Agile Service Management Guide V1.0 031615

34
  The Agile Service Management Guide     By Jayne Gordon Groll 

Transcript of Agile Service Management Guide V1.0 031615

Page 1: Agile Service Management Guide V1.0 031615

  

The Agile Service Management Guide

 

    

By Jayne Gordon Groll 

Page 2: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Sources and Acknowledgements   

 

The Scrum Guide by Ken Schwaber and Jeff Sutherland, July, 2013 

The ITSM Process Design Guide by Donna Knapp, ISBN: 978‐1‐60427‐049‐5 August 2010 

INVEST in Good Stories, and SMART Tasks by Bill Wake, August,2003 

Scrum.org  

ITIL® is a registered trade mark of AXELOS Limited.  Figures with "Based on AXELOS ITIL® material. Reproduced under license from AXELOS." are from ITIL® Service Lifecycle Publication Suite Books © Crown copyright 2011. Reproduced under license from AXELOS Limited. 

   

   

Page 3: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

About the Author   

Jayne Groll is an ITIL Expert, Certified ScrumMaster, Certified Agile Service Manager (CASM) and Certified Process Engineer (CPDE).  She has over 25 years of IT management experience that spans multiple industries including legal, telecommunications, retail, non‐profit, insurance and hospitality.  Jayne is co‐founder of the DevOps Institute whose mission is to bring enterprise level DevOps training and certification to the IT market.   Jayne is also President and co‐founder of ITSM Academy, an ITIL and ITSM training organization.  She is active in both the DevOps and ITSM communities and is a frequent webinar and conference speaker.  The inspiration for Agile Service Management grew out of Jayne’s recognition that end‐to‐end IT agility could only be achieved if Agile thinking and practices were exercised by both development and operational teams.   

Agile Software Development + Agile Service Management = DevOps.    

     

Page 4: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Agile Service Management Guide 

Table of Contents 

  

Introduction ................................................................................................................................................ 5 

Being Agile................................................................................................................................................... 5 

The Agile Manifesto .................................................................................................................................... 6 

What is Agile Service Management? .......................................................................................................... 7 

Agile Frameworks and Methods ................................................................................................................. 8 

Agile Process Design ................................................................................................................................. 11 

Scrum Basics .............................................................................................................................................. 12 

Agile Service Management Roles .............................................................................................................. 15 

Agile Service Management Artifacts ......................................................................................................... 18 

Agile Service Management Events ............................................................................................................ 21 

Agile Process Improvement ...................................................................................................................... 27 

Tools for Agile Service Management ........................................................................................................ 29 

Getting Started .......................................................................................................................................... 30 

Glossary of Terms ..................................................................................................................................... 31 

     

Page 5: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Introduction  Demands on IT for innovation and reliability have been steadily increasing since technology became a critical success factor for most businesses. IT has always been asked to do more with less, to improve its integration with business goals and to ensure the ongoing quality of IT services.  With the rise of mobile technology, the cloud and an "app" mentality, IT is being asked to do all that and more at breakneck speed.     While devices and applications are being introduced faster than ever before, it is the service behind the technology that is still most important to the customer.  As a result, IT will always need to manage its services and IT service management (ITSM) practices and processes will always be necessary.   The challenge is adapting service management practices to changing times so they can enable IT to go faster and deliver more ongoing value to the customer.  

Rapidly changing IT requirements require rapidly changing IT capabilities.  

New capabilities require new ways of thinking and performing.  IT must learn to be more agile.    

Being Agile  The MacMillan Dictionary defines “agile” as  

Able to move quickly and easily; able to think quickly, solve problems, and have new ideas.  Too often in IT, the concept of “being agile” is equated to “doing Scrum.”  While Scrum is an excellent framework for managing complex projects, the application of Scrum practices does not necessarily increase an organization’s agility.   Software developers recognized this many years ago when they crafted the Agile Manifesto’s guiding values and principles.   The tenets of agility must first be understood before embarking on agile practices such as Scrum and other frameworks.  Being agile is a state of mind.  It is more perspective than prescription.  In order for an organization to “be agile,” they must also be  

Customer‐centric 

Lean 

Collaborative 

Communicative 

Adaptive  

Measurable 

Consistent 

Results‐oriented 

Reflective    

Page 6: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Agile Manifesto  In 2001, a group of seventeen developers met at a ski lodge in Utah to discuss the increasing complexities associated with modern day software development.  The developers were frustrated by delays, rework and customer dissatisfaction that were resulting from constraints and were affecting their ability to get projects done on time and on budget.   Their goal in crafting the Agile Manifesto was to refocus stakeholders and developers on the aspects of software development that matter most.  

The Agile Manifesto              At first glance, the Agile Manifesto may seem to advocate against formal service management. Not true.  By the authors’ own admission, the Agile Manifesto was not meant to be anti‐methodology but rather an attempt to restore balance.  It is a reminder to implement “just enough” of the items on the right – process, tools, documentation, contracts and plans ‐ to make the outcome items on the left amazing!  The Agile Manifesto is underpinned by twelve principles of Agile software  

1. Our highest priority is to satisfy the customerthrough early and continuous deliveryof valuable software. 

2. Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage. 

3. Deliver working software frequently, from a couple of weeks to a couple of months, with apreference to the shorter timescale. 

4. Business people and developers must worktogether daily throughout the project. 

5. Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done. 

6. The most efficient and effective method of conveying information to and within a development team is face‐to‐face conversation. 

7. Working software is the primary measure of progress. 

8. Agile processes promote sustainable development. The sponsors, developers, and users should be 

ableto maintain a constant pace indefinitely. 9. Continuous attention to technical excellence and good design enhances agility. 10. Simplicity‐‐the art of maximizing the amount of work not done‐‐is essential. 11. The best architectures, requirements, and designs emerge from self‐organizing teams. 

12. At regular intervals, the team reflects on howto become more effective, then tunes and adjusts its behavior accordingly. 

 

We value  

Individuals and interactions    Processes and tools 

Working software  over  Comprehensive documentation 

Customer collaboration    Contract negotiations 

Responding to change    Following a plan  

While we value the items on the right, we value the items on the left more.  

