Effective Training Presentation Normala Baharudin Nesrin El Hadidi Mariam El Hadri Low Lih Jeng.
Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
-
Upload
asia-clean-energy-forum -
Category
Documents
-
view
225 -
download
0
Transcript of Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
1/37
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
2/37
FiT in Malaysia: The Beginning
2June 2005: Study mission to Berlin, Germany
2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
3/37
Why FiT Stern Review Report:
Sir Nicholas Stern stated that Comparisons between deploymentsupport through tradable quotas and feed-in tariff price support suggestthat feed-in mechanisms achieve larger deployment at lower costs.
UNDP-GEF Report: Promotion of Wind Energy - Lessons Learned FromInternational Experience and UNDP-GEF Projects
Feed-In tariff policies have been very effective in Germany, Spain ande
nmar , ea ng o e wor s rs , secon an ns a e w nenergy capacities.
International Energy Agency: Deploying Renewables - Principles for EffectivePolicies
Feed-in Tariffs are more effective and cheaper than quotas for RE Ernst & Young Report: Renewable Energy Country Attractiveness Indices:
Feed-in Tariffs are cheaper than Trading System
Traditional RPS country/state moving towards Feed-in Tariff
3 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
4/37
Learning Process: from Pioneer of FiT
4 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
5/37
Learning Process: from Pioneer of FiT
5 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
6/37
Learning Process: from FiT Advocates & RE Policy Experts
6 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
7/37
Learning Process: from Other Countries & Reports
Germany Italy
Thailand Taiwan Spain
South Korea USA France
Portugal Switzerland Others
7 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
8/37
Must be guaranteed via the RE Act, whereby:
Access to the grid is guaranteed utilities legally obliged to accept all electricitygenerated by RE private producers.
Local approval procedures are streamlined and clear . FiT rates must be high enough to produce a ROI plus reasonable profit (not
excessively) to act as an incentive.
FiT rates will be fixed for a period (typically 20 years) to give certainty and
Critical Factors for an Effective FiT Implementation
provide businesses with clear investment environment.
Adequate " degression " for the FiT rates to promote cost reduction to achievegrid parity
Adequate fund is created to pay for the FiT rates (incremental cost) andguarantee the payment for the whole FiT contract period.
The design of the FiT must be customized to suit contextual conditions of thecountry.
Implementation by a competent body in a professional manner that includesconstant monitoring, progress reporting and transparency .
8 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
9/37
Malaysia: Renewable Energy Policies
8 th Malaysia Plan (2001 2005)RE as the 5th fuel
Implied 5% RE in energy mix
th
300 MW in Peninsular Malaysia
50 MW in Sabah
10 th Malaysia Plan (2011 2015) & beyondNew RE Policy & Action Plan
9 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
10/37
National Renewable Energy Policy
Approved by Cabinet on 2 nd April 2010
Policy Statement: Enhancing the utilisation of indigenous renewable energy
resources to contribute towards national electricity supply security- .
Strategic Thrusts (RE Action Plans):1. Introduce appropriate regulatory framework.
2. Provide conducive environments for RE businesses.3. Intensify human capital development.4. Enhance RE research and development.5. Design and implement an RE advocacy programme.
10 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
11/37
10 th Jun 2010: 10 th Malaysia Plan (chapter 6) 15 th Oct 2010: National Budget 2011 (paragraph 34) 25 th Oct 2010: Economic Transformation Programme (chapter 6)
Feed-in Tariff: Government Policy
11 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
12/37
Renewable Energy Bill
RE Bill: an Act to provide for the establishment and implementation of aspecial tariff system to catalyse the generation of renewable energyand to provide for related matters.
Part I: Preliminary Part II: FiT System
, Part IV: Feed-in Tariff Part V: Renewable Energy Fund Part VI: Information Gathering Powers
Part VII: Enforcement Part VIII: General Part IX: Savings and Transitional
Passed in Parliament: April 201112 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
13/37
Definition of Renewable Energy
Renewable Energy (RE) is any form of primary energy fromrecurring and non-depleting indigenous resources, such asagricultural produce, hydro-power, solar, wind, solid-waste, etc.
