Royal Institute of Technology Stockholm, April 8th 2014
Dr. Alvaro Guarin Highway and Railway Engineering Department of Transportation Science
AF2903 Road Construction and Maintenance Design of Asphalt Mixtures
![Page 2: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/2.jpg)
Hot Mix Asphalt Design
Objective: Develop an economical blend of aggregates and asphalt that meet design requirements
Most important mix design methods
• Marshall • Superpave
![Page 3: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/3.jpg)
Requirements in Common
• Sufficient asphalt to ensure durability
• Sufficient stability under traffic loads
• Sufficient air voids Lower limit to allow room for initial densification due to traffic (bleeding)
Upper limit to prevent excessive environmental damage (aging)
• Sufficient workability
![Page 5: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/5.jpg)
Marshall Mix Design
Developed by Bruce Marshall for the Mississippi Highway Department in the late 30’s
Evaluated compaction effort Hammer weight: 10 lb 50 blows/side as an initial standard 4% voids after traffic
Initial criteria were established and upgraded for increased tire pressures and loads
![Page 7: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/7.jpg)
Marshall Mix Design
Select and test aggregate Select and test asphalt cement
Establish mixing and compaction temperatures Develop trial blends
Heat and mix asphalt cement and aggregates Compact specimen (100 mm diameter)
![Page 8: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/8.jpg)
•Temperature, C
•Viscosity, Pa s
Mixing/Compaction Temperatures
.1
.2
.3
.5
1
10 5
100 110 120 130 140 150 160 170 180 190 200
Temperature, C
Viscosity, Pa s
Compaction Range
Mixing Range
![Page 9: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/9.jpg)
Marshall Design Criteria
Light Traffic Medium Traffic Heavy Traffic ESAL < 104 10 4 < ESAL< 10 ESAL > 106
Compaction 35 50 75 Stability N (lb.) 3336 (750) 5338 (1200) 8006 (1800) Flow, 0.25 mm (0.1 in) 8 to 18 8 to 16 8 to 14 Air Voids, % 3 to 5 3 to 5 3 to 5 Voids in Mineral Agg. (VMA) Varies with aggregate size
![Page 10: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/10.jpg)
Marshall Mix Design Tests
Bulk specific gravity of compacted sample Maximum specific gravity of loose mix Stability and flow
60oC water bath (30 to 40 minutes) 50 mm/min loading rate Max. load = uncorrected stability Corresponding vertical deformation = flow
![Page 12: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/12.jpg)
Marshall Design / Asphalt Institute Procedure
Air Voids, %
Asphalt Content, %
Stability
Asphalt Content, %
Gmb
Asphalt Content, %
Target optimum asphalt content = average
4%
![Page 13: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/13.jpg)
Flow
Asphalt Content, %
VMA, %
Asphalt Content, %
Use target optimum asphalt content to check if these criteria are met
Lower Limit
Upper limit
Minimum
OK OK
Marshall Design / Asphalt Institute Procedure
![Page 14: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/14.jpg)
Marshall Design Method
Advantages
Attention on voids, strength, durability Inexpensive equipment Easy to use in process control/acceptance
Disadvantages Impact method of compaction Does not consider shear strength Load perpendicular to compaction axis
![Page 16: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/16.jpg)
Section objectives:
– Describe the Superpave gyratory compactor – Review the Superpave mixture requirements – Summarize the moisture sensitivity test
Gyratory Compaction and Mixture Requirements
![Page 17: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/17.jpg)
Four Steps of Superpave Mix Design
1. Materials Selection 2. Design Aggregate Structure
3. Design Binder Content 4. Moisture Sensitivity
TSR
![Page 18: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/18.jpg)
Simulate field densification Traffic Climate
Accommodate large aggregates Measure of compactability Conducive to QC
Goals of Compaction
![Page 19: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/19.jpg)
Basis
Texas equipment French operational characteristics
150 mm diameter Up to 37.5 mm nominal size Height recordation
Superpave Gyratory Compactor (SGC)
?
?
?
