American Public Power Association
-
Upload
valentine-mcfarland -
Category
Documents
-
view
19 -
download
1
description
Transcript of American Public Power Association
American Public Power Association
The Challenge of Building a Coal Plant in Today’s Environment
Raj RaoPresident, Indiana Municipal Power AgencyChairman, Prairie State Generating Company
Page 2
Campus Overview
• Site Area: 700+ Acres
• Coal Fuel: Adjacent New Mine
• Water Supply & Discharge: From the Kaskaskia River – 14 miles from the Site
• Waste Disposal: Rail Transport to Offsite Disposal Area and Limestone Delivery
• Transmission: Interconnect with Local Utility – Ameren 2 – 345 kV “Short” Lines at the Site 1 – 345 kV “Long Line” across the Mississippi River Other Transmission Upgrade Projects
• Base Target Completion Dates: Unit 1 – August 2011 Unit 2 – May 2012
3
Prairie State Owners Serve More Than 2.5 Million People In Nine States
AMP-Ohio368 MW
Indiana Municipal Power200 MW
Missouri Joint MunicipalElectric Utility Commission
195 MW
Prairie Power, Inc.130 MW
Illinois Municipal Electric240 MW
Southern IllinoisPower Cooperative
125 MW
Northern Illinois MunicipalPower Agency 120 MW
Kentucky Municipal Power124 MW
Page 2
Page 4
American Public Power AssociationPrairie State Energy Campus
Challenge of Building a Coal Plant in Today’s Environment
• Site Selection• Environmental Permits• Partners & Financing• EPC Contractor
Page 4
Page 5
American Public Power AssociationPrairie State Energy Campus
Challenge of Building a Coal Plant in Today’s Environment
• Procurement• Construction• Safety, Cost and Schedule• Staffing
Page 5
Page 6
American Public Power AssociationPrairie State Energy Campus
Challenge of Building a Coal Plant in Today’s Environment
• Construction– Bechtel EPC-M– Peabody-Mine– PSGC Staff
• Operations– Experienced Operator vs. Experienced
Staff (Hire)
Page 6
Page 7
Coal Mine Overview Project participants own 200 Million tons of
coal (recoverable) for a dedicated source of fuel for the project– Mineral rights to coal are owned– Reserves located adjacent to the plant to the East, West and
North of the project– Adequate to supply project for 30 years at approximately 6.5
Million tons per year– Using continuous mining technology
American Public Power AssociationPrairie State Energy Campus
Challenge of Building a Coal Plant in Today’s Environment
Page 8
Slope
Basin
StockpileFuture Office
In the Beginning:
Page 8
Page 9
Aerial of the Mine Slope
9Page 9
Page 10
Mine Slope – at Brow
Page 10
11
Power Plant Overview October 2007
Page 11
12
19 Months LaterFirst Unit 2 Structural
Steel
Page 12
Major Safety Milestone
Page 13
Power Plant Overview
2 x 800 MW Net Supercritical Units
Babcock & Wilcox Pulverized Coal Boilers
Toshiba Steam Turbine Generators
Siemens/Wheelabrator Air QualityControl System
Balance of Plant with: Cooling Towers Water Treatment Plant Single Shell, Dual Flue Chimney 14 mile Raw Water Pipeline 4 mile Railroad
General Contractor – Bechtel PowerCorporation
First ConcreteFeb. 2008
Completed Unit 1 Boiler Steel March
2009
Page 14
Page 15
Construction - Project Quantities
• Concrete – approx. 165,000 cubic yards, enough concrete to fill more than 50 Olympic-sized swimming pools
• Structural and Miscellaneous Steel – approx. 42,000 tons, about half of the steel tonnage of Sears Tower
• Pipe (A/G and U/G) – approx. 120 miles, enough pipe to stretch from Lively Grove, IL to Springfield, IL
• Scheduled Cable – approx. 1,200 miles, enough cable to stretch from St. Louis, MO to El Paso, TX
Unit 1 Turbine Pedestal & Boiler
16
Biggest Construction Project in the Country!
Page 16
PSGC Community OutreachPrairie State Project Poker Run
Sunday, October 5, 2008
137 individuals participated in this PSGC sponsored eventRaising $6,000 for the youth of Tilden
Page 17