Page 7: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

These principles are not significantly different than the principles that underpin service management  

Be aligned with the business  

Focus on customer outcomes 

Ensure ongoing customer value 

Understand and enable business success 

Deliver quality IT services 

Restore service as quickly as possible 

Adapt to changing requirements 

Minimize risks 

Be effective and efficient 

Make processes sustainable and repeatable 

Fulfill IT governance requirements  There is clearly alignment between the objectives of the Agile Manifesto and the objectives of service management.  Unfortunately, that alignment does not necessarily translate into end‐to‐end agility.     IT must now learn to be agile throughout the entire service lifecycle ‐ from concept to retirement.      

Agile Software Development + Agile Service Management =  Agile IT (DevOps).  

What is Agile Service Management?  

Agile Service Management (Agile SM) ensures that ITSM processes reflect Agile values and are designed with “just enough” control and structure in order to effectively and efficiently deliver services that facilitate customer outcomes when and how they are needed.  

The goals and objectives of Agile Service Management include  

Ensuring that agile values and principles are embedded into every service management process from design through implementation and continual improvement 

Improving IT’s entire ability to meet customer requirements faster 

Being effective and efficient (lean) 

Designing processes with “just enough” scalable control and structure 

Provide services that deliver ongoing customer value  

Agile Service Management encourages a continuous learning environment and promotes better collaboration between development and operational teams by cross‐pollinating vocabulary and methods.    There are two aspects of Agile Service Management:  Agile Process Design and Agile Process Improvement.     

Page 8: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Agile Process Design  Agile Process Design applies the same approach to process design that software developers apply to product development.  Each process is built and potentially released in small, frequent increments.  New procedures and behaviors are introduced gradually, providing greater opportunity for normalization as well more frequent feedback and input to guide the future direction of the process.      An iterative and incremental approach to process design also allows ITSM processes to mature organically and holistically.    Dependent increments can be built simultaneously or in succession.  Most importantly, the organization can test the boundaries of “just enough” process throughout the service lifecycle.  Agile Process Design does not attempt to redefine the underlying principles of process design.  There are solid, proven best practice approaches for process design, including those described in The ITSM Process Design Guide by Donna Knapp.   Agile Service Management supplements those principles with agile thinking and practices.  Agile Process Improvement  Agile Process Improvement seeks to continually align service management with Agile values and principles as part of Continual Service Improvement (CSI).  Processes are regularly audited and reviewed to ensure that they are at the right level of control and do not drift from “just enough” to “too much” or “not enough”.    Most importantly, Agile Process Improvement identifies and eliminates bottlenecks or waste in order to keep ITSM relevant, efficient and effective in the face of changing customer requirements.  Agile Service Management is framework agnostic and does not attempt to redefine any of the ITSM processes.  ITIL® and other service management frameworks have done an excellent job of describing best practices for managing IT services, including the processes that are necessary for a complete service lifecycle.  Agile Service Management supplements those frameworks with agile thinking and practices.  

Agile Frameworks and Methods  While Scrum is most commonly associated with Agile, there are several frameworks that are aligned with Agile values and Agile Service Management.  Scrum  Scrum.org defines Scrum as a   

“simple framework for effective team collaboration on complex projects.  Scrum provides a small set of rules that create “just enough” structure for teams to be able to focus their innovation on solving what might otherwise be an insurmountable challenge.” 

 Scrum is not a technique or process for building products.  It is a deceptively simple framework for managing projects.   While originally created for software development, its iterative and incremental approach has been applied to many other types of projects, including Agile Service Management.    Agile Process Design adapts the Scrum roles, events and artifacts to the design and implementation of service management processes.  

Page 9: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

 Kanban  

Kanban is a deceptively simple but powerful method for visualizing and communicating workflow in order to reduce or eliminate work in progress.    User stories expressed on sticky notes or index cards are moved through the Kanban columns until they are considered done.  Any work that does not progress as expected is identified and addressed as excessive work in progress or an impediment.    Kanban Boards are particularly useful tools for understanding 

impediments and team velocity.     Kanban Boards support Agile Service Management.  A Kanban Board can be used to manage the flow of process design activities or to identify bottlenecks in processes such as Change Management, Release Management or Problem Management.     ITSM  While IT service management is often overlooked as an Agile practice, it is the integrated approach to managing 

IT services that actually enables IT to meet customer requirements in a timely manner.  Whether formalized or not, ITSM processes transcend every aspect of the service lifecycle from design, development, deployment to operation and retirement.   By their nature, ITSM processes were not intended to be complex or bureaucratic.  Agile Service Management strives to instill Agile values into scaled ITSM processes thereby increasing IT’s end‐to‐end agility and ensuring consistency and speed.  ITIL® is the most prominent ITSM framework.  

DevOps  DevOps is a cultural and professional movement that stresses communication, collaboration, integration and automation between software developers and IT operations professionals.     The goal of DevOps is to cross traditional silos, instill shared accountabilities and improve the flow of work between development and operational teams.  Improved workflow, shorter feedback loops, shared practices and automation help the entire IT supply chain increase its rate of production and time to value.      Continuous delivery  Continuous delivery is a software development practice where software is always in a releasable state.   It allows organizations to rapidly deploy enhancements and fixes when needed.  Continuous delivery relies on automated testing and deployment as well as good collaboration between development and operational teams (DevOps).  Continuous delivery is not the same as continuous deployment.  Continuous deployment sends the release immediately into the production as soon as it is completed. Continuous delivery stages the release so it could be deployed quickly whenever it is needed.     Processes such as Change Management and Release Management will need to be much more agile in environments where continuous delivery is practiced.  

Based on AXELOS® ITIL

® material.

Reproduced under license from

Page 10: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Continuous integration  Continuous integration is a software development practice where a team of developers create separate pieces of code that are regularly integrated onto a central server.   Each integration goes through an automated build and test process to detect errors and defects.       Continuous integration leverages the capabilities and simultaneous work of multiple developers resulting in faster software builds.   Early and regular integration testing identifies correctable defects at the source.  Continuous integration aligns development standards within the organization and ensures that quality is built into the product throughout all phases of development.  Lean  Originally derived from the Toyota Production System, Lean is a production philosophy that seeks to create more value for customers with fewer resources and less waste.  Lean considers any activity that does not contribute value as “waste.” 

