Alternative Project Delivery Mechanisms The J. K. Spruce Experience Katherine Yates Assistant General Counsel

description

Alternative Project Delivery Mechanisms. The J. K. Spruce Experience Katherine Yates Assistant General Counsel. Overview. J.K. Spruce #2 planned as early as 1986. Authorized to proceed without permit in 2004. Chose Design-build methodology. Issued Two Phase RFP. - PowerPoint PPT Presentation

Transcript of Alternative Project Delivery Mechanisms

Page 1: Alternative Project Delivery Mechanisms

Alternative Project Delivery Mechanisms

The J. K. Spruce Experience

Katherine YatesAssistant General Counsel

Page 2: Alternative Project Delivery Mechanisms

Overview

• J.K. Spruce #2 planned as early as 1986. • Authorized to proceed without permit in

2004.• Chose Design-build methodology.• Issued Two Phase RFP.• Two Offerors Responded/Awarded July

2005.• Issued LNTP’s in August 2005 and full

NTP in April 2006.• Provisional acceptance expected no later

than March 2010.

Page 3: Alternative Project Delivery Mechanisms

Traditional Process

• Chapter 252 of Local Gov. Code governed procurement activities.

• Design-Bid-Build was only available method.

• Bids advertised, opened and awarded publicly.

• Award based on Lowest responsible bidder.

Page 4: Alternative Project Delivery Mechanisms

New Processes

• Chapter 271, Subchapter H added in 2001.

• Authorized “best value” determination.• Five new methods for project delivery:

– Competitive sealed proposals– Design-build– Construction manager-agency– Construction manager-at-risk– Job-order contracting

Page 5: Alternative Project Delivery Mechanisms

Design-Build process

• Single entity provides design and construction.

• Two phase procurement process:– Phase One RFQ based on

qualifications, references, past experience.

– Phase Two RFP based on schedule, implementation plan, technical approach, cost.

• Award to best value offeror.

Page 6: Alternative Project Delivery Mechanisms

Design-Build Advantages

• Fast-track schedule and construction

• Single point of contact.• Cost savings due to value

engineering.• Less owner administrative burden

during construction phase.• Potential for minimization of

change orders.

Page 7: Alternative Project Delivery Mechanisms

Initiation of CPS Energy Process

• Board Resolution selecting “best value” process.

• Engage Owner-Engineer to develop Design Criteria Package.– Functional specification and conceptual layout.– Desired equipment margins.– Quality and performance guarantees.– Transmission access.– Geotechnical and environmental information.

• Engaged the services of a surety consultant• Joint development of RFPP/RFP and evaluation

matrices.• Pre pre-bid meeting held with interested parties.

Page 8: Alternative Project Delivery Mechanisms

Phase One-RFPP

• RFPP advertised and sent to attendees.• Pre-bid meeting held with Site visit.• Evaluation criteria:

– Ability to bond penal value of $250 million.– Financial status.– Reputation in industry.– Past experience.– Resumes of proposed project team. – References.

• Two offerors qualified to proceed to Phase Two.

Page 9: Alternative Project Delivery Mechanisms

Phase Two

• Offerors given the RFP.• Agreement to reimburse losing entity of

up to $1 million for preparation costs.• Evaluation criteria:

– costs– Implementation plan– Project schedule– Safety record– Workforce and training plans– Costing methodology– Initial Design drawing and schematics

Page 10: Alternative Project Delivery Mechanisms

(con’t.) Phase Two

• Interviews conducted to clarify exceptions and technical response.

• Offerors asked to resubmit responses based on discussion and to provide pricing to remove exceptions.

• Signed agreement “fixing” responses for evaluation.

• Evaluation and recommendation of selected offeror.

• Negotiations with selected offeror and award based on reaching satisfactory contract.

Page 11: Alternative Project Delivery Mechanisms

Post Award

• Limited Notices to Proceed:– LNTP #1- Early planning and engineering for

procurement of long lead time items.– LNTP #2- Vendor engineering.– LNTP #3- Preparatory site construction work– LNTP #4- Material and Equipment purchase

release– LNTP #5- Controls upgrade

• Full Notice to Proceed upon issuance of permit.

Page 12: Alternative Project Delivery Mechanisms

Keys to Success

• Clear and comprehensive Design Criteria package.

• Effective integration of proposed Design-Build Team.

• Full and consistent communication. • Owner involvement.

Page 13: Alternative Project Delivery Mechanisms

Commercial Considerations

• Testing and commissioning done by third party.

• Contract price.• Payment and performance bonds.• Construction risks.• Bidding stipend.• Bonus for early completion.• Payment of prevailing wage.• Use of a Local Government Corp.