Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
Facility Assessment SummaryThis report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual observation only; they do not test operability or perform destructive testing inside walls, ceilings or floors. The rankings below reflect the assessors’ visual evaluations of the property condition as of that date. For additional information, you may review the detailed assessment report linked on this school’s profile page and visit the Facilities Standards webpage under CPS Policies and Guidelines at http://www.cps.edu/About_CPS/Policies_and_guidelines/Pages/facilitystandards.aspx.
Condition Rankings and Descriptions
Rank 7: The item/system is new or in good condition and no work is required.
Rank 6: The item/system requires general cleaning and/or routine maintenance.
Rank 5: The item/system requires repairs and has not reached the end of its serviceable life.
Rank 4: The item/system has reached its expected useful life, but is still fully operational. CPS will maintain until replacement occurs.
Rank 3: The item/system has surpassed its expected useful life and has limited operability. CPS will maintain until replacement occurs.
Rank 2: The item/system has surpassed its expected useful life and has low operability. CPS will maintain until replacement occurs.
Rank 1: The item’s/system’s failure leads to an immediate life safety condition for occupants or to the potential of an uninhabitable facility.¹
Total Quantity
Unit
means a basic estimate for each item needing some level of repair or replacement. Cost does not include all expenses that would be necessary to complete a repair or replacement project. This is because, depending on the item and on the overall scope of a construction project, repair/replacement projects can include additional costs such as destructive testing, environmental needs, discovered conditions, and additional work triggered by building codes.
Definitions
means, for each item, the total number (or amount) of that item that exists and was evaluated. Within that Total Quantity, different portions may have different rankings.
means the generally accepted standard unit of measure for each item. Some items, like doors, are measured individually and use the unit of measurement “EA” for “each.” Other items, like chimneys, are measured in terms of linear feet (“LF”). Still other items, like flooring, are generally measured in square feet (“SF”).
Cost
For the same reason, the Total Campus Need listed at the end of this report reflects only a portion of what it would actually cost to repair/replace all of the listed features.
Total Campus Need also does not reflect features that do not yet exist at a particular facility, such as: programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration, or construction to alleviate overcrowding; these are viewed as separate capital needs.
EXTERIOR
CANOPY
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUMetal Canopy SF81 $4,2895 81
$4,289
CHIMNEY
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREBrick Chimney - Concrete/ Mortar Liner LF120 $60,0606 120
GREMetal Flue LF120 $8,9236 121026
$68,983
Assessment Date: 3/11/2013 Page 1 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
DOORS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREExterior FRP Door EA8 $07 8
GREExterior Stainless Steel Door EA10 $5,0976 10
BLUExterior Steel Door EA40 $48,3935 17158
BLUExterior Wood Door EA60 $51,5355 512421
GREOverhead Rolling / Garage Door EA15 $18,4836 7521
GREStore Front Door EA2 $07 2
