ANAB AQMS Activity 2011 ~ Year so far January 2011. AQMS 2011 (including last ¼ of 2010) Overview. Accredited Certification Bodies (CBs) 36 AS9100 11 AS9110 28 AS9120 Applicant CBs 4 AS9110 Increased Surveillance Frequency 1 CB (twice per year for office assessments) - PowerPoint PPT Presentation

Transcript of ANAB AQMS Activity 2011 ~ Year so far January 2011

Page 1: ANAB AQMS Activity 2011 ~ Year so far January 2011

ANSI-ASQ National Accreditation Board

Page 2: ANAB AQMS Activity 2011 ~ Year so far January 2011

Accredited Certification Bodies (CBs) 36 AS9100 11 AS9110 28 AS9120

Applicant CBs 4 AS9110

Increased Surveillance Frequency 1 CB (twice per year for office assessments) 1 CB (twice per year for AQMS witnessed audits)

Suspensions 1 Voluntary (withdrawn) 1 nonconforming (lifted)

Withdrawals Alliance, voluntary, merged with AQA

01 Nov 2010

Page 3: ANAB AQMS Activity 2011 ~ Year so far January 2011

33 Completed (in OASIS)

3 In process

Heads Up 170, 175, 181

All CB’s applied prior to 1 Jan 2011 (no suspensions)

Requiring transition plan information; communications with customers, audit day calculation process, multiple site process

Page 4: ANAB AQMS Activity 2011 ~ Year so far January 2011

9

2

11

10

3

13

10

2

12

3

2

5

0

2

4

6

8

10

12

14

Valid Invalid/Unable to Substantiate

Under investigation Total

2007 2008 2009 2010

Page 5: ANAB AQMS Activity 2011 ~ Year so far January 2011

346 (Feb 2010) – Alleging a CB transferred an AS9100 certified client without following the transfer process. It was determined throughout the investigation and review

of CB records that the complaint was not valid.

Closed, invalid

Complaints in italics were provided previously and has no changes.

Complaints in bold are new or were updated since the last meeting.

Page 6: ANAB AQMS Activity 2011 ~ Year so far January 2011

347 (Mar 2010) – An OEM issued a complaint against a CB for not closing their nonconformity(s) in a timely and appropriate fashion. Additional action was taken by ANAB and the CB took

additional action.

Closed, with action

Complaints in italics were provided previously and has no changes.

Complaints in bold are new or were updated since the last meeting.

Page 7: ANAB AQMS Activity 2011 ~ Year so far January 2011

358 (July 2010) – An AQMS accredited CB has an arrangement with another body that include AS certification activities. The other activities of that other body are questionable and may include management system consulting. It was determined the organization was not consulting, but

they were misleading in their advertising/marketing.

Closed, with action

Complaints in italics were provided previously and has no changes.

Complaints in bold are new or were updated since the last meeting.

Page 8: ANAB AQMS Activity 2011 ~ Year so far January 2011

364 (Oct 2010) – An OEM issued a complaint against a CB for numerous findings issued during 2010 oversight.

Open, needs action (by ANAB)

Complaints in italics were provided previously and has no changes.

Complaints in bold are new or were updated since the last meeting.

Page 9: ANAB AQMS Activity 2011 ~ Year so far January 2011

367 (Nov 2010) – Against ANAB An ANAB Assessor took an organization’s Manual back to

the hotel to review during a WA.

Closed, with action

Complaints in italics were provided previously and has no changes.

Complaints in bold are new or were updated since the last meeting.

Page 10: ANAB AQMS Activity 2011 ~ Year so far January 2011

A91 – Received Dec 2010 – Open, hearing being scheduled Appealing several NCR’s from an AQMS witnessed audit Will be heard in early February

Appeals in italics were provided previously.

Appeals in bold are new.

Page 11: ANAB AQMS Activity 2011 ~ Year so far January 2011

Office Assessments 41 required (5 additional)

34 confirmed 7 unscheduled

Witnessed Audits 38 required (2 additional)

17 confirmed or tentative with dates 21 unscheduled

Page 12: ANAB AQMS Activity 2011 ~ Year so far January 2011

Office Assessments 22 NCR’s to aerospace requirements during 42 office assessments

5 majors (2 originally minor, escalated due to timing)

140 NCR’s to ISO 17021 or general requirements during 42 office assessments 16 majors (3 originally minor, escalated due to timing)

Witnessed Audits 61 (18 to AS requirements) NCR’s issued during 40 witnessed audits

22 majors (9 originally minor, escalated due to timing)