AGENDA Infrastructure Committee - Peoria County, IL
Transcript of AGENDA Infrastructure Committee - Peoria County, IL
AGENDA
Infrastructure Committee Tuesday, February 26, 2019
@ 3:00 p.m. Peoria County Courthouse, Room 402
1. Call to Order 2. Approval of Minutes
• January 29, 2019
3. Informational Items / Reports / Other Minutes / Updates • Greater Peoria Sanitary District minutes • Rural Peoria County Transportation System • Facilities Master Plan
4. Resolution
• Construction Engineering Agreement with Hutchison Engineering, Inc. for the Dirksen Parkway Reconstruction Project
5. Discussion
• USDOT Autonomous Vehicle Grant Overview
6. Miscellaneous
7. Adjournment
DRAFT
MINUTES Infrastructure Committee
January 29, 2019 @ 2:30 p.m.
Call to Order Chairman Salzer called the meeting to order at 2:30 p.m. Approval of Minutes A motion to approve the minutes of November 26, 2018, was made by Ms. Pastucha and seconded by Mr. Reneau. The motion carried. Informational
• Greater Peoria Sanitary District No verbal report. No questions or comments from committee.
• Rural Peoria County Transportation System Mr. Dwyer advised that both a new General Manager and Safety Manager have been hired. The General Manager will take over duties in February. He stated that finalization of the transition of services to the Greater Peoria Mass Transit District (GPMTD) is nearly complete, with the date of finalization to be retroactively set at July 1, 2018. Mr. Sorrel further explained that the Intergovernmental Agreement between Peoria County and the Mass Transit District has the GPMTD assuming the county’s third-party vendor contract with MV Transit to deliver rural transit services.
• Facilities Master Plan Mr. O’Connell updated the committee on the status of the following 2019 budgeted projects:
• Midwest Engineering is working on revised site drawings and specifications in order to alleviate water filtration issues near the Jefferson Street entrance, and which are affecting the Circuit Clerk’s Office. It is anticipated that the project will take approximately two months to complete.
• Upgrades to the prisoner’s elevator are complete, and staff is working with Kone Elevator Service to finalize construction documents on the upgrade to the judge’s elevator. The elevator is anticipated to be out of service for approximately 5-6 weeks in order to complete the upgrades.
• A Purchase Order has been issued to Bishop Brothers for an upgrade to the judge’s break area.
• The Fire Alarm System at the Peoria County Jail is in need of modernization in order to bring the system up to current code. Midwest Engineering is developing Phase II plans and specifications.
MEMBERS PRESENT:
Phillip Salzer - Chairman; Kate Pastucha – Vice-Chairman; Gregory Adamson, James Dillon, Rob Reneau, Matt Windish
MEMBERS ABSENT:
Barry Robinson
OTHERS PRESENT:
Scott Sorrel – County Administrator; Shauna Musselman – Assistant County Administrator; Larry Evans - State's Attorney's Office; Randy Brunner – Interim Chief Financial Officer; Dan O'Connell - Facilities Director; Amy Benecke McLaren, Jeff Gilles - County Highway; Andrew Dwyer - Greater Peoria Mass Transit District; Rena’ Parker, Jennifer Shadid -Courts Administration; Doug Gaa – Sheriff’s Office; Mark Little – Chief Information Officer; Tracy Coker, Chris Waible - Dewberry
2
• Dewberry presentation on Space Utilization Study Mr. Waible distributed a Facility Utilization Analysis final report, detailing a study of the current use of space within six county facilities housing Peoria County departments and offices. The report analyzes whether departments have adequate space to perform the duties of the department and evaluates any excess space that could be utilized more efficiently. He stated that the analysis also makes recommendations as to reorganization, relocation of employees and/or consolidation of various departments to maximize the utilization of available space. He commented that one of the recommendations made is due to a state requirement that each court facility provide a lactation room by June 1, 2019. Mr. Sorrel remarked that there is no specific funding source tied to the recommendations; however, he reiterated that the addition of a lactation room is state mandated. He also indicated that within the next 10-15 years, it will be necessary for the County Board and the Board of Health to initiate discussion of a life-cycle replacement of the buildings currently occupied by the Health Department, including the option to consolidate all health and human services agencies and departments. Mr. Dillon noted that both the Coroner and the Health Department facilities are beyond their life cycle, and the analysis provides useful options for future planning. Mr. Sorrel advised that he and Mr. Little will speak with each department that participated and responded to the inquiries by Dewberry and will report their feedback to this committee. Resolutions
• County Parking Deck Rate Increase A motion to approve was made by Mr. Reneau and seconded by Mr. Dillon. Mr. Little advised that a fully automated parking and payment system will be installed in the County owned parking deck in the spring of 2019. He explained that although the automated system will accept all forms of payment, it will have limited ability for the storage of coins. He stated that to decrease labor costs associated with a National Garages/Heartland Parking employee managing the coin intake on a daily basis, staff proposes increasing the ½ hour rate from $0.75 to $1.00. He added that all other rates would remain unchanged. He also noted that the ½ hour rate would not be increased until the automation is complete. The motion to approve carried unanimously.
• Participation of the 182nd Airlift Wing Peoria Air National Guard Rising 4 group in the Adopt-A-Highway Program on Airport Road
A motion to approve was made by Mr. Adamson and seconded by Mr. Reneau. Ms. McLaren advised that the 182nd Airlift Wing Peoria Air National Guard Rising 4 group has requested to adopt a portion of Airport Road from West Smithville Road to Garfield Avenue. The motion to approve carried unanimously.
• Intergovernmental Agreement with Princeville Road District A motion to approve was made by Mr. Dillon and seconded by Ms. Pastucha. Mr. Gilles advised that the Intergovernmental Agreement will allow for repair of a bridge located on Princeville Cemetery Road, with a 50/50 cost share between Peoria County and the Road District. He noted that although the bridge superstructure is in good condition, the bridge timber pile supports are deteriorating. The motion to approve carried unanimously.
• Agreement with Midwest Engineering Associates, Inc. for Phase I and II Preliminary Engineering for Cemetery Road Bridge repairs
A motion to approve was made by Mr. Reneau and seconded by Mr. Windish. Mr. Gilles advised that Midwest Engineering will be requested to provide the design work for the Princeville Cemetery Road bridge repair project. He stated that the engineering fee totals $37,885.00. The motion to approve carried unanimously. 3
• Federal Agreement with the State of Illinois for Dirksen Parkway construction A motion to approve was made by Mr. Adamson and seconded by Mr. Reneau. Mr. Gilles advised that $2.8 million in Federal funding received through PPUATS is allocated for Dirksen Parkway. He stated that R.A. Cullinan is the project’s low bidder. He advised that passage of the resolution will allow Peoria County to utilize Federal funding and appropriate $1.2 million in MFT funds for the local match portion of the construction. The motion to approve carried unanimously.
