HP ALM 11.0 TRAININGIT QA
Training for AMD Test Leads and TestersApril 2011
Advanced Micro Devices Inc. (AMD) Proprietary 2011. AMD is a trademark of Advanced Micro Devices.
This document contains proprietary intellectual property of AMD and may not be copied, modified or otherwise duplicated, reproduced or changed without the express written permission of AMD.
| QA Communications | February 2011 2
Objectives
Provide Training on key ALM 11.0 Features and Functionality based on Role
Demonstrate Installation
Show what has changed from QC 9.2 to ALM 11
Review the ALM 11.0 Environment, UI, Menus, Components, Screens
Demonstrate each module in ALM 11.0: Test Plan, Test Lab, Defects
Instruct on Best Practices to follow within each module
| QA Communications | February 2011 3
Training Outline
Objectives
Getting Started
New Account Request
New Project Request
Installation Process
Pre-requisites: ALM 11.0
Installation Steps
Logging in and Setting Passwords
Changing Password
What has Changed
New Requirements Types and Workflow: Refer to RCoE Training
User Interface has changed
PMO Projects grouped by Business Domain
Releases Functionality: Program/Project Release Folder/Structure
–
| QA Communications | February 2011 4
Training Outline Cont’d
Reports Configuration has changed
New Features: Libraries and Baselines
Version Control
TFS Synchronization
Test Execution
Tester Roles & Responsibilities
Test Plan: Creating and Revising Scripts
Test Lab: Executing and recording results; linking defects
Defects
Logging and retesting defects
* Also included in What has Changed Slide
Installation Process: ALM 11.0
| QA Communications | February 2011 6
c
ALM Client System Requirements
Operating System
Windows 7 32 bit (Recommended) Windows Vista (SP1) 32 bit Windows XP (SP3) 32 bit Notes: If you are integrating ALM with other HP testing tools, you must modify the DCOM permissions on your client machine. For more information, see _http://h20230._www2.hp.com/selfsolve/document/KM187086. You can work with the ALM client using a remote desktop.
Browser Microsoft Internet Explorer 7 or 8
Note: For customers who have restrictions on plug-ins in their browsers, such as ActiveX, ALM can be loaded in the HP ALM Explorer Add-in. For more information on downloading and installing the add-in, refer to the HP Application Lifecycle Management Installation Guide.
| QA Communications | February 2011 7
Prerequisites: ALM 11.0 cont.d
ALM Client System Requirements
Prerequisites
• Visual C++ 2005 SP1 ATL Security Update Redistributable • Microsoft .NET Framework 3.5 (SP1) • Microsoft Office 2007 (SP2)
| QA Communications | February 2011 8
Installation Steps
1. You must log on to the browser as administrator. To do this, select Internet Explorer from the Start Menu, and right click to Run as Administrator.
2. Type in ALM 11 or http://ausalmp00:8080/qcbin in the address bar of your browser, Internet Explorer.
3. Log on to ALM 11.0. This is what you will see:
| QA Communications | February 2011 9
4. Click the Application Lifecycle Management link.
5. You will see the Security Warning shown below: “Do you want to install this software?” Click Install.
| QA Communications | February 2011 10
6. On the screen that displays, you will be prompted to install Microsoft Visual C++ 2005 SP1 Security Update.
Note: Since this is a generic update, if the machine already had the C++ update installed by another windows or program update, this update will not be triggered. Then you will automatically be taken to Step 8 instead.
If you chose the Install option, you will see the following screen while the Microsoft Visual C++ install is initiated.
| QA Communications | February 2011 11
7. Next, the Microsoft Download Center displays:
| QA Communications | February 2011 12
8. The file-download options display on the next screen (shown below). The default option will be that for X86 systems – third on the list: Click Download.
| QA Communications | February 2011 13
9. Click Run on the standard Security warning that displays next:
| QA Communications | February 2011 14
10. You may see a second warning with a similar message once you click Run the first time. Click Run again.
| QA Communications | February 2011 15
11. Click Yes, on the screen that displays to accept the License Agreement
•Click Yes on the window that pops up, to allow the program to make necessary changes to your computer.
| QA Communications | February 2011 16
12. Click Yes on the window that pops up, subsequently to allow the program to make necessary changes to your computer.
| QA Communications | February 2011 17
13. You will see the following screen while Windows configures the Microsoft C++ Redistributable:
| QA Communications | February 2011 18
14. The following screen will display as ALM 11.0 loads:
| QA Communications | February 2011 19
You are now ready to log in, authenticate, and access your project.
