Aid Effectiveness to Infrastructure: A Comparative Study of East … · 2016-04-19 · JBICI...
Transcript of Aid Effectiveness to Infrastructure: A Comparative Study of East … · 2016-04-19 · JBICI...
JBICI Research Paper No. 36-3
July 2008
ISSN 1347-5703
4-1, Ohtemachi 1-chome, Chiyoda-ku, Tokyo 100-8144, Japan
Tel: 03-5218-9720 (JBIC Institute)Internet: http://www.jbic.go.jp/ Recycled paper
JBICI R
esearch Paper No. 36-3
JBIC InstituteJapan Bank for International Cooperation
July 2008
Aid Effectiveness to Infrastructure:A Comparative Study of East Asia and
Sub-Saharan Africa
Case Studies of Sub-Saharan Africa
Aid Effectiveness to Infrastructure: A
Com
parative Study of East Asia and Sub-Saharan A
frica, Case Studies of Sub-Saharan A
frica
JBICI Research Paper No. 36-3
July 2008
JBIC InstituteJapan Bank for International Cooperation
Aid Effectiveness to Infrastructure:A Comparative Study of East Asia and
Sub-Saharan Africa
Case Studies of Sub-Saharan Africa
JBICI Research Paper No. 36-3
Japan Bank for International Cooperation (JBIC)
Published in July 2008© 2008 Japan Bank for International Cooperation
All rights reserved.
This Research Paper is based on the findings and discussions of the JBIC. The views expressed in
this paper are those of the authors and do not necessarily represent the official position of the JBIC.
No part of this Research Paper may be reproduced in any form without the express permission of
the publisher. For further information please contact the Planning and Coordination Division of our
Institute.
Ernest AryeeteyPeter Quartey
University of Ghana
Aid Effectiveness to Infrastructure:a Comparative Study of East Asia and
Sub-saharan Africa1
Ghana Case Study
1 Mr. Emmanuel Joseph Mensah (ISSER) provided very helpful assistance
i
i
Table of CONTENTS
1. INTRODUCTION ………………………………………………………………………… 11.1 Research Issues ……………………………………………………………………… 11.2 Research Objectives ………………………………………………………………… 41.3 Methodology …………………………………………………………………………… 4
2. PROJECT CASE A: NATIONAL ELECTRIFICATION PROJECT ……………… 62.1 Project Objectives …………………………………………………………………… 62.2 Scope …………………………………………………………………………………… 92.3 Impact of the National Electrification Project …………………………………… 122.4 Factors affecting Implementation and Outcome ………………………………… 212.5 Comparing with Reference Project ………………………………………………… 232.6 Assessment of Donor Policy Influence and Practices on Institutional
Impacts ………………………………………………………………………………… 27
3. PROJECT CASE B: ANWIANKWANTA YAMORANSA ROAD PROJECT ……… 293.1 Project Objectives …………………………………………………………………… 293.2 Scope of the Project …………………………………………………………………… 303.3 Impact of the Project ………………………………………………………………… 313.4 Comparison with Reference Project ……………………………………………… 383.5 Assessment of Donor Policy Influence and Practices on Institutional
Impacts ………………………………………………………………………………… 39
4. CONCLUSIONS AND POLICY RECOMMENDATIONS ………………………… 42
REFERENCES ……………………………………………………………………………… 44APPENDICES ………………………………………………………………………………… 46
ii iii
List of Figures
Figure 1: Anwiankwanta-Yamoransa Road (Project Site) ……………………………… 30Figure 2: O & M Processes in Ghana Highway Authority …………………………… 34Figure 3: Donor Support for Infrastructure Development (2003-2005) ……………… 40
ii iii
List of Tables
Table 1 : Ghana Road Condition Mix ……………………………………………………… 2Table 2 : Road Condition Mix by Region (Paved and Gravel Roads) ………………… 3Table 3 : Areas Connected under the National Electrification Project (NEP) ……… 13Table 4 : Other Electrification Projects Executed (1989 – 2001) ……………………… 13Table 5 : Completed Projects (1990 – 2000) ……………………………………………… 14Table 6 : Other Completed Projects (2001 – 2005) ……………………………………… 14Table 7 : Economic Internal Rate of Return ……………………………………………… 15Table 8 : History of Tariff Reform in Ghana …………………………………………… 17Table 9 : Residential Tariff Structure (Cedis per KWh) ……………………………… 18Table 10: Actual Traffic Volume (1987-1998) …………………………………………… 31Table 11: A-Y Road Traffic Volume by Vehicle Types in Selected Sites ……………… 31Table 12: Interview Survey Major Results (n=150) …………………………………… 33Table 13: Road Fund Revenues by Source (Billions of Cedis) ………………………… 34Table 14: Characteristics of the Accra-Yamoransa Road ……………………………… 38Table 15: Tied and Untied Aid (Bilateral) to Electricity & Roads Sub-sectors
in Ghana …………………………………………………………………………… 40
iv 1
Acronyms and Abbreviations
AGI Association of Ghana Industries
ATL Akosombo Textile Limited
A-Y Anwiankwanta-Yamoransa
CEB Communaute Eletrique du Benin
CP Construction Pioneers
CSA Civil Servants Association
DANIDA Danish International Development Agency
ECG Electricity Company of Ghana
EEIC Energie Electrique de la Cote d’Ivoire
EIRR Economic Internal Rate of Return
FRP Financial Recovery Plan
GoG Government of Ghana
ICB International Competitive Bidding
LRMC Long Run Marginal Cost
LV Low Voltage
MMU Mobile Moving Unit
NDF NORDIC Development Fund
NED Northern Electricity Department
NEP National Electrification Programme
NERSRP Northern Electrification and System Reinforcement Project
OECF Overseas Economic Cooperation Fund
PURC Public Utility Regulatory Commission
SHEP Self Help Electrification Programme
SIDA Swedish International Development Agency
TUC Trades Union Congress
VALCO Volta Aluminum Company
VRA Volta River Authority
iv 1
1. INTRODUCTION
1.1 Research Issues
In the last two decades the development performance of sub-Saharan Africa has
contrasted sharply with that of Asian economies. While their circumstances in the
early post-independence period were generally comparable, this began to change
significantly after the first twenty years. The average GDP per capita in Sub-Saharan
Africa was $703 in 1975 while that of East Asia was $309. By 2001, GDP per capita for
SSA had declined to $460 while that of East Asia had increased to $900 (World Bank,
2003). The trend has not reversed and in 2005, while average GNI per capita2 for
East Asia and Pacific was $1630, that of SSA was $746. There have been suggestions
that the better performance of East Asia in the period could be attributed to more
effective institutions that presided over the transformation of economies and a better
use of resources (Nissanke and Aryeetey, 2003). The effective institutions were able to
attract and make better use of aid soon after independence than in SSA, it is argued.
This allowed the East Asian economies to subsequently reduce their intake of aid by
the mid-1970s. Over the period 1975-2002, total Official Development Assistance and
Official Aid to SSA was $318.8 billion which compares with $214.1 billion received
by East Asia and the Pacific Countries over the same period. The trend of growing
dependence on aid for SSA described above is not different for Ghana; GNI per capita
was $300 in 1975 and by 2005 it had increased to $450. In terms of Official aid,
between 1975 and 2002, Ghana received a total of $11.9 billion in aid (World Bank,
2005). The question is whether increasing aid to Ghana has had the appropriate
impact on economic performance and welfare.
There is a growing view that the differences in outcome between African economies
and East Asian economies can probably best be explained by the institutional
differences in how they managed infrastructure projects supported by aid. Did the
aid lead to better institutions? Some research has shown that infrastructure aid in
Asia has contributed to institutional reform, capacity building and human capital
development of the recipient countries (Arakawa and Wakabayashi, 2006). But
to what extent has this happened in Africa? We use Ghana as a case study of the
question. Ghana’s infrastructure development has not been the best in the sub-region
and this has had serious repercussions on the production, marketing and development
of agriculture in the country. The poor state of infrastructure in Ghana as in many
African countries does not promote effective and competitive agricultural production,
2 Atlas Method
2 3
trade and development. Teledensity is low although it has increased from 1.8 to 3.8
between 2003 and 2005 (ISSER, 2005). In 1996, Teledensity in South Africa was 10.2
as compared 6.02 in Asia and the African average of 1.85 (Jerome, 1999). Telephone
usage and access is urban bias which goes to compound trade in agriculture and agri-
business development. However, the privatization of the telecommunication industry
in Ghana has seen improvements in access and coverage but more particularly the
number of operators in both the fixed line and the cellular networks. However, the
limited telephone infrastructure has affected the potential for internet access and
trade in agribusiness in the country.
Road transport which forms the major means of distributing agricultural products
within Ghana and also for international trade remains to be adequately developed.
A significant proportion of roads in Ghana are not paved and most resources are
channeled into road building than into maintenance. Data on Ghana’s road network
is given in Table 1. There were also disparities in the quality of road in the regions
(Table 2). Generally, about half the network is in good condition and about a third of
the feeder road network is also in good condition. However, transport cost remains a
major challenge to doing business in Ghana.
Table 1: Ghana Road Condition Mix
Year Total (%) Paved (%) UnpavedGood Fair Poor Good Fair Poor Good Fair Poor
2003 29 17 54 42 26 32 17 9 742004 32 16 52 47 24 29 18 8 742005 40 15 46 54 21 25 24 8 692006 50 13 37 63 18 19 33 8 592007 60 14 26 70 17 13 45 9 452008 67 16 17 75 17 8 55 15 31
Source: Ministry of Roads and Transport, Road Sector development Review Report, 2003
2 3
Table 2: Road Condition Mix by Region (Paved and Gravel Roads)
RegionGood Fair Poor
TotalKm % Km % Km %
Ashanti 317 22.4 468 33.2 628 44.4 100Brong Ahafo 465 33.7 276 20.0 639 46.3 100Central 142 17.4 387 47.6 285 35.0 100Eastern 563 45.3 440 35.3 242 19.4 100Gt. Accra 199 50.4 112 28.3 84 21.4 100Northern 606 29.9 604 29.8 815 40.3 100Upper East 134 34.8 139 36.3 111 28.9 100Upper West 97 10.4 281 30.1 555 59.5 100Volta 465 38.5 303 25.1 440 36.4 100Western 284 21.4 303 22.8 743 55.9 100Total 3272 29.4 3314 29.8 4542 40.8 100
Source: Ministry of Roads and Transport, Road Sector development Review Report, 2003
The Ministry of Transport estimates that the costs of freight transport in Ghana
are approximately 12 per cent of final prices, compared to 6-7 per cent in developed
countries. An informal survey on freight charges indicates that, on average, it costs
$1.94 to move cargo by one kilometer in Ghana, compared with US$ 0.09 per kilometer
in the United States and US$1.41 in Nigeria.3 The FIAS regulatory and administrative
cost survey found that the worst external trade barrier for businesses was shipping
and transport costs. Forty per cent of businesses engaged in international trade
claimed that shipping and transportation was either a major or severe problem. The
electricity sub-sector also faces major challenges; transmission and distribution losses
are high; in 1993/94 it amounted to 17.8% in Ghana, as compared to 8% in Zambia,
14.3% in Senegal, and 12.5% in Kenya (Jerome, 1999). The International Energy
Agency (IEA) estimates that in 2004, distribution losses in Ghana accounted for 16.7%
of total final consumption.
Despite these challenges, infrastructure plays a major role in economic development.
It is against this background that the Government of Ghana sought donor assistance
particularly in the 1980s and 1990s to support infrastructure development in Ghana.
However, the outcome of infrastructure aid on Ghana’s development has received little
empirical investigation. The key issue is what were the initial conditions before Ghana
received aid for infrastructure development and to what extent has these funds led
to institutional transformation to ensure sustained growth in Ghana? This forms the
focus of the study.
3 World Bank, 2001
4 5
1.2 Research Objectives
This study aims to ascertain the “processes of institutional changes associated with
the two infrastructure projects and relationships between those institutional changes
to the overall impact of the infrastructure projects”. The study will examine impacts
“related to ideas influencing policy, transfer of knowledge and lessons learned,
organizational capacity to plan, implement and operate, and human resources
development in general.” While previous studies have used macroeconomic analysis
to address this issue, the study intends to use comparative analysis of specific case
studies. It is believed that such an approach will unravel the differences in the
mechanism for transforming aid into long-term growth and poverty reduction which
will then inform policy on accelerating economic growth in Ghana through aid. Thus,
the Ghana case study will focus on aid infrastructure investments and how they
contribute towards long term growth and poverty reduction. The paper hypothesizes
that `the Africa-Asia and Ghana-Asia contrast discussed above and the role of aid, to a
large extent can be explained by differences in the institutional linkages between aid
projects and wider systems at the national level’.
