Akbar Jazayeri Subject: Submission of Contracts for … · FlexEnergy, however, did not participate...

56
STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 September 29, 2008 Advice Letter 2203-E Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770 Subject: Submission of Contracts for Procurement of Renewable Energy Resulting from Bilateral Negotiations Dear Mr. Jazayeri: Advice Letter 2203-E is effective September 18, 2008. Sincerely, Kenneth Lewis, Acting Director Energy Division

Transcript of Akbar Jazayeri Subject: Submission of Contracts for … · FlexEnergy, however, did not participate...

STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor

PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298

September 29, 2008 Advice Letter 2203-E

Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770

Subject: Submission of Contracts for Procurement of Renewable Energy Resulting from Bilateral Negotiations Dear Mr. Jazayeri: Advice Letter 2203-E is effective September 18, 2008. Sincerely,

Kenneth Lewis, Acting Director Energy Division

P.O. Box 800 2244 Walnut Grove Ave. Rosemead, California 91770 (626) 302-3630 Fax (626) 302-4829

`

Akbar Jazayeri Vice President of Regulatory Operations

PUBLIC VERSION

January 23, 2008

ADVICE 2203-E (U 338-E)

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

SUBJECT: Submission of Contracts for Procurement of Renewable Energy Resulting From Bilateral Negotiations

PURPOSE

Southern California Edison Company (“SCE”) submits this Advice Letter in compliance with Cal. Pub. Util. Code § 399.11 et seq. (the “RPS Legislation”) seeking approval of two renewables portfolio standard (“RPS”) power purchase agreements (“PPAs”) between SCE and FlexEnergy Corporation (“FlexEnergy”) relating to power plants in Sun Valley, California ( “Flex LA”) and Beaumont, California (”Flex Riverside”) (together, the “FlexEnergy Contracts”).

A table summarizing the PPAs is as follows:

Project Generation Type

Initial Size (MW)

Possible Expansion Size (MW)

Estimated Annual Energy

Based on Initial Size

(GWh)

Estimated Annual Energy

Based On Expansion

Size (GWh)

Initial On- Line Date

Term of Agreement

(Years)

Flex LA Biomass 2 MW N/A 12.26 GWh N/A October 22, 2012

20

Flex Riverside

Biomass 2 MW N/A 12.26 GWh N/A October 22, 2012

20

SCE requests that the California Public Utilities Commission (“Commission” or “CPUC”) issue a Resolution containing findings in the form requested in this Advice Letter no later than April 24, 2008.

In accordance with General Order (“GO”) 96-B, the confidentiality of information included in this advice filing is described below. This Advice Letter contains both Confidential and Public Appendices. Appendices B-C and E-H are confidential.

Advice 2203-E (U 338-E) - 2 - January 23, 2008

Appendices A, D, and I are public. This advice filing includes a confidential version including all appendices and a public version including Appendices A, D, and I and a public version of Appendices B-C and E-H.

This advice letter contains the following appendices:

Appendix A: Designation of Confidential Information

Confidential Appendix B: Confidential Contract Summary

Confidential Appendix C: FlexEnergy Contracts’ Contributions to RPS Goals

Appendix D: SCE’s RPS Bid Evaluation and Selection Process and Criteria

Confidential Appendix E: Project Viability Matrices

Confidential Appendix F: CEC-SEP Pricing Worksheets

Confidential Appendix G: Power Purchase Agreement between SCE and FlexEnergy for Flex LA

Confidential Appendix H: Power Purchase Agreement between SCE and FlexEnergy for Flex Riverside

Appendix I: Proposed Protective Order

I. INTRODUCTION AND BACKGROUND

The RPS Legislation requires certain load serving entities (“LSEs”), including SCE, to increase their procurement from renewable resources by at least 1 percent of their annual retail electricity sales per year so that 20 percent of their annual electricity sales are procured from eligible renewable energy resources by no later than December 31, 2010. In Decision (“D.”) 03-06-071, the Commission provided its initial guidance for implementation of the RPS Legislation. In that decision, the Commission authorized the investor owned utilities (“IOUs”) to enter into bilateral RPS contracts if the contracts were prudent and did not require public goods charge funds.1 Pursuant to this authority, SCE now seeks approval of two bilaterally negotiated RPS-eligible PPAs between SCE and FlexEnergy.

In addition, in order to help small biomass projects contribute to the State’s RPS goals and to support California Governor Arnold Schwarzenegger’s goal to promote energy production from biomass fuel sources,2 SCE has voluntarily initiated a biomass power contracting initiative (“SCE Biomass Program” or “Program”) to offer a standardized contract for the purchase of renewable energy to biomass facilities with capacities of

1 See also D.06-10-019 at 31 (IOUs may enter into reasonable bilateral RPS contracts). 2 See Executive Order S-06-06.

Advice 2203-E (U 338-E) - 3 - January 23, 2008

20 MW or less. Through the Program, SCE has recognized that smaller biomass projects have had difficulties in participating in SCE’s annual solicitations. This has been especially true for projects with smaller generating capacities. By eliminating the complex negotiation process that is needed for larger projects, the Program gives smaller projects the opportunity to execute contracts with SCE and contribute to the State’s RPS goals. The FlexEnergy Contracts were executed as part of this Program.

A. General Description of the Flex LA and Flex Riverside Projects

The Flex LA and Flex Riverside projects are two new 2 megawatt (“MW”) biomass facilities being developed by FlexEnergy, a California corporation. Both the Flex LA and the Flex Riverside contracts obligate FlexEnergy to construct, own and operate a biomass electric energy generating facility and to sell all electric energy produced by that generating facility to SCE. The Flex LA facility will be located at a closed landfill in Sun Valley, California. The facility will utilize a new Flex-Microturbine. These turbines are a new lean-burning gas turbine technology that has been developed by FlexEnergy. The Flex Riverside facility will be located at a working landfill in Beaumont, California. This facility will also utilize new Flex-Microturbines. Both facilities will have an expected output of 12.26 GWh per year. The FlexEnergy contracts have a term of 20 years and are expected to come on-line in October 2012. The pricing under the FlexEnergy Contracts is the 2006 Market Price Referent (“MPR”) value for the year the project comes on line.

B. Contributions to IPT and APT

As stated above, the RPS Legislation and the Commission decisions implementing the RPS Legislation require SCE to increase its procurement from renewable resources by at least 1 percent of its annual retail electricity sales per year so that 20 percent of its annual electricity sales are procured from renewable resources by 2010. The 1 percent increase per year has been defined as the incremental procurement target (“IPT”) and the yearly required total has been defined as the annual procurement target (“APT”).3 By definition, the obligation to increase renewable procurement by 1 percent per year (i.e., the IPT) is eliminated in 2010. For 2010 and beyond, SCE is required to procure 20 percent of its energy from renewable resources. In other words, beyond 2009, SCE does not have an IPT obligation and its APT obligation remains at 20 percent.

The FlexEnergy Contracts are expected to begin deliveries by October 22, 2012. The renewable output from the Flex LA and Flex Riverside facilities are each expected to contribute approximately 12.26 GWh towards SCE’s APT for the term of the agreements.

Tables summarizing Flex LA’s and Flex Riverside’s contributions to SCE’s RPS goals can be found in Appendix C.

3 See D.06-10-050.

Advice 2203-E (U 338-E) - 4 - January 23, 2008

C. Above MPR Payments

Contracts entered into through the SCE Biomass Program are offered at an energy price set at the MPR. Therefore, no above MPR payments are required.

II. PRG PARTICIPATION AND FEEDBACK

A. PRG Participation

SCE’s procurement review group (“PRG”) was formed on or around September 10, 2002. Participants include representatives from the Commission’s Energy and Legal Divisions, the Division of Ratepayer Advocates, The Utility Reform Network, the Natural Resources Defense Council, California Utility Employees, the Union of Concerned Scientists, Aglet Consumer Alliance and the California Department of Water Resources. SCE has consulted with its PRG during each step of the renewable procurement process.

In April of 2007, SCE presented the PRG with the details of the SCE Biomass Program. On November 12, 2007, SCE briefed the PRG concerning the successful conclusion of discussions with FlexEnergy.

B. PRG Feedback

SCE does not keep recorded minutes, notes, or comments from PRG meetings. The PRG has requested that SCE not broadly characterize PRG responses and comments.

III. CONSISTENCY WITH COMMISSION DECISIONS

A. Commission Decisions Allow IOUs to Procure Renewable Resources Through Bilateral Negotiations

As stated above, D.03-06-071 allows the IOUs to enter into bilateral agreements outside of the competitive solicitation process. This authority was reaffirmed in D.06-10-019 so long as the agreements are reasonable. In addition, in a decision approving a bilaterally negotiated RPS agreement entered into by SCE, the Commission stated that bilateral agreements can be evaluated prior to the Commission establishing formal evaluation criteria for bilateral agreements.4 As discussed in more detail below and in the confidential appendices, based on the least-cost/best-fit (“LCBF”) analysis and the price of the contracts, the FlexEnergy Contracts are reasonable. Thus, the execution of the FlexEnergy Contracts is consistent with Commission decision.

B. The FlexEnergy Contracts Conform to SCE’s Portfolio Needs

Although the FlexEnergy Contracts are separate and apart from the contracts executed as a result of SCE’s annual solicitation, the FlexEnergy Contracts still fall within the

4 See D.07-08-028 at 4.

Advice 2203-E (U 338-E) - 5 - January 23, 2008

criteria identified in SCE’s 2007 RPS procurement plan, are expected to contribute significantly toward achievement of SCE’s RPS procurement goals, and are consistent with SCE’s portfolio needs. More specifically, the FlexEnergy Contracts satisfy SCE’s short-term need for eligible renewable energy from a new facility over a 20-year term. In addition, the FlexEnergy Contracts satisfy both SCE’s locational preference for facilities located in California and SCE’s delivery requirements. Furthermore, as agreements developed through the SCE Biomass Program, the FlexEnergy Contracts help SCE in its goal to promote energy production from biomass fuel sources as directed by the Governor’s Executive Order.

