:15

    Suspension tower is collapsedat location 357(13.18KM)&caused damage to theadjoining towers

    4 400kV Dhule-Bableshwar-IIMSETC

    L01/06/2

    018 16:42R-Y-B fault, ;Towers collapsedbetween locations 118-122

    5 400kV Dhule-Bableshwar-1MSETC

    L01/06/2

    018 16:42R-Y-B fault, ;Towers collapsedbetween locations 118-123

    6 765kV Bilaspur-Dharamjaygarh PGCIL27/04/2

    018 18:02

    Tower Collapse at locations121 & 122(Revived on 11/05/18 at22:18 hrs)

    The outage of 765kV Satna(PG)-Bina(PG)-II has reduced the security ingeneration evacuation from VSTPS, Sasan, Rihand-III and Jaypee Nigrie.Tripping of one of 765kV Satna-Bina/765 Satna-Gwalior/765kV Satna-Oraicircuits would require forced generation backing down of about 2000 MW atSasan/Rihand-III & Vchal IV,V & Jaypee Nigire.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 26

    Concerned utilities are requested to restore the above mentioned lines onEmergency Restoration Scheme (ERS).

    Discussions:During the meeting status given by concerned utilities is as under

    S.No

    Element Name OwnerOutageDate

    OutageTime

    Expected revivaldate(Status in 508thOCC)

    1 765kV Jabalpur(PS)-Bhopal(BDTCL)-S/C Sterlite18/05/2

    018 16:2916/06/18(NormalRestoration)

    2 765kV Tiroda-Koradi(3)-II ATIL02/06/2

    018 20:15 16/06/18 (ERS)

    3 400kV Dhule-Bableshwar-II MSETCL01/06/2

    018 16:42 31/07/18

    4 400kV Dhule-Bableshwar-1 MSETCL01/06/2

    018 16:42 31/07/18

    5 400kV Birsingpur-Damoh I & II MPPTCL12/06/2018 19:50 -

    6 765kV Bilaspur-Dharamjaygarh PGCIL27/04/2

    018 18:02Revived on11/05/18 at22:18 hrs

    7 765kV Satna(PG)-Bina(PG)-II PGCIL30/05/2

    018 19:31Revived on11/06/18 at13:09 hrs

    Concerned utilities are informed to revive the reactors at the earliest for better

    voltage regulation.

    The sub-committee noted the same.

    5. Tripping of Kalwa(MSETCL) 400/220kV ICT-2 at 01:02hrs of 01.06.18400/220kV ICT-2 (600MVA) at Kalwa tripped at 01:02hrs of 01.06.18 due tooperation of PRV and differential protection. Subsequently, 400/220kV ICT-1(500MVA) at Kalwa was hand tripped at 01:30hrs of 01.06.18 to avoid thespreading of fire from ICT-2.Due to this, load trimming scheme was operated and load was effected to a partof Navi Mumbai and Mulund. Load loss of around 304 MW was reported byMaharashtra. Subsequently, the damaged cables were replaced with new cablesand the ICT-1 was charged on 03.06.18 at 13:42 hrs.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 27

    Further, the telemetry data of 220kV Maharashtra system is not available atWRLDC, due to which the assessment of real time conditions in the affectedarea is not possible.In view of the above, Maharashtra is requested to expedite the restoration of400/220kV ICT-2 (600MVA) at Kalwa and take necessary actions to make220kV telemetry data available at WRLDC.

    SLDC, Maharashtra may apprise the OCC regarding the actions taken to controlthe Kalwa ICT loading and the details of load management in Mumbai area inview of above contingency.

    Discussions:Maharashtra informed that following actions were taken to control the Kalwa

    ICT loading on 01.06.18.

    LTS scheme operated and 250MW load relief was obtained

    Generation from Tata hydro/gas increased

    Ghatghar unit-1 (125MW) taken in service

    Maharashtra said that the ICT-IV at Kalwa would be commissioned within 4

    months.

    The sub-committee noted the same.

    6. Constraints in keeping the thermal units on-bar to manage the highdemand in day time and less demand during off peak hours

    It was observed that, due to bad weather condition and rains, the demand inWestern Region during off peaks hours was less and the demand in day timewas considerably high. Due to less demand in off peak hours, the states weresurrendering their share in IGGS generators, leading to the condition of belowtechnical minimum schedule in some ISGS thermal generators. It is observedduring last week that the difference in WR maximum demand to minimumdemand is ranging from 5000MW to 6500MW. In order to meet the highdemand in day time, the thermal generating stations for which schedule isbelow technical minimum are supported up to technical minimum. Thevariation in WR demand for a typical day (02/06/18) is shown below.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 28

    All states are requested to stagger their load to avoid the condition of technicalminimum in thermal stations during off peak hours in view of high anticipateddemand in day time.

    Discussions:WRLDC informed all states to stagger their load and give the requisition to avoid

    the condition of below technical minimum in thermal stations during off peak

    hours in view of high anticipated demand in day time.

    The sub-committee noted the same.

    7. Delayed/Non submission of DR for grid eventsThe utilities need to submit the DR/EL details for Grid events to RLDC within24 hours of occurrence as per IEGC 5.2(r).The non-submission /delayedsubmission of details from utilities lead to delay in detailed analysis of theevent. For the events DR/EL is still pending is attached at Annexure 9.7:Discussions:All the concerned utilities mentioned above are informed to submit the DR/ER

    by 18/06/18 and comply IEGC 5.2(r) for future grid events.

    The sub-committee noted the same.

    Minutes of 508thOCC meeting held on 14th June, 2018 Page 28

    All states are requested to stagger their load to avoid the condition of technicalminimum in thermal stations during off peak hours in view of high anticipateddemand in day time.