GRETransom Lite EA69 $39,2156 112335
$162,723
ENTRANCE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREConcrete Exterior Stairs LF289 $24,2396 13314214
GREConcrete Ramp LF280 $07 280
GREEntrance Controls - Audio and Video EA6 $07 6
GREPower Door Operator and Controls EA5 $07 5
GRERamp Handrails LF466 $07 466
GREStair Handrails LF267 $06 24720
GREStone Stairs LF1,125 $228,5146 156748221
$252,753
FOUNDATION
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREConcrete Foundation LF4,888 $07 4,888
$0
LIGHTING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREExterior Lights - Parapet or Roof Mounted EA5 $07 5
GREExterior Lights - Wall Mounted EA118 $24,3826 17992
$24,382
Assessment Date: 3/11/2013 Page 2 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
LINTELS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRELintels - Brick LF9 $07 9
YELLintels - Concrete LF40 $13,9684 40
YELLintels - Steel LF7,438 $3,216,1964 707,368
YELLintels - Terra Cotta LF2,635 $2,072,4284 2,635
$5,302,592
PARAPET
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUCoping - Metal LF2,608 $47,7325 3805251,703
GRECoping - Terra Cotta LF8,358 $217,9216 7,1581,16040
GREParapet < 16" Height LF3,772 $587,4026 3,772
GREParapet > 30" Height LF1,497 $440,4956 1,130367
GREParapet 16" to 30" Height LF2,580 $555,7096 2,54040
$1,849,259
ROOF SYSTEM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUAsphalt Gravel Ballast Roof SF170,780 $2,344,6035 157,54413,236
GREExterior Downspouts LF231 $8,1386 1832424
GREInterior Downspouts LF3,487 $15,4446 3,343144
GREMetal Roof SF3,243 $34,8116 2,2431,000
GREModified Bitumen Roof SF29,053 $207,3036 28,953100
GRERoof Structure: Concrete SF2,370 $07 2,370
GRERoof Structure: Steel with Clay Tile Arch SF223,775 $07 223,775
GRESlate Shingle Roof SF22,139 $135,8166 22,139
$2,746,115
SUPERSTRUCTURE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRESlab on Grade SF7,630 $07 7,630
Assessment Date: 3/11/2013 Page 3 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GRESteel with Clay Tile Arch SF709,000 $07 709,000
$0
WALLS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREBrick SF216,478 $2,998,3036 149,26357,9509,265
BLUConcrete Block SF1,127 $21,7575 1,127
BLUPrefabricated Metal Panel Wall SF1,338 $37,8215 360768210
GREStone - Cut SF4,919 $125,7406 4,563200156
BLUTerra Cotta SF25,075 $4,414,0605 15,9743,2285,873
$7,597,679
WINDOWS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUSkylite - Glass Single-Pane SF3,135 $176,2755 1,0261,933176
YELSkylite - Lexan SF216 $46,0734 216
GREStorefront Windows SF160 $07 160
BLUWindow - Guards wire guard SF7,525 $189,8205 7,525
YELWindows - Casement Lexan SF460 $52,9664 460
YELWindows - Casement Steel SF334 $91,4164 334
GREWindows - Decorative SF588 $3,3636 588
YELWindows - Sash Aluminum Double-pane SF93,528 $16,134,0304 12093,408
YELWindows - Sash Lexan SF30 $5,1814 30
$16,699,125
$34,707,900EXTERIOR Total
ELECTRICAL
EMERGENCY SYSTEM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAutomatic Transfer switch EA5 $8,8666 41
GREEmergency A/C power - Auditorium and aisle lighting SF23,695 $07 23,695
GREEmergency A/C power - Corridors and Stairs SF89,929 $1,1786 89,546383
Assessment Date: 3/11/2013 Page 4 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GREEmergency A/C power - Gym and Lunch rooms SF44,993 $07 44,993
GREEmergency Battery Packs - Lunchroom and Gym EA2 $2156 2
GREEmergency generator 200 -250 KW diesel - Outdoor EA1 $07 1
GREExit Signs - Auditorium EA16 $6996 133
GREExit Signs - Corridors and Stairs EA197 $13,0446 150443
