1 AJIT KUMAR ED(BD) CURRENT SCENARIO OF POWER GENERATION AND TRANSMISSION IN INDIA

description

CURRENT SCENARIO OF POWER GENERATION AND TRANSMISSION IN INDIA. AJIT KUMAR ED(BD). Agenda. Brief About NTPC Electricity Generation Scenario , Options & Challenges New Technologies Electricity Transmission Scenario of Transmission system Important Initiatives - PowerPoint PPT Presentation

Transcript of AJIT KUMAR ED(BD)

Page 1: AJIT KUMAR ED(BD)

1

AJIT KUMARED(BD)

CURRENT SCENARIO OF POWER GENERATION AND TRANSMISSION IN

INDIA

Page 2: AJIT KUMAR ED(BD)

• Brief About NTPC

• Electricity Generation

• Scenario , Options & Challenges

• New Technologies

• Electricity Transmission

• Scenario of Transmission system

• Important Initiatives

• Indian Power Sector- Challenges and Mitigation

• Conclusion

Agenda

Page 3: AJIT KUMAR ED(BD)

29 MARCH 2010

NTPC LimitedNTPC Limited- - An overviewAn overview

Page 4: AJIT KUMAR ED(BD)

Journey so far

11333

20249

36014

Today

1975NTPC

incorporated (wholly owned by

GoI)

1997

Became a Navratna

Comapany

2004Listed on

Indian Stock

Exchanges(GoI holding

89.5%)

2010• Became a

Maharatna Company

• GOI further divested 5% equity

Shareholding

As on 31.12.2011

11333

20249

39674

Page 5: AJIT KUMAR ED(BD)

NTPC - Stature

5

The Largest Power Generator in the Country

348th largest company in the world (FORBES ranking – 2011)

#1 Independent Power Producer (IPP) in the world (Platts-250 ranking – 2011)

10th largest power generator in the world, 3rd largest in Asia.

One of the largest Indian companies in terms of market cap

Page 6: AJIT KUMAR ED(BD)

20 Joint Ventures and 5 Subsidiaries 20 Joint Ventures and 5 Subsidiaries For Synergistic Business DiversificationFor Synergistic Business Diversification

Group NTPC

Page 7: AJIT KUMAR ED(BD)

Turnaround of Taken-over Power Plants

1978 1992 1995 2000

Page 8: AJIT KUMAR ED(BD)

Commissioned 2490 MW in FY11 – Highest ever in one year.

Commissioned 2660 MW from Apr’12 to Nov’12 IPMA award for Simhadri project in the year 2005.

IPMA award for Vindhyachal project in the year 2008.

IPMA award for Dadri Project Stage-II in the year 2011

Commercial Operation Time in Months

Excellence in Project Management

Page 9: AJIT KUMAR ED(BD)

Total Income PAT

8.9% 4.9%

COMPARISION – Three Quarter PeriodCOMPARISION – YEAR ON YEAR

Financial Performance

Total Income PAT

4.3%16.6%

Rs. Crores Rs. Crores

Net Worth ~ Rs. 67000 Cr.

Total Assets ~ Rs. 125000 Cr.

Market Cap ~ Rs. 145000 Cr.

Capex for FY13 - Rs. 20995 Crores

4923457399 8728 9103 41242

452526321

6630

Page 10: AJIT KUMAR ED(BD)

Human Capital – Continuously Improving Productivity

10%

Rs.1.38 Crs

Rs. 2.30 Crs

Rs 0.29 Crs

Rs. 0.38 Crs

Sales Per Employee

PAT Per Employee

Up67%

Up 31%

7.99MUs

9.27MUs

Generation Per Employee

Up 16%

Talent pool of ~25,000 employees Planned interventions at various stages of career Systematic training- 7 days training per employee per year Power Management Institute (PMI) – Playing a pivotal role in individual

and organizational learning. Leadership Development Centre to identify and groom potential

leaders. Training Simulators for 660 MW / 500 MW / 200 MW coal and gas based

plants Featured amongst the Great Places to work in India for last six years

consecutively

Ranked 6th in the Aon Hewitt Best

Employers in India 2011.

