AFRICAN DEVELOPMENT BANK - afdb.org · 4. Arguably one of the most fragile from a political and...
Transcript of AFRICAN DEVELOPMENT BANK - afdb.org · 4. Arguably one of the most fragile from a political and...
SCCD: F.S.
AFRICAN DEVELOPMENT BANK AFRICAN DEVELOPMENT FUND
ADB/BD/WP/2014/151 ADF/BD/WP/2014/101
16 September 2014
Prepared by: ORWA/ONRI/ORNG Original: English
Probable Date of Presentation to the Committee
Operations/Development Effectiveness
(CODE)
30 September 2014
FOR CONSIDERATION
MEMORANDUM
TO : THE BOARDS OF DIRECTORS
FROM : Cecilia AKINTOMIDE
Secretary General
SUBJECT : COMBINED MID-TERM REVIEW AND REGIONAL PORTFOLIO
PERFORMANCE REVIEW OF THE REGIONAL INTEGRATION
STRATEGY PAPER FOR WEST AFRICA 2011 – 2015*
Please find attached the above-mentioned document.
Attach:
Cc.: The President
*Questions on this document should be referred to:
Mr. F. PERRAULT Director ORWA Extension 2054
Mr. O. DORE Director ORNG Extension 6650
Mr. J. K. LITSE Director ONRI Extension 2047
Mrs. B. BARUNGI Lead Economist ORNG Extension 6651
Mr. F. BAKOUP Lead Economist ORWA Extension 4449
Mr. E. SANTI Chief Regional Economist ORWA Extension 4202
Mr. K. DIALLO Chief CPO ORWA Extension 4201
Mrs. A. VALKO CELESTINO Young Professional ORWA Extension 3881
AFRICAN DEVELOPMENT BANK GROUP
COMBINED MID-TERM REVIEW AND REGIONAL PORTFOLIO
PERFORMANCE REVIEW OF THE REGIONAL INTEGRATION
STRATEGY PAPER FOR WEST AFRICA 2011 – 2015
ORWA/ONRI/ORNG/DEPARTMENTS
September 2014
TABLE OF CONTENTS
LIST OF ACRONYMS AND ABBREVIATIONS ..................................................................... i
EXECUTIVE SUMMARY ......................................................................................................... iii
I. INTRODUCTION AND OBJECTIVES OF THE MTR-RPPR ..................................... 1
1.1 Introduction and background
1.2 Objectives and scope of the MTR for the WA-RISP 2011-2015 .......................................... 1
II. UPDATE ON REGIONAL CONTEXT AND PROSPECT ............................................ 2
2.1 Overview ............................................................................................................................... 2
2.2 Political and Security Developments ..................................................................................... 2
2.3 Economic Developments ....................................................................................................... 3
2.4 Social and Environmental Developments ............................................................................. 5
2.5 Regional Infrastructure .......................................................................................................... 7
2.6 Regional Integration Strategy Framework Developments .................................................... 8
2.7 Aid Coordination and Harmonization Mechanisms .............................................................. 9
2.8 Challenges and Opportunities .............................................................................................. 10
III. RISP IMPLEMENTATION: RESULTS ACHIEVED AT MID-TERM..................... 11
3.1 RISP Objectives and Expected Results ............................................................................... 11
3.2 Status of RISP Outputs and Outcomes at Mid-term ............................................................ 12
3.3 Bank Group Regional Portfolio Performance Review 12
3.4 Regional Portfolio Improvement Plan ................................................................................. 14
IV. LESSONS LEARNED AT MID-TERM 15
4.1 General Lessons ................................................................................................................... 15
4.2 Lessons and Recommendations for the Bank ...................................................................... 15
4.3 Lessons and Recommendations for the RECs ..................................................................... 16
4.4 Lessons and Recommendations for the Governments ......................................................... 16
4.5 Lessons and Recommendations for the Development Partners .......................................... 16
V. BANK GROUP REGIONAL INTEGRATION STRATEGY ADJUSTMENTS FOR THE
REMAINING WA-RISP PERIOD 16
5.1 Objective and pillars ............................................................................................................ 16
5.2 Criteria for Defining the Strategy for the Remaining WA-RISP Period ............................. 17
5.3 Key Deliverables and Targets ............................................................................................. 17
5.3.1 The RISP Indicative Pipeline ..................................................................................... 17
5.3.2 Pillar I: Regional Infrastructure Development ........................................................... 17
5.3.3 Pillar II: Capacity Building for Effective Implementation of the Regional Integration
Agenda ....................................................................................................................... 17
5.3.4 Areas of Special Emphasis ......................................................................................... 18
5.3.5 Economic and Sector Work ....................................................................................... 19 5.4 Institutional Arrangements and Resources ................................................................................. 19 5.5 Potential Risks and Mitigation Measures ............................................................................ 19
VI. CONCLUSION AND RECOMMENDATION ............................................................... 20
iii
FIGURES & TABLES Figure 1: Evolution of Commodity Prices
Figure 2: Breakdown of Regional Portfolio by Sectors
Table 1: Ibrahim Index of African Governance and Global Peace index for 2013
Table 2: Doing Business Report global ranking, 2013-2014
Table 3: Logistics Performance Index scores, on a scale from 1-5, for the years 2010-2012-2014
BOXES Box 1: Nigeria’s Role in Regional Integration
Box 2: Integration through private sector, the case of ECOBANK
Box 3: Some Observations on Regional Portfolio Implementation
Box 4: Causes of Limited Portfolio Performance
ANNEXES
ANNEXES Annex 1. ECOWAS Monetary Cooperation Programme Convergence Criteria
Annex 2: Indicative Program of Regional Operations and Economic and Sector Work as per the WA RISP 2011-
2015 and its effective implementation
Annex 3: New Indicative Regional Operations and ESW In Addition to Those Identified in the WA RISP 2011-2015
Annex 4a: Status of RISP Outputs at Mid-term
Annex 4b: Status of RISP Outcomes at Mid-term
Annex 5: List of Multinational Operations in West Africa
Annex 6: Overview of Regional Operations Directly Managed by the RECs
Annex 7: WA Regional Portfolio Improvement Plan
Annex 8: Consultative Process and Timeframe for the Preparation of the WA-RISP MTR
Annex 9: Conclusions of the Regional Dialogue Mission in Abuja, March 2014
Annex 10: Original Indicative Results Matrix of the WA-RISP 2011-2015
Annex 11: Revised Indicative Results Matrix of the WA-RISP 2011-2015 at MTR
Annex 12: Alignment between CSP and WA-RISP Pillars
The Mid-term Review for the West Africa RISP 2011-2015 was prepared under the guidance of Franck PERRAULT,
Director of ORWA, Ousmane DORE, Director of ORNG and Janvier LITSE, Director of ONRI. This review benefitted
from the outcome of consultations with regional stakeholders in West Africa, including the ECOWAS Commission and
the WAEMU Commission. The consultations were carried out during the MTR; a regional workshop was conducted in
Abuja (Nigeria) on March 17-18, 2014.
The task team included: Emanuele SANTI, Chief Regional Economist, ORWA; Barbara BARUNGI, Lead Economist,
ORNG (task managers); Ferdinand BAKOUP, Lead Economist, ORWA; Korka DIALLO, Chief Country Program
Officer, ORWA; Samba KAMARA, Country Program Officer, ORWA; Anne VALKO CELESTINO, Young
Professional, ORWA; Mohamed EL DAHSHAN, Consultant, ORWA; Christian Kitenge M. KINGOMBE, Chief
Trade and Regional Integration Officer, ONRI.1, Inye BRIGGS, Principal Trade Regulatory Officer, ONRI.2; Gabriel
MOUGANI, Chief Regional Integration Economist, ONRI.2; Ibrahim Ahmed AMADOU, Chief Agricultural
Economist, OSAN; Fessou LAWSON, Principal Statistician, ESTA.1; May BABIKER, Principal Socio-economist,
ORSF.1; Bitsat YOHANNES KASSAHUN, Infrastructure Environment Policy Expert, ORSF.2; ORWA and ORNG
Country Economists and CPOs.
The report benefited from inputs received from: Clotilde BAI, Architect, ONRI.1; Jean-Noël ILBOUDO, Infrastructure
Engineer, OITC; Pamphile CODO, Principal Infrastructure Specialist, ONRI.1; Usman MOHAMMED, Principal
Disbursement Officer, ORNG; Saloua SEHILI, Principal Policy Economist, COSP; Baba ABDULAI, Principal
Procurement Officer, ORNG; Danladi EBBAH, Agricultural Engineer, ORNG; Line PICARD, Chief Portfolio Officer,
OPSM 5; Tapio NAULA, Transport Economist, OICT1; Jeremy AGUMA, Transport Economist, OITC.1; Modibo
SANGARE, Coordinator Mano River Initiative, ORCE, Tom MUGOYA, Principal Water & Sanitation Engineer,
OWAS.1; Anouar CHAOUCH, Statistics Assistant, ESTA1, as well as from members of the Country Teams.
The report benefited from final comments received from Lawrence TAWAH, Assistant To Vice-President, SAOR;
Assitan DIARRA-THIOUNE, Regional Economist, ORNA; Tilahun TEMESGEN, Chief Regional Economist, EARC;
Emelly MUTAMBATSERE, Principal Research Economist, SARC.
Peer Reviewers of the MTR and RPPR: Mohamed CHERIF, Chief Country Program Officer, SARC; Yasser AHMAD,
Country Program Officer, ORNA; Mamadou TANGARA, Senior Country Program Officer, TDFO; Donatien Akoupo
KOUASSI, Principal Country Programme Officer, EARC.
Peer Reviewers of the Pre-mission Concept Note: Kennedy K MBEKEANI, Regional Economist, SARC; Tilahun
TEMESGEN, Chief Regional Economist, EARC; Yasser AHMAD, Country Programm Officer, ORNA.
i
LIST OF ACRONYMS AND ABBREVIATIONS
ACE African Coast to Europe
AfDB African Development Bank
ADF African Development Fund
AFD French Agency for Development (Agence Française de Développement)
AFRISTAT Economic and Statistical Observatory for Sub-Saharan Africa
AGIR Alliance Globale pour l’Initiative Résilience
AfTRA Africa Trade Fund
BCEAO Central Bank of West African States (Banque Centrale des Etats d’Afrique de l’Ouest)
BOAD West African Development Bank (Banque Ouest Africaine de Développement)
CEMAC Economic and Monetary Community of Central Africa
CET Common External Tariff
CILSS Comité Permanent Inter-Etats de Lutte contre la Sècheresse dans le Sahel
CLSG Côte d’Ivoire, Liberia, Sierra-Leone, Guinea
CMO Corridor Management Organizations
COMESA Common Market for Eastern and Southern Africa
CSP Country Strategy Paper
DP Development Partner
EBID ECOWAS Bank for Investment and Development
ECOWAS Economic Community Of West African States
EIB European Investment Bank
ENSEA Ecole Nationale Supérieure de Statistique et d’Economie Appliquée, Côte d’Ivoire
EPA Economic Partnership Agreement
EPSA Enhanced Private Sector Assistance
ESEA Ecole Supérieure d’Economie Appliquée, Sénégal (formerly Ecole Nationale d’Economie
Appliquée)
ESW Economic and Sector Work
EU European Union
FDI Foreign Direct Investment
FSF Fragile States Facility
GDP Gross Domestic Product
GPI Global Peace Index
ICP-Africa International Comparison Program for Africa
ICT Information and Communications Technology
IIAG Ibrahim Index of African Governance
IsDB Islamic Development Bank
IWRM Integrated Water Resource Management
KFW German Development Bank (KfW Bankengruppe)
MDGs Millennium Development Goals
MRU Mano River Union
MTR Mid Term Review
ii
NEPAD-IPPF New Partnership for Africa’s Development – Infrastructure Project Preparation Facility
NTF Nigeria Trust Fund
ODA Official Development Aid
OECD Organization for Economic Co-operation and Development
OFID OPEC Fund for International Development
OMVG Gambia River Development Organization
OMVS Organisation pour la Mise en Valeur du Fleuve Sénégal
OPEV AfDB’s Operations Evaluation Department
ORWA AfDB’s Regional Department for West Africa
PIDA Program for Infrastructure Development in Africa
PP Problematic Project
P2RS Programme de renforcement de la résilience à l’insécurité alimentaire et nutritionnelle
récurrente au Sahel
RBF Results-Based Framework
RBO River Basin Organizations
REC Regional Economic Community
RIS Regional Integration Strategy
RISP Regional Integration Strategy Paper
RMCs Regional Member Countries
ROs Regional Operations
RPPR Regional Portfolio Performance Review
SCB Statistical Capacity Building Program
SME Small and Medium Enterprises
SPC Special Purpose Company
STC Statistical Training Centers
TYS AfDB’s Ten Year Strategy
UA Unit of Account
UNFPA United Nations Population Fund
WA-RISP West Africa – Regional Integration Strategy Paper
WACS West Africa Cable System
WAEMU West African Economic and Monetary Union
WAMI-IMAO West African Monetary Institute
WAMZ West African Monetary Zone
WAPP West African Power Pool
WB World Bank
WTO World Trade Organization
iii
EXECUTIVE SUMMARY
1. In November 2011, the Board approved the Bank’s Regional Integration Strategy Paper for
West Africa 2011-2015 (WA-RISP), covering a grouping of 15 member countries of Economic
Community of West African States (ECOWAS). Such group has a diverse mix of political,
economic, social and geographic characteristics, ranging from the dominance of Nigeria the regional
heavyweight, to the small size of other national markets, including landlocked countries and an
island state. The WA-RISP is articulated around two pillars, (i) linking regional markets and, (ii)
building capacity for effective implementation of the regional integration agenda.
2. The main objectives of the MTR-RPPR of the Bank’s WA-RISP are (i) to assess the
relevance and effectiveness of the WA-RISP and (ii) propose possible adjustments to current
Bank approaches for enhancing regional integration.
3. Since 2011, West Africa’s growth has accelerated and is estimated to reach 7.4% in 2014,
making it the fastest growing region of the continent. However, the region is still home to some
of the poorest in the continent. Poverty and inequality are high across the region with poverty
levels in some countries averaging more than 60% of the population. Furthermore, gender-related
MDGs and indicators have shown moderate improvements.
4. Arguably one of the most fragile from a political and security stand point, the region is more
exposed to fragile situations since the inception of the strategy, further to the crisis in the Sahel and
the emergences of new terrorist threats.
5. The Regional Integration Strategy Framework remains largely shaped by ECOWAS and its
Vision 2020. Progress in implementing Vision 2020 has been mixed, so is the status of regional
integration, with intra-regional trade still low compared to other groupings.
6. As of December 1st, 2013, the Bank's active regional operations portfolio in West Africa
included 43 operations, for a global amount of UA 667 million and an average disbursement
rate of 31%. The overall implementation status of the WA-RISP is satisfactory: out of the 13
projects provisioned under the two pillars, four were approved between 2011 and 2013, four are in
process or under review, and one is postponed until 2016, while four are on stand-by due to limited
resources. All planned ESWs have been completed, yet some have been refocused in view of the
changing political landscape.
7. Analysis at mid-term supports that the two strategic pillars identified in the WA-RISP
(2011-2015) remain relevant for the remaining period. While the choice of pillars is also
consistent with the Ten Year Strategy, this MTR elaborates on adjustments to strengthen the Bank’s
contribution to the regional integration. These include focusing the first pillar around infrastructure
development and renewed attention at addressing fragility, gender and food security, including
through a new program on resilience in the Sahel.
8. The MTR suggests strengthening Bank support to Sahel and Mano River Union (MRU)
countries, and giving greater focus to the “soft” side of the Bank interventions, by (i) integrating
trade, transit and trade facilitation in all new transport operations; (ii) strengthening technical
assistance on trade facilitation; and (iii) boosting regional knowledge work.
9. The MTR also recognizes the important role of private sector, including through Private
Equity funds, and advocates for a deeper engagement with business organizations at regional level.
10. The MTR suggests a number of measures to improve performance of regional portfolio,
such as strengthening of the role of the Bank’s field offices in managing regional projects;
technical assistance on Bank’s procedures; setting-up and building capacity of dedicated units to
oversee Bank operations in selected RECs.
1
I. INTRODUCTION AND OBJECTIVES OF THE MTR-RPPR
1.1 Introduction and background
1.1.1 The West Africa region as a whole remains among the least integrated regions in the
world from a trade perspective. Despite good progress in the WAEMU region, where intra-
regional trade is 13.5%, the share of ECOWAS intra-regional trade has remained low, with around
7.5% of total trade. This is lower than many other Sub-Saharan Regional Economic Communities
(RECs), and it is generally lower compared to major RECs outside of Sub-Saharan Africa1.
1.1.2 In November 2011, the Board approved the Bank’s Regional Integration Strategy Paper
for West Africa 2011-2015 (WA-RISP), covering all 15 member countries of ECOWAS with a
diverse mix of political, economic, social and geographic characteristics2. All ECOWAS countries
are eligible for ADF resources only, with the exceptions of Nigeria and Cabo Verde, eligible for
ADB resources only, with access to ADF allocations3.
