1 1 Agile Project Planning ~ Erik Philippus ©IMPROVEMENT BV workshop agile project planning 2 workshop agile project planning 65% of projects significantly overrun their cost estimates 65% of product features are rarely or never used the average project exceeds its schedule by 100% Much work remains to be done before we can announce our failure to make progress Traditional Planning A Joyless Track Record

Transcript of Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning...

Page 1: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

1

1

Agile Project Planning~

Erik Philippus

©IMPROVEMENT BV workshop agile project planning

2

workshop agile project planning

• 65% of projects significantly overrun their cost estimates• 65% of product features are rarely or never used• the average project exceeds its schedule by 100%

Much work remains to be done before we can announce our failure to make progress

Traditional PlanningA Joyless Track Record

Page 2: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

2

3

workshop agile project planning

Traditional PlanningCauses of Planning Failure

• Planning is by activity rather than feature- Parkinson's Law

• Lateness is passed down the schedule- Antipattern: Anti-gravity Module

• Multitasking causes further delays- assigning work to individuals rather than to groups

- focus on high level of utilization of all individuals

• Features are not developed by priority- dropped features may be of greater value

than those that are delivered

• Uncertainty is not acknowledged- product specifications are generally imperfect or incomplete - assignment of precise estimates to imprecise work- estimates become commitments

4

workshop agile project planning

Parkinson's Law

Work expands so as to fill the time available for its completion.

The Colonial Office had its greatest number of staff at the point when there was a lack of colonies to administer.

Forces:

1 An official wants to multiply subordinates, not rivals2 Officials make work for each other

Colonial Office, London

Page 3: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

3

5

workshop agile project planning

Organizational Pattern:

Anti-gravity Module

Risky components are scheduled to be completed last.

“The launch module is 98% built -

all we need is the antigravity module.”

avoid do first

do seconddo last

low

low

high

high

risk

value

6

Agile PlanningDealing with Uncertainty

anticipation

adaptation

plan

actadapt

flexibility to adapt to

changing business conditions

absolute conformance

to original plans

workshop agile project planning

Page 4: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

4

7

Agile Planning Principle #1:

Apply Multiple Levels of Planning

workshop agile project planning

dayportfolio sprintreleaseproduct

focus of agile teamstrategic planning

2 - 3 months 2 weeks 1 day

8

Relating the Planning Levels

workshop agile project planning

Release 1 Release 2 Release 3

release plan

sprint 1 sprint 2 sprint 3 - 6

task A 4 hourstask B 6 hourstask C 3 hourstask D 8 hours

Page 5: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

5

9

Relating the Planning Levels

workshop agile project planning

as a …., I want to ….

as a …., I want to ….

as a …., I want to ….

as a …., I want to ….

as a …., I want to ….

as a …., I want to ….

as a …., I want to ….

as a …., I want to ….

2

5

1

4

6

2

3

1

itera

tion 2

itera

tion 1

task A

task B

task C

task D

task E

task F

task G

6 hours

4 hours

5 hours

12 hours

2 hours

6 hours

5 hours

yesterday, I started to work on ….

and I should finish before the end of today

product backlog sprint backlog

daily scrum

10

workshop agile project planning

Conditions of satisfaction

(user stories, budget, schedule)

ReleasePlanning

Conditions of satisfaction

(user stories, acceptance tests)

Product Increment

SprintPlanning

release

sprint

feedback

Conditions of SatisfactionDrivers for Release and Sprint Planning

Page 6: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

6

11

workshop agile project planning

Agile Planning Principle #2:

Use a Relative Measure of Size

traditional measures of size

function pointslines of code

agile measures of size

story points

12

workshop agile project planning

Estimating Sizeexample

I'd like 14 ounces of soda, 6 ounces of lasagna, and 3 ounces of bread

Page 7: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

7

13

workshop agile project planning

Estimating Sizeexample

I'd like a large soda, a medium size lasagna, and

a small serving of bread

14

workshop agile project planning

Story Points

Story Points are a unit of measure for expressing the overall size of a piece of work using relative values.

Story Points are a measurement of complexity and/or size of a requirement as compared to

the duration to complete that requirement.

Story Points are used for planning and tracking

on release-level

Page 8: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

8

15

workshop agile project planning

Assignment of Story Pointsexercise

Assign

'Zoo Points'

to the following

breeds:

16

workshop agile project planning

Assignment of Story Pointsexercise

Breed Zoo Points

LionKangarooRhinocerusBearGiraffeGorillaHippopotamusTiger

Page 9: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

9

17

workshop agile project planning

• Forces the use of relative estimatingstudies have shown that we're better at relative estimating (over one order of magnitude) rather than absolute estimating

• Help to drive cross-functional behavior

• Focuses us on the size, not the durationderive duration emperically

• Puts estimates in units we can add togetherstory points are unit-lesstime-based estimates are not additive

Story Pointskey advantages

18

workshop agile project planning

Elapsed TimeOverall amount of time that passes on a clock or calendar

Ideal TimeAmount of time something takeswhen stripped of all peripheral activities

Salvadore Dali ~ Persistance of Time

It is easier and more accurate to predict the durationof an event in ideal time than in elapsed time

Ideal TimeAlternative for Story Points

Page 10: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

10

19

workshop agile project planning

meetingsdemo'sphone callsspecial projectstraininge-mailreviewsbug fixingsupportsick time…

typically, you are able to work ten minutes between interruptions

Interruptions

20

workshop agile project planning

1. The story being estimated is the only thing you'll work on2. Everything you need will be on hand when you start3. There will be no interruptions

When estimating in ideal days, you assume:

In favor of ideal days:

- Ideal days are easier to explain outside the team- Ideal days are necessary/easier to estimate at first

However, the preference is for story points!