    Discussions:WRLDC informed all states to stagger their load and give the requisition to avoid

    the condition of below technical minimum in thermal stations during off peak

    hours in view of high anticipated demand in day time.

    The sub-committee noted the same.

    7. Delayed/Non submission of DR for grid eventsThe utilities need to submit the DR/EL details for Grid events to RLDC within24 hours of occurrence as per IEGC 5.2(r).The non-submission /delayedsubmission of details from utilities lead to delay in detailed analysis of theevent. For the events DR/EL is still pending is attached at Annexure 9.7:Discussions:All the concerned utilities mentioned above are informed to submit the DR/ER

    by 18/06/18 and comply IEGC 5.2(r) for future grid events.

    The sub-committee noted the same.

    Minutes of 508thOCC meeting held on 14th June, 2018 Page 28

    All states are requested to stagger their load to avoid the condition of technicalminimum in thermal stations during off peak hours in view of high anticipateddemand in day time.

    Discussions:WRLDC informed all states to stagger their load and give the requisition to avoid

    the condition of below technical minimum in thermal stations during off peak

    hours in view of high anticipated demand in day time.

    The sub-committee noted the same.

    7. Delayed/Non submission of DR for grid eventsThe utilities need to submit the DR/EL details for Grid events to RLDC within24 hours of occurrence as per IEGC 5.2(r).The non-submission /delayedsubmission of details from utilities lead to delay in detailed analysis of theevent. For the events DR/EL is still pending is attached at Annexure 9.7:Discussions:All the concerned utilities mentioned above are informed to submit the DR/ER

    by 18/06/18 and comply IEGC 5.2(r) for future grid events.

    The sub-committee noted the same.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 29

    8. Grid Occurrence on 03rd June 2018 at ACBIL Power station due to Badweather conditions

    On 03rd June 2018 at 16:22 Hrs, 400 kV MCCPL- Bilaspur tripped. Further at16:26Hrs 400 kV ACBIL-MCCPL and 400 kV ACBIL-Bilaspur tripped. Thisresulted in tripping of all the generators in both the power station due to loss ofevacuation path and led to a loss of 654 MW generation. The list of elementstripped are given below:-

    400 kV MCCPL- Bilaspur 400 kV ACBIL - Bilaspur 400 kV MCCPL- ACBIL Unit #1 ACBIL (135 MW) Unit#2 ACBIL (135 MW) Unit#1 ACBIL Chakabura (30 MW) Unit#2 ACBIL Chakabura (30 MW) Unit#1 SCPL (50 MW) Unit#2 SCPL (50 MW) Unit#1 MCCPL (300 MW).

    Discussions:

    WRLDC informed that the 400kV MCCPL-Bilaspur tripped on 03/06/18 at

    16:22 hrs on B phase to Earth fault during which A/R at MCCPL was

    unsuccessful. ACBIL to share the complete tripping details during the next

    Protection Committee Meeting (PCM).

    The sub-committee noted the same.

    9. Updating the “List of Important Grid Elements in Western Region –2018”

    In compliance with IEGC-5.2(c) document titled “List of Important GridElements in Western Region” has been updated in coordination with WR stakeholders during the 498th, 503rd and 507th OCCM. The updated document isavailable at following URL links

    a. http://wrldc.org/docs/LIST%20OF%20IMPORTANT%20GRID%20ELEMENTS%20Updated%20on%20May%202018.pdf

    b. http://wrldc.in/content/363_1_Procedures.aspx

    The sub-committee noted the same.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 30

    10. Updating the “Operating Procedure for Western Regional Grid”In compliance with IEGC-5.1(f) document titled “Operating Procedure forWestern Regional Grid” was prepared and was last updated on 20th July’2017.The document is available at following link.

    a. http://wrldc.org/docs/WR_OPERATING_PROCEDURE_2017.pdf

    WR entities may provide the feedback and suggestions for updating OperatingProcedure for Western Regional Grid for the year 2018.

    Discussions:WRLDC informed all utilities to give feedback and suggestions by 25/06/18 for

    updating Operating Procedure for Western Regional Grid for the year 2018

    The sub-committee noted the same.

    11. Black Start mock drill Exercise in Western RegionAs mandated by IEGC, the Black start capable units need to conduct mockblack start exercises once in every 6 months. Western Region has 29 generatingstations with black start capability. As per the information available withWRLDC, only 8 black Start stations have completed the Mock exercise in theyear 2018 as given below.

    S.NO Generating Station Date of mock drill exercisedone1 CLIPL, Gujarat 2nd Jan 20182 Tons, Madhyapradesh 23rd Jan 20183 GIPCL-I, Gujarat 6th Feb 2018

    4 Indira Sagar,Madhyapradesh 10th Feb 2018

    5 Kadana, Gujarat 4th March 20186 Ukai, Gujarat 4th March 20187 Bargi, Madhyapradesh 11th April 20188 Pench, Madhyapradesh 11th April 2018

    Constituents/regional entities are requested to plan the Mock exercise oftheir black start units and submit their plan for compliance of IEGCregulation 5.8(b).

    Discussions:WRLDC informed all Constituents/regional entities to complete the mock

    exercise of their black start units in compliance to IEGC regulation 5.8(b).

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 31

    Maharashtra informed that the black start mock drill exercise of Koyna isplanned in the last week of June’18. The exact date would be communicated toWRLDC once it is finalized.

    The sub-committee noted the same.