C. LCBF Methodology and Evaluation

1. SCE’s LCBF Methodology

SCE evaluates and ranks proposals based on LCBF principles that comply with criteria set forth by the Commission in D.03-06-071 and D.04-07-029 (the “LCBF Decisions”). The LCBF analysis evaluates both quantitative and qualitative aspects of each proposal to evaluate its absolute value to SCE’s customers and relative value in comparison to other proposals. Typically, this analysis is performed in connection with SCE’s annual RPS solicitations. FlexEnergy, however, did not participate in an SCE solicitation. Instead, the FlexEnergy Contracts were executed as part of the SCE Biomass program. SCE, however, performed a LCBF evaluation of the FlexEnergy Contracts in comparison to the proposals SCE received in its 2007 RPS solicitation in order to demonstrate that the FlexEnergy Contracts are relatively attractive in comparison to those proposals. Details regarding the LCBF analysis of the FlexEnergy Contracts are provided in Appendix B and a general description of the LCBF methodology is provided below.

While assumptions and methodologies have evolved slightly over time, the basic components of SCE’s evaluation and selection criteria and process for RPS contracts were established in the Commission’s LCBF Decisions. The three main steps that are undertaken by SCE are an initial data-gathering period, followed by a quantitative assessment of proposals, ending with adjustments to selection based on qualitative attributes of proposals.

Prior to receiving proposals, SCE finalizes major assumptions and methodologies that drive valuation, including power and gas price forecasts, existing and forecast resource portfolio, and firm capacity value forecast. Other assumptions, such as the Transmission Ranking Cost Report (“TRCR”), are filed with the Commission for approval prior to the release of the solicitation materials. In addition, SCE gathers the current input assumptions that are developed by external parties, such as the effective load-carrying capabilities set by the California Energy Commission (“CEC”).

Once proposals are received, SCE begins an initial review for completeness, conformance, and viability. The review includes a screen for reasonableness of

Advice 2203-E (U 338-E) - 6 - January 23, 2008

proposal parameters, such as generation profiles and capacity factors. SCE works directly with bidders to resolve any issues and ensure data is ready for evaluation.

After this initial review, SCE performs the quantitative assessment of each proposal individually. The result of the quantitative analysis is a relative ranking of proposals that helps define the preliminary short list. Qualitative attributes of each proposal are considered, if needed, to further screen the short list and arrive at a final short list of proposals.

After this analysis, SCE consults with its PRG regarding its final short list and specific evaluation criteria. Whether a proposal selected in this process results in an executed contract depends on how contract discussions proceed. Periodically, SCE updates the PRG regarding the contracting progress and also reviews contracts with the PRG prior to execution. Subsequently, SCE executes contracts and submits them to the Commission for approval.

A complete discussion of SCE’s RPS Bid Evaluation and Selection Process and Criteria is provided in Appendix D.

2. Comparison of the FlexEnergy Contracts With Bids Received in SCE’s 2007 RPS Solicitation With Regard to Each LCBF Factor

SCE’s LCBF quantitative evaluation of bids incorporates energy and capacity benefits with energy payments, transmission costs, and debt equivalence to create individual benefit-to-cost (“B/C”) ratios. It is this B/C ratio that is used to rank and compare each project. Comparing the individual components of the B/C ratio of one bid to another is not a useful means of evaluating projects.

The combination of benefits and costs for the FlexEnergy Contracts resulted in B/C ratios that ranked high enough to demonstrate that the FlexEnergy Contracts provide significant value for SCE’s customers relative to proposals received during SCE’s annual solicitation and represent contracts that provide for the delivery of relatively attractive renewable power pursuant to terms and conditions that meet all of the requirements of the RPS Legislation and the Commission’s decisions implementing the RPS Legislation.

More detailed information regarding the B/C ratios for the FlexEnergy Contracts can be found in Appendix B.

Advice 2203-E (U 338-E) - 7 - January 23, 2008

3. Portfolio Fit – Demonstrate Best Fit – Evaluation of FlexEnergy’s Costs and Benefits in the Context of SCE’s Portfolio Needs

SCE’s primary portfolio needs in the long term are for resource adequacy-eligible capacity, low-cost energy, and RPS-eligible energy. Due to the peaky nature of SCE’s demand profile, on-peak energy is valued much more highly than off-peak energy.

The Flex LA and Flex Riverside projects provide nameplate capacity of 2 MW each, which will be counted for resource adequacy purposes. Each project will also provide approximately 12.26 GWh of RPS-eligible energy annually, which will be largely distributed evenly over the year.

Remarketing costs are captured in the production cost simulations required in analyzing the energy benefits of the project. While the remarketing cost component of the results cannot be removed and evaluated on an individual basis, one can make some assumptions about the impact of the project on potential remarketing costs.

Generally, a must-take, biomass project, such as the FlexEnergy projects, will generate at the full capacity of the contract around-the-clock. While there would not be any cost to remarket the energy in peak periods, there could be some remarketing cost to selling excess energy that this project may contribute to in off-peak periods, particularly in the winter.

4. Transmission Adder – Consistency With Commission Decisions Addressing RPS Transmission Ranking Cost Methodology and IOU Transmission Ranking Cost Report

Transmission costs were estimated for those generating facilities that do not have an existing interconnection to the electric system or a completed system impact study, consistent with the TRCR requirements specified by D.04-06-013 and D.05-07-040. The ranking was applied accordingly and in compliance with Commission decisions.

5. Impact of Debt Equivalence

Specific information regarding the impact of debt equivalence on the FlexEnergy Contracts can be found in Appendix B.

D. Standard Terms and Conditions

In D.04-06-014, the Commission established a number of “modifiable” and “non-modifiable” standard terms and conditions to be used by the IOUs when contracting for RPS-eligible resources. In D.07-11-025, the Commission reduced the number of “non-modifiable” terms to the following four terms: (1) “CPUC Approval,” (2) “RECs and Green Attributes,” (3) “Eligibility,” and (4) “Applicable Law.” The remaining “non-modifiable” terms were converted to “modifiable.”

Advice 2203-E (U 338-E) - 8 - January 23, 2008

The FlexEnergy Contracts include the four “non-modifiable” terms identified above without change.

In addition, as permitted by D.04-06-014 and D.07-11-025, SCE modified most if not all of the “modifiable” terms. These modifications, however, include the same principles and serve the same purpose as the standard terms, and are consistent with the law and government regulation. Thus, pursuant to D.07-11-025, the modifications are permissible.

E. Project Viability

The viability of the Flex LA and Flex Riverside projects is low, because they are based on a commercially unproven technology. The developer of the projects, FlexEnergy, was launched in 1998. Following several years of research in the development of a lean-burn gas turbine, FlexEnergy developed its patented Flex-Microturbine, a technology which burns methane gas at a much lower level of concentration than other turbines. This new technology is able to convert landfill gas into electricity from sources that are unable to economically fuel conventional biomass microturbine technology due to low methane levels. FlexEnergy’s development has been funded largely through competitive grants from federal and state green energy programs, research institutes and private sources. A prototype of the Flex-Microturbine has exceeded 3,000 hours of operation on low Btu gas and continues to perform. FlexEnergy continues to seek funding and recently secured several million dollars in funds from private investors. FlexEnergy, however, has not demonstrated the technology at a commercial level.

The Flex LA facility is located at a closed landfill. The landfill gas from this landfill is not yet being used to support biomass microturbine technology. FlexEnergy believes that the landfill is an excellent resource for its new lean-burn gas turbine, which should be able to utilize the landfill's low methane levels more efficiently than conventional biomass microturbine technology.

The Flex Riverside facility is located at a working landfill. The landfill gas from this landfill is not yet being used to support biomass microturbine technology. FlexEnergy believes that the landfill is an excellent resource for its new lean-burn gas turbine, which should be able to utilize the landfill's low methane levels more efficiently than conventional biomass microturbine technology.

FlexEnergy has nearly completed site control of the Flex LA location. FlexEnergy has entered into a letter agreement with the landfill which will allow it to operate at the location.

FlexEnergy has nearly completed site control of the Flex Riverside location. FlexEnergy has entered into a letter agreement with the landfill which will allow it to operate at the location.

Advice 2203-E (U 338-E) - 9 - January 23, 2008

Neither FlexEnergy nor SCE anticipate that the construction of either facility or its equipment will be an impediment to the completion of the projects.

Finally, it is unknown at this time whether transmission will serve as an impediment to the viability of the projects, because it is unknown at this time how or when FlexEnergy intends to interconnect either project.

Project viability matrices for the Flex LA and Flex Riverside projects can be found in Appendix E.

F. Contingencies and Milestones

1. PTCs/ITCs

Specific information regarding production tax credits (“PTCs”) and investment tax credits (“ITCs”) for the FlexEnergy Contracts can be found in Appendix B.

2. Termination Rights Impacting the Schedule for Commission Approval

Specific information regarding termination rights that may impact the schedule for Commission approval of the FlexEnergy Contracts can be found in Appendix B.

G. Regulatory Process

1. Earmarking

SCE reserves the right to earmark any generation from these contracts into future RPS compliance years as applicable.

2. RPS-eligibility Certification From the CEC

To date, FlexEnergy has not received RPS-eligibility certification from the CEC. However, neither SCE nor FlexEnergy foresee any issues with obtaining CEC certification.

