AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014 © IETE 1 Q2 (a) Write the dual of the following LPP- minimise 2 1 x 20 x 10 z + = subject to 6 x x 2 8 x 3 x 18 x 2 x 3 2 1 2 1 2 1 + + 0 x , x 2 1 Answer Q2 (b) Solve the following LPP using simplex method Subject to 0 x , x 26 x 2 x 30 x 2 x 3 18 x x 2 2 1 2 1 2 1 2 1 = + + +

Transcript of AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. …

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 1

Q2 (a) Write the dual of the following LPP-

minimise 21 x20x10z +=

subject to

6xx28x3x18x2x3

21

21

21

≤−≥+≥+

0x,x 21 ≥

Answer

Q2 (b) Solve the following LPP using simplex method

Subject to

0x,x26x2x30x2x3

18xx2

21

21

21

21

≥=+≥+≤+

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 2

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 3

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 4

Q3 (a) Solve the linear programming problem by Graphical method maximise 21 x5x3z +=

Subject to :

0x,0x600x

1500xx2000x2x

21

2

21

21

≥≥≤

≤+≤+

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 5

Q3 (b) Model building is the essence of the “O.R. approach”, Discuss.

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 6

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 7

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 8

Q4 (a) A Project has the following time schedule

Activity: 1-2 1-3 1-4 2-5 3-6 3-7 4-6 5-8 6-9 7-8

Time in 2 2 1 4 8 5 3 1 5 4

Month:

Activity 8-9

Time in 3

Months

Construct network diagram and compute

(i) Total float for each activity

(ii) Critical path and its duration

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 9

Q4 (b) Distinguish between PERT and CPM techniques.

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 10

Answer

Q5 (a) Solve the following minimal assignment problem.

1 2 3 4

I 12 30 21 15

J II 18 33 9 31

o

b III 44 25 24 21

IV 23 30 28 14

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 11

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 12

Q5 (b) Find the initial solution for the transportation problem by Vogel’s approximation method (VAM)

To

W1 W2 W3 Supply

F1 2 7 4 5

From F2 3 3 1 8

F3 5 4 7 7

F4 1 6 2 14

Demand 7 9 18

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 13

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 14

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 15

Q6 (a) What do you understand by queue? Give some important applications of queuing theory?

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 16

Q6 (b) What do you mean by-

(i) Two person zero sum game

(ii) Saddle point

(iii) Pure and mixed strategies

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 17

Q7 (a) What are the different functions of management and what are the importance of these functions at various levels of management?

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 18

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 19

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 20

Q7 (b) What is the organisation structure and how the organisation charts are helpful to provide a broad picture of positions of authorities and their relationships in the organisation structure.

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 21

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 22

Q8 (a) Explain the various techniques of business forecasting.

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 23

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 24

Q8 (b) Explain the process of decision making.

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 25

Q9 (a) What do you understand by marketing mix?

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 26

Answer

AE62/AC62/AT62 OPERATIONS RESEARCH & ENGG. MANAGEMENT JUNE 2014

© IETE 27

Q9 (b) Define leadership and explain leadership characteristics.