Additions ‐ Various Schools · 2020. 1. 23. · Schematic Design Jan‐14 Sep‐15 Sep‐15...
Transcript of Additions ‐ Various Schools · 2020. 1. 23. · Schematic Design Jan‐14 Sep‐15 Sep‐15...
Architect:
General Contractor:
Scope of Work:
Phase of Work:
Plans & Engineering $500,000 $500,000
Construction $5,300,000 $5,300,000
FFE $200,000 $200,000
Project Support
Total $6,000,000 $6,000,000 $0
* FY20 Program
Current Status
Additions ‐ Various Schools
Administrative Data
Various
Various
Ongoing program to provide additions at various
schools.
Design and Construction
Project Schedule
See following sheet for details.
Fiscal Data
Crofton Woods ES
See following sheet for details.
See following
sheet for details
Approved
Budget *
Current
Appropriation*Encumbered
Glen Burnie Park ES
Solley ES
1 Construction Status January 2020
SchoolProject
DescriptionConst. Cost Fiscal Year
Ed Specs/
Schematic
Design Dev./
Const
Documents
Start
Const. Completion Architect
General
ContractorCurrent Status
11 Classroom
Addition
$10,000,000
(Estimate)FY 2020 Jun‐19/Nov‐19
Jan‐20/
May‐20Jul‐20 Dec‐21 HCM TBD 40%
SchoolProject
DescriptionConst. Cost Fiscal Year
Ed Specs/
Schematic
Design Dev./
Const
Documents
Start
Const. Completion Architect
General
ContractorCurrent Status
6 Classroom
Addition$3,126,300 FY 2020 Apr‐18 Oct‐18 / Jan‐19 Jul‐19 Aug‐20 G + P
Tech
Contracting 40%
Gym/Program
Addition $6,843,850 FY 2019 Aug‐17
Nov‐17/
Jan‐18Oct‐18 Feb‐20 SEI
Tech
Contracting 85%
6 Classroom
Addition$2,331,200
FY 2019/
FY 2020
Apr‐16/
Sept‐16
Dec‐16/
Feb‐17Jul‐18 Aug‐19 BWH TMI 99%
Crofton Woods ES
Structural steel has been set and the contractor is installing above ceiling mechanical, electrical, and plumbing rough‐ins.
Solley ES
Security vestibule work is complete and the contractor is working on finishing the remaining punch list work. This is the last report for this project.
Additions ‐ Various Schools ‐ continued
Schools in Design:
Glen Burnie Park ES
School has moved into new addition and the contractor is currently renovating the five existing classrooms.
Schools in Construction:
Arundel MS
Design Development documents presented to the Board of Education 1/8/20 meeting.
2 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 456 565
Gross Square Footage 56,255 89,253
Phase of Work:
Percent Complete: 99%
Educational Specifications Sep‐13 Sep‐13 Nov‐13
Feasibility Study Nov‐13 Mar‐14 Mar‐14
Schematic Design Jul‐14 Sep‐15 Sep‐15
Design Development Nov‐14 Dec‐15 Sep‐15
Bid Award Jan‐16 Jan‐17 Jan‐17
Start Construction Apr‐16 Apr‐17 Apr‐17
Occupancy Aug‐18 Aug‐19 Jun‐19
Plans & Engineering $3,271,000 $3,271,000 $3,231,207
Construction $35,362,000 $35,362,000 $33,058,691
FFE $2,104,000 $2,104,000 $1,556,640
Project Support $1,366,000 $1,366,000 $1,021,122
Total $42,103,000 $42,103,000 $38,867,660
Approved
Budget
Current
AppropriationEncumbered
Fiscal Data
Project Schedule
Approved
EdSpecCurrent Actual
Construction
Current Status
The project is complete and was occupied for the start of school. Punch list
work and close out will continue through the fall and winter. This is the last
report for this project.
Construction of a replacement school for Arnold
Elementary School.
Arnold ES ‐ Replacement
Administrative Data Vital Statistics
GWWO Architects
Jacobs, Inc.
