Agency C Procurement Process Business Process Map
description
Transcript of Agency C Procurement Process Business Process Map
LEVEL 1 UNIT 3 GREEN SQUARE KINGSTON 2604 P +61 6282 8852 F +61 2 6282 8832 WWW.THINKPLACE.COM.AU
AUSTRALIA NEW ZEALAND
Agency C Procurement ProcessBusiness Process Map
Project Analysis and Review of Commonwealth Procurement Processes for procurements under $80,000
Client Department of Finance and Deregulation
DateVersion
6 May 2011FINAL V1.0
ThinkPlace Team Raffaella RecuperoBehzad Emami
PAGE 2ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Purpose
This document contains a business process map for procurements under $80,000, which specifies the requirements set out in Agency C’s Operational Guidelines and other internal guidance, as well as the overarching requirements of the Commonwealth Procurement Framework.
ThinkPlace has worked with a small group of people in Agency C to develop this document.
ContentsIntent Statement 3
Business process maps 4Agency C CEI snapshot 5Role statements 7Map Levelling 10Level 0 map 11Level 1 map 12
Process analysis 17Process issues, pressure points and suggestions for improvement 18
PAGE 3ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Out of scope The project will not assess how well agencies implement the
CPGs and relevant FMA legislation when undertaking procurements
The project will not redesign policy
Where are we now?Analysis of ‘2008-09 AUSTENDER statistics indicate 85,000 contracts (over $10,000) were awarded. The total value of these contracts approx. $35bnOf those contracts, about 65,000 contracts falling under the $80,000 threshold were awarded. The total value of these contracts was about $12.6bnOver 80% of the total number of contracts correspond to about 4% total value. An APS 5/6 can spend up to 80% their time on low value contractsLow value contracts translate to a high administrative burden Agencies have tailored procurement approaches reflecting organisational structure, authority and delegations, approval processes, risk appetite, level of IT maturity, and resourcing, reporting processes and systemsProcurement functions differ in agencies – some functions are centralised, some are decentralisedParticipating agencies have undertaken work to review CEIs, processes and protocolsWhole of Government CEIs are under developmentWork has also been undertaken to simplify the standard short form contract, reducing the number of pages from 80 to 6
Intent
How do we get there?
Analyse and review Commonwealth procurement practices currently employed by selected agencies when conducting procurements under $80,000, identifying issues, pressure points and opportunities for improvement, and on that basis making recommendations for simplifying and streamlining processes.
What do we need to do?
What would success look like?A better practice model for procurements under the threshold that:
− Standardises the process across FMA agencies− Makes it easier for staff to know what to do and how
to conduct procurements − Reduces administrative burden
Finance will be able to use the project findings and recommendations as a basis for presenting a better practice model to FMA agencies, where appropriate. The project will influence agency CEIs and processes
Focussing question
How can we standardise and streamline the process for procurements under the $80,000 threshold, making it less onerous for FMA agencies, while also maintaining the integrity of the FMA Act?
A standardised, simple and safe process for all FMA agencies conducting procurements that fall under the $80,000 threshold
What is the problem/ opportunity?Agency procurement processes are complex, confusing, and onerous for staffRequirements vary from agency to agency – processes are not standardised across governmentSuppliers are frustrated
APPROACH FOR BRIDGING THE GAP
April
• Intent, planning and agency engagement
• CPG process modelling
May
• Agency CEI process mapping
• Case study development by agencies
• Case study analysis
June
• Synthesis • Design ‘better
practice model’
Timing
What do we need to consider?Avoid over-engineering or over prescribingAim to set a benchmarkImpact on behavioural change
Who do we need to involve?Agency C’s Procurement Policy BranchProcurement Policy Areas and representatives from line areas
Under the FMA Act, FMA agency CEOs have devolved authority to manage public money within their agency.
The FMA Act and Regulations set the framework for the proper management of public money and public property in the custody and control of the Commonwealth.
The Commonwealth Procurement Guidelines (CPGs) articulate the Government’s expectations for all department and agencies conducting procurement.
Agencies have evolved their procurement policies and practices within the context of the agency’s organisational structure, delegations, approval processes etc.
Agency specific policies and procedures are contained with large and complex volumes of CEIs, departmental policy documents and protocols.