   While conceived for manufacturing purposes, lean thinking has now been introduced across the business enterprise. 

 Lean IT  Applying the key ideas behind lean production to the development and management of IT products and services  Lean Enterprise Creating an organization that strategically applies the key ideas behind lean production across the entire business  

 Agile Service Management strives to take a lean approach by eliminating waste, getting more done with fewer resources and creating customer value faster by making processes and services more agile.     

Page 11: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Agile Process Design  What is an Agile Process?  An Agile process is one that delivers “just enough” structure and control to enable the organization to achieve its outcomes in the most expeditious, effective and efficient way possible.  An Agile process is easy to understand, easy to follow and prizes its collaboration and outcomes more than its artifacts.  The characteristics of an Agile process include  

Having an accountable owner  

Clarifying everyone’s roles and responsibilities 

Benchmarking itself against Agile values and principles 

Being lean, efficient and expedient 

Being scalable 

Adapting to change  

Leveraging automation  An Agile Approach to Process Design  The waterfall model is a sequential approach to software development where each phase of the process flows the project further downward until the product is built, tested, deployed and ready to maintain.    While the waterfall model is associated with software development, process designers often take a similar sequential approach in their projects.  There are several challenges when using the waterfall model to design processes including  

The rigidity of a sequential approach  

User feedback that comes late in the process  

The delays, rework and additional costs  resulting from user feedback and testing errors 

The need for integration with processes not yet in design 

The extensive time required to build and deploy an entire end‐to‐end process 

The learning curve that users will experience when trying to normalize an entire process and its procedures 

 The bodies of knowledge behind ITIL® and other ITSM frameworks do not necessarily promote a waterfall or sequential approach to end‐to‐end process design.  In fact, most frameworks recommend an integrated process approach as described ISO/IEC 20000, the international standard for service management.      While there is some benefit to methodically moving down a project waterfall, there is also a risk that climbing back up the waterfall may be more difficult and time consuming than expected.     Agile Process Design promotes a more adaptive approach by   

Implementing each process in smaller, more frequent increments 

Encouraging  shorter feedback and feed‐forward loops 

Shaping future increments based on current business conditions 

Page 12: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Taking a holistic approach to building, maturing and integrating process activities 

Giving process practitioners time to absorb and institutionalize new behaviors 

Getting more “done” and delivering value more quickly  The net result will be an agile process that delivers “just enough” structure and control while   

Tying success measures to business outcomes 

Engaging stakeholders and soliciting input and feedback  

Enabling effective communication 

Integrating other processes and frameworks 

Introducing timely improvements 

Having simple documentation    How much is “just enough” process?  The answer will vary from organization to organization and process to process.  Business requirements, governance, risk and compliance will be important factors.  Identifying the balance between just enough and too much process will take time, practice and stakeholder engagement.    To start, it is best to create a Minimum Viable Process (MVP).  Minimum Viable Process (MVP)  Like a Minimum Viable Product in software development, a Minimum Viable Process has three characteristics  

It has enough value that people are willing to use it initially 

It demonstrates enough future benefit to retain early adopters 

It provides a feedback loop to guide future capabilities  It is much easier to add to a process incrementally than it is to scale a process back later.  A MVP approach ensures that the core elements of a process are designed and introduced first.  It strips away the “wants” from the “needs.”    It provides a basis for dialogue and feedback so that future development will provide ongoing value to those who rely on the process.  

Scrum Basics  In many organizations, Scrum has become the preferred method for managing software development projects.  Scrum embodies the values and principles of the Agile Manifesto and focuses on getting more done.  By its own admission, Scrum is lightweight, simple to understand yet difficult to master.    

 Agile Service Management captures the essence of Scrum within the context of process design and process improvement.  While some of the roles, events and artifacts have been adapted, the core concepts, rules and processes are the same.    A comparison chart of Scrum and Agile Service Management counterparts precedes each section within Agile Service Management.     

Page 13: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Pillars of Scrum  Scrum is founded on empirical process control where knowledge comes from experience, decisions are based on what is known and three pillars underpin the entire framework.      The three pillars of Scrum are  

Transparency  Workflows and progress towards the Sprint Goal are made visible through daily standups, Kanban Boards, planned events and other methods.  Common standards, vocabulary and definitions are shared by all stakeholders.     Inspection  Scrum artifacts are regularly inspected to help assess progress towards or deviations from a Sprint Goal. 

 Adaptation  Workflows are adapted as soon as possible if a deviation, impediment or other need is detected during inspection.  

 Scrum Values  Scrum defines five values that Scrum teams should embrace and demonstrate at all times  

      

Page 14: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Important Scrum Terms  The following are key terms and concepts that will be used throughout this Guide.  In Scrum, these are defined in the context of a “product”.  In Agile Service Management, they may be adapted to the context of a “process”.   A more complete glossary is appended to the end of this guide. 

 Scrum Guide A document that describes Scrum concepts and practices, written by Ken Schwaber and Jeff Sutherland 

 Product/Process Backlog A prioritized list of functional and non‐functional requirements for a system or process; usually expressed as user stories  User Story A statement written from the user’s perspective that describes what a user wants to do with a feature of the software or aspect of a process 

 Increment Potentially shippable completed work that is the outcome of a Sprint 

 Sprint A period of 2‐4 weeks during which an increment of product work is completed  

 Sprint Goal The purpose and objective of a Sprint, often expressed as a business problem that is going to be solved 

 Sprint Backlog Defines the work that must be completed during the Sprint 

 Burndown Chart Shows how much work is left over a period of time for a product or Sprint 

 Definition of Done Shared understanding of what it means for work to be complete 

 Timebox The maximum duration of an event   

 Daily Scrum A fifteen‐minute daily meeting that synchronizes work completed since the prior meeting and forecasts the work to be done before the next one 

 Impediment Anything that prevents a Team member from performing work as efficiently as possible 

 Velocity How much product or process backlog effort a Team can handle in a single Sprint  

Additional definitions are contained in the glossary at the back of this guide. 

Page 15: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

 Scrum Components  The Scrum framework is built around the interaction and rules that govern roles, artifacts and events.  

