AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will...

32
AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN TRANSPORT PROJECT OITC DEPARTMENT September 2014 Translated document

Transcript of AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will...

Page 1: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

AFRICAN DEVELOPMENT BANK GROUP

BENIN

PARAKOU URBAN TRANSPORT PROJECT

OITC DEPARTMENT

September 2014

Translated document

Page 2: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

TABLE OF CONTENTS

I – STRATEGIC THRUST AND RATIONALE ...................................................................... 1

1.1. Project Background ..................................................................................................... 1

1.2. Project Linkages with Country and Regional Strategies ............................................. 1

1.3. Aid Coordination ......................................................................................................... 2

II – Project Description .......................................................................................................... 3

2.1 Project Objectives ........................................................................................................ 3

2.2 Project Components ..................................................................................................... 3

2.3. Technical Solutions Adopted and Alternatives Explored ............................................ 4

2.4. Project Type ................................................................................................................ 5

2.5. Project Cost Estimate and Financing Arrangements ................................................... 5

2.6. Project Area and Targeted Beneficiaries ..................................................................... 6

2.7. Participatory Process for Project Identification, Design and Implementation ............ 7

2.8. Reflecting Bank Group Experience and Lessons in Project Design ........................... 7

2.9. Key Performance Indicators ........................................................................................ 8

III –FEASIBILITY ..................................................................................................................... 8

3.1 Economic and Financial Performance ......................................................................... 8

3.2. Environmental and Social Impact ................................................................................ 9

IV –IMPLEMENTATION ....................................................................................................... 12

4.1. Implementation Arrangements .................................................................................. 12

4.2. Monitoring ................................................................................................................. 14

4.3. Governance ................................................................................................................ 14

4.4. Sustainability ............................................................................................................. 15

4.5. Risk Management ...................................................................................................... 16

4.6. Knowledge Building .................................................................................................. 16

V – LEGAL FRAMEWORK ................................................................................................... 17

5.1. Legal Instrument ....................................................................................................... 17

5.2. Conditions for Bank Intervention .............................................................................. 17

5.3. Compliance with Bank Policies ................................................................................. 18

5.4. Constraint Related to Frontloading............................................................................ 18

VI – CONCLUSIONS AND RECOMMENDATIONS ...................................................... 18

6.1. Conclusions ............................................................................................................... 18

6.2. Recommendations ..................................................................................................... 18

Appendix i. Comparative socio-economic indicators of benin.

Appendix ii: table of Bank portfolio in benin

Apendix iii: Major Related Projects Financed by the Bank and Benin’s other Development

Partners

Appendix iv.Justification of Frontloading for Benin

Appendix v. Map of the project area

Page 3: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

i

Currency Equivalents

May 2014

UA 1 = CFAF 733.957

UA 1 = USD 1.54969

UA 1 = EUR 1.11891

Fiscal Year

1 January - 31 December

Weights and Measures

1 metric tonne = 2 204 pounds

1 kilogramme (kg) = 2.200 pounds

1 metre (m) = 3.281 feet

1 millimetre (mm) = 0.03937 inch

1 kilometre (km) = 0.621 mile

1 hectare (ha) = 2.471 acres

Acronyms and Abbreviations

AFD French Development Agency!

APD Avant-Projet Détaillé (Detailed Design Studies)

BAD African Development Bank

CNSR National Road Safety Center

CPTF Committee of Technical and Financial Partners

DGTP Directorate-General of Public Works

CSP Country Strategy Paper

ADF African Development Fund

EDF European Development Fund

GEF Global Environment Facility

FR Road Fund

INSAE National Institute of Statistics and Economic Analysis

MDGs Millennium Development Goals

PACITR Community Infrastructure and Road Transport Action Programme

ESMP Environmental and Social Management Plan

PRFTTRIE Regional Programme to Facilitate Inter-State Road Transport and Transit

RNIE Inter-State Trunk Roads

LTS Long Term Strategy

UA Unit of Account

EU European Union

USD United States Dollar

PIA Project Impact Area

Page 4: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

ii

Project Information Sheet

Client Information

BORROWER: Benin

DONEE: Benin

PROJECT NAME: Parakou Urban Transport Project.

LOCATION: Department of Borgou in Benin.

EXECUTING AGENCY: Ministry of Public Works and Transport (MTPT) of Benin,

Financing Plan

Source Amount (UA) Amount (US$) Instrument

ADF

23 800 000

Loan

ADF 11 530 415 Loan

GEF 1 201 256 1 861 574 Grant

BOAD 34 042848 Loan

Government of Benin 7 591 256 Counterpart Fund

TOTAL COST 78 165 774

ADB Key Financial Information

Loan Currency

Unit of Account (UA)

Type of Interest* N/A

Commitment Fee on ADF Loan * 0.5% per annum, on the undisbursed portion of the loan

120 days after the signing of the loan agreement

Service Fee on ADF Loan 0.75% per annum on the amount disbursed and outstanding

Other Charges * N/A

Maturity 40 years

Grace Period 5 years

FRR, NPV (baseline case) CFAF 86.082 Billion

ERR (baseline case) 28.42%

Timeframe – Main Milestones (Expected)

Concept Note Approval

February 2014

Project Approval September 2014

Effectiveness March 2015

Last Disbursement December 2020

Completion December 2019

Last Repayment 2074

Page 5: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

iii

EXECUTIVE SUMMARY

Project Overview

1. The Parakou Urban Transport Project aims to upgrade urban mobility in Parakou and

improve living conditions of people in the project area while reducing road accidents. The

project will rehabilitate and widen the 17.55 km main roads of the city into 2x2 lanes. The

total cost of the project net of taxes and customs duties is estimated at UA 78.17 million

(UA 53.24 M in foreign exchange and UA 23.8 M in local currency) and will be financed

by the Government (UA 7.59 M), ADF (UA 35.33 M which includes 23,8 MoUA in 2014

and 11,53 MoUA in 2015), GEF (UA 1.20 M) and BOAD (UA 34.04 M).

2. Given the "Frontloading" requirements that a country cannot commit more than 50% of its

allocation during the first year of the relevant ADF cycle, it is therefore recommended that

the ADF will grant to the Government of Benin a UA 23, 80 million loan under 2014,

representing a portion of UA 35.33 million needed to co-finance the project. The balance

of UA 11.53 million will be submitted to the Board‘s approval during the year 2015 on

Lapse of Time basis.

3. Project activities will be implemented from June 2015 to December 2020. The expected

outcomes for the project thereof include improving the average speed of traffic at peak

times on the two project roads, reducing road accidents, creating jobs et improving the

productivity of urban economic activities in Parakou. The development of the city of

Parakou will attract some many people and businesses, resulting in increased agricultural

production and improved household incomes in the Department of Borgu while ensuring

competitiveness of the whole country.

4. The project will contribute to poverty reduction in the PIA by improving access to basic

social services and strengthening the activities of women and other disadvantaged groups

through the creation of socio-economic activities in the city of Parakou.

Needs Assessment

5. Parakou is the third largest city with over 200,000 inhabitants and is the regional capital of

one of the most productive regions of Benin. The city is a Crossroads of major

international roads (Benin-Niger, Benin-Burkina Faso, Benin-Togo and Benin-Nigeria),

terminus of the Cotonou-Parakou railway of the Benin-Niger Joint Organisation (OCBN),

mandatory crossing point for national, regional and international traffic, as well as the

capital of the cotton-producing and agricultural area of the country. Besides, the city of

Parakou occupies a strategic position in terms of decentralization policy and regional

development of the country. And yet the city, hub for national and regional traffic lacks

the adequate road infrastructure to expand its impact area. The poor and narrow conditions

of the two main roads crossing the city are a major constraint to the development of urban

economic activities and bring about many traffic accidents. In addition, the serious traffic

congestion on these roads is detrimental to national and international traffic and

undermines the competitiveness of the North-South corridor. The development of these

roads is provided by the huge trade potential conferred by their role as transit roads

towards Niger, Nigeria, Togo and Burkina Faso.

Bank’s Value Addition

6. There are three level of justification why the Bank is involved in this project: (i) the Bank

is already engaged in the development of the economic potential of Northern Benin,

particularly through the road projects of Djougou- N'dali completed in 2009 and N'dali-

Nikki-Chicandou- Nigeria Border nearing completion; (ii) the project objective to loosen

the constraints of urban and regional development related to the poor state of transport

Page 6: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

iv

infrastructure and low regional connectivity is consistent with the Ten-Year Bank Strategy

that promotes infrastructure and regional integration as well as the Urban Development

Strategy of the Bank; and (iii) in supporting the urban, regional and international

development project, the Bank will continue to play a leadership role for the development

of the continent.

Knowledge Management

7. The project provides a good opportunity for the Bank to extend the knowledge on the

impact of developmental projects on urban development and the impact of attractiveness

and urban development on trade and regional integration.

Page 7: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

v

RESULTS-BASED LOGFRAME

Project Country and Name: Parakou Urban Transport Project in Benin

Project Goal: Improve Urban Mobility in Parakou and living conditions of people in project area while reducing road accidents.

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/

MITIGATING MEASURES Indicator (Including CSI)

Baseline Target

IMP

AC

T

Urban economic

activities and trade with

other regions and

neighboring countries

have improved in

Parakou.

Incidence of income poverty

for the Department of

Borgou

In 2013 : 31.5%

In 2019 : 29.75% Source : Statistics

INSAE

:

Outcomes Risks: (i) Lack of resources for

infrastructure maintenance by the FER and

the City of Parakou; (ii) non-compliance with

road traffic code and rules for the use of

municipal infrastructure

Mitigating Measures:

(i) Listing of the road projects in FR’s

priority programme, support for the

establishment of a governance body for

market infrastructure (which is expected to

collect user charges for maintenance) and

study on mobilizing local financial resources;

and (ii) Awareness of road safety, support to

CNSR in mobile awareness units

Outputs Risks People affected by the project are reluctant to

leave the work sites and relocate in the new

marketplaces and car stations.