SYSTEM IN FOCUS
LEVEL 1 UNIT 3 GREEN SQUARE KINGSTON 2604 P +61 6282 8852 F +61 2 6282 8832 WWW.THINKPLACE.COM.AU
AUSTRALIA NEW ZEALAND
Business process maps
PAGE 5ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Snapshot agency requirements specified by Operational Guidelines
PRINCIPLES
Outcomes per the procurement framework
Value for money is the core principle governing all procurement within the Australian Government sector Planned procurement is required to comply with the policies of the Commonwealth (refer FMA Regulation 9) Officials will be expected to maintain high ethical standards when they undertake procurementAll participating potential suppliers are to be treated as equitably as possibleThe process rules for any procurement need to be unambiguous, open and equitably applied to all relevant parties It is essential that an appropriate level of documentation is maintained for any procurement
PROCESS CONDITIONSStandards
Officials undertaking procurement are to record all major steps, the selected procurement method and all relevant decisions and authorisations relating to the project/acquisitionFor purchases under $5,000 file details of key decisions are required (handwritten or formal)Purchases between $10,000 to $80,000 require documentation of key decisionsAs the value of the procurement increases, the General Procurement Requirements (Section 2 of Operating Guidelines Vol. 4.3) set a more rigorous set of requirements for testing the market, in line with Division 1 – Procurement Principles of the CPG procurement framework All procurement activity in Agency C should have a risk assessment undertaken as part of the procurement process. This assessment should scale with the size and complexity of the procurement
PROCESS RULES Workflow Leg & Approvals
Section 44 of the FMA Act and Financial Circular 2011/01 charges Chief Executives to promote the efficient, effective, ethical and economic use of Commonwealth resourcesAn agreement to spend public money may not be entered into unless approval for the expenditure of the money has been given under FMA Regulation 9 (and, if necessary, with FMA Regulation 10)FMA Regulation 9 requires an Approver must not approve a spending proposal unless the approver is satisfied, after reasonable inquiries, that giving effect to the spending proposal would be a proper use of Commonwealth resourcesThe CPGs set down the fundamental policies which are to apply to all Commonwealth procurement activity. Officials must act in accordance with the CPGs, as required by FMA Regulation 7 Where an official undertakes procurement that is inconsistent with the CPGs, he or she is required to document his/her reasons for doing so
Note: Information sourced from Agency C and Operating Guidelines
PAGE 6ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Snapshot agency requirements specified by Operational Guidelines
RULES
Continued…
Purchases under $5,000Obtain verbal or written quotes and pay invoice
Purchases up to $10,000Use existing supplier, panel member, multi-use list member or access suppliers in the open market Obtain single verbal or written quoteWhere appropriate, seek multiple quotes to ensure value for money
Purchases $10,000 up to $80,000The rules for purchases up to $10,000 also applyFor service provider panels, seek one or more written proposalsIn all other cases it is desirable to obtain three written proposals, or more where necessary, to demonstrate value for moneyBusiness Groups to self assess probity, unless rated as Extreme/High riskDetails of all agency procurements, with an estimated contract value of $10,000 or more, must be published on AusTender, within six weeks of entering into the agreement
TOOLS USED
Self assessment formsProcurement formsOperational Guidelines 1.0 Delegations and AuthorisationsOperational Guidelines 4.4 Entering into & Managing ContractsOperational Guidelines 4.5 Payment of AccountsOperating Guidelines 4.6 Official TravelOperating Guidelines 4.7 Official HospitalityOperational Guidelines 7.1 Risk Management Financial Management Information System (SAP)
Note: Information sourced from Agency C Operating Guidelines
PAGE 7ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
DELEGATE
What are my specific obligations under the FMA Act and CPGs?Required to make sure the appropriate procurement method is selected and followedWhere appropriate, ensure that the contract is published on AusTender in a timely mannerThat Commonwealth resources are used in an efficient, effective, economical and ethical mannerTo abide by the delegation limit and threshold considerations
What is my role and my responsibilities?Ensuring Commonwealth resources are used in an efficient, effective, economical and ethical mannerAppropriate documentation and justification has been providedBudget has been approved and funds are availableAuthorise payment of supplier invoices
What are my concerns?A lack of understanding of obligations under the FMA Act, CPGs and CEIsPoorly scoped procurement that may not meet agency requirementsI trust that Line Areas are managing obligations (probity, conflict of interest, etc)
END USER
What are my specific obligations under the FMA Act and CPGs?Ensuring that the procurement satisfies the principles of:Efficient, effective, ethical and economic procurementValue for moneyAccountability and transparency (through proper reporting)
What is my role and my responsibilities?Getting the required goods and/or services into the agencyUtilising or directing the goods and/or servicesDealing with supplier invoices by certifying goods and/or services receivedEnsuring due diligence has been demonstratedDeveloping initial specification requirementsEnsuring agreement of purchase order number on contract and invoiceConfirming completed procurement specifications and providing signoff
What are my concerns?That goods and/or services do not meet procurement requirementsBudgeting constraintsMeeting deadlines
PROCUREMENT OFFICER
What are my specific obligations under the FMA Act and CPGs?Ensure procurement meets the Commonwealth principles of:Value for moneyEfficient, effective, ethical and economic procurement processAccountability and transparency
What is my role and my responsibilities?Ultimately provide an outcome to the business area (end user)Appropriately approach the marketRecording procurement process stepsAssessing the risk throughout the processCreating documentationEnsuring value for money has been demonstratedEnsuring due diligence has been demonstratedEnsuring agreement of purchase order number on contract and invoice
What are my concerns?Procurement processes are onerousMaking sure that end user needs are satisfiedMeeting deadlinesEnsuring Statement of Requirements is scoped properly for the procurementMaking sure that the applicable procurement processes have been conducted in compliance with the Rules and Regulations.