• Agreement with Maurer-Stutz, Inc. for the Kickapoo-Edwards Road Safety Project A motion to approve was made by Mr. Windish and seconded by Mr. Dillon. Mr. Gilles commented that due to an extremely heavy workload for the 2019 construction season, the Highway Department must contract engineering duties for the Kickapoo-Edwards Road Safety Project. He advised that seven firms submit proposals for the project through the Request for Proposal process, with Maurer-Stutz, Inc. chosen as submitting the most qualified proposal. He stated that 90% of the $147,610.09 project cost will be reimbursed with Federal funds. He commented that the project will improve the safety in a section of road where two fatal accidents have occurred. The motion to approve carried unanimously. Discussion
• Bid Letting Update Mr. Sorrel updated the committee on the bid results and finances related to the Dirksen Parkway construction and the Kickapoo-Edwards Safety Project. He noted that both projects are Federally funded projects and the County Board does not approve the contract award, as IDOT holds both contracts. Mr. Sorrel advised that Dirksen Parkway will be completely rebuilt from the intersection of Airport Road to the intersection with Middle Road. He stated that in 2014, PPUATS estimated a $4 million project cost and that amount of funding was subsequently budgeted for the project. He noted that construction costs have increased since 2014, and an engineer’s estimate provided before bidding was just over $5.5 million. He advised that the low bid of R.A. Cullinan was $5.4 million. He advised that the cost difference between the original budgeted figure of $4 million and the low bid of $5.4 million will be alleviated by eliminating the highway lighting portion of the project, as well as deferring several budgeted projects. Mr. Sorrel advised that R.A. Cullinan was the sole bidder for the Kickapoo-Edwards Safety Project, with a bid of $190,000.00 more than the engineering estimate, and $230,000.00 above the project budget. He commented that staff must determine how to account for the overage within appropriations. He remarked that several projects budgeted for 2019 will be deferred to a future year. Ms. McLaren noted that the Highway Department will supplement the need for additional funds from projects budgeted in the County Bridge Fund, including bridge design funding for Evans Mill Bridge, culvert replacement funding, and savings realized from Richwoods bridge replacement and Schaefer Road culvert project. She also commented that the next design phase of Old Galena Road will be deferred.
• Fire Alarm System (FAS) Study Project – Phase II Mr. O’Connell advised that the Fire Alarm System Study Project is a multi-year project to replace both the 1985 and 1998 fire alarm systems at the Peoria County Jail, and as well as integrate the two systems into a single upgraded Fire Alarm System. He advised that Midwest Engineering has agreed provide a complete engineering analysis with deliverables so that the County may put a competitive procurement out to bid for the overall replacement and integration of a single fire alarm system. He advised that $350,000.00 in Capital Projects is allocated in 2019 for the work, and staff requests a commitment of up to $117,000.00 with Midwest Engineering for their services. 4
Mr. O’Connell advised that the balance remaining after the allocation to Midwest Engineering will be available to commit to the selected contractor. He stated that if the remaining balance is sufficient to complete the project, it will be unnecessary to request additional funding in fiscal year 2020. Adjournment The meeting was adjourned by Chairman Salzer at 4:11 p.m.
5
Peoria, Illinois, January 15, 2019
The regular meeting of the Board of Trustees of the Greater Peoria Sanitary and Sewage
Disposal District was held on Tuesday, January 15, 2019, at the office of the District, 2322
South Darst Street, in the City and County of Peoria, State of Illinois, and within the
boundaries of said District at the hour of 9:30 A.M.
Roll call showed the following Trustees were present: Michael F. Menke, Robert C. Gates,
Matthew R. Bender, Gene Petty, and Heather L. McCord. Executive Director Brian F.
Johnson, Attorney James F. Kane, Director of Administration Michelle R. Mortland,
Director of Operations Thomas W. Meyer, Director of Planning and Construction Timothy
F. Leach, and Director of Finance Joseph C. Merkle were also present.
President Menke acted as Chairperson and Clerk Petty as Secretary. Chairperson Menke
stated that there was a quorum, and that the meeting was duly and legally convened for the
transaction of business.
Chairperson Menke called for public participation and there was no response.
Trustee Gates moved the minutes of the regular meeting held on Tuesday, December 18,
2018 be approved, which motion was seconded by Trustee Bender. On voice vote being
taken, Trustees Menke, Gates, Bender, Petty, and McCord voted “Aye” and there were no
“Nays”. Chairperson Menke declared the minutes approved.
Trustee Bender moved the list of bills, totaling $1,027,393.14 be approved for payment as
presented. Trustee Petty seconded the motion. Following discussion of several individual
bills, and on roll call vote being taken, Trustees Menke, Gates, Bender, Petty, and McCord
voted "Aye" and there were no "Nays". Chairperson Menke declared the motion carried
and directed that payments be made.
Operating reports for the Administration, Operations, Planning and Construction, and
Finance Departments were thereafter discussed with various questions answered thereto.
The Director of Finance next presented a report for the Investment Committee, indicating
the Investment Policy had been reviewed and that no changes were recommended at this
time. He advised the Board that up to $1,000,000.00 would be available to invest this month
and recommended the following investment:
Bank Amount Type Term Yield
Morton Community Bank $1,000,000.00 CDARS 12 Months 2.84%
Trustee Petty moved to approve the recommendation, which motion was seconded by
Trustee McCord. Following discussion and on roll call vote being taken, Trustees Menke,
Gates, Bender, Petty, and McCord voted "Aye" and there were no "Nays". Chairperson
Menke stated that the motion carried.
Trustee McCord moved delinquent accounts listed as Batch #174 Illinois American Water
Company, Batch #77 Village of Peoria Heights, and Batch #79 Pleasant Valley Water Co.
be forwarded for disconnection from service in accordance with applicable water shutoff
6
agreements, which motion was seconded by Trustee Gates. Following discussion and on
roll call vote being taken, Trustees Menke, Gates, Bender, Petty, and McCord voted “Aye”
and there were no “Nays”. Chairperson Menke stated that the motion carried.
The Executive Director recommended authorizing a loan payment in the amount of
$376,847.55 to Illinois Environmental Protection Agency. This loan was secured to
construct treatment improvements in 2006. Trustee Gates moved to approve the
recommendation, which motion was seconded by Trustee Petty. Following discussion and
on roll call vote being taken, Trustees Menke, Gates, Bender, Petty, and McCord voted
“Aye” and there were no “Nays”. Chairperson Menke stated that the motion carried.
The Executive Director next recommended approving a Sewer Rehabilitation Pilot
program in the amount of $24,428.75 to Miller Pipeline Corporation. This program will be
used to investigate a third type of lining product used to perform sewer rehabilitation
projects. Trustee Bender moved to approve the recommendation, which motion was
seconded by Trustee McCord. Following discussion and on roll call vote being taken,
Trustees Menke, Gates, Bender, Petty, and McCord voted “Aye” and there were no “Nays”.
Chairperson Menke stated that the motion carried.
The Board next proceeded to review the fiscal year 2020 capital budget. The first draft of
the operating and user charge budget and 5- and 20-year capital/debt plan will be available
for the February 2019 meeting.
The Board next discussed capital bill priorities, including recommended projects.