    12. Follow-up of agenda items discussed in past OCC meetingi. Installation of PMU for observability of dynamic performance of

    STATCOMsFor dynamic reactive VAR compensation in Western Region, fourSTATCOM’s were approved in 36th SCM of WR. In order to monitor thedynamic performance of the STATCOM+ MSR / MSC, it is desired toinstall PMUs at STATCOM locations (SATNA PG, Gwalior PG, AurangabadPG and Solapur PG). The matter was already discussed in the 505th, 506thand 507th OCC meeting.

    Discussions:POWERGRID informed that the STATCOMs can be integrated with the existing

    PMUs by replacing any one of the feeders integrated to PMU.

    WRLDC informed that the list of lines to be replaced with STATCOMs for

    integration with existing PMUs would be forwarded to POWERGRID.

    The sub-committee noted the same.

    ii. Synchronous Condenser Mode of Operation at GhatgharDuring 505th& 506thOCC meeting, WRLDC advised Maharashtra SLDCto explore the possibilities of operating Ghatghar machines insynchronous condenser mode of operation to improve the voltageprofile at 220 kV Ghatghar and 220 kV Kalwa.

    Maharashtra SLDC vide its email dated 23.04.18 submitted theconcerns of Ghatgar Hydro Power Stations to operate the machines incondenser mode as given below. Operation in condenser mode requires the continuous water

    depression of draft tube. This is achieved by the pressurized airfrom the water depression compressor. These compressors areimported compressors and there are issues in the procurement ofthe spares for these compressors.

    There is no mention about the operation of machines in condensermode in the power purchase agreement (PPA). Being a policymatter, the proposal to be put up with higher officials.

    During 507th OCCM, it was requested Maharashtra to submit the finalopinion by 22.05.18 after discussion with their higher management.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 32

    And it was also requested to share the detailed concerns for operatingGhatgar machines in condenser mode.

    Discussions:WRLDC said that the proposal is being discussed from 505th OCCM. The

    view and concerns from Maharashtra are yet to be received. Maharashtra

    is once again informed to take up the matter with their higher

    management and inform the same at the earliest.

    The sub-committee noted the same.

    iii. Compliance to LVRT by Wind Turbine Generators connected at 66kV and aboveRegulation Part II (B2) (3) and Part II (B3) of the CEA (TechnicalStandards for Connectivity to the Grid) Amendment Regulations, 2013notified on 15th October 2013 and the CERC order dated 05.01.16 inPetition No.420/MP/2014 mandates compliance of LVRT in all WindTurbine Generators (except for Stall Type WTGs) having capacity morethan 500 kW connected to voltage level of 66 kV and above.

    During 504th, 506th OCCM and 3rd REIF meeting, WRLDC highlightedthe importance of LVRT to prevent simultaneous loss of generationfrom RES. All SLDCs were informed to compile the information asfollowing.a. Capacity of RES in the State that is exempted from LVRT : Stall

    type / Capacity below 500 kWb. Capacity of RES in the State that is mandated to have LVRTc. Capacity of RES in the State that is LVRT compliantd. The present methodology of checking LVRT compliance in vogue for

    giving clearance for integrationGujarat and Madhya Pradesh submitted the data during 3rd REIF heldon 17.04.18.

    Discussions:Maharashtra informed that the required inputs has been sent to WRLDC

    on 13/06/18.

    WRLDC informed that the inputs received would be verified and updated.

    The sub-committee noted the same.

  • Minutes of 508thOCC meeting held on 14th June, 2018 Page 33

    iv. Parallel operation of 220kV Kolhapur_MS(WR)-Chikodi(SR)and220kV Talangade-Chikodi lines with other WR-SR Inter Regionallines220kV Kolhapur_MS(WR)-Chikodi(SR) and 220kV Talangade-Chikodilines are natural interstate line between Maharashtra in WR andKarnataka in SR. These lines are operated in radial mode to supplypower from Maharashtra to Karnataka.During 505th& 506th OCC meeting, WRLDC shared the merits ofutilization of 220kV Kolhapur_MS(WR)-Chikodi(SR) and 220kVTalangade-Chikodi lines for inter-regional power transfer with ISTSstatus.During 507th OCCM, WRPC informed Maharashtra to take up thematter with Maharashtra STU and Karnataka with a copy ofcommunication to WRPC and WRLDC.

    Discussions:Maharashtra raised the concerns on overloading on Kolhapur ICTs during

    summer.

    WRLDC informed that ICT loading was analyzed for last one year and

    shared during 505th OCCM in which ICTs loading were normal except few

    days. And this ICTs overloading can be addressed by implementing inter

    tripping scheme.

    Maharashtra requested WRLDC to share the analysis on Kolhapur ICTs to

    take up the matter with STU. WRLDC agreed to sharethe study results

    with Maharashtra.

    Members of OCC suggested that the lines may be taken into operation as

    there are constraints only during few months. In case of high loading of

    Kolhapur ICTs in any time, the lines can be opened. He requested MSLDC

    to take action for parallel operation.

    The sub-committee noted the same.

    Item No. 10: Date and venue of next OCC meeting

    The date & venue of 509th OCC meeting will be intimated later on.

    The sub-committee noted the same.