Mitigating Measures

Public awareness by local authorities and the

Government along with compensation for

those people impacted by the project

EF

FE

TS

Outcome1: Mobility

and safety enhanced on

both project roads

Average speed on both

project roads during peak

hours

In 2013: 15km/h

In 2019: 30 km/h

(Or 100% increase)

Number of accidents on both

project roads.

In 2010: 162 In 2019: 100 Source: Statistics

CNSR

Outcome 2: Living

conditions of

populations improved

in the city of Parakou

Average household income

(total/ male/female)

En 2013:

66 291

/67918 / 50662

In 2019: 70 000

/72 000/ 52 000

Source: Statistics

INSAE

Percentage of population

spending less than a dollar a

day.

In 2013: 7.2% In 2019: 5%

Page 8: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

vi

Activity Rate

(Total/Male/Female)

In 2013 :

66.3%/75.2% /57.7

%

In 2019 :

67.5%/76.4% /59% Number of jobs created In 2013: 0 man-

month

In 2019 : 5000 men-

month

Sources: Office for

works oversight

PR

OD

UIT

S

Output 1:Urban

sections of roads built

and opened to traffic

Length of roads rehabilitated In 2013: 0 km

In 2019: 16.80 km

Source: DGTP

Output 2: Municipal

infrastructure and

women specific

activities strengthened.

1. Number of social and

commercial infrastructure

rehabilitated.

2. Proportion of women

operating in the three

markets;c

3. Number of youth and

women trained

4. Length of roads paved

5. Number of junctions built

In 2013:

1. Number = 0

2. Number = 70%

3. Number = 0

4. Length = 0 km

5. Units : =0

In 2019 :

1. =11

2.= 75%

3. =2000

4. 7 km

5. 5 junctions

Source: City Council

of Parakou.

Output 3:Urban

governance and

management tools

developed

1. Urban management

tools available (PDU,

addressing plan, traffic

plan, commercial

facilities management

body, etc.)

In 2013:

No management

tool developed

In 2019:

All study reports are

available.

AC

TIV

ITÉ

S C

S COMPONENTS RESOURCES (UA MILLION)

1.Road redesigning;

2. Freeing of the right-of-ways

3. Strengthening management aspects and municipal infrastructure

4. Project management.

1. Road redesigning: 52.01

2. Freeing of the right-of-ways: 5.85

3. Renforcement de la gestion et des infrastructures municipales:

10.16

4. Gestion du projet : 1.88

Imprévus et aléas : 8.27

TOTAL RESOURCES : 78.17

Page 9: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

vii

Calendrier d’exécution

Page 10: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

1

REPORT AND RECOMMENDATIONS OF THE BANK GROUP MANAGEMENT

TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO BENIN UNDER

THE PARAKOU URBAN TRANSPORT PROJECT

The Management hereby submits this report and recommendations on a proposed financing

for the Parakou Urban Transport Project

I – Strategic Thrust and Rationale

1.1. Project Background

The roads under the project are important sections of the Niamey-Malanville-Cotonou corridor

and the main urban roads of the city of Parakou. The first section, about 5.05 km, is the former bypass

of the city. Given the rapid urban growth, its surrounding areas are now highly urbanized. The second

section, about 11.75 km, is the crossing of the city of Parakou. There are particularly high risks of road

accidents on these two sections due to their poor condition and low urban, national and regional traffic

capacity. To solve these problems, the Government of Benin secured a BOAD funding in 2012 to

conduct a detailed execution studies for their rehabilitation. In January 2013, Benin's President

submitted a request to the Bank to finance the work and reiterated the importance of this project for his

country. A similar request was further submitted to BOAD who agreed to co-finance the project

alongside the Bank. The BOAD loan agreement was then signed on 31/03/2014.

1.2. Project Linkage with National and Regional Strategies

1.2.1 The project is aligned with the GPRS III (Growth and Poverty Reduction Strategy III)

for 2011-2015 which includes two strategic thrusts for the transport sector, namely (i)

establishment of transport, logistics and trade services; and (ii) improvement of transport

infrastructure. The project is also consistent with the 2014 -2018 Transport Sector Strategy

(TSS) which three strategic thrusts are (i) promotion and development of transport services;

(ii) management and development of transport infrastructure; and (iii) enhanced

competitiveness of ports and corridors. Finally, the project fits within the country’s

decentralization policy strategy and its space Agenda (National Land-Use Planning and

Implementation Framework ‘Schéma national d’aménagement du territoire et son cadre de

mise en œuvre’) adopted in 2013 and branding the city of Parakou as a balancing metropolis

against the Cotonou - Porto Novo tandem. The project is also in line with the Municipal

Development Plan of the city of Parakou for 2014-2016.

1.2.2 The project will improve the competitiveness of both corridors (Cotonou-Niamey and

Cotonou-Ouagadougou) as part of NEPAD's Short Term Agenda for Action (PACT) in terms

of regional integration and opening up, WAEMU and ECOWAS’ PRFTTRIE as well as

WAEMU’s PACITR. The project can therefore said to be supportive of the regional

strategies.

1.2.3 Furthermore, the project is aligned with the Ten-Year Strategy of the Bank as the

project will earmark at least 90% of its infrastructure cost to building an international corridor

and thereby foster regional economic integration, private sector, local SMEs, create jobs and

improve youth and women skills. The project will develop tools for local and national

governance as well as take measures for environmental protection. It is therefore an inclusive,

green, regionally-integrated and economically-diversified project. The project is well in

accordance with the two Pillars of the 2013-2017 CSP, namely, (i) Production and

competitiveness support infrastructure; and (ii) Promotion of good governance. In supporting

production, including agriculture and competitiveness through roads development and urban

management and governance capacity building of the city of Parakou, the project contributes

to the achievement of the two pillars of the CSP which revised mid –term programme

includes this project.

Page 11: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

2

Rationale for Bank’s Intervention

Key Development Issues

1.2.4 Though African cities generate about 35-40% of GDP and play a vital role in terms of

the economic development of the continent, so many constraints are undermining their

development including: (i) obsolete urban transport infrastructure for economic and social

growth and causing many road accidents; (ii) sloppy urban management and planning

1.2.5 Aware that well-managed cities and efficient transport is a prerequisite for economic

development, the Beninese authorities have placed urban development and the transport

infrastructure, including improved transport conditions of the city of Parakou among top

priorities. Parakou is the third largest city, enjoys a special status in the country with an

average annual growth rate of 3.76%, and faces the challenges related to urbanization, uneven

population distribution, traffic congestion in the inner city, planning and management of

urban services.

1.2.6 The city of Parakou is a crossroads of the major international roads connecting

neighbouring countries (Benin, Niger, Benin, Burkina Faso, Benin and Togo-Benin-Nigeria).

In addition, the terminus of the Cotonou-Parakou railway is the mandatory passage for

national, regional and international traffic and it is also the capital of the cotton and

agricultural region of the country. Yet, its contribution to the country's growth has remained

marginal due to poor road conditions, low traffic carrying capacity and lack of safety for the

two main roads of the urban road network. Therefore, Bank’s intervention is expected to put

in place a more efficient transport system likely to boost urban economic activities and

improve the country's competitiveness.

1.2.7 In addition to the development issues above-mentioned, Bank’s intervention can be

justified as follows: (i) the project objectives to upgrade the sections service in the Cotonou -

Niamey international road corridor crossing Parakou and traffic conditions in Parakou is, on

the one hand, in line with the NEPAD goals which leadership role under the activity

implementation is provided by the Bank and, on the other hand, with the ten-year strategy of

the Bank for the 2013-2022, which gives priority to infrastructure, regional integration and

governance in particular. They are also in line with the 2011-2015 West Africa Regional

Integration Strategy and the Bank’s Integrated Urban Development Strategy; (ii) the Bank has

decided to diversify its portfolio and increased its urban intervention, convinced of the central

role of African cities in the continent's growth; and ultimately (iii) The Bank support for this

project complements previous interventions in this region of the country and is part of a multi-

donor initiative (ADF, GEF and BOAD). Finally, the proposed project is a good example of

urban project involving donors, State and local authorities.

1.3. Aid Coordination

1.3.1 In Benin, the aid coordination is provided at both national and sector levels. At

national level, it is provided by the Technical Secretariat of the Economic and

Financial Programmes Monitoring Unit and the Ministry of Economic Analysis,

Development and Planning, through the Directorate-General of Investment and

Development Financing (DGIFD) and the Directorate-General for Project and

Program Monitoring. The implementation of the aid is provided by the Ministry of

Economy and Finance (MEF) via the Autonomous Amortization Fund (CAA). Given

the multiple stakeholders, unclear roles and responsibilities, the government

performance in project implementation and monitoring as well as aid coordination is

deemed moderately satisfactory. However, progress has been made in recent years

particularly in the context of the annual review of the GPRS. In this context, the TFPs

Page 12: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

3

split in joint thematic groups for cooperation chaired by the Government, with a TFP

that facilitates the work. A joint annual review government-TFPs for GPRS, preceded

by sector reviews, is conducted in June every year. At the sectoral level, the donors in

the country actively contributed to the development of the Transport Sector Strategy

(TSS), the National Rural Transport Strategy (SNTR) and the Road Maintenance

Strategy. The Road Fund Review Board (FR) is responsible for the dialogue with the

Government as a supreme body which brings together the Ministers involved in the

transport sector and two representatives of the donors (the EU and the Netherlands).

The board develops and monitors the Road Fund policy. As such, it generally

determines the prospects of its development. Donors involved in the transport sector in

Benin may meet whenever necessary upon invitation of the EU as the leader to

harmonize views on particular implementation of the Transport Sector Strategy,

programming of road projects, road maintenance financing, control of axle loads

limitation, and checkpoints limitation on the corridors.

