Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

download Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

of 9

Transcript of Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    1/9

    Weight CU. PLN % CU. ACT % Variance%

    100.00% 31.64% 33.21% 1.58%

    COMMON ACTIVITIES 3.00% 3.00% 3.00% 0.00%

    DOCUMENTATION 3.00% 3.00% 3.00% 0.00%

    PROCUREMENT 12.00% 12.00% 11.86% -0.14%

    OFFLINE ACTIVITIES 11.00% 10.03% 10.29% 0.26%

    PRESHUTDOWN ACTIVITIES 15.00% 3.60% 5.06% 1.45%

    SHUTDOWN 20.00%

    6 ACTIVITIES BY IMS 30.01%

    101 2 SAFETY WALKTHROUGH 2.00%

    5 PR OJECT CLOSEOUT 4.00%

    4

    3 1

    Engineering & Construction

    EXECUTIVE SUMMARY

    PROCUREMENT

    In-Direct 7-Sand Blasting and application of Primer for Fabricated Materials

    -Termination works for FO Cable will be done by EEC and P.O was raised.2 15m FO cable will be provided by EEC.

    -Safety Sign board P.O placed and will be delivered on 4th April.

    was done. See attached photo. Direct 28

    Project S-Curve

    DAILY PROGRESS REPORT

    Dated : April 2, 2016

    23-Apr-16

    Incident Report 0 TOTAL PROGRESS

    Near Miss 0 Project

    Target Date

    TOTALOVERALL PROGRESS

    Observation 0

    TotalManpower Status

    UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES HD) AF-1421074)

    Safety Officer 1

    Admin & Support

    PROGRESS IN REPORTING DAY: Apr 1 2016

    EHSS AS OF: Apr 1 2016 D - 34

    Docs Submitted to PRO/ISD:

    Total ID' s Received : Docs t o submi t to E&PM:ID STATUS

    Docs Submitted to PRO/ISD:Vehicle StatusSticker Received: Waiting for Mgr Signature

    Documents Reject:

    60.00%

    80.00%

    100.00%

    120.00%

    3.00%

    4.00%

    5.00%

    6.00%

    Daily Plan

    Daily Actual

    Cumulative Plan

    Cumulative Actual

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    2/9

    PROCUREMENT

    Figure 1 . Tube for Camera Figure 2. Tube for Projector

    UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES HD) AF-1421074)

    ATTACHMENT

    Dated : April 2, 2016

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    3/9

    Date:

    Activity ID Activity NameOriginalDuration

    Planned Start Planned FinishBudgeted

    LaborUnits

    Weight EarnedActivityStatus

    TodaysActivity %

    Cum.Activitys

    %

    Prev.Activity

    %AF-1421074 UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS MEASUREMENT GAUGE 655h 2/28/16 7:00 AM 4/23/16 5:00 PM 24090 100.00% 33.21% COMMON ACTIVITIES 244h 2/28/16 7:00 AM 3/24/16 8:00 AM 723 3.00% 3.00% MOBILIZATION 40h 3/20/16 4:00 PM 3/24/16 8:00 AM 200 0.83% 0.83% A1440 Mobilization of Manpower, Equipment & Materials 40h 3/20/16 4:00 PM 3/24/16 8:00 AM 200 0.83% 0.83% Finished 100.00% 100.00% SAFETY ORIENTATION & ID 144h 3/6/16 7:00 AM 3/20/16 4:00 PM 100 0.42% 0.42% A1020 Safety Program , Orientation and ID Preparation 144h 3/6/16 7:00 AM 3/20/16 4:00 PM 100 0.42% 0.42% Finished 100.00% 100.00% MATERIAL RECEIVING 26h 3/20/16 12:00 PM 3/22/16 2:00 PM 223 0.93% 0.93% A3930 Material Receiving Inspection for Free Issued Items 10h 3/20/16 12:00 PM 3/21/16 10:00 AM 60 0.25% 0.25% Finished 100.00% 100.00% A3910 Material Receiving Inspection for Structural Materials 10h 3/20/16 4:00 PM 3/21/16 2:00 PM 83 0.34% 0.34% Finished 100.00% 100.00% A3920 Material Receiving Inspection for Electrical Materials 10h 3/21/16 4:00 PM 3/22/16 2:00 PM 80 0.33% 0.33% Finished 100.00% 100.00% GENERAL ACTIVITIES 112h 2/28/16 7:00 AM 3/12/16 8:00 AM 200 0.83% 0.83% A1000 Award of P.O 10h 2/28/16 7:00 AM 2/28/16 5:00 PM 60 0.25% 0.25% Finished 100.00% 100.00% A3840 Kick-off Meeting 8h 3/6/16 7:00 AM 3/6/16 3:00 PM 60 0.25% 0.25% Finished 100.00% 100.00% A1010 Site Visit 24h 3/8/16 3:00 PM 3/12/16 8:00 AM 80 0.33% 0.33% Finished 100.00% 100.00%