Pursuant to Illinois law, the Trustees next reviewed a recommendation relating to
previously held executive session minutes. Based upon such recommendation, Trustee
Petty moved that all previously held minutes continue to be held as the need for
confidentiality or privacy still exists, except those that relate to the meetings held on June
20, 2017 and November 21, 2017, and that the audio recording of that meeting be destroyed
if at least eighteen (18) months old. Trustee Gates seconded the motion. Following
discussion and on voice vote being taken, Trustees Menke, Gates, Bender, Petty, and
McCord voted “Aye” and there were no “Nays”. Chairperson Menke stated that the motion
carried.
There being no further business to come before the Board, on motion duly made, seconded
and unanimously carried, the meeting was adjourned at 11:30 A.M.
7
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
CourthouseCounty Clerk &
Recorder of Deeds
The County Clerk and Recorder of Deeds
functions have been combined and the space
on the first floor needs to be remodeled to
accommodate these functions.
Remodel the current County Clerk area to
accommodate this merger of functions.
Project completed 12-12-17.
Courthouse
Circuit Clerk &
Exterior Building
Water Infiltration
Issue
Water is infiltrating the building on the
Jefferson Street side and running into the
Circuit Clerk Office area.
Investigate where and how the water is
infiltrating the building and eliminate the
problem.
FY 2019 Capital Funds were
approved to do the Project in 1-
Phase. MWE sent revised
drawings and specifications to
review so project can be bid this
spring.
CourthousePublic Defender
Area
Relocate the Public Defender Office into the
Courthouse.
Identify, design, bid out, and build out
space for the Public Defender Office in the
Courthouse.
Options are being gathered and
reviewed on how and where to
proceed with this Project.
Brandywine
Building
Election
Commission
Relocation
The Election Commission needs to vacate
the City owned facility. New
accommodations need to be found and fit-
out for this move.
A lease has been entered into to allow for
the Election Commission to relocate. The
new facility needs to be properly fit-out.
Project was Substantially
Complete on Monday, 09-17-18.
User Group has moved into the
Space 09-12-18.
Courthouse Elevator Upgrade
Elevators C & D (public elevators on the
Hamilton Square side of the Courthouse) are
no longer code compliant. Similar conditions
exist for Prisoners Elevator and Judges
Elevator.
Upgrades to restore code compliance Elevator C completed 11-10-15.
Elevator D completed 03-21-16.
Prisoner Elevator upgrade
completed 12-21-18. Judges
Elevator upgrade contract
language being finalized.
Courthouse New Front DoorsAccess/Egress Security Renovate all entry and exit points
including Sally Port
Delayed.
Courthouse Judges Break Area
Area has original appliances and casework. Update the appliances and casework. P.O. issued to BBI to do this
upgrade. Casework in fabrication.
Jail Jail Central Control
Central Control equipment at the Jail is the
original from 1985 & controls doors, alarms,
cameras. It provides the electronic backbone
of jail Security.
Final phase of project. Update cell block
guard stations/control centers; intercom
systems; & additional video cameras
Project complete.
FY 2
01
4 -
20
19
BU
DG
ETED
Updated: 2/22/201917
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
JailJail Generator /
Transfer Switch
Generator & Transfer Switch for 1985 Jail
have far exceeded useful life & parts are not
available. 24/365 power is necessary at the
Jail.
Replace Generator & Transfer Switch for
1985 Jail
Project Completed.
Jail Jail Improvements
Mechanical systems in cell blocks of 1985 jail
need replacement.
Electrical, Plumbing, HVAC, & Locks will be
replaced in 1 cell block per year for next 8
years.
MWEA preparing drawings and
specifications for upgrades to
AHUs 1-9 equipment and
controls.
JailJail Improvements
Jail Locks
Cell locks at the Jail are beyond their useful
life and require replacement.
Replace locks in batches as funds are
appropriated
Ph 1 lock installation completed .
JailJail Improvements
Jail Locks
Cell locks at the Jail are beyond their useful
life and require replacement.
Replace locks in batches as funds are
appropriated
Ph 2 in Capital Budget for 2017.
Jail Administration deciding on
next cell block(s). PO to follow.
Jail
Jail Improvements
HVAC AHUs 1-9
Upgrade
AHUs 1-9 are original 1985 Jail equipment.
They operate on DOS based operating
system and have minimal operating controls.
Upgrade the operating system to
Automated Logic System that is used in
HO and JDC. Upgrade control valves and
install VFDs.
MWEA preparing drawings and
specifications for upgrades to
AHUs 1-9 equipment and
controls.
Jail
Rolling/Locking
Gates at Receiving
Area
The original rolling/locking gates of the
original Jail have exhausted their useful life.
New gates are required.
Replace the East Side rolling/locking gate
in 2107. Budget for the West Side
rolling/locking gate in 2018 Capital
Budget.
Project Funds diverted to Ring
Road Phase 2. Jail Administration
and Facilities are reviewing "work-
around" for East Gate operation.
Jail Fire Alarm Panel
Fire alarm panel, many detectors and related
equipment is at or beyond its useful life.
Phase 1 is to engage a consultant to
design and develop specifications for a
replacement system.
MWEA Phase II Proposal
approved by Infrastructure
Committee and Board in
February. MWE is developing
Phase II plans and specifications
with the intention of bidding this
work in the spring.
JailJail Kitchen /
Laundry Expansion
Need expanded capacity Study physical, operational & cost
feasibility of expanding Jail
Delayed.
FY 2
01
4 -
20
19
BU
DG
ETED
FY 2
01
4 -
20
19
BU
DG
ETED
Updated: 2/22/201918
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
JailRing Road Repair
Phase 1
Wet weather this spring and summer has
accelerated the life cycle replacement of the
Jail's Ring Road.
Saw cut, remove, and replace multiple
sections of concrete roadway.
Ph 1 completed 10-30-15.
JailRing Road Repair
Phase 2
Wet weather this spring and summer has
accelerated the life cycle replacement of the
Jail's Ring Road.
Saw cut, remove, and replace multiple
sections of concrete roadway.
Ph 2 completed on 12-01-17.
JailMasonry Tuck
Pointing
Several areas of the Jail show masonry wall
deterioration. There is a need to repair the
masonry walls for structural integrity and
water infiltration elimination.
Survey the exterior masonry walls, identify
the areas that need attention, prepare
and bid the repair work.
MWEA met with Facilities at Jail
to review conditions. Preliminary
report received. More
investigation required once
weather improves so Scope-Of-
Work can be developed. Bid
package will then be issued for
this work.
JDCBuilding
Automation System
To better control the HVAC systems at JDC,
additional controllers are needed along with
the infrastructure for the controllers to talk
to the building automation system.
Design, procure, and install technology
needed to achieve result.
Project complete.
Coroner / CACGift Ave Roof &
Fascia
Sloped roof & vertical fascia are beyond
warranty & useful life and leak.
Replace sloped roof & vertical fascia Project deferred due to funding.
JDC JDC Site GradingSally Port Road washes out / floods
preventing transport
Regrade drainage areas Completed October 2015.
