Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication...
Transcript of Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication...
![Page 1: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/1.jpg)
![Page 2: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/2.jpg)
![Page 3: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/3.jpg)
Page 1 of 26
Annexure -A
GOVERNMENT OF HARYANA.
Communication & Connectivity Infrastructure Policy-2013
ELECTRONICS & INFORMATION TECHNOLOGY DEPARTMENT.
![Page 4: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/4.jpg)
Page 2 of 26
Table of Contents
Sr. No. Description Page No.
1. Preamble 2
2. Eligibility to apply 2
3. Permission on Non-Exclusive Basis 3
4. Validity of Permission 3
5. Submission of Applications 4
6. Processing of Application 5
7. Time-lines for decisions on the Applications 6
8. Time-lines to complete the work 6
9. Charges for grant of permissions for Right of Way (RoW)/Right of Use (RoU) and associated Infrastructure
7
10. Compliance of Technical standards and Safety conditions 7
11. Communication Infrastructure laid/installed without permission
7
12. Indemnity Bond 8
13. Other terms and conditions 8
14. Revision of the existing rules/guidelines by the respective Departments
8
15. Changes in the Policy 10
16. Additional Corporate Social Responsibility (CSR) initiatives 10
Appendix 1 Documents required to be attached with the Application 11-13
Appendix 2 Schedule of Charges 14-17
1. Location of Ground Based Mast (GBM)/ Communication/ Mobile Towers
18 - 19
2. Technical parameters to be followed by the Applicant while laying the cables (over-ground and underground), erecting of Poles/ Dish Antennas / Ground Based Masts/ Mobile & Communication Towers
19 - 21
Appendix 3
3. Other terms & conditions to be adhered by the applicant while laying the cables (over-ground and underground), erecting of Poles / Dish Antennas / Ground Based Masts/ Mobile & Communication Towers
21 - 24
Appendix 4 An illustrative list of additional facilities as part of the CSR 25
![Page 5: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/5.jpg)
Page 3 of 26
1. Preamble
1.1 Haryana is among the first few States to have established core IT infrastructure
to facilitate the e-enablement of life and work. In order to strengthen this core
Information and Communication infrastructure, the State intends to further
facilitate effective transformation of the socio-economic scenario through
accelerated equitable and inclusive economic growth by encouraging provision
of quality infrastructure for connectivity & telecommunication services across
the State, especially in the rural and remote areas of the State in a uniform and
time bound manner.
1.2 Keeping in view the renewed requirements of the State along side the latest
Information and Communication Technology (ICT) developments and the need
to ensure that the access to and benefits of ICT percolate to urban & rural
masses amid the changing economic environment, the State Government has
decided to revise its existing Right of Way (RoW) Policy, 2000 (amended vide
No. 2/286/1840 dated 08-10-2003) and replace the same with this ‘Policy for
Provision of Infrastructure for Communication & Connectivity in Haryana’.
1.3 This Policy seeks to encourage the use of latest technology advancements in
the telecom sector such as Fibre to the Home (FTTH) and innovative business
models such as the Open Access Network (OAN) where physical access to the
network is separated from the delivery of services. It provides a futuristic
roadmap for creation of an enabling infrastructure through pre-laid OFC with
sufficient bandwidth in proper ducts as part of the development infrastructure
so as to allow multiple service providers to use the same infrastructure on
sharing basis rather than the clamour for space by multiple infrastructure
providers on individual basis.
2. Eligibility to apply:
Any telecom infrastructure provider registered with the Department of
Telecommunications, Government of India or any telecom services provider
licensed from the Department of Telecommunication, Government of India or
an infrastructure provider duly authorised by a licensee to lay the
communication and connectivity infrastructure (hereinafter called as the
‘Applicant’) is eligible to seek permissions under this policy to lay Optic Fibre
Cable (OFC), erect Ground Based Masts (GBMs), Mobile and Communication
Towers within the areas of Urban Local Bodies, Gram Panchayats, statutory
authorities like the Haryana Urban Development Authority (HUDA) and the
Haryana State Agriculture Marketing Board (HSAMB), or other State Agencies
![Page 6: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/6.jpg)
Page 4 of 26
such as the Haryana State Industrial & Infrastructure Development Corporation
(HSIIDC) and the land belonging to State Government Departments like Public
Works Department (Building & Roads), Forests, Irrigation, Revenue,
Agriculture, Development & Panchayat etc.
3. Permission on Non-Exclusive Basis
3.1 Permission for Right of Way (ROW) or Right of Use (RoU) and installation of the
associated infrastructure shall be provided to an eligible Applicant (whether
existing or future) desirous of establishing underground communication
infrastructure, dish antennas, erection of GBMs, mobile towers and
communication towers, and poles for laying over-head cables on a Non-
Exclusive Basis under this policy. However, given the space constraints for RoW
for multiple service providers in any specific area, the principle of first mover
advantage would operate and the subsequent entrant, if any, may need to
share the infrastructure capacity already laid by first-moving service provider.
3.2 The concerned State Agencies or private developers are advised to earmark a
pre-defined route alignment along the internal road circulation network as per
the required specifications (with or without a duct) as part of their
development works for laying of the communication infrastructure so as to
avoid repeated digging and/or to facilitate the infrastructure providers seeking
permissions to lay the cables in future. The State development agencies are
encouraged to provide for ducts and lay the OFC with sufficient bandwidth
capacity/ redundancy as part of their development plans, which may be leased
out to operators/ service providers on a recurring charge basis. The modalities
with regard to the technology, specifications and applicable dues for use of the
duct, if any, shall be worked out separately.
4. Validity of Permission
4.1 The permissions for Right of Way (RoW) or Right of Use (RoU) for laying the
communication infrastructure and associated installations may be granted for
the period applied for, as may be prescribed in the license/ authorisation by
the competent authority, subject to a maximum of 20 years. This period would
be further co-terminus with the period of lease (for land or/and building)
entered into between the Applicant/Operator and the Landowner.