3. Applicability of Senate Bill (“SB”) 1368 and the Commission’s Greenhouse Gas Emissions Performance Standard

The California Legislature passed SB 1368 on August 31, 2006 and Governor Schwarzenegger signed the bill into law on September 29, 2006. Section 2 of SB 1368 adds Public Utilities Code section 8341(a), which provides that “No load-serving entity or local publicly owned electric utility may enter into a long-term financial commitment unless any baseload generation supplied under the long-term financial commitment

Advice 2203-E (U 338-E) - 10 - January 23, 2008

complies with the greenhouse gases emission performance standard established by the commission, pursuant to subdivision (d).”5

In order to institute the provisions of SB 1368, the Commission instituted Rulemaking 06-04-009. This proceeding resulted in the establishment of a GHG emissions performance standard (“EPS”), for CO2. D.07-01-039 noted, “SB 1368 establishes a minimum performance requirement for any long-term financial commitment for baseload generation that will be supplying power to California ratepayers. The new law establishes that the GHG emissions rates for these facilities must be no higher than the GHG emissions rate of a combined-cycle gas turbine (CCGT) powerplant.”6

The decision further explains:

SB 1368 describes what types of generation and financial commitments will be subject to the EPS (“covered procurements”). Under SB 1368, the EPS applies to “baseload generation,” but the requirement to comply with it is triggered only if there is a “long-term financial commitment” by an LSE. The statute defines baseload generation as “electricity generation from a powerplant that is designed and intended to provide electricity at an annualized plant capacity factor of at least 60%.” . . . For baseload generation procured under contract, there is a long-term commitment when the LSE enters into “a new or renewed contract with a term of five or more years.”7

In D.07-01-039, the Commission found that it would be redundant and costly to require LSEs to demonstrate EPS compliance for each new ownership investment, new contract or renewed contract with baseload renewable resources if the record clearly demonstrated that these resources comply with the EPS on a net emissions basis.8 The Commission found that the net GHG emissions from the following renewable resources/technologies meet the interim EPS:

• Solar Thermal Electric (with up to 25% gas heat input);

• Wind;

• Geothermal, with or without reinjection; and

• Generating facilities (e.g., agricultural and wood waste, landfill gas) using biomass that would otherwise be disposed of utilizing open burning, forest

5 California Public Utilities Code § 8341(a). 6 D.07-01-039 at 2-3. 7 Id. at 4. 8 Id. at 245-246, Finding of Fact No. 117.

Advice 2203-E (U 338-E) - 11 - January 23, 2008

accumulation, landfill (uncontrolled, gas collection with flare, gas collection with engine), spreading or composting.9

By this Advice Letter filing, SCE requests that the Commission approve two long-term PPAs with FlexEnergy. Although, in general, these two “new contracts with a term of five or more years” would be subject to the EPS, these PPAs are exempt from such regulations. Both Flex LA and Flex Riverside are biomass facilities utilizing landfill gas, a technology that has been deemed compliant with the EPS standard under D.07-01-039.

CONFIDENTIALITY

SCE is requesting confidential treatment of the confidential portions of Appendices B-C and E-H to this advice filing. The information for which SCE is seeking confidential treatment is identified in Appendix A hereto. The confidential version of this advice filing will be made available to appropriate parties (in accordance with SCE’s Proposed Protective Order, as discussed below) upon execution of the required non-disclosure agreement. Parties wishing to obtain access to the confidential version of this advice filing may contact Joni Templeton in SCE’s Law Department at [email protected] or (626) 302-6210 to obtain a non-disclosure agreement. In accordance with GO 96-B, a copy of SCE’s Proposed Protective Order is attached hereto as Appendix I. It is appropriate to accord confidential treatment to the information for which SCE requests confidential treatment in the first instance in the advice letter process because such information is entitled to confidentiality protection pursuant to D.06-06-066 and is required to be filed by advice letter as part of the process for obtaining Commission approval of RPS PPAs.

The information in this advice filing for which SCE requests confidential treatment, the pages on which the information appears, and the length of time for which the information should remain confidential, are provided in Appendix A. This information is entitled to confidentiality protection pursuant to D.06-06-066 (as provided in the IOU Matrix). The specific provisions of the IOU Matrix that apply to the confidential information in this advice filing are identified in Appendix A.

The confidential information provided in this advice filing cannot be aggregated, redacted, summarized, masked, or otherwise protected in a manner that would allow partial disclosure of the data, while still protecting confidential information, because the RPS contract advice filing template calls for the data to be provided in its present form. SCE would object to any disclosure of the confidential information in aggregated form. Based on the format of the RPS contract advice filing template, SCE is not aware of any manner that the confidential information could be aggregated that would qualify the information for public status under the IOU Matrix of D.06-06-066.

9 Id. at 246, Finding of Fact No. 118; 269-70, Conclusion of Law No. 35.

Advice 2203-E (U 338-E) - 12 - January 23, 2008

To the best of my knowledge, SCE maintains as confidential the information contained in this advice filing for which confidentiality is sought. I am informed and believe that this information is maintained by SCE’s Renewable and Alternative Power Department and the Independent Evaluator and provided internally only to those employees who need to know the information to carry out their job duties. I am also informed and believe that this information has not been disclosed to any person other than employees of SCE, the Independent Evaluator or non-market participants (such as staff of the CPUC).

TIER DESIGNATION

Pursuant to D.07-01-024, Energy Industry Rule 5.3, SCE submits this advice filing with a Tier 3 designation (effective after Commission approval).

REQUEST FOR COMMISSION APPROVAL

The terms of the FlexEnergy Contracts are conditioned on the occurrence of “CPUC Approval,” as it is defined in the PPAs. In order to satisfy that condition with respect to the PPAs, SCE requests that the Commission issue a resolution no later than April 24, 2008, containing:

1. Approval of the FlexEnergy Contracts in their entirety;

2. A finding that any electric energy sold or dedicated to SCE pursuant to the FlexEnergy Contracts constitutes procurement by SCE from an eligible renewable energy resource (“ERR”) for the purpose of determining SCE’s compliance with any obligation that it may have to procure from ERRs pursuant to the RPS Legislation or other applicable law concerning the procurement of electric energy from renewable energy resources;

3. A finding that all procurement under the FlexEnergy Contracts counts, in full and without condition, toward any annual procurement target established by the RPS Legislation or the Commission which is applicable to SCE;

4. A finding that all procurement under the FlexEnergy Contracts counts, in full and without condition, toward any incremental procurement target established by the RPS Legislation or the Commission which is applicable to SCE;

5. A finding that all procurement under the FlexEnergy Contracts counts, in full and without condition, toward the requirement in the RPS Legislation that SCE procure 20 percent (or such other percentage as may be established by law) of its retail sales from ERRs by 2010 (or such other date as may be established by law);

6. A finding that the FlexEnergy and SCE’s entry into these PPAs, is reasonable and prudent for all purposes, including, but not limited to, recovery in rates of

Advice 2203-E (U 338-E) - 13 - January 23, 2008

payments made pursuant to the PPAs, subject only to further review with respect to the reasonableness of SCE’s administration of the PPAs; and

7. Any other and further relief as the Commission finds just and reasonable. EFFECTIVE DATE

This advice filing will become effective on April 24, 2008.

NOTICE

Anyone wishing to protest this advice filing may do so by letter via U.S. Mail, facsimile, or electronically, any of which must be received by the Energy Division and SCE no later than 20 days after the date of this advice filing. Protests should be mailed to:

Akbar Jazayeri Vice President of Regulatory Operations Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, California 91770 Facsimile: (626) 302-4829 E-mail: [email protected]

Bruce Foster Senior Vice President, Regulatory Affairs c/o Karyn Gansecki 601 Van Ness Avenue, Suite 2040 San Francisco, California 94102 Facsimile: (415) 673-1116 E-mail: [email protected]

Stuart Hemphill Director of Renewable and Alternative Power c/o Mike Marelli Southern California Edison Company 2244 Walnut Grove Avenue, Quad 4D Rosemead, CA 91770 Facsimile: (626) 302-1103 E-mail: [email protected]

With a copy to:

Advice 2203-E (U 338-E) - 14 - January 23, 2008

Joni A. Templeton Attorney Southern California Edison Company 2244 Walnut Grove Avenue, 3rd Floor Rosemead, CA 91770 Facsimile: (626) 302-1935 E-mail: [email protected]

There are no restrictions on who may file a protest, but the protest shall set forth specifically the grounds upon which it is based and shall be submitted expeditiously.

In accordance with Section 4 of GO 96-B, SCE is furnishing copies of this advice filing to the interested parties shown on the attached R.06-05-027, R.06-02-012, and GO 96-B service lists. Address change requests to the GO 96-B service list should be directed to [email protected] or at (626) 302-2930. For changes to any other service list, please contact the Commission’s Process Office at (415) 703-2021 or at [email protected].

Further, in accordance with Public Utilities Code Section 491, notice to the public is hereby given by filing and keeping the advice filing at SCE’s corporate headquarters. To view other SCE advice letters filed with the Commission, log on to SCE’s web site at http://www.sce.com/AboutSCE/Regulatory/adviceletters.

All questions concerning this advice filing should be directed to James Woodruff at (626) 302-1924 (E-mail: [email protected]).

Southern California Edison Company

Akbar Jazayeri

Enclosures AJ:jw:sq

CALIFORNIA PUBLIC UTILITIES COMMISSION

ADVICE LETTER FILING SUMMARY ENERGY UTILITY

MUST BE COMPLETED BY UTILITY (Attach additional pages as needed)

Company name/CPUC Utility No.: Southern California Edison Company (U 338-E)

Utility type: Contact Person: James Yee

! ELC " GAS Phone #: (626) 302-2509

" PLC " HEAT " WATER E-mail: [email protected]

E-mail Disposition Notice to: [email protected] EXPLANATION OF UTILITY TYPE

ELC = Electric GAS = Gas PLC = Pipeline HEAT = Heat WATER = Water

(Date Filed/ Received Stamp by CPUC)

Advice Letter (AL) #: 2203-E Tier Designation: 3

Subject of AL: Submission of Contracts for Procurement of Renewable Energy Resulting From Bilateral Negotiations

Keywords (choose from CPUC listing): Contracts, Portfolio, Procurement

AL filing type: " Monthly " Quarterly " Annual ! One-Time " Other

If AL filed in compliance with a Commission order, indicate relevant Decision/Resolution #:

Does AL replace a withdrawn or rejected AL? If so, identify the prior AL:

Summarize differences between the AL and the prior withdrawn or rejected AL1:

Confidential treatment requested? ! Yes " No

If yes, specification of confidential information: See Appendix A. Confidential information will be made available to appropriate parties who execute a nondisclosure agreement. Name and contact information to request nondisclosure agreement/access to confidential information:

Joni Templeton, Law Department, at (626) 302-6210 or by electronic mail at [email protected]

Resolution Required? ! Yes " No

Requested effective date: 4/24/08 No. of tariff sheets: -0-

Estimated system annual revenue effect: (%):

Estimated system average rate effect (%):

When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting).