1.1.3 The overarching goal of the Regional Integration Strategy Paper 2011-2015 (RISP) is to
help advance the integration agenda and facilitate regional solutions. It specifically provides the
strategic framework for selecting and prioritizing Bank’s analytical, operational, and partnership
activities in support of regional integration in West Africa over that period.
1.1.4 The WA-RISP proposed Bank support that focuses on two pillars, namely (i) linking
regional markets and, (ii) building capacity for effective implementation of the regional
integration agenda. This strategy was aligned with ECOWAS’ Vision 2020 Regional Strategic
Plan, and the outcome of consultations with regional stakeholders.
1.2 Objectives and scope of the MTR for the WA-RISP 2011-2015
1.2.1 The main objectives of the MTR of the Bank’s WA-RISP are to assess the relevance,
performance and effectiveness of the WA-RISP in support to West Africa integration and
propose possible adjustments to current Bank approaches for enhancing regional integration.
More specifically the MTR reviews (i) recent political, economic, social and environmental
developments in the region, as well as new challenges and opportunities that may have affected the
RISP; (ii) the role of private sector engagement in areas supported by the RISP; (iii) developments in
donors’ support for regional integration in West Africa; (iv) the alignment of the RISP with the
Bank’s Ten Year strategy (TYS); and (v) recent progress in terms of regional integration.
1.2.2 In addition, the MTR assesses the experience in Regional and Country Dialogue activities
pertaining to the achievement of the RISP, while identifying key lessons.
1.2.3 Finally, it proposes revisions to the Bank strategy for regional integration in West Africa for the remaining period, confirming the two pillars, updating on deliverables and targets. The MTR
entailed (i) desk review of the implementation of the Bank’s regional operations, (ii) interviews with
task managers, sector teams, country directors and resident representatives (iii) a consultation
mission with officials from ECOWAS, other key RECs and stakeholders, including development
partners (see Annex 9).
1 According to the UNCTAD Handbook of Statistics 2013, the intra-trade of the main regional groups in Africa and the
world is as follows: EU27, 61.8%; NAFTA, 48.5%; EAC, 20.9%; MERCOSUR, 14.9%; WAEMU, 13.5%; SADC,
11.7%; ECOWAS, 7.5%; COMESA, 6.9%; UMA, 3.3%; ECCAS, 0.8%. 2 The countries of the ECOWAS region are Benin, Burkina Faso, Cabo Verde, Côte d’Ivoire, Gambia, Ghana, Guinea,
Guinea Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone, and Togo. Eight of the countries are Francophone,
five are Anglophone and two are Lusophone. The total population of the region in 2010 was 302.69 million. The region
is home to 29.3 percent of the continent’s population. 3 The Bank recently revised its Credit Policy, which will enable various ADF countries to benefit from ADB resources as
well.
2
II. UPDATE ON REGIONAL CONTEXT AND PROSPECTS
2.1. Overview
2.1.1 The West Africa region is a politically and culturally complex and heterogonous region,
ranging from the dominance of Nigeria, which accounts for an half of the region’s population and
has the largest economy in the region, accounting for around 80% of its GDP4; the small size of other
national markets, the limited market access of the three landlocked countries (Burkina Faso, Mali
and Niger); and a number of emerging and more diversified economies, namely Ghana, Senegal and
Côte d’Ivoire, as well as the Island States like Cabo Verde.
2.1.2 West Africa is also one of the most fragile regions in the continent from a political and
security stand point. With nearly half of its countries classified as fragile states, and some of the
countries also facing severe drought and food and public security challenges.
2.1.3 Almost all of the West African countries continue to suffer from a number of
vulnerabilities due to external shocks, environmental pressures due to drought, fluctuations in
commodity prices, high levels of unemployed youth population, which combined with porous
borders, often create a fertile ground for highly organized illegal activities and instability.
2.2. Political and Security Developments
2.2.1 Since the inception of the RISP, the region has been destabilized by coups d’état in Mali
and Guinea Bissau, and it has become the battlefield of a new wave of attacks by radical
groups. Reports on drug trafficking are of increasing concern. The region’s often porous borders and
coastlines, and wide desert spaces make it one of the hardest to control. Many of the regions’
problems are beyond the capacity of individual states to solve—especially states with limited
capacity and cohesion, making the case for regional cooperation even more compelling.
2.2.2 In the Sahel region5, countries face various destabilizing factors whose combination
continues to undermine livelihoods and promote an environment of insecurity. Lack of strong
local government structures in marginalized areas continues to make them a safe haven for radical
elements. These in turn promote their agendas by harnessing the discontent of young people with
little economic opportunities and the sentiments for autonomy based on a sense of exclusion.
2.2.3 In the MRU countries6, the effects of decades of conflict are evident in all aspects of life,
even though the region is enjoying relatively continued peace. Within this backdrop, the priorities
of the Heads of States in terms of regional peace and security continue to be: (i) organizing and
conducting joint patrols of the borders; (ii) developing, facilitating, fostering and promoting cordial
relations between the people of the border regions through cultural, social and sporting activities; (iii)
exchanging information and investigating reports or observations of all border security activities; and
(iv) monitoring the movement of goods at the border posts to minimize/avert the trafficking of illegal
arms and drugs and also smuggling of minerals.
2.2.4 Nevertheless, there are recent positive signs of stabilization, further to the end of Touareg
rebellion in 2013 and the return to an elected leadership in Mali, as well as the political transition in
Côte d’Ivoire, Guinea and Guinea Bissau. Peaceful elections in Ghana, Guinea Bissau, Mali and
Senegal bode well for political stability in the wider region.
2.2.5 The economies of the region would nevertheless still remain vulnerable to possible
drawbacks of the political process. The years 2014 and 2015 will be rife with electoral exercises in
4 Further to the last rebasing of its GDP, a collaborative effort of several organizations, including the African
Development Bank, Nigeria’s GDP was calculated to be $510 billion, a whopping 94 percent jump from the former
figure of $262 billion. 5 The Sahel stretches from Mauritania to Eritrea, including Chad and Sudan, with three of the five Sahelian countries in
greatest need are in West Africa: Mali, Burkina Faso and Niger (UN definition). 6 The Mano River Union countries are: Côte d’Ivoire, Liberia, Sierra Leone and Guinea.
3
many of the region’s countries7, with a risk of possible tensions in some of these countries and shift
in political agendas. Other local elections will be held in some countries over the same period.
2.2.6 Most countries are ranked in the bottom half of the latest Global Peace Index (GPI), which measures ongoing domestic and international conflict, societal safety and security, and
militarization (Table 1). However most countries hover around the middle quintile of the ranking
often reflecting the state of low-intensity conflict and safety concerns, rather than widespread
instability.
2.2.7 Despite notable improvements, governance issues remain a concern and possible cause of
political fragility. The region as a whole appears above the African average of Ibrahim Index of
African Governance (IIAG) but the region's countries represent both extremes. Cabo Verde ranks
third continent-wide, and leads the region in Governance. Ghana and Senegal also appear in the top
10 of the ranking. On the other hand, nine countries are below the average, with three countries in
the bottom 10 (Table 1).
Table 1: Ibrahim Index of African Governance and Global Peace index for 2013 (source: Mo
Ibrahim Foundation, Institute for Economics and Peace)
Ca
bo
Ver
de
Gh
an
a
Sen
ega
l
Ben
in
Ga
mb
ia
Bu
rkin
a F
aso
Ma
li
Nig
er
Lib
eria
Sie
rra
Leo
ne
To
go
Nig
eria
Gu
inea
Cô
te d
’Iv
oir
e
Gu
inea
Bis
sau
Wes
t A
fric
a
Afr
ica
GPI N/A 1.9 2.0 2.15 2.1 2.0 2.34 2.4 2.04 1.9 1.9 2.7 2.7 2.7 2.4 N/A N/A
IIAG 76.7 66.8 61 58.7 53.6 53 50.7 50.4 50.3 48 45.8 43.4 43.2 40.9 37.1 52.5 51.6
2.3 Economic Developments
2.3.1 Growth in West Africa has picked up over the past few years, with an expected growth to
near 6.7% in 2013 and estimated to reach 7.4% in 2014. Much of this growth was led by strong
performance in the oil and mining sectors, which made the bulk of the USD 15.1 billion8 FDI inflows
registered in 2012, arguably the largest volume of FDI of any other regions in the continent.9 The oil
and mining sectors remain predominant in Nigeria, and are the main drivers of the unprecedented
high growth in Ghana, Liberia and Sierra Leone in recent years, yet agriculture and services remain
key for the region. Agriculture also counts as an important driver of West African growth and the
service sector has become a main engine of growth in many countries. Services, such as transport,
trade, real estate and public administration, continued to play an important role in 2012; but with new
technologies and financial deepening, diversification in the region is on the rise.10
7 In 2014 Presidential elections are expected in Guinea Bissau and in 2016 in Niger, whereas the Parliament will be
renewed in Guinea Bissau, Liberia and Niger. In 2015 Presidential elections will take place in Burkina Faso, Côte
d’Ivoire, Guinea, Nigeria and Togo, whereas parliamentary elections will take place in Benin and Nigeria. 8 UNCTAD regional trends in FDI http://unctad.org/en/PublicationChapters/wir2013ch2_en.pdf
9 Nigeria, Guinea, Ghana and Niger’s resource sector attracted an estimated 88% of total FDI to the region. Nigeria’s
largest announced greenfield project in 2012 amounted to nearly USD 2 billion to increase oil production. The other large
greenfield projects for Nigeria were in manufacturing and information and communications, signaling some
diversification. Ghana has announced it expects at least $20 billion in investment in the oil industry over the next five
years, primarily from foreign companies9.
10 African Economic Outlook 2013. For instance, the recent rebasing of Nigeria’s GDP pointed to a sharp increase of the
share of services in GDP from 23.6% to almost 52% in 2013, and a rise of manufacturing from 1.9% to 6.8%.
4
Box 1: Nigeria’s Role in Regional Integration
With an estimated population of 167 million, Nigeria is the
region’s largest market and has great potential to be a main
driver of regional integration. With the GDP rebasing, Nigeria
now has the largest economy in Africa and a great potential for
its services and manufacturing sectors. It also attracts half the
FDI coming into the region (45% in 2012). Nevertheless its
intraregional trade has been steadily decreasing, now
constituting less than 1% of the country’s total imports and 3%
of its export. Informal trade networks however are significantly
larger, most notably for agricultural goods, petroleum products,
and re-export trade. On the investment side, the role of Nigeria is
certainly more prominent, with various Nigerian companies
having significant impact in the regional market particularly
banking services, as well as goods (cement, cassava flour, etc.)
to client across West Africa. Closer integration with the region
would require Nigeria to open its markets to regional exports,
but more crucially a change of perspective on the neighboring
countries as partners rather than merely clients. Regional value
chains have a real potential, particularly given the developments
in regional transport and connectivity infrastructure. Increasing
trade volumes will require improvements in regional corridors
reducing frictions related to nontariff barriers, as well as
accountability and transparency in regulations, both on the
national and on the regional level.
2.3.2 Investment within the
West African region has
expanded dramatically in the
past decade. This has been driven
by a strong increase in intra-
regional FDI, primarily from
Nigeria, Ghana, and Côte d’Ivoire
yet they remain rather limited.
2.3.3 But despite the flows of
FDI, West Africa remains a
challenging region to do
business. According to the 2014
World Bank’s Doing Business
Indicator, which ranks countries
and regions according to the ease
of managing business, only one
West African country, namely
Ghana, appears in the top 100
countries. Nine out of 15
countries appear in the bottom
20% of the ranking over 189
countries – as does the regional
average, which would
comparatively place the
ECOWAS region in the 152nd place (see table 2). The lack of competitive environment for business
at country level acts as a major constraint for growth, but also for regional integration.
Table 2: Doing Business Report global ranking, 2013-2014. (Source: The World Bank)
Ghan
a
Cab
o
Ver
de
Sie
rra
Leo
ne
Lib
eria
Nig
eria
Gam
bia
Burk
ina
Fas
o
Mal
i
Togo
Côte
d'I
voir
e
Ben
in
Guin
ea
Guin
ea
Bis
sau
Nig
er
Sen
egal
2014 67 121 142 144 147 150 154 155 157 167 174 175 180 176 178
2013 62 128 137 149 138 148 154 153 159 173 175 179 181 174 176
2.3.5 Naturally, areas of weakness and strength vary. For instance it is easy to start a business in
Liberia, but remarkably difficult to register and transfer property; Nigeria offers the easiest access to
credit in the region but put complex and lengthy procedural hurdles on import and suffers from high
contract enforcement costs. There are also sub-regional hurdles to the investment climate. Investors
point at the difficulty of transitioning from Anglophone countries to the Francophone, and vice-
versa, not only due to comprehension issues but mostly regulatory difficulties as the spirit of the laws
differs significantly between Anglo-Saxon and French-based laws.
2.3.5 Inflows of remittances and illicit capital outflows are also becoming more prominent in
the region with Nigeria taking the center stage. Nigeria remains by far and naturally the largest
recipient of remittances, not only within the ECOWAS region but also in the entire sub-Saharan
Africa11
. Intra-regional remittances are also very important, although often difficult to track. In 2010,
according to Global Financial Integrity the total illicit financial flows in the West Africa region,
11
In 2013, Nigeria received remittances worth about $21 billion out of the total US$32 billion and US$25.8 billion sent
to the SSA and ECOWAS countries, respectively, equivalent of 66% and 81%. This is followed at a very far distance by
Senegal that received about US$1.7 billion or 6.4% of remittances to ECOWAS during the same period.
5
40
50
60
70
80
90
100
110
120
130
140
Figure 1: Evolution of commodity prices January 2011 = 100
Cocoa Beans Cotton
Gold Crude Oil
stood at US$22.6 Billion with Nigeria responsible for US$19.7 billion or 87%. Reducing costs of
remittances and fighting corruption would free up huge resources for development.
2.3.6 West Africa’s countries have endured strong fluctuations in commodity prices over the
past few years, as depicted in Figure 1. The region’s key commodity prices have maintained a
generalized decline in the past two years, with the exception of oil. The sharp decline of price of
Cotton, Gold and Cocoa have hit many countries in the region12
; The relatively good performance of
Oil has benefited Nigeria, while adding
pressure on balance of payments for most
other countries, which remain net importers.
2.3.7 Price stability remained the focus of
the monetary policy thrust in all
ECOWAS countries, yet with mixed
results. While WAEMU countries have
managed to control inflation with fixed
exchange rate pegged to the euro, high
inflation and currency depreciation have been
experienced in WAMZ namely in Nigeria
and Ghana, where currencies have
depreciated and suffered from the impacts of
the US tapering of Quantitative Easing
unfold, and - in the case of Ghana – a sharp
macro-economic deterioration.
2.3.8 West Africa’s economic prospects in
the remaining period depend on global
and domestic factors, which remain somewhat uncertain. The
strengthening of global activity at the end of 2013 and the anticipation of further growth in 2014-
2015, led by a recovery in OECD countries, lend to a more optimistic outlook for West Africa. In a
wake of a lower than expected recovery and a slowdown of emerging economies, downside risks
may materialize, through lower commodity prices (namely cocoa and gold), shrinkages in export
volumes of other goods, lower tourism receipts, official development assistance (ODA), FDI and
worker’s remittances. Possible earlier mentioned political reversal in the region may also have a
major impact, particularly on FDI.
2.4 Social and Environmental Developments
2.4.1 The fastest growing economies in West Africa are still home to some of the poorest in the
continent. Poverty and inequality are high across the region with poverty levels in some countries
averaging more than 60% of the population13
.
2.4.2 Though recognized for positive strides and efforts towards the Millennium Development
Goals (MDGs), West Africa remains largely distant from meeting such goals.14
The high growth
12
Gold, which tops Mali’s exports as well as represents 28% of Ghana’s total exports value (2011), has lost 27% of its
value in the course of 2013. Cotton prices have experienced the largest and progressive decline (59% in the past 3 years)
affecting most countries in the region. Côte d’Ivoire and Ghana, the world’s premier cocoa producers generating 51% of
the world’s output, have endured declining prices for almost two years; while prices have risen over the past year, they
remain below their pre-2011 levels. 13
As of 2012, the countries with the highest number of people living with less than $1.25 a day (PPP) amounted to
83.76% in Liberia, 67.62% in Nigeria, 50.43% in Mali, 48.9% in Guinea Bissau, 47.33% in Benin. Inequality also
exacerbates poverty; this is even more so a problem in such countries as Cabo Verde, Nigeria, the Gambia, Ghana, and
Côte d’Ivoire which lead the region in inequality, displaying the highest Gini coefficients. (Source: World Bank). 14
MDG Report 2013, Assessing Progress in Africa toward the Millennium Development Goals
Data source: IndexMundi, AfDB
6
rate experienced in the region has faced difficulties in translating into major improvements in
inclusiveness and human development15
.
2.4.3 Since the inception of the strategy, gender-related MDGs and gender gap indicators have
broadly shown moderate improvements in the region, particularly in economic and political
participation.16
Economically, women make up the majority of small-scale farmers and yet are
penalized in terms of land rights. In many countries, women cannot become owners of the land they
plough and do not often have the right to inherit it when their husbands die17
.