1.3 Methodology
In order to ascertain the impact of infrastructure aid projects on policy reforms,
technology transfer, and human capacity in Ghana two infrastructure projects were
selected based on a set of criteria. Projects are selected based on the five (5) criteria
provided by the project steering committee on page 3 of the terms of reference.
These include (i) Size (ii) Sectors (iii) Number of Cases (iv) Time Perspective and (v)
Financier. Applying the five criteria, two infrastructure projects from two sectors of
the economy; one economic (road) and the other non-economic (energy) have been
selected. The road project selected is the Anwiankwanta-Yamoransa road financed
by JBIC and the other, an energy project, is the National Electrification Project
financed by the World Bank. Both projects are of great interest from an institutional
point of view. For instance, a third component of the energy project was to provide
institutional strengthening of Electricity Company of Ghana (ECG) through
regrouping of all its commercial activities under one directorate and hiring an outside
firm under a performance based management contract to run the newly created
directorate. The road project is also a large one and the only major road linking the
Takoradi Port to the middle and northern part of the country. It also facilitates trade
between Ghana and Burkina Faso (a land-locked country).
The study finds that although infrastructure aid has played a major role in Ghana’s
development, there is considerable room for improvement. It has led to technology
4 5
transfer, institutional capacity building, and policy reforms and improved livelihood.
However, tied infrastructure aid was cited by many stakeholders as a major
developmental challenge in the selected projects. The rest of the paper is organized
as follows: section two discusses the link between institutional developments and aid
effectiveness. Section three presents the National Electrification Project; project scope,
objectives, institutional impact, compares it with a reference project and discusses
how donor influence affected the outcome of these projects. Section three undertakes a
similar analysis of the Accra-Yamoransa road project. The fourth section provides the
concluding remarks and provides policy lessons.
6 7
2. PROJECT CASE A: NATIONAL ELECTRIFICATION PROJECT
Ghana’s total technically exploitable hydro potential is estimated at 10,000 GWh
annually (2300 MW installed capacity), derived mainly from the three major river
systems (Volta, Tano, Pra) in the central and western regions. It is reported that
installed hydro plant capacity is 1072 MW, based on two dams on the Volta River.
Other sites on the Black Volta, Pra, Tano and Oti rivers have been studied to their
full feasibility level. There has been a comprehensive country wide survey of small
hydro potential and some identified sites that can provide economic supply of isolated
centres (World Bank, 1999).
The Ministry of Energy is responsible for petroleum and electricity production
and distribution in Ghana while the Volta River Authority (VRA) and the Electricity
Company (ECG) remain the two dominant power sector entities. VRA supplies
electricity in bulk to ECG, the Volta Aluminum Company (VALCO), several mines
and Akosombo Textile Limited (ATL) and the Akosombo Township. VRA also exports
electricity to Communaute Eletrique du Benin (CEB) and Energie Electrique de
la Cote d’Ivoire (EEIC). Under the IDA assisted Northern Grid Extension Project
of February 1987, the responsibility for generating and distributing electricity
in Northern Ghana was transferred to VRA from ECG. Subsequently, these
responsibilities are handled by VRA’s Northern Electricity Department (NED). ECG
then distributes the electricity it receives from VRA to the rest of the country. Since
the VRA was founded in 1961, it has operated a quasi-enclave within the country with
considerable degree of autonomy. The RCG which is a much bigger organization was
established in 1967 to succeed the Electricity Division of the Ministry of Works and
Housing but had since struggled to become commercially viable.
Electricity accounts for 9.9% of net domestic energy consumption in 1990.
Petroleum products and electricity consumption increased steadily throughout the
1970s and early 1980s despite the deteriorating economy, coupled with subsidized
petroleum products and low real prices of electricity. Consumption declined sharply
after 1982 due to shortages of both petroleum and electricity, but has since recovered
as supply conditions improved (World Bank, 1999).
2.1 Project Objectives
The National Electrification Project, a World Bank sponsored project was approved
on March 4, 1993 and the project ended on 31st 2000 with a total project cost of
6 7
$138 million4. The Implementing agency for this project is the Electricity Company
of Ghana. The Project’s main objectives are to enable the Volta River Authority/
Electricity Company of Ghana (VRA/ECG) to provide electricity from the national
power grid to small urban centres and rural areas through a systematic electrification
programme. The project also aims to rationalize the sector institutions, particularly,
the ECG. The project has three parts, namely, (i) a portion of a time slice of the
investment programme defined under an IDA-financed National Electrification
Planning Study, which will include connection to the national power grid of all the
district capitals that are not yet connected to the grid, (ii) re-enforcement of ECG’s
existing distribution network by expanding sub-stations, and building or replacing
major links between sub-stations; and (iii) institutional strengthening of ECG through
regrouping of all its commercial activities under one directorate and hiring an outside
firm under a performance based management contract to run the newly created
directorate. The cost of the project can be classified under the following components:
(i) National electrification component cost US $ 124.0 million; (ii) the Distribution re-
enforcement component cost US$ 31.6 million; (iii) the Management contract cost US
$5.0 million; and (iv) the Training Studies component cost US $ 5.6 million (World
Bank, 2001).
The inception and subsequent implementation of the NEP followed a study by Acres
International for the Ghana Government. The study culminated in the development of
a 30-year electrification plan (1990-2020) which aimed at connecting all major towns
in Ghana, with a population of 500 or more, to the national grid. The report could
be described as a “master plan” particularly because of its comprehensive nature,
embodying all the necessary information and design (technical, financial, etc) for the
implementation of the project.
ECG’s input into the plan involved the seconding of two employees to assist with the
development of the plan, and also the opportunity to comment on the plan as part of
the consultation processes. Beneficiary communities and districts could only have been
consulted by the consultants as part of the processes for the development and design
of the project. According to ECG officials interviewed, the design of the project came
with the Acres report, which meant that ECG only had to implement its aspect of the
project. The ECG had to communicate with the beneficiary communities as part of the
process to promote household interest and to educate them on the potential benefits of
the project and the need to wire their houses to be connected to the national grid upon
completion of the project.
4 http://web.worldbank.org/
8 9
Based on the Acres’ report, the eligible towns were captured and the overall project
packaged into smaller components for funding. The World Bank sourced for funds for
the different components from the following: the Nordic, Netherlands government,
DANIDA, Swedish International Development Agency (SIDA) and the World Bank.
The ECG financed the local cost component of the project, which amounted to just
about 10 percent of the overall cost. The SIDA and NORDIC assistance came with
the condition that only construction firms originating from the respective countries be
contracted to execute the projects (tied aid) whereas the rest of the project components
were opened up for International Competitive Bidding (ICB). The Ashanti region
component of the project was however deemed small, and therefore a local firm was
contracted to execute it.
On the other hand, the World Bank insisted on ensuring the delivery of quality
work by engaging the services of an international project management firm to assist
the ECG with the execution of the project. For the Urban component of the project,
ESBI consults (Ireland) were engaged while Merc and McLeldan (UK) were also
engaged for the rural component of the project. The strongest contribution from such
international consulting firms is the managerial acumen – which mattered most. The
actual construction work could however be sub-contracted to local construction firms
and that is largely what happened with this project. The ECG has the right of way
during project implementation; thus, usually ECG does not consult communities in the
design of projects. Only marketing officers visit communities to interact and explain
usefulness of the project. Load forecasting is done based on assessment of economic
activities in the community and usually done at the time of the design of the project
(the acres’ study). The objectives of the NES are as follows:
To increase the overall socio-economic development of the nation and create wealth, •
thereby alleviating poverty, especially in the rural areas.
To increase peoples standard of living, especially those in the rural areas.•
To create small-to-medium scale industries in rural areas.•
To enhance activities in other sectors of the economy, such as agriculture, health, •
education, tourism etc
To create jobs in the rural areas and thereby reducing the rate of rural-urban •
migration.
To achieve the objectives, the Ministry of Energy was tasked to coordinate and
execute the implementation of the NES with technical engineering and supervision to
be provided by the Electricity Company of Ghana (ECG) and the Northern Electricity
Department of the Volta River Authority (NED/VRA) in their respective areas of
supervision.
8 9
2.2 Scope
The National Electrification Scheme (NES) was instituted in 1989 as Government’s
policy of extending the reach of reliable electricity supply to all parts of the country
over a thirty-year period, from 1990-2020. The importance of the NES was seen in the
fact that at the beginning of the NES, only 20% of the total population of Ghana had
access to electricity supply. However, for the rural population who form more than
70 percent of the country’s population, accessibility to electricity was only about 8
percent. At the time of enacting the NES policy, 64 out of the 110 district capitals in
the country were without reliable electricity supply from the national grid. Out of this
number, 5 had limited electricity supply from isolated diesel generation sets whilst the
remaining 59 district capitals were without any form of electricity supply.
The National Electrification Master Plan outlines an implementation plan made up
of six 5-year phases spanning the 30 year period. The first phase of the NES, executed
in the 1990’s entailed the electrification of all the District Capitals and towns/villages
on-route to the district capitals. The subsequent phases of the NES outlined the
electrification of communities based on the most economically viable criteria. The
first two-phases of the NES were completed in 1998. At the commencement of the
NES, about 4200 communities were identified as communities having population of
more than 500 and therefore qualified for connection to the national grid under NES.
Between 1989 and 2000, about 1900 towns/villages were connected to the national
electricity grid.
The NESwas financed by the World Bank and other bi-lateral funding agencies as
follows5:
Brong Ahafo, Northern and Upper East Component of the NEP under
World Bank Funding: This component of the NEP, which was executed under the
jurisdiction of VRA, covered the electrification of 13 district capitals and 129 towns/
villages along the supply route. The project was funded by the World Bank at the cost
of US$35.5 million and was executed by Norelec of France and KEC International of
India. The project commenced in 1995 and by end October 1998, all the capitals under
this project were connected to the grid. The entire project was completed in March
2000.
Eastern, Ashanti, Greater Accra, Central, Western, Volta Components
of NEP under World Bank Funding: This component of the NEP was executed
5 These information were obtained from Electricity Company of Ghana (unpublished report)
10 11
under the jurisdiction of the Electricity Company of Ghana (ECG) and it benefited 42
communities in the Eastern Region and 15 communities in the Ashanti Region under
the rural component of the NEP. The project also covered urban communities in the
six (6) regions of ECG under the NEP Urban Project. The project which started in
1996 was financed by the World Bank at a cost of US$42.5 million was completed in
March 2000.
Volta Region NEP Rural Project (NORDIC Development Fund): This
component of the NEP was executed under the jurisdiction of ECG and was initially
funded through the NORDIC Development Fund (NDF) with an initial amount of $ 5.5
million. The project was executed by KL Contractors of Denmark and it entailed the
electrification of 2 district capitals in the Volta Region and 33 towns/villages on-route
to the district capitals under the main contract. This project commenced in 1996 and
was completed in June 1998. Thereafter, an additional fund totaling US$ 1.4 million
was provided by the NDF for the connection of additional 21 communities to the grid.
Work on the additional towns commenced in September 1998, and was completed in
June 1999.
Western Region NEP Rural (Dutch Government Funding - ORET): This
component of the NEP was financed by the Dutch Government (ORET) at an
estimated cost of US$ 31.0 million and was executed by Holec Projects of Holland. The
project covered the electrification of 3 districts capitals, namely, Asankrangwa, Enchi
and Half-Assini, and 96 towns/villages on-route to the district capitals. By the end of
1997 all three district capitals had been connected to the national grid in addition to
60 other towns within the region. The funds provided by the Dutch Government were
able to cover the electrification of 63 towns and therefore the Government of Ghana
had to provide the additional funds and materials required for the remaining 33
towns. The project was completed in May 2000.
Central and Upper West Regions (DANIDA Funded): The Central Region and
Upper West Region component of the NEP were funded by the Danish International
Development Agency (DANIDA) at a cost of US$ 24.35 million and was executed by
Semco/Skansk Jensen of Denmark. The project covered the electrification of 2 district
capitals, namely, Ajumako, Twifo Praso, and 64 other towns/villages in the Central
Region and 3 district capitals, namely, Lawra, Jirapa, Nadawli and 10 other towns/
villages in the Upper West Region. This project commenced in early 1997 and was
completed in September, 1999.