Scope of Work:
3 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity n/a 1,696
Scope of Work: Gross Square Footage n/a 275,768
Phase of Work:
Percent Complete: 80%
Educational Specifications May‐16 May‐16 May‐16
Feasibility Study n/a n/a n/a
Schematic Design Aug‐16 Aug‐16 Aug‐16
Design Development Dec‐16 Nov‐16 Oct‐16
Construction Documents Aug‐17 Aug‐17 Aug‐17
Bid AwardDec‐17 Site Aug‐17
Bldg Oct‐17Aug‐18
Start Construction Jan‐18 Jan‐18 Jan‐18
Occupancy Aug‐20 Aug‐20
Plans & Engineering $10,078,000 $10,078,000 $6,972,834
Construction $114,304,000 $114,034,000 $105,919,335
FFE $8,641,000 $8,641,000 $1,344,971
Project Support $1,812,000 $1,812,000 $603,928
Total $134,835,000 $134,565,000 $114,841,068
Construction of a new high school to serve Crofton
and surrounding communities.
Crofton HS ‐ New School
Administrative Data Vital Statistics
GWWO Architects
Jacobs, Inc.
Construction
Current Status .
Crofton HS is a 2 phase project.
Phase 1 ‐ Building site work is 90% complete. Building interior work continues
and is 83% complete.
Phase 2 ‐ Athletic field site work is 80% complete.
Project Schedule
Approved
EdSpecCurrent Actual
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
4 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 455 669
Scope of Work: Gross Square Footage 52,326 89,634
Phase of Work:
Percent Complete: 46%
Educational Specifications May‐16 May‐16 May‐16
Feasibility Study Nov‐16 Nov‐16 Oct‐16
Schematic Design Sep‐17 Apr‐17 May‐17
Design Development Jan‐18 Aug‐17 Sep‐17
Construction Documents Aug‐18 Apr‐18 Apr‐18
Bid Award Mar‐19 Aug‐18 Sep‐18
Start Construction Apr‐19 Oct‐18 Oct‐18
Occupancy Aug‐21 Aug‐21
Plans & Engineering $3,600,000 $3,600,000 $3,552,880
Construction $42,119,000 $38,127,000 $33,596,585
FFE $2,408,000 $1,175,000 $670,740
Project Support $1,845,000 $1,505,000 $407,377
Total $49,972,000 $44,407,000 $38,227,582
Approved
Budget
Current
AppropriationEncumbered
Fiscal Data
Project Schedule
Approved
EdSpecCurrent Actual
Construction
Current Status
Edgewater ES is a 5 phase project
Phase 1 ‐ Administration, gym, cafeteria, and music room additions were
occupied at the beginning of the school year. Punchlist work is ongoing.
Phase 2 ‐ 4 classrooms, art room, 2 resource rooms were occupied on 01/02/20.
Phases 3 ‐ Renovation of six existing classrooms and replacement of three
existing modular classrooms. Demolition work is ongoing.
Phases 4‐5 have not started
Construction for the revitalization of Edgewater
Elementary School.
Edgewater ES ‐ Revitalization
Administrative Data Vital Statistics
Hord Coplan Macht
J. Vinton Schafer & Sons, Inc.
5 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 322 474
Scope of Work: Gross Square Footage 42,110 74,468
Phase of Work:
Percent Complete: 87%
Educational Specifications Sep‐13 Sep‐13 Nov‐13
Feasibility Study Nov‐13 Mar‐14 Mar‐14
Schematic Design Jul‐14 Jun‐16 Jul‐16
Design Development Nov‐14 Oct‐16 Oct‐16
Construction Documents Mar‐15 Jan‐17 Jan‐17
Bid Award Jan‐16 Jul‐17 Jul‐17
Start Construction Apr‐16 Aug‐17 Aug‐17
Occupancy Aug‐18 Mar‐20
Plans & Engineering $2,855,000 $2,855,000 $2,773,356
Construction $30,541,000 $30,541,000 $29,771,718
FFE $1,900,000 $1,900,000 $614,308
Project Support $964,000 $964,000 $13,930
Total $36,260,000 $36,260,000 $33,173,312
Approved
Budget
Current
AppropriationEncumbered
Fiscal Data
Project Schedule
Approved
EdSpecCurrent Actual
Construction
Current Status
George Cromwell ES is a 4 phase project.