GREExit Signs - Lunchroom - Gym - multipurpose rooms EA37 $2,3316 2710
GREIndependent Electrical Service for emergency power EA2 $5,0056 11
BLUPublic Announcement System SF709,000 $1,013,8705 709,000
$1,045,208
MAIN SERVICE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREMain Electrical service 1200 A 120/208/3PH EA1 $7,1506 1
GREMain Electrical service 1600 A 120/208/3PH EA1 $9,2956 1
GREMain Electrical service 2000 A 120/208/3PH EA1 $12,1556 1
GREMain Electrical service 2000 to 3000 A 120/208/3PH EA2 $48,6206 2
GREMain Electrical service 800 A and below 120/208/3PH EA1 $3,5756 1
$80,795
POWER DISTRIBUTION
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRELighting and power panels EA135 $282,5686 503847
GREMain distribution panels 400-600 amp EA13 $60,7756 85
GREMain distribution panels above 600 amp EA4 $18,5906 31
GREMain distribution panels less than 400 amp EA3 $07 3
BLUTransformers 277/480-120/208 EA8 $111,5405 35
$473,473
$1,599,476ELECTRICAL Total
Assessment Date: 3/11/2013 Page 5 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
FIRE PROTECTION
FIRE ALARM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREFire Alarm Strobe Lights SF709,000 $07 709,000
GREFire Alarm System SF709,000 $861,7906 709,000
$861,790
$861,790FIRE PROTECTION Total
MECHANICAL
AIR CONDITIONING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECondensing Unit - Roof Mounted 5 to 10 tons EA1 $07 1
GREWindow A/C Unit EA92 $49,3356 39251513
$49,335
AIR HANDLING SYSTEMS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUAir Handling Unit Package - Multi Zone - Steam less than 6,000 cfm EA1 $15,7305 1
BLUAir Handling Unit Package - Single Zone - Steam 4,000 to 8,000 cfm EA2 $31,4605 2
GREAir Intake - Built Up Air Handling Unit EA10 $27,4566 181
GREAir intake for all Air Handling Units except built up AHU EA3 $8,5806 21
GREFan Coil Unit - Electric EA1 $1,1876 1
BLUMulti Zone Built Up Air Handling Unit - Steam 15,001 to 25,000 cfm EA1 $35,7505 1
BLUMulti Zone Built Up Air Handling Unit - Steam 25,001 to 35,000 cfm EA2 $85,8005 2
GREMulti Zone Built Up Air Handling Unit - Steam 8,000 to 15,000 cfm EA1 $7,5796 1
BLUMulti Zone Built Up Air Handling Unit - Steam above 35,000 cfm EA6 $303,1605 15
BLUMulti Zone Built Up Air Handling Unit Auxiliaries - Steam 15,001 to 25,000 cfm EA1 $12,8705 1
YELMulti Zone Built Up Air Handling Unit Auxiliaries - Steam 25,001 to 35,000 cfm EA2 $57,2004 11
GREMulti Zone Built Up Air Handling Unit Auxiliaries - Steam 8,000 to 15,000 cfm EA1 $07 1
BLUMulti Zone Built Up Air Handling Unit Auxiliaries - Steam above 35,000 cfm EA6 $157,3005 132
GREReheat Boxes With Steam Coils EA64 $66,8106 64
Assessment Date: 3/11/2013 Page 6 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GREReturn Duct Work - Indoor - Vertical Shaft and Ducts LF80 $07 80
YELReturn Duct Work - Masonry and Ducts - Existing or Missing Exterior Shaft LF1,000 $2,645,5004 1,000
GRERoof Top Unit - Single Zone - Electric 11 to 20 tons EA1 $4,2906 1
$3,460,672
BOILER SYSTEMS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREBoiler Assembly - Steam - Flexible Tube Boiler less than 50 HP EA1 $14,3006 1
BLUBoiler Assembly - Steam - High Pressure Scotch Marine Boiler greater than 200 HP EA4 $400,4005 4
BLUBoiler Assembly - Steam - Low Pressure Scotch Marine Boiler 151 - 200 HP EA1 $68,6405 1
BLUBoiler Auxiliary - Steam Boiler 101-150 HP EA1 $11,4405 1
BLUBoiler Auxiliary - Steam Boiler greater than 200 HP EA4 $65,7805 4
GREBoiler Auxiliary - Steam Boiler less than 50 HP EA1 $07 1