Tariff schedules affected: None

Service affected and changes proposed1:

Pending advice letters that revise the same tariff sheets:

1 Discuss in AL if more space is needed.

Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this filing, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Ave., San Francisco, CA 94102 [email protected] and [email protected]

Akbar Jazayeri Vice President of Regulatory Operations Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, California 91770 Facsimile: (626) 302-4829 E-mail: [email protected] Bruce Foster Senior Vice President, Regulatory Affairs c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2040 San Francisco, California 94102 Facsimile: (415) 673-1116 E-mail: [email protected] Stuart Hemphill Director of Renewable and Alternative Power c/o Mike Marelli Southern California Edison Company 2244 Walnut Grove Avenue, Quad 4D Rosemead, California 91770 Facsimile: (626) 302-1103 E-mail: [email protected] With a copy to: Joni Templeton Attorney Southern California Edison Company 2244 Walnut Grove Avenue, 3rd Floor Rosemead, California 91770 Facsimile: (626) 302-6210 E-mail: [email protected]

Appendix A

Designation of Confidential Information

A-1

DESIGNATION OF CONFIDENTIAL INFORMATION

Identified below are the data in SCE’s Advice Letter for which SCE is seeking

confidential protection and the categories of the Matrix of Allowed Confidential Treatment

Investor Owned Utility (“IOU”) Data (the “IOU Matrix”) to which these data correspond. Also

set forth is the period of time for which confidential protection is authorized by the IOU Matrix.

Data

Page

Matrix Category

Period of Confidentiality

Confidential Contract Summary for FlexEnergy

Appendix B VII.F/VII.G RPS Contracts

VII.H Score sheets, analyses, evaluations of proposed RPS projects

VIII.A Bid Information

VIII.B Specific quantitative analysis involved in the scoring and evaluation of participating bids

RPS contracts confidential for three years, or until one year following expiration, whichever comes first.

Score sheets, analyses, evaluations of proposed RPS projects confidential for three years.

For bid information, total number of projects and megawatts bid by resource type public after final contracts submitted to CPUC for approval.

Specific quantitative analysis involved in the scoring and evaluation of participating bids confidential for three years after winning bidders selected.

Flex LA’s and Flex Riverside’s Contributions to RPS Goals

Appendix C VII.F/VII.G RPS Contracts

V.C LSE Total Energy Forecast – Bundled Customer

RPS contracts confidential for three years, or until one year following expiration, whichever comes first.

LSE total energy forecast – bundled customer front three years of forecast data confidential.

A-2

Project Viability Matrices for the FlexEnergy Contracts

Appendix E VII.H Score sheets, analyses, evaluations of proposed RPS projects

Score sheets, analyses, evaluations of proposed RPS projects confidential for three years.

CEC-SEP Pricing Worksheets for FlexEnergy

Appendix F VII.F/VII.G RPS Contracts

VII.H Score sheets, analyses, evaluations of proposed RPS projects

RPS contracts confidential for three years, or until one year following expiration, whichever comes first.

Score sheets, analyses, evaluations of proposed RPS projects confidential for three years.

Flex LA Contract Appendix G VII.F RPS Contracts

RPS contracts confidential for three years, or until one year following expiration, whichever comes first.

Flex Riverside Contract

Appendix H VII.G RPS Contracts

RPS contracts confidential for three years, or until one year following expiration, whichever comes first.

Appendix B

Confidential Contract Summary

Confidential Protected Materials – Public Disclosure Prohibited

Appendix C

FlexEnergy’s Contributions to RPS Goals

Confidential Protected Materials – Public Disclosure Prohibited

Appendix D

SCE’s RPS Bid Evaluation and Selection Process and Criteria

D-1

SCE’s Written Description of RPS Bid Evaluation and Selection Process and Criteria (“LCBF Written Report”)

I. Introduction

A. Note relevant language in statute and CPUC decisions approving LCBF process and requiring LCBF Reports Under the direction of the California Public Utilities Commission (the “Commission”), SCE conducts annual solicitations for the purpose of procuring power from eligible renewable resources to meet California’s Renewables Portfolio Standard (“RPS”). SCE evaluates and ranks proposals based on least-cost/best-fit principles (“LCBF”) that comply with criteria set forth by the Commission in D.03-06-071 and D.04-07-029 (“LCBF Decisions”). See also Pub. Util. Code Section 399.14(a)(2)(B).

B. Goals of bid evaluation and selection criteria and processes The LCBF analysis evaluates both quantitative and qualitative aspects of each proposal to estimate its value to SCE’s customers and relative value in comparison to other proposals.

II. Bid Evaluation and Selection Criteria

While assumptions and methodologies have evolved slightly over time, the basic components of SCE’s evaluation and selection criteria and process for RPS contracts were established in the Commission’s LCBF Decisions. The three main steps that are undertaken by SCE are an initial data gathering period, followed by a quantitative assessment of proposals, ending with adjustments to selection based on qualitative attributes of proposals. Prior to receiving proposals, SCE finalizes major assumptions and methodologies that drive valuation, including power and gas prices forecasts, existing and forecast resource portfolio, and firm capacity value forecast. Other assumptions, such as the Transmission Ranking Cost Report (“TRCR”), are filed with the Commission for approval prior to the release of the solicitation materials. In addition, SCE gathers the current input assumptions that are developed by external parties, such as the integration costs set by the California Energy Commission (“CEC”). Once proposals are received, SCE begins an initial review for completeness, conformance, and viability. The review includes a screen for reasonableness of proposal parameters, such as generation profiles and capacity factors. SCE works directly with bidders to resolve any issues and ensure data is ready for evaluation. After this initial review, SCE performs the quantitative assessment of each proposal individually. The result of the quantitative analysis is a relative ranking of proposals that helps define the preliminary short list. Qualitative attributes of each proposal are then considered to further screen the short list and determine tie-breakers, if needed, to arrive at a final short list of proposals.

D-2

After this analysis, SCE consults with its Procurement Review Group (“PRG”) regarding its final short list and specific evaluation criteria. Whether a proposal selected in this process results in an executed contract depends on how negotiations proceed. Periodically, SCE updates the PRG regarding the progress of negotiations and also reviews contracts with the PRG prior to execution. Subsequently, SCE executes contracts and submits them to the Commission for approval via advice letter filing.

A. Description of Criteria

1. List and discuss the quantitative and qualitative criteria used to evaluate and select bids. This section should include a full discussion of the following:

Quantitative Assessment

SCE evaluates the quantifiable attributes of each proposal individually and subsequently ranks them based on their benefit-to-cost ratio. The benefit-to-cost ratio used in the LCBF evaluation is different than a typical benefit-to-cost ratio, which would usually represent net benefits or value divided by the project cost. In the context of LCBF evaluation, the benefit-to-cost ratio measures total benefits divided by total costs because there is no readily cognizable “project cost” for these proposals. Benefits are comprised of separate capacity and energy components, while costs include the contract price, integration costs, transmission cost, and debt equivalence. SCE discounts the annual benefit and cost streams to a common base year prior to calculating the benefit-to-cost ratio for each proposal.

eEquivalencDebt Cost onTransmissi Cost nIntegratio PaymentsBenefit Energy Benefit Capacity Ratio C-B

++++=

In developing its relative ranking of proposals, SCE’s evaluation methodology incorporates information provided by sellers and assumptions prescribed and set by the CPUC and CEC, with its internal methodologies and forecasts of market conditions. The objective of the quantitative assessment and relative ranking is to develop a preliminary short list that is further refined based on the non-quantifiable attributes discussed below. Each of the elements for the RPS benefit-to-cost ratio is described briefly below.

Capacity Benefit

Each proposal is assigned capacity benefits based on SCE’s forecast of capacity value and a technology-specific effective load carrying capability (“ELCC”). SCE’s capacity value forecast consists of a market view for the first two years and a combustion turbine (“CT”) proxy thereafter. The market view of capacity is derived from current broker quotes for SP15 power using a Black’s option model. The CT proxy is based on the annual deferral value of a General Electric 7FA simple-cycle combustion turbine. ELCC values are established by the CEC’s Renewable Generation Integration Cost Analysis (“RGICA”). Annual capacity benefits are the product of SCE’s firm capacity value

D-3

forecast, the total proposed capacity of the project, and the ELCC. For partial years, the capacity value is distributed throughout the year according to SCE’s relative loss-of-load probability factors.

Energy Benefit

SCE measures the energy benefits of a proposal by evaluating its effect on the total production cost of SCE’s forecasted resource portfolio to serve its bundled customer load. The evaluation of energy benefits is performed with a portfolio and system that is consistent with SCE’s most recently approved Long-Term Procurement Plan (“LTPP”), with some updates to account for the latest gas price and load forecasts and the results of recent procurement activities.

SCE uses Global Energy Decisions’ ProSym model to compare the total production costs of SCE’s base resource portfolio (“project out”) with the total production costs when each proposal is individually added to the base portfolio (“project in”). ProSym performs an hourly, least-cost dispatch with SCE’s known resource portfolio and generic generation (Because SCE’s complete resource portfolio in the future is uncertain, generic generation is added to the portfolio to ensure that RPS and resource adequacy requirements are satisfied and customer load can be met) to meet customer demand. Each proposal is added to the resource portfolio as a no-cost, must-take hourly generation profile that is provided by the seller. The difference in total production costs between the “project in” and “project out” cases is the energy benefit for each proposal.

SCE’s resource portfolio is dispatched against an SP15 power price forecast. For proposals of out-of-area resources, additional congestion charges may be added to the cost of delivering the energy depending on the power price forecast of the originating area relative to SP15 power prices. SCE’s power and gas price forecasts are both based on a near-term market view and a longer-term fundamental view of prices.

The simulation model, and hence the energy benefit calculation, captures additional quantitative effects that SCE has been asked to consider by the CPUC, including dispatchability and curtailability. The benefits of these characteristics are rolled into the energy benefit and are not addressed separately.