Phases 1 and 2 are complete.
Phase 3 ‐ Classroom renovation and new Media Center are complete.
Phase 4 ‐ Work is ongoing and on schedule to be completed in March 2020.
New furniture deliveries are scheduled for summer 2020.
Construction for the revitalization of George
Cromwell Elementary School.
George Cromwell ES ‐ Revitalization
Administrative Data Vital Statistics
Hord Coplan Macht
Oak Contracting, LLC
6 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 574 747
Scope Of Work: Gross Square Footage 75,764 98,681
Phase of Work:
Percent Complete: 99%
Educational Specifications Jun‐14 Jun‐14 Jun‐14
Feasibility Study Sep‐14 Sep‐14 Sep‐14
Schematic Design Jan‐14 Sep‐15 Sep‐15
Design Development May‐15 Dec‐15 Dec‐15
Construction Documents Nov‐15 Aug‐16 May‐16
Bid Award Mar‐16 Dec‐16 Dec‐16
Start Construction Jun‐16 Apr‐17 Apr‐17
Occupancy Aug‐18 Aug‐19 Aug‐19
Plans & Engineering $3,500,000 $3,500,000 $2,596,722
Construction $33,801,000 $33,801,000 $34,836,091
FFE $2,301,000 $2,301,000 $1,382,343
Project Support $923,000 $923,000 $161,041
Total $40,525,000 $40,525,000 $38,976,197
Construction of the modernization of High Point
Elementary School.
High Point ES ‐ Modernization
Administrative Data Vital Statistics
Smolen, Emr, Ilkovitch Architects (SEI)
J. Vinton Schafer & Sons, Inc.
Construction
Current Status
The project is complete and was occupied for the start of school. Punch list
work and close out will continue through the fall and winter. This is the last
report for this project.
Project Schedule
Approved
EdSpecCurrent Actual
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
7 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 509 506
Gross Square Footage 45,885 68,042
Phase of Work:
Percent Complete: 10%
Educational Specifications May‐19 May‐19 May‐19
Feasibility Study Sep‐19 Oct‐19 Oct‐19
Schematic Design Jan‐20 Feb‐20
Design Development Apr‐20 May‐20
Bid Award Jan‐21 Feb‐21
Start Construction Apr‐21 Apr‐21
Occupancy Aug‐23 Aug‐23
Plans & Engineering $784,000 $784,000 $783,460
Construction $0 $0 $0
FFE $0 $0 $0
Project Support $0 $0 $0
Total $784,000 $784,000 $783,460
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
Approved
EdSpecCurrent Actual
Design contract was approved by Board of Education on November 6, 2019.
The construction management services proposal from Whiting‐Turner
Construction was approved at the December 1, 2019, Board of Education
meeting. Schematic Design documents are scheduled for presentation to the
Board of Education in February 2020.
Project Schedule
Hillsmere ES ‐ Replacement
Administrative Data Vital Statistics
Gaudreau, Inc.
Whiting‐Turner Construction Co.
Scope of Work:Design of a replacement school for Hillsmere
Elementary School.
Design
Current Status
8 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 435 773
Scope of Work: Gross Square Footage 83,686 98,879
Phase of Work:
Percent Complete: 89%
Educational Specifications Sep‐13 Sep‐13 Nov‐13
Feasibility Study Nov‐13 Mar‐14 Mar‐14
Schematic Design Jul‐14 Sep‐15 Sep‐15
Design Development Nov‐14 Dec‐15 Dec‐15
Construction Documents Mar‐15 Oct‐16 Dec‐16
Bid Award Jan‐16 Feb‐17 Feb‐17
Start Construction Apr‐16 Apr‐17 Jun‐17
Occupancy Aug‐18 Aug‐19 Jun‐19
Plans & Engineering $3,477,000 $3,477,000 $2,815,145
Construction $41,632,000 $41,632,000 $41,052,242
FFE $2,418,000 $2,418,000 $1,896,564
Project Support $982,000 $982,000 $381,717
Total $48,509,000 $48,509,000 $46,145,668
Construction of a replacement school for Jessup
Elementary School.
