Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

download Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

of 37

Transcript of Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    1/37

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    2/37

    FiT in Malaysia: The Beginning

    2June 2005: Study mission to Berlin, Germany

    2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    3/37

    Why FiT Stern Review Report:

    Sir Nicholas Stern stated that Comparisons between deploymentsupport through tradable quotas and feed-in tariff price support suggestthat feed-in mechanisms achieve larger deployment at lower costs.

    UNDP-GEF Report: Promotion of Wind Energy - Lessons Learned FromInternational Experience and UNDP-GEF Projects

    Feed-In tariff policies have been very effective in Germany, Spain ande

    nmar , ea ng o e wor s rs , secon an ns a e w nenergy capacities.

    International Energy Agency: Deploying Renewables - Principles for EffectivePolicies

    Feed-in Tariffs are more effective and cheaper than quotas for RE Ernst & Young Report: Renewable Energy Country Attractiveness Indices:

    Feed-in Tariffs are cheaper than Trading System

    Traditional RPS country/state moving towards Feed-in Tariff

    3 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    4/37

    Learning Process: from Pioneer of FiT

    4 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    5/37

    Learning Process: from Pioneer of FiT

    5 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    6/37

    Learning Process: from FiT Advocates & RE Policy Experts

    6 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    7/37

    Learning Process: from Other Countries & Reports

    Germany Italy

    Thailand Taiwan Spain

    South Korea USA France

    Portugal Switzerland Others

    7 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    8/37

    Must be guaranteed via the RE Act, whereby:

    Access to the grid is guaranteed utilities legally obliged to accept all electricitygenerated by RE private producers.

    Local approval procedures are streamlined and clear . FiT rates must be high enough to produce a ROI plus reasonable profit (not

    excessively) to act as an incentive.

    FiT rates will be fixed for a period (typically 20 years) to give certainty and

    Critical Factors for an Effective FiT Implementation

    provide businesses with clear investment environment.

    Adequate " degression " for the FiT rates to promote cost reduction to achievegrid parity

    Adequate fund is created to pay for the FiT rates (incremental cost) andguarantee the payment for the whole FiT contract period.

    The design of the FiT must be customized to suit contextual conditions of thecountry.

    Implementation by a competent body in a professional manner that includesconstant monitoring, progress reporting and transparency .

    8 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    9/37

    Malaysia: Renewable Energy Policies

    8 th Malaysia Plan (2001 2005)RE as the 5th fuel

    Implied 5% RE in energy mix

    th

    300 MW in Peninsular Malaysia

    50 MW in Sabah

    10 th Malaysia Plan (2011 2015) & beyondNew RE Policy & Action Plan

    9 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    10/37

    National Renewable Energy Policy

    Approved by Cabinet on 2 nd April 2010

    Policy Statement: Enhancing the utilisation of indigenous renewable energy

    resources to contribute towards national electricity supply security- .

    Strategic Thrusts (RE Action Plans):1. Introduce appropriate regulatory framework.

    2. Provide conducive environments for RE businesses.3. Intensify human capital development.4. Enhance RE research and development.5. Design and implement an RE advocacy programme.

    10 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    11/37

    10 th Jun 2010: 10 th Malaysia Plan (chapter 6) 15 th Oct 2010: National Budget 2011 (paragraph 34) 25 th Oct 2010: Economic Transformation Programme (chapter 6)

    Feed-in Tariff: Government Policy

    11 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    12/37

    Renewable Energy Bill

    RE Bill: an Act to provide for the establishment and implementation of aspecial tariff system to catalyse the generation of renewable energyand to provide for related matters.

    Part I: Preliminary Part II: FiT System

    , Part IV: Feed-in Tariff Part V: Renewable Energy Fund Part VI: Information Gathering Powers

    Part VII: Enforcement Part VIII: General Part IX: Savings and Transitional

    Passed in Parliament: April 201112 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    13/37

    Definition of Renewable Energy

    Renewable Energy (RE) is any form of primary energy fromrecurring and non-depleting indigenous resources, such asagricultural produce, hydro-power, solar, wind, solid-waste, etc.