Note: Please let all the components run before logging off.
| QA Communications | February 2011 20
Logging in and Setting Passwords
In your browser window, type in ALM 11 or– http://ausalmp00:8080/qcbin/
you may try the alternate link– http://ausalmp00.amd.com:8080/qcbin/start_a.htm
On the first screen that displays, click on the Application Lifecycle Management link.
| QA Communications | February 2011 21
ALM 11.0 Login Screen
1. Enter your ALM 11.0 User Name and Password, then select Authenticate
• Your new User Name is the same as your NT ID. Example: jsmith
• Your new Password is the same as your User Name.
• User Name and Password are all lower case characters.
• If you’re new to ALM 11.0, please change your Password once you successfully log in.
2. Enter the Domain and Project, and click the Login button
• Domain is: AMD_QA
• Project is: Current Project
Notes:
• Admin Rights on your workstations are required.
• Listing the ALM 11.0 URL as a trusted site in IE is also recommended.
• The first time you launch ALM 11.0 you will see horizontal progress bars as your workstation is being configured for ALM
| QA Communications | February 2011 22
Changing Password
• If logged in, click on Tools -> Customize - >User Properties -> Click on Change Password tab.• On Change Password pop-up enter old password, new password twice, and click OK button.• Click Save, then click on Return button.
• Please keep your passwords private, and do not share.
• On the ALM 11.0 home page, click on the Forgot Password link.
What has Changed: ALM 11.0
| QA Communications | February 2011 24
What has changed from QC 9.2 New Requirements Types and Workflow
– Specific Functionality is implemented as per the RCoE Training
Changed User Interface: The Dashboard has a new look and feel
PMO Projects are now grouped by business domain
– 10 business domains with Programs - >Projects under the business domains
Releases functionality: Modified QC project creation strategy. We will create 10 ALM 11.0 projects based on business domains. Each domain will have multiple PMO projects.
| QA Communications | February 2011 25
What has changed from QC 9.2
New Features: Libraries, Baselines New Features and Best Practices to be rolled out in 2011.
Reporting Configuration Changes: There is a new method for changing parameters when configuring a report. A graph wizard may be used to configure standard reports.
Version Control (Test Plan, Requirements, Components section) - > With the new Version Control it is necessary to check- out – check-in to prevent locking files
TFS Synchronization: New fields have been added when creating requirements and logging defects, to enable synchronization
The EDW/SAP flag is a key part of synchronization. It is also used to display custom information for SAP and EDW.
| QA Communications | February 2011 26
ALM 11.0: User Interface - > Menus
ALM 11.0’s Navigation structure includes these major menus with modules under them: * The Menu items in bold indicate implemented functionality.
Menu Functionality
Dashboard Menu Analysis (Reporting)
Management Menu: Releases, Libraries
Requirements Menu Requirements
Testing Menu Test Plan, Test Lab
Defects Menu
| QA Communications | February 2011 27
27
ALM 11.0: Modules
Standard icons :
Sections to be used: Test Lab and Defects
ALM 11.0’s structure includes these major modules:
Dashboard: Analysis View - To access reporting functionality
Releases – Tool to manage the Release Life Cycle
Libraries - Tool to manage a set of entities in a project and the relationships between them
Requirements – A repository for requirements
Business Models
Business Components – Used by IT QA Automation Team to create business components (details not covered in this document)
Test Plan – A repository for manual and automated tests (Library of scripts)
Test Lab –Tool for scheduling and executing manual or automated tests (Record Test Run results)
Defects– Defect management and tracking tool (log defects)
ALM 11.0 Toolbar
| QA Communications | February 2011 28
Business Domains – Why by Business Domains
Projects will be created under Business Domains. Project fields will be dependent on which Business Domain the project is mapped to. You will see in ALM 11.0 fields for defects and requirements to select the pmo project and application from a predefined list. This selection determines implications of synchronization and other potential customizations
Support alignment of the different systems
– Troux (Business Domains and Application Lists by Domain)
– HP Application Lifecycle Management (ALM 11.0)
– Team Foundation Server (TFS 2010)
– Project Resource Cost Table (PRCT)
Support the synchronization hooks between ALM and TFS
Balances the needs for reporting and the management of project, requirements, testing, and development.