Electrification of Bekwai, Kuntunanse and Other Communities (JICA-1):
This was the first Japanese Government Grant aid for electrification which covered
10 11
2 district capitals, namely, Bekwai and Kuntenase and 29 other communities in the
Ashanti and Central Regions. The project commenced in 1989 and was completed in
1990 with a total cost of US$ 7.8 million.
Electrification of Ada-Foah, Sogakope and Adidome and Other
Communities JICA -2: This involved connecting three district capitals, namely, Ada-
Foah, Sogakope and Adidome and 19 other communities in the Greater Accra and
Volta Regions. The project commenced in 1993 and was completed in 1995, at a total
cost of US$ 17.1 million.
Electrification of Asesewa and Yeji Areas, JICA 3: This project covered
electrification of communites in the Asesewa and Yeji areas. The project was funded
by the Government of Japan with a grant of US$ 10.2 million, and was executed by
the Japanese contractors Nishizawa Limited and Tochs Corporation. The first phase of
the project, that is, the electrification of Asesewa and surrounding areas, commenced
in March 1997 and was completed in December 1997. A total of 21 communities
benefited from Phase-1 of the project. The second phase of the project which involved
the electrification of Yeji and surrounding areas, commenced in March 1997. A total
of 13 communities benefited under the Phase-2 project, which was completed in
September 1999.
Electrification of Nyinahin and 23 Surrounding Communities under
Japanese Government Grant Financing, JICA 4, Phase-1: The project connected
Nyinahin and 23 other communities in the Atwima District of the Ashanti Region to
the national electricity grid. The amount involved was US$ 6.3 million with a ¢7.5
billion Ghana Government component. The project was executed in 2003.
Electrification in the Amansie West District under Japanese Government
Grant Financing, JICA 4, Phase-2: The project connected 10 communities in the
Amansie West District to the national grid. The amount involved was US$ 2.6 million
and the project was executed in the year 2004.
Juabeso-Bia Electrification Project: This project covered the District capital of
Juabeso-Bia District namely, Juabeso and 33 other communities in the Juabeso-Bia
and Sefwi-Wiawso districts. The project commenced in 1992 and was completed in
1994. The project was funded by the Government of Ghana.
Electrification in the Greater Accra and Volta Regions: This project initially
covered the electrification of 63 towns/ villages in the Volta Region and 13 towns/
villages in the Greater Accra Region. The project was funded by the Swedish
12 13
Government through the Swedish International Development Agency (SIDA) with
an initially amount of US$ 8.3 million and was executed by a Swedish Contractor,
Transelectric AB. Works under the main contract commenced in October 1997 and
was completed in October 1999. A supplementary amount of US$ 2.47 million from
SIDA was used for the electrification of additional 34 towns in the project area, which
commenced in May 2000 and was completed in Mid-2001.
Upper East Electrification Project: This project was funded by the Spanish
Government and it covered 51 communities in the Upper East Region of Ghana. A
concessionary loan amounting to US$ 10 million was secured by the GOG to undertake
the project. The project commenced in June 1999 and was completed in December
2000. Installation works on the project were carried out by Elecnor of Spain.
Electrification in the Western Region under EU Grant Financing: This
project connected 108 communities in eleven Districts in the Western Region to the
national grid with European Union Grant Aid of € 10 million. The project commenced
in July 2001 and was completed in July 2004. Norelec of France executed the work.
Electrification of Volta Lake Resettlement Townships under Chinese EXIM
Bank: This project connected 144 communities in the catchments area of the Volta
Lake Resettlement Townships to the national grid at the cost of US$ 32.8 million
from the Chinese Exim Bank. The project was executed by China International Water
and Electric Corporation. Extension of the national grid to the 144 communities was
completed in 2003. Currently, about 580 communities throughout the country will
be benefiting from the China International Water and Electrical Corporation’s credit
facility of $81 million. Government of Ghana will make a counterpart contribution of
$ 9 million making a total of $ 90 million. The Government of Ghana’s contribution is
covered under the 2007 budget.
2.3 Impact of the National Electrification Project
The study examines the impact of the two infrastructure projects in terms of
effectiveness, ideas influencing policy, transfer of knowledge and lessons learned,
organizational capacity to plan, implement and operate, and human resources
development in general.
Effectiveness
Before the commencement of the NES only about 480 towns were connected to the
national grid. Since the commencement of the NES in 1989, about 3000 town/villages
in all parts of the country have been connected to the national electricity grid as of
12 13
September 2005. These include towns under the main NES Programme as well as the
SHEP (Tables 3, 4, 5). Accessibility to electricity increased from 15 percent in 1989 to
43 percent in 2000 according to the 2000 population census. At present, it is estimated
that accessibility is in excess of 45 percent.
Table 3: Areas Connected under the National Electrification Project (NEP)
Region District Capitals Other Towns TotalAshanti 0 15 15Central 2 64 66Eastern 0 42 42Volta 2 54 56Western 3 93 96Upper West 3 10 13Brong Ahafo - - -Northern and Upper East 13 129 142TOTAL 23 407 430
World Bank, 2001
Table 4: Other Electrification Projects Executed (1989 – 2001)
Name of Project YearNo. of Dist. Capitals
Other Towns Total Region
Juabeso-Bia Electrification Project 1992-1994 1 33 34 Western
Hohoe/Jasikan Electrification Project 1993-1995 2 31 33 Volta
Grid Extension from Dodowa-Kordiabe-Agomeda 1993-1995 0 8 8 Gt. Accra
Ashanti Region Electrification Project 1993-1995 4 48 52 Ashanti
Eastern Region Electrification Project 1993-1995 2 24 26 Eastern
JICA I Project 1989-1990 2 29 31 Ashanti-CentralJICA II Project 1993-1995 2 19 21 Gt. Accra/VoltaGt. Accra Electrification Project 1996-1998 0 13 13 Gt. AccraVolta Reg. Electrification Project 1996-1998 0 63 63 Volta
JICA III Project1997-1999 0 21 21 Eastern1997-1999 0 13 13 Brong Ahafo
Gt. Accra/Volta Region Electrification Project (Extension)
2000-20010 10 10 Gt. Accra
0 28 28 Volta
Upper East Electrification Project 1998-2000 0 52 52 Upper East
TOTAL 13 392 405World Bank, 2001
14 15
Table 5: Completed Projects (1990 – 2000)
Project Package Number of TownsNational Electrification Project (NEP) 430Other Projects 405SHEP 1 50SHEP 2 250SHEP 3 Phase-1 280SHEP 3 Phase-2 494Total of Completed Projects under NES 1909
World Bank, 2001
Table 6: Other Completed Projects (2001 – 2005)
Project Package Number of Towns
Number Completed
SHEP 3 Phase -3 700 573SHEP 4 Phase-1 193 17Electrification of Volta Lake Resettlement Townships 144 144EU Funded Electrification Project (Western Region) 108 108Electrification of Nyinahin and 23 other towns 24 24Electrification in the Amansie West District 10 10Other Electrification Projects 364 204Total Projects under NES 1543 1080
World Bank, 2001
According to the VRA evaluation report, the project objectives have been fully
met with the provision of 881 km route transmission lines and the electrification of
16 District Capitals as well as 127 other rural communities. It is reported that the
project provided electricity to more than 99% of the communities that were planned.
However, the achievement in terms of the number of customers that were connected
was moderate, especially in the Northern Region (World Bank, 2001). This is due to
the ethnic conflict which affected areas covering 20 towns out of 48 towns electrified in
the region. The conflict resulted in the relocation of people from the area, damage to
property including houses, and disruption in economic activities.
At appraisal, the economic internal rate of return (EIRR) was estimated for major
sub-projects for VRA and ECG investment programmes. However, because the project
encountered an unexpected shortage of construction materials and other factors,
actual implementation of the investment programme was delayed substantially.
Consequently, the EIRRs were calculated based on the revised time-slice. Despite the
delay in project implementation, the actual EIRRs were higher than the appraisal
14 15
estimates due to substantially lower costs and larger electricity consumption than
originally anticipated. Table 7 compares the EIRRs at appraisal and completion for
major sub-projects.
Table 7: Economic Internal Rate of Return
Region EIRR at Appraisal (%) EIRR at Completion (%)Northern Region 5.5 8.3Brong Ahafo Region 12.6 16.7Eastern Region 12.7 29.7Western Region 13.5 19.7
Source: World Bank, 2001
The social, economic and commercial activities of these towns has also been
enhanced which has led to a decline in the drift of the youth from the communities to
urban centres. The project with the assistance of a contract administrator from Acres
International Ltd, Canada, was implemented within the estimated costs and schedule
(VRA, 2000). The project marked the second time in the history of the World Bank
Office in Ghana that a project of this nature was managed in-house. The experience
gained in the execution of the project was subsequently passed on to other staff
members of VRA which led to significant capacity-building.
Sustainability
According to the project completion report, the overall sustainability of the project
is uncertain. The economic viability of the project was computed without taking
into effect the negative environmental impacts and by applying the conventional
technical approach. Also, the financial appraisal report presents a gloomy picture and
questions sustainability. Financial performance targets were set requiring VRA and
ECG to achieve (i) rates of return on revalued assets at 8% annually; (ii) debt service
coverage ratios of at least 1.5 times. Also, ECG was expected to reduce and maintain
its accounts receivable at no higher than 45 days sales revenue. The formulation of
a financial recovery plan (FRP) in 1998 did not turn things round; it was partially
implemented and the tariff component was not pursued after the initial increases
in 1998, despite 30% depreciation in the Cedi. To date, tariff increases have been
delayed and government has been subsidizing utility companies. Thus, the overall
sustainability of the project is uncertain unless government continues to support it,
especially when the project is being extended to rural areas with less customer density
and demand.
It must be added that currently there is considerable government subsidy to utility
companies, especially the electricity sub-sector. For instance, the overall fiscal drain
16 17
of the electricity sector had become substantial; in 2002 deficits of the three electricity
companies (VRA, ECG, NED) approached 11% of Government spending, or 4% of
GDP. From a deficit of US$204 million, US$124 million alone stemmed from interest
and exchange rate losses. This financial situation significantly affected the utility
investments and resulted in inadequate generation reserve, transmission network
constraints, overloaded transformers, and degraded distribution networks to mention
but a few. All these reduced the quality of service to customers, particularly in the
more populated areas in Ghana. Ageing equipment further increased system losses,
and indirectly added to the cost of production and distribution of electricity. If full cost
recovery as well as full debt service were to be included, total costs would be near USD
0.08 – 0.10 per kWh in 2003 (Keener and Banerjie, 2005).
Attempts to reform electricity tariffs in Ghana are not a recent phenomenon and in
fact predates other major reform initiatives in the power sector. There is a long history
of attempts to reconcile the desire to have tariffs that reflect economic costs and yet
that are affordable to consumers. Tariffs that adjust regularly to reflect fluctuations
in costs (such as exchange rate or inflation) were implemented between 1994 and
1997. In pursuance of the agreement to ensure that tariffs approximate the Long Run
Marginal Cost (LRMC), the GoG continued to increase electricity tariffs without any
opposition until an increase of over 300% in May 1997 provoked intense nationwide
protest with the Association of Ghana Industries (AGI), the Trades Union Congress
(TUC) and the Civil Servants Association (CSA) at the forefront. Consequently, draft
legislation was enacted to establish an independent regulatory agency called the
Public Utility Regulatory Commission (PURC) bill became law. Shortly thereafter, in
October 1997, and an eight member PURC board was sworn in on November 10, 1997
(Table 8).
16 17
Table 8: History of Tariff Reform in Ghana
Year Event1976 – 1986 No changes in tariff1986 Coopers & Lybrand first major tariff study. Study recommends tariffs based on
Long-Run Marginal Cost (LRMC), classifying consumers based on groupings of consumers who impose similar costs on the systems, and grouping residential consumers by level of consumption. Progressive with lifeline consumption of 50 kWh applying to all consumers. Also adopted uniform national tariff structure.
1988 The level of tariffs recommended by Coopers and Lybrand was substantially adopted and approximated 75% of LRMC
1989 Tariff increases, ranging from 6% for low-income consumers to 20% for non-residential consumers, were implemented in order to enable VRA to continue to earn 8% and ECG a 6% Rate of Return. However, in fixing the tariff, the GoG expressed concerns at the prospect of further adjustments to domestic tariffs to reflect recent devaluation and inflationary pressures at a time when the service remained unreliable. The GoG expressed the wish to re-examine certain aspects of the 1986 tariff study, and this led to commissioning of next major tariff study (ACRES).
