Analysis of Indirect Cost

download Analysis of Indirect Cost

of 5

Transcript of Analysis of Indirect Cost

  • 8/10/2019 Analysis of Indirect Cost

    1/5

    l-5

    Selden H. Harlow

    Construction Manager

    C. Thoma s McCreedy

    Charles T. Main International, Inc.

    Prudential Center

    Boston, Massachuse tts, USA

    Charles T. Main International, Inc.

    Prudential Center

    Boston, Massachuse tts, USA

    ANALYS IS OF THE INDIRECT COSTS OF PROJECT CAPITAL

    INVESTMENT COST ESTIMATES

    INTRODUCTION

    There is a wide variance throughout the

    industry in the manner of estimating the in-

    direct costs of major capital investment pro-

    jects of long duration.

    This paper is present-

    ed to (1) identify the components of total

    project cost, (2) analyze the direct costs,

    (3) analyze the indirect costs, (4) identify

    optional direct costs that could, instead,

    be categorized as indirect, and (5) recommend

    a position with regard to the indirect cost

    approach.

    GENERAL

    This paper is the result of a study con-

    ducted by Charles T. Main International, Inc.

    for a Federal Agency whereby conceptual esti-

    mates were prepared by Main and one other

    professional firm for similar advanced energy

    sys tems. The results were substantially

    different, both as to the makeup of Direct

    Cost and the amount of Indirect Cost, and an

    analysis was undertaken as reported herein.

    This paper is directed toward the pre-

    paration of conceptual estimates for a project

    of several years duration.

    For conceptual

    estimating purposes, percentages are often

    used to estimate indirect costs.

    As the pro-

    ject proceeds,

    the estimate is refined and

    updated and, in many cases,

    actual estimates

    of cost,

    rather than percent factors, are

    used for the indirect accounts.

    All per-

    centages shown herein are percentages of

    total project cost except Table No. 5

    which recasts the cost into percent of

    Direct Cost.

    COMPONENTS OF TOTAL PROJECT COST

    The two major categories of total project

    cost are the direct costs and all other costs

    which are identified in this paper as indirect

    costs.

    Table No. 1 identif ies the components

    of total project cost and gives approximate

    percentages allocated to each component. A

    detailed analysis of each of these components

    follows, but it should be noted that indirects,

    as defined herein, include indirect construc-

    tion cost, contingency reserves, professional

    services,

    owner's and other charges, escala-

    tion and financing costs.

    TABLE NO. 1

    COM P ONENTS OF TOTA L P ROTE CT COS T

    Approximate Percentage

    E.5

    of Total Cost

    1 Direct Cat

    57.0

    2

    Indirect Construction Cost

    8.2

    3

    Professional Services

    5.2

    4

    Owners and Other Charges

    1.0

    5

    contingency Reserves

    5.0

    6

    Escalation

    10.2

    7

    Financing Costs

    13.4

    Total Project Cost

    100.0

    Note that, in this case,

    a typical coal

    fired steam electric power station, the in-

    direct costs amount to 43% of the total cost.

    The direct costs (57%) are calculated by ex-

    perienced estimators working with drawings,

    estimated quantities,

    and material and labor

    costs drawn from current data and past exper-

    ience with similar projects.

    The indirects

    are then calculated by applying percent

    factors to the direct cost. The higher the

    percent, the greater the likelihood of error.

    Therefore,

    we believe it is best to maximize

    the items considered in the direct cost es-

    timating.

    ANALYSIS OF DIRECT COST

    The direct cost can be divided into

    three main categories:

    land, materials,

    and installation, which are further broken

    down into the subcategories shown in Table

    No. 2.

    The land costs include the purchase of

    the properties required for the project and

    all costs associated with the acquisition of

    the land, including agent's fees, title search

    and property surveys, condemnations, removals,

    relocations, etc.