13 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
14/37
RE Law Enables Feed-in Tariff System
Establishment of FiT System
Biogas
Small
Biomass
Solar PV
Hydro
Feed-in Tariff (FiT) system provides:
Connection to supply line by RE installationsPriority of purchase and distribution by DL
Payment by DL to FIAH according to FiT rates
14 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
15/37
20,000
25,000
30,000
W
Cumulative RE Installed Capacity
Solar PP
Solar PV
Small Hydro
Biomass-WasteBiomass
Biogas-Waste
Biogas
20303.5 GW
20202.1 GW
205011.5 GW
2030:7,088 MW (25%)
2050:26.3 GW (74%)42.6 GWh/Yr (19%)Cum. 597.2 mil T-CO2
National RE Goals
-
5,000
10,000
,
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
2 0 1 5
2 0 1 6
2 0 1 7
2 0 1 8
2 0 1 9
2 0 2 0
2 0 2 1
2 0 2 2
2 0 2 3
2 0 2 4
2 0 2 5
2 0 2 6
2 0 2 7
2 0 2 8
2 0 2 9
2 0 3 0
2 0 3 1
2 0 3 2
2 0 3 3
2 0 3 4
2 0 3 5
2 0 3 6
2 0 3 7
2 0 3 8
2 0 3 9
2 0 4 0
2 0 4 1
2 0 4 2
2 0 4 3
2 0 4 4
2 0 4 5
2 0 4 6
2 0 4 7
2 0 4 8
2 0 4 9
2 0 5 0
M
Year
2020:3,140 MW (14%)12.6 GWh/Yr (9%)Cum. 45.6 mil T-CO2
.
Cum. 165.7 mil T-CO2
2015:1,275 MW (7%)5.7 GWh/Yr (5%)Cum. 11.3 mil T-CO2
15 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
16/37
RE Law Schedule: Biogas
16 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
17/37
RE Law Schedule: Biomass
17 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
18/37
RE Law Schedule: Small Hydropower
18 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
19/37
Schedule: Renewable Resources, FiT RatesRE Law Schedule: Solar PV
19 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
20/37
FiT Rates = Empirical Value
ConduciveFiT rates
20 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
21/37
Basis of Determining FiT Rates:Economic Viability of RE Projects
Factors Biomass Solid Waste Solar PV
IRR (based on typical rates forpower generation sector)
8% - 13% 8% - 13% 5% - 12%
Simple Payback Period (SPB) < 7 years < 7 years < 12 years
Positive cash-flow Yes Yes Yes / Neutral
Factors to calculate IRR Biomass Solid Waste Solar PV
Capital expenditure 6-8.5 RM/W RM/W RM/W
Loan rates & tenure 7-8.8%, 15 yrs 7-8.8%, 15 yrs 6-7%, 15 yrs
Fuel cost & transport 30 RM/tonne N/a N/a
O&M cost, depreciation, insurance % of capex % of capex % of capexAnnual cost increment 3% 4% 3%
Revenues: FiT duration 16 yrs 21 yrs 21 yrs
Capacity factor 70% 70% 13-16%%
Other revenue N/a Yes N/a21 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
22/37
Cost Breakdown forAverage Domestic Electricity Tariff
Subsidized Fuel for Power Generation
Generation CostTransmission & Distribution CostFiT LevyCustomer Service Charge
FiT Cost 1% collection goes to REFund under the RE Law
RE Fund: Allocation from Electricity Tariff
38%
25%
20%
1%16%
2011 22
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
23/37
1,000
1,200
1,400
i o n
Annual RE Fund vs Annual FiT Transaction Cost
Annual RE Fund
Annual FIT Cost
Final RE FundCollection
(2030)
RE Fund
start
RE Fundincrement
The quota (MW) allocated foreach RE technology for eachyear is based on the:
Availability of RE Fund
Balancing Act: RE Fund VS FiT Transaction Cost
-
200
400
600
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
2 0 1 5
2 0 1 6
2 0 1 7
2 0 1 8
2 0 1 9
2 0 2 0
2 0 2 1
2 0 2 2
2 0 2 3
2 0 2 4
2 0 2 5
2 0 2 6
2 0 2 7
2 0 2 8
2 0 2 9
2 0 3 0
2 0 3 1
2 0 3 2
2 0 3 3
2 0 3 4
2 0 3 5
2 0 3 6
2 0 3 7
2 0 3 8
2 0 3 9
2 0 4 0
2 0 4 1
2 0 4 2
2 0 4 3
2 0 4 4
2 0 4 5
2 0 4 6
2 0 4 7
2 0 4 8
2 0 4 9
2 0 5 0
R M - m
i l l
Last REPPA (FiT) (21 years)
First REPPA (FiT) (21 years)
2 0 4 8
RE Fund.