Debt Equivalence

Debt equivalence, the term used by credit rating agencies to describe the fixed financial obligation resulting from long-term purchased power contracts, can have significant effects on credit quality and cost of borrowing. The CPUC has recognized this cost and ordered it to be used in evaluation of proposals in RPS solicitations. Consistent with D.04-12-048, SCE utilizes a modified Standard & Poor’s methodology that employs a 20% risk factor. In cases in which contracts only include energy payments, as with RPS contracts, SCE will use credit agency guidance to determine the percentage of payments that are equivalent to capacity payments and calculate debt equivalence accordingly.

D-4

a. Market valuation (i.e. price) The primary costs associated with each proposal are the payments that SCE pays to sellers for the expected renewable energy deliveries under the terms of the contracts. Proposals include an all-in price for delivered renewable energy, which is adjusted in each time-of-delivery period by energy payment allocation factors (“TOD factors”). SCE develops and submits its TOD factors for each solicitation to the CPUC for approval prior to the issuance of the RFP. The total payments are then determined using the generation profile provided in the proposal and adjusted for electric energy loss factors (to calculate the scheduled amount of electric energy).

- include treatment of integration costs Integration costs are the additional system costs required to provide load following and regulation as a result of integrating various resources. As per D.04-07-029 and clarified in D.07-02-011, the integration cost adder for all proposals is zero.

- include treatment of dispatchability/curtailability benefits Dispatchability and curtailability are both attributes that are incorporated into the production simulations used to evaluate the energy benefits. Any proposal received with such characteristics would be modeled as such and the energy benefits would capture the qualitative benefit. SCE has not received any proposals with dispatchability or curtailability attributes in any of its RPS solicitations to date.

b. Portfolio fit SCE’s LCBF quantitative evaluation process inherently captures the impact of portfolio fit. For example, as different proposals are added to the overall portfolio, the resultant residual net short or net long is impacted. Projects that more often increase SCE’s net long positions are assigned less value than those projects that are more often filling net short positions. As such, a project that provides more energy when it is most needed and less energy in periods of low need will receive the greatest energy benefit.

c. Credit and collateral requirements SCE requests that bidders provide pricing for a number of defined collateral levels. For the purposes of the LCBF ranking process, a common collateral point is chosen by SCE by which to evaluate all of the projects. While other considerations are incorporated when determining which collateral point is eventually chosen for individual projects, SCE uses the common point to determine the pricing that is used for ranking purposes.

d. Transmission Cost Adders System transmission upgrades costs are estimated using SCE’s TRCR for resources that do not have an existing interconnection to the electric system or a completed Facilities Study. TRCRs are published prior to the release of the solicitation and are based only on responses to a request for

D-5

prospective/potential bids. Transmission cost adders for new generation are assigned by cluster, or regions, and are based on standard off-the-shelf unit cost guides. Proposals received in the actual solicitation that do not fit into the clusters defined by the TRCR will have adders developed using the same methodology as was used in the original TRCR.

- Discuss how much detailed transmission cost information the IOU requires for each project

Other than the assumptions provided in a bidder’s proposal, SCE does not require additional transmission information, unless the bidder has completed a feasibility study. If a feasibility study has been completed then the bidder must provide the results.

- Discuss whether cost adders are always imputed for projects in transmission-constrained areas, or whether and how costs for alternative commercial transactions (i.e., swapping, remarketing) are substituted.

SCE uses the best available information it can find when determining the cost of potential upgrades for projects in transmission-constrained areas. For those projects whose transmission upgrade costs cannot be determined from SCE’s TRCR, the TRCRs of PG&E or SDG&E are used as appropriate. SCE applies the required upgrade costs to get the project delivered to the nearest defined market (e.g., NP15, SP26, etc.). For projects with an assumed delivery point outside SP26, SCE applies a power swapping methodology, where the power is assumed to be sold into the local market with replacement power purchased in SP26.

Qualitative Assessment (including Project Viability)

In addition to the identified benefits and costs that are quantified in the evaluation, SCE assesses non-quantifiable characteristics of each proposal. These qualitative attributes are used to consider the inclusion of additional sellers on the short list due to: (a) the strength of particular seller’s proposal; or (b) the relative weakness of the high ranked proposals.

The attributes that SCE considers include, but are not limited to: (a) extent of Seller’s mark-up of SCE’s pro forma agreement; (b) project viability; (c) status of project development efforts; (d) timing and progress towards gaining access to transmission; (e) technology viability; (f) technology and economic viability; and (g) seller’s capability to perform all of its financial and other obligations under the pro forma agreement.

Where there are weaknesses in some of these factors, SCE utilizes additional contract requirements to manage these issues during the development of the project.

In addition, SCE assesses additional non-quantifiable characteristics of each proposal that are used to determine tie-breakers.

The attributes that SCE considers include, but are not limited to: (a) environmental impacts of seller’s proposed project on California’s water quality and use; (b) resource

D-6

diversity; (c) benefits to minority and low income communities; (d) local reliability; and (e) environmental stewardship.

Pursuant to D.04-07-029, the presence of demonstrated qualitative attributes may justify moving a proposal onto SCE’s final short list of proposals if (a) the initial proposal rank is within reasonable valuation proximity to those selected for the short list and (b) SCE receives support from its PRG to elevate the proposal based on qualitative factors.

f. Impact of quantitative and qualitative factors on the LCBF ranking process

SCE evaluates the quantifiable attributes of each proposal individually and subsequently ranks them based on their benefit-to-cost ratio. The benefit-to-cost ratio used in the LCBF evaluation is different than a typical benefit-to-cost ratio, which would usually represent net benefits or value divided by the project cost. In the context of LCBF evaluation, the benefit-to-cost ratio measures total benefits divided by total costs because there is no readily cognizable “project cost” for these proposals. Benefits are comprised of separate capacity and energy components, while costs include the contract price, integration costs, transmission cost, and debt equivalence. SCE discounts the annual benefit and cost streams to a common base year prior to calculating the benefit-to-cost ratio for each proposal.

eEquivalencDebt Cost onTransmissi Cost nIntegratio PaymentsBenefit Energy Benefit Capacity Ratio C-B

++++=

SCE also assesses non-quantifiable characteristics of each proposal. Qualitative attributes of each proposal are considered to further screen the short list and determine tie-breakers to arrive at a final short list of proposals.

B. Criteria Weightings

1. If a weighting system is used, please describe how each LCBF component is assigned a quantitative or qualitative weighting compared to other components. Discuss the rationale for the weightings. SCE does not apply a weighing system in its LCBF evaluation. 2. If a weighting system is not used, please describe how the LCBF evaluation criteria are used to rank bids. SCE’s LCBF quantitative evaluation of the bids incorporates energy and capacity benefits with energy payments, transmission & integration costs, and debt equivalence to create individual benefit-to-cost ratios. It is this benefit-to-cost ratio that is used to rank and compare each project. Qualitative attributes of each proposal are then considered to

D-7

further screen the short list and determine tie-breakers to arrive at a final short list of proposals. 3. Discuss how the IOU LCBF methodology evaluates project commercial operation date relative to transmission upgrades required for the project. SCE starts its evaluation with the assumption that the proposed online date for the project is correct and that any transmission upgrades will be complete in accordance with the schedule. For those projects which SCE has concerns over the viability of the timeframe, a range of online dates (and transmission facilities availability) are evaluated to determine the sensitivity of the results to the timing. If the project ranking does not change in a manner that would change its original selection status over a range that SCE deems reasonable, then the original assessment is used. For projects whose selection is dependent on the timing of the project and the availability of upgraded transmission facilities, further analysis of the timing of the projects is required. SCE has not experienced the latter situation in any of its solicitations to date. 4. Discuss how the LCBF methodology takes into account bids that may be more expensive, but have a high likelihood of resulting in viable projects. SCE’s LCBF methodology incorporates project viability in a qualitative assessment after the preliminary ranking of bids has been completed and in determining the size of the shortlist. Bids that are more expensive tend to be lower on the quantitative ranking of projects, and, therefore, often fall near the projects cut-point. SCE errs on the side of inclusiveness in the selection of its final shortlist. For projects with a high likelihood of resulting in viable projects that lie just below, the cut-point may be adjusted or the projects may be included in the final shortlist.

C. Evaluation of utility-owned, turnkey, buyouts, and utility-affiliate projects

1. Describe how utility-owned projects are evaluated against PPAs SCE views utility-owned cost-of-service generation as a good option for customers to have. SCE does not intend to evaluate utility-owned projects against PPAs, as utility-owned generation and contracted-for generation are fundamentally different products. As such, any attempt to do a numerical comparison of them is unworkable. This topic is discussed in detail in the Supplemental Testimony to SCE’s 2006 Long-term Procurement Plan (Section I.B, pgs 2-5). Moreover, approval of a utility-owned project would not be submitted through the solicitation process, but through a formal application. 2. Describe how turnkey projects are evaluated against PPAs Turnkey projects are similar to utility-owned projects. Refer to response above.

D-8

3. Describe how buyout projects are evaluated against PPAs Project buyout options are essentially a hybrid of utility-owned projects and PPAs. Refer to response above. 4. Describe how utility-affiliate projects are evaluated against non-affiliate projects Utility-affiliate projects are evaluated in the same manner as non-affiliate projects. In addition, evaluation of utility affiliate projects would be subject to review by the independent evaluator, the PRG, and the Commission through the application approval process.

III. Bid Evaluation and Selection Process

A. What is the process by which bids are received and evaluated, selected or rejected for shortlist inclusion, and further evaluated once on the shortlist? See above.

B. What is the typical amount of time required for each part of the process? It takes approximately eight weeks for SCE to complete the LCBF evaluation process, which includes quality control of bidders’ information, transmission assessment, quantitative assessment, qualitative assessment, management review, and PRG meetings. Many of these events overlap and may require additional time for clarification from sellers.

C. How is the size of the shortlist determined? The size of SCE’s shortlist is determined largely by an assessment of the attractiveness of RPS-eligible energy bids and a desire for a robust, inclusive set of developer proposals. The shortlist is expanded well beyond the point that is needed for SCE to meet its RPS goals, as there is an expectation that some projects that are selected will not join the shortlist and that negotiations will not be successful with some sellers that are initially on the shortlist.