1.3.2 The project preparation mission was conducted jointly with BOAD who co-signed the

memorundum thereto. During the appraisal mission, the consultation between BOAD,

the Bank and the Government finalised additional funding of CFAF 15 billion, so

completing the loan agreement of CFAF 10 billion already signed between BOAD and

the Government. An expanded consultation with the EU and AFD reaffirmed project

relevance. The joint financing agreement between the Bank and BOAD following the

Bank's rules and procedures of goods, works and services procurement, the annual

appraisal of the performance of key members of the project Implementation Unit

along with the commitment of the Government to enforce the axle load control on the

roads illustrate positive results from the Bank and other donors’ commitment. The

consultation will continue during the project execution through the joint organization

of project supervision missions with BOAD.

II – PROJECT DESCRITPION

2.1 Project Objectives

The project goal is to improve urban mobility in Parakou and living conditions of

people in the project area while reducing road accidents. Project specific objectives outline as

follows (i) upgrade the level of road service and reduce road accidents; (ii) ensure efficiency

of urban activities and improved living conditions of the communities in the city of Parakou.

2.2 Project Components

To achieve the objectives, Project activities have been classified into four components

as indicated in the table below.

Table 2.1 : Project Components

Component

Name

Estima

base

ted

Cost

(UAM)

Component Description

1. Road

Development

52.01

1.1 1 Rehabilitation works of 2x2 lanes of 11.75 km-long Parakou urban

crossing including footbridge at Arzéké market ;

1.2 Rehabilitation works of 2x2 lanes of the 5.05 km-long Parakou old bypass,

including protective wall;

1.3 Mitigation of environmental impacts and climate risk (planting of 3,600 trees,

development of forest reserves restoration of burrow area, reduction of CO2

emissions, etc.);

Page 13: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

4

1.3 Control/ monitoring of road works and raising public awareness;

2. Ancillary road

works 5,85 2.1 Displacement/relocation of water, electricity and telephone networks;

2.2 Compensation of persons affected by the project;

3. Upgrading

Municipal

Infrastructure

7,02

Support for women activities 3.1 Rehabilitation of Guéman and Azékê markets;

3.2 Rehabilitation of two social welfare centers;

3.3 Rehabilitation of arts and crafts center;

3.4 Provision of two women awareness / training mobile units.

Social infrastructure

3. Construction of fences for Sinagourou (750 ml) and Wansirou schools

Transport, Traffic and Road Safety

3.7 Upgrading and paving 4 km of urban roads;

3.8 Development of three road junctions;

3.9 Construction of a bus station in the southern part of the city;

3.10 Provision of 200 road signs;

3.11 Formulation of the national road safety policy;c

3.12 Provision of two mobile sensitization units to the National Road Safety

Center (CNSR) ;

3.13 Supply of 2 equipped ambulances for Parakou Firefighters;

3.14 Feasibility study for the Parakou new bypass ;

Urban Management Support

3.15 Study on the mobilization of local financial resources;

3.16 Support for the establishment of a business facilities management agency

( software, computer hardware, furniture + training) ;

3.17 Updating the Urban Development Master Plan (UDMP) and Traffic Plan

Development;

Employability and job creation

3.18 Training of truck drivers and mechanics;

3. 19Work control and supervision.

4. Project

Management

1,52

4.1 Auditing project accounts;

4.2 Technical audit of project;

4.3 3 Road Safety audit;

4.4 Monitoring and evaluation of project impacts;

4.5 Coordination and operation of executing agency

4.6 Delegated project management ;

4.7 Technical Assistance to the Municipality of Parakou.

2.3. Technical Solutions Adopted and Alternatives Explored

The Government et the Bank explored several options as to the technical and financial

design of the project. The technical solution adopted is the rehabilitation of the old bypass and

the road through (crossing) the city of Parakou. It is therefore planned to develop a 24.5 to

26.5 m platform, two 2-way roadways of 3.75 m each, separated by a 2 to 4 m median, with a

2.5m bicycle lane on both sides, 2m sidewalk with locations for urban furniture and

equipment (bus shelters, etc.). Given the high cost of such a development work, road

rehabilitation on a 16.5 m right-of-way with a single 2x1 lane roadway was considered but

was abandoned due it low a traffic carrying capacity both urban, national and international.

Table 2.2: Alternatives Considered and Reasons for Rejection

Alternative Brief Description Reasons for Rejection

Variant 1:Rehabilitation

following two profiles: (i)

PT1 in 2x2 lanes and PT2

in 1x2 lanes on the old

bypass; and (ii) PT2 in 1x2

lanes crossing the city

city 24.5 to 26.5 m platform for PT1 with

2x2 lanes of 3.75 m, a median and two bike

paths; and 16.5 m platform for PT2 with 1x2

lanes of 3.75 m

This profile has different

sections causing contraction areas which

bring about road accidents.

Page 14: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

5

2.4. Project Type

The specific project loan is the financing instrument which has proved most suitable

for Bank intervention within the framework of this operation. The ADF loan will enable the

financing, construction and rehabilitation of the socioeconomic infrastructure identified as

part of the project. Thus, the funds will be disbursed for well defined and specific

investments. It is a national stand-alone investment operation.

2.5. Project Cost Estimate and Financing Arrangements

2.5.1 The total cost of project, net of taxes and customs duty, is estimated at UA 78.17

million (CFAF 57.37 billion) of which UA 55.72 million in foreign exchange (CFAF 40.89

billion) or 71.28% and UA 22.45 million in local currency (CFAF16.48 billion) or 28.72%.

The project cost estimate was based on the feasibility studies and unit costs for works and

similar services dating back to 2014. It includes a provision for physical contingencies of

8.5% of certain base costs and 3.07% price increase of the base cost plus the physical

contingencies. The summaries of project cost estimates by component are indicated in Table

2.3. The detailed cost estimates and the expenditure schedule are given in Appendix 1.A of

the attached document.

Table 2.3 : Summary of Estimated Project Cost by Component [in CFAF and UA million ]

COMPONENTS CFAF billion UA million

FE LC Total FE LC Total

1. Road development 30,42 7,75 38,17 41,44 10,56 52,01

2. Ancillary road works 0,00 4,30 4,30 0,00 5,85 5,85

3. Upgrading municipal infrastructures 5,29 2,16 7,45 7,21 2,95 10,16

4 Project Management 0,86 0,52 1,38 1,17 0,71 1,88

Base Cost 36,57 14,73 51,30 49,82 20,07 69,90

Physical contingencies 3,11 1,25 4,36 4,23 1,71 5,94

Financial contingencies 1,22 0,49 1,71 1,66 0,67 2,33

Total Cost excl. taxes & customs duty

40.89 16.48 57.37 55.72 22.45 78.17

2.5.2 The project will be jointly financed by the ADF, GEF, the Government of Benin and

BOAD. The ADF as the main donor, will finance 45.2% of the project or UA 35.33 million (

CFA F 25.93 billion) of a loan to Benin in two phases : The first in 2014 (23,8 MoUA) and

the second in 2015 (11,53 MoUA). Counterpart funds represent 9.71% (UA 7.59 milllion) of

project cost. The financing plan is shown in Table 2.4 below and costs breakdown by category

and by source in Appendix III.

Table 2.4 : Sources of Financing [amount in CFAF billion and UA million]

SOURCES UA million CFAF billion

% Devises ML Total Devises ML Total

GOV. OF BENIN 0.84 6.76 7.59 0.61 4.96 5.57 9.71%

ADF 28.04 7.29 35.33 20.58 5.35 25.93 45.20%

GEF 0.87 0.34 1.20 0.64 0.25 0.88 1.54%

BOAD 2677 7.27 34.04 19.65 5.33 24.99 43.55%

Total project Cost 56.52 21.65 78.17 41.48 15.89 57.37 100%

2.5.3 The ADF contribution will entirely come from ADF 13’s country allocation of for

2014 and 2015.

Page 15: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

6

2.6. Project Area and Targeted Beneficiaries

2.6.1 Location. Parakou is located at the crossroads of major international road connecting,

in addition to the Niger north by the RNIE2, Burkina Faso north-west, Togo west and Nigeria

east. Moreover, the city is the terminus of the Cotonou - Niger railway. Parakou enjoys this

traffic dispatching role from the port of Cotonou, one of the main ports in West Africa, due to

its central location in the country that gives them access to all the Benin neighbouring

countries. Therefore, the city is characterized by high movement of people and an influx of

nationals of neighbouring countries, attracted by the regional and international scale of the

local markets.

2.6.2 Located in northern Benin, Borgou is a department of 25,856 square kilometres, 724,

171 inhabitants in 2002 and a density of 28 inhabitants per square kilometer. The direct

project impact area is the city of Parakou with its high movement of s population due to its

position as a hub. Parakou is the largest city in the northern part of the country and is situated

in north-central Benin and about 450 kilometres away from Cotonou. It is the regional capital

of the Department of Borgu and as such houses the public administration of the Department as

well as various community services needed to run a city. The city of Parakou enjoys a very

high population density estimated at more than 340 inhabitants per km² for an 441 km2 area.