4.2 Permissions granted for moveable communication Towers shall be co-terminus
with the period of that event or maximum three months against a specific
requirement to provide communication facility to public at large subject to
fulfilment of all the conditions laid in this policy for communication Towers.
![Page 7: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/7.jpg)
Page 5 of 26
4.3 Permission(s) granted to the applicant company under this policy will not be
transferable and will be applicable only for the period for which it has been
granted.
4.4 The permission granted under the Policy shall not, in any manner, be deemed
to convey to the Applicant/ Service Provider any ownership or perpetual rights
in respect of the land or structures used for laying the underground/overhead
cables or other installations e.g. any Towers/ Masts etc. other than what is
therein expressly granted.
4.5 In case of violation of any terms and conditions, the Competent Authority shall
cause a notice to be served upon the Service Provider to rectify the violation
within the period specified and grant an opportunity of hearing. Where the
service provider either does not respond to the show cause notice or fails to
carry out the requisite rectification within the time specified (which shall be a
reasonable time), the Competent Authority may revoke or cancel the
permission granted earlier. Where the competent authority is compelled to
revoke or cancel the permission, the Service Provider applicant shall not be
entitled for any compensation or any loss caused to it by such cancellation.
5. Submission of Applications
5.1 All applications for seeking permission of any competent authority to lay the
communication infrastructure, shall be submitted by the Applicant
Infrastructure provider/ Service Provider, along with all the particulars and
documents specified in Appendix-1, to the designated nodal officer of the
concerned State Government Department/ Statutory Authority/ State Agency
under whose jurisdiction the area falls.
5.2 In so far as possible, any scheme for laying of overhead cables on poles
specifically erected for the purpose would be discouraged as the same tends to
interfere with the overhead electricity distribution system apart from
disturbing the aesthetics of the eco system.
5.3 Incomplete applications shall not be processed and shall be rejected out-
rightly.
5.4 Each Department/ Statutory Authority/ State Agency shall appoint a Nodal
Officer within a period of 15 days of the notification of this Policy, to receive
and process the applications in this behalf. The particulars and contact details
of such Nodal Officer shall be published on the website of such Department/
Statutory Authority/ State Agency along with his/ her contact details.
![Page 8: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/8.jpg)
Page 6 of 26
6. Processing of applications:
6.1 Each application shall be duly scrutinized by the concerned designated nodal
officer who may seek such additional information from the Applicant Service
Provider/ Operator, as may be considered necessary for scrutiny of the
application. While processing the said application, the concerned authority
shall take into consideration not only the existing infrastructure services and
their safety and operations but also future requirements of widening of the
roads or augmentation of services. In case the proposed route alignment
interferes with any services already laid, and it is feasible to relay/ re-align
such services at the cost of the Applicant or the Applicant offers to undertake
such realignment at his cost to the satisfaction of the competent authority, the
same may be considered and allowed.
6.2 Once the concerned State Government Department/ Statutory Authority/ State
Agency is satisfied with the proposed alignment route/ site or such route is
determined and finalized through mutual agreement and the time schedule in
which the work is proposed to be executed/ completed, a Letter of Intent
(LoI), along with the Agreement to be executed in this behalf, and (ii) Demand
Notice for various charges including the performance Bank Guarantee, shall be
issued to the Applicant by the concerned Nodal Officer of the State
Government Department/ Statutory Authority/ State Agency.
6.3 The Applicant is required to submit the refundable performance Bank
Guarantee as a security for satisfactory restoration of the sites/ area and such
other fees as specified in Appendix-2 of this policy and to execute an
Agreement with the concerned State Government Department/ Statutory Body/
State Agency within 15 days from the date of issue of the Letter of Intent.
6.4 Upon issue of the LoI, the Applicant shall be expected to furnish the
Agreement, along with all the applicable charges to the Nodal Officer within a
period of 15 days. However, such documents may be accepted by the Nodal
Officer up to a maximum period of 60 days from the date of issue of the LoI.
6.5 As soon as the LoI holder completes the documentation and deposits all the
relevant charges, including the performance Bank Guarantee, the Nodal Officer
of the concerned Department/ Statutory Authority/ State Agency shall issue a
formal permission in favour of the Applicant so as to enable the Applicant
Service Provider/ operator to commence execution of related infrastructure
works.
![Page 9: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/9.jpg)
Page 7 of 26
7. Time-lines for decisions on the Applications:
7.1 The State Government Departments/ Urban Local Bodies/ Statutory
Authorities/ other Agencies will adhere to the following time-lines for grant of
the relevant permissions:
Sr. No.
Event No. of Working days
(i) Processing of applications and seeking of additional information, if any, from the date of receipt of complete application;
30 days
(ii) Issue of LoI or rejection of application along with reasons thereof;
15 days
(iii) Compliance of the LoI conditions (para 6.4) 15 days subject to a maximum of 60 days
(iv) Execution of Agreements and issue of formal permission.
15 days from the date of receipt of papers from the LoI holder
7.2 The Government Departments/ Statutory Authorities/ State Agencies are
expected to issue their respective Standing Orders in this behalf prescribing the
appropriate delegations in a manner so as to ensure adherence to the
prescribed time-lines.
8. Time-lines to complete the infrastructure works
8.1 The Applicant Infrastructure/ Service Provider shall be required to submit the
time-frame within which it plans to execute the infrastructure works. The said
plan may provide stretch-wise completion schedule, along with the complete
plan. It shall make its best efforts to complete the execution of works within
the time-frame indicated in the application.
8.2 During the execution of related infrastructure works, the Applicant shall ensure
that no inconvenience is caused to the general public in the process of carrying
out its operations. If found necessary, the competent authority may direct the
Applicant to undertake execution of its works during the off-peak hours or
during the night times.
8.3 The Applicant shall keep the Nodal Officer of the Department/ Authority/
Agency duly informed about the progress on a monthly basis, which may be
reviewed at regular intervals between the parties.