D. Are rejected bidders told why they were rejected? If so, what is the process? Yes. Bidders are informed verbally over the phone and in writing by letter.

E. Describe involvement of the Independent Evaluator The independent evaluator monitors SCE’s RPS solicitations, provides an independent evaluation of SCE’s process and the proposals it may receive, and helps the Commission and SCE’s PRG participants by providing them with information and assessments to ensure that the solicitation was conducted fairly and that the best resources were acquired. The independent evaluator also provides an assessment of SCE’s RPS solicitation from the initial phase of the solicitation (i.e., the publicizing of the issuance of the RFP) through the development of a short list of proposals/bidders with whom SCE has commenced negotiations.

F. Describe involvement of the Procurement Review Group SCE consults with its PRG during each step of the renewable procurement process. Among other things, SCE provides solicitation materials and pro forma contracts to the PRG for

D-9

review and comment before commencing the RFP; informs the PRG of the initial results of the RFP; explains the evaluation process; and updates the PRG periodically concerning the status of contract formation.

G. Discuss whether and how feedback on the solicitation process is requested from bidders (both successful and unsuccessful) after the solicitation is complete In 2006, SCE held a conference that solicited feedback regarding SCE’s RFP and contracting process from both successful and unsuccessful bidders.

Appendix E

Project Viability Matrices

Confidential Protected Materials – Public Disclosure Prohibited

Appendix F

CEC-SEP Pricing Worksheets

Confidential Protected Materials – Public Disclosure Prohibited

Appendix G

Power Purchase Agreement between SCE and FlexEnergy (“Flex LA”)

Confidential Protected Materials – Public Disclosure Prohibited

Appendix H

Power Purchase Agreement between SCE and FlexEnergy (“Flex Riverside”)

Confidential Protected Materials – Public Disclosure Prohibited

Appendix I

Proposed Protective Order

- 1 -

BEFORE THE PUBLIC UTILITIES COMMISSION

OF THE STATE OF CALIFORNIA

Submission of Contracts for Procurement of Renewable Energy Resulting From Bilateral Negotiations

)))

Advice 2203-E

PROTECTIVE ORDER

1. Scope. This Protective Order shall govern access to Protected Materials contained in

the confidential version of Advice Letter 2203-E. This Protective Order does not address the

right of employees of the California Public Utilities Commission (“CPUC” or “Commission”)

acting in their official capacities (“Commission Staff”) to view Protected Materials because

Commission Staff are entitled to view Protected Materials in accordance with the requirements

of Section 583 of the Public Utilities Code and the Commission’s General Order 66-C.

2. Modification. This Protective Order shall remain in effect until it is modified or

terminated by the Commission after all affected parties have been given notice and have had a

reasonable opportunity to be heard.

3. Definitions.

A. The term “Protected Material(s)” means (i) trade secret, market sensitive, or other

confidential and/or proprietary information as determined in good faith by the Disclosing Party

in accordance with the provisions of D.06-06-066 and subsequent decisions, General

Order 66-C, Public Utilities Code Sections 583 and 454.5(g), or any other right of confidentiality

provided by law, or (ii) any other materials that are made subject to this Protective Order by the

Assigned Administrative Law Judge (“ALJ”), Law and Motion Administrative Law Judge (“Law

and Motion ALJ”), Assigned Commissioner, the Commission, or any court or other body having

appropriate authority. Protected Materials also includes memoranda, handwritten notes,

spreadsheets, computer files and reports, and any other form of information (including

- 2 -

information in electronic form) that copies, discloses, or compiles other Protected Materials or

from which such materials may be derived. Protected Materials do not include: (i) any

information or document contained in the public files of the CPUC or any other state or federal

agency, or in any state or federal court, unless such information or document has been

determined to be protected by such agency or court; or (ii) any information that is public

knowledge, or which becomes public knowledge, other than through disclosure in violation of

this Protective Order or any other protective order.

B. The term “redacted” refers to situations in which Protected Materials in a document,

whether the document is in paper or electronic form, have been covered, blocked out, or

removed. The term “unredacted” refers to situations in which the Protected Materials in a

document, whether in paper or electronic form, have been shaded but not covered, blocked out,

or removed.

C. The term “Disclosing Party” means a party who initially discloses any specified

Protected Materials in this proceeding.

D. The term “Market Participant” (“MP”) refers to a party that is:

1) A person or entity, or an employee of an entity, that engages in the wholesale purchase, sale or marketing of energy or capacity, or the bidding on or purchasing of power plants, or bidding on utility procurement solicitations, or consulting on such matters, subject to the limitations in 3) below.

2) A trade association or similar organization, or an employee of such organization,

a) whose primary focus in proceedings at the Commission is to advocate for persons/entities that purchase, sell or market energy or capacity at wholesale; bid on, own, or purchase power plants; or bid on utility procurement solicitations; or

b) a majority of whose members purchase, sell or market energy or capacity at wholesale; bid on, own, or purchase power plants; or bid on utility procurement solicitations; or

c) formed for the purpose of obtaining market sensitive information; or

- 3 -

d) controlled or primarily funded by a person or entity whose primary purpose is to purchase, sell or market energy or capacity at wholesale; bid on, own, or purchase power plants; or bid on utility procurement solicitations.

3) A person or entity that meets the criteria of 1) above is nonetheless not a market participant for purpose of access to market sensitive data unless the person/entity seeking access to market sensitive information has the potential to materially affect the price paid or received for electricity if in possession of such information. An entity will be considered not to have such potential if:

a) the person or entity’s participation in the California electricity market is de minimis in nature. In the resource adequacy proceeding (R.05-12-013) it was determined in D.06-06-064 § 3.3.2 that the resource adequacy requirement should be rounded to the nearest megawatt (MW), and load serving entities (LSEs) with local resource adequacy requirements less than 1 MW are not required to make a showing. Therefore, a de minimis amount of energy would be less than 1 MW of capacity per year, and/or an equivalent of energy; and/or

b) the person or entity has no ability to dictate the price of electricity it purchases or sells because such price is set by a process over which the person or entity has no control, i.e., where the prices for power put to the grid are completely overseen by the Commission, such as subject to a standard offer contract or tariff price. A person or entity that currently has no ability to dictate the price of electricity it purchases or sells under this section, but that will have such ability within one year because its contract is expiring or other circumstances are changing, does not meet this exception; and/or

c) the person or entity is a cogenerator that consumes all the power it generates in its own industrial and commercial processes, if it can establish a legitimate need for market sensitive information.

E. A Market Participant’s Reviewing Representatives are limited to persons designated

by the Market Participant who meet the following criteria:

1. Are outside experts, consultants or attorneys;

2. Are not currently engaged, directly or indirectly, in (a) the purchase, sale, or marketing of electrical energy or capacity or natural gas (or the direct supervision of any employee(s) whose duties include such activities), (b) the bidding on or purchasing of power plants (or the direct supervision of any employee(s) whose duties include such activities), or (c) consulting with or advising

- 4 -

others in connection with any activity set forth in subdivisions (a) or (b) above (or the direct supervision of any employee(s) whose duties include such activities or consulting); and

3. Are not an employee of a market participant.

F. Persons or entities that do not meet the definition of market participant are non-market

participants (“NMPs”), and may have access to market sensitive information through their

designated Reviewing Representatives. Any NMP Reviewing Representative who is

simultaneously representing a Market Participant in other proceedings before the Commission

shall disclose such representation to the Disclosing Party. If the Disclosing Party objects to

reviewing representative status for such person, the Disclosing Party shall bring the matter before

the Presiding Administration Law Judge for resolution within ten (10) days.

H. All Reviewing Representatives are required to execute a non-disclosure agreement

and are bound by the terms of this Protective Order.

4. Designation of Materials.

When filing or providing in discovery any documents containing Protected Materials, a

party shall physically mark such documents on each page (or in the case of non-documentary

materials such as computer diskettes, on each item) as “PROTECTED MATERIALS SUBJECT

TO PROTECTIVE ORDER,” or with words of similar import as long as one or more of the

terms, “Protected Materials,” “Protective Order,” “Section 583” or “General Order No. 66-C” is

included in the designation to indicate that the materials in question are protected.

All materials so designated shall be treated as Protected Materials unless and until (a) the

designation is withdrawn pursuant to Paragraph 17 hereof, or (b) there is a determination

pursuant to Paragraph 4 hereof changing the designation and a period of 14 calendar days has

elapsed without an appeal or other challenge to the determination pending.

All documents containing Protected Materials that are filed with the Commission or

served shall be placed in sealed envelopes or otherwise appropriately protected and shall be

- 5 -

endorsed to the effect that they are filed or served under seal pursuant to this Protective Order.

Such documents shall be served upon Reviewing Representatives and persons employed by or

working on behalf of the state governmental agencies referred to in Paragraphs 11(a), 11(b) and

11(c) hereof who are eligible and have requested to review such materials. Service upon the

persons specified in the foregoing sentence may either be (a) by electronic mail in accordance

with the procedures adopted in this proceeding, (b) by facsimile, or (c) by overnight mail or

messenger service. Whenever service of a document containing Protected Materials is made by

overnight mail or messenger service, the Assigned ALJ shall be served with such document by

hand on the date that service is due.

5. Redaction of Documents. Whenever a party files or provides in discovery a document

that includes Protected Materials (including but not limited to briefs, testimony, exhibits, and

responses to data requests), such party shall also prepare a redacted version of such document.

The redacted version shall enable persons familiar with this proceeding to determine with

reasonable certainty the nature (but not magnitude) of the data that has been redacted and where

the redactions occurred. The redacted version of a document to be filed shall be served on all

persons on the service list, and the redacted version of a discovery document shall be served on

all persons entitled thereto.