Three quarters of the population live in truly urbanized area. Due its economic importance,

Parakou is the third largest city in Benin after Cotonou and Porto-Novo, so a big centre for

socio-economic activities. Parakou urban economy is characterized by a relatively active

commercial, industrial fabric making the city the second largest industrial platform of the

country, development of tractor trailer transport activities and predominant craft and informal

sector. Parakou activity rate is estimated at 58.5% and 30.6% for young people. The existence

of major local, regional and international in the city is due to the availability of local

agricultural commodities (cereals, tubers, legumes, livestock, and fisheries) and attracts

citizens of the four countries bordering Benin. The intense commercial activities around the

city induce various jobs for unskilled women and youth (motorcycle taxis and other survival

services). Moreover, Parakou has important tourist attractions such as the Royal Palace, arts

and cultural festivals, museum, market. However, this potential is not yet fully harnessed

since income poverty has reached over 33.1% of households in 2011 in the urban part of the

Department of Borgou and 22.5% of the city of Parakou. Parakou health situation is marked

by the presence of infectious and parasitic diseases such as malaria, diarrhoea, intestinal,

food-related or waterborne diseases and skin diseases as well. These pathologies are

attributable to poor sanitation. Furthermore, the narrowed project roads and the large vehicle

fleet and two wheels is the source of many traffic accidents.

2.6.3 Beneficiaries. 200,000 inhabitants are the beneficiaries of the project (49.9% women)

of the 3 districts of the city of Parakou. Specifically, the direct beneficiaries will be the main

socio-professional groups in the PIA (road users, carriers/transport operators, traders,

industrialists, women's groups, farmers, , schools and health centres users bordering the two

project roads, etc.) and local communities along the roads. The indirect beneficiaries include

people from other cities of Benin, including Borgou cotton farmers and also from

neighbouring countries, especially Niger, Burkina Faso, Togo and Nigeria.

2.6.4 Expected Outcomes. The beneficiaries will benefit from (i) low cost of vehicle

operation; (ii) a better access to production areas and basic social services; (iii) reduced

journey times, greater transport safety and security and relief crossing procedures at border

crossing; (iv) increase in household incomes; and (v) improved health status of the city

through reduction of the spread of infectious diseases and road accidents.

Page 16: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

7

2.7. Participatory Process for project identification, design and

implementation

2.7.1 The participatory process was incorporated into the appraisal process both during the

detailed feasibility studies and during the project development missions. Participatory

meetings were held with the communities of the PIA particularly those in the city of Parakou.

These plenary briefings and public consultation recorded the attendance of political and

administrative authorities of the municipality, officials of decentralized technical services,

transporters, traders and representatives of NGOs and women's associations and youth. They

focused on modalities of stakeholder information and participation. Plenary consultation

sessions were also held.

2.7.2 During these sessions, community and technical services representatives were able to

express their concerns and expose local realities regarding urban mobility, heavy vehicles

parking, preservation of road assets, road safety, marketing of agricultural products, spread of

water-borne and sexually transmitted infections and lack of access to socio-economic

activities. These discussions also identified some specific activities and related facilities for

women and take into account concerns about possible adverse effects of the project in its

formulation and in its Environmental and Social Management Plan (ESMP).

2.7.3 During project implementation, the participatory process was to be stepped up,

especially during supervision missions and mid-term reviews as well as in assessing the

project impact. Public consultations are also recommended for the implementation of the

ESMP.

2.8. Reflecting Bank Group Experience and Lessons in Project Design

2.8.1 Since the adoption of its integrated urban development strategy in April 2010, the

Bank began to diversify its portfolio including transport projects in urban areas. Such projects

could face the following problems at different levels: i) Until 2009, urban development was

ignored in the Bank research program; ii) few African countries have addressed the issues and

the opportunities of sustainable urban development. In addition, the peculiarities of urban

projects lie in; (i) the need to strengthen the participatory approach and interact closely with

communities; iii) opposed interests among social groups and emergence of lobbying groups;

iv) weak municipal governments responsible for implementation and management of

municipal infrastructure; v) overlap or lack of clear responsibilities between state and local

governments; vi) the poor ownership of project by local authorities; and (vii) lack of tools for

urban planning and management. Direct experience of the Bank in this area is relatively small

given that the Integrated Urban Development Strategy (from 2010) is at its infancy. Currently,

some isolated sector-specific interventions are underway in cities. The following lessons can

already be learnt from the implementation of these interventions: (i) there is a need for quality

baseline studies and to alleviate the procurement procedures to serve a diligent performance;

(ii) ownership and capacity of local authorities should be properly appraised and strengthened

to ensure a smooth implementation; and (iii) the implementation schedule of the project

should be drawn up taking into account the strong reluctance of people to vacate worksites.

2.8.2 The portfolio of the Bank's operations in Benin includes 17% of risky projects, but no

transport project is at risk. The latest project to be completed in the transport sector is the

development project of the N'dali-Nikki-Chicandou- Nigeria border road which was

completed a year before the deadline for final disbursement and can be viewed as a successful

project. The only current project is a multinational project to rehabilitate the Lomé-Cotonou

road and Transport Facilitation on the Abidjan-Lagos corridor which is implemented without

major constraints. The main lessons learned from completed projects relate to (i) securing

counterpart funds in a specific account; (ii) the judicious allotment of road and associated

Page 17: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

8

works to prevent flaws in procurement; (iii) the use of long-standing structures for project

execution; and (iv) close supervision of projects.

2.8.3 Key lessons have been incorporated into this project as follows: (i) address

institutional weaknesses of the City of Parakou; technical assistance, delegated Project

Management and urban management tools will be established; (ii) the technical, social,

environmental and institutional aspects have been prepared well in advance and consolidation

of the work and services in homogenous lots has been done; (iii) consultation and

involvement of beneficiaries and affected persons is done through a specific purpose entity at

municipal level; and (iv) ensure resources are available, and the opening of an account for the

counterpart funds will be a precondition for first disbursement.

2.9. Key Performance Indicators

The expected accomplishments of the project are mainly the reduction of travel time

and transportation costs, improved mobility and community access to socio-economic

infrastructure. The main outcome indicators are: (i) travel time; (ii) vehicle operating costs

(VOC); (iii) travel time, (iv) the mobility index, (v) passenger rate per kilometre, (vi) number

of road accidents; (vii) income per household in the PIA; (viii) access to water supply

facilities and sanitation, health infrastructure and public education. These indicators will be

monitored during the execution of the project and will be disaggregated by gender. Progress

towards the achievement of these results will be monitored through supervision reports of the

consultant in charge, as well as for follow-up and appraisal. A consulting firm will be hired to

establish the baseline for these indicators before work start-up, and assess the socio-economic

impact at the end of the project.

III – Projeect Feasibility

3.1 Economic and Financial Performance

3.1.1 Economic analysis: it was made using HDM4 model based on cost-benefit analysis

comparing the situation "without" (current situation) and "with" project (development of road

sections for Parakou crossing). The main factors taken into account in this analysis are: (i)

costs excluding all taxes of investments and maintenance of road improvements; (ii) a 15

years investment lifespan from the date of commissioning; (iii) the volume of normal traffic

on different roads and estimated future development on investment lifespan; (iv) comparison

of project benefits resulting from gains on vehicle operating costs and travel time on the road

sections (after the completion of work) compared to the baseline situation. A discount rate

12% and a 45% residual value of investments were considered by applying the optimal road

maintenance strategy.

3.1.2 The economic benefits (Net Present Value) arising from the project during the analysis

period (2014-2031 including 2014-2016 for the work) are estimated at CFAF 86.082 billion

across road sections. The internal rate of return (IRR) on the entire project amounts to 25.0%;

and is higher than the discount rate and thus demonstrates to the national community that the

project is viable.

3.1.3 Sensitivity analysis: Sensitivity tests of the economic viability of the project were

realized. The results of these tests confirm the economic viability of the project. They cover

incremental costs of work and /or a decrease in the normal traffic by 10% as shown in the

table below.

Page 18: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

9

Project Appraisal and Sensitivity Analysis

Baseline Analysis

Sensitivity Analysis

Cost+10% Traffic–10% Cost+10% &

Traffic–10%

IRR (%) 25.0 21.5 21.8 18.4

Updated balance (in billion CFA

francs) 86.082 82.816 76.317 73.052

NB: detailed calculations are shown in Technical Appendix IV.

3.2. Environmental and social impact

Environment

3.2.1 The project has been categorized on one type of work and the cumulative number of

people affected. The Study of Environmental and Social Impact Assessment (ESIA)

accompanied by a detailed Environmental and Social Management Plan (ESMP) and a

Comprehensive Resettlement Plan (CRP) was prepared between May and November 2013

and completed in March 2014 with support from the Bank. It has been validated by the

Ministry for the Environment of Benin by the issuance of a Certificate of Environmental

Compliance. Abstracts of the ESIA and CRP were posted on the Bank website on 28 April

2014.

3.2.2 The main positive environmental impacts of the project are: (i) improved quality of

life environment and movement of populations; (ii) the contribution to sustainable

development of urban transport in the city of Parakou and to a lesser extent in Benin. For the

latter impact details are provided in the section on climate change and promoting green

transport. The main negative environmental impacts and risks are: (i) the felling of trees; (ii)

the decommissioning of 10 ha of forest reserve in Parakou; (iii) the potential enhancement of

the degradation of said forest; (iv) the potential deterioration of the living environment of

residents and users of the various ways in pollution during construction, including noise, dust,

discharges of sewage, trash, etc. ; (v) the qualitative and quantitative potential degradation of

water resources. These negative impacts will be contained and manageable by the

implementation and monitoring of mitigation measures whose main concern are: (i) the

planting of 3600 trees (alignment and for the rehabilitation of burrow areas); (ii) the

classification of compensatory forest on at least 10 acres; (iii) the development and protection

of the forest of Parakou into a city park with goals of environmental education, rest and

recreation for the population; (ii) the implementation by companies of Plan for Site

Environmental Protection (PPES) and the Plan for Environmental Management of Worksites

(PGEC) containing all the measures to protect sites including material extraction and

execution program.

The cost of ESMP excluding cost of resettlement and related activities is estimated at CFAF

775 762 098.