    DOCUMENTATION 150h 2/29/16 7:00 AM 3/16/16 8:00 AM 723 3.00% 3.00% A1030 Safety Plan 96h 2/29/16 7:00 AM 3/10/16 1:00 PM 120 0.50% 0.50% Finished 100.00% 100.00% A1050 Project Quality Plan 150h 2/29/16 7:00 AM 3/16/16 8:00 AM 200 0.83% 0.83% Finished 100.00% 100.00% A1060 Work Method Statement 120h 2/29/16 7:00 AM 3/13/16 2:00 PM 120 0.50% 0.50% Finished 100.00% 100.00% A1070 All documents and Material Approvals 70h 3/9/16 7:00 AM 3/16/16 8:00 AM 283 1.17% 1.17% Finished 100.00% 100.00% PROCUREMENT 192h 3/8/16 11:00 AM 3/27/16 4:00 PM 2891 12.00% 11.86% STRUCTURAL 192h 3/8/16 11:00 AM 3/27/16 4:00 PM 1020 4.23% 4.23% A2350 Beams 108h 3/8/16 11:00 AM 3/19/16 4:00 PM 300 1.25% 1.25% Finished 100.00% 100.00% A2360 Plates 120h 3/8/16 11:00 AM 3/20/16 4:00 PM 320 1.33% 1.33% Finished 100.00% 100.00% A2390 Channels 120h 3/8/16 11:00 AM 3/20/16 4:00 PM 200 0.83% 0.83% Finished 100.00% 100.00% A2400 Bolts 192h 3/8/16 11:00 AM 3/27/16 4:00 PM 200 0.83% 0.83% Finished 15.00% 100.00% 85.00% PIPING 144h 3/13/16 4:00 PM 3/27/16 4:00 PM 671 2.79% 2.65% A4250 Tube 144h 3/13/16 4:00 PM 3/27/16 4:00 PM 120 0.50% 0.47% On-going 15.00% 9 5. 00 % 80 .0 0% A4260 Fittings 144h 3/13/16 4:00 PM 3/27/16 4:00 PM 151 0.63% 0.60% On-going 15.00% 9 5. 00 % 80 .0 0%

    A4270 Pipe Bend 144h 3/13/16 4:00 PM 3/27/16 4:00 PM 200 0.83% 0.79% On-going 15.00%

    9 5. 00 % 80 .0 0% A4280 Hose Nozzle 144h 3/13/16 4:00 PM 3/27/16 4:00 PM 200 0.83% 0.79% On-going 15.00% 9 5. 00 % 80 .0 0% ELECTRICAL 132h 3/8/16 11:00 AM 3/21/16 4:00 PM 600 2.49% 2.49% A2410 GI Conduits 130h 3/8/16 11:00 AM 3/21/16 2:00 PM 300 1.25% 1.25% Finished 100.00% 100.00% A2430 Electrical Consumables 132h 3/8/16 11:00 AM 3/21/16 4:00 PM 300 1.25% 1.25% Finished 100.00% 100.00% FREE ISSUED ITEMS 40h 3/16/16 8:00 AM 3/20/16 12:00 PM 600 2.49% 2.49% A2370 Withdrawal of Free Issued Items from IMS 30h 3/16/16 8:00 AM 3/19/16 2:00 PM 300 1.25% 1.25% Finished 100.00% 100.00% A2380 QC Inspection 10h 3/19/16 2:00 PM 3/20/16 12:00 PM 300 1.25% 1.25% Finished 100.00% 100.00% CONSTRUCTION 381h 3/15/16 8:00 AM 4/12/16 3:00 PM 11081 46.00% 15.35% OFFLINE ACTIVITIES 242h 3/15/16 8:00 AM 4/6/16 7:00 AM 2650 11.00% 10.29% FABRICATION WORKS 119h 3/24/16 4:00 PM 4/4/16 5:00 PM 1370 5.69% 5.09% PROJECTOR FRAME 79h 3/24/16 4:00 PM 4/1/16 12:00 PM 276 1.15% 1.01% A3230 Cutting of Beams 10h 3/24/16 4:00 PM 3/26/16 2:00 PM 50 0.21% 0.21% Finished 100.00% 100.00% A3240 Fit-Up 10h 3/24/16 4:00 PM 3/26/16 2:00 PM 60 0.25% 0.25% Finished 100.00% 100.00% A3250 QC Inspection 10h 3/26/16 2:00 PM 3/27/16 12:00 PM 20 0.08% 0.08% Finished 100.00% 100.00%

    A3260 Full Weld 11h 3/27/16 12:00 PM 3/28/16 11:00 AM 55 0 23% 0 23% Finished 100 00% 100 00%

    Report # 9 WEEKLY PROGRESS REPORT

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD

    UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES (HD)(AF-1421074)

    April 2, 2016

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    4/9

    Date:

    Activity ID Activity NameOriginalDuration

    Planned Start Planned FinishBudgeted

    LaborUnits

    Weight EarnedActivityStatus

    TodaysActivity %

    Cum.Activitys

    %

    Prev.Activity

    %AF-1421074 UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS MEASUREMENT GAUGE 655h 2/28/16 7:00 AM 4/23/16 5:00 PM 24090 100.00% 33.21%

    Report # 9 WEEKLY PROGRESS REPORT

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD

    UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES (HD)(AF-1421074)