JDCCentral Control
Equipment Upgrade
Central Control equipment at JDC is the
original equipment and controls doors,
alarms, cameras. It provides the electronic
backbone of Security.
Initial phase of project. Update control
center.
Work substantially complete.
Courthouse Courts Remodel
Multiple deficiencies per current courts
standards
Study, Reprogram, Plan & Design
Upgrades
Courtrooms 123, 222, 322, 221,
and121 completed and
operational.
Courthouse KVO Memorial
Create a war memorial honoring all veterans
that have died while in service for all
conflicts since WWII.
KVO Committee was created to define,
fund raise, and construct a war memorial
honoring all veterans that died in duty
since WWII.
Work Substantially complete on
October 5, 2018. Dedication was
October 20, 2018. Third statue
due by summer 2019.
PCAPS PCAPS QuarantineIsolation of sick animals Create isolated area Project complete.
PCAPSPCAPS Entry Separation of aggressive animals Create new separate entry point Project complete.
FY 2
01
4 -
20
19
BU
DG
ETED
Updated: 2/22/201919
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
ALLPaper Records
Storage
Record Storage & Management Conduct more in-depth analysis & study Future Project
Heddington
Oaks
Paper Records
Storage
Basement Storage Compartmentalization &
Security
See reference above to County-wide study Records moved from Gift Avenue
to H.O.
Bel-WoodHazardous
Materials
Hazardous Materials Abate and demolish this facility. Completed October 2015.
Space Utilization & Operational Efficiency Conduct Analysis/Study Dewberry engaged to do initial
usage study.
Departmental meeting space Study size and number of shared meeting
spaces
Dewberry engaged to do initial
usage study.
Life Safety
Deficiencies
Life Safety Deficiencies Conduct Health Life Safety Survey &
Implement Corrective Measures
Future Project
Physical environment no longer conducive to
operational mission
Develop a short & long term facility
replacement plan.
Future Project
Roof Leaks Replacement Bids Received Future Project
Future Use of HCWC
Options
Adaptive Re-use for the public good w/o cost
to Peoria County
Develop Business Plan to determine
operational & physical viability as self
sustaining entity
Future Project. Discussion in
progress with Federal
Representatives.
Future Use of HCWC
Options
Property Financial & Legal Liability for Peoria
County
Sell property to entity approved by State
of Illinois
Future Project. Discussion in
progress with Federal
Representatives.
Future Use of HCWC
Options
Minimize as Financial & Legal Liability Demolish physical structures, clear land
under County control and revert to natural
prairie habitat
Front 9-Houses abated and
demolished November 2014.
Future Use of HCWC
OptionsEliminate as Financial & Legal Liability Revert ownership to State of Illinois Future Project
Future Use of HCWC
Options
Adaptive re-use as shooting range for
Sheriff's Department
Public engagement response not
supportive of this use
Future Project
Highway
Restroom &
Mechanical Systems
Replacement
Sub-standard Restrooms & Mechanical
systems
Renovate restrooms & Upgrade
mechanical systems
Future Project
JDC Roof ReplacementRoofs at end of life cycle Replace roofs Capital Funding issues affecting
this work.
HIG
H
ALL
Space Utilization
EMA EMA Options
HCWC
Updated: 2/22/201920
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
PCAPS PCAPS QuarantineIsolation of sick animals Create isolated area Project complete.
PCAPSPCAPS Noise
Reduction
Excessive noise level Install Acoustical treatments Complete mid-2015.
PCAPS PCAPS EntrySeparation of aggressive animals Create new separate entry point Project complete.
West CampusBel-Wood Kitchen
Use
Need expanded capacity & "newer"
equipment
Study physical, operational & cost
feasibility of renovating portions of
Bel‑Wood
Completed.
Bel-WoodBel-Wood Site
Disposition
Future use & value Demolish building & clear site of all
improvements for outright sale or future
alternate County use
Completed October 2015.
CourthouseCounty Boardroom
Accessibility
Public Accessibility to County Boardroom Plan, Design & Remodel Future Project
CourthouseCounty Admin
Remodel
Operational Inefficiencies & HIPPA privacy Revise office plan layout & Remodel Future Project
Courthouse Courts Remodel
Multiple deficiencies per current courts
standards
Study, Reprogram, Plan & Design
Upgrades
Courtrooms 222, 322, 221, 123,
and 121 completed.
Courthouse Probation RemodelPrivacy & safe separation Reconfigure space to provide better public
access
Future Project
CourthouseState's Attorney
Remodel
Lack of contiguous functional space Close off corridor to eliminate office
separation
Future Project
Courthouse Grand Jury RemodelGrand jury room - upgrade quality of space Renovate to create more professional &
presentable space
Future Project
ETSBETSB Remodel -
ADA
Non-ADA compliant access Replace existing access/egress ramp with
ADA compliant access component
Future Project
Coroner / CACCountywide Record
Storage
Inefficient, sub-standard storage
environments
Renovate former juvenile cellblock,
reconfigure old gymnasium area &
upgrade storage systems
Future Project. Annual (2016)
record rotation completed.
Coroner / CACCoroner's Inquest
Remodel
Sub-standard interior environment & public
space for hearings
Renovate Inquest Room and integrate SOA
technologies for inquests & training uses
Future Project
Coroner / CACCoroner Lobby
Remodel
Sub-standard interior environment Renovate Lobby area Future Project
MED
IUM
Updated: 2/22/201921
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
PCCHDNew Health Dept
Facility
Building condition & configuration not
conducive to effective & efficient delivery of
services
Replace building at current location or re-
locate to Gift Avenue site
Future Project
PCCHDNew Health Dept
Facility
Explore opportunities to locate other County
departments or agencies in new complex,
i.e.: coroner's office
Conduct in-depth analysis of programming
needs, building, site and cost implications
Future Project
HighwayReplace Maxwell
Station
Sub-standard Facilities Developing Short & Long Term Facility
Replacement Plan
Future Project
HighwayReplace Fleet
Garage
Sub-standard Facility Replace Garage Future Project
HighwayReplace Maxwell
Station Salt Dome
Sub-standard Facility Replace Facility Future Project
Highway
Replace Maxwell
Station Vehicle
Storage
Sub-standard Facilities Replace Facilities Future Project
HighwayReplace Fueling
Station
Sub-standard Fuel Tanks & Fueling Station Replace & relocate Future Project
HighwayDemolish Maxwell
Station Yellow Bldg.
Sub-standard Facility Abate hazardous materials, demolish &
remove
Completed August 2015.
Highway
Addition to North
Station Vehicle
Storage
Lack of vehicle storage space Construct Additional storage building &
renovate old section of vehicle storage bay
Future Project. Moved old Bel-
Wood out building to North
station in early 2015.
HighwaySalt Dome
Upgrades
Need additional capacity & safer loading
system
Construct additional domes & loading
system
Future Project
JailJail Kitchen /
Laundry Expansion
Capacity & Operational deficiencies Expand core support functional areas -
food service, laundry, personal & evidence
storage, recreational space
Deferred to cover higher bids for
Jail Central Control and Jail Ring
Road.