3 Roles  

4 Artifacts 

5 Events  

In the Scrum Guide, these are defined in the context of a “product.”  In Agile Service Management these are adapted to the context of a “process.”     Product vs Process  Software products and service management processes are not fundamentally different.  Both shape behaviors, enable people to “do something” and have defined inputs and outputs.  Customer requirements drive design and development and are usually captured in some type of document or repository.  Products and processes each benefit from having an accountable owner.  Cross‐functional expertise is essential in order to create and maintain the product or process.   Products are often built to replicate processes.  Scrum roles, artifacts and events can be adapted to Agile Service Management, allowing ITSM processes to be designed iteratively and in complete, potentially releasable increments.     

Agile Service Management Roles  

Counterparts 

 

Scrum Role  Agile Service Management Role 

The Team  The Team 

Product Owner  Process Owner 

ScrumMaster  Agile Service Manager 

  The Agile Service Management Team  An Agile Service Management Team is  

Self‐organizing  

Cross‐functional  

Without titles  

Without sub‐teams  

Accountable for the work produced as a whole regardless of individual skills or experience  

A self‐organizing team understands what it takes to get things done.  For each increment of work, they are provided a goal, a backlog of tasks, a completion date and a clear and shared Definition of Done.  The Team agrees on an approach for completing the work and meeting the goal.   Essentially, the Team is given the “what”; they collectively determine the “how.”  

Page 16: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Successful self‐organizing teams are   

Stable  

Trusting 

Empowered 

Motivated  

Accountable 

Focused 

Business centric 

Communicative 

Quality driven  These characteristics are often matured over time and experience.  Different perspectives and cross‐functional skills are essential to an Agile Service Management Team.  Membership should include a  

Process Owner 

Agile Service Manager 

Customer and/or process practitioner  

Process architect  

Tool administrator 

Change Manager 

Documenter  The Agile Service Management Team must include a customer or practitioner representative.     Each member of the Team will work on some aspect of items from the Process Backlog.  None are observers.  The Team should have at least three members but no more than nine to ensure sufficient cross functional skills and the ability to self organize.   Members may be on multiple teams, although it is recommended that an individual not work on more than two process Teams at any given time.  Velocity  Velocity is a metric that estimates how much of the Process Backlog a Team can handle in a single Sprint.   The more mature and stable the Team, the higher the Team’s velocity (or ability to absorb and complete work).     Velocity is often measured by work accomplished during past Sprints and serves as a predictor of future Team performance.         

Page 17: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Agile Process Owner  Most service management frameworks advocate for a Process Owner role that is accountable for the end‐to‐end results of the process.    Frameworks such as ITIL® do a good job of describing the responsibilities of a Process Owner for a specific process.  The Agile Process Owner role supplements the Process Owner role description by adding responsibilities for integrating Scrum practices and instilling agile thinking into the process.   The key responsibility of the Process Owner is to create, manage, prioritize and own the Process Backlog.  The Process Backlog is the single source of current or future requirements for a single ITSM process including activities, tools, plans, interfaces, documentation, training and improvements.  The Process Owner has ultimate authority over the items in the Process Backlog and ensures that the items are clear and visible.  This role understands how to prioritize items in the Process Backlog and helps the Team understand the next process increment.   The Process Owner is the only individual who can change the Team’s direction and/or add, remove or cancel items in a Sprint.  Other responsibilities of a Process Owner include  

Communicating the process’ vision and goals  

Ensuring that Agile values are embedded into the process so that outcomes and collaboration are prized over tools and artifacts 

Clarifying a Definition of Done for each process increment 

Inspecting the progress and status of the process after each Sprint 

Auditing and reviewing the process on a regular basis 

Prioritizing improvements in the Process Backlog  

Being accountable for overall process quality and deliverables  

The Process Owner is not necessarily responsible for performing any or all of the tasks associated with managing a process.  Depending on the size and complexity of the organization, the Process Owner may assign one or more roles to oversee day‐to‐day process execution.    The Agile Service Manager  The Agile Service Manager is the operational process counterpart to development’s product ScrumMaster.   While the context is different, the role and its responsibilities are very similar.  Responsibilities of the Agile Service Manager include  

Instilling agile thinking into the management of IT services.   

Ensuring that Agile values and principles are understood and applied     

Helping the Team adhere to Scrum practices and rules 

Refocuses IT Teams to the items on the left of the Agile Manifesto instead of prizing the items on the right 

Removing impediments whenever possible 

Facilitating Scrum meetings 

Serving as a facilitator, educator, protector and coach  

Page 18: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Agile Service Manager works closely with the Process Owner and the Team to get the work done.     The Agile Service Manager does not manage the Team.  The Team is self‐organizing.  The Agile Service Manager is a servant‐leader that helps the Process Owner integrate the guidance between ITSM and Scrum in order to build and maintain an accurate and relevant Process Backlog.   The Agile Service Manager coaches the Team and helps the members write effective process‐related user stories.    Most importantly, the Agile Service Manager protects the Team and does everything possible to ensure its success.    This includes helping those outside the Team understand how to (and how not to) interact with the Team.   The Agile Service Manager educates the organization on Agile values and Scrum practices so that everyone knows what to expect.    The Agile Service Manager bridges a relationship with the organization’s software development ScrumMasters.  Cross‐populating Agile practices, vocabulary and automation across all sides of IT will serve to increase speed and consistency.  Collaboration between Agile Service Managers and ScrumMasters helps to create and maintain a DevOps culture.  

Agile Service Management Artifacts  

Counterparts 

Scrum Artifact  Agile Service Management Artifact 

Product Backlog  Process Backlog 

Increment  Process Increment 

Sprint Backlog  Sprint Backlog 

Burndown Chart  Burndown Chart 

 The Process Backlog  The Process Backlog is the single source of current or future requirements including process  activities, tool updates, plans, interfaces, documentation, training and improvements for a single ITSM process.   The Process Backlog continually evolves, is regularly re‐prioritized and is never complete.  It exists as long as the process exists.  It is solely owned and managed by the Process Owner.     The form and format of the Process Backlog is not prescribed – items can be captured in anything from a Kanban Board to a spreadsheet to a database.  It should be visible to all process stakeholders and readily available for inspection.  Each item in the Process Backlog should be expressed as a user story.  The Process Backlog and User Stories  A user story is a simple statement that describes what a user or process practitioner wants from an aspect of the process.  It is always written from the user’s perspective and in their words.  It is not meant to include all of the details about the process aspect but is intended to encourage further dialogue and collaboration.  User stories are generally captured on index cards or sticky notes.  That fact alone should demonstrate how succinct the user story should be.     