Agreed upon by the PMO, RCOE, QA, and Dev.
| QA Communications | February 2011 29
Business Domains - List
Corporate Services Finance
Global Operations Engineering
Information Technology
Manufacturing Marketing PG
Engineering Sales
Supply Chain Management
TG Engineering
| QA Communications | February 2011 30
Business Domains – what does this mean to you All project requirements in HP ALM will be in a single business
domain to support requirements management, UAT testing, and reporting. However, your project will be a sub-folder within a business domain.
In Troux, applications are aligned to business domains. Thus, in order for us to manage requirements affecting an application in different business domains, we require functional requirements to have an application assignment.
– The application assignment is made during the hand-off to Dev. Dev will be responsible for identifying the application. Business Analysts are responsible for updating the requirements in ALM with the application name and in some cases, splitting the requirements so there is a single functional requirement to application.
All requirements will require a PMO Project and if needed, the TFS Sync flag or SAP/EDW flag.
| QA Communications | February 2011 31
Program/project release structure - folder
A
CB
ED
| QA Communications | February 2011 32
Program/project release structure - release
B
A
| QA Communications | February 2011 33
Program/Project release structuresKey User interface elements
UI Element Icon HP ALM Definition AMD Application
Release Folder A folder for organizing releases. AMD uses folders to organize releases. Nesting of release folders are used when a Release does not represent a go-live distribution of changes. (e.g. Multiple iterations before a go-live implementation)
Release A release represents a group of changes in one or more applications that will be available for distribution at the same time. Each release can contain a number of cycles.
AMD expands the use of releases to include a group of changes that may not be distributed.
Reschedule Opens the Reschedule dialog box, enabling you to reschedule the start and end date of a release, cycle, or milestone
No change
Cycle A cycle is a set of development and quality assurance efforts performed to achieve a common goal based on the release timeline.
AMD’s QA organization uses cycles to represent the different stages of testing. (e.g. SIT, UAT). The QA Analyst will create and assign the cycles.
Delete Deletes selected release folders, releases, or cycles. Deleting a folder also deletes its releases and cycles. Deleting a release also deletes its cycles. Note: Deleting a release folder, release, or cycle also unassigns the associated requirements, test set folders, and defects.
AMD does not allow for deletion exception by HP ALM Administrators.
| QA Communications | February 2011 34
Libraries and BaselinesLibraries - A library represents a set of entities in a project and the relationships between them. The entities in a library can include requirements, tests, test resources, and business components. Baseline - A baseline is a snapshot of the library at a specific point in time. You can compare baselines at all stages of the application development lifecycle.
Why Use Libraries and Baselines Viewing baseline history enables you to track changes made to individual entities in your library over time. As development continues, you can view and compare all versions of an entity that are stored in a baseline. At AMD, we are leveraging the baselining capabilities to take a snapshot of the requirements at each Phase Exit and after a Project Change Request is approved and the requirements have been updated. You can also import a library. Importing a library enables you to reuse and share an existing set of entities. As development continues, you can compare and synchronize libraries.
| QA Communications | February 2011 35
Create a Library and a Baseline1. From the Management module on the ALM sidebar, select Libraries.
2. In Libraries root folder, create your project’s folder by click on the Create Folder button . Creating your project folder is important because there may be other projects using the ALM project container.
3. Name your folder with your Project Number and Project Name (e.g. Project 123 Sales Enhancement) and click OK.
4. Select your project folder and click on the Create Library icon to create a library.
5. Name your library as Requirements.
6. If needed, Select Content from the sidebar. Click on your project folder. It is suggested that you select all requirements for your baseline. It may be necessary to filter the view by Targeted Release before you check the requirements. You can do the same with test cases.