GREChemical Feeder - Steam Boiler EA2 $6016 2
GRECombustion Dampers EA3 $8586 3
BLUFeed Water Pumps and Tank - Steam Boilers EA1 $19,3055 1
$581,324
HEAT EXCHANGERS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
YELHeat Exchanger - Steam to Hot Water Shell Type EA2 $25,8834 11
$25,883
HEATING DEVICES
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUCabinet Heaters With Steam Coils EA9 $16,7315 9
GREFin Tube Electric LF40 $07 40
GREFin Tube Hot Water LF138 $2,0086 75576
GRERadiators - Steam EA233 $41,9056 218132
GREUnit Heater - Gas EA2 $2,1456 11
GREUnit Heater - Hot Water EA2 $2,8606 2
GREWall Heater - Electric EA30 $7,0016 12882
$72,650
Assessment Date: 3/11/2013 Page 7 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
MECHANICAL PLUMBING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECondensate Assembly - Pumps and Tank EA10 $31,1746 343
YELPiping - Condensate - Steel or Galvanized LF3,000 $293,8654 3,000
BLUPiping - Steam - Steel or Galvanized LF3,000 $148,4345 3,000
$473,473
TEMPERATURE CONTROL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUPneumatic System SF709,000 $3,041,6105 709,000
GREThermostats - Pneumatic EA225 $37,3236 21510
GREZone Dampers EA279 $39,8976 279
$3,118,830
UNIT VENTILATION
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUUnit Ventilators - Self Contained Electric Heating and Cooling EA6 $51,4805 6
$51,480
VENTILATION
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
YELExhaust Fan - Indoor EA38 $191,9784 14294
GREExhaust Fans - Roof Mounted 1,501 to 8,000 cfm EA4 $4,5056 13
BLUExhaust Fans - Roof Mounted 500 to 1,500 cfm EA9 $9,4675 27
BLUExhaust Fans - Roof mounted less than 500 CFM EA7 $7,7515 61
YELLab Exhaust Hood EA5 $131,5604 113
GREType I Exhaust Hood - Kitchen or Culinary Arts EA3 $5,1486 3
$350,407
$8,184,053MECHANICAL Total
Assessment Date: 3/11/2013 Page 8 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
PLUMBING
HOT WATER
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREHot Water Heater - Electric less than 50 KW EA1 $1,4016 1
GREStorage Tank more than 500 gallons EA1 $7,4366 1
$8,837
PIPING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREDomestic Piping - Cold Water from Risers to Fixtures SF716,630 $1,3096 709,0007,630
YELDomestic Piping - Cold Water Risers SF716,630 $458,7514 7,630709,000
GREDomestic Piping - Hot Water from Riser to fixtures SF716,630 $8,7296 709,0007,630
YELDomestic Piping - Hot Water Return Risers SF716,630 $326,0754 7,630709,000
YELDomestic Piping - Hot Water Risers SF716,630 $387,2354 7,630709,000
YELDomestic Piping Cold Water Horizontal lines SF716,630 $1,699,9284 7,630709,000
YELDomestic Piping Hot Water Horizontal lines SF716,630 $1,403,1784 7,630709,000
YELDomestic Piping Hot Water Return Lines SF716,630 $815,2424 7,630709,000
BLUSanitary Piping SF716,630 $439,0195 7,630709,000
BLUStorm Piping SF716,630 $340,0335 709,0007,630
BLUVent Piping SF716,630 $254,6685 7,630709,000
$6,134,165
POOL SYSTEMS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREPool Drain Piping LF60 $07 60
GREPool Filtration System EA1 $27,8856 1
GREPool Hot Water Heater - Gas Fired EA1 $3,7186 1
GREPool Supply and Return Piping LF610 $07 610
$31,603
Assessment Date: 3/11/2013 Page 9 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
PUMPS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREDomestic Booster Pump simplex EA2 $3,4326 2
GREEjector Pump EA2 $07 2
BLUSump Pump EA10 $36,3225 46
$39,754
$6,214,360PLUMBING Total
INTERIOR
ADMINISTRATIVE SUITES
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECeiling - Exposed SF1,140 $5956 825315