    April 2, 2016

    A2580 Disassemble of Existing cable and blowers 12h 3/30/16 6:00 AM 3/30/16 6:00 PM 90 0.37% 0.37% Finished 100.00% 100.00% A2590 Removal of Old Frame for the Flatness Gauge 12h 3/31/16 6:00 AM 3/31/16 6:00 PM 100 0.42% 0.42% Finished 100.00% 100.00% A4410 Removal of Dust Protection 5h 4/1/16 7:00 AM 4/1/16 12:00 PM 120 0.50% 0.50% Finished 100.00% 100.00% ELECTRICAL 23h 3/29/16 7:00 AM 3/30/16 6:00 PM 228 0.95% 0.95% A4380 Disconnection of Existing Cables 4h 3/29/16 7:00 AM 3/29/16 11:00 AM 60 0.25% 0.25% Finished 100.00% 100.00% A4390 Disconnection of Existing Cables from Flatness Gauge Cable from Rm3-1 12h 3/30/16 6:00 AM 3/30/16 6:00 PM 84 0.35% 0.35% Finished 100.00% 100.00% A4400 Disconnection & Isolation of Cable to be used 12h 3/30/16 6:00 AM 3/30/16 6:00 PM 84 0.35% 0.35% Finished 100.00% 10 0. 00 % 0 .0 0% ROOM 2 20h 4/3/16 6:00 AM 4/4/16 2:00 PM 420 1.74% 0.52% ASSEMBLY 20h 4/3/16 6:00 AM 4/4/16 2:00 PM 420 1.74% 0.52% A3210 Installation of Holder for Water Chiller 8h 4/3/16 6:00 AM 4/3/16 2:00 PM 220 0.91% 0.27% On-going 3 0. 00 % 30 .0 0% A3220 Lifting and Installation of Water Chiller 12h 4/3/16 2:00 PM 4/4/16 2:00 PM 200 0.83% 0.25% On-going 3 0. 00 % 30 .0 0% ROOM 3 66h 3/31/16 6:00 AM 4/5/16 2:00 PM 1165 4.84% 1.49% DISASSEMBLY 36h 3/31/16 6:00 AM 4/3/16 8:00 AM 560 2.32% 1.49%

    A3640 Dismantling of Existing cable connected to Flatness Gauge 12h 3/31/16 6:00 AM 3/31/16 6:00 PM 160 0.66% 0.66% Finished 90.00% 100.00% 10.00% A3620 Disassemble of Existing Central Stations (41JE15.H102) 6h 4/2/16 8:00 AM 4/2/16 2:00 PM 100 0.42% 0.42% Finished 90.00% 100.00% 10.00% A3630 Disassemble of Existing Central Stations (41JE15.H03) 6h 4/2/16 8:00 AM 4/2/16 2:00 PM 100 0.42% 0.42% Finished 90.00% 100.00% 10.00% A4420 Removal of 1 Warning Light for Flatness Gauge 6h 4/2/16 2:00 PM 4/3/16 8:00 AM 200 0.83% 0.00% Not Started 0.00% 0.00% ASSEMBLY 36h 4/2/16 2:00 PM 4/5/16 2:00 PM 605 2.51% 0.00% A3650 Lifting & Installation of TopPlan Central Station (430BO2) 8h 4/2/16 2:00 PM 4/3/16 10:00 AM 120 0.50% 0.00% Not Started 0.00% A3670 Cable Laying Activities for TopPlan Central Station 24h 4/3/16 10:00 AM 4/5/16 10:00 AM 245 1.02% 0.00% Not Started 0.00% A3680 Wiring and Termination Works for TopPlan Central Station 10h 4/4/16 4:00 PM 4/5/16 2:00 PM 240 1.00% 0.00% Not Started 0.00% PIPING WORKS 58h 4/2/16 6:00 AM 4/6/16 11:00 AM 800 3.32% 0.00% A3850 Cutting & Bending of Pipes 12h 4/2/16 6:00 AM 4/2/16 6:00 PM 120 0.50% 0.00% Not Started 0.00% A3860 Fit-Up 22h 4/2/16 6:00 AM 4/3/16 4:00 PM 150 0.62% 0.00% Not Started 0.00% A3880 QC Inspection 5h 4/3/16 4:00 PM 4/4/16 9:00 AM 10 0.04% 0.00% Not Started 0.00% A3870 Full Weld 12h 4/4/16 9:00 AM 4/5/16 9:00 AM 100 0.42% 0.00% Not Started 0.00% A3890 Qc Inspection 7h 4/5/16 9:00 AM 4/5/16 4:00 PM 200 0.83% 0.00% Not Started 0.00% A3900 Service Test 12h 4/5/16 4:00 PM 4/6/16 11:00 AM 220 0.91% 0.00% Not Started 0.00% SHUTDOWN 140h 4/6/16 6:00 AM 4/12/16 3:00 PM 4818 20.00% 0.00% GROUND FLOOR 140h 4/6/16 6:00 AM 4/12/16 3:00 PM 2587 10.74% 0.00% SCAFFOLDING 10h 4/6/16 6:00 AM 4/6/16 5:00 PM 130 0.54% 0.00% A4430 Installation of Scaffolding around roller 4h 4/6/16 6:00 AM 4/6/16 10:00 AM 100 0.42% 0.00% Not Started 0.00% A4440 Installation of Dummy Beam Support for Removal of Cobble Guard 6h 4/6/16 10:00 AM 4/6/16 5:00 PM 30 0.12% 0.00% Not Started 0.00% DISASSEMBLY 48h 4/6/16 5:00 PM 4/8/16 9:00 PM 1106 4.59% 0.00% ELECTRICAL 9h 4/7/16 5:00 PM 4/8/16 3:00 AM 100 0.42% 0.00% A2460 Removal of Existing Control Panel 3h 4/7/16 5:00 PM 4/7/16 8:00 PM 60 0.25% 0.00% Not Started 0.00% A2470 Removal of Existing Housing for Water Monitoring 6h 4/7/16 8:00 PM 4/8/16 3:00 AM 40 0.17% 0.00% Not Started 0.00% MECHANICAL 48h 4/6/16 5:00 PM 4/8/16 9:00 PM 1006 4.18% 0.00% A2450 Disassemble of Existing Cobble Guard (Part 1 & Part 2) 12h 4/6/16 5:00 PM 4/7/16 6:00 AM 216 0.90% 0.00% Not Started 0.00% A2480 Disassemble of Existing Heat Shield 1 5h 4/7/16 6:00 AM 4/7/16 11:00 AM 120 0.50% 0.00% Not Started 0.00% A2490 Disassemble of Existing Heat Shield 2 5h 4/7/16 11:00 AM 4/7/16 5:00 PM 120 0.50% 0.00% Not Started 0.00% A2500 Disassemble of Existing Tube for Width Gauge 4h 4/7/16 5:00 PM 4/7/16 9:00 PM 70 0.29% 0.00% Not Started 0.00%

