Additions - Various Schools...Current Status Additions - Various Schools Administrative Data Various...
Transcript of Additions - Various Schools...Current Status Additions - Various Schools Administrative Data Various...
Architect:General Contractor:Scope of Work:
Phase of Work:
Plans & Engineering $580,000 $580,000Construction $8,005,000 $8,005,000FFE $0 $0Project Support Total $8,585,000 $8,585,000 $0* FY19 Program
Current Status
Additions - Various Schools
Administrative DataVariousVariousOn-going program to provide additions at various schools. Design and Construction
See following sheet for details.
Project ScheduleMarley ES
See following sheet for details.
Crofton Woods ES
Fiscal Data
Approved Budget *
Current Appropriation*
Encumbered
See following sheet for details
Severn ES
1 Construction Status July 2018
School Project Description
Const. Cost Fiscal Year Ed Specs/ Schematic
Design Dev./ Const
Documents
Start Const.
Substantial Completion
Architect General Contractor
Current Status
6 Classroom Addition
$3,400,000 (Estimate)
FY 2020 Apr-18 Oct-18 Jul-19 Jul-20Grimm &
ParkerTBD 5%
Gym/Program Addition
$7,700,000 (Estimate)
FY 2019 Aug-17Nov-17/ Jan-18
Sep-18 Dec-19 SEI TBD 90%
4 Classroom Addition
$2,600,000 (Estimate)
FY 2020 Apr-18 Oct-18 Jul-19 Jul-20 WGM TBD 5%
4 Classroom Addition
$1,750,000 FY 2018 Apr-16/ Sept-16
Dec-16/ Feb-17
Oct-17 Oct-18 BWH Tech Contracting
45%
Severn ESDesign documents in progress.
Additions - Various Schools - continued
Schools in Design:
Marley ES
The general contractor is continuing work on the foundations, concrete slabs and decks, exterior walls and brick veneer, and strutural framing.
Glen Burnie Park ES
Bid documents sent to State and purchasing July 1, 2018.
Schools in Construction:
Crofton Woods ES
Design documents in progress.
2 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 456 565
Gross Square Footage 56,255 89,253
Phase of Work:
Percent Complete: 42%
Educational Specifications Sep-13 Sep-13 Nov-13Feasibility Study Nov-13 Mar-14 Mar-14Schematic Design Jul-14 Sep-15 Sep-15Design Development Nov-14 Dec-15 Sep-15Bid Award Jan-16 Jan-17 Jan-17Start Construction Apr-16 Apr-17 Apr-17Occupancy Aug-18 Aug-19
Plans & Engineering $3,271,000 $3,271,000 $3,270,899Construction $35,362,000 $35,362,000 $27,740,664FFE $2,104,000 $2,104,000 $33,669Project Support $1,366,000 $1,366,000 $985,931Total $42,103,000 $42,103,000 $32,031,163
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Project Schedule
Approved EdSpec
Current Actual
Construction
Current Status
Construction of the masonry walls, brick veneer, roof joists, and decks are ongoing. Interior electric rough-ins, exterior window installation, and roofing have been initiated.
The construction of a replacement school for Arnold Elementary School.
Arnold ES - Replacement
Administrative Data Vital StatisticsGWWO ArchitectsJacobs, Inc.
Scope of Work:
3 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity n/a 1,696Scope of Work: Gross Square Footage n/a 275,768
Phase of Work:
Percent Complete: 22%
Educational Specifications May-16 May-16 May-16Feasibility Study n/a n/a n/aSchematic Design Aug-16 Aug-16 Aug-16Design Development Dec-16 Nov-16 Oct-16Construction Documents Aug-17 Aug-17 Aug-17
Bid Award Dec-17 Site Aug-17 Bldg Oct-17
Aug-18
Start Construction Jan-18 Jan-18 Jan-18Occupancy Aug-20 Aug-20
Plans & Engineering $10,078,000 $10,078,000 $6,957,365Construction $114,304,000 $93,700,000 $53,687,885FFE $8,641,000 $5,185,000Project Support $1,812,000 $1,450,000 $60,173Total $134,835,000 $110,413,000 $60,705,423
The construction of a new high school to serve Crofton and surrounding communities.