GRECeiling - Lay-In SF2,333 $1726 2,25380
GRECeiling - Plaster/Drywall SF23,181 $35,9286 12,3548,9651,862
GRECeiling - Splined SF5,190 $9,0416 9754,215
GREFlooring - Carpet SF9,493 $10,5966 3,6064,8721,015
GREFlooring - Terrazzo SF356 $07 356
GREFlooring - Tile Ceramic/Porcelain SF207 $5276 207
GREFlooring - Tile/Sheet SF8,371 $24,2956 2,5213,6541,415781
GREFlooring - Wood SF12,494 $76,0136 4,6995,1982,597
GRELighting - Lay-In SF30 $16 282
GRELighting - Pendant/Surface SF473 $3616 3379145
GRELighting - Wall Mounted EA186 $07 186
GREWalls - Concrete Block SF1,468 $4,7366 614365489
GREWalls - Plaster/Drywall SF46,384 $96,0916 7,08637,8711,427
GREWalls - Structural Glazed Tile SF11,633 $53,1756 4,1967,437
$311,529
AUDITORIUM - DEDICATED
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUBalcony Seating EA902 $109,5615 902
Assessment Date: 3/11/2013 Page 10 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GREChandelier - Incandescent EA18 $5,7926 18
GREMain Floor Seating EA1,201 $07 1,201
GRESound System EA1 $35,7506 1
BLUStage Curtains EA9 $05 9
GREStage Lighting System EA1 $07 1
$151,102
CHORAL ROOM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRERisers LF90 $07 90
$0
CORRIDOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREStair Handrails LF770 $06 770
GREStairs - Asphalt LF595 $4,2546 595
GREStairs - Terrazzo LF34 $3856 34
GREStairs - Wood LF44 $8186 44
$5,457
DOORS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREInterior Steel Doors incl hw EA209 $60,1206 618914
GREInterior Wood Doors incl hw EA760 $315,2296 16934421037
GRESide-lite SF435 $8,0876 435
GRETransom Window SF4,320 $80,3096 4,320
$463,745
DRINKING FOUNTAINS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRESingle Fountain EA43 $30,1166 25315
$30,116
Assessment Date: 3/11/2013 Page 11 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GYMNASIUM - STANDARD DEDICATED
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREScoreboards EA1 $07 1
$0
GYMNASIUM / AUDITORIUM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREBleacher Seating EA1,029 $24,8686 1,029
GRECeiling - Plaster/Drywall SF28,587 $244,6346 28,467120
GREFlooring - Tile/Sheet SF4,765 $6,8146 4,765
GREFlooring - Wood SF13,310 $38,5076 8,2105,100
GRELighting - Metal Halide/Sodium Vapor EA73 $13,0496 73
GRELighting - Pendant/Surface EA48 $5,8346 48
GREScoreboards EA3 $6,2296 3
GRESound System EA2 $10,0106 2
BLUWalls - Plaster/Drywall SF1,235 $17,6615 1,235
GREWalls - Structural Glazed Tile SF24,305 $412,8206 18,3355,970
$780,425
KITCHEN
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECeiling - Plaster/Drywall SF2,600 $9,8166 2,600
BLUFlooring - Tile/Sheet SF2,600 $18,1215 2,200400
GRELighting - Pendant/Surface SF27 $396 216
GREWall - Plaster/Drywall SF870 $2,0536 870
GREWall - Structural Glazed Tile SF4,320 $30,8886 4,320
$60,917
LIBRARY
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECasework LF402 $12,3316 402
GRECeiling - Splined SF4,212 $07 4,212
Assessment Date: 3/11/2013 Page 12 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GREFlooring Tile/ Sheet SF5,265 $7,5296 5,265
GRELighting - Pendant/ Surface SF24 $176 24
$19,877
LOCKER/SHOWER ROOM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREBenches LF479 $2,8776 4781
GRELockers EA1,755 $132,5496 271,60816104
GREShowers EA99 $41,5706 2266110
$176,996
LUNCHROOM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUCeiling - Exposed SF3,256 $6,1465 2163,040
GRECeiling - Lay-In SF16,406 $35,1916 16,406
GRECeiling - Plaster/Drywall SF9,505 $29,1696 1,8564,9962,653