    **********************

  • ANNEXURE A

    Sl.No. Organisation, Name & Designation Mobile No. E-mail Address

    I WRPC1 Shri A. Balan, M.S. 9483540528 [email protected] Shri J.K. Rathod, S.E. 9987910799 [email protected] Shri K.B. Jagtap, S.E. 86527760334 Shri L.K.S. Rathore, E.E. 9833371844 [email protected] Shri P. Peddi Reddy, A.D.-I 7840894702 [email protected] Shri B.V. Sandeep, A.D.-I 8527622170 [email protected]

    II GETCo. / GSECL7 Shri B.B. Mehta, C.E. 9879200736 [email protected] Shri B.M. Shah, D.E. 9925212836 [email protected] Shri G.K. Gohel 9925208588 [email protected]

    III MSETCL / MSEDCL/MahaGenco/MSPGCL10 Shri Anil V. Kolap, C.E. 7030964444 [email protected] Shri P.S. Sharma, S.E. 9769213865 [email protected]

    IV MPPTCL / MPPGCL12 Shri S.S. Patel, S.E 9425805270 [email protected] Shri Sushil Kumar Pal, A.E. 9425806638 [email protected] Shri Shikhar Nema, A.E. 9425805299 [email protected]

    V CSPTCL15 Shri A.K. Shrivastava, Addl.C.E. 9827177466 [email protected]

    VI POSOCO/WRLDC16 Shri Abhimanyu Gartia, G.M. 9869088058 [email protected] Shri K. Muralikrishna, D.G.M. 9869450219 [email protected] Shri N. Roy, D.G.M. 9869080265 [email protected] Smt. Pushpa S., Asst. G.M. 9869404482 [email protected] Shri Pradeep Kumar Sanodiya, Sr. Eng. 8452045338 [email protected] Shri Ch. Jagadeesh, Sr, Eng. 9869469376 [email protected] Shri Absar Ahmad, Sr. Eng. 8080484278 [email protected]

    VII POWERGRID23 Shri K.K. Thakur, A.GM. 9428819594 [email protected] Shri Kuleshwar Sahu, D.G.M. 9425294214 [email protected] Shri Manoj Kumar Tripathi, Asst. G.M. 8275025586 [email protected] Shri Sanjoy Das, C.M. 9429976244 [email protected] Shri Onkar Singh, Dy. Mgr. 9428371368 [email protected]

    VIII NTPC28 Shri P. Sreenivas, G.M. 9004677573 [email protected] Shri N.P. Shahar, A.G.M. 9428511769 [email protected] Shri P. Mondal, D.G.M 9424141560 [email protected] Shri P. Chandankhede, D.G.M. 9403780553 [email protected] Shri C.P. Agarwal, Sr. Mgr. 9423877192 [email protected] Shri Bhaskar Maheshwari 8275045062 [email protected] Shri Manas Kapoor, Mgr. 9425177986 [email protected]

    LIST OF PARTICIPANTS OF 508th OCC MEETING OF WRPC HELD AT WRPC, MUMBAI ON 14.06.18

  • IX NSPCL35 Shri Pavan Kumar Nukala 9425293596 [email protected]

    X NPCIL36 Shri A. Sarmasarkar, SO/G 9423982702 [email protected] Shri Sonu Singh, SO/E 9403642631 [email protected] Shri Samir Pathan, SO/E 9409309743 [email protected]

    XI RELIANCE ADA39 Shri Pavan K. Sharma, A.V.P. 9325119773 [email protected]

    XII APML/APL40 Shri Manoj Taunk, G.M. 9099005517 [email protected] Shri Rakesh Bhalerao, A.M. 7045953823 [email protected] Shri Nilesh Wankhede, A.M. 8291118849 [email protected]

    XIII TATA POWER43 Shri Avinash Kumar, G.M. -Opn. 8866058628 [email protected] Shri Rajendra V. Saraf, Head G.Opn. 9969334420 [email protected]

    XIV STERLITE POWER45 Shri Nithin A. Skaria, Eng. 9673007426 [email protected]

    XV M.B. POWER46 Shri Prateek Dubey, Sr. Eng. 7773011366 [email protected]

    XVI VEDANTA47 Shri Sangeet Ku. Sahu, Mgr. 9893592588 [email protected]

    XVII RATTAN INDIA48 Shri Anil Kumar Mishra, G.M. 9665070111 [email protected]

    XVIII TORRENT POWER LTD.49 Shri Ronak Naik, Mgr. 9227410210 [email protected]

    XIX JINDAL POWER LTD.50 Shri Ajeet Kumar 9329444989 [email protected]

    XX KSK51 Shri Ramakant Upadhyay, Dy. Mgr. 7869916080 [email protected]

    XXI JHABUA POWER Ltd.52 Shri Dileep Singh, Mgr. 9713063449 [email protected]

    XXII RKM POWER53 Shri T. Rajesh Kumar, Mgr. 8435000779 [email protected]

    XXIII ESSAR POWER54 Shri Ashwin Ande 9909993594 [email protected]

  • Anaulagnak 2.1

    maah ma[- 2018

    1. INTEGRATED OVER AN-HOURek GaMTo maoM samaakilat

    1.1 MAXIMUM FREQUENCY 50.10 Hz. BETWEEN 0400 Hrs & 0500 Hrs Hrs. ON 03.05.2018

    AiQaktma AavaRi%t

    1.2 MINIMUM FREQUENCY 49.77 Hz. BETWEEN 1900 Hrs & 2000 Hrs Hrs. ON 26.05.2018

    nyaUnatma AavaRi%t

    1.3 AVERAGE FREQUENCY 49.95 Hz.

    AaOsat AavaRi%t

    2. INSTANTANEOUS ta%kailak

    2.1 MAXIMUM FREQUENCY 50.20 Hz. AT 04:03:10 Hrs. ON 03.05.2018

    AiQaktma AavaRi%t

    2.2 MINIMUM FREQUENCY 49.57 Hz. AT 19:49:10 hrs Hrs. ON 26.05.2018

    nyaUnatma AavaRi%t

    3. %AGE OF TIME WHEN FREQUENCY WAS MAY 2018 APRIL 2018 MARCH 2018

    AavaRi%t ka samaya p`itSat maoM

    3.1 BELOW 48.5 Hz. 0.00 0.00 0.00

    48.5 hT\ja ko naIcao3.2 BETWEEN 48.5 Hz. AND 48.8 Hz. 0.00 0.00 0.00

    48.5 hT\ja AaOr 48.8 hT\ja ko baIca3.3 BETWEEN 48.8 Hz. AND 49.2 Hz. 0.00 0.00 0.00