Climate Change

Climate Change

3.2.3 The key issue in climate change is the production of greenhouse gas emissions which

about 5,000 tonnes of CO2 per year. The main mitigating measures concern mainly

plantations of trees, the green space development and restoration of the classified forest of

Parakou. Also, specific actions, financed from the resources of the Global Environment

Facility (GEF) for the improvement of air quality contribute to this objective. This will mainly

include: (i) establishing the baseline for air quality in relation to the transport sector Parakou

accompanied by training actors for monitoring; (ii) training of mechanics gear 2 and 4 wheels

with the possibility of garage; (iii) emission control and monitoring and evaluation of impacts;

(iv) awareness of those involved in the entire chain. These actions are detailed in Appendix xi.

Page 19: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

10

3.2.4 In addition to the above actions, it is provided: (i) the implementation of the Strategic

Environmental and Social Assessment (SESA) of the transport sector in Benin that will define

the outline of the E & S measures to implement and consistent with the policy and strategy of

the transport sector development in Benin; (ii) improving public transport by building bus

stops and two bus stations consistent with the green growth strategy of the Bank; (iii) the

development and implementation of waste and by-products transportation strategy including

waste oils, used batteries as well as used tires.

Gender

3.2.5 The female population of Parakou (49.89%) is roughly equal to the male population

(50.11%). 64.1% of these women (against 45% of men) are illiterate while according to the

latest survey of integrated modular households living conditions in Benin, the analysis by

level of education, unambiguously indicates that incidence of poverty, whatever its form,

decreases with education. Indeed, Benin, women have little economic power compared to

men but are less vulnerable to poverty than men. Discrimination based on sex that explain the

access in terms of economic power in Benin inequalities are mainly related to education

which in turn influences the size of the household, type of employment, occupational status,

the branch activities, place of residence, migration status, etc. To reduce these inequalities, a

component "supporting specific activities of women" has been specifically developed and

includes: i) rehabilitation and upgrading markets Azékê, Depot and Guéman; ii) the

reconstruction of three centres (two centres of social promotion and a centre of arts and

crafts); and 3) provision of two mobile awareness / training units for women.

3.2.6 53% of women in the PIA are heavily involved in the business which focuses on the

distribution of local agricultural and handicraft products (cereals, tubers, citrus, poultry) and

manufactured goods. They play a very important role in the city markets where they represent

70% of traders. In addition, the location of crossroads city of Parakou is great potential for

trade, which is why this city has 13 markets, which are supplied by local producers despite

their low production and especially the products coming neighbouring regions. The supply of

these markets is done by road and is provided primarily by the RNIE2. The accessibility of

streets and certainly the resumption of traffic and intensification will therefore have a positive

impact on the functioning of markets as it will facilitate the supply and flow of goods. The

profitability of women's economic activities will be enhanced by rehabilitating three major

markets of the city, planned as part of this project.

3.2.7 Furthermore, according to the Demographic and Health Survey 2012, 30% of women in

PIA tolerate or justify domestic violence and 41% of women reported having been

circumcised, which affects their well-being and is attributable mainly to a lack of awareness,

training and legal assistance. Therefore, the project will rehabilitate two social welfare centres

in order to set up a drop-in and counselling service for women and girl victims of gender-

based violence. The main mission of this service is to provide legal support and advice to

victims and educate and inform on the rights of women and girls and fight against violence.

Moreover, the most significant adverse impacts of the project on women especially girls

emanates from the influx of foreigners and job seekers in the phase of implementation of the

project. 20% of adolescent girls in the PIA have already started early reproductive lives, while

the proportion of women (71%) aware of AIDS is one of the lowest in the country. Indeed,

this promiscuity and mixing can lead to moral depravity, development of prostitution and

adultery, unwanted pregnancies and sexually transmitted infections. Mitigating measures will

include the establishment of a centre of arts and crafts as well as two mobile learning units to

provide training and awareness campaigns for female population in PIA.

Page 20: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

11

Social

3.2.8 The expected social impacts of the proposed project include reducing the travel time

for transportation services, operating costs of vehicles and reduced rates as well as improved

safety and quality of transport services. The project will have a positive impact in terms of

poverty reduction, to the extent that it will create more employment opportunities and income

generation through the development of economic activities and improving accessibility socio-

economic infrastructure (health and education facilities, local markets, etc.). Despite the risks

that could result from failure to comply with safety standards for drivers and pedestrians,

widening the RNIE2 and bypass included in the project will reduce the risk of traffic accident.

Improving sanitation in the vicinity of two project roads will fight recurrent flooding in some

areas and reduce the incidence of malaria and waterborne diseases. During construction, the

project will create jobs and investment income for more than 200 local workers for three

years. The influx of workers will boost demand for services such as accommodation, catering,

transport and permit the establishment of small shops for the sale of agricultural, fishery and

handicraft, which will improve the living conditions of these workers and their families and to

enhance savings and the creation of individual and family microprojects.

3.2.9 However, during and after construction, road safety, the risk of road accidents, the

spread of STI/ HIV /AIDS will increase due to increased traffic, speed of movement and the

influx of workers into the project area. California building walls, closing schools and health

centers close to the road, the construction of speed bumps were incorporated into the project

to mitigate these risks. In addition, awareness campaigns on road safety, HIV/ AIDS and

environmental protection are included in the contract office that will be responsible for the

control and supervision of road works.

3.2.10 In order to enhance the socio-economic impact and contribute to improving the living

conditions of people in the PIA, the project includes the rehabilitation of the two markets, the

provision of two mobile training units and construction three social promotion centres. This

support will improve the conditions of the trade so traders returned, strengthening vulnerable

through training and sensitization populations.

Forced relocation

3.2.11 The project will result in the total or partial destruction of property including: (i)

informal trade facilities (551 and 917 barracks buildings); (ii) 470 terraces which are growths

of small, informal and formal businesses; (iii) 431 houses, unfinished buildings and boundary

walls. A total of 2,459 persons are affected along the two roads which RNIE2 for 1703 and

756 for the bypass. The cost of the resettlement plan including monitoring and auditing, is

CFAF 1,482,075,691 and is borne by the Government of Benin. An action plan for the

finalization and implementation of the resettlement plan has been agreed with all

stakeholders. This is especially important in finalizing the plan, submitting evidence of

compensation for affected before work begins will be a condition for loan disbursement.

Monitoring the implementation of the ESMP and capacity building

3.2.12 ESMP implementation will be monitored by a local ESMP monitoring unit, composed

of representatives of the relevant municipal and county services performed. This unit will be

supported by the Department of the ESIA of DGTP and Benin Environmental Agency who

will follow up according to their powers. Regarding the latter, and pending the signing of an

order fixing the amount of the fee for projects in general and highway projects in particular, a

Memorandum of Understanding to be signed between the DGTP and EBA to define the

monitoring methodology.

Page 21: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

12

3.2.13 In the context of strengthening the environmental and social capacities of actors it is

considered providing: (i) the training of actors on the EESS; (ii) updating the how to manual

for road projects by integrating the aspects concerning expropriations, gender and climate

change coupled with the training of actors; (iii) training of 2 and 4 wheels mechanics under

the pilot phase under the GEF; (iv) capacity building of stakeholders responsible for the forest

reserve management.

IV –Implementation

4.1. Implementation arrangement

4.1.1 The project executing agency is the Ministry of Public Works and Transport (MTPT)

through the Directorate-General of Public Works (DGTP). This Directorate has sufficient

staff and a proven track record in implementing projects regarding national or international

roads, funded by donors including the ADF, IDA, EU, IDB, BOAD, etc. DGTP therefore has

the skills to coordinate and oversee the implementation of the components related to road

construction, environmental and social policies and institutional support.

To ensure effective monitoring of project delivery, a coordinator (experienced road engineer)

at the DTN whose résumé has been approved by the evaluation mission staff has been

appointed. He monitored the detail design studies and the project preparedness and appraisal

missions. A 2nd

engineer from DTN will be seconded on the ground to work with a City

Council Officer from Parakou to set up a team of 2 counterparts who will closely liaise with

the various technical departments concerned as well as the consultant responsible for work

supervision. In addition, the Senior Accounting Officer and the Executive responsible for the

financial management of road projects in progress, who are fully conversant with SYSCOA

accounting set of references will take care of the financial and accounting management of the

project. The team thus formed will be set up through the order issued by the Minister of

Public Works and Transport and will be equipped based on the Government counterpart with

the means necessary for the performance of its mission (operation, etc.). The staff of the DTN

has already received training in project management and on the rules and procedures of the

Bank with regard to the acquisition and disbursement. Another training session is scheduled

during the project launch mission. The project coordinator’s performance will be subject to

annual evaluation on the basis of a contract of performance to be finalized before negotiation.

4.1.2 Progress has been made in terms of harmonization of aid and of implementation of the

Paris Declaration on aid responsiveness in respect of the use of public bodies as regards

projects delivery in both countries. As part of the Bank's portfolio in Benin, the share of

projects at risk increased from 47% in 2010 to 25% in 2014, which reflects a net improvement

in the implementing capacity of countries.

Procurement activities

4.1.3 The national procurement procedures in Benin were assessed by the Bank in 2011.

The national system of public procurement mostly complies with international standards and

the standard files for national invitations to bid (DTAON) were inspired by the standard

documents of multilateral development banks and international financial institutions.

Accordingly, in accordance with the letter of agreement established between the Government

of Benin and the Bank in respect of the use of national procedures for national invitation to

bid, acquisitions of goods whose amounts are below the thresholds established by the Bank

for Benin, will be processed through National Competitive Bidding (AON) in accordance

with the national legislation on public procurement using the standard documents for local

invitations to bid. All other acquisitions of goods will be made by international competitive

Page 22: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

13

bidding (AOI) and by selection of consultancy services, in accordance with the “Rules and

Procedures of the Bank for the acquisition of goods and works”, dated May 2008, revised in

July 2012 and with the “Rules and Procedures of the Bank for the use of Consultants”, dated

May 2008, revised in July 2012, using the standard documents for invitation to bids relevant

to the Bank, as well as to the provisions which will be laid down in the financing agreement.