GRECeiling - Splined SF682 $1,4636 682
GREFlooring - Tile/Sheet SF22,748 $45,3976 19,7083,040
GRELighting - Lay-In SF62 $07 62
GRELighting - Pendant/Surface SF130 $2596 633136
GREServing Line LF250 $07 250
GREWall - Concrete Block SF830 $1,7766 209621
BLUWall - Plaster/Drywall SF18,227 $66,1985 2117,97610,040
GREWall - Structural Glazed Tile SF6,848 $22,4516 3,7083,140
$208,050
MDF/IDF
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREFinishes SF325 $1,1066 325
GREVentilation and Cooling EA1 $1,4016 1
$2,508
Assessment Date: 3/11/2013 Page 13 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
MECHANICAL/SERVICE ROOMS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREJanitor's Closet SF10 $476 10
GREMechanical/Service Rooms SF5,888 $38,2146 1,9908983,000
GREStorage Room SF17,747 $57,4596 5,57112,176
$95,720
PHYSICAL EDUCATION ROOMS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUWall Mirrors SF36 $4265 36
$426
STAFF RESTROOM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAccessories SF19,816 $30,8076 16,5972,884335
GRECeiling - Lay-In SF7,252 $10,4356 3,7232,929400200
GRECeiling - Plaster/Drywall SF21,552 $58,6626 3,94915,7331,403467
GREFloor Drain EA72 $12,9136 49185
GREFlooring - Concrete SF4,683 $22,0996 4,683
GREFlooring - Tile Ceramic/Porcelain SF17,127 $64,5146 8,6345,4642,837192
BLUFlooring - Tile/Sheet SF5,786 $24,5275 4241,3793,983
GREHand Dryer EA61 $9,2476 50623
GRELavatory EA110 $34,9496 682913
YELLighting - Lay-In SF864 $2,7854 815778
GRELighting - Pendant/ Surface SF285 $1326 2263425
GRELighting - Wall Mounted EA4 $6446 22
GREPartitions EA216 $43,4436 8297334
GREUrinals EA151 $20,4496 14011
GREWall - Concrete Block SF4,633 $1,8306 3,993640
GREWall - Plaster/Drywall SF27,606 $65,5406 2,97221,4913,143
GREWall - Structural Glazed Tile SF24,609 $99,7936 10,65213,957
GREWall - Tile Ceramic/ Porcelain SF4,118 $29,8286 1202,7461,048204
Assessment Date: 3/11/2013 Page 14 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GREWater Closet EA210 $40,5266 17519142
$573,123
SWIMMING POOL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAccessories SF7,530 $07 7,530
GREBleacher Seating/Plank seating EA146 $2,0676 146
GREFloor Tile SF7,530 $25,6286 7,530
GRELighting - Pendant/ Surface SF61 $656 4021
GREPool Basin SF3,000 $07 3,000
GREPool Deck SF3,383 $22,3506 3,383
GREPool deck drains EA8 $07 8
GRESplined Ceiling including access SF7,530 $80,7596 7,530
GREWall Tile SF5,784 $07 5,784
$130,868
THEATER
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECeiling - Exposed SF2,410 $07 2,410
GRECeiling - Plaster/Drywall SF9,885 $07 9,885
GRECeiling - Splined SF11,704 $92,0526 11,704
GREFlooring - Concrete SF12,978 $61,2436 12,978
GREFlooring - Tile/Sheet SF3,685 $5,2706 3,685
GREFlooring - Wood SF3,473 $29,1296 3,033440
GRELighting - Chandelier, Incandescent EA4 $1,2876 4
GRELighting - Pendant/ Surface SF49 $1136 3982
GRELighting - Wall Mounted EA15 $07 15
GREStage SF2,790 $11,8496 2,790
GREWall - Plaster/Drywall SF22,078 $189,4296 22,078
$390,373
Assessment Date: 3/11/2013 Page 15 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
VERTICAL CONVEYANCE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREElevator - Roped Holeless Hydraulic EA1 $17,1606 1
GREElevator - Traction EA2 $42,9006 2
GREStage Lift EA1 $07 1
$60,060
VOCATIONAL SHOP
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREWork Sink EA131 $96,1396 148433
$96,139
$3,557,431INTERIOR Total
ROOM
ADMIN_FLOOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAdministrative Office Floor SF416 $5956 416