2.4.4 Women representation in the political landscape varies within the region. Some countries
have made progress towards better participation of women, such as Senegal, with 43% of women in
parliament after the 2012 legislative elections. However, most parliaments have between 10% and
16% of women members, even in the countries where quotas are provisioned.18
In addition, women
are increasingly taking the posts of ministers of health, education, and family or women affairs.
Niger and Senegal are here an exception, where the former had a woman heading the ministry of
foreign affairs and the latter a woman as prime minister.
2.4.5 Women in the troubled Sahel region are often the first to experience the devastation of
food and financial crises, armed conflict, and natural disaster. They are often victims of
discrimination, exceptional physical and human insecurity, chronic poverty and marginalization.
Immediately following the start of hostilities in northern Mali in April 201219
, women and girls were
subject to rape and sexual violence. During repeated droughts in Niger and elsewhere, women and
children are the majority of those displaced and suffer from a lack of access to water and food.
2.4.6 West Africa is also facing a youth bulge with about 40% of the population being under 15,
and nearly 70% under 30. The region has, however, not been able to tap into the opportunities this
bulge provides. Several youth are still idle, unemployed or under-employed. The problem is
compounded in such countries as Côte d’Ivoire, Sierra Leone or Liberia, where many unemployed
youth are also ex-combatants20
, thereby constituting a potential risk to the stability of the region. The
high incidence of poverty, unemployment and inequality in a region with such impressive growth
records is an indication that growth has not been sufficiently inclusive.
2.4.7 The health challenges can become additional threats to the development and national
security situations in the West Africa region. Although ECOWAS has made some progress in
promoting cooperation among its member countries in the health sector, the health problems in the
region remain significant. The regional health integration programs21
are yet to translate into
improved coordination, harmonized policies and regulations, regionally financed regional public
health goods, and ultimately improved healthcare systems. These health issues often transcend
15
Nevertheless, some of the region’s countries are among Africa’s best performers compared to their original condition.
Burkina Faso is distinguished by being among the most successful in the continent, leading the way in 16 out of 22
indicators. Ghana is also among the top performers continent-wide. 16
Four West African countries rank in the bottom ten on the Gender Equality Index. The literacy rate (MDG 2) is lower
than in other regions, with seven West African countries ranking in the bottom ten; maternal health (MDG 5) also shows
low results for the region (1/10 death during pregnancy in West Africa, compared to an average of 1/16 for Sub-Saharan
Africa). In turn, the picture is more positive with regards to women as economic agents (MDG 3), with more than 60% of
women in the labor force yet mainly in vulnerable economic sectors. . 17
Fatima Kyari Mohammed, "Women’s Economic Empowerment in the Sahel Region and the impact on Food Security",
background paper, April 2013. http://trvw.in/1iK9BoI 18
Quotas of seats for women: 30% each in Côte d’Ivoire, Burkina Faso, and Guinea; 30% in Mali (within political
parties); equal representation in Togo and Cabo-Verde, and Senegal. http://www.quotaproject.org/fr/ 19
In April 2012, rebels seeking more autonomy for the northern part of Mali took control of the region. The President
was deposed in a coup over his handling of the crisis; In parallel, infighting within rebels who had overtaken the north
left hardline Islamists in control of the region. In January-February 2013, foreign intervention allowed the government to
regain control of the North. A peace agreement was signed on 18 June 2013, but occasional hostilities still occur. 20
Youth Unemployment and Stability http://blog.fundforpeace.org/blog-20131108-youthunemployment 21
ECOWAS created the West African Health Organization in 1987 with the objective to promote and protect the “health
of the peoples in the sub-region through the harmonization of the policies of the Member States, pooling of resources and
encourage a collective and strategic combat against the health problems of the sub-region”.
7
borders, as demonstrated by the recent outbreak of Ebola, and can turn into additional factors of
vulnerability for the politically unstable and economically disadvantaged West African countries.
2.4.8 The recent drought in the Sahel has also shown the vulnerability of the region to climate
change; Communities remain highly exposed to watershed erosion, loss of woodlands of soil
productivity, reduced crop yields, and the spread of diseases such as malaria. Furthermore, the effect
of climate change on increasing the diversification of agricultural conditions across the region,
coupled with the weakness of crop storage facilities could also affect food security22
. While the
percentage of the population that is undernourished is on decline in West Africa, wide differences
remain between countries23
.
2.4.9 A strategic approach to prevent, mitigate risks and ensure adaptation to evolving climate
conditions is required. Including the gender aspect among drivers of conflict, fragility, or resilience
can lead to a better assessment and better development of avenues for resilience.
2.5 Regional Infrastructure
2.5.1 Over the past decades, the West African transport network has widely expanded,
particularly along the primary road networks. Higher traffic matches areas of high population and
economic activity (such as western Senegal, parts of Nigeria and the Gulf of Guinea)24
. Nevertheless,
the length of paved roads does not necessarily speak for their quality and maintenance. The flagship
project in West African transport is the Trans-West African Highway, which will link 11 ECOWAS
countries, from Nigeria to Senegal, with additional feeder roads connecting Mali and Burkina Faso.
The network also extends further west past Senegal to reach Nouakchott in Mauritania. Of a total of
4010 km, 3,260 km are paved. Yet large swathes of the road, most notably those in Guinea, Liberia
and Sierra Leone, remain to be paved. While air transport coverage has increased, thanks to the
emergence of regional champions like Asky Airlines, air traffic integration is still limited , partly due
to the slow implementation of the Yamoussoukro decision, which liberalized air transport25
. Over
25% of travel routes are still serviced by a single airline and up to 70% of air transport served by a
monopoly carrier26
. Railways integration has been slow to come by, as West Africa’s railways are
largely perpendicular to the coast, and disconnected from one another27
. Plans are underway to
establish a sub-regional railway network, namely through the Cotonou-Niamey-Ouagadougou-
Abidjan Railway. A major obstacle for railway integration in West Africa is the existence of
different gauges between countries, which simply makes it impossible to carry goods and passengers
across borders. In fact, two countries in the region, namely Guinea and Liberia, have two different
gauges each28
.
2.5.2 Crises and infighting in some countries in the region have destroyed parts of their energy
infrastructure; in others, the lack of investment has led to its deterioration and obsolescence. As a
result, electricity production remains very expensive for many countries and access to electricity is
among the lowest in the world29
. While at present West Africa has a very low per capita electricity
use, this situation is likely to change rapidly in the future. It is projected that demand may increase
22
Agricultural Growth in West Africa (AGWA): Market and Policy Drivers. Edited by Frank Hollinger (FAO) John M.
Staatz (Michigan State University) February 2014 23
FAO’s 2012 State of Food Insecurity Report: Ghana, Nigeria, Mali and Niger have been making strong progress,
whereas Liberia, The Gambia, Senegal, and Sierra Leone have been lagging behind. In Côte d’Ivoire, The Gambia,
Guinea, Liberia, Senegal, Sierra Leone, and Togo, the absolute number of undernourished people has increased. 24
OCDE, Rapport Afrique de l'Ouest 2007-2008. Paris: OCDE. December 2008.
www.oecd.org/fr/csao/publications/42358554.pdf 25
Charles Schlumberger, "Open Skies for Africa - Implementing the Yamoussoukro Decision". Washington DC: The
World Bank, 2010. P. 76 26
Lee Crawfurd, "What ails African Carriers?". The East African, 25 January 2014, 27
OCDE, Rapport Afrique de l'Ouest 2007-2008, idem 28
Joel Macharia, « The legendary lunatic express is barely chugging along”, in “Africa in Fact”, issue 16, Oct. 2013. 29
In 2009-10, it was estimated that ~175 million people in ECOWAS region had no access to electricity, particularly in
the rural area (80% of the people without access). While six countries already have a significant national electricity
access rate greater than 30% (Cabo Verde, Ghana , Nigeria, Côte d’Ivoire and Senegal), in all remaining ECOWAS
countries only 18% of the population in average had access to electricity with most of them in urban areas (83%).
8
ten-fold in the coming two decades as the economic activity increases. Energy interconnectivity is
key to address such demand at regional level. While many interventions are planned at country level,
the West African Power Pool (WAPP), now a specialized institution within ECOWAS, is expected to
play a major role in creating a cross-border energy market to harness the competitiveness for all
West Africans, such as through the Bank supported "Côte d’Ivoire - Liberia - Sierra Leone - Guinea
(CLSG) Interconnection Project”. The project will bring a high voltage transnational transmission of
1357 km, with a capacity of 225 kV, linking all four countries. The region also features a large
potential for renewable energy30
. Research suggests that that up to 54% of Western African power
supply could be based on renewables by 2030.
2.5.3 In terms of ICT, West Africa has traditionally suffered from low access to high-speed
telecommunications and broadband. Prices have often been artificially maintained high due to
monopolistic positions, and users have suffered from high prices coupled with low connection
quality and speed. Two large projects were launched in 2012 to offset this major weakness: (i) the
West Africa Cable System (WACS), a 16,000 km fiber optic cable system running across the
Western coast of the continent, from South Africa to the United Kingdom, and (ii) the African Coast
to Europe (ACE) cable connecting 20 countries from France to West Africa, and representing the
first submarine cable to service several West African countries. It has a capacity of 5.12 Tbit/s, a
significant jump of capacity and quality of service offered to the region’s users.
2.5.4 The performance of West African countries in trade, transit and transport facilitation, as
measured by key facilitation indices, is mixed. The ECOWAS region is at par with the continent in
terms of cost to export and import; number of documents to export and import as well as time to
export and import. 31
However, averages masked large gaps in performances between the best
performing ECOWAS countries and the worst performing, as measured by the Logistics
Performance Index (Table 3).
Table 3: Logistics Performance Index scores, on a scale from 1 (low) to 5 (high), for the years
2010-2012-2014 (Source: The World Bank)
Nig
eria
Côte
d'I
voir
e
Burk
ina
Fas
o
Ghan
a
Sen
egal
Lib
eria
Ben
in
Mal
i
Guin
ea
Guin
ea
Bis
sau
Nig
er
Togo
Gam
bia
Sie
rra
Leo
ne
Cab
o
Ver
de
2014 2.81 2.76 2.64 2.63 2.62 2.62 2.56 2.50 2.46 2.43 2.39 2.32 2.25 -- --
2012 2.45 2.73 2.32 2.51 2.49 2.45 2.85 -- 2.48 2.60 2.69 2.58 2.46 2.08 --
2010 2.59 2.53 2.23 2.47 2.86 2.38 2.79 2.27 2.60 2.10 2.54 2.60 2.49 1.97 --
2.6 Regional Integration Strategy Framework Developments
2.6.1 The WA Regional Integration Strategy Framework remains predominantly shaped by the
ECOWAS and its Vision 2020, which aims to create an “ECOWAS of the People,” underpinned by
the establishment of a seamless regional market with economies of scale in economic activities and
free movement of persons, goods and services. The Vision 2020 focuses on five themes: regional
resource endowment; peace and security; governance; economic and monetary integration; and
private sector. Since 2011, the progress in implementing the Vision 2020 has been mixed.
2.6.2 Since 2011, one of the most remarkable landmarks in the development of economic co-
operation and regional integration in the ECOWAS was the adoption in October 2013 of the
30
Some example include: (i) Small hydro potential in the southern part of the region (ii) solar resources in the desert
areas (in Mali and Niger and in the North-Eastern part of Nigeria) with a potential of 1,700 kWh/installed (iii) Wind
potential is concentrated in the costal zones (Cabo Verde, Senegal, The Gambia, and possibly Ghana, Mali and Nigeria) 31
The composition of national exports to the region differs greatly. Nigeria’s exports are largely dominated by crude oil,
Côte d’Ivoire and Senegal by refined petroleum products, Ghana by manufactured wood, plastic and textile products.
Togo has the highest share of regional trade; it exports construction products (steel and cement), packaging material, and
some food products. Others, like Mali, Niger, and Burkina Faso, primarily export agricultural products..
9
Common External Tariff (CET), the principal attribute of Customs Union32
, which will become
operational on January 1, 2015. The CET will lead to a reduction of the most-favored nation import
tariff from 12.0% to 11.5%. This is a major achievement given the earlier controversies and
disagreements since the commencement of negotiations in 2004. Reduction of the MFN import tariff
should contribute to relaxing trade restrictions, harmonizing and strengthening the common market
of ECOWAS member states, a necessary condition for a customs union and common trade policy.
Steps towards deepening regional integration also included the creation of an ECOWAS Community
Integration Levy in 2013, which is to replace the existing community levy regimes, namely the
ECOWAS community levy and its WEAMU counterpart and the Community Solidarity Levy, with
the aim to ensure compliance with international WTO requirements.
2.6.3 The ongoing negotiations on ECOWAS–EU Economic Partnership Agreement (EPA)
represent a potential game changer in the trade and regional integration agenda. The EPA
would entail greater preferential access to European markets, but also require the opening of West
Africa’s market, albeit through a longer time transition time line of 20 years. There are already
signals from some concerned members over the impact of the EPA on their economies. West African
leaders, arising from their summit on 25 March 2014, called for more internal consultations in order
to further iron out divergences. Following this development, it thus points to the kind of challenges
EPA might pose to the cohesion of the region and indeed to the implementation of the CET, namely
on the need to reduce cost of doing business and address barriers to intra-regional trade as
prerequisite for a successful EPA which can build on and not hamper intra-regional integration. This
thus presents both challenges and opportunities for the ECOWAS going forward.
2.6.4 Progress has been made towards the establishment of the ECOWAS Monetary Union, yet
the deadline of 2020 appears unrealistic due to limited convergence to common criteria, with
the partial exception of WAEMU33
(see Annex 1). Efforts are underway to integrate the Nigerian
Stock Exchange, the Ghana Stock Exchange, the Sierra Leone Stock Exchange, with the Bourse
régionale de valeurs mobilières in Abidjan, including mutual cross-listing and trading of stocks. The
integration process for capital markets initiated in 2010 in the ECOWAS effectively took off with the
inauguration of the West African Capital Markets Integration Council, in Abuja in early 2013.
2.6.5 A number of sub-regional and specialized RECs are also emerging as key players for
regional integration, most notably agencies such as WAPP and smaller groupings like the MRU.
2.6.6 In recent years private sector in the region has also emerged as a new driver of regional
integration, with the affirming of new players operating across countries in the areas of agro-
industry, banking, transport, and ICT. In 2012 a new initiative called “Douala process” was
established to create a network of business organizations across French, Portuguese, and Spanish-
speaking Africa to improve business organizations’ governance and develop networks of alliances
for them to seek synergies. A private sector–led regional sea-link project is expected to contribute to
deeper trade integration by sea.
2.7 Aid Coordination and Harmonization Mechanisms
2.7.1 A number of major donors have been active in the regional integration process through
financing regional and multinational operations. These include the African Development Bank,
the World Bank, the European Union, the United Nations System, and many bilateral donors. From
32
The negotiations were concluded in Praia, Cabo Verde in March 2013, while the ECOWAS Heads of State finally
adopted it in their Summit in Dakar, Senegal in October 2013. The CET will however come into a full scale operation
from 15 January 2015. 33
None of the six Member States satisfied all the four WAMZ primary criteria in 2012, same as in 2011. The Gambia,
Ghana, Liberia and Nigeria satisfied three criteria each, while Guinea and Sierra Leone were in compliance with two
each. The most challenging criterion was fiscal deficit, followed by inflation. Concerns about the lack of preparedness for
the planned launch of the regional currency in 2015, a precursor for the establishment of the ECOWAS Monetary Union,
were also raised by ECOWAS and Heads of State at the recent WAMZ meeting in July 2013.
10
an aid coordination standpoint, a number of institutional actors in the region have been active in the
coordination of donors’ aid for regional integration.
2.7.2 While numerous aid coordination mechanisms exist at country level, there is no formal
aid coordination and harmonization framework for regional integration. Donor assistance is
generally scattered, particularly for capacity building efforts. Lack of coordination and
harmonization of interventions is clear not only at strategy and planning level, but during the
implementation, creating a multitude of procedures, supervision missions and incoherence in the
programming and functioning of activities. As indicated in Annex 4a, the track record of co-
financing regional integration projects is limited.
2.7.3 As a follow up to the various waves of droughts in the Sahel and the recent conflict in
Mali, efforts have been deepened to create a closer coordination in the Sahel region through the
establishment of a UN-led coordination platform on the Sahel gathering Sahelian countries,
Multilateral Development Banks, bilateral agencies and RECs. Yet this initiative is still at its infancy
and lack of common strategic planning is evidenced by the “proliferation” of Sahel strategies. New
more focused initiatives have emerged to strengthen regional and coordinated approaches to
resilience such as AGIR, P2RS and Lake Chad.
2.7.4 The Bank is also supporting new platforms for coordination and co-financing, notably
under the umbrella of the Mano-River Initiative, a new framework to facilitate financing of
regional backbones infrastructure for the four members of the MRU countries. The Bank is also
taking a key role in the Sahel Initiative and the recently established ECOWAS–led thematic groups,
including the Bank chaired group on infrastructure.