The BOAD has agreed to abide by the rules and procedures of the Bank in respect of

acquisitions.

Financial Management

4.1.4 The implementing agency selected to deliver the project should have adequate technical,

human and material resources; a reliable institutional environment, including an effective

system of internal control; qualified, readily available and motivated senior personnel, as well

as appropriate tools, in support of (i) proper accountability and exhaustively the whole of the

operations performed during the project life cycle; (ii) the backup of both financial data and

assets acquired; (iii) the information and the audit of available financial resources. A review

of the financial management system of the project has been carried out. The evaluation was

related to the Project Delivery Unit within the General Directorate of Public Works (DGTP)

of Benin which will be responsible for administrative, financial and accounting management.

A Project Coordinator and a Senior Accountant were identified. The formal decision

(ministerial order) to set up the aforesaid Unit or to appoint previously designated officials

will be taken before the negotiations relating to the project. Moreover, the shortcomings

detailed in the technical Appendix B4 were identified on the various components of the

financial management. That is why the national system will not be used in the context of this

project.

4.1.5 An accounting system specific to the project will therefore be put in place and will be

linked to (A) an integrated management software configured according to commitment

accounting rules of a private type adapted to project management and capable of (i) producing

financial statements for annual summaries comprising a consolidated and cumulative cash

flow statement mode of the year, as well as a balance sheet; (ii) carry out the monitoring of

budget implementation through the establishment of an acceptable budgetary accounting; (iii)

record the expenditures by category and by components, and resources by funding source.

The project Management will keep an independent accounting system so as to produce its

own financial statements. Transactions to be recorded in the accounting records of the project

will include not only those relating to the use of AfDF funds, but also those being

implemented against the counterpart funds and (B) a guidebook of administrative, accounting

and financial procedures with a clear separation of duties

Disbursement

4.1.6 Disbursements out of the AfDF funds will be done through the following two

methods: (i) via direct payments as recommended for the payment of the expenses relating to

work and control, as well as the other consultants’ services, including the audit of the

accounts, etc. etc. and (ii) through the method of reimbursement which will only be used in

case of need for reimbursement of eligible expenditure to the project and whose the

prefinancing has been authorized on the counterpart funds. Disbursements on the counterpart

funds will be done following the national procedures in accordance with the provisions (i) of

Decree N° 2012-226 of 13 August 2012 issued by the President of the Benin Republic on the

establishment and management terms and conditions of a Beninese fund of counterpart funds

devoted to projects; (ii) of the decree of the Minister of Economy and Finance No.

1136/MEF/DC/SGM/CAA of the December 07, 2012 laying down detailed rules for the

application of the decree on the establishment and to the modalities of management of

Beninese counterpart funds in respect of projects; (iii) and the Economy and Finance

Page 23: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

14

Minister’s circular letter N° 2157/MEF/DC/SGM/CAA relating to procedures for mobilizing

and using Beninese counterpart funds devoted to projects.

Audit

4.1.7 An independent external private auditor will be recruited on the basis of terms of

reference acceptable to the Bank and in accordance with the rules and procedures of the Bank.

His/Her contract will cover a budget year renewable on the basis of the quality of the services

previously provided. The reports that he/she will produce for each budget year will be

forwarded to the Bank for approval, not later than six months after the close of the said budget

year.

Timeline for implementation and supervision

4.1.8 Project delivery will run from June 2015 to December 2019. The relevant timeline for

implementation, abstract at the beginning of this report is outlined in detail in Appendix C. 1

of the attached document. Upon the approval of the funding of the project, the AfDF will

launch the project and will subsequently conduct supervisory missions whose provisional

timetable and composition are shown in Appendix VI of the document attached hereto.

4.2. Monitoring

Monthly and quarterly progress reports will be prepared by the consultants responsible

for monitoring and supervising the work on behalf of the implementing agency which will on

a quarterly basis regularly provide to the Bank the projects progress reports of including the

implementation of the PGES based on the standard format of the Bank and encapsulating the

whole of the project activities. These reports will include physical, financial, social and

environmental issues in order to help appraise the level of achievement of project goals.

Furthermore, supervisory missions of the Bank will be regularly carried out, in accordance

with the manual of operations of the Bank. A mid-term review, if needed, and a final

assessment including building sites completion reports and the completion report of the Bank

are also planned.

Timeline for monitoring Project Delivery

Duration Steps Follow-up activities / feedback loop

Quarter 1 -

2015 Launch of the project Supervisory report and progress reports

Quarter 2 -

2015

Completion of acquisitions relating to civil

engineering work Procurement Plan /Progress Report

Quarter 3 -

2015 Mobilization of service providers Supervisory report and progress report

Quarter 4 -

2015 Start of road and related work Supervisory report and progress report

Quarter 1 -

2016

10% of rate of delivery of civil engineering

work Supervisory report and progress report

Quarter 3 -

2016

25% rate of delivery of civil engineering

work Supervisory report and progress report

Quarter 1 -

2017

60% rate of delivery of civil engineering

work Mid-term review and progress report

Quarter 3 –

2017 Completion of civil engineering work Supervisory report and progress report

Quarter 3 –

2018 Expiry of the warranty period Supervisory report and progress report

Quarter 4 –

2019 Project Completion Project Completion Report

Page 24: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

15

4.3. Governance

4.3.1 The Government of Benin has taken strong action to combat corruption and has started

work on the reform issues related to internal control, notification and audits. Transparency

and fairness in the management of funds and government contracting have improved

markedly since 2006 through the following measures: i) release of a directory on reference

prices for government contracting; ii) enactment of a new code of government contracting; iii)

enactment in 2008 of a decree laying down the maximum deadlines for competitive bidding

steps; i) establishment in 2007 of an office of the State Inspectorate General reporting directly

to the President’s Office ; v) since 2008 the legal representative of the Treasury Department

has been reporting directly to the President’s Office; (vi) strengthening of the Inspectorate

General of Finance; and (vii) development of a new legal framework, the regulatory function

of government contracting being differentiated from that of public procurement management.

Besides, since 2008, the financial contribution of projects from the Beninese government is

granted by the CAA. These improvements have been secured thanks to the Bank’s active

contribution through a Project in Support of Audit Institutions and Support Programmes for

Growth Strategy and Poverty Reduction (PASCRP III and IV).

4.3.2 Corruption risks during procurement processes and the performance of relatively

highly-paid civil engineering contracts will be detected and mitigated through: i) the pre-

review process conducted by government contracting bodies from both countries; ii) the

review of procurement documents that helps the Bank to control the process via its non-

objection notification issued at each of the main steps; (iii) the Bank’s regular supervision and

the financial and accounting audit of the project underscoring abnormal discrepancies

between the scopes of work, service delivery and the work actually done and disbursements

and loan agreements; iv) the choice of direct method of payment with regard to the

disbursement of funds for contractors and service providers; and (v) the use of post-

qualification procedures which ensures for greater competition.

4.4. Sustainability

In respect of sustainable highway infrastructure, the road work relating to the project

involved will monitored by an engineering firm selected from among those with proven

experience and required engineering and technical skills. Moreover, it is anticipated that a

consultant will be tasked to conduct a technical audit. Finally, the existence of a financially-

independent National Strategy for Road Maintenance Fund (RF) in Benin shows evidence of

sustainability. The RF revenue which covers approximately 53% of current and periodic

maintenance requirements is expected to increase with the commissioning of new-built

tollbooths. As a result of such a deficit, resources are primarily allocated to a priority network

forming the two roads under the ongoing project in respect of the four major roads of the

national highway system. The project roads will therefore be maintained in the long term To

ensure both the satisfactory coverage of maintenance needs and upscale the local industry of

road maintenance, the EU funded since 2011, multi-year pilot routine maintenance programs.

As regards socio-economic infrastructure (markets, schools, women's centres, etc. ) which

will be renovated as part of the project, related maintenance will be provided by the City

Council of Parakou, thanks to the levies to be collected by the autonomous state-owned

bodies that the project will help to set up, as well as by Parents’ Associations. Finally, in

accordance with the road map adopted in May 2013 by WAEMU Ministers responsible for

Transport and Public Works, axle load control should become effective starting from the first

day of July 2014. Biannual campaigns to measure axle loads are carried out along the major

inter-African road systems, including the roads under the project and in terms of the platforms

with traffic of more than 200,000 tonnes of freight per year. Submission of campaign reports

to the Bank will be a condition of the project funding.

Page 25: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

16

4.5. Risk Management

4.5.1 The successful implementation of the project and the achievement of its objectives

will depend on several factors that may each be a risk to the said project. Besides the risks

related to the governance and sustainability, the main ones are as shown below:

Risks related to results

4.5.2 Lack of resources for infrastructure maintenance: it is a moderate risk that is mitigated

by the inclusion of the project roads into the RMF priority program, the support to the

establishment of a management body of market infrastructure (which should help collect the

user charges for maintenance purposes) and a study on mobilizing local financial resources

which should help identify new sources of municipal revenues.

4.5.3 Resilience of the persons affected by the project to integrate the new locations of

markets and stations: this high risk will be mitigated by awareness of population and the

establishment of a framework for dialogue with local and governmental authorities.

Risks related to operations

4.5.4 Resilience of persons affected by the project to release the work sites: this risk deemed

to moderate will be mitigated through raising the awareness of local populations, the

establishment of a framework for concerted action with the local authorities and the

Government and compensation for the people affected by the said project.