Estimation in Ideal Days

Page 11: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

11

21

workshop agile project planning

Agile Architecting

How long will it take …

• to read the latest Harry Potter book?

• to drive from Amsterdam to Maastricht?

Velocityexamples

22

workshop agile project planning

Velocity is a measure of a team's rate of progress

It is calculated by summing the number of story points assigned to each user story

that the team completed during the iteration

Team Velocity

Page 12: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

12

23

workshop agile project planning

Agile Planning Principle #3:

Let Velocity take care of Estimation Errors

Velocity corrects most estimation inaccuracies

The correctness of estimates isn't crucialWhat matters is that they are consistent

24

workshop agile project planning

Estimation of Velocity

• Use historical values• Run an iteration• Make a forecast

The cone of uncertainty

0.6x

1.6x

x

0.8x

1.25x

iterations low high completed multiplier multiplier

1 0.60 1.602 0.80 1.253 0.85 1.154 or more 0.90 1.10

Express estimations as a range! bad time for estimation

better time for realistic estimations

Page 13: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

13

25

workshop agile project planning

Determining Velocity

1517 18

20

12

20

15

19

iterations

observ

ed v

elo

city

mean (last eight)

mean (worst three)

last

26

workshop agile project planning

Forecasting Velocity

Step 1 Estimate the numbers of hours that each person will be available to work on the project each day

- typically 4 - 6 hours/day for a full-time assignment

Step 2Determine the total number of hours that will be spenton the project during the iteration

Step 3Find a representative set of stories, and expand them into tasks.Estimate each task in ideal hours.Repeat until you have identified enough tasks to fill the iteration.

Step 4Convert the velocity determined in step 3 into a range

Page 14: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

14

27

workshop agile project planning

Re-Estimation

golden rule:re-estimate only when the relative size of one or more user stories has changed

Do not re-estimate solely because progress is not

coming as rapidly as you'd expected

28

workshop agile project planning

ESTIMATION OF OF EFFORT

ESTIMATION OF DURATION

story points

+

velocity

Agile Planning Principle #4:

Estimate Size, but Derive Duration

Page 15: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

15

29

workshop agile project planning

• Utilize collaborate estimates

• Prefer estimations by those who will do the work

• Use an appropriate estimation scale

• Remove all (political) bias from the estimate

Agile Estimation in Practice

additional estimation effort yields little value beyond a certain point

accura

cy

100

50

effort

30

workshop agile project planning

Use the Right Units

can you distinct a 1-point story from a 2?and a 17 from an 18?

you need an ever growing scale

• Use a set of numbers that make sense; I like:1, 2, 3, 5, 8, 13, 20, 40, 100(stay mostly in a 1-10 range) include 0

and 1/2 if

you want

fibonacci sequence

Page 16: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

16

31

workshop agile project planning

Planning Poker

1 All the team members have a set of cards

2 Moderator reads description of the backlog item

3 Everyone selects and simultaneously shows cards

4 If estimates vary significantly, high and low estimators brieflyexplain their estimates

5 Repeat steps 3-4 until estimates stop converging

6 Decide estimate for backlog item

7 Move to next backlog item

32

workshop agile project planning

Planning PokerExercise

User Stories

As a Software Engineer, I want to have a basic version of the specification, sufficient to assess the potentialpotential of the application

As an Art Worker, I want to have a basic version of the specification, sufficient to develop the artwork for the mockup

As a Software Engineer , I want to have specification of the product configuration for the upcoming release

As a Product Development Manager, I want to have proof that the application will run without problems in the final product environment

ID

1.6

1.7

2.10

3.7

Estimation(ideal days)

?

?

?

?

Page 17: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

17

33

workshop agile project planning

Plannign Pokerwhy it works

• Combining individual estimates throughgroup discussion leads to better estimates

- estimators are required to justify estimates

• Emphasizes relative rather than absolute estimating- focuses most estimates within an

approximate one order of magnitude

• Estimates are constrained to a set of values,so we don't waste time in meaningless arguments

• Everyone's opinion is heard- those who will do the work, estimate the work!

