Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age and condition of old voice/data equipment Impact Increase voice data capability to facility Improve tenet units ability to operate in maintenance building New system meets unit needs for 10-15 years Procurement Contractor: Tru-Edge Communications. Obligations: $ 23,977.85 Prime contractor is a small business concern Project Status COMPLETED: September 2009 Facilities Sustainment, Restoration, & Modernization (FSRM) New data rack and cat 5 cable installed in Maintenance building

Transcript of Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to...

Page 1: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Albany Compound Voice/Data Rewire Albany, Oregon

1

Project Description• Upgrade and modernization to the voice/data

system in the motor pool due to age and condition of old voice/data equipment

Impact • Increase voice data capability to facility• Improve tenet units ability to operate in

maintenance building • New system meets unit needs for 10-15 years

Procurement• Contractor: Tru-Edge Communications.• Obligations: $ 23,977.85• Prime contractor is a small business concern

Project Status• COMPLETED: September 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

New data rack and cat 5 cable installed in Maintenance building

Page 2: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Albany Compound Voice/Data Rewire Albany, Oregon

2

Project Description• Upgrade and modernization to the voice/data

system and MDF room in the motor pool due to age and condition of old voice/data equipment

Impact • Increase voice data capability to facility• Improve tenet units ability to operate in

maintenance building • New system meets unit needs for 10-15 years

Procurement• Contractor: TruEdge Communications.• Obligations: $ 23,977.85• Prime contractor is a small business concern

Project Status• COMPLETED: September 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed voice data system in Maintenance Building

Page 3: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Albany Compound Voice/Data Rewire Albany, Oregon

3

Project Description• Upgrade and modernization to the voice data

system and MDF room in the motor pool due to age and condition of old equipment

Impact • Increase voice data capability to facility• Improve tenet units ability to operate in

maintenance building • New system meets unit needs for 10-15 years

Procurement• Contractor: TruEdge Communications.• Obligations: $ 23,977.85• Prime contractor is a small business concern

Project Status• COMPLETED: September 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed voice data system in Maintenance Building

Page 4: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Biak Restrooms and ShowersPowell Butte, Oregon

4

Project Description• Construction of a new male and female

shower and restroom facility at the Biak Training Center

Impact • Increase usability of Biak Training Center for

soldiers training in a desert environment• Improve health and well being of soldiers • Improves Biak as a viable training area for

many years to come

Procurement• Contractor: Keeton-King Construction, Inc.• Obligations: $ 451,085.00• Prime contractor is a small business concern

Project Status• COMPLETED: May 2010

Facilities Sustainment, Restoration, & Modernization (FSRM)

CMU walls starting to go up for restrooms and showers

Page 5: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Biak Restrooms and ShowersPowell Butte, Oregon

5

Project Description• Construction of a new male and female

shower and restroom facility at the Biak Training Center

Impact • Increase usability of Biak Training Center for

soldiers training in a desert environment• Improve the health and well being of soldiers • Improves Biak as a viable training area for

many years to come

Procurement• Contractor: Keeton-King Construction, Inc.• Obligations: $ 451,085.00• Prime contractor is a small business concern

Project Status• COMPLETED: May 2010

Facilities Sustainment, Restoration, & Modernization (FSRM)

Partially constructed restroom and shower area with new breezeway

Page 6: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Biak Restrooms and ShowersPowell Butte, Oregon

6

Project Description• Construction of a new male and female

shower and restroom facility at the Biak Training Center

Impact • Increase usability of Biak Training Center for

soldiers training in a desert environment• Improve the health and well being of soldiers • Improves Biak as a viable training area for

many years to come

Procurement• Contractor: Keeton-King Construction, Inc.• Obligations: $ 451,085.00• Prime contractor is a small business concern

Project Status• COMPLETED: May 2010

Facilities Sustainment, Restoration, & Modernization (FSRM)

New wall lockers and sinks in shower area

Page 7: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Biak Restrooms and ShowersPowell Butte, Oregon

7

Project Description• Construction of a new male and female

shower and restroom facility at the Biak Training Center

Impact • Increase usability of Biak Training Center for

soldiers training in a desert environment• Improve health and well being of soldiers • Improves Biak as a viable training area for

many years to come

Procurement• Contractor: Keeton-King Construction, Inc.• Obligations: $ 451,085.00• Prime contractor is a small business concern