Crofton Area HS - New School
Administrative Data Vital StatisticsGWWO ArchitectsJacobs, Inc.
Construction
Current Status .
Phase 1 - Building site work is 40% complete. Building interior work continues along with plumbing and electrical rough-in activities. Phase 2 - Athletic field site work is 10% complete.
Project Schedule
Approved EdSpec
Current Actual
Fiscal Data
Approved Budget
Current Appropriation
Encumbered
4 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 455 669Scope of Work: Gross Square Footage 52,326 90,617
Phase of Work:
Percent Complete:
Educational Specifications May-16 May-16 May-16Feasibility Study Nov-16 Nov-16 Oct-16Schematic Design Sep-17 Apr-17 May-17Design Development Jan-18 Aug-17 Sep-17Construction Documents Aug-18 Apr-18 Apr-18Bid Award Mar-19 Aug-18Start Construction Apr-19 Oct-18Occupancy Aug-21 Mar-21
Plans & Engineering $3,600,000 $3,600,000 $2,935,554Construction $37,989,000 $15,995,000 $269,015FFE $2,300,000Project Support $2,007,000 $803,000 $63,424Total $45,896,000 $20,398,000 $3,267,993
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Project Schedule
Approved EdSpec
Current Actual
Bidding
Current Status
Construction documents are being prepared for bidding. The modular swing space unit is being fabricated and will be installed onsite pending the release of the grading and building permits.
The design and construction for the revitalization of Edgewater Elementary School.
Edgewater ES - Revitalization
Administrative Data Vital StatisticsHord Coplan MachtJ. Vinton Schafer & Sons, Inc.
5 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 322 451
Scope of Work: Gross Square Footage 42,110 74,468
Phase of Work:
Percent Complete: 28%
Educational Specifications Sep-13 Sep-13 Nov-13Feasibility Study Nov-13 Mar-14 Mar-14Schematic Design Jul-14 Jun-16 Jul-16Design Development Nov-14 Oct-16 Oct-16Construction Documents Mar-15 Jan-17 Jan-17Bid Award Jan-16 Jul-17 Jul-17Start Construction Apr-16 Aug-17 Aug-17Occupancy Aug-18 Jan-20
Plans & Engineering $2,855,000 $2,855,000 $2,432,220Construction $30,541,000 $27,527,000 $14,015,823FFE $1,900,000 $1,140,000 $45,139Project Support $964,000 $744,000 $13,507Total $36,260,000 $32,266,000 $16,506,689
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Project Schedule
Approved EdSpec
Current Actual
Construction
Current Status
Phase 1 is 76% complete. In progress activies include: HVAC ductwork, exterior doors and hardware, acoustical ceilings, final painting, and flooring installation.
The revitalization of George Cromwell Elementary School.
George Cromwell ES - Revitalization
Administrative Data Vital StatisticsHord Coplan MachtOak Contracting, LLC
6 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 574 747Scope Of Work: Gross Square Footage 75,764 98,681
Phase of Work:
Percent Complete: 51%
Educational Specifications Jun-14 Jun-14 Jun-14Feasibility Study Sep-14 Sep-14 Sep-14Schematic Design Jan-14 Sep-15 Sep-15Design Development May-15 Dec-15 Dec-15Construction Documents Nov-15 Aug-16 May-16Bid Award Mar-16 Dec-16 Dec-16Start Construction Jun-16 Apr-17 Apr-17Occupancy Aug-18 Aug-19
Plans & Engineering $3,500,000 $3,500,000 $2,445,259Construction $33,801,000 $33,801,000 $32,091,756FFE $2,301,000 $2,301,000 $697,736Project Support $923,000 $923,000 $20,727Total $40,525,000 $40,525,000 $35,255,478
The construction of the modernization of High Point Elementary School.
High Point ES - Modernization
Administrative Data Vital StatisticsSmolen, Emr, Ilkovitch & Associates (SEI)J. Vinton Schafer & Sons, Inc.
Construction
Current Status
Phase 1A is 89% complete. Interior finishes including: bathroom partitions, hardware installations, flooring, and classroom visual boards are in progress. Phase 1B is 100% complete. Phase 1C and 1D are 82% complete. The installation of accoustical ceilings in the corridors, and flooring in the bathrooms and kitchen are in progress. Phase 1E is 11% complete.