    A2510 Disassemble of Existing Tube for Flatness Gauge 4h 4/7/16 9:00 PM 4/8/16 2:00 AM 100 0 42% 0 00% Not Started 0 00%

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    5/9

    Date:

    Activity ID Activity NameOriginalDuration

    Planned Start Planned FinishBudgeted

    LaborUnits

    Weight EarnedActivityStatus

    TodaysActivity %

    Cum.Activitys

    %

    Prev.Activity

    %AF-1421074 UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS MEASUREMENT GAUGE 655h 2/28/16 7:00 AM 4/23/16 5:00 PM 24090 100.00% 33.21%

    Report # 9 WEEKLY PROGRESS REPORT

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD

    UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES (HD)(AF-1421074)

    April 2, 2016

    A2930 Weding of Frame to Plates 4h 4/7/16 11:00 PM 4/8/16 4:00 AM 28 0.12% 0.00% Not Started 0.00% A2940 Lifting and Allignment of Projector Housing 5h 4/8/16 4:00 AM 4/8/16 9:00 AM 80 0.33% 0.00% Not Started 0.00% A3000 Bolt Torquing 5h 4/8/16 9:00 AM 4/8/16 3:00 PM 35 0.15% 0.00% Not Started 0.00% TOP PLAN PROJECTOR 19h 4/8/16 3:00 PM 4/9/16 11:00 AM 158 0.66% 0.00% A4340 Survey & Marking of Centerline for TopPlan Projector Installation 3h 4/8/16 3:00 PM 4/8/16 6:00 PM 18 0.07% 0.00% Not Started 0.00% A4000 Welding of Mounting Plates 3h 4/8/16 6:00 PM 4/8/16 9:00 PM 18 0.07% 0.00% Not Started 0.00% A2960 Instalaltion of Holder for Projector 6h 4/8/16 9:00 PM 4/9/16 4:00 AM 36 0.15% 0.00% Not Started 0.00% A2970 Lifting and Alignment of Top plan Projector 2h 4/9/16 4:00 AM 4/9/16 6:00 AM 16 0.07% 0.00% Not Started 0.00% A2950 Installation of Top plan Projector 5h 4/9/16 6:00 AM 4/9/16 11:00 AM 35 0.15% 0.00% Not Started 0.00% A2980 Bolt Torquing 5h 4/9/16 6:00 AM 4/9/16 11:00 AM 35 0.15% 0.00% Not Started 0.00% WIDTH GAUGE 22h 4/9/16 4:00 AM 4/10/16 4:00 AM 90 0.37% 0.00% A4330 Survey & Marking of Centerline for Width Gauge Installation 3h 4/9/16 4:00 AM 4/9/16 7:00 AM 30 0.12% 0.00% Not Started 0.00% A3030 Installation and Alignment of IMS Width Gauge 16h 4/9/16 7:00 AM 4/10/16 12:00 AM 50 0.21% 0.00% Not Started 0.00%

