AGEC/FNR 406 LECTURE 10
Rice drying on the Philippine National Highway
![Page 2: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/2.jpg)
Benefit-Cost Measures
Lecture Goals:
1. Present three tools of benefit-cost analysis
2. Discuss advantages and disadvantages of BCA
Don’t neglect to review the BCA packet!
![Page 3: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/3.jpg)
Three BCA tools:
1. Net Present Value (NPV)
2. Benefit-Cost Ratio (BCR)
3. Net Present Value (NPV)
![Page 4: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/4.jpg)
Net Present Value (NPV)
The net present value of benefits is the present value of those net benefits.
Net benefit is simply the sum of benefits minus the sum of costs.
NPV is the current value of all net benefits associated with a project
The net benefits are converted to present value by discounting.
![Page 5: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/5.jpg)
NPV Formula
Tt
tt
tt
r
CostBenefitNPV
1 1
![Page 6: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/6.jpg)
Key Point
If the project has a NPV > 0, then it is worth considering on its economic merits.
If the project has a NPV < 0, then it fails to return benefits greater than the value of the resources used.
![Page 7: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/7.jpg)
NPV Example
Time Benefit Cost Net Benefit
0 100 150 -50
1 100 100 0
2 100 50 50
all 300 300 0
-50/(1+.1)0 + 0/(1+.1)1 + 50/(1+.1)2 = -8.68
![Page 8: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/8.jpg)
Benefit Cost Ratio (BCR)
BCR is computed as the PV of Benefits divided by the present value of Costs.
Discounted benefits and discounted costs are calculated and summed separately, then divided.
![Page 9: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/9.jpg)
BCR Formula
Tt
tt
t
Tt
tt
t
r
Costr
Benefit
BCR
1
1
1
1
![Page 10: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/10.jpg)
Key Point
If the project has a BCR > 1, then it is worth considering on its economic merits.
If the project has a BCR < 1, then it fails to return benefits larger than its costs.
![Page 11: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/11.jpg)
BCR Example
Num. = 100/(1.1)0 + 100/(1.1)1 +100/(1.1)2 = 273.54
Den. = 150/(1.1)0 + 100/(1.1)1 +50/(1.1)2 = 282.22
BCR = 273.54/282.22 = 0.97 < 1
![Page 12: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/12.jpg)
Internal Rate of Return (IRR)
The IRR is the maximum interest rate that could be paid for the project resources that would leave enough money to cover investment costs and still allow society to break even.
The IRR is the discount rate at which the PVof benefits equals the present value of costs.
![Page 13: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/13.jpg)
IRR Formula
Solve for the IRR by finding i that solves:
PV(Benefits) = PV(Costs)
Use algebra or a spreadsheet
![Page 14: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/14.jpg)
Key Point
The IRR must exceed the chosen discount rate for the project to be accepted.
![Page 15: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/15.jpg)
IRR Example
100/(1 + i)0 + 100/(1 + i)1 +100/(1 + i)2 =
150/(1 + i)0 + 100/(1 + i)1 +50/(1 + i)2
i = 0
![Page 16: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/16.jpg)
Advantages of BCA
1. Provides a framework
2. BCA is quantitative
3. BCA is based on facts
4. The methods provide clarity
5. Results allow comparability
![Page 17: AGEC/FNR 406 LECTURE 10 Rice drying on the Philippine National Highway.](https://reader036.fdocuments.in/reader036/viewer/2022081602/551a85a1550346b52d8b58c2/html5/thumbnails/17.jpg)
Disadvantages of BCA
1. Requires valuation
2. Discount rate sensitivity
3. Plagued by uncertainty
4. Silent on equity
5. BCA is anthropocentric