    361

  • 8/10/2019 Analysis of Indirect Cost

    2/5

    1.00

    1.10

    1.20

    .21

    .22

    .23

    .24

    .25

    .26

    .27

    .2S

    .29

    1.30

    .31

    .32

    .33

    .34

    .35

    .36

    .37

    .38

    TABLE NO. 2

    ANALYSIS OF DIRECT C OST

    Approximate Percentage

    of Total Cost

    Direct Cost

    Land and Acquisition Cost

    Permanent Materials and Equipment

    Ma,or Purchase Order

    Field Purchase Order

    Furnish and Erect Contracts

    Contra&or FurnIshed Materials

    Freight and Special Packaging

    Technica l Service Engineers

    Customs and Dutiw

    spare parts

    Sales Taxes

    Installation cost

    Manual Labor Wages

    Wage Related C osts (fringe benefits)

    Health and Welfare

    Pension Plan

    Apprenticeship

    Trave l and Subsistence

    .X&iOS

    spec1a1 Insurance costs

    Industry Promotion Funds

    Payroll Taxes

    FICE

    State Unemployment

    Federal Unemployment

    Payroll Premium Costs

    Casual overtime

    High, Tool, Mask, etc.

    Workmens Compensation Insurance

    Supervision (foremanshlp)

    Construction Equ ipmen t forSpecialty Work

    Contractors Fees

    57.0

    0.7

    39.2

    35.4

    0.6

    0.4

    1.5

    0.2

    0.1

    0.2

    0.8

    17.1

    10.4

    1.5

    0.9

    0.3

    0.7

    1.5

    0.8

    1.0

    The permanent materials and equipment

    include the cost of all materials permanently

    incorporated in the work from whatever source

    t.hey are procured. The major purchase orders

    are the engineered equipment, sys tems and

    materials requiring long lead times.

    These are

    generally procured by the engineer or the own-

    er's central purchasing department.

    Certain

    llong lead time items such as chimneys, cooling

    towers,

    elevators, field assembled tanks, and

    architectural features are often procured on

    a furnished and erected basis.

    The erection

    cost portion is carried in installation cost.

    The field purchase orders are for those

    materials which can be purchased with less

    lead time and are normally procured by the

    construction manager or contractor.

    These

    materials usually include civ il engineering

    materials such as sand, gravel , concrete and

    paving materials,

    and miscellaneous piping

    and electrical materials purchased to supple-

    ment the major purchases.

    We consider all

    costs associated with the procurement of

    permanent materials and equipment as part

    of the direct cost.

    Allowances for freight,

    especial packaging,

    technical serv ice engineers,

    (customs and duties, spare parts, and sales

    taxes are included in direct cost materials.

    For international projects the costs

    ,allowed for freight,

    special packaging and

    customs and duties will var y from the stan-

    dards shown in Table No. 2 and special atten-

    tion must be paid to these categories.

    The installation portion of direct cost

    j.ncludes wage costs for all manual labor,

    foremanship,

    all wage related costs mandated

    by labor agreement, payroll taxes, construc-

    tion equipment associated with certain civi l

    work items to which the costs can be directly

    charged, and contractor fees.

    The cost o f all manual labor is estimated

    in the direct accounts. The percent used in

    this example includes ancillary labor for

    unloading, storing and sorting materials and

    equipment, general and final cleanup, and

    other miscellaneous activities charged to the

    direct accounts.

    Also included are all fringe benef its,

    payroll taxes, payroll premium costs (casual

    overtime, mask, tool, high time pay, etc.)

    and workmen's compensation insurance costs

    which are built into the wage rate.

    Con-

    tractor fees, which are frequently included

    in unit price estimates which are generated

    in later updates of the estimate, are also

    included.

    Finally, for items such as earthwork,

    piling, roads,

    specialties (such as chimneys

    and cooling towers), contractor equipment

    and other overhead costs are estimated on

    a lump sum or unit price basis and charged

    directly to a single account.

    COMPONEmS OF INDIRECT CONSTRUCTION COST

    There are many items of cost associated

    with any construction project which cannot

    be convenient ly charged direct ly to a single

    estimating account. These items are commonly

    referred to as indirect costs, or distribu-

    tables, in the industry.