Page 19: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

User stories generally follow the formula   

“As a (role), I want to (do something) so I can (achieve something)  In 2003, Bill Wake recommended the INVEST model to describe the elements of a good user story  

Independent 

Negotiable 

Valuable 

Estimable 

Small 

Testable  A process user story can be written for any aspect of the process including an activity, a procedure or process artifact.  Process Backlog Refinement  The Process Backlog should be refined regularly to add detail, estimates and prioritization to Process Backlog items.  The Process Owner and the Team will determine when and how the Process items should be reviewed and refined.   As items become higher priorities, the amount of detail needed will become greater and therefore refinement more necessary.   Details can come from a variety of sources, but the Team is responsible for updating the work estimates as important inputs into Sprint Planning.  Each user story in the Process Backlog should be refined with at least the following details  

A unique reference number for querying 

The stakeholders or customers 

An assigned priority 

The estimated number of hours to complete 

Who the story has been assigned to 

The anticipated Sprint that will include this story 

An approximate date of completion  Process Increments  A Process Increment is a potentially releasable and completed aspect of the process that was the pre‐defined outcome of a Sprint.   A Process Activity Increment could be an activity, procedure or work instruction.    The Process Increment is defined during the Sprint Planning Meeting.  It is built during the Sprint from items in the Sprint Backlog.  A Process Increment is considered finished when it meets the agreed Definition of Done.  It is demonstrated and discussed during the Sprint Review meeting.   The Process Owner then decides whether and when the Process Increment should be released.     

Page 20: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The “Definition of Done”  The Team and process stakeholders must share an understanding of the “definition of done” for each Process Backlog item or Process Increment.    

 

The Definition of Done is critical to Sprint Planning.   It guides how many items can be added to the Sprint Backlog and reasonably accomplished during the Sprint.  As the Team’s velocity increases, their ability to get more “done” in each Sprint will also increase.  

 

When is a Process Increment Done? 

 The Definition of Done may vary from Process Increment to Process Increment depending on scope of work in the Sprint Backlog.  Process Activity Increments should be considered “done” when the following questions have been answered  

Have the inputs, outputs, triggers and outcomes been defined? 

Have procedures been defined and documented? 

Have roles and responsibilities been mapped? 

Have tools and automation been updated? 

Have policies been reviewed and updated if necessary? 

Has training been developed and scheduled? 

Has communication been drafted? 

Have suppliers been engaged? 

Have all of these been reviewed and tested by stakeholders and process practitioners?  In simple terms, the Definition of Done is when you do not need to think about it anymore. 

 The Sprint Backlog  The Sprint Backlog is a subset of the Process Backlog and forecasts what increment of the process will be designed during the next Sprint.   It is created during the Sprint Planning Meeting and documents all of the items that will be necessary in order to meet the Sprint Goal.  It should be highly visible and available for inspection.  The Sprint Backlog provides a central artifact around which the Team can self‐organize in order to meet the Sprint Goal.  It should have enough detail so that the Team understands the Definition of Done and can inspect progress during the Daily Scrum.      The Sprint Backlog expires at the end of the Sprint – hopefully with all items completed.   Outstanding items do not automatically carry over to the next Sprint.  They are reprioritized with other Process Backlog items and considered during the next Sprint Planning Meeting.      

Page 21: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Burndown Charts  A Burndown Chart is a graph that shows the trend of completed and remaining work over a specified time period such as the timebox of the Sprint or the planned rollout of the new or improved process.  The most common types of Burndown Charts are the Process Burndown and the Sprint Burndown.  

 The Sprint Burndown is particularly important since it visually demonstrates whether the Team is on course to complete the Sprint on time.  It also shows where they may be ahead or behind schedule, whether they are under or over‐allocated.   The Burndown Chart is a useful tool for conducting a post‐sprint analysis of the Team’s velocity.  

Agile Service Management Events  

Counterparts 

Scrum Event  Agile Service Management Event 

Release Planning Meeting (optional)  Process Planning Meeting (optional) 

Sprint Planning Meeting  Sprint Planning Meeting 

Sprint  Sprint 

Daily Scrum  Daily Scrum 

Sprint Review  Sprint Review 

Sprint Retrospective  Sprint Retrospective 

     

Page 22: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Timeboxes  Scrum prescribes a maximum duration or “timebox” for each event.  The timebox range depends on the length of the Sprint (from two weeks to one month).  

Timeboxes  

Event  Timebox 

Process Planning Meeting (optional)  Not timeboxed 

Sprint Planning Meeting  4 to 8 hours 

Sprint  2 to 4 weeks 

Daily Scrum  15 minutes 

Sprint Review  2 to 4 hours 

Sprint Retrospective  1.5 to 3 hours 

  The Process Planning Meeting  The Process Planning Meeting is a high level planning event that establishes the Process Definition Document for a single process.  Outcomes of the meeting include a definition of the    

Goals, objectives, inputs and outputs of the process 

Features/activities of the process 

Expected integration with other processes 

Stakeholders 

Necessary tools 

Regulatory, governance or policy requirements 

Major risks 

Delivery date and cost  This event is not timeboxed, mainly because it may take multiple meetings to establish the high level Process Definition Document.  While Scrum considers a Release Planning Meeting to be optional, Agile Service Management strongly recommends that this event occur in order to plan the end‐to‐end process before it is broken down into Process Increments.   The ITSM Process Design Guide by Donna Knapp provides detailed guidance on creating a Process Definition Document.  The Sprint Planning Meeting  The Sprint Planning Meeting is timeboxed for 4 to 8 hours which demonstrates the importance of proper Sprint Planning.   The Agile Service Manager facilitates the meeting and the Process Owner describes the next Process Increment. The entire Team collaborates on planning the details of the next Sprint.     