8.4 Wherever the Applicant is found to be casual or non-serious about timely
execution of the related works, the competent authority may revoke the
permission granted after grant of an opportunity of hearing to the Applicant’s
![Page 10: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/10.jpg)
Page 8 of 26
authorised representative. However, where the Applicant’s representative is
able to establish that any such delay is for reasons beyond their control, the
Competent Authority may extend the execution period and allow the work to
be completed within the mutually agreed time-frame.
9. Charges for grant of permissions for the Right of Way (RoW)/ Right of Use (RoU) and associated infrastructure etc.
With the exception of M/s Bharat Broadband Network Limited (BBNL) in respect
of payment of RoW/ RoU charges, every Applicant shall be required to pay (i)
the RoW/ RoU permission charges, (ii) lease charges for the Land used for its
purposes, and (iii) furnish the performance Bank Guarantee as a refundable
security for restoration of sites as per the details specified in Appendix - 2 of
this policy.
10. Compliance of Technical Standards and Safety conditions:
10.1 The Applicant Infrastructure/ Service Provider shall execute the
communication and connectivity infrastructure works strictly as per the
technical standards and parameters specified in Appendix -3 of this policy.
10.2 Notwithstanding the details specified in Appendix-3, the Applicant shall, in the
course of execution of its works and maintenance thereof thereafter, at all
times, adhere to all the safety standards applicable as per relevant guidelines
of the Government of India/ State Government. Further, the applicant shall
ensure that the system laid or the infrastructure created by him (e.g. Ground
Based Masts/ Mobile/Communication Towers etc.) at all times conform to the
EMF radiation norms as prescribed by the Department of Telecom, Government
of India or the Telecom Regulatory Authority of India, as the case may be,
from time to time.
10.3 No GBM or Tower Structures shall be allowed to be installed by any Applicant/
Service/ Infrastructure Provider unless a Structure Stability/ Safety Certificate
(SSC) is obtained from one of the institutes (a) any of the IITs, (b) PEC
University of Technology, Chandigarh (c) National Institute of Technology,
Kurukshetra (d) Central Building Research Institute (CBRI) Roorkee or (e) any
such reputed Institution/or Institute mentioned in Rule 38 (xxix-a) of Rules
1965.
11. Communication Infrastructure laid/ installed without permission
11.1 From the date of the notification of this policy, if any communication
infrastructure has already been installed for which either permission has not
![Page 11: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/11.jpg)
Page 9 of 26
been applied for or not granted by the competent authority, the
Infrastructure/ Service provider shall be required to apply for the same with in
a period of 90 days to get such unauthorised action compounded, for which he
shall be liable to pay a compounding fee, which shall be calculated @ 50% of
the applicable charges as specified in Appendix-2 of this policy, subject to the
condition that such communication infrastructure fulfils the conditions
prescribed in this policy. Wherever any rectifications are required in this
process, he may be permitted a reasonable time to undertake such
rectifications.
11.2 If the infrastructure/service provider neither apply and/nor remove the
communication structure, the infrastructure provider/cellular operator would
be called upon to show cause as to why action should not be taken against
them as per Law. If the infrastructure provider/ operator/ service provider
fails to show cause or take corrective measures, the competent authority will
proceed to get the unauthorized communication structure removed at the
expense of such infrastructure/ service providers/ operators after having
exhausted all the available opportunities to effect the show causes besides
taking action as per law.
12. Indemnity Bond
The Applicant Infrastructure provider/ licensee/Operator shall indemnify the
Government and any of its agencies against any loss of life or property in the
process of execution of works or against any claims thereafter during the
period of Operation & Maintenance of such infrastructure at all times. The
Applicant shall submit the Indemnity Bond on a non-judicial stamp paper of Rs.
100/- denomination, duly attested by the competent authority.
13. Other terms and conditions:
13.1 This policy shall take effect from the date of its Notification and shall be
applicable for all proposals/ requests that are pending decisions as on such
date.
13.2 The applicant infrastructure/service provider/ operator shall ensure that each
of the sites of the infrastructure systems, such as GBMs/ Towers or any other
structure, for which permissions have been granted, are easily approachable
for maintenance and operation.
14. Revision of the existing Statutes/ rules/ guidelines by the respective Departments:
![Page 12: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/12.jpg)
Page 10 of 26
14.1 Following sets of rules/ bye-laws/ policies/ guidelines have been issued on the
subject by the respective departments/ agencies:
(i) Haryana Municipal (communication, cables, erection of dish antenna),
Bye-Laws 2007 and Haryana Municipal (communication, cables, erection
of dish antenna) Amendment, Bye-Laws 2008 notified by Urban Local
Bodies Department vide No. S.O. 88/ H.A.24/ 1973/Ss.200 and
214/2007 dated 31.10.2007 and S.O. 52/ H.A.24/ 1973/ Ss.200 and
214/2008 dated 09.06.2008 respectively ;
(ii) Haryana Municipal Corporation (Erection of Communication Towers)
Bye-Laws 2009 and Haryana Municipal (Erection of Communication
Towers) Bye-Laws notified by Urban Local Bodies Department vide No.
3/7/2003-R(1) dated 11.11.09 and No. 3/7/2003-R1(2) dated 11.11.09
respectively.
(iii) Haryana Panchayati Raj (Regulation of Communication Towers) Rules,
2012 framed and Notified by the Development & Panchayat Department
vide Notification bearing No. S.O. 56/ H.A. 11/1994/S.209/2012 dated
20.07.2012.
(iv) Policy for setting-up of communication towers by private operators as
notified by Haryana Urban Development Authority vide No. CTP/DTP
(BP) 5466-69 dated 20.08.04 and Amendment vide No. CTP/DTP(BP)
6228-6231 dated 24.09.04.
(v) Policy for setting up of mobile towers in the controlled areas issued by
Town & Country Planning Department, Haryana vide No. 7/19/ 2012 -
2TIP dated 13.01.2012;
14.2 All the concerned Government Departments/ Statutory Authorities/ Agencies
shall undertake suitable and appropriate amendments/ revisions in their
respective statutes/ rules/ byelaws so as to bring the same in conformity with
this policy within a period of 30 days of the notification of this Policy.