Jessup ES ‐ Replacement
Administrative Data Vital Statistics
Grimm + Parker Architects
Heery International, Inc.
Construction
Current Status
Jessup ES is a 2 phase project.
Phase 1 ‐ Building construction is 99% complete and was occupied at the start
of the 2019‐2020 school year. The punch list work and contract closeout is
ongoing.
Phase 2 ‐ Final use and occupancy is pending the spring 2020 completion of site
work and bus lot.
Project Schedule
Approved
EdSpecCurrent Actual
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
9 Construction Status January 2020
Architect:
General Contractor:
Scope Of Work:
Phase of Work:
Plans & Engineering $800,000 $800,000
Construction $8,700,000 $8,700,000
FFE $500,000 $500,000
Project Support $1,000,000 $1,000,000
Total $11,000,000 $11,000,000 $0
* FY20 Program
Millersville ES
Sunset ES
Fiscal Data
Approved
Budget *
Current
Appropriation *Encumbered
See following
sheet for
details
Project Schedule
See following sheet for details. Linthicum ES
See following sheet for details.
Current Status
Kindergarten Additions ‐ Various Schools
Administrative Data
Various
Various
Ongoing program to provide kindergarten
classroom additions at various schools.
Design and Construction
10 Construction Status January 2020
School Project Description Const. Cost Fiscal YearEd Specs/
Schematic
Design Dev./
Const
Documents
Start
Const. Completion Architect
General
ContractorCurrent Status
4 Classroom Addition $3,200,000
(Estimate) FY 2020 May‐19 Dec‐19 Jul‐20 Jul‐21
Murphy
Dittenhafer TBD 95%
4 Classroom Addition $3,200,000
(Estimate) FY 2020 May‐19 Dec‐19 Jul‐20 Jul‐21 Moseley TBD 95%
School Project Description Const. Cost Fiscal YearEd Specs/
Schematic
Design Dev./
Const Cost
Start
Const. Completion Architect
General
ContractorCurrent Status
6 Classroom Addition $3,125,200 FY 2020 Apr‐18Oct‐18/
Feb‐19Jul‐19 Aug‐20 TCA
Towson
Mechanical 40%
4 Classroom Addition $2,800,000 FY 2020 Apr‐18Oct‐18/
Feb‐19Jul‐19 Aug‐20 HCM
James W. Ancel
Inc.78%
Millersville ESExterior walls and roofing are complete. Mechanical, electrical, and plumbing rough‐ins, site work, and finishes are all ongoing and are currently 85% complete. Security vestibule
scheduled for summer 2020.
Kindergarten Additions at Various Schools
Linthicum ES
Schools in Design:
Schools in Construction:
Roof decking has been installed. Masonry and mechanical/ electrical/ plumbing work is ongoing.
Sunset ES
Construction documents are being prepared to bid in early spring 2020.
Van Bokkelen ES
Construction documents are being prepared to bid in early spring 2020.
11 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 529 516
Scope Of Work: Gross Square Footage 72,267 71,576
Phase of Work:
Percent Complete: 98%
Educational Specifications Jun‐14 Jun‐14 Jun‐14
Feasibility Study Sep‐14 Sep‐14 Sep‐14
Schematic Design Jan‐15 Jan‐15 Sep‐15
Design Development May‐15 May‐15 Dec‐15
Construction Documents Nov‐15 Aug‐16 Dec‐16
Bid Award Mar‐16 Jan‐17 Jan‐17
Start Construction Jun‐16 Apr‐17 Apr‐17
Occupancy Aug‐18 Aug‐19 Jun‐19
Plans & Engineering $2,962,000 $2,962,000 $2,132,837
Construction $28,620,000 $28,620,000 $28,804,107
FFE $1,926,000 $1,926,000 $1,164,548
Project Support $891,000 $891,000 $45,810
Total $34,399,000 $34,399,000 $32,147,302
The punch list and project closeout are ongoing. The roofing contractor is on
site and the new roof is 20% complete.