2.7.5 On and beyond the Mano River, co-financing with the European Union represents a
major opportunity, as around 1,2 billion Euros is planned to be rolled out for regional projects for
West Africa alone, as part of the EU’s Regional Indicative Program (2014-2020) currently under
preparation, with concrete opportunities for the Bank to co-finance some of its interventions and take
advantage of their “blending” instruments.
2.8 Challenges and Opportunities
2.8.1 The RISP 2011- 2015 identified various challenges for regional integration, such as poor
cross-border trade and infrastructure, as well as the weaknesses of human capacity and national
and regional institutions, fragmentation of the region’s market, multiplicity of integration
architecture and insufficient involvement of private sector and civil society in integration effort,
while it highlighted the political will
and the regional resource wealth as
the key opportunities. These still
remain today and undoubtedly, the
lack of adequate infrastructure
represents one of the most important
factors constraining African
economies’ move to a high growth
trajectory. However, they have been
exacerbated by new emerging
priorities, including governance and
increased fragility.
2.8.2 The increased exposure to
fragile situations in the region
indeed represents a major
challenge for maintaining peace and
security as well as state building, and
as a result has the potential to hinder
the deepening of regional integration.
Box 2: Integration through private sector, the case of
ECOBANK
Togo-headquartered "Pan African Bank" is a prime example
of the African private sector serving the mission of
strengthening ties and deepening integration between
countries – and of the difficulties of this endeavor. Established
in 1985 as a private effort led by the Federation of West
African Chambers of Commerce and Industry, Ecobank’s
largest shareholder upon launch was the ECOWAS Fund for
Cooperation, Compensation and Development. The bank was
granted the status of an international organization by the
Government of Togo, and considered a non-resident financial
institution. The bank boasts banking operations in 35 African
countries; yet Nigeria alone accounts for 70% of its customer
base. Ecobank posted a 16% growth in net revenue in FY13
and first quarter 2014, with $2 billion and $525 million
respectively. In West Africa, the bank has seen a 20.8%
increase in Net Interest Income in 2013 and a 15% growth in
net profits regionally, despite a 36% decline in Nigeria.
11
Further to the Sahel crisis, an additional country (Mali) has joined the classification of fragile states
and new pockets of fragility are emerging in the aftermath of regional security threats such as is the
case of North-Eastern Nigeria, spreading beyond its borders.
2.8.3 Governance challenges in some countries in the region continue to have a negative impact
on trade and investments. With only four African countries scoring above 50 (out of 100) on
Transparency International’s Corruption Perception Index, West Africa remains highly perceived as
a region that suffers from corruption and anti-transparent politics34
. This perception deeply affects
domestic and foreign private sector investments, resulting in a lack of confidence in investing in
national and cross-border investments.
2.8.4 Poor logistics and trade facilitation affecting the region greatly limit the benefits from
new infrastructure developments. Illegal checkpoints, long and non-harmonized customs
procedures, smuggling and corruption are important obstacles to the free movement of goods and
people. Long port dwell time, typically 12 to 20 days, are compounded for traffic to and from
landlocked countries. Improving trade facilitation in ECOWAS is vital to boosting the region’s trade
performance, both with regards to intra-regional trade as well as exports globally35
.
2.8.5 With six out of 10 African fastest growing economies in 2013 being West African36
,
mobilizing private sector around regional integration is a major opportunity. New waves of
FDIs and the emergence of a middle class in the region are leading to the emergence of a vibrant
private sector operating across countries, which can continue to serve as a natural catalyst for closer
collaboration and integration, towards the development of regional and global value chains.
2.8.6 Building regional value chains in West Africa, in areas such as agro processing, would
help support the efforts in better linking regional markets. For example, while the region is the
world’s largest producer of cocoa beans, 90 per cent of the crop is exported raw or roasted, packaged
and sent to the United States or Europe. This denies Africa of the most profitable part of the
confectionary market value chain – the processing of the cocoa into chocolate. The first steps in
undoing this disadvantage are to promote policies within the broader development framework,
attracting FDI, building productive capacities in local firms, and encouraging manufacturing.37
2.8.7 The increased stabilization of the region and opportunity of strengthening the regional
responses to common political and security threats in fragile situations can also offer a turning
point towards regional cooperation. The more recent positive signs of stabilization in affected
places such as in Mali and political transition in Côte d’Ivoire can be considered as a real opportunity
to enhanced trade in such pivotal countries. The regional dimension of fragility makes the case for
regional approaches and closer collaboration among States more compelling.
III. RISP IMPLEMENTATION: RESULTS ACHIEVED AT MID-TERM
3.1 RISP Objectives and Expected Results
34
According to the 2013 Transparency International Corruption Perception Index, one West African country scores
higher than 50, Cabo Verde (58 points) ranking 41st , followed by Ghana (46 points) at the 63
rd position and Senegal (41
points) at the 77Th
position. The bottom three West African countries are Nigeria (25 points) ranking 144th
, Guinea (24
points) at the 150th
position and Guinea Bissau, (19 points) for the 163rd
position. 35
The WAEMU has drafted plans for a regional transit reform to reduce sub-regional logistic costs by 25%, establish
interconnection of the customs IT systems, reduce time required for transit goods from ports to hinterland destinations by
50%, increase capacity in electronic trading and regulation, and remove obstacles from value-added logistics. The
preparatory phase of this sub-regional project was pre-approved for funding by the Africa Trade Fund. 36
The six West African fastest growing economies are: Burkina Faso (8% GDP growth), Niger (11.2%), Ghana (8%),
Sierra Leone (18.3%), Liberia (8%), and Côte d’Ivoire (8%). 37
Côte d’Ivoire provided incentives to major grinders including tax breaks on foreign investment, to locate processing
facilities in the country and has been able to attract global players. This has led to a broader network of input sourcing
and promises to strengthen linkages with the biggest players in the market. AfDB Annual Development Report 2012
12
3.1.1 The WA-RISP rests on two pillars: (i) linking regional markets and, (ii) building capacity
for effective implementation of the regional integration agenda. Within its two pillars, the WA-
RISP identified key investments, particularly in the area of energy and transport.
3.1.2 The WA-RISP has provisioned for 13 regional operations and five economic and sector
works to support the implementation of this strategy (detailed list in Annex 2). Out of the 13
projects, four were approved between 2011 and 2013, four are in process or under review, one is
postponed until 2016 and four are on stand-by due to an overoptimistic availability of ADF resources
(country and regional operations envelopes) when identifying the RISP portfolio. All ESWs have
been completed. Out of the 13 operations, five are in transport infrastructure, six in energy
infrastructure and two in capacity building. In addition to these 13 identified projects, twelve
regional operations were included in the pipeline for 2013 to 2015 (see Annex 3 for more details).
3.1.3 The global review of the WA-RISP implementation status is satisfactory, notwithstanding
the various difficulties that the projects are experiencing. The key challenge for the remaining
period will be to mobilize enough resources to deliver the four operations on stand-by. The
effectiveness and expected results of the RISP were monitored on the basis of the RISP’s Results-
Based Framework (RBF). The indicative results matrix in Annex 4 summarizes the outputs and
outcomes targeted in this RISP and their status at the mid-term.
3.1.4 Since its inception, alignment of CSPs to the WA-RISP has been fairly strong, with 14
newly approved strategies and one update, all displaying consistency with the two pillars of the
RISP. Country planning has also included an increasingly sizable share of projects with regional
dimensions, notably in Benin, Ghana, Nigeria and Senegal (see Annex 12).
3.2. Status of RISP Outputs and Outcomes at Mid-term
The analysis of the mid-term outputs and outcomes status compared with the expected
indicators indicated in the RBF of the WA-RISPs shows limited progress further to the delays in
approval and given that most results are likely to accelerate towards the end of the strategy period
and fully materialize beyond 2015. Nevertheless some tangible achievements have already occurred
at mid-term, namely through the first two operations approved in 2011 which are under an advanced
stage of implementation. The Rehabilitation of the Lomé – Cotonou Road and Transport Facilitation
on the Abidjan-Lagos Corridor Project has reached a completion rate of 40% as of March 2014. The
detailed indicators for regional integration will be calculated upon completion of the project
(scheduled for 2016). The Construction of the Trans-Gambia Bridge and Transport Facilitation on
the Trans-Gambian Corridor Project encountered delays in signature and only became effective for
first disbursement in March 2013. Construction works are scheduled to start mid-2014 after due
procurement process. Details of the expected results are in Annex 11.
3.3 Bank Group Regional Portfolio Performance Review
3.3.1 The Regional Portfolio Performance Review was undertaken by Bank field offices at three
different locations: in Ouagadougou with WAEMU, in Dakar with OMVS and OMVG, and in Abuja
with ECOWAS. Results of these reviews were then discussed during the wider MTR of the WA-
RISP which took place in Abuja on March 17-18 (see Annex 9). The review assessed the strengths
and weaknesses of the portfolio, and suggested proposals to improve its performance.
3.3.2 As of December 1st, 2013, the Bank's
active regional operations portfolio in West
Africa included 43 operations, including six
projects identified under the two strategic
pillars of the current RISP, for a global
amount of UA 667 million and an average
disbursement rate of 31%. The portfolio,
depicted in Figure 2, is dominated by the
infrastructure sector, namely energy and
transport projects, which accounts for 26
Energy (14 projects)
Transport (12 projects)
Agriculture (2)
Finance (6)
Social (2 projects)
Others (7 projects)
Figure 2: Breakdown of Regional Portfolio by value of
Sector
13
interventions for a total of UA 513 million or 77% of commitments. This predominance is due to the
priority assigned to these sectors in the Bank’s support for regional integration and, consequently, the
considerable resources mobilized for electrical interconnections and road corridor projects. The
regional portfolio is rated 2.07 / 3.
3.3.3 The Bank regional portfolio in West Africa also comprises six active private sector
operations amounting to UA 100 million, primarily in the finance sector and consisting of Lines of
Credits and Equity Participation in Regional Banks, as well as a few operations in the area of
monetary and banking reforms. By investing in funds, the Bank not only developed adequate
management capacity in the region, but also deployed relevant equity in companies which contribute
to strengthening entrepreneurship and governance. It also provides the growth capital required for
SMEs to potentially become the regional integration players of coming years.
3.3.4 The overall portfolio performance of the West Africa Region is relatively weak with an
average disbursement rate of 31% and presents a number of challenges, as described below.
3.3.4.1 Projects at risk: The total West African
regional operations portfolio includes two
problematic projects (PP), as well as 5 potentially
problematic projects (PPP); hence a total of seven
projects at risk (or 16% of the regional active
portfolio, in line with the Bank average).
3.3.4.2 Aging projects: the West African regional
portfolio comprises two aging projects, or 5% of
its operations, compared to a Bank’s overall
average of 12% for regional operations. However
an analysis of projects directly managed by the
RECs indicates that there is a large risk that, in the
coming 2 to 3 years, the regional portfolio will
include 5 to 6 additional aging projects, as the portfolio includes 7 operations with an average
disbursement rate of 50% and age of 6.4 years.
3.3.4.3 Signature delays: The regional portfolio of the West Africa region is experiencing
significant signature delays; this contributes to significant delays in projects startup, which in turn
affect the disbursement ratio. In addition, this situation exposes the said operations to cancellation, as
they fall into the criteria of operations being approved but unsigned for 180 days or more. Out of the
current portfolio of 43 projects, 15 have experienced signature delays. Lack of closer and proper
follow up from both the Bank and the RECs on conditions of signature and effectiveness and poor
coordination between the two entities are the primary reasons affecting projects start up and
disbursement. The new practice at the Bank is to propose loan agreements at national level to reduce
signature delays.
3.3.5 Regional operations directly managed by the RECs: various regional operations are directly
implemented by the ECOWAS and WAEMU
Commissions (four and three projects respectively)
as well as by OMVG and OMVS, to ensure an
adequate solution to specific challenges or
difficulties of these projects. With regard to
ECOWAS, the portfolio’s average age is 7.15 years
and the disbursement rate is 56%; for the WAEMU
portfolio, average age is 5.5 years and disbursement
rate 45%, representing a satisfactory disbursement
rate but similar aging average compared to the
overall regional average. Annex 6 provides the
overview of the regional operations managed by
14
WAEMU and ECOWAS.
3.3.5.1 These relatively weak results are essentially due to: (i) low level of quality at entry (low
maturity level of projects, institutional delays and long procedures in setting-up management teams
monitoring tools); (ii) Slow implementation (lack of follow-up from the Bank, weak monitoring
mechanism at the Bank and at the Commissions).
3.3.5.2 Portfolio performance and implementation challenges: implementation of the WA-RISP
generated many achievements in hard infrastructure, especially in road and energy projects, and in
strengthening collaboration between Member States of the sub-region.
3.3.5.3 However, impact from these investments remains limited due to obstacles encountered in
implementing trade facilitation and free movement of people, and procedures harmonization.
Construction and operationalization of checkpoints along corridors remain to be finalized.
3.3.5.4 Generally, the major challenges in implementing regional operations in West Africa
are: (i) lack of capacities within the RECs; (ii) low monitoring of activities by the regional structures
in charge of these projects, or lack of such structures; (iii) weak support from the Bank to these
structures; and (iv) lack of communication and follow-up mechanism for the regional portfolio.
Recommendations have been formulated as an Improvement Plan to respond to these difficulties.
3.3.5.5 Non-lending work, namely the ESW, also enabled the Bank to strengthen the dialogue
on regional issues and raised the awareness on the potential for regional integration. In the case of
Senegal, Nigeria and Cabo Verde, the studies triggered discussions on the respective role of such
countries in terms of regional integration. All planned ESW have been completed and in some cases
refocused in view of the changing political landscape.
3.3.6 Performance of the Bank, RECs, and RMCs: The portfolio review has unveiled a number of
key challenges that remain to be overcome, in order to improve the quality and performance of
multinational operations in West Africa; it also identified a number of lessons (see Section IV).
3.3.6.1 The main challenges to the performance of the Bank include (i) inadequate project
supervision, (ii) very strong centralization of decision taking at the temporary relocation agency in
Tunis (iii) insufficient proximity assistance to RECs, and (iv) inadequate supply of training on
Bank’s rules and procedures for project implementing organizations.
3.3.6.2 Performance of the RECs is often limited by (i) their low involvement in the project
planning phase, which translates into weak ownership, (ii) inexistent or inadequate follow-up
mechanism for projects, (iii) inadequate human resources allocated to projects, (iv) delays in the
selection of teams tasked with implementation, and (v) insufficient delegation of responsibilities.
3.3.6.3 Performance of RMCs has been found to suffer from (i) weak cross-country coordination in
project planning and implementation, (ii) insufficient consultations to determine appropriate project
launch conditions, and (iii) inadequate information sharing and dissemination.
3.4 Regional Portfolio Improvement Plan
3.4.1 The consultative approach on the portfolio review led to several proposals aimed at
improving the performance of regional operations in West Africa. These recommendations are
developed under an Improvement Plan (see Annex 7) and include the following measures:
(i) Strengthen decentralized responsibilities at field office level to ensure direct support to the
projects;
(ii) Deploy technical assistance (within the activities of capacity building to the RECs and to the
RMCs) on Bank’s procedures, such as procurement, financial management and audit;
(iii) Knowledge dissemination, sharing of good practices and experiences between the institutions;
(iv) Increase monitoring and evaluation mechanism through joint regular review of portfolio;
(v) Establish a taskforce of field office representatives and RECs to take appropriate actions on
cancellable projects.
15
IV. LESSONS LEARNED AND RECOMMENDATIONS AT MID-TERM
4.1 General Lessons
4.1.1 Despite the important developments and the progress achieved since the adoption of the
WA RISP, more needs to be done to strengthen market integration in West Africa and achieve
the objectives of the ECOWAS Vision 2020. Weaknesses in key infrastructure areas and in regional
and national capacities continue to represent key challenges for the regional integration process. In
addition, the RECs’ ability to implement regional operations remains constrained by insufficient
institutional capacity.
4.1.2 From the regional operations and programs implementation point of view, the analysis of
the WA-RISP MTR identifies key lessons that can be separated into four categories: (i) lessons
for the Bank; (ii) lessons for the RECs; (iii) lessons for RMCs; and (iv) lessons for the DPs.
4.2 Lessons and Recommendations for the Bank
4.2.1 To effectively strengthen the capacities of the RECs in the implementation of the regional
operations and improve the performance of the portfolio, the following lessons and recommendations
have been identified:
(i) Feasibility of the RISP indicative program of regional operations: The RISP was rather
optimistic on the Bank’s capacity to implement all regional operations. Some operations were
therefore dropped or put on stand-by for lack of funding. The MTR recommends a more realistic
planning of regional operations and a greater resource mobilization effort to leverage on
additional resources from partners. Good lessons were learned by the CLSG Interconnection
Power Project, where the Bank’s contribution of UA 130 million leveraged UA 331 million from
other partners.