14.3 In so far as Policy guidelines issued by HUDA or the Town & Country Planning
Departments are concerned, the same shall stand subsumed in this policy from
the date of its Notification.
14.4 The existing service providers, having availed the benefit of free Right of Way
as per the provisions under Right of Way Policy 2000 (amended vide No.
2/286/1840 dated 08-10-2003) will be required to apply as per the new policy
within a period of 90 days from the notification of the new policy. They shall
be obliged to fulfil their part of the obligations under the old policy till such
![Page 13: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/13.jpg)
Page 11 of 26
time they start their operations under this policy.
15. Changes in the Policy
This policy shall be suitably adjusted to accommodate any changes that may be
necessitated on account of any technology or regulatory changes which may be
introduced by the Department of Telecommunications, Government of India or
any other competent authority in order to keep this policy dynamically
responsive to changing technology, regulatory regime or any other unforeseen
developments.
16. Additional Corporate Social Responsibility (CSR) initiatives:
The competent authorities in the Municipal Areas or in respect of areas developed
by other State Agencies (e.g. HUDA, HSIIDC, HSAMB etc.) or the Gram Panchayats
may encourage and persuade the Communication Infrastructure Provider
Applicants to undertake some additional activities in furtherance of the principles
of Corporate Social Responsibility. However, any such initiatives may be mutually
agreed and decided, for which no coercive methods shall be applied. Some
illustrations of the CSR initiatives/ facilities are given in Appendix-4 of this policy.
0-0-0-0-0
![Page 14: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/14.jpg)
Page 12 of 26
Appendix - 1
Documents to be attached with the Application
1. Documents to be submitted in all cases:-
1.1 Copy of registration as a Telecom Infrastructure provider with the Department
of Telecommunications, Government of India or a license granted by the
Department of Telecommunications, Government of India or an authorisation
from the licensee to lay the said infrastructure facilities on its behalf;
1.2 Two sets of the proposed route layout plan drawings clearly indicating the
locations of any Poles/ structures/ Boxes/ Towers/ GBMs etc. for which the
permission is being sought;
1.3 Time schedule (stretch-wise) for completion of the work and investment;
1.4 Indemnity bond to indemnify the Government/ Local Body/ Authority in the
prescribed format against (i) any liability for the damage caused to the
infrastructure laid by the applicant for any reasons, and (ii) claims against any
accidents on account of the infrastructure laid/ facilities installed or against
any claims thereafter during the period of Operation & Maintenance of such
infrastructure at all times;
1.5 Undertaking to pay all the applicable charges and the Performance Bank
Guarantee, as specified in the Schedule of Charges (Appendix-2) to the agency
according permission without any default;
1.6 Undertaking to maintain the infrastructure facilities in good and safe condition
at all times during the O&M period;
1.7 Undertaking to execute an Agreement with the competent authority;
1.8 Undertaking to re-lay/ re-align the communication network/ relocate the
poles/ dish antenna/ communication/ mobile tower/ ground based mast at its
own cost in the event of requirement of the area for augmentation of public
services e.g. widening of roads, pedestrian walkways, water supply and
distribution network, sewage/ drainage network etc.);
1.9 Undertaking to abide by the terms and conditions of grant of permission and
adherence to the radiation norms as prescribed by the Department of
Telecommunications, Government of India or the TRAI.
![Page 15: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/15.jpg)
Page 13 of 26
2. Documents for laying underground Optic Fibre/ Co-axial Cables (in addition to those listed at Sr. No. 1 above):
2.1 Technology/ method proposed to be used for laying the cables (Horizontal
Directional Digging (HDD)/ Horizontal Boring methods/ Micro Trenching or
open digging) with preference for use of HDD/ Micro Trenching;
2.2 Specific area details (in sq. ft. or sq. mtrs.) required for any structures
(Manholes/ Boxes/ Towers/ GBMs etc.) for which land is proposed to be taken
on lease;
2.3 Dimensions (depth, length and width) of the area proposed to be used for
RoW/ RoU for laying the Optic fibre cables and other communication devices/
structures.
3. Documents for erection of Poles for overhead communication cables (subject to para 5.2 of the Policy) in addition to those listed at Sr. No. 1 above):
3.1 Specific area details (in sq. ft. or sq. mtrs.) required for erection of poles and
connection boxes for which land is proposed to be taken on lease;
3.2 Details marked on town map (i) proposed route (ii) no. of poles (iii) dimension
of poles (height, thickness/diameter), (iv) distance between each pole, and (v)
minimum ground clearance for the cable.
4. Documents for installation of Dish Antennas (in addition to those listed at Sr. No. 1 above) [does not include Dish Antennas installed under direct to home (DTH)]:
4.1 The proposed location of the dish antenna/ panel box/ dish/ inspection box/
connection box duly marked on town map.
4.2 Ownership document or lease deed of the site/ premises, on which dish
antenna is proposed to be set up. The lease agreement should be co-terminus
with the period for which the permission is being sought;
4.3 Structure safety certificate from the competent authority as prescribed;
5. Documents for erection of Ground Based Mast (GBM)/ Communication/ Mobile Tower (in addition to those listed at Sr. No. 1 above)