| QA Communications | February 2011 36
Configuring Reports
Reporting Configuration is different in ALM 11.0, from QC 9.2:
This section describes how to:
• Add a new graph
• Apply a new filter to existing graph
| QA Communications | February 2011 37
Create a New graph in ALM 11.0
ALM 11.0 has introduced a new module dedicated to store and manage user reports and graphs
– There can be Private or Public entities
– The procedure to create a new graph is the same for both
37
| QA Communications | February 2011 38
Create a New graph in ALM 11.0
1. Choose the folder for your graph and click on the
38
2. Select the type of output (In this case a New Graph)
1
2
| QA Communications | February 2011 39
Create a New graph in ALM 11.0
2. Select the Entity that you want to graph3. Select the Graph Type.4. Enter the new Graph Name.
3
4
5
| QA Communications | February 2011 40
Create a New graph in ALM 11.0
5. Once the new graph is created, click on the View Tab to access the report:
6
| QA Communications | February 2011 41
Applying Filters to a New Graph
1
2
3
1. Select your graph and click on the View tab2. Modify general graph parameters3. Click on for data specific filters
| QA Communications | February 2011 42
Applying Filters to a New Graph
4. Select your criteria from the filter screen, using the Filter tab, click OK.5. Choose Create Filter, select settings. Click OK:
| QA Communications | February 2011 43
Applying Filters to a New Graph
6. Click on the View tab to access the filtered graph
Test Execution: ALM 11.0
| QA Communications | February 2011 45
45
Tester Roles & Responsibilities by Module
• The three main modules that a Tester will interact with are:
1. Test Plan
2. Test Lab
3. Defects Module
Roles by moduleTest Plan
• Creating test scripts
• Reviewing and updating existing test scripts
Test Lab
• Executing tests and documenting test results
• Adding and modifying test sets in Test Lab
• Reviewing and updating existing test scripts in Test Lab
Defects
• Logging defects
• Retesting after defect resolution
| QA Communications | February 2011 46
Tester Responsibilities
Tester Responsibilities
• Create TCP
• Executing tests and documenting test results
• Logging defects
• Retesting after defect resolution
Tester Permissions
Approver
Originator
Business Components Manager
Test Plan Module
| QA Communications | February 2011 48
48
Test Plan – Best Practices
The Application folder may have subfolders with folder names to help identify sub-groups.
Tests should be included under the associated application/module folder.
Script naming conventions should be consistent:
The prefix BUS should be used to differentiate between IT scripts and Business scripts (additions or revised copies). EX: BUS_HCM-IT-077
The Test Name should be short and should deliver the objective of the test to some extent.
Duplicate Tests should not be generated.
Tests should be marked as Ready for Review only after all the steps are verified and no more changes are to be made.
Design Step Description should be precise so that the test executor does not face any issues while executing even if he is not trained on the application or has not read the process definition.
Expected Results must be included in each step if applicable.
Mock ups, screen shots, or other documents which carry information that is needed for running the test should be attached to the test.
Tests should be be generic so that they can be resued. For instance, homepage look and feel needs to be tested for all environments then the URL mentioned in test should be: http://(server).amd.com
Mention any pre-conditions/post-conditions if applicable in the Description field in a highlighted format.
Enter test execution priority before sending for approvals.
Test Case Procedure should be approved before the run
Manual Test Case Procedure Review Process should be followed.
| QA Communications | February 2011 49
49
Test Plan Workflow
Roles: 1. Test Plan Originator 2. Test Plan Approver - IT Lead 3. Business Component Dev
Transition Rules For Test Plan Status Field By Role
Test Plan Originator
Test Plan Approver
Test Script is entered directly into QC (Manual or Imported from MS-
Word or MS-Excel)
Status: Manual Test – In Design
Approved?
Yes
No
Test Plan Originator
Test Plan Approver
Status: Manual Test - Approved
Status:Manual Test – In Design
Status: Manual Test - Ready for Review
Yes
Business Component Dev
Status: Automation – In Design
Need Automation
?
Status: Ready for Automation
Yes
No
Fit for Automation
?
No
Status: Automation – Ready for Review
Approved?
Yes
No
Test Plan Approver
Status: Automation - Approved
Status:Manual Test – In Design
Any Change?