6. Selection of Reviewing Representatives. Each MP and NMP selecting a Reviewing

Representative shall first identify its proposed Reviewing Representative to all other parties and

the Division Director and shall provide all parties with a curriculum vitae of each candidate,

including a brief description of the candidate’s professional experience and past and present

professional affiliations for the last 10 years. Any party who objects to a proposed Reviewing

Representative shall advise the proposing party in writing within five (5) business days from

receipt of such notice, setting forth in detail the reasons therefor. In the event of such objection,

the proposing party, the objecting party or parties, and the Division Director shall promptly meet

and confer to try to resolve the issue, and if necessary seek a ruling from either the Assigned ALJ

- 6 -

or the Law and Motion ALJ. In ruling on the motion, the Assigned ALJ or the Law and Motion

ALJ shall consider all relevant facts, including whether the proposed Reviewing Representative

has a need to know the information in the Protected Materials to prove or defend against a

material element of one or more issues presented in this proceeding, and whether it is reasonable

to conclude that the information sought by the Reviewing Representative is essential to a fair

resolution of an issue in this proceeding. If a party desires to designate a Reviewing

Representative who has previously been approved for that status in a prior Commission

proceeding and that person’s professional responsibilities have not changed since the prior

designation, the party need not repeat the process described above unless the Disclosing Party

raises an objection to the person’s selection as a Reviewing Representative, in which case the

proposing party, the objecting party, and the Division Director shall promptly meet and confer to

try to resolve the issue, and if necessary follow the remaining steps set forth above.

7. Access to Protected Materials and Use of Protected Materials. Subject to the terms of

this Protective Order, Reviewing Representatives shall be entitled to access to Protected

Materials. All other parties shall not be granted access to Protected Materials, but shall instead

be limited to reviewing redacted versions of documents. Reviewing Representatives may make

copies of Protected Materials, but such copies become Protected Materials. Reviewing

Representatives may make notes of Protected Materials, which shall be treated as Notes of

Protected Materials if they disclose the contents of Protected Materials. Protected Materials

obtained by a party in this proceeding may also be requested by that party in a subsequent

Commission proceeding, subject to the terms of any protective order governing that subsequent

proceeding, without constituting a violation of this order.

8. Maintaining Confidentiality of Protected Materials. Each Reviewing Representative

shall treat Protected Materials as confidential in accordance with this Protective Order and the

Non-Disclosure Certificate executed pursuant to Paragraph 6 and 7 hereof. Protected Materials

shall not be used except as necessary for the resolution of the advice letter filing, and shall not be

disclosed in any manner to any person except (i) Reviewing Representatives who have executed

- 7 -

Non-Disclosure Certificates; (ii) Reviewing Representatives’ paralegal employees and

administrative personnel, such as clerks, secretaries, and word processors, to the extent necessary

to assist the Reviewing Representatives, provided that they shall first ensure that such personnel

are familiar with the terms of this Protective Order, and have signed a Non-Disclosure

Certificate, (iii) persons employed by or working on behalf of the CEC or other state

governmental agencies covered by Paragraph 12. Reviewing Representatives shall adopt

suitable measures to maintain the confidentiality of Protected Materials they have obtained

pursuant to this Protective Order, and shall treat such Protected Materials in the same manner as

they treat their own most highly confidential information. Reviewing Representatives shall be

liable for any unauthorized disclosure or use by their paralegal employees or administrative staff.

In the event any Reviewing Representative is requested or required by applicable laws or

regulations, or in the course of administrative or judicial proceedings (in response to oral

questions, interrogatories, requests for information or documents, subpoena, civil investigative

demand or similar process) to disclose any of Protected Materials, the Reviewing Representative

shall oppose disclosure on the grounds that the requested information has already been

designated by the Commission as Protected Materials subject to this Protective Order lawfully

issued by the Commission and therefore may not be disclosed. The Reviewing Representative

shall also immediately inform the Disclosing Party of the request, and such party may, at its sole

discretion and cost, direct any challenge or defense against the disclosure requirement, and the

Reviewing Representative shall cooperate in good faith with such party either to oppose the

disclosure of the Protected Materials consistent with applicable law, or to obtain confidential

treatment of them by the person or entity who wishes to receive them prior to any such

disclosure. If there are multiple requests for substantially similar Protected Materials in the same

case or proceeding where a Reviewing Representative has been ordered to produce certain

specific Protected Materials, the Reviewing Representative may, upon request for substantially

similar materials by another person or entity, respond in a manner consistent with that order to

those substantially similar requests.

- 8 -

9. Exception for California Independent System Operator (ISO). Notwithstanding any

other provision of this Protective Order, with respect to an ISO Reviewing Representative only,

participation in the ISO’s operation of the ISO-controlled grid and in its administration of the

ISO-administered markets, including, but not limited to, markets for ancillary services,

supplemental energy, congestion management, and local area reliability services, shall not be

deemed to be a violation of this Protective Order.

10. Non-Disclosure Certificates. A Reviewing Representative shall not inspect,

participate in discussions regarding, or otherwise be granted access to, Protected Materials unless

and until he or she has first completed and executed a Non-Disclosure Certificate, attached

hereto as Appendix A, and delivered the original, signed Non-Disclosure Certificate to the

Disclosing Party. The Disclosing Party shall retain the executed Non-Disclosure Certificates

pertaining to the Protected Materials it has disclosed and shall promptly provide copies of the

Non-Disclosure Certificates to Commission Staff upon request.

11. Return or Destruction of Protected Materials. Protected Materials shall remain

available to Reviewing Representatives until the later of the date that a letter or resolution

resolving this advice letter becomes no longer subject to judicial review, or the date that any

other Commission proceeding relating to the Protected Material is concluded and no longer

subject to judicial review. If requested to do so in writing after that date, the Reviewing

Representatives shall, within fifteen days of such request, return the Protected Materials

(including Notes of Protected Materials) to the Participant that produced them, or shall destroy

the materials, except that copies of filings, official transcripts and exhibits in this proceeding that

contain Protected Materials, and Notes of Protected Material may be retained, if they are

maintained in accordance with Paragraph 7. Within such time period each Reviewing

Representative, if requested to do so, shall also submit to the Disclosing Party an affidavit stating

that, to the best of its knowledge, all Protected Materials and all Notes of Protected Materials

have been returned or have been destroyed or will be maintained in accordance with Paragraph 7.

To the extent Protected Materials are not returned or destroyed, they shall remain subject to the

- 9 -

Protective Order, Section 583 of the California Public Utilities Code and CPUC General Order

No. 66-C. In the event that a Reviewing Representative to whom Protected Material are

disclosed ceases to be engaged to provide services in this proceeding, or ceases to be eligible for

Reviewing Representative status pursuant to Paragraph 3.E., then access to such materials by that

person shall be terminated. Even if no longer engaged in this proceeding and/or no longer

eligible for Reviewing Representative status, every such person shall continue to be bound by the

provisions of this Protective Order and the Non-Disclosure Certificate.

12. Access and Use by Governmental Entities.

(a) In the event the CPUC receives a request from the CEC for a copy of or access to any

party’s Protected Materials, the procedure for handling such requests shall be as follows. Not

less than five (5) days after delivering written notice to the Disclosing Party of the request, the

CPUC shall release such Protected Materials to the CEC upon receipt from the CEC of an

Interagency Information Request and Confidentiality Agreement (“Interagency Confidentiality

Agreement”). Such Interagency Confidentiality Agreement shall (i) provide that the CEC will

treat the requested Protected Materials as confidential in accordance with this Protective Order,

(ii) include an explanation of the purpose for the CEC’s request, as well as an explanation of how

the request relates to furtherance of the CEC’s functions, (iii) be signed by a person authorized to

bind the CEC contractually, and (iv) expressly state that furnishing of the requested Protected

Materials to employees or representatives of the CEC does not, by itself, make such Protected

Materials public. In addition, the Interagency Confidentiality Agreement shall include an

express acknowledgment of the CPUC’s sole authority (subject to judicial review) to make the

determination whether the Protected Materials should remain confidential or be disclosed to the

public, notwithstanding any provision to the contrary in the statutes or regulations applicable to

the CEC.

(b) In the event the CPUC receives a request for a copy of or access to a party’s

Protected Materials from a state governmental agency other than the CEC that is authorized to

enter into a written agreement sufficient to satisfy the requirements for maintaining

- 10 -

confidentiality set forth in Government Code Section 6254.5(e), the CPUC may, not less than

five (5) days after giving written notice to the Disclosing Party of the request, release such

protected material to the requesting governmental agency, upon receiving from the requesting

agency an executed Interagency Confidentiality Agreement that contains the same provisions

described in Paragraph 10(a) above.

(c) The CEC may use Protected Materials when needed to fulfill its statutory

responsibilities or cooperative agreements with the CPUC. Commission confidentiality

designations will be maintained by the CEC in making such assessments, and the CEC will not

publish any assessment that directly reveals the data or allows the data submitted by an

individual load serving entity (“LSE”) to be “reverse engineered.”

13. CPRA Requests. If a request is made pursuant to the California Public Records Act

(“CPRA”), Government Code sections 6250, et seq., that a party’s Protected Materials filed with

or otherwise in the possession of the CPUC be produced, the CPUC will notify such party of the

CPRA request. The CPUC also will notify the requester that the Protected Materials are public

records that have been filed with or submitted to the CPUC accompanied by a claim that they are

confidential and/or that there is a public interest served by withholding the records. The CPUC

will thereafter proceed to determine, pursuant to applicable law, whether the requested Protected

Materials are excluded from public inspection. In the event the CPUC receives a request from a

federal government agency or a judicial subpoena for the production of a party’s Protected

Materials in the CPUC’s possession, the CPUC will also notify the Disclosing Party of such

request. In the event that a PRA requester brings suit to compel disclosure of a party’s Protected

Materials, the CPUC will promptly notify the Disclosing Party of such suit, and Commission

Staff and the Disclosing Party shall cooperate in opposing the suit.

14. Derivative Materials. There shall be a rebuttable presumption that (a) any study that

incorporates, describes or otherwise employs Protected Materials in a manner that could reveal

all of a part of such materials, or (b) any model that relies upon Protected Materials for

algorithms or other computation(s) critical to the functioning of the model, are Protected

- 11 -

Materials that are subject to Section 583 of the Public Utilities Code, the Commission’s General

Order 66-C, and this Protective Order. However, models that merely use Protected Materials as

inputs will not themselves be considered Protected Materials. There shall also be a rebuttable

presumption that where the inputs to studies or models include Protected Materials, or where the

outputs of such studies or models reveal such inputs or can be processed to reveal such materials,

such inputs and/or outputs shall be considered Protected Materials subject to this Protective

Order, unless such inputs and/or outputs have been redacted or aggregated to the satisfaction of

the Disclosing Party. Unless a party, by means of notice and motion, obtains a ruling from the

Assigned ALJ or the Law and Motion ALJ holding that the applicable presumption(s) from

among the foregoing has been rebutted with respect to the model or study at issue, then any party

who devises or propounds a model or study that incorporates, uses or is based upon such

materials shall label the model or study “Protected Materials,” and it shall be subject to the terms

of this Protective Order.