5.1 Copies of site plan indicating Specific area details (in sq. ft. or sq. mtrs.)
required for the Manholes, GBM/ Communication/ Mobile Towers (for which
land is proposed to be taken on lease), along with the dimensions in each case;
5.2 Location of the GBM/ Communication/ Mobile Tower duly marked on the route
map, preferably with GPS readings/values;
5.3 True copy of the approval/ clearance from the Standing Advisory Committee
for Frequency Allocation (SACFA) for the said location issued by Wireless
![Page 16: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/16.jpg)
Page 14 of 26
Planning & Coordination (WPC) Wing of the Department of
Telecommunications, Government of India;
5.4 Ownership document or lease deed of the site, on which GBM/
Communication/ Mobile Tower is proposed to be set up. The lease agreement
should be co-terminus with the period for which the permission is being
sought;
5.5 True copy of permission from the Airport Authority of India or any defence
establishment in case the height of GBM/ Communication/ Mobile Towers
requires such approval/clearance;
5.6 If the communication/ mobile tower is to be erected on roof-top, copy of the
agreement with the owner of the building and structure safety certificate;
5.7 Two sets of the structural Drawings of towers with complete details including
the specifications of foundation, design parameters, dimensions and type of
construction along with a structural safety certificate;
5.8 Certificate of adherence to the radiation emission norms as prescribed by the
Department of Telecommunications, Government of India or any other
competent authority;
5.9 Data Sheet containing the name of the service/ Infrastructure provider;
5.10 In case of mobile tower, capacity of Towers or antenna in megawatt;
5.11 Undertaking that the generator sets installed at the communication/ mobile
towers sites/ moveable communication towers conform to the noise and
emission norms prescribed by the Haryana State Pollution Control Board;
5.12 Undertaking that the applicant has taken all precautions for fire safety,
lightening etc. and shall obtain necessary permission from the concerned Fire
Office of the area.
0-0-0-0-0
![Page 17: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/17.jpg)
Page 15 of 26
Appendix - 2
Schedule of Charges
1. Reference has been made in this Schedule to different parts of the state
situated in different zones. The areas forming part of each zone are given
below for the purposes of clarity. The description of said zones may change
over time, as notified by the Town & Country Planning Department of the state
of Haryana.
Hyper Potential Zone
High Potential Zone Medium Potential Low Potential Other areas
Urban Areas in and around Gurgaon town including the Urban Areas declared by the Government for Gurgaon- Manesar Urban complex
Faridabad-Ballabgarh Complex, Panchkula, Kalka, Pinjore, Gwal Pahari-Balola Bandhwari Complex in Gurgaon District, Sonepat-Kundli Urban Complex, Panipat.
Karnal, Kurukshetra, Ambala City, Ambala Cantt, Yamuna Nagar, Bahadurgarh, Jagadhari, Hisar, Rohtak, Ganaur , Palwal, Hodal, Rewari, Dharuhera-Bawal and Oil Refinery Panipat.
All other urban areas in the State.
Rest of the state areas including all rural areas
2. Charges:
2.1 RoU/ RoW charges:
The charges for grant of permission for the RoU/ RoW for the Communication
infrastructure shall be payable at the rates given in table 2.1 below. These charges
shall be payable only one time for a period of up to 20 years or the period of license/
permission granted, whichever is lower. The Applicant Service Provider would be
required to pay such one-time charges afresh on completion of the period of initial
permission/ license/ or on completion of 20 years period, whichever is earlier, at the
rates applicable at such time.
2.1 Charges for permission to Right of Way/ Right of Use (in Rs.)
Areas of the state
Sr.
Purpose Hyper Potential Zone
High Potential Zone
Medium Potential Zone
Low Potential Zone
Other Areas including the rural areas
1
Laying of Underground OFC/ Co-axial Cables (per route meter)
100/- 80/- 65/- 50/- 30/-
![Page 18: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/18.jpg)
Page 16 of 26
2.1 Charges for permission to Right of Way/ Right of Use (in Rs.)
Areas of the state
Sr.
Purpose Hyper Potential Zone
High Potential Zone
Medium Potential Zone
Low Potential Zone
Other Areas including the rural areas
2
Laying of overhead communication Cables using Poles (per route meter)
35/- 25/-
3
For every Pit dug-up, other than a man-hole with spacing of 100 mtrs. centre to centre. (in sq mtrs.)
900/- 750/- 600/- 500/- 300/-
4 Dish Antenna (other than Dish Antenna installed under DTH)
Rs. 5,000/ - per Dish Antenna
5
For every pole erected to lay overhead communication cables (per pole)
2000/- 1500/- 1500/- 1000/- 1000/-
6 Erection of Ground Based Masts (per site)
1,00,000/- 75,000/- 50,000/- 25,000/-
7 Erection of Mobile/ Communication Towers (per site)
2,50,000/- 2,00,000/- 1,50,000/- 1,00,000/-
8
In case Mobile/ Communication Towers are shared (per sharing)
75,000/- 50,000/- 50,000/- 25,000/-
9
Moveable communication towers mounted on vehicles (per such tower per month)
50,000/- 40,000/- 30,000/- 25,000/-
2.2 Annual Lease Charges:
2.2.1 The annual lease charges in respect of land area used for the construction of
manhole, erection of Dish Antenna/ Poles/ Ground Based Masts/ Mobile/
Communication Towers shall be as per Table 2.2 given below. The lease
charges, initially determined at the time of grant of permission, shall be
increased at the rate of 5% every year for a period up to 5 years. The Lease
Charges will be re-fixed after a period of 5 years for another block of 5 years
and so on and so forth with reference to the Circle Rates applicable at the
time. The Applicant shall also have the option of depositing the lease charges
![Page 19: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/19.jpg)
Page 17 of 26
upfront on lump-sum basis for a period of five years calculated at the rates
determined initially without any escalation.
2.2 Annual Lease Charges/ Fees (in Rs./ per sq. mtr.)
Lease Charges Hyper Potential Zone
High Potential Zone
Medium Potential Zone
Low Potential Zone
Other Areas
1
As a percentage of the applicable Circle Rates of land
6% 6% 6% 6% 6%
2.2.2 The above prescribed lease charges shall be applicable only in respect of the
land owned by the Government Departments/ Urban Local Bodies/ Gram
Panchayats/ Statutory Authorities and other state agencies. Wherever the
Applicant service provider/ infrastructure provider proposes to use privately
owned land for the said purpose, no lease charges shall be payable to the
concerned agencies to that extent and the lease agreements/ charges shall be
decided/ settled mutually between the parties. The competent Authority would
only ask for the lease agreements between the parties in such cases.
