Alliance, an excellent solution to meet Project Execution ...€¦ · Joint Ruhr Oel/Fluor Daniel...
Transcript of Alliance, an excellent solution to meet Project Execution ...€¦ · Joint Ruhr Oel/Fluor Daniel...
RUHR OEL GMBH VEBA OEL VERARBEITUNG
Alliance, an excellent solution to meet Project Execution Challenges
Presentation at
7 November 2002, Zürich
By: H.D. van Wieren Fluor Daniel BV
RUHR OEL GMBH VEBA OEL VERARBEITUNG 1
Story
Project Background
Execution Challenges and Solutions
Alliance
Key Project Objectives
Project Organisation and Execution
Results
Conclusions
RUHR OEL GMBH VEBA OEL VERARBEITUNG 2
Change in German Requirements for Sulfur in Automotive Fuels
In second quarter of 1999: Max. 50 ppm sulfur fuels to be available at the market by 1.11.2001
In August 1999 :Ultra-clean fuels to be available at the market by 1.1.2003
This meant upgraded plants had to be available for maximum 50 ppm sulfur production by 1.8.2001
Due to this short time between the 50 ppm and ultra-clean fuels schedules the facilities shall be upgraded immediately to the highest standard..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 3
Situation at Ruhr Oel Gelsenkirchen Refineries in the second quarter 1999
The refineries in Horst and Scholven were not in a position to produce economically automotive fuels with maximum 50 ppm sulfur
Additional refinery optimisation plans were being considered for simultaneous execution with the desulfurisation project
No final process technology selection had been made for most of the new, or to be revamped facilities
Consequences for utilities and off-sites were not yet determined and available information was fragmented..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 4
Ruhr Oel Objectives for the AOP II project
Last plant ready for operation 1 August 2001
Start EPC work 2 January 2000
Internal decision by mid December 1999
10% Estimates ready by mid November 1999
Construction work to fit the already established turn-around schedules
Cost should be fitting the low refining margins..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 5
Project Execution Challenges
Early discussions with Engineering Contractors and other operating companies indicated to Ruhr Oel that a conventional Lump Sum project execution route would not be successful within the set timeframe
The proven alternative of splitting the project into smaller sub-projects would require much (unavailable) Ruhr Oel management and coordination effort and leave them the total responsibility for the integration of the packages
Crash LS projects tend to be very expensive..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 6
Chosen Solutions
Joint Ruhr Oel/Fluor Daniel project team proposed solution – Fluor Daniel will be the “managing” contractor for the basic phase
– Strong integration of Ruhr Oel and Fluor Daniel project teams during the basic engineering
– Execute the EPC phase in an Alliance format
The solution for the basic engineering phase was quickly accepted; and
Because of the outstanding results of the joint team during the basic engineering phase, Ruhr Oel management agreed to the challenge of the Alliance concept for the EPC phase..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 7
What is an Alliance
It is a group of companies with a common goal
Which are contractually bound
Which have a common interest
Which can only succeed together or fail together..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 8
Alliance Process
Outside consultant engaged
Training of own team
Partner selection
Alliance development
Contract and Consequences..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 9
Alliance Partner selection
Type of partners determined
Selection criteria determined
Long list of possible contractors; reduced after questionnaire evaluation
In depth interviews with all selected contractors
Final selection based on evaluation of both hard and soft criteria by the joint Ruhr Oel / Fluor Daniel team..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 10
Alliance Development Schedule
Potential Partner selection started in September 1999
First shortlisting October
Interviews during November
Final rating of each contractor immediately after interview
Final selection end November
Ruhr Oel decision to go ahead and Alliance Workshop meeting 2 December
Final Risk & Reward meeting 16 December 1999
First Alignment meeting 19 January 2000..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 11
Selected Contract Form
One Alliance contract (36 pages)
Five partners
– Client Ruhr Oel (Germany)
– Engineering contractor Fluor Daniel (The Netherlands)
– Civil contractor (Germany)
– Piping/mechanical contractor (France)
– Electrical/instruments contractor (Belgium) Target price with Sharing of over/under-run
All expenses are being paid at cost
Bonus for timely completion (RFSU)
No claims allowed against other partners..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 12
Consequences of the Alliance contract
Only one project team
The best man was nominated for each key position
Strong cooperation between, and integration of all team members from all companies
As no claims are possible the only way to resolve conflicts is through communication
An Alliance Board was set up as outside independent body to regularly monitor the project and check that all parties involved remain aligned..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 13
Key Project Objectives
1 Schedule; end schedule plus shutdown schedules
2 Budget; under-run the Target Price
3 Quality; of the parts and the total
4 Safety; Meet Fluor Daniel standards
5 Relationships; good relationships and communication
6 Meet statutory requirements; no negative publicity
7 Make the Alliance a success
RUHR OEL GMBH VEBA OEL VERARBEITUNG 14
Project Management
Project Management team - day-to-day operations– Project managers of all partners
– Engineering manager
– Procurement manager
– Construction manager
Alliance Board - Monthly meetings– Senior manager of each company
– Project managers from Ruhr Oel and Fluor Daniel
Steering Committee - ad-hoc meetings– Ruhr Oel Management
– Fluor Daniel Management
Outside Consultant - as and when required
RUHR OEL GMBH VEBA OEL VERARBEITUNG 15
Organisation ChartProject Directors
Engineering Managers Construction Manager Procurement Manager Contracts Engineer
Expediter
Inspector
Manager CSA
Strabag
Manager pip/mech
Ponticelli
Manager E&I
Fabricom
Lead Eng. process
Lead Eng. Mech.