4.5.5 Unforeseeable rise in the cost of the work: this risk, though moderate, will be

mitigated by the availability of relatively recent detailed working designs (2013) and a

provision for price increases. Furthermore, the procurement files are in the process of being

finalised, which will help us to kick-start competitive bidding processes upon the approval of

the loan including acquisition modes ensuring wide competition (publication in UNDB, in

newspapers having wide circulation and with the embassies of the member countries present

in both countries, in the General Procurement Notice and in specific notices);

4.5.6 Lengthy delays in the ratification of the loan: it is a moderate risk that can be mitigated

by the simplification of existing ratification procedures since the establishment of the new

Ministry for Relations with Institutions and whose role is to make relations with the

Parliament easier, among other things.

4.5.7 Fiduciary Risk (procurement and financial management): it is a moderate risk that will

be mitigated by regular oversight of the project, annual audits of the project accounts,

monitoring system of project delivery (reports, etc. ) and the launch of the project which will

be the occasion to ponder over the project delivery terms and conditions. Moreover, the office

of the Bank based in Togo (30 min flight from Cotonou) will provide close support to the

implementing body;

4.5.8 Non-provision in a timely manner of the counterpart funds: this is a substantial risk

given the high level of the counterpart fund (10% of project cost). It will be mitigated by the

funding terms which provide for the opening of the project’s account for counterpart funds

and its replenishment according to the schedule of expenditures of the project;

4.6. Knowledge Development

4.6.1 A number of studies have shown that the cost and conditions of transportation impact

the cost of goods, the cross-border trade and the living conditions of the populations. In order

to check on this relationship in its context, project design will include an agreed set of

Page 26: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

17

performance indicators aimed to effectively appraise the project achievements and results.

Such indicators were outlined in paragraph 2.10 above.

4.6.2 The establishment of an operational monitoring and assessment mechanism for this

project impact will help build and disseminate knowledge. The monitoring of indicators will

be done by a consultancy firm that will confirm the reference base prior to the onset of the

project activities and the impact evaluation at the end of the project.

4.6.3 The main knowledge will be disseminated through a national participatory workshop

and will be incorporated into the database of the Directorate of Planning and monitoring-

evaluation (DPSE) at the DGTP in Benin.

V – Legal Framework

5.1. Legal Instrument

The instruments devoted to fund this project include (i) an ADF concessionary loan; (ii) a

BOAD concessional loan of 13.62 million UA; and (iii) a BOAD non-concessional loan of

20.44 million UA, (iii) a GEEF grant of 1 861 574 USD. The ADF loan amounting to

23 800 000 UA from 2014 PBA and 11 530 415 UA from 2015 PBA, will be fully funded

from the country ADF 13 allocation.

5.2. Conditions associated with the Bank’s intervention

A. Conditions precedent to the entry into force

A.1 Conditions precedent to the entry into force of the AfDF loan and GEF grant

The entry into force of the loan agreement will be conditional on the borrower’s

implementation of the conditions laid down in section 12.0.1 of the General Conditions

applicable to loan and security agreements. The GEF grant with enter into force upon the

signature of the Agreement.

B. Conditions precedent to the first disbursement of the AfDF loan

The first disbursement of the loan will be conditional on the borrower’s implementation of the

following conditions:

i) Provide the AfDF with the evidence of the opening of an account with the General

Directorate of the Treasury and Public Accounting Department, on behalf of the project

and its replenishment with an amount equivalent to the expenditures of the national

counterpart for the first year (paragraphs 2.8.3);

C. Other Conditions

AfDF Loan and GEF grant:

i) Provide to the ADF, not later than 30 April of each budget year, the evidence of the

account replenishment in accordance with the needs for the year including the account for

counterpart funds (para. 2.8.3);

ii) Provide to the ADF, not later than 31 March of each budget year, the reports of the

biannual campaigns to measure axle loads, carried out during the previous year,

throughout the system of inter-African major roads, including the project roads of and the

platforms generating a traffic of more than 200,000 tonnes of freight per year (paragraph

4.4.2).

iii) Provide, as and when progress before any work begins, evidence of compensation for

those affected by Project in the concerned area, according to resettlement plan and the

Page 27: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

18

rules and procedures of the Fund on the subject, including Policy on involuntary

resettlement Fund.

D. Undertakings. The Borrower agrees to the satisfaction of the Fund:

i) Implement the Project, the Environmental and Social Management Plan (ESMP) and the

Abridged Resettlement Plan (ARP) and also enforce their implementation by its

contracting parties, in accordance with the national law and with the recommendations,

requirements and procedures contained in the ESMP, the CRP and the relevant rules and

procedures of the Fund.

ii) Refrain from commencing construction work on a concerned area without the affected

persons in such areas having received full compensation; and

iii) To report on a quarterly basis in form acceptable to the Fund on the Environmental and

Social Management Plan (ESMP) and the Abridged Resettlement Plan (ARP), including

the appropriate corrective actions to be undertaken.

5.3. Compliance with the Bank’s Policies

* No exception is provided within the policies.

* The proposed project is consistent with all applicable policies of the Bank.

5.4. Constraint related to the concentration at the beginning of the cycle

(Frontloading)

Taking into account the concentration rule at the beginning of the ADF cycle which imply

that a country should not commits, during the first year of the ADF cycle concerned, more

than 50% of its allocation. It is therefore recommended that a loan of 23, 8 million of UA

being accorder in 2014 and the remaining balance, 11,53 million of UA, being subject to a

request for approval by the Board during the year 2015 on a lapse-of-time procedure. A

request substantiating the frontloading by the country’s absorptive capacity, the undertaken

reforms and the performance of the country is attached as appendix IV.

VI – CONCLUSIONS AND RECOMMENDATIONS

6.1. Conclusions

The project relates to one of the missing road sections of one of the most important corridors

from an economic standpoint in West Africa. It will help promote the urban economic

activities in Parakou, thereby responding to Benin poverty reduction strategies. It is consistent

with the 2013-2022 Long-term Strategy of the Bank. Thanks to its contribution to the

reduction of transportation costs, to economic growth and to the improvement of the living

conditions of the populations of its area of influence, the project will be instrumental in

reducing poverty in Benin. Its internal economic rate of return estimated at 25.0 % is

satisfactory.

6.2. Recommendations

The Management recommends that (i) the Board of Directors approve the ADF loan proposal

amounting to UA 23,800 million to the Benin Republic; (ii) the Boards of Directors approve

the implementation of the project by the Bank of GEF Fund amounting to US 1,861,574, for

funding the project described in this report and according to the above conditions and (iii) the

Board of Directors approve during the year 2015 on Lapse of Time basis the balance of UA

11.53 million on the basis of the same appraisal report.

Page 28: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

I

Appendix I. Benin Comparative Socio-economic Indicators

Year Benin Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 113 30 323 98 458 35 811Total Population (millions) 2013 10,3 1 109,0 5 909,3 1 252,8Urban Population (% of Total) 2013 46,2 40,2 47,7 78,3Population Density (per Km²) 2013 80,8 46,9 70,7 23,5GNI per Capita (US $) 2012 750 1 719 3 815 38 412Labor Force Participation - Total (%) 2012-2013 36,9 37,4 67,9 72,1Labor Force Participation - Female (%) 2012-2013 47,7 42,5 38,6 44,6Gender -Related Dev elopment Index Value 2007-2011 0,477 0,502 0,694 0,911Human Dev elop. Index (Rank among 187 countries) 2012 166 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2003-2011 47,3 40,0 20,6 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2013 2,7 2,5 1,3 0,3Population Grow th Rate - Urban (%) 2013 4,1 3,4 2,5 0,6Population < 15 y ears (%) 2013 42,8 40,9 28,3 16,4Population >= 65 y ears (%) 2013 2,9 3,5 6,1 16,8Dependency Ratio (%) 2013 86,1 77,9 52,4 49,9Sex Ratio (per 100 female) 2013 99,3 100,0 103,3 94,4Female Population 15-49 y ears (% of total population) 2013 23,8 24,0 53,1 45,2Life Ex pectancy at Birth - Total (y ears) 2013 59,3 59,2 68,4 77,8Life Ex pectancy at Birth - Female (y ears) 2013 60,7 60,3 70,3 81,2Crude Birth Rate (per 1,000) 2013 36,4 34,8 21,2 11,2Crude Death Rate (per 1,000) 2013 9,5 10,4 7,6 10,4Infant Mortality Rate (per 1,000) 2013 68,1 61,9 39,8 5,5Child Mortality Rate (per 1,000) 2013 107,3 97,4 56,3 6,6Total Fertility Rate (per w oman) 2013 4,8 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 350,0 415,3 240,0 16,0Women Using Contraception (%) 2013 21,6 34,9 62,6 71,3

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2011 5,9 47,1 117,8 297,8Nurses (per 100,000 people)* 2004-2011 77,1 132,6 202,7 842,7Births attended by Trained Health Personnel (%) 2006-2011 74,0 52,6 66,3 ...Access to Safe Water (% of Population) 2012 76,1 68,8 87,2 99,2Access to Health Serv ices (% of Population) 2000 42,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2012 14,3 39,4 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS2006-2012 1,1 3,9 1,2 ...Incidence of Tuberculosis (per 100,000) 2012 70,0 223,6 144,0 23,0Child Immunization Against Tuberculosis (%) 2012 94,0 83,0 81,5 96,1Child Immunization Against Measles (%) 2012 72,0 74,0 83,0 94,3Underw eight Children (% of children under 5 y ears) 2005-2012 20,2 19,7 17,0 1,4Daily Calorie Supply per Capita 2009 2 592 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2011-2012 2,4 2,9 3,0 7,5