    13 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    14/37

    RE Law Enables Feed-in Tariff System

    Establishment of FiT System

    Biogas

    Small

    Biomass

    Solar PV

    Hydro

    Feed-in Tariff (FiT) system provides:

    Connection to supply line by RE installationsPriority of purchase and distribution by DL

    Payment by DL to FIAH according to FiT rates

    14 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    15/37

    20,000

    25,000

    30,000

    W

    Cumulative RE Installed Capacity

    Solar PP

    Solar PV

    Small Hydro

    Biomass-WasteBiomass

    Biogas-Waste

    Biogas

    20303.5 GW

    20202.1 GW

    205011.5 GW

    2030:7,088 MW (25%)

    2050:26.3 GW (74%)42.6 GWh/Yr (19%)Cum. 597.2 mil T-CO2

    National RE Goals

    -

    5,000

    10,000

    ,

    2 0 1 1

    2 0 1 2

    2 0 1 3

    2 0 1 4

    2 0 1 5

    2 0 1 6

    2 0 1 7

    2 0 1 8

    2 0 1 9

    2 0 2 0

    2 0 2 1

    2 0 2 2

    2 0 2 3

    2 0 2 4

    2 0 2 5

    2 0 2 6

    2 0 2 7

    2 0 2 8

    2 0 2 9

    2 0 3 0

    2 0 3 1

    2 0 3 2

    2 0 3 3

    2 0 3 4

    2 0 3 5

    2 0 3 6

    2 0 3 7

    2 0 3 8

    2 0 3 9

    2 0 4 0

    2 0 4 1

    2 0 4 2

    2 0 4 3

    2 0 4 4

    2 0 4 5

    2 0 4 6

    2 0 4 7

    2 0 4 8

    2 0 4 9

    2 0 5 0

    M

    Year

    2020:3,140 MW (14%)12.6 GWh/Yr (9%)Cum. 45.6 mil T-CO2

    .

    Cum. 165.7 mil T-CO2

    2015:1,275 MW (7%)5.7 GWh/Yr (5%)Cum. 11.3 mil T-CO2

    15 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    16/37

    RE Law Schedule: Biogas

    16 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    17/37

    RE Law Schedule: Biomass

    17 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    18/37

    RE Law Schedule: Small Hydropower

    18 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    19/37

    Schedule: Renewable Resources, FiT RatesRE Law Schedule: Solar PV

    19 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    20/37

    FiT Rates = Empirical Value

    ConduciveFiT rates

    20 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    21/37

    Basis of Determining FiT Rates:Economic Viability of RE Projects

    Factors Biomass Solid Waste Solar PV

    IRR (based on typical rates forpower generation sector)

    8% - 13% 8% - 13% 5% - 12%

    Simple Payback Period (SPB) < 7 years < 7 years < 12 years

    Positive cash-flow Yes Yes Yes / Neutral

    Factors to calculate IRR Biomass Solid Waste Solar PV

    Capital expenditure 6-8.5 RM/W RM/W RM/W

    Loan rates & tenure 7-8.8%, 15 yrs 7-8.8%, 15 yrs 6-7%, 15 yrs

    Fuel cost & transport 30 RM/tonne N/a N/a

    O&M cost, depreciation, insurance % of capex % of capex % of capexAnnual cost increment 3% 4% 3%

    Revenues: FiT duration 16 yrs 21 yrs 21 yrs

    Capacity factor 70% 70% 13-16%%

    Other revenue N/a Yes N/a21 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    22/37