Project Schedule
Approved EdSpec
Current Actual
Fiscal Data
Approved Budget
Current Appropriation
Encumbered
7 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 435 782Scope of Work: Gross Square Footage 83,686 98,879
Phase of Work:
Percent Complete: 22%
Educational Specifications Sep-13 Sep-13 Nov-13Feasibility Study Nov-13 Mar-14 Mar-14Schematic Design Jul-14 Sep-15 Sep-15Design Development Nov-14 Dec-15 Dec-15Construction Documents Mar-15 Oct-16 Dec-16Bid Award Jan-16 Feb-17 Feb-17Start Construction Apr-16 Apr-17 Jun-17Occupancy Aug-18 Aug-19
Plans & Engineering $3,477,000 $3,477,000 $2,540,346Construction $41,632,000 $41,632,000 $32,374,316FFE $2,418,000 $2,418,000Project Support $982,000 $982,000 $244,900Total $48,509,000 $48,509,000 $35,159,562
The construction of a replacement school for Jessup Elementary School.
Jessup ES - Replacement
Administrative Data Vital StatisticsGrimm + Parker ArchitectsHeery International, Inc.
Construction
Current Status
The site work grading, storm water facilities, utilities, retaining walls, foundation walls, concrete slabs, and structual framing are in progress. Anne Arundel County Public School staff, the Department of Public Works, and State Highway Administration continue to discuss access to MD 175.
Project Schedule
Approved EdSpec
Current Actual
Fiscal Data
Approved Budget
Current Appropriation
Encumbered
8 Construction Status July 2018
Architect:General Contractor:Scope Of Work:
Phase of Work:
Plans & Engineering $600,000 $600,000Construction $6,250,000 $6,250,000FFE $450,000 $450,000Project Support $200,000 $200,000Total $7,500,000 $7,500,000 $0* FY19 Program
Maryland City ES
Linthicum ES
Fiscal Data
Approved Budget *
Current Appropriation *
Encumbered
See following sheet for details
Park ES
See following sheet for details.
Project Schedule
See following sheet for details.
Current Status
Kindergarten Additions - Various Schools
Administrative DataVariousVariousOn-going program to provide kindergarten classroom additions at various schools. Design and Construction
9 Construction Status July 2018
School Project Description Const. Cost Fiscal Year Ed Specs/ Schematic
Design Dev./ Const Cost
Start Const.
Substantial Completion
Architect General Contractor
Current Status
6 Classroom Addition$3,600,000 (Estimate)
FY 2020 Apr-18 Oct-18 Jul-19 Jul-20 TCA TBD 5%
4 Classroom Addition$2,800,000 (Estimate)
FY 2020 Apr-18 Oct-18 Jul-19 Jul-20 HCM TBD 5%
4 Classroom Addition $3,471,000 FY 2018 Apr-16/ Sept-16
Dec-16/ Feb-17
Jul-17 Jul-18 WRA Towson Mechancial
85%
6 Classroom Addition $2,422,300 FY 2018 Apr-16/ Apr-17
Dec-16/ Feb-17
Jul-17 Mar-18 TCA Tuckman Barbee
99%
Kindergarten Additions at Various Schools
Linthicum ES
Schools in Design:
Park ES
Schools in Construction:
Design documents in progress.
Design documents in progress.
The roof, electrical, and HVAC piping rough-ins are 95% complete. Accoustical ceiling rough-ins as well as window and flooring installations are in progress.
Millersville ES
Shady Side ES
The addition was occupied on March 15, 2018. The project is currently under warranty and in closeout.
10 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 529 454Scope Of Work: Gross Square Footage 72,267 70,934
Phase of Work:
Percent Complete: 40%
Educational Specifications Jun-14 Jun-14 Jun-14Feasibility Study Sep-14 Sep-14 Sep-14Schematic Design Jan-15 Jan-15 Sep-15Design Development May-15 May-15 Dec-15Construction Documents Nov-15 Aug-16 Dec-16Bid Award Mar-16 Jan-17 Jan-17Start Construction Jun-16 Apr-17 Apr-17Occupancy Aug-18 Aug-19
Plans & Engineering $2,962,000 $2,962,000 $1,821,691Construction $28,620,000 $28,620,000 $26,729,931FFE $1,926,000 $1,926,000 $761,533Project Support $891,000 $891,000 $30,884Total $34,399,000 $34,399,000 $29,344,039
The revitalization of Manor View Elementary School.
