Alabama State Port AuthorityInfrastructure for Tomorrow’s Market
October 2005
Who is the Alabama State Port Authority? Full Transportation Services for State/Regional Industries
Automotive Aerospace Forest Products Distribution Centers
14th Largest Port in USA - Throughput Tonnage
What is ASPA Doing for the Future? New Infrastructure New Container Terminal Marketing Large Tracts for
Distribution and Value Added Industries
General Cargo & Oversized/Heavy Lift Cargo
General Cargo & Oversized/Heavy Lift Cargo
Berth E ExpansionBerth E Expansion
Future Choctaw Point Container Intermodal Yard
Future Choctaw Point Container Intermodal Yard
Pier 2 Container Terminal/Interchange Gate
Pier 2 Container Terminal/Interchange Gate
I-65I-65
Port of Mobile
ASPA Terminal Railway Interchange (5 Class 1 RRs)
ASPA Terminal Railway Interchange (5 Class 1 RRs)
I-10 (I-65 3 Mi. South)I-10 (I-65 3 Mi. South)
McDuffie Bulk TerminalMcDuffie Bulk Terminal
Bulk PlantBulk Plant
TENNESSEE
MISSISSIPPI
ALABAMA Tennessee River
Tennessee-Tombigbee
Warrior-Tombigbee
Coosa-Alabama
Apalachicola-Chattahoochee-Flint
Gulf Intracoastal Waterway
Port of Mobile Provides Access to Nearly 15,000 Miles of Inland Waterways Serving Great Lakes, Ohio, Upper Miss. And Tennessee Valley Ports
2001-2004 Capital Projects
• McDuffie $ 4M• Pier 2 Yard Improvements $ 2M• North A Redevelopment $ 15M• Pier C Expansion $ 7M• Pier D $ 7M• Freezer Terminal* $ 9M• Cement Terminal Expansion* $ 10M• Grain Elevator Expansion* $ 6M• Choctaw Point Property $ 18M
Acquisition, Environmental, Engineering, Permitting
Total 2001-2004 Expenditure $ 78M
* Private Investment
2005 Capital Plans
•Choctaw Point Container Terminal $ 60.5M•McDuffie Expansion $ 28M•Pier E Expansion $ 9M•Security Enhancements $ 4M
•Other – Land, Equipment, IT $ 13M
Total 2005 Capital Expenditure$114.5M
Security Enhancements
• Additional Police Officers
• New Police Building
• New Fencing & Lighting
• New CCTV System
• Digital Video Analysis Software
• Digital Fingerprinting Equipment
$4.5 Million in FY 2005
Berth E Improvement Serves General Cargo
• Converts Ro/Ro Berth to Conventional Berth
• Provides an additional 250,000+ sq. ft. for General Cargo Use• Up to $9M is Being
Invested• Operational Fall 2005
McDuffie Coal Terminal
• Expansion• $28-30 Million Invested• Adds New Unloading
Capability at Berth 1• Additional
Stacker/Reclaimer• Unit Train Loading
Capability
• Increases Import Capacity to 16-18 Million Tons
• Brings Terminal to a Minimum of 24 Million Tons in Throughput Capacity
Choctaw Point Terminal380 Acre Site
CPT – Container Terminal – Stage 1
CPT - Intermodal Container Transfer Facility
CPT Near-Term Schedule
Design/Construction (Stage 1)
Concept Design . . . . . Oct. 03
Site Demolition . . . . . Jan. 04
Began Final Design . . . . . May 04
Permits Approved . . . . . . March 05
Began Construction . . . . . May 05
Operational . . . . . 2nd Qtr. 07
2005 Expenditures (Stage 1)
Bulkhead & Dredging ($22.3M). . April 05
Land Reclamation . . . Bids Open May 05
Site Stabilization . . . . . Bids Open May 05
Private Partner Selection… Aug. 05
Engineering, Design,
& Construction ($40-50M)….4th Qtr. 05
Alabama State Port AuthorityInfrastructure for Tomorrow’s Market
Thank You!