    A3040 Bolt Torquing 3h 4/10/16 1:00 AM 4/10/16 4:00 AM 10 0.04% 0.00% Not Started 0.00% TOP PLAN CAMERA 18h 4/10/16 1:00 AM 4/10/16 8:00 PM 104 0.43% 0.00% A3120 Installation of Console for Camera 2h 4/10/16 1:00 AM 4/10/16 3:00 AM 16 0.07% 0.00% Not Started 0.00% A3130 Fit up of Frame 5h 4/10/16 3:00 AM 4/10/16 8:00 AM 20 0.08% 0.00% Not Started 0.00% A3140 Alignment of Frame 2h 4/10/16 8:00 AM 4/10/16 10:00 AM 14 0.06% 0.00% Not Started 0.00% A3150 Bolting of Frame to Plates 5h 4/10/16 10:00 AM 4/10/16 4:00 PM 20 0.08% 0.00% Not Started 0.00% A3160 Lifting and Allignment of Camera Housing & Console 2h 4/10/16 4:00 PM 4/10/16 6:00 PM 20 0.08% 0.00% Not Started 0.00% A3170 Bolting Activities 2h 4/10/16 6:00 PM 4/10/16 8:00 PM 14 0.06% 0.00% Not Started 0.00% ON-SITE CABINET 5h 4/10/16 8:00 PM 4/11/16 2:00 AM 10 0.04% 0.00% A3200 Installation of on-site Cabinet 5h 4/10/16 8:00 PM 4/11/16 2:00 AM 10 0.04% 0.00% Not Started 0.00% ROOM 3 67h 4/7/16 10:00 PM 4/10/16 11:00 PM 730 3.03% 0.00% DISASSEMBLY 25h 4/7/16 10:00 PM 4/9/16 2:00 AM 360 1.49% 0.00% ELECTRICAL 15h 4/7/16 10:00 PM 4/8/16 3:00 PM 180 0.75% 0.00% A2670 Dissassemble of Existing Central Station(41JE15.H101) 10h 4/7/16 10:00 PM 4/8/16 9:00 AM 140 0.58% 0.00% Not Started 0.00% A2680 Dismantling of Existing Cable for Width Gauge 5h 4/8/16 9:00 AM 4/8/16 3:00 PM 40 0.17% 0.00% Not Started 0.00% PIPING 10h 4/8/16 3:00 PM 4/9/16 2:00 AM 180 0.75% 0.00% A2690 Disconnection of Piping , Tube and Hoses 4h 4/8/16 3:00 PM 4/8/16 7:00 PM 80 0.33% 0.00% Not Started 0.00% A2700 Removal of Existing (Water Service Box) Panels 6h 4/8/16 7:00 PM 4/9/16 2:00 AM 100 0.42% 0.00% Not Started 0.00% ASSEMBLY 42h 4/9/16 2:00 AM 4/10/16 11:00 PM 370 1.54% 0.00% ELECTRICAL 42h 4/9/16 2:00 AM 4/10/16 11:00 PM 370 1.54% 0.00% A3560 Modification of Existing Cable Tray Cover 15h 4/9/16 2:00 AM 4/9/16 6:00 PM 150 0.62% 0.00% Not Started 0.00% A3730 Cabling works for Central Station (430B01) 12h 4/9/16 6:00 PM 4/10/16 7:00 AM 120 0.50% 0.00% Not Started 0.00% A3740 Wiring & Termination Works for Width Gauge 15h 4/10/16 7:00 AM 4/10/16 11:00 PM 100 0.42% 0.00% Not Started 0.00% ELECTRICAL AND AUTOMATION WORKS 45h 4/9/16 6:00 PM 4/11/16 7:00 PM 693 2.88% 0.00% TOPPLAN 45h 4/9/16 6:00 PM 4/11/16 7:00 PM 542 2.25% 0.00% A4010 Cable Laying & Termination for Main Power Supply Sation 5h 4/9/16 6:00 PM 4/9/16 11:00 PM 120 0.50% 0.00% Not Started 0.00% A4020 Cable Laying & Termination for 100v Power Supply (40m) 4h 4/9/16 11:00 PM 4/10/16 4:00 AM 80 0.33% 0.00% Not Started 0.00% A4030 Cable Laying & Termination for Camera , Service & EtherCAT 3h 4/10/16 4:00 AM 4/10/16 7:00 AM 30 0.12% 0.00% Not Started 0.00% A4040 Cable Laying & Termination for Equipotential Bonding Measuring Point 4h 4/10/16 7:00 AM 4/10/16 11:00 AM 20 0.08% 0.00% Not Started 0.00%

    A4050 Cable Laying & Termination for Power Supply Fan Camera Housing 3h 4/10/16 11:00 AM 4/10/16 3:00 PM 12 0 05% 0 00% Not Started 0 00%

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    6/9

    Date:

    Activity ID Activity NameOriginalDuration

    Planned Start Planned FinishBudgeted

    LaborUnits

    Weight EarnedActivityStatus

    TodaysActivity %

    Cum.Activitys

    %

    Prev.Activity

    %AF-1421074 UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS MEASUREMENT GAUGE 655h 2/28/16 7:00 AM 4/23/16 5:00 PM 24090 100.00% 33.21%

    Report # 9 WEEKLY PROGRESS REPORT

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD

    UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES (HD)(AF-1421074)

    April 2, 2016

    A4750 Switch on Power & Computer of Central Station 2h 4/11/16 8:00 AM 4/11/16 10:00 AM 200 0.83% 0.00% Not Started 0.00% A5170 Checking of cable termination/connections 20h 4/11/16 8:00 AM 4/12/16 6:00 AM 220 0.91% 0.00% Not Started 0.00% A5120 Installation supervision of Cobble guard 2h 4/11/16 5:00 PM 4/11/16 7:00 PM 100 0.42% 0.00% Not Started 0.00% A5140 Back light installation inspection 4h 4/11/16 6:00 PM 4/11/16 10:00 PM 100 0.42% 0.00% Not Started 0.00% A5180 Switch on power of cameras & width gauge housing 2h 4/12/16 8:00 AM 4/12/16 10:00 AM 100 0.42% 0.00% Not Started 0.00% A4780 Communication Check of All internal Components(Camera) 3h 4/12/16 10:00 AM 4/12/16 2:00 PM 120 0.50% 0.00% Not Started 0.00% A5150 Inspection of Grease Protection 3h 4/12/16 10:00 AM 4/12/16 2:00 PM 130 0.54% 0.00% Not Started 0.00% A5110 Piping supervision for blow off Spray Backlight 2h 4/12/16 7:00 PM 4/12/16 9:00 PM 150 0.62% 0.00% Not Started 0.00% A4790 I/O Signal Testing(Internal) 4h 4/13/16 6:00 AM 4/13/16 10:00 AM 200 0.83% 0.00% Not Started 0.00% A4800 Data interface Checking (IMS to Customer 8h 4/13/16 10:00 AM 4/13/16 6:00 PM 300 1.25% 0.00% Not Started 0.00% A4810 Checking of All interlock in System 2h 4/14/16 6:00 AM 4/14/16 8:00 AM 200 0.83% 0.00% Not Started 0.00% A4820 Hardware interface Check with Customer 4h 4/14/16 8:00 AM 4/14/16 12:00 PM 200 0.83% 0.00% Not Started 0.00% A4830 Camera & Backlight Allignment 5h 4/14/16 8:00 AM 4/14/16 1:00 PM 100 0.42% 0.00% Not Started 0.00%