(ii) The Bank should fully benefit from effective decentralization and delegation of
responsibilities to enhance timely and adequate responses to project identification,
implementation and monitoring. Various partners recommended the Bank should strengthen the
role of the field offices in the management of the regional operations and, if necessary, under the
supervision of a more experienced Task Manager;
(iii)The performance of multinational projects should be monitored and evaluated in a
different way compared to national operations, as responsibilities at the Bank are not always
well defined, in particular with regard to activities assigned to the RECs. Quality at entry and
quality at exit of regional projects need to be monitored more closely by ORWA and ORNG, in
order to reduce the risks of delays and eligibility for cancellation. For instance, assigning clear
responsibility for supervision to field staff, undertaking regular consultations between the field
offices and the implementing partners have proven effective tools of monitoring. Another crucial
activity to ensure timely implementation is the organization of procurement, financial
management, and audit workshops;
(iv) Trade, transit and transport facilitation are key: emerging evidence shows that multinational
operations in the area of infrastructure (hard side) need to be accompanied by trade and transport
facilitation and harmonization efforts (soft side) to fully deliver results. While visible
achievements have been made in hard infrastructure, operationalization of the soft side still
encounters difficulties, where the major challenge remains the application of agreed regulations
on facilitation, free movements, harmonization of customs practice, etc. The MTR recommends
mainstreaming the soft aspects across all new regional operations; 38
38 A few examples include: WAEMU Decision N°15/2005/CM/WAEMU on regional controls on roads, ECOWAS’
Inter-State Road Transit—Convention A/P.4/5/82 and Supplementary Convention A/SP.1/5/90, stipulating that the
transport of all transit goods should take place under the cover of an Inter State Road Transit Declaration booklet from
the point of departure in one country to the final destination in another country. ECOWAS Inter-State Road
Transportation—Convention A/P.2/5/82, setting out the conditions for inter-state road transport, and defines limits for
16
(v) Support to private sector and cross-country collaboration among companies should be
deepened to enable it to play a more prominent role in regional integration, trade facilitation,
knowledge transfer and financing;
(vi) Knowledge studies undertaken by the Bank are a valuable source of knowledge that should
be widely disseminated. The MTR recommends increasing knowledge generation and sharing,
including through the creation of a network of regional research centers and engagement with
RECs’ macroeconomic policy and research departments;
(vii) Institutional capacity of the RECs needs to be properly assessed: preparatory phases of
multinational projects often failed to adequately assess capabilities of regional institutions
(human resources, management arrangements and operating mechanisms). In the future, the Bank
should carry out a capacity assessment of the RECs and devise a set of measures to fill the
necessary capacity gaps. This is in line with the recent OPEV report on regional projects, which
stressed the importance of consultation and engagement with all stakeholders.
4.3 Lessons and Recommendations for the RECs
(i) RECs should create or strengthen existing structures within the RECs in charge of
implementing projects financed by the Bank. This includes assigning them more strategic and
coordination role, and reduced the operational responsibilities of these institutions
(ii) Regular portfolio review consultations with the Bank and other implementing partners are
needed to ensure coordinated, timely and effective monitoring of implementation status;
(iii)RECs should work more closely with their Member States to follow up on the
implementation of regional integration reforms, which are agreed at REC level but lack
operationalization at national level (e.g. those mentioned in footnote 39).
4.4 Lessons and Recommendations for RMCs
(i) There is a need to accelerate the above mentioned application of conventions and
regulations on regional integration agreed at REC level, which often fall short of being
implemented at national level, including rationalization of the number of specialized institutions
and dissemination of agreements, protocols and trade-related decisions to non-governmental
actors (civil society, private sector and trade unions);
(ii) Need for harmonization between the various norms, procedures and regulations at national
level. This should be supported by additional measures to spread knowledge about them to all
actors involved and to facilitate free movements of services across borders.
4.5 Lessons and Recommendations for the Development Partners
(i) Coordination among DPs needs to be strengthened, as weak coordination among various
stakeholders in the execution of multinational projects often creates huge disparities in the
implementation of the activities of these operations, which inevitably affect the achievement of
the expected outputs and results;
(ii) Harmonization of procedures and strategies of funding agencies should be encouraged.
Across the variety of actors involved in regional operations. Greater coordinated planning and
harmonization would ensure timely delivery and achieve successful project implementation, as
well as reduce drudgery and transaction costs.
V. BANK GROUP STRATEGY FOR THE REMAINING WA-RISP PERIOD
5.1 Rationale and Pillars
Analysis at mid-term supports that the challenges and two strategic pillars identified in the
WA-RISP (2011-2015) remain broadly relevant for the remaining period yet there is a need to
truck dimensions and axle loads. ECOWAS Brown Card insurance scheme—Convention A/P.1/5/82 facilitating the free
movement of persons and goods through a common insurance cover.
17
refocus Pillar I into Regional Infrastructure Development to ensure alignment to the TYS39
and take
into account the new political landscape and new fragility dimensions in the region.
5.2 Criteria for Defining the Strategy for the Remaining WA-RISP Period
The Bank Strategy for the remaining period proposes a new filtering process to be adopted
in view of the changes occurring in the region:
(i) Ownership – At the regional institutions’ level, the Bank takes stock of the progress
achieved by the RECs, which has shown moderate results within the regional integration
agenda. In particular, the Bank advocates for enhanced ownership of regional integration
agreements by countries and by the RECs and supports strengthened implementation of the
Vision 2020. The Indicative Lending Program is fully aligned with PIDA and the 2020 plan.
(ii) Alignment with TYS - At the strategic level, all new initiatives should be more closely
aligned with the TYS operational priorities and areas of special emphasis. The MTR
proposes supporting regional integration mainly through a more focused regional infrastructure
pipeline, while increasing its support to “soft” aspects, in line with the orientations from the new
Bank’s Regional Integration Strategy under preparation. The Bank will also pay stronger
attention to TYS’s areas of special interest (see para 5.3.4);
(iii)Fragility – Building on the new and changing political landscape (para 2.2), priority will
also be given to transformative activities which could support to areas of persistent and
renewed fragility, namely through initiatives with high potential to contribute to regional
stability, such as the Sahel and the MRU;
(iv) Partnership and leveraging – Taking stock of the notable economic developments (para 2.3)
the Bank will be encouraged to support catalytic interventions, which offer opportunities
for new partnerships with the private sector and other development partners to boost regional
infrastructure and expand intra-regional trade markets.
5.3. Key Deliverables and Targets
5.3.1 The RISP Indicative Pipeline has been update revised in view of the above criteria and
lessons learnt. The list of old and new operations are found in Annexes 2 and 3.
5.3.2 Pillar I: Regional Infrastructure Development
5.3.2.1 Under Pillar I, the Bank will put a stronger focus on regional infrastructure
development, namely on energy and transport. With a view towards taking into account
emerging issues linked to fragility in the Sahel, emphasis will also be put on agricultural
infrastructure. Bank investments in these sectors will enhance trade and transport through
efficiency gains, leading to decreasing transport cost and time, and increasing access to more
affordable and reliable electricity. This includes a new multi-donor initiative for the MRU countries
aimed at financing regional infrastructure backbones, where the Bank will finance various transport
missing links. A number of new catalytic interventions of rehabilitation of cross-border roads in Côte
d’Ivoire-Mali and the construction of the bridge on the Rosso (Senegal-Mauritania) will also be
financed. The Bank will also support a regional air transport project and a new program to strengthen
resilience to food insecurity (para. 5.3.4.4).
5.3.2.2 Finally, the Bank will deepen its work on trade, transit and transport facilitation which
will become an integral part of all new transport operations, and support a standalone
WEAMU’s Trade Facilitation program.40
Annex 3 provides the full list of newly identified regional
operations for the remaining period.
5.3.3 Pillar II: Capacity Building for Effective Implementation of the Regional Integration
Agenda
39
The TYS’s priority areas are: infrastructure, regional integration, private sector development, governance and
accountability, and skills and technology. The TYS’s areas of special focus: agriculture and food security, fragility and
gender. 40
Support will also be provided for the formation of Corridor Management Organizations (CMO), which would be
established by the states for particular corridors, but funded and driven by the private sector and stakeholders.
18
5.3.3.1 Within the WA-RISP MTR framework, the AfDB will continue to provide capacity
development to RMCs and the RECs, in order to offset the lingering weaknesses of human
capacity of national and regional institutions, market fragmentation, and complex integration
infrastructure. In this regard, attention will be paid to building institutional capacity for
implementation of a common market occasioned by the conclusion of the CET, a renewed migration
policy and the private sector.
5.3.3.2 The Bank will refocus its capacity building efforts towards cross border trade, namely
through the Africa Trade Fund, which will support a number of programs, like the Trade
Transparency Initiative, Customs Reform and modernization programs, as well as through the
monitoring and evaluation of trends that can inform improved border and transit management.
5.3.3.3, The Bank will also continue building stronger statistical capacity of the RECs and the
wider stakeholders to nourish a wider debate on regional integration. Under the ongoing statistical
capacity building of the RISP, the Bank will accelerate the implementation of its support to (i) the
ECOWAS Commission, (ii) WEAMU, (iii) MRU, (iv) AFRISTAT, (v) two Statistical Training
Centers (ENSEA in Côte d’Ivoire and ENEA in Senegal) and (vi) WAMI.
5.3.3.4 Under this pillar, the Bank will also establish a new knowledge platform gathering
regional think tanks and research center. The Bank will aim at significantly increasing the
repository of knowledge on regional integration, build stronger capacity of local and regional
institutions to play a key role in shaping dialogue at country level, as well as generate a space for
bottom-up dialogue. It is expected that this platform will enhance the repository of knowledge on
regional integration and contribute to the broader ESW agenda (see para 5.3.5).
5.3.3.5 The Bank will also support the creation of a network of SME supporting agencies in the
WAEMU region through the initiative “Making Finance Work for Africa”, further to the preparatory
work and foundations for such a network in 201241
.
5.3.4 Areas of Special Emphasis
5.3.4.1 The MTR suggested greater efforts are deployed to address the various areas of special
emphasis defined by the TYS, namely Gender, Fragility and Agriculture and Food Security.
5.3.4.2 Fragility. In line with its new approach to addressing fragility and building resilience, the
Bank will strengthen its programming by applying a strong “fragility lens” to detect, respond and
prevent fragility through a political economy analysis in the design of policy documents and through
project interventions that can lead to peace- and state-building. The Bank’s focus will be to build
resilience not only at the national level but also at the regional level, by working through and with
regional organizations; assisting governments to address fragility, addressing capacity gaps in fragile
situations; and integrating a gender perspective in all programs to build resilience.
5.3.4.3 Gender. The MTR proposes that the Bank deepen its regional integration activities towards
gender inclusive interventions, including through conducting country gender profiles for the whole
sub-region (three completed in 2011 and two to be finalized in 201442
), as well as undertaking a
regional gender assessment for the Sahel. These studies will inform regional and country-level
strategies and operations, as well as build a baseline to develop targeted indicators to measure
specific impacts of its regional projects on girls and women for the future RISP and projects. A
stronger emphasis will be put on having inclusive processes, where women are equally represented in
the decision-making structures and the political dialogue. Regional operations teams will be
41
Declaration of Intent for the Establishment of the Regional Formal Network of SME Supporting Agencies in the
WAEMU Region, "The Dakar Declaration”, March 30th, 2012 42
Mali (2011), The Gambia (2011), Sierra Leone (2011), Liberia (expected 2014), Côte d’Ivoire (expected 2014) and
Nigeria (expected 2014).
19
encouraged to include a Gender Specialist. Capacity building activities will include components
targeted at women’s specific needs43
.
5.3.4.4 Agriculture and food security. The Bank will also pay closer attention to agriculture and
food security, namely through a new agriculture infrastructure program to strengthen resilience to
food insecurity in the Sahel. Through this program and various country interventions, the Bank will
try to reverse the agricultural and food trade balances for West Africa, which have remained negative
over the past decade44
.
5.3.5 Economic and Sector Work
The Bank will give greater focus on creating knowledge for the remaining period. A
dedicated knowledge management strategy will be developed to encourage the Bank to “think
regionally” and get a better understanding of, monitor and provide policy advice on common
challenges affecting the region, including through a number of new policy series and quarterly
publications. The Bank will also deliver a number of flagship publications and detailed studies, such
as (i) fragility assessments in the Sahel region and in the MRU countries; (ii) an economic analysis of
the potential for growth for the MRU; (iii) studies on Trade facilitation and investment; (iv) a gender
study on Sahel and (iv) a number of studies addressing and assessing regional projects, including the
planned railway network and the Abidjan-Lagos corridor. These studies, mostly funded by IPPF and
Trust Funds, will support dialogue on regional integration and also prepare the ground for the next
RISP. The full list of new planned ESW can be found in Annex 3.
5.4 Institutional Arrangements and Resources
5.4.1 The RISP recommends mainstreaming the regional integration agenda across all
interventions. Greater emphasis and preference should be assigned to country operations which have
the potential to contribute to regional agenda. While national utilities and adequately mandated sub-
regional institutions are identified as the main implementing agents, ECOWAS will play a greater
coordination role for regional programs through the establishment of a framework agreement
between AfDB and ECOWAS.
5.4.2 At the Bank’s level, ORWA, ORNG and ONRI will jointly manage and coordinate
implementation of the RISP, in collaboration with sector departments. Gaps in RISP
implementation modalities were identified namely in terms of supervision. To address this gap, the
MTR recommends strengthening the role of key field offices (Nigeria, Burkina Faso and Senegal) in
overseeing the implementation of regional operations.
5.4.3 Financing for lending operations is expected to primarily come from ADF resources
(national and regional), Fragile States Facility and ADB for private sector operations. In line
with the TYS, the Bank will put a greater effort in playing a catalytic role for regional integration.
The Bank will seek to mobilize co-financing from the development partners, such as the co-financing
with the EU of the Mano River Road Program, and private sector, particularly through participation
and support to regional private equity funds. It will also leverage on Bank’s own initiatives such as
the Africa50 Fund, EPSA and the Africa Trade Fund. Non-lending activities will benefit from grant
resources including Trust Funds and the NEPAD-IPPF.
5.5 Potential Risks and Mitigation Measures
The RISP identified three major risks to implementing the Strategy: (i) weak
commitment of member states to integration; (ii) duality and multiplicity of integration
architecture; nd (iii) political fragility. These risks are still relevant. To address them the Bank will
continue working on capacity building and increase its monitoring of the regional challenges through
43
The WA RISP will build on the award winning Multi-sector Support Project in Côte d’Ivoire, which addressed the
capacity deficit in providing services to victims of gender-based-violence. 44
This trend towards growing food imports coincided with a period of strong growth of merchandise exports, which has
led to a greater capacity of many countries to import. Nevertheless, there are concerns about the sustainability of this
import capacity, as it is based heavily on the export of non-renewable resources.
20
its regional knowledge program. In addition, the scarcity of ADF resources further to the latest ADF
replenishment represents a new major risk, leaving the Bank with limited resources to deliver on its
ambitions. The Bank shall therefore seek greater pooling of resources already available within the
Bank and establish of closer partnerships with other DPs, such as the EU.
VI. CONCLUSION AND RECOMMENDATION
6.1 It is proposed to maintain the WA-RISP’s strategic thrust during the remaining period (2014-2015), while refocusing the first pillar around infrastructure development and continuing its
capacity building support.
6.2 The Bank will also support new initiatives, such as the Sahel and the MRU Initiative, and
deepen its work on trade, transit and transport facilitation. On and beyond such initiatives, the
Bank will reach out to other development partners to increase collaborations, especially with the EU.
The WA-RISP will give a special focus to inclusiveness and transition to green growth through the
TYS’ three areas of special emphasis (fragility, gender and agriculture and food security).
6.3 It is recommended that CODE members approve the WA-RISP MTR (2011-2015) and
RPPR.
I
Annex 1. ECOWAS Monetary Cooperation Program Convergence Criteria
There are three sets of macroeconomic convergence programs in West Africa, namely ECOWAS, WAEMU, and WAMZ. Each of these
programs adopts an independent set of primary and secondary convergence criteria for multilateral surveillance. The macroeconomic
convergence indicators are not entirely uniform across the programs, and where similarities exist, the values for the indicators vary in some
instances. The WAEMU convergence criteria are overall stricter than those of ECOWAS or WAMZ, particularly on fiscal balance and price
inflation. Overall, and particularly for the secondary criteria, the countries seem quite far from achieving their convergence goals.