    The indirect accounts include indirect

    construction cost, contingency reserve, pro-

    fessional serv ices, owner's and other charges,

    escalation and financing costs. For concep-

    tual estimates, these items are often expressed

    as a percent of the direct cost.

    When detailed

    construction cost

    estimates

    are produced later

    in the project period,

    many of these items can

    be calculated on a unit or fixed cost basis,

    but they are still considered indirects be-

    cause of their multipurpose nature.

    Indirect Construction Costs include

    facilities,

    equipment and serv ices required

    to directly support the construction opera-

    tions. These items are summarized in Table

    No. 3.

    TABLE NO. 3

    COM P ONE NTS OF INDIRECT CONS TRUCTION COS TS

    2.10 Field Offic e and Labor Expenses

    Office Space and Equipment

    Opera ting Expenses and Supplies

    Communications

    Safety Equipment

    Inclement Weather Gear

    Gmstruction Camp Operations

    On-site Transportation

    .20 Non-Manual Labor Wages and Benefits

    .30 Tempo rary Construction Buildings

    -40 Construction Tools and Equipment

    Heavy Equipment

    Automotive Equipment

    Maintenance Costs

    Small Tools

    Special Equipment Rentals

    Approximate Percentage

    of Total Cost

    1.3

    0.8

    0.9

    2.7

    362

  • 8/10/2019 Analysis of Indirect Cost

    3/5

    NC?,

    .50

    .EO

    .>'O

    . HO

    .30

    TABLE NO. 3 (Continued)

    Approximate Percentage

    of Total Cost

    Temporary Facil i ties

    Utility Distribution Syst ems

    Trans port, Railroad, Parking , Roads

    Inclement Weather Protection

    Scaffolding

    Expendable Supplies

    Utility Charges

    Fuels; Oils

    and

    Lubricants

    G.St?S

    Chemicals

    Concrete Fo rm Materials

    Construction Service Contracts or Costs

    Testins Laboratodes

    0.4

    0.5

    0.3

    Guard service

    Toilet Rental

    Trash Disposal

    surveying

    Premium Payments (pay for non-productive time)

    0.3

    Showup Time

    Paid Holidays

    Absence or Sick Leave

    Scheduled Overtime

    Labor Dlsruptio

    Insurance and Bonds 1.0

    All Risk Builders Risk

    Public Liability and Property Dam age

    Vehicle PL and PD

    Bid and Performance Bond Premiums

    Field o ff ice and labor expense (1.3%)

    includes the cost of providing the field

    off ice building and furnishing and equipping

    it: with offi ce equipment. This category

    also includes the field off ice operating

    expense, such as janitorial service, util ity

    services, stationery supplies and reproduction

    costs, and communications costs.

    The costs

    associated with the employment of construction

    labor, such as safet y equipment, inclement

    weather gear, and labor administrative costs

    are also included in this category of indirect

    construction cost. If the project is at an

    isolated site requiring a construction camp,

    t'he.costs of developing and operating the camp

    would be included here.

    The second category of indirect construc-

    tion cost in non-manual labor (0.8%) which

    includes the wages and benefits for inspectors

    and technicians, clerks, typist s, draftsmen,

    timekeepers, messengers, and such other field

    personnel that are usually locally hired. It

    should be noted that construction management

    personnel are not included herein, but will be

    covered later under Professional Services.

    The cost of temporary construction build-

    ings (0.9%) is included as a component of in-

    direct construction cost and includes change

    buildings, warehouses,

    workshops and assembly

    buildings,

    toilet buildings, and all trailers

    and buildings used by service engineers.

    The cost of construction tools and equip-

    ment (2.7%) is the fourth part of indirec

    construction cost and includes the cost o

    procuring and maintaining heavy equipment,

    automotive equipment, and special equipment

    rentals as required. The source of supply

    of such equipment is not considered signifi -

    cant for estimating purposes arid could be

    owner-furnished, or leased or furnished by

    contractors working on the job.