JailJail Night Court
Addition
Bed capacity & operational efficiencies Study feasibility and cost effectiveness of
locating night court at jail
Future Project
Jail Shooting RangeCounty controlled range Study feasibility of developing range at
Hanna City or Bel‑Wood site
Future Project
MED
IUM
Updated: 2/22/201922
Facilities Master Plan
Project Status Update
PRIORITY FACILITY PROJECT ISSUE SOLUTION STATUS
CourthouseDepartment
Relocation
Lack of natural light Relocate offices to provide natural light Future Project
CourthouseDepartment
Relocation
Office location Office location in courthouse not essential
for effective operation. Explore optimum
location for County needs.
Future Project
RRC / VAC Office Remodel Minimal Public Visibility Add site/building signage Owner added some signage.
RRC / VAC Office RemodelMore efficient office layout could
accommodate additional small department.
Space utilization analysis, planning RRC moved to PCCHD. VAC
moved into their new space.
West Campus Property Disposal Disposition of property Sell property Future Project
One Tech Plaza Property Disposal Disposition of property Sell property Future Project
West Campus Develop PropertyOptimize value & return for Peoria County Sell property using proceeds for capital
improvement projects
Future Project
LOW
Updated: 2/22/201923
AGENDA BRIEFING
COMMITTEE: Infrastructure LINE ITEM: 036-2-036-5-514-55105
MEETING DATE: February 26, 2019 AMOUNT: $150,873.42
ISSUE: Resolution for a Construction Engineering Agreement with Hutchison Engineering, Inc. for the
Dirksen Parkway Reconstruction Project
BACKGROUND/DISCUSSION: The Dirksen Parkway Reconstruction project is scheduled to start in Spring,
2019. Two members of the Highway Department staff will perform the construction engineering for the project.
However, the Department has not been able to hire a Materials Engineering Technician to perform the required
testing of the concrete and earthwork. The testing is a requirement of the project, and specialized training is
required to perform the testing.
It is necessary for the Highway Department to utilize a consultant to perform the materials testing on the
Dirksen Parkway project. The consultant will also be available to perform supplemental construction inspection
on an as needed basis. The consultant will only be utilized when necessary to keep costs as low as possible.
This resolution will allow Peoria County to enter into an agreement with Hutchison Engineering, Inc. to perform
construction engineering inspection services for the Dirksen Parkway Reconstruction Project.
COUNTY BOARD GOALS:
INFRASTRUCTURE STEWARDSHIP
STAFF RECOMMENDATION: Approve the Resolution
COMMITTEE ACTION:
PREPARED BY: Jeffrey D. Gilles
DEPARTMENT: Highway DATE: January 23, 2019
24
Printed 1/18/2019 Page 1 of 6
Municipality
N/A
Name
Hutchison Engineering, Inc.
Township
Preliminary/Construction Engineering Services
Agreement For
Motor Fuel Tax Funds
Address
N/A 2015 W. Glen Ave., Ste 210
County City
Peoria Peoria
Section State
14-00102-PV IL
THIS AGREEMENT is made and entered into this day of February , 2019 between the above Local
Agency (LA) and Consultant (ENGINEER) and covers certain professional engineering services in connection with the improvement of the above PROJECT. Motor Fuel Tax Funds, allotted to the LA by the State of Illinois under the general supervision of the State Department of Transportation, hereinafter called the ”DEPARTMENT”, will be used entirely or in part to finance ENGINEERING services as described under AGREEMENT PROVISIONS.
WHEREVER IN THIS AGREEMENT or attached exhibits the following terms are used, they shall be interpreted to mean: Regional Engineer Deputy Director Division of Highways, Regional Engineer, Department of
Transportation Resident Construction Supervisor Authorized representative of the LA in immediate charge of the engineering details of the
PROJECT Contractor Company or Companies to which the construction contract was awarded
Section Description
Name Dirksen Parkway Rou
FAU 6671 Length 1.25 miles Structure
N/A
Termini Dirksen Parkway sta. 106+33 to 145+91 (Middle Road to Airport Road).
Description Reconstruction of Dirksen Parkway between Middle Road and Airport Road, including new PCC Pavement, curb and gutter, storm sewer, PCC sidewalk, lighting, traffic signals at Airport Road, and other colateral work.
Agreement Provisions
The Engineer Agrees,
1. To perform or be responsible for the performance of the following engineering services for the LA in connection with the proposed improvement herein before described, and checked below:
a. Make such detailed surveys as are necessary for the preparation of detailed roadway plans.
b. Make stream and flood plain hydraulic surveys and gather high water data and flood histories for the preparation of detailed bridge plans.
c. Make or cause to be made such soil surveys or subsurface investigations including borings and soil profiles and analyses thereof as may be required to furnish sufficient data for the design of the proposed improvement. Such investigations are to be made in accordance with the current requirements of the DEPARTMENT.
d. Make or cause to be made such traffic studies and counts and special intersection studies as may be required to furnish sufficient data for the design of the proposed improvement.
L O CAL AGENCY
CONSULTANT
25
Printed 1/18/2019 Page 2 of 6
e. Prepare Army Corps of Engineers Permit, Division of Water Resources Permit, Bridge waterway sketch and/or Channel Change sketch, Utility plan and locations and Railroad Crossing work agreements.
f. Prepare Preliminary Bridge Design and Hydraulic Report, (including economic analysis of bridge or culvert types) and high water effects on roadway overflows and bridge approaches.
NOTE Four copies to be submitted to the Regional Engineer
g. Make complete general and detailed plans, special provisions, proposals and estimates of cost and furnish the
LA with five (5) copies of the plans, special provisions, proposals and estimates. Additional copies of any or all documents, if required shall be furnished to the LA by the ENGINEER at his actual cost for reproduction.
h. Furnish the LA with survey and drafts in quadruplicate of all necessary right-of-way dedications, construction easements and borrow pit and channel change agreements including prints of the corresponding plats and staking as required.
i. Assist the LA in the receipt and evaluation of proposals and the awarding of the construction contract.
j. Furnish or cause to be furnished:
(1) Proportioning and testing of concrete mixtures in accordance with the “Manual of Instructions for Concrete Proportioning and Testing” issued by the Bureau of Materials and Physical Research, of the DEPARTMENT and promptly submit reports on forms prepared by said Bureau.
(2) Proportioning and testing of bituminous mixtures (including extracting test) in accordance with the “Manual of Instructions for Bituminous Proportioning and Testing” issued by the Bureau of Materials and Physical Research, of the DEPARTMENT, and promptly submit reports on forms prepared by said Bureau.
(3) All compaction tests as required by the specifications and report promptly the same on forms prepared by the Bureau of Materials and Physical Research.
(4) Quality and sieve analyses on local aggregates to see that they comply with the specifications contained in the contract.
(5) Inspection of all materials when inspection is not provided at the sources by the Bureau of Materials and Physical Research, of the DEPARTMENT and submit inspection reports to the LA and the DEPARTMENT in accordance with the policies of the said DEPARTMENT.
k. Furnish or cause to be furnished
(1) A resident construction supervisor, inspectors, and other technical personnel to perform the following work: (The number of such inspectors and other technical personnel required shall be subject to the approval of the LA.)
a. b. c. d. e. f.