    A4840 System Calibration 10h 4/14/16 8:00 AM 4/14/16 6:00 PM 40 0.17% 0.00% Not Started 0.00% A5100 Lock valve installation supervision for Air & Water connections 3h 4/14/16 10:00 AM 4/14/16 1:00 PM 40 0.17% 0.00% Not Started 0.00% A5160 Connecting Media to Equipments 3h 4/14/16 1:00 PM 4/14/16 4:00 PM 40 0.17% 0.00% Not Started 0.00% A4850 Software & Accuracy Check 20h 4/15/16 9:00 AM 4/16/16 6:00 PM 500 2.08% 0.00% Not Started 0.00% A4860 System Observation 20h 4/15/16 2:00 PM 4/17/16 11:00 AM 300 1.25% 0.00% Not Started 0.00% SAFETY WALKTHROUGH 66h 4/17/16 11:00 AM 4/23/16 5:00 PM 482 2.00% 0.00% A5190 Safety Walkthrough 3h 4/17/16 11:00 AM 4/17/16 2:00 PM 200 0.83% 0.00% Not Started 0.00% A5200 PSSR and Puchlisting 15h 4/17/16 2:00 PM 4/18/16 5:00 PM 120 0.50% 0.00% Not Started 0.00% A5210 Punchlist Rectification 48h 4/18/16 5:00 PM 4/23/16 5:00 PM 162 0.67% 0.00% Not Started 0.00% PROJECT CLOSEOUT 126h 4/12/16 8:00 AM 4/23/16 11:00 AM 963 4.00% 0.00% A4110 Lifting and Disposal of Removed Equipment 36h 4/12/16 8:00 AM 4/14/16 3:00 PM 200 0.83% 0.00% Not Started 0.00% A1430 Demobilization of Manpower & Equipments 60h 4/17/16 11:00 AM 4/23/16 11:00 AM 363 1.51% 0.00% Not Started 0.00% A2320 Removal of Scaffolding 20h 4/18/16 5:00 PM 4/20/16 1:00 PM 400 1.66% 0.00% Not Started 0.00%

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    7/9

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD.

    Sr No. Item Description Discipline Material / Service No MAR STATUS REMARKS

    001 FLEXIBLE METAL CONDUIT ElectricalFLEXIBLE METAL

    CONDUIT APPROVED

    002 FLEXIBLE METAL CONDUI COUPLING ElectricalFLEXIBLE METAL

    CONDUI COUPLING APPROVED

    003 RIGID CONDUIT Electrical RIGID CONDUIT APPROVED

    004 RIGID BUSH END Electrical RIGID BUSH END APPROVED

    005 ONE SIDE HOLE CLAMP Electrical ONE SIDE HOLE CLAMP APPROVED

    006 UNISTRAT Electrical UNISTRAT APPROVED

    007 UNISTRAT CLA MP Electrical UNISTRAT CLAMP APPROVED

    008 PIPE(316 L) MECHANICAL EN ISO 1127- 1.4301 APPROVED

    009 TEE -PIECE MECHANICAL DIN 2987 - 1.4301 APPROVED

    010 PIPE BEND 90 DEGREE MECHANICAL ISO 3419 - 1.4301 APPROVED

    011 VIEGA, 1845, MECHANICAL R1/2 X R1/2 APPROVED

    012 CHANNEL MECHANICAL DIN1026-S235JR APPROVED

    013 PLATE MECHANICAL EN10029-S235JR APPROVED

    014 hexagon head screw MECHANICAL ISO 4017 APPROVED

    015 hex nut MECHANICAL ISO 4032 APPROVED

    016 WASHER MECHANICAL ISO 7089 APPROVED

    017 PLATE MECHANICAL EN10029-S235JR APPROVED

    018 PLATE MECHANICAL EN10029-S235JR APPROVED

    019 FLAT BAR MECHANICAL EN10029-S235JR APPROVED

    020 BULP PLATE MECHANICAL DIN 59220 -S235JR APPROVED

    021 washer MECHANICAL ISO 7089-8 APPROVED

    022 hexagon head screw MECHANICAL ISO 4017 APPROVED

    023 washer MECHANICAL ISO 7089 APPROVED

    Shutdown Materials

    MATERIAL APPROVAL TRACKING SHEETProject Title: UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES

    Project No: AF-1421074

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    8/9

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD.

    Status as of : Progress of total Delivey: 0.00%

    Affiliate: Rev:

    Sr No. Item Description Discipline Material / Service No PR No. PR . Date PO No. P.O Date Size Quantity Ordered Unit Vendor Present StatusDelivery As

    Per PO

    Delay orRemaining

    Days

    ActualDelivery

    date

    QuantityArrived

    BalanceTo Arrive

    Delivery % Remarks

    001 FLEXIBLE METAL CONDUIT ElectricalFLEXIBLE METAL

    CONDUIT35720 9-Mar-16 4027 16/ 03/ 201 6 1'' 600 M TRS A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 600 0.00%

    002 FLEXIBLE METAL CONDUI COUPLING Electrical FLEXIBLE METALCONDUI COUPLING

    35720 9-Mar-16 4027 16/03/2016 1'' 50 PCS Al-Basela Trading Est. RECEIVED 17/03/2016 50 100.00%

    0 03 R IG ID C ON DU IT Electrical RIGID CONDUIT 35720 9-Mar-16 4027 16/ 03/ 201 6 1'' 25 M TRS A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 25 100.00%

    0 04 R IG ID BU SH EN D Electrical RI GI D BU SH E ND 35 720 9 -Mar -16 4027 16/ 03/ 201 6 1'' 30 P CS A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 30 100.00%