Construction for the revitalization of Manor View
Elementary School.
Manor View ES ‐ Revitalization
Administrative Data Vital Statistics
WGM Architects
Whiting‐Turner Construction Co.
Construction
Current Status
Approved
EdSpecCurrent Actual
Approved
Budget
Current
AppropriationEncumbered
Fiscal Data
Project Schedule
12 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 2,527 2,527
Scope Of Work: Gross Square Footage 351,142 386,081
Phase of Work:
Percent Complete: 50%
Educational Specifications Jan‐18 Feb‐18 Feb‐18
Feasibility Study n/a n/a n/a
Schematic Design Apr‐18 Jun‐19 Jun‐19
Design Development Oct‐18 Nov‐19 Nov‐19
Construction Documents Apr‐19 May‐20
Bid Award Nov‐19 Jun‐20
Start Construction Jun‐20 Jul‐20
Occupancy Aug‐24 Jul‐24
Plans & Engineering $5,918,311 $5,868,159
Construction $0
FFE $0
Project Support $0
Total $5,996,183 $0 $5,868,159
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
Current Actual
Meade HS ‐ Revitalization
Administrative Data Vital Statistics
Smolen‐Emr Ilkovitch Architects (SEI)
Jacobs, Inc.
Design for the revitalization of Meade High School.
Design
Current Status
Project Schedule
Design Development documents were approved by the Board of Education on
November 6, 2019. Plan reviews with the Anne Arundel County Inspection and
Permits, Maryland IAC, Fort George G Meade Department of Public Works and
Anne Arundel County Public Schools Facilities are ongoing.
Approved
EdSpec
13 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity n/a 1,882
Gross Square Footage n/a 295,919
Phase of Work:
Percent Complete: 30%
Educational Specifications May‐19 May‐19 May‐19
Feasibility Study n/a n/a n/a
Schematic Design Oct‐19 Nov‐19 Nov‐19
Design Development Mar‐20 Mar‐20
Bid Award Apr‐21 Apr‐21
Start Construction May‐21 May‐21
Occupancy Aug‐23 Aug‐24
Plans & Engineering $10,007,000 $10,007,000 $8,450,218
Construction $0 $0 $0
FFE $0 $0 $0
Project Support $0 $0 $0
Total $10,007,000 $10,007,000 $8,450,218
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
Approved
EdSpecCurrent Actual
Schematic Design was approved at the November 6, 2019 Board of Education
meeting. Design Development documents are 15% complete.
Project Schedule
Old Mill West HS ‐ New School
Administrative Data Vital Statistics
GWWO Architects
Jacobs, Inc.
Scope of Work: Construction of a new high school to serve Severn
and surrounding communities.
Design
Current Status
14 Construction Status January 2020
Architect:
General Contractor:
Scope of Work:
Phase of Work:
Plans & Engineering $0 $0
Construction $8,000,000 $8,000,000
FFE $0 $0
Project Support
Total $8,000,000 $8,000,000 $0
* FY19 Program
See following
sheet for details
Fiscal Data
Approved
Budget*
Current
Appropriation*Encumbered
See following sheet for details.
Open Space Enclosures ‐ Various Schools
Administrative Data
Various
Various
Provide full height walls, modification of ceilings,
lighting systems, fire alarms, public address
systems, and HVAC systems as required.
Construction
Chesapeake Bay MS
Current Status
See following sheet for details.
Project Schedule
15 Construction Status January 2020
School Const. Cost Fiscal YearEd Specs/
Schematic
Design Dev./
Const Doc.
Start
Const.Completion Architect
General
ContractorCurrent Status
$6,569,888 FY 2018 Nov‐15 Apr‐18 Oct‐18 Sep‐20 WGMBaltimore
Contractors95%
Open Space Enclosures at Various Schools
Chesapeake Bay MS
Phases 1 ‐ 7 are complete. The security vestibule will be completed during summer 2020.