1990 - 1992 ACRES study points out that the inverted block rate structure recommended by Coopers and Lybrand was cumbersome to administer and a source of customer discontent. Recommended adoption of “adjusted LRMC” – LRMC adjusted to reflect the financial requirements of the utilities. Recommended merging of all residential tariff structure into a single energy rate with the exception of the lifeline tariff. New electricity tariffs introduced in January 1992 based on the recommendation of ACRES International, which was actively supported by the World Bank.
1993 The GoG agrees to adopt a formula-based approach to tariff adjustment and provide for the regular and systematic adjustment of the tariff thereafter on the basis of the agreed formula. Essentially, the formula provided for phasing-in prevailing tariff to LRMC adjusting for inflation and exchange rate movements. Tariff increases were implemented in January 1993 and an agreement reached for further increases in 1994 and 1995 within the framework of this agreement.
1994-1997 Tariffs continue to increase per the agreed formula, although the focus is on a set Rate of Return for the utilities rather than LRMC.
1997 Tariff increases of over 300% prompted nationwide protest. President Rawlings suspends increase until a regulatory commission (PURC) is formed. In response PURC was formed and placed in charge of tariff setting rather than Parliament.
Feb. 1998Sept. 1998May 2001
PURC Tariff Adjustments
2001 PURC outlines a Transitional Plan for tariffs to cover 2001 – 2004, including regulations for consumer consultation on tariffs
2003 January - Tariff formula allowing for automatic adjustment to reflect exchange rate and inflation is enacted and supposed to take effect July 2003. October, 2003 - First automatic adjustment of the tariff per the formula.
2005 PURC scheduled to carry out major tariff reviewSource: Keener and Banerjie, 2005
18 19
The residential tariff structure has moved from 5 sub-groups based on levels of
consumption, to four and then three during the 2003 tariff review process. The lowest
group often called `the lifeline’, offers a flat rate to customers consuming 50 KWh per
month or less, and was originally created to minimize the cost to the utility of billing
small accounts. Starting from August 2002, the Government of Ghana introduced a
subsidy for those consuming within the lifeline, and it came to be used as a tool for
ensuring that lower income users were protected from tariff increases. When the
automatic adjustment formula for tariffs was set to start in 2002, the GoG increased
the subsidy on the lifeline to protect this block from the automatic adjustment but
the adjustment to the formula did not take effect until October, 2003 (Keener and
Banerjie, 2005)
Table 9: Residential Tariff Structure (Cedis per KWh)
KW/month Feb. 98 Sept. 98 May 01 Aug.02 ** Mar 03 Oct 03 ***0-50 ¢/Month 2000 4000 7800 9000 13000 130000-50* 87 174 339 391 565 56551-300 50 120-150 242-304 400 550 610Over 300 75-180 220-350 570 960 960 1065
Source: PURC, 2003 & Cited in Keener and Banerjie (2005:4). * Is a flat rate, assumes average consumption levels of 23 kWh/month** Government subsidy of ¢5000 begins*** Government Subsidy increased to ¢6080 to keep lifeline constant
By 2005, tariff increases had brought the average end user tariff to the point that
they covered the PURC-defined economic costs which do not include an allowance
for current inefficiencies; which is estimated at 2 US cents/kWh (PURC 2002).
Subsequent financial analysis of the sector indicated that the middle tariff band (51
– 300 kWh) was paying below the actual average cost and therefore they were being
subsidized as well as the lifeline band.
Policy Reforms
The implementation of the energy project led to some policy reforms. First, contrary
to previous norms, under the energy project, the Electricity Company of Ghana
(ECG) now sends marketing officers to interact with communities’ way ahead of the
project completion. This has also informed government policy to absorb a significant
fraction of the connection fees since communities now make marginal contributions
towards the cost of connecting to the national grid, particularly under the National
Electrification Programme (NEP). Secondly, an international consultant was hired
to update the electrification plan and ECGs technical specifications for distribution
works. However, although the design and implementation of the pilot programme to
promote productive uses of electricity was not implemented, it is being undertaken as
18 19
an integral part of the implementation of the EC funded rural electrification for the
Western Region which commenced in June 2000 (World Bank, 2001:7).
Although the project alone cannot take full credit for the energy sector policy
reforms outlined by the GoG in 1996-2000, the NEP can partly be credited for the
reform (Statement of Power Sector Development Policy) which seeks to among
others privatize ECG and the unbundling of VRA (World bank, 2001). Another policy
issue relates to the implementation of the SHEP (GoG financed) alongside the NEP
(Donor financed) which created some problems due to the differences in the financing
arrangement. While beneficiaries of NEP pay virtually nothing to access the national
grid, customers captured under SHEP require some minimum contribution before
being assisted to get connected. Thus, where a SHEP-community gets to know that
the connection fee is free for nearby communities under NEP they become dissatisfied.
This creates the impression that some communities are more favoured than others
which brings suspicion and social tension. Currently, there are discussions to
harmonize the two arrangements.
Technology Transfer
Lessons drawn from field interviews on the two infrastructure projects are: first,
there was significant technology transfer but higher at the lower level of manpower
than at the higher levels of manpower. In the case of the energy project, foreign
employees involved in the execution of the ECG component of the NEP could only
be about 5 percent and they were mainly managerial staff. The local experts and
contractors largely lack the organizational skills and operational efficiency necessary
to respond to the challenges of project implementation (they are quite unprofessional).
In the instance of the ECG’s rural electrification project, only two expatriates were
sent down by the assisting consulting firm. They served as the Project Managers who
worked with the local Project Manager and the Construction Supervisor.
In terms of work output, all the two expatriates were highly experienced and
brought onto the project a high level of experience and knowledge in procedures for
the management of the project. Knowledge transfer was significant. For instance,
an innovative technology using the shieldwires of a 161kV transmission lines to
carry power was applied to serve 14 communities in the Brong Ahafo and Northern
regions. The use of the shieldwires also led to a 50 percent reduction in investment
cost as compared to conventional technology (World Bank, 2001). There was high
level of interaction between the foreign experts and their local counterparts. The field
interview revealed that at the time of the project implementation, the local Project
Management had no in-depth experience with the management of projects of such size.
Following the implementation of the NEP project over the 4-year period, the Manager
20 21
is now able to handle any major project. Recently, he managed a $15 million project to
upgrade ECG’s distribution systems while another project, amounting to about $155
million has been lined for implementation. Also, capacity development within ECG
during the project implementation stage has enabled the company to redeploy those
employees that worked on the project to the regions, to be called back whenever the
need arise, thus creating further impact downstream.
Capacity Development
The arrangement between local and foreign contractors has worked very well in
terms of local capacity building. For instance, under the distribution reinforcement
component, a 161/34.5kV, 13.3MVA sub-station with seven radial sub-transmission
lines was constructed at Yendi in the Northern was executed using local installation
contractors (World Bank, 2001). Local contractors or workers were supervised by
the expatriates during the implementation and they delivered timely and standard
outputs. If left to them alone, this would not have occurred. Thus, local contractors
when sub-contracted, they should be supervised to execute projects to satisfaction.
Generally, local contractors have serious limitations in terms of managerial skills and
therefore very few are capable of executing projects on `supply and erect’ basis. They
generally do well when sub-contracted and strictly supervised. With NEP, the only
local-foreign partnership had serious problems arising from the lack of understanding
on the management procedures and this hampered the progress of that project.
Nevertheless, all the other projects undertaken by the local contractors were done
satisfactorily.
Management capacity was also improved. For instance, in order to achieve
improvement in ECG’s operational efficiency and strengthen its commercial
operations, a performance- based management contract was instituted. At the end
of the contract, it was reported that commercial losses had reduced by 3%; debtor/
sales ratio decreased from 198 days to 109 days; an organizational structure of
decentralized and efficient customer service was established and accurate bills
produced before the next month’s meter reading is undertaken (World Bank, 2001:6).
Other capacity building components include a pilot programme for pre-payment
metering and training studies, staff training in finance, audit system planning and
utility management which was partly completed. According to the project completion
report (World Bank, 2001), some ECG’s senior management visited foreign utilities to
become familiar with divestiture and utility management programmes.
However, the VRA Engineers hold the view that the VRA was capable of planning,
implementing and managing the project. The VRA developed sufficient capacity
during the implementation of the Northern Electrification and System Reinforcement
20 21
Project (NERSRP) in the 1980s. During the NERSRP, two consultants on the project
were retained by VRA, and upon the inception of the NEP, one was seconded to the
project. This proved most useful in managing the interactions with the external
agencies, especially the donors
Institutional Changes
According to the project completion report, there was a pilot programme for pre-paid
metering and training studies. The programme introduced a pre-payment metering
system in the VRA/NED operational area in the four regional capitals of Sunyani,
Tamale, Wa and Bolgatanga. Staff training in finance, audit system planning and
utility management was partly completed. Also, discussions with stakeholders
involved with the energy project revealed that initial attempts were made to
implement some institutional reforms in 1997/1998. The reform proposal came as part
of the conditions for financing the GDAP project by international donor agencies but
it did not take off primarily due to the change in government. It is however expected
to come on board soon otherwise no major institutional change has occurred over the
past 10 years. There are also suggestions of Management Service agreements to be
arranged for ECG but yet to take off.
Other Impacts
The usefulness of the project to the communities is immense. Most significantly,
since all major services such as education, health care delivery, water supply and
communication depends extensively on electricity, the energy project undoubtedly
enhanced the provision of such services in the beneficiary districts. Again, until the
execution of the project, most professionals had difficulty accepting postings to those
districts due to the absence of electricity and the services that came with it. Following
the implementation of the project, the situation has changed and professionals now
adopt different attitude when posted to such districts. Therefore, electricity connection
served as an important catalyst in boosting economic activities in the communities.
It is also suggested that women are now able to make optimal use of their time
during the day while domestic activities such as cooking etc are undertaken in the
evening. At the community level, some of the benefits arose from the casual jobs
generated by the construction activities and the contribution it made to the local
community, especially the demand for services along the road. Also, camps created
by the construction firms also provided significant boost to economic activities in the
communities.
2.4 Factors Affecting Implementation and Outcome
This can be discussed under factors outside the control of government or
22 23
implementing agency; factors generally subject to government control and factors
subject to implementing agency. First, in terms of factors outside the control of
government, the shortage of wood poles and other construction materials
The main factor which was subject to government control which significantly
affected the project has to do with tariff adjustment. The government was slow
in increasing tariffs in response to the devaluation of the Cedi and the resultant
inflation. There were attempts to increase tariffs in early 1997 but this met stiff
opposition from the public through demonstrations and the increases were suspended.
Consequently, legislation to set up autonomous regulatory bodies was fast tracked and
the Public Utilities Regulatory Commission (PURC) and the Energy Commission were
established by the end of 1997. Subsequently, the average tariff was increased by
more than 200% in 1998. However, PURC did not approve new increases until April,
2001 despite substantial depreciation in the currency and inflation in the intervening
two years. As a result, the financial position of the utilities companies has deteriorated
significantly by early 2001. This led to substantial project implementation delays and
therefore the expiration date of the Credit had to be extended for 18 months in order
to compensate for the lost time due to the delay.
Stakeholders interviewed reported that undue influence from political offices was
not recorded. However, the use of infrastructure projects to reward towns and cities
who are party faithful remains a major challenge. For instance, beneficiaries of donor
funded energy projects are required to contribute towards the connection to the
national grid while beneficiary communities of government funded energy projects do
not. However, in terms of project execution, since the VRA had signed a subsidiary
agreement with the World Bank on the project, the agency could operate transparent
processes without any pressure from political offices. Moreover, all the donor
institutions had clearly stated guidelines on the execution of their projects, which
were adhered to. Evidence the field interview indicates that no interference could
have been entertained from any source. The constraint however arose when in certain
special cases the need to modify those procedures became inevitable since these offices
strictly adhered to their procedures.
Another major challenge identified relates to disputes regarding chieftaincy in some
beneficiary communities. This delayed commissioning of projects. In Drobo (Brong
Ahafo), Gambaga and Narigu (Upper East Region) for instance, existing chieftaincy
disputes led to delays in commissioning completed projects and subsequent extension
of networks in respective cases. In the Northern region, 20 towns out of 48 towns
were not electrified due to ethnic conflict (World Bank, 2001).
22 23
There was limited success of ECG’s contract management component of the project
and it continued to experience managerial weaknesses in customer services, especially
with respect to difficulties in bill collection and high system losses. To date, these
issues continue to face the organization’s management. Although the project comprised
of an option to strengthen ECG’s technical and project management capacity, as the
volume of work load grew, capacity constraints in project contract management led to
delays in some of the contracts and this led to the 18months extension.