    48.8 hT\ja AaOr 49.2 hT\ja ko baIca3.4 BETWEEN 49.2 Hz. AND 49.5 Hz. 0.00 0.00 0.00

    49.2 hT\ja AaOr 49.5 hT\ja ko baIca3.5 BETWEEN 49.5 Hz. AND 49.7 Hz. 0.00 0.00 0.00

    49.5 hT\ja AaOr 49.7 hT\ja ko baIca3.6 BETWEEN 49.7 Hz. AND 49.9 Hz. 22.52 12.80 12.99

    49.7 hT\ja AaOr 50.2 hT\ja ko baIca3.7 BETWEEN 49.9 Hz. AND 50.05 Hz. 70.06 79.57 79.29

    49.9 hT\ja AaOr 50.05 hT\ja ko baIca3.8 BETWEEN 50.05 Hz. AND 51.5 Hz. 7.42 7.63 7.72

    50.05 hT\ja AaOr 51.5 hT\ja ko baIca3.9 ABOVE 51.5 Hz. 0.00 0.00 0.00

    51.5 hT\ja ko }pr

    4.1 NO. OF TIMES FREQUENCY 0 0 0

    TOUCHED 48.80 Hz. AavaRi%t 48.80 hT\ja kao CUhI

    4.2 NO. OF TIMES FREQUENCY 0 0 0

    TOUCHED 48.60 Hz. AavaRi%t 48.60 hT\ja kao CUhI

    4.3 NO. OF TIMES FREQUENCY 0 0 0

    TOUCHED 51.00 Hz. AavaRi%t 51.00 hT\ja kao CUhI

    maoM AavaRi%t ko AaMkD,aoM ka ivavarNa

    FREQUENCY PARTICULARS DURING MAY 2018

    (AS PER FREQUENCY REPORT OF WRLDC)

    (piScama xao~ Baar p`oYaNa kond` kI AavaRi%t irpaoT- ko AaQaar pr)

  • मई 2018 Voltage Profile during the month of May'18

    Date

    Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min

    1 413 400 423 411 413 401 420 409 418 405 417 404 410 390 422 416 425 4202 413 396 420 407 412 397 421 407 417 399 417 399 415 400 421 414 424 4113 415 396 422 407 414 396 425 406 418 401 417 400 417 391 422 415 426 4184 411 396 420 407 410 396 418 404 415 402 415 401 407 393 420 413 423 4165 411 398 421 408 410 397 418 403 417 401 415 401 410 393 419 414 424 4166 416 399 424 412 416 400 422 404 420 405 419 404 408 390 419 414 422 4177 411 399 422 412 410 400 418 406 418 405 415 405 406 392 418 413 423 4168 411 398 421 410 411 399 419 405 417 402 416 402 409 392 418 412 421 4169 411 399 419 409 409 398 418 404 416 402 414 401 410 395 418 412 422 41510 412 398 422 408 410 398 418 404 419 402 417 401 414 395 417 411 419 41611 411 399 422 410 410 399 417 404 417 404 415 403 407 391 418 413 419 41412 416 400 425 413 414 401 424 406 419 407 418 405 411 393 421 414 419 41413 415 400 423 412 414 400 419 402 418 406 417 404 415 394 419 414 422 41614 411 398 421 409 410 397 416 400 417 402 416 401 410 392 422 412 422 41515 414 397 422 409 411 397 424 406 417 402 416 401 413 398 421 415 420 415

    Annexure 2.3

    रायपुर रायगढ़Bhopal Khandwa Itarsi Damoh Nagda Indore Gwaliorभोपाल खंडवा इटारसी दमोह नागदा इंदौर

    Raipur Raigarh400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV 400kV

    15 414 397 422 409 411 397 424 406 417 402 416 401 413 398 421 415 420 41516 414 398 421 409 412 399 424 408 417 404 415 402 418 391 423 414 422 41317 413 399 421 410 411 399 421 406 418 405 416 404 411 391 420 414 421 41418 414 398 421 408 412 398 420 409 417 404 416 402 415 397 420 412 422 41319 414 402 422 411 412 403 422 408 420 406 418 406 416 394 420 411 420 41320 414 397 422 411 414 400 422 408 419 407 418 405 411 392 421 417 421 41721 414 397 422 406 413 398 421 406 420 401 418 400 412 391 420 413 421 41422 411 398 421 406 410 397 420 405 417 399 416 400 413 398 418 413 418 41223 415 401 421 409 413 401 424 409 419 401 417 402 414 393 420 415 421 41524 413 395 421 406 412 398 422 410 417 401 416 399 416 398 419 413 420 41425 414 400 421 407 412 399 421 407 419 402 417 400 411 396 420 413 420 41326 412 399 421 407 412 399 420 408 419 403 418 401 410 393 420 413 420 41327 415 399 422 412 414 402 423 411 419 408 418 407 414 396 421 417 421 41628 413 400 421 408 412 400 421 408 417 402 415 402 411 396 420 413 420 41429 412 398 422 410 411 398 421 409 418 406 417 405 412 396 420 414 421 41430 413 396 420 408 411 397 422 406 418 402 415 401 412 395 421 414 422 41531 414 396 422 406 413 396 422 407 417 398 415 398 411 395 421 415 424 417