Schools in Construction:
16 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 463 585
Gross Square Footage 45,885 84,081
Phase of Work:
Percent Complete: 15%
Educational Specifications May‐19 May‐19 May‐19
Feasibility Study Sep‐19 Oct‐19 Oct‐19
Schematic Design Jan‐20 Feb‐20
Design Development Apr‐20 May‐20
Bid Award Jan‐21 Jan‐21
Start Construction Apr‐21 Apr‐21
Occupancy Aug‐23 Aug‐23
Plans & Engineering $947,000 $947,000 $902,823
Construction $0 $0 $0
FFE $0 $0 $0
Project Support $0 $0 $0
Total $947,000 $947,000 $902,823
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
Approved
EdSpecCurrent Actual
The design services proposal from Hord Coplan Macht was approved at the
November 6, 2019 Board of Education meeting . The construction management
services proposal from Oak Contracting, LLC was approved at the December 1,
2019 Board of Education meeting. Schematic Design documents are scheduled
for presentation to the Board of Education in February 2020.
Project Schedule
Quarterfield ES ‐ Replacement
Administrative Data Vital Statistics
Hord Coplan Macht
Oak Contracting, LLC
Scope of Work: Design for the construction of a replacement
school for Quarterfield Elementary School.
Design
Current Status
17 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 479 509
Scope of Work: Gross Square Footage 61,000 80,979
Phase of Work:
Percent Complete: 60%
Educational Specifications May‐16 May‐16 May‐16
Feasibility Study Oct‐16 Oct‐16 Oct‐16
Schematic Design Sep‐17 Apr‐17 May‐17
Design Development Dec‐17 Jul‐17 Sep‐17
Construction Documents Aug‐18 Feb‐18 Mar‐18
Bid Award Feb‐19 Aug‐18 Aug‐18
Start Construction Apr‐19 Sep‐18 Oct‐18
Occupancy Aug‐21 Sep‐20
Plans & Engineering $3,248,000 $3,248,000 $2,944,447
Construction $33,662,000 $30,268,000 $28,402,361
FFE $2,026,000 $1,455,000
Project Support $853,000 $446,000 $609,992
Total $39,789,000 $35,417,000 $31,956,800
Approved
Budget
Current
AppropriationEncumbered
Fiscal Data
Project Schedule
Approved
EdSpecCurrent Actual
Construction
Current Status
Site work, exterior walls, roofing, interior walls, and mechanical, electrical, and
plumbing rough‐ins are ongoing.
Construction for the revitalization of Richard
Henry Lee Elementary School.
Richard Henry Lee ES ‐ Revitalization
Administrative Data Vital Statistics
Grimm + Parker Architects
Whiting‐Turner Contracting Co.
18 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 613 775
Gross Square Footage 76,500 101,523
Phase of Work:
Percent Complete: 4%
Educational Specifications May‐19 May‐19 May‐19
Feasibility Study Sep‐19 Oct‐19 Oct‐19
Schematic Design Jan‐20 Feb‐20
Design Development Apr‐20 May‐20
Bid Award Jan‐21 Jan‐21
Start Construction Apr‐21 Apr‐21
Occupancy Aug‐23 Aug‐23
Plans & Engineering $1,241,000 $1,241,000 $1,144,471
Construction $0 $0 $0
FFE $0 $0 $0
Project Support $0 $0 $0
Total $1,241,000 $1,241,000 $1,144,471
Fiscal Data
Approved
Budget
Current
AppropriationEncumbered
Approved
EdSpecCurrent Actual
The design services proposal from Grimm + Parker Architects was approved at
the November 6, 2019 Board of Education meeting . The construction
management services proposal from Heery International, Inc.was approved at
the December 1, 2019 Board of Education meeting. Schematic Design
documents are scheduled for presentation to the Board of Education in
February 2020.
Project Schedule
Rippling Woods ES ‐ Replacement
Administrative Data Vital Statistics
Grimm + Parker Architects
Heery International, Inc.
Scope of Work:Design of a replacement school for Rippling Woods
Elementary School.