2.3 Performance Bank Guarantee (PBG):
The applicant shall furnish a refundable Performance Bank Guarantee (PBG)
towards security for restoration of the sites dug/ used in the process of execution of
works. The BG shall be valid for a period of six months over and above the completion
period and would have to be renewed accordingly in the event of grant of extension of
execution period. The competent authority shall discharge the BG on satisfactory
restoration of the area. The PBG shall be furnished at the following rates:
Performance Bank Guarantee against restoration works (Rs. per route meter)
Performance Bank Guarantee
Cement Concrete Roads/ Pavements
Cement Concrete Paver Blocks
Metalled Roads/ Pavements
Unpaved (Kutcha) Roads/ Rastas
Others
1 Micro Trenching Method 50/- 50/- 30/- NA 20/-
2
Horizontal Directional Drilling Method/ Horizontal Boring Method
100/- 100/- 100/- 100/- 100/-
3 Open Digging Method Not Allowed
Not allowed
Not Allowed 500/-
![Page 20: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/20.jpg)
Page 18 of 26
2.3.1 The amount for performance Bank Guarantee against restoration shall be
reviewed every five years.
2.3.2 The performance Bank Guarantee, as a security against satisfactory restoration
of sites, shall be valid for a period of six months over and above the project
completion period. In case of time-over runs for completion of the works, the
Bank Guarantee shall be renewed/ got extended by the Applicant
corresponding to the revised completion period + 6months. The Applicant
shall obtain formal permission for time-extension from the competent
authority.
2.3.3 The Applicant shall report satisfactory completion of restoration of related
work sites, which shall be visited/ ascertained by a representative of the State
Government Department/ Agency within a period of 15 days of such report.
Thereafter, the Bank Guarantee shall be discharged to the Applicant within 15
days from the date of inspection thereof or 30 days of submission of the
request subject to such restoration works having been carried out to the
satisfaction of the said authority.
2.3.4 The Applicant may provide the PBG, as applicable for a stretch over which the
work is proposed to be undertaken and roll the same over to each of the
subsequent stretches, subject to the validity of such PBG for the period of
execution + 6 months.
2.3.5 In case the work contemplated by the Applicant is not completed to the
satisfaction of the concerned Government Department/ Statutory Authority/
State Agency granting the permission, the Competent Authority may extend
the completion period as deemed appropriate, along with extension in Bank
Guarantee. Where the Applicant fails to meet his performance obligations in
this behalf within the agreed time-frame, the Competent Authority may en-
cash the Bank Guarantee and undertake restoration of the site on its own at
the risk and cost of the Applicant.
0-0-0-0-0
![Page 21: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/21.jpg)
Page 19 of 26
Appendix -3
1. Location of Ground Based Masts (GBM) / Communication / Mobile Towers
The location of GBM/ Communication/ Mobile towers is important in view of
any likely adverse impact of radiation on human health. Accordingly, it is important
that the infrastructure installed conforms to the radiation and safety norms prescribed
by the Department of Telecom, Government of India or the TRAI or any other
competent authority in this behalf at all times. Further, the location thereof shall be
governed by radio-frequency system adopted by the applicant and shall be allowed
subject to the following conditions namely:-
1.1 Location of GBM/ Towers should be avoided in thickly populated residential
areas in so far as feasible. In case it becomes absolutely unavoidable to do so,
efforts should be made to install these structures in the open spaces such as
the Parks or Green belts available in the residential sectors or open spaces/
fields in rural areas maintaining a safe distance of about 50 meters from the
residential areas;
1.2 Wherever it is critical to install these communication towers in the populated
residential areas to maintain the communication services and no open spaces
are available, the infrastructure provider should use Micro Cell based stations
where there are high number of users;
1.3 The GBMs/ Communication/ Mobile towers may be installed in the
Commercial, Industrial, Institutional zones or in the open areas (except set-
back area of the buildings) within the Commercial, Industrial, Institutional sites
and fields outside the populated areas;
1.4 In the case of roof-top mobile/ communication towers with multiple antennas,
the roof top usage is desirable to be restricted in the residential areas.
However, the permission to install a mobile/communication tower may be
allowed on the roof-tops of commercial or institutional buildings subject to
Structural Safety Certificates as issued by the designated institutes specified in
this policy.
1.5 The State Government Departments/ Statutory Authorities/ State Agencies
should endeavour to explore the possibility of identifying suitable spaces within
their premises or land as found suitable by the infrastructure provider for the
installation of the GBMs/ Mobile/ communication Towers. The space for such
facilities will be made available to the Applicant/ Service Provider on lease
basis in accordance with this policy within a period of one month from the date
![Page 22: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/22.jpg)
Page 20 of 26
of application, failing which the Applicant shall be free to install the said
structures at alternate locations/ sites identified by them, subject to the
conditions laid down in this policy.
1.6 All the above conditions pertaining to the location of Towers shall also be
applicable to the Moveable Communication Towers.
2. Technical parameters to be followed by the Infrastructure/ Service
Providers while laying the cables (over-ground and underground), erection and installation of Poles/ Dish Antennas / Ground Based Masts/ Mobile & Communication Towers.
2.1 Laying of underground cables:-
2.1.1 The Applicant shall undertake communication infrastructure works in a manner
so as to cause least public inconvenience. He would be expected to suitably
cordon-off the area to ensure public safety and encouraged to execute the
works during off-peak times so as to cause minimum inconvenience to the
public traffic. The Applicant shall restore the dug up area/ sites to their
original condition simultaneously, clear the area of any unused earth/ debris,
and dispose off such debris/ earth at the sites away from the work site as
permitted by the competent authority and to the satisfaction of the concerned
authority.