    416 395 425 406 416 396 425 400 420 398 419 398 418 390 423 411 426 411

  • Date

    Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min

    1 419 412 425 418 434 414 424 406 420 410 429 415 426 413 414 400 422 4072 417 410 423 416 429 412 422 405 421 400 428 402 423 403 413 397 421 4053 419 410 424 414 433 411 424 401 417 396 425 399 422 404 414 395 418 4064 417 408 424 416 431 411 420 399 415 400 422 400 421 400 413 397 421 4065 415 409 422 416 430 410 419 399 414 396 421 399 423 400 412 397 420 4056 416 410 422 418 432 415 422 399 416 402 424 406 422 404 415 401 422 4097 415 409 424 418 430 416 420 401 417 399 422 398 422 406 415 400 422 4078 415 407 423 417 430 411 422 399 416 396 423 398 423 406 414 399 422 4069 415 408 424 417 430 412 419 401 415 397 421 396 422 405 413 396 421 406

    10 414 407 424 417 431 410 422 400 418 396 425 398 426 404 415 397 424 40511 414 409 421 415 433 412 420 400 417 404 420 401 424 406 413 400 425 40912 418 411 420 413 431 416 423 402 420 403 426 403 425 409 416 402 423 40913 416 411 418 412 430 412 421 401 416 400 424 402 424 406 414 401 420 40914 418 409 420 412 429 392 421 400 415 396 421 395 421 406 413 398 421 40515 417 411 422 414 429 411 422 402 414 393 421 394 420 407 413 397 420 40516 419 411 421 412 429 411 422 401 411 392 418 391 422 402 412 399 420 40617 416 411 420 412 429 409 421 405 414 396 421 396 424 401 412 399 421 400

    धुले बोईसर कलवा कराड़ असोज देहगामKarad Asoj Dehgam

    400kV 400kV 400kV 400kV 400kV 400kV 400kVBhilai Wardha Dhule Parli Boisar Kalwa

    400kV 400kV

    17 416 411 420 412 429 409 421 405 414 396 421 396 424 401 412 399 421 40018 417 409 419 412 430 410 422 399 413 395 421 395 421 406 413 397 419 40519 419 412 418 410 433 412 421 403 416 395 423 396 421 405 415 400 422 40620 418 413 418 414 432 415 421 403 415 404 422 407 421 407 415 404 422 41121 417 409 417 409 433 380 419 398 415 391 422 392 422 404 413 397 420 40522 414 408 422 412 433 400 419 395 414 392 420 393 420 406 413 396 421 40323 417 412 420 413 432 412 420 400 414 393 422 392 421 402 414 397 422 40424 416 409 418 410 430 408 418 396 415 394 422 396 421 405 413 397 420 40525 416 409 418 410 433 412 419 395 414 399 422 400 422 402 413 396 422 40426 416 409 422 411 430 412 419 396 412 396 419 394 423 402 412 398 419 40527 418 414 422 414 432 411 421 404 412 399 419 398 420 405 413 401 420 40628 417 409 421 413 433 389 423 400 411 394 417 392 420 400 412 397 421 39529 417 411 420 412 432 411 421 397 411 394 418 394 424 410 413 399 422 40030 418 411 420 411 431 409 419 400 414 392 419 390 420 402 413 396 420 39731 417 410 424 415 433 410 423 401 410 393 417 393 419 398 412 394 418 400

    419 407 425 409 434 380 424 395 421 391 429 390 426 398 416 394 425 395

  • Date

    Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min

    1 418 408 414 404 418 408 420 409 417 400 419 407 422 412 419 405 785 763 781 7572 417 405 416 404 419 407 422 402 420 383 419 399 425 401 420 398 788 756 785 7453 418 407 417 403 419 406 418 398 421 398 416 396 419 400 419 397 795 755 786 7514 418 407 415 403 418 406 417 400 421 400 415 398 418 402 418 400 779 754 780 7495 418 408 416 404 417 408 417 397 420 400 415 396 418 400 417 400 783 755 782 7526 418 407 417 403 420 408 416 400 424 400 415 400 420 405 419 401 793 762 790 7567 419 407 415 404 419 408 419 399 424 402 417 399 420 404 420 400 787 766 783 7578 418 408 417 406 420 408 418 399 424 399 415 396 420 399 421 401 787 763 779 7539 417 407 416 405 420 409 417 399 427 399 414 396 419 401 419 405 782 763 780 756

    10 419 406 416 404 420 408 420 397 433 405 417 395 421 400 420 401 787 763 788 75811 419 409 415 403 419 407 417 403 427 403 415 401 420 408 418 402 783 762 783 76312 419 409 416 405 420 410 420 403 424 408 418 401 424 406 419 399 791 764 790 75913 417 408 418 406 421 409 418 403 426 404 416 401 418 400 416 400 794 765 787 75714 417 408 418 406 421 410 417 397 423 402 415 397 418 400 418 395 786 754 786 75615 418 408 416 405 420 410 414 397 423 395 412 396 415 397 415 398 786 761 785 75416 417 408 417 407 420 410 413 396 425 392 410 394 415 394 416 397 794 755 780 75417 419 410 417 406 422 411 416 399 424 399 413 397 417 401 415 399 782 762 786 75518 417 407 416 405 420 411 415 397 424 406 413 395 416 399 416 396 787 760 787 75919 419 409 417 403 423 409 417 398 422 399 414 396 416 400 416 401 787 762 790 76720 419 410 417 407 421 410 417 403 423 406 414 401 416 406 414 395 788 760 787 755