Design
Current Status
19 Construction Status January 2020
Architect:
General Contractor:
Scope of Work:
Phase of Work:
Plans & Engineering $1,400,000 $1,400,000
Construction $20,100,000 $20,100,000
FFE
Project Support
Total $21,500,000 $21,500,000 $0
* FY20 Program
Various
Arundel MS
Design and Construction
Current Status
Fiscal Data
Approved
Budget*
Systemic Project ‐ Various Schools ‐ Building Systemics
Administrative Data
Various
Project Schedule
See following sheet for details.
See following sheet for details.
Annapolis MS
See following
sheet for details
Building Systemics ‐ Various Schools
Current
Appropriation*Encumbered
20 Construction Status January 2020
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const. Completion Engineer
General
ContractorCurrent Status
HVAC /Fire Alarm$27,800,000
(Estimate)FY2020 Dec‐19 Jun‐20 Aug‐23
James Posey
Associates, Inc.TBD 100%
Roof Replacement $1,715,000
(Estimate)FY 2020 May‐19 Jun‐20 Aug‐21 Gale Associates TBD 100%
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const. Completion Engineer
General
ContractorCurrent Status
HVAC/Windows $21,441,775 FY 2019 Feb‐18 Nov‐18 Dec‐20James Posey
Associates, Inc.
Phillips Way,
Inc.75%
Building Systemics ‐ Various Schools
Maryland City ES
Construction documents are being prepared for bid.
Schools in Design:
Annapolis MS
Evening work in classrooms.
Construction documents were sent to the State for review on 12/16/19. The project is scheduled to bid in winter 2020.
North County HS
Schools in Construction:
21 Construction Status January 2020
Architect:
General Contractor:
Scope of Work:
Phase of Work:
Plans & Engineering $70,000 $70,000
Construction $430,000 $430,000
FFE
Project Support
Total $500,000 $500,000 $0
* FY20 Program
Systemic Project ‐TIMS Electrical Upgrades
Administrative Data
Various
Design and Construction
Various
Electrical system distribution upgrade projects at
selected schools.
See following
sheet for details
Project Schedule
See following sheet for details.
Current Status
See following sheet for details.
Fiscal Data
Approved
Budget*
Current
Appropriation*Encumbered
Lindale MS
22 Construction Status January 2020
SchoolProject
DescriptionConst. Cost Fiscal Year Const. Doc. Start Const. Completion Engineer
General
ContractorCurrent Status
TIMS $200,000 FY2020 Dec‐19 Jun‐20 Aug‐23James Posey
Associates, Inc.TBD 100%
TIMS $500,000 FY2020 Dec‐19 Jun‐20 Aug‐23 JMT TBD 100%
Construction documents were sent to the State for review on 12/16/19. The project is scheduled to bid in winter 2020.
TIMS Electric ‐ Various Schools
Schools in Design:
North County HS
Lindale MS
Construction documents were sent to the State for review on 1/6/20. The project is scheduled for bid in winter 2020.
23 Construction Status January 2020
Architect: Before After
Construction Manager: State Rated Capacity 479 549
Scope of Work: Gross Square Footage 45,813 84,813
Phase of Work:
Percent Complete: 47%
Educational Specifications May‐16 May‐16 May‐16
Feasibility Study Oct‐16 Oct‐16 Oct‐16
Schematic Design Sep‐17 Apr‐17 May‐17
Design Development Dec‐17 Jul‐17 Sep‐17
Construction Documents Aug‐18 Jan‐18 May‐18
Bid Award Feb‐19 Aug‐18 Sep‐18
Start Construction Apr‐19 Oct‐18 Oct‐18
Occupancy Aug‐21 Mar‐21
Plans & Engineering $3,464,000 $3,464,000 $3,318,095
Construction $36,412,000 $33,112,000 $30,911,960
FFE $2,137,000 $1,175,000 $435,803
Project Support $1,084,000 $592,000 $238,635
Total $43,097,000 $38,343,000 $34,904,493
Approved
Budget
Current
AppropriationEncumbered
Fiscal Data
Approved
EdSpecCurrent Actual
Project Schedule
Tyler Heights ES is a 7 phase project.
Phase 1 ‐ Site preparation ‐ 100% complete
Phase 2 ‐ Classrooms and gym/cafeteria additions are 99% complete and
occupied. Punch list work is ongoing.