Continuous observation of the work and the contractor’s operations for compliance with the plans and specifications as construction proceeds, but the ENGINEER does not guarantee the performance of the contract by the contractor. Establishment and setting of lines and grades. Maintain a daily record of the contractor’s activities throughout construction including sufficient information to permit verification of the nature and cost of changes in plans and authorized extra work. Supervision of inspectors, proportioning engineers and other technical personnel and the taking and submitting of material samples. Revision of contract drawings to reflect as built conditions. Preparation and submission to the LA in the required form and number of copies, all partial and final payment estimates, change orders, records and reports required by the LA and the DEPARTMENT.
NOTE: When Federal funds are used for construction and the ENGINEER or the ENGINEER’s assigned staff is named as resident construction supervisor, the ENGINEER is required to be prequalified with the STATE in Construction Inspection. The onsite resident construction supervisor and project inspectors shall possess valid Documentation of Contract Quantities certification.
26
Printed 1/18/2019 Page 3 of 6
2. That all reports, plans, plats and special provisions to be furnished by the ENGINEER pursuant to this agreement will be in accordance with the current standard specifications and policies of the DEPARTMENT, it being understood that all such reports, plats, plans and drafts shall before being finally accepted, be subject to approval by the LA and the said DEPARTMENT.
3. To attend conferences at any reasonable time when requested to do so by the LA or representatives of the DEPARTMENT.
4. In the event plans, surveys or construction staking are found to be in error during the construction of the PROJECT and revisions of the plans or survey or construction staking corrections are necessary, the ENGINEER agrees that he will perform such work without expense to the LA, even though final payment has been received by him. He shall give immediate attention to these changes so there will be a minimum delay to the contractor.
5. The basic survey notes and sketches, charts, computations and other data prepared or obtained by the ENGINEER pursuant to this agreement will be made available upon request to the LA or the DEPARTMENT without cost and without restriction or limitations as to their use.
6. To make such changes in working plans, including all necessary preliminary surveys and investigations, as may be required after the award of the construction contract and during the construction of the improvement.
7. That all plans and other documents furnished by the ENGINEER pursuant to the AGREEMENT will be endorsed by him and will show his professional seal where such is required by law.
8. To submit, upon request by the LA or the DEPARTMENT a list of the personnel and the equipment he/she proposes to use in fulfilling the requirements of this AGREEMENT.
The LA Agrees,
1. To pay the Engineer as compensation for all services performed as stipulated in paragraphs 1a, 1g, 1i, 2, 3, 5 and 6 in accordance with one of the following methods indicated by a check mark:
a A sum of money equal to percent of the awarded contract cost of the proposed improvement as
approved by the DEPARTMENT. b. A sum of money equal to the percentage of the awarded contract cost for the proposed improvement as
approved by the DEPARTMENT based on the following schedule:
Schedule for Percentages Based on Awarded Contract Cost Awarded Cost Percentage Fees Under $50,000 (see note)
%
%
%
%
%
Note: Not necessarily a percentage. Could use per diem, cost-plus or lump sum.
2. To pay for services stipulated in THE ENGINEER AGREES in accordance with the Total Compensation and Fixed Fee formulas shown on Exhibit A. Actual hourly rates shall be utilized. The hourly rates shown on Exhibit A represent the current rates on file with the Department. The total amount shown on Exhibit A shall be considered the Not-to-Exceed amount of this Agreement. The classifications of the employees used in the work should be consistent with the employee classifications for the services performed. If the personnel of the firm including the Principal Engineer perform routine services that should normally be performed by lesser-salaried personnel, the wage rate billed for such services shall be commensurate with the work performed.
27
Printed 1/18/2019 Page 4 of 6
Grade Classification of Employee Hourly Rate
Principal Engineer
Resident Construction Supervisor
Chief of Party
Instrument Man
Rodmen
Inspectors
The hourly rates itemized above shall be effective the date the parties, hereunto entering this AGREEMENT, have affixed their
hands and seals and shall remain in effect until . In event the services of the ENGINEER extend
beyond , the hourly rates will be adjusted yearly by addendum to this AGREEMENT to compensate for
increases or decreases in the salary structure of the ENGINEER that are in effect at that time. 3. That payments due the ENGINEER for services rendered pursuant to this AGREEMENT will be made as soon as
practicable after the services have been performed, in accordance with the following schedule:
a. Upon completion of detailed plans, special provisions, proposals and estimate of cost - being the work required by paragraphs 1a through 1g under THE ENGINEER AGREES - to the satisfaction of the LA and their approval by the DEPARTMENT, 90 percent of the total fee based on the above fee schedule and the approved estimate of cost.
b. Upon award of the contract for the improvement by the LA and its approval by the DEPARTMENT, 100 percent of the total fee (excluding any fees paragraphs 1j and 1k of the ENGINEER AGREES), based on the above fee schedule and the awarded contract cost, less any previous payment.
c. Upon completion of the construction of the improvement, 90 percent of the fee due for services stipulated in paragraphs 1j and 1k.
d. Upon completion of all final reports required by the LA and the DEPARTMENT and acceptance of the improvement by the DEPARTMENT, 100 percent of the total fees due under this AGREEMENT, less any amounts previously paid.
By mutual agreement, partial payments, not to exceed 90 percent of the amount earned, may be made from time to time as the work progresses.
4. That should the improvements be abandoned at any time after the ENGINEER has performed any part of the services provided for in paragraphs 1a and 1g, and prior to the completion of such services the LA shall reimburse the ENGINEER
for his actual costs plus percent incurred up to the time he is notified in writing of such abandonment
“actual cost” being defined as material costs plus actual payrolls, insurance, social security and retirement deductions. Traveling and other out-of-pocket expenses will be reimbursed to the ENGINEER at his actual cost.
5. That should the LA require changes in any of the detailed plans, specifications or estimates (except for those required pursuant to paragraph 4 of THE ENGINEER AGREES) after they have been approved by the DEPARTMENT, the LA
will pay the ENGINEER for such changes on the basis of actual cost plus percent to cover profit, overhead
and readiness to serve - “actual cost” being defined as in paragraph 4 above. It is understood that “changes” as used in this paragraph shall in no way relieve the ENGINEER of his responsibility to prepare a complete and adequate set of plans.
6. That should the LA extend completion of the improvement beyond the time limit given in the contract, the LA will pay the ENGINEER, in accordance with 2. of THE LA AGREES. The time limit used for this contract shall be the number of hours shown on Exhibit A. Any additional hours that require the ENGINEER to be on site beyond these hours shall be reason for a Supplement to this Agreement.
7. To submit approved forms BC 775 and BC 776 with this AGREEMENT when federal funds are used for construction.
28
Printed 1/18/2019 Page 5 of 6
It is Mutually Agreed,
1. That any difference between the ENGINEER and the LA concerning the interpretation of the provisions of this AGREEMENT shall be referred to a committee of disinterested parties consisting of one member appointed by the ENGINEER one member appointed by the LA and a third member appointed by the two other members for disposition and that the committee’s decision shall be final.