$595
ADMIN_LIGHT
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAdministrative Office Lighting EA8 $07 8
$0
ADMIN_WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAdministrative Office Walls SF5,768 $6,7176 2,9212,847
$6,717
Assessment Date: 3/11/2013 Page 16 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
CASEWORK
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECasework LF5,878 $258,1156 3265,135417
$258,115
CEILING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECeiling SF840 $2,3786 840
GREExposed Ceiling SF3,439 $2,4586 2,1371,302
GRELay-In/Drop SF13,120 $20,8926 3,5779,423120
GREPlaster/Drywall SF156,765 $307,2896 52,400100,2014,164
GRESplined Ceiling SF9,411 $13,1446 4,4694,219723
$346,161
CHALK BOARD
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
YELChalk Board LF2,856 $344,7164 202,836
$344,716
CLASSROOM
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREScience Lab Elements SF192 $4,3936 192
$4,393
CORRIDORS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREConcrete Block SF1,242 $3,5526 1,242
GREConcrete Epoxy/Painted SF1,072 $5,0596 1,072
GREDrop/Lay-In SF943 $2,0236 943
GREExposed SF140 $07 140
GREFloors SF4,322 $07 4,322
GRELay-In EA945 $2866 5603832
Assessment Date: 3/11/2013 Page 17 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GRELighting EA29 $2,6966 29
GREPendant/Surface EA81,696 $2,2046 80,3608424922
GREPlaster/Drywall SF95,778 $226,0266 3,00389,7563,019
GRESingle Water Cooler EA10 $4,3046 721
GREStair Handrails LF2,146 $06 1,915231
GREStructural Glazed Tile SF91,289 $734,5306 20089,0102,079
GREStudent Lockers EA3,539 $6,8646 3,49148
GRETerrazzo SF38,040 $81,0406 23,72914,311
GRETile/Sheet Flooring SF62,466 $39,0986 35,12527,341
GREWalls SF11,563 $16,4766 4,9386,267358
$1,124,158
CORRIDORS CEILING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREPlaster/Drywall SF105,476 $298,1446 6,85991,9356,682
$298,144
FLOOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECarpet SF7,014 $10,5516 1,8263,7281,460
GREConcrete SF8,368 $23,9256 3,2981,6583,412
GREFloor SF1,926 $5,1616 7231,203
GRETile/Sheet SF50,957 $178,3546 9,80317,61721,1972,340
GREWood SF113,903 $910,2736 14,52775,25924,06750
$1,128,264
GYM_FLOOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREGymnasia Floor SF10,512 $97,4116 8,3882,124
$97,411
Assessment Date: 3/11/2013 Page 18 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GYM_WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREGymnasia Walls SF300 $2,5746 300
$2,574
LIBRARY_CEILING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREPlaster/Drywall SF1,053 $07 1,053
$0
LIBRARY_WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREPlaster/Drywall 5,245 $12,3766 5,245
$12,376
LIGHTING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRELay-In EA96 $7,0796 45348
GRELighting EA15 $07 15
GREPendant/Surface EA3,219 $62,2056 2,64650766
$69,284
LUNCH_FLOOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRELunchroom Floor SF5,737 $17,7636 1,1681,9162,653
$17,763
LUNCH_WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRELunchroom Walls SF7,526 $16,8546 1,6335,893
$16,854
Assessment Date: 3/11/2013 Page 19 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
MARKER BOARD
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREMarker Board LF1,640 $3,8326 1,5347828
$3,832
RESTROOM_FLOOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRERestroom Floor SF1,208 $1,8286 490718
$1,828
RESTROOM_WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRERestroom Walls SF4,404 $4,8116 2,8661,47068
