ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015

Transcript of ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS...

Page 1: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

ALDOT HSIP FUNDING OPPORTUNTIESALABAMA DEPARTMENT OF TRANSPORTATION

OFFICE OF SAFETY OPERATIONSSONYA BAKER

TIMOTHY BARNETTMAY 13, 2015

Page 2: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

ALDOT HSIP FUNDING OPPORTUNITESObjectives

• What is the HSIP?• What type of projects are eligible/ineligible?• What is the application process?– Application Details– Project Sponsors Responsibility– HSIP Application Flow Chart/Process

• Summary/Next Steps– Additional Training available

Page 3: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

WHAT IS HIGHWAY SAFETY IMPROVEMENT

PROGRAM (HSIP)?

Page 4: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Objective of HSIP

MAP-21 continued the Highway Safety Improvement Program (HSIP) as a core federal-aid program.

The goal of the program is to achieve a significant reduction in traffic fatalities

and serious injuries on all public roads.

The program requires a “data-driven, strategic approach to improving highway safety on all public roads that focuses on performance”.

Page 5: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Federal HSIP Requirements

Under 23 USC 148(c)(1), to obligate HSIP funds, a State must:

- Develops, implements, and updates a strategic highway safety plan (SHSP) that identifies and analyzes highway safety problems and opportunities.

- Produces a program of projects or strategies to reduce identified safety problems; and

- Evaluates the SHSP on a regularly recurring basis.

Page 6: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Alabama Strategic Highway Safety Plan (SHSP)2nd Edition 2012

SHSP Emphasis Areas

• Driver Behavioral Crashes• Infrastructure

Countermeasures• Legislative Initiative• Traffic Safety Information

Systems• Safety Stakeholder

Community

http://www.safehomealabama.gov/DataandAnalysis/SHSPDocument.aspx

Page 7: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

SHSP Infrastructure CountermeasuresCategory of HSIP Projects

• Systemic Safety Improvements – Installation of Rumble Stripes– Horizontal Curve Resigning– Shoulder Widening– Widening of Inside and Outside Shoulders on Horizontal Curves– Signage and Markings

• Non-Systemic Improvements– Safety Improvements that DO NOT fail into the broad safety improvements

categories – Based on Benefit to Cost(B/C) Ratio

Page 8: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Examples of Types of HSIP Projects• GEOMETRIC COUNTERMEASURES

– Offset Left Turn and Right Turn Lanes– Delineation– Left Turn and Right Turn Traffic Control and Geometric

Improvements– Passing Lanes– Roundabouts

• TRAFFIC CONTROL DEVICE COUNTERMEASURES– Intersection illumination– Signage– Upgraded pedestrian crossings

Page 9: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Examples of Types of HSIP Projects• ROADSIDE AND ROADWAY

DEPARTURE COUNTERMEASURES– Installation of Rumble Stripes– Horizontal Curve Resigning– Shoulder Widening– Installation of Guardrail

Page 10: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP “Expanded” Eligible Projects

• Roundabouts• Offset Left-turn and Right-Turn Lanes

• Construction and Operational Improvement on High Risk Rural Roads

• Bicycle & Pedestrian Countermeasures

• Safety Assessments – Road Safety Assessments (RSA)– Safety and Operational Studies for

high crash corridors

• Non-infrastructure projects– Public Relations Activities– Enhanced Enforcements– Improvement in the collection

and analysis of crash data

Page 11: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

INELIGIBLE HSIP PROJECT ACTIVITIES

• Work deemed to be a highway maintenance activity• Grade separation projects• Major horizontal or vertical realignments• Major drainage improvements• Major utility relocations• Projects requiring extensive right-of-way acquisitions• Work zone activities necessary for the management of the construction site during

construction

Page 12: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP APPLICATION DETAILS

Page 13: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Overview of HSIP Application

The HSIP Project Application Form contains the following sections:

• Section I: Project Sponsor Information• Section II: Project Location and Description• Section III: Risk Narrative• Section IV: Traffic and Crash Data• Section V: Proposed Improvement Action(s)• Section VI: Project Phase Costs• Section VII: Benefit/Cost Ratio Calculation

• It is critically important that the application form contain accurate and • relevant data, analysis, and other supporting information to “make the case” for the proposed project.