Project Status• COMPLETED: May 2010

Facilities Sustainment, Restoration, & Modernization (FSRM)

Completed restrooms and showers with breezeway

Page 8: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Brett Hall Classroom RemodelPowell Butte, Oregon

8

Project Description• Remodel of classroom and meeting space to

accommodate unit training

Impact • Increase usability of classroom for scenario

based training exercises• Increased voice/data capability to maximize

the training of transient units using facility • Improvement in technology for classroom

Procurement• Contractor: HSW Builders, LLC.• Obligations: $ 94,947• Prime contractor is a small business concern

Project Status• COMPLETED: December 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Brett Hall classroom before remodel

Page 9: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Brett Hall Classroom RemodelPowell Butte, Oregon

9

Project Description• Remodel of classroom and meeting space to

accommodate unit training

Impact • Increase usability of classroom for scenario

based training exercises• Increased voice/data capability to maximize

the training of transient units using facility • Improvement in technology for classroom

Procurement• Contractor: HSW Builders, LLC.• Obligations: $ 94,947• Prime contractor is a small business concern

Project Status• COMPLETED: December 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Old metal doorway leading into classroom before remodel

Page 10: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Brett Hall Classroom RemodelPowell Butte, Oregon

10

Project Description• Remodel of classroom and meeting space to

accommodate unit training

Impact • Increase usability of classroom for scenario

based training exercises• Increased voice/data capability to maximize

the training of transient units using facility • Improvement in technology for classroom

Procurement• Contractor: HSW Builders, LLC.• Obligations: $ 94,947• Prime contractor is a small business concern

Project Status• COMPLETED: December 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Cutting out old metal doorway during demolition phase

Page 11: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Brett Hall Classroom RemodelPowell Butte, Oregon

11

Project Description• Remodel of classroom and meeting space to

accommodate unit training

Impact • Increase usability of classroom for scenario

based training exercises• Increased voice/data capability to maximize

the training of transient units using facility • Improvement in technology for classroom

Procurement• Contractor: HSW Builders, LLC.• Obligations: $ 94,947• Prime contractor is a small business concern

Project Status• COMPLETED: December 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Sheetrock and HVAC ductwork being installed in classroom during remodel

Page 12: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Brett Hall Classroom RemodelPowell Butte, Oregon

12

Project Description• Remodel of classroom and meeting space to

accommodate unit training

Impact • Increase usability of classroom for scenario

based training exercises• Increased voice/data capability to maximize

the training of transient units using facility • Improvement in technology for classroom

Procurement• Contractor: HSW Builders, LLC.• Obligations: $ 94,947• Prime contractor is a small business concern

Project Status• COMPLETED: December 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

New doorway into classroom that replaced old metal doorway after remodel

Page 13: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Brett Hall Classroom RemodelPowell Butte, Oregon

13

Project Description• Remodel of classroom and meeting space to

accommodate unit training

Impact • Increase usability of classroom for scenario

based training exercises• Increased voice/data capability to maximize

the training of transient units using facility • Improvement in technology for classroom

Procurement• Contractor: HSW Builders, LLC.• Obligations: $ 94,947• Prime contractor is a small business concern

Project Status• COMPLETED: December 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

New classroom after remodel is complete

Page 14: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Hermiston Armory HVAC Improvements Hermiston, Oregon

14

Project Description• Construction of a new HVAC system for the

assembly hall which previously did not have an HVAC system and installation of a new generator

Impact • Increase drill hall rent ability for public use• Improve unit use of drill floor space for training• New HVAC system meets unit needs for the

next 20 years

Procurement• Contractor: Pendleton Heating and Air, Inc.• Obligations: $ 157,650.98• Prime contractor is a small business concern

Project Status• COMPLETED: August 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed heating and cooling duct work on drill hall ceiling

Page 15: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Hermiston Armory HVAC Improvements Hermiston, Oregon

15

Project Description• Construction of a new HVAC system for the

assembly hall which previously did not have an HVAC system and installation of a new 150 KW emergency generator