2.5 Comparing with Reference Project (The Self Help Electrification Project - SHEP)
The SHEP aims to extend electricity to rural communities which are located within
20km of existing 33 or 11 Kv network, and through `Self-Help’ provide some of the
material inputs required to electrify their own areas. Government provides matching
funds assistance to link the towns and villages to the national grid. Towns and
villages wishing to be connected should be willing to purchase all the low voltage poles
required for the project and must ensure that a minimum number of houses within
the town or village are wired up and ready to receive electricity. It was also decided
that anybody who wires his or her house and applies for connection within 18 months
from the date of commissioning electricity supply in the area pays a flat connection fee
of five thousand Cedis or five Ghana Cedis (Gh¢ 0.50).
The government’s Self Help Electrification Programme (SHEP) is a complementary
activity to the plan outline in the National Electrification Master Plan. Under the
SHEP, communities which are 20km from an existing 33KV or 11KV network, and
have procured the Low Voltage (LV) poles required for the electrification of their
communities, qualified to benefit under the SHEP. Thus far, phases 1 and 2 have been
completed while phase 3 is on-going with about 4000 communities in Ghana being
connected under the NES. Consequently, access to electricity had grown from about
15 percent of the population at the inception of the NES to the current level of over
45 percent. As part of the Government’s efforts to deepen the NES programme, the
Ministry of Energy had carried out studies for the fourth phase of the SHEP. A total of
about 2500 communities had been identified to be connected to the national grid under
this phase. The total cost of the networks under this phase was estimated at US$ 350
million.
There has not been an official evaluation of the Self Help Project except for an
evaluation of the Lower Volta component supported by Japanese Aid. This component
of the SHEP aims to provide power at the downstream of the Volta through towns
like Sogakope, Adidome and Ada Foah in order to connect three district capitals to
the national grid. The overall goal of the project is to ensure that living standards
24 25
are improved for residents in the targeted regions and also their local economies are
revitalized. The project scope covers three district capitals and twenty villages and it
cost 1,876 million Yen.
Effectiveness
The project managed to provide electricity to the three district capitals and 20
villages in addition to connecting 42 other villages as at the end of 2002. According
to JICA (2007), a total of 9,400 electric meters were installed in the project area
and altogether, 60,000 people have benefited from the project. Consequently, public
services such hospitals and health in have been connected to the national grid and
therefore these services (medical etc) were provided on a 24 hour basis which has
led to significant increases in the number of patients attended to in these health
facilities compared to what prevailed previously. For instance, according to a JICA ex-
post evaluation report on three hospitals and a health post surveyed, the completion
of the project enabled the authorities not only to procure more medical supplies but
also managed to properly preserve items such as vaccines and other perishable drugs.
Besides, the cost of power became more affordable compared to other sources of power
such as diesel and other power generators. JICA (2007), reports that the electrification
rates in the elementary and middle schools were lower compared to the high
schools; all the high schools were connected. However, although all high schools had
electricity, the electrification rate for elementary and middle schools in the targeted
region was only about 20%. Nevertheless, it has enabled students to make efficient
use of electrical appliances in experiments and workshops in addition to the use of
modern ICT. It has also enabled more water pumping plants to be built and existing
ones made to function efficiently in these communities. For instance, the Ghana
Water Company Ltd. built a water treatment plant in Sogakope and Ada Foah, which
supplies water from these two cities to ninety villages and towns. Besides, the stable
power enjoyed by these communities facilitated its smooth operation.
Another interesting finding is that although many farmers in these communities
recognized the importance of irrigated agriculture and therefore expressed interested
in developing one, only a few practiced irrigation using electric pumps similar to
what is being used in large-scale commercial farms as well as in the government’s
rice cultivation project. Since the introduction of electricity, diesel generators were
no longer in use and this has facilitated environmental friendly irrigated agriculture
in the area since noise and exhaust gas have been eliminated. Besides, efficient use
of motors and processing machinery which often suffer from power fluctuations have
benefited from stable power. It was also reported that there has been positive spill
over effects on management performance. Despite these positive spill-over effects,
much cannot be said about the processing of agricultural products. JICA (2007)
24 25
reports that, two large salt manufacturing companies who also happen to be high
consumers of electricity have discontinued operations as a result of land litigation
problems while another company had continued operations but with no increase in its
scale of production or management.
The report further indicated that there has been a significant increase in the number
of commercial activities in the beneficiary communities. Small-scale businesses such
as restaurants and general merchandisers have expanded their operations within
the municipalities. These businesses were set up by both the local people as well as
by people who have moved from large cities such as Accra. A major development
is the setting up of a local FM radio station which supported the dissemination of
information such as announcements concerning educational programs, medical
services, elections and commercial adverts to mention but a few. All of this has been
facilitated by the stable power supply enjoyed within these communities.
Sustainability
Sustained power supply to the targeted areas is anticipated but that depends on
whether revenue generated will be enough to cover costs and maintenance. It is
interesting to note that stable power supply has been recorded in these areas. JICA
(2007) reports that `the stability of electricity supplied to the Asiekpe substation and
the secondary Sogakope substation which is the feeder station for electricity from the
national grid to the targeted regions is extremely high’. Also, evidence at the Volta
River Authority’s high-tension transmitting station indicates a high power stability
rate of around 98% (JICA 2007). Unfortunately, the stability of power was adversely
affected by less rainfall between 1998 and 2001 and this led to nationwide scheduled
blackouts. However, the situation was restored in 2002 and electricity has since
been supplied on a 24-hour basis except during the load shedding period in 2007. It
is important to add that records from the Electricity Corporation of Ghana (ECG)
points to some degree of power outages to low-end consumers. For instance, supply
rate was 95% in Sogakope and 80-85% in Ada, indicating some blackouts. Generally,
power supply has been stable and has improved over the years and therefore it can
be concluded that the project is sustainable. In terms of project management and
reforms, after the completion of the project, the Volta River Authority and Electricity
Corporation of Ghana started to decentralize. As a result, the Electricity Corporation
of Ghana was privatized in 1997 and named the Electricity Company of Ghana.
Nevertheless, the government continued to hold all of its stock, and therefore it
remained a government organization. Besides, there was no change in its functions; it
continued to generate and distribute electricity in the project’s targeted communities.
The Electricity Corporation of Ghana in order to meet the needs of the target
communities in 1998 set up a new office in Sogakope and consequently the number
26 27
of staff in charge of the project area increased from 38 in 1998 to 50 in 2002 (JICA,
2007).
Another major institution involved in the generation and distribution of power is the
Volta River Authority. It is mainly responsible for the maintenance of `high-tension
transmitters (66kV) and the upstream substations, and inspects the high-tension lines
twice a year and the substation at least once a month’. However, Lower tension power
lines (33kV), substations and facilities for power distribution to individual consumers
are the responsibility of the Electricity Corporation of Ghana. Despite the enormous
role played by ECG and VRA in the production and distribution of power to low end
consumers, a major challenge faced by these two institutions is low electricity fees,
high delinquency rate for payments and the high rate of stolen electricity (JICA, 2007).
For instance, the expenditure reports of the Ho office of the Electricity Corporation
of Ghana’s which has jurisdiction over the project’s target regions indicated that this
regional office had declared a deficit for four of the five fiscal years since 1997. This
clearly questions the financial sustainability of the project.
However, aside financial sustainability issues, the project outcomes were met and
a major factor identified as key to promoting the outcome of the project relates to
the financing of the project. Under the Self Help Electrification Programme (SHEP),
residents were required to provide 90% of the utility poles while the government
provided the rest including the transmission equipment and materials as well as the
construction. All these were meant to reduce the financial burden on government
and also increase the number of villages to benefit from the scheme. Although this
strategy worked, the project also came with its own challenges. First, the power lines
in the Ada region were often damaged by salt water in view of its proximity to the
ocean. Consequently, the area recorded some power outages. Besides, the utility poles
were made of wood and were prone to bushfires which aggravates the power instability
problem in these villages. As mentioned earlier, there was little progress with
agricultural processing and a major reason has been due to the type of transformers
installed in these villages. `Agricultural production equipment requires three-phase
transformers especially machines used in producing cornmeal, but some villages only
have single-phase transformers’ (JBIC, 2007). The three-phase transformers are
expensive and often not easy to come by compared to the single-phase transformers.
Despite these shortcomings, the project was able to stabilize power supply to
beneficiary communities made up 65 villages, including municipalities, with an
estimated 60,000 beneficiaries (JICA, 2007). This accounted for about 40% of
population of the target regions. In order to consolidate the gains made, it is necessary
26 27
that the Electricity Corporation of Ghana regularly cleans its transmission facilities
(this indicates pin insulators, the nonconductors of the transmitters) at least once
a month to stabilize the supply of electricity in the targeted areas. Besides, for the
project to realize its full benefit, it is important that three-phase transformers rather
than single-phase transformers are installed. This will significantly promote the
processing of local agricultural products in addition to promoting the spillover effects
of electricity these regions.
In comparing both energy projects, it is obvious that SHEP complemented NEP in
many respects and ensured that power was extended from main lines to rural areas.
However, the two projects operated under different policies; whereas beneficiaries
under NEP do not contribute 90% of the poles, those under SHEP were required to do
so. Although this ensured that more towns and villages were connected to the national
grid at a lesser cost, it often generates political and social tensions between rival
towns. Towns who get connected under NEP feel more superior and this according
to stakeholders interviewed can fuel ethnic conflicts. Sustainability of both projects
remains questionable unless government and the donor community find a solution to
the deficit incurred by the utility companies.
2.6 Assessment of Donor Policy Influence and Practices on Institutional Impacts
Donor support for electricity expansion has been tremendous and this has
significantly improved institutional development particularly in the areas of capacity
building of staff of VRA and ECG. The project came with skilled contractors which
significantly affected the outcome of the project. It has also significant spillover
effects on other sectors of the economy that relies on electricity. The most worrying
aspects however, relates to the tying nature of most of these donor funded projects.
Stakeholders interviewed confirm the existence of tied aid in the two energy projects
examined. An earlier study by Aryeetey, Osei and Quartey (2003) revealed that
out of three electrification projects studied; only one underwent open competitive
tendering. In one of the surveyed projects, a single source Chinese company provided
the materials and services for the project which was found to be very expensive.
Stakeholders interviewed believed that some savings could have been made from the
project had procurement been tendered through open competitive bidding. The project
managers believed a savings of 25% could have been made had the project been
executed efficiently. Another limitation identified is that Chinese vehicles and funds
were not adequately provided for the supervision of the construction as required under
the agreement.
Another issue relates to the parallel nature of the National Electrification Project
28 29
(NEP) and the Self Help Electrification Project (SHEP). Whereas donors such as
JICA had financed the SHEP others financed NEP but under different conditions
which often generates political tension. Under SHEP, beneficiaries contributed 90%
of the utility poles while the government provided the remaining utility poles, the
transmission equipment and materials and the construction work in order to reduce
the financial burden on government, this did not happen under NEP. Beneficiaries
under NEP did not provide the poles. This has often led to the suspicion that
government uses these parallel programmes to reward party faithful. Besides, there
are no clear cut criteria for selecting which locality benefits from the electrification
programme since some towns and villages are yet to benefit.
A major limitation of donor influence relates to project sustainability. Towns and
villages were connected to the national grid but they are yet to pay for the true
cost of electricity. Whether this should be continually subsidized by government or
other ways are found to generate funds to cover the utility subsidies remains to be
addressed by government and donors. Should urban consumers be taxed to fund the
rural consumers or just like the road fund, a similar means is found to pay for the cost
of electricity and also increase the coverage.
28 29
3. PROJECT CASE B: ANWIANKWANTA YAMORANSA ROAD PROJECT
Prior to the start of the Anwiankwanta-Yamoransa (A-Y) road, an appraisal by
Overseas Economic Cooperation Fund (OECF, previous name for JBIC) in 1986
revealed that out of 28,290km trunk roads (14,130km) and feeder roads (14,160 km) ,
only 5782 km (ie 20.4%) had been paved and often in a deteriorating condition (JBIC,
2002). The Ministry of Highways (2003:11) reports that in 2003, the road network
is 50,000 km long of trunk, feeder and urban roads. The road condition mix was as
follows: 30% good, 21% fair and 49% poor. Of the national road network (39,483 km),
Ghana Highway Authority is managing 35% of the total network and 45% (6,289 km)
of the paved road network. At the time of the OECF appraisal of the A-Y road, the
Government of Ghana was implementing the second phase of the Economic Recovery
Programme (ERP-2), with a focus on agriculture, mining, road and other means of
transport and telecommunications (JBIC, 2002). Within the road sector, the focus was
to improve the coastal trunk network connecting the capital Accra and two hub cities
of Takoradi and Kumasi, of which the World Bank financed the Accra-Takoradi Road
and the Kumasi Road Projects.
