Analytical models of learning curves with variable processing time
-
Upload
sagarika-muthukumarana -
Category
Documents
-
view
27 -
download
0
Transcript of Analytical models of learning curves with variable processing time
ANALYTICAL MODELS OF LEARNING CURVES WITH
VARIABLEPROCESSING TIME
M.S.P,MUTHUKUMARANAGE
E/11/267 1
New labour
INTRODUCTION
2
INTRODUCTION
New or unskilled operators cannot achieved acceptable speed at first time.
The operator will require less and less time to complete the similar task as time goes on.
This is the basic concept of learning curves.
3
INTRODUCTION
The concept of learning curve was reported by wright in 1936.Wright developed a mathematically representation of learning curve
4
LEARNING RATE (¢)
The operator’s performance will improve at a constant rate each time the output doubles.
5
MATHEMATICALLY REPRESENTATIONLearning curve has mathematically representation.The basic model is log linear model.The equation of the log linear model
Y=KX ^n Y- direct labour hours required to produce xth unit. K- direct labour hours to produce first unit. X- cumilative unit numbers N- learning index
N= log ¢ / log 2
6
OTHER MODELS
1. The plateau model
2. The stanford-b model
3. The dejong model
4. The S model
Above all models are the different form of log linear model.
1
2
3
4
Cumulative unit numberDi
rect
labo
ur h
ours
per
un
it
7
OBJECTIVES
Calculate the time to complete a given batch of items exactly for
1. One machine system
Start Buffer Activity End
8
• 2. Two machine system (2M1B)
Develop equations to find variability of processing time and average processing time.
Start Activity Buffer Activity End
9
CALCULATION Single machine processing time to complete 1000 parts by using log
linear model when
Processing time is deterministic.
Cumulative Unit Number
Dire
ct la
bor h
ours
10
11
Processing time has exponential distribution.
1 2 3 4 5Cumulative Unit Number
Dire
ct la
bor h
ours K
K3n
K4n K5n
K2n
Mean = K*Xn
12
Exponential distribution
Mean=1/λ
Hypo-exponential distribution
λ(i)
13
CALCULATION
Considering hypo exponential distribution
Mean time for produce 1000 parts =1587 hr
Variance =3062 hr0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0.000X
Dens
ity
1479
0.025
1695
0.025
1587
Distribution PlotNormal, Mean=1587, StDev=55.33
14
Results Using Other Models
Model Name Equation Mean Variance
Stanford-B model
Y(x)=Y1(X+B)-b
1559.857 2813.13
Dejong’s model
Y(x)=Y1[M+(1-M)X-b]2428.25 6336.51
15
Work To Be Done
Develop above calculations for two machine one buffer system (2M1B)
1.With Infinite buffer size
Start Activity Buffer Activity End
Infinite 16
2. With finite buffer size(by increasing one by one)
Start Activity Buffer Size= 1 Activity End
Start Activity Buffer size=2 Activity End
17
THANK YOU
18