Impact • Increase drill hall rent ability for public use• Improve unit use of drill floor space for training• New HVAC system meets unit needs for the

next 20 years

Procurement• Contractor: Pendleton Heating and Air, Inc.• Obligations: $ 157,650.98• Prime contractor is a small business concern

Project Status• COMPLETED: August 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed 150 KW Generator with new pad and bollards

Page 16: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Hermiston Armory HVAC Improvements Hermiston, Oregon

16

Project Description• Construction of a new HVAC system for the

assembly hall which previously did not have an HVAC system and installation of a new 150 KW generator

Impact • Increase drill hall rent ability for public use• Improve unit use of drill floor space for training• New Heating and Cooling system meets unit

needs for the next 20 years

Procurement• Contractor: Pendleton Heating and Air, Inc.• Obligations: $ 157,650.98• Prime contractor is a small business concern

Project Status• COMPLETED: August 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed 10 ton cooling unit installed on roof

Page 17: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Hermiston Armory HVAC Improvements Hermiston, Oregon

17

Project Description• Construction of a new HVAC system for the

assembly hall which previously did not have an HVAC system and installation of a new 150 KW generator

Impact • Increase drill hall rent ability for public use• Improve unit use of drill floor space for training• New Heating and Cooling system meets unit

needs for the next 20 years

Procurement• Contractor: Pendleton Heating and Air, Inc.• Obligations: $ 157,650.98• Prime contractor is a small business concern

Project Status• COMPLETED: August 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

New control panel for newly installed heating and cooling system

Page 18: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Hermiston Armory HVAC Improvements Hermiston, Oregon

18

Project Description• Construction of a new HVAC system for the

assembly hall which previously did not have an HVAC system and installation of a new 150 KW generator

Impact • Increase drill hall rent ability for public use• Improve unit use of drill floor space for training• New Heating and Cooling system meets unit

needs for the next 20 years

Procurement• Contractor: Pendleton Heating and Air, Inc.• Obligations: $ 157,650.98• Prime contractor is a small business concern

Project Status• COMPLETED: August 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

New infrared heaters installed on drill floor ceiling

Page 19: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Salem Armory Window Replacement

Salem, Oregon

19

Project Description• Remove and replace single pane non energy

efficient windows with new energy efficient double pane windows

Impact • Increase heating and cooling efficiency• Cost savings of six to eight thousand yearly• Payback (current electrical costs) is 10 years

Procurement• Contractor: North Pacific Construction LLC.• Obligations: $ 71,680• Prime contractor is a small business concern

Project Status• COMPLETED: July 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed energy efficient double pane windows at entryway

Page 20: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Salem Armory Window Replacement Salem, Oregon

20

Project Description• Remove and replace single pane non energy

efficient windows with new energy efficient double pane windows

Impact • Increase heating and cooling efficiency• Cost savings of six to eight thousand yearly• Payback (current electrical costs) is 10 years

Procurement• Contractor: North Pacific Construction LLC.• Obligations: $ 71,680• Prime contractor is a small business concern

Project Status• COMPLETED: July 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Removing old single pane non energy efficient windows in classroom

Page 21: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Salem Armory Window Replacement Salem, Oregon

21

Project Description• Remove and replace single pane non energy

efficient windows with new energy efficient double pane windows

Impact • Increase heating and cooling efficiency• Cost savings of six to eight thousand yearly• Payback (current electrical costs) is 10 years

Procurement• Contractor: North Pacific Construction LLC.• Obligations: $ 71,680• Prime contractor is a small business concern

Project Status• COMPLETED: July 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

A new window installed and an old window being taken out

Page 22: Albany Compound Voice/Data Rewire Albany, Oregon 1 Project Description Upgrade and modernization to the voice/data system in the motor pool due to age.

Salem Armory Window Replacement Salem, Oregon

22

Project Description• Remove and replace single pane non energy

efficient windows with new energy efficient double pane windows

Impact • Increase heating and cooling efficiency• Cost savings of six to eight thousand yearly• Payback (current electrical costs) is 10 years

Procurement• Contractor: North Pacific Construction LLC.• Obligations: $ 71,680• Prime contractor is a small business concern

Project Status• COMPLETED: July 2009

Facilities Sustainment, Restoration, & Modernization (FSRM)

Newly installed energy efficient double pane windows in classroom