Analysis of Monetary Times Building
-
Upload
sam-exeeson -
Category
Documents
-
view
224 -
download
6
description
Transcript of Analysis of Monetary Times Building
Monetary Times BuildingRyerson University
Comprehensive and integrated building analysis.
Overview
341 Church Street. Toronto
Monetary Times Building. Ryerson University
Introduction
Analysis on the compliance of Ontario Building Code
Analysis of the materials and methods of Construction
Use of Building Information Modeling – Revit
Conclusion
01
02
03
04
05The Team
The following analysis evaluates Monetary Times building for its
compliance of Ontario Building code, the materials and methods of
construction and illustrates the findings using BIM. Revit 2015 is used
for building information modeling. Rania Matta Jasleen Bedi Goncalo Leitao Farid Ahamadi Sam Exeeson
Location and Site Context
Monetary Times Building
Is located at the North end of Ryerson Campus
< N
OR
TH
Eric Palin Hall
Architecture Building
Engineering Building
Kerr Hall
Eric Palin Hall
On the East side of the building
Ryerson Architecture Building and Ryerson Engineering Building
On the South side of the building
Kerr Hall
On the West side of the building
Church Street
On the West side of the building
< N
OR
TH
Gerrard Street East
On the North side of the building
< N
OR
TH
Years of History
Square meters of Total Area
First Register found at Toronto Lands Registry Office
The property was sold to Monetary Printing Press Company
Designed and built by J. A. Thatcher
Ryerson University acquired the property
Exterior renovation by Lett Smith Architects
Renovation Completed
Interior renovation
Renovation Completed
160
2450
1848
1927
1931
1966
1989
1993
2008
2012The building was initially planned to be of six floors for printing operations of
Monetary Times printing press, but only four floors were constructed.
Project Overview and Background
341 Church Street. Toronto
Monetary Times Building. Ryerson University
Building description
Concrete and Brick Cladding with Art-Deco ornaments on North and West facade
Church StreetGerrard Street East
• 34 meters long
• 18 meters wide
• 4 Storey
Building description
Simple Brick Cladding on South and East facade
West Entrance
East Entrance
South Service Entrance
< N
OR
TH
Gerrard Street East
34 meters
Ch
urc
h S
tre
et
17
me
ters
Building Program
Entrances and Exits
Building description
Floor occupancies and general layout
ele
va
tor
sta
irca
se
Basement
First floor
2 laboratories, 1 machine shop, 3 offices, 1
student competition room, janitor room &
Barrier free water closet
Second floor
2 computer Laboratories, photocopy Room,
Boardroom, 3 water closets (one female,
one men and one barrier-free) Faculty
Lounge and 9 Offices
Third and Fourth floor
2 laboratories, 9 offices and 3 water closets
Class rooms
Laboratories
Offices
Toilets
Janitors Room F
irst
flo
or
Se
con
d f
loo
rT
hir
d f
loo
rF
ort
h f
loo
r
Ontario Building Code
• Major Occupancy : Group A Division 2
• Building Area: 557.08 m2
• Gross Area: 2453 m2
• Number of Storey: 4
• Number of Streets Fire Fighting Access : 2
• Applicable parts of Building Codes: Division B, Part 1, 3, 4,5,6,7, 10, 11, 12
• Building Classification : 3.2.2.24 Any area, up to 6 Storey
1
2
3
4
1. Sprinkler system required on each floor of the building.
2. Non-combustible construction
3. Building height up to 6 storey
4. Floor assemblies to have 1 Hr. Fire Separation
5. Load bearing walls and columns to have 1 Hr. Fire-resistance rating
a aaa
r
Ontario Building CodeBuilding Classification and Major occupancy
Exit 1
Fire Hydrant
Gerrard Street East
Ch
urc
h S
tre
et
Exit 3
Fire Department Connection
6 m
11 m
Provision for Fire fighting
Ontario Building Code
3 m
< N
OR
TH
1. 38mm diameter hose connection in each floor of the building.
2. Fire Hydrants to be located within 90 m
3. Fire detectors – service spaces, elevations
4. Smoke Detector – Staircases, Elevator machine room
5. Fire alarm system is required
6. Access to Above Grade Storeys for fire fighters
7. Roof Access required by stairway or hatch with fixed ladder.
8. Barrier free design for passenger elevator
9. Elevator Hoist Way, Machine Room - 1 Hr. FFR
10. Services room - 1 Hr. FFR
aaaaa
a
aaa
r
NORTH >
First floor Second floorFire Protection and Occupant Safety
Ontario Building Code
Vertical Shafts
Elevator Shaft
Janitor
FHCFHC
Fire Alarm – Manual pull system
Fire Hose Cabinet
Exit Signage
FHC
EXIT
EX
IT
EXIT
EXIT
EXIT EXIT
EXIT
EXIT
EXIT
1 Hr. Fire Separation
45 Min. Fire Separation
Area Required FR and compliance
Corridor used by the public 1 hr.