    कासोर जेतपुर वापी मापुसा कला मगरवाड़ा हज़ीराKasor Jetpur Amreli Vapi Mapusa Kala Magarwada Hazira Bina

    400kV 400kV400kV 400kV 400kV 400kV 400kV 400kV

    बीना इंदौर

    765Kv 765Kv

    Indore

    20 419 410 417 407 421 410 417 403 423 406 414 401 416 406 414 395 788 760 787 75521 412 408 415 405 420 410 416 394 425 401 414 392 416 395 415 395 786 756 788 75422 417 406 414 402 419 408 414 393 424 399 413 392 415 395 416 393 782 763 786 75623 419 407 415 404 421 408 415 398 421 396 414 397 415 397 417 399 789 764 787 75924 418 407 415 403 420 407 415 394 421 397 413 391 415 397 415 394 788 766 783 76025 417 405 414 404 418 407 415 397 420 395 412 393 416 399 417 394 789 765 786 75626 418 408 414 403 418 405 414 398 421 399 413 397 414 401 416 402 785 763 786 75627 417 406 411 402 416 406 413 399 422 403 412 397 414 401 416 401 789 765 789 75928 417 407 413 402 418 408 415 397 420 398 414 396 414 398 417 395 783 761 784 75829 417 407 412 402 417 406 413 396 424 408 411 395 413 399 418 398 788 765 784 75530 417 404 413 402 417 408 416 395 420 394 416 394 415 395 415 396 789 765 785 751

    419 403 418 402 423 405 422 393 433 383 419 391 425 394 421 393 796 754 790 745

  • Date

    Max Min Max Min Max Max Max Min Max Min Max Min Max Min Max Min Max Min Max Min

    1 777 758 784 752 803 792 804 793 789 763 808 790 791 756 773 762 790 771 804 7802 774 760 782 754 801 790 801 790 785 753 804 790 795 762 769 761 784 767 798 7813 785 755 791 748 806 790 806 789 786 752 809 787 799 752 771 760 786 765 803 7734 765 756 764 750 800 786 800 785 785 757 805 786 781 752 766 757 782 761 802 7745 768 757 773 750 804 787 805 787 783 757 808 788 783 752 766 758 783 764 799 7756 777 759 786 758 800 788 800 788 789 765 802 791 794 760 770 760 786 769 794 7807 774 761 777 758 800 789 800 788 790 765 804 791 788 763 768 761 786 770 800 7838 773 761 777 760 796 787 796 786 787 759 801 790 795 764 769 761 785 768 799 7789 769 761 775 759 797 775 797 785 784 755 803 790 789 765 767 760 783 768 800 781

    10 772 762 780 763 795 787 795 786 791 758 801 789 795 762 767 760 784 768 801 78111 771 761 778 759 793 785 792 784 788 762 798 786 783 758 769 760 784 768 798 78012 779 761 786 763 794 785 794 785 793 765 798 786 793 761 774 762 792 775 795 77813 777 761 786 763 801 785 801 785 787 763 804 785 801 756 767 761 791 773 793 77614 770 752 778 749 797 784 798 784 787 758 801 783 792 752 764 757 788 765 794 77315 766 756 777 756 792 785 792 783 787 756 797 785 791 763 768 760 788 771 800 761

    16 774 756 789 755 799 783 799 778 784 760 804 779 803 744 772 757 793 766 797 77117 769 760 775 759 796 784 797 782 787 761 800 780 784 756 768 759 785 769 793 77318 770 760 778 760 798 781 798 779 789 757 798 775 793 759 769 759 787 767 792 769

    19 771 761 779 761 794 781 793 780 794 766 798 777 795 758 769 761 788 773 791 772

    20 772 759 780 756 798 789 797 780 792 771 801 790 792 757 770 762 789 775 795 78221 767 757 773 752 795 782 796 781 790 756 802 777 787 753 768 756 786 765 793 766

    सासन सतना तमनार कोटरा वडोदराSasan Satna Tamnar Kotra Vadodara

    765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765Kv 765KvDurg Gwalior Sipat Seoni Wardha

    21 767 757 773 752 795 782 796 781 790 756 802 777 787 753 768 756 786 765 793 766

    22 768 760 773 757 791 780 790 778 790 755 795 774 790 763 766 757 785 765 793 769

    23 771 761 776 759 794 787 795 787 791 759 800 789 792 757 771 762 791 776 799 77924 771 761 777 759 795 784 794 783 788 756 798 783 793 768 770 760 789 769 793 76825 773 760 779 759 794 783 795 783 789 756 798 781 794 765 768 759 787 767 792 76926 769 761 775 758 792 783 793 782 789 759 798 781 793 752 767 756 789 764 798 767

    27 770 760 775 758 795 788 795 788 790 767 801 791 795 762 771 762 791 776 797 780

    28 769 759 773 756 794 785 794 784 787 759 799 785 789 757 769 761 789 771 800 777

    29 773 762 780 760 797 784 797 780 790 764 802 785 792 760 772 761 792 772 800 77630 774 761 781 757 797 784 798 784 789 758 802 783 795 763 773 759 792 773 798 774

    785 752 791 748 806 775 806 778 794 750 809 774 803 744 774 756 796 761 805 761

  • Annexure-2.5Power Cut/Restrictions in Western Region for the month of May-2018

    k : gaujarat Gujarat

    1 ]VaoogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid1 Power Cut/ Restriction on Industries, Load Shedding in the state etc

    ivavarNa Details ivaVut kTaOtI kI maa~aQuantum ofpower cut

    (MW)

    pabandI ka samayaRestriction Timing

    p`it idna kula }jaa-kTaOtI TotalEnergy Cut(MUs /day

    Remark

    From TotalEnergy Cut(MUs /day

    (a) PowerRestrictions(Evening peakHour) on non continuous

    process HT/LT Industries M(b) Baar inayamana Load Shedding

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    All industries areallowed to run theirunits on all days ofweek & if they want toavail staggered holiday,then they will have tostagger on notified dayonly & cannot avail asper their choice. Allindustries are requiredto keep their recesstimings staggered.