Page 23: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The primary purpose of the Sprint Planning Meeting is to   

Establish the Sprint Goal 

Define what increment of the Process Backlog will be completed during the Sprint 

Determine how the increment will be done 

Ensure that the Team has all of the necessary skills and resources to complete the increment 

Define any dependencies or integrations with other processes that need to be considered 

Create a Sprint Backlog  

Inputs to the Sprint Planning Meeting include the Process Backlog, the past velocity of the Team, the availability of Team members and the dependencies on other processes and tools.  Only the Team can determine how much it can accomplish during the next Sprint.    The Sprint Planning Meeting is also where the Team begins to self‐organize by determining how they will accomplish the Sprint Goal.   They plan their approach and prioritize the items going into the Sprint Backlog.    By the end of the Sprint Planning meeting, the Team should be able to articulate what they are going to accomplish and how they are going to do it.  The Sprint  A Sprint is a period of 2 to 4 weeks during which the work needed to meet the Sprint Goal is performed.   The Process Increment is built from items in the Sprint Backlog based on the approach agreed to during Sprint Planning.  Progress is inspected during the Daily Scrum and visualized on the Sprint Burndown Chart.    The Sprint is guided by the Definition of Done.  During the Sprint, the Agile Service Manager keeps the Team focused, coaches the members and stakeholders on Scrum practices and protects the Team from outside distractions.  The Agile Service Manager also removes impediments whenever possible.   The Process Owner ensures that no one else attempts to change the Team’s priorities or tasks during the Sprint.  Agile Service Management embraces the Scrum principle of being iterative and incremental. Every Sprint is considered an iteration that progresses the service management process forward by building Process Increments.  When one iteration is completed, another is planned and repeated until all increments of the process are done.  Sprint Types  Agile Service Management defines three basic types of Sprints   

Strategic Sprint   A Strategic Sprint is committed to working on the underpinning items from the Process Backlog that are essential to the process but do not usually appear on the process flowchart.  They include  

Establishing a high level process definition document 

Allocating resources 

Inventorying and assessing existing tools 

Creating new or updating existing policies 

Mapping stakeholders to high‐level activities 

Page 24: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Drafting training and communication plans  Strategic Sprints follow the rules of any other type of Sprint.  They are guided by a Sprint Goal, agreed Definition(s) of Done and produce a Process Increment that is demonstrated during a Sprint Review.  The first Strategic Sprint will establish a high level Process Definition Document.  Subsequent Strategic Sprint iterations can be planned when they make sense to do so. Planning simultaneous Strategic Sprints from multiple processes may help to ensure alignment and integration. 

 Process Activity Sprint  Process Activity Sprints are planned in order to complete a Process Increment for a single activity, procedure or work instruction including   

Roles and responsibilities  

Timelines and escalations 

Documentation 

Metrics 

Updated tools and automation 

Interfaces or dependencies on other processes 

Training or communication  Some activities have too many user stories or are too large to complete in a single Process Activity Sprint.  In this case, the Process Owner should logically group related user stories into smaller Process Increments that can be planned over multiple Process Activity Sprints.  The collective Process Increments could be released either separately or together. Continual Service Improvement (CSI) Sprint  A CSI Sprint commits a cycle of work to implementing prioritized improvements from the Process Backlog.   CSI Sprints are based on Deming’s Plan‐Do‐Check‐Act (PDCA) improvement cycle.  A CSI Sprint is usually undertaken as part of Agile Process Improvement.   It is an opportunity to adapt the process based on input and feedback from prior Process Increment releases.     CSI Sprints should be regularly planned throughout the lifecycle of the process to maintain or increase the process’ agility.    Typecasting Sprints is done solely for the purpose of ensuring that all aspects of the process are addressed. There is no limit to the number or frequency of each type of Sprint.  There may also be other Sprint cycles that do not fall into a particular type and are just iterations to progress the process forward. 

    

Page 25: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Daily Scrum  The Daily Scrum (sometimes called a Daily Standup) is timeboxed for 15 minutes.  It is not a status meeting but a daily opportunity to inspect progress towards the Sprint Goal and identify impediments as quickly as possible.    During the Daily Scrum, each Team member in turn shares    

What he/she has accomplished since the last meeting 

What he/she is going to do before the next meeting 

What obstacles are in his/her way  While observers and stakeholders may attend, Team members are the only ones allowed to speak.  Questions are not allowed during the timebox.  The Agile Service Manager facilitates the meeting.  There may be a temptation to hold the Daily Scrum less frequently.    The importance of this daily inspection should not be undervalued – the faster deviations and impediments are identified, the greater the opportunity to meet the Sprint Goal and get more done.   Fifteen minutes a day during an active Sprint is usually time well spent.  The Sprint Review  The Sprint Review is timeboxed for 2‐4 hours and is attended by the Team and stakeholders.  It is an important opportunity for transparency, inspection and adaptation (the pillars of Scrum).  During the Sprint Review, the Team demonstrates the aspects of the process that were designed during the last Sprint.  The Team shares the challenges they faced, successful resolutions and outstanding issues.  The Process Owner explains the current state of the process and the Process Backlog.   The Process Owner also describes any feedback received from process practitioners about any previously released Process Increments. A decision on whether the current Process Increment will be released is made.  The Sprint Review allows the Team and stakeholders to discuss the next steps for the process as input to the next Sprint Planning Meeting.      Should the Increment be Released? 

Page 26: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

One of the key decisions made during the Sprint Review is whether or not to release the Process Increment.   While releasing aspects of service management processes incrementally gives the organization time to adopt and adapt to new behaviors, there are several considerations that should be discussed including whether  The Process Owner will decide if the Process Activity Increment should be released.  Consideration include whether  

The organization is ready  and receptive  

It won’t confuse practitioners 

It delivers business value 

The increment can stand alone 

The status of any dependencies 

The process increment will not affect the accuracy or validity of data or reporting 

It does not contribute to “change fatigue”  Change fatigue can occur when too many changes are made to a process in rapid succession.  Some of the benefits of releasing a Process Increment include  

Changing organizational behaviors one increment at a time  

Capturing more data or information  

Shortening feedback loops and using feedback to influence future Process Increments 

Helping the process adapt to changing requirements as it is slowly being matured 

Identifying and aligning dependencies on other processes  

Encouraging an integrated approach to service management 

Keeping tools relevant and updated  Sprint Retrospective  The Sprint Retrospective is an internal opportunity for the Team to reflect on and inspect the progress and organization of the last Sprint.  In some ways, it resembles the form and format of a post‐implementation review in that it addresses  

What did we do right? 