Agency C Procurement Process
Role statements
PAGE 8ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Role statements
PAYMENT PROCESSING
What are my specific obligations under the FMA Act and CPGs?Obligated under the conditions set out under the Certificate of Compliance
What are my responsibilities?Check if goods and/or services have been receivedMonitor the supply of goods and/or servicesProduce Certification of Suppliers InvoiceAuthorisation of supplier paymentFormally pay suppliers for goods and/or servicesEnsuring duel diligence has been demonstratedEnsure procurements under contract feature contract number on invoiceEnsure payment is made against currently appropriated fundingSAP data entry of Contracts / ordersCertify supplier invoice for correctness
What are my concerns?That Reg. 9 approval is in place and documentation has correct purchase value stated and there is delegate approvalPerson certifying goods receipt has appropriate knowledge of receiptPayment is being processed for the correct vendor
Central Procurement Unit (Procurement Advice Team)
What are my specific obligations under the FMA Act and CPGs?No specific obligations
What is my role and my responsibilities?Assist in meeting compliance requirementsProvide procurement related adviceDevelop templates and support materials for Line Areas Internal policy development (CEIs & OPGs)Reporting contractsDevelop Certificate of ComplianceCoordinate internal delegations instrumentsConducting training and education on procurement mattersEnsuring due diligence has been demonstrated
What are my concerns?Compliance mattersQuality of documentationStaff level of knowledge is appropriate and sufficient to competently perform dutiesCircumstances and processes related to ‘contract splitting’
SPECIALIST
What are my specific obligations under the FMA Act and CPGs?There are no specific obligations as it is assumed that the Procurement Officer is responsible for obligations under the FMA Act and CPGsSpecialists are accountable for the advice they provide, ensuring advice is accurate and complete to the best of their knowledge and that they are competent to provide such advice
What is my role and my responsibilities?To provide appropriate specialist (legal, audit, insurance, risk, etc) advice in accordance with the information provided, within the specified timeframes, and in accordance with legislation and internal policyEnsuring that due diligence has been demonstrated
What are my concerns?That accurate and relevant information has been provided in order to make a judgementTensions between time constraints (i.e. request deadlines) and quality of adviceUnclear whether specialist needs to be proactive in providing advice on procurements or should they wait for the Procurement Officer to solicit information
PAGE 9ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Role statements
SUPPLIER
What are my specific obligations under the FMA Act and CPGs?No specific obligations
What is my role and my responsibilities?Win the procurement contract by submitting documentation for evaluation in response to request documentationSupply goods and/or services in accordance with the statement of work/requirements Provide value for money serviceMake sure resources are available for the period of the serviceEnsure allocated resources are competent and competitive for the task at hand
What are my concerns?The amount of time it takes to go through the procurement processAmbiguities about how to do business with government and how to win business in governmentStandardisation of documentationThe possibility of delays or late payments for goods or servicesMeeting the expectations of the purchaserOften there is a lack of transparency which makes it unclear if suppliers have all been equitably treated
PAGE 10ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Level 0 – Process phases
This map provides an overview of the entire process end to end, including the process triggers, process phases, and main workflows.
Level 1 – Process activities
These maps drills down into each of the Level 0 process phases, detailing the activities that occur.
Level 2 – Procedural tasks, support products and systems
Level 2 is not generally documented as a map, but rather references guidelines, operational instructions, instruments and / or business systems such as databases. These things underpin the delivery of a process.