    (c) Anya jaanakarI Otherinformation

    1.Weekly Off2.Staggering of powersupply

    SaUnya NilSaUnya Nil

    SaUnya NilSaUnya Nil

    SaUnya NilSaUnya Nil

    SaUnya NilSaUnya Nil

    2 kRiYa xao~ kao ivaVut AapUit-2. Power supply to Agricultural Sector: -

    ivavarNa Details sao FromidnaaMk Date

    tk To idnaaMkDate

    p`it idna AapUit- GaMTo Supply Hours per dayMax. (Hrs) Min. (Hrs) Average (Hrs)

    2.1 Three phase supply 01.05.2018 31.05.2018 8:00 8:00 8:00

    2.2 Single Phase supply 01.05.2018 31.05.2018 16:00 16:00 16:00Remarks:08 Hrs. power supply in staggered form in rotation of day & night is given to AG. During21.07.2017 to 28.07.2017 -- 10 hours AG supply given to Lunavada area for paddy crops. 10Hrs. power supply in staggered form in rotation of day & night is given to AG from 17.08.2017to 31.08.2017. In PGVCL area 10 Hrs. AG Supply given from 17.09.2017 to 1.10.2017. In allGujarat 10 Hrs. AG Supply given from 05.10.2017 to 19.10.2017 and further from 24.10.2017to 20.11.2017. In all Gujarat 10 Hrs. AG Supply given from 02.12.2017 to 31.12.2017. InDGVCL area 10 Hrs. AG supply given to 118 feeders for paddy crops from 20.01.2018 to28.02.2018. Single Phase supply given during rest of 16 Hrs by providing LSTC.

    3 Anya jaanakarI3. Any other information

    1. Jayotigram Yojana-24 hours.2. There is no load shedding in Urban areas

  • K : maQya p`doSa Madhya Pradesh1 ]VaoogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid1 Power Cut/ Restriction on Industries, Load Shedding in the state etc

    ivavarNa Details ivaVut kTaOtI kI maa~aQuantum of

    power cut (MW)

    pabandI ka samayaRestriction Timing

    p`it idna kula }jaa- kTaOtITotal Energy Cut

    (MUs /daysao From tk To(a) Power Restrictions(Eveningpeak Hour) on non continuous

    process HT/LT Industries M(b) Baar inayamana Load Shedding

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    SaUnya Nil

    (c) Anya jaanakarI Other information1.Weekly Off2.Staggering of power supply

    SaUnya NilSaUnya Nil

    SaUnya NilSaUnya Nil

    SaUnya NilSaUnya Nil

    SaUnya NilSaUnya Nil

    2 kRiYa xao~ kao ivaVut AapUit-2. Power supply to Agricultural Sector: -

    ivavarNa Details sao FromidnaaMk Date

    tk To idnaaMkDate

    p`it idna AapUit- GaMTo Supply Hours per dayMax. (Hrs) Min. (Hrs) Average (Hrs)

    2.1 Three-PhaseSupply(Mixed) 01.05.2018 31.05.2018 23:33 22:10 23:152.2 Three-PhaseSupply(DLF) 01.05.2018 31.05.2018 23:37 23:39 23:232.3 Three-PhaseSupply(Irrigation) 01.05.2018 31.05.2018 09:49 09:24 09:44

    3 Anya jaanakarI3. Any other information

    SahrI xao~aoM maoM inayamana ivaVut kTaOityaaM Scheduled Power cuts in Urban AreasivavarNa Details sao From

    idnaaMk Datetk To idnaaMk

    DateAaosat pìtidna Average SupplyAapUit- GaMTo Hours per day

    Max.(Hrs)

    Min. (Hrs) Average (Hrs)

    3.1 Commissionary H. Qtrs. 01.05.2018 31.05.2018 23:54 23:18 23:443.2 District Head Qtrs. 01.05.2018 31.05.2018 23:55 23:30 23:463.3 Tehsil Head Qtrs. 01.05.2018 31.05.2018 23:50 23:17 23:40

    ga : maharaYT/ Maharashtra1 ]QyaaogaaoM ko ilayao ivaVut kTaOityaaM / pabMaidyaaM , rajya maoM Baar inayamana Aaid

    1 Power Cut/ Restriction on Industries, Load Shedding in the stateetcDetails Quantum

    of powercut (MW)

    Restriction Timing

    Total Energy Cut(MUs /day

    From To(a) Power Restrictions(Evening peak Hour) on

    non continuousprocess HT/LT IndustriesM(b) Load Shedding

    NIL

    (c)Other information1.Weekly Off2.Staggering of power supply

    NIL

  • 2. Power supply to Agricultural Sector: -Details From

    DateTo

    DateSupplyHoursperday

    Max.(Hrs)

    Min.(Hrs)

    Average (Hrs)

    2.1 Three-PhaseSupply(DLF) 01.05.2018 31.05.2018 Not Applicable

    2.2 Three-PhaseSupply(Irrigation) 01.05.2018 31.05.2018

    10 8 9

    2.3 Three-PhaseSupply(Mixed) 01.05.2018 31.05.2018

    24 24 24

    3. Scheduled Power cuts in Urban Areas

    Details FromDate