Yes
No
Business Component Dev
Transition Rules For Test Plan Status Field By Role
Test Plan Originator
Test Plan Approver
From ToManual Test - In Design Manual Test - Ready for Review
From ToManual Test - Ready for Review Manual Test - In DesignManual Test - Ready for Review Manual Test - ApprovedManual Test - Approved Ready for AutomationAutomation - Ready for Review Automation - In DesignAutomation - Ready for Review Automation - ApprovedAutomation - Approved Manual Test - In Design
From ToReady for Automation Manual Test - ApprovedReady for Automation Automation - In DesignAutomation - In Design Automation - Ready for Review
Business Component Dev
| QA Communications | February 2011 50
50
Navigate Test Plan Tree: Access the right folder
1. Click on the Test Plan icon in the column to the left to bring the Test Plan Tree into the foreground.• Locate Functional Business Folder
(Functionality BB in the example)• Additional folders can be added by your
test lead2. Click on a folder, then Tests can be created by
clicking on this icon.
| QA Communications | February 2011 51
51
Create a Test Case
• Test ID is automatically assigned by Quality Center.• Status - Imported (uploaded from an existing script) or Design (written directly in QC).• Approver - Automatic E-mail sent to Approver when Status updated to Ready for Review. • Test Name – Name of test• Type – Select Manual• Creation Date• Execution Priority - High, low, medium; prioritize execution for limited test windows• TCP Automation Priority – Not used• Designer - Author• Fields highlighted in red are mandatory
| QA Communications | February 2011 52
52
Test Plan – Design Steps Tab
Step – Step number assigned by QC, Step column can be renumbered if steps are deleted, added, or rearranged
User Type – The type of account executing a section of test steps
T-Code – Used for R3 tests
Process Step – a category for a group of steps
Description – Detailed description of the test step
Data Input – Data entered or selected during execution of test step
Expected – Expected test result
Screen – Current application screen where test actions are executed
Tab – Specific tab of a screen where test actions are executed
*To link steps from another manual test choose the Called Test icon.
| QA Communications | February 2011 53
53
Test Plan – Create Design Steps
Click on this icon to create a new Step.
Use the yellow arrow keys to move back and forth between Design Steps.
Click on the OK button to return to Design Step Grid.
| QA Communications | February 2011 54
54
Requirement Details: Link Test to Requirements From Test Plan Tree Select the Requirements Tab
Click on the Test Plan Tree tab to bring it into the foreground.
Highlight a Test. Click on the green arrow to move it into the list under Entity Name column.
| QA Communications | February 2011 55
55
Manual TCP Review Process
1. All new test cases procedures (tcp) must be assigned Status “Manual Test – In Design”
2. Approver must be selected from the dropdown menu.
3. Execution priority can stay blank
4. Automation priority should be blank for now
5. Once test case is ready, status should change from “Manual Test- In design” to “Manual Test- Ready for Review”
6. The Test plan Approver group reviews TCPs in Status: “Manual Test- Ready for Review” and inputs comments in the Comments field in ALM 11.0 with name and date stamp
7. During review meetings TCP comments for all “Manual Test- Ready for Review” TCPs are reviewed and TCP concerns are discussed in detail.
8. During review meetings the execution priority for TCPs are defined.
9. The TCP is then moved to “Manual Test- Approved” or “Manual Test- In design” status as per the review session and comments
• Fields highlighted in red are mandatory
– ** TCP names should be in format “application name_test case name_version of requirement documents”.“Manual
Test Approved”
Yes
“Manual Test In Design”
Ready?
“Manual Test Ready for Review”
Comments?
“Manual Test Approved”
Yes
Yes
Not
Not
Test Lab Module
| QA Communications | February 2011 57
57
Test Lab - Best Practices
Responsible Tester should be selected while configuring Test Lab/Test Sets.
Planned Execution Date should be selected while configuring Test Lab/Test Sets.
Test Set Name should be as per defined standards.
All tests pulled into a Test Lab/Test Set should be in “Manual Test - Approved” status
Test Case Procedure marked as failed should have an associated defect.
Scripts ready for execution will be marked No Run in the Status field.
During Execution of a Test Set, the Actual Result field should be marked “As expected” if the test step passes and in case of any failures. actual results should be precisely mentioned so that the Defect Fixer can have a clear view of the scenario encountered at your end. Attach screen shot of the behavior if applicable.
Mention the test data input at the time of execution if applicable, so that database can be checked if required. Test Data would refer to: folder name, Asset name, content ID, etc.
Use Tester Comments field to pass along information between testers during hand-offs.
Dynamic data generated should be entered in the Expected Result field for the next tester to retrieve.
Each test set folder must be associated to the corresponding cycle/release.
| QA Communications | February 2011 58
58
Test Lab: Create a New Test Set• Click on the Test Lab icon in the
column to the left to bring the Test Lab Tree into the foreground.