    005 ONE SIDE HOLE CLAMP ElectricalONE SIDE HOLE

    CLAMP35720 9-Mar-16 4027 16/ 03/ 201 6 1'' 100 P CS A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    0 06 U NI ST RAT Electrical UNISTRAT 35720 9-Mar -16 4027 16/ 03/ 201 6 50X50 20 M TRS A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 20 100.00%0 07 U NI ST RAT C LA MP Electrical UNISTRAT CLAMP 35720 9-Mar-16 4027 16/ 03/ 201 6 1'' 50 S ET A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 50 100.00%

    008 BOLT AND NUT (SS) Electrical BOLT AND NUT (SS) 35720 9-Mar-16 4027 16/03/2016 11/2''X10MM 20 E/A Al-Basela Trading Est. RECEIVED 17/03/2016 20 100.00%

    0 09 B OLT A ND NU T ( SS ) Electrical BOLT AND NUT (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 11/2'X8MM 50 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 50 100.00%

    0 10 B OLT A ND NU T ( SS ) Electrical BOLT AND NUT (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 1''X10MM 20 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 20 100.00%

    0 11 B OLT A ND NU T ( SS ) Electrical BOLT AND NUT (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 1''X8MM 50 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 50 100.00%

    0 12 F LAT WAS HE R Electrical FLAT WASHER 35720 9-Mar-16 4027 16/ 03/ 201 6 10MM 100 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    013 FLAT WASHER Electrical FLAT WASHER 35720 9-Mar-16 4027 16/03/2016 8MM 200 E/A Al-Basela Trading Est. RECEIVED 17/03/2016 200 100.00%

    0 14 S PR IN G WAS HE R Electrical SPRING WASHER 35720 9-Mar-16 4027 16/ 03/ 201 6 10MM 100 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    0 15 S PR IN G WAS HE R Electrical SPRING WASHER 35720 9-Mar-16 4027 16/ 03/ 201 6 8MM 100 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    0 16 T HR EA DA D RO D( SS ) Electrical THREADAD ROD(SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 20MM DIA 12 M TRS A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 12 100.00%

    017 NUT ( SS ) Electrical NUT (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 20MM DIA 50 E/ A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 50 100.00%

    0 18 F LAT WAS HE R Electrical FLAT WASHER 35720 9-Mar-16 4027 16/ 03/ 201 6 20MM DIA 100 E /A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    0 19 C AB LE T IE ( SS ) Electrical CABLE TIE (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 300 MM L 5 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 5 100.00%

    0 20 C AB LE T IE ( SS ) Electrical CABLE TIE (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 200 MM L 5 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 5 100.00%

    0 21 C AB LE T IE ( SS ) Electrical CABLE TIE (SS) 35720 9-Mar-16 4027 16/ 03/ 201 6 100 MM L 5 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 5 100.00%

    0 22 I NS UL AT IO N TAP E Electrical INSULATION TAPE 35720 9-Mar-16 4027 16/ 03/ 201 6 RED 10 RO LL A l- Ba sel a T radi ng Es t. R EC EIV ED 17/03/2016 10 100.00%

    0 23 I NS UL AT IO N TAP E Electrical INSULATION TAPE 35720 9-Mar-16 4027 16/ 03/ 201 6 YELLOW 10 RO LL A l- Ba sel a T radi ng Es t. R EC EIV ED 17/03/2016 10 100.00%

    0 24 I NS UL AT IO N TAP E Electrical INSULATION TAPE 35720 9-Mar-16 4027 16/ 03/ 201 6 BLUE 10 RO LL A l- Ba sel a T radi ng Es t. R EC EIV ED 17/03/2016 10 100.00%

    0 25 I NS UL AT IO N TAP E Electrical INSULATION TAPE 35720 9-Mar-16 4027 16/ 03/ 201 6 BLACK 10 RO LL A l- Ba sel a T radi ng Es t. R EC EIV ED 17/03/2016 10 100.00%

    0 26 I NS UL AT IO N TAP E Electrical INSULATION TAPE 35720 9-Mar-16 4027 16/ 03/ 201 6 GREEN 10 RO LL A l- Ba sel a T radi ng Es t. R EC EIV ED 17/03/2016 10 100.00%

    027 NYLON CABLE TIE Electrical NYLON CABLE TIE 35720 9-Mar-16 4027 16/03/2016 300 MM L 5 PKT Al-Basela Trading Est. RECEIVED 17/03/2016 5 100.00%

    0 28 N YL ON CA BL E T IE Electrical NYLON CABLE TIE 35720 9-Mar-16 4027 16/ 03/ 201 6 200MM L 5 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 5 100.00%

    0 29 N YL ON CA BL E T IE Electrical NYLON CABLE TIE 35720 9-Mar-16 4027 16/ 03/ 201 6 100 MM L 5 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 5 100.00%

    030 SCREW Electrical SCREW 35720 9-Mar-16 4027 16/ 03/ 201 6 11/2'' X4 MM DIA 100 E \A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    031 SCREW Electrical SCREW 35720 9-Mar-16 4027 16/ 03/ 201 6 1''X4 MM DIA 100 E \A A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 100 100.00%

    032 FISHER Electrical FISHER 35720 9-Mar-16 4027 16/ 03/ 201 6 8 MM 3 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 3 100.00%

    033 FISHER Electrical FISHER 35720 9-Mar-16 4027 16/ 03/ 201 6 6MM 3 P KT A l- Ba sel a T radi ng E st . R EC EIV ED 17/03/2016 3 100.00%