Manor View ES - Revitalization
Administrative Data Vital StatisticsWGM Architects Whiting-Turner Construction Co.
Construction
Current Status
Phase 1A is 99% complete and occupied. Phase 1B is 50% complete. The main corridor and above ceiling work will be ongoing until June 2019. Phase 2 is 99% complete. Punch list work is ongoing. Phase 3A is 98% complete and occupied. Punch list work is ongoing. Phase 3B is 30% complete. Concrete slabs are complete. Construction of mechanical, electrical, plumbing rough-ins, and masonry walls with brick veneer are ongoing.
Approved EdSpec
Current Actual
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Project Schedule
11 Construction Status July 2018
Architect:General Contractor:Scope of Work:
Phase of Work:
Plans & Engineering $0 $0Construction $8,000,000 $8,000,000FFE $0 $0Project Support Total $8,000,000 $8,000,000 $0* FY19 Program
Chesapeake HS
Shady Side ES
Fiscal Data
Approved Budget*
Current Appropriation*
Encumbered
See following sheet for details
See following sheet for details.
Project Schedule
See following sheet for details. Brock Bridge ES
Current Status
Open Space Enclosures - Various Schools
Administrative DataVariousVarious
Provide full height walls, modification of ceilings, lighting systems, fire alarms, public address systems, and HVAC systems as required.
Design and Construction
12 Construction Status July 2018
School Const. Cost Fiscal YearEd Specs/ Schematic
Design Dev./ Const Doc.
Start Const.
Substantial Completion
ArchitectGeneral
ContractorCurrent Status
$8,271,500 FY 2018 Nov-15 Apr-18 Oct-18 Sep-20 WGM TBD 95%
School Const. Cost Fiscal YearEd Specs/ Schematic
Design Dev./ Const Doc.
Start Const.
Substantial Completion
ArchitectGeneral
ContractorCurrent Status
$2,984,500 FY 2018Apr-16/ Feb-17
Dec-16/ Feb-17
Jul-17 Mar-19 TCABaltimore
Contractors30%
$6,268,800 FY 2017 Jun-15 May-16 Aug-16 Aug-18 BWHE. Pikounis
Constr. Co. Inc. 95%
$2,892,000 FY 2018Apr-16/ Feb-17
Dec-16/ Feb-17
Jul-17 Aug-18 TCATuckman Barbee
96%Shady Side ES
Phase 3 will be complete by the end of July 2018. The health suite and security vestibule work is ongoing.
Open Space Enclosures at Various Schools
Chesapeake HS
Phases 1, 2, 3, 4, 5, 6 and 7 are complete. Currently expediting completion on Phase 8.
Brock Bridge ES
Phase1 is complete. Phase 2 is underway. The health suite and security vestibule work is ongoing.
Chesapeake Bay MS
Bid documents will be issued in summer 2018.
Schools in Design:
Schools in Construction:
13 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 479 509Scope of Work: Gross Square Footage 61,000 81,000
Phase of Work:
Percent Complete: 100%
Educational Specifications May-16 May-16 May-16Feasibility Study Oct-16 Oct-16 Oct-16Schematic Design Sep-17 Apr-17 May-17Design Development Dec-17 Jul-17 Sep-17Construction Documents Aug-18 Feb-18 Mar-18Bid Award Feb-19 Aug-18Start Construction Apr-19 Sep-18Occupancy Aug-21 Sep-20
Plans & Engineering $3,248,000 $3,248,000 $2,654,617Construction $33,401,000 $15,401,000 $195,017FFE $2,026,000Project Support $1,114,000 $446,000 $21,460Total $39,789,000 $19,095,000 $2,871,094
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Project Schedule
Approved EdSpec
Current Actual
Bidding
Current Status
Construction documents are currently out for bidding. Bid openings are scheduled for the end of July 2018, with contracts being awarded by the Board of Education in August 2018. Construction documents are currently pending Anne Arundel County permit approval. The Corkran MS & Oakwood ES swing spaces are being prepared for an August 2018 occupancy by Richard Henry Lee ES .