• Locate the desired folder• Additional folders can be added
by your test lead• Click on a folder, then Tests Sets can be
created by clicking on New Test Set icon
• On the New Test Set pop-up, enter the Test Set Name and a brief Description. Click the OK button.
| QA Communications | February 2011 59
59
Test Lab: Add TCPs to Test Set
Click on Test Plan Tree tab to bring it into the foreground.
Highlight a TCP. Click on the green arrow to move it to the list under the Execution Grid.
| QA Communications | February 2011 60
60
Assign Test Set Folders to Cycles1. In the Test Sets tree, select the test set folder
that you want to assign to a cycle.
2. Click the Assign To Cycle button or choose Test Sets > Assign To Cycle. Alternatively, in the Details tab, click the browse button next to the Assigned to cycle box. The Assign To Cycle dialog box opens.
3. Expand the tree and select a cycle. Click OK to close the Assign To Cycle dialog box. In the test set tree, the test set folder icon is replaced by the assigned test set folder icon
| QA Communications | February 2011 61
61
Test Lab – Adding TCPs to Test Set
• After adding the TCP to Test Set fill in the Required Test Set fields: Client and Test Environment from the drop-down menus.
• You may include several TCPs in a Test Set
| QA Communications | February 2011 62
62
Run Tests & Record Results
1. In Test Lab: • Select a folder.• EX: Unit folder (test cycle)• Select Test Set.
2. Select Test by highlighting that tab.3. Click on the Run button to start a new run.
1.2.
3.
| QA Communications | February 2011 63
63
4. First Manual Runner window will open.Click on Begin Run button
Update Status Results End Run after updating
| QA Communications | February 2011 64
64
If you have a Failed Step:Link Defects to Failed steps
1. Mark failed step:
• Click on Defect dropdown.
• Click on New Defect to log a new defect.
2. Screen will open to New Defect module.
• Log as usual.
3. To link an existing defect:
• Click on Linked Defects option. A new window will open.
• Click on Select option and the entire Defect list will appear.
• Select your Defect and click on Link.
4. Stop Run!!!
Window will close automatically and
you will return to the Execution Grid.
STOP RUN!!
1.
2.
3.
| QA Communications | February 2011 65
65
Test Run Execution Hand-Over Process: need screen shot showing failed run
1. Tester 1 will mark a test step
• Tester 1 will Stop the run after completing this portion.
2. Tester 1 will be taken back to main Execution Grid. The Test status will be: Not Completed or Failed
3. Tester 1 will change the Responsible Tester field to Tester 2 (next tester to hand-off to) for the Test.
• An auto E-mail will be sent to new Responsible Tester.
| QA Communications | February 2011 66
66
4. Tester 2 will highlight the test script in Test Lab.
5. Click on Run button on the menu bar: Continue Manual Run.
6. Tester 2 will then be taken to the Manual Runner screen and continue with the normal run process.
7. Tester 2 will stop the run after completion.
• Manual Runner will close automatically and return to the Execution Grid.
Note: If tester 1 needs to pass dynamic test data to tester 2, add the data to the “Actual” field in test step Run. Tester 2 should refer to the previous/last executed step to retrieve any such information.
| QA Communications | February 2011 67
67
Obtain Test Execution Report
1. Select the Test Set
2. From analysis, select Reports.
3. From the menu select Current Test Set
| QA Communications | February 2011 68
Obtain Test Execution Report - Cont’d
4. The report is displayed on the screen
5. Click Save.
| QA Communications | February 2011 69
Obtain Test Execution Report - Cont’d
5. Enter a Name for the report. Click Save.
6. The report will now display under Analysis View.
.
7. Click on Save
| QA Communications | February 2011 70
Get Test Execution Report – Cont.d
8. To add filter criteria, click on the Configuration tab and the Filter icon:
9. Now it is available to be consulted under Dashboard module
| QA Communications | February 2011 71
71
a. Go to the Responsible Tester field and click on the button with 3 dots.
b. On the Select Filter Condition screen, enter tester name >>click on binoculars to search>>choose.
c. Click on OK, then again OK to close filters.
d. Click on Apply to generate report.
Get Test Execution Report – Cont’d
| QA Communications | February 2011 72
72
9. The test execution report is displayed by:
• Tester
• Ascending Planned Execution Date
10. To Print:
Click on the Print icon to print (**ALL PAGES).