Page 14: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP APPLICATION DETAILS

• Section I: Project Sponsor Information– Contact Information

• Section II: Project Location and Description– Proposed Project Limits– Functional Classification– OSO Identified High Risk study – Existing Traffic Control Devices

• Section III: Risk Narrative– Description of Safety Countermeasures– Sketches, Photos, Articles, Collision Diagrams, etc.

Page 15: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP APPLICATION DETAILS

– Section IV: Traffic and Crash Data• Review and Analysis of Crash Data

– Crash Types (Run Off Road, Side Swipe, Head On, etc.)– Crash Severity (Fatality, Injuries, PDO)

• AADT– Approach AADT (Intersections)

• Length and Width of Roadway (Segments)• Functional Classification• Any previous Safety Studies

– (not all inclusive )

Page 16: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP APPLICATION DETAILS

• Section V: Proposed Improvement Action(s)– Proposed Countermeasures– Crash Reduction Factors (CRFs)• Estimate of the Percentage of Crashes Reduction (all crashes, targeted

crashes) per Countermeasure– Most common CRFs are included in the application as a guide– Service Life per Countermeasures

Page 17: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Alabama CRF Guide

Page 18: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP APPLICATION

• Section VI: Project Phase Costs– Preliminary Engineering – Utilities and ROW Cost (minimal cost)– Construction

• Section VII: Benefit/Cost Ratio Calculation (automatically calculated when the other sections are inputted)

Page 19: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Completing HSIP Applications

• Address ALL checklist items for completeness• Submit application as directed in HSIP manual • Application must be signed by PE• Responsibility of Project Sponsor(for approved projects)– Comment supporting matching funds (90% Federal/10% Local)– Comply to Federal Regulations, including providing information for

annual HSIP Report– Projects that are not progressing may be deleted from the program

Page 20: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

HSIP Project Process

Page 21: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Project SelectionHSIP Project

Priority CriteriaAssigned Points Proposed

WeightRange of Values

Project Location 5 = project located at a high- risk location established through a safety study (intersection or segment)0 = project not located at a high-risk location

5

0 to 25

Composite Benefit/Cost Ratio (B/C) for

Proposed Project

Value of the B/C ratio

10

10 times the B/C

value

Ease of Project Delivery 5 = Relatively easy/straightforward2 = Some potential risks0 = Likely to have significant risks

5

0 to 25

Crash Severity Potential 5 = High potential as assessed by OSO0 = Low potential as assessed by OSO

5 0 to 25

TOTAL POINTS: To be determined by OSO

Page 22: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

SUMMARY

• The proposed project must address a stated goal(s) of the Alabama SHSP

• There must be a documented description of the safety issue(s) along with supporting data and quantitative and/or qualitative information on the proposed safety countermeasures.

• A project sponsor(s) must be identified who is willing to implement the project according to Federal and ALDOT guidance and requirements.

Page 23: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Next Step: Upcoming HSIP Training!!• Attend the upcoming HSIP Training, Gresham Smith, along with

Dr. Dan Turner– Thursday, May 21, 2015 from 8 to 12 PM• Central Office in Montgomery, Conference Room 5 and 6• Teleconference at ALDOT Region Offices

– Can’t make it? It will be video recorded and made available on OSO website!!!– Applications will be taken year round starting in July/August 2015

Page 24: ALDOT HSIP FUNDING OPPORTUNTIES ALABAMA DEPARTMENT OF TRANSPORTATION OFFICE OF SAFETY OPERATIONS SONYA BAKER TIMOTHY BARNETT MAY 13, 2015.

Questions?Sonya BakerSafety Engineering

Manager(334) [email protected]

Timothy Barnett, P.E., P.T.O.E.

Safety Operations Engineer(334) [email protected]