2. This AGREEMENT may be terminated by the LA upon giving notice in writing to the ENGINEER at his last known post office address. Upon such termination, the ENGINEER shall cause to be delivered to the LA all drawings, specifications, partial and completed estimates and data if any from traffic studies and soil survey and subsurface investigations with the understanding that all such material becomes the property of the LA. The ENGINEER shall be paid for any services completed and any services partially completed in accordance with Section 4 of THE LA AGREES.
3. That if the contract for construction has not been awarded one year after the acceptance of the plans by the LA and their approval by the DEPARTMENT, the LA will pay the ENGINEER the balance of the engineering fee due to make 100 percent of the total fees due under the AGREEMENT, based on the estimate of cost as prepared by the ENGINEER and approved by the LA and the DEPARTMENT.
4. That the ENGINEER warrants that he/she has not employed or retained any company or person, other than a bona fide employee working solely for the ENGINEER, to solicit or secure this contract and that he/she has not paid or agreed to pay any company or person, other than a bona fide employee working solely for the ENGINEER, any fee, commission, percentage, brokerage fee, gifts or any other consideration contingent upon or resulting from the award or making of this contract. For breach or violation of this warranty the LA shall have the right to annul this contract without liability.
29
Printed 1/18/2019 Page 6 of 6
IN WITNESS WHEREOF, the parties have caused this AGREEMENT to be executed in quadruplicate counterparts, each of which shall be considered as an original by their duly authorized offices.
Executed by the LA:
Peoria County of the
(Municipality/Township/County)
ATTEST: State of Illinois, acting by and through its
By ,
Clerk By
(Seal) Title:
Executed by the ENGINEER: Hutchison Engineering, Inc.
2015 W. Glen Ave., Suite 210
ATTEST: Peoria, IL 61614
By
Title: Secretary Title: President
Approved
Date Department of Transportation
Regional Engineer
30
Page 7 of 9 BLR 05611 (Rev. 11/09/17) Printed on 1/18/2019 4:26:48 PM
Exhibit A - Construction Engineering
Route: FAU 6671 (CH D49)
Local
*Firm’s approved rates on file with
(Municipality/Township/County) Bureau of Accounting and Auditing:
Section: 14-00102-01-PV
Project: OPEA(712) Overhead Rate (OH) 189.49 %
Job No.: C-94-014-17 Complexity Factor (R) 0.00
Calendar Days 275
Cost Plus Fixed Fee Methods of Compensation:
Fixed Fee 1 14.5%[DL + R(DL) + OH(DL) + IHDC]
Fixed Fee 2 14.5%[(2.3 + R)DL + IHDC] Specific Rate Lump Sum
Cost Estimate of Consultant’s Services in Dollars Element of Work Employee
Classification Man-Hours
Payroll Rate
Payroll Costs (DL)
Overhead (OH*DL)
Services by Others (SBO)
In-House Direct Costs
(IHDC)
Fixed Fee (FF) Total
1. Const Insp & Prinicpal 4.00 $70.00 $280.00 $530.57 $0.00 $0.00 $117.53 $ 928.10
Admin. Project Manager 4.00 $69.15 $276.60 $524.12 $0.00 $0.00 $116.10 $ 916.82
Engineer III 32.00 $51.58 $1,650.56 $3,127.64 $0.00 $0.00 $692.83 $5,471.03
Engineer I 50.00 $38.67 $1,933.50 $3,663.78 $0.00 $0.00 $811.60 $6,408.88
Eng Tech II 1100.00 $32.01 $35,211.00 $66,721.32 $0.00 $0.00 $14,780.18 $116,712.50
Eng Tech I 58.00 $25.65 $1,487.70 $2,819.04 $0.00 $0.00 $624.47 $4,931.21
2. Direct Costs
Vehicle Owned 0.00 $0.00 $0.00 $0.00 $0.00 $10,400.00 $1508 $11,908.00
Vehcile Mileage 0.00 $0.00 $0.00 $0.00 $0.00 $1,044.00 151.38 $1,195.38
OT Premium 0.00 $0.00 $0.00 $0.00 $0.00 $2,401.50 $0.00 $2,401.50
0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Totals 1,248.0
$40,839.36 $77,386.47 $13,845.50 $18,802.09 $150,873.42
31
Bureau of Design and Environment
Prepared By: Consultant
Printed 1/18/2019 8:41 AM Page 1 of 2 BDE 3608 Template (Rev. 10/19/17)
PAYROLL ESCALATION TABLEFIXED RAISES
FIRM NAME DATE 01/18/19PRIME/SUPPLEMENT PTB-ITEM# Prepared By
CONTRACT TERM 9 MONTHS OVERHEAD RATE 189.49%START DATE 4/1/2019 COMPLEXITY FACTOR 0RAISE DATE 12/31/2019 % OF RAISE 2%
END DATE 12/31/2019
ESCALATION PER YEAR
year First date Last date Months % of Contract0 4/1/2019 12/31/2019 9 100.00%
The total escalation = 0.00%
Hutchison Engineering, Inc.PrimeShane Larson
32
Bureau of Design and Environment
Prepared By: Consultant
Printed 1/18/2019 8:41 AM Page 2 of 2 BDE 3608 Template (Rev. 10/19/17)
FIRM NAME Hutchison Engineering, DATE 01/18/19PRIME/SUPPLEMENT PrimePTB-ITEM # 190
ESCALATION FACTOR 0.00%Note: Rates should be capped on the AVG 1 tab as necessary
IDOTCLASSIFICATION PAYROLL RATES CALCULATED RATE
ON FILEPRINCIPAL $75.00 $70.00
PROJECT MANAGER $69.15 $69.15
ENG V $62.53 $62.53
Eng IV $57.84 $57.84
ENG III $51.58 $51.58
ENG II $47.09 $47.09
ENG I $38.67 $38.67
ENG TECH VI $50.23 $50.23
ENG TECH V $43.90 $43.90
ENG TECH IV $40.49 $40.49
ENG TECH III $36.69 $36.69
ENG TECH II $32.01 $32.01
ENG TECH I $25.65 $25.65
PAYROLL RATES
33
PRINTED 1/18/2019 BDE 436 (Rev. 02/02/17)
COMPANY NAME:PTB NUMBER:
TODAY'S DATE:
ITEM ALLOWABLE UTILIZEW.O. ONLY
QUANTITYJ.S. ONLY
CONTRACT RATE TOTAL
Per Diem (per GOVERNOR’S TRAVEL CONTROL
BOARD)Up to state rate maximum $0.00 $0.00
Lodging
(per GOVERNOR’S TRAVEL CONTROL BOARD)Actual cost (Up to state rate maximum) $0.00 $0.00
Lodging Taxes and Fees
(per GOVERNOR’S TRAVEL CONTROL BOARD)Actual cost $0.00 $0.00
Air FareCoach rate, actual cost, requires minimum two weeks' notice,
with prior IDOT approval$0.00 $0.00
Vehicle Mileage (per GOVERNOR’S TRAVEL
CONTROL BOARD)Up to state rate maximum 1,800 $0.580 $1,044.00
Vehicle Owned or Leased $32.50/half day (4 hours or less) or $65/full day 160 $65.00 $10,400.00
Vehicle Rental Actual cost (Up to $55/day) $0.00 $0.00