![Page 20: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/20.jpg)
reaction frame
rotating base
loading ram
control and data acquisition panel
mold
height measurement
tilt bar
Superpave Gyratory Compactor (SGC)
![Page 21: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/21.jpg)
150 mm diameter mold
ram pressure 600 kPa
1.25 degrees (external)
30 gyrations per minute
Superpave Gyratory Compactor (SGC)
![Page 23: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/23.jpg)
Specimen Preparation
Mechanical mixer 0.170 Pa-s binder viscosity
Short term oven aging
4 hours at 135°C 2 hours at Compaction Temperature (optional)
![Page 24: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/24.jpg)
Specimen height
Mix design - 115 ± 5 mm (4700 g) Moisture sens. - 95 mm (3500 g)
Loose specimen for max. theor. (Rice)
Varies with nominal max size 19 mm (2000 g) 12.5 mm (1500 g) 150 mm
Specimen Preparation
![Page 28: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/28.jpg)
% Gmm
Log Gyrations
10 100 1000
Nini
Ndes
Nmax
Three Points on SGC Curve
During Design: Compact to Ndes to get opt. Compact to Nmax to check
Log Nmax = 1.10 Log Ndes Log Nini = 0.45 Log Ndes
Ni: measure of mixture compactability during compaction Ndes: expected density in the field after the indicated amount of traffic Nmax: laboratory density that should never be exceeded in the field
![Page 29: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/29.jpg)
Nini, Ndes, and Nmax
Traffic
Level initial design maximum
< 0.3 6 50 75
0.3 to < 3.0 7 75 115
3.0 to 30.0 8 100 160
9 125 205
Traffic
Level
Compaction Level
N initial N design N maximum
< 0.3 6 50 75
0.3 to < 3.0 7 75 115
8 100 160
> 30.00 125 205
![Page 30: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/30.jpg)
Superpave Mixture Requirements
Mixture Volumetrics
Air Voids (Va) Voids in the Mineral Aggregate (VMA) Voids Filled with Asphalt (VFA) Mixture Density Characteristics
Dust Proportion Moisture Sensitivity
![Page 31: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/31.jpg)
Mix Air Voids Requirement
% binder
air voids
4 % at Ndes Regardless of
the Traffic Level
![Page 32: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/32.jpg)
VMA Requirements
9.5 15.0 12.5 14.0 19 13.0
25 12.0 37.5 11.0
Nom Max Size (mm)
Minimum VMA %
% binder
VMA
![Page 33: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/33.jpg)
VFA Requirements
< 0.3 70 – 80 0.3 to < 3 65 – 7
3.0 to < 30 65 – 75 > 30 65 - 75
Traffic 106 ESALs
Range of VFA %
% binder
VFA
![Page 34: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/34.jpg)
Log Gyrations
84
86
88
90
92
94
96
98
100
% Gmm
Limit for Nini
Limit for Nmax
Nmax Nini
Mixture Density
![Page 35: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/35.jpg)
% Gmm
Log Gyrations
10 100 1000
weak aggr structure
strong aggr structure
Evaluate Aggregate Structure
![Page 36: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/36.jpg)
Dust Proportion
100 100 92 83 65 48 36 22 15 9 4
% weight of - 0.075 material % weight of effective asphalt
0.6 < < 1.2
Unabsorbed binder in mix
![Page 37: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/37.jpg)
Moisture Sensitivity AASHTO T 283
Measured on proposed aggregate blend and asphalt content
80 % minimum
3 Conditioned Specimens
3 Dry Specimens Tensile Strength Ratio
![Page 38: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/38.jpg)
AASHTO T 283 Conditioning
• Short term aging
– Loose mix 16 hrs @ 60°C – Comp mix 72-96 hrs @ 25°C
• Two subsets with equal voids
– One “dry” – One saturated
Dry
6 to 8 % air
6 to 8 % air
55 to 80 % saturation
![Page 39: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/39.jpg)
AASHTO T 283 Conditioning
Optional freeze cycle Hot water soak
16 hours @ -18 oC
24 hours @ 60 oC
![Page 40: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/40.jpg)
AASHTO T 283 Test Procedure
TSR = ≥ 80 % Wet
Dry
51 mm / min @ 25 oC
Avg Dry Tensile Strength Avg Wet Tensile Strength
![Page 41: AF2903 Road Construction and Maintenance Design of … · AF2903 Road Construction and Maintenance . ... 50 blows/side as an initial standard . ... Moisture Sensitivity AASHTO T 283](https://reader031.fdocuments.in/reader031/viewer/2022013113/5b53669d7f8b9add3a8bcb46/html5/thumbnails/41.jpg)
% binder
VMA
% binder
VFA
% binder
%Gmm at Nini
% binder
%Gmm at Nmax
% binder
DP
% binder
Va
Aggregate gradation
Selection of Design Asphalt Binder Content