Janitor room 1 hr.
Basement (sprinklered) 1 hr.
Doors in fire separation between Rooms and Corridor 45 min.
Vertical shafts 45 min.
Exits 1 hr.
Elevator and Staircases 1 hr.
Elevator hoist way 1 hr.
Elevator Machine room 1 hr.
Service rooms 1 hr.
Basement 1 hr.
* The walls separating the staff offices, classrooms, laboratories and/or computer labs don’t need to be
fire rated as these form a part of the overall suite and cannot be considered as different occupancies.
FHC
NORTH >
Fire Protection and Occupant Safety
Ontario Building Code
Vertical Shafts
Elevator Shaft
Janitor
FHC Fire Alarm – Manual pull system
Fire Hose Cabinet
Exit Signage
FHC
EXIT
EXIT
1 Hr. Fire Separation
45 Min. Fire Separation
* The walls separating the staff offices, classrooms, laboratories and/or computer labs don’t need to be
fire rated as these form a part of the overall suite and cannot be considered as different occupancies.
Third floor Forth floor
EX
IT
FHC
FHC
EXIT
EX
IT
FHC
Area Required FR and compliance
Corridor used by the public 1 hr.
Janitor room 1 hr.
Basement (sprinklered) 1 hr.
Doors in fire separation between Rooms and Corridor 45 min.
Vertical shafts 45 min.
Exits 1 hr.
Elevator and Staircases 1 hr.
Elevator hoist way 1 hr.
Elevator Machine room 1 hr.
Service rooms 1 hr.
Basement 1 hr.
NORTH >
First floor Second floorSafety within floor areas
Ontario Building Code
Total Occupant load 357 persons
Requirements Comments
A Two Exits
One Barrier Free entrance/ exit
C Travel Distance between exits - 30 m
DTravel Distance from inside of room to egress door
- 15 m
Capacity of Access To Exits based on 6.1 mm per
person= 2177 mm (1090 x 2) - 1100 mm provided
Minimum Width Of Corridor-1100 mm
Exit Doors Swing towards direction of travel to exit
Floor Occupants
Basement 0
First Floor 94
Second Floor 95
A
A
C
C
A
A
D
D
D
D
X
X
NORTH >
Third floor & Forth floor Exit stairSafety within floor areas
Ontario Building Code
Floor Occupants
Third Floor 104
Forth Floor 64
Requirements Comments
G Dead End Corridor
I Capacity of stairs in access to exit 1100 mm
J Exit Staircase tread/ run 255- 355 mm 229 mm
K Exit Staircase riser 125- 200 mm 180 mm
Headroom clearance of exit doors and stairways
Door hardware operable by one hand
Door release hardware
X Exit signage
A
A
C
J
K
I
1100
G
D
D
NORTH >
First floor Second floor Third floor Forth floor
Accessibility and Health Requirements
Ontario Building Code
Barrier free CirculationMale WC Female WC Bar. Free WC Universal WC
First Floor - - 1 -
Second Floor 1 1 1 -
Third Floor 1 1 1 -
Forth Floor 1 1 1 -
Universal Washrooms
Required number – 2
Building does not comply
Drinking Water
Drinking Water Fountain is provided on all
the floors
OBC ref. Div. B 3.7.4.3(15) & Table 3.8.2.3.A
North Side Unprotected Openings
Limiting Distance is 10 m
Condition First Floor 2 - 4 Floor (Sep.)
Exposed Building Face 145 125
Percentage UPO Allowed 60% 72%
Percentage UPO Created 41% 48%
FR Required and Created 45 min. 45 min.
C/NC Const. as/Req. NC NC
C/NC Clad. as/Req. NC NC
West Side Unprotected Openings
Limiting Distance is 10 m
Condition First Floor 2 - 4 Floor (Sep.)
Exposed Building Face 75 60
Percentage UPO Allowed 100% 100%
Percentage UPO Created 31% 46%
FR Required and Created 45 min. 45 min.
C/NC Const. as/Req. NC NC
C/NC Clad. as/Req. NC NC
Limiting Distance of 10 m on North and West Side
Fire Compartment
South Side Unprotected Openings
Limiting Distance is 6 m
Condition First Floor 2 - 4 Floor (Sep.)