• It's quick and fun

see www.planningpoker.comfor planning poker for distributed teams

34

workshop agile project planning

Prioritizing User Stories

• The financial value of having the feature• The cost of developing / supporting the new feature• The amount and signficance of learning and new knowledge

created by developing the feature• The amount of risk removed by developing the feature• The business impact of not having the feature

Guidelines for prioritizing user stories or themes:

Page 18: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

18

35

workshop agile project planning

Relative Penalty

Golden Rule:Incorporate the relative penalty

in your prioritization

Look at features from the perspective of how users will be affected by the presence as well

as by the absence of the feature

36

workshop agile project planning

Relative Weighting

Rela

tive B

enefit

Rela

tive P

enalty

Tota

l Valu

e

Valu

e %

Estim

ate

Cost

%

Pri

ori

ty

Feature

uploading pictures 8 6 14 42 32 53 0.8

3D touchscreen 9 2 11 33 21 34 1.0

voice recognition 3 5 8 25 8 13 1.9

Total 20 13 33 100 61 100

Page 19: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

19

37

workshop agile project planning

exciters anddelighters

must-have,mandatory

perfo

rman

ce/li

near

Feature Presenceabsent fullyimplemented

Custo

mer

Satisfa

ction

low

high

unspoken

unspoken

indifferent

Desirability of FeaturesKano Model

38

workshop agile project planning

Paired Questions

If you can upload photo's with your mobile,

how do you feel?

If you cannot upload photo's with your mobile,

how do you feel?

functional form:

dysfunctional form:

+

-

I expect it to be that way X

I am neutral

I dislike it that way

I expect it to be that way

XI am neutral

I dislike it that way

Page 20: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

20

39

workshop agile project planning

Differentiating Product Features

Feature Implemented

Feature Absent

Don't Like Neutral Expect

Don't Like

Neutral

Expect

user perception

indifferent delighter

linearmust-be

reversereverse

reverse

skeptical

skeptical

40

workshop agile project planning

Trackingrelease burn-down chart

250

200

150

100

50

01 2 3 4 5 6 7 8

240-point projectcompleted in 8 sprints

sto

ry p

oin

ts

sprint

Page 21: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

21

41

workshop agile project planning

Trackingrelease burn-down chart

250

200

150

100

50

01 2 3 4 5 6 7 8

240-point projectcompleted in 8 iterations

sto

ry p

oin

ts

sprint

240-point projectcompleted in 8 iterations

Burn down charts:• Raise questions, they

don't answer them• Facilitate early discussions• Make it impossible to lie

42

workshop agile project planning

TrackingRelease Burn-down Bar

sprints

sto

ry p

oin

ts

0

-50

300

work is completed

new work is added

work isremoved

work is re-estimated

Page 22: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

22

43

workshop agile project planning

Multiple-team Projects

Planning a complex projects with many interteam dependencies may require:

• establishing a common basis for estimates- story points or ideal time

• adding detail to the user stories sooner- allows multiple teams to coordinate work

• performing lookahead planning- maintaining a rolling lookahead window

during release and iteration planning

• incoporating feeding buffers into the plan- preventing late start of a team caused by

a late delivery of another team

44

workshop agile project planning

Release Planning

Determineconditions ofsatisfaction

Estimate theuser stories

Select sprintlength

Estimatevelocity

Prioritizeuser stories

Select storiesand a

release date

do in anysequence

iterate until the conditionsof satisfaction for the

release can best be met

5-10 iteratons2-5 months

combination ofschedule, scope

resources

estimation instory points

Page 23: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

23

45

workshop agile project planning

Sprint Planning

AdjustPriorities

Determinetarget

velocity

Select userstories

do in anysequence

Identifysprintgoal

Split userstories

into tasks

EstimateTasks

equals mostrecent velocity(for new teams,

forecast velocity)

estimation inideal hours

1 sprint2-4 weeks

ask team forcommitment

46

workshop agile project planning

Strategic Planningproduct backlog 1 quarter ahead

quarter

start of upcoming sprint

updated launch planwith rough estimations

product backlog with prioritized

user story estimations

Page 24: Agile Project Planning - Scrum Training Project Planning.pdf · workshop agile project planning meetings demo's phone calls special projects training e-mail reviews bug fixing support

24

47

Agile Architecting

Agile Project Planning8 reasons why it works

Agile Architecting Essentials - Agile Estimation & Planning

• Estimates of size and duration are separated- translate story points into duration using velocity

• Plans are made at different levels- 3 different levels/perspectives: release, sprint, daily

• Plans are based on features, not tasks- focus on product that must be built

• Small stories keep work flowing- short cycle times will deliver value as fast as possible

• Work in progress is eliminated every sprint- no high amounts of work in progress, 'Kanban' principle

• Tracking is at the team level- buidling commitment; elimination of the 'blame game'

• Uncertainty is acknowledged and planned for- express uncertainty in either the functionality or the date

48

Agile Architecting

References

Agile Architecting Essentials - Agile Estimation & Planning

1 Mike CohnAgile Estimating and Planning, Prentice Hall, 2007

2 Todd Little:Software Schedule Estimation and Uncertainty Surrounding the Cone of Uncertainty, IEEE Software, May 2006, Vol. 23, No. 3

3 Kent Beck and Martin Fowler Planning Extreme Programming, Addison-Wesley, 2001

4 George D. Githens Rolling Wave Project Planning, 1998http://www.catalystpm.com/NP02.PDF