2.1.2 The applicant shall carry out Ground penetration/ probing Radar survey for
detection of existing utilities/ services along the route where the cable is
proposed to be laid. The data collected in respect of existing utility services
through this survey would be unconditionally shared with the concerned
Government Department/ Statutory Authority/ State Agency free of any
charge;
2.1.3 As far as possible, the Applicant should carry out the work by using Micro
Trenching/ Horizontal Directional Digging (HDD) techniques or Horizontal
boring methods so as to minimize the damage and to cause minimum
inconvenience to public;
2.1.4 The cable shall ordinarily be laid at the edge of the Right of Way or as
permitted/ approved by the competent authority. In case of restricted width of
the Right of Way, which may be adequate only to accommodate the
carriageways, central verge, shoulders, slopes of embankment and drains, the
cables shall be laid beyond the toe-line of the embankments and clear of the
drain. Wherever it is found that it is not feasible to lay the cable without
adversely impacting the existing utilities/ services, the permission may be
![Page 23: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/23.jpg)
Page 21 of 26
declined;
2.1.5 The top of the casing/ conduit pipe containing the cables shall be at least 1.5
meters below the top surface subject to at least 0.3 m below the drain inverts;
2.1.6 Pits of 2 mtrs x 2 mtrs and 1.5 mtrs deep, or of lower size shall be made at a
distance of 100 mtrs, centre-to-centre, for laying cables. However, in case of
special site conditions, variable depth/ dimensions may be permitted
depending on the site conditions;
2.1.7 Route markers shall be fixed, preferably in steel or concrete, along the route
at an interval of 300 mtrs with clear marking of the ownership and depth of the
cable laid.
2.2 Erection of poles for overhead communication cables:-
2.2.1 Permission to lay Overhead cables shall be restricted in terms of para 5.2 of
the Policy;
2.2.2 The electric poles/towers etc. of Power utilities shall not be allowed to lay
overhead communication cables;
2.2.3 Wherever, it is not feasible to avoid laying of overhead cables, the applicant
shall take all precautionary measures to maintain the ecosystem and aesthetics
of that area.
2.2.4 The height of the pole shall be such that it does not interfere with the electric
cables/ distribution transmission system and minimum distance between two
poles would be forty meters;
2.2.5 Subject to availability, a maximum 1mtr x 1mtr space shall be made available
for erection of the pole at a minimum distance of 300mm from the edge of the
walkway of road (road berm) as the case may be and should be installed in
cement-concrete foundation;
2.2.6 The sag of cable should be such that it does not interfere with the movement
of vehicles at any crossing or movement of public transport/ traffic.
2.3 Dish antennas:-
No person (other than Dish Antenna installed under DTH) shall install or
operate cable head-end, dish antenna, dish or any other mode for originating
and communicating cable services and cable modem services to subscribers
unless he has obtained permission in this regard from the concerned authority
of the State Govt department/statutory authority/state agency;
2.4 Ground based Masts:-
![Page 24: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/24.jpg)
Page 22 of 26
The maximum height of Ground Based Mast shall not exceed 30 mtrs. from the
adjoining ground level and distance between two masts shall be maintained at
a distance of not less than 150 meters in line of sight to the extent feasible.
2.5 Mobile/ Communication towers:-
The height of the Mobile/communication Tower from the adjoining ground
level shall not exceed 75 mtrs. subject to clearance from the defence and civil
aviation authorities. Erection of the mobile/ communication towers should be
avoided in narrow lanes (≤ 5 mtrs). However, in the case of moveable
communication towers, the maximum permissible height shall be 21 mtrs.
3. Other terms and conditions to be adhered by the Applicant Service Provider while laying the cables (over-ground and underground), erection of Poles / Dish Antennas / Ground Based Masts/ Mobile/ Communication Towers.
3.1 The terms and conditions/ guidelines issued/ notified by the Department of
Telecommunications, Government of India in respect of any conditions
applicable to the Infrastructure providers or licensees, as amended from to
time, shall be applicable and binding in all cases;
3.2 The permission to lay underground/ over-head communication/ connectivity
infrastructure will not be granted, where it causes disruption of public services
and facilities, obstruction/ hindrance to the pedestrian movement or vehicular
traffic. The principle of public convenience and safety shall over-ride all other
considerations. However, the Competent authority may grant permission in
cases of extreme criticality only if the Applicant offers to suitably adjust and/
or realign such services at his own cost without any adverse impact on the
public services to the satisfaction of the competent authority;
3.3 In the case of GBM/ Mobile/ Communication Towers, permission shall not be
granted, if any building is found in front of the Antenna within the safe
distance in mtrs. as mentioned below:-
Sr. No
No of multiple antennas
Building /structure distance from the antenna (safe distance in mtrs.
1. 2 35 2. 4 45 3. 6 55 4. 8 65 5. 10 70 6. 12 75
3.4 The Applicant, to whom permission for installation of GBM/ Mobile/
![Page 25: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/25.jpg)
Page 23 of 26
communication towers has been granted, shall be responsible to get the
required technical safety checks of the GBM/ Mobile/ Communication towers
from the designated institute and will submit the report to the competent
authority;
3.5 The Applicant Service Provider must get the radiation levels checked at regular
intervals during the O&M period from any competent authority and submit the
conformance reports to the concerned authority. In the absence of such
reports, the Competent Authority may ask for such Tests at the costs of the
Applicant. Non-compliance with the radiation emission standards shall attract
penalties as prescribed by the DoT, GoI from time to time.
