Collaboration to Clarify the Costs of Curation
The Action Sessions - 4C Case Studies and Quantitative Data
Our goal was to try and get commentary and verification on some 4C concepts and objectives and then to crowdsource some data and actively collaborate with participants ...
We did some exercises and collected data
We set out some objectives and checked some assumptions
We heard new stakeholder perspectives
This slide deck is an annotated version of the Action Session summary I gave on the last day of the ANADP II conference .... (with an extra 2 slides to feature some results of a ranking exercise we did during the session)
![Page 2: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/2.jpg)
Exercise 1A journey that you are familiar with ...
Start
End
Collaboration to Clarify the Costs of Curation
1
2
3
4
5What strikes you about your journey?
Digital Curation is a journey not a place ...
We asked people to think about ....
We said make a list of ....
![Page 3: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/3.jpg)
Exercise 1A journey that you are familiar with ...
Start
End
Collaboration to Clarify the Costs of Curation
1
2
3
4
5
What strikes you about your journey?
Digital Curation is a journey not a place ...
Home
Junction to decide which route – depends on traffic
Narrow section on lane with oncoming traffic
Zig-zag – oncoming lorries
Petrol station
Car park (taffic)
“My spot” to drop (School)
This was one example of what people came up with ....
![Page 4: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/4.jpg)
Collaboration to Clarify the Costs of Curation
Exercise 2In relation to your activity ... what are the associated cost categories?
v
Then we got them to think about what this journey cost and what the cost components were ....
![Page 5: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/5.jpg)
Collaboration to Clarify the Costs of Curation
Exercise 3How might you describe the sequencing of a digital asset in your organisation?
Start
End
1
2
3
4
5
Then we asked them to apply this approach to the journey a digital asset makes through time ....
![Page 6: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/6.jpg)
Collaboration to Clarify the Costs of Curation
Exercise 4In relation to your digital asset ... what are the associated cost categories?
v
![Page 7: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/7.jpg)
Collaboration to Clarify the Costs of Curation
Exercise 4In relation to your digital asset ... what are the associated cost categories?
v
Capital investment for physical infrastructure
Capital investment for e-infrastructure
Operating costs physical inc. staff to run instruments & work with visitors Visiting scientists
time
Operating costs e-infra inc. staff to talk to physical infra people
Small marginal cost of each dataset (media etc.)
Software development for data analysis & maintenance
Consultation with users to plan future developments and keep service relevant
This is an example of how one of the participants broke down the cost categories of managing assets over time ...
![Page 8: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/8.jpg)
Exercise 5 - Indirect Economic Determinants To what extent would your organisation regard the following 15 outcomes as an investment priority?
IED High Medium Low Notes
Authenticity
Benefit
Efficiency
Impact
Innovation
Interoperability
Quality
Reputation
Risk
Sensitivity
Skills
Sustainability
Transparency
Trustworthiness
Value
We asked them to prioritise what the 4C project is calling the indirect economic determinants of digital curation ...
![Page 9: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/9.jpg)
17 forms were returned at the end of the session and the ranked results are below ...
Collaboration to Clarify the Costs of Curation
Value
Trustworthiness
Risk
Sustainability
Reputation
Impact
Efficiency
Benefit
Quality
Authenticity
Interoperability
Transparency
Skills
Innovation
Sensitivity
0 5 10 15 20 25 30 35 40
![Page 10: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/10.jpg)
Collaboration to Clarify the Costs of Curation
Risk
Trustworthiness
Sustainability
Benefits
Efficiency
Value
Transparency
Reputation
Confidentiality
Interoperability
Flexibility
Sensitivity
Impact
Authenticty
Innovation
0 5 10 15 20 25 30 35 40
Which loosely correlates in places with an earlier iteration of the exercise carried out with a completely different group 2 months earlier ...
‘Flexibility’ and ‘Confidentiality’ have been replaced in the later exercise by ‘Skills’ and ‘Quality’
![Page 11: ANADP II Conference 4C Project Action Session Summary](https://reader036.fdocuments.in/reader036/viewer/2022082808/55625e82d8b42aab1a8b45b4/html5/thumbnails/11.jpg)
Collaboration to Clarify the Costs of Curation
Discussion ....
To what extent can digital curation adopt the approach where we benchmark against an ‘industry standard’ (e.g. insurance comparison sites)
Larger organisations don’t need a Curation Costs Exchange – the value of it will be for smaller organisations who need to understand cost structures for planning their budgets
OpenAIRE is doing a costs/benefits analysis of running an institutional repository
4C should explain terminology and let people combine their cost structures themselves
We need a very concise way of bringing out the benefits of investing into digital curation. The costs should always be linked to the benefits. Focusing on the return on investment is vital
We need to acknowledge that calculating the cost of curation is a significant cost in itself
Data usage (web stats etc. any quantitative figures for data use are very important)
THANKYOU and please continue to help us with this work www.4Cproject.eu
The main points to come out in discussion were as follows ...
We now need to analyse the cost categories that people defined on their sheets ...