    The cost of

    small tools is also included, although these

    are usually furnished by the contractors

    who are responsible for controlling their

    use. As mentioned earlier, specia lty equip-

    ment required for equipment intensive work,

    such as pile driving and earth work, is

    included in the direct cost section of the

    estimate.

    Temporary facilities (0.4%) is the fif th

    component of indirect construction cost and

    includes the installation of temporary util-

    ity distribution systems (water, air, gases,

    sanitary, electricity,

    etc.),

    and temporary

    transport facil ities, such as roads, rail-

    roads,

    and parking areas. Special provisions

    for inclement weather protection, including

    enclosures and services (heat, lights, etc.) ,

    are also estimated herein.

    The sixth component of indirect construc-

    tion cost is the category of expendable supplies

    (0.5%) and this includes charges fo r util ity

    services, fuels, oils and lubricants used

    during construction. The cost of other expen-

    dable supplies,

    such as gases and chemicals,

    are also in this category, as is the cost of

    concrete form materials which can be distri-

    buted to the direct accounts upon completion

    of the work.

    Construction service contracts or costs

    (0.3%), such as testing laboratories and

    surveying, security services, toilet rental,

    trash disposal, are estimated as a component

    of indirect construction cost whether perform-

    ed by service contractors, the construction

    manager, or included in installation contracts.

    Premium payments for

    time

    not worked

    (0.3%) are also estimated as an indirect con-

    struction cost and include such premiums as

    inclement weather, showup time, paid holidays,

    paid absences and sick leave, if any, and

    allowances for lost time due to labor dis-

    ruptions.

    In the event that an accelerated sched-

    ule or severe labor shortages make it desirable

    to schedule overtime, the premium pay cost,

    together with a factor to cover the reduction

    in productivity which usually follows, is

    carried as an indirect cost. The 0.3% value

    used here does not represent any allowance

    for scheduled overtime as this practice is

    avoided whenever possible.

    The cost o f insurnnce and bonds (1.0%)

    is the final component of indirect construction

    cost and includes the premiums paid for all

    risk, builders risk coverage, public liabil-

    it y and property damage, vehicle PL and PD,

    and bid and performance bonds whether procured

    on a project umbrella coverage policy or con-

    tractor's individual policy basis.

    It should

    be noted that workmen's compensation coverage

    is included in the direct cost.

    CONTINGENCY RESERVE (5.0%)

    Contingency is an allowance for costs

    which may be incurred as a result of factors

    which cannot be speci fical ly anticipated and,

    therefore, cannot be included in the direct

    accounts.

    Items such as unknown site condi-

    363

  • 8/10/2019 Analysis of Indirect Cost

    4/5

    tions, unforeseen construction problems,

    minor scope changes,

    estimating errors and

    omissions, engineering uncertainty and var-

    iances in labor productivity are included.

    In recent years it has also been necessary

    to consider the effects of an uncertain and

    ralpidly changing economy. Wage rates and

    benefits, escalation and financing costs are

    all accounted for elsewhere in the estimate,

    but the uncertainty with respect to these

    forecasts may also be considered as part of

    the contingency reserve.

    Contingency does not include Force Majeure

    or major scope changes.

    There are many ways to estimate contin-

    gency at the conceptual level. Frequently,

    a higher factor is used on that portion of the

    project estimate involving the civil works,

    if the site conditions are uncertain. In

    addition, the factor varies with the degree

    of uncertainty with respect to engineering

    an.d technology.

    In some advanced technology

    projects, a separate factor is carried for

    engineering uncertainties. In this case, we

    have used 5% which amounts to 8.8% of the

    direct cost.

    EOFESSIONAL SERVICES (5.2%)

    Professional services include the follow-

    ing activities:

    project management, prelimin-

    ary engineering,

    detail engineering and design,

    construction management, procurement services,

    architectural design, shop inspection and

    expediting. These serv ices may be performed

    by the owner,

    a single professional engineering

    firm,

    or by a combination of professional firms,

    but we recommend that all professional services

    be grouped together in this manner for estima-

    ting purposes.