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2012 122,8 101,9 109,4 100,9 Primary School - Female 2012 115,9 97,9 107,6 100,6 Secondary School - Total 2011-2012 47,7 47,4 69,1 100,2 Secondary School - Female 2011-2012 36,1 44,0 67,8 99,7Primary School Female Teaching Staff (% of Total) 2012 20,9 46,6 58,0 84,3Adult literacy Rate - Total (%) 2006-2012 28,7 62,0 80,3 99,2Adult literacy Rate - Male (%) 2006-2012 40,6 70,7 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 18,4 53,7 74,9 99,0Percentage of GDP Spent on Education 2010-2012 5,3 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 22,9 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 2,3 0,6 0,4 -0,2Forest (As % of Land Area) 2011 40,0 23,0 28,2 35,0Per Capita CO2 Emissions (metric tons) 2011 0,5 1,2 3,0 11,6

Sources: AfDB Statistics Department Databases; last update :

United Nations Population Division, World Population Prospects: The 2012 Revision;

World Bank: World Development Indicators; UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

For any given interval, the value refers to the most recent year available during the period

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Benin

mai 2014

0102030405060708090

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

Infant Mortality Rate( Per 1000 )

Benin Africa

0

200

400

600

800

1000

1200

1400

1600

1800

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

GNI Per Capita US $

Benin Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

Population Growth Rate (%)

Benin Africa

111213141516171

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

Life Expectancy at Birth (years)

Benin Africa

Page 29: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

II

Appendix II: Table of the AfDB’s portfolio in Benin

Project Name Status Age Appr.Date Into Force ComplDate Disbursed Approved Rate disbursed

WATER AND SANITATION

SUUPORT TO DECENTRALIZATION OF WATER &

SANITATION SERVICES OnGo 1,7 29/10/2012 22/03/2013 31/12/2016 227 748,92 929 096,23 24,51

FAECAL SLUDGE MANAGEMENT IN GRAND

COTONOU OnGo 1,5 04/01/2013 10/06/2013 31/03/2017 54 212,14 989 995,72 5,48

TRANSPORTATION

NDALI-NIKKI ROAD PROJECT OnGo 4,3 07/04/2010 22/10/2010 30/06/2014 4 867 930,12 11 500 000,00 42,33

NDALI-NIKKI ROAD PROJECT OnGo 4,3 07/04/2010 22/04/2010 30/06/2014 15 841 086,19 22 180 000,00 71,42

FARMING

RURAL INFRA PROJECT SUPPORT_VALLÉE L'OUÉMÉ OnGo 0,8 30/09/2013 25/11/2013 31/12/2017 0,00 444 000,00 0,00

RURAL INFRA PROJECT SUPPORT_VALLÉE L'OUÉMÉ OnGo 0,7 23/10/2013 09/05/2014 31/12/2017 0,00 39 500 000,00 0,00

RURAL INFRA PROJECT SUPPORT_VALLÉE L'OUÉMÉ OnGo 0,7 23/10/2013 09/01/2014 31/12/2017 0,00 530 000,00 0,00

RURAL INFRA PROJECT SUPPORT_VALLÉE L'OUÉMÉ APVD 0,7 23/10/2013 31/12/2017 0,00 4 679 457,00 0,00

URG PROG FOR MUNICIP MALANVILLE & KARIMAMA APVD 0,3 19/03/2014 31/12/2014 0,00 516 232,28 0,00

SUPP. PROJECT TO MILK, MEAT SECTORS OnGo 5,6 27/11/2008 20/01/2010 31/12/2015 5 479 470,65 25 000 000,00 21,92

MUNICIPAL FORESTS MANAGEMENT (PAGEFCOM) OnGo 9,0 06/07/2005 24/03/2006 31/12/2014 10 721 318,62 19 240 000,00 55,72

MUNICIPAL FORESTS MANAGEMENT (PAGEFCOM) OnGo 9,0 06/07/2005 24/03/2006 31/12/2014 15 750 444,15 15 760 000,00 99,94

GOVERNANCE

PROJECT IN SUPPORT OF PUBLIC FINANCE

MANAGEMENT OnGo 3,6 24/11/2010 14/10/2011 31/12/2015 1 122 937,35 5 000 000,00 22,46

SOCIAL

DEVELOPMENT OF THE HEALTH SYSTEM OnGo 9,2 22/04/2005 28/12/2005 31/12/2014 15 103 348,30 22 000 000,00 68,65

MULTINATIONAL

BENIN/TOGO: ROAD REHABILITATION PROJECT OnGo 2,8 05/10/2011 12/11/2012 31/12/2016 8 364 209,85 38 870 000,00 21,52

BENIN/TOGO: ROAD REHABILITATION PROJECT OnGo 2,8 05/10/2011 02/12/2011 31/12/2016 6 715 062,74 34 270 000,00 19,59

PROJECT IN SUPPORT OF COTTON INDUSTRY -

BENIN OnGo 7,6 29/11/2006 27/02/2008 31/12/2014 5 965 918,10 8 000 000,00 74,57

BENIN - TOGO - GHANA POWER INTERCONNECTION OnGo 7,3 04/04/2007 12/07/2010 31/12/2015 2 836 586,94 17 390 000,00 16,31

93 050 274,07 266 798 781,23

Page 30: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

III

Appendix III: table of costs per category and per source

CATEGORIES AfDF BENIN BOAD FEM

TOTAL

PROJECT Currency ML Total Currency ML Total Currency ML Total Currency ML Total

GOODS 0,11 0,03 0,14 0,00 0,00 0,00 0,19 0,05 0,25 0,00 0,00 0,00 0,38

WORKS 23,40 5,86 29,26 0,75 4,13 4,88 22,40 5,61 28,01 0,20 0,09 0,29 62,44

SERVICES 1,56 0,64 2,20 0,00 0,00 0,00 1,34 0,84 2,18 0,57 0,21 0,79 5,17

SUNDRY 0,00 0,00 0,00 0,00 1,91 1,91 0,00 0,00 0,00 0,00 0,00 0,00 1,91

Total baseline

costs 25,07 6,52 31,59 0,75 6,04 6,79 23,94 6,50 30,44 0,77 0,30 1,07 69,90

Material

contingencies 2,13 0,55 2,69 0,06 0,51 0,58 2,04 0,55 2,59 0,07 0,03 0,09 5,94

Financial

contingency 0,83 0,22 1,05 0,02 0,20 0,23 0,80 0,22 1,01 0,03 0,01 0,04 2,33

TOTAL 28,04 7,29 35,33 0,84 6,76 7,59 26,77 7,27 34,04 0,87 0,34 1,20 78,17

Page 31: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

IV

Appendix IV. Benin: Parakou Urban Transportation Project

Frontloading Justification Note for the Country-Team Meeting

1. Country performance

The country’s growth economy has undergone some reorganization during the past three

years. The actual rate of growth of the economy has indeed increased from 2.6 % in 2010 to

3.5 % in 2011; 5.4 % in 2012, and 5.0 % in 2013. Growth recovery is mainly linked to the

increase in agricultural production and the activity of the trade segment. Inflation fell below

the community threshold of 3% in 2013. Public finance has improved with a public deficit

from 1.8 % of GDP in 2011 to 1.3 % in 2012 and 1.2 % in 2013, in connection with the

progress of customs receipts. External trade is still marked by a deficit which was aggravated

in 2013 due to the imports of mining interests. Economic outlook is bright with an economic

growth expected to be more than 6.0 % on average between 2014 and 2016, in connection

with the reforms undertaken in the port sector and in the agricultural sector and the

implementation of a major structuring investments program between 2014 and 2018.

2. Absorptive Capacity

Beninese authorities have been making efforts to increase its absorptive capacity. The active

portfolio of the Bank in Benin has 12 projects and is characterized by the predominance of

infrastructure (transportation, power, water and sanitation) with about 47 %. The portfolio

has two transportation projects, namely the Ndali-Nikki-Chicandou road located at the

Nigeria border and the multinational Lomé-Cotonou road rehabilitation project and

facilitation of the corridor Abidjan-Lagos. The overall disbursement rate is 38.1 %, with an

average age of 4.3 years. The most satisfactory performances are identified in transportation

infrastructure and in agriculture, according to the review of portfolio conducted in May 2014.

The country has just secured on the occasion of a round table held in June 2014 an important

support from the international financial community for the funding of a major investment

program seeking to increase the rate of investment to nearly 27.0 % in 2018 against 19%

currently. The country thus intends to set up before the end of 2014 a follow-up and

mobilization of commitment project deriving from the round table and increase its absorptive

capacity. Besides, the priority given by the Senior Management of the transportation sector,

the implementation of the new government contracting Code and the operationalization of the

public procurement unit at the Ministry of Transport and Public Works contribute to increase

the absorptive capacity in the transport sector.

3. Commitment of the country to carry out the reforms

Benin authorities have yielded encouraging results since 2012 by initiating a number of

structural reforms in the public finance management and key economic sectors. These reforms

aimed, inter alia (i) the increased mobilization of tax revenues and the improvement of the

efficiency of public expenditure; (ii) the modernization of the customs department and the

port authority; (iii) the improvement of the legal and organizational framework of the private

sector, (iv) the modernization of public administration.

The Bank has supported these reforms through the program in support of the economic and

financial reforms (PAREF) delivered in a satisfactory manner over the 2012-2013 period. The

country also concluded in June 2014, the implementation of the program of structural reforms

supported by the IMF extended Fund Facility. Discussions are ongoing with the IMF for the

development of a new program which should come into play before the end of 2014. The

implementation of structural reforms is still made more relevant for the delivery of the major

program of structuring investments decided on for the period 2014-2018.

Page 32: AFRICAN DEVELOPMENT BANK GROUP BENIN PARAKOU URBAN ... · development project, the Bank will continue to play a leadership role for the development of the continent. Knowledge Management

V

Appendix V. Project Area Mapping

This map has been provided by the staff of the African Development Bank exclusively for the use of the readers of the report to which it is attached. The

names used and the borders shown on this map do not infer on the part of the AfDB Group and its members any judgment regarding the legal status of

a territory nor any approval or acceptance of its borders.