Symbols
ActivityActivity
DecisionDecision
Database/ Storage
Workflow
DocumentDocument Off page connector
Ongoing Activity
Ongoing Activity
EndEnd
Level 0Level 0
Level 1Level 1
Level 2Level 2
TriggerTrigger
Agency C Procurement Process
Map Levelling
PAGE 11ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
End User
ProcurementOfficer
Delegate
CPU (PAT)
PaymentProcessing
Specialist
Supplier
Agency C Procurement ProcessLevel 0 – Process Phases
Initiate procurement
process
Initiate procurement
process
Approachmarket
Approachmarket
Establishcontract
Establishcontract
Receive goods and services
Receive goods and services
Pay for goods and services
Pay for goods and services
Identifybusiness need
Identifybusiness need
Provide procurement submission
documentation
Provide procurement submission
documentation
Sign contractSign contract
Review SAP contract
Review SAP contract
PAGE 12ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
End User
ProcurementOfficer
Delegate
CPU (PAT)
PaymentProcessing
Specialist
Supplier
Agency C Procurement ProcessLevel 1 – Initiate procurement process
❷❷
Identifybusiness need
Identifybusiness need
ResourcesAGIMO wiki, agency intranet or business
group share drive contain guidance documents
such as Project plans, business plans, client
request purchase orders, strategic plan, etc
ResourcesAGIMO wiki, agency intranet or business
group share drive contain guidance documents
such as Project plans, business plans, client
request purchase orders, strategic plan, etc
Develop draft statement of work
(requirements)
Develop draft statement of work
(requirements)
Assist with formulating statement of work
Assist with formulating statement of work
Considerations•Estimated value of procurement / project•Check for existing arrangements in place•Review approach types
Considerations•Estimated value of procurement / project•Check for existing arrangements in place•Review approach types
Supply procurement templates
Supply procurement templates
Draft procurement plan
Draft procurement plan
Consider•Risk assessment•Procurement method•Identify conflict of interest•Evaluation approach•Identify potential venders
Consider•Risk assessment•Procurement method•Identify conflict of interest•Evaluation approach•Identify potential venders
Evaluation plan (draft)
Evaluation plan (draft)
Business proc. plan
Business proc. plan
Review documents against FMA Reg. 9/10 (as required)
Review documents against FMA Reg. 9/10 (as required)
Provide advice(as required)
Provide advice(as required)
Value of procurement
?
> $5,000< $10,000
Draftbusiness case
Draftbusiness case
Business case
template
Business case
template
Procurement plan
Procurement plan
Executive minute
Executive minute
Draft request documentation
Draft request documentation
Pre-approval?
No
EndEnd
Yes
RFQ / RFTTemplate
RFQ / RFTTemplate
Estimate procurement
costing
Estimate procurement
costing
Pre-approval considerationsHas the procurement initiate documentation clearly shown:•What is being purchased?•Why is it being purchased?•How is it being purchased?•Complies with FMA Reg. 9?
Pre-approval considerationsHas the procurement initiate documentation clearly shown:•What is being purchased?•Why is it being purchased?•How is it being purchased?•Complies with FMA Reg. 9?
Template storage
Template storage
SoW template
SoW template
< $5,000
> $10,000< $80,000
1 x Quote (verbal)
2 x Quote (written)
3 x Quote(written)
Issues•The business case, procurement plan executive minute all perform the same function•The requirements for documentation vary across business areas, and usually depend on the delegate’s needs
Seek delegate approval
Seek delegate approval
PAGE 13ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
End User
ProcurementOfficer
Delegate
CPU (PAT)
PaymentProcessing
Specialist
Supplier
Agency C Procurement ProcessLevel 1 – Approach market
❸❸❶❶ Approach marketApproach marketApproved
RFQ / RFT
Approved RFQ / RFT Evaluate submissionsEvaluate submissions Seek delegate
approval
Seek delegate approval
Approve?
Evaluation report
Evaluation report
Reg. 9/10 Evaluation
report
Reg. 9/10 Evaluation
report
Yes
❶❶
Provide completed procurement submission
documentation
Provide completed procurement submission
documentationTender response or quote
Tender response or quote
AusTender or direct
AusTender or direct
Participate in evaluating
submissions
Participate in evaluating
submissions
NoRe-evaluate
submissions or refine requirements
PAGE 14ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
End User
ProcurementOfficer
Delegate
CPU (PAT)
PaymentProcessing
Specialist
Supplier
Agency C Procurement ProcessLevel 1 – Establish contract
❹❹
❷❷ Negotiate contractNegotiate contract
Negotiate contractNegotiate contract
Sign contractSign contract
Advise unsuccessful suppliers of
procurement decision
Advise unsuccessful suppliers of
procurement decision
Accept contract?