Exposed Building Face 145 125
Percentage UPO Allowed 26% 30%
Percentage UPO Created 17% 28%
FR Required and Created 45 min. 45 min.
C/NC Const. as/Req. NC NC
C/NC Clad. as/Req. NC NC
East Side Unprotected Openings
Limiting Distance is 6 m
Condition First Floor 2 - 4 Floor (Sep.)
Exposed Building Face 60 50
Percentage UPO Allowed 49% 57%
Percentage UPO Created 30% 36%
FR Required and Created 45 min. 45 min.
C/NC Const. as/Req. NC NC
C/NC Clad. as/Req. NC NC
Limiting Distance of 6 m on South and East Side
Fire Compartment
Materials and Methods
Building Structure and Foundation
Materials and Methods
Below Grade
• Retaining walls are reinforced concrete.
• The steel columns are encased in concrete
• The slab over the basement storage 8.75” flat slab with 5.75” drop panels
• 5’ by 5’ feet capitals supports (Fig. 1)
Above Grade
• The building has a steel frame structure with moment resistance frames. (Fig. 2 & 3)
• The reinforced concrete joist and slab structure are supported by a steel frame of beams and
columns 6.75 X 5.5 Grid (Fig. 4)
• The typical floor - 8” concrete joist and 3” concrete slab
• The roof structure is a reinforced concrete joist and slab construction
Structural stability
Monetary Times Building was designed to support 6 floors, but only 4 were built.
Studies shows that the steel columns and concrete footings, along with the floors, indicate a load
capacity of 150 #/sf. over six floors.
Fig. 1 Column Capital Fig. 2 Steel frame Structure Fig. 3 Moment Resistance Fig. 4 Grid
6.7
5.5
Concrete and Steel Structure
Building Envelope and Components
Simple Brick Cladding on South and East facade
South and East Facade
• Designed as typical industrial structure, the elevations are
composed of concrete masonry units brick facing in common
bond (Fig. 1), with large industrial steel sash windows (Fig. 2)
(2.4m high x 3 to 6m wide) and concrete sills.
• Steel canopy at the East entrance (Fig. 3)
• Tall neighboring buildings shade the Monetary Times building
at the south and east side of the building (Fig. 4 & 5)
Fig. 1 Brick Cladding Fig. 2 Steel Sash Windows Fig. 3 Entrance Canopy Fig. 4 Winter Sun Fig. 5 Summer Sun
Building Envelope and Components
North and West facade
Building Envelope and Components
The concrete vertical piers reaching up to two and half floor high on a
four-foot high concrete base along Church and Gerrard Street
Building Envelope and Components
The spandrels over the first floor windows are finished in precast terrazzo, the second
floor level in art-deco motifs and the third floor in brick cladding
Building Envelope and Components
At the roofline, the piers terminate in delightful multiple-plane stone caps
that project slightly above the parapet
Building Envelope and Components
North and East facade details
South East Facade
• At the roofline, the piers terminate in stone caps that project slightly above the parapet.
(Fig. 1)
• Between these caps are decorative panels featuring sunbursts framed by stylized foliage(Fig. 2)
• At the top of the cast-stone base, the piers are decorated with subtle grooves
• Art-Deco floral motif, with rows of simple dentils on second floor (Fig. 3)
• The spandrels over the first floor windows were finished with precast terrazzo
• Fluted-recessed concrete surrounded with terrazzo and decorated iron work (Fig. 4) at the
main door (Fig. 5)
Fig. 1 Stone Cap Fig. 2 Decorative Panels Fig. 3 Art-Deco details
Bri
ck C
lad
din
gC
on
cre
te C
lad
din
gNorth Elevation West ElevationFig. 4 & 5 West Door Detail
Building Envelope and Components
Recent renovation
During the renovation, Lett-Smith architects added a new layer of insulation on the inside of all exterior walls
Co
ncr
ete
Cla
dd
ing
Co
ncr
ete
Cla
dd
ing
Bri
ck M
aso
nry
Ad
de
d I
nsu
lati
on
Ste
el S
tru
ctu
re
Fo
un
da
tio
n
Be
fore
Re
no
va
tio
n
Concrete Cab
Concrete Cladding
Asphalt felt
8” Concrete Joist + 3” Concrete Slab
Air gap
Gypsum false ceiling
Ro
of
Co
nst
ruct
ion
Ex
t. W
all
Co
nst
ruct
ion
Double Glazed windows with Thermal Break
Window Sill
External brick/concrete cladding
Masonry wall
3 inch Rigid Insulation + 6 Mil. Poly Vapor Barrier
Gypsum board w/ paint finish
Plastic laminate sill and Apron
External concrete cladding
Masonry wall
3 inch Rigid Insulation + 6 Mil. Poly Vapor Barrier
Concrete retaining wall
Concrete footing
Building Envelope and Components
Failures in building envelope
Fo
un
da
tio
n
Be
fore
Re
no
va
tio
n
Ro
of
Co
nst
ruct
ion
Ex
t. W
all
Co
nst
ruct
ionLeakage in
Barrier continuity
Water shedding surface
Air Barrier
Vapor Barrier
Evidence of failures in the building envelope is visible through out the external facade
Cracked window sills around the building
Cracked conc. cladding Water logging in facade
Interior Partitions and finishes
Materials and methods
Interior Partitions
• Standard 6”concrete block in the 1st floor (with 1 hr. fire rating for corridors walls)
• ULC- W407- 1 hr. rating with 1 ½”mineral wool Batts, 3 5/8” steel studs & 1/2” THK G.W.B
on both sides used in the upper floor as fire rated separation for the corridor walls)
• 3 5/8” steel studs with 1 ½” sound attenuation Batts & 5/8” THK G.W.B.