3.1 Project Objectives
The A-Y road is an important because export commodities such as Cocoa, Gold
Ore, and Timber from the central Ashanti, and the Western Region are transported
to Takoradi Port for export (Figure 1). Thus, the construction of the A-Y road will
significantly help to achieve the objectives in ERP-2 through export promotion by
removing barriers to road transport. The A-Y road is located within the Central and
Ashanti regions of Ghana. Prior to the inception of project the A-Y road was in a very
bad condition; the old bitumen surfaced road is potholed with several depressions
in several sections. The 75km section from Anwiankwanta to Praso through Bekwai
passes through rolling to hilly terrain with a 3km scarp section near Farmena. The
average width of the carriageway is 5.7m with 1.4m shoulders. Also, the horizontal
and vertical alignment varies from fair to poor. The pavement has old deformed
bitumen surface. Although some badly failed sections were being resurfaced by the
Ghana Highway Authority, there were significantly damaged sections that required
attention. The road goes through several towns and villages and in a number of
the settlements there was very little right of way to allow for widening of the road
without demolition houses. Also, there were a number of bridges in the section which
are narrow and in poor structural condition. The remaining 97km road from Praso
to Yamoransa has poor horizontal and vertical alignment. In addition, it had narrow
pavements and many stretches had deformed posing danger to commuters. Besides,
30 31
the settlements along this section are too close to the road and therefore improvements
in the road will require by-passes.
Figure 1: Anwiankwanta-Yamoransa Road (Project Site)
Given the state of the road and its importance the Government of Ghana
approached the Japanese aid agencies for credit facility to reconstruct the road.
Thus, the main objective of the project is to improve road transport between the
two regions to facilitate trade. The Ministry of Road and Transport is responsible
for planning, construction and maintenance of trunk roads, feeder roads and urban
roads. Implementation is undertaken by three agencies, namely, the Ghana Highway
Authority; the Department of Feeder Roads; and the Department of Urban Roads.
3.2 Scope of the Project
The scope of work includes: (i) Rehabilitation of the A-Y road; (ii) Procurement of
road maintenance equipment; and (iii) Consulting services. The total project cost is
eleven billion, ninety one million Japanese Yen (¥11,091,000,000). The interest rate
was 3.0% per annum and the repayment period was 30 years with 10 years Grace
Period. The loan was partially untied and this explains why Japanese contractors
had to work on the project. The project agreement was signed on September 16, 1987
between the OECF of Japan and the Republic of Ghana. The road was constructed
from 1991-1994 with OECF financing as a single layer Asphalted Concrete pavement
road.
30 31
3.3 Impact of the Project
Effectiveness
The JBIC post evaluation report indicates that all civil works were completed on
schedule and with the exception of the additional replacement of two bridges in `Lot
1’. Also, in order to compensate for the increases in the cost of construction work, some
road maintenance equipment were not procured but this had no adverse effect on the
project outcome. Similar some modifications to the project scope were undertaken
including amendments to the design speed from 60km/h to 8-km/h to correspond
with speeds on other trunk roads in the country (JBIC, 2002). Consequently, the
construction part of the project delayed and was completed approximately two years
later than originally scheduled. This has been attributed to lengthy procurement
approval and review procedure within the Government. It was also reported that
heavy rainfalls (which should have been known at the appraisal stage) in the central
regions during the construction period delayed the civil works but more particularly
road earthworks. Consequently, the total cost increased by 1,300 million Yen due to
sharp increases in the local currency component in addition to increases in earthworks
and underground water problems at the site (JBIC, 2002). It is important to add that
the increment was funded by Government of Ghana.
Despite the shortcoming, the implementation of the project has resulted in the
rise in traffic volumes on the road which hitherto was virtually without much traffic
(Tables 10 & 11). Since the completion of the project, actual traffic volume has exceeded
the projected volume by more than a 100% (JBIC, 2002).
Table 10: Actual Traffic Volume (1987-1998)
1987 1994 1995 1996 1997 1998Planned 424 522 538 554 570 587Actual - 1012 1129 1374 1278 1409
Source: GHA & JBIC (2002)
Table 11: A-Y Road Traffic Volume by Vehicle Types in Selected Sites (1997 Survey)
Section (Km) Light (%) Medium (%) Heavy (%) AADTYamoransa – Tetsi Jct. (24) 52 26 22 1371Tetsi Jct. – Assin Manso (22) 43 48 9 1061Assin Manso - Assin Praso (53) 81 11 8 1606Assin Praso – Asokwa (40) 70 19 11 1242Asokwa – Anwiankwanta (36) 75 13 12 891
Source: GHA & JBIC (2002)
32 33
Prior to the execution of the project, big and heavy commercial vehicles had
considerable difficulty using the A-Y road because it was narrow and mostly unpaved.
However, the completion of the project has led to improved road access to both
passenger cars and commercial vehicles (JBIC, 2002). The increase in traffic volume
obviously implies high economic activity within the project area. In addition, satellite
markets have sprung up with the project area thus providing livelihood for the people.
Compared to other Japanese funded projects (the water sector project, Kumasi-Paga
Road project, the Telecommunication Rehabilitation Project etc), the A-Y road has not
achieved its long term objective. Some parts of the pavement surface started to show
signs of distress even before the construction works were completed. It is clear that
where the road condition is poor, market activities are unable to operate effectively.
An interview with opinion leaders in three communities who make regular use of
the road appreciated the importance of the road. They mentioned that the road had
reduced their traveling time and risk between Kumasi and their communities but
were quick to add that the road was not the best in the country in terms of quality.
The recent increase in road maintenance sometimes creates delays on the road.
According to JBIC (2002:5), an interview of 150 road users living within in proximity
to the A-Y road randomly selected re-affirmed the importance of the road (Table 12).
From Table 12, a significant proportion of sampled individuals (93%) agreed that the
road condition has largely improved or partly improved since the project came into
being. About 79% also indicated that they were `very satisfied’ or `satisfied’ with the
road improvement. This was attributed to `widened’ and `safer’ roads while those who
were not satisfied mentioned `lack of maintenance’ (52%). Many consider the positive
impact of the project as `faster trip to villages’ (45%) and the negative impact is
perceived to be the `increase in accidents’ (53%). It must be added that the survey also
mentioned that in some sections of the A-Y road, there has been sharp increases in
traffic accidents. Although there is no quantitative evidence, residents have indicated
the dangerous spots where accidents mostly occur and this has been attributed to
deteriorating road conditions, neglect of traffic safety regulations. It is not surprising
since traffic law enforcement, including speed limits and axle load control has not seen
much enforcement in the urban but more particularly in the rural areas.
32 33
Table 12: Interview Survey Major Results (n=150)
How much has the condition of the road improved? Largely improvedPartly improvedNot so much improvedNot improved
69%24%
6%1%
Are you satisfied with the level of road improvement? Very much satisfiedSatisfiedLess satisfiedDissatisfied
13%66%16%
4%
If you are very satisfied or satisfied, please explain the reason.
Road has widenedRoad has become saferRoad has been paredOthers
73%21%
3%3%
In case of less satisfied or dissatisfied, please explain the reason.
Roads are still nanowAccidents liave increasedThere is lack of maintenanceOthers2
18%9%
52%21%
What is the positive impact of the project? New shops and factoriesFaster trips to villagesNew housesOthers3
6%45%
6%43%
What is the negative impact of the project? Air pollutionHigher cost of livingIncreases in accidentsOthers4
1%1%
53%45%
Source: JBIC, 2002
Project Sustainability
According to the JBIC A-Y road post evaluation report, the GHA Maintenance
Department is mainly responsible for the Operation and Maintenance (O&M)
activities. However, routine decisions are taken at the regional office level. The report
added that about 90% of such routine periodic maintenance works sub-contracted to
local contractors as suggested by the World Bank. The rest (10%), which is usually
less of labour-intensive and requires more advanced technology are undertaken by the
Mobile Maintenance Unit (JBIC, 2002:7). Figure 2 aptly describes O&M processes with
the A-Y road.
34 35
Figure 2: O & M Processes in Ghana Highway Authority
Ghana HighwayAuthority
Deputy Chief Executive/Maintenance
Plant andEquipment
10 RegionalOfficesStore and Supplies
RoadMaintenance
Central MechanicalWorkshop
Greater Accra, Central, Western,
Brong-Ahafo, Upper West, Volta,
Eastern, Ashanti, Northern, Upper,
East
Mobile MaintenanceUnit I
Mobile MaintenanceUnit II
Bridge MaintenanceUnit
Source JBIC, 2002
The routine maintenance has often been financed by the Government of Ghana
through the Road Fund. In 1985, Ghana was among the first Sub-saharan African
country to establish a Road Fund for road maintenance. The operations of the fund
has since 1997 been restructured in order to ensure a public-private harmonization
in fund management and to strengthen its financial base. The main source of revenue
for the fund include fuel levies, tolls, vehicle license and inspection fees, international
transit fees and other extra-resources as approved by Parliament (Table 13).
Table 13: Road Fund Revenues by Source (Billions of Cedis)
1996 1997 1998 1999Fuel Levy 59.35 98.65 180.60 193.49Bridge Tolls 0.85 1.60 2.36 2.74Road Tolls 0.74 1.83 2.77 3.35Ferry Tolls 0.07 0.06 0.02 0.06Vehicle Registration Fees 1.85 2.10 7.81 11.89Road User Fees 0.00 0.00 0.00 8.05International Transit Fee 0.00 0.00 0.18 0.53Grand Total 62.86 104.24 193.74 220.11
Source: GHA and JBIC, 2002
Since the inception of the A-Y road, the northern sections in particular have
34 35
recorded significant deterioration due to overloaded trucks and non-functional
drainage structure. Despite occasional repairs, such as resurfacing and replacement
of surface asphalt by local contractors and GHA Mobile Moving Unit (MMU), the road
has not yielded the expected results (JBIC, 2002).
DAC evaluation criteria define sustainability as the continuation of benefits from a
development intervention after major development assistance has been completed. It
also refers to the probability of continued long term benefits as well as the resilience to
risk of the net benefit flows over time. In recent times, the Japanese Aid agencies have
established a Counter-Value Fund to support project sustainability of which the A-Y
road is benefiting. As part of the grant process, Japan provides value funds whereby
the recipient government keeps a portion of a loan for a particular project to maintain
the project upon completion. There is also a scheme whereby the Japanese give funds
to the government to undertake crop cultivation and the revenue generated from the
sale of the farm produce is deposited at the Bank of Ghana. As and when needed, the
government applies for it to use to ensure sustainability of other projects. Interviews
with stakeholders such as the GHA and other key beneficiaries have attested to the
fact that Japanese aid strives to ensure sustainability. According to the respondents,
they `establish a maintenance culture where they support the district that will
undertake the road maintenance work with the appropriate equipments’.
Stakeholders at the Ministry of Finance also affirmed the assertion that the
Japanese support projects fully. Food aid and income from other forms of aid are
paid into Bank of Ghana designated accounts collectively called the `Counter Value
Fund’. There is also the non-project grant or aid which is given as some kind of loan
to citizens. When these loans are paid they are also paid into the Counter Value
Accounts. Between 2003 and 2005, $2.8 million of CVF has been used to promote
microfinance for women entrepreneurs, $4.25 million for education and $30,000
for Irrigated agriculture. These funds are for micro-financing, agriculture and
rural infrastructure. In the past, Ghana was allowed to use ¢140 billion for road
construction, ¢7.45 billion to enable COCOBOD to purchase cocoa chemical analyzing
equipment to analyze the chemical content of cocoa particularly those to be exported
to Japan. Currently, a total of ¢35 billion is expected for the school feeding program. It
must be added that Japan’s concentration is in the three northern regions.
The A-Y road is currently being reconstructed by the Japanese government in
collaboration with the Government of Ghana. The ever increasing traffic volume,
especially heavy cargo trucks, but more specifically illegally overloaded cargo trucks
estimated to be 2.3 times of the forecast standard axle, have led to deterioration of the
pavement structure and this has consequently affected the efficient use of the road.
36 37
Policy Reforms
The A-Yroad project cannot be said to be one of the successful infrastructure
projects financed by JBIC because it has started to deteriorate quickly. This is
attributed to (i) Bad soil condition and (ii) Overloaded trucks carrying timber logs
etc. The implementation of this and other infrastructure projects has led to major
policy reforms. First, third party evaluation of roads or other infrastructure projects
is now encouraged by JBIC and the results are published. Secondly, the evaluation
has provided JBIC with information on the condition of the road and also the benefits
enjoyed by the community. It has also led to policies to effectively check the soil
condition of roads as well as overloading.