    Cost Breakdown forAverage Domestic Electricity Tariff

    Subsidized Fuel for Power Generation

    Generation CostTransmission & Distribution CostFiT LevyCustomer Service Charge

    FiT Cost 1% collection goes to REFund under the RE Law

    RE Fund: Allocation from Electricity Tariff

    38%

    25%

    20%

    1%16%

    2011 22

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    23/37

    1,000

    1,200

    1,400

    i o n

    Annual RE Fund vs Annual FiT Transaction Cost

    Annual RE Fund

    Annual FIT Cost

    Final RE FundCollection

    (2030)

    RE Fund

    start

    RE Fundincrement

    The quota (MW) allocated foreach RE technology for eachyear is based on the:

    Availability of RE Fund

    Balancing Act: RE Fund VS FiT Transaction Cost

    -

    200

    400

    600

    2 0 1 1

    2 0 1 2

    2 0 1 3

    2 0 1 4

    2 0 1 5

    2 0 1 6

    2 0 1 7

    2 0 1 8

    2 0 1 9

    2 0 2 0

    2 0 2 1

    2 0 2 2

    2 0 2 3

    2 0 2 4

    2 0 2 5

    2 0 2 6

    2 0 2 7

    2 0 2 8

    2 0 2 9

    2 0 3 0

    2 0 3 1

    2 0 3 2

    2 0 3 3

    2 0 3 4

    2 0 3 5

    2 0 3 6

    2 0 3 7

    2 0 3 8

    2 0 3 9

    2 0 4 0

    2 0 4 1

    2 0 4 2

    2 0 4 3

    2 0 4 4

    2 0 4 5

    2 0 4 6

    2 0 4 7

    2 0 4 8

    2 0 4 9

    2 0 5 0

    R M - m

    i l l

    Last REPPA (FiT) (21 years)

    First REPPA (FiT) (21 years)

    2 0 4 8

    RE Fund.

    23 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    24/37

    FiT Quota: Open & Transparent Platform

    24 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    25/37

    FiT Rates: Open & Transparent Platform

    25 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    26/37

    RE Fund: Open & Transparent Platform

    26 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    27/37

    FiT Application: Online

    FiT quota approvals onfirst come, first servedbasis upon submission

    of complete application &document

    FiT quota is dynamic

    27 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    28/37

    Other Critical Issues: RE Connection & Approvals

    PMU132kV / 33kV

    PPU33kV / 11kV

    PE11kV / 0.4kV

    Feeder Pillar0.4kV / 0.23kV

    PPU

    DL AFiT Meter

    33kV / 11kV

    DL B

    1MW

    DL Meter

    DL Meter

    FiT Meter28 2011

    DL Meter

    FiT Meter

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    29/37

    FiT Payment

    RE installations Biogas Biomass Small Hydro Solar PV

    RE installed capacity [A] 4 MW 10 MW 10 MW 6 kW

    RE generation/month [B]2,044

    MWh/month5,110

    MWh/month4,166.67

    MWh/month600

    kWh/month

    FiT payment is calculated based on actual kWh reading by the revenue meter[ (new kWh reading minus last kWh reading) x FiT rate ]

    FiT rate [C].

    per kWh

    .

    per kWh

    .

    per kWh

    .

    per kWh

    FiT duration [D] 16 years 16 years 21 years 21 years

    FiT payment by TNB to FIAH per

    month= [ C x B ]

    RM

    694,960per month

    RM

    1,686,300per month

    RM

    1,000,000per month

    RM

    876per month

    Capex RM 40 mil RM 90 mil RM 90 mil RM 90,000

    Simple Payback Period 4.8 4.5 7.5 8.629 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    30/37

    Recovery of FiT Payments by Power Utilities

    RE Fund (SEDA)

    SEDA

    (U) (S) (A)

    (F) FiT payment

    (D) Displaced Cost

    (S) = (F) - (D) Recovery of Money

    (U) = 2% x (S) Admin fee to DL

    (A) = 3% x (S) Admin fee to SEDA

    30

    Distribution Licensee

    FIAH

    (F)

    (D) (S)