15. Dispute Resolution. All disputes that arise under this Protective Order, including but

not limited to alleged violations of this Protective Order and disputes concerning whether

materials were properly designated as Protected Materials, shall be presented for resolution to the

Assigned ALJ or the Law and Motion ALJ. Prior to presenting any such dispute to the

applicable ALJ, the parties to the dispute shall use their best efforts to resolve it. The parties and

Commission Staff reserve the right to seek additional administrative or judicial remedies after

the Assigned ALJ or the Law and Motion ALJ has made a ruling regarding the dispute.

16. Other Objections to Use or Disclosure. Nothing in this Protective Order shall be

construed as limiting the right of a party, the Commission Staff, or a state governmental agency

covered by Paragraph 10 10(a), 10(b) and 10(c) from objecting to the use or disclosure of

Protected Material on any legal ground, such as relevance or privilege.

17. Remedies. Any violation of this Protective Order shall constitute a violation of an

order of the CPUC. Notwithstanding the foregoing, the parties and Commission Staff reserve

- 12 -

their rights to pursue any legal or equitable remedies that may be available in the event of an

actual or anticipated disclosure of Protected Materials.

18. Withdrawal of Designation. A Disclosing Party may agree at any time to remove the

“Protected Materials” designation from any materials of such party if, in its opinion,

confidentiality protection is no longer required. In such a case, the Disclosing Party will notify

all other parties that the Disclosing Party believes are in possession of such materials of the

change of designation.

- 13 -

19. Interpretation. Titles are for convenience only and may not be used to restrict the

scope of this Protective Order.

Entered: __________________________________

Administrative Law Judge

Date: __________________________________

APPENDIX A TO PROTECTIVE ORDER

BEFORE THE PUBLIC UTILITIES COMMISSION

OF THE STATE OF CALIFORNIA Submission of Contracts for Procurement of Renewable Energy Resulting From Bilateral Negotiations

)))

Advice 2203-E

NON-DISCLOSURE CERTIFICATE

I hereby certify my understanding that access to Protected Materials is provided to me pursuant to the terms and restrictions of the Protective Order in this proceeding, that I have been given a copy of and have read the Protective Order, and that I agree to be bound by it. I understand that the contents of the Protected Materials, any notes or other memoranda, or any other form of information that copies or discloses Protected Materials shall not be disclosed to anyone other than in accordance with that Protective Order. I acknowledge that a violation of this certificate constitutes a violation of an order of California Public Utilities Commission.

By: _____________________________ Title: ____________________________ Representing: _____________________ Date: ____________________________

1

APPENDIX B TO PROTECTIVE ORDER

INTERAGENCY INFORMATION REQUEST AND CONFIDENTIALITY AGREEMENT BETWEEN THE CALIFORNIA PUBLIC UTILITIES COMMISSION AND THE CALIFORNIA ENERGY RESOURCES

CONSERVATION AND DEVELOPMENT COMMISSION

A. INTERAGENCY INFORMATION REQUEST

The California Energy Resources Conservation and Development Commission (“CEC”) hereby requests the following information from the California Public Utilities Commission (“Commission”) provided to the Commission by [IOU] pursuant to the Order Instituting Rulemaking to Establish Policies and Cost Recovery Mechanisms for Generation Procurement and Renewable Resource Development, issued on October 25, 2001 by the Commission as Rulemaking (R.) 01-10-024:

[List of Information Requested]

[IOU] has provided the above-described data to the Commission and the Commission is treating the data as confidential pursuant to the Public Utilities Code §583.

The CEC declares that it has a need for the above-described data for the following purposes:

1. [to be added] 2. [to be added] 3. [to be added]

The CEC agrees to keep this information confidential in its entirety, disclosing it only to its employees and representatives whose work requires them to review and analyze such data.

2

APPENDIX B B. CONFIDENTIALITY AGREEMENT 1. This agreement is limited to records that are not open to public inspection, that are in the

possession and control of the Commission, and that are identified above.

2. The Commission shall permit the CEC to review and copy the records identified above that are not open to public inspection (“confidential records”), upon the representation of an authorized representative of the CEC that the confidentiality of such records will be maintained and that they will not be made available for inspection by any other governmental agency, or by the public, except as provided for herein.

3. The CEC agrees that the confidential records identified above shall be released only to persons authorized in writing by the person(s) in charge of the CEC to obtain the confidential records, and that the CEC will inform each of its employees, and any consultants or contractors who have access to the confidential records, that they are subject to the requirements of this confidentiality agreement. The CEC shall have each such consultant or contractor sign the attached “acknowledgment” form obligating the consultant or contractor to comply with this agreement. The CEC further agrees that it will require each such consultant or contractor to inform the consultant’s or contractor’s employees that they are subject to this Confidentiality Agreement, and to have each such employee with access to the confidential records sign the attached acknowledgement form. Copies of the signed acknowledgment forms will be provided to the Commission upon request.

4. The CEC shall take reasonable security precautions to keep confidential the records provided to the CEC pursuant to this agreement. The CEC shall notify the Commission immediately upon the discovery of any unauthorized use or disclosure of the confidential records or of any other breach of this agreement, and will cooperate in every reasonable way to help the Commission prevent further unauthorized disclosure or use of the confidential records covered by this agreement.

3

APPENDIX B

5. The Commission reserves its authority under Section 583 of the California Public Utilities Code and General Order 66-C to consider and determine whether the records identified above should be made available for public inspection. The CEC agrees that its Executive Director will not exercise his authority under California Code of Regulations, title 20, section 2507(e), and will not release any confidential records or other documents designated as confidential by the CPUC in R.01-10-024 unless explicitly authorized by the CPUC.

6. In the event the CEC determines for any reason that it is required, or that it would be desirable, to disclose or make available the contents of the confidential records identified above to other governmental agencies or to the public, the CEC agrees not to do so without first notifying the Commission of its intent and the reason for the requested disclosure. The CEC further agrees that such notice shall be given be no less than 20 days prior to the planned disclosure in order that the Commission, the Assigned Commissioner for R.01-10-024, the Assigned Administrative Law Judge (ALJ) for that proceeding or the Law and Motion ALJ, as the case may be, can give adequate consideration, in accordance with Section 583 of the Pubic Utilities Code and the Commission’s General Order 66-C, to the issue of whether it is in the public interest to make such records available to other governmental agencies or to the public. The CEC agrees to abide by the determination of the Commission, the Assigned Commissioner or the applicable ALJ on this issue, but may appeal such determination pursuant to the CPUC’s Rules of Practice and Procedure.

7. With respect to the use of data by the CEC contained in the confidential records subject to this agreement (“confidential data”), it shall be a rebuttable presumption that (i) any study that incorporates, describes or otherwise employs such confidential data in a manner that could reveal all or part of the confidential data, or (ii) any model that relies upon such confidential data for algorithms or other computation(s) critical to the functioning of the model, shall also be considered a confidential record subject to Section 583 of the Public Utilities Code, the Commission’s General Order 66-C, and this agreement. However, models that merely use confidential data as inputs will not themselves be considered such confidential records. It shall also be a rebuttable presumption that where the inputs

4

APPENDIX B

to studies or models include confidential data, or where the outputs of such studies or models reveal the inputs or can be processed to reveal the confidential data, such inputs and/or outputs shall be considered confidential records subject to this agreement, unless such inputs and/or outputs have been redacted or aggregated to the satisfaction of the party producing the confidential records. Any disputes concerning the appropriate scope of redaction or aggregation that the CEC and the party producing the confidential records cannot resolve shall be presented for resolution to the Assigned ALJ for R.01-10-024 or to the Law and Motion ALJ.

8. This agreement shall continue in effect unless or until either of the undersigned parties determines that the agreement should be terminated. Unless otherwise provided for by the written agreement of both the CEC and the Commission, unilateral termination of this agreement shall be effected no sooner than 30 days from the date that either party provides notice, in writing, of its intent to terminate this agreement. All obligations created by this agreement during its term shall survive termination of the agreement.

9. This agreement shall not be modified except by a written agreement dated subsequent to the date of this agreement and signed by authorized representatives of both parties. None of the provisions of this agreement shall be deemed to have been waived by any act or acquiescence on the part of either party, its agents, or employees, but only by an instrument in writing signed by an authorized representative of the party. No waiver of any provisions of this agreement shall constitute a waiver of any other provisions(s) or of the same provision on another occasion.

10. If any provision of this agreement shall be held by a court of competent jurisdiction to be illegal, invalid or unenforceable, the remaining provisions shall remain in full force and effect.

Name General Counsel Position at the CEC: California Public Utilities _______________________ Commission

Dated: Dated:

APPENDIX B

ACKNOWLEDGEMENT AND ACCEPTANCE OF THE REQUIREMENTS OF THE CONFIDENTIALITY AGREEMENT BETWEEN THE CALIFORNIA STATE ENERGY

RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION (CEC) AND THE CALIFORNIA PUBLIC UTILITIES COMMISSION FOR CEC CONSULTANTS AND CONTRACTORS

The Undersigned acknowledges that he/she/it has received copies of the Interagency Information Request and Confidentiality Agreement Between the California Public Utilities Commission (CPUC) and the California Energy Resources Conservation and Development Commission (CEC) dated ___________ (Interagency Confidentiality Agreement), Public Utilities Code Section 583 and CPUC General Order 66-C. The undersigned acknowledges that he/she/it will be subject to the requirements of the Interagency Confidentiality Agreement, and agrees to be bound by the requirements set forth therein. Signed: _______________________ Name ________________________ Title: _________________________ Organization: __________________ Dated: ________________________