Lead Eng. Piping
Lead Eng. CSA
Lead Eng. E&I
CSA TeamPiping/mechanical
TeamE&I Team
Comm/SU Coordinator
Proj Controls Eng
Authority Coordinator
Site Engineer Const Eng Scholven Warehouse Superv isor
Proj Controls Eng
Contracts Eng
RUHR OEL GMBH VEBA OEL VERARBEITUNG 16
Project Organisation Specifics
Engineering– Close integration between Ruhr Oel and Fluor Daniel
– Strong involvement of the construction partners in their area of competence
Procurement– Done from the Fluor Daniel offices but in an integrated team
effort with Ruhr Oel procurement• For most E & I items and bulks used standard Ruhr Oel agreements
• For other materials and equipment used FD and Ruhr Oel resources
– Inspection and expediting mixed but never double
Construction– One construction team, one office, no double functions..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 17
Project Quality
Fluor Daniel system, founded on TQM, formed the basis
– Operating System Requirements
– Operating System Implementation Plan
– SHE Management System
– Knowledge On-Line
– Project Activity Model
All partners had their own Quality Management system
Project Execution Plan/ Project Procedures Manual..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 18
Project Execution
Alignment meetings used to share information and to get involvement and buy-in by project personnel
Monitoring systems in place for:
– Schedule
– Efficiency
– Cost
– Quality
– Safety
– Relationships
Project Management Meetings to develop and implement corrective actions
RUHR OEL GMBH VEBA OEL VERARBEITUNG 19
Key Project Results
In spite of 25% increase in work due to scope development and added scope during the EPC phase:
1 Project completed on time; shutdowns not delayed
2 Cost 9% under Target Price
3 Plants operating as specified and meeting quality standards
4 No LTI’s; incidence rate 0.65 (limit 0.90)
5 Good relationships prevailed; excellent communication
6 All authority requirements fulfilled and positive publicity
7 The Alliance is considered very successful by all involved
RUHR OEL GMBH VEBA OEL VERARBEITUNG 20
Progress Curves
ENGINEERING PROGRESS AOP II
-
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
% C
om
ple
te
CONSTRUCTION PROGRESS AOP II
0
10
20
30
40
50
60
70
80
90
100
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG
% C
om
ple
te
RUHR OEL GMBH VEBA OEL VERARBEITUNG 21
Results of the Alliance set up
Excellent relations and understanding between the project managers
A very high mutual trust level between the Partners and all individual team members
Hidden agendas could be defused early
The inevitable battles between the various parties were nipped in the bud
High morale of all involved personnel..
RUHR OEL GMBH VEBA OEL VERARBEITUNG 22
Basic Engineering (months)
Bidding and Evaluation EPC (months)
EPC phase
Delays due to changes
Change orders
Contract form
Flexibility
Cooperation between parties
Team satisfaction
Competitive bidding
6
0
19
0
open book
at cost with incentives
high
high
high
very difficult
8 - 10
3
24
2
closed
lump sum
limited
limited
varying
possible
Alliance Normal
What is the difference
RUHR OEL GMBH VEBA OEL VERARBEITUNG 23
Conclusions
The applied Alliance approach of mutual trust and cooperation enabled to us to achieve the desired, very challenging, project targets
But it cannot replace a decent Quality Management System on the project
A very attractive way of working for all people involved
Possible in a multi-cultural environment
Financially attractive for all parties
People are the key element !
RUHR OEL GMBH VEBA OEL VERARBEITUNG 24
We would be happy to share
our gained experience with you!