A third policy reform is that the standards for constructing roads have changed;
previously, the roads had 5cm thickness but now 10cm thickness level is
recommended. Thus solid roads with high standards are being constructed although
they are very expensive. A related issue is that since the project was not satisfactorily
executed, and even signs of failure were observed at the time of handing over, policy
statements were issued on standards of road projects in Ghana. Generally, the project
failed prematurely. Thus, the experience derived from the A-Y road among others
might have informed the blanket instruction given in the 1990s by Col. Mensah (a
former Minister of State) that all asphalt roads in Ghana must be laid with granite
sand, which has no plastic materials. Another major observation in terms of policy
reforms relates to monitoring of projects. At the time of the project implementation,
confidence in foreign contractors and engineers was very high, thus monitoring was
not done on any rigorous basis. However, the outcome of the road project among others
has changed that perception and currently monitoring is done on a very rigorous basis,
just as it is done for jobs undertaken by local firms.
Technology Transfer
Under the A-Y road project, although the contract was won by a Japanese company,
it only worked with 10-15 expatriate staff and with over 1,000 Ghanaian construction
workers. The company came with Japanese equipment and this led to significant
transfer of knowledge to local staff. The project could be said to have contributed to
knowledge transfer in the sector through two facilities promoted by the contractors.
First, as part of the project implementation, some experts of the Ministry and the
GHA were selected and sponsored to take a short course in Construction Management.
The interviewee was a beneficiary and could attest to how the course has helped
in enhancing his professional capacity and that of the ministry and the agency.
Secondly, the consultants on the project also assisted the GHA to prepare a project
supervision manual, titled: Site Operation Manual . Until then, no specific format
or guideline existed for the supervision and preparation of report on projects under
36 37
implementation. The manual has since been used in the sub-sector and presently
forms the basis for all reports presented to the Ministry and its Agencies.
However, personnel at the higher level of management believe the project did not
lead to any significant knowledge transfer. They argued that as far back as 1987, the
GHA was able to provide Engineering Services and also managed major projects such
as the Kaneshie-Ordokor-Mallam road and the Obetsebi Lamptey circle – Korle Bu
road. One of the interviewees served as the acting-Resident Engineer for most part
of the duration of the first project, and then Resident Engineer for the latter project.
Thus, GHA had the capacity and the staff strength to manage and execute major
projects at the time of implementation of the A-Y project. According to personnel of
GHA, they usually send their employees on `secondment’ to work on such projects
and the technology used was essentially the same. Thus, no particular knowledge or
technology transfer could be cited. For young Engineers who had the chance to visit
the site, the only thing is the site experience, which comes with any project.
Capacity Development
The viewpoint that most local contractors do not have capacity was also emphasized
under the road project. At the time the A-Y road was being constructed, local
contractors simply did not have the capacity to execute such project and this has not
changed over the years. The managerial capacity of local firms was extremely low,
and they also exercise very low commitment to ensuring quality. In terms of capacity
to form partnership with foreign contractors, the defunct Kasadjan construction firm
could be cited as an example of such potential. The firm was largely a Lebanese-
Ghanaian partnership though at the onset it was influenced extensively by its
Lebanese partner. At the peak of its operations, the firm was managed entirely by
Ghanaians and could construct an asphalt road (Kumasi and Sunyani for instance) in
as far back as 1988.
Institutional Changes
GHA had the capacity at the time of implementing the road project to play the role
of the expatriate Engineers but they worked on jobs fully financed by the Government
of Ghana (GoG). No major institutional change has occurred in the past; nevertheless,
in the past, when most projects were financed by GoG, GHA used to be involved
extensively in the entire cycle of projects, but had to scale down because most projects
were financed from external sources. Recent increase in GoG financed projects has
led to a return to the old order. In terms of institutional changes, various units of
GHA are charged with the management of various stages of project cycle. This has
helped to strengthen the present institutional setup of GHA. Even at present, when
suggestions have been made for some reforms, GHA still undertakes its operational
38 39
responsibilities including raising resources to finance its investment needs.
3.4 Comparison with Reference Project (Accra-Yamoransa Road)
The A-Y road was specifically selected as a reference project because it links
the Yamonsa-Cape Coast road and has been one of the excellent road networks
reconstructed in Ghana in the 1990s by the Construction Pioneers (CP). The proposed
reconstruction includes expanding a short 16.4 km section to dual carriageway,
widening other sections to a uniform standard, which would provide design speeds
for 100km/hr on all but one 16 km section through hilly terrain, where an 80km/hr
design is acceptable. Climbing lanes are also provided to increase capacity on steep
grades (4-5%), where the speed of a loaded truck is expected to be reduced by more
than 16 km/hr below average travel speeds and where total traffic and the percentage
of trucks warrant their use. Table 14 indicates characteristics of each section of the
Accra-Yamoransa Road. Roadway capacity analysis has been carried out using the
Highway Capacity Manual, Special Report 209, TRB, 1985. As a result, a four lane
cross section was proposed for the 16 km link closest to Accra and two lanes for the
remaining sections. The economic assessment employed the RODEMAN program,
which is a slightly simplified version of the World Bank HDM-III model. The ERRs for
each of the six sections are presented in Table 14.
Table 14: Characteristics of the Accra-Yamoransa Road
AADT Est. 1993
AADT 2011
Lanes Proposed
Length (km) Terrain ERR
(%)Accra-Mallam 5500 21500 2X2 16.4 Flat/R 30Oduponkpehe 5000 16300 2Oduponkpehe-Awutu 3200 8500 2 10.2 Hilly 30Awutu-Winneba Jct. 2900 7700 2 20.9 Hilly 32Winneba Jct. Apam Jct. 2550 6800 2 14.2 Flat 22Apam Jct. – Mankesim 2150 5700 2 30.7 Rolfing 8Mankesim - Yamoransa 2750 7300 2 23.9 Various 33TOTAL 116.3 25
Source: World Bank (1999), Highway Sector Investment Project Staff Appraisal Report
The A-Y road compares very well with the Accra Yamoransa road; both deteriorated
quickly with the latter deteriorating faster than the former. Inadequate funds to
undertake maintenance coupled with overloading significantly affected the project
outcome. Whereas the A-Y road was funded by a bilateral donor, the latter was
financed by a multilateral. Whereas the JBIC project did not undergo open competitive
bidding, the Accra-Yamoransa project did. Despite these similarities and differences,
38 39
both projects deteriorated quickly and it is not evident what role the type of donor
played
3.5 Assessment of Donor Policy Influence and Practices on Institutional Impacts
In terms of aid for infrastructure development, only a few donors are directly
involved as depicted in Figure 3 below and this has been the trend since the 1980s.
The road project which was mainly donor financed was demand driven and therefore
country ownership was highly considered. The project appraisal report mentions that
the Government of Ghana approached the Japanese government for assistance to
support the project. The road project coincided with the period when the Japanese
had little influence on aid allocation except for technical matters. During the period,
Japanese were noted for being less `intrusive’ in policies or programmes of national
governments. Aryeetey and Cox (1995) observe that the transformation of Japan into
the single largest source of bilateral assistance went for a long time unnoticed by many
Ghanaians. Many have argued that this development had taken place without much
notice mainly due to the usually `low profile’ nature of Japanese officials in Ghana.
The `low profile’ signifies the non-involvement of Japanese aid officials in what they
perceived to be `domestic affairs’. Japanese aid officials were seen to be unlikely to
discuss with government and civil society in Ghana, aid issues of a non-technical nature
although this attitude has been changing over time.
Indeed, in the 1990s Japanese aid officials begun to show interest in the
management of aid resources beyond technical issues, a development that surprised
a number of Ghanaian officials. During the policy dialogue between the Ghana
Government and the Japanese Government in March 1995, the Japanese side
emphasized the need for `transparency and accountability’ in ODA use as a major
principle for convincing Japanese taxpayers about the necessity of ODA and stressed
the importance of `good governance’ as a conditionality (Aryeetey and Cox, 1995).
This marked a major departure from previous discussions where `the Japanese never
insisted on non-technical conditions’6. The dialogue signaled new Japanese interest
in issues beyond economic and technical cooperation. The new development brought
Japanese aid conditions closer to those of other bilateral donors. It is therefore not
surprising that Japanese aid has moved beyond technical cooperation and even
into budget support currently; highlighting the interest in non-technical nature of
Japanese aid.
6 This refers to issues involving the use of technical cooperation in Japanese ODA which used to be the focus of Japanese aid until interest in issues of governance, etc took the centre stage in Japanese aid modalities.
40 41
Figure 3: Donor Support for Infrastructure Development (2003-2005)
Source: Development Partners (DPs) Envelope June 2006
Table 15: Tied and Untied Aid (Bilateral) to Electricity & Roads Sub-sectors in Ghana
Source: Ministry of Finance, Ghana
A major donor factor which affected the outcome of the project is the issue of tied
aid. A micro-economic study of tied aid by Aryeetey, Osei and Quartey (2005) on the
energy and road sub-sectors of the economy revealed that while stakeholders including
project managers felt project funds have been of tremendous assistance to Ghana,
they also argued that they would have had greater impact on the community and help
reduce poverty if there had been no delay in securing counterpart funds, and if the
high cost of materials and services of consultants had been contained. On average, it
is estimated that the sampled projects would have saved 18% of the cost had the funds
not been tied to conditions and if procurements had been subject to open competitive
bidding (Table 15 & also see appendix).
40 41
Project staff observed that only foreign contractors worked on the road projects.
While this ensured that quality roads were constructed, the practice did not promote
local capacity-building. It is argued that it would have been more appropriate if foreign
contractors teamed up with local firms to strengthen existing local capacity. Secondly,
road maintenance funds were woefully inadequate which has affected the general
sustainability of road projects in Ghana. Government has not been able to match the
growing donor support for road infrastructure with an equally significant amount of
resources for road maintenance. Consequently, more new roads are being funded by
donors and the government while old ones are left to deteriorate. This phenomenon is
not new, according to the World Bank’s HSIC staff appraisal report (1999), `there has
been increasing concern that insufficient funds are being allocated for maintenance
while new reconstruction works continue to be funded’. The charging of road tolls to
cover part of the maintenance has not been widely accepted. It has been argued that
before road tolls are charged, there should be alternative routes so that those who
are not willing to pay the toll can use. Unfortunately, there is hardly any alternative
route connecting major cities and towns in Ghana except a major road. This obviously
explains why road tolls form less than 5% of total revenue from roads. Unfortunately,
the 1996-2000 Road Sector Expenditure Programme which was jointly developed by
the government, user groups, Parliament sub-committee for infrastructure and all
donors active in the sector (OECF, KfW, EU, the Dutch Government, BADEA, OPEC,
DANIDA, USAID and ADF) is yet to turn the situation round.
42 43
4. CONCLUSIONS AND POLICY IMPLICATIONS
The paper investigates aid effectiveness in infrastructure, particularly, its impact on
policy reforms, transfer of knowledge and organizational capacity to plan, implement
and operate, and human resources development in general. Two infrastructure
projects in Ghana, an energy project and a road project were selected based on set
criteria outlined above. Secondary data such as project contracts, project completion
reports and other secondary data sources were used to complement primary
information. The primary data was obtained from interviews with donors and relevant
stakeholders.
A major finding from the study is that the project, particularly, the road sector
project which has been referred to as a `failed project’ has led to significant policy
reforms. New road standards has been adopted and the use of external or third party
monitoring and evaluation is now been used by JBIC in all of its projects in Ghana.
The energy project also highlighted a policy failure as a result of parallel sources
of funding and guidelines for energy projects in Ghana. Whereas beneficiaries of
donor financed energy projects do not pay connection fee, their counterpart in nearby
communities who connect under SHEP are required to pay a fee. Thus, it is believed
that infrastructure projects are used to reward the `political faithful’. Another
interesting observation from the stakeholder interviews is that more technology
transfer occurred at the lower level of personnel than at the management level. Most
management personnel have been trained locally or overseas to meet the standards
of the foreign consultants. A related issue is that a greater proportion of lower level
personnel are hired locally and they have benefited considerably from the new
technology and better ways of doing things. It was also evident that most major donor
funded infrastructure projects are executed by foreign companies sometimes tied to
the loan facility. Even in cases where local contractors could bid for such projects,
it is believed they did not have the capacity to do so single handedly or to form
partnerships with foreign companies. However, when the local contractors are sub-
contracted and supervised by the foreign ones, they are able to deliver.