    OWNER'S AND OTHER CHARGES (1.0%)

    -

    Allowances must be made in the project

    estimate for owner's charges that are capi-

    talized as part of the project.

    These own-

    er's charges include such categories as

    general office expense, owner's field staff,

    legal fees, ad valorum taxes, and capitalized

    startup costs. Other charges that are esti-

    mated in this category include spare parts

    and special tools for operation and main-

    tenance of the completed project.

    PsCALATION (10.2%)

    The Cost of major projects of long dura-

    tion are affec ted greatly by international

    economic conditions and we recommend that

    the

    project estimate be prepared for the cur-

    rent

    Y = ~ L

    and the costs be escalated to meet

    the project schedule.

    The other option is

    to calculate the escalation individually for

    each component of direct cost and include

    escalation as part of the direct cost. We

    recommend that escalation be carried as a

    line item of indirect cost where it is vis-

    ible to management.

    FINANCING COSTS (13.4%)

    The final item in the estimate is fi-

    nancing costs which include the total cost

    of all financing charges that are capital-

    ized as project costs.

    Included are allow-

    ances for funds used during construction

    (AFDC) and any fund commitment fees for

    international projects. To calculate AFDC,

    it is necessary to prepare a cash flow match-

    ing the cost and schedule and for loans at

    different interest rates, separate calcula-

    tions are desirable.

    For conceptual estimating purposes these

    financing costs are often combined into an

    interest factor which is a percentage of

    the total project cost.

    OPTIONAL COSTS - DIRECT OR INDIRECT

    Throughout the text of this paper, we have

    identified project costs and indicated our

    preference for treating them as direct or

    indirect costs.

    In Table No. 4 the i tems which we include

    in the direct cost , but which could be treated

    as indirects, are listed.

    TABLE NC. 4

    OPTIONAL COSTS - DIRECT OR INDIRECT

    Approximate Percent

    y&

    of Total Cost

    1

    Freight and special packaging cost

    .2

    for material and equipment

    2

    cost of technical service engineers

    .1

    from manufacturers

    3

    customs charges, duties and sales taxes

    .8

    4

    Spare parts

    .2

    5

    Payroll taxes and workmens compensation

    1.6

    lSranCe

    6

    Payroll premium costs

    .3

    (casual OYertlme, etc.)

    7

    Supervision (foremanship)

    1.5

    8

    Ancillary labor (unloading and stora ge,

    .7

    housekeeping, final cleanup)

    9

    Construction equipment for equipment

    .8

    Intensive work (such as earth work

    and pi11ng) and for specialty erection

    contracts (such as chimneys and

    c001i11g towers)

    10

    cc,ntractor fees

    1.0

    7.2

    SUMMARY AND RECOMMENDATIONS

    We have summarized and explained the

    components of capital cost estimate for a

    major project. We have also identified op-

    tional costs which could be considered in-

    direct rather than direct cost,

    To place this in perspective for objec-

    tive analysis,

    we have recast the estimate

    with all categories shown as a percentage

    of direct cost.

    This enables us to compare

    the total project cost if the optional costs

    are in the directs,

    as we recommend against

    the other extreme with all optional costs

    as indirects.

    364

  • 8/10/2019 Analysis of Indirect Cost

    5/5

    Analysis of Table 5 points out the value

    of minimizing the percent added for indirect

    costs

    Considerable time and eff ort is ex-

    pended by estimators to accurately forecast

    tke Direct Cost.

    If the inflated multipliers

    are incorrect,

    the error in the estimate is

    magnified.

    If direct cost estimates are

    inaccurate because of error or poor defini-

    tfLon

    the inflated multipliers again magni fy

    the rhange in the estimate. Last,

    and per-

    haps most important,

    indirect costs are dif f-

    i