    Grid Connection PointDisplaced

    Cost

    Medium voltage 1kV 0.2047

    Low voltage

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    31/37

    FiT Degression: To Promote cost reduction towards Grid Parity

    Degression rate to commence on 1 st January every yearRevision: at least once every 3 years

    31 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    32/37

    1.00

    1.10

    1.20

    1.30

    1.40

    1.50

    1.60

    1.70

    1.80

    W h

    Displaced Cost (LV)

    Displaced Cost (MV)

    FiT BiogasFiT Biogas-Waste

    FiT Biomas

    FiT Biomass-Waste

    FiT Small Hydro

    Degression & Grid Parity (Projected)

    Upon grid parity:FIAH will be paid prevailing DC rate.DL cannot claim from RE Fund (SEDA)

    0.00

    0.10

    0.20

    0.30

    0.40

    0.50

    0.60

    0.70

    0.80

    0.90

    2 0 1 1

    2 0 1 2

    2 0 1 3

    2 0 1 4

    2 0 1 5

    2 0 1 6

    2 0 1 7

    2 0 1 8

    2 0 1 9

    2 0 2 0

    2 0 2 1

    2 0 2 2

    2 0 2 3

    2 0 2 4

    2 0 2 5

    2 0 2 6

    2 0 2 7

    2 0 2 8

    2 0 2 9

    2 0 3 0

    2 0 3 1

    2 0 3 2

    2 0 3 3

    2 0 3 4

    2 0 3 5

    2 0 3 6

    2 0 3 7

    2 0 3 8

    2 0 3 9

    2 0 4 0

    2 0 4 1

    2 0 4 2

    2 0 4 3

    2 0 4 4

    2 0 4 5

    2 0 4 6

    2 0 4 7

    2 0 4 8

    2 0 4 9

    2 0 5 0

    R M /

    FiT Solar PV

    FiT Solar PP

    Grid Parity

    32 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    33/37

    Other Critical Factors: Quality Standard and Reliable Services

    2011 33

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    34/37

    Sustainable Energy Development Authority of Malaysia

    (SEDA Malaysia)

    Ministry of Energy, Green Technology & Water

    Energy Green Technology Water

    Electricity SectorRE (& EE)

    SectorGreen Technology

    Sector Water & Sewage Sector

    ST

    Regulator

    SEDAImplementing

    Authority

    MGTC

    Green TechnologyPromoter

    SPAN

    Regulator

    JBA

    ImplementingDepartment

    JPP

    ImplementingDepartment

    34 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    35/37

    SEDA Bill

    SEDA Bill: an Act to provide for the establishment of the SustainableEnergy Development Authority of Malaysia and to provide for itsfunctions and powers and for related matters.

    Part I: Preliminary Part II: The Authority

    Part IV: Employee of the Authority Part V: Finance Part VI: General

    sustainable energy means energy which, in its generation, provisionand use, is such that it meets the needs of the present withoutcompromising the ability of future generations to meet their needs,and includes renewable energy.

    35 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    36/37

    Part III S.15: Functions of SEDA Malaysia

    a) Advise the Minister & Government entities on all matters relating to sustainableenergy;

    b) Promote & implement national policy objectives for renewable energy;

    c) Promote, stimulate, facilitate & develop sustainable energy;d) Implement, manage, monitor & review the Feed-In Tariff system;e) Implement sustainable energy laws including the Renewable Energy Act &

    recommend reforms

    f) Promote private sector investment in sustainable energy sector;g) Carry out / arrange research, advisory services & disseminate information;h) Conduct, promote & support sustainable energy researches & innovations;i) Conduct, promote & support sustainable energy training and human capacity

    development; j) Implement measures to improve public awareness;k) Act as focal point to assist the Minister on matters relating to sustainable

    energy & climate change matters relating to energy;

    l) Other function under sustainable energy law. 36 2011

  • 8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences

    37/37

    Thank You

    More info on feed-in tariff is available from

    coming soon...www.seda.gov.my