Despite the benefits or impacts outlined above, major challenges remain. For
infrastructure projects to be successful, certain conditions must exist for the
institutional effects to be significant. First, the project must be country owned, there
should be enough funds to ensure maintenance, must be economically viable in some
cases, donor influence has to be minimal and quality has to be key. In addition,
regulations on usage must be enforced to the maximum. Unfortunately, in the projects
discussed above, many of these were lacking. Lack of third party monitoring and
42 43
evaluation has affected the impact of infrastructure projects in Ghana. Secondly,
land conflicts and chieftaincy disputes affected the completion of the energy projects
in some selected communities. The road project failed because of poor soil quality,
overloading and the absence of third party evaluation of the project.
The policy lessons to be drawn from this are: first, there should be a properly
enforced regulation on the use of infrastructure in the country. Weighing stations
should be set up at the entrance and exit of major roads and the maximum loading
capacity should be strictly enforced. Secondly, the connection fee to electrification
projects should be uniform to minimize the political patronage problem. Also important
is the need to minimize land conflicts and chieftaincy disputes in the country through
effective implementation of the Land Administration Project. Finally, support should
be provided to upgrade the skills and competencies of local contractors to a point
where they can jointly bid with foreign companies for infrastructure projects. This
should be complemented with policies to consciously promote partnership between
local and foreign contractors.
44 45
REFERENCES
Arakawa H and Wakabayashi J (2006), Budget Support and Aid Effectiveness: Experience in East Asia, JBIC Review, No. 14
Aryeetey, E., and A. Cox (1997), ‘Aid Effectiveness in Ghana’, in J. Carlson et al. (eds), Foreign Aid in Africa: Learning from Country Experiences. Motala Grafiska, Sweden.
E. Aryeetey, J. Harrigan and M. Nissanke (2000), Economic Reforms in Ghana: The Miracle and the Mirage. London: James Currey Ltd.
Aryeetey, E., O. Baffour, and P. Quartey (2003), ‘Does Tying Aid make it More Costly? A Ghanaian Case Study’, Paper presented at the workshop on ‘Quantifying the Impact of Rich Countries’ Policies on Poor Countries’, 23-24 October. Washington, DC: Center for Global Development and the Global Development Network.
Nissanke and Aryeetey (2003), Comparative Development Experiences of Sub-Saharan Africa and East Asia: An Institutional Approach, Chapters 1&2, Ashgate, UK
Institute of Statistical Social and Economic Research (2005), State of Ghanaian Economy Report, ISSER, University of Ghana
Japan Bank for International Cooperation (2002), Ex-post Evaluation Report of Anwiankwanta-Yamoransa Road Rehabilitation Project
Japan International Cooperation Agency (2007), The Project for Electrification of Lower Volta Area, Ex-post Evaluation Report.http://www.jica.go.jp/english/evaluation/reports/ex-post/14-14-53.html. (Assessed December 2007)
Jerome A and Ariyo A (2004) Infrastructure Reform and Poverty Reduction, a paper presented at the TIPS / DPRU Forum, 2004
Keener S.K and Banerjee G (2005), Ghana: Poverty and Social Impact Analysis of Electricity Tariffs, ESMAP Technical Paper 088, World Bank, Washington DC
Ministry of Roads and Transport (2003), Road Sector development Review Report 2003
OECD (2006), 2006 Survey on Monitoring the Paris Declaration, Ghana Chapter, OECD, Paris.
Osei, R., and P. Quartey (2001), ‘The HIPC Initiative and Poverty Reduction in Ghana: An Assessment’, WIDER Working Paper No. 2001/119, Helsinki: UNU-WIDER.
Public Utilities Regulatory Commission Data, 2002
Quartey, P. (1997). The Macroeconomic Impact of Aid on Economic Growth: A Comparative Analysis of Ghana and Malaysia’. Warwick: University of Warwick MA Dissertation.
44 45
Quartey, P. (2005). ‘Innovative Ways of Making Aid Effective: Tied Aid versus Direct Budgetary Support’, Journal of International Development, Vol. 17, pp 1077-1092
Volta River Authority (2000), National Electrification Project, Implementation Completion Report, Accra, Ghana
World Bank (1999), Highway Sector Investment Program, Staff Appraisal Report
World Bank (2001), National Electrification Project Implementation Completion Report, World Bank Energy Unit, Africa Region
World Bank (2003), World Development Indicators, World Bank, Washington DC
World Bank (2005), World Development Indicators, World Bank, Washington DC
46 47
APPENDICES
Appendix 1
Table A1: Aid Flow to Ghana by Major Donors (2003-20067)
Source: World Bank, 2006
7 2006 figures are up June only
46 47
Table A2: Total Disbursements by Economic Activity (2003-2006)
Source: Extracted from DPs Envelope, June 2006
48 49
Appendix 2: Interview Guide
QUESTION GUIDE
GOAL: The focus of the research is to ascertain the “processes of institutional
changes associated with the two infrastructure projects and the relationships
between those institutional changes to the overall impact of the infrastructure
projects”. The study will examine impacts “related to ideas influencing policy,
transfer of knowledge and lessons learned, organizational capacity to plan,
implement and operate, and human resources development in general.”
1. Ideas Influencing Policy
How was this infrastructure project designed? And how did the community’s need for
the project reach the government? Were members of your community consulted in
designing this project? Who were the contractors of this project? Were they local or
foreign? Were the contractors selected on a competitive basis or they were part of the
programme conditionalities? How useful is this project to the community? What policy
lessons can we draw from this project? Do you think the outcome of this project has
influenced policy in anyway?
2. Transfer of Knowledge
How many people were directly employed on this project? Were there local employees?
What proportion were local employees? Were they middle and low level personnel or
some were part of management? Did the project sub-contract some of its components
to local contractors? If yes, were they executed satisfactorily? Were the local employees
on this project familiar with the technology used by the contractor? Or a new
technology was used. Did the project promote technology transfer in Ghana within the
sub-sector?
3. Organizational Capacity (plan, implement and operate, and human resources
development in general).
Does the District Assembly in the community where the project was implemented
have the capacity to plan a demand-driven infrastructure project? During the project
phase, did your organization have the capacity to (i) Plan (ii) Implement (iii) Operate
the project? Was your organization adequately staffed? Did the project lead to human
resource development in your organization? If yes, in what way?
Were local contractors or personnel involved in the project implementation?
Do you think local contractors have the capacity to form partnerships with foreign
contractors or they should be sub-contracted by the main executors of the project?
Do you think infrastructure projects in your area led to human resource development
48 49
in general?
4. Institutional Processes (use a specific project)
Please describe the institutional changes that have occurred in this organization over
the past ten yearsIn what way has these changes affected
- project identification
- project preparation
- Appraisal
- Approval
- Implementation
- Evaluation
Are there any specific factors explaining success or failure?
What was the role of the JBIC office, the World Bank office in the design and
implementation of the project? Did these institutions affect (positive or negative) the
outcome the project? Was there any political factor or influence which affected the
outcome of the project?
What other institutional challenges do you think may have affected the outcome of the
project (be specific). Example, lateness, dedication of some key staff etc
50 51
Appendix 3: Institutions & Persons Contacted and/or Interviewed
NAME INSTITUTION ADDRESSMr. Samuel Adjidjonu Deputy Manager (Rural Projects),
Electricity Company of [email protected]
Mr. Kenji Murata Assistant Resident Representative and Acting Head (Transport) – Japan International Cooperation Agency
[email protected], 0243702407, 021760781/2
Shinichi Tamamitsu Embassy of Japan, Accra [email protected] Mr. Michael Abbey Director of Contracts, Ghana
Highways [email protected], 0244709643, 021666591/4
Mr. E.K. Twumasi Deputy Director, Monitoring and evaluation. Ministry of Transportation
[email protected], 0249251483
Mr. Emmanuel D. Osafo Principal Electrical Engineer, Volta River Authority
[email protected], 025120620
Mr. Richmond Evans Appiah
Director of Engineering Services. Volta River Authority
Mr. Samuel Abu-Bonsrah Head of Japan, Ghana and South Korea Desk. Ministry of Finance and Economic Planning
Mr. Boakye-Appiah Divisional Manager (Urban Projects). Electricity Company of Ghana.
0208118709
Mr. B.K. Dapatem Former Divisional Manager (Urban Projects). Electricity Company of Ghana.
0244323253
Edumfa, AgyiriKrom, Abaka, Yamoransa
Assemblyman and Community Leaders
50 51
Project Specific Cost of Tied Aid in Ghana
52
Japan’s Assistance to Ghana
Disbursements by Japanese Fiscal Year (April-March) and by Type (100 million Japanese Yen)
Fiscal Year
Loan Aid Grant AidTechnical
Cooperation
2000 Project for Eradication of Poliomyelitis (1.09)•Project for Improving Primary Health Care (6.51)•Project for Rural Water Supply (5.11)•Non-project Grant Aid (20.00)•Grant Aid for Increase of Food Production (4.00)•Food Aid (2.80)•Grassroots Projects (18 projects) (0.69)•
(Total 23.98)(Total 40.20)
2001 Project for Construction of Small and Medium Scale Bridges (2.62)•Project for Eradication of Poliomyelitis (through UNICEF) (1.02)•Food Aid (3.00)•Grassroots Project Grants (27 projects) (0.78)•
(Total 21.95)(Total 7.42)
2002 The Project for Construction of Small and Medium Scale Bridges (6.03)• Infectious Diseases Prevention for Childlen (through UNICEF) (1.00)•The Project for Rural Electrification (7.55)•The Project for Rehabilitation of Trunk Road (1.16)• Supply of Sound and Lighting Equipments to the National Theater •(0.45) The Construction of School Building at Kajero (0.04)• Supply of Second-Hand Ambulance to Okomfo Anokei Teaching •Hospital (0.02)Grassroots Project Grants (13 projects) (0.51)•
(Total 17.79)(Total 16.76)
2003 The Project for Rehabilitation of Trunk Road (9.98)• Infectious Diseases Prevention for Children (through UNICEF) (1.16)• The Project for Construction of Small and Medium Scale Bridges (1.36)•The Project for Rural Electrification (3.06)• Non-Project Grant Aid (5.00)• Supply of Sports Equipment to National Sports Stadium (0.04)• Grassroots/Human Security Project Grants (19 projects) (1.20)•
(Total 15.55)(Total 22.19)
2004 Debt Relief •(1,046.78)
The Project for Rehabilitation of Trunk Road (17.78)•The Project for Rehabilitation of Trunk Road (1.13)• Infectious Diseases Prevention for Children (through UNICEF) (1.18)•Sector Programme Grant Aid (5.00)•Grassroots Cultural Grant (1 project) (0.01)•Grassroots/Human Security Project Grants (2 projects) (0.17)•
(Total 18.74)(Total 25.27)
2005 The Project for Rehabilitation of Trunk Road (21.89)•Non-Project Grant Aid (5.00)• Infectious Disease Prevention for Children (through UNICEF) (3.00)• Grant for Increase in Food Production with Special Emphasis on •Under Privileaed Farmers (3.60) Grassroots Cultural Grant (0.46)•Grassroots/Human Security Projects Grants (6 projects) (0.38)•
(Total 19.44)(Total 34.33)
2006 The Project for Rehabilitaion of Trunk Road (14.61)•The Project for Rural Electrification (6.78)• Improvement of Fundamental Medical Equipment in Upper West •Region (1.63) Infectious Diseases Prevention for Children (through UNICEF) (2.98)•Sector Programme Grant Aid (14.00)•Grassroots/Human Security Project Grants (6 projects) (0.26)•
(Total 2.74)(Total 40.26)
2007 DebtRelief
The Project for Rural Electrification (4.10)•Infectious Diseases Prevention for Children (through UNICEF) (1.22)•
up to October 2007(Total 5.32)
Source: http://www.mofa.go.jp/policy/oda/data/05ap_af02.html#GHANA
JBICI Research Paper No. 36-1
July 2008
ISSN 1347-5703
4-1, Ohtemachi 1-chome, Chiyoda-ku, Tokyo 100-8144, Japan
Tel: 03-5218-9720 (JBIC Institute)Internet: http://www.jbic.go.jp/ Recycled paper
JBICI R
esearch Paper No. 36-1
JBIC InstituteJapan Bank for International Cooperation
July 2008
Aid Effectiveness to Infrastructure:A Comparative Study of East Asia and
Sub-Saharan Africa
Framework Paper
Aid Effectiveness to Infrastructure: A
Com
parative Study of East Asia and Sub-Saharan A
frica, Framew
ork Paper