    034 Tubing MECHANICAL EN ISO 1127- 1.4301 35716 8-Mar-1617,2MM X 2,3MM

    1/2'' 80 MTRS RECEIVED 0.00%

    035 Valves MECHANICAL D IN 2 98 7 - 1 .4 30 1 3 57 16 8 -M ar -1 617,2MM X 2,3MM

    1/2'' 2 E/A RECEIVED 0.00%

    036 PIPE BEND 90 DEGREE MECHANICAL I SO 3 41 9 - 1 .4 30 1 3 57 16 8 -M ar -1 617,2MM X 2,3MM

    1/2'' 17 E/A RECEIVED 0.00%

    0 37 V IE GA , 1 84 5, MECHANICAL R1/2 X R1/2 35716 8-Mar-16 VIEGA, 1845, 9 E/A 0.00%038 CHA NNE L MECHANICAL DIN1026-S235JR 35716 8-Mar-16 4051 160 24 MTRS RECEIVED 24 100.00%039 PLATE MECHANICAL EN10029-S235JR 35716 8-Mar-16 4051 20MM THICK 12 MTRS RECEIVED 12 100.00%040 hexagon head screw MECHANICAL ISO 4017 35716 8-Mar-16 M 20 X70-A2-70 32 E/A RECEIVED 0.00%041 hex nut MECHANICAL ISO 4032 35716 8-Mar-16 M2O-A2-70 40 E/A RECEIVED 0.00%042 WASHER MECHANICAL ISO 7089 35716 8-Mar-16 21-140 HV-A2 70 E/A RECEIVED 0.00%043 PLATE MECHANICAL EN10029-S235JR 35716 8-Mar-16 4085 10MM THICK 24 MTRS RECEIVED 24 100.00%

    044 PLATE MECHANICAL EN10029-S235JR 35716 8-Mar-16 4051 5MM THICK 12 MTRS RECEIVED 12 100.00%045 FLAT BAR MECHANICAL EN10029-S235JR 35716 8-Mar-16 4085 30X10 24 MTRS RECEIVED 24 100.00%0 46 B UL P P LATE MECHANICAL DIN 59220 -S235JR 35716 8-Mar-16 4085 5X1000X2000 12 MTRS RECEIVED 12 100.00%047 washer MECHANICAL ISO 7089-8 35716 8-Mar-16 4-140 HV-A2 140 E/A RECEIVED 0.00%048 hexagon head screw MECHANICAL ISO 4017 35716 8-Mar-16 M8x30-A2-70 140 E/A RECEIVED049 hexagon head screw MECHANICAL ISO 4017 35716 8-Mar-16 M20x60-A2-70 16 E/A RECEIVED050 hexagon head screw MECHANICAL ISO 4017 35716 8-Mar-16 M24x100-A2-70 24 E/A RECEIVED 0.00%051 hexagon head screw MECHANICAL ISO 4017 35716 8-Mar-16 M24x120-A2-70 6 E/A RECEIVED 0.00%052 washer MECHANICAL ISO 7089 35716 8-Mar-16 21-140 HV-A2 32 E/A RECEIVED 0.00%053 washer MECHANICAL ISO 7089 35716 8-Mar-16 21-140 HV-A2 32 E/A RECEIVED 0.00%054 washer MECHANICAL ISO 7089 35716 8-Mar-16 25-140 HV 60 E/A RECEIVED 0.00%055 hex nut MECHANICAL ISO 4032 35716 8-Mar-16 M20-A2-70 16 E/A RECEIVED 0.00%056 hex nut MECHANICAL ISO 4032 35716 8-Mar-16 M24-A2-70 30 E/A RECEIVED 0.00%

    057 eye bolt MECHANICAL RUD 35716 8-Mar-16STARPOINT VRS-F

    M24 4 E/A RECEIVED 0.00%

    058 eye b ol t MECHANICAL RUD 35716 8-Mar-16STARPOINT VRS-F

    M20 4 E/A RECEIVED 0.00%

    Shutdown Materials

    MATERIAL TRACKING RECORDProject Title: UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES 2-Apr-16

    Project No: AF-1421074 HADEED

    4/2/2016 PLANNING DEPARTMENT

  • 8/18/2019 Af-1421074 Upgrade of Hsm Finishing Mill Width and Flatness Gauges(Daily Progress Report)

    9/9

    SPECIALIZED INDUSTRIAL SERVICES CO. LTD.

    Status as of : Progress of total Delivey: 0.00%

    Affiliate: Rev:

    Sr No. Item Description Discipline Material / Service No PR No. PR . Date PO No. P.O Date Size Quantity Ordered Unit Vendor Present StatusDelivery As

    Per PO

    Delay orRemaining

    Days

    ActualDelivery

    date

    QuantityArrived

    BalanceTo Arrive

    Delivery % Remarks

    MATERIAL TRACKING RECORDProject Title: UPGRADE OF HSM FINISHING MILL WIDTH AND FLATNESS GAUGES 2-Apr-16

    Project No: AF-1421074 HADEED

    059 bolt MECHANICAL 35716 8-Mar-16 sample 100 E/A RECEIVED 0.00%0 60 h il ti b ol t MECHANICAL 35716 8-Mar-16 M 16 X150 10 E/A RECEIVED 0.00%061 CHA NNE L MECHANICAL S 235 JR 35716 8-Mar-16 4051 75X50X8MM 48 MTRS RECEIVED 48 100.00%062 FLAT BAR MECHANICAL S 235 JR 35716 8-Mar-16 4085 75X4 24 MTRS RECEIVED 24 100.00%063 Paints RECEIVED

    4/2/2016 PLANNING DEPARTMENT