Yes
No
s. 44 Procurement
contract
s. 44 Procurement
contract
Provide advice during contract negotiations
Provide advice during contract negotiations
Prepare SAP contract purchase order
Prepare SAP contract purchase order
SAP “simple” template
SAP “simple” template
Review SAP contractReview SAP contractSAP
contract acceptable?
Clear SAP contractClear SAP contract
Release SAP documentation
Release SAP documentation
Yes
No
SAP contract
SAP contract
Purchase order
Purchase order
❺❺If invoice and PO do not match…
SAPSAP
PAGE 15ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
End User
ProcurementOfficer
Delegate
CPU (PAT)
PaymentProcessing
Specialist
Supplier
Agency C Procurement ProcessLevel 1 – Receive goods and services
❺❺
Supply goods and/or services
Supply goods and/or services❸❸
Invoice for goods and/or services
provided
Invoice for goods and/or services
provided Supplier invoice
Supplier invoice
Contract managementContract management
Contract managementContract management
CEIManaging of contract
CEIManaging of contract
CEIManaging of contract
CEIManaging of contract
Out of scope
Out of scope
PAGE 16ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
End User
ProcurementOfficer
Delegate
CPU (PAT)
PaymentProcessing
Specialist
Supplier
Agency C Procurement ProcessLevel 1 – Payment for goods and services
❹❹ Verify supplier invoiceVerify supplier invoiceEnsure supplier invoice matches
purchase order (PO)
Ensure supplier invoice matches
purchase order (PO)AP form or
P/ON
AP form or P/ON
(APU) Approve payment
(APU) Approve payment
Receive paymentReceive payment
Invoice and PO match?
❸❸No
EndEnd
Contract managementContract management
Contract managementContract management Certify and receive goods and/or services
Certify and receive goods and/or services
CEIManaging of contract
CEIManaging of contract
CEIManaging of contract
CEIManaging of contract
Out of scope
Out of scope
Check SAP contract with Procurement Officer
Yes
FMISFMIS
Authorise paymentAuthorise payment
LEVEL 1 UNIT 3 GREEN SQUARE KINGSTON 2604 P +61 6282 8852 F +61 2 6282 8832 WWW.THINKPLACE.COM.AU
AUSTRALIA NEW ZEALAND
Process analysis
PAGE 18ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Agency C Procurement Process
Process issues, pressure points and suggestions for improvement
ISSUES
Current problems with the process – Documentation
Business Case, Procurement Plan, Statement of Work, Executive Minute, and request documentation all perform a similar function, yet are separate documents, resulting in several documents being developed at different stages of the procurement process.
It is also not clear which documentation is required for which procurement type.
In conjunction with the ambiguous documentation requirements, there is no minimum standard of documentation outlined for Delegate approval
The process is the same irrespective of procurement value. That is, all procurements require a business case.
Some business areas within the agency have their own set of procurement templates e.g. Government Network Services Branch This results in multiple and varied templates for common forms. The lack of standardisation of document templates is a major concern.
PRESSURE POINTSElements of the process that affect efficiency
For people new to procurement− Difficulties in specifying requirements− Unclear what quality looks like− Lack of understanding of red tape− End user doesn’t understand technical
requirementsTime constraints
Tight deadlines and onerous processes lead to shortcuts that comprise the procurement (at a principles level)
Risk assessments Assessment of risks are subjective and no
clear definitions, examples, methodologies are present
Roles and responsibilities A number of roles in the process have
accountability, yet it is not clear who is ultimately accountable
Processes and templates General lack of standardisation and ambiguity
of process and documentation Duplication of effort through the implementation
of different standards Tools not appropriately used for streamlining
due to lack of user friendly tools and guidanceLack of flexibility
Lack of recognition for the different categories of procurement and streamlining of processes
Whole of govt. arrangements and coop arrangements are disconnected and treated differently
SUGGESTIONS FOR IMPROVEMENTOutcomes from the workshop
Implement a standardised and streamlined process, minimum standards documentation that is commensurate with the procurement (i.e. less documentation for procurements <$5,000)
Educate relevant staff on processes, roles, accountabilities, etc
Investigate options to centralise procurement to specialists to reduce the impact / burden on business areas
Simplify procurement risk assessment procedures and tools
Increase implementation of e-tools for : Contract reporting (AusTender, SAP,
other) Volume purchase orders (Blanket
orders) in SAP Provide common terms & conditions
on internet
Create single product catalogue (for common items) across whole of government
Create more multi-use lists that leverage the expertise of other agencies e.g. Archives for file storage procurements
PAGE 19ANALYSIS AND REVIEW OF COMMONWEALTH PROCUREMENT PROCESSES UNDER $80,000 – AGENCY C PROCUREMENT V1.0
Page intentionally blank