The design and construction for the revitalization of Richard Henry Lee Elementary School.
Richard Henry Lee ES - Revitalization
Administrative Data Vital StatisticsGrimm + Parker Architects Whiting-Turner Contracting Co.
14 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 1,805 2,141Scope of Work: Gross Square Footage 296,191 354,162
Phase of Work:
Percent Complete: 98%
Educational Specifications Jul-10 Jul-10 Jul-10Feasibility Study Jul-10 Feb-11 Feb-11Schematic Design Mar-12 Mar-12 Mar-12Design Development Sep-12 Oct-12 Oct-12Construction Documents Feb-13 May-13 May-13Bid Award May-13 Jan-14 Feb-14Start Construction Aug-13 May-14 Jun-14Occupancy Feb-16 Bldg Jan-17/Site Mar-18 Bldg Jan-17/Site Mar-18
Plans & Engineering $7,722,000 $7,722,000 $7,590,792Construction $107,314,000 $107,314,000 $105,872,450FFE $3,566,000 $3,566,000 $3,046,539Project Support $563,000 $563,000 $562,201Total $119,165,000 $119,165,000 $117,071,982
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Project Schedule
Approved EdSpec
Current Actual
Construction
Current Status
Phase 2 encompassing the athletic fields and stadium was completed on March 1, 2018, and turned over to the school for occupancy. Due to temperature and weather constraints, the tennis court, running track surfaces, turf field grasses, and additional biorientation plantings will be completed in the summer of 2018.
The construction of a replacement school for Severna Park High School.
Severna Park HS - Replacement
Administrative Data Vital StatisticsGWWOOak Contracting, LLC
15 Construction Status July 2018
Architect:
General Contractor:
Scope of Work:
Phase of Work:
Plans & Engineering $1,400,000 $1,400,000Construction $15,794,000 $15,794,000FFEProject Support Total $17,194,000 $17,194,000 $0* FY19 Program
Crofton Meadows ES
Millersville ES
Bodkin ES
Fiscal Data
Approved Budget*
Current Appropriation*
Encumbered
See following sheet for details
See following sheet for details.
Project Schedule
See following sheet for details.
Current Status
Systemic Project - Various Schools - Building Systemics
Administrative DataVarious
Various
Building Systemics - Various Schools
Design and Construction
16 Construction Status July 2018
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const.
Substantial Completion
EngineerGeneral
ContractorCurrent Status
HVAC/Windows$18,939,300
(Estimate)FY 2019 Feb-18 Aug-18 Mar-20
James Posey Associates, Inc.
N/A 100%
The construction documents have been submitted to the State for review and comment. An anticipated bid award is scheduled in August 2018.
Building Systemics - Various Schools
Schools in Design:
Annapolis MS
17 Construction Status July 2018
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const.
Substantial Completion
EngineerGeneral
ContractorCurrent Status
Roof Replacement $3,182,000 FY 2019 Jan-18 Jun-18 Aug-19 Gail Associates Vatica 20%
Roof Replacement $1,189,990 FY 2018 Jan-17 Jun-17 Aug-18 Colmore. Inc Vatica 70%
HVAC $3,897,000 FY 2019 Jan-18 Jun-18 Aug-19Gannett -Fleming
Towson Mechanical
20%
Roof Replacement $1,534,000 FY 2018/2019 Sep-17 Jun-18 Aug-19 Gail Associates Vatica 20%
Boiler Replacement
$677,147 FY 2018 Dec-16 Jun-17 Aug-18James Posey
Associates, Inc.M & E Sales 100%
Windows & HVAC $2,964,076 FY 2017 Dec-15 Jul-16 Aug-17Gannett-Fleming
Heer Brothers, Inc.