FY07 FY11

2011

Page 11: AJIT KUMAR ED(BD)

Planning for accelerated growth Today

~39674 MW

Coal Gas Nuclear Hydro Renewables

2032~ 128000 MW

Page 12: AJIT KUMAR ED(BD)

ELECTRICITY GENERATIONSCENARIO

Page 13: AJIT KUMAR ED(BD)

India: Installed Power generation capacity

Status as of Oct 2012

3 %

Installed capacity : 209 GW

Source : CEA

RES :Renewable Energy Sources

66%

19%

12 %

Page 14: AJIT KUMAR ED(BD)

Per Capita Consumption-Global scenario

USAOECD countriesMiddle EastLatin AmericaChinaWorld Average India

14000 8365 2980 1695 1802 2596 800

Values are in KWh

Page 15: AJIT KUMAR ED(BD)

Electric Power- Demand projections

220441

8611381

1854

0

500

1000

1500

2000

GW

2011-12

2021-22

2031-32

2041-42

2051-52

Year

Installed Capacity Reqd (GW)

Source : Central Electricity Authority (CEA), India1 GW(gigawatt) = 1O6 KW(kilowatt)

Page 16: AJIT KUMAR ED(BD)

The task ahead India’s growing economy requires adequate supply of energy Per capita consumption of electricity of 800 Kwh is lower than

world average of 2200 Kwh Energy deficit ~ (-7%) & Peak Demand Deficit ~(-9.4%) T&D Losses ~ 25 to 50% India’s installed electric power generation would have to

increase to 861 GW by 2030 to sustain economic growth of 8-9%.

India needs to effectively tap all sources of Power Generation

Page 17: AJIT KUMAR ED(BD)

17

India’s Energy Resource Base

Resource Estimated Reserves

COAL 285 Billion Tonnes

LIGNITE 40 Billion Tonnes

GAS 1240 Billion Cu m

URANIUM 61,000 Tonnes

THORIUM 2,25,000 Tonnes

HYDRO 1,48,000 MW(Potential)

RENEWABLES 1,83,000 MW(Potential)

Page 18: AJIT KUMAR ED(BD)

Coal Based Power

•High ash content (25-45%)•Low sulphur (< 0.5%)•Low calorific value~3000Kcal/kg

•CO2 emissions•Ash disposal•Coal transportation bottleneck through rail

Need for Clean Coal Technologies

•Supercritical/Ultrasupercritical

•Integrated Gasification Combined Cycle

• Carbon Capture & Sequesterization

Indian Coal Quality Issues with Coal based PowerInstalled capacity : 17624 MW

Page 19: AJIT KUMAR ED(BD)

660/800 MW units planned for all future coal based projects Parameters adopted

247 kg/cm2 535/565 and 565/593 deg C Supercritical technology mandatory for Ultra Mega Projects Many more supercritical units in pipeline.

Supercritical TechnologyImpact Area

Efficiency Improvement CO2 Reduction Affordability

Page 20: AJIT KUMAR ED(BD)

Integrated Gasification Combined Cycle

Gasifier

Gas Cleanup

Combined Cycle

RawGas

CleanGasCoal Powe

r

High efficiency ~ 43-45 %

Potential for achieving even higher efficiency ~ Using advanced class Gas Turbines( Up to 50 %)

Potential for Green House Gas(GHG) Reduction

Low water consumption: Since 2/3 of power is generated from Gas Turbine

India pursuing demo project of 100 MW- Feasibility study done by Nexant USA through USAID

Page 21: AJIT KUMAR ED(BD)

Gas based power

•Gas Availability for power generation to be enhanced.

•Expanding gas pipelines/LNG terminals

•Advanced class Gas turbines : Thermal efficiency of 60%

• Installed capacity – 18903 MW

Page 22: AJIT KUMAR ED(BD)

Nuclear Power

4780 MWe

4800 MWe(*)

21780 MWe(cumulative)

63000 MWe(cumulative)

Projections- 2020

Projections- 2030

Under Construction

CurrentCapacity

(*) at Kudankulam, Kakrapar, Rawathbhata

Page 23: AJIT KUMAR ED(BD)

Nuclear Power - Positive developments

•Signing of Indo-US Civil Nuclear agreement•Nuclear Supplier Group (NSG) waiver•India can now import fuel and technology even for existing nuclear plants•Govt of India is in discussions with advanced technology

suppliers •NTPC and NPCIL have formed a JV company for setting up nuclear plants•BHEL and L&T are augmenting nuclear manufacturing capabilities through colloborations.