23 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
24/37
FiT Quota: Open & Transparent Platform
24 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
25/37
FiT Rates: Open & Transparent Platform
25 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
26/37
RE Fund: Open & Transparent Platform
26 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
27/37
FiT Application: Online
FiT quota approvals onfirst come, first servedbasis upon submission
of complete application &document
FiT quota is dynamic
27 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
28/37
Other Critical Issues: RE Connection & Approvals
PMU132kV / 33kV
PPU33kV / 11kV
PE11kV / 0.4kV
Feeder Pillar0.4kV / 0.23kV
PPU
DL AFiT Meter
33kV / 11kV
DL B
1MW
DL Meter
DL Meter
FiT Meter28 2011
DL Meter
FiT Meter
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
29/37
FiT Payment
RE installations Biogas Biomass Small Hydro Solar PV
RE installed capacity [A] 4 MW 10 MW 10 MW 6 kW
RE generation/month [B]2,044
MWh/month5,110
MWh/month4,166.67
MWh/month600
kWh/month
FiT payment is calculated based on actual kWh reading by the revenue meter[ (new kWh reading minus last kWh reading) x FiT rate ]
FiT rate [C].
per kWh
.
per kWh
.
per kWh
.
per kWh
FiT duration [D] 16 years 16 years 21 years 21 years
FiT payment by TNB to FIAH per
month= [ C x B ]
RM
694,960per month
RM
1,686,300per month
RM
1,000,000per month
RM
876per month
Capex RM 40 mil RM 90 mil RM 90 mil RM 90,000
Simple Payback Period 4.8 4.5 7.5 8.629 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
30/37
Recovery of FiT Payments by Power Utilities
RE Fund (SEDA)
SEDA
(U) (S) (A)
(F) FiT payment
(D) Displaced Cost
(S) = (F) - (D) Recovery of Money
(U) = 2% x (S) Admin fee to DL
(A) = 3% x (S) Admin fee to SEDA
30
Distribution Licensee
FIAH
(F)
(D) (S)
Grid Connection PointDisplaced
Cost
Medium voltage 1kV 0.2047
Low voltage
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
31/37
FiT Degression: To Promote cost reduction towards Grid Parity
Degression rate to commence on 1 st January every yearRevision: at least once every 3 years
31 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
32/37
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
W h
Displaced Cost (LV)
Displaced Cost (MV)
FiT BiogasFiT Biogas-Waste
FiT Biomas
FiT Biomass-Waste
FiT Small Hydro
Degression & Grid Parity (Projected)
Upon grid parity:FIAH will be paid prevailing DC rate.DL cannot claim from RE Fund (SEDA)
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
2 0 1 5
2 0 1 6
2 0 1 7
2 0 1 8
2 0 1 9
2 0 2 0
2 0 2 1
2 0 2 2
2 0 2 3
2 0 2 4
2 0 2 5
2 0 2 6
2 0 2 7
2 0 2 8
2 0 2 9
2 0 3 0
2 0 3 1
2 0 3 2
2 0 3 3
2 0 3 4
2 0 3 5
2 0 3 6
2 0 3 7
2 0 3 8
2 0 3 9
2 0 4 0
2 0 4 1
2 0 4 2
2 0 4 3
2 0 4 4
2 0 4 5
2 0 4 6
2 0 4 7
2 0 4 8
2 0 4 9
2 0 5 0
R M /
FiT Solar PV
FiT Solar PP
Grid Parity
32 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
33/37
Other Critical Factors: Quality Standard and Reliable Services
2011 33
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
34/37
Sustainable Energy Development Authority of Malaysia
(SEDA Malaysia)
Ministry of Energy, Green Technology & Water
Energy Green Technology Water
Electricity SectorRE (& EE)
SectorGreen Technology
Sector Water & Sewage Sector
ST
Regulator
SEDAImplementing
Authority
MGTC
Green TechnologyPromoter
SPAN
Regulator
JBA
ImplementingDepartment
JPP
ImplementingDepartment
34 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
35/37
SEDA Bill
SEDA Bill: an Act to provide for the establishment of the SustainableEnergy Development Authority of Malaysia and to provide for itsfunctions and powers and for related matters.
Part I: Preliminary Part II: The Authority
Part IV: Employee of the Authority Part V: Finance Part VI: General
sustainable energy means energy which, in its generation, provisionand use, is such that it meets the needs of the present withoutcompromising the ability of future generations to meet their needs,and includes renewable energy.
35 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
36/37
Part III S.15: Functions of SEDA Malaysia
a) Advise the Minister & Government entities on all matters relating to sustainableenergy;
b) Promote & implement national policy objectives for renewable energy;
c) Promote, stimulate, facilitate & develop sustainable energy;d) Implement, manage, monitor & review the Feed-In Tariff system;e) Implement sustainable energy laws including the Renewable Energy Act &
recommend reforms
f) Promote private sector investment in sustainable energy sector;g) Carry out / arrange research, advisory services & disseminate information;h) Conduct, promote & support sustainable energy researches & innovations;i) Conduct, promote & support sustainable energy training and human capacity
development; j) Implement measures to improve public awareness;k) Act as focal point to assist the Minister on matters relating to sustainable
energy & climate change matters relating to energy;
l) Other function under sustainable energy law. 36 2011
-
8/6/2019 Ahmad Hadri Haris - Feed-In Tariff the Malaysian Experiences
37/37
Thank You
More info on feed-in tariff is available from
coming soon...www.seda.gov.my