What could we have done better? 

What have we learned? 

What will do differently next time?  In the spirit of continual improvement, the Team also discusses 

 

Team composition and skill sets 

Tools 

Meeting logistics 

The Definition of Done 

Internal and external communications 

Input and feedback from stakeholders 

Velocity 

Process performance thus far 

Page 27: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

The Sprint Retrospective is timeboxed for 1.5 to 3 hours.  While the temptation may be to go from the Sprint Review directly into the next Sprint Planning Meeting, encouraging the Team to take the time to review and improve their past performance will absolutely increase their maturity and velocity.     

Agile Process Improvement  Designing agility into a process is a great first step towards Agile Service Management.  However, the ability to remain agile once a process is in use is the bigger challenge and requires a long term commitment.   If left unchecked, processes can become complex and bureaucratic over time.  The leap from “just enough” to “too much” process can happen almost overnight.      There is also a risk that people will revert to old ways and potentially “not enough” process control.  At that point, the temptation might be to put in place a more bureaucratic approach.   Agile Process Improvement’s goal is to ensure that service management processes are not   

Bureaucratic 

Unclear  

Constrained 

Time consuming 

Irrelevant 

Circumvented 

Nice on paper, but…  Agile Process Improvement is a key aspect of Continual Service Improvement.  Whether a new or existing process, improvement opportunities should be assessed against Agile values and principles from concept to retirement.     Agile Process Improvement Audits and Reviews  Agile Process Improvement requires Process Owners to conduct regular audits and reviews of their processes.  While process audits are often undertaken to determine compliance, Agile Process Improvement audits and reviews also help to   

Identify and eliminate waste and bottlenecks 

Detect drifting trends 

Benchmark against Agile values and principles 

Assess ongoing relevancy  

Maintain or move closer to “just enough” structure and control 

Improve effectiveness, efficiency and agility  

The process audit will include a review of process artifacts including  

The Process Definition Document 

Documented procedures 

Plans 

Documentation 

Page 28: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Tools and databases 

SLAs, OLAs, contracts 

The agility of the process artifacts will help determine whether the process is providing “just enough” structure and control.  For each artifact, process stakeholders, Team members and others may be asked  

Is it simple to use, read and/or understand?    

It is timely?   

Does it enable the process’ effectiveness and efficiency? 

Can it easily measure compliance, usage or achievements?   

Is it readily available?   

Is it relevant to the current business environment?  

Do you use it and is it helpful?  

When was the last time it was updated?  Different perspectives will help the Process Owner understand how to keep or improve the value of the process in the management of IT services.    The Agile Service Manager should help facilitate the audits and assist the Process Owner in collecting and evaluating the output in line with Agile values and principles.  Agile Process Improvement as an essential element of Continual Service Improvement ensures that agility is as important to the ongoing relevancy of a process as effectiveness and efficiency.   Agile Process Improvement should therefore overarch the entire service lifecycle.  The Process Backlog as the CSI Register  There will be many opportunities and recommendations for improvements during Continual Service Improvement and Agile Process Improvement.    ITIL® and other ITSM frameworks encourage the creation and maintenance of a Continual Service Improvement (CSI) Register – a repository for capturing and prioritizing recommended improvements for a process or service.     In Agile Service Management, the Process Backlog serves as the CSI Register in that it  

Documents improvement opportunities and recommendations 

Maps improvements to user stories 

Prioritizes user story improvements according to business requirements  

Can be used as the basis for planning CSI Sprints  As described above, a CSI Sprint is an opportunity to commit a cycle of work to implementing a Process Increment of prioritized improvements.   It is based on Deming’s Plan‐Do‐Check‐Act approach and is critical to successful Agile Service Management.    A CSI Sprint can occur whenever it makes sense for new or existing processes.    

Page 29: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

   

Tools for Agile Service Management  Agility is often supported by automation.  If done well, automated processes or procedures can be more consistent, effective, efficient, expeditious and provide long term data repositories.  All tools currently used as part of an ITSM program are still (if not more) relevant to Agile Service Management including  

ITSM suites (some of which have Agile modules) 

Automated testing, quality assurance and deployment 

Monitoring and event management  

Dashboards 

Metrics and analytics 

Flowcharts and drawing 

Project management  

There are also many Agile tools that can 

Capture and maintain the Product Backlog 

Track user stories 

Plan and manage a Sprint 

Burndown the process and Sprint 

Visualize workflows (Kanban) 

Analyze results and report on velocity 

Track testing and pilots 

Capture feedback 

Automate aspects and activities of each process  Some of the ITSM tools may already be in use by the organization’s operational teams and software development team.  The ability to leverage and share tools may help to cuts costs while potentially increasing collaboration.  It is important to note that technology alone will not make an organization agile.  

   

Page 30: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Getting Started  Agility does not happen overnight.  Moving an organization to an Agile mindset and an Agile Service Management approach takes practice and perseverance.   Identifying an organization’s “just enough” level takes time and experience.  Changing the thinking and behavior of individuals takes repetition, openness and patience.   Embracing the Scrum values of Commitment, Focus, Respect, Openness and Courage is essential.  Wherever you are in your Agile Service Management journey, remember that it is important to understand what it means to “be agile” before you attempt to “do agile (or Scrum).”    Start simple and stay simple.  Pick one process to pilot as a learning experience.  Identify a Process Owner, Agile Service Manager and stakeholders.  Build a small self‐organizing team with cross‐functional skills and appropriate levels of ITSM and Agile Service Management training.  Engage stakeholders and encourage feedback.  Don’t rush.  Start with a Minimum Viable Process and move forward from there.  Introduce the new or improved process in small, frequent increments.  Give the organization time to absorb, adopt and adapt to new behaviors.  Mature the processes holistically and organically.  Small, short term wins will deliver greater wins in the long term.       

Page 31: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

   

 

Agile Service Management

Glossary of Terms  

   

Page 32: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Term  Definition 

Agile  A project management method for complex projects that divides tasks into small “sprints” of work with frequent reassessment and adaptation of plans. 