WEAMU Countries [2013 data] WAMZ Countries [2013 data]
PRIMARY CONVERGENCE CRITERIA
Ben
in
Bu
rkin
a
Fa
so
Cô
te
d’I
vo
ire
Ma
li
Nig
er
Gu
inea
Bis
sau
Sen
ega
l
To
go
Ga
mb
ia
Gh
an
a
Gu
inea
Lib
eria
Nig
eria
Sie
rra
Leo
ne
Ca
bo
Ver
de
WAMZ ECOWAS UEAMOA
Inflation ≤10% (Single
Digit)
End-period
≤5%
End-period
≤ 3%
Annual -average
3 3 2.8 3 2 1 0.7 3 5.3 11.7 11.9 7.7 8.5 9.9 1.5
Fiscal
balance/ GDP
≤4%
Excluding
grants
≤4%
Excluding
grants
≥ 0
Basic balance
0.4 -0.2 -1.5 -0.9 1.3 -1 -2.4 0.7 -3.3 -7.8 -5.2 -2.6 -1.8 0.0 -7.9
Central Bank
Financing
≤10%
Previous year’s
tax revenue
≤10%
Previous year’s
tax revenue
Not
Applicable
0.4
(201
2)
9.4
(201
2)
6.8
(201
2)
0.0
(201
2)
0.0
(201
2)
0.0
(2012)
N/A
Gross
External
Reserves
≥3 Months
(Months of
import cover)
≥6 Months
(Months of
import cover)
Not
Applicable
4.8
(201
2)
3.4
(201
2)
3.1
(201
2)
3 9.5
(201
2)
3.1
(2012)
N/A
Public
Debt/GDP
Not
Applicable
Not
Applicable
≤ 70%
Domestic &
External Debt
20.6 26.3 31.7 29.7 24.1 35.5 45.2 46.3
Payment
Arrears
Not
Applicable
Not
Applicable
Non-
accumulation
Arrears
0 0 0 0 0 0 0 0
Number of
Criteria
4 4 4 4 3 3 3 4 3 3 4 3 3 2 3 3 2 N/A
II
SECONDARY CONVERGENCE CRITERIA
WAMZ ECOWAS UEMOA
Arrears Non-
accumulation &
liquidation of
Domestic
arrears
Non-
accumulation &
Settlement of
all arrears
Not
Applicable
Tax Revenue
/GDP
≥20% ≥20% ≥17% 16.6 16.5 17.2 15.6 15.6 8.2 19.1 16.8 14.5 16.3 18 20.1 2.8 9.9 N/A
Salary
Mass/Tax
Revenue
≤35% ≤35% ≤35% 43.6 34.8 43.1 35.7 30.9 60.2 32.7 34.4 42 54.6 25 54.7 89.3 48.9 N/A
Public
Investment
From
Domestic
Receipts / Tax Revenue
≥20%
(Domestic
Receipts)
≥20%
(Tax Revenue)
≥20%
(Tax
Revenue)
23.3 48 27.9 18.7 41.8 12 36.4 20.4 85 58.3 36 37.7 21.8 39.2 11.3
(public
investm
ent)
Real Interest
Rate
>0
Savings
deposits less
inflation
(Positive)
>0
Savings deposits
less inflation
(Positive)
Not
Applicable
22.5 N/A N/A 9 14.9 8.1 6.3
Exchange
Rate Stability
±15
(WAMZ ERM
II)
±15
(Real Exchange
Rate)
Not
Applicable
8.7
(201
2)
52.9
(201
2)
71.3
(201
2)
N/A 12.9
(201
2)
40.9
(2012)
N/A
Current
Account
Balance/GDP
Not
Applicable
Not
Applicable
≥ -5%
(Excluding
grants)
-8.7 -5.6 -3.6 -5.1 -
23.5
-7.7 -9.4 -9.6
Number of
Criteria
6 6 4 0 1 2 1 1 1 3 1 2 0 2 1 3 2 N/A
Sources: WAEMU Commission, West African Monetary Institute, African Development Bank.
III
Annex 2: Indicative Program of Regional Operations and Economic and Sector Work as per the WA RISP 2011-
2015 and its effective implementation
Project Name Sector Est. Cost (in
million)
Co-financing (UA in million) Status
PILLAR I: LINKING REGIONAL MARKETS
1. Rehabilitation of the Lomé - Cotonou Road and
Transport Facilitation on the Abidjan-Lagos Corridor
Project
Road Transport UA 132 0.9 (WAEMU) Approved (2011)
2. Construction of the Trans-Gambia Bridge and Transport
Facilitation on the Trans-Gambian Corridor
Road Transport UA 90 0.63 (Governments) Approved (2011)
3. Boke-Kebo Road Rehabilitation Project Road Transport UA 60 Stand-by
4. Rehabilitation and Transport Facilitation of the Lomé -
Ouagadougou Corridor
Road Transport UA 252 9.46 (IsDB), 7.92 (KFW), 2.06
(EU), 3.6 (Prives), 23.95
(BOAD), 13.56 (EBID), 0.93
(WAEMU), 0.17 (UNFPA)
Approved (2012)
5. Integrated System of Multimodal Transport Transport UA 40 N/A Project done without
the Bank
6. Côte d’Ivoire-Liberia-Sierra-Leone-Guinea Power
Interconnection Project
Energy UA 331,51 88.57 (WB), 61.98 (IsDB), 8.55
(EU), UA 26.27 (KFW)
Approved (2013)
7. OMVG Energy Project, Phase I (Gambia, Guinea,
Guinea Bissau and Senegal)
Energy (production) UA 101 113 (WB), 34 (BOAD), 107
(IsDB), 74 (EIB), 22 (KFW), 241
(China Exim), 33 (AFD), 19.5
(Governments)
In process (2014)
8. Ghana-Burkina-Faso-Mali Power Interconnection
Project
Energy UA 70 N/A Postponed to 2016
9. FOMI Power Interconnection Project (Guinea and Mali) Energy € 165 N/A In process (study
completed, project
under review)
10. Adjaralla Hydroelectric Development Project Energy (production) € 247 N/A Stand-by
11. Emergency Power Supply Security Plan (400MW
Plan at Maria Gleta in Benin, 400MW Plan in Aboadze in
Ghana and 150MW Plan in OMVS System)
Energy (production) N/A N/A Stand-by
IV
PILLAR II: CAPACITY BUILDING
12. Strengthening ECOWAS/WAEMU Commission
Capacity
Capacity Building UA 30 N/A Under review
13. Program for Building Statistical Capacity in RMCs Capacity Building UA 40 N/A In process
ECONOMIC AND SECTOR WORK
14. A Role for Senegal in Regional Integration Multisector (Flagship) Completed
15. Study on Regional Integration and Stability: Integrated
Infrastructure Action Plans for Fragile States
Infrastructure (Flagship) Converted into 2 country studies on Liberia and Sierra
Leone and completed
16. Flagship Report- Nigeria Infrastructure Infrastructure (Flagship) Completed
17. A Regional Success Story: The Case of Cape Verde Multisector (Flagship) Completed
18. Study for the Creation of the ECOWAS Fund for the
Development of Transport and Energy (FODETE)
Energy In process (2014)
V
Annex 3: New Indicative Regional Operations and ESW In Addition to Those
Identified in the WA RISP 2011-2015
New Regional Operations Sector Est. Funding* Co-financing Status
PILLAR I: REGIONAL INFRASTRUCTURE DEVELOPMENT (former Linking Regional Market)
1. Trans-Saharan Road (Chad, Niger, Algeria) Road
Transport
UA 120 M N/A Approved (2013)
2. Mali - Côte d’Ivoire Cross-Border Road Road
Transport
UA 98.8 M UA 22.5 M IsDB
UA 0.8 M WAEMU
In pipeline
(2015)
3. Mano River Union Road Transport Program (Phase 1):
Cross-Border Road Corridors Project (Côte d’Ivoire,
Guinea) and Fish Town - Harper Road Project Phase 2
(Côte d’Ivoire, Liberia)
Road
Transport
Phase 1: UA
265 M
Phase 2:UA 75
M
UA 18 M
(Governments)
USD 80 M WB
In the pipeline
(2014)
4. Mano River Union Road Transport Program (Phase 2) :
Trans-West African Coastal Highway – Bo - Bandajuma –
Zimmi-MRU Bridge (Liberia Border) [150 km] & MRU
Bridge – Klay - Monrovia [117km]
Road
Transport
UA178 M € 107 M (EU) and
UA 10 M (OFID)
In the pipeline
(2015)
5. Program to Strengthen Resilience to Food Insecurity
(Burkina Faso, Chad, Gambia, Mali, Mauritania, Niger,
Senegal)
Agriculture
Infra. & Food
security
UA 155 M UA 27 M
(Governments)
In process (2014)
6. Construction Project of Rosso Bridge (Senegal,
Mauritania)
Road
Transport
UA 50 M € 40 M (EU) In the pipeline
(2015)
7. Program to Support the Air Transport Sector in Central
and Western Africa (PASTA-CO)
Air Transport UA 22,3 M N/A In process (2014)
8. WAEMU Transport and Trade Facilitation All Transport
and trade
UA 7 M UA 1 M (WEAMU) In the pipeline
(2014)
PILLAR II: CAPACITY BUILDING
9. Senegal Customs Modernization & Corridor
Management Program
All Transport
and trade
UA 300,000 USD 260,000
(Senegalese
customs / Gainde
2000)
Pre-approved
by AfTRA
(2014)
10. WAEMU Transport and Trade Facilitation Project –
Phase I
All Transport
and trade
UA 361,000 USD 50,000
(WAEMU)
Pre-approved
by AfTRA
(2014)
11. Preparation of Establishing Continental PKI
Infrastructure and Trade Portal for electronic verification
and digital signature
All Transport
and trade
UA 271,000 USD 479,000
(Africa Alliance
for eCommerce)
Pre-approved
by AfTRA
(2014)
*Total Bank financing, subject to availability of funding
ECONOMIC AND SECTOR WORK Sector Est. Cost Funding Key Dept. Key partner
1. Unlocking the Potential for Mano River,
Infrastructure Study for Mano River
Road Transport,
Energy
UA 80 K Canadian TF ORWA/
OICT/ ONEC/
ONRI
Mano River Union
2. Fragility Assessment for Mano River Multi-Sector UA 16 K Admin ORFS Mano River Union
3. Feasibility Study on Road Corridors under
the MRU Initiative
Road Transport USD 1,5 M IPPF ONRI
4. Fiscal Regime on Mineral Taxation
Harmonization Study
Governance UA 80 K FSF Pillar 3 OSGE
5. Gender Study in the Sahel Gender UA 70 K NTF ORWA/ORQR
/ SEOG/
ORFS
6. Feasibility Study Abidjan/Lagos Highway Transport UA 5 M FAPA, IPPF ONRI ECOWAS
7. Study on “Sustainable Market Access for
African Road Transport” (SMART)
Road Transport UA 400 K OITC
8. Technical, Economic, and Financial Study
for the Abidjan- Yamoussoukro-Ougadougou
Highway (Phase 2)
Road Transport USD 6,5 M IPPF ONRI WAEMU
USD 12 M
9. Benin – Nigeria Interconnection Study Energy USD 3,6 M IPPF ONRI
VI
Annex 4a: Status of RISP Outputs at Mid-term (IOP 2011-2015 and ongoing projects)
A= Achieved; OT= On-Track; BS= Behind Schedule
Pillars Mid-term Outputs
Indicators (by RISP)
Status of Mid-term
Outputs Indicators
by April 2014
Statu
s Remarks
PIL
LA
R I
LIN
KIN
G R
EG
ION
AL
MA
RK
ET
S (i) Investments in roads
corridors and transport
and trade facilitation
Construction works on the Lomé-
Cotonou, the Lomé – Ouagadougou,
and the Trans-Gambia bridge have
commenced and are on-going
Lomé-Cotonou under
construction
OT Execution rate at
40%, slightly
behind schedule
due to a delay in
disbursing but the
works are catching
up
Lomé-Ouagadougou
under construction\ BS
Construction works
scheduled to start
in September 2014,
due to procurement
difficulties
Trans-Gambia study
completed,
procurement process
ongoing
BS
Delays in
signatures, causing
delays in
procurement and
study completion.
Since 2013,
significant progress
has been made
Draft reports of the EU-funded
detailed engineering design studies
available
3 studies completed
(one market study,
one on economic and
financial profitability,
one on institutional
arrangements for the
railway project)
A
Studies completed
in 2012 and
submitted to
ECOWAS
(ii) Regional energy
production and markets
integration
Construction works on the OMVG,
CLSG projects commenced and are
on-going.
OMVG under
evaluation
BS Evaluation to be
completed in 2014
CLSG under bidding
process
OT
PIL
LA
R I
I: C
AP
AC
ITY
BU
ILD
ING
FO
R
FF
EC
TIV
E I
MP
LE
ME
NT
AT
ION
OF
RE
GIO
NA
L I
NT
EG
RA
TIO
N A
GE
ND
A
(i) Capacity building for
financial sector
integration
Installation of the Real Time Gross
Settlement, Automated Clearing
House, Automated Check
Processing, and Scriptless Securities
Settlement systems, in the Gambia,
Guinea, Liberia, and Sierra-Leone
about 90% complete
A These outputs were
achieved with the
completion of the
WAMZ 2007 and
2010 projects
(ii) Capacity building
for effective policy and
regional projects
implementation
Training and consultancy services
provided to WAPP
BS WAPP project
approved last
quarter 2013
(iii) Support to Regional
Centers of Excellence
Support provided to strengthen
ECOWAS identified centers of
excellence.
Evaluation to be
completed in 2014
(iv) Statistical support to
ECOWAS Institutions
Bank Group’s Program for Building
Statistical Capacity in RMCs.