• Glass Block wall Decora Pattern 8”x8”x4”, used in the laboratories of the second floor.
Painted gypsum false ceiling with light cove, Vinyl flooring and metal framed doors. Glass block wall at second floorWest side staircase
Building Information Modeling - Revit
Revit
Advantages of Building Informational Modeling over other drafting software
“The idea is to create a 3D model or "virtual" representation of the real physical building. Each 3D element has Information ( referred to as "metadata" ) input into it so that the data can be scheduled automatically, and shared downstream with other stakeholders and team members who may use Revit or other programs such as Navisworks to combine all models from the various design teams”
Qamar Ul Islam, Savoir-Faire | Assistant Professor | Revit enthusiast
Revit was used as the primary tool of analysis for the purpose of this assignment. To achieve maximum
productivity in a short period of time, work-collaboration was used. This allowed multiple users to work
simultaneously to create and develop the building information model.
Existing AutoCAD files provided by the planning department of Ryerson University were imported into the
Revit model as reference. This allowed to create an accurate BIM model based on the as-built drawings.
These are some of many features of Revit which helped us achieve this analysis.
• Work Sharing
• Constraints, Element Identity and Documentation
• Parametric Components, and 3-Directional associativity
• Customizable drawing templates
Floors & Grid Envelope Interiors Ext-Cladding Site and LandscapeStructureWork-sets
Building Information Modeling
Work-sharing
Work sets were established to categorize the development of BIM in the order of
construction. The BIM manager developed the base-model structural elements, base building
envelopes, standardized doors and windows etc. Thereafter each team member developed
the details to create a complete model.
Building Structure
• Foundation
• Retaining walls
• Columns and beams
• Service and circulation cores
Building Envelope
• Exterior walls
• External doors and windows
• External cladding
Building Interiors
• Internal partition walls
• Interior doors and openings
Site and Related Elements
• Site components and massing.
Building Information Modeling
Constraints, Element Identity and Documentation
Each element created in Revit has a an Identity and set of data attached to it. This can be the physical
properties of the indented material of construction or the quantification. Documentation is no longer
manual. The information is already there. All you have to do is extract it.
Element Identity Stair• Type
• Level Constraints
• Offset from Wall
Customization 1• Length
• Height
• Number of Stairs
Customization 2• Details of Riser
• Structural Details
• Nosing Detail
Extract Schedule• Required Information
• Quantity of building materials
• Load and Structural information
Publish Schedule• Bill of Quantities
• Load Schedule
• Manufacture's details
Building Information Modeling
Parametric Components, and 3-Directional associativity
5050 X 2350
4150 X 2350
3950 X 2350
3450 X 2350
Each element is a 3d object with parameters that can be modified to modify the entity
Entire model is a single database with all elements interrelated. The significance of this is that when
you make any changes in one location all affected elements will dynamically update.
Ext - WindowArt – Deco Ornament
Building Information Modeling
Parametric Components, and 3-Directional associativity
Art–Deco Detailing
Building Information Modeling
Art–Deco Detailing
Photograph of Staircase Revit 360 Rendering
Building Information Modeling
Customizable drawing templates
Default workspace• Concept Design
• Working Drawings
• Co-ordination
Architectural Plan Template• Presentation Drawings
• Tender Drawings
• Working Drawings
Color Schemes• Room Tags
• Occupancy classification
• Phasing
3D Drawings• I-Plan Presentation
• Client Meetings
• Reference Views
Building Information Modeling
Renderings
Photograph of Staircase Revit 360 Rendering
Thank you.