Agile Manifesto  A formal proclamation of four key values and 12 principles to guide an iterative and people‐centric approach to software development.  

Agile principles  The twelve principles that underpin the Agile Manifesto. 

Agile Process Design  The aspect of Agile Service Management (Agile SM) that applies the same Agile approach to process design as developers do to software development. 

Agile Process Improvement  The aspect of Agile SM that aligns Agile values with ITSM processes through continuous improvement. 

Agile Service Management (Agile SM) 

A framework that ensures that ITSM processes reflect Agile values and are designed with “just enough” control and structure in order to effectively and efficiently deliver services that facilitate customer outcomes when and how they are needed. 

Burndown Chart  A chart showing the evolution of remaining effort against time.  

Continuous delivery  A software development practice where software is always in a releasable state. 

Continuous integration  A software development practice where members of a team code separately but integrate their work at least daily. Each integration goes through an automated build and test to detect errors and defects so as to allow faster deployments. 

Critical success factor  Something that must happen for a process, plan, project or other activity to succeed. 

CSI Register  A vehicle for recording and managing improvement opportunities throughout their lifecycle. 

Daily Scrum  A daily timeboxed event of 15 minutes or less for the Team to re‐plan the next day of work during a Sprint.  

Definition of Done  A shared understanding of what it means for work to be complete. 

DevOps  A cultural and professional movement that stresses communication, collaboration and integration between software developers and IT operations professionals. 

Impediment  Anything that prevents a Team member from performing work as efficiently as possible. 

Increment  Potentially shippable completed work that is the outcome of a Sprint. 

ITIL®  Set of best practice publications for IT service management. Published in five core books representing the five stages of the IT service lifecycle:  Service Strategy, Service Design, Service Transition, Service Operation and Continual Service Improvement. 

INVEST  A mnemonic was created by Bill Wake as a reminder of the characteristics of a quality user story  

Kanban  A method for visualizing and communicating workflow in order to reduce or eliminate work in progress. 

Page 33: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Term  Definition 

Key performance indicator  Key metric used to measure the achievement of critical success factors. KPIs underpin critical success factors and are measured as a percentage. 

Lean thinking  The goal of lean thinking is to create more value for customers with fewer resources and less waste.  Waste is considered any activity that does not add value to the process. 

Minimum Viable Product  The most minimal version of a product that can be released and still provide enough value that people are willing to use it. 

Plan‐Do‐Check‐Act  A four‐stage cycle for process management and improvement attributed to W. Edwards Deming.  Sometimes called the Deming Cycle or PDCA. 

Post Implementation Review  A review that takes place after a change or a project has been implemented that assesses whether the change was successful and opportunities for improvement. 

Potentially shippable product  An increment of work that is “done” and capable of being released if it makes sense to do so. 

Procedure  Step‐by‐step instructions that describe how to perform the activities in a process. 

Process  Interrelated work activities that take specific inputs and produce specific outputs that are of value to a customer. 

Process Backlog  A prioritized list of everything that needs to be designed or improved for a process including current and future requirements. 

Process customer  A recipient of a process’ output. 

Process Owner  Role accountable for the overall quality of a process and owner of the Process Backlog. 

Process Planning Meeting  A high level event to define the goals, objectives, inputs, outcomes, activities, stakeholders, tools and other aspects of a process.  This meeting is not timeboxed. 

Process Supplier  A creator of process input. 

Product Backlog  A prioritized list of functional and non‐functional requirements for a system usually expressed as “User Stories.” 

Product Backlog Refinement  An ongoing process of adding detail, estimates and order to backlog items.  Sometimes referred to as Product Backlog grooming.   

Product Owner  An individual who manages the Product Backlog and ensures the value of the work that the Team performs. 

Release Planning Meeting  A non‐timeboxed event that establishes the goals, risks, features, functionality, delivery date and cost of a release.  It also includes prioritizing the Product Backlog.   

Scrum  A simple framework for effective team collaboration on complex projects.  Scrum provides a small set of rules that create “just enough” structure for teams to be able to focus their innovation on solving what might otherwise be an insurmountable challenge. 

Scrum components  Scrum’s roles, events, artifacts and the rules that bind them together. 

Page 34: Agile Service Management Guide V1.0 031615

© DevOps Institute 

  

Term  Definition 

Scrum Guide  The definition of Scrum concepts and practices, written by Ken Schwaber and Jeff Sutherland. 

ScrumMaster  An individual who ensures that the Team adheres to Scrum practices, values and rules. 

Scrum Team  A self‐organizing team consisting of a Product Owner, Development Team and ScrumMaster. 

Scrum values  A set of fundamental values and qualities underpinning the Scrum framework:; commitment, focus, openness, respect and courage. 

Self‐organizing  The management principle that teams autonomously organize their work. Self‐organization happens within boundaries and against given goals. Teams choose how best to accomplish their work, rather than being directed by others outside the team. 

Sprint  A period of 2‐4 weeks during which an increment of product work is completed. 

Sprint Backlog  Defines the work that must be completed during the Sprint. 

Sprint Goal  The purpose and objective of a Sprint, often expressed as a business problem that is going to be solved.  

Sprint Planning Meeting  A 4‐8 hour timeboxed event that defines the Sprint Goal, the increment of the Product Backlog that will be done during the Sprint and how it will be done.   

Sprint Retrospective  A 1.5‐3 hour timeboxed event during which the Team reviews the last Sprint and identifies and prioritizes improvements for the next Sprint.   

Sprint Review  A timeboxed event of 4 hours or less where the Team and stakeholders inspect the work resulting from the Sprint and update the Product Backlog. 

Strategic Sprint  A 2‐4 week timeboxed Sprint during which strategic elements that were defined during the Process Planning Meeting are completed so that the Team can move on to designing the activities of the process. 

Timebox  The maximum duration of an event. 

User Story  A statement written from the user’s business perspective that 

describes how the user will achieve a goal from a feature of the 

product.   User stories are captured in the Product Backlog.  

Velocity  How much Product Backlog effort a team can handle in a single Sprint. 

Waste  Any activity which does not add value to a process. 

Waterfall  A linear and sequential approach to software development.