3.6 The Applicant, to whom permission has been granted for setting up of GBM/
Mobile/ communication towers, shall be solely responsible for any damage to
the building, adjoining buildings and for the public safety;
3.7 Lightening arresters provided at the top of the GBM/mobile/communication
Tower, shall be of adequate height so that all protruding antennas hoisted on
the mast are protected within its conical safety zone;
3.8 Aviation warning lights installed at the top of the GBM/Mobile/Communication
Towers shall be as per International Civil Aviation Organisation’s guideline and
should be checked regularly for good operating conditions;
3.9 The earth resistance of the GBM/ Mobile/ Communication towers should be
maintained within the prescribed range and should be checked periodically
every year;
3.10 The Applicant to whom the permission has been granted for setting up of
communication infrastructure other than the GBM/Mobile/Communication
Tower shall also be responsible to get the required checks of such
communication infrastructure at regular intervals from any Government
approved agency and will submit the report to the competent authority;
3.11 The optic fibre cable/ communication cables shall not be brought into use by
the Applicant unless a completion certificate is obtained to the effect that the
Telecom cables/ ducts/ manholes have been laid in accordance with the
approved specifications and drawings and the pits have been filled-up to the
satisfaction of the concerned Authority;
3.12 In case any shifting or change in alignment of the already laid optic fibre
cable/ other communication cables/ ground based masts/ mobile/
communication towers is necessitated due to widening of roads/ construction
of flyovers or public buildings, the Applicant shall be bound to do the same at
![Page 26: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/26.jpg)
Page 24 of 26
his own cost within the period specified by the respective authority. If the
Applicant fails to comply with this condition to the satisfaction of the
Authority, the same shall be got executed by the Authority at the risk and cost
of the Applicant. The charges so incurred on this account shall be recoverable
from the Applicant;
3.13 In order to avoid repeated digging on the same routes, the Applicant may
voluntarily lay extra ducts /conduits with redundant capacity so as to take care
of any future needs. However, the creation of excess capacity shall not be a
pre-condition for giving right of way permission;
3.14 The Applicant shall ensure safety and security of all underground installations/
utilities/ facilities and shall be solely responsible for compensation/
indemnification of concerned authority for damage caused/ claims or
replacements sought for at the cost and risk of Applicant to the concerned
authority;
3.15 The extent of the digging trenches should be strictly regulated so that the
cables are laid and trenches are filled up before the close of the work for that
day. Filling should be to the satisfaction of the concerned agency designated by
the department/statutory body;
3.16 The applicant shall not undertake any work of shifting, repair or alterations to
the said cables /communication cables without the prior permission of the
concerned authorities in writing. The Applicant shall be liable to give a notice
of 15 days with route/ location details prior to digging for fresh/ maintenance/
repair works;
3.17 The Applicant shall be advised to obtain insurance cover from an IRDA
approved insurance company against damages to the existing cables/
underground installations etc. during digging;
3.18 The applicant shall make his own arrangement for crossing of cross drainage
structures, rivers, etc, below the bed. In case, this is not feasible, the cables/
ducts may be carried outside the railings/parapets and supported on brackets
fixed to the outside of the bridge super-structure. The fixing and supporting
arrangement with all details shall be got approved in advance from the
concerned Authority granting such permission. Additional cost on account of
fixing and supporting arrangement, as assessed by the Authority, shall be
payable by the Applicant. If the Applicant fails to comply with this condition to
the satisfaction of the Authority, the same shall be got executed by the
Authority at the risk and cost of the Applicant and the cost so incurred on this
![Page 27: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/27.jpg)
Page 25 of 26
account shall be recoverable from the applicant;
3.19 In case of any damage to the essential services i.e. water supply, sewerage
system and telecommunication lines, electricity supply etc, it will be the
responsibility of the company to get the services restored to their original and
satisfactory condition at its own cost;
3.20 Concerned Authority / Department shall not be responsible for any damage to
Optic Fibre cable and resultant losses, if any, during performance of official
duties by any employee of concerned Authority / Department;
3.21 The Applicant shall have to provide barricading, danger lighting and other
necessary caution boards, danger lights while executing the works;
3.22 If any traffic diversion works are found necessary during the working period,
such diversion shall be provided by the Applicant at his cost;
3.23 The concerned authority will be competent to effect an modification/
alterations in the site plan/ route, if necessary, in the interest of public safety;
3.24 The structures/cables shall not be sub-let without the permission of the
Concerned Authority;
3.25 The applicant shall have to abide by all the terms & conditions laid in this
Policy for provision of Infrastructure for communication & connectivity In
Haryana;
3.26 Any dispute arising between the signatories to an agreement under this policy
shall be settled /resolved in accordance with the procedures outlined in the
Agreement i.e. all the disputes will be settled at Chandigarh. In case of breach
of any of the clauses of the Agreement, the competent authority will be
entitled to terminate the contract after giving a show cause notice of 15 days.
An officer of the rank of Administrative Secretary, (to be nominated by the
Government of Haryana) and a representative (to be nominated by the
Applicant) will act as Arbitrators to whom the dispute will be referred and the
decision of the Arbitrators will be final and binding on both parties.
0-0-0-0-0
![Page 28: Annexure -A Wing Policy... · 2013. 8. 21. · 4.2 Permissions granted for moveable communication Towers shall be co-terminus with the period of that event or maximum three months](https://reader033.fdocuments.in/reader033/viewer/2022051809/60152416e1fccf71d95f6d82/html5/thumbnails/28.jpg)
Page 26 of 26
Appendix - 4
An illustrative list of additional facilities as part of the
CSR
Development and maintenance of public parks/roundabouts within the
jurisdiction of the Urban Local Bodies/ areas developed by state agencies/
Gram Panchayats, where the services are rolled out. In such cases, the
concerned department/ authority/ agency shall permit the Infrastructure
Provider to display its Board/ credit for the same as mutually decided/ agreed;
Free-of-charge use of Poles erected by the Infrastructure Provider for provision
of street lights/ LED Solar lights on the Poles (with or without supply of the
fixtures) for provision of the facility of street lighting in a defined area.
Provision of bandwidth/ internet connectivity, free or at discounted rates, to
the local authority for its office and other Community Service Centers, by
whatever name called, for e-delivery of citizen services;
Provide computing hardware (two desktops of latest configuration with laser
printer, webcam, head phone and mike, computer furniture, online UPS etc.)
for at least 10 Village Information Centers/ Citizen Service Centers in the area
where the applicant rolls out its services.
Sponsorship of certain number of Community Service Centers for e-delivery of
citizen services for a particular period;
Establishment of training/ skill development facilities and operation &
management of such Skill Development Centres for an agreed period for
capacity building for the low income groups for improving their employability.
Free-of-cost supply and installation of surveillance cameras on the towers to
be put up on public land. These cameras shall be connected to the designated
police control rooms in the cities and the connectivity may be provided free of
cost or at a discounted price for the agreed period.
0-0-0-0-0