Alternative Delivery for
Municipal Water & Wastewater Projects in 2012
OWEA 2012
Making a Pass at Going Green …
Looking Towards the Future
Dennis Tinkler, P.E.
Ohio’s Methods of Performing Public Construction
Ohio Construction Reform (OCR) – Alternative Project Delivery Methods
Is a Work in Progress
Chartered Cities vs. Other Jurisdictions
Single-Prime Design/Bid/Build (D/B/B)
Design/Build (D/B) project delivery
Construction Manager at Risk (CMR) delivery
Making a Pass at Going Green ($) … Looking Towards the Future
General Contractor Led D/B
Actions to Move Us Forward
2
Agenda
Ohio Construction Reform (OCR)
June 2011: OCR HB 153 signed by Governor
Alternative Project Delivery Methods:
Retains multiple-prime Design/Bid/Build (D/B/B)
project delivery (not recommended)
Retains Construction Manager (CM) as agent delivery
Allows Single-Prime D/B/B*
Allows Construction Manager at Risk (CMR)*
Allows Design/Build (D/B)*
Allows for open-book Guaranteed Maximum Price
(GMP), design-assist, and subcontractor
prequalification within D/B and CMR delivery
methods First changes in Ohio’s method
of performing public
construction in over 134 years!
3
*To be discussed further today…
2012: Ohio Construction Reform – Work in Progress
Check this website for updates on Ohio
Construction Reform: http://ocr.ohio.gov/
Allows Single-Prime D/B/B…
CMR documents final in February 2012
D/B documents final in April 2012
CMR and D/B Standard Requirements for
Public Facility documents are a Work in
Progress … and are expected to be
updated for Water/Wastewater projects
4
Go To: http://ocr.ohio.gov/
to sign up for updates,
make comments, learn, etc.
OCR: Chartered Cities vs. Other Jurisdictions Alternative Delivery Requirements for Ohio Public Water/Wastewater Facilities
OCR not
Applicable
Ohio
Administrative
Rules Apply
Much flexibility to
select best value
of Numerous
Alternative
Delivery Methods
Chartered Cities Jurisdictions including Non-Chartered
Cities, Villages, Townships, Etc.
5
OCR
Applies
OCR
Developed
for State
Work
BUSINESS! – Jacob Marley
OCR is a Work in Progress and
did not generally consider
Water/Wastewater Projects
OCR: Single-Prime D/B/B
Owner Advantages
All Parties are Familiar
Time-Tested Process
Allows Thorough Collaboration/ Input between
Owner and Design Engineer
Owner Disadvantages
Takes Time – Linear Process
Min. Collaboration between Engineer & Contractor
Risks to Owner
Relies on Engineer’s Estimates
Errors and Omissions result in Change Orders (but
much less than Multi-Prime)
Workable Project
6
Engineer
GC
Owner
Contractual Relationships
Working Relationships
Trade Subcontractors
OCR: CMR (“D/B Lite”)
Owner Advantages
CMR Pre-Construction Services: Improved Constructability,
Pricing, and Possibly Schedule
Price Guaranteed Maximum Price (GMP) During Design
Reduces Project Risk, Contingency, Design Omissions –
thereby less potential of Change Order
Prequalification of Subcontractors may Increase Quality
Owner Disadvantages
No Single Responsible Party – Separate
Design/Construction Contracts
Engineer and CMR “forced marriage”
Relies on Criteria Engineer for Initial Estimates
Complex GMP Process – Risk of Agreement
Added Costs for CMR Pre-Con Services
7
Engineer
CMR
Owner
Contractual Relationships
Working Relationships
Trade Subcontractors
Owner Advantages
Single Point of Contact and Single Contract for
Performance and Guarantees
Owner Disadvantages (Just for Starts)
Subcontracting Process is Burdensome:
Project Cost Unknown until final Subcontract Packages
are designed, bid, and awarded
Public Owners will need significant staff to review
Subcontract Packages
Higher Design Costs
Will Delay Project and Add Administrative Costs;
Project at Risk to Proceed unless all Sub Packages are
designed, bid, and awarded
Key Subcontractors are not Members of D/B Team and;
therefore, do not provide meaningful innovation
OCR: Design/Build
8
Contractual Relationships
Working Relationships
Design/Builder
Trade Subcontractors
Criteria
Engineer Owner
Government does not solve
problems; it subsidizes
them. Ronald Reagan
Owner Disadvantages
Procurement can be Complex
(Evaluated Bid)
Limited to Predict what will be Proposed (if
Minimal Criteria Design for Complex
Project)
Price may include Significant Costs to offset
Risk (if Minimal Criteria Design for
Complex Project)
Possible Limited Owner and D/B Team
Collaboration
Looking Toward the Future …
General Contractor Led Design/Build
9
Contractual Relationships
Working Relationships
Criteria
Engineer City
Design/Builder
Trade Subcontractors
Why Select GC Led Design/Build?
Single-Point of Responsibility
D/B Team (GC, Engineer, Subs) is Highly
Collaborative with Owner
Deliver Project Quickly - Problem Solved
Costs:
Earliest GMP (Lump Sum with Proposal)
Low Procurement Costs
Competition: Minimize Design/Construction
Costs
Potential for Maximum Innovation
No Contractor Led Change Order
Looking Toward the Future …
Most D/B Projects in US are
General Contractor Led Design/Build
Source: The Water Design/Build Council
10
Evaluate Proposals: What’s Important to Customers?
For Example, we “ran into” Changes in Site Conditions
Rather than going to Our own separate Corners and then
arguing, delaying, sending letters, holding meetings…
…we solved the problems together as a Team with No
Project Delay.
As a Team, we completed Value Engineering and
Constructability Review to:
Improve Facility Operations, Safety, and Reliability
Improve Odor Control Design to Reduce Both Construction
and Lifecycle Costs
Later, Kokosing D/B Team was selected for $10M
Sewer D/B Project (Repeat Business)
Looking Toward the Future …General Contractor Led Design/Build
Delaware, Ohio Upper Olentangy Water Reclamation Center
11
The Team developed Trust and, as a
result, delivered more Value for the
same Cost to the City
Take Advantage of Ohio Construction Reform (OCR)
After 134 Years, Stop the Craziness … Get Rid of Multi-Prime Design/Bid/Build
Owners – Use Alternative Project Delivery that is most Advantageous to Your Customers
Invest Time, Training, and Resources to Learn about all Alternative Delivery Methods
Understand Advantages and Disadvantages of Each Alternative Project Delivery Method
Recognize that any Alternative Delivery Method can Work with Proper Planning,
Execution, and the Right Team
Recognize that Owner must have strong leader to follow through with new Alternatives
Encourage Ohio Department of Administrative Service to Update D/B Subcontractor Rules
Go to http://ocr.ohio.gov/ and submit comments
Looking Toward the Future …
Actions to Move Us Forward
12
Source: The
Water
Design/Build
Council
a
Questions & Answers