You can also save the report to your desktop.
Repeat the process to change any filter criteria
Defects: ALM 11.0
| QA Communications | February 2011 74
74
Defects - Best Practices
When logging a Defect, verify that similar defects do not already exist. If a similar defect does exist, link the Defect to the script.
In case the defect matches one with status Closed, create a brand new defect.
The Summary of the defect should be precise, unique, and should convey the defect baseline.
Defect Description should include complete and comprehensive information about the Defect.
Screen shots (if applicable) should be attached to the Defect.
Defect should be correctly linked to the test step at which it is encountered, so that the Defect Fixer can go back to the Test Set and review the steps and duplicate the actual result.
In case the Defect is to be fixed in the next cycle as per plan. The Target Release should be assigned to the new one and the Target Cycle should be assigned to the next Cycle.
In case the Defect is related to another Defect already logged into the system; create a defect link between the two.
In case of reassigning, reopening or cancellation of a Defect, Comments field must be entered suggesting the reason for the action.
Assign all defects to Defect Reviewer for review followed by assignment to an IT Fixer.
Once the Defect is fixed, the Defect Originator will rerun the tests from the Test Set.
Before closing a Defect, a tester should go to Linked Entities and make sure that all test instances attached with the Defects have the status Passed. In case any tests are in a Failed Status, then the Defect should not be closed.
Entering Comments by team members at the time of changing any Defect field is a good practice. To do this, click on the Add Comment button which generates a name/timestamp and add your comments.
| QA Communications | February 2011 75
ALM 11.0- Defect Workflow
75
Defect Originator
Defect Reviewer
Defect Fixer
Defect Verifier
Transition Rules For Defect Current Status Field By Role
| QA Communications | February 2011 76
76
Defects Grid
• Click on Defects icon at bottom of column on the left to bring Defect Grid into the foreground.• Click on the New Defects button to open the New Defect screen.
Detected in Release – release number detected by default, can be changed.
Detected in Cycle - cycle number detected by default, can be changed.
Detected on Date – defaults to today’s date, can be changed
Detected By – defaults to logged in ALM 11.0 user, can be changed
System – list of systems used for testing
Assigned To – user assigned for next defect work stage, must be a Defect Reviewer for New defects
Severity – 4 levels of severity, Show Stopper to Low
Functional Area – functional area specific to the defect
Test Cycle – current cycle of testing
Current Status – defect status, relates to workflow
Reproducible – Yes, No, or Intermittent
Priority – 5 levels, Urgent to Low
Change Request Number (2 fields) – cross-reference for Remedy Ticket Numbers
| QA Communications | February 2011 77
77
New Defects
• When a New defect is created, the first assignment must be an ALM 11.0 user with the assigned role of Defect Reviewer.
• Functionality is built into the Assigned To field to assist with your selection.
• Activate the drop-down list, and checkmark View by Group.
• Then click on Group: Defect Reviewer. Click to select from that list.
An automatic Defect E-mail is triggered when Assigned To field is changed.
| QA Communications | February 2011 78
78
Modifying Defects
• Click on a Defect in the Defect Grid to open up Defect Details screen.
• To enter a Comment click on the Add Comment button to the right. This will add the logged in user name and a date.
• If you are a Defect Fixer, remember to select Defect Type.
• If you are closing a Defect, complete Closing Date field.
| QA Communications | February 2011 79
79
Defects - Linked Entities
• Click on Linked Entities icon in the column at the left.• Click on Defects tab to bring it to the foreground.• Click on this icon to open Link Existing Defect window.• Enter an existing Defect ID, and click on Link button.
| QA Communications | February 2011 80
80
Defects – Test Set Instance
• Click on Others tab to bring it to the foreground.
• This Defect information originated when the Defect was created during a manual test run.
| QA Communications | February 2011 81
81
ALM 11.0 Logout
To exit ALM 11.0, click on the Logout button in the upper right.
| QA Communications | February 2011 82
Reporting Functionality in ALM 11.0 - What’s New
| QA Communications | February 2011 83
Trademark Attribution
AMD, the AMD Arrow logo and combinations thereof are trademarks of Advanced Micro Devices, Inc. in the United States and/or other jurisdictions. Other names used in this presentation are for identification purposes only and may be trademarks of their respective owners.
©2009 Advanced Micro Devices, Inc. All rights reserved.