OT Evaluation to be
completed in 2014
VII
Annex 4b: Status of RISP Outcomes at Mid-term (IOP 2011-2015 and ongoing projects) A= Achieved; OT= On-Track; BS= Behind Schedule
Pillars Mid-term Outcomes Indicators (by
RISP)
Status of Mid-term
Outcomes
Indicators by end
2013
Status Remarks
PIL
LA
R I
: L
INK
ING
RE
GIO
NA
L
MA
RK
ET
S
(i) Investments in roads
corridors and transport
and trade facilitation
About 750 jobs created in the road
infrastructure development related to
Lomé-Cotonou, the Lomé –
Ouagadougou, and the Trans-Gambia
bridge works
750 jobs created
OT Will be exactly
measured upon
project
completion report
Progress on consultations with
donors for the mobilization of
resources for the railways sector
Consultations were
held in Niger with
ADB, further
consultations to be
organized
BS Meeting between
Ministries of
Transport in 2014,
with ADB and EU
as interested
partners
ii) Regional energy
production and markets
integration
About 2000 and 500 direct and
indirect jobs respectively are created
during construction phase of the
OMVG energy project
BS Project under
evaluation
5000 jobs created during
implementation of the CLSG Project
BS CLSG Project
only approved in
2013
PIL
LA
R I
I:
CA
PA
CIT
Y B
UIL
DIN
G
(i) Capacity building for
financial sector
integration
Not applicable
(ii) Capacity building
for effective policy and
regional projects
implementation
Improvement in implementation of
WAPP priority projects
BS WAPP project
approved last
quarter 2013
(iii) Support to Regional
Centers of Excellence
Use of science and technology to
develop other sectors, social
infrastructure, industry, environment
and climate change, makes progress
in ECOWAS
Strengthened culture of science and
technology in the region
Agents of regional integration trained
with shared approach on integration
Enhanced capacity in technological
skills for economic transformation
Project under
evaluation
(iv) Statistical support to
ECOWAS Institutions
Bank Group’s Program for Building
Statistical Capacity in RMCs
Project under
evaluation
VIII
Annex 5: List of Multinational Operations in West Africa Long name Sector Name Appr. Date Closing Date Net loan Disb. Ratio
Projet appui filliere coton -WAEMU Agriculture 29.11.2006 30.06.2014 2,000,000.00 75.75
Projet de gestion durable du betail rumi Agriculture 25.01.2006 31.12.2014 10,240,000.00 83.22
Projet de reforestation et de réhabilita Environment 29.11.2011 31.12.2016 173,435.61 59.32
Apiculture améliorée et reforestation Environment 30.11.2011 31.12.2016 204,261.48 57.22
Conservation international foundation Environment 09.06.2010 30.06.2015 900,462.48 12.78
Appui au programme élargi de formation Environment 15.05.2011 31.12.2016 5,862,832.40 69.09
Appui à la participation multi acteurs Environment 13.12.2011 31.12.2016 1,463,150.55 64.22
FAPA technical assistance to EBID-BIDC Finance 26.02.2013 31.12.2018 405,196.75 0
BOAD ligne de credit Finance 30.01.2008 31.12.2014 30,755,902.58 100
BOAD FAPA TA Finance 04.02.2008 31.12.2014 409,078.19 26.06
BOAD- LDC II augmentation de capital Finance 23.02.2011 31.12.2016 49,209,444.13 100
Payments systems dev project in WAMZ Finance 09.07.2008 30.06.2014 14,000,000.00 82.21
Supplementary grant to WAMI for the mult Finance 09.11.2010 30.06.2014 5,000,000.00 20.62
Institutional support - Mano River Union Multi-Sector 01.10.2013 30.12.2018 942,640 0
CLSG - WAPP- Sierra Leone Power 06.11.2013 30.12.2018 703,000 0
CLSG - Côte d'Ivoire Power 06.11.2013 30.12.2018 26,173,000 0
CLSG Liberia Power 06.11.2013 30.12.2018 8,102,000 0
CLSG Sierra Leone Power 06.11.2013 30.12.2018 88,355,000 0
CLSG Guinee Power 06.11.2013 30.12.2018 28,910,000 0
CLSG Guinee Power 06.11.2013 30.12.2018 834,000 0
CLSG - WAPP- Côte d'Ivoire Power 06.11.2013 30.12.2018 721,000 0
CLSG - WAPP- Guinee Power 06.11.2013 30.12.2018 781,000 0
CLSG - electrification rurale Power 06.11.2013 30.12.2018 6,106,000 0
CLSG-rural electrification -Liberia Power 06.11.2013 30.12.2018 16,838,000 0
CLSG-rural electrification -Liberia Power 06.11.2013 30.12.2018 1,120,000 0
CLSG- rural electrification Sierra Leone Power 06.11.2013 30.12.2018 13,432,000 0
CLSG-rural electrification Guinea Power 06.11.2013 30.12.2018 10,275,000 0
Assistance à l'OMVG- réalisation énergie Power 18.04.2007 31.12.2013 343,402.47 100
WAEMU appui à l'enseignement supérieur Social 24.07.2006 15.12.2014 20,000,000.00 55.82
Support to AUST & 2IE project Social 18.03.2009 15.12.2014 12,000,000.00 44.68
Railways loop Coto-Niam-Ouaga-Abid Transport 16.06.2013 31.12.2018 1,315,789.47 0
Port autonome de San Pedro Phase II Transport 27.12.2012 31.12.2017 852,686.76 0
WAEMU -Ghana -programme routier 1 Transport 19.11.2003 30.12.2013 62,680,078.37 91.48
WAEMU -Ghana -programme routier 1 Transport 19.11.2003 30.12.2013 3,500,000.00 74.46
Burkina-Faso facilitation corridor Transport 27.06.2012 31.12.2018 84,600,000.00 0
Togo – facilitation Transport 27.06.2012 31.12.2018 30,230,000.00 0
Togo – facilitation Transport 27.06.2012 31.12.2018 21,500,000.00 0
Projet d'amenagement de la route Labe-Se Transport 04.12.2006 31.12.2013 5,580,000.00 28.62
Projet d'amenagement de la route Labe-Se Transport 04.12.2006 31.12.2013 30,320,000.00 99.51
Programme d'amenagement routier et de fa Transport 21.12.2005 31.12.2013 56,213,265.19 100
Programme d'amenagement routier et de fa Transport 21.12.2005 30.06.2014 7,900,000.00 5.82
Programme d'amenagement routier et de fa Transport 31.03.2006 31.10.2014 5,980,190.62 0
Appui mise en place observ. Eau CEDEAO WAS 22.11.2013 31.12.2018 523,487.61 0
667,455,305 31
IX
Annex 6: Overview of Regional Operations Directly Managed by the RECs
Bank’s Active Portfolio at the ECOWAS Commission – March 2014
Bank’s Active Portfolio at the WAEMU Commission – March 2014
X
Annex 7: WA Regional Portfolio Improvement Plan
Identified
Problems
Problem’s
Sources
Recommended Actions Responsible Timeline
Very late start of
operations
managed by the
RECs (more than
two years on
average)
Low level of
maturity and weak
project ownership
by the RECs
Lack of capacity
in RECs
RECs have to be more
engaged in project
preparations
AfDB’s technicians to
strengthen local
support
Regular training on
Bank’s procedures for
staff at the RECs
Setting up and
operationalization of
dedicated units for
project implementation
at REC level
WAEMU,
ECOWAS,
OMVS, OMVG
BFFO, SNFO,
ORNG
FFCO, ORPF
WAEMU,
ECOWAS,
OMVS, OMVG
Ongoing
Dec. 2014
Sept. 2014
Ongoing
Weakness in
project
monitoring
Low frequency of
supervision
undertaken by the
AfDB
Inadequate
monitoring
mechanism at the
RECs
Transfer more project
management
responsibilities to
AfDB’s offices in the
countries
Conduct periodic
monitoring missions on
projects status
ORWA, ORNG
and Sector
Departments
WAEMU,
ECOWAS,
OMVS, OMVG
Dec. 2014
June 2014
Inadequate level
of communication
or exchange
between AfDB
and the RECs
Lack of regular
consultation
mechanism
between the
parties
Establish regular
(quarterly) meetings on
portfolio
implementation status
Share good practices
and experiences
between institutions
BFFO,ORNG,
SNFO +
WAEMU,
ECOWAS,OM
VS, OMVG)
RECs
Ongoing
Ongoing
Significant delays
in loans/grant
signature
Lack of proper
follow-up on
conditions of
signature and
effectiveness
Field Offices and RECs
to closely monitor on a
monthly basis status of
signature of loans or
grants
BFFO, ORNG,
SNFO
RECs
June 2014
XI
Annex 8: Consultative Process and Timeframe for the Preparation of the WA-
RISP MTR
The WA-RISP MTR Team was composed of ORWA/ORNG’s regional economists and country
portfolio officers, as well as of sector experts from ONRI, OWAS, OSAN, OPSM, ORSF and
OITC, who carried out the preparation mission.
The Bank has engaged in a close collaboration with the two major regional institutions, namely
ECOWAS and WAEMU, as well as with the Governments, DPs, private sector, civil society and
other relevant stakeholders to ensure a participatory approach in the assessment of the
implementation and performance of the WA-RISP. Discussions have evolved around the
effectiveness of this RISP and whether a strategic adjustment is recommended at the mid-term.
A preparation mission has included a major seminar in Abuja (ECOWAS Headquarters) with all
stakeholders on the strategic relevance and implementation of regional operations, as well as to
collect data and information required to prepare the full MTR report. The seminar was preceded by
a portfolio review varied by the field offices of Nigeria, Senegal, and Burkina Faso with key RECs.
Upon return from the preparation mission, the full MTR report was prepared and submitted for
review through the Bank’s internal review process
Activity Indicative Date
Submit RISP MTR CN to CT & Readiness Review 07 February 2014
Country Team Review of RISP MTR Concept Note 21 February 2014
Submit RISP MTR CN to VP 25 February 2014
VP Clearance of CN 04 March 2014
Mission/ Abuja workshop 16-20 March 2014
Drafting RISP MTR 21 March - 08
April 2014
ORWA Director Clearance 10 April 2014
Peer Review of RISP MTR 16 April 2014
Submit to CT 18 April 2014
Country Team Review of draft RISP MTR 29 April 2014
VP Clearance of RISP MTR 28 May 2014
RISP MTR submission to PRST 29 May 2014
Translation of RISP MTR (21 days) 30 May 2014
Submit to CODE (4 day lead) 18 June 2014
CODE LOTB 24 June 2014
XII
Annex 9: Conclusions of the Regional Dialogue Mission in Abuja, March 2014
REGIONAL CONSULTATION AND DIALOGUE WORKSHOP
17-18 March 2014
ABUJA, NIGERIA
Participants:
African Development Bank (AfDB), Economic Community Of West African States (ECOWAS),
Central Bank of West African States (BCEAO), Union Economique et Monétaire Ouest Africaine
(WEAMU), Comité Inter-Etat de Lutte Contre la Sècheresse au Sahel (CILLS), Mano River Union
(MRU), West African Power Pool (WAPP), Organisation pour la Mise en Valeur du fleuve
Gambie (OMVG). Organisation pour la Mise en Valeur du fleuve Sénégal (OMVS), West African
Monetary Institute (WAMI), Conseil Régional de l'Epargne Publique et des Marchés
Financiers (CREPMF), Economic and Statistical Observatory for Sub-Saharan Africa –
Observatoire économique et statistique d'Afrique subsaharienne(AFRISTAT), Organisation du
Corridor Abidjan-Lagos (OCAL). Borderless Alliance, Fédération des Organisations Patronales
de l'Afrique de l'Ouest (FOPAO), Institute for Security Studies (ISS), African Center for Economic
Transformation (ACET).
Highlight of discussions and key recommendations
The objective of the workshop was for the African Development Bank (AfDB or the Bank) to
present the current status of implementation of its regional integration strategy for West Africa
(2011-2015) to key regional stakeholders, as well as to gather recommendations from the
participants for the remaining period 2014/2015.
Following the welcome statement of Mr. DORE, Director of the Nigeria Department, AfDB and the
opening remarks of Mrs. TOURE, Representative of the WAEMU Commission, the regional
workshop was officially opened by H.E. OUEDRAOGO, President of the ECOWAS Commission.
The discussions focused on the regional strategies of the three major institutions present
(ECOWAS, WEAMU, AfDB), with a special attention to the interventions of the Bank in West
Africa. The participants shared their observations and comments during the AfDB mid-term review
of its West Africa Regional Integration Strategy.
The key recommendations are as follows:
Fragility in many of West Africa States (8 out of the 15 West African countries are fragile)
demonstrates that the challenge is both national and regional; responses to this challenge must
take into consideration and propose regional approaches that are adaptable to the national
context where need be. Furthermore, there is a clearer need to give a stronger focus on fragility
issues within the Bank’s strategy and interventions in the region, as well as to strengthen the
support to address various vulnerabilities.
A reference framework should be set up between ECOWAS and the Bank so as to enable more
transparent and deeper consultative process of regional project/operations identification. This
would help the Bank to have a well-defined outline of the RECs’ interests and priorities when
formulating and selecting projects.
Coordination mechanisms and alignment of procedures between the ECOWAS and the Bank
can be further improved and strengthened. As such, regional integration efforts are even more
valuable when supported by capacity building and knowledge transfer mechanisms.
XIII
ECOWAS has recognized the need to work closely with its Member States in the
implementation of regional integration reforms, which are agreed at ECOWAS level but lack
operationalization at national level.
The process of selection of Project Implementation Unit (PIU) staff for regional operations
should be further clarified to enable a common understanding of the role of the PIUs.
Harmonization of procedures of funding agencies and improved coordination among agencies is
critical for successful project implementation.
Regular consultations between the Bank and ECOWAS Commissioners and Directorates should
be held along thematic areas e.g. Infrastructure, private sector, agriculture, etc. Also, regular
joint portfolio review meetings and improved communication could enable a more coordinated
monitoring of project implementation and follow up.
Potential benefits from effective decentralization and delegation of responsibilities, including at
AfDB level, to enhance timely and adequate responses to project identification, implementation
and monitoring.
The Bank should review its own internal procedures with a view to simplify in particular the
conditions for first disbursement and granting of "no objection".
Deepen the support to private sector and cross-country collaboration among companies to
enable it to play a more prominent role in regional integration, trade facilitation, knowledge
transfer and financing.
Quality at entry and quality at exit of regional projects need to be monitored more closely, in
order to reduce the risks of delays and eligibility of abandon. For instance, regular consultations
between the Bank and the implementing partners have proven effective tools of monitoring.
Increase knowledge generation and sharing, including through the creation of a network of
research and effective engagement with ECOWAS macroeconomic policy and research
department.
Key areas were identified that need strengthened collaboration between the Bank and the RECs,
eg. free movement of persons, labor mobilization, statistics data sharing, alignment of
procedures and resources mobilization.
Capacity building has been highlighted as an area the Bank should emphasize, be it through
technical assistance, adequate trainings or support in the pipeline development (preparing,
promoting, and mobilizing funding for bankable projects).
Knowledge studies undertaken by the Bank are a valuable source of knowledge that should be
widely disseminated.
XIV
Annex 10: Original Indicative Results Matrix of the WA-RISP 2011-2015 Regional
integration
objectives
Constraints to achieving
regional integration
objectives
Final Outputs Final Outcomes Mid-term Outputs Mid-term outcomes Indicative program of new
operations (2011-2015) and
ongoing projects (expected at the end of RISP period in 2015) (expected at mid-term of RISP period in 2013)
Pillar I: Linking Regional Markets
Enhance the
linkage of
regional
markets,
creating an
open and
seamless
regional
market with
opportunitie
s for rapid
and
sustained
regional
growth, job
creation,
and poverty
reduction
(i) Investments in roads corridors and transport and trade facilitation
Poor and inadequate
national and regional
transport infrastructure;
Absence of maintenance
culture –dilapidated
transport infrastructure,
particularly roads.
Impediments to cross-
border transit.
Lomé-Cotonou (77.5 km) on the Abidjan-
Lagos Corridor rehabilitated by 2014;
410 km on the Lomé – Ouagadougou
Corridor rehabilitated by 2015;
Manantali-Tambanga (100 km) and
Babaroto-Mahina (6km) of the integrated
multimodal OMVS System rehabilitated
The Trans-Gambia bridge on the Dakar-
Lagos corridor is constructed by 2016
The Hillacondji joint border posts is
constructed by 2014;
Users of the rehabilitated corridors are
sensitized to trade facilitation measures
The Trans-Gambia joint border posts is
constructed by 2016
Support provided to regional training
programs & institutions for trade
facilitation and standards.
Creation of 1475 jobs in road
infrastructure development works (1250
and 225 jobs on the Lomé –
Ouagadougou and Lome-Cotonou
corridors works respectively)
Creation of about 200 jobs during
construction of the Trans-Gambia
Bridge by 2016.
Travel time on the Atakpame-Kara road
reduced from 12 days in 2011 to 8 days
in 2015
Travel time between Pahou –
Hillacondji on the Abidjan-Lagos
corridor road reduced from 115mn in
2010 to 55 mn in 2014
Transit time on the Trans-Gambian
Corridor reduced from 34mn before the
bridge to 1.5 in 2016 mn after the
bridge.
Construction works on the
Lomé-Cotonou, the Lomé
– Ouagadougou, and the
Trans-Gambia bridge
have Commenced and are
on-going
About 750 jobs
created in the road
infrastructure
development related
to Lomé-Cotonou,
the Lomé –
Ouagadougou, and
the Trans-Gambia
bridge works.
Rehabilitation and transport
facilitation of the Lomé-
Ouagadougou Corridor
Project
Rehabilitation of the Lomé-
Cotonou Road and transport
facilitation on the Abidjan-
Lagos Corridor Project
OMVS Integrated
Multimodal Transport
System Project
Trans-Gambia Bridge on the
Dakar - Lagos Corridor
Guinea-Guinea Bissau:
Boke-Quebo Road Project
Regionally unconnected
and inefficient railway
systems
Dialogue with stakeholders to ensure
timely completion of the on-going EU-
financed detailed engineering design
studies for the prioritized B2 and B1
links.
High-Level consultations held with
potential donors on investments in
railways in West Africa.
Progress on resource mobilization for
the railways sector in West Africa
Draft reports of the EU-
funded detailed
engineering design
studies available
Progress on
consultations with
donors for the
mobilization of
resources for the
railways sector
None
(ii) Regional energy production and markets integration
Deficiency in clean
energy supply;
Inadequate integration of
regional energy markets
Construction of the 240 MW
hydroelectric dam and plant at Kaléta in
Guinea (OMVG energy Project),
Construction of 1700 kilometers of high
tension transmission lines (OMVG
Project)
1360 km of 225 kV line interconnecting
Côte d’Ivoire, Liberia, Sierra Leone and
Guinea (CLSG) constructed in 2015
Construction of a 742 km transmission
line, three new substations, and extension
works for the 225 kV incoming and
outgoing transmission lines between
About 4400 and 1400 direct and indirect
jobs respectively are created during
construction phase of the OMVG energy
project, and 250 permanent jobs and 350
indirect jobs created during exploitation
of the plant from 2016
Average number of blackouts in the
OMVG countries reduced from 600 to
between 150 and 200 by 2016.
The costs of electricity reduced to Euro
11,5 cents by 2016 from Euro 15 cents
in 2016 in OMVG Countries
5000 jobs during implementation and
Construction works on the
OMVG, CLSG projects
Commenced and are on-
going.
About 2000 and 500
direct and indirect
jobs respectively are
created during
construction phase
of the OMVG
energy project,
5000 jobs created
during
implementation of
the CLSG Project
Côte d’Ivoire-Liberia-Sierra
Leone-Guinée,
Interconnexion Power
Project ;
OMVG energy program 1.
Gambia-Guinée-Guinéa-
Bissau-Senegal ; 2.
Hydroelectric sites at Kaleta
(240 MW) and
Sambangalou (128 MW) ;
Han (Ghana) – Bobo
Dioulasso (Burkina Faso) –
Sikasso (Mali) – Bamako
XV
Regional
integration
objectives
Constraints to achieving
regional integration
objectives
Final Outputs Final Outcomes Mid-term Outputs Mid-term outcomes Indicative program of new
operations (2011-2015) and
ongoing projects (expected at the end of RISP period in 2015) (expected at mid-term of RISP period in 2013)
Ghana-Burkina-Faso, and Mali. 450 permanent jobs after commissioning
of the CLSG Project
Electricity access rate in CLSG
increased from 9% in 2010 and 13% in
2015 on average
(Mali))- Interconnection
power project
Guinea-Mali –
Interconnexion Power
Project.
Pillar II: Capacity building for effective implementation of regional integration agenda
Strengthen
regional
capacity to
advance the
regional
integration
agenda
(i) Capacity building for financial sector integration
Inadequate capacity to
carry out the payments
systems integration
project of the WAMZ
Real Time Gross Settlement, Automated
Clearing House, Automated Check
Processing, and Scriptless Securities
settlement systems installed in the
Gambia, Guinea, Liberia, and Sierra-
Leone to support financial and monetary
integration in the WAMZ.