$4,811
STAIRS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRETerrazzo SF1,131 $12,8096 1,131
$12,809
THEATER_FLOOR
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAuditorium Floor SF3,559 $07 3,559
$0
THEATER_WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAuditorium Walls SF15,462 $25,1106 3,35212,110
$25,110
Assessment Date: 3/11/2013 Page 20 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
WALL
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
BLUConcrete Block SF4,441 $24,2025 1,9892,452
GREMetal/Folding Panel SF5,688 $12,3576 4515,237
GREPlaster/Drywall SF182,983 $428,5686 4,782174,7673,434
GREStructural Glazed Tile SF46,373 $281,4606 7,00839,365
$746,586
$4,522,501ROOM Total
SITE
CIVIL/DRAINAGE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GRECatch Basin EA17 $24,5826 1313
GRESite Manhole EA34 $1,2166 331
$25,797
FENCING
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
YELChain Link LF1,085 $94,9164 300785
GREOrnamental Iron LF700 $07 700
$94,916
LANDSCAPE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAsphalt Play Area/Hardscape SF15,000 $30,8886 6,0006,0003,000
GREBenches EA23 $18,8766 158
GREHardscape - Concrete SF88,900 $294,3916 81,3002007,400
GREHardscape - Pavers SF4,740 $07 4,740
GREIrrigation SF365,950 $07 365,950
GREParkway trees EA21 $2,4546 201
GREPlanting Beds/ Areas SF14,000 $07 14,000
Assessment Date: 3/11/2013 Page 21 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
GRERetaining Wall - Concrete SF9,880 $379,8806 2,0604,2203,600
GRERetaining Wall - Masonry SF400 $5,6636 400
GRETrash Receptacles EA36 $9,8676 306
$742,018
PARKING LOT
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREAsphalt SF248,280 $349,7936 225,0007,48015,800
GREConcrete SF11,235 $06 11,235
GRETrash Compactor EA1 $07 1
GRETrash Enclosure SF1,435 $07 1,435
GREVehicular Screening LF1,800 $07 1,800
$349,793
SIDEWALKS
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREInternal Walks LF460 $2,8316 43030
GREPerimeter Sidewalks SF27,000 $18,8766 26,0001,000
$21,707
SIGNAGE
Assessed Item
Composite
Rank Unit
Total
Quantity Cost
Rank 7
Qty
Rank 6
Qty
Rank 5
Qty
Rank 4
Qty
Rank 3
Qty
Rank 2
Qty
Rank 1
Qty
GREFlag Pole EA1 $07 1
GREMarquee - Free Standing Back Lighted w/ LED EA1 $07 1
$0
$1,234,232SITE Total
Assessment Date: 3/11/2013 Page 22 of 23
Albert G Lane Technical High School
2501 W Addison St Chicago, IL 60618
$60,881,743Total Campus Need ² ³
² As stated above, Total Assessed Campus Need does not include the addition of features not already in a particular facility, such as programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration or construction to alleviate overcrowding; these items are treated as separate capital needs. The Total Assessed Campus Need includes current deficiencies and is based on current unit cost estimates; it does not reflect a complete project cost.
³ The overall condition of different items can change after an assessment date due to many variables, including newly occurring deficiencies, renovation or repairs and cost changes. These dollar figures in this report are estimates only and are based solely on the data that was collected as of the assessment date in the footer below.
¹ It is very rare for an assessor to find a feature in this condition. If they do, they are required to report it immediately to CPS, and CPS addresses it immediately. Thus, no features will be ranked “1” in summary reports; by the time the report is compiled, they have been resolved.
Assessment Date: 3/11/2013 Page 23 of 23