Phase 3‐ Adminstration and classroom renovations have started with selective
demolition.
Phases 4 through 7 have not started.
Construction for the revitalization of Tyler Heights
Elementary School.
Tyler Heights ES ‐ Revitalization
Administrative Data Vital Statistics
TCA
Heery International, Inc.
Construction
Current Status
24 Construction Status January 2020
MAJOR SUBDIVISIONS REVIEWED IN THE MONTHS OF SEPTEMBER THRU DECEMBER, 2019
Project Project Status
Number/Type of Units
Number of
Students School
A 7522 Old Stage Road Sketch 33 SF 6 2 3
Richard H. Lee Elementary Corkran Middle Glen Burnie High
B Woodside Glen Final 15 SF, net 13 2 1 1
Woodside Elementary Corkran Middle Glen Burnie High
C Apartments at 1815 Crain
Preliminary 33 Apts. 5 2 3
Glen Burnie Park Elem. Old Mill Middle South Old Mill High
D Tanyard Shores, Sec. 6 Sketch 35 TH 7 2 3
Marley Elementary Marley Middle Glen Burnie High
E 1402 Old Ft. Smallwood Rd.
Sketch 11 SF, net 10 2 1 1
Ft. Smallwood Elementary Chesapeake Bay Middle Chesapeake High
F Grandfields at Severna Park
Sketch 315 SF, net 13 3 2 2
Benfield Elementary Severna Park Middle Severna Park High
G Gardetto Ridge Sketch 62 SF, net 56 14 4 5
Jessup Elementary Meade Middle Meade High
H Parkside, Phase 6, Section 2
Sketch 36 2-over-2’s 9 3 3
Meade Heights Elementary MacArthur Middle Meade High
I Parkside, Phase 3, Sec. 1 & Bulk Parcel 1RRRRR
Final 140 TH 36 11 13
Meade Heights Elementary MacArthur Middle Meade High
J Parkside, Phase 3, Sec. 2 & Bulk ParceL 1RRRRRR
Final 117 TH 30 9 11
Meade Heights Elementary MacArthur Middle Meade High
K Shipley Homestead, Section 3, Parcel B
Sketch 39 TH, 300 Apts. (125 2+ BR)
40 12 15
Jessup Elementary Meade Middle Meade High
L Watershed, Lot 3RR, Section 2
Final 200 TH 52 16 19
Maryland City Elementary Meade Middle Meade High
M Sanctuary at Two Rivers, Parcel S, Phase 2 *
Final 23 SF 5 2 3
Crofton Elementary Crofton Middle Arundel High
25 Construction Status January 2020
N Logwood Estates Sketch 21 SF, net 20 3 1 2
South Shore Elementary Old Mill Middle South Old Mill High
O Hideaway Estates * Sketch 20 SF, net 29 5 3 4
Crofton Woods Elementary Crofton Middle South River High
P Birch Manor Final 7 SF 1 1 1
Central Elementary Central Middle South River High
Q Selby on the Bay, Resub. Lot 97, Block S
Sketch 7 SF 1 1 1
Central Elementary Central Middle South River High
26 Construction Status January 2020
Development Process (Project Status)
Sketch: Developer refines the concept drawing to include the location of housing units on a lot, streets, sidewalks, and public spaces. This is a topographic line drawing that receives in-depth comments from the County review team. School capacities and the student population likely to be attributable to this development are recalculated.Site Development Plan: Applies to properties that will not be subdivided into individual lots, principally commercial and multi-family projects such as condominiums and apartments. Used to address APFO conformity. School capacities and the student population likely to be attributable to this development are recalculated. Final: Developer submits a detailed plan that addresses all of the County review team comments. Once a developer receives Final Submission Approval, applications for waivers and permits are submitted.
* This subdivision will be in the new Crofton area high school attendance zone beginning in the 2020-2021school year.
Construction Status January 2020 27
H,I,J
Project Reviews for September—December 2019
Anne Arundel County Subdivision Review
B G A
M
K
L
C
F
D
O
P
E
N
Q