Progress on financial and monetary
integration within WAMZ as measured
by:
Same day funds transfers within WAMZ
achieved.
Volume of high value funds transfers in
the Gambia, Guinea, Liberia, and
Sierra-Leone increases by 45% from
2007 level
Installation of the Real
Time Gross Settlement,
Automated Clearing
House, Automated Check
Processing, and Scriptless
Securities Settlement
systems, in the Gambia,
Guinea, Liberia, and
Sierra-Leone about 90%
complete.
Not applicable. WAMZ Payment System
Development Project (the
Gambia, Guinea, Liberia,
and Sierra Leone).
(ii) Capacity building for effective policy and regional projects implementation of
Slow process of
development and
implementation of
regional energy projects
Capacity building provided to the
WAPP in the context of the CLSG
interconnection project
Efficient implementation of the WAPP
priority projects
Training and consultancy
services provided to
WAPP
Improvement in
implementation of
WAPP priority
projects
Côte d’Ivoire-Liberia-Sierra
Leone-Guinée,
Interconnexion Power
Project.
(iii) Support to Regional Centers of Excellence
Weak regional capacity
to undertake research
and copy/adapt/develop
science and technology;
Absence of regional
SPS standards;
Lack of harmonized
regional systems;
Skills shortage for
implementation of
regional projects.
Support provided to strengthen
ECOWAS identified centers of
excellence.
Use of science and technology to
develop other sectors, social
infrastructure, industry, environment
and climate change, makes progress in
ECOWAS;
Strengthened culture of science and
technology in the region;
Agents of regional integration trained
with shared approach on integration;
Enhanced capacity in technological
skills for economic transformation.
Idem as final outputs. Idem as final
outcomes.
Regional Centres of
Excellence dealing with
infrastructure and public
governance.
(iv) Statistical support to ECOWAS Institutions
Weak institutional
structure and capacity in
West Africa to meet the
regional statistical
responsibilities.
Support provided to national and
regional statistical structures in line with
the Bank Group’s Program for Building
Statistical Capacity in RMCs.
See Bank Group’s Program for Building
Statistical Capacity in RMCs.
Bank Group’s Program
for Building Statistical
Capacity in RMCs.
Bank Group’s
Program for
Building Statistical
Capacity in RMCs
Bank Group’s Program for
Building Statistical
Capacity in RMCs.
XVI
Annex 11: Revised Indicative Results Matrix of the WA-RISP 2011-2015 at MTR Regional
integration
objectives
Constraints to achieving
regional integration
objectives
Final Outputs Final Outcomes Mid-term Outputs Mid-term outcomes Indicative program of new
operations (2011-2015)
and ongoing projects (expected at the end of RISP period in 2015) (expected at mid-term of RISP period in 2013)
Pillar I: Regional Infrastructure Development
Enhance the
linkage of
regional
markets,
creating an
open and
seamless
regional
market with
opportunitie
s for rapid
and
sustained
inclusive
regional
growth,
equitable
job
creation,
and poverty
reduction
(iii) Investments in roads corridors and transport and trade facilitation
Poor and inadequate
national and regional
transport infrastructure;
Absence of maintenance
culture –dilapidated
transport infrastructure,
particularly roads.
Impediments to cross-
border transit.
Lomé-Cotonou (77.5 km) on
the Abidjan-Lagos Corridor
rehabilitated by 2014;
410 km on the Lomé –
Ouagadougou Corridor
rehabilitated by 2015;
Manantali-Tambanga (100
km) and Babaroto-Mahina
(6km) of the integrated
multimodal OMVS System
rehabilitated
The Trans-Gambia bridge on
the Dakar-Lagos corridor is
constructed by 2016
The Hillacondji joint border
posts is constructed by 2014;
Users of the rehabilitated
corridors are sensitized to
trade facilitation measures
The Trans-Gambia joint
border posts is constructed by
2016
The Trans-Saharan road
works and related works in
Chad and Niger are under
construction (new)
Support provided to regional
training programs &
institutions for trade
facilitation and standards.
Creation of 1475 jobs in road
infrastructure development works
(1250 and 225 jobs on the Lomé –
Ouagadougou and Lome-Cotonou
corridors works respectively)
Creation of about 200 jobs during
construction of the Trans-Gambia
Bridge by 2016.
Travel time on the Atakpame-Kara
road reduced from 12 days in 2011
to 8 days in 2015
Travel time between Pahou –
Hillacondji on the Abidjan-Lagos
corridor road reduced from 115mn
in 2010 to 55 mn in 2014
Transit time on the Trans-Gambian
Corridor reduced from 34mn before
the bridge to 1.5 in 2016 mn after
the bridge.
By 2018: Increase of traffic at land
borders (87% between
Algeria/Niger and 375% between
Niger/Chad)
By 2018: Reduction of travel time
along the Trans-Saharan road from
2 days to 3.5 hours
(Assamakka/Arlit) and from 5 days
to 5.5 hours (Niger
border/Ndjamena)
By 2018: Creation of about 75,000
person/days (20% by women and %
by young people) (new)
Construction works
on the Lomé-
Cotonou, the Lomé –
Ouagadougou, and
the Trans-Gambia
bridge have
Commenced and are
on-going
About 750 jobs created
in the road
infrastructure
development related to
Lomé-Cotonou, the
Lomé – Ouagadougou,
and the Trans-Gambia
bridge works.
Rehabilitation and
transport facilitation of
the Lomé-Ouagadougou
Corridor Project
Rehabilitation of the
Lomé-Cotonou Road and
transport facilitation on
the Abidjan-Lagos
Corridor Project
OMVS Integrated
Multimodal Transport
System Project
Trans-Gambia Bridge on
the Dakar - Lagos
Corridor
Guinea-Guinea Bissau:
Boke-Quebo Road Project
Trans-Saharan Road
(Chad, Niger, Algeria)
Regionally unconnected
and inefficient railway
systems
Dialogue with stakeholders to
ensure timely completion of
the on-going EU-financed
detailed engineering design
studies for the prioritized B2
and B1 links.
High-Level consultations held
Progress on resource mobilization
for the railways sector in West
Africa
Draft reports of the
EU-funded detailed
engineering design
studies available
Progress on
consultations with
donors for the
mobilization of
resources for the
railways sector
None
XVII
Regional
integration
objectives
Constraints to achieving
regional integration
objectives
Final Outputs Final Outcomes Mid-term Outputs Mid-term outcomes Indicative program of new
operations (2011-2015)
and ongoing projects (expected at the end of RISP period in 2015) (expected at mid-term of RISP period in 2013)
with potential donors on
investments in railways in
West Africa.
(iv) Regional energy production and markets integration
Deficiency in clean energy
supply;
Inadequate integration of
regional energy markets
Construction of the 240 MW
hydroelectric dam and plant at
Kaléta in Guinea (OMVG
energy Project),
Construction of 1700
kilometers of high tension
transmission lines (OMVG
Project)
1360 km of 225 kV line
interconnecting Côte d’Ivoire,
Liberia, Sierra Leone and
Guinea (CLSG) constructed in
2015
Construction of a 742 km
transmission line, three new
substations, and extension
works for the 225 kV
incoming and outgoing
transmission lines between
Ghana-Burkina-Faso, and
Mali..
About 4400 and 1400 direct and
indirect jobs respectively are
created during construction phase
of the OMVG energy project, and
250 permanent jobs and 350
indirect jobs created during
exploitation of the plant from 2016
(% of jobs created for women and
young people)
Average number of blackouts in the
OMVG countries reduced from 600
to between 150 and 200 by 2016.
The costs of electricity reduced to
Euro 11,5 cents by 2016 from Euro
15 cents in 2016 in OMVG
Countries
5000 jobs during implementation
and 450 permanent jobs after
commissioning of the CLSG
Project
Electricity access rate in CLSG
increased from 9% in 2010 and
13% in 2015 on average
Construction works
on the OMVG,
CLSG projects
Commenced and are
on-going.
About 2000 and 500
direct and indirect jobs
respectively are
created during
construction phase of
the OMVG energy
project,
5000 jobs created
during implementation
of the CLSG Project
Côte d’Ivoire-Liberia-
Sierra Leone-Guinée,
Interconnexion Power
Project ;
OMVG energy program
1. Gambia-Guinée-
Guinéa-Bissau-Senegal ;
2. Hydroelectric sites at
Kaleta (240 MW) and
Sambangalou (128 MW) ;
Han (Ghana) – Bobo
Dioulasso (Burkina Faso)
– Sikasso (Mali) –
Bamako (Mali))-
Interconnection power
project
Guinea-Mali –
Interconnexion Power
Project.
Pillar II: Capacity building for effective implementation of regional integration agenda
Strengthen
regional
capacity to
advance the
regional
integration
agenda
(v) Capacity building for financial sector integration
Inadequate capacity to
carry out the payments
systems integration project
of the WAMZ
Real Time Gross Settlement,
Automated Clearing House,
Automated Check Processing,
and Scriptless Securities
settlement systems installed in
the Gambia, Guinea, Liberia,
and Sierra-Leone to support
financial and monetary
integration in the WAMZ.
Progress on financial and monetary
integration within WAMZ as
measured by:
Same day funds transfers within
WAMZ achieved.
Volume of high value funds
transfers in the Gambia, Guinea,
Liberia, and Sierra-Leone increases
by 45% from 2007 level
Installation of the
Real Time Gross
Settlement,
Automated Clearing
House, Automated
Check Processing,
and Scriptless
Securities
Settlement systems,
in the Gambia,
Guinea, Liberia, and
Sierra-Leone about
90% complete.
Not applicable. WAMZ Payment System
Development Project (the
Gambia, Guinea, Liberia,
and Sierra Leone).
XVIII
Regional
integration
objectives
Constraints to achieving
regional integration
objectives
Final Outputs Final Outcomes Mid-term Outputs Mid-term outcomes Indicative program of new
operations (2011-2015)
and ongoing projects (expected at the end of RISP period in 2015) (expected at mid-term of RISP period in 2013)
(vi) Capacity building for effective policy and regional projects implementation of
Slow process of
development and
implementation of regional
energy projects
Capacity building provided to
the WAPP in the context of
the CLSG interconnection
project
Efficient implementation of the
WAPP priority projects
Training and
consultancy services
provided to WAPP
Improvement in
implementation of
WAPP priority
projects
Côte d’Ivoire-Liberia-
Sierra Leone-Guinée,
Interconnexion Power
Project.
(vii) Support to Regional Centers of Excellence
Weak regional capacity to
undertake research and
copy/adapt/develop
science and technology;
Absence of regional SPS
standards;
Lack of harmonized
regional systems;
Skills shortage for
implementation of regional
projects.
Support provided to
strengthen ECOWAS
identified centers of
excellence.
Use of science and technology to
develop other sectors, social
infrastructure, industry,
environment and climate change,
makes progress in ECOWAS;
Strengthened culture of science and
technology in the region;
Agents of regional integration
trained with shared approach on
integration;
Enhanced capacity in technological
skills for economic transformation.
Idem as final
outputs.
Idem as final
outcomes.
Regional Centres of
Excellence dealing with
infrastructure and public
governance.
(viii) Statistical support to ECOWAS Institutions
Weak institutional
structure and capacity in
West Africa to meet the
regional statistical
responsibilities.
Weak sex and age
disaggregated data
collection system/capacity
Support provided to national
and regional statistical
structures in line with the
Bank Group’s Program for
Building Statistical Capacity
in RMCs.
See Bank Group’s Program for
Building Statistical Capacity in
RMCs.
Bank Group’s
Program for
Building Statistical
Capacity in RMCs.
Bank Group’s
Program for Building
Statistical Capacity in
RMCs
Bank Group’s Program
for Building Statistical
Capacity in RMCs.
XIX
Annex 12: Alignment Between CSP And WA-RISP Pillars
Co
un
try
CSP Pillars
RISP RI-
related
national
portfolio
projects
Pillar 1 Pillar 2
Infrastructure
development
Capacity
building
Ben
in
(20
12
-201
6)
Pillar 1: Production and Competitiveness Support Infrastructure: (i) the
development of agricultural production infrastructure (ii) infrastructure
consolidation to boost competitiveness and ensure greater integration
4/12 Pillar 2: Enhancement of Good Governance: (i) the improvement of public
resource mobilisation; (ii) consolidation of public expenditure efficiency (iii)
capacity-building to ensure adequate implementation of policies on gender
promotion and adaptation to climate change; and (iv) improvement of the business
environment
Bu
rkin
a F
aso
(20
12
-201
6)
Pillar 1: Developing infrastructure and trade facilitation, strengthening the
competitiveness of the private sector as an engine of growth
3/15 Pillar 2: Strengthening the fiduciary framework and management of public
finances, improving the business environment and private sector development,
strengthening macroeconomic reform, developing promising sectors, and raising
the level of inclusion of public policies for solidarity
Cab
o V
erd
e
(20
14
-201
8)
Pillar 1: Enhancing and Diversifying Infrastructure for Sustainable Development.
(sea ports construction and rehabilitation, strengthening the electricity production
and network, supporting investments in renewable energy)
2/8 Pillar 2: Strengthening Economic Governance in the Public and Private Sectors
(enhancing the overall business and investment climate, promoting public
investment program prioritization and rationalization, improving and modernizing
the management and operations of state-owned enterprises (SOEs)
Cô
te d
’Iv
oir
e
(20
13
-201
7)
Pillar 1: Strengthening Governance and Accountability (creating an environment
that will foster socio-economic inclusion and address demands for improved
governance)
2/10 Pillar 2: Infrastructure Development in support of Economic Recovery (promote
the optimal use of natural resources through the development of high quality
infrastructure in the agriculture, transport and energy sectors, in order to bolster
economic recovery)
Gam
bia
(20
12
-
20
15)
Pillar 1: Enhancing Productive Capacity and Competitiveness in order to
Strengthen Resilience to External Shocks
2/8 Pillar 2: Strengthening the Institutional Capacity for Economic Governance and
Public Service Delivery
Gh
ana
(20
12
-20
16
) Pillar 1: Improving productivity in Ghanaian enterprises and in particular in the
micro, small and medium agribusiness firms. (investing in infrastructure that
supports the growth and development of the private sector and improving skills,
thereby supporting government’s efforts towards strengthening the productive
environment in Ghanaian enterprises)
7/22
Pillar 2: Supporting economic and structural reforms aimed at improving the
business environment (supporting key economic policy-oriented and oversight
institutions)
Gu
inea
(20
12
-201
6) Pillar 1: economic and financial governance (building public finance management
capacity, improving governance in the extractive sector and strengthening the
central government’s budget)
1/7
Pillar 2: development supportive infrastructure (reducing the power generation
gap and developing transport infrastructure )
Gu
ine
a-
Bis
sa
u
(20
14
-
20
18) Pillar 1: Strengthening institutional capabilities and governance (institutional
support; targeted budget support; business climate)
0/9
XX
Pillar 2: Support infrastructure for the internal and external opening up of the
country (including transport and energy)
Lib
eria
(20
13
-201
7)
Pillar 1: Promoting inclusive economic growth through transformative
infrastructure investments (focusing on energy and road infrastructure, promoting a
competitive private sector, agricultural production and
market access, employment creation across age and gender, welfare and public
service delivery)
3/13
Pillar 2: Enhancing governance and the efficient management of resources
Mal
i (T
ran
siti
on
Su
pp
ort
20
13
-14) Outcome 1: Mitigate the impact of the crisis and strengthen the resilience of the
population
3/12 Outcome 2: Consolidate the State's stability and the foundations for economic
recovery
Nig
er
(20
13
-201
7)
Pillar 1: strengthening resilience to food insecurity (by supporting the
development of anchor infrastructure focusing on water control and management,
transport, and energy)
3/18 Pillar 2: strengthening governance, particularly of natural resources (strengthening
the governance framework to enable the country to take full advantage of its
natural resources, ensure sustainable exploitation of these resources, promote and
maintain macroeconomic stability and create an enabling environment for private
investment)
Nig
eria
(20
13
-201
7) Pillar 1: Supporting the Development of a Sound Policy Environment
8/29 Pillar 2: Investing in Critical Infrastructure to Promote the Development of the
Real Sector of the Economy
Sen
egal
(20
10
-
20
15
) –
rev
iew
ed
in 2
012
Pillar 1: support for inclusive growth through diversification and economic
integration
3/9 Pillar 2: sustainable management of natural resources (including water) and
resilience.
Sie
rra
Leo
ne
(20
13
-201
7)
Pillar 1: Enhancing Economic Governance and Transparent Management of
Natural Resources Revenue (promote the transparent management of natural
resource revenues)
1/10 Pillar 2: Supporting Transformational and Sustainable Infrastructure Development
(in energy, roads and water will facilitate inclusive green growth, foster regional
integration and enhance private sector development and competitiveness)
To
go
(20
11
-201
5)
Pillar 1: development of economic infrastructure capable of effectively connecting
the economic zones within Togo, and connecting the Togolese economy to the
regional economic space
1/6 Pillar 2: the promotion of economic and financial governance reforms