Tolls Actual cost $0.00 $0.00
Parking Actual cost $0.00 $0.00
Overtime Premium portion (Submit supporting documentation) 150 $16.01 $2,401.50
Shift Differential Actual cost (Based on firm's policy) $0.00 $0.00
Overnight Delivery/Postage/Courier Service Actual cost (Submit supporting documentation) $0.00 $0.00
Copies of Deliverables/Mylars (In-house) Actual cost (Submit supporting documentation) $0.00 $0.00
Copies of Deliverables/Mylars (Outside) Actual cost (Submit supporting documentation) $0.00 $0.00
Project Specific Insurance Actual cost $0.00 $0.00
Monuments (Permanent) Actual cost $0.00 $0.00
Photo Processing Actual cost $0.00 $0.00
2-Way Radio (Survey or Phase III Only) Actual cost $0.00 $0.00
Telephone Usage (Traffic System Monitoring Only) Actual cost $0.00 $0.00
CADD Actual cost (Max $15/hour) $0.00 $0.00
Web Site Actual cost (Submit supporting documentation) $0.00 $0.00
Advertisements Actual cost (Submit supporting documentation) $0.00 $0.00
Public Meeting Facility Rental Actual cost (Submit supporting documentation) $0.00 $0.00
Public Meeting Exhibits/Renderings & Equipment Actual cost (Submit supporting documentation) $0.00 $0.00
Recording Fees Actual cost $0.00 $0.00
Transcriptions (specific to project) Actual cost $0.00 $0.00
Courthouse Fees Actual cost $0.00 $0.00
Storm Sewer Cleaning and Televising Actual cost (Requires 2-3 quotes with IDOT approval) $0.00 $0.00
Traffic Control and Protection Actual cost (Requires 2-3 quotes with IDOT approval) $0.00 $0.00
Aerial Photography and Mapping Actual cost (Requires 2-3 quotes with IDOT approval) $0.00 $0.00
Utility Exploratory Trenching Actual cost (Requires 2-3 quotes with IDOT approval) $0.00 $0.00
Testing of Soil Samples* Actual cost $0.00 $0.00
Lab Services* Actual cost (Provide breakdown of each cost) $0.00 $0.00
Equipment and/or Specialized Equipment Rental* Actual cost (Requires 2-3 quotes with IDOT approval) $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
TOTAL DIRECT COST $13,845.50
*If other allowable costs are needed and not listed, please add in the above spaces provided.LEGEND
Hutchison Engineering, Inc.N/A1/18/2019
Direct Costs Check Sheet
34
OT Premium Rate Calculations
HEI Classification Rate on File with IDOT Escalated rate for Project OT Premium Rate Eng Tech II $32.01 $32.01 $16.01
35
LABOR COSTS
ProjectWORK ITEM Prinicpal Manager Eng V Eng IV Eng III Eng II Eng I Eng Tech VI Eng Tech V Eng Tech IV Eng Tech III Eng Tech II Eng Tech I Total
Pre-Construction Actvities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Pre-Construction Meeting 0 Prep for Meeting (Agenda, Sign in Sheet) 0 Plan Review 0 Meeting Attendance 0 Meeting Minutes 0 Field Layout 0 Stationing 0 Checking horizontal/vertical control 0 Measuring Removal Items 0 Traffic Control Layout 0 Shop Drawing Review 0Construction Obersvation 32 50 1100 50 1232Documentation 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Project File Setup 0 RE/PM Meeting to discuss doc procedures/issues 0 Daily 0 Before & After X-Sections 0 QC/QA Reviews at 25% and 75% 0 Project Closeout 0 Finalizing Files 0 Review Revisions 0Progess Meetings 0Process Pay Requests/Estimates 0Administration 4 4 8 16
Total Hours 4 4 0 0 32 0 50 0 0 0 0 1100 58 1248Current IDOT Rates $70.00 $69.15 $62.53 $57.84 $51.58 $47.09 $38.67 $50.23 $43.90 $40.49 $36.69 $32.01 $25.65Total Direct Labor (DL) $280 $277 $0 $0 $1,651 $0 $1,934 $0 $0 $0 $0 $35,211 $1,488 $40,839
DIRECT COSTS
ITEM Quantity Unit Rate TotalMileage Survey Miles $0.580 $0.00 Pre-Construction Field Layout (25 miles/trip x 6 trips) Miles $0.580 $0.00 Construction Observation (150 days x 65 miles/day x 1 person) 1800 Miles $0.580 $1,044.00 Preconstruction Meeting Miles $0.580 $0.00 Progress Meetings (PM) Miles $0.580 $0.00 PM Site Visits (25 miles/visit x 20 visits) Miles $0.580 $0.00Premium OT for ENG TECH II 150 Hours $16.010 $2,401.50CADD Hours $15.000 $0.00Daily Vehicle Rate (200 days x 2 people) 160 Days $65.000 $10,400.00GPS Days $200.00 $0.00Nuclear Density Gauge Days $50.00 $0.00Concrete Cylinders Molds Each $2.00 $0.00 Testing Each $0.00Proctors Each $0.00
Total In House Direct Costs (IHDC) $13,845.50
TOTAL COMPENSATION
Overhead Rate (OH) = 1.8949Complexity Factor (R) = 0Fixed Fee (FF) = [DL+R(DL)+OH(DL)+IHDC] $18,802.13Overhead Amount = $77,386.50Services By Others SBO) = $0.00
Total Compensation = DL+IHDC+OH+FF+SBO $150,873
MANHOURSDIRKSEN PARKWAY RECONSTRUCTION
PEORIA COUNTY
36
TO THE HONORABLE COUNTY BOARD ) ) COUNTY OF PEORIA, IL ) Your Infrastructure Committee does hereby recommend the passage of the following Resolution:
RE: CONSTRUCTION ENGINEERING SERVICES AGREEMENT RESOLUTION
RESOLUTION
WHEREAS, your Infrastructure Committee, having considered the economic effects of the following project, believes that the best interests of Peoria County will be served by the approval of a Construction Engineering Services Agreement using the County Motor Fuel Tax Fund for:
Construction engineering for improvements to Dirksen Parkway, designated as Section 14-00102-PV, at a cost not to exceed $150,873.42, with Hutchison Engineering, Inc.
NOW THEREFORE BE IT RESOLVED, that the engineering agreement be approved and that the County Administrator be designated as the officer to sign the agreement with Hutchison Engineering, Inc. for construction engineering for improvements to Dirksen Parkway, designated as Section 14-00102-PV; and BE IT FURTHER RESOLVED, that the County Treasurer is hereby authorized to issue checks from the County Motor Fuel Tax Fund in payment for construction engineering services for Section 14-00102-PV. Respectfully Submitted, Infrastructure Committee
37