100%
HVAC, Ceiling & Lights
$17,146,000 FY 2016 n/a Feb-16 Dec-18James Posey
Associates, Inc.Phillips Way,
Inc.99%
Windows & HVAC $3,529,000 FY 2017 Dec-15 Jun-16 Aug-17 JMTHeer Brothers,
Inc.99%
Roof Replacement $40,221,401 FY 2018 Feb-17 Jun-17 Aug-19 Gale Associates Vatica 35%
HVAC, Ceiling & Lights
$11,758,646 FY 2015 n/a Jun-14 Aug-17 JMTPhillips Way,
Inc.99%
HVAC Replacement
$3,739,000 FY 2018 Dec-16 Jun-17 Aug-18 JMT TMI 74%
HVAC Replacement
$4,302,134 FY 2018 Dec-16 Jun-17 Oct-18James Posey
Associates, Inc.Maryland
Mechanical50%
Millersville ES
Installing new mechanical equipment in classrooms.
Woodside ES
Classroom unit installation continues and chiller enclosure is underway.
Maryland City ES
Back punch and closeout underway.
Meade MS
Phase 2 of 3 is in progress.
Meade HS
Project is substantially completed with commissioning and punch list work in closeout.
Project is in closeout. This is the last report for this project.
J.A. Adams Academy
MacArthur MS
Commissioning is ongoing at 99%.
Glen Burnie HS
Building Systemics - Various Schools
Arundel MS
Phase 2 of 2 underway.
Bodkin ES
Final payment processed. This is the last report for this project.
Schools in Construction:
Phase 1 of 2 roof replacement is in progress.
The construction documents have been submitted to the State for review and comment.
Broadneck ES
Phase 1 of 2 roof replacement is in progress.
Belevedere ES
18 Construction Status July 2018
Architect:General Contractor:Scope of Work:
Phase of Work:
Plans & Engineering $70,000 $70,000Construction $429,000 $429,000FFEProject Support Total $499,000 $499,000 $0* FY19 Program
Design and Construction
VariousElectrical system distribution upgrade projects at selected schools.
Systemic Project -TIMS Electrical Upgrades
Administrative DataVarious
Project Schedule
See following sheet for details.
Current Status
See following sheet for details.
Fiscal Data
Broadneck ES
Approved Budget*
Current Appropriation*
Encumbered
See following sheet for details
Brooklyn Park ES
Crofton Woods ES
19 Construction Status July 2018
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const.
Substantial Completion
EngineerGeneral
ContractorCurrent Status
TIMS $33,405 FY 2018 Feb-18 Aug-18 May-19 BKM N/A 100%
TIMS $33,405 FY 2018 Feb-18 Aug-18 May-19 BKM N/A 100%
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const.
Substantial Completion
EngineerGeneral
ContractorCurrent Status
TIMS $79,712 FY 2017 Dec-16 Jul-17 May-18 BKM Lee's Electric 100%
TIMS $193,295 FY 2017 Dec-16 Jul-17 May-18 BKM Lee's Electric 100%
The project is in closeout. This is the last report for this project.
The project is in closeout. This is the last report for this project.
Broadneck ES
Bid opens on July 17, 2018.
TIMS Electric - Various Schools
Four Seasons ES
Bid opens on July 17, 2018.
Schools in Design:
Schools in Construction:
Brooklyn Park ES
Crofton Woods ES
20 Construction Status July 2018
Architect: Before AfterConstruction Manager: State Rated Capacity 479 549Scope of Work: Gross Square Footage 45,813 84,896
Phase of Work:
Percent Complete: 100%
Educational Specifications May-16 May-16 May-16Feasibility Study Oct-16 Oct-16 Oct-16Schematic Design Sep-17 Apr-17 May-17Design Development Dec-17 Jul-17 Sep-17Construction Documents Aug-18 Jan-18 May-18Bid Award Feb-19 Aug-18Start Construction Apr-19 Oct-18Occupancy Aug-21 Dec-20
Plans & Engineering $3,464,000 $3,464,000 $3,226,080Construction $30,015,000 $15,007,000 $179,432FFE $2,137,000Project Support $1,481,000 $592,000 $4,500Total $37,097,000 $19,063,000 $3,410,012
Approved Budget
Current Appropriation
Encumbered
Fiscal Data
Approved EdSpec
Current Actual
Project Schedule
The design and construction for the revitalization of Tyler Heights Elementary School.
Tyler Heights - Revitalization
Administrative Data Vital StatisticsTCAHeery International, Inc.
Bidding
Current Status
Permit process is ongoing. Construction documents are being prepared for bidding.
21 Construction Status July 2018