Page 24: AJIT KUMAR ED(BD)

Nuclear power - Challenges

•Issues related to Nuclear Civil liability bill

•Fuel policy of Govt of India

•Availability of Nuclear sites

•Availability of Skilled Manpower

•Augmentation in domestic manufacturing capabilities

•Amendment of Atomic Energy Act to allow wider

participation

Page 25: AJIT KUMAR ED(BD)

Hydroelectric Power

• Installed capacity – 39,000 MW• Estimated potential – 148,000 MW

•Land acquisition issues

•Resettlement and Rehabilitation issues

•Regulatory delays affecting clearances

•Impact on eco system and submergence of forest land

•Financing issues for projects with large gestation period

•Constraints related to transmission capacity particularly from NE states

Page 26: AJIT KUMAR ED(BD)

Solar Power

•Estimated potential– 2.5 trillion MWp• Installed capacity – 1000 MWp

Jawaharlal Nehru National Solar Mission has been launched by Govt of India in Jan-10 to boost the development of Solar Power. TARGETS UNDER JNNSM

Page 27: AJIT KUMAR ED(BD)

Wind Power

• Installed capacity – 17,000 MW• Estimated potential – 45,000 MW

•Identification of high wind potential sites•Improvements in technology to increase availability • Focus on new growth avenues

•Offshore Wind turbines•Large capacity Wind Turbines( > 3 MW)•Small capacity Turbines ( < 600 KW)

•Improved grid infrastructure in unconnected high potential areas

Page 28: AJIT KUMAR ED(BD)

Biomass Power

• Installed capacity – 2000 MW• Estimated potential – 16000 MW

•Unorganized biomass market

•Addressing issues related to transportation and storage issues for biomass

Page 29: AJIT KUMAR ED(BD)

ELECTRICITY TRANSMISSION

Page 30: AJIT KUMAR ED(BD)

• Present installed capacity - 294000ckm 220kV Transmission Line - 150000ckm 400kV Transmission Line - 125000ckm HVDC 800/600kV Line - 3600ckm HVDC 500kV Line – 7400 ckm 765kV Transmission Line - 7600ckm

• Present Inter regional Capacity – 38650MW• Expected by 2017 - 75000MW

• Estimated Additions of Transmission Network in 12th Plan – 155000 to 180000ckm

Source: CEA & Planning Commission reports

Transmission System

Page 31: AJIT KUMAR ED(BD)

Source: CEA & Planning Commission reports

Transmission System and Its Growth

Page 32: AJIT KUMAR ED(BD)

Transmission System and Its Growth

+/- 600 kV / 800 kV

Page 33: AJIT KUMAR ED(BD)

• Implementing HVDC lines for Interregional links• Development of 1200kV UHVAC Test Station at Bina• Smart Grid • GPS/GIS (Global Positioning/Information System) based survey techniques• High temperature endurance conductor• Controlled switching of circuit breakers• Multi circuit and Compact towers to reduce corridor requirement.• High rise towers to avoid tree cutting and hindrance in

monuments

Important Initiatives

Page 34: AJIT KUMAR ED(BD)

New Technologies •Ultrasupercritical Technology ( 700 deg C)

•Integrated Gasification Combined Cycle

•HV Transmission system – AC & DC

•Energy Storage systems

•Smart Grid & Smart Networking

•Solar Thermal- High temperature and grid parity

•Solar Photo Volataic – High Efficiency solar cells

•Fuel cells

Page 35: AJIT KUMAR ED(BD)

CHALLENGES MITIGATING MEASURESLand Acquisition Revamping of land acquisition policy backed

by a win-win R&R policyEnvironmental Clearances

-Expeditious approval

Fuel Availability -Development of new coal mines by CIL/Utilities matching planned generation capacities.-Securing coal linkages not only in india but abroad also

Equipment Shortage -Procurement from abroad

Indian Power Sector Challenges & Mitigating Measures

Page 36: AJIT KUMAR ED(BD)

CHALLENGES MITIGATING MEASURES

Manpower shortage -Proper training-New courses in power generation tech.

Financials - Multilateral financing-Development of power plants in PPP initiatives

Project execution -World best practices in project management

Regulatory issues -Ensuring Grid Discipline

Indian Power Sector Challenges & Mitigating Measures

Page 37: AJIT KUMAR ED(BD)

• Adoption of New and Efficient Technologies

• Investing in Research and Development

• Availability of large scale skilled/unskilled manpower

• Extensive Engagement with Society

• Sensitivity towards Environment

• Sustainable Growth

ConclusionsGROWTH IN POWER GENERATION AND TRANSMISSION

CAPACITIES REQUIRE

Page 38: AJIT KUMAR ED(BD)

Discussions

Page 39: AJIT KUMAR ED(BD)

NTPC Limited NTPC Limited ( A Government of India Enterprise)

Lighting every third bulb in Indiawww.ntpc.co.in

39

Page 40: AJIT KUMAR ED(BD)

4040

Highest capacity utilization

Performing at global levelsElectricity Generation Billion Units

#